Anda di halaman 1dari 41

DAFTAR ANALISA HARGA SATUAN BAHAN DAN UPAH

UNTUK PEKERJAAN KABUPATEN LAMPUNG TENGAH

HARGA HARGA HARGA


ANALIS URAIAN SATUAN UPAH BAHAN
( RP.) ( RP.) ( RP.)
1 2 3 4 5

A.1 1 M2 PEMBERSIHAN LAPANGAN


0.1000 Pekerja 80,000.00 8,000.00
0.0500 Mandor 175,000.00 8,750.00
16,750.00
A.1 1 M3 GALIAN TANAH PONDASI
0.7500 Pekerja 80,000.00 60,000.00
0.0250 Mandor 175,000.00 4,375.00
64,375.00
1 M2 Galian tanah 20 Cm + 1/5 x A1 12,875.00
A.2, 1 M3 GALIAN TANAH KROKOS
0.7500 Pekerja 80,000.00 60,000.00
0.0330 Mandor 175,000.00 5,775.00
65,775.00
A.3, 1 M3 GALIAN TANAH LUMPUR
1.5000 Pekerja 80,000.00 120,000.00
0.0500 Mandor 175,000.00 8,750.00
128,750.00
A.6 1 M3 ANGKUT TANAH SEJAUH .30 M'
0.3300 Pekerja 80,000.00 26,400.00
0.0100 Mandor 175,000.00 1,750.00
28,150.00
A.7 1 M3 ANGKUT TANAH SEJAUH > 30 M'
20.000,- 10,909.09 10,909.09
K= 275 ( 75+75) -
10,909.09
A.9 1 M3 ANGKAT TANAH DG KEDALAMAN > 1 M'
0.1500 Pekerja 80,000.00 12,000.00
0.0075 Mandor 175,000.00 1,312.50
13,312.50
A.10 1 M3 ANGKAT HUMUS SEJAUH > 1 M'
0.2500 Pekerja 80,000.00 20,000.00
0.1250 Mandor 175,000.00 21,875.00
41,875.00
A.16 1 M3 TIMBUNAN TANAH DIPADATKAN
1.2000 M3 tanah didatangkan 45,000.00 54,000.00
0.2500 Pekerja 80,000.00 20,000.00
0.0100 Mandor 175,000.00 1,750.00
21,750.00 54,000.00
A.16a 1 M3 TIMBUNAN DAN PEMADATATAN TANAH DARI GAL. SETEMPAT
0.2500 Pekerja 80,000.00 20,000.00
0.0100 Mandor 175,000.00 1,750.00
21,750.00
A.18 1 M3 URUGAN PASIR SAMPAI PADAT
1.2000 M3 Pasir urug 65,000.00 78,000.00
0.3000 Pekerja 80,000.00 24,000.00
0.0100 Mandor 175,000.00 1,750.00
25,750.00 78,000.00
A.18 1 M3 MENGHAMPAR BASE COURSE SAMPAI PADAT
1.2000 M3 Base B 150,000.00 180,000.00
1.0000 Pekerja 80,000.00 80,000.00
0.0500 Mandor 175,000.00 8,750.00
88,750.00 180,000.00
A.18 1 M3 MENGHAMPAR AGREGATE 1/2 SAMPAI PADAT
1.2000 M3 Agregate 1/2 200,000.00 240,000.00
1.2000 Pekerja 140,000.00 168,000.00
0.0500 Mandor 105,000.00 5,250.00
173,250.00 240,000.00
A.18 1 M3 MENGHAMPAR AGREGATE 3/5 SAMPAI PADAT
1.2000 M3 Agregate 3/5 140,000.00 168,000.00
1.5000 Pekerja 140,000.00 210,000.00
0.0500 Mandor 105,000.00 5,250.00
215,250.00 168,000.00
A.1+A.6 1 M3 TIMBUNAN TANAH BIASA DIPADATKAN
+A.16 A.1 60,000.00 60,000.00
A.6 28,150.00 28,150.00
A.16,a 21,750.00 21,750.00
109,900.00 -
A.1+A.9 1 M3 GALIAN TANAH BIASA DIANGKAT > 1 M'
A.1 60,000.00 60,000.00
A,9 13,312.50 13,312.50
73,312.50 -
A.2+A.16 1 M3 GALIAN TANAH DAN TIMBUNAN TANAH KROKOS
3.0000 Pekerja 80,000.00 240,000.00
0.1500 Mandor 175,000.00 26,250.00
266,250.00 -
C,1 1 M3 MEMECAH BATU BELAH
A.2 128,750.00 128,750.00
A,16 21,750.00 21,750.00
150,500.00 -

1 2 3 4 5
F.1.A 1 M2 PASANG PLAFOND DAN DINDING
a 0.3500 Lbr Teakwood ( 240x120x0,3 ) Cm 105,000.00 36,750.00
b 0.3500 Lbr Giypsun ( 240x120x0,6 ) Cm 125,000.00 43,750.00
c 0.3500 Lbr Multipleks ( 240x120x0,6 ) Cm 95,000.00 33,250.00
d 0.3500 Lbr Tripleks ( 240x120x0,3 ) Cm 45,000.00 15,750.00
e 0.0300 M3 Papan 2 cm kelas II 2,000,000.00 60,000.00
0.0200 Kg Paku tripleks 12,000.00 240.00
0.0200 Kg Paku Gypsun 19,000.00 380.00
0.2000 Kg Paku papan/reng 9,000.00 1,800.00
0.0120 M3 Kayu balok kelas II 1,900,000.00 22,800.00
0.8000 Tukang 150,000.00 120,000.00
0.0800 Kepala tukang 175,000.00 14,000.00
0.2800 Pekerja 80,000.00 22,400.00
0.1400 Mandor 175,000.00 24,500.00
a. 180,900.00 61,590.00
b. 180,900.00 68,730.00
c. 180,900.00 58,090.00
d. 180,900.00 40,590.00
e. 180,900.00 84,600.00
F.1.B 1 M2 PASANG TRIPLEK DAN ALMUNIUM VOIL
0.3500 Lbr Tripleks ( 240x120x0,3 ) Cm 45,000.00 15,750.00
0.8300 M2 Almunium voil 26,000.00 21,580.00
0.0830 M2 Penyambungan Almunium voil 20,000.00 1,660.00
0.0200 Kg Paku tripleks 12,000.00 240.00
0.2000 Kg Paku papan/reng 9,000.00 1,800.00
0.4000 Tukang 150,000.00 60,000.00
0.0400 Kepala tukang 175,000.00 7,000.00
0.1400 Pekerja 80,000.00 11,200.00
0.0140 Mandor 175,000.00 2,450.00
80,650.00 41,030.00
F.1.C 1 M2 PASANG TRIPLEK DAN GIYPSUN
a 0.3500 Lbr Tripleks ( 240x120x0,3 ) Cm 45,000.00 15,750.00
b 0.3500 Lbr Giypsun ( 240x120x0,6 ) Cm 125,000.00 43,750.00
0.0200 Kg Paku Gypsun 19,000.00 380.00
0.4000 Tukang 150,000.00 60,000.00
0.0400 Kepala tukang 175,000.00 7,000.00
0.1400 Pekerja 80,000.00 11,200.00
0.0140 Mandor 175,000.00 2,450.00
a 2,450.00 41,030.00
b 2,450.00 41,030.00
F.2 1 M2 JENDELA KAYU DAN VENTILASI KACA MATI
a 1.0000 M2 Kaca bening/polos tebal 3 mm 40,000.00 40,000.00
b 1.0000 M2 Kaca buram tebal 3 mm 45,000.00 45,000.00
c 1.0000 M2 Kaca bening/polos t = 8 mm 200,000.00 200,000.00
0.0070 M3 Kayu papan kelas II 2,000,000.00 14,000.00
0.0300 Kg Paku Papan 9,000.00 270.00
3.0000 Tukang 150,000.00 450,000.00
0.3000 Kepala tukang 175,000.00 52,500.00
1.0000 Pekerja 80,000.00 80,000.00
a 582,500.00 54,270.00
b 582,500.00 59,270.00
Pasang ventilasi non kaca c 582,500.00 14,270.00
d 582,500.00 214,270.00

F.2A 1 M2 JENDELA / VENTILASI KACA MATI ( Almunium)


a 1.0000 M2 Kaca bening/polos tebal 5 mm 52,000.00 52,000.00
b 1.0000 M2 Kaca buram tebal 5 mm 68,000.00 68,000.00
c 1.0000 M2 Kaca bening/polos t = 8 mm 185,000.00 185,000.00
4.4000 M' Karet Lis Kaca 4,000.00 17,600.00
2.0000 Tukang 150,000.00 300,000.00
0.0200 Kep. Tukang 175,000.00 3,500.00
2.0000 Pekerja 80,000.00 160,000.00
a 463,500.00 69,600.00
b 463,500.00 85,600.00
c 463,500.00 202,600.00

F.3 1 M2 DAUN JENDELA KREPYAK DAN JALUSI


0.0400 a. M3 Kayu papan kelas II 2,000,000.00 80,000.00
0.0400 b. M3 Kayu papan kelas III 1,400,000.00 56,000.00
0.0500 Kg Paku papan 9,000.00 450.00
4.5000 Tukang 150,000.00 675,000.00
0.4500 Kepala tukang 175,000.00 78,750.00
1.5000 Pekerja 80,000.00 120,000.00
0.0750 Mandor 175,000.00 13,125.00
1 M2 DAUN JENDELA KREPYAK a 886,875.00 80,450.00
b 886,875.00 56,450.00
1 M2 VENTILASI JALUSI PAPAN 0,5 upah F.3 V.a 443,437.50 40,225.00
V.b 443,437.50 28,225.00

