Anda di halaman 1dari 7

Bill of Quantity (BOQ)

PROJECT : PT. PERSADA TEKNIK MANDIRI


LOKASI : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
MATA ANGGARAN : Bpk. Rahmat Putranto (Manager)
### 1

VOLUME HARGA SATUAN TOTAL HARGA


NO WORK DESCRIPTION MATERIAL JASA MATERIAL JASA
QTY UNIT
Rp. Rp. Rp. Rp.

I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi (Man Power, Peralatan, Material) 1.00 ls Rp 305,269,080 Rp 305,269,080
2 Temporary Facilities (Direksi Kit Container 20ft, Listrik Kerja) 1.00 ls Rp 594,611,592 Rp 594,611,592
3 Project Management 1.00 ls Rp 1,569,458,685 Rp 1,569,458,685
- Pembuatan Shop Drawing, Datasheet, Calculation, As Built Drawing, Project Procedure
- Review Engineering
- Man Power sesuai dengan RKS
- Dokumentasi dan Pelaporan
- Fit to Work Test (Medical Check-Up, DCU pemenuhan protokol kesehatan)
4 Pembuatan jalan akses sementara ke area tangki 1.00 ls Rp 249,427,260 Rp 249,427,260
- Bongkar dan pembuatan kembali bundwall
- Urugan pasir
- Plat
5 Pembersihan area kerja 1.00 ls Rp 8,160,600 Rp 8,160,600
6 Sewa Scaffolding 1.00 ls Rp 724,434,969 Rp 724,434,969
7 Tirai Air 1.00 ls Rp 154,351,920 Rp 154,351,920
8 Pembuatan dan pembongkaran kembali sistem penyangga (Strong Back) - Pipa CS 3" + Base plate 6 x 150 x 150 mm 1.00 ls Rp 34,274,520 Rp 34,274,520

JUMLAH I Rp 3,639,988,626

II PEKERJAAN SIPIL

1 Pekerjaan pengangkatan dan menurunkan Tangki menggunakan Sistem Hydraulic Jacking termasuk kelengkapannya 1.00 ls Rp 1,479,000,000 Rp 1,479,000,000
Kapasitas min. @ 50 Ton / titik - min. 39 titik
2 Pekerjaan perbaikan lapisan aspal
1 Pembongkaran lapisan aspal eksisting 1,763.26 m2 Rp 49,590 Rp 87,440,124
2 Pekerjaan pengaspalan ; Tebal min. 5 cm, slope 1 : 120 1,763.26 m2 Rp 60,900 Rp 107,382,609
3 Pekerjaan jalan inspeksi :
1 Chipping jalan inspeksi eksisting 6.25 m3 Rp 843,900 Rp 5,274,375
2 Urugan pasir padat 404.68 m3 Rp 85,608 Rp 34,643,538
3 Lantai kerja K - 100 ; Tebal 5 cm 7.54 m3 Rp 535,920 Rp 4,040,742
4 Beton K - 225 40.08 m3 Rp 565,500 Rp 22,665,039
5 Bekisting / form work 275.44 m2 Rp 287,100 Rp 79,078,929
6 Wiremesh M6-150 1,110.88 kg Rp 9,570 Rp 10,631,102
7 Pemasangan batu belah 1 : 4 ; keliling tangki tebal 30 cm 100.96 m3 Rp 675,990 Rp 68,251,002
4 Pekerjaan saluran drainase keliling tangki :
1 Galian tanah 114.46 m3 Rp 287,100 Rp 32,860,888
2 Backfill 28.61 m3 Rp 150,510 Rp 4,306,768
3 Lantai kerja K - 100 ; Tebal 5 cm 8.80 m3 Rp 535,920 Rp 4,718,487
4 Bekisting / form work 675.01 m2 Rp 287,100 Rp 193,794,983
5 Beton K - 225 70.44 m3 Rp 565,500 Rp 39,831,380
6 Pembesian Ø8 2,744.12 kg Rp 11,310 Rp 31,036,013
5 Pekerjaan Pembuatan Oil Catcher, p x l x t = 60 x 50 x 50 mm
1 Galian tanah 0.20 m3 Rp 287,100 Rp 56,846
2 Backfill 0.04 m3 Rp 150,510 Rp 5,960
3 Buang tanah hasil galian 0.16 m3 Rp 957,000 Rp 151,589
4 Lantai kerja K - 100 ; Tebal 5 cm 0.03 m3 Rp 535,920 Rp 16,078
5 Bekisting / form work 3.24 m2 Rp 287,100 Rp 930,204
6 Beton K - 225 0.35 m3 Rp 565,500 Rp 196,794
7 Pembesian Ø8 14.24 kg Rp 11,310 Rp 161,023
6 Pekerjaan pondasi Pipe Support :
1 Bongkar pondasi beton pipa eksisting 5.13 m3 Rp 1,174,500 Rp 6,025,185
2 Angkut hasil bongkaran 5.13 m3 Rp 957,000 Rp 4,909,410
3 Galian tanah 13.78 m3 Rp 287,100 Rp 3,956,597

