2) Pekerjaan beton
a. Beton K-350 NFA untuk balok beton; readymix m3 43.6 5.5% 5 1.1% 1.1% 1.1% 1.1% 1.1%
3) Pekerjaan Pembesian
a. Besi beton ulir U-39, untuk dia. 10 mm untuk balok beton kg 2,876.0 4.9% 5 1.0% 1.0% 1.0% 1.0% 1.0%
4) Pagar
a. Pre cast Concrete panel (50 x 400 x 2400) ex. BEP m1 531.4 22.9% 6 3.8% 3.8% 3.8% 3.8% 3.8% 3.8%
h = 2000 mm, K-400
b. Kolom Pre cast (200x160) mm & (200x200) mm untuk sudut bh 222.0 7.2% 5 1.4% 1.4% 1.4% 1.4% 1.4%
ex. BEP, K-400
c. Besi siku L-40x40x3.5 / 2.42 kg/m galvanized e. Trikarya m1 531.4 6.0% 2 3.0% 3.0%
Kawat berduri Beva Barb 5 baris galvanis tebal 260-300 g/m2
ex. Bevananda Mustika
5) Lain-lain
a. Anchor D13 @500 mm panjang 500 mm bh 1152.0 1.1% 5 0.2% 0.2% 0.2% 0.2% 0.2%
3 0 10 15 15 15 15 12 4 0 1 5 5 1
100.0%
KOMULATIF 3 4 14 29 44 58 73 85 89 89 89 94 99 100
AKTUAL
KOM.AKTUAL
APROVE BY ADHI