DAFTAR STANDARISASI HARGA SATUAN BAHAN & UPAH KERJA

KABUPATEN BANGKALAN TAHUN 2020

HARGA SATUAN
NO. NAMA BAHAN SAT KET
EE 2020

I. BAHAN PASIR

1 Pasir Pasang ( Lokal ) M³ 230,000.00


2 Pasir Pasang ( Jawa ) M³ 285,000.00
3 Pasir Cor ( Jawa ) M³ 423,000.00
4 Tanah Urug ( Lokal ) M³ 175,000.00
5 Pudel Putih ( Lokal ) M³ 120,000.00

II. BAHAN BATU

1 Batu Gunung Belah 15/20 ( Lokal ) M³ 150,000.00


2 Batu Gunung Pecah 2/3 ( Lokal ) M³ 450,000.00
3 Batu Ampyang (Koral Sikat) M² 225,000.00
4 Batu Pecah Tempel/Hiasan ( Jawa ) M² 160,000.00
5 Batu Ukir Palimanan (Paras Jogja) Uk. 20 x 60 Bh 195,000.00 Terpasang
6 Batu Ukir Palimanan (Paras Jogja) Uk. 25 x 120 Bh 425,000.00 Terpasang
7 Batu Ukir Palimanan (Paras Jogja) Sisi Miring Bh 835,000.00 Terpasang
8 Batu Granite Alam + Huruf Grafir Uk. 140 x 280 Unit 15,680,000.00 Terpasang

III. BAHAN BATU BATA

1 Batu Putih ( Lokal ) Bh 850.00


2 Batu Bata Merah ( Lokal ) Bh 700.00
3 Rooster / Terawang bakar 25 x 25 Bh 27,000.00
4 Paving Stone 6 Cm K-300 ( Jawa ) / Conblok M² 80,000.00
5 Topi Uskup 6 cm K-300 (Jawa) Bh 6,500.00

IV. PORTLAND CEMENT ( PC )

1 Semen Gresik 40 Kg Zak 54,000.00


2 Semen Putih ( Gresik ) 40 Kg Zak 100,000.00

V. BAHAN BESI

1 Besi Beton Polos Kg 8,500.00


2 Kawat Beton / Kawat Bendrat Kg 16,000.00
3 Kawat BWG Kg 7,000.00
4 Wall Angel ; 4 m' ljr 4,000.00
5 Baut Baja + Mur Baja Kg 25,000.00
6 Baut + Mur Ø 20 mm Bh 2,700.00
7 Besi Hollow 50 x 50 Ljr 255,000.00
8 Besi Hollow 40 x 40 Ljr 205,000.00
9 Besi Hollow 20 x 40 Ljr 175,000.00
10 Rangka Atap Baja Ringan C.75.74 M² 185,000.00 terpasang
11 Atap Galvalume t = 0.35 M² 44,000.00
12 Baja Konstruksi / Profil Kg 18,950.00
13 Angkur Ø16 mm L = 40 cm Bh 35,000.00
14 Pipa Air Galvanish Medium 1,5" - 6m Ljr 276,000.00
15 Pipa Air Galvanish Medium 2,5" - 6m Ljr 517,000.00
16 Pipa Air Galvanish Medium 3" - 6m Ljr 542,000.00

VI. BAHAN ALUMUNIUM

1 Aluminium 3" putih M' 90,000.00


2 Slimar Aluminium Jendela 3/5 M' 125,000.00
3 Selimar daun pintu aluminium uk. 3/12 M' 200,000.00
4 Krepyak alumunium M² 205,000.00
5 Skrup fixer Bh 750.00
6 Sealant Tube 45,000.00
7 Karet M' 2,200.00

VII. ALAT PENGGANTUNG DAN PENGUNCI

1 Kunci 2X putar setara Ex. Kuda Terbang (Kecil) Bh 80,500.00


2 Handle/Gagang Pintu Steinlessteel 40 cm Set 285,000.00
3 Engsel Nylon setara Arch Besar (pintu) Stel 70,000.00
HARGA SATUAN
NO. NAMA BAHAN SAT KET
EE 2020
4 Engsel Nylon setara Arch Kecil (jendela) Stel 55,000.00
5 Grendel Jendela Bh 7,500.00
6 Hak Angin Kecil Bh 15,000.00

VIII. BAHAN KAYU

1 Kayu Meranti Balok 3/15, 8/12, 6/12 Klas I M³ 6,000,000.00


2 Kayu Meranti Papan 2/20, 3/20 x 4,00 m' M³ 6,500,000.00
3 Kayu Papan Begesting 2/20 x 4,00 m' M³ 4,000,000.00
4 Kayu Untuk Perancah M³ 2,000,000.00
5 Kayu Dolken Btg 25,000.00
6 Kayu Kempas Balok M³ 5,500,000.00
7 Kayu Kempas Papan M³ 6,000,000.00

