ANALISA BIAYA KONSTRUKSI

PEKERJAAN PERSIAPAN

PA 6.1. 1 m' Pagar Sementara dari kayu tinggi 2 meter

6.1.1. Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Semen Portland 2.500 Kg x Rp 1,400 = Rp 3,500.00
- Pasir Beton 0.005 M3 x Rp 300,000 = Rp 1,500.00
- Koral Beton 0.009 M3 x Rp 205,000 = Rp 1,845.00
- Kayu 5/7 0.038 M3 x Rp 3,107,500 = Rp 118,085.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp 18,000 = Rp 1,080.00
- Residu/colter 0.400 Lt x Rp 9,000 = Rp 3,600.00
Jumlah (1) = Rp 153,672.50

6.1.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 150,000 = Rp 30,000.00
- Pekerja 0.400 Oh x Rp 100,000 = Rp 40,000.00
- Kepala tukang 0.020 Oh x Rp 150,000 = Rp 3,000.00
- Mandor 0.020 Oh x Rp 175,000 = Rp 3,500.00
Jumlah (2) = Rp 76,500.00
Jumlah (1) + (2) = Rp 230,172.50

PA 6.2. 1 m' Pagar sementara dari seng gelombang tinggi 2 meter

6.2.1. Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Semen Portland 2.500 Kg x Rp 1,400 = Rp 3,500.00
- Seng Gelombang 1.200 Lbr x Rp 59,640 = Rp 71,568.00
- Pasir beton 0.005 M3 x Rp 300,000 = Rp 1,500.00
- Koral beton 0.009 M3 x Rp 205,000 = Rp 1,845.00
- Kayu 5/7 0.012 M3 x Rp 3,107,500 = Rp 37,290.00
- Paku biasa 2" - 5" 0.060 Kg x Rp 18,000 = Rp 1,080.00
- Meni besi 0.450 Kg x Rp 25,410 = Rp 11,434.50
Jumlah (1) = Rp 152,280.00

6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 150,000 = Rp 30,000.00
- Pekerja 0.400 Oh x Rp 100,000 = Rp 40,000.00
- Kepala tukang 0.020 Oh x Rp 150,000 = Rp 3,000.00
- Mandor 0.020 Oh x Rp 175,000 = Rp 3,500.00
Jumlah (2) = Rp 76,500.00
Jumlah (1) + (2) = Rp 228,780.00
PA. Hal. 1
PA 6.3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter

6.3.1. Bahan
- Kayu Laut/Dolken 1.000 Btg x Rp 19,250 = Rp 19,250.00
- Semen Portland 2.000 Kg x Rp 1,400 = Rp 2,800.00
- Kawat duri 1.625 Kg x Rp 4,030 = Rp 6,548.75
- Pasir beton 0.005 M3 x Rp 300,000 = Rp 1,500.00
- Koral beton 0.009 M3 x Rp 205,000 = Rp 1,845.00
- Paku biasa 2" - 5" 0.060 Kg x Rp 18,000 = Rp 1,080.00
Jumlah (1) = Rp 33,023.75

6.3.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 150,000 = Rp 30,000.00
- Pekerja 0.400 Oh x Rp 100,000 = Rp 40,000.00
- Kepala tukang 0.020 Oh x Rp 150,000 = Rp 3,000.00
- Mandor 0.020 Oh x Rp 175,000 = Rp 3,500.00
Jumlah (2) = Rp 76,500.00
Jumlah (1) + (2) = Rp 109,523.75

PA 6.4 Pengukuran dan Pemasangan bouplank

6.4.1. Bahan
- Kayu 5/7 0.012 M3 x Rp 3,107,500 = Rp 37,290.00
- Paku biasa 2" - 5" 0.020 Kg x Rp 18,000 = Rp 360.00
- Kayu papan 2/20 0.007 M3 x Rp 3,107,500 = Rp 21,752.50
Jumlah (1) = Rp 59,402.50

6.4.2. Tenaga
- Tukang kayu 0.100 Oh x Rp 150,000 = Rp 15,000.00
- Pekerja 0.100 Oh x Rp 100,000 = Rp 10,000.00
- Kepala tukang 0.010 Oh x Rp 150,000 = Rp 1,500.00
- Mandor 0.005 Oh x Rp 175,000 = Rp 875.00
Jumlah (2) = Rp 27,375.00
Jumlah (1) + (2) = Rp 86,777.50
PA. Hal. 2
PA 6.5 1 m2 Pembuatan Kantor Sementara dengan Lantai Plesteran

6.5.1. Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Kayu 0.180 M3 x Rp 37,400 = Rp 6,732.00
- Batu Belah/Kali 15 - 20 cm 0.850 Kg x Rp 145,000 = Rp 159,500.00
- Besi Strip 1.100 Kg x Rp 165,000 = Rp 5,775,000.00
- Semen Portland 35.000 Kg x Rp 1,400 = Rp 210.00
- Pasir pasang 0.150 M3 x Rp 165,000 = Rp 16,500.00
- Pasir beton 0.100 M3 x Rp 187,500 = Rp 28,125.00
- Koral beton 0.150 M3 x Rp 215,900 = Rp 6,477,000.00
- Bata merah 30.000 Bh x Rp 130,000 = Rp 32,500.00
- Seng plat 0.250 Lbr x Rp 9,500 = Rp 19,000.00
- Jendela nako 2.000 Bh x Rp 13,590 = Rp 1,087.20
- Kaca polos 0.080 M2 x Rp 175,000 = Rp 26,250.00
- Kunci tanam 0.150 Bh x Rp 205,000 = Rp 12,300.00
- Plywood 4 mm 0.060 Lbr x Rp 225,000 = Rp 0.00
Jumlah (1) = Rp 12,578,266.70
6.5.2. Tenaga
- Tukang kayu 2.000 Oh x Rp 150,000 = Rp 300,000.00
- Tukang batu 1.000 Oh x Rp 150,000 = Rp 150,000.00
- Pekerja 2.000 Oh x Rp 100,000 = Rp 200,000.00
- Kepala tukang 0.300 Oh x Rp 150,000 = Rp 45,000.00
- Mandor 0.050 Oh x Rp 175,000 = Rp 8,750.00
Jumlah (2) = Rp 703,750.00
Jumlah (1) + (2) = Rp 13,282,016.70

PA 6.6. 1 m2 Pembuatan gudang semen dan alat - alat

6.6.1. Bahan
- Kayu Laut/Dolken 1.700 Btg x Rp 19,250 = Rp 32,725.00
- Kayu 0.210 M3 x Rp 37,400 = Rp 7,854.00
- Paku biasa 0.300 Kg x Rp 145,000 = Rp 43,500.00
- Semen Portland 10.500 Kg x Rp 1,400 = Rp 14,700.00
- Pasir beton 0.030 M3 x Rp 187,500 = Rp 5,625.00
- Koral beton 0.050 M3 x Rp 215,900 = Rp 10,795.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
Jumlah (1) = Rp 204,659.00

6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 150,000 = Rp 30,000.00
- Pekerja 0.400 Oh x Rp 100,000 = Rp 40,000.00
- Kepala tukang 0.020 Oh x Rp 150,000 = Rp 3,000.00
- Mandor 0.020 Oh x Rp 175,000 = Rp 3,500.00
Jumlah (2) = Rp 76,500.00
Jumlah (1) + (2) = Rp 281,159.00
PA. Hal. 3
PA 6.7 1 m2 Pembuatan rumah jaga / kontruksi kayu

6.7.1 Bahan
- Kayu Laut/Dolken 3.000 Btg x Rp 19,250 = Rp 57,750.00
- Kayu 0.276 M³ x Rp 37,400 = Rp 10,322.40
- Paku biasa 0.700 Kg x Rp 145,000 = Rp 101,500.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
Jumlah (1) = Rp 259,032.40

6.7.2 Tenaga
- Tukang kayu 1.500 Oh x Rp 150,000 = Rp 225,000.00
- Pekerja 1.000 Oh x Rp 100,000 = Rp 100,000.00
- Kepala Tukang 0.150 Oh x Rp 150,000 = Rp 22,500.00
- Mandor 0.050 Oh x Rp 175,000 = Rp 8,750.00
Jumlah (2) = Rp 356,250.00
Jumlah (1) + (2) = Rp 615,282.40

PA 6.8 1 m2 Membersihkan lapangan dan perataan

6.8.1 Tenaga
- Pekerja 0.100 Oh x Rp 100,000 = Rp 10,000.00
- Mandor 0.050 Oh x Rp 175,000 = Rp 8,750.00
Jumlah = Rp 18,750.00

PA 6.9 1 m2 Pembuatan bedeng buruh

6.9.1 Bahan
- Kayu Laut/Dolken 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Kayu 0.186 M³ x Rp 37,400 = Rp 6,956.40
- Paku biasa 0.300 Kg x Rp 145,000 = Rp 43,500.00
- Semen portland 18.000 Kg x Rp 1,400 = Rp 25,200.00
- Pasir beton 0.030 M³ x Rp 187,500 = Rp 5,625.00
- Koral beton 0.050 M³ x Rp 215,900 = Rp 10,795.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
- Plywood 4mm 1.350 Lbr x Rp 225,000 = Rp 303,750.00
Jumlah (1) = Rp 509,348.90

6.9.2 Tenaga
- Tukang kayu 2.000 Oh x Rp 150,000 = Rp 300,000.00
- Pekerja 1.000 Oh x Rp 100,000 = Rp 100,000.00
- Kepala tukang 0.200 Oh x Rp 150,000 = Rp 30,000.00
- Mandor 0.050 Oh x Rp 175,000 = Rp 8,750.00
Jumlah (2) = Rp 438,750.00
Jumlah (1) + (2) = Rp 948,098.90
PA. Hal. 4
PA 6.10. 1 m2 Pembuatan bak adukan ukuran ( 40 x 50 x 20 ) cm

6.10.1. Bahan
- Waterfroof 0.036 M3 x Rp 65,000 = Rp 2,340.00
- Paku biasa 0.080 Kg x Rp 145,000 = Rp 11,600.00
- Kaso 5/7 1.000 Btg x Rp 1,400 = Rp 1,400.00
Jumlah (1) = Rp 15,340.00

6.10.2 Tenaga
- Tukang kayu 0.300 Oh x Rp 150,000 = Rp 45,000.00
- Mandor 0.002 Oh x Rp 175,000 = Rp 262.50
Jumlah (2) = Rp 45,262.50
Jumlah (1) + (2) = Rp 60,602.50

PA 6.11. 1 m2 Pembuatan Stegger dari bambu, ukuran ( 40 x 50 x 20 ) cm

6.11.1 Bahan
- Bambu ø 6 - 8 / 600 cm 1.000 Btg x Rp 145,000 = Rp 145,000.00
- Tali ijuk 0.250 Kg x Rp 4,500 = Rp 1,125.00
Jumlah (1) = Rp 146,125.00

6.11.2 Tenaga
- Tukang kayu 0.017 Oh x Rp 150,000 = Rp 2,550.00
- Kepala tukang 0.002 Oh x Rp 150,000 = Rp 300.00
- Pekerja 0.250 Oh x Rp 100,000 = Rp 25,000.00
- Mandor 0.013 Oh x Rp 175,000 = Rp 2,275.00
Jumlah (2) = Rp 30,125.00
Jumlah (1) + (2) = Rp 176,250.00

PA 6.12 1 m2 Pembuatan jalan sementara

6. 12.1 Bahan
- Batu belah 15/20 0.150 M³ x Rp 145,000 = Rp 21,750.00
- Batu pecah 5/7 0.090 M³ x Rp 165,000 = Rp 14,850.00
- Pasir pasang 0.010 M³ x Rp 265,000 = Rp 2,650.00
Jumlah (1) = Rp 39,250.00

6.12.2 Tenaga
- Pekerja 1.000 Oh x Rp 100,000 = Rp 100,000.00
- Mandor 0.050 Oh x Rp 175,000 = Rp 8,750.00
Jumlah (2) = Rp 108,750.00
Jumlah (1) + (2) = Rp 148,000.00
PA. Hal. 5
PA 6.13 1 m3 Bongkaran beton betulang

6.13.1 Tenaga
- Pekerja 6.667 Oh x Rp 100,000 = Rp 666,700.00
- Mandor 0.333 Oh x Rp 175,000 = Rp 58,275.00
Jumlah = Rp 724,975.00

PA 6.14 1 m3 Bongkaran dinding tembok bata merah

6.14.1 Tenaga
- Pekerja 5.000 Oh x Rp 100,000 = Rp 500,000.00
- Mandor 0.250 Oh x Rp 175,000 = Rp 43,750.00
Jumlah = Rp 543,750.00

PA 6.15 1 m' Pasangan pagar kawat jaring galvanis, tinggi 1.00 m

6.15.1 Bahan
- Kawat jaring galvanis/BRC 0.434 Lbr x Rp 235,950 = Rp 102,402.30
Jumlah (1) = Rp 102,402.30

6.15.2. Tenaga
- Pekerja 0.042 Oh x Rp 100,000 = Rp 4,200.00
- Kepala tukang 0.004 Oh x Rp 150,000 = Rp 600.00
- Tukang 0.042 Oh x Rp 150,000 = Rp 6,300.00
- Mandor 0.002 Oh x Rp 175,000 = Rp 350.00
Jumlah (2) = Rp 11,450.00
Jumlah (1) + (2) = Rp 113,852.30

PA 6.16 1 m' Pasang pagar beton pracetak (5 x 50 x 213) cm

6.16.1. Bahan
- Panel beton pracetak 0.986 Lbr x Rp 205,000 = Rp 202,130.00
- Kolom beton pracetak 0.525 Btg x Rp 315,000 = Rp 165,375.00
- Pasir beton 0.074 M³ x Rp 187,500 = Rp 13,875.00
- Koral 2/3 0.146 M³ x Rp 315,000 = Rp 45,990.00
- Batu Bata biasa 5x10x20 cm 45.000 Kg x Rp 1,400 = Rp 63,000.00
Jumlah (1) = Rp 490,370.00

6.16.2. Tenaga
- Pekerja 0.042 Oh x Rp 100,000 = Rp 4,200.00
- Kepala tukang 0.004 Oh x Rp 150,000 = Rp 600.00
- Tukang 0.042 Oh x Rp 150,000 = Rp 6,300.00
- Mandor 0.002 Oh x Rp 175,000 = Rp 350.00
Jumlah (2) = Rp 11,450.00
Jumlah (1) + (2) = Rp 501,820.00
PA. Hal. 6
ANALISA BIAYA KONSTRUKSI
PEKERJAAN TANAH

PT 6.1. 1 m³ Galian tanah biasa sedalam 1 meter

6.1.1. Tenaga
- Pekerja 0.400 Oh x Rp. 100,000 = Rp. 40,000.00
- Mandor 0.040 Oh x Rp. 175,000 = Rp. 7,000.00
Jumlah (1) = Rp. 47,000.00

PT 6.2. 1 m³ Galian tanah biasa sedalam 2 meter

6.2.1. Tenaga
- Pekerja 0.526 Oh x Rp. 100,000 = Rp. 52,600.00
- Mandor 0.0526 Oh x Rp. 175,000 = Rp. 9,205.00
Jumlah (1) = Rp. 61,805.00

PT 6.3. 1 m³ Galian tanah biasa sedalam 3 meter

6.3.1. Tenaga
- Pekerja 0.735 Oh x Rp. 100,000 = Rp. 73,500.00
- Mandor 0.0735 Oh x Rp. 175,000 = Rp. 12,862.50
Jumlah (1) = Rp. 86,362.50

PT 6.4. 1 m³ Galian tanah keras sedalam 1 meter

6.4.1 Tenaga
- Pekerja 0.625 Oh x Rp. 100,000 = Rp. 62,500.00
- Mandor 0.062 Oh x Rp. 175,000 = Rp. 10,850.00
Jumlah = Rp. 73,350.00

PT 6.5. 1 m³ Galian tanah cadas sedalam 1 meter

6.5.1. Tenaga
- Pekerja 1.250 Oh x Rp. 100,000 = Rp. 125,000.00
- Mandor 0.125 Oh x Rp. 175,000 = Rp. 21,875.00
Jumlah = Rp. 146,875.00

PT 6.6.. 1 m³ Galian tanah lumpur sedalam 1 meter

6.6.1. Tenaga
- Pekerja 0.823 Oh x Rp. 100,000 = Rp. 82,300.00
- Mandor 0.083 Oh x Rp. 175,000 = Rp. 14,525.00
Jumlah = Rp. 96,825.00

PT 6.7. 1 m² Pekerjaan stripping setinggi 1 meter

6.7.1. Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (1) = Rp. 5,875.00
PT. Hal. 1
PT 6.8. 1 m³ Pembuangan tanah sejauh 150 meter

6.8.1. Tenaga
- Pekerja 0.515 Oh x Rp. 100,000 = Rp. 51,500.00
- Mandor 0.0515 Oh x Rp. 175,000 Rp. 9,012.50
Jumlah = Rp. 60,512.50

PT 6.9. 1 m³ Urugan kembali

6.9.1. Tenaga
- Pekerja 0.192 Oh x Rp. 100,000 = Rp. 19,200.00
- Mandor 0.019 Oh x Rp. 175,000 = Rp. 3,325.00
Jumlah = Rp. 22,525.00

PT 6.10. 1 m³ Pemadatan tanah

6.10.1. Tenaga
- Pekerja 0.500 Oh x Rp. 100,000 = Rp. 50,000.00
- Mandor 0.050 Oh x Rp. 175,000 = Rp. 8,750.00
Jumlah = Rp. 58,750.00

PT 6.11. 1 m³ Urugan pasir

6.11.1. Bahan
- Pasir urug 1.200 M³ x Rp. 130,000 = Rp. 156,000.00
Jumlah (1) = Rp. 156,000.00

6.11.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 32,625.00
Jumlah (1) + (2) = Rp. 188,625.00

PT 6.12. 1 m³ Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL

6.12.1. Bahan
- Pasir urug 0.330 M³ x Rp. 130,000 = Rp. 42,900.00
- Kapur padam 0.109 M³ x Rp. 4,500 = Rp. 490.50
- Tanah liat 0.763 M³ x Rp. 145,000 = Rp. 110,635.00
Jumlah (1) = Rp. 154,025.50

6.12.2. Tenaga
- Pekerja 0.500 Oh x Rp. 100,000 = Rp. 50,000.00
- Mandor 0.050 Oh x Rp. 175,000 = Rp. 8,750.00
Jumlah (2) = Rp. 58,750.00
Jumlah (1) + (2) = Rp. 212,775.50

PT 6.13. 1 m³ Lapisan pudel campuran 1 Kp : 5 TL

6.13.1. Bahan
- Kapur padam 0.200 M³ x Rp. 4,500 = Rp. 900.00
- Tanah liat 1.000 M³ x Rp. 145,000 = Rp. 145,000.00
Jumlah (1) = Rp. 145,900.00

6.13.2. Tenaga
- Pekerja 0.500 Oh x Rp. 100,000 = Rp. 50,000.00
- Mandor 0.050 Oh x Rp. 175,000 = Rp. 8,750.00
Jumlah (2) = Rp. 58,750.00
Jumlah (1) + (2) = Rp. 204,650.00

PT. Hal. 2
PT 6.14. 1 m³ Urugan Tanah

6.11.1. Bahan
- Tanah Urug 1.200 M³ x Rp. 145,000 = Rp. 174,000.00
Jumlah (1) = Rp. 174,000.00

6.11.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 32,625.00
Jumlah (1) + (2) = Rp. 206,625.00

PT 6.15. 1 m³ Urugan Sirtu

6.11.1. Bahan
- Sirtu 1.200 M³ x Rp. 165,000 = Rp. 198,000.00
Jumlah (1) = Rp. 198,000.00

6.11.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 32,625.00
Jumlah (1) + (2) = Rp. 230,625.00

PT 6.16. 1 m³ Pembuatan jalan sementara, tebal 25 cm

6.14.1. Bahan
- Batu belah 10/15 0.275 M³ x Rp. 165,000 = Rp. 45,375.00
- Batu koral 5/7 0.030 M³ x Rp. 205,000 = Rp. 6,150.00
- Pasir pasang 0.050 M³ x Rp. 265,000 = Rp. 13,250.00
Jumlah (1) = Rp. 64,775.00

6.14.2. Tenaga

- Pekerja 0.500 Oh x Rp. 100,000 = Rp. 50,000.00


- Mandor 0.050 Oh x Rp. 175,000 = Rp. 8,750.00
Jumlah (2) = Rp. 58,750.00
Jumlah (1) + (2) = Rp. 123,525.00
PT. Hal. 3
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PONDASI

PP 6.1. 1 M³ Pasangan pondasi batu kali, 1 Pc : 1 Ps

6.1.1. Bahan :
- Batu belah 15/20 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 392.000 Kg x Rp. 1,400.00 = Rp. 548,800.00
- Pasir pasang 0.314 M³ x Rp. 265,000.00 = Rp. 83,210.00
Jumlah (1) = Rp. 791,510.00

6.1.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) + (2) = Rp. 1,053,635.00

PP 6.2. 1 M³ Pasang pondasi batu kali 1 Pc : 2 Ps

6.2.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 267.000 Kg x Rp. 1,400.00 = Rp. 373,800.00
- Pasir Pasang 0.427 M³ x Rp. 265,000.00 = Rp. 113,155.00
Jumlah (1) = Rp. 646,455.00

6.2.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 908,580.00

PP 6.3. 1 M³ Pasang pondasi batu kali, 1 Pc : 2,5 Ps

6.3.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 392.000 Kg x Rp. 1,400.00 = Rp. 548,800.00
- Pasir Pasang 0.314 M³ x Rp. 265,000.00 = Rp. 83,210.00
Jumlah (1) = Rp. 791,510.00

6.3.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 1,053,635.00
PP. Hal. 1
PP 6.4. 1 M³ Pasang pondasi batu kali, 1 Pc : 3 Ps

6.4.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 202.000 Kg x Rp. 1,400.00 = Rp. 282,800.00
- Pasir Pasang 0.485 M³ x Rp. 265,000.00 = Rp. 128,525.00
Jumlah (1) = Rp. 570,825.00

6.4.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 832,950.00

PP 6.5. 1 M³ Pasang pondasi batu kali, 1 Pc : 4 Ps.

6.5.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 163.000 Kg x Rp. 1,400.00 = Rp. 228,200.00
- Pasir Pasang 0.520 M³ x Rp. 265,000.00 = Rp. 137,800.00
Jumlah (1) = Rp. 525,500.00

6.5.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 787,625.00

PP 6.6. 1 M³ Pasang pondasi batu kali, 1 Pc : 5 Ps

6.6.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 136.000 Kg x Rp. 1,400.00 = Rp. 190,400.00
- Pasir Pasang 0.544 M³ x Rp. 265,000.00 = Rp. 144,160.00
Jumlah (1) = Rp. 494,060.00

6.6.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) 262,125.00
Jumlah (1) +(2) 756,185.00
PP. Hal. 2
PP 6.7. 1 M³ Pasang pondasi batu kali, 1 Pc : 6 Ps

6.7.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 117.000 Kg x Rp. 1,400.00 = Rp. 163,800.00
- Pasir Pasang 0.561 M³ x Rp. 265,000.00 = Rp. 148,665.00
Jumlah (1) = Rp. 471,965.00
6.7.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 734,090.00

PP 6.8. 1 M³ Pasang pondasi batu kali, Pc : 8 Ps

6.8.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Semen porland 91.000 Kg x Rp. 1,400.00 = Rp. 127,400.00
- Pasir Pasang 0.561 M³ x Rp. 265,000.00 = Rp. 148,665.00
Jumlah (1) = Rp. 435,565.00

6.8.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 697,690.00

PP 6.9. 1 M³ Pasang pondasi batu kali, 1 Kp : 1 Sm : 1 Ps

6.9.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Kapur pasang 0.229 Kg x Rp. 325,000.00 = Rp. 74,425.00
- Batu Bata biasa 5x10x20 cm 0.229 M³ x Rp. 25,080.00 = Rp. 5,743.32
- Pasir Pasang 0.544 M³ x Rp. 6,270.00 = Rp. 3,410.88
Jumlah (1) = Rp. 243,079.20

6.9.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 505,204.20
PP. Hal. 3
PP 6.10. 1 M³ Pasang pondasi batu kali, 1 Kp : 1 SM : 2 Ps

6.10.1. Bahan
- Batu belah 15/20 cm 1.100 M³ x Rp. 145,000.00 = Rp. 159,500.00
- Kapur pasang 0.170 Kg x Rp. 325,000.00 = Rp. 55,250.00
- Batu Bata biasa 5x10x20 cm 0.170 M³ x Rp. 25,080.00 = Rp. 4,263.60
- Pasir Pasang 0.340 M³ x Rp. 6,270.00 = Rp. 2,131.80
Jumlah (1) = Rp. 221,145.40

6.10.2. Tenaga
- Pekerja 1.500 Oh x Rp. 100,000.00 = Rp. 150,000.00
- Tukang batu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 262,125.00
Jumlah (1) +(2) = Rp. 483,270.40

PP 6.11. 1 M³ Pasang pondasi batu kosong

6.11.1. Bahan
- Batu belah 10/15 cm 1.200 M³ x Rp. 165,000.00 = Rp. 198,000.00
- Pasir pasang 0.300 M³ x Rp. 265,000.00 = Rp. 79,500.00
Jumlah (1) = Rp. 277,500.00
6.11.2. Tenaga
- Pekerja 0.780 Oh x Rp. 100,000.00 = Rp. 78,000.00
- Tukang batu 0.390 Oh x Rp. 150,000.00 = Rp. 58,500.00
- Kepala tukang 0.039 Oh x Rp. 150,000.00 = Rp. 5,850.00
- Mandor 0.039 Oh x Rp. 175,000.00 = Rp. 6,825.00
Jumlah (2) = Rp. 149,175.00
Jumlah (1) +(2) = Rp. 426,675.00

PP 6.12. 1 M³ Pasang pondasi sumuran diameter 100 Cm

6.12.1. Bahan
- Batu belah 15/20 cm 0.450 M³ x Rp. 145,000.00 = Rp. 65,250.00
- Semen portland 280.000 Kg x Rp. 1,400.00 = Rp. 392,000.00
- Pasir Pasang 0.670 M³ x Rp. 265,000.00 = Rp. 177,550.00
Jumlah (1) = Rp. 634,800.00

6.12.2. Tenaga
- Pekerja 2.380 Oh x Rp. 100,000.00 = Rp. 238,000.00
- Tukang batu 0.300 Oh x Rp. 150,000.00 = Rp. 45,000.00
- Kepala tukang 0.030 Oh x Rp. 150,000.00 = Rp. 4,500.00
- Mandor 0.080 Oh x Rp. 175,000.00 = Rp. 14,000.00
Jumlah (2) = Rp. 301,500.00
Jumlah (1) +(2) = Rp. 936,300.00
PP. Hal. 4
PP 6.13. 1 M³ Pembuatan tiang pancang (40 x 40) Cm, beton bertulang

6.13.1. Bahan
- Pasir urug darat 0.019 M³ x Rp. 130,000.00 = Rp. 2,470.00
- Pasir beton 0.094 M³ x Rp. 300,000.00 = Rp. 28,200.00
- Koral beton 0.150 M³ x Rp. 215,900.00 = Rp. 32,385.00
- Semen porland 60.500 Kg x Rp. 1,400.00 = Rp. 84,700.00
- Besi beton 45.000 Kg x Rp. 19,500.00 = Rp. 877,500.00
- Kawat beton 0.900 Kg x Rp. 19,500.00 = Rp. 17,550.00
- Kayu kaso 5/7 0.032 M³ x Rp. 3,107,500.00 = Rp. 99,440.00
- Paku 0.120 Kg x Rp. 18,000.00 = Rp. 2,160.00
- Minyak bekisting 0.090 Lt x Rp. 9,000.00 = Rp. 810.00
- Plamur tembok 0.240 Kg x Rp. 17,500.00 = Rp. 4,200.00
Jumlah (1) = Rp. 1,149,415.00
6.13.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000.00 = Rp. 100,000.00
- Tukang batu 0.670 Oh x Rp. 150,000.00 = Rp. 100,500.00
- Kepala tukang 0.067 Oh x Rp. 150,000.00 = Rp. 10,050.00
- Mandor 0.050 Oh x Rp. 175,000.00 = Rp. 8,750.00
Jumlah (2) = Rp. 219,300.00
Jumlah (1) +(2) = Rp. 1,368,715.00

PP 6.14. 1 M³ Pembuatan tiang pancang (35 x 35) Cm, beton bertulang

6.14.1. Bahan
- Pasir urug darat 0.016 M³ x Rp. 130,000.00 = Rp. 2,080.00
- Pasir beton 0.080 M³ x Rp. 300,000.00 = Rp. 24,000.00
- Koral beton 0.125 M³ x Rp. 215,900.00 = Rp. 26,987.50
- Semen porland 49.000 Kg x Rp. 1,400.00 = Rp. 68,600.00
- Besi beton 34.500 Kg x Rp. 19,500.00 = Rp. 672,750.00
- Kawat beton 0.700 Kg x Rp. 19,500.00 = Rp. 13,650.00
- Kayu kaso 5/7 0.027 M³ x Rp. 3,107,500.00 = Rp. 83,902.50
- Paku 0.120 Kg x Rp. 18,000.00 = Rp. 2,160.00
- Minyak bekisting 0.090 Lt x Rp. 9,000.00 = Rp. 810.00
- Plamur tembok 0.200 Kg x Rp. 17,500.00 = Rp. 3,500.00
Jumlah (1) = Rp. 898,440.00

6.14.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang batu 0.500 Oh x Rp. 150,000.00 = Rp. 75,000.00
- Kepala tukang 0.050 Oh x Rp. 150,000.00 = Rp. 7,500.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 169,500.00
Jumlah (1) +(2) = Rp. 1,067,940.00
PP. Hal. 5
ANALISA BIAYA KONSTRUKSI
PEKERJAAN DINDING

PD 6.1. 1 M² Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps


6.1.1. Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 64.030 Kg x Rp. 1,400 = Rp 89,642.00
- Pasir pasang 0.059 M³ x Rp. 265,000 = Rp 15,635.00
Jumlah (1) = Rp 287,277.00

6.1.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 3,000.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 5,250.00
Jumlah (2) = Rp 103,250.00
Jumlah (1) + (2) = Rp 390,527.00

PD 6.2 1m² Pasangan bata merah tebal 1 bata, 1Pc : 2 Ps


6.2.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 43.500 Kg x Rp. 1,400 = Rp 60,900.00
- Pasir pasang 0.080 M³ x Rp. 265,000 = Rp 21,200.00
Jumlah (1) = Rp 264,100.00

6.2.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 3,000.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 5,250.00
Jumlah (2) = Rp 103,250.00
Jumlah (1) + (2) = Rp 367,350.00

PD 6.3 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 3 Ps


6.3.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 32.950 Kg x Rp. 1,400 = Rp 46,130.00
- Pasir pasang 0.091 M³ x Rp. 265,000 = Rp 24,115.00
Jumlah (1) = Rp 252,245.00

6.3.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 3,000.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 5,250.00
Jumlah (2) = Rp 103,250.00
Jumlah (1) + (2) = Rp 355,495.00

PD 6.4 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 4 Ps


6.4.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 26.550 Kg x Rp. 1,400 = Rp 37,170.00
- Pasir pasang 0.093 M³ x Rp. 265,000 = Rp 24,645.00
Jumlah (1) = Rp 243,815.00

6.4.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 3,000.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 65,000.00
Jumlah (2) = Rp 98,000.00
Jumlah (1) + (2) = Rp 341,815.00

PD. Hal. 1
PD 6.5 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 5 Ps

6.5.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 22.200 Kg x Rp. 1,400 = Rp 31,080.00
- Pasir pasang 0.102 M³ x Rp. 265,000 = Rp 27,030.00
Jumlah (1) = Rp 240,110.00

6.5.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 0.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 0.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 5,250.00
Jumlah (2) = Rp 70,250.00
Jumlah (1) + (2) = Rp 310,360.00

PD 6.6 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 6 Ps

6.6.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 22.200 Kg x Rp. 1,400 = Rp 31,080.00
- Pasir pasang 0.102 M³ x Rp. 265,000 = Rp 27,030.00
Jumlah (1) = Rp 240,110.00

6.6.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 3,000.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 5,250.00
Jumlah (2) = Rp 103,250.00
Jumlah (1) + (2) = Rp 343,360.00

PD 6.7 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Ps

6.7.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 1,300 = Rp 182,000.00
- Semen portland 10.080 Kg x Rp. 1,400 = Rp 14,112.00
- Pasir pasang 0.0925 M³ x Rp. 265,000 = Rp 24,512.50
Jumlah (1) = Rp 38,624.50

6.7.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp 65,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp 3,000.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp 5,250.00
Jumlah (2) = Rp 103,250.00
Jumlah (1) + (2) = Rp 141,874.50

PD 6.8 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 1 Ps

6.8.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 27.800 Kg x Rp. 1,400 = Rp 38,920.00
- Pasir pasang 0.028 M³ x Rp. 265,000 = Rp 7,420.00
Jumlah (1) = Rp 137,340.00

6.8.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 188,465.00

PD. Hal. 2
PD 6.9 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 2 Ps

6.9.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 18.950 Kg x Rp. 1,400 = Rp 26,530.00
- Pasir pasang 0.038 M³ x Rp. 265,000 = Rp 10,070.00
Jumlah (1) = Rp 127,600.00

6.9.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 178,725.00

PD 6.10 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Ps

6.10.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 14.370 Kg x Rp. 1,400 = Rp 20,118.00
- Pasir pasang 0.040 M³ x Rp. 265,000 = Rp 10,600.00
Jumlah (1) = Rp 121,718.00

6.10.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 172,843.00

PD 6.11 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps

6.11.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 11.500 Kg x Rp. 1,400 = Rp 16,100.00
- Pasir pasang 0.043 M³ x Rp. 265,000 = Rp 11,395.00
Jumlah (1) = Rp 118,495.00

6.11.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 169,620.00

PD 6.12 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 5 Ps

6.12.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 9.680 Kg x Rp. 1,400 = Rp 13,552.00
- Pasir pasang 0.045 M³ x Rp. 265,000 = Rp 11,925.00
Jumlah (1) = Rp 116,477.00

6.12.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 167,602.00
PD. Hal. 3
PD 6.13 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 6 Ps
6.13.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 8.320 Kg x Rp. 1,400 = Rp 11,648.00
- Pasir pasang 0.049 M³ x Rp. 265,000 = Rp 12,985.00
Jumlah (1) = Rp 115,633.00

6.13.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 166,758.00

PD 6.14 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 8 Ps


6.14.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 6.500 Kg x Rp. 1,400 = Rp 9,100.00
- Pasir pasang 0.050 M³ x Rp. 265,000 = Rp 13,250.00
Jumlah (1) = Rp 113,350.00