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 1/7
Bill of Quantity (BOQ)
PROJECT : PT. PERSADA TEKNIK MANDIRI
LOKASI : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
MATA ANGGARAN : Bpk. Rahmat Putranto (Manager)
### 1

VOLUME HARGA SATUAN TOTAL HARGA


NO WORK DESCRIPTION MATERIAL JASA MATERIAL JASA
QTY UNIT
Rp. Rp. Rp. Rp.
4 Backfill 3.45 m3 Rp 150,510 Rp 518,554
5 Lantai kerja K - 100 ; Tebal 5 cm 0.92 m3 Rp 535,920 Rp 492,377
6 Bekisting / form work 21.24 m2 Rp 287,100 Rp 6,098,004
7 Beton K – 250 6.38 m3 Rp 565,500 Rp 3,605,911
8 Pembesian D13 897.80 kg Rp 11,310 Rp 10,154,094
7 Pekerjaan Struktur Baja Support
1 H Beam 200x200x8x12 ASTM A36 1,101.13 kg Rp 25,230 Rp 27,781,500
2 Painting / Coating 3 lapis 23.04 m2 Rp 41,412 Rp 954,132

JUMLAH II Rp - Rp 2,270,970,236

III PEKERJAAN MEKANIKAL TANGKI

Data Tangki
Kapasitas : 21,939 KL
Diameter : 46.98 m
Tinggi : 12.88 m

A Pembongkaran Material Eksisting Tangki


1 Bottom Plate (Bongkar Las Potong) 617.39 m Rp 48,070 Rp 29,678,219
1 Roof Plate (Bongkar Las Potong) 570.22 m Rp 48,070 Rp 27,410,454
2 Bongkar Rafter/Struktur (termasuk alat bantu kerja, dll) 69,400.83 kg Rp 13,270 Rp 920,969,793
3 Pengangkutan plat/struktur baja ex bongkaran ke tempat yg ditentukan (termasuk alat bantu kerja, dll) 172,667.29 kg Rp 2,653 Rp 458,148,472
4 Asesories tangki
1 Bongkar dan pasang kembali Jalur In-Out Tangki 1.00 ls Rp 10,016,331 Rp 10,016,331
a. Jalur Inlet 18" - sampai MOV terdekat (incl gasket, bolt & nuts dan asesories)
b. Jalur Inlet 28" - sampai MOV terdekat (incl gasket, bolt & nuts dan asesories)
2 Bongkar dan pasang kembali Instrumentasi ATG dan SDD incl asesories 1.00 ls Rp 11,082,095 Rp 11,082,095
3 Bongkar instalasi PVV dan Free Vent incl asesories 1.00 ls Rp 2,506,470 Rp 2,506,470
4 Bongkar Foam Chamber dan Fire Protection Sytem incl asesories 1.00 ls Rp 5,341,473 Rp 5,341,473
a. Foam Chamber
b. Top Pourer

