I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Man Power, Peralatan, Material) 1.00 ls Rp 305,269,080 Rp 305,269,080
2 Temporary Facilities (Direksi Kit Container 20ft, Listrik Kerja) 1.00 ls Rp 594,611,592 Rp 594,611,592
3 Project Management 1.00 ls Rp 1,569,458,685 Rp 1,569,458,685
- Pembuatan Shop Drawing, Datasheet, Calculation, As Built Drawing, Project Procedure
- Review Engineering
- Man Power sesuai dengan RKS
- Dokumentasi dan Pelaporan
- Fit to Work Test (Medical Check-Up, DCU pemenuhan protokol kesehatan)
4 Pembuatan jalan akses sementara ke area tangki 1.00 ls Rp 249,427,260 Rp 249,427,260
- Bongkar dan pembuatan kembali bundwall
- Urugan pasir
- Plat
5 Pembersihan area kerja 1.00 ls Rp 8,160,600 Rp 8,160,600
6 Sewa Scaffolding 1.00 ls Rp 724,434,969 Rp 724,434,969
7 Tirai Air 1.00 ls Rp 154,351,920 Rp 154,351,920
8 Pembuatan dan pembongkaran kembali sistem penyangga (Strong Back) - Pipa CS 3" + Base plate 6 x 150 x 150 mm 1.00 ls Rp 34,274,520 Rp 34,274,520
JUMLAH I Rp 3,639,988,626
II PEKERJAAN SIPIL
1 Pekerjaan pengangkatan dan menurunkan Tangki menggunakan Sistem Hydraulic Jacking termasuk kelengkapannya 1.00 ls Rp 1,479,000,000 Rp 1,479,000,000
Kapasitas min. @ 50 Ton / titik - min. 39 titik
2 Pekerjaan perbaikan lapisan aspal
1 Pembongkaran lapisan aspal eksisting 1,763.26 m2 Rp 49,590 Rp 87,440,124
2 Pekerjaan pengaspalan ; Tebal min. 5 cm, slope 1 : 120 1,763.26 m2 Rp 60,900 Rp 107,382,609
3 Pekerjaan jalan inspeksi :
1 Chipping jalan inspeksi eksisting 6.25 m3 Rp 843,900 Rp 5,274,375
2 Urugan pasir padat 404.68 m3 Rp 85,608 Rp 34,643,538
3 Lantai kerja K - 100 ; Tebal 5 cm 7.54 m3 Rp 535,920 Rp 4,040,742
4 Beton K - 225 40.08 m3 Rp 565,500 Rp 22,665,039
5 Bekisting / form work 275.44 m2 Rp 287,100 Rp 79,078,929
6 Wiremesh M6-150 1,110.88 kg Rp 9,570 Rp 10,631,102
7 Pemasangan batu belah 1 : 4 ; keliling tangki tebal 30 cm 100.96 m3 Rp 675,990 Rp 68,251,002
4 Pekerjaan saluran drainase keliling tangki :
1 Galian tanah 114.46 m3 Rp 287,100 Rp 32,860,888
2 Backfill 28.61 m3 Rp 150,510 Rp 4,306,768
3 Lantai kerja K - 100 ; Tebal 5 cm 8.80 m3 Rp 535,920 Rp 4,718,487
4 Bekisting / form work 675.01 m2 Rp 287,100 Rp 193,794,983
5 Beton K - 225 70.44 m3 Rp 565,500 Rp 39,831,380
6 Pembesian Ø8 2,744.12 kg Rp 11,310 Rp 31,036,013
5 Pekerjaan Pembuatan Oil Catcher, p x l x t = 60 x 50 x 50 mm
1 Galian tanah 0.20 m3 Rp 287,100 Rp 56,846
2 Backfill 0.04 m3 Rp 150,510 Rp 5,960
3 Buang tanah hasil galian 0.16 m3 Rp 957,000 Rp 151,589
4 Lantai kerja K - 100 ; Tebal 5 cm 0.03 m3 Rp 535,920 Rp 16,078
5 Bekisting / form work 3.24 m2 Rp 287,100 Rp 930,204
6 Beton K - 225 0.35 m3 Rp 565,500 Rp 196,794
7 Pembesian Ø8 14.24 kg Rp 11,310 Rp 161,023
6 Pekerjaan pondasi Pipe Support :
1 Bongkar pondasi beton pipa eksisting 5.13 m3 Rp 1,174,500 Rp 6,025,185
2 Angkut hasil bongkaran 5.13 m3 Rp 957,000 Rp 4,909,410