1 2 3 4 5

F.4 1 M2 DAUN PINTU DAN JENDELA PANEL


0.0350 a. M3 Kayu papan kelas II 2,000,000.00 70,000.00
0.0350 b. M3 Kayu papan kelas III 1,400,000.00 49,000.00
0.0500 Kg Paku papan 9,000.00 450.00
4.0000 Tukang 150,000.00 600,000.00
0.4000 Kepala tukang 175,000.00 70,000.00
1.2500 Pekerja 80,000.00 100,000.00
0.0620 Mandor 175,000.00 10,850.00
a 780,850.00 70,450.00
b 780,850.00 49,450.00
F.5 1 M2 JENDELA KACA NAKO
1.2000 a Kaca Putih/Polos 5 mm 52,000.00 62,400.00
1.2000 b Kaca Riben/Buram 5 mm 68,000.00 81,600.00
1.0000 M2 Teralis Besi 170,000.00 170,000.00
1.2000 Tukang 150,000.00 180,000.00
0.1200 Kepala Tukang 175,000.00 21,000.00
0.4000 Pekerja 80,000.00 32,000.00
a 233,000.00 232,400.00
b 233,000.00 251,600.00
F.5A 1 M2 PEKERJAAN TRALIS
1.0000 a. M2 Teralis Besi polos 170,000.00 170,000.00
1.0000 b. M2 Teralis Besi tempa ulir 220,000.00 220,000.00
1.2000 Tukang 150,000.00 180,000.00
0.1200 Kepala Tukang 175,000.00 21,000.00
0.4000 Pekerja 80,000.00 32,000.00
a. 233,000.00 170,000.00
b. 233,000.00 220,000.00
F 1 M2 PAPAN SUSUN
0.0220 a. M3 Kayu papan kelas II 20,000.00 440.00
0.0220 b. M3 Kayu papan kelas III 18,000.00 396.00
0.2000 Kg Paku papan 5,000.00 1,000.00
1.8000 Tukang 150,000.00 270,000.00
0.1800 Kepala tukang 175,000.00 31,500.00
0.6000 Pekerja 80,000.00 48,000.00
0.0300 Mandor 175,000.00 5,250.00
a 354,750.00 1,440.00
b 354,750.00 1,396.00
F.8 1 M2 PAPAN SUSUN DAN DINDING SEKATAN
0.0220 a. M3 Kayu papan kelas II 2,000,000.00 44,000.00
0.0220 b. M3 Kayu papan kelas III 1,200,000.00 26,400.00
0.2000 Kg Paku papan 9,000.00 1,800.00
1.8000 Tukang 150,000.00 270,000.00
0.1800 Kepala tukang 175,000.00 31,500.00
0.6000 Pekerja 80,000.00 48,000.00
0.0300 Mandor 175,000.00 5,250.00
a 354,750.00 45,800.00
b 354,750.00 28,200.00
F.8 1 M2 DINDING SPANDEK RANGKA BAJA
0.1667 Lbr. Spandek 636,000.00 106,000.00
0.6700 Btg. Truss C.75.75 SNI BMT 75,000.00 50,250.00
0.0800 Kg Paku skrup 23,000.00 1,840.00
1.8000 Tukang 150,000.00 270,000.00
0.1800 Kepala tukang 175,000.00 31,500.00
0.6000 Pekerja 80,000.00 48,000.00
0.0300 Mandor 175,000.00 5,250.00
a 354,750.00 158,090.00
F.8a 1 M2 DINDING SEKATAN BAMBU
0.0072 M3 Kayu papan kelas III 1,400,000.00 10,080.00
14.0000 M' Bambu Ø 10cm 1,500.00 21,000.00
1.0000 Kg Paku papan 9,000.00 9,000.00
0.7000 Tukang 150,000.00 105,000.00
0.0700 Kepala tukang 175,000.00 12,250.00
0.3000 Pekerja 80,000.00 24,000.00
0.0150 Mandor 175,000.00 2,625.00
a 143,875.00 40,080.00
F.8b 1 M2 DINDING SEKATAN GERIBIK
0.0016 M3 Kayu papan kelas III 1,400,000.00 2,240.00
1.2000 M2 Geribik 35,000.00 42,000.00
0.5000 Kg Paku 11,000.00 5,500.00
0.5000 Tukang 150,000.00 75,000.00
0.0500 Kepala tukang 175,000.00 8,750.00
0.2000 Pekerja 80,000.00 16,000.00
0.0100 Mandor 175,000.00 1,750.00
a 101,500.00 49,740.00
F.9 1 M2 KAYU RULLER BUBUNGAN
0.0330 a. M3 Kayu papan kelas II 2,000,000.00 66,000.00
0.0330 b. M3 Kayu papan kelas III 1,200,000.00 39,600.00
0.2500 Kg Paku papan 9,000.00 2,250.00
0.8000 Tukang 150,000.00 120,000.00
0.0800 Kepala tukang 175,000.00 14,000.00
0.2800 Pekerja 80,000.00 22,400.00
0.0140 Mandor 175,000.00 2,450.00
a 158,850.00 68,250.00
b 158,850.00 41,850.00
F.16 1 M2 PASANG KASAU DAN RENG
0.0110 a. M3 Kayu balok kelas II 1,900,000.00 20,900.00
0.0110 b. M3 Kayu balok kelas III 1,200,000.00 13,200.00
0.2500 Kg Paku papan/reng 9,000.00 2,250.00
0.1000 Tukang 150,000.00 15,000.00
0.0100 Kepala tukang 175,000.00 1,750.00
0.1000 Pekerja 80,000.00 8,000.00
0.0025 Mandor 175,000.00 437.50
a 25,187.50 23,150.00
b 25,187.50 15,450.00
F.21 1 M2 PASANG LISPLANK KAYU
0.0300 a. M3 Kayu papan kelas II 2,000,000.00 60,000.00
0.0300 b. M3 Kayu papan kelas III 1,400,000.00 42,000.00
0.1000 Kg Paku papan/reng 9,000.00 900.00
0.8000 Tukang 150,000.00 120,000.00
0.0800 Kepala tukang 175,000.00 14,000.00
0.2800 Pekerja 80,000.00 22,400.00
0.0140 Mandor 175,000.00 2,450.00
a 158,850.00 60,900.00
b 158,850.00 42,900.00
F.22 1 M3 KUDA-KUDA BENTANG HINGGA 7 M'
1.1000 a. M3. Kayu balok kelas II 1,900,000.00 2,090,000.00
1.1000 b. M3. Kayu balok kelas III 1,200,000.00 1,320,000.00
1.0000 Kg Paku balok 8,000.00 8,000.00
7.0000 Mur, baut, plat 15,000.00 105,000.00
24.0000 Tukang 150,000.00 3,600,000.00
2.4000 Kepala tukang 175,000.00 420,000.00
8.0000 Pekerja 80,000.00 640,000.00
0.4000 Mandor 175,000.00 70,000.00
a 4,730,000.00 2,203,000.00
b 4,730,000.00 1,433,000.00

1 2 3 4 5

F.22a 1 M3 KUDA-KUDA GORDING, JURAI, IKATAN ANGIN


1.1000 a. M3. Kayu balok kelas II 1,900,000.00 2,090,000.00
1.1000 b. M3. Kayu balok kelas III 1,200,000.00 1,320,000.00
1.0000 Kg Paku balok 8,000.00 8,000.00
10.0000 Tukang 150,000.00 1,500,000.00
1.0000 Kepala tukang 175,000.00 175,000.00
10.0000 Pekerja 80,000.00 800,000.00
0.5000 Mandor 175,000.00 87,500.00
a 2,562,500.00 2,098,000.00
b 2,562,500.00 1,328,000.00
F.22b 1 M3 BALOK LANTAI KAYU 7/14
1.1000 a. M3. Kayu balok kelas II 1,900,000.00 2,090,000.00
1.1000 b. M3. Kayu balok kelas III 1,200,000.00 1,320,000.00
1.0000 Kg Paku balok 11,000.00 11,000.00
5.0000 Tukang 150,000.00 750,000.00
1.0000 Kepala tukang 175,000.00 175,000.00
10.0000 Pekerja 80,000.00 800,000.00
0.5000 Mandor 175,000.00 87,500.00
a 1,812,500.00 2,101,000.00
b 1,812,500.00 1,331,000.00
F.23 1 M3 KUDA-KUDA BENTANG LEBIH 7 M'
1.2000 a. M3 Kayu balok kelas II 1,900,000.00 2,280,000.00
1.2000 b. M3.Kayu balok kelas III 1,200,000.00 1,440,000.00
11.0000 bh Mur, baut, plat 15,000.00 165,000.00
36.0000 Tukang 150,000.00 5,400,000.00
3.6000 Kepala tukang 175,000.00 630,000.00
12.0000 Pekerja 80,000.00 960,000.00
0.6000 Mandor 175,000.00 105,000.00
a 7,095,000.00 2,445,000.00
b 7,095,000.00 1,605,000.00

F.27 1 M3 PEK.KAYU KUSEN PINTU/JENDELA


1.2000 a. Kayu balok kelas II 1,900,000.00 2,280,000.00
1.2000 b. Kayu balok kelas III 1,200,000.00 1,440,000.00
2.5000 Paku balok 8,000.00 20,000.00
36.0000 Tukang 150,000.00 5,400,000.00
3.6000 Kepala tukang 175,000.00 630,000.00
12.0000 Pekerja 80,000.00 960,000.00
0.8000 Mandor 175,000.00 140,000.00
a 7,130,000.00 2,300,000.00
b 7,130,000.00 1,460,000.00
F.28 1 M3 PEK.KAYU KUSEN BENTUK BUSUR
1.2000 a. Kayu balok kelas II 1,900,000.00 2,280,000.00
1.2000 b. Kayu balok kelas III 1,200,000.00 1,440,000.00
2.5000 Paku balok 8,000.00 20,000.00
42.0000 Tukang 150,000.00 6,300,000.00
4.2000 Kepala tukang 175,000.00 735,000.00
7.0000 Pekerja 80,000.00 560,000.00
0.7000 Mandor 175,000.00 122,500.00
7.0000 Penggergaji 80,000.00 560,000.00
a 8,277,500.00 2,300,000.00
b 8,277,500.00 1,460,000.00

F.30 1 M2 PINTU DOUBLE TRIPLEK


0.0200 M3 Kayu kelas III 1,400,000.00 28,000.00
0.2650 Lbr Triplek 3 mm 45,000.00 11,925.00
0.2000 Kg. Paku Triplek 12,000.00 2,400.00
2.0000 Tukang 150,000.00 300,000.00
0.2000 Kepala tukang 175,000.00 35,000.00
0.6500 Pekerja 80,000.00 52,000.00
0.0325 Mandor 175,000.00 5,687.50
392,687.50 42,325.00
F.33 1 M2 PINTU PANEL PENUH
0.7000 a. Lbr Multipleks ( 240x120 x0,6 ) Cm 95,000.00 66,500.00
0.7000 b. Lbr Teakwood ( 240 x 120 x 0,3 ) 105,000.00 73,500.00
0.0400 M3. Kayu Papan kls II 2,000,000.00 80,000.00
0.8000 Kg. Lem Kayu 33,000.00 26,400.00
0.0500 Kg. Paku papan/reng 9,000.00 450.00
1.2500 Tukang 150,000.00 187,500.00
3.7500 Kepala tukang 175,000.00 656,250.00
0.3750 Pekerja 80,000.00 30,000.00
0.0620 Mandor 175,000.00 10,850.00
a 884,600.00 173,350.00
b 884,600.00 180,350.00
F.33.A 1 M2 PINTU PANEL PENUH LAPIS TEAKWOOD
DAN FERMIKA
0.0400 a. M3 Kayu papan kelas II 2,000,000.00 80,000.00
0.0400 b. M3. Kayu Papan III 1,400,000.00 56,000.00
0.3500 a.Lbr Mul Lbr Formika ( 240x120 x0,6 ) Cm 45,000.00 15,750.00
0.3500 b Lbr TeaLbr Teakwood ( 240 x 120 x 0,3 ) 105,000.00 36,750.00
0.0500 Kg. Paku papan/reng 9,000.00 450.00
3.7500 Tukang 150,000.00 562,500.00
0.3750 Kepala tukang 175,000.00 65,625.00
1.2500 Pekerja 80,000.00 100,000.00
0.0620 Mandor 175,000.00 10,850.00
a 738,975.00 96,200.00
b 738,975.00 92,750.00