B Erection, Penyetelan dan Pengelasan


1 Bottom Plate
a. ASTM A 283 Gr. C (6 mm x 6096 mm x 1828 mm) 146.00 lbr Rp 2,284,385 Rp 333,520,225
b. ASTM A 283 Gr. C (8 mm x 6096 mm x 1828 mm) 26.00 lbr Rp 2,284,385 Rp 59,394,013
c. ASTM A 283 Gr. C (10 mm x 6096 mm x 1828 mm) 1.00 lbr Rp 2,284,385 Rp 2,284,385
2 Roof Plate
a. ASTM A 283 Gr. C (6 mm x 6096 mm x 1828 mm) 182.00 lbr Rp 2,284,385 Rp 415,758,088
3 Rafter & Structure
1 Kolom Pipa 10" Sch.40 ASTM A252 Gr.2 254.00 m Rp 291,450 Rp 74,028,300
2 Kolom Pipa 8" Sch.40 ASTM A252 Gr.2 283.00 m Rp 262,305 Rp 74,232,315
3 Girder H 300x150x6.5x9 3,935.00 kg Rp 14,573 Rp 57,342,788
4 Girder H 250x125x6x9 3,261.00 kg Rp 14,573 Rp 47,520,923
5 Purlin C 150x75x6.5 1,411.00 kg Rp 14,573 Rp 20,561,798
6 Plate, Bolts & Nuts, incl. asesories 9,053.00 kg Rp 9,793 Rp 88,653,494
7 Top Angle - L 200x200x15 incl. Plate, Bolts & Nuts, incl. asesories 7,359.69 kg Rp 14,573 Rp 107,249,146
4 Spiral Staiways
1 Grating 32x3/30x100/Serrated/Galvanized 6.72 kg Rp 14,573 Rp 97,923
4 Roof Perimeter Handrail
1 L 75x75x6 858.99 kg Rp 14,573 Rp 12,517,632
2 Pipe 1-1/4" SCH.40 147.60 m Rp 29,213 Rp 4,311,733
3 Flat Bar 50x6 347.59 kg Rp 9,909 Rp 3,444,413
4 Flat Bar 75x6 521.39 kg Rp 9,909 Rp 5,166,620

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 2/7
Bill of Quantity (BOQ)
PROJECT : PT. PERSADA TEKNIK MANDIRI
LOKASI : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
MATA ANGGARAN : Bpk. Rahmat Putranto (Manager)
### 1

VOLUME HARGA SATUAN TOTAL HARGA


NO WORK DESCRIPTION MATERIAL JASA MATERIAL JASA
QTY UNIT
Rp. Rp. Rp. Rp.
5 Plate, Bolts & Nuts, dll. 334.25 kg Rp 9,909 Rp 3,312,183
5 Acccess Roof Platform
1 PL. 6x250 471.00 kg Rp 9,909 Rp 4,667,280
2 L 75x75x6 416.48 kg Rp 14,573 Rp 6,069,155
3 L 75x75x6 342.50 kg Rp 14,573 Rp 4,991,081
4 L 75x75x6 128.44 kg Rp 14,573 Rp 1,871,655
5 Pipe 1-1/4" SCH.40 50.00 m Rp 29,213 Rp 1,460,631
6 Flat Bar 50x6 117.75 kg Rp 9,909 Rp 1,166,820
7 Flat Bar 75x6 176.63 kg Rp 9,909 Rp 1,750,230
8 Grating 32x3/30x100/G/S 18.75 m2 Rp 65,576 Rp 1,229,555
9 Plate, Bolts & Nuts, dll. 273.34 kg Rp 14,573 Rp 3,983,304
6 Jacking lug 39.00 set Rp 64,119 Rp 2,500,641
7 Stilling Well ATG, API 5L Grade B Sch. 40 dia. 6" c/w support, hole dia. 25 mm dengan jarak maksimum 150 mm 1.00 set Rp 21,684 Rp 21,684
8 Meja ukur incl. asesoris 1.00 set Rp 4,255,170 Rp 4,255,170
9 Pekerjaan support Pipa
1 Pondasi Beton Pipe Support Inlet & Outlet
1 Bongkar pondasi beton eksisting 10.80 m3 Rp 1,093,520 Rp 11,810,020
2 Galian tanah 18.00 m3 Rp 4,220,196 Rp 75,963,528
3 Backfill 4.50 m3 Rp 4,220,196 Rp 18,990,882
4 Lantai kerja K - 100 ; Tebal 5 cm 0.90 m3 Rp 816,060 Rp 734,454
5 Bekisting / form work 30.00 m2 Rp 652,848 Rp 19,585,440
6 Beton K – 250 8.28 m3 Rp 816,060 Rp 6,756,977
7 Pembesian D16 & D13 1,358.70 kg Rp 9,909 Rp 13,463,787
2 Pekerjaan Struktur Baja Pipe Support Inlet & Outlet
1 H Beam 200x200x8x12 ASTM A36 1,376.41 kg Rp 14,573 Rp 20,057,764
2 Painting / Coating 28.80 m2 Rp 30,311 Rp 872,951