6.14.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 164,475.00

PD 6.15 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Kp : 10 Ps


6.15.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Semen portland 4.500 Kg x Rp. 1,400 = Rp 6,300.00
- Pasir pasang 0.050 M³ x Rp. 265,000 = Rp 13,250.00
- Kapur pasang 0.015 M³ x Rp. 0 = Rp 0.00
Jumlah (1) = Rp 110,550.00

6.15.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 161,675.00

PD 6.16 1 m² Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 1 Ps


6.16.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Kawat Duri 0.018 M³ x Rp. 4,030 = Rp 72.54
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp 4,770.00
- Kapur padam 0.018 M³ x Rp. 68,290 = Rp 1,229.22
Jumlah (1) = Rp 97,071.76

6.16.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 148,196.76
PD. Hal. 4
PD 6.17 1 m² Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 2 Ps
6.17.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 1,300 = Rp 91,000.00
- Kawat Duri 0.014 Kg x Rp. 1,400 = Rp 19.60
- Pasir pasang 0.028 M³ x Rp. 265,000 = Rp 7,420.00
- Kapur padam 0.014 M³ x Rp. 68,290 = Rp 956.06
Jumlah (1) = Rp 99,395.66

6.17.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 150,520.66

PD 6.18 1 m² Pasangan dinding holowblock (HB.20)


6.18.1 Bahan
- Hollow block (HB.20) 12.500 Bh x Rp. 17,070 = Rp 213,375.00
- Semen portland 13.500 Kg x Rp. 1,400 = Rp 18,900.00
- Pasir pasang 0.048 M³ x Rp. 265,000 = Rp 12,720.00
- Besi beton polos 1.950 M³ x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 573,082.50

6.18.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp 2,250.00
- Mandor 0.017 Oh x Rp. 175,000 = Rp 2,975.00
Jumlah (2) = Rp 59,725.00
Jumlah (1) + (2) = Rp 632,807.50

PD 6.19 1 m² Pasangan dinding holowblock (HB.15)


6.19.1 Bahan
- Hollow block (HB.15) 12.500 Bh x Rp. 8,540 = Rp 106,750.00
- Semen portland 10.450 Kg x Rp. 1,400 = Rp 14,630.00
- Pasir pasang 0.038 M³ x Rp. 265,000 = Rp 10,070.00
- Besi beton polos 1.950 M³ x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 459,537.50

6.19.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.120 Oh x Rp. 150,000 = Rp 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp 1,800.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 54,425.00
Jumlah (1) + (2) = Rp 513,962.50

PD 6.20 1 m² Pasangan dinding holowblock (HB.10)


6.20.1 Bahan
- Hollow block (HB.10) 12.500 Bh x Rp. 17,330 = Rp 216,625.00
- Semen portland 7.500 Kg x Rp. 1,400 = Rp 10,500.00
- Pasir pasang 0.027 M³ x Rp. 265,000 = Rp 7,155.00
- Besi beton polos 1.950 M³ x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 562,367.50

6.20.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 51,125.00
Jumlah (1) + (2) = Rp 613,492.50

PD. Hal. 5
PD 6.21 1 m² Pasangan dinding conblock (CB.20)
6.21.1 Bahan
- Concrete block (CB 20) 12.500 Bh x Rp. 5,500 = Rp 68,750.00
- Semen portland 14.050 Kg x Rp. 1,400 = Rp 19,670.00
- Pasir beton 0.004 M³ x Rp. 300,000 = Rp 1,200.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp 11,130.00
- Besi beton polos 3.870 Bh x Rp. 19,500 = Rp 75,465.00
- Paku biasa 2" - 5" 0.006 Kg x Rp. 18,000 = Rp 108.00
- Kayu sembarang 0.001 M³ x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.030 M³ x Rp. 19,500 = Rp 585.00
- Koral beton 0.005 M³ x Rp. 215,900 = Rp 1,079.50
Jumlah (1) = Rp 181,095.00

6.21.2 Tenaga
- Pekerja 0.370 Oh x Rp. 100,000 = Rp 37,000.00
- Tukang batu 0.157 Oh x Rp. 150,000 = Rp 23,550.00
- Tukang besi 0.007 Oh x Rp. 150,000 = Rp 1,050.00
- Kepala tukang 0.0164 Oh x Rp. 150,000 = Rp 2,460.00
- Mandor 0.0185 Oh x Rp. 175,000 = Rp 3,237.50
Jumlah (2) = Rp 67,297.50
Jumlah (1) + (2) = Rp 248,392.50

PD 6.22 1 m² Pasangan dinding Conblock (CB.15)


6.22.1 Bahan
- Concrete block (CB 15) 12.500 Bh x Rp. 4,000 = Rp 50,000.00
- Semen portland 10.460 Kg x Rp. 1,400 = Rp 14,644.00
- Pasir beton 0.003 M³ x Rp. 300,000 = Rp 900.00
- Pasir pasang 0.032 M³ x Rp. 265,000 = Rp 8,480.00
- Besi beton polos ø 8 mm 2.870 Bh x Rp. 19,500 = Rp 55,965.00
- Paku biasa 2" - 5" 0.004 Kg x Rp. 18,000 = Rp 72.00
- Kayu sembarang 0.001 M³ x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.020 M³ x Rp. 19,500 = Rp 390.00
- Koral beton 0.004 M³ x Rp. 215,900 = Rp 863.60
Jumlah (1) = Rp 134,422.10

6.22.2 Tenaga
- Pekerja 0.340 Oh x Rp. 100,000 = Rp 34,000.00
- Tukang batu 0.130 Oh x Rp. 150,000 = Rp 19,500.00
- Tukang besi 0.007 Oh x Rp. 150,000 = Rp 1,050.00
- Kepala tukang 0.0137 Oh x Rp. 150,000 = Rp 2,055.00
- Mandor 0.017 Oh x Rp. 175,000 = Rp 2,975.00
Jumlah (2) = Rp 59,580.00
Jumlah (1) + (2) = Rp 194,002.10

PD 6.23 1 m² Pasangan dinding Conblock (CB.10)


6.23.1 Bahan
- Concrete block (CB 10) 12.500 Bh x Rp. 900 = Rp 11,250.00
- Semen portland 7.200 Kg x Rp. 1,400 = Rp 10,080.00
- Pasir beton 0.002 M³ x Rp. 300,000 = Rp 600.00
- Pasir pasang 0.021 M³ x Rp. 265,000 = Rp 5,565.00
- Besi beton polos 2.540 Bh x Rp. 19,500 = Rp 49,530.00
- Paku biasa 2" - 5" 0.003 Kg x Rp. 18,000 = Rp 54.00
- Kayu sembarang 0.001 M³ x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.015 M³ x Rp. 19,500 = Rp 292.50
- Koral beton 0.003 M³ x Rp. 215,900 = Rp 647.70
Jumlah (1) = Rp 81,126.70

6.23.2 Tenaga
- Pekerja 0.340 Oh x Rp. 100,000 = Rp 34,000.00
- Tukang batu 0.107 Oh x Rp. 150,000 = Rp 16,050.00
- Tukang besi 0.007 Oh x Rp. 150,000 = Rp 1,050.00
- Kepala tukang 0.0114 Oh x Rp. 150,000 = Rp 1,710.00
- Mandor 0.017 Oh x Rp. 175,000 = Rp 2,975.00
Jumlah (2) = Rp 55,785.00
Jumlah (1) + (2) = Rp 136,911.70

PD. Hal. 6
PD 6.24 1 m² Pasang dinding lantai
6.24.1 Bahan
- Bondbeam 40 x 20 x 20 cm 2.500 Bh x Rp. 47,500 = Rp 118,750.00
- Semen portland 5.100 Kg x Rp. 1,400 = Rp 7,140.00
- Pasir beton 0.080 M³ x Rp. 300,000 = Rp 24,000.00
- Besi beton polos 1.500 Kg x Rp. 19,500 = Rp 29,250.00
- Koral beton 0.150 M³ x Rp. 215,900 = Rp 32,385.00
Jumlah (1) = Rp 211,525.00

6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp 10,000.00
- Tukang batu 0.030 Oh x Rp. 150,000 = Rp 4,500.00
- Tukang besi 0.030 Oh x Rp. 150,000 = Rp 4,500.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp 900.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp 875.00
Jumlah (2) = Rp 20,775.00
Jumlah (1) + (2) = Rp 232,300.00

PD 6.25 1 m² Pasang dinding roster / terawang


6.25.1 Bahan
- Roster/terawang 36.000 Bh x Rp. 7,500 = Rp 270,000.00
- Semen portland 12.800 Kg x Rp. 1,400 = Rp 17,920.00
- Pasir pasang 0.035 M³ x Rp. 265,000 = Rp 9,275.00
Jumlah (1) = Rp 297,195.00

6.25.2 Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp 30,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 49,125.00
Jumlah (1) + (2) = Rp 346,320.00

PD 6.26 1 m² Pasang bata berongga ukuran ( 5 x 10 x 20 ) cm


6.26.1 Bahan
- Batu berongga 80.000 Bh x Rp. 900 = Rp 72,000.00
- Semen portland 23.650 Kg x Rp. 1,400 = Rp 33,110.00
- Pasir pasang 0.570 M³ x Rp. 265,000 = Rp 151,050.00
Jumlah (1) = Rp 256,160.00

6.26.2 Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp 32,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp 2,250.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp 2,625.00
Jumlah (2) = Rp 59,375.00
Jumlah (1) + (2) = Rp 315,535.00

PD 6.27 1 m² Pasang dinding anyaman bambu, rangka kayu


6.27.1 Bahan
- Bilik bambu 1.500 M² x Rp. 16,340 = Rp 24,510.00
- Kayu 5/7 0.014 M³ x Rp. 5,225,000 = Rp 73,150.00
- Paku 0.012 Kg x Rp. 18,000 = Rp 216.00
- List kayu 2/4 0.003 M³ x Rp. 5,225,000 = Rp 15,675.00
Jumlah (1) = Rp 113,551.00

6.27.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp 10,000.00
- Tukang batu 0.050 Oh x Rp. 150,000 = Rp 7,500.00
- Kepala tukang 0.005 Oh x Rp. 150,000 = Rp 750.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp 350.00
Jumlah (2) = Rp 18,600.00
Jumlah (1) + (2) = Rp 132,151.00

PD. Hal. 7
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PLESTERAN

PPL 6.1. 1 M² Plesteran 1 Pc : 1 Ps, tebal 15 mm


6.1.1. Bahan
- Semen portland 12.920 Kg x Rp. 1,400 = Rp. 18,088.00
- Pasir pasang 0.013 M³ x Rp. 265,000 = Rp. 3,445.00
Jumlah (1) = Rp. 21,533.00
6.1.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 68,033.00

PPL 6.2. 1 M² Plesteran 1 Pc : 2 Ps, tebal 15 mm


6.2.1. Bahan
- Semen portland 8.520 Kg x Rp. 1,400 = Rp. 11,928.00
- Pasir pasang 0.017 M³ x Rp. 265,000 = Rp. 4,505.00
Jumlah (1) = Rp. 16,433.00
6.2.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 62,933.00

PPL 6.3. 1 M² Plesteran 1 Pc : 3 Ps, tebal 15 mm


6.3.1. Bahan
- Semen portland 6.480 Kg x Rp. 1,400 = Rp. 9,072.00
- Pasir pasang 0.019 M³ x Rp. 265,000 = Rp. 5,035.00
Jumlah (1) = Rp. 14,107.00
6.3.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 60,607.00

PPL 6.4. 1 M² Plesteran 1 Pc : 4 Ps, tebal 15 mm


6.4.1. Bahan
- Semen portland 5.200 Kg x Rp. 1,400 = Rp. 7,280.00
- Pasir pasang 0.020 M³ x Rp. 265,000 = Rp. 5,300.00
Jumlah (1) = Rp. 12,580.00
6.4.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 59,080.00
PPL. Hal. 1
PPL 6.5. 1 M² Plesteran 1 Pc : 5 Ps, tebal 15 mm
6.5.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,400 = Rp. 6,048.00
- Pasir pasang 0.022 M³ x Rp. 265,000 = Rp. 5,830.00
Jumlah (1) = Rp. 11,878.00
6.5.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 58,378.00

PPL 6.6. 1 M² Plesteran 1 Pc : 6 Ps, tebal 15 mm


6.6.1. Bahan
- Semen portland 3.680 Kg x Rp. 1,400 = Rp. 5,152.00
- Pasir pasang 0.023 M³ x Rp. 265,000 = Rp. 6,095.00
Jumlah (1) = Rp. 11,247.00
6.6.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 57,747.00

PPL 6.7. 1 M² Plesteran 1 Pc : 8 Ps, tebal 15 mm


6.7.1. Bahan
- Semen portland 2.880 Kg x Rp. 1,400 = Rp. 4,032.00
- Pasir pasang 0.024 M³ x Rp. 265,000 = Rp. 6,360.00
Jumlah (1) = Rp. 10,392.00
6.7.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 46,500.00
Jumlah (1) + (2) = Rp. 56,892.00

PPL 6.8. 1 M² Plesteran 1 Pc : 2 Ps, tebal 20 mm


6.8.1. Bahan
- Semen Portland 14.280 Kg x Rp. 1,400 = Rp. 19,992.00
- Pasir pasang 0.023 M³ x Rp. 265,000 = Rp. 6,095.00
Jumlah (1) = Rp. 26,087.00

6.8.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 60,187.50
Jumlah (1) + (2) = Rp. 86,274.50
PPL. Hal. 2
PPL 6.9. 1 M² Plesteran 1 Pc : 3 Ps, tebal 20 mm
6.9.1. Bahan
- Semen Portland 10.800 Kg x Rp. 1,400 = Rp. 15,120.00
- Pasir pasang 0.026 M³ x Rp. 265,000 = Rp. 6,890.00
Jumlah (1) = Rp. 22,010.00
6.9.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 60,187.50
Jumlah (1) + (2) = Rp. 82,197.50

PPL 6.10. 1 M² Plesteran 1 Pc : 4 Ps, tebal 20 mm


6.10.1. Bahan
- Semen Portland 8.680 Kg x Rp. 1,400 = Rp. 12,152.00
- Pasir pasang 0.028 M³ x Rp. 265,000 = Rp. 7,420.00
Jumlah (1) = Rp. 19,572.00
6.10.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 60,187.50
Jumlah (1) + (2) = Rp. 79,759.50

PPL 6.11. 1 M² Plesteran 1 Pc : 5 Ps, tebal 20 mm


6.11.1. Bahan
- Semen Portland 7.290 Kg x Rp. 1,400 = Rp. 10,206.00
- Pasir pasang 0.028 M³ x Rp. 265,000 = Rp. 7,420.00
Jumlah (1) = Rp. 17,626.00
6.11.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 60,187.50
Jumlah (1) + (2) = Rp. 77,813.50

PPL 6.12. 1 M² Plesteran 1 Pc : 6 Ps, tebal 20 mm


6.12.1. Bahan
- Semen Portland 6.240 Kg x Rp. 1,400 = Rp. 8,736.00
- Pasir pasang 0.030 M³ x Rp. 265,000 = Rp. 7,950.00
Jumlah (1) = Rp. 16,686.00

6.12.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 60,187.50
Jumlah (1) + (2) = Rp. 76,873.50
PPL. Hal. 3
PPL 6.13. 1 M² Plesteran 1 Pc : 2 Ps, tebal 25 mm
6.13.1. Bahan
- Semen Portland 15.500 Kg x Rp. 1,400 = Rp. 21,700.00
- Pasir pasang 0.013 M³ x Rp. 265,000 = Rp. 3,445.00
Jumlah (1) = Rp. 25,145.00
6.13.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 65,187.50
Jumlah (1) + (2) = Rp. 90,332.50

PPL 6.14. 1 M² Plesteran 1 Pc : 3 Ps, tebal 25 mm


6.14.1. Bahan
- Semen Portland 11.750 Kg x Rp. 1,400 = Rp. 16,450.00
- Pasir pasang 0.035 M³ x Rp. 265,000 = Rp. 9,275.00
Jumlah (1) = Rp. 25,725.00
6.14.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 65,275.00
Jumlah (1) + (2) = Rp. 91,000.00

PPL 6.15. 1 M² Plesteran 1 Pc : 4 Ps, tebal 25 mm


6.15.1. Bahan
- Semen Portland 9.480 Kg x Rp. 1,400 = Rp. 13,272.00
- Pasir pasang 0.038 M³ x Rp. 265,000 = Rp. 10,070.00
Jumlah (1) = Rp. 23,342.00
6.15.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 65,275.00
Jumlah (1) + (2) = Rp. 88,617.00

PPL 6.16. 1 M² Plesteran 1 Pc : 5 Ps, tebal 25 mm


6.16.1. Bahan
- Semen Portland 7.940 Kg x Rp. 1,400 = Rp. 11,116.00
- Pasir pasang 0.039 M³ x Rp. 265,000 = Rp. 10,335.00
Jumlah (1) = Rp. 21,451.00
6.16.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 65,275.00
Jumlah (1) + (2) = Rp. 86,726.00
PPL. Hal. 4
PPL 6.17. 1 M² Plesteran 1 Pc : 2 Ps, tebal 30 mm
6.17.1. Bahan
- Semen Portland 18.650 Kg x Rp. 1,400 = Rp. 26,110.00
- Pasir pasang 0.035 M³ x Rp. 265,000 = Rp. 9,275.00
Jumlah (1) = Rp. 35,385.00
6.17.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 75,875.00
Jumlah (1) + (2) = Rp. 111,260.00

PPL 6.18. 1 M² Plesteran 1 Pc : 3 Ps, tebal 30 mm


6.18.1. Bahan
- Semen Portland 14.150 Kg x Rp. 1,400 = Rp. 19,810.00
- Pasir pasang 0.039 M³ x Rp. 265,000 = Rp. 10,335.00
Jumlah (1) = Rp. 30,145.00
6.18.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 75,875.00
Jumlah (1) + (2) = Rp. 106,020.00

PPL 6.19. 1 M² Plesteran 1 Pc : 4 Ps, tebal 30 mm


6.19.1. Bahan
- Semen Portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
Jumlah (1) = Rp. 27,062.00
6.19.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 75,875.00
Jumlah (1) + (2) = Rp. 102,937.00

PPL 6.20. 1 M² Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm


6.20.1. Bahan
- Semen Portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
Jumlah (1) = Rp. 17,790.00
6.20.2. Tenaga
- Pekerja 0.260 Oh x Rp. 100,000 = Rp. 26,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 61,275.00
Jumlah (1) + (2) = Rp. 79,065.00
PPL. Hal. 5
PPL 6.21. 1 M² Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm
6.21.1. Bahan
- Semen Portland 7.070 Kg x Rp. 1,400 = Rp. 9,898.00
- Pasir pasang 0.021 M³ x Rp. 265,000 = Rp. 5,565.00
Jumlah (1) = Rp. 15,463.00
6.21.2. Tenaga
- Pekerja 0.260 Oh x Rp. 100,000 = Rp. 26,000.00
- Tukang batu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 61,275.00
Jumlah (1) + (2) = Rp. 76,738.00

PPL 6.22. 1 M² Plesteran Skoning 1 Pc : 2 Ps


6.22.1. Bahan
- Semen Portland 0.500 Kg x Rp. 1,400 = Rp. 700.00
- Pasir pasang 0.002 M³ x Rp. 265,000 = Rp. 530.00
Jumlah (1) = Rp. 1,230.00
6.22.2. Tenaga
- Pekerja 0.057 Oh x Rp. 100,000 = Rp. 5,700.00
- Tukang batu 0.038 Oh x Rp. 150,000 = Rp. 5,700.00
- Kepala tukang 0.038 Oh x Rp. 150,000 = Rp. 5,700.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 17,450.00
Jumlah (1) + (2) = Rp. 18,680.00

PPL 6.23. 1 M² Plesteran Ciprat, 1 Pc : 2 Ps, tebal 10 mm


6.23.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,400 = Rp. 6,048.00
- Pasir pasang 0.016 M³ x Rp. 265,000 = Rp. 4,240.00
Jumlah (1) = Rp. 10,288.00
6.23.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.015 Oh x Rp. 175,000 = Rp. 2,625.00
Jumlah (2) = Rp. 44,125.00
Jumlah (1) + (2) = Rp. 54,413.00

PPL 6.24. 1 M² Plesteran Siar adukan, 1 Pc : 2 Ps


6.24.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,400 = Rp. 6,048.00
- Pasir pasang 0.016 M³ x Rp. 265,000 = Rp. 4,240.00
Jumlah (1) = Rp. 10,288.00
6.24.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang batu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 27,950.00
Jumlah (1) + (2) = Rp. 38,238.00
PPL. Hal. 6
ANALISA BIAYA KONSTRUKSI
PEKERJAAN KAYU

PK 6.1. 1 M³ Pasang kusen pintu dan jendela kayu jati :

6.1.1. Bahan
- Kayu jati, balok 1.100 M³ x Rp. 23,925,000.00 = Rp. 26,317,500.00
Jumlah (1) = Rp. 26,317,500.00
6.1.2. Tenaga
- Pekerja 6.000 Oh x Rp. 100,000.00 = Rp. 600,000.00
- Tukang kayu 20.000 Oh x Rp. 150,000.00 = Rp. 3,000,000.00
- Kepala tukang 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Mandor 0.300 Oh x Rp. 175,000.00 = Rp. 52,500.00
Jumlah (2) = Rp. 3,952,500.00
Jumlah (1) +(2) = Rp. 30,270,000.00

PK 6.2. 1 M³ Pasang kusen pintu dan jendela kayu damar laut :

6.2.1. Bahan
- Kayu meranti, balok 1.200 M³ x Rp. 9,075,000.00 = Rp. 10,890,000.00
Jumlah (1) = Rp. 10,890,000.00
6.2.2. Tenaga
- Pekerja 6.000 Oh x Rp. 100,000.00 = Rp. 600,000.00
- Tukang kayu 18.000 Oh x Rp. 150,000.00 = Rp. 2,700,000.00
- Kepala tukang 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Mandor 0.300 Oh x Rp. 175,000.00 = Rp. 52,500.00
Jumlah (2) = Rp. 3,652,500.00
Jumlah (1) +(2) = Rp. 14,542,500.00

PK 6.3. 1 M³ Pasang kusen pintu dan jendela kayu meranti :

6.3.1. Bahan
- Kayu kapur, balok 1.200 M³ x Rp. 6,490,000.00 = Rp. 7,788,000.00
Jumlah (1) = Rp. 7,788,000.00
6.3.2. Tenaga
- Pekerja 6.000 Oh x Rp. 100,000.00 = Rp. 600,000.00
- Tukang kayu 18.000 Oh x Rp. 150,000.00 = Rp. 2,700,000.00
- Kepala tukang 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Mandor 0.300 Oh x Rp. 175,000.00 = Rp. 52,500.00
Jumlah (2) = Rp. 3,652,500.00
Jumlah (1) +(2) = Rp. 11,440,500.00

PK 6.4. 1 M³ Pasang kusen pintu dan jendela kayu damar laut :

6.4.1. Bahan
- Kayu damar laut, balok 1.200 M³ x Rp. 9,350,000.00 = Rp. 11,220,000.00
Jumlah (1) = Rp. 11,220,000.00
6.4.2. Tenaga

- Pekerja 6.000 Oh x Rp. 100,000.00 = Rp. 600,000.00


- Tukang kayu 18.000 Oh x Rp. 150,000.00 = Rp. 2,700,000.00
- Kepala tukang 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Mandor 0.300 Oh x Rp. 175,000.00 = Rp. 52,500.00
Jumlah (2) = Rp. 3,652,500.00
Jumlah (1) +(2) = Rp. 14,872,500.00
PK. Hal. 1
PK 6.5. 1 M² Pasang pintu klamp kayu meranti batu

6.5.1. Bahan
- Kayu meranti batu, papan 0.036 M³ x Rp. 9,375,000.00 = Rp. 337,500.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 338,400.00
6.5.2. Tenaga
- Pekerja 0.350 Oh x Rp. 100,000.00 = Rp. 35,000.00
- Tukang kayu 1.050 Oh x Rp. 150,000.00 = Rp. 157,500.00
- Kepala tukang 0.105 Oh x Rp. 150,000.00 = Rp. 15,750.00
- Mandor 0.018 Oh x Rp. 175,000.00 = Rp. 3,150.00
Jumlah (2) = Rp. 211,400.00
Jumlah (1) +(2) = Rp. 549,800.00

PK 6.6. 1 M³ Pasang pintu klamp kayu jati

6.6.1. Bahan
- Kayu jati, papan 0.036 M³ x Rp. 24,104,440.00 = Rp. 867,759.84
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 868,659.84
6.6.2. Tenaga
- Pekerja 0.350 Oh x Rp. 100,000.00 = Rp. 35,000.00
- Tukang kayu 1.050 Oh x Rp. 150,000.00 = Rp. 157,500.00
- Kepala tukang 0.105 Oh x Rp. 150,000.00 = Rp. 15,750.00
- Mandor 0.018 Oh x Rp. 175,000.00 = Rp. 3,150.00
Jumlah (2) = Rp. 211,400.00
Jumlah (1) +(2) = Rp. 1,080,059.84

PK 6.7. 1 M² Pasang pintu panel kayu jati :

6.7.1. Bahan
- Kayu jati, papan 0.036 M³ x Rp. 24,104,440.00 = Rp. 867,759.84
Jumlah (1) 867,759.84
6.7.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000.00 = Rp. 100,000.00
- Tukang kayu 2.500 Oh x Rp. 150,000.00 = Rp. 375,000.00
- Kepala tukang 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Mandor 0.050 Oh x Rp. 175,000.00 = Rp. 8,750.00
Jumlah (2) = Rp. 521,250.00
Jumlah (1) +(2) = Rp. 1,389,009.84

PK 6.8. 1 M² Pasang pintu panel kayu meranti batu

6.8.1. Bahan
- Kayu meranti batu, papan 0.040 M³ x Rp. 9,375,000.00 = Rp. 375,000.00
Jumlah (1) = Rp. 375,000.00
6.8.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000.00 = Rp. 100,000.00
- Tukang kayu 2.500 Oh x Rp. 150,000.00 = Rp. 375,000.00
- Kepala tukang 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Mandor 0.050 Oh x Rp. 175,000.00 = Rp. 8,750.00
Jumlah (2) = Rp. 521,250.00
Jumlah (1) +(2) = Rp. 896,250.00
PK. Hal. 2
PK 6.9. 1 M² Pasang pintu dan jendela kaca panel kayu jati :

6.9.1. Bahan
- Kayu jati, papan 0.035 M³ x Rp. 24,104,440.00 = Rp. 843,655.40
- Kaca polos 5 mm 0.800 M³ x Rp. 175,000.00 = Rp. 140,000.00
Jumlah (1) = Rp. 983,655.40
6.9.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 417,000.00
Jumlah (1) +(2) = Rp. 1,400,655.40

PK 6.10. 1 M² Pasang pintu dan jendela kaca panel kayu meranti batu :

6.10.1. Bahan
- Kayu meranti batu, papan 0.035 M³ x Rp. 9,375,000.00 = Rp. 328,125.00
- Kaca polos 5 mm 0.800 M³ x Rp. 175,000.00 = Rp. 140,000.00
Jumlah (1) = Rp. 468,125.00
6.10.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 417,000.00
Jumlah (1) +(2) = Rp. 885,125.00

PK 6.11. 1 M² Pasang pintu dan jendela kaca panel kayu meranti :

6.11.1. Bahan
- Kayu meranti, papan 0.035 M³ x Rp. 5,475,000.00 = Rp. 191,625.00
- Kaca polos 5 mm 0.800 M³ x Rp. 175,000.00 = Rp. 140,000.00
Jumlah (1) = Rp. 331,625.00
6.11.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 417,000.00
Jumlah (1) +(2) = Rp. 748,625.00

PK 6.12. 1 M² Pasang pintu dan jendela jalusi kayu jati :

6.12.1. Bahan
- Kayu jati, papan 0.064 M³ x Rp. 24,104,440.00 = Rp. 1,542,684.16
Jumlah (1) = Rp. 1,542,684.16
6.12.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000.00 = Rp. 100,000.00
- Tukang kayu 3.000 Oh x Rp. 150,000.00 = Rp. 450,000.00
- Kepala tukang 0.300 Oh x Rp. 150,000.00 = Rp. 45,000.00
- Mandor 0.300 Oh x Rp. 175,000.00 = Rp. 52,500.00
Jumlah (2) = Rp. 647,500.00
Jumlah (1) +(2) = Rp. 2,190,184.16
PK. Hal. 3
PK 6.13. 1 M² Pasang pintu dan jendela jalusi kayu meranti batu :
6.13.1. Bahan
- Kayu meranti batu, papan 0.064 M³ x Rp. 9,375,000.00 = Rp. 600,000.00
Jumlah (1) = Rp. 600,000.00
6.13.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000.00 = Rp. 100,000.00
- Tukang kayu 3.000 Oh x Rp. 150,000.00 = Rp. 450,000.00
- Kepala tukang 0.300 Oh x Rp. 150,000.00 = Rp. 45,000.00
- Mandor 0.500 Oh x Rp. 175,000.00 = Rp. 87,500.00
Jumlah (2) = Rp. 682,500.00
Jumlah (1) +(2) = Rp. 1,282,500.00

PK 6.14. 1 M² Pasang pintu plywood rangka, rangka kayu jati :


6.14.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa ½" - 1" 0.030 Kg x Rp. 18,000.00 = Rp. 540.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 536,127.02
6.14.2. Tenaga
- Pekerja 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.030 Oh x Rp. 175,000.00 = Rp. 5,250.00
Jumlah (2) = Rp. 395,250.00
Jumlah (1) +(2) = Rp. 931,377.02

PK 6.15. 1 M² Pasang pintu plywood rangka, rangka kayu meranti batu :


6.15.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa ½" - 1" 0.030 Kg x Rp. 18,000.00 = Rp. 540.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 247,430.00
6.15.2. Tenaga
- Pekerja 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.030 Oh x Rp. 175,000.00 = Rp. 5,250.00
Jumlah (2) = Rp. 395,250.00
Jumlah (1) +(2) = Rp. 642,680.00

PK 6.16. 1 M² Pasang jalusi mati kusen kayu jati :


6.16.1. Bahan
- Kayu jati, papan 0.060 M³ x Rp. 24,104,440.00 = Rp. 1,446,266.40
- Paku biasa ½" - 1" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 1,448,966.40
6.16.2. Tenaga
- Pekerja 0.500 Oh x Rp. 100,000.00 = Rp. 50,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.025 Oh x Rp. 175,000.00 = Rp. 4,375.00
Jumlah (2) = Rp. 384,375.00
Jumlah (1) +(2) = Rp. 1,833,341.40
PK. Hal. 4
PK 6.17. 1 M² Pasang jalusi mati kusen kayu damar laut :
6.17.1. Bahan
- Kayu damar laut, papan 0.060 M³ x Rp. 9,650,000.00 = Rp. 579,000.00
- Paku biasa ½" - 1" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 581,700.00
6.17.2. Tenaga
- Pekerja 0.500 Oh x Rp. 100,000.00 = Rp. 50,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.025 Oh x Rp. 175,000.00 = Rp. 4,375.00
Jumlah (2) = Rp. 384,375.00
Jumlah (1) +(2) = Rp. 966,075.00

PK 6.18. 1 M² Pasang pintu plywood rangka, rangka kayu meranti :


6.18.1. Bahan
- Kayu meranti, papan 0.0196 M³ x Rp. 5,475,000.00 = Rp. 107,310.00
- Paku biasa ½" - 1" 0.030 Kg x Rp. 18,000.00 = Rp. 540.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 63,140.00
6.18.2. Tenaga
- Pekerja 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.030 Oh x Rp. 175,000.00 = Rp. 5,250.00
Jumlah (2) = Rp. 395,250.00
Jumlah (1) +(2) = Rp. 458,390.00

PK 6.19. 1 M² Pasang pintu teakwood rangka, rangka kayu jati :


6.19.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa ½" - 1" 0.300 Kg x Rp. 18,000.00 = Rp. 5,400.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
Jumlah (1) = Rp. 543,517.02
6.19.2. Tenaga
- Pekerja 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.030 Oh x Rp. 175,000.00 = Rp. 5,250.00
Jumlah (2) = Rp. 395,250.00
Jumlah (1) +(2) = Rp. 938,767.02

PK 6.20. 1 M² Pasang pintu teakwood rangka, rangka kayu meranti batu :


6.20.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa ½" - 1" 0.300 Kg x Rp. 18,000.00 = Rp. 5,400.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
Jumlah (1) = Rp. 254,820.00
6.20.2. Tenaga
- Pekerja 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00
- Tukang kayu 2.000 Oh x Rp. 150,000.00 = Rp. 300,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Mandor 0.030 Oh x Rp. 175,000.00 = Rp. 5,250.00
Jumlah (2) = Rp. 395,250.00
Jumlah (1) +(2) = Rp. 650,070.00
PK. Hal. 5
PK 6.21. 1 M² Pasang pintu plywood & formika, rangka kayu jati :

6.21.1. Bahan
- Kayu jati, papan 0.0196 M³ x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa ½" - 1" 0.300 Kg x Rp. 18,000.00 = Rp. 5,400.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 633,937.02
6.21.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang kayu 2.500 Oh x Rp. 150,000.00 = Rp. 375,000.00
- Kepala tukang 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 499,500.00
Jumlah (1) +(2) = Rp. 1,133,437.02

PK 6.22. 1 M² Pasang pintu plywood & formika, rangka kayu meranti batu :

6.22.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa ½" - 1" 0.300 Kg x Rp. 18,000.00 = Rp. 5,400.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 345,240.00

6.22.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang kayu 2.500 Oh x Rp. 150,000.00 = Rp. 375,000.00
- Kepala tukang 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 499,500.00
Jumlah (1) +(2) = Rp. 844,740.00
PK. Hal. 6
PK 6.23. 1 M² Pasang pintu plywood & formika, rangka kayu damar laut (divermis) :
6.23.1. Bahan
- Kayu meranti batu, papan 0.0196 M³ x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa ½" - 1" 0.300 Kg x Rp. 18,000.00 = Rp. 5,400.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Teakwood 4' x 8' x 4 mm 0.500 Lbr x Rp. 0.00 = Rp. 0.00
- Vernis 0.500 Lt x Rp. 48,280.00 = Rp. 24,140.00
- Formica 4' x 8' 0.500 Lbr x Rp. 0.00 = Rp. 0.00
Jumlah (1) = Rp. 243,210.00
6.23.2. Tenaga
- Pekerja 0.800 Oh x Rp. 100,000.00 = Rp. 80,000.00
- Tukang kayu 2.500 Oh x Rp. 150,000.00 = Rp. 375,000.00
- Kepala tukang 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Mandor 0.040 Oh x Rp. 175,000.00 = Rp. 7,000.00
Jumlah (2) = Rp. 499,500.00
Jumlah (1) +(2) = Rp. 742,710.00

PK 6.24. 1 M³ Pasang konstruksi kuda-kuda kayu damar laut :


