NO JENIS PEKERJAAN
Galian Tanah ( 3 * 3 * 5
( 6 * 1 * 2
( 28 * 1 * 2
( 15 * 2 * 6
Urugan Kembali ( 3 * 3 * 5
( 6 * 1 * 2
( 28 * 1 * 2
( 15 * 2 * 6
TA KOTA MALANG
PERHITUNGAN VOLUME
)* 1 = 45 M3
)* 1 = 12 M3
)* 1 = 56 M3
)* 1 = 180 M3 +
293 M3
293 * 1 =
)* 1 = 45 M3
)* 1 = 12 M3
)* 1 = 56 M3
)* 1 = 180 M3 +
293 M3
* 52 )* 1 = 6.5371 M3 +
6.5371 M3
293 - 6.5371 * 1 =
293
293
286.462857142857
286.462857142857
RENCANA ANGGARAN BIAYA
HARGA (Rp.)
ANALISA
SATUAN HARGA SATUAN HARGA SELURUH
5 6 7 8
: B.01. A 78,395.37 22,969,842.92
22,969,842.92
: B.10 32,042.50 9,178,986.09
9,178,986.09
REKAPITULASI RENCANA ANGGARAN BIAYA
Keterangan : Biaya tersebut diatas berdasarkan analisa SNI Malang, 07 December 2021
VOLUME PEKERJAAN
PEKERJAAN : PEMASANGAN INTERKONEKSI PIPA BALANCE PIPA PE O 400 MM SEPANJANG 52 METER
LOKASI : JL KH MALIK (TANDON AIR BURING) PERUMDA AIR MINUM TUGU TIRTA KOTA MALANG
4 BUANGAN TANAH GALIAN TANAH KERAS + GALIAN TANAH BIASA - URUGAN TANAH KEMBALI 0.00000 + 0.00000 - 0.00000 = 0.00000 m3
5 PEMBUATAN THURST BLOCK
BEND
HDPE PN 12.5 16 ((( 0.9 x 1.5188 )+( 0.55 x 0.9 ))/ 2 )x 0.3 x 4 titik = 1.11714 m3
HDPE PN 12.5 16 ((( 0.9 x 1.5188 )+( 0.55 x 0.9 ))/ 2 )x 0.3 x 2 titik = 0.55857 m3
I PEKERJAAN PERSIAPAN
PENGUKURAN PIPA U/ MC 0 km 1.0000
II PEKERJAAN PASANGAN
PEMBUATAN THURSTBLOCK M3 5.8949
B. AKSESORIS JARINGAN
1. DETAIL 1
PACKING KARET FLANGE EPDM 16" buah 1.0000
PACKING KARET FLANGE EPDM 24'' buah 3.0000
STUB FLANGE 400 MM 16'' buah 1.0000
STUB FLANGE 630 MM 24'' buah 2.0000
PIPA GP 24" m 1.0000
ALL FLANGE TEE 24" X 16" buah 1.0000
MUR BAUT (JUMLAH 16 BH) 1'' X 4 1/2" lokal 16.0000
MUR BAUT (JUMLAH 20 BH) 1 1/4'' X 5 1/2" buah 60.0000
PLENDES/FLANGE & LUBANG 24'' buah 2.0000
2. DETAIL 2 (4X)
BUTTFUSION ELBOW 45 PN12.5 400 MM 16'' buah 4.0000
3. DETAIL 3
BUTTFUSION ELBOW 45 PN12.5 400 MM 16'' buah 2.0000
4. DETAIL 4
GATE VALVE RESILENT 16" buah 1.0000
PACKING KARET FLANGE EPDM 12" buah 3.0000
PACKING KARET FLANGE EPDM 16" buah 4.0000
PIPA GP/MS 12" meter 1.0000
PLENDES/FLANGE & LUBANG 12" buah 2.0000
REDUCER ALL FLANGE 16" X 12" buah 2.0000
STUB FLANGE 400 MM 16'' buah 1.0000
MUR BAUT (JUMLAH 12 BH) 7/8'' X 4" lokal 36.0000
ALL FLANGE TEE 16" X 16" buah 1.0000
MUR BAUT (JUMLAH 16 BH) 1'' X 4 1/2" lokal 64.0000
5. PENYAMBUNGAN BUTTFUSION
PENYAMBUNGAN PIPA HDPE 16" (BUTTFUSION) 16'' buah 4.0000
2. UPAH
A. PEMASANGAN PIPA
HDPE PN 12.5 16 m 52.0000
B. UPAH DETAIL 1
STUB FLANGE 400 MM 16'' titik 1.0000
STUB FLANGE 630 MM 24'' titik 2.0000
ALL FLANGE TEE 24" X 16" titik 1.0000
C. UPAH DETAIL 2 (4X)
BUTTFUSION ELBOW 45 PN12.5 400 MM 16'' titik 4.0000
D. UPAH DETAIL 3
BUTTFUSION ELBOW 45 PN12.5 400 MM 16'' titik 2.0000
E. UPAH DETAIL 4
GATE VALVE RESILENT 16" titik 1.0000
STUB FLANGE 400 MM 16'' titik 1.0000
ALL FLANGE TEE 16" X 16" titik 1.0000
F. UPAH PENYAMBUNGAN BUTTFUSION
PENYAMBUNGAN PIPA HDPE 16" (BUTTFUSION) 16'' titik 4.0000
G. BIAYA PENGELASAN
HDPE PN 12.5 24 M 594.0000
HDPE PN 12.5 16 M 377.1429
HARGA (Rp.)
ANALISA
SATUAN HARGA SATUAN HARGA SELURUH
5 6 7 8
LS 100,000.00 100,000.00
100,000.00
Keterangan : Biaya tersebut diatas berdasarkan analisa SNI Malang, 07 December 2021
Menyetujui,
Manajer Perencanaan Teknik
Hendrik Ribowo, ST
NPP : 06090593
Mengetahui, Mengetahui,
Direktur Administrasi dan Keuangan Direktur Teknik
Disetujui,
Untuk dilaksanakan,
Direktur Utama
M. Nor Muhlas, S.Pd, M.Si