C Shell and Roof Opening


1 Roof - Free Vent : 8 inch ASME #150 SO RFWN 4.00 set Rp 145,725 Rp 582,900
2 Roof - Dip Hatch : 8 inch ASME #150 SO RFWN 1.00 set Rp 145,725 Rp 145,725
3 Roof - ATG : 6 inch ASME #150 SO RFWN c/w well 1.00 set Rp 112,471 Rp 112,471
4 Roof - Temp Transmitter : 2 inch ASME #150 SO RFWN 1.00 set Rp 41,170 Rp 41,170
5 Roof - Nozzle Return From PRV/PSV : 2 inch ASME #150 SO RFWN 1.00 set Rp 41,170 Rp 41,170
6 Roof - Manhole : 24 inch ASME #150 SO RFWN c/w blind flange 2.00 set Rp 402,182 Rp 804,365
7 Roof - Emergency Vent : 24 inch ASME #150 SO RFWN c/w blind flange 1.00 set Rp 402,182 Rp 402,182
8 Shell - Liquid Drain : 4 inch ASME #150 SO RFWN 3.00 set Rp 338,175 Rp 1,014,526

E Tank Appurtenance
1 Free Vent + In-Line Flame Arrester : 8 inch ASME #150 RF 4.00 set Rp 145,725 Rp 582,900
2 Gate Valve (Water drain) : 4 inch ASME #150 RF, ASTM A216 WCB 3.00 unit Rp 338,175 Rp 1,014,526
3 Gate Valve (Inlet) : 28 inch ASME #150 RF, ASTM A216 WCB 1.00 unit Rp 2,367,227 Rp 2,367,227
4 Gate Valve (Outlet) : 18 inch ASME #150 RF, ASTM A216 WCB 1.00 unit Rp 1,521,789 Rp 1,521,789
5 Check Valve (Inlet) : 28 inch ASME #150 RF, ASTM A216 WCB 1.00 unit Rp 2,367,227 Rp 2,367,227
6 Pipa water drain incl. asesories : 4 inch ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan 9.00 m Rp 338,175 Rp 3,043,577
7 Flexible Pipe : 18 inch ANSI 150# SS304 - 50cm Overall Length 1.00 unit Rp 1,521,789 Rp 1,521,789
8 Flexible Pipe : 28 inch ANSI 150# SS304 - 50cm Overall Length 1.00 unit Rp 2,367,227 Rp 2,367,227
9 Pengadaan & Pemasangan PSV
1 Pressure Safety Valve : 1" x 2" ASME #150 RF 2.00 bh Rp 169,088 Rp 338,175
2 Ball valve : 1" ASME #150 RF, ASTM A105 Gr. WCB, Non Metal Seal, Full Bore 2.00 bh Rp 84,544 Rp 169,088
3 Ball valve : 2" ASME #150 RF, ASTM A105 Gr. WCB, Non Metal Seal, Full Bore 2.00 bh Rp 169,088 Rp 338,175
4 Pipa : 1" API 5L Gr. B, SCH 40, ERW 1.00 m Rp 84,544 Rp 84,544
5 Pipa : 2" API 5L Gr. B, SCH 40, ERW 8.00 m Rp 169,088 Rp 1,352,701
6 Flange : 1" ASME #150 SO RF, ASTM A105 4.00 bh Rp 84,544 Rp 338,175
7 Flange : 2" ASME #150 SO RF, ASTM A105 4.00 bh Rp 169,088 Rp 676,351
8 Equal Tee : 2" ASTM A234 Gr. WPB SCH 40 BW 1.00 bh Rp 192,590 Rp 192,590

