Anda di halaman 1dari 1

ANALISA ANGGARAN JARINGAN AIR BERSIH GRAND SULAWESI MANDAI

HARGA SATUAN TOTAL HARGA


No. URAIAN SAT. VOLUME
(RP) (RP)

I MATERIAL
a Pipa 3" btg 107.00 159,460.00 Rp 17,062,220.00
b Pipa 2" btg 78.00 159,460.00 Rp 12,437,880.00
c Samb. TEE 3" bh 5.00 11,825.00 Rp 59,125.00
d Samb. TEE 2" bh 2.00 11,825.00 Rp 23,650.00
e Samb. ELBOW 3" bh 13.00 14,500.00 Rp 188,500.00
f Samb. Opor Shock 3" ke 2" bh 10.00 14,500.00 Rp 145,000.00
g Dop 3" bh 3.00 11,500.00 Rp 34,500.00
h Dop 2" bh 6.00 11,500.00 Rp 69,000.00
i Lem Pipa klg 10.00 15,000.00 Rp 150,000.00
Jumlah Rp 30,169,875.00
II UPAH KERJA
a 1 M' Upah Kerja Galian + Pemasangan Pipa m1 740.00 15,000.00 Rp 11,100,000.00

TOTAL ANGGARAN Rp 41,269,875.00

Maros, 21 Mei 2021


Diajukan Oleh :

M. Z. HAMZAH
Pelaksana

Anda mungkin juga menyukai