6.24.1. Bahan
- Kayu damar laut, balok 1.1000 M³ x Rp. 9,350,000.00 = Rp. 10,285,000.00
- Besi strip 15.000 Kg x Rp. 11,880.00 = Rp. 178,200.00
- Paku biasa 2" - 5" 0.800 Kg x Rp. 18,000.00 = Rp. 14,400.00
Jumlah (1) = Rp. 10,477,600.00
6.24.2. Tenaga
- Pekerja 4.000 Oh x Rp. 100,000.00 = Rp. 400,000.00
- Tukang kayu 12.000 Oh x Rp. 150,000.00 = Rp. 1,800,000.00
- Kepala tukang 1.200 Oh x Rp. 150,000.00 = Rp. 180,000.00
- Mandor 0.200 Oh x Rp. 175,000.00 = Rp. 35,000.00
Jumlah (2) = Rp. 2,415,000.00
Jumlah (1) +(2) = Rp. 12,892,600.00

PK 6.25. 1 M³ Pasang konstruksi kuda-kuda kayu meranti :


6.25.1. Bahan
- Kayu meranti, balok 1.1000 M³ x Rp. 5,225,000.00 = Rp. 5,747,500.00
- Besi strip 15.000 Kg x Rp. 11,880.00 = Rp. 178,200.00
- Paku biasa 2" - 5" 0.800 Kg x Rp. 18,000.00 = Rp. 14,400.00
Jumlah (1) = Rp. 5,940,100.00
6.25.2. Tenaga
- Pekerja 4.000 Oh x Rp. 100,000.00 = Rp. 400,000.00
- Tukang kayu 12.000 Oh x Rp. 150,000.00 = Rp. 1,800,000.00
- Kepala tukang 1.200 Oh x Rp. 150,000.00 = Rp. 180,000.00
- Mandor 0.200 Oh x Rp. 175,000.00 = Rp. 35,000.00
Jumlah (2) = Rp. 2,415,000.00
Jumlah (1) +(2) = Rp. 8,355,100.00

PK 6.26. 1 M² Pasang kaso + reng genteng kodok kayu meranti :


6.26.1. Bahan
- Kayu meranti, balok 0.012 M³ x Rp. 5,225,000.00 = Rp. 62,700.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 65,400.00
6.26.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 27,375.00
Jumlah (1) +(2) = Rp. 92,775.00
PK. Hal. 7
PK 6.27. 1 M² Pasang kaso + reng genteng kodok kayu damar laut :

6.27.1. Bahan
- Kayu damar laut, balok 0.012 M³ x Rp. 9,350,000.00 = Rp. 112,200.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 114,900.00
6.27.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 27,375.00
Jumlah (1) +(2) = Rp. 142,275.00

PK 6.28. 1 M² Pasang kaso + reng genteng monier kayu jati :

6.28.1. Bahan
- Kayu jati, balok 0.014 M³ x Rp. 23,925,000.00 = Rp. 334,950.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 337,650.00
6.28.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 27,375.00
Jumlah (1) +(2) = Rp. 365,025.00

PK 6.29. 1 M² Pasang kaso + reng genteng monier kayu damar laut :

6.29.1. Bahan
- Kayu damar laut, balok 0.014 M³ x Rp. 9,350,000.00 = Rp. 130,900.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 133,600.00
6.29.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 27,375.00
Jumlah (1) +(2) = Rp. 160,975.00

PK 6.30. 1 M² Pasang kaso + reng genteng beton kayu damar laut :

6.30.1. Bahan
- Kayu damar laut, balok 0.014 M³ x Rp. 9,350,000.00 = Rp. 130,900.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 18,000.00 = Rp. 2,700.00
Jumlah (1) = Rp. 133,600.00
6.30.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 27,375.00
Jumlah (1) +(2) = Rp. 160,975.00
PK. Hal. 8
PK 6.31. 1 M² Pasang kaso + reng atap sirap kayu damar laut :

6.31.1. Bahan
- Kayu damar laut, balok 0.165 M³ x Rp. 9,350,000.00 = Rp. 1,542,750.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 18,000.00 = Rp. 3,600.00
Jumlah (1) = Rp. 1,546,350.00
6.31.2. Tenaga
- Pekerja 0.120 Oh x Rp. 100,000.00 = Rp. 12,000.00
- Tukang kayu 0.120 Oh x Rp. 150,000.00 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000.00 = Rp. 1,800.00
- Mandor 0.006 Oh x Rp. 175,000.00 = Rp. 1,050.00
Jumlah (2) = Rp. 32,850.00
Jumlah (1) +(2) = Rp. 1,579,200.00

PK 6.32. 1 M² Pasang kaso + reng atap sirap kayu meranti :

6.32.1. Bahan
- Kayu meranti, balok 0.165 M³ x Rp. 5,225,000.00 = Rp. 862,125.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 18,000.00 = Rp. 3,600.00
Jumlah (1) = Rp. 865,725.00
6.32.2. Tenaga
- Pekerja 0.120 Oh x Rp. 100,000.00 = Rp. 12,000.00
- Tukang kayu 0.120 Oh x Rp. 150,000.00 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000.00 = Rp. 1,800.00
- Mandor 0.006 Oh x Rp. 175,000.00 = Rp. 1,050.00
Jumlah (2) = Rp. 32,850.00
Jumlah (1) +(2) = Rp. 898,575.00

PK 6.33. 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, kayu jati :

6.33.1. Bahan
- Kayu jati, balok 0.012 M³ x Rp. 23,925,000.00 = Rp. 287,100.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
Jumlah (1) = Rp. 288,900.00
6.33.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000.00 = Rp. 3,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 69,375.00
Jumlah (1) +(2) = Rp. 358,275.00

PK 6.34. A 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, damar laut :

6.34.1. Bahan
- Kayu damar laut, balok 0.012 M³ x Rp. 9,350,000.00 = Rp. 112,200.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
Jumlah (1) = Rp. 114,000.00
6.34.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000.00 = Rp. 3,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 69,375.00
Jumlah (1) +(2) = Rp. 183,375.00
PK. Hal. 9
PK 6.34. B 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, Kayu meranti :

6.34.1. Bahan
- Kayu meranti, balok 0.012 M³ x Rp. 5,225,000.00 = Rp. 62,700.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
Jumlah (1) = Rp. 64,500.00
6.34.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000.00 = Rp. 3,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 69,375.00
Jumlah (1) +(2) = Rp. 133,875.00

PK 6.35. 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu jati :

6.35.1. Bahan
- Kayu jati, balok 0.027 M³ x Rp. 23,925,000.00 = Rp. 645,975.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 18,000.00 = Rp. 3,600.00
Jumlah (1) = Rp. 649,575.00
6.35.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000.00 = Rp. 25,000.00
- Tukang kayu 0.350 Oh x Rp. 150,000.00 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000.00 = Rp. 5,250.00
- Mandor 0.0125 Oh x Rp. 175,000.00 = Rp. 2,187.50
Jumlah (2) = Rp. 84,937.50
Jumlah (1) +(2) = Rp. 734,512.50

PK 6.36. 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu damar laut :

6.36.1. Bahan
- Kayu damar laut, balok 0.027 M³ x Rp. 9,350,000.00 = Rp. 252,450.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 18,000.00 = Rp. 3,600.00
Jumlah (1) = Rp. 256,050.00
6.36.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000.00 = Rp. 25,000.00
- Tukang kayu 0.350 Oh x Rp. 150,000.00 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000.00 = Rp. 5,250.00
- Mandor 0.0125 Oh x Rp. 175,000.00 = Rp. 2,187.50
Jumlah (2) = Rp. 84,937.50
Jumlah (1) +(2) = Rp. 340,987.50

PK 6.37. 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu meranti :


6.37.1. Bahan
- Kayu meranti, balok 0.027 M³ x Rp. 5,225,000.00 = Rp. 141,075.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 18,000.00 = Rp. 3,600.00
Jumlah (1) = Rp. 144,675.00
6.37.2. Tenaga
- Pekerja 0.250 Oh x Rp. 100,000.00 = Rp. 25,000.00
- Tukang kayu 0.350 Oh x Rp. 150,000.00 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000.00 = Rp. 5,250.00
- Mandor 0.0125 Oh x Rp. 175,000.00 = Rp. 2,187.50
Jumlah (2) = Rp. 84,937.50
Jumlah (1) +(2) = Rp. 229,612.50
PK. Hal. 10
PK 6.38. 1 M´ Pasang lisplang ukuran (3 x 20) cm, kayu meranti :

6.38.1. Bahan
- Kayu meranti, papan 0.0072 M³ x Rp. 5,475,000.00 = Rp. 39,420.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 40,320.00
6.38.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Kepala tukang 0.025 Oh x Rp. 150,000.00 = Rp. 3,750.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 44,625.00
Jumlah (1) +(2) = Rp. 84,945.00

PK 6.39. 1 M´ Pasang lisplang ukuran (3 x 20) cm, kayu meranti batu :

6.39.1. Bahan
- Meranti batu, papan 0.0072 M³ x Rp. 9,375,000.00 = Rp. 67,500.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 68,400.00
6.39.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.200 Oh x Rp. 150,000.00 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000.00 = Rp. 3,000.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 43,875.00
Jumlah (1) +(2) = Rp. 112,275.00

PK 6.40. 1 M´ Pasang lisplang ukuran (3 x 30) cm, kayu jati :

6.40.1. Bahan
- Kayu jati, papan 0.0110 M³ x Rp. 24,104,440.00 = Rp. 265,148.84
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 266,048.84
6.40.2. Tenaga
- Pekerja 0.110 Oh x Rp. 100,000.00 = Rp. 11,000.00
- Tukang kayu 0.220 Oh x Rp. 150,000.00 = Rp. 33,000.00
- Kepala tukang 0.022 Oh x Rp. 150,000.00 = Rp. 3,300.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 48,175.00
Jumlah (1) +(2) = Rp. 314,223.84

PK 6.41. 1 M´ Pasang lisplang ukuran (3 x 30) cm, kayu meranti batu :

6.41.1. Bahan
- Meranti batu, papan 0.011 M³ x Rp. 9,375,000.00 = Rp. 103,125.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 104,025.00
6.41.2. Tenaga
- Pekerja 0.110 Oh x Rp. 100,000.00 = Rp. 11,000.00
- Tukang kayu 0.220 Oh x Rp. 150,000.00 = Rp. 33,000.00
- Kepala tukang 0.022 Oh x Rp. 150,000.00 = Rp. 3,300.00
- Mandor 0.005 Oh x Rp. 175,000.00 = Rp. 875.00
Jumlah (2) = Rp. 48,175.00
Jumlah (1) +(2) = Rp. 152,200.00
PK. Hal. 11
PK 6.42. 1 M´ Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti batu :

6.42.1. Bahan
- Meranti batu, papan 0.0145 M³ x Rp. 9,375,000.00 = Rp. 135,937.50
- Paku biasa 2" - 5" 0.060 Kg x Rp. 18,000.00 = Rp. 1,080.00
Jumlah (1) = Rp. 137,017.50
6.42.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.250 Oh x Rp. 150,000.00 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000.00 = Rp. 3,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 69,375.00
Jumlah (1) +(2) = Rp. 206,392.50

PK 6.43. 1 M´ Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti batu :

6.43.1. Bahan
- Meranti batu, papan 0.0086 M³ x Rp. 9,375,000.00 = Rp. 80,625.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 18,000.00 = Rp. 1,080.00
Jumlah (1) = Rp. 81,705.00
6.43.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.050 Oh x Rp. 175,000.00 = Rp. 8,750.00
Jumlah (2) = Rp. 35,250.00
Jumlah (1) +(2) = Rp. 116,955.00

PK 6.44. 1 M´ Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti :

6.44.1. Bahan
- Kayu meranti,papan 0.0086 M³ x Rp. 5,475,000.00 = Rp. 47,085.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 18,000.00 = Rp. 1,080.00
Jumlah (1) = Rp. 48,165.00
6.44.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000.00 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000.00 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000.00 = Rp. 1,500.00
- Mandor 0.050 Oh x Rp. 175,000.00 = Rp. 8,750.00
Jumlah (2) = Rp. 35,250.00
Jumlah (1) +(2) = Rp. 83,415.00

PK 6.45. 1 M´ Pasang rangka dinding pemisah, kayu damar laut :

6.45.1. Bahan
- Kayu damar laut, balok 0.0195 M³ x Rp. 9,350,000.00 = Rp. 182,325.00
- Meranti batu, papan 0.007 M³ x Rp. 9,375,000.00 = Rp. 65,625.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
Jumlah (1) = Rp. 249,750.00
6.45.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.450 Oh x Rp. 150,000.00 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000.00 = Rp. 6,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 102,375.00
Jumlah (1) +(2) = Rp. 352,125.00
PK. Hal. 12
PK 6.46. 1 M´ Pasang rangka dinding pemisah, kayu meranti :
6.46.1. Bahan
- Kayu meranti, balok 0.0195 M³ x Rp. 5,225,000.00 = Rp. 101,887.50
- Kayu meranti, papan 0.007 M³ x Rp. 5,475,000.00 = Rp. 38,325.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
Jumlah (1) = Rp. 142,012.50
6.46.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.450 Oh x Rp. 150,000.00 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000.00 = Rp. 6,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 102,375.00
Jumlah (1) +(2) = Rp. 244,387.50

PK 6.47. 1 M² Pasang dinding pemisah teakwood rangka, rangka kayu damar laut :
6.47.1. Bahan
- Kayu damar laut, balok 0.0195 M³ x Rp. 9,350,000.00 = Rp. 182,325.00
- Teakwood 4' x 8' 1.000 M³ x Rp. 54,450.00 = Rp. 54,450.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
Jumlah (1) = Rp. 238,575.00
6.47.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000.00 = Rp. 15,000.00
- Tukang kayu 0.450 Oh x Rp. 150,000.00 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000.00 = Rp. 6,750.00
- Mandor 0.075 Oh x Rp. 175,000.00 = Rp. 13,125.00
Jumlah (2) = Rp. 102,375.00
Jumlah (1) +(2) = Rp. 340,950.00

PK 6.48. 1 M² Pasang dinding pemisah double plywood, rangka kayu damar laut :
6.48.1. Bahan
- Kayu damar laut, balok 0.0195 M³ x Rp. 9,350,000.00 = Rp. 182,325.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
- Lem kayu 0.560 Lt x Rp. 37,400.00 = Rp. 20,944.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 256,989.00
6.48.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000.00 = Rp. 20,000.00
- Tukang kayu 0.600 Oh x Rp. 150,000.00 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000.00 = Rp. 9,000.00
- Mandor 0.010 Oh x Rp. 175,000.00 = Rp. 1,750.00
Jumlah (2) = Rp. 120,750.00
Jumlah (1) +(2) = Rp. 377,739.00

PK 6.49. 1 M² Pasang dinding lambrizering dari papan meranti :


6.49.1. Bahan
- Kayu meranti, papan 0.0120 M³ x Rp. 5,475,000.00 = Rp. 65,700.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 18,000.00 = Rp. 1,800.00
- Paku skrup 3,5" 0.150 Lbr x Rp. 25,000.00 = Rp. 3,750.00
Jumlah (1) = Rp. 71,250.00
6.49.2. Tenaga
- Pekerja 0.600 Oh x Rp. 100,000.00 = Rp. 60,000.00
- Tukang kayu 1.800 Oh x Rp. 150,000.00 = Rp. 270,000.00
- Kepala tukang 0.180 Oh x Rp. 150,000.00 = Rp. 27,000.00
- Mandor 0.030 Oh x Rp. 175,000.00 = Rp. 5,250.00
Jumlah (2) = Rp. 362,250.00
Jumlah (1) +(2) = Rp. 433,500.00
PK. Hal. 13
PK 6.50. 1 M² Pasang plywood tebal 4 mm, untuk dinding :

6.50.1. Bahan

- Plywood 4' x 8' x 4 mm 0.4000 Lbr x Rp. 51,920.00 = Rp. 20,768.00


- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000.00 = Rp. 900.00
Jumlah (1) = Rp. 21,668.00
6.50.2. Tenaga

- Pekerja 0.025 Oh x Rp. 100,000.00 = Rp. 2,500.00


- Tukang kayu 0.075 Oh x Rp. 150,000.00 = Rp. 11,250.00
- Kepala tukang 0.0075 Oh x Rp. 150,000.00 = Rp. 1,125.00
- Mandor 0.0013 Oh x Rp. 175,000.00 = Rp. 227.50
Jumlah (2) = Rp. 15,102.50
Jumlah (1) +(2) = Rp. 36,770.50

PK 6.51. 1 M' Pasang list plafond kayu profil :

6.51.1. Bahan

- Kayu profil 2" 1.050 M' x Rp. 12,540.00 = Rp. 13,167.00


Jumlah (1) = Rp. 13,167.00
6.51.2. Tenaga

- Pekerja 0.021 Oh x Rp. 100,000.00 = Rp. 2,100.00


- Tukang kayu 0.021 Oh x Rp. 150,000.00 = Rp. 3,150.00
- Kepala tukang 0.002 Oh x Rp. 150,000.00 = Rp. 300.00
- Mandor 0.001 Oh x Rp. 175,000.00 = Rp. 175.00
Jumlah (2) = Rp. 5,725.00
Jumlah (1) +(2) = Rp. 18,892.00
PK. Hal. 14
ANALISA BIAYA KONSTRUKSI
PEKERJAAN BETON

PB 6.1. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr


6.1.1 Bahan
- Semen portland 218.000 Kg x Rp. 1,400 = Rp. 305,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 5/7 0.870 M³ x Rp. 205,000 = Rp. 178,350.00
Jumlah (1) = Rp. 639,550.00
6.1.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 859,800.00

PB 6.2. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr


6.2.1 Bahan
- Semen portland 197.000 Kg x Rp. 1,400 = Rp. 275,800.00
- Pasir beton 0.470 M³ x Rp. 300,000 = Rp. 141,000.00
- Koral beton 5/7 0.940 M³ x Rp. 205,000 = Rp. 192,700.00
Jumlah (1) = Rp. 609,500.00
6.2.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 829,750.00

PB 6.3. 1 M³ Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr


6.3.1 Bahan
- Semen portland 173.000 Kg x Rp. 1,400 = Rp. 242,200.00
- Pasir beton 0.570 M³ x Rp. 300,000 = Rp. 171,000.00
- Koral beton 5/7 0.870 M³ x Rp. 205,000 = Rp. 178,350.00
Jumlah (1) = Rp. 591,550.00
6.3.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 811,800.00

PB 6.4. 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 Cm


6.4.1 Bahan
- Semen portland 10.000 Kg x Rp. 1,400 = Rp. 14,000.00
- Pasir beton 0.026 M³ x Rp. 300,000 = Rp. 7,800.00
- Koral beton 5/7 0.044 M³ x Rp. 205,000 = Rp. 9,020.00
Jumlah (1) = Rp. 30,820.00
6.4.2. Tenaga
- Pekerja 0.165 Oh x Rp. 100,000 = Rp. 16,500.00
- Tukang batu 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Kepala tukang 0.002 Oh x Rp. 150,000 = Rp. 300.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 21,600.00
Jumlah (1) + (2) = Rp. 52,420.00
PB. Hal. 1
6.5. 1 M³ Membuat beton 1 Pc : 2 Ps : 3 Kr

6.5.1 Bahan
- Semen portland 232.000 Kg x Rp. 1,400 = Rp. 324,800.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 5/7 0.780 M³ x Rp. 205,000 = Rp. 159,900.00
Jumlah (1) = Rp. 640,700.00
6.5.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 860,950.00

PB 6.6. 1 M³ Membuat beton 1 Pc : 2 Ps : 4 Kr

6.6.1 Bahan
- Semen portland 280.000 Kg x Rp. 1,400 = Rp. 392,000.00
- Pasir beton 0.450 M³ x Rp. 300,000 = Rp. 135,000.00
- Koral beton 3/5 0.900 M³ x Rp. 215,900 = Rp. 194,310.00
Jumlah (1) = Rp. 721,310.00
6.6.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 941,560.00

PB 6.7. 1 M³ Membuat beton 1 Pc : 2 Ps : 2,5 Kr

6.7.1 Bahan
- Semen portland 352.000 Kg x Rp. 1,400 = Rp. 492,800.00
- Pasir beton 0.560 M³ x Rp. 300,000 = Rp. 168,000.00
- Koral beton 3/5 0.700 M³ x Rp. 215,900 = Rp. 151,130.00
Jumlah (1) = Rp. 811,930.00
6.7.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 1,032,180.00

PB 6.8. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 3 Kr

6.8.1 Bahan
- Semen portland 357.000 Kg x Rp. 1,400 = Rp. 499,800.00
- Pasir beton 0.420 M³ x Rp. 300,000 = Rp. 126,000.00
- Koral beton 3/5 0.540 M³ x Rp. 215,900 = Rp. 116,586.00
Jumlah (1) = Rp. 742,386.00
6.8.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 962,636.00
PB. Hal. 2
PB 6.9. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr

6.9.1 Bahan
- Semen portland 386.000 Kg x Rp. 1,400 = Rp. 540,400.00
- Pasir beton 0.470 M³ x Rp. 300,000 = Rp. 141,000.00
- Koral beton 3/5 0.780 M³ x Rp. 215,900 = Rp. 168,402.00
Jumlah (1) = Rp. 849,802.00
6.9.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 1,070,052.00

PB 6.10. 1 M³ Membuat beton 1 Pc : 1 Ps : 2 Kr

6.10.1 Bahan
- Semen portland 479.000 Kg x Rp. 1,400 = Rp. 670,600.00
- Pasir beton 0.370 M³ x Rp. 300,000 = Rp. 111,000.00
- Koral beton 3/5 0.740 M³ x Rp. 215,900 = Rp. 159,766.00
Jumlah (1) = Rp. 941,366.00

6.10.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 1,161,616.00

PB 6.11. 1 M³ Membuat tiang pancang prestressed beton

6.11.1 Bahan
- Semen portland 440.000 Kg x Rp. 1,400 = Rp. 616,000.00
- Pasir beton 0.500 M³ x Rp. 300,000 = Rp. 150,000.00
- Koral beton/batu pecah 2/3 0.800 M³ x Rp. 205,000 = Rp. 164,000.00
- Rapidrant 2.460 Gln x Rp. = Rp. 0.00
Jumlah (1) = Rp. 930,000.00
6.11.2. Tenaga
- Pekerja 1.650 Oh x Rp. 100,000 = Rp. 165,000.00
- Tukang batu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.080 Oh x Rp. 175,000 = Rp. 14,000.00
Jumlah (2) = Rp. 220,250.00
Jumlah (1) + (2) = Rp. 1,150,250.00

PB 6.12. 1 M³ Membuat beton 1 Pc : 2 Ps : 3 Kr

6.12.1 Bahan
- Semen portland 336.000 Kg x Rp. 1,400 = Rp. 470,400.00
- Pasir beton 0.540 M³ x Rp. 300,000 = Rp. 162,000.00
- Koral beton/batu pecah 2/3 0.810 M³ x Rp. 205,000 = Rp. 166,050.00
Jumlah (1) = Rp. 798,450.00
6.12.2. Tenaga
- Pekerja 2.000 Oh x Rp. 100,000 = Rp. 200,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 1.000 Oh x Rp. 175,000 = Rp. 175,000.00
Jumlah (2) = Rp. 432,750.00
Jumlah (1) + (2) = Rp. 1,231,200.00

PB. Hal. 3
PB 6.13. 1 M³ Membuat beton 1 Pc : 2 Ps : 4 Kr

6.13.1 Bahan
- Semen portland 291.000 Kg x Rp. 1,400 = Rp. 407,400.00
- Pasir beton 0.470 M³ x Rp. 300,000 = Rp. 141,000.00
- Koral beton/batu pecah 2/3 0.930 M³ x Rp. 205,000 = Rp. 190,650.00
Jumlah (1) = Rp. 739,050.00
6.13.2. Tenaga
- Pekerja 2.000 Oh x Rp. 100,000 = Rp. 200,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 1.000 Oh x Rp. 175,000 = Rp. 175,000.00
Jumlah (2) = Rp. 432,750.00
Jumlah (1) + (2) = Rp. 1,171,800.00

PB 6.14. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 3 Kr

6.14.1 Bahan
- Semen portland 367.000 Kg x Rp. 1,400 = Rp. 513,800.00
- Pasir beton 0.440 M³ x Rp. 300,000 = Rp. 132,000.00
- Koral beton 2/3 0.880 M³ x Rp. 205,000 = Rp. 180,400.00
Jumlah (1) = Rp. 826,200.00
6.14.2. Tenaga

- Pekerja 2.000 Oh x Rp. 100,000 = Rp. 200,000.00


- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 1.000 Oh x Rp. 175,000 = Rp. 175,000.00
Jumlah (2) = Rp. 432,750.00
Jumlah (1) + (2) = Rp. 1,258,950.00

PB 6.15. 1 M³ Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr

6.15.1 Bahan
- Semen portland 400.000 Kg x Rp. 1,400 = Rp. 560,000.00
- Pasir beton 0.480 M³ x Rp. 300,000 = Rp. 144,000.00
- Koral beton 2/3 0.880 M³ x Rp. 205,000 = Rp. 180,400.00
Jumlah (1) = Rp. 884,400.00
6.15.2. Tenaga
- Pekerja 2.000 Oh x Rp. 100,000 = Rp. 200,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 1.000 Oh x Rp. 175,000 = Rp. 175,000.00
Jumlah (2) = Rp. 432,750.00
Jumlah (1) + (2) = Rp. 1,317,150.00

PB 6.16. 1 M³ Membuat beton 1 Pc : 1 Ps : 1 Kr

6.16.1 Bahan
- Semen portland 615.000 Kg x Rp. 1,400 = Rp. 861,000.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 2/3 0.520 M³ x Rp. 205,000 = Rp. 106,600.00
Jumlah (1) = Rp. 1,123,600.00
6.16.2. Tenaga
- Pekerja 2.000 Oh x Rp. 100,000 = Rp. 200,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 1.000 Oh x Rp. 175,000 = Rp. 175,000.00
Jumlah (2) = Rp. 432,750.00
Jumlah (1) + (2) = Rp. 1,556,350.00
PB. Hal. 4
PB 6.17. 1 M³ Membuat beton kedap air dengan strorox - 100
6.17.1 Bahan
- Semen portland 400.000 Kg x Rp. 1,400 = Rp. 560,000.00
- Pasir beton 0.480 M³ x Rp. 300,000 = Rp. 144,000.00
- Koral beton 2/3 0.800 M³ x Rp. 205,000 = Rp. 164,000.00
- Strorox - 100 1.200 M³ x Rp. = Rp. 0.00
Jumlah (1) = Rp. 868,000.00
6.17.2. Tenaga
- Pekerja 2.000 Oh x Rp. 100,000 = Rp. 200,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 1.000 Oh x Rp. 175,000 = Rp. 175,000.00
Jumlah (2) = Rp. 432,750.00
Jumlah (1) + (2) = Rp. 1,300,750.00

PB 6.18. 1 M' Memasang PVC Waterstop lebar 150 mm


6.18.1 Bahan
- Waterstop lebar 150 mm 1.050 M' x Rp. 20,000 = Rp. 21,000.00
Jumlah (1) = Rp. 21,000.00
6.18.2. Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Tukang batu 0.030 Oh x Rp. 150,000 = Rp. 4,500.00
- Kepala tukang 0.003 Oh x Rp. 150,000 = Rp. 450.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 10,300.00
Jumlah (1) + (2) = Rp. 31,300.00

PB 6.19. 1 M' Memasang PVC Waterstop lebar 200 mm


6.19.1 Bahan
- Waterstop lebar 200 mm 1.050 M' x Rp. 25,000 = Rp. 26,250.00
Jumlah (1) = Rp. 26,250.00
6.19.2. Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Tukang batu 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Kepala tukang 0.0035 Oh x Rp. 150,000 = Rp. 525.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 11,125.00
Jumlah (1) + (2) = Rp. 37,375.00

PB 6.20. 1 M' Memasang PVC Waterstop lebar 230 mm


6.20.1 Bahan
- Waterstop lebar 230 mm 1.050 M' x Rp. 30,000 = Rp. 31,500.00
Jumlah (1) = Rp. 31,500.00
6.20.2. Tenaga
- Pekerja 0.550 Oh x Rp. 100,000 = Rp. 55,000.00
- Tukang batu 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 60,600.00
Jumlah (1) + (2) = Rp. 92,100.00

PB 6.21. 1 M' Memasang PVC Waterstop lebar 250 mm


6.21.1 Bahan
- Waterstop lebar 250 mm 1.050 M' x Rp. 35,000 = Rp. 36,750.00
Jumlah (1) = Rp. 36,750.00
6.21.2. Tenaga
- Pekerja 0.550 Oh x Rp. 100,000 = Rp. 55,000.00
- Tukang batu 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 60,775.00
Jumlah (1) + (2) = Rp. 97,525.00
PB. Hal. 5
PB 6.22. 1 M' Memasang PVC Waterstop lebar 300 mm

6.22.1. Bahan
- Waterstop lebar 300 mm 1.050 M' x Rp. 40,000 = Rp. 42,000.00
Jumlah (1) = Rp. 42,000.00
6.22.2. Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.260 Oh x Rp. 150,000 = Rp. 39,000.00
- Kepala tukang 0.026 Oh x Rp. 150,000 = Rp. 3,900.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 73,775.00
Jumlah (1) + (2) = Rp. 115,775.00

PB 6.23. 1 Kg Pembesian dengan Besi polos

6.23.1. Bahan
- Besi beton polos 1.050 Kg x Rp. 19,500 = Rp. 20,475.00
- Kawat beton 0.015 Kg x Rp. 19,500 = Rp. 292.50
Jumlah (1) = Rp. 20,767.50
6.23.2. Tenaga
- Pekerja 0.007 Oh x Rp. 100,000 = Rp. 700.00
- Tukang besi 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Kepala tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 3,325.00
Jumlah (1) + (2) = Rp. 24,092.50

PB 6.24 1 M² Kabel Presstressed polos / strands

6.24.1 Bahan
- Besi Presstressed polos 1.050 Kg x Rp. 19,500 = Rp. 20,475.00
- Kawat beton 0.010 Kg x Rp. 19,500 = Rp. 195.00
Jumlah (1) = Rp. 20,670.00
6.24.4 Tenaga
- Pekerja 0.005 Oh x Rp. 100,000 = Rp. 500.00
- Tukang besi 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Kepala tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 2,525.00
Jumlah (1) + (2) = Rp. 23,195.00

PB 6.25 1 M² Pasang bekisting untuk pondasi

6.25.1 Bahan
- Kayu sembarang 0.040 M³ x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2" - 5" 0.300 Kg x Rp. 18,000 = Rp. 5,400.00
- Minyak bekisting 0.100 Ltr x Rp. 9,000 = Rp. 900.00
Jumlah (1) = Rp. 130,600.00
6.25.2 Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang besi 0.260 Oh x Rp. 150,000 = Rp. 39,000.00
- Kepala tukang 0.026 Oh x Rp. 150,000 = Rp. 3,900.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 73,775.00
Jumlah (1) + (2) = Rp. 204,375.00
PB. Hal. 6
PB 6.26 1 M² Pasang bekisting untuk sloof

6.26.1 Bahan
- Kayu sembarang 0.045 M³ x Rp. 3,107,500 = Rp. 139,837.50
- Paku biasa 2' - 5" 0.300 Kg x Rp. 18,000 = Rp. 5,400.00
- Minyak bekisting 0.100 Lt x Rp. 9,000 = Rp. 900.00
Jumlah (1) = Rp. 146,137.50
6.26.2 Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.260 Oh x Rp. 150,000 = Rp. 39,000.00
- Kepala tukang 0.026 Oh x Rp. 150,000 = Rp. 3,900.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 73,775.00
Jumlah (1) + (2) = Rp. 219,912.50

PB 6.27 1 M² Pasang bekisting untuk kolom

6.27.1 Bahan
- Kayu sembarang 0.040 M³ x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 18,000 = Rp. 7,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,000 = Rp. 1,800.00
- Balok kayu sembarang 0.015 M³ x Rp. 3,107,500 = Rp. 46,612.50
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut Ø 3"-4"/4 m 2.000 Btg x Rp. 19,250 = Rp. 38,500.00
Jumlah (1) = Rp. 259,299.50
6.27.2 Tenaga
- Pekerja 0.300 Oh x Rp. 100,000 = Rp. 30,000.00
- Tukang batu 0.330 Oh x Rp. 150,000 = Rp. 49,500.00
- Kepala tukang 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 85,500.00
Jumlah (1) + (2) = Rp. 344,799.50

PB 6.28. 1 M² Pasang bekisting untuk balok

6.28.1 Bahan
- Kayu sembarang 0.040 M³ x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 18,000 = Rp. 7,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,000 = Rp. 1,800.00
- Balok kayu sembarang 0.018 M³ x Rp. 3,107,500 = Rp. 55,935.00
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut Ø 3"-4"/4 m 2.000 Btg x Rp. 19,250 = Rp. 38,500.00
Jumlah (1) = Rp. 268,622.00
6.28.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.330 Oh x Rp. 150,000 = Rp. 49,500.00
- Kepala tukang 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 87,500.00
Jumlah (1) + (2) = Rp. 356,122.00
PB. Hal. 7
PB 6.29. 1 M² Pasang bekisting untuk lantai

6.29.1 Bahan
- Kayu sembarang 0.040 M³ x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 18,000 = Rp. 7,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,000 = Rp. 1,800.00
- Balok kayu sembarang 0.015 M³ x Rp. 3,107,500 = Rp. 46,612.50
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut Ø 3"-4"/4 m 6.000 Btg x Rp. 19,250 = Rp. 115,500.00
Jumlah (1) = Rp. 336,299.50
6.29.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.330 Oh x Rp. 150,000 = Rp. 49,500.00
- Kepala tukang 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 87,500.00
Jumlah (1) + (2) = Rp. 423,799.50

PB 6.30. 1 M² Pasang bekisting untuk dinding

6.30.1 Bahan
- Kayu sembarang 0.030 M³ x Rp. 3,107,500 = Rp. 93,225.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 18,000 = Rp. 7,200.00
- Minyak bekisting 0.200 Lt x Rp. 9,000 = Rp. 1,800.00
- Balok kayu sembarang 0.020 M³ x Rp. 3,107,500 = Rp. 62,150.00
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut Ø 3"-4"/4 m 3.000 Btg x Rp. 19,250 = Rp. 57,750.00
- Formtie/penjaga jarak bekisting/space 4.000 Btg x Rp. 5,000 = Rp. 20,000.00
Jumlah (1) = Rp. 283,012.00

6.30.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.330 Oh x Rp. 150,000 = Rp. 49,500.00
- Kepala tukang 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 87,500.00
Jumlah (1) + (2) = Rp. 370,512.00