XI. BAHAN CAT

1 Plamur Tembok Kg 25,000.00


2 Plamur Kayu Ex Pedang Kg 35,000.00
3 Cat Kayu/ Besi ex EMCO Kg 75,000.00
4 Cat Tembok Decolith ( 5 Kg ) Gln 110,000.00
5 Minyak Cat /Tinner A Ltr 25,000.00
6 Minyak Cat /Tinner B Ltr 20,000.00
7 Cat Meni ( Kayu ) Kg 35,000.00
8 Cat Meni ( Besi ) Kg 35,000.00
9 Cat Dasar ( Kayu ) Kg 75,000.00
10 Cat Dasar ( Dinding ) Kg 45,000.00
11 Lem Kg 13,000.00
12 Amplas Lbr 5,000.00
13 Lem Pipa Tube 8,500.00
14 Kuas Bh 10,000.00

X. BAHAN PENUTUP ATAP

1 Genteng Kodok ex. Karang Penang Bh 2,400.00


2 Bubungan Kodok ex. Karang Penang Bh 3,300.00
3 Genteng Glossur Bh 14,500.00
4 Bubungan Genteng Glossur Bh 35,000.00

XI. BAHAN KERAMIK

1 Keramik 20 x 20 cm Kw I M² 60,000.00
2 Keramik 20 x 25 cm Kw I M² 65,000.00
3 Keramik 40 x 40 cm Kw I M² 70,000.00
4 Keramik 60 x 60 cm Kw I M² 80,000.00
5 Keramik Lantai Warna 60 x 60 cm (Granite Tile) M² 185,000.00

XII. BAHAN TRIPLEK/KAYU LAPIS

1 Multiplek 1,22 x 2,44 x 6 mm Lbr 80,000.00


2 Multiplek 1,22 x 2,44 x 9 mm Lbr 110,000.00

XIII. BAHAN PAKU

1 Paku Reng Kg 16,000.00


2 Paku Usuk Kg 16,000.00
3 Paku Triplek Kg 17,000.00

XIV. BAHAN KACA

1 Kaca Polos 5 mm M² 110,000.00

XV. BAHAN LAMPU

1 Lampu SL 5 watt Ex. Philips + Fitting Bh 45,000.00


3 Titik Lampu + Instalasi Bh 132,600.00
4 Stop Kontak + Instalasi Ex. Merk Broco Bh 163,200.00
5 Stop Kontak Tunggal Ex. Merk Broco Bh 15,000.00
6 Saklar Tunggal Ex. Merk Broco Bh 13,500.00
7 Saklar Ganda Ex. Merk Broco Bh 18,000.00
8 MCB + Box 1 Group Lokal Bh 95,000.00

XVI. BAHAN KABEL LISTRIK/SUPREME

1 Kabel NYY Uk 3 x 2.5 mm M' 16,500.00


HARGA SATUAN
NO. NAMA BAHAN SAT KET
EE 2020
2 Kabel NYM Uk 2 x 2.5 mm M' 12,000.00

XVII. BAHAN SANITASI

1 Kran Air 1/2 Plastik Bh 11,000.00


2 Floor Drain Bh 10,000.00
3 Avour Bak Mandi Bh 36,000.00

XVIII. BAHAN LAIN-LAIN

1 Calsiboard 1,22 x 2,44 m Tebal 4 mm Lbr 63,000.00


2 Woodplank 0.8/20 x 4 m' (Motif) ljr 78,000.00
3 Hollow galvanis 2 x 4 x 4 m' ljr 20,000.00
4 Hollow galvanis 4 x 4 x 4 m' ljr 25,000.00
5 Minyak Begisting Ltr 3,500.00
6 Minyak Diesel / solar Ltr 7,200.00
7 Minyak Pelumas / Oli Ltr 35,000.00
8 Kasa + Compound M' 1,000.00
9 Sealtipe Bh 4,200.00
10 Sealent Tube 45,000.00
11 1juk Kg 21,000.00
12 Elekteoda Las kg 14,000.00
13 Sewa Welding Set jam 130,000.00
14 Sewa Bor Strouss hari 27,000.00
15 Pipa PVC 1/2" x 4,00 M' (AW) Ljr 24,000.00
16 Pipa PVC 2" x 4,00 M' (D) Ljr 45,000.00
17 Daun Pintu Km/Wc (PVC komplit) Set 350,000.00

