REKAPITULASI
RENCANA ANGGARAN BIAYA RENOVASI RUKO
PEKERJAAN RENOVASI EXTERIOR, INTERIOR DAN ME
LANTAI 1
I PEKERJAAN PERSIAPAN 8,250,000
II PEKERJAAN BONGKARAN 1,500,000
III PEKERJAAN INTERIOR 14,371,000
IV PEKERJAAN PINTU 4,950,000
V PEKERJAAN FINISHING 10,815,000
VI PEKERJAAN SANITAIR 969,000
VII PEKERJAAN FURNITURE 24,000,000
TOTAL LANTAI 1 64,855,000
LANTAI 2
I PEKERJAAN INTERIOR 31,890,600
II PEKERJAAN PINTU 18,567,500
III PEKERJAAN FINISHING 11,200,000
IV PEKERJAAN SANITAIR 6,018,000
V PEKERJAAN FURNITURE -
TOTAL LANTAI 2 67,676,100
TOTAL 132,531,100
PEMBULATAN 132,500,000
Terbilang : Seratus Tiga Puluh Dua Juta Lima Ratus Ribu Rupiah
1 2 3 4 5 6 7 8
I PEKERJAAN PERSIAPAN
1 Perapihan dan kebersihan lokasi kerja 1.00 ls 750,000 750,000
2 Air dan listrik kerja 1.00 ls 1,000,000 1,000,000
3 Peralatan dan material bantu (scaffolding, terpal, plastik cor, exhaust/blower, dll.) 1.00 ls 1,500,000 1,500,000
4 Pekerjaan desain dan gambar 1.00 ls 5,000,000 5,000,000
TOTAL I 8,250,000
II PEKERJAAN BONGKARAN
1 Bongkar Folding gate 1.00 unit 1,500,000 1,500,000
TOTAL II 1,500,000
III PEKERJAAN INTERIOR
A PEKERJAAN LANTAI
LANTAI 1
1 Perbaikan lantai eksisting akibat bongkaran dan/atau penggantian yang rusak 5.00 m² 300,000 1,500,000
2 seperti pop-up,
Plint lantai Areapecah, dll.
Back Office 77.00 m¹ 61,000 4,697,000
- Tinggi 100 mm
- GRC 10 mm fin. Cat Glovin 300 Natural White ex. Avian Paint
B PEKERJAAN PLAFON
LANTAI 1
1 List plafond gypsum (ukuran dan desain mengikuti eksisting ) 30.00 m¹ 51,300 1,539,000
2 Main hole pada plafond 1.00 unit 150,000 150,000
3 Perbaikan plafon eksisting akibat pekerjaan 1.00 LS 1,000,000 1,000,000
Page 3 of 13
LANTAI 1
1 2 3 4 5 6 7 8
TOTAL IV 4,950,000
V PEKERJAAN FINISHING
LANTAI 1
1 Pengecatan partisi dan dinding interior C1 195.00 m² 35,000 6,825,000
- ex Vinilex
2 Pengecatan plafon C2 80.00 m2 35,000 2,800,000
- 300 white ex. Vinilex
3 Pengecatan dinding exterior (termasuk kolom) C3 34.00 m² 35,000 1,190,000
- ex Vinilex
TOTAL V 10,815,000
VI PEKERJAAN SANITAIR
LANTAI 1
Toilet
Page 4 of 13
LANTAI 1
1 2 3 4 5 6 7 8
1 Pengadaan + pasang Tissue paper holder 1.00 bh 150,000 150,000
2 Pengadaan + pasang Kran Air Tembok 1.00 bh 135,000 135,000
3 Pengadaan + pasang bak cuci piring 1.00 bh 450,000 450,000
4 Pengadaan + pasang Kran sink 1.00 bh 234,000 234,000
TOTAL VI 969,000
VII PEKERJAAN FURNITURE
LANTAI 1
1 Meja Bar 1.00 unit 9,250,000 9,250,000
- Ukuran meja 2400x800/400x800/1100 mm
- Top table melaminto block Finish HPL ex. TACO + PVC edging (warna selaras HPL)
- Body melaminto block Finish HPL ex. TACO + PVC edging (warna selaras HPL)
3 Lemari bawah pantry ( termasuk lemari kulkas & aqua dispenser) 1.00 unit 10,500,000 10,500,000