PB 6.31. 1 M² Pasang bekisting untuk tangga

6.31.1 Bahan
- Kayu sembarang 0.030 M³ x Rp. 3,107,500 = Rp. 93,225.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 18,000 = Rp. 7,200.00
- Minyak bekisting 0.150 Lt x Rp. 9,000 = Rp. 1,350.00
- Balok kayu sembarang 0.015 M³ x Rp. 3,107,500 = Rp. 46,612.50
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut Ø 3"-4"/4 m 2.000 Btg x Rp. 19,250 = Rp. 38,500.00
Jumlah (1) = Rp. 227,774.50
6.31.2. Tenaga
- Pekerja 0.320 Oh x Rp. 100,000 = Rp. 32,000.00
- Tukang batu 0.330 Oh x Rp. 150,000 = Rp. 49,500.00
- Kepala tukang 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 87,500.00
Jumlah (1) + (2) = Rp. 315,274.50
PB. Hal. 8
PB 6.32. 1 M³ Pasang beton dengan mutu K 225
6.32.1 Bahan
- Semen portland 388.000 Kg x Rp. 1,400 = Rp. 543,200.00
- Pasir beton 0.650 M³ x Rp. 300,000 = Rp. 195,000.00
- Batu pecah 0.650 M³ x Rp. 215,000 = Rp. 139,750.00
Jumlah (1) = Rp. 877,950.00
6.32.2. Tenaga
- Pekerja 6.000 Oh x Rp. 100,000 = Rp. 600,000.00
- Tukang batu 1.000 Oh x Rp. 150,000 = Rp. 150,000.00
- Kepala tukang 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Mandor 0.300 Oh x Rp. 175,000 = Rp. 52,500.00
Jumlah (2) = Rp. 817,500.00
Jumlah (1) + (2) = Rp. 1,695,450.00

PB 6.33. 1 M³ Pasang beton dengan mutu K 275


6.33.1 Bahan
- Semen portland 400.000 Kg x Rp. 1,400 = Rp. 560,000.00
- Pasir beton 0.400 M³ x Rp. 300,000 = Rp. 120,000.00
- Koral beton 0.820 M³ x Rp. 215,000 = Rp. 176,300.00
Jumlah (1) = Rp. 856,300.00
6.33.2. Tenaga
- Pekerja 6.000 Oh x Rp. 100,000 = Rp. 600,000.00
- Tukang batu 1.000 Oh x Rp. 150,000 = Rp. 150,000.00
- Kepala tukang 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Mandor 0.300 Oh x Rp. 175,000 = Rp. 52,500.00
Jumlah (2) = Rp. 817,500.00
Jumlah (1) + (2) = Rp. 1,673,800.00

PB 6.34. 1 M² Pasang jembatan cor


6.34.1 Bahan
- Kayu sembarang 0.0264 M³ x Rp. 3,107,500 = Rp. 82,038.00
- Paku biasa 2" - 5 " 0.600 Kg x Rp. 18,000 = Rp. 10,800.00
- Kayu dolken/Laut Ø 3"-4"/4 m 0.500 Btg x Rp. 19,250 = Rp. 9,625.00
Jumlah (1) = Rp. 102,463.00
6.34.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang batu 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Kepala tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 24,475.00
Jumlah (1) + (2) = Rp. 126,938.00

PB 6.35. 1 M³ Membuat pondasi beton bertulang (150 kg besi + bekisting)


6.35.1 Bahan
- Kayu sembarang 0.2000 M³ x Rp. 3,107,500 = Rp. 621,500.00
- Paku biasa 2" - 5 " 1.500 Kg x Rp. 18,000 = Rp. 27,000.00
- Minyak bekisting 0.400 Lt x Rp. 9,000 = Rp. 3,600.00
- Besi beton polos 150.000 Kg x Rp. 19,500 = Rp. 2,925,000.00
- Kawat beton 2.250 Kg x Rp. 19,500 = Rp. 43,875.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
Jumlah (1) = Rp. 4,396,875.00
6.35.2. Tenaga
- Pekerja 3.900 Oh x Rp. 100,000 = Rp. 390,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 1.040 Oh x Rp. 150,000 = Rp. 156,000.00
- Tukang besi 1.050 Oh x Rp. 150,000 = Rp. 157,500.00
- Kepala tukang 0.245 Oh x Rp. 150,000 = Rp. 36,750.00
- Mandor 0.165 Oh x Rp. 175,000 = Rp. 28,875.00
Jumlah (2) = Rp. 821,625.00
Jumlah (1) + (2) = Rp. 5,218,500.00

PB. Hal. 9
PB 6.36. 1 M³ Membuat sloof beton bertulang (200 kg besi + bekisting)

6.36.1 Bahan
- Kayu sembarang 0.2700 M³ x Rp. 3,107,500 = Rp. 839,025.00
- Paku biasa 2" - 5 " 2.000 Kg x Rp. 18,000 = Rp. 36,000.00
- Minyak bekisting 0.600 Lt x Rp. 9,000 = Rp. 5,400.00
- Besi beton polos 200.000 Kg x Rp. 19,500 = Rp. 3,900,000.00
- Kawat beton 3.000 Kg x Rp. 19,500 = Rp. 58,500.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
Jumlah (1) = Rp. 5,614,825.00

6.36.2. Tenaga
- Pekerja 4.850 Oh x Rp. 100,000 = Rp. 485,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 1.560 Oh x Rp. 150,000 = Rp. 234,000.00
- Tukang besi 1.400 Oh x Rp. 150,000 = Rp. 210,000.00
- Kepala tukang 0.331 Oh x Rp. 150,000 = Rp. 49,650.00
- Mandor 0.170 Oh x Rp. 175,000 = Rp. 29,750.00
Jumlah (2) = Rp. 1,060,900.00
Jumlah (1) + (2) = Rp. 6,675,725.00

PB 6.37. 1 M³ Membuat kolom beton bertulang (300 kg besi + bekisting)

6.37.1 Bahan
- Kayu sembarang 0.4000 M³ x Rp. 3,107,500 = Rp. 1,243,000.00
- Paku biasa 2" - 5 " 4.000 Kg x Rp. 18,000 = Rp. 72,000.00
- Minyak bekisting 2.000 Lt x Rp. 9,000 = Rp. 18,000.00
- Besi beton polos 300.000 Kg x Rp. 19,500 = Rp. 5,850,000.00
- Kawat beton 4.500 Kg x Rp. 19,500 = Rp. 87,750.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
- Kayu sembarang balok 0.150 M³ x Rp. 3,107,500 = Rp. 466,125.00
- Plywood 9 mm 3.500 Lbr x Rp. 116,820 = Rp. 408,870.00
- Kayu dolken/Laut Ø 3"-4"/4 m 20.000 Btg x Rp. 19,250 = Rp. 385,000.00
Jumlah (1) = Rp. 9,306,645.00

6.37.2. Tenaga
- Pekerja 7.300 Oh x Rp. 100,000 = Rp. 730,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 3.300 Oh x Rp. 150,000 = Rp. 495,000.00
- Tukang besi 2.100 Oh x Rp. 150,000 = Rp. 315,000.00
- Kepala tukang 0.570 Oh x Rp. 150,000 = Rp. 85,500.00
- Mandor 0.250 Oh x Rp. 175,000 = Rp. 43,750.00
Jumlah (2) = Rp. 1,721,750.00
Jumlah (1) + (2) = Rp. 11,028,395.00
PB. Hal. 10
PB 6.38. 1 M³ Membuat balok beton bertulang (200 kg besi + bekisting)

6.38.1 Bahan
- Kayu sembarang 0.3200 M³ x Rp. 3,107,500 = Rp. 994,400.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 18,000 = Rp. 57,600.00
- Minyak bekisting 1.600 Lt x Rp. 9,000 = Rp. 14,400.00
- Besi beton polos 200.000 Kg x Rp. 19,500 = Rp. 3,900,000.00
- Kawat beton 3.000 Kg x Rp. 19,500 = Rp. 58,500.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
- Kayu sembarang balok 0.140 M³ x Rp. 3,107,500 = Rp. 435,050.00
- Plywood 9 mm 2.800 Lbr x Rp. 116,820 = Rp. 327,096.00
- Kayu dolken/Laut Ø 3"-4"/4 m 16.000 Btg x Rp. 19,250 = Rp. 308,000.00
Jumlah (1) = Rp. 6,870,946.00

6.38.1 Tenaga
- Pekerja 5.960 Oh x Rp. 100,000 = Rp. 596,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 2.800 Oh x Rp. 150,000 = Rp. 420,000.00
- Tukang besi 1.400 Oh x Rp. 150,000 = Rp. 210,000.00
- Kepala tukang 0.455 Oh x Rp. 150,000 = Rp. 68,250.00
- Mandor 0.208 Oh x Rp. 175,000 = Rp. 36,400.00
Jumlah (2) = Rp. 1,383,150.00
Jumlah (1) + (2) = Rp. 8,254,096.00

PB 6.39. 1 M³ Membuat balok beton bertulang (150 kg besi + bekisting)

6.39.1 Bahan
- Kayu sembarang 0.320 M³ x Rp. 3,107,500 = Rp. 994,400.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 18,000 = Rp. 57,600.00
- Minyak bekisting 1.600 Lt x Rp. 9,000 = Rp. 14,400.00
- Besi beton polos 150.000 Kg x Rp. 19,500 = Rp. 2,925,000.00
- Kawat beton 2.250 Kg x Rp. 19,500 = Rp. 43,875.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
- Kayu sembarang balok 0.120 M³ x Rp. 3,107,500 = Rp. 372,900.00
- Plywood 9 mm 2.800 Lbr x Rp. 116,820 = Rp. 327,096.00
- Kayu dolken/Laut Ø 3"-4"/4 m 32.000 Btg x Rp. 19,250 = Rp. 616,000.00
Jumlah (1) = Rp. 6,127,171.00

6.39.2 Tenaga
- Pekerja 5.800 Oh x Rp. 100,000 = Rp. 580,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 2.800 Oh x Rp. 150,000 = Rp. 420,000.00
- Tukang besi 1.050 Oh x Rp. 150,000 = Rp. 157,500.00
- Kepala tukang 0.420 Oh x Rp. 150,000 = Rp. 63,000.00
- Mandor 0.185 Oh x Rp. 175,000 = Rp. 32,375.00
Jumlah (2) = Rp. 1,305,375.00
Jumlah (1) + (2) = Rp. 7,432,546.00
PB. Hal. 11
PB 6.40. 1 M³ Membuat dinding beton bertulang (150 kg besi + bekisting)

6.40.1 Bahan
- Kayu sembarang 0.240 M³ x Rp. 3,107,500 = Rp. 745,800.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 18,000 = Rp. 57,600.00
- Minyak bekisting 1.600 Lt x Rp. 9,000 = Rp. 14,400.00
- Besi beton polos 150.000 Kg x Rp. 19,500 = Rp. 2,925,000.00
- Kawat beton 2.250 Kg x Rp. 19,500 = Rp. 43,875.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
- Kayu sembarang balok 0.160 M³ x Rp. 3,107,500 = Rp. 497,200.00
- Plywood 9 mm 2.800 Lbr x Rp. 116,820 = Rp. 327,096.00
- Kayu dolken/Laut Ø 3"-4"/4 m 24.000 Btg x Rp. 19,250 = Rp. 462,000.00
Jumlah (1) = Rp. 5,848,871.00

6.40.2. Tenaga
- Pekerja 5.600 Oh x Rp. 100,000 = Rp. 560,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 2.640 Oh x Rp. 150,000 = Rp. 396,000.00
- Tukang besi 1.050 Oh x Rp. 150,000 = Rp. 157,500.00
- Kepala tukang 0.400 Oh x Rp. 150,000 = Rp. 60,000.00
- Mandor 0.193 Oh x Rp. 175,000 = Rp. 33,775.00
Jumlah (2) = Rp. 1,259,775.00
Jumlah (1) + (2) = Rp. 7,108,646.00

PB 6.41. 1 M³ Membuat tangga beton bertulang (150 kg besi + bekisting)

6.41.1 Bahan
- Kayu sembarang 0.250 M³ x Rp. 3,107,500 = Rp. 776,875.00
- Paku biasa 2" - 5 " 3.000 Kg x Rp. 18,000 = Rp. 54,000.00
- Minyak bekisting 1.200 Lt x Rp. 9,000 = Rp. 10,800.00
- Besi beton polos 200.000 Kg x Rp. 19,500 = Rp. 3,900,000.00
- Kawat beton 3.000 Kg x Rp. 19,500 = Rp. 58,500.00
- Semen portland 323.000 Kg x Rp. 1,400 = Rp. 452,200.00
- Pasir beton 0.520 M³ x Rp. 300,000 = Rp. 156,000.00
- Koral beton 0.780 M³ x Rp. 215,000 = Rp. 167,700.00
- Kayu sembarang balok 0.105 M³ x Rp. 3,107,500 = Rp. 326,287.50
- Plywood 9 mm 2.500 Lbr x Rp. 116,820 = Rp. 292,050.00
- Kayu dolken/Laut Ø 3"-4"/4 m 14.000 Btg x Rp. 19,250 = Rp. 269,500.00
Jumlah (1) = Rp. 6,463,912.50

6.41.2. Tenaga
- Pekerja 5.600 Oh x Rp. 100,000 = Rp. 560,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Tukang kayu 2.300 Oh x Rp. 150,000 = Rp. 345,000.00
- Tukang besi 1.400 Oh x Rp. 150,000 = Rp. 210,000.00
- Kepala tukang 0.405 Oh x Rp. 150,000 = Rp. 60,750.00
- Mandor 0.202 Oh x Rp. 175,000 = Rp. 35,350.00
Jumlah (2) = Rp. 1,263,600.00
Jumlah (1) + (2) = Rp. 7,727,512.50
PB. Hal. 12
PB 6.42. 1 M' Membuat kolom penguat beton bertulang (11 x 11) cm

6.42.1 Bahan
- Kayu sembarang 0.002 M³ x Rp. 3,107,500 = Rp. 6,215.00
- Paku biasa 2" - 5 " 0.010 Kg x Rp. 18,000 = Rp. 180.00
- Besi beton polos 3.000 Kg x Rp. 19,500 = Rp. 58,500.00
- Kawat beton 0.450 Kg x Rp. 19,500 = Rp. 8,775.00
- Semen portland 4.000 Kg x Rp. 1,400 = Rp. 5,600.00
- Pasir beton 0.006 M³ x Rp. 300,000 = Rp. 1,800.00
- Koral beton 0.009 M³ x Rp. 215,000 = Rp. 1,935.00
Jumlah (1) = Rp. 83,005.00

6.42.2. Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang batu 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Tukang kayu 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Tukang besi 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 16,425.00
Jumlah (1) + (2) = Rp. 99,430.00

PB 6.43. 1 M' Membuat ring balok beton bertulang (10 x 15) cm

6.43.1 Bahan
- Kayu sembarang 0.003 M³ x Rp. 3,107,500 = Rp. 9,322.50
- Paku biasa 2" - 5 " 0.020 Kg x Rp. 18,000 = Rp. 360.00
- Besi beton polos 3.600 Kg x Rp. 19,500 = Rp. 70,200.00
- Kawat beton 0.050 Kg x Rp. 19,500 = Rp. 975.00
- Semen portland 5.500 Kg x Rp. 1,400 = Rp. 7,700.00
- Pasir beton 0.009 M³ x Rp. 300,000 = Rp. 2,700.00
- Koral beton 0.015 M³ x Rp. 215,000 = Rp. 3,225.00
Jumlah (1) = Rp. 94,482.50

6.43.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang batu 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Tukang kayu 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Tukang besi 0.033 Oh x Rp. 150,000 = Rp. 4,950.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 27,225.00
Jumlah (1) + (2) = Rp. 121,707.50
PB. Hal. 13
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PENUTUP ATAP

PPA 6.1 1 M² Pasang atap genteng palentong kecil

6.1.1 Bahan
- Genteng Palentong 25.000 Bh x Rp. 1,670 = Rp. 41,750.00
Jumlah (1) = Rp. 41,750.00
6.1.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang Kayu 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 28,850.00
Jumlah (1) + (2) = Rp. 70,600.00

PPA 6.2 1 M² Pasang atap genteng kodok / glazzur

6.2.1 Bahan
- Genteng Kodok 25.000 Bh x Rp. 2,170 = Rp. 54,250.00
Jumlah (1) = Rp. 54,250.00
6.2.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang Kayu 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 28,850.00
Jumlah (1) + (2) = Rp. 83,100.00

PPA 6.3 1 M² Pasang atap genteng palentong super / besar

6.3.1 Bahan
- Genteng Palentong super 12.000 Bh x Rp. 3,980 = Rp. 47,760.00
Jumlah (1) = Rp. 47,760.00
6.3.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang Kayu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala Tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 26,300.00
Jumlah (1) + (2) = Rp. 74,060.00

PPA 6.4 1 M² Pasang genteng bubung palentong

6.4.1 Bahan
- Bubung geneteng palentong 5.000 Bh x Rp. 9,350 = Rp. 46,750.00
- Semen portland 8.000 Kg x Rp. 1,400 = Rp. 11,200.00
- Pasir Pasang 0.032 M³ x Rp. 265,000 = Rp. 8,480.00
Jumlah (1) = Rp. 66,430.00
6.4.2 Tenaga
- Pekerja 0.400 Oh x Rp. 100,000 = Rp. 40,000.00
- Tukang Kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala Tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 73,350.00
Jumlah (1) + (2) = Rp. 139,780.00

PPA 6.5 1 M' Pasang bubung genteng kodok glazzuur

6.5.1 Bahan
- Bubung genteng kodok 5.000 Bh x Rp. 9,560 = Rp. 47,800.00
- Semen portland 8.000 Kg x Rp. 1,400 = Rp. 11,200.00
- Pasir Pasang 0.032 M³ x Rp. 265,000 = Rp. 8,480.00
Jumlah (1) = Rp. 67,480.00
6.5.2 Tenaga
- Pekerja 0.400 Oh x Rp. 100,000 = Rp. 40,000.00
- Tukang Kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala Tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 73,350.00
Jumlah (1) + (2) = Rp. 140,830.00
PPA. Hal. 1
PPA 6.6 1 M' Pasang bubung genteng palentong besar

6.6.1 Bahan
- Bubung genteng palentong super 4.000 Bh x Rp. 12,740 = Rp. 50,960.00
- Semen portland 8.000 Kg x Rp. 1,400 = Rp. 11,200.00
- Pasir Pasang 0.032 M³ x Rp. 265,000 = Rp. 8,480.00
Jumlah (1) = Rp. 70,640.00
6.6.2 Tenaga
- Pekerja 0.400 Oh x Rp. 100,000 = Rp. 40,000.00
- Tukang Kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala Tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 73,350.00
Jumlah (1) + (2) = Rp. 143,990.00

PPA 6.7 1 M² Pasang roof light fiberglass ( 180 x 90 ) cm

6.7.1 Bahan
- Roof light fibreglass 0.600 Lbr x Rp. 46,390 = Rp. 27,834.00
- Paku biasa ½ " - 1" 0.050 Kg x Rp. 18,000 = Rp. 900.00
Jumlah (1) = Rp. 28,734.00
6.7.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.067 Oh x Rp. 150,000 = Rp. 10,050.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) + (2) = Rp. 55,059.00

PPA 6.8 1 M² Pasang atap asbes gelombang ( 2,70 x 0,92 m ) x 5 mm

6.8.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 106,810 = Rp. 48,064.50
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 51,064.50
6.8.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 27,850.00
Jumlah (1) + (2) = Rp. 78,914.50

PPA 6.9 1 M² Pasang atap asbes gelombang ( 2,40 x 0,92 m ) x 5 mm

6.9.1 Bahan
- Atap asbes gelombang 0.500 Lbr x Rp. 97,020 = Rp. 48,510.00
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 51,510.00
6.9.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 27,850.00
Jumlah (1) + (2) = Rp. 79,360.00

PPA 6.10 1 M² Pasang atap asbes gelombang ( 2,10 x 0,92 m ) x 5 mm

6.10.1 Bahan
- Atap asbes gelombang 0.600 Lbr x Rp. 88,770 = Rp. 53,262.00
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 56,262.00
6.10.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 27,850.00
Jumlah (1) + (2) = Rp. 84,112.00
PPA. Hal. 2
PPA 6.11 1 M² Pasang atap asbes gelombang ( 1,80 x 0,92 m ) x 5 mm

6.11.1 Bahan
- Atap asbes gelombang 0.750 Lbr x Rp. 70,950 = Rp. 53,212.50
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 56,212.50
6.11.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,775.00
Jumlah (1) + (2) = Rp. 82,987.50

PPA 6.12 1 M² Pasang atap asbes gelombang ( 2,40 x 1,05 m ) x 4 mm

6.12.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 108,130 = Rp. 48,658.50
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 51,658.50
6.12.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,775.00
Jumlah (1) + (2) = Rp. 78,433.50

PPA 6.13 1 M² Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm

6.13.1 Bahan
- Atap asbes gelombang 0.500 Lbr x Rp. 93,170 = Rp. 46,585.00
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 49,585.00
6.13.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,775.00
Jumlah (1) + (2) = Rp. 76,360.00

PPA 6.14 1 M² Pasang atap asbes gelombang ( 1,80 x 1,05 m ) x 4 mm

6.14.1 Bahan
- Atap asbes gelombang 0.600 Lbr x Rp. 59,380 = Rp. 35,628.00
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 38,628.00
6.14.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.067 Oh x Rp. 150,000 = Rp. 10,050.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) + (2) = Rp. 64,953.00

PPA 6.15 1 M² Pasang atap asbes gelombang ( 2,70 x 1,08 m ) x 6 mm

6.15.1 Bahan
- Atap asbes gelombang 0.380 Lbr x Rp. 59,380 = Rp. 22,564.40
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 25,564.40
6.15.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.067 Oh x Rp. 150,000 = Rp. 10,050.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) + (2) = Rp. 51,889.40
PPA. Hal. 3
PPA 6.16 1 M² Pasang atap asbes gelombang ( 2,4 x 1,08 m ) x 6 mm

6.16.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 128,370 = Rp. 57,766.50
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 60,766.50
6.16.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.067 Oh x Rp. 150,000 = Rp. 10,050.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) + (2) = Rp. 87,091.50

PPA 6.17 1 M² Pasang atap asbes gelombang ( 2,1 x 1,08 m ) x 6 mm

6.17.1 Bahan
- Atap asbes gelombang 0.490 Lbr x Rp. 120,450 = Rp. 59,020.50
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 62,020.50
6.17.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.067 Oh x Rp. 150,000 = Rp. 10,050.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) + (2) = Rp. 88,345.50

PPA 6.18 1 M² Pasang atap asbes gelombang ( 1,80 x 1,08 m ) x 6 mm

6.18.1 Bahan
- Atap asbes gelombang 0.570 Lbr x Rp. 103,620 = Rp. 59,063.40
- Paku seng 0.120 Kg x Rp. 25,000 = Rp. 3,000.00
Jumlah (1) = Rp. 62,063.40
6.18.2 Tenaga
- Pekerja 0.140 Oh x Rp. 100,000 = Rp. 14,000.00
- Tukang Kayu 0.067 Oh x Rp. 150,000 = Rp. 10,050.00
- Kepala Tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.007 Oh x Rp. 175,000 = Rp. 1,225.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) + (2) = Rp. 88,388.40

PPA 6.19 1 M' Pasang bubung stel gelombang 0,92 m

6.19.1 Bahan
- Bubung stel gelombang 2.400 Lbr x Rp. 19,590 = Rp. 47,016.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 49,476.00
6.19.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 79,276.00

PPA 6.20 1 M' Pasang nok stel gelombang 1,05 m

6.20.1 Bahan
- Bubung stel gelombang 2.100 Lbr x Rp. 25,990 = Rp. 54,579.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 57,039.00

6.20.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 86,839.00
PPA. Hal. 4
PPA 6.21 1 M' Pasang nok stel gelombang 1,08 m

6.21.1 Bahan
- Bubung stel gelombang 2.050 Lbr x Rp. 28,510 = Rp. 58,445.50
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 60,905.50
6.21.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 90,705.50

PPA 6.22 1 M' Pasang nok paten 1,05 m

6.22.1 Bahan
- Nok paten 5 mm 1.200 Lbr x Rp. 36,810 = Rp. 44,172.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 46,632.00
6.22.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 76,432.00

PPA 6.23 1 M' Pasang nok paten 1,05 m

6.23.1 Bahan
- Nok paten 4 mm 1.200 Lbr x Rp. 30,950 = Rp. 37,140.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 39,600.00
6.23.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 69,400.00

PPA 6.24 1 M' Pasang nok paten 1,08 m

6.24.1 Bahan
- Nok paten 6 mm 1.200 Lbr x Rp. 42,960 = Rp. 51,552.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 54,012.00
6.24.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 83,812.00

PPA 6.25 1 M' Pasang nok stel rata 0,92 m

6.25.1 Bahan
- Nok stel rata 5 mm 1.100 Lbr x Rp. 36,080 = Rp. 39,688.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 42,148.00
6.25.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang Kayu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 35,150.00
Jumlah (1) + (2) = Rp. 77,298.00
PPA. Hal. 5
PPA 6.26 1 M' Pasang nok stel rata 1,05 m

6.26.1 Bahan
- Nok stel rata 4 mm 1.100 Lbr x Rp. 30,250 = Rp. 33,275.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 35,735.00
6.26.2 Tenaga
- Pekerja 0.084 Oh x Rp. 100,000 = Rp. 8,400.00
- Tukang Kayu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala Tukang 0.013 Oh x Rp. 150,000 = Rp. 1,950.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 29,800.00
Jumlah (1) + (2) = Rp. 65,535.00

PPA 6.27 1 M² Pasang atap genteng beton

6.27.1 Bahan
- Atap genteng beton 11.000 Bh x Rp. 5,970 = Rp. 65,670.00
- Paku biasa 2" - 5" 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 66,210.00
6.27.2 Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang Kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala Tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 38,250.00
Jumlah (1) + (2) = Rp. 104,460.00

PPA 6.28 1 M² Pasang atap genteng aspal

6.28.1 Bahan
- Nok genteng aspal 6.900 Lbr x Rp. 11,320 = Rp. 78,108.00
- Plywood 4" x 8" x 6 mm 0.350 Lbr x Rp. 77,880 = Rp. 27,258.00
- Paku biasa ½" - 1" 0.030 Kg x Rp. 18,000 = Rp. 540.00
- Plastic aerator 0.500 Bh x Rp. 27,500 = Rp. 13,750.00
Jumlah (1) = Rp. 119,656.00
6.28.2 Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang Kayu 0.300 Oh x Rp. 150,000 = Rp. 45,000.00
- Kepala Tukang 0.003 Oh x Rp. 150,000 = Rp. 450.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 67,200.00
Jumlah (1) + (2) = Rp. 186,856.00

PPA 6.29 1 M² Pasang atap genteng metal / multi roof

6.29.1 Bahan
- Atap genteng metal 1.020 Bh x Rp. 64,130 = Rp. 65,412.60
- Paku biasa 2" - 5" 0.200 Kg x Rp. 18,000 = Rp. 3,600.00
Jumlah (1) = Rp. 69,012.60
6.29.2 Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang Kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala Tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 38,250.00
Jumlah (1) + (2) = Rp. 107,262.60

PPA 6.30 1 M² Pasang atap sirap

6.30.1 Bahan
- Atap sirap 60.000 Bh x Rp. 1,030 = Rp. 61,800.00
- Paku biasa ½" - 1" 0.200 Kg x Rp. 18,000 = Rp. 3,600.00
Jumlah (1) = Rp. 65,400.00
6.30.2 Tenaga
- Pekerja 0.166 Oh x Rp. 100,000 = Rp. 16,600.00
- Tukang Kayu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala Tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 59,250.00
Jumlah (1) + (2) = Rp. 124,650.00
PPA. Hal. 6
PPA 6.31 1 M' Pasang nok genteng beton
6.31.1 Bahan
- Nok atap genteng beton 3.500 Bh x Rp. 13,440 = Rp. 47,040.00
- Paku biasa 2" x 5" 0.050 Kg x Rp. 18,000 = Rp. 900.00
- Semen PC 10.800 Kg x Rp. 1,400 = Rp. 15,120.00
- Pasir pasang 0.032 M³ x Rp. 265,000 = Rp. 8,480.00
- Semen warna 1.000 Kg x Rp. 5,000 = Rp. 5,000.00
Jumlah (1) = Rp. 76,540.00
6.31.2 Tenaga
- Pekerja 0.400 Oh x Rp. 100,000 = Rp. 40,000.00
- Tukang Kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala Tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.020 Oh x Rp. 175,000 = Rp. 3,500.00
Jumlah (2) = Rp. 76,500.00
Jumlah (1) + (2) = Rp. 153,040.00

PPA 6.32 1 M' Pasang nok genteng aspal


6.32.1 Bahan
- Nok genteng aspal 2.000 Bh x Rp. 11,320 = Rp. 22,640.00
- Paku biasa ½" - 1" 0.050 Kg x Rp. 18,000 = Rp. 900.00
- Kayu papan 0.0035 M³ x Rp. 9,650,000 = Rp. 33,775.00
Jumlah (1) = Rp. 57,315.00
6.32.2 Tenaga
- Pekerja 0.125 Oh x Rp. 100,000 = Rp. 12,500.00
- Tukang Kayu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala Tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 54,800.00
Jumlah (1) + (2) = Rp. 112,115.00

PPA 6.33 1 M' Pasang nok genteng metal


6.33.1 Bahan
- Nok genteng decra bond 1.100 Bh x Rp. 41,140 = Rp. 45,254.00
- Paku biasa ½" - 1" 0.050 Kg x Rp. 18,000 = Rp. 900.00
Jumlah (1) = Rp. 46,154.00
6.33.2 Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang Kayu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala Tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 52,025.00
Jumlah (1) + (2) = Rp. 98,179.00

PPA 6.34 1 M' Pasang nok sirap


6.34.1 Bahan
- Seng plat 3" x 6" BJLS 35 0.400 Lbr x Rp. 115,500 = Rp. 46,200.00
- Paku biasa ½" - 1" 0.060 Kg x Rp. 18,000 = Rp. 1,080.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 18,000 = Rp. 900.00
- Kayu papan tbl. 3 cm 0.004 M³ x Rp. 9,650,000 = Rp. 38,600.00
Jumlah (1) = Rp. 86,780.00
6.34.2 Tenaga
- Pekerja 0.125 Oh x Rp. 100,000 = Rp. 12,500.00
- Tukang Kayu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala Tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 54,800.00
Jumlah (1) + (2) = Rp. 141,580.00

PPA 6.35 1 M' Pasang atap seng gelombang


6.35.1 Bahan
- Seng gelombang 3" x 6" BJLS 30 0.700 Lbr x Rp. 59,640 = Rp. 41,748.00
- Paku seng 0.040 Kg x Rp. 25,000 = Rp. 1,000.00
Jumlah (1) = Rp. 42,748.00
6.35.2 Tenaga
- Pekerja 0.120 Oh x Rp. 100,000 = Rp. 12,000.00
- Tukang Kayu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala Tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 22,950.00
Jumlah (1) + (2) = Rp. 65,698.00
PPA. Hal. 7
PPA 6.36 1 M' Pasang atap nok seng

6.36.1 Bahan
- Seng plat 3" x 6" BJLS 35 0.300 Bh x Rp. 115,500 = Rp. 34,650.00
- Paku seng 0.020 Kg x Rp. 25,000 = Rp. 500.00
Jumlah (1) = Rp. 35,150.00
6.36.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang Kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 27,750.00
Jumlah (1) + (2) = Rp. 62,900.00

PPA 6.37 1 M' Pasang atap aluminium

6.37.1 Bahan
- Atap aluminium gelombang 0,55 1.050 Bh x Rp. 127,000 = Rp. 133,350.00
- Paku hak panjang 15 cm 0.020 Kg x Rp. 30,530 = Rp. 610.60
Jumlah (1) = Rp. 133,960.60
6.37.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang Kayu 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala Tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 28,500.00
Jumlah (1) + (2) = Rp. 162,460.60

PPA 6.38 1 M' Pasang nok aluminium

6.38.1 Bahan
- Nok standard 40 cm 18 SWG 22 1.200 Bh x Rp. 65,000 = Rp. 78,000.00
- Paku hak panjang 15 cm 0.040 Kg x Rp. 30,530 = Rp. 1,221.20
Jumlah (1) = Rp. 79,221.20
6.38.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang Kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala Tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 28,250.00
Jumlah (1) + (2) = Rp. 107,471.20

PPA 6.39 1 M² Pasang aluminium foil / sisalation

6.39.1 Bahan
- Sisalation / Aluminium foil 1.050 M² x Rp. 77,200 = Rp. 81,060.00
Jumlah (1) = Rp. 81,060.00
6.39.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang Kayu 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Kepala Tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.008 Oh x Rp. 175,000 = Rp. 1,400.00
Jumlah (2) = Rp. 24,650.00
Jumlah (1) + (2) = Rp. 105,710.00
PPA. Hal. 8
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PENUTUP LANTAI

PPL 6.1 1 M² Pasang lantai ubin granito ukuran 40 x 40 cm


6.1.1 Bahan
- Ubin granito 40 x 40 cm 6.930 Bh x Rp. 46,590 = Rp. 322,868.70
- Semen portland 9.800 Kg x Rp. 1,400 = Rp. 13,720.00
- Pasir pasang 0.0215 M³ x Rp. 265,000 = Rp. 5,697.50
- Semen warna 1.300 Kg x Rp. 5,000 = Rp. 6,500.00
Jumlah (1) = Rp. 348,786.20
6.1.2 Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 46,987.50
Jumlah (1) + (2) = Rp. 395,773.70

PPL 6.2 1 M² Pasang lantai ubin granito ukuran 30 x 30 cm

6.2.1 Bahan
- Ubin granito 30 x 30 cm 11.870 Bh x Rp. 26,260 = Rp. 311,706.20
- Semen portland 10.000 Kg x Rp. 1,400 = Rp. 14,000.00
- Pasir pasang 0.0215 M³ x Rp. 265,000 = Rp. 5,697.50
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 338,903.70
6.2.2 Tenaga
- Pekerja 0.260 Oh x Rp. 100,000 = Rp. 26,000.00
- Tukang batu 0.125 Oh x Rp. 150,000 = Rp. 18,750.00
- Kepala tukang 0.0125 Oh x Rp. 150,000 = Rp. 1,875.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 48,900.00
Jumlah (1) + (2) = Rp. 387,803.70

PPL 6.3 1 M² Pasang lantai ubin teralux marmer ukuran 60 x 60 cm

6.3.1 Bahan
- Ubin marmer 60 x 60 cm 2.780 Bh x Rp. 109,510 = Rp. 304,437.80
- Semen portland 8.190 Kg x Rp. 1,400 = Rp. 11,466.00
- Pasir pasang 0.0215 M³ x Rp. 265,000 = Rp. 5,697.50
- Semen warna 1.000 Kg x Rp. 5,000 = Rp. 5,000.00
Jumlah (1) = Rp. 326,601.30
6.3.2 Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang batu 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.0125 Oh x Rp. 175,000 = Rp. 2,187.50
Jumlah (2) = Rp. 46,987.50
Jumlah (1) + (2) = Rp. 373,588.80