1 2 3 4 5

F.36 1 M2 PASANG PINTU dan JENDELA KACA BINGKAI


0.8000 a. M2 Kaca Bening/polos tebal 5 mm 52,000.00 41,600.00
0.8000 b. M2 Kaca Buram / Riben tebal 5 mm 68,000.00 54,400.00
0.0400 M3. Kayu papan kelas II 2,000,000.00 80,000.00
0.0500 Kg. Paku papan 9,000.00 450.00
3.0000 Tukang 150,000.00 450,000.00
0.3000 Kepala tukang 175,000.00 52,500.00
1.0000 Pekerja 80,000.00 80,000.00
0.0500 Mandor 175,000.00 8,750.00
a 591,250.00 122,050.00
b 591,250.00 134,850.00
F.37 1 M3 PAS. SINGGETAN DINDING DAN PROFIL
0.0350 M3 Kayu Papan kls II 2,000,000.00 70,000.00
0.2000 Kg Paku Papan / Reng 9,000.00 1,800.00
0.8000 Tukang 150,000.00 120,000.00
0.0800 Kepala tukang 175,000.00 14,000.00
0.2800 Pekerja 80,000.00 22,400.00
0.0140 Mandor 175,000.00 2,450.00
158,850.00 71,800.00
F.38C 1 M2 PAS. DAUN PINTU LAPIS SENG ALUMUNIUM
0.0250 M3 Kayu Papan kls II 2,000,000.00 50,000.00
0.0500 M2 Kg Paku 9,000.00 450.00
1.0000 Seng Alumunium 40,000.00 40,000.00
0.3500 Lbr. Triplek ( 240 x 120 x 0,3 ) Cm 45,000.00 15,750.00
0.7500 Lem Kayu 33,000.00
0.8500 Pekerja 80,000.00 68,000.00
3.0000 Tukang 150,000.00 450,000.00
518,000.00 106,200.00
G.2 1 M3 PAS. BATU BELAH KOSONG
1.2000 a. M3 Batu belah hitam 115,000.00 138,000.00
1.2000 b. Batu Belah Putih 61,000.00 73,200.00
1.5000 Pekerja 80,000.00 120,000.00
0.0750 Mandor 175,000.00 13,125.00
a 370,000.00 138,000.00
b 370,000.00 73,200.00
G.14 1 M3 PAS. PEREKAT ADUKAN 1 PC : 2PS
11.3600 Sak Semen Batu Raja 61,000.00 692,960.00
0.9500 M3 Pasir pasang 75,000.00 71,250.00
764,210.00
G.16 1 M3 PAS. PEREKAT ADUKAN 1 PC : 3PS
7.2500 Sak Semen Batu Raja 61,000.00 442,250.00
1.1600 M3 Pasir pasang 75,000.00 87,000.00
529,250.00
G.19 1 M3 PAS. PEREKAT ADUKAN 1 PC : 4PS
9.0000 Sak Semen Batu Raja 61,000.00 549,000.00
1.0500 M3 Pasir pasang 75,000.00 78,750.00
627,750.00
G.32 H 1 M3 PAS. BATU BELAH ADUKAN 1 PC : 4 PS
1.2000 M3 Batu Belah Putih 85,000.00 102,000.00
3.2570 zak Semen Baturaja 61,000.00 198,677.00
0.5220 M3 Pasir pasang 75,000.00 39,150.00
1.2000 Tukang Batu 150,000.00 180,000.00
0.1200 Kepala tukang 175,000.00 21,000.00
3.6000 Pekerja 80,000.00 288,000.00
0.1800 Mandor 175,000.00 31,500.00
520,500.00 339,827.00
G.33.H 1 M3 PAS. BATU BATA MERAH ADUKAN 1 PC : 4 PS
700.0000 Buah Bata Merah 500.00 350,000.00
2.5330 Zak Semen Batu Raja 61,000.00 154,513.00
0.4060 M3 Pasir pasang 75,000.00 30,450.00
1.5000 Tukang Batu 150,000.00 225,000.00
0.1500 Kepala tukang 175,000.00 26,250.00
4.5000 Pekerja 80,000.00 360,000.00
0.2250 Mandor 175,000.00 39,375.00
650,625.00 534,963.00
1 M2 Pasang Bata Merah = 1/10 x G.33.H 65,062.50 53,496.30
G.33.H1 1 M3 PASANGAN BATU ROSTER ADUKAN 1PC : 4 PS
222.0000 Buah Roster 2,350.00 521,700.00
2.5360 M3 Pasir Pasang 75,000.00 190,200.00
0.4060 Zak Semen Batu Raja 61,000.00 24,766.00
1.5000 Tukang Batu 150,000.00 225,000.00
0.1500 Kepala tukang 175,000.00 26,250.00
4.5000 Pekerja 80,000.00 360,000.00
0.2250 Mandor 175,000.00 39,375.00
650,625.00 736,666.00
1 M2 Pasang Bata Roster = 1/10 x G.33.H 65,062.50 73,666.60

1 2 3 4 5

G.33 M 1 M3 PAS. BATU BATA MERAH ADUKAN 1 PC : 2 PS


700.0000 Buah Bata Merah 500.00 350,000.00
4.1170 Zak Semen Batu Raja 61,000.00 251,137.00
0.3330 M3 Pasir Pasang 80,000.00 26,640.00
1.0000 Upah Kerja (G.33.H) 650,625.00 179,625.00
179,625.00 627,777.00

G.40 1 M3 BETON TUMBUK ADUKAN 1 : 3 : 5


1.0000 M3 Kerikil Sungai 55,000.00 55,000.00
0.5000 M3 Pasir Beton 80,000.00 40,000.00
4.2400 Zak Semen Batu Raja 61,000.00 258,640.00
1.0000 Tukang 150,000.00 150,000.00
0.1000 Kepala Tukang 175,000.00 17,500.00
6.0000 Pekerja 80,000.00 480,000.00
0.3000 Mandor 175,000.00 52,500.00
700,000.00 353,640.00
1 M2 Pasangan Beton Sikat Tebal 8 Cm ( 1/12,5 ) 56,000.00 28,291.20

A1+ 1 M' PASANG KANSTIN BATA MERAH


G.33+ A. 1 X 0.20 12,875.00 -
G.50.B G. 33 H X 0.20 13,012.50 14,733.32
G. 50 B X 0.20 12,125.00 1,905.88
38,012.50 16,639.20

G.41.A1 1 M3 BETON ADUKAN 1 PC : 2 PS : 3KR


0.8200 a. M3 Kerikil Sungai 55,000.00 45,100.00
0.8200 b. M3 Batu Pecah 2/3 Cm 165,000.00 135,300.00
0.5400 M3 Pasir Beton 80,000.00 43,200.00
6.8000 Zak Semen Batu Raja 61,000.00 414,800.00
1.0000 Tukang 150,000.00 150,000.00
0.1000 Kepala tukang 175,000.00 17,500.00
6.0000 Pekerja 80,000.00 480,000.00
0.3000 Mandor 175,000.00 52,500.00
a. 700,000.00 503,100.00
b. 700,000.00 593,300.00

G.41.A2 1 M3 BETON ADUKAN 1 PC : 1,5 PS : 2,5 KR


0.9560 a. M3 Kerikil Sungai 55,000.00 52,580.00
0.9560 b. M3 Batu Pecah 2/3 Cm 165,000.00 157,740.00
0.6750 M3 Pasir Beton 175,000.00 118,125.00
8.1100 Zak Semen Batu Raja 61,000.00 494,710.00
1.0000 Upah Pekerja ( G.41.A1) 700,000.00 700,000.00
a 200,750.00 720,415.00
b 200,750.00 935,575.00

G.41.B 100 KG BESI BETON PEKERJAAN KASAR


110.0000 a. Kg Besi Beton Polos 10,000.00 1,100,000.00
110.0000 b. M3 Beton Ulir 11,000.00 1,210,000.00
2.0000 Kg Kawat Beton 9,000.00 18,000.00
9.0000 Tukang 150,000.00 1,350,000.00
3.0000 Kepala Tukang 175,000.00 525,000.00
9.0000 Pekerja 80,000.00 720,000.00
a 2,595,000.00 1,118,000.00
b 2,595,000.00 1,228,000.00
Upah Untuk Pekerja Kasar x3/4 nya a 1,946,250.00 838,500.00
- b 1,946,250.00 921,000.00
1 M3 Beton di Perlukan 125 Kg Besi = 1,25 x G.41.B a 3,243,750.00 1,397,500.00
b 3,243,750.00 1,535,000.00

G.41.C 1 M3 BETON PERLU TIANG BEKISTING


0.4000 M3 Kayu Balok Kelas III 1,200,000.00 480,000.00
4.0000 Kg Paku Kasau 8,000.00 32,000.00
5.0000 Tukang 150,000.00 750,000.00
0.5000 Kepala Tukang 175,000.00 87,500.00
2.0000 Pekerja 80,000.00 160,000.00
0.1000 Mandor 175,000.00 17,500.00
4.0000 Pekerja Bongkar Bekisting 80,000.00 320,000.00
1,335,000.00 512,000.00

G.41.D 10 M2 PEKERJAAN PAPAN CETAKAN BETON


0.4000 M3 Kayu papan kls III 1,400,000.00 560,000.00
4.0000 kg Paku papan/reng 9,000.00 36,000.00
5.0000 Tukang 150,000.00 750,000.00
0.5000 Kepala tukang 175,000.00 87,500.00
2.0000 Pekerja 80,000.00 160,000.00
0.1000 Mandor 175,000.00 17,500.00
4.0000 Pekerja bongkar bekisting 80,000.00 320,000.00
1 1 M3 Beton segi empat 1 x G.41.D 1,335,000.00 596,000.00
2 1 M3 Beton melingkar 1.5 x G.41.D 2,002,500.00 768,000.00

1 2 3 4 5
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 2 PS : 3 KRL
G.41.BCD G. 41.A1 a. Beton dgn Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Beton dgn Batu pecah 2/3 700,000.00 593,300.00
G. 41.B a. Besi polos 2,595,000.00 1,118,000.00
G. 41.B b. Besi ulir 2,595,000.00 1,228,000.00
G. 41.C Tiang begisting 1,335,000.00 512,000.00
G. 41.D X 0,5 ( papan begisting ) 667,500.00 298,000.00
G. 41.A1.a + G.41.B.a + G.41.C + G41 D a 5,297,500.00 2,431,100.00
G. 41.A1.b + G.41.B.a + G.41.C + G41 D b 5,297,500.00 2,631,300.00
1 M3 Beton Memakai Batu Pecah Dengan Besi Ulir 1,723,750.00 2,631,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 2 PS : 3 KRL
BD G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.B a. Besi polos 2,595,000.00 1,118,000.00
G. 41.B b. Besi ulir 2,595,000.00 1,228,000.00
G. 41.D X 0,5 ( papan begisting ) 667,500.00 298,000.00
G. 41.A1.a + G.41.B.a+ G.41 D 3,962,500.00 1,919,100.00
G. 41.A1.b + G.41.B.a+ G.41 D 3,962,500.00 2,009,300.00
1 M3 Beton Memakai Batu Pecah Dengan Besi Ulir 3,962,500.00 2,119,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 2 PS : 3 KRL ( tanpa Begisting )
B G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.B a. Besi polos 2,595,000.00 1,118,000.00
G. 41.B b. Besi ulir 2,595,000.00 1,228,000.00
G. 41.A1.a + G.41.B.a 3,295,000.00 1,621,100.00
G. 41.A1.b + G.41.B.a 3,295,000.00 1,711,300.00
1 M3 Beton Memakai Batu Pecah Dengan Besi Ulir 3,295,000.00 1,821,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 2 PS : 3 KRL
D G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.D X 0,5 ( papan begisting ) 667,500.00 298,000.00
a 1,367,500.00 801,100.00
b 1,367,500.00 891,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 2 PS : 3 KRL
CD G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.C Tiang begisting 1,335,000.00 512,000.00
G. 41.D Papan begisting 667,500.00 298,000.00
a 2,702,500.00 1,313,100.00
b 2,702,500.00 1,403,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 1,5 PS : 2,5 KRL
G.41.BCD G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.B a. Besi polos 2,595,000.00 1,118,000.00
G. 41.B b. Besi ulir 2,595,000.00 1,228,000.00
G. 41.C Tiang begisting 1,335,000.00 512,000.00
G. 41.D Papan begisting 667,500.00 298,000.00
G. 41.A1.a + G.41.B.a + G.41.C + G41 D 5,297,500.00 2,431,100.00
G. 41.A1.b + G.41.B.a + G.41.C + G41 D 5,297,500.00 2,521,300.00
1 M3 Beton Memakai Batu Pecah Dengan Besi Ulir 5,297,500.00 2,631,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 1,5 PS : 2,5 KRL
G.41.BD G. 41.A2 a. Batu krikil 700,000.00 503,100.00
G. 41.A2 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.B a. Besi polos 2,595,000.00 1,118,000.00
G. 41.B b. Besi ulir 2,595,000.00 1,228,000.00
G. 41.D X 0,5 ( papan begisting ) 667,500.00 298,000.00
G. 41.A1.a + G.41.B.a + G41 D 3,962,500.00 1,919,100.00
G. 41.A1.b + G.41.B.a + G41 D 3,962,500.00 2,009,300.00
1 M3 Beton Memakai Batu Pecah Dengan Besi Ulir 3,962,500.00 2,119,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 1,5 PS : 2,5 KRL
G.41.B G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.B a. Besi polos 2,595,000.00 1,118,000.00
G. 41.B b. Besi ulir 2,595,000.00 1,228,000.00
G. 41.A1.a + G.41.B.a 3,295,000.00 1,621,100.00
G. 41.A1.b + G.41.B.a 3,295,000.00 1,821,300.00
1 M3 Beton Memakai Batu Pecah Dengan Besi Ulir 3,295,000.00 1,821,300.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 1,5 PS : 2,5 KRL
G.41.D G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.D X 0,5 ( papan begisting ) 667,500.00 298,000.00
G. 41.A1.a + G41 D 1,367,500.00 801,100.00
G. 41.A1.b + G41 D 2,067,500.00 1,394,400.00
G.41.A1+ 1 M3 BETON BERTULANG 1 PC : 1,5 PS : 2,5 KRL
G.41.CD G. 41.A1 a. Batu krikil 700,000.00 503,100.00
G. 41.A1 b. Batu pecah 2/3 700,000.00 593,300.00
G. 41.C Tiang begisting 1,335,000.00 512,000.00
G. 41.D Papan begisting 667,500.00 298,000.00
G. 41.A1.a + G.41.C + G41 D 2,702,500.00 1,313,100.00
G. 41.A1.b + G.41.C + G41 D 2,702,500.00 1,403,300.00