- Ukuran meja 4200x600x800 mm
- Top table melaminto block Finish HPL ex. TACO + PVC edging (warna selaras HPL)
- Body meja melaminto block Finish HPL ex. TACO + PVC edging (warna selaras
HPL)
4 Meja beton pantry tipe
Beton tebal 100mm termasuk, bekesting dan pembesian 0.25 m³ 2,850,000
Penutup atas meja beton, keramik keramik ukuran 600x600 mm warna putih 2.30 m² 150,000
polos ex platinum
4 Lemari bawah dapur 1.00 unit -
- Ukuran meja L shape 2000/1000x600x800 mm
- Top table melaminto block Finish keramik
- Body meja melaminto block Finish HPL ex. TACO + PVC edging (warna selaras
HPL)
- Exclude equipment ( kompor, oven, cookerhood dll)
5 Lemari pakaian (K. Pembantu) 1.00 unit -
Ukuran lemari 1000x600x2400 mm
Page 5 of 13
LANTAI 1
1 2 3 4 5 6 7 8
- Body meja melaminto block Finish HPL ex. TACO + PVC edging (warna selaras
HPL)
Pintu dan laci singleface melaminto block 18 mm fin. HPL ex. TACO
Ambalan doubleface melaminto block 18 mm PVC edging ex Taco senada
- Body meja melaminto block Finish HPL ex. TACO + PVC edging (warna selaras
HPL)
Page 6 of 13
LANTAI 2
1 2 3 4 5 6 7 8
I PEKERJAAN INTERIOR
A PEKERJAAN LANTAI
LANTAI 2
1 Perbaikan lantai eksisting akibat bongkaran dan/atau penggantian yang rusak 3.00 m² 300,000 900,000
2 seperti pop-up,
Plint lantai Areapecah, dll.
Back Office 77.00 m¹ 61,000 4,697,000
- Tinggi 100 mm
- GRC 10 mm fin. Cat Glovin 300 Natural White ex. Avian Paint
4 Lantai keramik kamar mandi
- Pasangan lantai keramik 5.50 m² 145,000.00 797,500
B PEKERJAAN PLAFON
LANTAI 2
1 List plafond gypsum (ukuran dan desain mengikuti eksisting 62.00 m¹ 51,300 3,180,600
1 Main hole pada plafond 1.00 unit 150,000 150,000
2 Perbaikan plafon eksisting akibat pekerjaan 1.00 LS 1,000,000 1,000,000
Page 7 of 13
LANTAI 2
1 2 3 4 5 6 7 8
2 Dinding bata kamar mandi
a Pasangan dinding bata ringan tebal 10 cm 23.00 m² 145,000.00 3,335,000
b Sloof beton ; ukuran 15/20 cm 0.15 m³ 2,750,000.00 412,500
c Kolom uk. 13/13 cm dan ring balok praktis uk. 15/20 cm 0.60 m³ 2,500,000.00 1,500,000
d Plesteran dinding 46.00 m² 37,000.00 1,702,000
e Acian dinding 46.00 m² 21,000.00 966,000
3 Dinding keramik kamar mandi
- Pasangan dinding keramik 28.00 m² 145,000.00 4,060,000
4 Perapihan dinding karena pekerjaan bongkaran 1.00 ls 1,000,000 1,000,000
- Plesteran dan acian dinding
TOTAL II 18,567,500
Page 8 of 13
LANTAI 2
1 2 3 4 5 6 7 8
III PEKERJAAN FINISHING
LANTAI 2
1 Pengecatan partisi dan dinding interior C1 197.00 m² 35,000 6,895,000
- ex Vinilex
2 Pengecatan plafon C2 80.00 m2 35,000 2,800,000
- 300 white ex. Vinilex
3 Pengecatan dinding exterior (termasuk kolom) C3 43.00 m² 35,000 1,505,000
- ex Vinilex
TOTAL IV 6,018,000