PPL 6.4 1 M² Pasang lantai ubin teralux marmer ukuran 40 x 40 cm

6.4.1 Bahan
- ubin marmer 40 x 40 cm 6.250 Bh x Rp. 48,400 = Rp. 302,500.00
- Semen portland 8.800 Kg x Rp. 1,400 = Rp. 12,320.00
- Pasir pasang 0.0215 M³ x Rp. 265,000 = Rp. 5,697.50
- Semen warna 1.300 Kg x Rp. 5,000 = Rp. 6,500.00
Jumlah (1) = Rp. 327,017.50
6.4.2 Tenaga
- Pekerja 0.672 Oh x Rp. 100,000 = Rp. 67,200.00
- Tukang batu 0.224 Oh x Rp. 150,000 = Rp. 33,600.00
- Kepala tukang 0.022 Oh x Rp. 150,000 = Rp. 3,300.00
- Mandor 0.034 Oh x Rp. 175,000 = Rp. 5,950.00
Jumlah (2) = Rp. 110,050.00
Jumlah (1) + (2) = Rp. 437,067.50

PPL. Hal. 1
PPL 6.5 1 M² Pasang lantai ubin teralux marmer ukuran 30 x 30 cm

6.5.1 Bahan
- Ubin marmer 30 x 30 cm 11.870 Bh x Rp. 27,230 = Rp. 323,220.10
- Semen portland 10.000 Kg x Rp. 1,400 = Rp. 14,000.00
- Pasir pasang 0.0215 M³ x Rp. 265,000 = Rp. 5,697.50
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 350,417.60
6.5.2 Tenaga
- Pekerja 0.700 Oh x Rp. 100,000 = Rp. 70,000.00
- Tukang batu 0.340 Oh x Rp. 150,000 = Rp. 51,000.00
- Kepala tukang 0.034 Oh x Rp. 150,000 = Rp. 5,100.00
- Mandor 0.035 Oh x Rp. 175,000 = Rp. 6,125.00
Jumlah (2) = Rp. 132,225.00
Jumlah (1) + (2) = Rp. 482,642.60

PPL 6.6 1 M' Pasang plint ubin granito ukuran 10 x 40 cm

6.6.1 Bahan
- Plint ubin granito 10 x 40 cm 2.650 Bh x Rp. 62,800 = Rp. 166,420.00
- Semen portland 1.200 Kg x Rp. 1,400 = Rp. 1,680.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.100 Kg x Rp. 5,000 = Rp. 500.00
Jumlah (1) = Rp. 169,448.00
6.6.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.030 Oh x Rp. 150,000 = Rp. 4,500.00
- Kepala tukang 0.003 Oh x Rp. 150,000 = Rp. 450.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 65,475.00
Jumlah (1) + (2) = Rp. 234,923.00

PPL 6.7 1 M' Pasang plint ubin granito ukuran 10 x 30 cm

6.7.1 Bahan
- Plint ubin granito 10 x 30 cm 3.330 Bh x Rp. 27,950 = Rp. 93,073.50
- Semen portland 1.650 Kg x Rp. 1,400 = Rp. 2,310.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.100 Kg x Rp. 5,000 = Rp. 500.00
Jumlah (1) = Rp. 96,731.50
6.7.2 Tenaga
- Pekerja 0.900 Oh x Rp. 100,000 = Rp. 90,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 105,637.50
Jumlah (1) + (2) = Rp. 202,369.00

PPL 6.8 1 M' Pasang plint ubin teralux marmer ukuran 10 x 60 cm

6.8.1 Bahan
- Plint ubin marmer 10 x 60 cm 1.700 Bh x Rp. 65,700 = Rp. 111,690.00
- Semen portland 1.650 Kg x Rp. 1,400 = Rp. 2,310.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.100 Kg x Rp. 5,000 = Rp. 500.00
Jumlah (1) = Rp. 115,348.00

6.8.2 Tenaga
- Pekerja 0.900 Oh x Rp. 100,000 = Rp. 90,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 105,637.50
Jumlah (1) + (2) = Rp. 220,985.50

PPL. Hal. 2
PPL 6.9 1 M' Pasang plint ubin teralux marmer ukuran 10 x 40 cm
6.9.1 Bahan
- Plint ubin marmer 10 x 40 cm 2.500 Bh x Rp. 29,040 = Rp. 72,600.00
- Semen portland 1.650 Kg x Rp. 1,400 = Rp. 2,310.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.100 Kg x Rp. 5,000 = Rp. 500.00
Jumlah (1) = Rp. 76,258.00

6.9.2 Tenaga
- Pekerja 0.900 Oh x Rp. 100,000 = Rp. 90,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 105,637.50
Jumlah (1) + (2) = Rp. 181,895.50

PPL 6.10 1 M' Pasang plint ubin teralux marmer ukuran 10 x 30 cm


6.10.1 Bahan
- Plint ubin marmer 10 x 30 cm 3.330 Bh x Rp. 16,340 = Rp. 54,412.20
- Semen portland 1.650 Kg x Rp. 1,400 = Rp. 2,310.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.100 Kg x Rp. 5,000 = Rp. 500.00
Jumlah (1) = Rp. 58,070.20

6.10.2 Tenaga
- Pekerja 0.900 Oh x Rp. 100,000 = Rp. 90,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 105,637.50
Jumlah (1) + (2) = Rp. 163,707.70

PPL 6.11 1 M² Pasang lantai keramik artistik 10 x 20 cm


6.11.1 Bahan
- Keramik artistik 10 x 20 cm 50.000 Bh x Rp. 1,760 = Rp. 88,000.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 122,562.00

6.11.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 247,562.00

PPL 6.12 1 M² Pasang lantai keramik artistik 10 x 10 cm


6.12.1 Bahan
- Keramik artistik 10 x 10 cm 50.000 Bh x Rp. 910 = Rp. 45,500.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 2.000 Kg x Rp. 5,000 = Rp. 10,000.00
Jumlah (1) = Rp. 82,562.00

6.12.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 207,562.00

PPL. Hal. 3
PPL 6.13 1 M² Pasang lantai keramik artistik ukuran 5 x 20 cm

6.13.1 Bahan
- Keramik artistik 5 x 20 cm 100.000 Bh x Rp. 910 = Rp. 91,000.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 125,562.00
6.13.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 250,562.00

PPL 6.14 1 M' Pasang plint keramik artistik ukuran 10 x 20 cm

6.14.1 Bahan
- keramik artistik 10 x 20 cm 5.000 Bh x Rp. 1,760 = Rp. 8,800.00
- Semen portland 1.650 Kg x Rp. 1,400 = Rp. 2,310.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.100 Kg x Rp. 5,000 = Rp. 500.00
Jumlah (1) = Rp. 12,458.00
6.14.2 Tenaga
- Pekerja 0.090 Oh x Rp. 100,000 = Rp. 9,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 24,637.50
Jumlah (1) + (2) = Rp. 37,095.50

PPL 6.15 1 M' Pasang plint keramik artistik ukuran 10 x 10 cm

6.15.1 Bahan
- keramik artistik 10 x 10 cm 10.000 Bh x Rp. 910 = Rp. 9,100.00
- Semen portland 1.650 Kg x Rp. 1,400 = Rp. 2,310.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.120 Kg x Rp. 5,000 = Rp. 600.00
Jumlah (1) = Rp. 12,858.00

6.15.2 Tenaga
- Pekerja 0.090 Oh x Rp. 100,000 = Rp. 9,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 24,637.50
Jumlah (1) + (2) = Rp. 37,495.50

PPL 6.16.A 1 M' Pasang plint keramik ukuran 10 x 20 cm

6.16.1 Bahan
- Keramik 10 x 20 cm 5.000 Bh x Rp. 1,210 = Rp. 6,050.00
- Semen portland 0.850 Kg x Rp. 1,400 = Rp. 1,190.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.080 Kg x Rp. 5,000 = Rp. 400.00
Jumlah (1) = Rp. 8,488.00
6.16.2 Tenaga
- Pekerja 0.090 Oh x Rp. 100,000 = Rp. 9,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 24,637.50
Jumlah (1) + (2) = Rp. 33,125.50

PPL. Hal. 4
PPL 6.16.B 1 M' Pasang plint keramik ukuran 10 x 30 cm

6.16.1 Bahan
- Keramik 10 x 30 cm 3.340 Bh x Rp. 4,110 = Rp. 13,727.40
- Semen portland 0.850 Kg x Rp. 1,400 = Rp. 1,190.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.080 Kg x Rp. 5,000 = Rp. 400.00
Jumlah (1) = Rp. 16,165.40

6.16.2 Tenaga
- Pekerja 0.090 Oh x Rp. 100,000 = Rp. 9,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 24,637.50
Jumlah (1) + (2) = Rp. 40,802.90

PPL 6.16.C 1 M' Pasang plint keramik ukuran 10 x 40 cm

6.16.1 Bahan
- Keramik 10 x 40 cm 2.500 Bh x Rp. 5,690 = Rp. 14,225.00
- Semen portland 0.850 Kg x Rp. 1,400 = Rp. 1,190.00
- Pasir pasang 0.0032 M³ x Rp. 265,000 = Rp. 848.00
- Semen warna 0.080 Kg x Rp. 5,000 = Rp. 400.00
Jumlah (1) = Rp. 16,663.00

6.16.2 Tenaga
- Pekerja 0.090 Oh x Rp. 100,000 = Rp. 9,000.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0045 Oh x Rp. 175,000 = Rp. 787.50
Jumlah (2) = Rp. 24,637.50
Jumlah (1) + (2) = Rp. 41,300.50

PPL 6.17 1 M' Pasang plint vinyil tanpa adukan

6.17.1 Bahan
- Vinyl 30 x 30 cm 3.500 Bh x Rp. 8,230 = Rp. 28,805.00
- Lem vinyl 0.080 Kg x Rp. 44,900 = Rp. 3,592.00
Jumlah (1) = Rp. 32,397.00
6.17.2 Tenaga
- Pekerja 0.080 Oh x Rp. 100,000 = Rp. 8,000.00
- Tukang batu 0.080 Oh x Rp. 150,000 = Rp. 12,000.00
- Kepala tukang 0.008 Oh x Rp. 150,000 = Rp. 1,200.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 21,900.00
Jumlah (1) + (2) = Rp. 54,297.00

PPL 6.18 1 M² Pasang lantai keramik 10 x 20 cm

6.18.1 Bahan
- Ubin keramik 10 x 20 cm 50.000 Bh x Rp. 1,210 = Rp. 60,500.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 95,062.00
6.18.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 220,062.00
PPL. Hal. 5
PPL 6.19 1 M² Pasang lantai keramik 15 x 15 cm
6.19.1 Bahan
- Ubin keramik 15 x 15 cm 44.000 Bh x Rp. 1,400 = Rp. 61,600.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 96,162.00
6.19.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 221,162.00

PPL 6.20 1 M² Pasang lantai keramik 20 x 20 cm


6.20.1 Bahan
- Ubin keramik 20 x 20 cm 25.000 Bh x Rp. 2,490 = Rp. 62,250.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 96,812.00

6.20.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 221,812.00

PPL 6.21 1 M² Pasang lantai keramik 20 x 25 cm


6.21.1 Bahan
- Ubin keramik 20 x 25 cm 20.000 Bh x Rp. 3,150 = Rp. 63,000.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 97,562.00

6.21.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 222,562.00

PPL 6.22 1 M² Pasang lantai keramik 25 x 25 cm


6.22.1 Bahan
- Ubin keramik 25 x 25 cm 16.000 Bh x Rp. 3,870 = Rp. 61,920.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 96,482.00

6.22.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 221,482.00
PPL. Hal. 6
PPL 6.23 1 M² Pasang lantai keramik 30 x 30 cm

6.23.1 Bahan
- Ubin keramik 30 x 30 cm 11.120 Bh x Rp. 5,570 = Rp. 61,938.40
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 96,500.40
6.23.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 221,500.40

PPL 6.24 1 M² Pasang lantai keramik 30 x 30 cm anti slip

6.24.1 Bahan
- Ubin keramik 30 x 30 cm anti slip 11.120 Bh x Rp. 6,290 = Rp. 69,944.80
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 104,506.80
6.24.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 229,506.80

PPL 6.25 1 M² Pasang lantai keramik 40 x 40 cm

6.25.1 Bahan
- Ubin keramik 40 x 40 cm 6.250 Bh x Rp. 9,680 = Rp. 60,500.00
- Semen portland 11.380 Kg x Rp. 1,400 = Rp. 15,932.00
- Pasir pasang 0.042 M³ x Rp. 265,000 = Rp. 11,130.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 95,062.00
6.25.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 220,062.00

PPL 6.26 1 M² Pasang lantai mosaik 30 x 30 cm, ex lokal

6.26.1 Bahan
- Mosaik 30 x 30 cm 12.000 Bh x Rp. 13,920 = Rp. 167,040.00
- Semen portland 14.150 Kg x Rp. 1,400 = Rp. 19,810.00
- Pasir pasang 0.039 M³ x Rp. 265,000 = Rp. 10,335.00
- Semen warna 2.000 Kg x Rp. 5,000 = Rp. 10,000.00
Jumlah (1) = Rp. 207,185.00
6.26.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 332,185.00
PPL. Hal. 7
PPL 6.27 1 M² Pasang lantai marmer

6.27.1 Bahan
- Marmer 1.052 Bh x Rp. 261,970 = Rp. 275,592.44
- Semen portland 14.150 Kg x Rp. 1,400 = Rp. 19,810.00
- Pasir pasang 0.039 M³ x Rp. 265,000 = Rp. 10,335.00
- Semen warna 2.000 Kg x Rp. 5,000 = Rp. 10,000.00
Jumlah (1) = Rp. 315,737.44
6.27.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 440,737.44

PPL 6.28 1 M² Pasang lantai karpet 100% wool

6.28.1 Bahan
- Karpet wool 1.050 M² x Rp. 85,250 = Rp. 89,512.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 105,227.50
6.28.2 Tenaga
- Pekerja 0.170 Oh x Rp. 100,000 = Rp. 17,000.00
- Tukang 0.170 Oh x Rp. 150,000 = Rp. 25,500.00
- Kepala tukang 0.017 Oh x Rp. 150,000 = Rp. 2,550.00
- Mandor 0.0085 Oh x Rp. 175,000 = Rp. 1,487.50
Jumlah (2) = Rp. 46,537.50
Jumlah (1) + (2) = Rp. 151,765.00

PPL 6.29 1 M² Pasang lantai karpet 80% wool, 20% nylon

6.29.1 Bahan
- Karpet wool + nylon 1.050 M² x Rp. 87,450 = Rp. 91,822.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 107,537.50

6.29.2 Tenaga
- Pekerja 0.170 Oh x Rp. 100,000 = Rp. 17,000.00
- Tukang 0.170 Oh x Rp. 150,000 = Rp. 25,500.00
- Kepala tukang 0.017 Oh x Rp. 150,000 = Rp. 2,550.00
- Mandor 0.0085 Oh x Rp. 175,000 = Rp. 1,487.50
Jumlah (2) = Rp. 46,537.50
Jumlah (1) + (2) = Rp. 154,075.00

PPL 6.30 1 M² Pasang lantai karpet

6.30.1 Bahan
- Carpet 1.050 M² x Rp. 90,750 = Rp. 95,287.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 111,002.50
6.30.2 Tenaga
- Pekerja 0.170 Oh x Rp. 100,000 = Rp. 17,000.00
- Tukang 0.170 Oh x Rp. 150,000 = Rp. 25,500.00
- Kepala tukang 0.017 Oh x Rp. 150,000 = Rp. 2,550.00
- Mandor 0.0085 Oh x Rp. 175,000 = Rp. 1,487.50
Jumlah (2) = Rp. 46,537.50
Jumlah (1) + (2) = Rp. 157,540.00
PPL. Hal. 8
PPL 6.31 1 M² Pasang lantai parquet jati

6.31.1 Bahan
- Perquet jati 1.050 M² x Rp. 368,500 = Rp. 386,925.00
- Lem vinyl 0.600 Kg x Rp. 44,900 = Rp. 26,940.00
Jumlah (1) = Rp. 413,865.00
6.31.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp. 65,000.00
- Tukang 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.0325 Oh x Rp. 175,000 = Rp. 5,687.50
Jumlah (2) = Rp. 128,437.50
Jumlah (1) + (2) = Rp. 542,302.50

PPL 6.32 1 M² Pasang dinding porselin 11 x 11 cm, putih

6.32.1 Bahan
- Porselin 11 x 11 cm 83.000 Bh x Rp. 1,210 = Rp. 100,430.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 125,720.00

6.32.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 149,750.00
Jumlah (1) + (2) = Rp. 275,470.00

PPL 6.33 1 M² Pasang dinding porselin 11 x 11 cm, warna

6.33.1 Bahan
- Porselin 11 x 11 cm warna 83.000 Bh x Rp. 145 = Rp. 12,035.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 37,325.00

6.33.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 149,750.00
Jumlah (1) + (2) = Rp. 187,075.00

PPL 6.34 1 M² Pasang dinding porselin 15 x 15 cm, putih

6.34.1 Bahan
- Porselin 15 x 15 cm putih 45.000 Bh x Rp. 2,300 = Rp. 103,500.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 128,790.00
6.34.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 268,290.00

PPL. Hal. 9
PPL 6.35 1 M² Pasang dinding porselin 15 x 15 cm, warna

6.35.1 Bahan
- Porselin 15 x 15 cm warna 45.000 Bh x Rp. 2,540 = Rp. 114,300.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 139,590.00
6.35.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 279,090.00

PPL 6.36 1 M² Pasang dinding keramik artistik 10 x 20 cm

6.36.1 Bahan
- Keramik artistik 10 x 20 cm 100.000 Bh x Rp. 1,760 = Rp. 176,000.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 201,290.00

6.36.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 340,790.00

PPL 6.37 1 M² Pasang dinding keramik artistik 5 x 20 cm

6.37.1 Bahan
- Keramik artistik 5 x 20 cm 100.000 Bh x Rp. 910 = Rp. 91,000.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 116,290.00
6.37.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 255,790.00

PPL 6.38 1 M² Pasang dinding keramik 10 x 20 cm

6.38.1 Bahan
- Keramik 10 x 20 cm 50.000 Bh x Rp. 1,210 = Rp. 60,500.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 85,790.00
6.38.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 225,290.00

PPL. Hal. 10
PPL 6.39 1 M² Pasang dinding keramik 15 x 15 cm

6.39.1 Bahan
- Keramik 15 x 15 cm 45.000 Bh x Rp. 1,400 = Rp. 63,000.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 88,290.00
6.39.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 227,790.00

PPL 6.40 1 M² Pasang dinding keramik 20 x 20 cm

6.40.1 Bahan
- Keramik 20 x 20 cm 25.000 Bh x Rp. 2,490 = Rp. 62,250.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 87,540.00
6.40.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.045 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 87,000.00
Jumlah (1) + (2) = Rp. 174,540.00

PPL 6.41 1 M² Pasang dinding keramik 20 x 25 cm

6.41.1 Bahan
- Keramik 20 x 25 cm 20.000 Bh x Rp. 3,150 = Rp. 63,000.00
- Semen portland 9.300 Kg x Rp. 1,400 = Rp. 13,020.00
- Pasir pasang 0.018 M³ x Rp. 265,000 = Rp. 4,770.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 88,290.00
6.41.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang batu 0.450 Oh x Rp. 150,000 = Rp. 67,500.00
- Kepala tukang 0.0450 Oh x Rp. 150,000 = Rp. 6,750.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 139,500.00
Jumlah (1) + (2) = Rp. 227,790.00

PPL 6.42 1 M² Pasang dinding marmer

6.42.1 Bahan
- Marmer 1.020 M² x Rp. 261,970 = Rp. 267,209.40
- Paku pancing 2.000 Bh x Rp. 720 = Rp. 1,440.00
- Semen portland 12.440 Kg x Rp. 1,400 = Rp. 17,416.00
- Pasir pasang 0.025 M³ x Rp. 265,000 = Rp. 6,625.00
- Semen warna 1.500 Kg x Rp. 5,000 = Rp. 7,500.00
Jumlah (1) = Rp. 300,190.40
6.42.2 Tenaga
- Pekerja 0.720 Oh x Rp. 100,000 = Rp. 72,000.00
- Tukang batu 0.650 Oh x Rp. 150,000 = Rp. 97,500.00
- Kepala tukang 0.065 Oh x Rp. 150,000 = Rp. 9,750.00
- Mandor 0.035 Oh x Rp. 175,000 = Rp. 6,125.00
Jumlah (2) = Rp. 185,375.00
Jumlah (1) + (2) = Rp. 485,565.40

PPL. Hal. 11
PPL 6.43 1 M² Pasang dinding bata pelapis 7 x 3 x 20 cm

6.43.1 Bahan
- Bata pelapis dinding 60.000 Bh x Rp. 2,040 = Rp. 122,400.00
- Semen portland 12.440 Kg x Rp. 1,400 = Rp. 17,416.00
- Pasir pasang 0.025 M³ x Rp. 265,000 = Rp. 6,625.00
Jumlah (1) = Rp. 146,441.00
6.43.2 Tenaga
- Pekerja 0.650 Oh x Rp. 100,000 = Rp. 65,000.00
- Tukang batu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 152,750.00
Jumlah (1) + (2) = Rp. 299,191.00

PPL 6.44 1 M² Pasang dinding batu poros

6.44.1 Bahan
- Batu poros 1.050 M² x Rp. 114,680 = Rp. 120,414.00
- Semen portland 11.750 Kg x Rp. 1,400 = Rp. 16,450.00
- Pasir pasang 0.035 M³ x Rp. 265,000 = Rp. 9,275.00
Jumlah (1) = Rp. 146,139.00
6.44.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 271,139.00

PPL 6.45 1 M² Pasang dinding batu tempel hitam

6.45.1 Bahan
- Batu tempel hitam 1.050 M² x Rp. 104,500 = Rp. 109,725.00
- Semen portland 11.750 Kg x Rp. 1,400 = Rp. 16,450.00
- Pasir pasang 0.035 M³ x Rp. 265,000 = Rp. 9,275.00
Jumlah (1) = Rp. 135,450.00
6.45.2 Tenaga
- Pekerja 0.620 Oh x Rp. 100,000 = Rp. 62,000.00
- Tukang batu 0.350 Oh x Rp. 150,000 = Rp. 52,500.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.030 Oh x Rp. 175,000 = Rp. 5,250.00
Jumlah (2) = Rp. 125,000.00
Jumlah (1) + (2) = Rp. 260,450.00

PPL 6.46 1 M² Pasang lantai vinyl karet 30 x 30 cm KL I

6.46.1 Bahan
- Vinyl karet 11.050 Bh x Rp. 9,800 = Rp. 108,290.00
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 124,005.00
6.46.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 41,062.50
Jumlah (1) + (2) = Rp. 165,067.50
PPL. Hal. 12
PPL 6.47 1 M² Pasang lantai vinyl karet 30 x 30 cm KL II
6.47.1 Bahan
- Vinyl karet 11.050 Bh x Rp. 9,080 = Rp. 100,334.00
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 116,049.00
6.47.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 41,062.50
Jumlah (1) + (2) = Rp. 157,111.50

PPL 6.48 1 M² Pasang lantai vinyl asbes 30 x 30 cm


6.48.1 Bahan
- Vinyl asbes 30 x 30 cm 11.050 Bh x Rp. 8,230 = Rp. 90,941.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 106,656.50
6.48.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 41,062.50
Jumlah (1) + (2) = Rp. 147,719.00

PPL 6.49 1 M² Pasang lantai vinyl motif kembang 30 x 30 cm


6.49.1 Bahan
- Vinyl motif kembang 11.050 Bh x Rp. 9,440 = Rp. 104,312.00
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 120,027.00
6.49.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang batu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 41,062.50
Jumlah (1) + (2) = Rp. 161,089.50

PPL 6.50 1 M² Pasang wall corvering lebar 50 cm


6.50.1 Bahan
- Corvering L.50 cm 1.100 M² x Rp. 63,250 = Rp. 69,575.00
- Lem 0.250 Kg x Rp. 44,900 = Rp. 11,225.00
Jumlah (1) = Rp. 80,800.00
6.50.2 Tenaga
- Pekerja 0.750 Oh x Rp. 100,000 = Rp. 75,000.00
- Tukang batu 0.170 Oh x Rp. 150,000 = Rp. 25,500.00
- Kepala tukang 0.017 Oh x Rp. 150,000 = Rp. 2,550.00
- Mandor 0.0085 Oh x Rp. 175,000 = Rp. 1,487.50
Jumlah (2) = Rp. 104,537.50
Jumlah (1) + (2) = Rp. 185,337.50

PPL 6.51 1 M² Plint kayu Jati 2 x 10 cm


6.51.1 Bahan
- Kayu jati papan 0.0024 M³ x Rp. 24,104,440 = Rp. 57,850.66
- Paku skrup 3,5" 0.050 Kg x Rp. 20,350 = Rp. 1,017.50
Jumlah (1) = Rp. 58,868.16
6.51.2 Tenaga
- Pekerja 0.120 Oh x Rp. 100,000 = Rp. 12,000.00
- Tukang kayu 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 32,850.00
Jumlah (1) + (2) = Rp. 91,718.16
PPL. Hal. 13
PPL 6.52. 1 M² Plint kayu Meranti batu 2 x 10 cm

6.52.1 Bahan
- Kayu meranti batu, papan 0.0024 M³ x Rp. 9,375,000 = Rp. 22,500.00
- Paku skrup 3,5" 0.050 Kg x Rp. 20,350 = Rp. 1,017.50
Jumlah (1) = Rp. 23,517.50
6.52.2 Tenaga
- Pekerja 0.120 Oh x Rp. 100,000 = Rp. 12,000.00
- Tukang kayu 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 32,850.00
Jumlah (1) + (2) = Rp. 56,367.50
PPL. Hal. 14
ANALISA BIAYA KONSTRUKSI
PEKERJAAN KUNCI DAN KACA

PKK 6.1 1 buah pasang kunci tanam antik


6.1.1 Bahan
- Kunci tanam antik 1.000 Bh x Rp. 214,500 = Rp. 214,500.00
Jumlah (1) = Rp. 214,500.00
6.1.2 Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang Kayu 0.600 Oh x Rp. 150,000 = Rp. 90,000.00
- Kepala Tukang 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 105,525.00
Jumlah (1) + (2) = Rp. 320,025.00

PKK 6.2 1 buah pasang kunci tanam biasa


6.2.1 Bahan
- Kunci tanam biasa 1.000 Bh x Rp. 195,000 = Rp. 195,000.00
Jumlah (1) = Rp. 195,000.00
6.1.2 Tenaga
- Pekerja 0.010 Oh x Rp. 100,000 = Rp. 1,000.00
- Tukang Kayu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala Tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 78,375.00
Jumlah (1) + (2) = Rp. 273,375.00

PKK 6.3 1 buah pasang kunci tanam kamar mandi


6.3.1 Bahan
- Kunci tanam kamar mandi 1.000 Bh x Rp. 54,690 = Rp. 54,690.00
Jumlah (1) = Rp. 54,690.00
6.3.2 Tenaga
- Pekerja 0.005 Oh x Rp. 100,000 = Rp. 500.00
- Tukang Kayu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala Tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 76,687.50
Jumlah (1) + (2) = Rp. 131,377.50

PKK 6.4 1 buah pasang kunci silinder


6.4.1 Bahan
- Kunci silinder 1.000 Bh x Rp. 34,490 = Rp. 34,490.00
Jumlah (1) = Rp. 34,490.00
6.4.2 Tenaga
- Pekerja 0.005 Oh x Rp. 100,000 = Rp. 500.00
- Tukang Kayu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala Tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.00025 Oh x Rp. 175,000 = Rp. 43.75
Jumlah (2) = Rp. 76,293.75
Jumlah (1) + (2) = Rp. 110,783.75

PKK 6.5 1 buah pasang engsel pintu


6.5.1 Bahan
- engsel pintu 1.000 Bh x Rp. 35,000 = Rp. 35,000.00
Jumlah (1) = Rp. 35,000.00
6.5.2 Tenaga
- Pekerja 0.015 Oh x Rp. 100,000 = Rp. 1,500.00
- Tukang Kayu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala Tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 26,381.25
Jumlah (1) + (2) = Rp. 61,381.25
PPK. Hal. 1
PKK 6.6 1 buah pasang engsel jendela kupu-kupu

6.6.1 Bahan
- Engsel jendela 1.000 Bh x Rp. 17,500 = Rp. 17,500.00
Jumlah (1) = Rp. 17,500.00
6.6.2 Tenaga
- Pekerja 0.010 Oh x Rp. 100,000 = Rp. 1,000.00
- Tukang Kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala Tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0005 Oh x Rp. 175,000 = Rp. 87.50
Jumlah (2) = Rp. 17,587.50
Jumlah (1) + (2) = Rp. 35,087.50

PKK 6.7 1 buah pasang engsel angin

6.7.1 Bahan
- Engsel angin 1.000 Bh x Rp. 25,050 = Rp. 25,050.00
Jumlah (1) = Rp. 25,050.00
6.7.2 Tenaga
- Pekerja 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Tukang Kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala Tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 36,750.00
Jumlah (1) + (2) = Rp. 61,800.00

PKK 6.8 1 buah pasang spring knip

6.8.1 Bahan
- Spring knip 1.000 Bh x Rp. 9,080 = Rp. 9,080.00
Jumlah (1) = Rp. 9,080.00
6.8.2 Tenaga
- Pekerja 0.015 Oh x Rp. 100,000 = Rp. 1,500.00
- Tukang Kayu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala Tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 26,381.25
Jumlah (1) + (2) = Rp. 35,461.25

PKK 6.9 1 buah pasang kait angin

6.9.1 Bahan
- Kait angin 1.000 Bh x Rp. 25,000 = Rp. 25,000.00
Jumlah (1) = Rp. 25,000.00
6.9.2 Tenaga
- Pekerja 0.015 Oh x Rp. 100,000 = Rp. 1,500.00
- Tukang Kayu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala Tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 26,381.25
Jumlah (1) + (2) = Rp. 51,381.25

PKK 6.10 1 buah pasang door closer

6.10.1 Bahan
- Door closer 1.000 Bh x Rp. 109,750 = Rp. 109,750.00
Jumlah (1) = Rp. 109,750.00
6.10.2 Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Tukang Kayu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala Tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 87,937.50
Jumlah (1) + (2) = Rp. 197,687.50
PPK. Hal. 2
PKK 6.11 1 buah pasang kunci selot

6.11.1 Bahan
- Kunci selot 1.000 Bh x Rp. 27,230 = Rp. 27,230.00
Jumlah (1) = Rp. 27,230.00
6.11.2 Tenaga
- Pekerja 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Tukang Kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala Tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.001 Oh x Rp. 175,000 = Rp. 175.00
Jumlah (2) = Rp. 35,175.00
Jumlah (1) + (2) = Rp. 62,405.00

PKK 6.12 1 buah pasang pegangan pintu / door holder

6.12.1 Bahan
- Pegangan pintu / door holder 1.000 Bh x Rp. 113,010 = Rp. 113,010.00
Jumlah (1) = Rp. 113,010.00
6.12.2 Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Tukang Kayu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala Tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 87,937.50
Jumlah (1) + (2) = Rp. 200,947.50

PKK 6.13 1 buah pasang door stop

6.13.1 Bahan
- Door stop 1.000 Bh x Rp. 38,120 = Rp. 38,120.00
Jumlah (1) = Rp. 38,120.00
6.13.2 Tenaga
- Pekerja 0.010 Oh x Rp. 100,000 = Rp. 1,000.00
- Tukang Kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala Tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0005 Oh x Rp. 175,000 = Rp. 87.50
Jumlah (2) = Rp. 17,587.50
Jumlah (1) + (2) = Rp. 55,707.50

PKK 6.14 1 buah pasang rel pintu dorong

6.14.1 Bahan
- Rel pintu dorong 1.000 Bh x Rp. 160,330 = Rp. 160,330.00
Jumlah (1) = Rp. 160,330.00
6.14.2 Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang Kayu 0.600 Oh x Rp. 150,000 = Rp. 90,000.00
- Kepala Tukang 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 105,525.00
Jumlah (1) + (2) = Rp. 265,855.00

PKK 6.15 1 buah pasang kunci lemari

6.15.1 Bahan
- Kunci lemari 1.000 Bh x Rp. 12,340 = Rp. 12,340.00
Jumlah (1) = Rp. 12,340.00
6.15.2 Tenaga
- Pekerja 0.025 Oh x Rp. 100,000 = Rp. 2,500.00
- Tukang Kayu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala Tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.00125 Oh x Rp. 175,000 = Rp. 218.75
Jumlah (2) = Rp. 43,968.75
Jumlah (1) + (2) = Rp. 56,308.75
PPK. Hal. 3
PKK 6.16 1 M² pasang kaca, tebal 3 mm

6.16.1 Bahan
- Kaca 1.100 M² x Rp. 87,120 = Rp. 95,832.00
Jumlah (1) = Rp. 95,832.00
6.16.2 Tenaga
- Pekerja 0.015 Oh x Rp. 100,000 = Rp. 1,500.00
- Tukang Kayu 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Kepala Tukang 0.015 Oh x Rp. 150,000 = Rp. 2,250.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 26,381.25
Jumlah (1) + (2) = Rp. 122,213.25

PKK 6.17 1 M² pasang kaca, tebal 5 mm

6.17.1 Bahan
- Kaca 1.100 M² x Rp. 175,000 = Rp. 192,500.00
Jumlah (1) = Rp. 192,500.00
6.17.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 100,000 = Rp. 1,550.00
- Tukang Kayu 0.1550 Oh x Rp. 150,000 = Rp. 23,250.00
- Kepala Tukang 0.0155 Oh x Rp. 150,000 = Rp. 2,325.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 27,256.25
Jumlah (1) + (2) = Rp. 219,756.25

PKK 6.18 1 M² pasang kaca, tebal 8 mm

6.18.1 Bahan
- Kaca polos 1.100 M² x Rp. 232,320 = Rp. 255,552.00
Jumlah (1) = Rp. 255,552.00
6.18.2 Tenaga
- Pekerja 0.0165 Oh x Rp. 100,000 = Rp. 1,650.00
- Tukang Kayu 0.165 Oh x Rp. 150,000 = Rp. 24,750.00
- Kepala Tukang 0.0165 Oh x Rp. 150,000 = Rp. 2,475.00
- Mandor 0.0008 Oh x Rp. 175,000 = Rp. 140.00
Jumlah (2) = Rp. 29,015.00
Jumlah (1) + (2) = Rp. 284,567.00

PKK 6.19 1 M² pasang kaca buram, tebal 5 mm

6.19.1 Bahan
- Kaca buram 1.100 M² x Rp. 111,320 = Rp. 122,452.00
- Sealent 0.050 Kg x Rp. 39,330 = Rp. 1,966.50
Jumlah (1) = Rp. 124,418.50
6.19.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 100,000 = Rp. 1,550.00
- Tukang Kayu 0.1550 Oh x Rp. 150,000 = Rp. 23,250.00
- Kepala Tukang 0.0155 Oh x Rp. 150,000 = Rp. 2,325.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 27,256.25
Jumlah (1) + (2) = Rp. 151,674.75