1 2 3 4 5
G.44 1 M3 BETON ADK. 1 PC : 2 PS : 3 KRL
1.0000 a. M3 Batu Kerikil Sungai 55,000.00 55,000.00
1.0000 b. M3 Batu Split 2/3 Cm 165,000.00 165,000.00
0.5000 M3 Pasir Beton 80,000.00 40,000.00
4.2400 Zak Semen Batu Raja 61,000.00 258,640.00
0.5000 Tukang 150,000.00 75,000.00
0.0500 Kepala Tukang 175,000.00 8,750.00
6.0000 Pekerja 80,000.00 480,000.00
0.6000 Mandor 175,000.00 105,000.00
a 668,750.00 353,640.00
b 668,750.00 463,640.00
a. 1 M2 beton t = 7 cm (0.07 x G.44 ) a 46,812.50 24,754.80
b 46,812.50 32,454.80
b. 1 M2 beton t = 5 cm (0.05 x G.44 ) a 33,437.50 17,682.00
b 33,437.50 23,182.00
c. 1 M2 beton t = 10 cm (0.10 x G.44 ) a 66,875.00 35,364.00
b 66,875.00 46,364.00

G.50 B 1 M2 PLESTERAN TEBAL 1,5 CM ADUKAN 1 PC : 4 PS


0.1304 Zak semen Baturaja 61,000.00 7,954.40
0.0210 M3 Pasir pasang 75,000.00 1,575.00
0.1500 Tukang 150,000.00 22,500.00
0.0150 Kepala tukang 175,000.00 2,625.00
0.4000 Pekerja 80,000.00 32,000.00
0.0200 Mandor 175,000.00 3,500.00
60,625.00 9,529.40

G.50 H 1 M2 PLESTERAN TEBAL 1,5 CM ADUKAN 1 PC : 2 PS


0.2150 Zak semen Batu Raja 61,000.00 13,115.00
0.0170 M3 Pasir pasang 75,000.00 1,275.00
0.1500 Tukang 150,000.00 22,500.00
0.0150 Kepala tukang 175,000.00 2,625.00
0.4000 Pekerja 80,000.00 32,000.00
0.0200 Mandor 175,000.00 3,500.00
60,625.00 14,390.00

G.53 100 M2 MENGAPUR DINDING 3X KAPURAN


0.1000 M3 Kapur Sirih Diayak 150,000.00 15,000.00
1.0000 Tukang Batu 150,000.00 150,000.00
0.1000 Kepala Tukang 175,000.00 17,500.00
6.0000 Tukang Kapur 150,000.00 900,000.00
1,067,500.00 15,000.00
1 M2 Mengapur dinding baru = 1/100 x G,53 10,675.00 150.00

G.60 1 M2 PASANG BETON CETAK / PAVING BLOK


40.0000 Bh. Paving blok 1,500.00 60,000.00
0.1000 M3 Pasir Beton 80,000.00 8,000.00
0.1000 Tukang batu 150,000.00 15,000.00
0.4000 Pekerja 80,000.00 32,000.00
47,000.00 68,000.00

G.68 A 1 M1 PASANGAN PLINT LANTAI


1.6700 a. Bh F. Keramik 10 x 60 Cm 2,700.00 4,509.00
2.5000 b. Bh F. Keramik 10 x 40 Cm 1,800.00 4,500.00
3.3300 c. Bh F. Keramik 10 x 30 Cm 1,600.00 5,328.00
5.0000 d. Bh F. Keramik 10 x 20 Cm 1,300.00 6,500.00
1.6700 e. Bh F. Marmer 10 x 60 Cm 3,600.00 6,012.00
2.5000 f . Bh F. Marmer 10 x 40 Cm 2,400.00 6,000.00
1.6700 g. Bh F. Granit 10 x 60 Cm 6,000.00 10,020.00
2.5000 h. Bh F. Granit 10 x 40 Cm 4,000.00 10,000.00
0.0620 Zak semen Batu Raja 61,000.00 3,782.00
0.0020 M3 Pasir pasang 75,000.00 150.00
0.1000 Tukang 150,000.00 15,000.00
0.0100 Kepala tukang 175,000.00 1,750.00
0.2000 Pekerja 80,000.00 16,000.00
0.0100 Mandor 175,000.00 1,750.00
a 34,500.00 8,441.00
b 34,500.00 8,432.00
c 34,500.00 9,260.00
d 34,500.00 10,432.00
e 34,500.00 9,944.00
f 34,500.00 9,932.00
g 34,500.00 13,952.00
h 34,500.00 13,932.00
1 2 3 4 5
G.69.A 1 M2 PASANGAN LANTAI KERAMIK
2.7000 a. Bh Keramik 60 x 60 Cm 16,250.00 43,875.00
6.2500 b. Bh Keramik 40 x 40 Cm 7,200.00 45,000.00
11.1000 c. Bh Keramik 30 x 30 Cm 4,100.00 45,510.00
25.0000 d. Bh Keramik 20 x 20 Cm 1,800.00 45,000.00
100.0000 e. Bh. Keramik 10 x 10 cm 700.00 70,000.00
2.7800 f. Bh Marmer 60 x 60 Cm 51,500.00 143,170.00
4.1700 g. Bh Marmer 40 x 60 Cm 43,250.00 180,352.50
6.2500 h. Bh Marmer 40 x 40 Cm 35,000.00 218,750.00
2.7800 i. Bh Granit 60 x 60 Cm 55,000.00 152,900.00
4.1700 j. Bh Granit 40 x 60 Cm 47,500.00 198,075.00
6.2500 k. Bh Granit 40 x 40 Cm 40,000.00 250,000.00
0.0250 Perekat G,14 764,210.00 19,105.25
0.0560 Zak semen Batu Raja 61,000.00 3,416.00
0.0320 M3 Pasir pasang 75,000.00 2,400.00
0.3000 Tukang 150,000.00 45,000.00
0.0250 Kepala tukang 175,000.00 4,375.00
0.5000 Pekerja 80,000.00 40,000.00
0.0250 Mandor 175,000.00 4,375.00
a 93,750.00 68,796.25
b 93,750.00 69,921.25
c 93,750.00 70,431.25
d 93,750.00 69,921.25
e 93,750.00 94,921.25
f 93,750.00 205,273.75
g 93,750.00 243,671.25
h 93,750.00 177,821.25
i 93,750.00 222,996.25
j 93,750.00 274,921.25
G.69.C 1 M2 PASANGAN DINDING KERAMIK
50.0000 a buah Kramik 10 x 20 cm 1,300.00 65,000.00
25.0000 b buah Keramik 20 x 20 cm 1,800.00 45,000.00
11.1000 c buah Keramik 30 x 30 cm 4,100.00 45,510.00
2.7800 d buah Marmer 60 x 60 cm 51,500.00 143,170.00
4.1700 e buah Marmer 40 x 60 cm 43,250.00 180,352.50
2.7800 f buah Granit 60 x 60 cm 55,000.00 152,900.00
4.1700 g buah Granit 40 x 40 cm 40,000.00 166,800.00
1.2000 h M2 batu muka hitam 35,000.00 42,000.00
0.0180 zak Semen putih 70,000.00 1,260.00
0.1175 zak Semen Baturaja 61,000.00 7,167.50
0.0095 M3 Pasir pasang 75,000.00 712.50
1.0000 Tukang 150,000.00 150,000.00
0.1000 Kepala tukang 175,000.00 17,500.00
0.5000 Pekerja 80,000.00 40,000.00
0.0750 Mandor 175,000.00 13,125.00
a 220,625.00 74,140.00
b 220,625.00 54,140.00
c 220,625.00 54,650.00
d 220,625.00 152,310.00
e 220,625.00 189,492.50
f 220,625.00 162,040.00
g 220,625.00 175,940.00
h 220,625.00 51,140.00
1 M2 Pasang Dinding Keramik Ornamen = b x 1,4 i
G.81 10 M' PASANGAN SALURAN AIR HUJAN
400.0000 buah Batu bata merah 500.00 200,000.00
0.5340 Perekat G,19 627,750.00 335,218.50
2.9000 Tukang 150,000.00 435,000.00
0.2900 Kepala tukang 175,000.00 50,750.00
0.4000 Mandor 175,000.00 70,000.00
555,750.00 535,218.50
Untuk 1 M' Pas. Saluran air hujan 1/10 x nya 55,575.00 53,521.85
H. 1 M' PASANG BOWPLANK
0.0100 M3 Kayu kasau kelas III 1,200,000.00 12,000.00
0.0600 Kg paku 8,000.00 480.00
0.0420 Pekerja 80,000.00 3,360.00
0.0110 Tukang 150,000.00 1,650.00
0.0014 Kepala Tukang 175,000.00 245.00
5,255.00 12,480.00
H.2 1 M2 PASANGAN ATAP GENTENG
23.0000 a. Buah Genteng Mantili 750.00 17,250.00
11.0000 b. Buah Genteng Beton 3,500.00 38,500.00
22.0000 c. Buah Genteng Kodok, plentong 1,500.00 33,000.00
25.0000 d. Buah Genteng Biasa 550.00 13,750.00
18.0000 e. Genteng kramik 3,250.00 58,500.00
0.1000 Tukang 150,000.00 15,000.00
0.0100 Kepala tukang 175,000.00 1,750.00
0.2000 Pekerja 80,000.00 16,000.00
0.0100 Mandor 175,000.00 1,750.00
a. 34,500.00 17,250.00
b. 34,500.00 38,500.00
c. 34,500.00 33,000.00
d. 34,500.00 13,750.00
e. 34,500.00 58,500.00

1 2 3 4 5

H.6 1 M! PASANGAN BUBUNGAN GENTENG


5.0000 a. Buah Bubungan Genteng Mantili 1,500.00 7,500.00
4.0000 b. Buah Bubungan Genteng Beton 4,250.00 17,000.00
5.0000 c. Buah Bubungan Genteng Kodok, plentong 4,500.00 22,500.00
5.0000 d. Buah Bubungan Genteng Biasa 1,250.00 6,250.00
5.0000 e. Buah Bubungan Genteng kramik 4,500.00 22,500.00
0.0300 Perekat G,16 529,250.00 15,877.50
0.0324 M3 Pasir Pasang 75,000.00 2,427.75
0.2000 Tukang 150,000.00 30,000.00
0.0200 Kepala tukang 175,000.00 3,500.00
0.4000 Pekerja 80,000.00 32,000.00
0.0200 Mandor 175,000.00 3,500.00
a. 69,000.00 25,805.25
b. 69,000.00 35,305.25
c. 69,000.00 40,805.25
d. 69,000.00 24,555.25
e. 69,000.00 40,805.25

H.8 1 M2 PASANG ATAP SENG/ASBES GELOMBANG


0.3650 a. Lbr Asbes gelombang( 300x105x0,4 ) Cm 44,000.00 16,060.00
0.4600 b. Lbr Asbes gelombang( 240x105x0,4 ) Cm 36,000.00 16,560.00
0.6200 c. Lbr Asbes gelombang( 240x80x0,4 ) Cm 25,000.00 15,500.00
0.6200 d. Lbr Asbes gelombang( 180x105x0,4 ) Cm 27,000.00 16,740.00
0.8500 e. Lbr Asbes gelombang( 180x80x0,4 ) Cm 19,000.00 16,150.00
0.0800 kg Paku skrup / Asbes 23,000.00 1,840.00
0.2000 Tukang 150,000.00 30,000.00
0.0200 Kepala tukang 175,000.00 3,500.00
0.1000 Pekerja 80,000.00 8,000.00
0.0050 Mandor 175,000.00 875.00
a. 42,375.00 17,900.00
b. 42,375.00 18,400.00
c. 42,375.00 17,340.00
d. 42,375.00 18,580.00
e. 42,375.00 17,990.00

H.10 1 M' BUBUNGAN SENG/ASBES


1.0000 a,Lbr Asbes bubungan 20,000.00 20,000.00
1.0000 a,Lbr Bubungan Seng 24,000.00 24,000.00
0.0400 kg Paku skrup 50 buah/kg 23,000.00 920.00
0.0250 Tukang 150,000.00 3,750.00
0.0025 Kepala tukang 175,000.00 437.50
0.0250 Pekerja 80,000.00 2,000.00
a. 6,187.50 20,920.00
b. 6,187.50 24,920.00