V PEKERJAAN FURNITURE
LANTAI 2
1 Lemari pakaian (K. Utama) CR1 1.00 unit -
Ukuran lemari 2400x600x3000 mm
- Body meja melaminto block Finish HPL ex. TACO + PVC edging (warna selaras
HPL)
Pintu dan laci singleface melaminto block 18 mm fin. HPL ex. TACO
Ambalan doubleface melaminto block 18 mm PVC edging ex Taco senada
Page 9 of 13
LANTAI 2
1 2 3 4 5 6 7 8
- Body meja melaminto block Finish HPL ex. TACO + PVC edging (warna selaras
HPL)
Pintu dan laci singleface melaminto block 18 mm fin. HPL ex. TACO
Ambalan doubleface melaminto block 18 mm PVC edging ex Taco senada
TOTAL V -
GRAND TOTAL 67,676,100
Page 10 of 13
RENCANA ANGGARAN BIAYA RENOVASI RUKO
GBR
1 2 3 4 5 6 7 8
B Pekerjaan instalasi
LANTAI 1
1 Instalasi penerangan down light, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar setara + pipa 13.00 ttk 250,000.00 3,250,000.00
konduit (conduit pipe high impact) Ø 20 mm²
2 Instalasi penerangan lampu baret, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar setara + 2.00 ttk 250,000.00 500,000.00
pipa konduit (conduit pipe high impact) Ø 20 mm²
3 Instalasi stop kontak PLN 1 gang normal, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar 9.00 ttk 275,000.00 2,475,000.00
setara + pipa konduit (conduit pipe high impact) Ø 20 mm²
4 Instalasi exhaust fan, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar + pipa konduit (conduit 3.00 ttk 250,000.00 750,000.00
pipe high impact) Ø 20 mm²
LANTAI 2
1 Instalasi penerangan down light, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar setara + pipa 12.00 ttk 250,000.00 3,000,000.00
konduit (conduit pipe high impact) Ø 20 mm²
2 Instalasi penerangan lampu baret, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar setara + 2.00 ttk 250,000.00 500,000.00
pipa konduit (conduit pipe high impact) Ø 20 mm²
3 Instalasi stop kontak PLN 1 gang normal, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar 7.00 ttk 275,000.00 1,925,000.00
setara + pipa konduit (conduit pipe high impact) Ø 20 mm²
4 Instalasi exhaust fan, kabel NYM 3 x 2,5 mm2 ex Kabel 4 Besar + pipa konduit (conduit 1.00 ttk 250,000.00 250,000.00
pipe high impact) Ø 20 mm²
LANTAI 2
1 Pekerjaan down Light LED 12 Watt (jenis day light) )warna putih , fittings dan bola 12.00 bh 296,300.00 3,555,600.00
lampu, komponen ex Panasonic/Phillips
2 Pekerjaan lampu baret, fittings dan bola lampu, komponen ex Panasonic/Phillips 2.00 bh 293,000.00 586,000.00
LANTAI 2
1 Skaklar ganda (double)-2 gang/2 Way/10A - 250 V ex Clipsal 2.00 bh 56,200.00 112,400.00
2 Skaklar tinggal (single)-1 gang/1 Way/10A - 250 V ex Clipsal 4.00 bh 47,000.00 188,000.00
3 Stop kontak normal PLN - 1 Gang 10/16 A - 250 V ex Clipsal warna putih 7.00 bh 39,300.00 275,100.00