PKK 6.20 1 M² pasang kaca cermin, tebal 5 mm

6.20.1 Bahan
- Kaca cermin 1.100 M² x Rp. 161,700 = Rp. 177,870.00
Jumlah (1) = Rp. 177,870.00
6.20.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 100,000 = Rp. 1,550.00
- Tukang Kayu 0.1550 Oh x Rp. 150,000 = Rp. 23,250.00
- Kepala Tukang 0.0155 Oh x Rp. 150,000 = Rp. 2,325.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 27,256.25
Jumlah (1) + (2) = Rp. 205,126.25

PPK. Hal. 4
PKK 6.21 1 M² pasang kaca cermin, tebal 8 mm

6.21.1 Bahan
- Kaca cermin 1.100 M² x Rp. 258,720 = Rp. 284,592.00
Jumlah (1) = Rp. 284,592.00
6.21.2 Tenaga
- Pekerja 0.0165 Oh x Rp. 100,000 = Rp. 1,650.00
- Tukang Kayu 0.165 Oh x Rp. 150,000 = Rp. 24,750.00
- Kepala Tukang 0.0165 Oh x Rp. 150,000 = Rp. 2,475.00
- Mandor 0.0008 Oh x Rp. 175,000 = Rp. 140.00
Jumlah (2) = Rp. 29,015.00
Jumlah (1) + (2) = Rp. 313,607.00

PKK 6.22 1 M² pasang kaca "wireglass" , tebal 5 mm

6.22.1 Bahan
- Kaca wireglass 1.100 M² x Rp. 151,250 = Rp. 166,375.00
Jumlah (1) = Rp. 166,375.00
6.22.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 100,000 = Rp. 1,550.00
- Tukang Kayu 0.1550 Oh x Rp. 150,000 = Rp. 23,250.00
- Kepala Tukang 0.0155 Oh x Rp. 150,000 = Rp. 2,325.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 27,256.25
Jumlah (1) + (2) = Rp. 193,631.25

PKK 6.23 1 M² pasang kaca patri, tebal 5 mm

6.23.1 Bahan
- Kaca patri 1.100 M² x Rp. 169,400 = Rp. 186,340.00
Jumlah (1) = Rp. 186,340.00
6.23.2 Tenaga
- Pekerja 0.0250 Oh x Rp. 100,000 = Rp. 2,500.00
- Tukang Kayu 0.2500 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala Tukang 0.0250 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.00125 Oh x Rp. 175,000 = Rp. 218.75
Jumlah (2) = Rp. 43,968.75
Jumlah (1) + (2) = Rp. 230,308.75

PKK 6.24. 1 M² pasang kaca Reyben, tebal 5 mm

6.24.1 Bahan
- Kaca reyben 1.100 M² x Rp. 225,000 = Rp. 247,500.00
Jumlah (1) = Rp. 247,500.00
6.24.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 100,000 = Rp. 1,550.00
- Tukang Kayu 0.1550 Oh x Rp. 150,000 = Rp. 23,250.00
- Kepala Tukang 0.0155 Oh x Rp. 150,000 = Rp. 2,325.00
- Mandor 0.00075 Oh x Rp. 175,000 = Rp. 131.25
Jumlah (2) = Rp. 27,256.25
Jumlah (1) + (2) = Rp. 274,756.25
PPK. Hal. 5
ANALISA BIAYA KONTRUKSI
PEKERJAAN PENGECATAN

PC 6.1 1M² Mengikis/ mengerok permukaan cat tembok lama


6.1.1 Bahan
- Soda api 0.050 Kg x Rp. 12,100 = Rp. 605.00
Jumlah (1) = Rp. 605.00
6.1.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 15,437.50
Jumlah (1) + (2) = Rp. 16,042.50

PC 6.2. 1M² Mencuci bidang permukaan tembok yang pernah di cat


6.2.1 Bahan
- Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50
Jumlah (1) = Rp. 514.50
6.2.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 15,437.50
Jumlah (1) + (2) = Rp. 15,952.00

PC 6.3. 1M² Mengerok karat cat lama permukaan baja dengan cara manual
6.3 .1 Bahan
- Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50
Jumlah (1) = Rp. 514.50
6.3.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 15,437.50
Jumlah (1) + (2) = Rp. 15,952.00

PC 6.4 1M² Menyabun permukaan tembok lama


6.4 .1 Bahan
- Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50
Jumlah (1) = Rp. 514.50
6.4.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 15,437.50
Jumlah (1) + (2) = Rp. 15,952.00

PC 6.5 1M² Mendempul dan menggosok kayu


6.5 .1 Bahan
- Dempul jadi 0.080 Kg x Rp. 15,000 = Rp. 1,200.00
- Minyak cat 0.020 Kg x Rp. 11,010 = Rp. 220.20
- Amplas 0.100 Lbr x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 1,670.20
6.5.2 Tenaga
- Pekerja 0.040 Oh x Rp. 100,000 = Rp. 4,000.00
- Tukang cat 0.040 Oh x Rp. 150,000 = Rp. 6,000.00
- Kepala tukang 0.040 Oh x Rp. 150,000 = Rp. 6,000.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 16,437.50
Jumlah (1) + (2) = Rp. 18,107.70
PC. Hal. 1
PC 6.6 1M² Pengecatan bidang kayu lama
6.6.1 Bahan
- Plamir 0.150 Kg x Rp. 17,500 = Rp. 2,625.00
- Minyak Cat 0.170 Kg x Rp. 11,010 = Rp. 1,871.70
- Cat Minyak 0.170 Kg x Rp. 35,700 = Rp. 6,069.00
Jumlah (1) = Rp. 10,565.70
6.6.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang cat 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Kepala tukang 0.0075 Oh x Rp. 150,000 = Rp. 1,125.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 19,812.50
Jumlah (1) + (2) = Rp. 30,378.20

PC 6.7 1M² Pengecatan bidang kayu baru 1 lps plamir, 1 lps cat dasar, 2 lps cat minyak
6.7.1 Bahan
- Cat menie kayu 0.200 Kg x Rp. 20,570 = Rp. 4,114.00
- Plamir 0.150 Kg x Rp. 17,500 = Rp. 2,625.00
- Cat dasar 0.170 Kg x Rp. 17,500 = Rp. 2,975.00
- Cat Minyak 0.260 Kg x Rp. 35,700 = Rp. 9,282.00
Jumlah (1) = Rp. 18,996.00
6.7.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang cat 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.0090 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 22,287.50
Jumlah (1) + (2) = Rp. 41,283.50

PC 6.8 1M² Pengecatan bidang kayu baru 1 lps plamir, 1 lps cat dasar, 3lps cat minyak
6.8.1 Bahan
- Cat menie kayu 0.200 Kg x Rp. 20,570 = Rp. 4,114.00
- Plamir 0.150 Kg x Rp. 17,500 = Rp. 2,625.00
- Minyak Cat 0.170 Kg x Rp. 11,010 = Rp. 1,871.70
- Cat Minyak 0.350 Kg x Rp. 35,700 = Rp. 12,495.00
Jumlah (1) = Rp. 21,105.70
6.8.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang cat 0.105 Oh x Rp. 150,000 = Rp. 15,750.00
- Kepala tukang 0.0105 Oh x Rp. 150,000 = Rp. 1,575.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 24,762.50
Jumlah (1) + (2) = Rp. 45,868.20

PC 6.9 1M² Peleburan kayu dengan politur


6.9.1 Bahan
- Minyak politur 0.150 Kg x Rp. 11,010 = Rp. 1,651.50
- Politur Jadi / vernis 0.372 Kg x Rp. 48,280 = Rp. 17,960.16
- Amplas 2.000 Kg x Rp. 2,500 = Rp. 5,000.00
Jumlah (1) = Rp. 24,611.66
6.9.2 Tenaga
- Pekerja 0.040 Oh x Rp. 100,000 = Rp. 4,000.00
- Tukang cat 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.0160 Oh x Rp. 150,000 = Rp. 2,400.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 15,837.50
Jumlah (1) + (2) = Rp. 40,449.16
PC. Hal. 2
PC 6.10 1M² Peleburan kayu dengan residu

6.10.1 Bahan
- Residu 0.350 Kg x Rp. 9,000 = Rp. 3,150.00
Jumlah (1) = Rp. 3,150.00
6.10.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 11,050.00
Jumlah (1) + (2) = Rp. 14,200.00

PC 6.11 1M² Peleburan bidang kayu dan vernis

6.11.1 Bahan
- Vernis 0.150 Ltr x Rp. 48,280 = Rp. 7,242.00
- Dempul 0.050 Kg x Rp. 15,000 = Rp. 750.00
- Ampelas 0.100 Lbr x Rp. 2,500 = Rp. 250.00
- Kuas 0.010 bh x Rp. 10,000 = Rp. 100.00
Jumlah (1) = Rp. 8,342.00
6.11.2 Tenaga
- Pekerja 0.160 Oh x Rp. 100,000 = Rp. 16,000.00
- Tukang cat 0.160 Oh x Rp. 150,000 = Rp. 24,000.00
- Kepala tukang 0.016 Oh x Rp. 150,000 = Rp. 2,400.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 42,837.50
Jumlah (1) + (2) = Rp. 51,179.50

PC 6.12 1M² Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )

6.12.1 Bahan
- Plamir 0.120 Kg x Rp. 17,500 = Rp. 2,100.00
- Cat dasar 0.120 Kg x Rp. 17,500 = Rp. 2,100.00
- Cat tembok 2 x 0.260 Kg x Rp. 75,000 = Rp. 19,500.00
Jumlah (1) = Rp. 23,700.00
6.12.2 Tenaga
- Pekerja 0.040 Oh x Rp. 100,000 = Rp. 4,000.00
- Tukang cat 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Kepala tukang 0.0120 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.002 Oh x Rp. 175,000 = Rp. 350.00
Jumlah (2) = Rp. 24,150.00
Jumlah (1) + (2) = Rp. 47,850.00

PC 6.13 1M² Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )

6.13.1 Bahan
- Cat dasar 0.120 Kg x Rp. 17,500 = Rp. 2,100.00
- Cat tembok 2 x 0.260 Kg x Rp. 75,000 = Rp. 19,500.00
Jumlah (1) = Rp. 21,600.00
6.13.2 Tenaga
- Pekerja 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Tukang cat 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.0090 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0015 Oh x Rp. 175,000 = Rp. 262.50
Jumlah (2) = Rp. 18,112.50
Jumlah (1) + (2) = Rp. 39,712.50
PC. Hal. 3
PC 6.14 1M² Pemasangan wall paper

6.14.1 Bahan
- wall paper 1.200 M² x Rp. 30,610 = Rp. 36,732.00
- Perekat lem karet 0.200 Kg x Rp. 44,900 = Rp. 8,980.00
Jumlah (1) = Rp. 45,712.00
6.14.2 Tenaga
- Pekerja 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Tukang cat 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.002 Oh x Rp. 150,000 = Rp. 300.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 32,737.50
Jumlah (1) + (2) = Rp. 78,449.50

PC 6.15 1M² Pengecatan permukaan baja dengan meni besi

6.15.1 Bahan
- Meni besi 0.100 Kg x Rp. 25,410 = Rp. 2,541.00
- Kuas 0.010 Bh x Rp. 10,000 = Rp. 100.00
Jumlah (1) = Rp. 2,641.00
6.15.2 Tenaga
- Pekerja 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Tukang cat 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Kepala tukang 0.02 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.01 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 9,750.00
Jumlah (1) + (2) = Rp. 12,391.00

PC 6.16. 1M² Pengecatan permukaan baja dengan meni besi dan perancah

6.16.1 Bahan
- Meni besi 0.100 Kg x Rp. 25,410 = Rp. 2,541.00
- Kuas 0.010 Bh x Rp. 10,000 = Rp. 100.00
- Peranca kayu 0.002 M³ x Rp. 3,107,500 = Rp. 6,215.00
Jumlah (1) = Rp. 8,856.00
6.16.2 Tenaga
- Pekerja 0.250 Oh x Rp. 100,000 = Rp. 25,000.00
- Tukang cat 0.225 Oh x Rp. 150,000 = Rp. 33,750.00
- Kepala tukang 0.0225 Oh x Rp. 150,000 = Rp. 3,375.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 63,437.50
Jumlah (1) + (2) = Rp. 72,293.50

PC 6.17. 1M² Pengecatan permukaan baja lapis seng (galbani) secara manual
sistem 1 lapis cat konvensional dengan tebal 200 um.

6.17.1 Bahan
- Cat Minyak besi 0.300 Kg x Rp. 39,330 = Rp. 11,799.00
Jumlah (1) = Rp. 11,799.00
6.17.2 Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang cat 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.1200 Oh x Rp. 150,000 = Rp. 18,000.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 34,050.00
Jumlah (1) + (2) = Rp. 45,849.00
PC. Hal. 4
PC 6.18. 1M² Pengecatan permukaan baja lapis seng (galbani) secara manual
sistem 3 lapis cat konvensional dengan tebal 200 um.

6.18.1 Bahan
- Cat dasar 0.110 Kg x Rp. 17,500 = Rp. 1,925.00
- Cat menie besi 0.170 Kg x Rp. 25,410 = Rp. 4,319.70
- Cat minyak besi 0.080 Kg x Rp. 39,330 = Rp. 3,146.40
Jumlah (1) = Rp. 9,391.10
6.18.2 Tenaga
- Pekerja 0.500 Oh x Rp. 100,000 = Rp. 50,000.00
- Tukang cat 0.800 Oh x Rp. 150,000 = Rp. 120,000.00
- Kepala tukang 0.300 Oh x Rp. 150,000 = Rp. 45,000.00
- Mandor 0.200 Oh x Rp. 175,000 = Rp. 35,000.00
Jumlah (2) = Rp. 250,000.00
Jumlah (1) + (2) = Rp. 259,391.10

PC 6.19. 1M² Pengecatan permukaan baja lapis seng (galbani) secara semprot
(airless spray) dengan sistem 1 lapis cat konvensional dengan tebal 200 um.

6.19.1 Bahan
- Cat dasar 0.300 Kg x Rp. 17,500 = Rp. 5,250.00
Jumlah (1) = Rp. 5,250.00
6.19.2 Tenaga
- Pekerja 0.400 Oh x Rp. 100,000 = Rp. 40,000.00
- Tukang cat 0.700 Oh x Rp. 150,000 = Rp. 105,000.00
- Kepala tukang 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Mandor 0.200 Oh x Rp. 175,000 = Rp. 35,000.00
Jumlah (2) = Rp. 210,000.00
Jumlah (1) + (2) = Rp. 215,250.00
PC. Hal. 5
ANALISA BIAYA KONSTRUKSI
PEKERJAAN LANGIT - LANGIT ( Plafond )

PLL 6.1 1 M² langit - langit asbes ( 1,00 x 1,00 ) m tebal 6 mm


6.1.1 Bahan
- Pelat asbes tebal 6 mm 1.100 Lbr x Rp. 17,330 = Rp. 19,063.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
Jumlah (1) = Rp. 19,243.00
6.1.2 Tenaga
- Pekerja 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Tukang kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.0015 Oh x Rp. 175,000 = Rp. 262.50
Jumlah (2) = Rp. 14,812.50
Jumlah (1) +(2) = Rp. 34,055.50

PLL 6.2 1 M² langit - langit asbes ( 1,00 x 1,00 ) m tebal 5 mm


6.2.1 Bahan
- Pelat asbes tebal 5 mm 1.100 Lbr x Rp. 14,440 = Rp. 15,884.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
Jumlah (1) = Rp. 16,064.00
6.2.2 Tenaga
- Pekerja 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Tukang kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.0015 Oh x Rp. 175,000 = Rp. 262.50
Jumlah (2) = Rp. 14,812.50
Jumlah (1) +(2) = Rp. 30,876.50

PLL 6.3 1 M² langit - langit asbes ( 1,00 x 1,00 ) m tebal 4 mm


6.3.1 Bahan
- Pelat asbes tebal 4 mm 1.100 Lbr x Rp. 11,550 = Rp. 12,705.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
Jumlah (1) = Rp. 12,885.00
6.3.2 Tenaga
- Pekerja 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Tukang kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.0015 Oh x Rp. 175,000 = Rp. 262.50
Jumlah (2) = Rp. 14,812.50
Jumlah (1) +(2) = Rp. 27,697.50

PLL 6.4 1 M² langit - langit asbes ( 1,00 x 1,00 ) m tebal 3,5 mm


6.4.1 Bahan
- Pelat asbes tebal 3,5 mm 1.100 Lbr x Rp. 9,350 = Rp. 10,285.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
Jumlah (1) = Rp. 10,465.00
6.4.2 Tenaga
- Pekerja 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Tukang kayu 0.070 Oh x Rp. 150,000 = Rp. 10,500.00
- Kepala tukang 0.007 Oh x Rp. 150,000 = Rp. 1,050.00
- Mandor 0.0015 Oh x Rp. 175,000 = Rp. 262.50
Jumlah (2) = Rp. 14,812.50
Jumlah (1) +(2) = Rp. 25,277.50

PLL 6.5 1 M² Langit - langit akustik ( 30 x 30 ) cm


6.5.1 Bahan
- Akustik ukuran 30 x 30 cm 11.500 Lbr x Rp. 8,540 = Rp. 98,210.00
- Paku 0.050 Kg x Rp. 18,000 = Rp. 900.00
Jumlah (1) = Rp. 99,110.00
6.5.2 Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang kayu 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 26,325.00
Jumlah (1) +(2) = Rp. 125,435.00

PLL. Hal. 1
PLL 6.6 1 M² Langit - langit akustik ( 30 x 60 ) cm
6.6.1 Bahan
- Akustik ukuran 30 x 60 cm 5.800 Lbr x Rp. 17,070 = Rp. 99,006.00
- Paku 0.050 Kg x Rp. 18,000 = Rp. 900.00
Jumlah (1) = Rp. 99,906.00
6.6.2 Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 23,025.00
Jumlah (1) +(2) = Rp. 122,931.00

PLL 6.7 1 M² Langit - langit akustik ( 60 x 120 ) cm


6.7.1 Bahan
- Akustik arm strong ukuran 60 x 120 cm 1.500 Lbr x Rp. 68,290 = Rp. 102,435.00
- Paku 0.050 Kg x Rp. 18,000 = Rp. 900.00
Jumlah (1) = Rp. 103,335.00
6.7.2 Tenaga
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 23,025.00
Jumlah (1) +(2) = Rp. 126,360.00

PLL 6.8 1 M² Langit - langit plywood ( 30 x 60 ) cm, tebal 4 mm


6.8.1 Bahan
- Plywood 4' x 8' x 4 mm 0.360 Lbr x Rp. 51,920 = Rp. 18,691.20
- Paku 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 19,231.20
6.8.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0035 Oh x Rp. 175,000 = Rp. 612.50
Jumlah (2) = Rp. 24,112.50
Jumlah (1) +(2) = Rp. 43,343.70

PLL 6.9 1 M² Langit - langit plywood ( 30 x 60 ) cm, tebal 6 mm


6.9.1 Bahan
- Plywood 4' x 8' x 6 mm 0.360 Lbr x Rp. 77,880 = Rp. 28,036.80
- Paku 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 28,576.80
6.9.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0035 Oh x Rp. 175,000 = Rp. 612.50
Jumlah (2) = Rp. 24,112.50
Jumlah (1) +(2) = Rp. 52,689.30

PLL 6.10 1 M² Langit - langit plywood ( 60 x 120 ) cm, tebal 4 mm


6.10.1 Bahan
- Plywood 4' x 8' x 4 mm 0.375 Lbr x Rp. 51,920 = Rp. 19,470.00
- Paku 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 20,010.00
6.10.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0035 Oh x Rp. 175,000 = Rp. 612.50
Jumlah (2) = Rp. 24,112.50
Jumlah (1) +(2) = Rp. 44,122.50
PLL. Hal. 2
PLL 6.11 1 M² Langit - langit plywood ( 60 x 120 ) cm, tebal 6 mm
6.11.1 Bahan
- Plywood 4' x 8' x 6 mm 0.375 Lbr x Rp. 77,880 = Rp. 29,205.00
- Paku 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 29,745.00
6.11.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0035 Oh x Rp. 175,000 = Rp. 612.50
Jumlah (2) = Rp. 24,112.50
Jumlah (1) +(2) = Rp. 53,857.50

PLL 6.12 1 M² Langit - langit teakwood ( 30 x 60 ) cm, tebal 4 mm


6.12.1 Bahan
- Teakwood 4' x 8' x 4 mm 0.360 Lbr x Rp. 54,450 = Rp. 19,602.00
- Paku 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 20,142.00
6.12.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0035 Oh x Rp. 175,000 = Rp. 612.50
Jumlah (2) = Rp. 24,112.50
Jumlah (1) +(2) = Rp. 44,254.50

PLL 6.13 1 M² Langit - langit teakwood ( 60 x 120 ) cm, tebal 4 mm


6.13.1 Bahan
- Teakwood 4' x 8' x 4 mm 0.375 Lbr x Rp. 54,450 = Rp. 20,418.75
- Paku 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 20,958.75
6.13.2 Tenaga
- Pekerja 0.070 Oh x Rp. 100,000 = Rp. 7,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0035 Oh x Rp. 175,000 = Rp. 612.50
Jumlah (2) = Rp. 24,112.50
Jumlah (1) +(2) = Rp. 45,071.25

PLL 6.14 1 M² Langit - langit lat kayu jati


6.14.1 Bahan
- Kayu jati, papan 0.024 M³ x Rp. 24,104,440 = Rp. 578,506.56
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
- Paku sekrup 0.050 Kg x Rp. 25,000 = Rp. 1,250.00
Jumlah (1) = Rp. 579,936.56
6.14.2 Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang kayu 0.600 Oh x Rp. 150,000 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 120,750.00
Jumlah (1) +(2) = Rp. 700,686.56

PLL 6.15 1 M² Langit - langit lat kayu ramin


6.15.1 Bahan
- Kayu ramin 0.024 Lbr x Rp. 0 = Rp. 0.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
- Paku sekrup 0.050 Kg x Rp. 25,000 = Rp. 1,250.00
Jumlah (1) = Rp. 1,430.00
6.15.2 Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang kayu 0.600 Oh x Rp. 150,000 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 120,750.00
Jumlah (1) +(2) = Rp. 122,180.00
PLL. Hal. 3
PLL 6.16 1 M² Langit - langit lat papan rider
6.16.1 Bahan
- Papan rider 1.000 Lbr x Rp. 315,000 = Rp. 315,000.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
- Paku sekrup 0.050 Kg x Rp. 25,000 = Rp. 1,250.00
Jumlah (1) = Rp. 316,430.00
6.16.2 Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang kayu 0.600 Oh x Rp. 150,000 = Rp. 90,000.00
- Kepala tukang 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Mandor 0.010 Oh x Rp. 175,000 = Rp. 1,750.00
Jumlah (2) = Rp. 120,750.00
Jumlah (1) +(2) = Rp. 437,180.00

PLL 6.17 1 M² Langit - langit soft board


6.17.1 Bahan
- Soft board 4' x 8' x 4 mm 0.350 Lbr x Rp. 55,990 = Rp. 19,596.50
- Paku biasa 0.030 Kg x Rp. 18,000 = Rp. 540.00
Jumlah (1) = Rp. 20,136.50
6.17.2 Tenaga
- Pekerja 0.600 Oh x Rp. 100,000 = Rp. 60,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 77,025.00
Jumlah (1) +(2) = Rp. 97,161.50

PLL 6.18 1 M² Langit - langit akustik 60 x 120 cm + rangka alluminium


6.18.1 Bahan
- Profil alluminium "T" 3.600 M' x Rp. 8,470 = Rp. 30,492.00
- Kawat seng polos 0.150 Kg x Rp. 22,530 = Rp. 3,379.50
- Ramset/dina bolt 1.000 Bh x Rp. 2,500 = Rp. 2,500.00
- Akustik arm strong 60 x 120 cm 1.500 Lbr x Rp. 68,290 = Rp. 102,435.00
Jumlah (1) = Rp. 138,806.50
6.18.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang kayu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 98,812.50
Jumlah (1) +(2) = Rp. 237,619.00

PLL 6.19 1 M' List Langit - langit Kayu profil 3"


6.19.1 Bahan
- List kayu profil 1.100 M' x Rp. 18,810 = Rp. 20,691.00
- Paku 0.010 Kg x Rp. 18,000 = Rp. 180.00
Jumlah (1) = Rp. 20,871.00
6.19.2 Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Tukang kayu 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Kepala tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.003 Oh x Rp. 175,000 = Rp. 525.00
Jumlah (2) = Rp. 13,775.00
Jumlah (1) +(2) = Rp. 34,646.00

PLL 6.20 1 M² Langit - langit asbes (1,00 x 1,00) m, rangka kayu meranti
6.20.1 Bahan
- Kayu meranti 0.012 M³ x Rp. 5,225,000 = Rp. 62,700.00
- Paku 0.060 Kg x Rp. 18,000 = Rp. 1,080.00
- Asbes 1,00 x 1,00 m 1.100 Lbr x Rp. 11,550 = Rp. 12,705.00
Jumlah (1) = Rp. 76,485.00
6.20.2 Tenaga
- Pekerja 0.180 Oh x Rp. 100,000 = Rp. 18,000.00
- Tukang kayu 0.320 Oh x Rp. 150,000 = Rp. 48,000.00
- Kepala tukang 0.032 Oh x Rp. 150,000 = Rp. 4,800.00
- Mandor 0.009 Oh x Rp. 175,000 = Rp. 1,575.00
Jumlah (2) = Rp. 72,375.00
Jumlah (1) +(2) = Rp. 148,860.00
PLL. Hal. 4
PLL 6.21 1 M² Langit - langit plywood 4 mm + rangka kayu meranti
6.21.1 Bahan
- Kayu meranti 0.013 M³ x Rp. 5,225,000 = Rp. 67,925.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 18,000 = Rp. 1,080.00
- Plywood 4' x 8' x 4 mm 0.390 Lbr x Rp. 51,920 = Rp. 20,248.80
Jumlah (1) = Rp. 89,253.80
6.21.2 Tenaga
- Pekerja 0.270 Oh x Rp. 100,000 = Rp. 27,000.00
- Tukang kayu 0.400 Oh x Rp. 150,000 = Rp. 60,000.00
- Kepala tukang 0.040 Oh x Rp. 150,000 = Rp. 6,000.00
- Mandor 0.0135 Oh x Rp. 175,000 = Rp. 2,362.50
Jumlah (2) = Rp. 95,362.50
Jumlah (1) +(2) = Rp. 184,616.30

PLL 6.22 1 M² Langit - langit akustik ( 30 x 60 ) cm + rangka kayu meranti


6.22.1 Bahan
- Kayu meranti 0.013 M³ x Rp. 5,225,000 = Rp. 67,925.00
- Paku 0.060 Kg x Rp. 18,000 = Rp. 1,080.00
- Akustik 30 x 60 cm 5.800 Lbr x Rp. 17,070 = Rp. 99,006.00
Jumlah (1) = Rp. 168,011.00
6.22.2 Tenaga
- Pekerja 0.260 Oh x Rp. 100,000 = Rp. 26,000.00
- Tukang kayu 0.400 Oh x Rp. 150,000 = Rp. 60,000.00
- Kepala tukang 0.040 Oh x Rp. 150,000 = Rp. 6,000.00
- Mandor 0.013 Oh x Rp. 175,000 = Rp. 2,275.00
Jumlah (2) = Rp. 94,275.00
Jumlah (1) +(2) = Rp. 262,286.00

PLL 6.23 1 M² Langit - langit akustik ( 30 x 30 ) cm + rangka kayu borneo


6.23.1 Bahan
- Kayu meranti 0.013 M³ x Rp. 5,225,000 = Rp. 67,925.00
- Paku 0.060 Kg x Rp. 18,000 = Rp. 1,080.00
- Akustik 30 x 30 cm 11.500 Lbr x Rp. 8,540 = Rp. 98,210.00
Jumlah (1) = Rp. 167,215.00
6.23.2 Tenaga
- Pekerja 0.310 Oh x Rp. 100,000 = Rp. 31,000.00
- Tukang kayu 0.470 Oh x Rp. 150,000 = Rp. 70,500.00
- Kepala tukang 0.047 Oh x Rp. 150,000 = Rp. 7,050.00
- Mandor 0.0155 Oh x Rp. 175,000 = Rp. 2,712.50
Jumlah (2) = Rp. 111,262.50
Jumlah (1) +(2) = Rp. 278,477.50

PLL 6,24.A 1 M² Langit - langit gypsum board, tebal 9 mm


6.24.1 Bahan
- Gypsum board (120 x 240 x 9) mm 0.364 Lbr x Rp. 115,000 = Rp. 41,860.00
- Paku sekrup 0.110 Kg x Rp. 25,000 = Rp. 2,750.00
Jumlah (1) = Rp. 44,610.00

6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang kayu 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Kepala tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 19,125.00
Jumlah (1) +(2) = Rp. 63,735.00

PLL 6.24.B 1 M² Langit - langit gypsum board, tebal 6 mm


6.24.1 Bahan
- Gypsum board (120 x 240 x 6) mm 0.364 Lbr x Rp. 65,000 = Rp. 23,660.00
- Paku sekrup 0.110 Kg x Rp. 25,000 = Rp. 2,750.00
Jumlah (1) = Rp. 26,410.00

6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang kayu 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Kepala tukang 0.005 Oh x Rp. 150,000 = Rp. 750.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) = Rp. 19,125.00
Jumlah (1) +(2) = Rp. 45,535.00

PLL. Hal. 5
PLL 6.24.C 1 M² Langit - langit gypsum board, tebal 12 mm
6.24.1 Bahan
- Gypsum board (120 x 240 x 12) mm 0.364 Lbr x Rp. 125,000 = Rp. 45,500.00
- Paku sekrup 0.110 Kg x Rp. 25,000 = Rp. 2,750.00
Jumlah (1) = Rp. 48,250.00

6.24.2 Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang kayu 0.080 Oh x Rp. 150,000 = Rp. 12,000.00
- Kepala tukang 0.0075 Oh x Rp. 150,000 = Rp. 1,125.00
- Mandor 0.0075 Oh x Rp. 175,000 = Rp. 1,312.50
Jumlah (2) = Rp. 29,437.50
Jumlah (1) +(2) = Rp. 77,687.50
PLL. Hal. 6
ANALISA BIAYA KONSTRUKSI
PEKERJAAN SANITASI

PS 6.1. Memasang 1 buah kloset duduk/monoblok


6.1.1. Bahan
- Klosed duduk/monoblok 1.000 Bh x Rp. 1,931,600 = Rp. 1,931,600.00
- Perlengkapan 6% harga klosed x Rp. 1,931,600 = Rp. 115,896.00
Jumlah (1) = Rp. 2,047,496.00
6.1.2. Tenaga
- Pekerja 3.300 Oh x Rp. 100,000 = Rp. 330,000.00
- Tukang batu 1.500 Oh x Rp. 150,000 = Rp. 225,000.00
- Kepala tukang 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Mandor 0.160 Oh x Rp. 175,000 = Rp. 28,000.00
Jumlah (2) = Rp. 605,500.00
Jumlah (1) +(2) = Rp. 2,652,996.00

PS 6.2. Memasang 1 buah kloset jongkok porselen


6.2.1. Bahan
- Klosed jongkok porselin 1.000 Bh x Rp. 225,280 = Rp. 225,280.00
- Semen portland 6.000 Kg x Rp. 1,400 = Rp. 8,400.00
- Pasir pasang 0.010 M³ x Rp. 265,000 = Rp. 2,650.00
Jumlah (1) = Rp. 236,330.00
6.2.2. Tenaga
- Pekerja 1.100 Oh x Rp. 100,000 = Rp. 110,000.00
- Tukang batu 1.500 Oh x Rp. 150,000 = Rp. 225,000.00
- Kepala tukang 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Mandor 0.110 Oh x Rp. 175,000 = Rp. 19,250.00
Jumlah (2) = Rp. 376,750.00
Jumlah (1) +(2) = Rp. 613,080.00

PS 6.3. Memasang 1 buah kloset jongkok teraso


6.3.1. Bahan
- Klosed jongkok teraso 1.000 Bh x Rp. 526,350 = Rp. 526,350.00
- Bata merah 5x10x20 cm 7.000 Bh x Rp. 900 = Rp. 6,300.00
- Semen portland 6.000 Kg x Rp. 1,400 = Rp. 8,400.00
- Pasir pasang 0.010 M³ x Rp. 265,000 = Rp. 2,650.00
Jumlah (1) = Rp. 543,700.00
6.3.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
- Tukang batu 1.500 Oh x Rp. 150,000 = Rp. 225,000.00
- Kepala tukang 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Mandor 0.100 Oh x Rp. 175,000 = Rp. 17,500.00
Jumlah (2) = Rp. 365,000.00
Jumlah (1) +(2) = Rp. 908,700.00

PS 6.4 Memasang 1 buah urinoir


6.4.1. Bahan
- Urinoir 1.000 Bh x Rp. 557,480 = Rp. 557,480.00
- Perlengkapan 15% harga urinoir x Rp. 557,480 = Rp. 83,622.00
- Semen portland 6.000 Kg x Rp. 1,400 = Rp. 8,400.00
- Pasir pasang 0.010 M³ x Rp. 265,000 = Rp. 2,650.00
Jumlah (1) = Rp. 652,152.00
6.4.2. Tenaga
- Pekerja 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
- Tukang batu 1.000 Oh x Rp. 150,000 = Rp. 150,000.00
- Kepala tukang 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Mandor 0.100 Oh x Rp. 175,000 = Rp. 17,500.00
Jumlah (2) = Rp. 282,500.00
Jumlah (1) +(2) = Rp. 934,652.00
PS. Hal. 1
PS 6.5 Memasang 1 buah wastafel
6.5.1. Bahan
- Wastafel 1.000 Bh x Rp. 526,350 = Rp. 526,350.00
- Perlengkapan 12% harga wastafel x Rp. 526,350 = Rp. 63,162.00
- Semen portland 6.000 Kg x Rp. 1,400 = Rp. 8,400.00
- Pasir pasang 0.010 M³ x Rp. 265,000 = Rp. 2,650.00
Jumlah (1) = Rp. 600,562.00
6.5.2. Tenaga
- Pekerja 1.200 Oh x Rp. 100,000 = Rp. 120,000.00
- Tukang batu 1.450 Oh x Rp. 150,000 = Rp. 217,500.00
- Kepala tukang 0.150 Oh x Rp. 150,000 = Rp. 22,500.00
- Mandor 0.100 Oh x Rp. 175,000 = Rp. 17,500.00
Jumlah (2) = Rp. 377,500.00
Jumlah (1) +(2) = Rp. 978,062.00