XIX. UPAH KERJA

1 Mandor Hari 150,000.00


2 Kepala Tukang Gali Tanah Hari 140,000.00
3 Kepala Tukang Batu Hari 140,000.00
4 Kepala Tukang Kayu Hari 140,000.00
5 Kepala Tukang Besi Hari 140,000.00
6 Kepala Tukang Cat Hari 140,000.00
7 Kepala Tukang Listrik Hari 140,000.00
8 Tukang Gali Tanah Hari 130,000.00
9 Tukang Batu Hari 130,000.00
10 Tukang Kayu Hari 130,000.00
11 Tukang Besi Hari 130,000.00
12 Tukang Cat / Plitur Hari 130,000.00
13 Tukang Listrik Hari 130,000.00
14 Tukang Pipa Hari 130,000.00
15 Pembantu Tukang / Pekerja Hari 100,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEKERJAAN ATAP GALVALUM RUANG ARSIP PENGADILAN NEGERI BANGKALAN


LOKASI : KEC. BANGKALAN

JUMLAH
NO JENIS PEKERJAAN (Rp)
1 2 3

I. PEKERJAAN PERSIAPAN 2,500,000.00


II. PEKERJAAN ATAP 14,922,000.00

JUMLAH 17,422,000.00
PEMBULATAN 17,422,000.00
PPN 11% 1,916,420.00
JUMLAH TOTAL 19,338,420.00

Terbilang : Err:511

BANGKALAN, 2023

CV. DUA PUTRI GEMILANG

IMAM SYAFII
Direktur
RENCANA ANGGARAN BIAYA
PEKERJAAN : PEKERJAAN ATAP GALVALUM RUANG ARSIP PENGADILAN NEGERI BANGKALAN
LOKASI : KEC. BANGKALAN

HARGA JUMLAH TOTAL


NO JENIS PEKERJAAN VOLUME SAT
SATUAN (Rp) HARGA (Rp) (Rp)
1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi Pekerjaan 1.00 Ls 1,000,000.00 1,000,000.00
3 Pembongkaran Atap Existing 1.00 Ls 1,500,000.00 1,500,000.00
2,500,000.00
II PEKERJAAN ATAP
1 Pek. Pas. Rangka Galvalume C 75x40x8, T= 0,75mm 39.00 m² 245,000.00 9,555,000.00
2 Pek. Pas. Penutup Atap Spandex 39.00 m² 108,000.00 4,212,000.00
3 Pek. Pas. Bubungan 21.00 m' 55,000.00 1,155,000.00
14,922,000.00

JUMLAH 17,422,000.00
ANALISA HARGA SATUAN PEKERJAAN

1 Pemasangan 1 m2 Rangka atap Galvalume C 80.0,75mm


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.165 110,000.00 18,150.00
Tukang L.03 OH 0.117 130,000.00 15,210.00
Kepala tukang L.03 OH 0.078 140,000.00 10,920.00
Mandor L.04 OH 0.018 150,000.00 2,700.00
JUMLAH TENAGA KERJA 46,980.00
B BAHAN
Galvalum C80.0,75mm M1 3.25 30,000.00 97,500.00
Reng galvalume M1 5.1 10,000.00 51,000.00
Self Driling screw 6x20 mm bh 25 375.00 9,375.00
Self Driling screw 4x16 mm bh 25 350.00 8,750.00
JUMLAH HARGA BAHAN 166,625.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 213,605.00


E Overhead & Profit 0.15 x D 32,040.75
F Harga Satuan Pekerjaan (D+E) 245,645.75
G Harga Satuan Pekerjaan per - m2 dibulatkan 245,000.00

2 Pemasangan 1 m2 atap spandex


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.06 110,000.00 6,600.00
Tukang besi L.03 OH 0.06 130,000.00 7,800.00
Kepala tukang L.03 OH 0.006 140,000.00 840.00
Mandor L.04 OH 0.003 150,000.00 450.00
JUMLAH TENAGA KERJA 15,690.00
B BAHAN
Atap spandex M2 1.05 70,000.00 73,500.00
Sekrup Fixer Kg 0.2 24,500.00 4,900.00
JUMLAH HARGA BAHAN 78,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 94,090.00


E Overhead & Profit 0.15 x D 14,113.50
F Harga Satuan Pekerjaan (D+E) 108,203.50
G Harga Satuan Pekerjaan per - m2 dibulatkan 108,000.00

3 Pasang Bubungan Zincalume t : 0.35 mm


No. Uraian Kode Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja L.01 OH 0.02 110,000.00 2,200.00
Tukang besi L.03 OH 0.08 130,000.00 10,400.00
Kepala tukang L.03 OH 0.01 140,000.00 1,400.00
Mandor L.04 OH 0.006 150,000.00 900.00
JUMLAH TENAGA KERJA 14,900.00
B BAHAN
Bubungan Zincalum m2 1.1 30,000.00 33,000.00
Baut/screw bh 2 200.00 400.00
JUMLAH HARGA BAHAN 33,400.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 48,300.00


E Overhead & Profit 0.15 x D 7,245.00
F Harga Satuan Pekerjaan (D+E) 55,545.00
G Harga Satuan Pekerjaan Per - 1 m1 dibulatkan 55,000.00