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 3/7
Bill of Quantity (BOQ)
PROJECT : PT. PERSADA TEKNIK MANDIRI
LOKASI : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
MATA ANGGARAN : Bpk. Rahmat Putranto (Manager)
### 1

VOLUME HARGA SATUAN TOTAL HARGA


NO WORK DESCRIPTION MATERIAL JASA MATERIAL JASA
QTY UNIT
Rp. Rp. Rp. Rp.
9 Elbow 90 Deg : 2" ASTM A234 Gr. WPB SCH 40 BW 4.00 bh Rp 169,088 Rp 676,351
10 Sockolet : 1" ASME #3000, ASTM A105 2.00 bh Rp 84,544 Rp 169,088
11 Gasket : 1" Spiral Wound 3.0MM & Seat SS304/SS316L #150 2.00 bh
12 Gasket : 2" Spiral Wound 3.0MM & Seat SS304/SS316L #150 2.00 bh
13 Bolt & Nuts : 5/8" x 2,75'" Stud Bolts With Nuts ASTM A193-B8 / A194-2H 16.00 set
14 Bolt & Nuts : 5/8" x 3,25" Stud Bolts With Nuts ASTM A193-B8 / A194-2H 16.00 set

F Tank Fire System


1 Pipa Roof Sprayer (Top Pourer)
1 Pipa Top Pourer : 4" ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan di atas support 39.00 m Rp 338,175 Rp 13,188,835
2 Elbow 45 : 4" schd. 40 ASTM A-234 WPB BW LR SEAMLESS 2.00 bh Rp 338,175 Rp 676,351
3 Elbow 90 : 4" schd. 40 ASTM A-234 WPB BW LR SEAMLESS 1.00 bh Rp 338,175 Rp 338,175
4 Flange : 4" Slip On A105 Class 150 RF 6.00 bh Rp 338,175 Rp 2,029,052
5 Flexible Pipe : 4" ANSI 150# SS304 - 50cm Overall Length 1.00 bh Rp 338,175 Rp 338,175
6 Gasket : 4" Spiral Wound 3.0MM & Seat SS304/SS316L #150 4.00 bh
7 Bolt & Nuts : 5/8" x 3,75" Stud Bolts With Nuts ASTM A193-B8 / A194-2H 32.00 set
8 Pipe support (Roof to Top) : L - 60x60x6 - Plate 6 x 150 x 150 - UBolt 8.00 set Rp 995,593 Rp 7,964,746
2 Pipa Water Sprayer
1 Pipa Riser Water Sprayer : 3" ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan di atas support 41.00 m Rp 60,521 Rp 2,481,375
2 Pipa Ring Water Sprayer (Shell) : 3" ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan di atas support 298.00 m Rp 60,521 Rp 18,035,359
3 Pipa Ring Water Sprayer (Roof) : 3" ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan di atas support 307.00 m Rp 60,521 Rp 18,580,051
4 Elbow 45 : 3" schd. 40 ASTM A-234 WPB BW LR SEAMLESS 8.00 bh Rp 60,521 Rp 484,171
5 Elbow 90 : 3" schd. 40 ASTM A-234 WPB BW LR SEAMLESS 4.00 bh Rp 60,521 Rp 242,085
6 Equal Tee : 3" A-234 WPB BW Schd. 40 SEAMLESS 3.00 bh Rp 60,521 Rp 181,564
7 Cross Tee : 3" A-234 WPB BW Schd. 40 SEAMLESS 3.00 bh Rp 60,521 Rp 181,564
8 Flange : 3" A105 Class 150 RF 92.00 bh Rp 60,521 Rp 5,567,963