PS 6.6. Memasang 1 buah bak mandi teraso volume 0,30 m³


6.6.1. Bahan
- Bak teraso 1.000 Bh x Rp. 181,500 = Rp. 181,500.00
- Semen portland 6.000 Kg x Rp. 1,400 = Rp. 8,400.00
- Pasir pasang 0.010 M³ x Rp. 265,000 = Rp. 2,650.00
Jumlah (1) = Rp. 192,550.00
6.6.2. Tenaga
- Pekerja 2.100 Oh x Rp. 100,000 = Rp. 210,000.00
- Tukang batu 0.750 Oh x Rp. 150,000 = Rp. 112,500.00
- Kepala tukang 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Mandor 0.110 Oh x Rp. 175,000 = Rp. 19,250.00
Jumlah (2) = Rp. 353,000.00
Jumlah (1) +(2) = Rp. 545,550.00

PS 6.7. Memasang 1 buah bak mandi fibreglass volume 0,30 m³


6.7.1. Bahan
- Bak fibreglass 1.000 Bh x Rp. 181,500 = Rp. 181,500.00
- Perlengkapan 18% Harga bak x Rp. 181,500 = Rp. 32,670.00
Jumlah (1) = Rp. 214,170.00
6.7.2. Tenaga
- Pembantu tukang 1.800 Oh x Rp. 100,000 = Rp. 180,000.00
- Tukang batu 0.540 Oh x Rp. 150,000 = Rp. 81,000.00
- Kepala tukang 0.054 Oh x Rp. 150,000 = Rp. 8,100.00
- Mandor 0.110 Oh x Rp. 175,000 = Rp. 19,250.00
Jumlah (2) = Rp. 288,350.00
Jumlah (1) +(2) = Rp. 502,520.00

PS 6.8. Memasang 1 buah bak mandi batu bata volume 0,30 m³


6.8.1. Bahan
- Batu bata 44.000 M³ x Rp. 1,300 = Rp. 57,200.00
- Semen portland 120.000 Kg x Rp. 1,400 = Rp. 168,000.00
- Pasir pasang 0.300 M³ x Rp. 265,000 = Rp. 79,500.00
- Porselin (11x11) cm 360.000 Bh x Rp. 145 = Rp. 52,200.00
- Semen putih 6.000 Kg x Rp. 5,000 = Rp. 30,000.00
Jumlah (1) = Rp. 386,900.00
6.8.2. Tenaga
- Pekerja 3.000 Oh x Rp. 100,000 = Rp. 300,000.00
- Tukang batu 3.000 Oh x Rp. 150,000 = Rp. 450,000.00
- Kepala tukang 0.300 Oh x Rp. 150,000 = Rp. 45,000.00
- Mandor 0.300 Oh x Rp. 175,000 = Rp. 52,500.00
Jumlah (2) = Rp. 847,500.00
Jumlah (1) +(2) = Rp. 1,234,400.00

PS. Hal. 2
PS 6.9. Memasang 1 buah badkip porselin

6.9.1. Bahan
- Badkip 1.000 Bh x Rp. 3,025,000 = Rp. 3,025,000.00
- Perlengkapan 20% Harga badkip x Rp. 3,025,000 = Rp. 605,000.00
Jumlah (1) = Rp. 3,630,000.00
6.9.2. Tenaga
- Pekerja 2.500 Oh x Rp. 100,000 = Rp. 250,000.00
- Tukang batu 0.750 Oh x Rp. 150,000 = Rp. 112,500.00
- Kepala tukang 0.075 Oh x Rp. 150,000 = Rp. 11,250.00
- Mandor 0.250 Oh x Rp. 175,000 = Rp. 43,750.00
Jumlah (2) = Rp. 417,500.00
Jumlah (1) +(2) = Rp. 4,047,500.00

PS 6.10. Memasang 1 buah bak mandi beton volume 1 m³ air

6.10.1. Bahan
- Beton 1 : 1 ½ : 2½ 0.900 M³ x Rp. 12,500 = Rp. 11,250.00
- Besi beton 180.000 Kg x Rp. 19,500 = Rp. 3,510,000.00
- Kayu cetakan 0.096 M³ x Rp. 3,107,500 = Rp. 298,320.00
- Ubin porselin 420.000 M² x Rp. 145 = Rp. 60,900.00
- Perlengkapan 10% Hrg total bahan x Rp. 3,880,470 = Rp. 388,047.00
Jumlah (1) = Rp. 4,268,517.00
6.10.2. Tenaga
- Pekerja 3.500 Oh x Rp. 100,000 = Rp. 350,000.00
- Tukang batu 4.500 Oh x Rp. 150,000 = Rp. 675,000.00
- Kepala tukang 0.900 Oh x Rp. 150,000 = Rp. 135,000.00
- Mandor 0.900 Oh x Rp. 175,000 = Rp. 157,500.00
Jumlah (2) = Rp. 1,317,500.00
Jumlah (1) +(2) = Rp. 5,586,017.00

PS 6.11. Memasang 1 buah bak fibreglass volume 1 m³ air

6.11.1. Bahan
- Bak fibreglass 1.000 Bh x Rp. 181,500 = Rp. 181,500.00
- Perlengkapan 12% Harga bak x Rp. 181,500 = Rp. 21,780.00
Jumlah (1) = Rp. 203,280.00
6.11.2. Tenaga
- Pekerja 3.000 Oh x Rp. 100,000 = Rp. 300,000.00
- Tukang batu 4.500 Oh x Rp. 150,000 = Rp. 675,000.00
- Kepala tukang 0.900 Oh x Rp. 150,000 = Rp. 135,000.00
- Mandor 0.900 Oh x Rp. 175,000 = Rp. 157,500.00
Jumlah (2) = Rp. 1,267,500.00
Jumlah (1) +(2) = Rp. 1,470,780.00

PS 6.12. Memasang 1 m' pipa beton, diameter 30 cm - 100 cm

6.12.1. Bahan
- Pipa beton 1.100 Bh x Rp. 56,270 = Rp. 61,897.00
- Batu bata 55.000 Bh x Rp. 1,300 = Rp. 71,500.00
- Semen portland 10.300 Kg x Rp. 1,400 = Rp. 14,420.00
- Pasir pasang 0.061 M³ x Rp. 265,000 = Rp. 16,165.00
- Pasir urug 0.069 M³ x Rp. 130,000 = Rp. 8,970.00
Jumlah (1) = Rp. 172,952.00
6.12.2. Tenaga
- Pekerja 0.380 Oh x Rp. 100,000 = Rp. 38,000.00
- Tukang batu 0.190 Oh x Rp. 150,000 = Rp. 28,500.00
- Kepala tukang 0.019 Oh x Rp. 150,000 = Rp. 2,850.00
- Mandor 0.019 Oh x Rp. 175,000 = Rp. 3,325.00
Jumlah (2) = Rp. 72,675.00
Jumlah (1) +(2) = Rp. 245,627.00
PS. Hal. 3
PS 6.13. Memasang 1 buah bak kontrol pasangan batu bata ukuran (30 x 30) cm
tinggi 35 cm

6.13.1. Bahan
- Batu bata 145.000 Bh x Rp. 1,300 = Rp. 188,500.00
- Semen portland 44.000 Kg x Rp. 1,400 = Rp. 61,600.00
- Pasir pasang 0.070 M³ x Rp. 265,000 = Rp. 18,550.00
- Batu kerikil 0.070 M³ x Rp. 215,900 = Rp. 15,113.00
- Besi beton 1.600 Kg x Rp. 19,500 = Rp. 31,200.00
- Pasir beton 0.060 M³ x Rp. 165,000 = Rp. 9,900.00
Jumlah (1) = Rp. 324,863.00
6.13.2. Tenaga
- Pekerja 3.200 Oh x Rp. 100,000 = Rp. 320,000.00
- Tukang batu 1.015 Oh x Rp. 150,000 = Rp. 152,250.00
- Kepala tukang 0.0015 Oh x Rp. 150,000 = Rp. 225.00
- Mandor 0.016 Oh x Rp. 175,000 = Rp. 2,800.00
Jumlah (2) = Rp. 475,275.00
Jumlah (1) +(2) = Rp. 800,138.00

PS 6.14. Memasang 1 buah bak kontrol pasangan batu bata ukuran (45 x 45) cm
tinggi 50 cm

6.14.1. Bahan
- Batu bata 250.000 Bh x Rp. 1,300 = Rp. 325,000.00
- Semen portland 77.000 Kg x Rp. 1,400 = Rp. 107,800.00
- Pasir pasang 0.130 M³ x Rp. 265,000 = Rp. 34,450.00
- Batu kerikil 0.020 M³ x Rp. 215,900 = Rp. 4,318.00
- Besi beton 2.600 Kg x Rp. 19,500 = Rp. 50,700.00
- Pasir beton 0.090 M³ x Rp. 165,000 = Rp. 14,850.00
Jumlah (1) = Rp. 537,118.00
6.14.2. Tenaga
- Pekerja 1.420 Oh x Rp. 100,000 = Rp. 142,000.00
- Tukang batu 0.473 Oh x Rp. 150,000 = Rp. 70,950.00
- Kepala tukang 0.047 Oh x Rp. 150,000 = Rp. 7,050.00
- Mandor 0.071 Oh x Rp. 175,000 = Rp. 12,425.00
Jumlah (2) = Rp. 232,425.00
Jumlah (1) +(2) = Rp. 769,543.00

PS 6.15. Memasang 1 buah bak kontrol pasangan batu bata ukuran (60 x 60) cm
tinggi 65 cm

6.15.1. Bahan
- Batu bata 371.000 Bh x Rp. 1,300 = Rp. 482,300.00
- Semen portland 114.000 Kg x Rp. 1,400 = Rp. 159,600.00
- Pasir pasang 0.184 M³ x Rp. 265,000 = Rp. 48,760.00
- Batu koral 0.033 M³ x Rp. 215,900 = Rp. 7,124.70
- Besi beton 4.850 Kg x Rp. 19,500 = Rp. 94,575.00
- Pasir beton 0.120 M³ x Rp. 165,000 = Rp. 19,800.00
Jumlah (1) = Rp. 812,159.70
6.15.2. Tenaga
- Pekerja 2.160 Oh x Rp. 100,000 = Rp. 216,000.00
- Tukang batu 0.720 Oh x Rp. 150,000 = Rp. 108,000.00
- Kepala tukang 0.072 Oh x Rp. 150,000 = Rp. 10,800.00
- Mandor 0.108 Oh x Rp. 175,000 = Rp. 18,900.00
- Tukang gali 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
Jumlah (2) = Rp. 363,700.00
Jumlah (1) +(2) = Rp. 1,175,859.70
PS. Hal. 4
PS 6.16. Memasang 1 m' pipa galvanis diameter ½"

6.16.1. Bahan
- Pipa galvanis 1.200 M´ x Rp. 14,770 = Rp. 17,724.00
- Perlengkapan 35% harga pipa x Rp. 14,770 = Rp. 5,169.50
Jumlah (1) = Rp. 22,893.50

6.16.2. Tenaga
- Pekerja 0.054 Oh x Rp. 100,000 = Rp. 5,400.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.027 Oh x Rp. 175,000 = Rp. 4,725.00
Jumlah (2) = Rp. 24,975.00
Jumlah (1) +(2) = Rp. 47,868.50

PS 6.17. Memasang 1 m' pipa galvanis diameter 3/4"

6.17.1. Bahan
- Pipa galvanis 1.200 M´ x Rp. 20,140 = Rp. 24,168.00
- Perlengkapan 35% harga pipa x Rp. 20,140 = Rp. 7,049.00
Jumlah (1) = Rp. 31,217.00
6.17.2. Tenaga
- Pekerja 0.054 Oh x Rp. 100,000 = Rp. 5,400.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.027 Oh x Rp. 175,000 = Rp. 4,725.00
Jumlah (2) = Rp. 24,975.00
Jumlah (1) +(2) = Rp. 56,192.00

PS 6.18. Memasang 1 m' pipa galvanis diameter 1"

6.18.1. Bahan
- Pipa galvanis 1.200 M´ x Rp. 29,520 = Rp. 35,424.00
- Perlengkapan 35% harga pipa x Rp. 29,520 = Rp. 10,332.00
Jumlah (1) = Rp. 45,756.00
6.18.2. Tenaga
- Pekerja 0.054 Oh x Rp. 100,000 = Rp. 5,400.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.027 Oh x Rp. 175,000 = Rp. 4,725.00
Jumlah (2) = Rp. 24,975.00
Jumlah (1) +(2) = Rp. 70,731.00

PS 6.19. Memasang 1 m' pipa galvanis diameter 1 ½"

6.19.1. Bahan
- Pipa galvanis 1.200 M´ x Rp. 37,580 = Rp. 45,096.00
- Perlengkapan 35% harga pipa x Rp. 37,580 = Rp. 13,153.00
Jumlah (1) = Rp. 58,249.00
6.19.2. Tenaga
- Pekerja 0.108 Oh x Rp. 100,000 = Rp. 10,800.00
- Tukang batu 0.180 Oh x Rp. 150,000 = Rp. 27,000.00
- Kepala tukang 0.018 Oh x Rp. 150,000 = Rp. 2,700.00
- Mandor 0.0054 Oh x Rp. 175,000 = Rp. 945.00
Jumlah (2) = Rp. 41,445.00
Jumlah (1) +(2) = Rp. 99,694.00
PS. Hal. 5
PS 6.20. Memasang 1 m' pipa galvanis diameter 2"

6.20.1. Bahan
- Pipa galvanis 1.200 M´ x Rp. 47,600 = Rp. 57,120.00
- Perlengkapan 35% harga pipa x Rp. 47,600 = Rp. 16,660.00
Jumlah (1) = Rp. 73,780.00
6.20.2. Tenaga
- Pekerja 0.108 Oh x Rp. 100,000 = Rp. 10,800.00
- Tukang batu 0.180 Oh x Rp. 150,000 = Rp. 27,000.00
- Kepala tukang 0.018 Oh x Rp. 150,000 = Rp. 2,700.00
- Mandor 0.0054 Oh x Rp. 175,000 = Rp. 945.00
Jumlah (2) = Rp. 41,445.00
Jumlah (1) +(2) = Rp. 115,225.00

PS 6.21. Memasang 1 m' pipa galvanis diameter 3"

6.21.1. Bahan
- Pipa galvanis 1.200 M´ x Rp. 52,440 = Rp. 62,928.00
- Perlengkapan 35% harga pipa x Rp. 52,440 = Rp. 18,354.00
Jumlah (1) = Rp. 81,282.00
6.21.2. Tenaga
- Pekerja 0.135 Oh x Rp. 100,000 = Rp. 13,500.00
- Tukang batu 0.225 Oh x Rp. 150,000 = Rp. 33,750.00
- Kepala tukang 0.0225 Oh x Rp. 150,000 = Rp. 3,375.00
- Mandor 0.0068 Oh x Rp. 175,000 = Rp. 1,190.00
Jumlah (2) = Rp. 51,815.00
Jumlah (1) +(2) = Rp. 133,097.00

PS 6.22. Memasang 1 m' pipa PVC tipe AW diameter ½"

6.22.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 5,540 = Rp. 6,648.00
- Perlengkapan 35% harga pipa x Rp. 5,540 = Rp. 1,939.00
Jumlah (1) = Rp. 8,587.00
6.22.2. Tenaga
- Pekerja 0.036 Oh x Rp. 100,000 = Rp. 3,600.00
- Tukang batu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.0018 Oh x Rp. 175,000 = Rp. 315.00
Jumlah (2) = Rp. 13,815.00
Jumlah (1) +(2) = Rp. 22,402.00

PS 6.23. Memasang 1 m' pipa PVC tipe AW diameter ¾"

6.23.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 7,440 = Rp. 8,928.00
- Perlengkapan 35% harga pipa x Rp. 7,440 = Rp. 2,604.00
Jumlah (1) = Rp. 11,532.00
6.23.2. Tenaga
- Pekerja 0.036 Oh x Rp. 100,000 = Rp. 3,600.00
- Tukang batu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.0018 Oh x Rp. 175,000 = Rp. 315.00
Jumlah (2) = Rp. 13,815.00
Jumlah (1) +(2) = Rp. 25,347.00
PS. Hal. 6
PS 6.24. Memasang 1 m' pipa PVC tipe AW diameter 1"

6.24.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 13,620 = Rp. 16,344.00
- Perlengkapan 35% harga pipa x Rp. 13,620 = Rp. 4,767.00
Jumlah (1) = Rp. 21,111.00
6.24.2. Tenaga
- Pekerja 0.036 Oh x Rp. 100,000 = Rp. 3,600.00
- Tukang batu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.0018 Oh x Rp. 175,000 = Rp. 315.00
Jumlah (2) = Rp. 13,815.00
Jumlah (1) +(2) = Rp. 34,926.00

PS 6.25. Memasang 1 m' pipa PVC tipe AW diameter 1 ½"

6.25.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 19,670 = Rp. 23,604.00
- Perlengkapan 35% harga pipa x Rp. 19,670 = Rp. 6,884.50
Jumlah (1) = Rp. 30,488.50
6.25.2. Tenaga
- Pekerja 0.036 Oh x Rp. 100,000 = Rp. 3,600.00
- Tukang batu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.0018 Oh x Rp. 175,000 = Rp. 315.00
Jumlah (2) = Rp. 13,815.00
Jumlah (1) +(2) = Rp. 44,303.50

PS 6.26. Memasang 1 m' pipa PVC tipe AW diameter 2"

6.26.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 23,190 = Rp. 27,828.00
- Perlengkapan 35% harga pipa x Rp. 23,190 = Rp. 8,116.50
Jumlah (1) = Rp. 35,944.50
6.26.2. Tenaga
- Pekerja 0.054 Oh x Rp. 100,000 = Rp. 5,400.00
- Tukang batu 0.090 Oh x Rp. 150,000 = Rp. 13,500.00
- Kepala tukang 0.009 Oh x Rp. 150,000 = Rp. 1,350.00
- Mandor 0.0027 Oh x Rp. 175,000 = Rp. 472.50
Jumlah (2) = Rp. 20,722.50
Jumlah (1) +(2) = Rp. 56,667.00

PS 6.27. Memasang 1 m' pipa PVC tipe AW diameter 2 ½"

6.27.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 26,620 = Rp. 31,944.00
- Perlengkapan 35% harga pipa x Rp. 26,620 = Rp. 9,317.00
Jumlah (1) = Rp. 41,261.00
6.27.2. Tenaga
- Pekerja 0.036 Oh x Rp. 100,000 = Rp. 3,600.00
- Tukang batu 0.060 Oh x Rp. 150,000 = Rp. 9,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.0018 Oh x Rp. 175,000 = Rp. 315.00
Jumlah (2) = Rp. 13,815.00
Jumlah (1) +(2) = Rp. 55,076.00
PS. Hal. 7
PS 6.28. Memasang 1 m' pipa PVC tipe AW diameter 3"

6.28.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 29,840 = Rp. 35,808.00
- Perlengkapan 35% harga pipa x Rp. 29,840 = Rp. 10,444.00
Jumlah (1) = Rp. 46,252.00
6.28.2. Tenaga
- Pekerja 0.081 Oh x Rp. 100,000 = Rp. 8,100.00
- Tukang batu 0.135 Oh x Rp. 150,000 = Rp. 20,250.00
- Kepala tukang 0.0135 Oh x Rp. 150,000 = Rp. 2,025.00
- Mandor 0.0041 Oh x Rp. 175,000 = Rp. 717.50
Jumlah (2) = Rp. 31,092.50
Jumlah (1) +(2) = Rp. 77,344.50

PS 6.29. Memasang 1 m' pipa PVC tipe AW diameter 4"

6.29.1. Bahan
- Pipa PVC 1.200 M´ x Rp. 49,920 = Rp. 59,904.00
- Perlengkapan 35% harga pipa x Rp. 49,920 = Rp. 17,472.00
Jumlah (1) = Rp. 77,376.00
6.29.2. Tenaga
- Pekerja 0.081 Oh x Rp. 100,000 = Rp. 8,100.00
- Tukang batu 0.135 Oh x Rp. 150,000 = Rp. 20,250.00
- Kepala tukang 0.0135 Oh x Rp. 150,000 = Rp. 2,025.00
- Mandor 0.0041 Oh x Rp. 175,000 = Rp. 717.50
Jumlah (2) = Rp. 31,092.50
Jumlah (1) +(2) = Rp. 108,468.50

PS 6.30. Memasang 1 bh bak cuci piring stainles steel

6.30.1. Bahan
- Bak cuci stainless steel 1.000 Bh x Rp. 466,700 = Rp. 466,700.00
- Water drain asesories 1.000 Set x Rp. 15,000 = Rp. 15,000.00
Jumlah (1) = Rp. 481,700.00
6.30.2. Tenaga
- Pekerja 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Tukang batu 0.300 Oh x Rp. 150,000 = Rp. 45,000.00
- Kepala tukang 0.030 Oh x Rp. 150,000 = Rp. 4,500.00
- Mandor 0.0015 Oh x Rp. 175,000 = Rp. 262.50
Jumlah (2) = Rp. 52,762.50
Jumlah (1) +(2) = Rp. 534,462.50

PS 6.31. Memasang 1 bh bak cuci piring teraso

6.31.1. Bahan
- Bak cuci teraso 1.000 Bh x Rp. 272,250 = Rp. 272,250.00
- Water drain + asesories 1.000 Bh x Rp. 15,000 = Rp. 15,000.00
- Semen portland 20.000 Kg x Rp. 1,400 = Rp. 28,000.00
- Pasir 0.050 M³ x Rp. 265,000 = Rp. 13,250.00
Jumlah (1) = Rp. 328,500.00
6.31.2. Tenaga
- Pekerja 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Tukang batu 0.500 Oh x Rp. 150,000 = Rp. 75,000.00
- Kepala tukang 0.050 Oh x Rp. 150,000 = Rp. 7,500.00
- Mandor 0.0025 Oh x Rp. 175,000 = Rp. 437.50
Jumlah (2) = Rp. 87,937.50
Jumlah (1) +(2) = Rp. 416,437.50
PS. Hal. 8
PS 6.32. Memasang 1 bh kran diameter ¾" atau ½"

6.32.1. Bahan
- Kran air 1.000 Bh x Rp. 27,350 = Rp. 27,350.00
- Seal tape 0.025 Bh x Rp. 92,570 = Rp. 2,314.25
Jumlah (1) = Rp. 29,664.25
6.32.2. Tenaga
- Pekerja 0.010 Oh x Rp. 100,000 = Rp. 1,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) 18,375.00
Jumlah (1) +(2) 48,039.25

PS 6.33. Memasang 1 bh Floor drain

6.33.1. Bahan
- Floor drain 1.000 Bh x Rp. 15,000 = Rp. 15,000.00
Jumlah (1) = Rp. 15,000.00

6.33.2. Tenaga
- Pekerja 0.010 Oh x Rp. 100,000 = Rp. 1,000.00
- Tukang batu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.005 Oh x Rp. 175,000 = Rp. 875.00
Jumlah (2) 18,375.00
Jumlah (1) +(2) 33,375.00
PS. Hal. 9
ANALISA BIAYA KONSTRUKSI
PEKERJAAN BESI DAN ALUMINIUM

PBA 6.1 1 Kg Pasang rangka atap baja


6.1.1 Bahan
- Besi profil WF 1.100 Kg x Rp. 15,950 = Rp. 17,545.00
- Meni besi 0.080 Kg x Rp. 25,410 = Rp. 2,032.80
Jumlah (1) = Rp. 19,577.80
6.1.2. Tenaga
- Tukang besi 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Pekerja 0.060 Oh x Rp. 100,000 = Rp. 6,000.00
- Kepala tukang 0.006 Oh x Rp. 150,000 = Rp. 900.00
- Mandor 0.0003 Oh x Rp. 175,000 = Rp. 52.50
Jumlah (2) = Rp. 7,852.50
Jumlah (1) +(2) = Rp. 27,430.30

PBA 6.2 1 M² Pasang pintu besi baja


6.2.1 Bahan
- Pintu besi baja 1.000 M² x Rp. 816,750 = Rp. 816,750.00
Jumlah (1) = Rp. 816,750.00
6.2.2. Tenaga
- Tukang besi konstruksi 0.650 Oh x Rp. 150,000 = Rp. 97,500.00
- Pekerja 0.650 Oh x Rp. 100,000 = Rp. 65,000.00
- Kepala tukang 0.065 Oh x Rp. 150,000 = Rp. 9,750.00
- Mandor 0.032 Oh x Rp. 175,000 = Rp. 5,600.00
Jumlah (2) = Rp. 177,850.00
Jumlah (1) +(2) = Rp. 994,600.00

PBA 6.3 1 M² Pasang jendela besi


6.3.1 Bahan
- Jendela besi 1.000 M² x Rp. 347,270 = Rp. 347,270.00
Jumlah (1) = Rp. 347,270.00
6.3.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 150,000 = Rp. 157,500.00
- Pekerja 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.105 Oh x Rp. 150,000 = Rp. 15,750.00
- Mandor 0.00525 Oh x Rp. 175,000 = Rp. 918.75
Jumlah (2) = Rp. 279,168.75
Jumlah (1) +(2) = Rp. 626,438.75

PBA 6.4 1 M² Pasang pintu gulung besi


6.4.1 Bahan
- Pintu gulung besi 1.000 M² x Rp. 828,850 = Rp. 828,850.00
Jumlah (1) = Rp. 828,850.00
6.4.2. Tenaga
- Tukang besi konstruksi 1.200 Oh x Rp. 150,000 = Rp. 180,000.00
- Pekerja 1.200 Oh x Rp. 100,000 = Rp. 120,000.00
- Kepala tukang 0.120 Oh x Rp. 150,000 = Rp. 18,000.00
- Mandor 0.006 Oh x Rp. 175,000 = Rp. 1,050.00
Jumlah (2) = Rp. 319,050.00
Jumlah (1) +(2) = Rp. 1,147,900.00

PBA 6.5 1 M² Pasang pintu lipat


6.5.1 Bahan
- Pintu lipat 1.000 M² x Rp. 837,320 = Rp. 837,320.00
Jumlah (1) = Rp. 837,320.00
6.5.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 150,000 = Rp. 157,500.00
- Pekerja 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.105 Oh x Rp. 150,000 = Rp. 15,750.00
- Mandor 0.0052 Oh x Rp. 175,000 = Rp. 910.00
Jumlah (2) = Rp. 279,160.00
Jumlah (1) +(2) = Rp. 1,116,480.00
PBA. Hal. 1
PBA 6.6 1 M² Pasang pintu Sunscreen alluminium
6.6.1 Bahan
- Sunscreen alluminium 1.000 M² x Rp. 350,000 = Rp. 350,000.00
Jumlah (1) = Rp. 350,000.00
6.6.2. Tenaga
- Tukang besi konstruksi 0.800 Oh x Rp. 150,000 = Rp. 120,000.00
- Pekerja 0.080 Oh x Rp. 100,000 = Rp. 8,000.00
- Kepala tukang 0.080 Oh x Rp. 150,000 = Rp. 12,000.00
- Mandor 0.004 Oh x Rp. 175,000 = Rp. 700.00
Jumlah (2) = Rp. 140,700.00
Jumlah (1) +(2) = Rp. 490,700.00

PBA 6.7 1 M² Pasang Rolling door


6.7.1 Bahan
- Roll door 1.000 M² x Rp. 465,850 = Rp. 465,850.00
Jumlah (1) = Rp. 465,850.00
6.7.2. Tenaga
- Tukang besi konstruksi 1.500 Oh x Rp. 150,000 = Rp. 225,000.00
- Pekerja 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.105 Oh x Rp. 150,000 = Rp. 15,750.00
- Mandor 0.0052 Oh x Rp. 175,000 = Rp. 910.00
Jumlah (2) = Rp. 346,660.00
Jumlah (1) +(2) = Rp. 812,510.00

PBA 6.8 1 M² Pasang pintu alluminium


6.8.1 Bahan
- Pintu alluminium 1.000 M² x Rp. 550,000 = Rp. 550,000.00
Jumlah (1) = Rp. 550,000.00

6.8.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 150,000 = Rp. 157,500.00
- Pekerja 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.105 Oh x Rp. 150,000 = Rp. 15,750.00
- Mandor 0.0052 Oh x Rp. 175,000 = Rp. 910.00
Jumlah (2) = Rp. 279,160.00
Jumlah (1) +(2) = Rp. 829,160.00

PBA 6.9 1 M² Pasang Venetions blinds

6.9.1 Bahan
- Venetions blinds 1.000 M² x Rp. 163,350 = Rp. 163,350.00
Jumlah (1) = Rp. 163,350.00

6.9.2. Tenaga
- Tukang kayu 0.350 Oh x Rp. 61,775 = Rp. 21,621.25
- Pekerja 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.00175 Oh x Rp. 175,000 = Rp. 306.25
Jumlah (2) = Rp. 62,177.50
Jumlah (1) +(2) = Rp. 225,527.50

PBA 6.10 1 M² Pasang Vertikals blinds


6.10.1 Bahan
- Vertikals blinds 1.000 M² x Rp. 175,450 = Rp. 175,450.00
Jumlah (1) = Rp. 175,450.00

6.10.2. Tenaga
- Tukang kayu 0.350 Oh x Rp. 61,775 = Rp. 21,621.25
- Pekerja 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 150,000 = Rp. 5,250.00
- Mandor 0.00175 Oh x Rp. 175,000 = Rp. 306.25
Jumlah (2) = Rp. 62,177.50
Jumlah (1) +(2) = Rp. 237,627.50
PBA. Hal. 2
PBA 6.11 1 M² Pasang teralis besi

6.11.1 Bahan
- Besi strip 2 x 3 11.500 M' x Rp. 11,880 = Rp. 136,620.00
Jumlah (1) = Rp. 136,620.00

6.11.2. Tenaga
- Tukang las 1.200 Oh x Rp. 61,775 = Rp. 74,130.00
- Pekerja 1.200 Oh x Rp. 100,000 = Rp. 120,000.00
- Kepala tukang 0.012 Oh x Rp. 150,000 = Rp. 1,800.00
- Mandor 0.0006 Oh x Rp. 175,000 = Rp. 105.00
Jumlah (2) = Rp. 196,035.00
Jumlah (1) +(2) = Rp. 332,655.00

PBA 6.12 1 M² Pasang kawat harmonika

6.12.1 Bahan
- Kawat harmonika 1.100 M² x Rp. 23,600 = Rp. 25,960.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 18,000 = Rp. 360.00
- Kayu meranti 0.0018 M³ x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 35,725.00

6.12.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0005 Oh x Rp. 175,000 = Rp. 87.50
Jumlah (2) = Rp. 26,587.50
Jumlah (1) +(2) = Rp. 62,312.50

PBA 6.13 1 M² Pasang kawat nyamuk

6.13.1 Bahan
- Kawat nyamuk 1.100 M² x Rp. 11,980 = Rp. 13,178.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 18,000 = Rp. 360.00
- Kayu meranti 0.0018 M³ x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 22,943.00

6.13.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0005 Oh x Rp. 175,000 = Rp. 87.50
Jumlah (2) = Rp. 26,587.50
Jumlah (1) +(2) = Rp. 49,530.50

PBA 6.14 1 M² Pasang kawat kassa

6.14.1 Bahan
- Kawat kassa 1.100 M² x Rp. 13,920 = Rp. 15,312.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 18,000 = Rp. 360.00
- Kayu meranti 0.0018 M³ x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 25,077.00

6.14.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0005 Oh x Rp. 175,000 = Rp. 87.50
Jumlah (2) = Rp. 26,587.50
Jumlah (1) +(2) = Rp. 51,664.50
PBA. Hal. 3
PBA 6.15 1 M² Pasang kawat burung
6.15.1 Bahan
- Kawat burung 1.100 M² x Rp. 12,710 = Rp. 13,981.00
- Paku biasa ½" - 1" 0.020 Kg x Rp. 18,000 = Rp. 360.00
- Kayu meranti 0.0018 M³ x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 23,746.00

6.15.2. Tenaga
- Pekerja 0.100 Oh x Rp. 100,000 = Rp. 10,000.00
- Tukang kayu 0.100 Oh x Rp. 150,000 = Rp. 15,000.00
- Kepala tukang 0.010 Oh x Rp. 150,000 = Rp. 1,500.00
- Mandor 0.0005 Oh x Rp. 175,000 = Rp. 87.50
Jumlah (2) = Rp. 26,587.50
Jumlah (1) +(2) = Rp. 50,333.50

PBA 6.16 1 M² Pasang jendela nako dan teralis


6.16.1 Bahan
- Jendela nako 1.100 M² x Rp. 201,660 = Rp. 221,826.00
- Paku biasa ½" - 1" atau skrup 0.020 Kg x Rp. 18,000 = Rp. 360.00
- Besi strip # 12 mm 1.500 M² x Rp. 11,880 = Rp. 17,820.00
Jumlah (1) = Rp. 240,006.00

6.16.2. Tenaga
- Pekerja 0.200 Oh x Rp. 100,000 = Rp. 20,000.00
- Tukang kayu 0.200 Oh x Rp. 150,000 = Rp. 30,000.00
- Kepala tukang 0.020 Oh x Rp. 150,000 = Rp. 3,000.00
- Mandor 0.001 Oh x Rp. 175,000 = Rp. 175.00
Jumlah (2) = Rp. 53,175.00
Jumlah (1) +(2) = Rp. 293,181.00

PBA 6.17 1 M' Pasang talang datar, seng bjls 35


6.17.1 Bahan
- Seng plat 3' x 6' bjls 35 0.500 Lbr x Rp. 115,500 = Rp. 57,750.00
- Paku biasa ½" - 1" atau skrup 0.015 Kg x Rp. 18,000 = Rp. 270.00
- Kayu meranti 0.0096 M³ x Rp. 5,225,000 = Rp. 50,160.00
- Flincote / meni besi 0.250 Kg x Rp. 25,410 = Rp. 6,352.50
Jumlah (1) = Rp. 114,532.50

6.17.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang kayu 0.400 Oh x Rp. 150,000 = Rp. 60,000.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.00125 Oh x Rp. 175,000 = Rp. 218.75
Jumlah (2) = Rp. 78,968.75
Jumlah (1) +(2) = Rp. 193,501.25

PBA 6.18 1 M' Pasang talang miring, seng bjls 35


6.18.1 Bahan
- Seng plat 3' x 6' bjls 35 0.500 Lbr x Rp. 115,500 = Rp. 57,750.00
- Paku biasa ½" - 1" atau skrup 0.015 Kg x Rp. 18,000 = Rp. 270.00
- Kayu meranti 0.019 M³ x Rp. 5,225,000 = Rp. 99,275.00
- Flincote / meni besi 0.300 Kg x Rp. 25,410 = Rp. 7,623.00
Jumlah (1) = Rp. 164,918.00

6.18.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang kayu 0.400 Oh x Rp. 150,000 = Rp. 60,000.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.00125 Oh x Rp. 175,000 = Rp. 218.75
Jumlah (2) = Rp. 78,968.75
Jumlah (1) +(2) = Rp. 243,886.75
PBA. Hal. 4
PBA 6.19 1 M' Pasang talang ½ lingkaran D-10 cm, seng bjls 35

