Anda di halaman 1dari 1

PEMERINTAH KABUPATEN BUTON UTARA

DESA LINSOWU, KECAMATAN KULISUSU


Alamat : Desa Linsowu, Kec. Kulisusu

RINCIAN ANGGARAN BIAYA


PEKERJAAN : PENINGKATAN BANGUNAN MASJID NUR-IKHLAS
LOKASI : Desa Linsowu, Kec. Kulisusu, Kab. Buton Utara
TAHUN ANGGARAN : 2022
HARGA SATUAN JUMLAH TOTAL
NO. URAIAN KEBUTUHAN SATUAN
(Rp.) (Rp.)
I. BAHAN
2 Besi Beton Polos Ø12 36.00 Btg 145,000.00 5,220,000.00
3 Besi Beton Polos Ø8 27.00 Btg 73,000.00 1,971,000.00
4 Kawat Beton 8.00 Kg 30,000.00 240,000.00
5 Kayu kelas III 2.00 M3 1,900,000.00 3,800,000.00
6 Balok Kayu Kelas II 1.00 M3 2,500,000.00 2,500,000.00
7 Kerikil/Koral Beton 2.50 M3 320,000.00 800,000.00
8 Minyak bekisting 10.00 Ltr 25,000.00 250,000.00
9 Paku Campur 20.00 kg 25,000.00 500,000.00
10 Pasir 2.00 M3 200,000.00 400,000.00
11 Semen Portland 19.00 Zak 100,000.00 1,900,000.00
12 Plywood 9 mm 17.00 Lbr 90,000.00 1,530,000.00
13 Dolken Kayu Ø8-10cm Panjang 4 m 98.00 Btg 8,000.00 784,000.00
15 Air Kerja / P3K 1.00 Ls 500,000.00 500,000.00
17 Adminstrasi dan Dokumentasi 1.00 Ls 500,000.00 500,000.00
18 Pembersihan Akhir / Finishing 1.00 Ls 405,000.00 405,000.00
Sub Total I 21,300,000.00
II. UPAH KERJA
1 Pekerja 41.00 HOK 100,000.00 4,100,000.00
2 Tukang 20.00 HOK 125,000.00 2,500,000.00
3 Kepala tukang 2.00 HOK 130,000.00 260,000.00
4 Mandor 2.00 HOK 120,000.00 240,000.00
Sub Total II 7,100,000.00
A REAL COST 28,400,000.00
B BIAYA DESAIN & RAB 3 % 800,000.00
C OPERASIONAL TPK 2 % 500,000.00
D TOTAL COST (A+B) 29,700,000.00

Linsowu, 2022
Diperiksa Oleh; Dibuat Oleh;
Sekretaris Desa Linsowu Konsultan Perencana
Kec. Kulisusu, Kab.Buton Utara CV. ARY ANARCHINDO CONSULTANT

…………………….. LAODE MAHDIYANTO SAMARA, ST


Estimator

Mengetahui dan menyetujui ;


Kepala Desa Linsowu
Kec. Kulisusu, Kab.Buton Utara

SUHARDIN, SE.Sy