9 Blind Flange : 3" A105 Class 150 RF 12.00 bh Rp 60,521 Rp 726,256
10 Flexible Pipe : 3" ANSI 150# SS304 - 50cm Overall Length 4.00 bh Rp 60,521 Rp 242,085
11 Threadolet : Ø 1/2" x 3" SA/A105N MSS SP-97 174.58 bh
12 Gasket : 3" Spiral Wound 3.0MM & Seat SS304/SS316L #150 65.00 bh
13 Bolt & Nuts : 5/8" x 3,75" Stud Bolts With Nuts ASTM A193-B8 / A194-2H 520.00 set
14 Nozzle Sprinkler (Shell) : 1/2" NPT,316 Stainles Steel / Brass, 140/150/160 Deg, K-19/20/22, Flat Type 89.00 unit Rp 26,657 Rp 2,372,489
15 Nozzle Sprinkler (Roof) : 1/2" NPT,316 Stainles Steel / Brass, 140/150/160 Deg, K-21/22, MV Type 85.66 unit Rp 26,657 Rp 2,283,495
16 Pipe support (Shell Clip) : L 75x75x6 - Plate 115x115x6mm - UBolt 24.00 set Rp 497,797 Rp 11,947,118
17 Pipe support (Ring System) : L 75x75x6 - Plate 115x115x6mm - UBolt 200.00 set Rp 497,797 Rp 99,559,320
3 Foam Chamber
1 Pipa Foam Chamber : 4" ASTM A53 Gr. A, SCH 40, ERW, incl. penyetelan, pengelasan dan pemasangan di atas support 52.00 m Rp 338,175 Rp 17,585,114
2 Flange : 4" Slip On A105 Class 150 RF 40.00 bh Rp 338,175 Rp 13,527,010
3 Elbow 45 : 4" schd. 40 ASTM A-234 WPB BW LR SEAMLESS 8.00 bh Rp 338,175 Rp 2,705,402
4 Elbow 90 : 4" schd. 40 ASTM A-234 WPB BW LR SEAMLESS 4.00 bh Rp 338,175 Rp 1,352,701
5 Flexible Pipe : 4" ANSI 150# SS304 - 50cm Overall Length 4.00 bh Rp 338,175 Rp 1,352,701
6 Gasket : 4" Spiral Wound Gasket 3.0MM & Seat SS304/SS316L #150 36.00 bh
7 Bolt & Nuts : 3/4" x 4" Stud Bolts With Nuts ASTM A193-B8 / A194-2H 288.00 bh
8 Pipe support : L 75x75x6 - Plate 115x115x6mm - UBolt 24.00 set Rp 497,797 Rp 11,947,118
9 Foam Chamber : 4" x 8" 4.00 unit Rp 497,797 Rp 1,991,186
10 Platform Foam Chamber :
1 UNP 150 x 65 x 6.5 108.48 kg Rp 14,573 Rp 1,580,791
2 Pipa Ø1 1/4 sch 40 21.29 kg Rp 14,573 Rp 310,237
3 L 65 x 65 x 6 78.72 kg Rp 14,573 Rp 1,147,165
4 L 75 x 75 x 6 25.59 kg Rp 14,573 Rp 372,934
5 FB 50 x 6 9.24 kg Rp 14,573 Rp 134,653
6 FB 75 x 6 14.47 kg Rp 14,573 Rp 210,908
7 PL 6 mm 8.24 kg Rp 14,573 Rp 120,102
8 PL 10 mm 3.28 kg Rp 14,573 Rp 47,832
9 Grating 32x3/30x100/Serrated/Galvanized 63.20 kg Rp 14,573 Rp 921,018

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 4/7
Bill of Quantity (BOQ)
PROJECT : PT. PERSADA TEKNIK MANDIRI
LOKASI : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
MATA ANGGARAN : Bpk. Rahmat Putranto (Manager)
### 1