H.15 10 M' TALANG PATAHAN


10.0000 M Seng talang 21,000.00 210,000.00
0.3500 kg Paku seng 18,000.00 6,300.00
6.0000 Tukang 150,000.00 900,000.00
0.6000 Kepala tukang 175,000.00 105,000.00
3.6000 Pekerja 80,000.00 288,000.00
0.1750 Mandor 175,000.00 30,625.00
1,323,625.00 216,300.00
Untku 1 M = 1/10 x nya 132,362.50 21,630.00

H 18 A 1 M' PASANG PIPA PARALON


0.4000 a Btg Pipa paralon 3" 90,000.00 36,000.00
0.4000 b Btg Pipa paralon 2,5 " 70,000.00 28,000.00
0.4000 c Btg Pipa paralon 1" 30,000.00 12,000.00
0.4000 d Btg Pipa paralon 3/4 " 22,500.00 9,000.00
0.4000 e Btg Pipa paralon 4" 130,000.00 52,000.00
0.2500 Sock 12,000.00 3,000.00
0.0200 Kg lem Pipa / Plastik 23,000.00 460.00
0.3750 Tukang pipa 150,000.00 56,250.00
0.0250 Pekerja 80,000.00 2,000.00
0.0110 Mandor 175,000.00 1,925.00
a 60,175.00 39,460.00
b 31,460.00
c 15,460.00
d 15,460.00
e 55,460.00

H 18 C 1 M' PASANG PIPA DORONG


0.2000 Pipa Galvanis dia. 1,5" 110,000.00 22,000.00
0.2000 Shock Drat 18,000.00 3,600.00
0.2813 Tukang pipa 150,000.00 42,187.50
0.1688 Pekerja 80,000.00 13,500.00
0.0083 Mandor 175,000.00 1,443.75
57,131.25 25,600.00

1 2 3 4 5

K.17 10 M2 MENGERJAKAN CAT WARNA


1.2500 Kg. Cat Warna 25,000.00 31,250.00
0.9600 Ltr Minyak cat 9,500.00 9,120.00
0.7500 Tukang cat 150,000.00 112,500.00
0.0750 Kepala tukang 175,000.00 13,125.00
0.5000 Pekerja 80,000.00 40,000.00
0.0250 Mandor 175,000.00 4,375.00
170,000.00 40,370.00
1 m2 mengecat warna 1/10 x k 17 17,000.00 4,037.00

K.18 10 M2 MENGECAT MENI


0.8400 Kg. Cat Meni 9,000.00 7,560.00
0.4400 Ltr Minyak cat 9,500.00 4,180.00
5.0000 Lbr Amplas 3,000.00 15,000.00
0.7500 Tukang cat 150,000.00 112,500.00
0.0750 Kepala tukang 175,000.00 13,125.00
0.5000 Pekerja 80,000.00 40,000.00
0.0250 Mandor 175,000.00 4,375.00
170,000.00 26,740.00
1 m2 mengecat warna 1/10 x k 18 17,000.00 2,674.00

K.30 10 M2 MENGERJAKAN DEMPUL


0.8000 Kg. Dempul 10,000.00 8,000.00
0.1000 Kg. Batu Kembang 2,500.00 250.00
0.4000 Tukang cat 150,000.00 60,000.00
0.0400 Kepala tukang 175,000.00 7,000.00
67,000.00 8,250.00
1 m2 Mengerjakan dempul 1/10 x K 30 6,700.00 825.00

K.17 + 1 M2 MENGECAT KAYU / BESI JADI


K.18 + 1 m2 mengecat kayu / besi jadi ( 1 x Cat ) 1 x K 17 17,000.00 4,037.00
K.30 1 x K 18 17,000.00 2,674.00
1 x K 30 6,700.00 825.00
40,700.00 7,536.00
K.17 + 1 m2 mengecat kayu / besi jadi ( 2 x Cat ) 2 x K 17 34,000.00 8,074.00
K.18 + 1 x K 18 17,000.00 2,674.00
K.30 1 x K 30 6,700.00 825.00
57,700.00 11,573.00

1 m2 mengecat kayu / besi jadi ( 3x Cat ) 3 x K 17 51,000.00 12,111.00


1 x K 18 17,000.00 2,674.00
1 x K 30 6,700.00 825.00
74,700.00 15,610.00
K.17 1 M2 MENGERJAKAN CAT BIDANG BESI
0.1500 Lbr. Amplas 3,000.00 450.00
0.2000 Kg. Cat Meni 9,000.00 1,800.00
0.1500 Ltr. Minyak cat 9,500.00 1,425.00
0.0300 bh. Kuas 20,000.00 600.00
0.1700 Kg. Cat dasar 25,000.00 4,250.00
0.2600 Kg. Cat penutup 25,000.00 6,500.00
0.7500 Tukang cat 150,000.00 112,500.00
0.0750 Kepala tukang 175,000.00 13,125.00
0.5000 Pekerja 80,000.00 40,000.00
0.0250 Mandor 175,000.00 4,375.00
170,000.00 15,025.00

K.1 10 M2 MENGERJAKAN POLITUR


1.0000 Ltr Politur 23,000.00 23,000.00
0.1000 Upah mengecat K.17 17,000.00 1,700.00
1.0000 K.30 7,525.00 7,525.00
9,225.00 23,000.00

K.35 10 M2 KAYU DI TEER / DIRESIDO 2 KALI


0.3500 Kg Teer 5,000.00 1,750.00
0.1000 Pekerja 80,000.00 8,000.00
0.0050 Mandor 175,000.00 875.00
8,875.00 1,750.00
1 M2 Meresidu 2 kali = 1/10 nya 887.50 175.00
1m2 Meresidu 3 x = 1.5 x K35 1,331.25 262.50
1m2 Meresidu 1 x = 0.5 x K35 443.75 87.50
Supl.IX.A 1M2 MENGECAT TEMBOK / PLAFOND 3 X CAT
0.4000 Kg Cat tembok 11,000.00 4,400.00
0.0800 Kg Plamir Tembok 7,000.00 560.00
0.0500 Lbr Amplas 3,000.00 150.00
0.0750 Tukang cat 150,000.00 11,250.00
0.0500 Pekerja 80,000.00 4,000.00
0.0750 Mandor 175,000.00 13,125.00
1M2 3 X CAT TEMBOK / DINDING 1 X SUPL IX A 28,375.00 5,110.00
1M2 3 X CAT PLAFOND/ GENTENG 1,5 X SUPL IX A 42,562.50 5,110.00
1M 2 1X Cat tembok = 0.33 x Supl IX A 9,363.75 1,686.30
1M 2 1X Cat plafond/genteng = 0.33 x 1,5 X Supl IX A 14,045.63 1,686.30
1 M2 2 X Cat Plafond/genteng =0.67x 1,5 x Supl IX A 28,516.88 3,423.70
1M 2 2X Cat tembok = 0.67 x Supl IX A 19,011.25 3,423.70
Supl .K PAS. KUNCI PINTU
1.0000 a. Buah Kunci 2 Slaag Kualitas Baik 120,000.00 120,000.00
1.0000 b. Buah Kunci 1 Slaag Kualitas Baik 50,000.00 50,000.00
0.5000 Tukang 150,000.00 75,000.00
0.1000 Pekerja 80,000.00 8,000.00
0.0500 Mandor 175,000.00 8,750.00
a. 91,750.00 120,000.00
b. 91,750.00 50,000.00

1 2 3 4 5

Supl.F29 PAS. ENGSEL PINTU/JENDELA


3.0000 a. Set Engsel Pintu Kualitas Baik 15,000.00 45,000.00
2.0000 b. Set Engsel Jendela Kualitas Baik 9,500.00 19,000.00
2.0000 c. Set Grendel Pintu Kualitas Baik 13,000.00 26,000.00
2.0000 d. Set Grendel Jendela Kualitas Baik 7,000.00 14,000.00
1.0000 e. Tarikan Jendela Kualitas Baik 6,000.00 6,000.00
2.0000 f. Hak Angin 7,000.00 14,000.00
0.3500 Tukang 150,000.00 52,500.00
0.1000 Pekerja 80,000.00 8,000.00
0.0500 Mandor 175,000.00 8,750.00
a. 69,250.00 45,000.00
b. 69,250.00 19,000.00
c. 69,250.00 26,000.00
d. 69,250.00 14,000.00
e. 69,250.00 6,000.00
f. 69,250.00 14,000.00

G.69.D 1 M2 PAS. DINDING BATU TEMPEL


1.0000 a, M2Batu tempel Palimanan 80,000.00 80,000.00
1.0000 b, M2 Batu Muka Hitam 35,000.00 35,000.00
0.1175 zak Semen Baturaja 61,000.00 7,167.50
0.0095 M3 Pasir pasang 75,000.00 712.50
1.0000 Tukang 150,000.00 150,000.00
0.1000 Kepala tukang 175,000.00 17,500.00
0.5000 Pekerja 80,000.00 40,000.00
0.0750 Mandor 175,000.00 13,125.00
a 220,625.00 87,880.00
b 220,625.00 42,880.00

70 10 M2 MENURUNKAN RANGKA ATAP DARI KAYU


(Dipakai kembali)
1.0000 Pekerja 80,000.00 80,000.00
0.2500 Tukang 150,000.00 37,500.00
0.0250 Kepala Tukang 175,000.00 4,375.00
0.0500 Mandor 175,000.00 8,750.00
130,625.00
1 m2 nya

70a 1 M2 Menurunkan Atap Tidak dipakai lagi


0.1000 Pekerja 80,000.00 8,000.00
0.0050 Mandor 175,000.00 875.00
8,875.00

70b 1 M3 MEMBONGKAR KUDA-KUDA/GORDING


kayu bongkaran dapat dipakai lagi
4.0000 Pekerja 80,000.00 320,000.00
6.0000 Tukang 150,000.00 900,000.00
0.6000 Kepala Tukang 175,000.00 105,000.00
0.2000 Mandor 175,000.00 35,000.00
1,360,000.00

Supl. XII 100 kg KONTRUKSI BAJA RINGAN


110.0000 kg Profil baja ringan 25,000.00 2,750,000.00
1.0000 Ls Plat penyambung baja ringan 60,000.00 60,000.00
250.0000 bh Sekrup baja ringan 200.00 50,000.00
0.1300 Hari Mesin bor listrik 40,000.00 5,200.00
0.0600 Hari Mesin genset 150,000.00 9,000.00
2.0000 Hari Kepala Tukang 175,000.00 350,000.00
0.5000 Hari Mandor 175,000.00 87,500.00
5.0000 Hari Tukang konst. Baja / besi 150,000.00 750,000.00
10.0000 Hari Pekerja 80,000.00 800,000.00
1,987,500.00 2,874,200.00
untuk 1 Kg kontruksi baja baja ringan = 0,01 x a 19,875.00 28,742.00

Supl. XIIA 100 kg KONTRUKSI BAJA


110.0000 Kg Baja Profil 11,000.00 1,210,000.00
1.0000 Kg Las 12,000.00 12,000.00
0.1300 Hari Mesin las 65,000.00 8,450.00
0.0600 Hari Mesin derek 50,000.00 3,000.00
2.0000 Hari Kepala Tukang 175,000.00 350,000.00
0.5000 Hari Mandor 175,000.00 87,500.00
5.0000 Hari Tukang Las 150,000.00 750,000.00
10.0000 Hari Pekerja 80,000.00 800,000.00
1,987,500.00 1,233,450.00
untuk 1 Kg kontruksi baja baja ringan = 0,01 x Sup.XIIA 19,875.00 12,334.50
Supl. XIIB 10 buah Pasang Dyna Bolt
10.0000 Bh Dyna Bolt 1,750.00 17,500.00
0.2500 Kg Kawat Las 20,000.00 5,000.00
0.5000 Hari Mesin las 65,000.00 32,500.00
0.5000 Hari Bor tangan 65,000.00 32,500.00
0.0025 Hari Kepala Tukang 175,000.00 437.50
0.0250 Hari Mandor 175,000.00 4,375.00
0.0250 Hari Tukang 150,000.00 3,750.00
0.5000 Hari Pekerja 80,000.00 40,000.00
48,562.50 87,500.00
untuk 1 buah dyna bolt = 0,1 x Supl. XIIC 4,856.25 8,750.00
Supl. XIIC 100 kg KONTRUKSI BAJA
110.0000 Kg Baja Profil 11,000.00 1,210,000.00
1.0000 Kg Kawat Las 20,000.00 20,000.00
0.1300 Hari Mesin las 65,000.00 8,450.00
2.0000 Hari Kepala Tukang 175,000.00 350,000.00
0.5000 Hari Mandor 175,000.00 87,500.00
5.0000 Hari Tukang Las 150,000.00 750,000.00
10.0000 Hari Pekerja 80,000.00 800,000.00
1,987,500.00 1,238,450.00
untuk 1 Kg kontruksi baja baja ringan = 0,01 x Sup.XIID 19,875.00 12,384.50