3 Galian tanah 13.78 m3 Rp 287,100 Rp 3,956,597
JUMLAH II Rp - Rp 2,270,970,236
Data Tangki
Kapasitas : 21,939 KL
Diameter : 46.98 m
Tinggi : 12.88 m
E Tank Appurtenance
1 Free Vent + In-Line Flame Arrester : 8 inch ASME #150 RF 4.00 set Rp 145,725 Rp 582,900
2 Gate Valve (Water drain) : 4 inch ASME #150 RF, ASTM A216 WCB 3.00 unit Rp 338,175 Rp 1,014,526
3 Gate Valve (Inlet) : 28 inch ASME #150 RF, ASTM A216 WCB 1.00 unit Rp 2,367,227 Rp 2,367,227
4 Gate Valve (Outlet) : 18 inch ASME #150 RF, ASTM A216 WCB 1.00 unit Rp 1,521,789 Rp 1,521,789
5 Check Valve (Inlet) : 28 inch ASME #150 RF, ASTM A216 WCB 1.00 unit Rp 2,367,227 Rp 2,367,227
6 Pipa water drain incl. asesories : 4 inch ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan 9.00 m Rp 338,175 Rp 3,043,577
7 Flexible Pipe : 18 inch ANSI 150# SS304 - 50cm Overall Length 1.00 unit Rp 1,521,789 Rp 1,521,789
8 Flexible Pipe : 28 inch ANSI 150# SS304 - 50cm Overall Length 1.00 unit Rp 2,367,227 Rp 2,367,227
9 Pengadaan & Pemasangan PSV
1 Pressure Safety Valve : 1" x 2" ASME #150 RF 2.00 bh Rp 169,088 Rp 338,175
2 Ball valve : 1" ASME #150 RF, ASTM A105 Gr. WCB, Non Metal Seal, Full Bore 2.00 bh Rp 84,544 Rp 169,088
3 Ball valve : 2" ASME #150 RF, ASTM A105 Gr. WCB, Non Metal Seal, Full Bore 2.00 bh Rp 169,088 Rp 338,175
4 Pipa : 1" API 5L Gr. B, SCH 40, ERW 1.00 m Rp 84,544 Rp 84,544
5 Pipa : 2" API 5L Gr. B, SCH 40, ERW 8.00 m Rp 169,088 Rp 1,352,701
6 Flange : 1" ASME #150 SO RF, ASTM A105 4.00 bh Rp 84,544 Rp 338,175
7 Flange : 2" ASME #150 SO RF, ASTM A105 4.00 bh Rp 169,088 Rp 676,351
8 Equal Tee : 2" ASTM A234 Gr. WPB SCH 40 BW 1.00 bh Rp 192,590 Rp 192,590
A Internal Coating for Bottom Plate, Shell Ring 1, Roof Plate, Roof Structure DFT 300 μm (airless spray)
1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 5,011.97 m2 Rp 75,777 Rp 379,792,019
2 Primer coating - phenolic epoxy c/w thinner, DFT 150 μm 5,011.97 m2 Rp 30,311 Rp 151,916,807
3 Finish coating - phenolic epoxy c/w thinner, DFT 150 μm 5,011.97 m2 Rp 30,311 Rp 151,916,807
F Jalur Pipa, Fitting, Flange & Aksesoris, DFT 250 μm (airless spray)
1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 256.13 m2 Rp 75,777 Rp 19,408,813
2 Primer coating - epoxy mastic c/w thinner, DFT 175 μm 256.13 m2 Rp 36,140 Rp 9,256,511
3 Finish coating - acrylic polyurethane c/w thinner, DFT 75 μm 256.13 m2 Rp 36,140 Rp 9,256,511
JUMLAH IV Rp - Rp 1,297,932,370
C Certificate of Inspection (COI) Tangki Timbun (PJIT persetujuan Migas) 1.00 ls Rp 174,870,000 Rp 174,870,000
JUMLAH V Rp 1,530,873,534
VI PEKERJAAN PENYELESAIAN
1 Pembersihan ex. Lokasi pekerjaan & membuang material sisa pekerjaan ke lokasi yang sudah ditentukan 1.00 ls Rp 19,650,725 Rp 19,650,725
JUMLAH VI Rp 19,650,725
TOTAL HARGA
NO WORK DESCRIPTION MATERIAL JASA
Rp. Rp.
TERBILANG :
Dua Belas Miliar Sembilan Ratus Sembilan puluh Sembilan Juta Sembilan Ratus Lima Ribu Rupiah
PURNOMO