VOLUME HARGA SATUAN TOTAL HARGA


NO WORK DESCRIPTION MATERIAL JASA MATERIAL JASA
QTY UNIT
Rp. Rp. Rp. Rp.
10 FB 50 x 9 19.01 kg Rp 14,573 Rp 277,061
11 RB Ø19 7.38 kg Rp 14,573 Rp 107,545

E Pekerjaan Elektrikal dan Instrumen


1 Bongkar, pasang dan instalasi kembali sistem grounding Tangki 1.00 ls Rp 35,403,884 Rp 35,403,884

JUMLAH III Rp - Rp 3,277,533,894

IV PEKERJAAN COATING / PENGECATAN

A Internal Coating for Bottom Plate, Shell Ring 1, Roof Plate, Roof Structure DFT 300 μm (airless spray)
1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 5,011.97 m2 Rp 75,777 Rp 379,792,019
2 Primer coating - phenolic epoxy c/w thinner, DFT 150 μm 5,011.97 m2 Rp 30,311 Rp 151,916,807
3 Finish coating - phenolic epoxy c/w thinner, DFT 150 μm 5,011.97 m2 Rp 30,311 Rp 151,916,807

C Eksternal Shell, DFT 250 μm (airless spray)


1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 1,604.66 m2 Rp 75,777 Rp 121,596,493
2 Primer coating - epoxy mastic c/w thinner, DFT 175 μm 1,604.66 m2 Rp 36,140 Rp 57,992,174
3 Finish coating - acrylic polyurethane c/w thinner, DFT 75 μm 1,604.66 m2 Rp 36,140 Rp 57,992,174

D Eksternal Roof, DFT 250 μm (airless spray)


1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 1,757.53 m2 Rp 75,777 Rp 133,180,273
2 Primer coating - epoxy mastic c/w thinner, DFT 175 μm 1,757.53 m2 Rp 36,140 Rp 63,516,746
3 Finish coating - acrylic polyurethane c/w thinner, DFT 75 μm 1,757.53 m2 Rp 36,140 Rp 63,516,746

E Stairway & Handrail, DFT 250 μm (airless spray)


1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 530.81 m2 Rp 75,777 Rp 40,223,380
2 Primer coating - epoxy mastic c/w thinner, DFT 175 μm 530.81 m2 Rp 36,140 Rp 19,183,458
3 Finish coating - acrylic polyurethane c/w thinner, DFT 75 μm 530.81 m2 Rp 36,140 Rp 19,183,458

F Jalur Pipa, Fitting, Flange & Aksesoris, DFT 250 μm (airless spray)
1 Surface preparation w/ sandblasting as SSPC-SP-10/SIS-SA 2.1/2 256.13 m2 Rp 75,777 Rp 19,408,813
2 Primer coating - epoxy mastic c/w thinner, DFT 175 μm 256.13 m2 Rp 36,140 Rp 9,256,511
3 Finish coating - acrylic polyurethane c/w thinner, DFT 75 μm 256.13 m2 Rp 36,140 Rp 9,256,511

JUMLAH IV Rp - Rp 1,297,932,370

V PEKERJAAN INSPEKSI, TEST, KALIBRASI DAN FINISHING

A Inspeksi dan Pengujian / Test Tangki


1 Vacuum Test 1.00 ls Rp 192,860,626 Rp 192,860,626
2 Pengujian coating (thickness, holiday test, pull test) 1.00 ls Rp 287,194,830 Rp 287,194,830
3 Roundness-Plumbness test 1.00 ls Rp 42,435,120 Rp 42,435,120
4 Peaking bending test 1.00 ls Rp 4,962,577 Rp 4,962,577
5 Hydrostatic test 1.00 ls Rp 192,823,320 Rp 192,823,320
6 Pneumatic Test (Shell Opening - Liquid Drain) 1.00 ls Rp 37,801,065 Rp 37,801,065
7 Dye penetrant (Shell Opening - Liquid Drain) : 100 % 1.00 ls Rp 157,383,000 Rp 157,383,000
8 Terra Tangki Dit. Metrologi (PJIT persetujuan Migas) 1.00 ls Rp 87,435,000 Rp 87,435,000