0.320

1 2 3 4 5

Supl. XIII 1 M2 Menutup atap dengan genteng Metal .


a 2.150 Lbr Genteng Metal Superoof 77,000.00 165,550.00
b 2.150 Lbr Genteng Metal Versa trim t = 0.25 mm 39,930.00 85,849.50
c 2.150 Lbr Genteng Metal Transparan 1,4 Kg 111,800.00 240,370.00
d 2.150 Lbr Spandek -
4.000 Bh Paku skrup anti karat 200.00 800.00
1.000 Ls Alat Bantu 5,000.00 5,000.00
0.100 Pekerja 80,000.00 8,000.00
0.100 Tukang konst. Baja / besi 150,000.00 15,000.00
0.010 Kepala Tukang 175,000.00 1,750.00
0.010 Mandor 175,000.00 1,750.00
a 31,500.00 166,350.00
b 31,500.00 86,649.50
c 31,500.00 241,170.00
d 31,500.00 800.00

Supl. XIV 1 M' Talang Metal " Zincalume"


1.100 M Talang T. 0,4 mm 47,000.00 51,700.00
1.220 Kg Reng Baja Ringan RT 25,000.00 30,500.00
4.000 Bh Paku sekrup anti karat 200.00 800.00
0.250 Pekerja 80,000.00 20,000.00
0.100 Tukang besi 150,000.00 15,000.00
0.080 Kepala Tukang 175,000.00 14,000.00
0.025 Mandor 175,000.00 4,375.00
53,375.00 83,000.00
Supl. XV 1 M' Lisplank" Zincalume " dengan Lebar = 24 Cm
1.100 M Lisplank Zincalume 58,380.00 64,218.00
0.810 Kg Profil baja ringan 25,000.00 20,250.00
4.000 Bh Paku anti karat 200.00 800.00
0.250 Pekerja 80,000.00 20,000.00
0.100 Tukang kayu 150,000.00 15,000.00
0.080 Kepala Tukang 175,000.00 14,000.00
0.025 Mandor 150,000.00 3,750.00
52,750.00 85,268.00
Supl. XVI 1 M' Tutup bubungan / NOK dengan genteng Metal
a 0.870 Bh Nok puncak Gtg, Mtl Versatrim 36,000.00 31,320.00
b 2.900 Bh Nok Bulat Gtg, Metal superoof 52,360.00 151,844.00
2.000 Bh Paku anti karat 200.00 400.00
0.025 Pekerja 80,000.00 2,000.00
0.025 Tukang besi 150,000.00 3,750.00
0.0025 Kepala Tukang 175,000.00 437.50
0.0025 Mandor 175,000.00 437.50
a 6,625.00 31,720.00
b 6,625.00 152,244.00
Supl. XVII 1 M2 Pasang Dek Lantai Combideck,
a 1.000 M2 Combideck Tebal 0,75 mm 192,000.00 192,000.00
b 1.000 M2 Combideck tebal 0,85 mm 216,000.00 216,000.00
c 1.000 M2 Combideck tebal 1,00 mm 259,200.00 259,200.00
4.000 BH Paku anti karat 200.00 800.00
1.000 Ls Alat bantu 16,000.00 16,000.00
0.150 Pekerja 80,000.00 12,000.00
0.300 Tukang besi 150,000.00 45,000.00
0.030 Kepala Tukang 175,000.00 5,250.00
0.015 Mandor 175,000.00 2,625.00
a. 64,875.00 208,800.00
b. 64,875.00 232,800.00
c. 64,875.00 276,000.00
Sip. 1 1 M2 Pas. Jendela/Pintu Almunium
4.4000 M' Rangka Almunium 36,000.00 158,400.00
1.0000 M' Karet Lis 4,000.00 4,000.00
1.0000 M2 Kaca bening/polos t = 5 mm 52,000.00 52,000.00
6.0000 BH Paku keling / Rivet 300.00 1,800.00
4.4000 M' Karet Lis 4,000.00 17,600.00
2.0000 Tukang 150,000.00 300,000.00
0.0300 Kep. Tukang 175,000.00 5,250.00
0.1500 Pekerja 80,000.00 12,000.00
317,250.00 233,800.00
Sip. 2 1 M1 Pas. Kusen Almunium
1.1000 M' Rangka Almunium 50,000.00 55,000.00
4.0000 BH Paku keling / Rivet 300.00 1,200.00
1.0000 M' Karet Lis 4,000.00 4,000.00
Upah pemasangan 30,000.00
30,000.00 60,200.00
Sip. 3 Pas.Titik Lampu
0.2000 M' Kabel N Y A 3,000.00 600.00
0.2000 Pas. Accecories 6,000.00 1,200.00
2.0000 Instalator 175,000.00 350,000.00
0.0300 Mandor 175,000.00 5,250.00
0.1500 Pekerja 80,000.00 12,000.00
367,250.00 1,800.00

1 2 3 4 5

Supl.X , a 1 M' Pengeboran dia. 6" dari 0 s/d 40 m


1.100 kg Pengadaan Bentonit 55,000.00 60,500.00
0.200 hari Mesin Bor 120,000.00 24,000.00
0.200 hari Pompa 20000.00 4,000.00
0.400 hari Generator 30000.00 12,000.00
0.011 hari Mata Bor 1000000.00 11,000.00
0.040 hari Ahli Bor 35000.00 1,400.00
0.275 hari Operator 32000.00 8,800.00
0.168 hari Pekerja 25000.00 4,200.00
0.011 hari Mandor 32000.00 352.00
14,752.00 111,500.00
Supl.X , b 1 M' Pengeboran dia. 6" dari 40 s/d 100 m
1.350 kg Pengadaan Bentonit 55,000.00 74,250.00
0.600 hari Mesin Bor 120,000.00 72,000.00
0.600 hari Pompa 20000.00 12,000.00
1.200 hari Generator 30000.00 36,000.00
0.033 hari Mata Bor 1000000.00 33,000.00
0.040 hari Ahli Bor 35000.00 1,400.00
0.825 hari Operator 32000.00 26,400.00
0.504 hari Pekerja 25000.00 12,600.00
0.011 hari Mandor 32000.00 352.00
40,752.00 227,250.00
Supl.X , c 1 M' Pengadaan/Pemasangan Pipa PVC, dia. 4"
0.300 Btg a. Pipa "PVC" dia 4" 130,000.00 39,000.00
0.300 Btg b. Pipa "PVC" dia 3" 90,000.00 27,000.00
0.300 Btg c. Pipa "PVC" dia 2" 60,000.00 18,000.00
0.300 Btg d. Pipa "PVC" dia 1/2" 15,000.00 4,500.00
0.300 Btg e. Pipa "PVC" dia 3/4" 22,500.00 6,750.00
0.250 Bh Lem Pipa 25,000.00 6,250.00
0.375 hari Tukang Pipa 55,000.00 20,625.00
0.025 hari Pekerja 80,000.00 2,000.00
0.011 hari Mandor 175,000.00 1,925.00
a 24,550.00 45,250.00
b 24,550.00 33,250.00
c 24,550.00 24,250.00
d 24,550.00 10,750.00
e 24,550.00 13,000.00
Supl.X , d 1 M' Pengadaan/Pemasangan Gravel Pack
0.092 M3 Gravel Pack 60,000.00 5,520.00
0.025 hari Pekerja 25,000.00 625.00
0.375 hari Tukang 32000.00 12,000.00
0.011 hari Kepala Tukang 35000.00 385.00
1.000 Set Alat Bantu 20000.00 20,000.00
32,385.00 6,145.00
Supl.X , c 1 M' Pengadaan/Pemasangan Pipa PVC, dia. 3"
a 0.300 Btg Pipa "PVC" dia 3" 85,000.00 25,500.00
b 0.300 Btg Pipa "PVC" dia 3/4" 50,000.00 15,000.00
c 0.300 Btg Pipa "PVC" dia 1/2" 40,000.00 12,000.00
d 0.300 Btg Pipa "PVC" dia 1" 55,000.00 16,500.00
0.250 Bh Lem Pipa 25,000.00 6,250.00
0.375 hari Tukang Pipa 55,000.00 20,625.00
0.025 hari Pekerja 60,000.00 1,500.00
0.011 hari Mandor 175,000.00 1,925.00
a 24,050.00 31,750.00
b 24,050.00 21,250.00
c 24,050.00 18,250.00
d 24,050.00 22,750.00
JUMLAH
HARGA
( RP.)
6

16,750.00

64,375.00
12,875.00

65,775.00

128,750.00

28,150.00

10,909.09

13,312.50

41,875.00

75,750.00

21,750.00

103,750.00

268,750.00

413,250.00

383,250.00

109,900.00
73,312.50

266,250.00

150,500.00

242,490.00
249,630.00
238,990.00
221,490.00
265,500.00

121,680.00

43,480.00
43,480.00

636,770.00
641,770.00
596,770.00
796,770.00
533,100.00
549,100.00
666,100.00

967,325.00
943,325.00
483,662.50
471,662.50

851,300.00
830,300.00

465,400.00
484,600.00

403,000.00
453,000.00

356,190.00
356,146.00

400,550.00
382,950.00
512,840.00

183,955.00

151,240.00

227,100.00
200,700.00

48,337.50
40,637.50

219,750.00
201,750.00

6,933,000.00
6,163,000.00

4,660,500.00
3,890,500.00
3,913,500.00
3,143,500.00

9,540,000.00
8,700,000.00

9,430,000.00
8,590,000.00

10,577,500.00
9,737,500.00

435,012.50

1,057,950.00
1,064,950.00

835,175.00
831,725.00

6
713,300.00
726,100.00

230,650.00

624,200.00

508,000.00
443,200.00

764,210.00

529,250.00

627,750.00

860,327.00

1,185,588.00
118,558.80

1,387,291.00
138,729.10

6
807,402.00

1,053,640.00
84,291.20

54,651.70

1,203,100.00
1,293,300.00

921,165.00
1,136,325.00

3,713,000.00
3,823,000.00
2,784,750.00
2,867,250.00
4,641,250.00
4,778,750.00

1,847,000.00

1,931,000.00
2,770,500.00

6
7,728,600.00
7,928,800.00
4,355,050.00
-

5,881,600.00
5,971,800.00
6,081,800.00

4,916,100.00
5,006,300.00
5,116,300.00

2,168,600.00
2,258,800.00

4,015,600.00
4,105,800.00

7,728,600.00
7,818,800.00
7,928,800.00

5,881,600.00
5,971,800.00
6,081,800.00

4,916,100.00
5,116,300.00
5,116,300.00

2,168,600.00
3,461,900.00

4,015,600.00
4,105,800.00

6
1,022,390.00
1,132,390.00
71,567.30
79,267.30
51,119.50
56,619.50
102,239.00
113,239.00

70,154.40

75,015.00

1,082,500.00
10,825.00

115,000.00

42,941.00
42,932.00
43,760.00
44,932.00
44,444.00
44,432.00
48,452.00
48,432.00
6

162,546.25
163,671.25
164,181.25
163,671.25
188,671.25
299,023.75
337,421.25
271,571.25
316,746.25
368,671.25

294,765.00
274,765.00
275,275.00
372,935.00
410,117.50
382,665.00
396,565.00
271,765.00
384,671.00

1,090,968.50
109,096.85

17,735.00

51,750.00
73,000.00
67,500.00
48,250.00
93,000.00

94,805.25
104,305.25
109,805.25
93,555.25
109,805.25

60,275.00
60,775.00
59,715.00
60,955.00
60,365.00

27,107.50
31,107.50

1,539,925.00
153,992.50

99,635.00
31,460.00
15,460.00
15,460.00
55,460.00
82,731.25

210,370.00
21,037.00

196,740.00
19,674.00

75,250.00
7,525.00

48,236.00

69,273.00

90,310.00

185,025.00

32,225.00

10,625.00
1,062.50
1,593.75
531.25
33,485.00
47,672.50
11,050.05
15,731.93
31,940.58
22,434.95

