3 1 M BETON K175 ~ Bahan : a Semen PC kg 326.000 2,208.00 Rp 719,808.00 3 b Pasir Beton m 0.543 506,400.00 Rp 274,902.86 3 c Batu Pecah m 0.710 606,000.00 Rp 430,051.03 d Air ltr 215 150.00 Rp 32,250.00 ~ Upah : a Pekerja oh 1.650 180,000.00 Rp 297,000.00 b Tukang oh 0.275 216,000.00 Rp 59,400.00 c Kepala Tukang oh 0.028 240,000.00 Rp 6,720.00 d Mandor oh 0.083 240,000.00 Rp 19,920.00 Total Rp 1,840,051.89 1 M³ PEK. SIRTU BAWA PONDASI Bahan : 3 a Sirtu m 1.200 422,400.00 Rp 506,880.00 ~ Upah : a Pekerja oh 0.250 180,000.00 Rp 45,000.00 b Mandor oh 0.025 240,000.00 Rp 6,000.00 Total Rp 557,880.00 1 M2 PEK. PEMBERSIHAN LAHAN DAN PERALATAN ~ Upah : a Pekerja oh 0.100 180,000.00 Rp 18,000.00 b Mandor oh 0.050 240,000.00 Rp 12,000.00 Total Rp 30,000.00 1 M2 PEK. PEMBERSIHAN LAHAN DAN PERALATAN ~ Upah : a Pekerja oh 0.400 180,000.00 Rp 72,000.00 b Mandor oh 0.040 240,000.00 Rp 9,600.00 Total Rp 81,600.00 3 1 M Pasangan Batu ~ Bahan : a Semen PC kg 163.000 2,208.00 Rp 359,904.00 3 b Pasir Beton m 0.520 506,400.00 Rp 263,328.00 3 c Batu Gunung m 1.200 489,600.00 Rp 587,520.00 d Air ltr 215 - Rp - ~ Upah : a Pekerja oh 1.500 180,000.00 Rp 270,000.00 b Tukang oh 0.750 216,000.00 Rp 162,000.00 c Kepala Tukang oh 0.075 240,000.00 Rp 18,000.00 d Mandor oh 0.075 240,000.00 Rp 18,000.00 Total Rp 1,678,752.00