B Inspeksi dan Pengujian / Test Pipa


1 Dye penetrant : 100 % 1.00 ls Rp 42,843,150 Rp 42,843,150
2 Pengujian coating (thickness) 1.00 ls Rp 76,062,621 Rp 76,062,621
3 Hydrostatic test 1.00 ls Rp 66,322,362 Rp 66,322,362

C Certificate of Inspection (COI) Tangki Timbun (PJIT persetujuan Migas) 1.00 ls Rp 174,870,000 Rp 174,870,000

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 5/7
Bill of Quantity (BOQ)
PROJECT : PT. PERSADA TEKNIK MANDIRI
LOKASI : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
MATA ANGGARAN : Bpk. Rahmat Putranto (Manager)
### 1

VOLUME HARGA SATUAN TOTAL HARGA


NO WORK DESCRIPTION MATERIAL JASA MATERIAL JASA
QTY UNIT
Rp. Rp. Rp. Rp.
D Sertifikasi-Kalibrasi PRV dan PV Valve (PJIT persetujuan Migas) 1.00 ls Rp 64,119,000 Rp 64,119,000
E Mechanical completion, start-up dan commisioning 1.00 ls Rp 103,760,863 Rp 103,760,863

JUMLAH V Rp 1,530,873,534

VI PEKERJAAN PENYELESAIAN

1 Pembersihan ex. Lokasi pekerjaan & membuang material sisa pekerjaan ke lokasi yang sudah ditentukan 1.00 ls Rp 19,650,725 Rp 19,650,725

JUMLAH VI Rp 19,650,725

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 6/7
Rekapitulasi Bill of Quantity (BOQ)
KEPADA : PT. PERSADA TEKNIK MANDIRI
ALAMAT : JL. KH. Mansur No. 179, Nerogtog, Tangerang, Indonesia
Up : Bpk. Rahmat Putranto (Manager)
-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

PROJECT : REVITALISASI TANGKI TIMBUN 213


LOKASI : IT BALONGAN
MATA ANGGARAN : 20F3.001
REVISI - 1

TOTAL HARGA
NO WORK DESCRIPTION MATERIAL JASA
Rp. Rp.

I PEKERJAAN PERSIAPAN Rp 3,639,988,626

II PEKERJAAN SIPIL Rp - Rp 2,270,970,236

III PEKERJAAN MEKANIKAL TANGKI Rp - Rp 3,277,533,894

IV PEKERJAAN COATING / PENGECATAN Rp - Rp 1,297,932,370

V PEKERJAAN INSPEKSI, TEST, KALIBRASI DAN FINISHING Rp 1,530,873,534

VI PEKERJAAN PENYELESAIAN Rp 19,650,725

JUMLAH I s.d. VI Rp - Rp 12,036,949,384


MATERIAL DAN JASA Rp 12,036,949,384
KEUNTUNGAN DAN RESIKO 8 % Rp 962,955,951
TOTAL Rp 12,999,905,335
PEMBULATAN Rp 12,999,905,000
VERIFIKATOR TKDN At Cost

TERBILANG :
Dua Belas Miliar Sembilan Ratus Sembilan puluh Sembilan Juta Sembilan Ratus Lima Ribu Rupiah

Quotation Terms & Condition : Surabaya 19 September 2023


1. The price excludes 11% PPn.
2. The price shown above is NET . PT. BRAZELL BASS INDONESIA
3. The price term is FRANCO DIREKTUR
4. The scope of work is displayed above, with details attached on another page (BOQ).
5. The project work started after the down payment was received in full
6. Term of payment :
a. Payment I (Down payment) is 20% of the total price.
b. Payment II (Progress Payment) as per 10% of the total work (TERMIJN)
c. Maximum payment deadline is 5 working days after the invoice released.

PURNOMO

REVITALISASI TANGKI TIMBUN 213


IT BALONGAN 7/7

Anda mungkin juga menyukai