211,750.00
141,750.00

114,250.00
88,250.00
95,250.00
83,250.00
75,250.00
83,250.00

308,505.00
263,505.00

130,625.00
13,062.50

8,875.00

1,360,000.00
48,617.00

32,209.50

136,062.50
13,606.25

32,259.50

197,850.00
118,149.50
272,670.00
32,300.00

136,375.00
138,018.00

38,345.00
158,869.00

273,675.00
297,675.00
340,875.00

551,050.00

90,200.00

369,050.00

126,252.00

268,002.00
69,800.00
57,800.00
48,800.00
35,300.00
37,550.00

38,530.00

55,800.00
45,300.00
42,300.00
46,800.00
DAFTAR HARGA UPAH DAN BAHAN
UNTUK PEKERJAAN KABUPATEN LAMPUNG SELATAN

No. URAIAN SATUAN HARGA SATUAN KETERANGAN


Rp
1 2 3 4 5

I A. UPAH
1 Mandor hari 175,000.00
2 Kepala Tukang hari 175,000.00
3 Tukang (Batu, Kayu, Besi) hari 150,000.00
4 Pekerja hari 80,000.00
5 Penggergaji hari 80,000.00
6 Instalator hari 150,000.00

II B. Bahan
1 Batu belah hitam M3 115,000.00
2 Batu belah putih M3 85,000.00
3 Batu pecah 10-15 cm M3 105,000.00
4 Batu pecah 7-10 cm M3 115,000.00
5 Batu pecah 5-7 cm M3 125,000.00
6 Batu pecah 3-5 cm M3 140,000.00
7 Batu pecah 2-3 cm M3 165,000.00
8 Batu pecah 1-2 cm M3 200,000.00
9 Batu pecah 0,5-1 cm M3 200,000.00
10 Base B M3 150,000.00
11 Batu muka M3 90,000.00
12 Batu bata Bh 500.00
13 Batu Kembang Kg 2,500.00
14 Paving Blok Bh 1,500.00
15 Beton roster Bh 2,350.00
16 Batu Tempel palimanan M2 80,000.00
17 Batu cor/split ( 1-2 / 2-3 ) cm M3 165,000.00
18 Koral M3 55,000.00
19 Paving Blok M2 65,000.00
20 Batu muka hitam M2 35,000.00
21 Batu tempel kasar/parimanan M2 75,000.00
22 Kerikil Galian bukit M3 45,000.00
23 Kerikil Sungai M3 55,000.00
24 Kerikil kali disaring M3 60,000.00
25 Sirtu M3 70,000.00
26 Tanah Timbunan Pilihan M3 45,000.00
27 Air liter 50.00

III Pasir
1 Pasir Urug M3 65,000.00
2 Pasir pasang M3 75,000.00
3 Pasir cor / beton M3 80,000.00

IV Semen
1 Semen Zak 61,000.00
2 Semen PC 50 Kg Zak 61,000.00
3 Semen Putih Zak 70,000.00
4 Kapur sirih di ayak M3 150,000.00
5 Pasta semen untuk nat kramik Kg 10,000.00
1 2 3 4 5
V Atap
1 Genteng Mantili Bh 750.00
2 Bubungan Genteng Mantili Bh 1,500.00
3 Genteng Biasa Bh 550.00
4 Bubungan Genteng Biasa Bh 1,250.00
5 Genteng kodok/ plentong Bh 1,500.00
6 Bubungan genteng kodok/plentong Bh 4,500.00
7 Seng BJLS 35" Lbr 23,000.00
8 Seng Rata Lbr 25,000.00
9 Seng Almunium Lbr 40,000.00
10 Kerpus genteng plentong Bh 4,500.00
11 Bubungan genteng beton Bh 4,250.00
12 Genteng beton Bh 3,500.00
13 Atap asbes gelombang kecil Bh 7,500.00
14 Bubungan Asbes Lbr 20,000.00
15 Bubungan Seng Lbr 24,000.00
16 Asbes gelombang (300x105x0.4) cm Lbr 44,000.00
17 Asbes super rata Bh 36,100.00
18 Genteng multiroof M2 90,000.00
19 Genteng Kramik Bh 3,250.00
20 Bubungan Genteng Kramik Bh 4,500.00
21 Genteng Morondo S7 Biasa Bh 1,800.00
22 Bubungan Genteng Morondo S7 Biasa Bh 2,400.00
23 Genteng Kaca Bh 6,000.00
24 Asbes gelombang (300x105x0,4) cm Lbr 44,000.00
25 Asbes gelombang (120x105x0,4) cm Lbr 24,000.00
26 Asbes gelombang (180x80x0,4) cm Lbr 19,000.00
27 Asbes gelombang (240x80x0,4) cm Lbr 25,000.00
28 Asbes gelombang (240x105x0,4) cm Lbr 36,000.00
29 Asbes gelombang (180x105x0,4) cm Lbr 27,000.00
30 Nok asbes gelombang stl 18,000.00
31 Asbes pla. (200x120x0,4) cm m2 15,000.00
32 Asbes pla. (200x120x0,4) cm m2 20,000.00
33 Asbes pla. (100x120x0,4) cm m2 18,000.00
34 Nok Asbes rata Stl 10,000.00
35 Koraflek/Harfleks M2 10,000.00
36 Daun Pintu Almunium M2 350,000.00

VI Kayu
1 Kayu papan kls I M3 2,500,000.00
2 Kayu balok kls I M3 2,400,000.00
3 Kayu balok kls II M3 1,900,000.00
4 Kayu papan Kls II M3 2,000,000.00
5 Kayu balok Kls III M3 1,200,000.00
6 Kayu papan Kls III M3 1,400,000.00
7 Kayu Papan kls IV M3 1,200,000.00
8 Kayu Bekisting M3 1,200,000.00
9 Kayu kasau/Reng klas IV M3 1,200,000.00
10 Triplek (240x120x0.3) cm Lbr 45,000.00
11 Teak wood ( 240x120x0,3)Cm Lbr 105,000.00
12 Giypsum ( 240 x 120 x 0,6 ) Cm Lbr 125,000.00
13 Multiplek ( 240x120x1,2 ) Cm Lbr 155,000.00
14 Multiplek (240x120x0,1 ) Cm Lbr 130,000.00
15 Multiplek ( 240 x 120 x0,8) Cm Lbr 115,000.00
16 Multiplek ( 240 x 120 x 0,6) Cm Lbr 95,000.00
17 Formika ( 240 x 120 x 0,6) Cm Lbr 45,000.00
18 Almunium Voil M2 26,000.00
19 Lem Kayu Kg 33,000.00

1 2 3 4 5

20 Sambungan Almunium Voil M2 20,000.00


21 List Plafond Profile 4/4 cm m' 12,000.00
22 Bambu m' 1,500.00
23 Pagar hidup (tanaman) Btg 250.00
24 Tanaman taman Btg 7,500.00
25 Rotan Btg 12,500.00
26 Karpet talang M1 7,500.00
27 List Profil Beton M1 60,000.00
28 Rumput m2 5,000.00
29 Profile pagar m2 54,000.00
30 Geribik M2 35,000.00
31 Bingkai lampu profil gypsum Bh 35,000.00
32 Profil Gypsum M' 60,000.00

VII Besi dan Kaca


1 Kawat Berduri ( 50 mm) m' 3,000.00
2 Kawat beton Kg 9,000.00
3 Paku Kg 10,000.00
4 Paku triplek Kg 12,000.00
5 Paku kasau/Balok Kg 8,000.00
6 Paku papan/Reng Kg 9,000.00
7 Paku keling BH 1,000.00
8 Paku Gypsum Kg 19,000.00
9 Paku Cacing Kg 22,000.00
10 Paku Sekerup (50 Bh/Kg) Kg 23,000.00
11 Paku Seng (100 Bh/Kg) Kg 18,000.00
12 Besi beton Ulir Kg 11,000.00
13 Besi beton Polos Kg 10,000.00
14 Besi Siku Kg 11,000.00
15 Besi persegi Kg 11,000.00
16 Besi Kotak 60x60 Kg 11,000.00
17 Besi Kotak 40x60 Kg 11,000.00
18 Besi Kotak 40x40 Kg 11,000.00
19 Dyna Bolt Ø 10mm Bh 1,750.00
20 Besi teralis m2 170,000.00
21 Besi teralis tempa ulir m2 220,000.00
22 Plat 400x300/3 Btg 40,000.00
23 Pagar BRC m2 27,000.00
24 Kaca bening/polos 8 mm m2 185,000.00
25 Kaca bening/polos 5 mm m2 52,000.00
26 Kaca bening/ polos 3 mm m2 40,000.00
27 Kaca riben/ buram 3 mm m2 45,000.00
28 Kaca riben/ buram 5 mm m2 68,000.00
29 Kaca Warna tebal 8 mm m2 200,000.00
30 Kaca bayang/rias 5 mm M' 43,000.00
31 Seng alumunium m2 21,000.00
32 Seng gelombang Lbr 22,000.00
33 Seng bubungan M' 16,000.00
34 Seng rata Lbr 20,000.00
35 Baut , Mur , Plat U 40.3 Set 15,000.00
36 Kawat las Kg 20,000.00
37 Kawat harmonika Kg 17,000.00
38 Kawat nyamuk m2 10,000.00
39 pasangan profil beton M' 60,000.00
40 Kusen Fiber kamar mandi Lengkap Unit 350,000.00
41 Pintu besi lapis plat 1.2 mm m2 600,000.00
42 Pintu lipat besi 0.8 mm (2.5x4 m2) m2 500,000.00
43 Jalusi besi O 12 mm m2 150,000.00
44 Seng BJLS 28 " m2 20,000.00

1 2 3 4 5

VIII Lantai
1 Keramik lantai uk 20x20 cm Bh 1,800.00
2 Keramik lantai uk 30x30 cm Bh 4,100.00
3 Keramik lantai uk 40x40 cm Bh 7,200.00
4 Keramik lantai uk 60x60 cm Bh 16,250.00
5 F. Keramik 10x20 Bh 1,300.00
6 F. Keramik 10x30 Bh 1,600.00
7 F. Keramik 10x60 Bh 2,700.00
8 F. Keramik 10x40 Bh 1,800.00
9 F. Marmer 10x60 Bh 3,600.00
10 F. Marmer 10x30 Bh 8,000.00
11 F.Marmer 10x40 Bh 2,400.00
12 Granit 60x60 cm Bh 55,000.00
13 Granit 40x60 cm Bh 47,500.00
14 Granit 40x40 cm Bh 40,000.00
15 Granit 10x40 cm Bh 4,000.00
16 Granit 10x60 cm Bh 6,000.00
17 Marmer 60x60 cm Bh 51,500.00
18 Marmer 40x40 cm Bh 35,000.00
19 Marmer 40x60 Bh 43,250.00
IX Penggantung dan Kunci
1 Kunci 2 slag kwt baik Bh 120,000.00
2 Kunci 2 slag biasa Bh 70,000.00
3 Kunci 1 slag Bh 50,000.00
4 Engsel pintu Bh 15,000.00
5 Grendel pintu Bh 13,000.00
6 Engsel Jendela Bh 9,500.00
7 Grendel jendela Bh 7,000.00
8 Tarikan jendela Bh 6,000.00
9 Hak angin Bh 7,000.00
10 Plat, Mur, Baut/Begel U Set 15,000.00
11 Gembok pintu stenlis Bh 30,000.00

X Sanitasi air
1 Kloset jongkok porselen Bh 150,000.00
2 Kloset duduk porselen Bh 1,250,000.00
3 Floor Drain Bh 12,000.00
4 Wastafel porselen Bh 600,000.00
5 Bak fiber Glass 50.50.70 Bh 170,000.00
6 Bak cuci piring alumunium 1 lubang Bh 125,000.00
7 Bak besar porselen Bh 300,000.00
8 Bak kecil porselen Bh 150,000.00
9 Bak traso biasa Bh 83,000.00
10 Bentonit Kg 55,000.00
11 Gravel Pack 3-6mm M3 60,000.00
12 Lem pipa Bh 25,000.00
13 Pipa GIV Diameter 0,50" Btg 35,000.00
14 Pipa GIV Diameter 0,75" Btg 45,000.00
15 Pipa GIV Diameter 1" Btg 60,000.00
16 Pipa GIV Diameter 1,50" Btg 90,000.00
17 Pipa GIV Diameter 2,00" Btg 120,000.00
19 Paralon dia 0,50" Btg 15,000.00
20 Paralon dia 0,75" Btg 22,500.00
21 Paralon dia 1,00" Btg 30,000.00
22 Paralon dia 1,50" Btg 45,000.00
23 Paralon dia 2,00" Btg 60,000.00
23 Paralon dia 2,50" Btg 70,000.00
24 Paralon dia 3,00" Btg 90,000.00

1 2 3 4 5

25 Paralon dia 4,00" Btg 130,000.00


26 Paralon dia 6,00" Btg 150,000.00
27 Paralon dia 8,00" Btg 240,000.00
28 Kran air 1" Bh 90,000.00
29 Kran air 3/4" Bh 34,000.00
30 Kran Dia. 1/2" bh 15,000.00
31 Kran air Stenlis bh 20,000.00
32 Saringan air m' 60,000.00
33 Selang water pass m' 1,800.00
34 Septi tank & Resapan Unit 3,500,000.00
35 Water Torn/ Tower 4 m3 Unit 3,000,000.00
36 Sumur Gali Unit 2,000,000.00
37 Bak kontrol Unit 215,000.00
38 Air mancur/ Terjun Unit 2,000,000.00
39 Lem plastik Kg 23,000.00
40 Jet Pump Unit 2,500,000.00
41 Pompa air kapasitas t = 12m Unit 500,000.00
42 Bak Fiber 1 M3 Bh 1,200,000.00
43 Bak Fiber Dia. 60 cm Bh 750,000.00
44 Pipa Galvanis D,3" Btg 110,000.00
45 Shock Drat Bh 18,000.00
XI Peralatan Mesin Sumur Bor
I Tenaga Kerja Sumur Bor
1 Pekerja Hari 25,000.00
2 Mandor Hari 32,000.00
3 Tukang batu Hari 32,000.00
4 Tukang besi Hari 32,000.00
5 Tukang pipa Hari 55,000.00
6 Tukang Anyam, Las Hari 32,000.00
7 Tukang cat Hari 32,000.00
8 Kepala Tukang Hari 35,000.00
9 Operator terlatih Hari 32,000.00
10 Pembantu operator Hari 25,000.00
11 Sopir terlatih Hari 32,000.00
12 Pembantu Sopir Hari 25,000.00
13 Ahli bor Hari 35,000.00

XII Peralatan Mesin Sumur Bor


1 Alat Bantu Kerja Jalan Set 20,000.00
2 Alat Bantu Pipa Gl Dia 250 - 400 Set 60,000.00
3 Alat Bantu Pipa Gl Dia 150 Set 25,000.00
4 Alat Bantu Pipa Gl Dia 100 Set 20,000.00
5 Alat Bantu Pipa Gl Dia 75 Set 15,000.00
6 Alat Bantu Pipa Gl Dia 50 Set 10,000.00
7 Alat Bantu Asesoris GIP dia 200-150 mm Set 35,000.00
8 Alat Bantu Asesoris GIP dia 100-75 mm Set 30,000.00
9 Alat Bantu Logging dan Test Set 20,000.00
10 Alat Bantu Perpipaan PVC dia 200 mm Set 25,000.00
11 Alat Bantu Perpipaan PVC dia 150 mm Set 20,000.00
12 Alat Bantu Pipa PVC dia 100 Set 15,000.00
13 Alat Bantu Pipa PVC dia 75 Set 10,000.00
14 Alat Bantu Pipa PVC dia 50 Set 10,000.00
15 Alat Bantu Pengesetan Air Set 10,000.00
16 Alat Bantu Pompa air Ls 5,000.00
17 Wall Head, Grouting dll Ls 1,000,000.00

1 2 3 4 5

18 Compressor Jam 25,000.00


19 Alat Bantu untuk Pengecoran Set 12,500.00
20 Pompa Hari 20,000.00
21 Generator Hari 30,000.00
22 Mesin Bor Hari 120,000.00
23 Mata Bor Hari 1,000,000.00

XIII Listrik
1 Penyambungan Api Listrik Fasa 2,500,000.00
2 Pasang Titik Mata Lampu Ttk 130,000.00
3 Saklar tunggal Bh 20,000.00
4 Saklar ganda Bh 30,000.00
5 Lampu pijar 25 Watt/220 Volt Bh 17,500.00
6 Lampu TL 20 Watt/220 Vlt lengap Bh 40,000.00
7 Lampu lilin 20 watt/220 volt Bh 25,000.00
8 Lampu lilin 40 watt/220 volt Bh 40,000.00
9 Lampu Kapsul Bh 32,500.00
10 sekering/MCB Bh 150,000.00
11 Pasang stop kontak Bh 30,000.00
12 Saklar triple Bh 50,000.00
13 Lampu hias sorot Bh 275,000.00
14 Lampu HE Bh 40,000.00
15 Kabel listrik 1,5 mm Rol 56,250.00
16 Kabel listrikNYA M 3,000.00
17 Asesoris listrik Psg 6,000.00
18 Genset 5000 watt Unit 9,000,000.00
19 Control Panel Bh 2,500,000.00

XIV Cat dan Finishing


1 Cat tembok Kwt.baik Kg 11,000.00
2 Cat kayu kwt baik Kg 25,000.00
3 Cat meni Kg 9,000.00
4 Cat genting kwt baik Kg 18,000.00
5 Dempul Kayu Kg 10,000.00
6 Dempul Tembok Kg 10,000.00
7 Pelamir tembok Kg 7,000.00
8 Ter/ Residu Kg 5,000.00
9 Cherlag Kg 47,000.00
10 Cat warna Kg 25,000.00
11 Pelitur jadi Ltr 23,000.00
12 Politur Kg 15,000.00
13 Cat besi Kg 25,000.00
14 Minyak cat/abdur Ltr 9,500.00
15 Residu/teer Ltr 5,000.00
16 Sepritus Ltr 3,000.00
17 Amplas Lbr 3,000.00
18 Lem kayu Kg 30,000.00
19 Dempul kayu Kg 10,000.00
20 Plamur Ltr 8,500.00
21 Ember adukan bh 4,000.00
22 Gergaji besi bh 10,000.00
23 Benang nilon rol 3,000.00
24 Tali plastik m' 6,000.00
25 Pelamir kayu/ besi Kg 4,200.00
26 Kuas buah 20,000.00
27 meni kayu/besi Kg 9,000.00

1 2 3 4 5

XV Kuda -- kuda / Atap Baja Ringan


1 Profil baja ringan Destal C-Truss , Kg 25,000.00
2 Plat Penyambung Badan LS 60,000.00
3 Reng baja ringan RT- 15, Kg 25,000.00
4 Braccket U Truss, K - 31 BH 16,800.00
5 Plat Kopel K- 32 BH 2,160.00
6 Bracket Siku C Truss , K - 33 BH 16,080.00
7 Corner Plat C-Truss K- 34 m' 45,360.00
8 Corner Plat U Truss K - 35 m' 32,150.00
9 Plat Perletakan bh 45,000.00
10 Genteng Metal Superoof Tile Uk. 1,31 x 0,41 M bh 77,000.00
11 Genteng Metal Polycolor 2 reguler Uk. 1,31 x 0,41 M bh 48,400.00
12 Genteng Metal Versatrim Uk. 1,31 x 0,41 M bh 39,930.00
13 Nok Puncak Versatrim t = 0,25mm Panj, 1,20 M bh 36,000.00
14 Barge Berlekuk Superouf Panj. 1,373 M bh 62,900.00
15 Apron Flashing Superouf Panj. 1,373 M bh 62,900.00
16 Nok Bulat Superouf Panj. 0,395 M bh 52,360.00
17 Talang , T= 0,4 mm m' 47,000.00
18 Talang Zincalume destal Truss , T= 0,4 mm m' 39,000.00
19 Paku Sekrup anti karat bh 200.00
20 Lisplank Zincalume Lebar 24 cm m' 58,380.00
21 Combideck Tebal 0,75 mm uk. Dek plat beton M2 192,000.00
22 Combideck tebal 0,85 mm uk. Dek plat beton M2 216,000.00
23 Combideck tebal 1,00 mm uk. Dek plat beton M2 259,200.00
24 Rangka Almunium M' 36,000.00
25 Kusen Almunium M' 50,000.00
26 Karet lis kusen almunium M' 4,000.00
27 Mesin Bor Listrik Unit 40,000.00
28 Mesin Genset Unit 150,000.00
29 Alat bantu LS 16,000.00
30 Truss C 75.75 SNI BMT btg 75,000.00
31 Spandek 0.75 x 1m x 6m lbr 636,000.00
32 Paku keling Rivet Almunium bh 300.00
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : PEMBANGUNAN GUDANG PENYIMPANAN MATERIAL RETURN
LOKASI : PLTU
TAHUN : 2019

HARGA
JUMLAH HARGA
NO. URAIAN PEKERJAAN VOLUME SATUAN
(Rp.)
(Rp.)
1 2 4 5 6

I PEKERJAAN PERSIAPAN
1 Pembersihan Lapangan/Lean Clearing 502.79 M2 16,750.00 8,421,809.55
2 Mobilisasi dan demobilisasi 1.00 ls 5,000,000.00 5,000,000.00
3 Pengukuran dan pasangan bouwplank 117.00 M' 17,735.00 2,074,995.00
15,496,804.55

II PEKERJAAN PONDASI
1 Galian tanah pondasi 23.27 M3 64,375.00 1,498,006.25
2 Urugan pasir dibawah pondasi 3.10 M3 103,750.00 321,625.00
3 Pasang pondasi batu belah adk 1 : 4 15.51 M3 860,327.00 13,343,671.77
4 Urug tanah kembali pondasi 7.76 M3 21,750.00 168,780.00
15,332,083.02

III PEKERJAAN SLOOF DAN KOLOM


1 Sloof 15/20 adk 1:2:3 6.20 M3 5,971,800.00 37,025,160.00
37,025,160.00

IV PEKERJAAN DINDING
1 Pasang dinding spandek+tulangan 195.00 M2 512,840.00 100,003,800.00
2 Pasang tiang besi hollow 12.00 unit 3,100,000.00 37,200,000.00
137,203,800.00

V PEKERJAAN PINTU GUDANG SLIDING DOOR


1 Pasang pintu slide 2 arah bahan spandek+tulangan+besi hollow+pengecata 1.00 unit 16,750,000.00 16,750,000.00
16,750,000.00

VI PEKERJAAN LANTAI DAN JALAN


1 Pasang hamparan lantai split 1/2 cm 40.96 M3 413,250.00 16,926,720.00
2 Pasang hamparan lantai split 3/5 cm 40.96 M3 383,250.00 15,697,920.00
3 Pasang hamparan base B 61.43 M3 268,750.00 16,509,312.50
49,133,952.50

VII PEKERJAAN PENGECATAN


1 Pengecatan sloof 2 x Cat eksterior 58.75 M2 22,434.95 1,318,075.75
1,318,075.75
REKAPITULASI
PEKERJAAN : PEMBANGUNAN GUDANG PENYIMPANAN MATERIAL RETURN
LOKASI : PLTU
TAHUN : 2019

NO. ITEM PEKERJAAN BIAYA (Rp.)

A PEKERJAAN SHELTER

I PEKERJAAN PERSIAPAN 15,496,804.55

II PEKERJAAN PONDASI 15,332,083.02

III PEKERJAAN SLOOF DAN KOLOM 37,025,160.00

IV PEKERJAAN DINDING 137,203,800.00

V PEKERJAAN PINTU GUDANG SLIDING DOOR 16,750,000.00

VI PEKERJAAN LANTAI DAN JALAN 49,133,952.50

VII PEKERJAAN PENGECATAN 40,852,173.00

SUB TOTAL 311,793,973.07

PPN 10 % 31,179,397.31

DIBULATKAN 342,974,000.00

Terbilang : --- Dua Ratus Sembilan Puluh Sembilan Juta Empat Puluh Delapan Ribu Rupiah ----