6.19.1 Bahan
- Seng plat 3' x 6' bjls 35 0.300 Lbr x Rp. 115,500 = Rp. 34,650.00
- Paku biasa ½" - 1" atau skrup 0.100 Kg x Rp. 18,000 = Rp. 1,800.00
- Kayu meranti 0.019 M³ x Rp. 5,225,000 = Rp. 99,275.00
- Besi strip 0.500 Kg x Rp. 11,880 = Rp. 5,940.00
Jumlah (1) = Rp. 141,665.00

6.19.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang kayu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.00125 Oh x Rp. 175,000 = Rp. 218.75
Jumlah (2) = Rp. 56,468.75
Jumlah (1) +(2) = Rp. 198,133.75

PBA 6.20 1 M' Pasang talang ½ lingkaran D-10 cm, seng bjls 30

6.20.1 Bahan
- Seng plat 3' x 6' bjls 30 0.300 Lbr x Rp. 103,950 = Rp. 31,185.00
- Paku biasa ½" - 1" atau skrup 0.100 Kg x Rp. 18,000 = Rp. 1,800.00
- Kayu meranti 0.019 M³ x Rp. 5,225,000 = Rp. 99,275.00
- Besi strip 0.500 Kg x Rp. 11,880 = Rp. 5,940.00
Jumlah (1) = Rp. 138,200.00

6.20.2. Tenaga
- Pekerja 0.150 Oh x Rp. 100,000 = Rp. 15,000.00
- Tukang kayu 0.250 Oh x Rp. 150,000 = Rp. 37,500.00
- Kepala tukang 0.025 Oh x Rp. 150,000 = Rp. 3,750.00
- Mandor 0.00125 Oh x Rp. 175,000 = Rp. 218.75
Jumlah (2) = Rp. 56,468.75
Jumlah (1) +(2) = Rp. 194,668.75
PBA. Hal. 5
DAFTAR HARGA SATUAN UPAH DAN BAHAN
PEKERJAAN PEMBANGUNAN GEDUNG NEGARA
TAHUN ANGGARAN 2018

NO. URAIAN HARGA UPAH HARGA SATUAN

1 2 3 4

1 Pekerja @Rp. 100,000.00 / Org/Hari


2 Mandor @Rp. 175,000.00 / OH
3 Tukang Batu @Rp. 150,000.00 / OH
4 Tukang Kayu @Rp. 150,000.00 / OH
5 Tukang Besi @Rp. 150,000.00 / OH
6 Tukang Keramik @Rp. 150,000.00 / OH
7 Tukang Plafond @Rp. 150,000.00 / OH
8 Tukang Pasang Pipa @Rp. 150,000.00 / OH
9 Tukang Cat @Rp. 150,000.00 / OH
10 Kepala Tukang @Rp. 150,000.00 / OH
11 Jaga Malam @Rp. 150,000.00 / OM

NO. URAIAN HARGA BAHAN HARGA SATUAN

1 2 3 4

A TIMBUNAN / GALIAN
1 Tanah Timbun/Merah @Rp. 145,000.00 / M3
2 Pasir Timbun / Urug @Rp. 130,000.00 / M3
3 Pasir Pasang @Rp. 265,000.00 / M3
4 Pasir beton @Rp. 300,000.00 / M3
5 Sirtu @Rp. 165,000.00 / M3
6 Tanah Humus @Rp. 180,000.00 / M3
B BAHAN PEREKAT
1 Portland Cement (PC) @Rp. 1,400.00 / Kg
2 Cement Putih @Rp. 5,000.00 / Kg
3 Lem Kayu @Rp. 37,400.00 / Kg
4 Lem Vinyl / Karet @Rp. 44,900.00 / Kg
5 Perekat Kaca @Rp. 76,500.00 / Kg
6 Waterfroof @Rp. 65,000.00 / Kg
C BATU / BATU CETAKAN
1 Kolom beton Pracetak @Rp. 315,000.00 / Btg
2 Koral 2/3 @Rp. 315,000.00 / M3
3 Batu Krikil / Koral 3 - 5 cm @Rp. 215,900.00 / M3
4 Batu Krikil / Koral 5 - 7 cm @Rp. 205,000.00 / M3
5 Batu Krikil / Koral 7 - 10 cm @Rp. 185,000.00 / M3
6 Batu Belah/Kali 10 - 15 cm @Rp. 165,000.00 / M3
7 Batu Belah/Kali 15 - 20 cm @Rp. 145,000.00 / M3
8 Batu Pecah 1 - 2 cm @Rp. 215,000.00 / M3
9 Batu Pecah 2 - 3 cm @Rp. 205,000.00 / M3
10 Batu Pecah 3 - 5 cm @Rp. 187,500.00 / M3
11 Batu Pecah 5 - 7 cm @Rp. 165,000.00 / M3
12 Batu Kacang /jagung 0,5 - 1 cm @Rp. 225,000.00 / M3
13 Batu Splyt @Rp. 230,000.00 / M3
14 Batu Bata biasa 5x10x20 cm @Rp. 900.00 / Bh
15 Batu Bata Mesin 5x10x20 cm @Rp. 1,300.00 / Bh
1 2 3 4

16 Batu Bataco 6x12x24 cm @Rp. 9,500.00 / Bh


17 Batu Krawang 10x10x20 cm @Rp. 7,500.00 / Bh
18 Batu Krawang 10x15x15 cm @Rp. 8,000.00 / Bh
19 Batu Krawang 10x20x20 cm @Rp. 8,500.00 / Bh
20 Concrete Block (CB) 10 @Rp. 900.00 / Bh
21 Concrete Block (CB) 15 @Rp. 4,000.00 / Bh
22 Concrete Block (CB) 20 @Rp. 5,500.00 / Bh
23 Bondbeam 40x20x20 cm @Rp. 47,500.00 / Bh
24 Con Block warna type Holland tb 6 cm @Rp. 4,500.00 / Bh
25 Con Block warna type Uni pave tb 6 cm @Rp. 4,500.00 / Bh
26 Con Block warna type Dosex Six tb 6 cm @Rp. 4,500.00 / Bh
25 Con Block warna type Hexagon tb 6 cm @Rp. 4,500.00 / Bh
26 Con Block K 125 @Rp. 4,500.00 / Bh
27 Con Block K 175 @Rp. 5,500.00 / Bh
D KAYU / LANGIT - LANGIT
1 Balok Kayu Jati @Rp. 23,925,000.00 / M3
2 Papan Kayu Jati @Rp. 24,104,440.00 / M3
3 Balok Kayu Damar Laut @Rp. 9,350,000.00 / M3
4 Papan Kayu Damar Laut @Rp. 9,650,000.00 / M3
5 Balok Kayu Meranti Batu @Rp. 9,075,000.00 / M3
6 Papan Kayu Meranti Batu @Rp. 9,375,000.00 / M3
7 Balok Kayu Kapur @Rp. 6,490,000.00 / M3
8 Papan kayu Kapur @Rp. 6,790,000.00 / M3
9 Balok Kayu Meranti Kls I @Rp. 5,225,000.00 / M3
10 Papan Kayu Meranti Kls I @Rp. 5,475,000.00 / M3
11 Kayu Sembarang/Bekisting @Rp. 3,107,500.00 / M3
12 Kayu Bakar @Rp. 325,000.00 / M3
13 Papan Lambersering/Rider @Rp. 315,000.00 / M2
14 Kayu Lat Asbes 5x30x400 mm @Rp. 15,000.00 / Btg
15 Kayu Kaso 5 - 7 /400 cm @Rp. 87,780.00 / Btg
16 Kayu Dolken / Kayu Laut Ø 7,5 - 10 / 400 cm @Rp. 19,250.00 / Btg
17 Bambu Ø 6 - 8 /600 cm @Rp. 13,750.00 / Btg
18 Bilik Bambu @Rp. 16,340.00 / M2
19 Kayu Profil 1" @Rp. 6,270.00 / M'
20 Kayu Profil 2" @Rp. 12,540.00 / M'
21 Kayu Profil 3" @Rp. 18,810.00 / M'
22 Kayu Profil 4" @Rp. 25,080.00 / M'
23 Profil Gypsum 2" @Rp. 8,000.00 / M'
24 Profil Gypsum 3" @Rp. 9,500.00 / M'
25 Profil Gypsum 4" @Rp. 12,500.00 / M'
26 Profil Gypsum 6" @Rp. 15,000.00 / M'
27 Plywood 120x240 tbl. 18 mm @Rp. 233,640.00 / Lbr
28 Plywood 120x240 tbl. 12 mm @Rp. 155,760.00 / Lbr
29 Plywood 120x240 tbl. 9 mm @Rp. 116,820.00 / Lbr
30 Plywood 120x240 tbl. 6 mm @Rp. 77,880.00 / Lbr
31 Plywood 120x240 tbl. 4 mm @Rp. 51,920.00 / Lbr
32 Teakwood 120x240 tbl. 3 mm @Rp. 54,450.00 / Lbr
33 Triplek Jati 120x240 tbl. 3 mm @Rp. 85,250.00 / Lbr
34 Triplek Sungkai 120x240 tbl. 3 mm @Rp. 79,750.00 / Lbr
35 Formika 120x240 @Rp. 74,250.00 / Lbr
36 Soft Board 120x240 tbl. 4 mm @Rp. 55,990.00 / Lbr
1 2 3 4

37 Soft Board 120x240 tbl. 6 mm @Rp. 84,150.00 / Lbr


38 Soft Board 120x240 tbl. 9 mm @Rp. 126,230.00 / Lbr
39 Soft Board 120x240 tbl. 12 mm @Rp. 168,250.00 / Lbr
40 Gypsum 120x240 tbl. 6 mm @Rp. 65,000.00 / Lbr
41 Gypsum 120x240 tbl. 9 mm @Rp. 115,000.00 / Lbr
42 Gypsum 120x240 tbl. 12 mm @Rp. 125,000.00 / Lbr
43 Asbes Lokal 100x100 cm @Rp. 9,350.00 / Lbr
44 Asbes Atrisco 100x100 cm t= 4 mm @Rp. 11,550.00 / Lbr
45 Asbes Atrisco 100x100 cm t= 5 mm @Rp. 14,440.00 / Lbr
46 Asbes Atrisco 100x100 cm t= 6 mm @Rp. 17,330.00 / Lbr
47 Akustik 30x30 cm @Rp. 8,540.00 / Lbr
48 Akustik 30x60 cm @Rp. 17,070.00 / Lbr
49 Akustik 60x120 cm @Rp. 68,290.00 / Lbr
50 Rangka Furing Ceiling Gypsum @Rp. 52,250.00 / M2
51 Rangka Furing Dinding Gypsum @Rp. 95,000.00 / M2
52 Tepung Dempul @Rp. 10,450.00 / Kg
53 Kain kasa/Paper Tape @Rp. 57,750.00 / Roll
E BESI / ALUMINIUM
1 Besi Beton polos @Rp. 19,500.00 / Kg
2 Besi Beton Ulir @Rp. 20,000.00 / Kg
3 Besi Profil WF/INP @Rp. 15,950.00 / Kg
4 Besi siku @Rp. 11,990.00 / Kg
5 Besi CNP @Rp. 13,090.00 / Kg
6 Besi Plat Strip @Rp. 11,880.00 / Kg
7 Besi Plat Polos @Rp. 13,630.00 / Kg
8 Kawat Besi Beton @Rp. 19,500.00 / Kg
9 Kawat Licin / Seng Polos @Rp. 22,530.00 / Kg
10 Kawat Duri @Rp. 4,030.00 / M'
11 Kawat Nyamuk @Rp. 11,980.00 / M2
12 Kawat Kasa @Rp. 13,920.00 / M2
13 Kawat Harmonika # 1" @Rp. 23,600.00 / M2
14 Kawat Burung @Rp. 12,710.00 / M2
15 Pagar kawat BRC 120 Polos @Rp. 235,950.00 / Lbr
16 Pintu Besi @Rp. 816,750.00 / M2
17 Pintu gulung Besi @Rp. 828,850.00 / M2
18 Pintu Lipat Besi @Rp. 837,320.00 / M2
19 Pintu Rolling Door @Rp. 465,850.00 / M2
20 Jerajak besi Bermotif @Rp. 347,270.00 / M2
21 Jerajak Besi Strip @Rp. 312,180.00 / M2
22 Rangka Baja Ringan @Rp. 177,870.00 / M2
23 Kosen Pintu Aluminium (80 x 210) Coklat @Rp. 550,000.00 / Bh
24 Kosen Pintu Aluminium (80 x 210) Putih @Rp. 371,470.00 / Bh
25 Kosen Jendela aluminium (120x60) Coklat @Rp. 350,000.00 / Bh
26 Kosen Jendela aluminium (120x60) Putih @Rp. 248,050.00 / Bh
27 Pintu Aluminium ( 80 x 210) Coklat @Rp. 1,500,000.00 / Bh
28 Pintu Aluminium ( 80 x 210) Putih @Rp. 609,840.00 / Bh
29 Jendela Aluminium + Kaca 5 mm (120 x 60) Coklat @Rp. 750,000.00 / Bh
30 Jendela Aluminium + Kaca 5 mm (120 x 60) Putih @Rp. 261,360.00 / Bh
31 Kosen Pintu / Jendela Aluminium Coklat @Rp. 78,650.00 / M'
1 2 3 4

32 Kosen Pintu / Jendela Aluminium Putih @Rp. 66,550.00 / M'


33 Daun Jendela Aluminium Coklat @Rp. 54,450.00 / M'
34 Daun Jendela Aluminium Putih @Rp. 48,400.00 / M'
35 Profil Aluminium T @Rp. 8,470.00 / M'
36 Ventions Blinds @Rp. 163,350.00 / M2
37 Verticals Blinds @Rp. 175,450.00 / M2
38 Bingkai Naco Niki Hitam @Rp. 201,660.00 / M2
39 Bingkai Naco Niki Putih @Rp. 168,060.00 / M2
40 Paku Beton 0,5 - 2" @Rp. 310.00 / Bh
41 Paku Beton 2" - 5" @Rp. 530.00 / Bh
42 Paku Biasa 0,5 - 2" @Rp. 18,000.00 / Kg
43 Paku Biasa 2" - 5" @Rp. 18,000.00 / Kg
44 Sekrup macam ukuran @Rp. 25,000.00 / Kg
45 Sekrup 0,5 - 2" @Rp. 500.00 / Bh
46 Sekrup fisher @Rp. 500.00 / Bh
47 Baut Ø 5/8" - 8" @Rp. 21,000.00 / Bh
48 Baut Angker Ø 3/4" - 10" @Rp. 50,000.00 / Bh
49 Baut Ramset / Dina Bolt @Rp. 2,500.00 / Bh
50 Rangka Atap Twin light @Rp. 475,000.00 / M2
F PENUTUP LANTAI DAN DINDING
1 Ubin Granito 30 x 30 cm @Rp. 26,260.00 / Bh
2 Ubin Granito 40 x 40 cm @Rp. 46,590.00 / Bh
3 Ubin Granito 60 x 60 cm @Rp. 135,000.00 / Bh
4 Ubin Mosaik 30 x 30 cm @Rp. 13,920.00 / Bh
5 Ubin Marmer Ex. DN @Rp. 261,970.00 / M2
6 Ubin teralux marmer 30 x 30 cm @Rp. 27,230.00 / Bh
7 Ubin teralux marmer 40 x 40 cm @Rp. 48,400.00 / Bh
8 Ubin teralux marmer 60 x 60 cm @Rp. 109,510.00 / Bh
9 Ubin keramik 10 x 20 cm @Rp. 1,210.00 / Bh
10 Ubin keramik 15 x 15 cm @Rp. 1,400.00 / Bh
11 Ubin keramik 20 x 20 cm @Rp. 2,490.00 / Bh
12 Ubin keramik 20 x 25 cm @Rp. 3,150.00 / Bh
13 Ubin keramik 25 x 25 cm @Rp. 3,870.00 / Bh
14 Ubin keramik 30 x 30 cm @Rp. 5,570.00 / Bh
15 Ubin keramik 30 x 30 cm anti slip @Rp. 6,290.00 / Bh
16 Ubin keramik 40 x 40 cm @Rp. 9,680.00 / Bh
17 Ubin keramik artistik 5 x 20 cm @Rp. 910.00 / Bh
18 Ubin keramik artistik 10 x 10 cm @Rp. 910.00 / Bh
19 Ubin keramik artistik 10 x 20 cm @Rp. 1,760.00 / Bh
20 Ubin keramik Essenza 30 x 30 cm @Rp. 21,180.00 / Bh
21 Ubin keramik Essenza 40 x 40 cm @Rp. 37,630.00 / Bh
22 Porselin 11 x 11 cm Putih @Rp. 1,210.00 / Bh
23 Porselin 11 x 11 cm, warna @Rp. 145.00 / Bh
24 Porselin 15 x 15 cm, putih @Rp. 2,300.00 / Bh
25 Porselin 15 x 15 cm, warna @Rp. 2,540.00 / Bh
26 Plint ubin teralux marmer 10 x 30 cm @Rp. 16,340.00 / Bh
27 Plint ubin teralux marmer 10 x 40 cm @Rp. 29,040.00 / Bh
28 Plint ubin teralux marmer 10 x 60 cm @Rp. 65,700.00 / Bh
29 Plint ubin granito 10 x 30 cm @Rp. 27,950.00 / Bh
30 Plint ubin granito 10 x 40 cm @Rp. 62,800.00 / Bh
1 2 3 4

31 Plint ubin granito 10 x 60 cm @Rp. 157,180.00 / Bh


32 Plint ubin keramik 10 x 30 cm @Rp. 4,110.00 / Bh
33 Plint ubin keramik 10 x 40 cm @Rp. 5,690.00 / Bh
34 Plint ubin keramik 10 x 60 cm @Rp. 8,110.00 / Bh
35 Plint ubin keramik 15 x 30 cm @Rp. 5,810.00 / Bh
36 Plint ubin keramik 15 x 40 cm @Rp. 7,740.00 / Bh
37 Plint ubin keramik 15 x 60 cm @Rp. 11,620.00 / Bh
38 Batu Lapis Dinding 7x3x24 @Rp. 2,040.00 / Bh
39 Batu Tempel Hitam @Rp. 104,500.00 / M2
40 Batu Poros @Rp. 114,680.00 / M2
41 Carpet @Rp. 90,750.00 / M2
42 Carpet 80 % wool, 20 % nylon @Rp. 87,450.00 / M2
43 Feltex carpet 100 % wool-T-21 @Rp. 85,250.00 / M2
44 Underlyer tebal 6 mm / rubber corrugated @Rp. 104,500.00 / M2
45 Vynil asbes 30 x 30 cm @Rp. 8,230.00 / Bh
46 Vynil karet 30 x 30 cm KL I @Rp. 9,800.00 / Bh
47 Vynil karet 30 x 30 cm KL II @Rp. 9,080.00 / Bh
48 Vynil motif kembang ex DN 30 x 30 cm @Rp. 9,440.00 / Bh
49 Vynil wall covering lebar 50 cm @Rp. 63,250.00 / M2
50 Perquet Jati @Rp. 368,500.00 / M2
51 Gymfloor @Rp. 79,750.00 / M2
52 Paku Pancing 60 - 230 @Rp. 720.00 / Bh
53 Sekrup 3,5" @Rp. 410.00 / Kg
54 Sekrup 3,5" @Rp. 20,350.00 / Kg
G PENUTUP ATAP
1 Atap Genteng Palentong @Rp. 1,670.00 / Bh
2 Atap Genteng Palentong super @Rp. 3,980.00 / Bh
3 Atap Genteng Kodok @Rp. 2,170.00 / Bh
4 Atap Genteng Beton @Rp. 5,970.00 / Bh
5 Atap Genteng Keramik @Rp. 11,390.00 / Bh
6 Atap Genteng Aspal @Rp. 11,320.00 / Lbr
7 Atap Genteng Metal/Multi Roof 35 @Rp. 64,130.00 / M2
8 Atap Genteng Asbes cement 0,35 @Rp. 66,790.00 / Lbr
9 Atap Sirap @Rp. 1,030.00 / Bh
10 Atap Aluminium gelombang tebal 0,55 @Rp. 127,000.00 / Lbr
11 Atap seng Gelombang 3' x 6' bjls 35 @Rp. 59,640.00 / Lbr
12 Atap seng Super Deck 3' x 6' tbl 0,30 @Rp. 68,750.00 / Lbr
13 Roof light fibreglass gelombang @Rp. 46,390.00 / Lbr
14 Atap Asbes Gelombang 1,8 x 1,05 tbl.4 mm @Rp. 59,380.00 / Lbr
15 Atap Asbes Gelombang 2,1 x 1,05 tbl.4 mm @Rp. 93,170.00 / Lbr
16 Atap Asbes Gelombang 2,4 x 1,05 tbl.4 mm @Rp. 108,130.00 / Lbr
17 Atap Asbes Gelombang 2,7 x 1,05 tbl.4 mm @Rp. 113,300.00 / Lbr
18 Atap Asbes Gelombang 1,8 x 0,92 tbl.5 mm @Rp. 70,950.00 / Lbr
19 Atap Asbes Gelombang 2,1 x 0,92 tbl.5 mm @Rp. 88,770.00 / Lbr
20 Atap Asbes Gelombang 2,4 x 0,92 tbl.5 mm @Rp. 97,020.00 / Lbr
21 Atap Asbes Gelombang 2,7 x 0,92 tbl.5 mm @Rp. 106,810.00 / Lbr
22 Atap Asbes Gelombang 1,8 x 1,08 tbl.6 mm @Rp. 103,620.00 / Lbr
23 Atap Asbes Gelombang 2,1 x 1,08 tbl.6 mm @Rp. 120,450.00 / Lbr
24 Atap Asbes Gelombang 2,4 x 1,08 tbl.6 mm @Rp. 128,370.00 / Lbr
25 Atap Asbes Gelombang 2,7 x 1,08 tbl.6 mm @Rp. 155,430.00 / Lbr
26 Genteng bubung palentong @Rp. 9,350.00 / Bh
1 2 3 4

27 Genteng bubung palentong super @Rp. 12,740.00 / Bh


28 Genteng bubung kodok @Rp. 9,560.00 / Bh
29 Nok genteng beton @Rp. 13,440.00 / Bh
30 Nok genteng keramik @Rp. 15,040.00 / Bh
31 Nok Genteng Aspal @Rp. 29,350.00 / Bh
32 Nok Genteng Metal/Multi Roof (decra bond) @Rp. 41,140.00 / Bh
33 Nok Genteng Asbes cement 0,35 @Rp. 33,770.00 / Lbr
34 Nok Aluminium standard 40 cm 18 swg22 @Rp. 65,000.00 / M2
35 Bubung/Nok Stel Gelombang 0,92 m' tbl.5 mm @Rp. 19,590.00 / Lbr
36 Bubung/Nok Stel Gelombang 1,05 m' tbl.4 mm @Rp. 25,990.00 / Lbr
37 Bubung/Nok Stel Gelombang 1,08 m' tbl.6 mm @Rp. 28,510.00 / Lbr
38 Bubung/Nok Paten 0,92 m' tbl.5 mm @Rp. 36,810.00 / Lbr
39 Bubung/Nok Paten 1,05 m' tbl.4 mm @Rp. 30,950.00 / Lbr
40 Bubung/Nok Paten 1,08 m' tbl.6 mm @Rp. 42,960.00 / Lbr
41 Bubung/Nok Stel Rata 0,92 m' tbl.5 mm @Rp. 36,080.00 / Lbr
42 Bubung/Nok Stel Rata 1,05 m' tbl.4 mm @Rp. 30,250.00 / Lbr
43 Bubung/Nok Stel Rata 1,08 m' tbl.6 mm @Rp. 40,600.00 / Lbr
44 Seng Plat 3" x 6" bjls 35 @Rp. 115,500.00 / Lbr
45 Seng Plat 3" x 6" bjls 30 @Rp. 103,950.00 / Lbr
46 Plastic aerator @Rp. 27,500.00 / Bh
47 Sisalation / aluminium foil @Rp. 77,200.00 / M2
48 Paku seng + Ring karet @Rp. 25,000.00 / Kg
49 Paku seng + Ring karet @Rp. 410.00 / Bh
50 Paku hak panjang 15 cm @Rp. 30,530.00 / Kg
51 Atap Seng Alumi Zinc warna 0,35 @Rp. 75,000.00 / M2
52 Atap Twin light @Rp. 74,250.00 / M2
H KUNCI DAN KACA
1 Kunci tanam antik @Rp. 214,500.00 / Bh
2 Kunci tanam biasa @Rp. 195,000.00 / Bh
3 Kunci tanam kamar mandi @Rp. 54,690.00 / Bh
4 Kunci silinder @Rp. 34,490.00 / Bh
5 Kunci selot @Rp. 27,230.00 / Bh
6 Kunci lemari @Rp. 12,340.00 / Bh
7 Engsel pintu 4" @Rp. 35,000.00 / Bh
8 Engsel jendela 3" @Rp. 15,000.00 / Bh
9 Engsel angin @Rp. 25,050.00 / Bh
10 Kait angin @Rp. 25,000.00 / Bh
11 Rel pintu dorong @Rp. 160,330.00 / Bh
12 Sealent @Rp. 39,330.00 / Kg
13 Spring Knip @Rp. 9,080.00 / Bh
14 Door closer @Rp. 109,750.00 / Bh
15 Door handle @Rp. 113,010.00 / Bh
16 Door stoop @Rp. 38,120.00 / Bh
17 Espanyolet @Rp. 88,450.00 / Bh
18 Kaca Block 20 x 20 cm @Rp. 26,020.00 / Bh
19 Kaca polos tbl.3 mm @Rp. 87,120.00 / M2
20 Kaca polos tbl.5 mm @Rp. 175,000.00 / M2
21 Kaca polos tbl.8 mm @Rp. 232,320.00 / M2
22 Kaca Reyben tbl.5 mm @Rp. 225,000.00 / M2
23 Kaca Reyben tbl.8 mm @Rp. 308,980.00 / M2
24 Kaca Buram tbl.3 mm @Rp. 72,600.00 / M2
1 2 3 4

25 Kaca Buram tbl.5 mm @Rp. 111,320.00 / M2


26 Kaca buram tbl.8 mm @Rp. 193,600.00 / M2
27 Kaca cermin tbl.5 mm @Rp. 161,700.00 / M2
28 Kaca cermin tbl.6 mm @Rp. 194,040.00 / M2
29 Kaca cermin tbl.8 mm @Rp. 258,720.00 / M2
30 Kaca patri @Rp. 169,400.00 / M2
31 Kaca Wireglass @Rp. 151,250.00 / M2
32 Kaca Reyben Naco 30 x 60 cm tbl.5 mm @Rp. 13,590.00 / Lbr
33 Kaca Bening Naco 30 x 60 cm tbl.5 mm @Rp. 10,730.00 / Lbr

I CAT / MINYAK
1 Cat dasar @Rp. 17,500.00 / Kg
2 Cat Tembok setara Vinilex @Rp. 75,000.00 / Kg
3 Cat Minyak untuk kayu @Rp. 35,700.00 / Kg
4 Cat Minyak untuk Besi @Rp. 39,330.00 / Kg
5 Cat Menie kayu @Rp. 20,570.00 / Kg
6 Cat Menie besi @Rp. 25,410.00 / Kg
7 Cat sending @Rp. 54,450.00 / Kg
8 Cat Melamix @Rp. 59,290.00 / Kg
9 Cat Vernis Jadi @Rp. 48,280.00 / Kg
10 Plamir @Rp. 17,500.00 / Kg
11 Dempul gypsum @Rp. 12,500.00 / Kg
12 Dempul Cat @Rp. 15,000.00 / Kg
13 Minyak Cat @Rp. 11,010.00 / Kg
14 Minyak Bekisting @Rp. 9,000.00 / Ltr
15 Residu / Kolter @Rp. 9,000.00 / Ltr
16 Soda api @Rp. 12,100.00 / Kg
17 Sabun @Rp. 10,290.00 / Kg
18 Kuas @Rp. 10,000.00 / Bh
19 Ampelas / Kertas pasir @Rp. 2,500.00 / Lbr
20 Wall paper @Rp. 30,610.00 / M2
J SANITASI / PIPA
1 Kloset duduk / monoblok lengkap tangki @Rp. 1,931,600.00 / Bh
2 Kloset duduk / monoblok tanpa tangki @Rp. 1,391,500.00 / Bh
3 Kloset jongkok porselin @Rp. 225,280.00 / Bh
4 Bakkif Porselin @Rp. 3,025,000.00 / Bh
5 Wastafel @Rp. 526,350.00 / Bh
6 Urinoir @Rp. 557,480.00 / Bh
7 Kran air Ø 1/2" - 3/4" @Rp. 27,350.00 / Bh
8 Kran air leher angsa Ø 1/2" @Rp. 77,200.00 / Bh
9 Kran shower @Rp. 92,570.00 / Bh
10 Kran Cebok @Rp. 72,240.00 / Bh
11 Bak fibreglass 0,3 M3 @Rp. 181,500.00 / Bh
12 Bak fibreglass 1 M3 @Rp. 522,720.00 / Bh
13 Bak cuci piring stainless 2 lobang @Rp. 466,700.00 / Bh
14 Bak cuci piring teraso 2 lobang @Rp. 272,250.00 / Bh
15 Tempat sabun keramik @Rp. 56,270.00 / Bh
16 Floor drain Ø 4" steinless @Rp. 15,000.00 / Bh
17 Stop kran Ø 3/4" @Rp. 27,500.00 / Bh
18 Tutup bak air Ø 1" Kuningan @Rp. 12,500.00 / Bh
19 Instalasi air bersih @Rp. 100,000.00 / Ttk
1 2 3 4

20 Instalasi air kotor/limbah @Rp. 125,000.00 / Ttk


21 Buis Beton 1/2 Ø 15 cm @Rp. 11,250.00 / M'
22 Buis Beton 1/2 Ø 20 cm @Rp. 17,790.00 / M'
23 Buis Beton 1/2 Ø 30 cm @Rp. 20,090.00 / M'
24 Buis Beton Ø 15 cm @Rp. 19,240.00 / M'
25 Buis Beton Ø 20 cm @Rp. 27,350.00 / M'
26 Buis Beton Ø 30 cm @Rp. 56,270.00 / M'
27 Buis Beton Ø 40 cm @Rp. 63,400.00 / M'
28 Buis Beton Ø 50 cm @Rp. 95,950.00 / M'
29 Buis Beton Ø 60 cm @Rp. 136,000.00 / M'
30 Buis Beton Ø 80 cm @Rp. 201,100.00 / M'
31 Buis Beton Ø 100 cm @Rp. 345,820.00 / M'
32 Pipa PVC Tipe AW Ø 1/2" @Rp. 25,300.00 / Btg
33 Pipa PVC Tipe AW Ø 3/4" @Rp. 7,440.00 / Btg
34 Pipa PVC Tipe AW Ø 1" @Rp. 13,620.00 / Btg
35 Pipa PVC Tipe AW Ø 1 1/2" @Rp. 19,670.00 / Btg
36 Pipa PVC Tipe AW Ø 2" @Rp. 23,190.00 / Btg
37 Pipa PVC Tipe AW Ø 2 1/2" @Rp. 26,620.00 / Btg
38 Pipa PVC Tipe AW Ø 3" @Rp. 29,840.00 / Btg
39 Pipa PVC Tipe AW Ø 4" @Rp. 49,920.00 / Btg
40 Pipa Besi Hitam Ø 1/2" @Rp. 14,770.00 / Btg
41 Pipa Besi Hitam Ø 3/4" @Rp. 20,140.00 / Btg
42 Pipa Besi Hitam Ø 1" @Rp. 29,520.00 / Btg
43 Pipa Besi Hitam Ø 1 1/2" @Rp. 37,580.00 / Btg
44 Pipa Besi Hitam Ø 2" @Rp. 47,600.00 / Btg
45 Pipa Besi Hitam Ø 2 1/2" @Rp. 50,220.00 / Btg
46 Pipa Galvanis Ø 1/2" @Rp. 14,770.00 / Btg
47 Pipa Galvanis Ø 3/4" @Rp. 20,140.00 / Btg
48 Pipa Galvanis Ø 1" @Rp. 29,520.00 / Btg
49 Pipa Galvanis Ø 1 1/4" @Rp. 33,560.00 / Btg
50 Pipa Galvanis Ø 1 1/2" @Rp. 37,580.00 / Btg
51 Pipa Galvanis Ø 2" @Rp. 47,600.00 / Btg
52 Pipa Galvanis Ø 2 1/2" @Rp. 52,440.00 / Btg
53 Fitting Pipa AW Ø 1" @Rp. /
54 Knee AW 1" @Rp. 5,230.00 / Bh
55 Tee AW 1" @Rp. 7,150.00 / Bh
56 Socht AW 1" @Rp. 4,680.00 / Bh
57 F-Knee 1" @Rp. / Bh
58 F-Tee 1" @Rp. 11,500.00 / Bh
59 Bocht LL-D 1" @Rp. 24,750.00 / Bh
60 Union Socht 1" @Rp. 7,430.00 / Bh
61 D-Nipple 1" @Rp. 18,150.00 / Bh
62 Water Moer 1" @Rp. 29,500.00 / Bh
63 Tali Ijuk @Rp. 4,500.00 / Kg
J SANITASI / PIPA
1 Kloset duduk / monoblok lengkap tangki @Rp. 1,931,600.00 / Bh
2 Kloset duduk / monoblok tanpa tangki @Rp. 1,391,500.00 / Bh
3 Kloset jongkok porselin @Rp. 225,280.00 / Bh
4 Bakkif Porselin @Rp. 3,025,000.00 / Bh
5 Wastafel @Rp. 526,350.00 / Bh
6 Urinoir @Rp. 557,480.00 / Bh
1 2 3 4

7 Kran air Ø 1/2" - 3/4" @Rp. 27,350.00 / Bh


8 Kran air leher angsa Ø 1/2" @Rp. 77,200.00 / Bh
9 Kran shower @Rp. 92,570.00 / Bh
10 Kran Cebok @Rp. 72,240.00 / Bh
11 Bak fibreglass 0,3 M3 @Rp. 181,500.00 / Bh
12 Bak fibreglass 1 M3 @Rp. 522,720.00 / Bh
13 Bak cuci piring stainless 2 lobang @Rp. 466,700.00 / Bh
14 Bak cuci piring teraso 2 lobang @Rp. 272,250.00 / Bh
15 Tempat sabun keramik @Rp. 56,270.00 / Bh
16 Floor drain Ø 4" steinless @Rp. 15,000.00 / Bh
17 Stop kran Ø 3/4" @Rp. 27,500.00 / Bh
18 Tutup bak air Ø 1" Kuningan @Rp. 12,500.00 / Bh
19 Instalasi air bersih @Rp. 100,000.00 / Ttk
20 Instalasi air kotor/limbah @Rp. 125,000.00 / Ttk
21 Buis Beton 1/2 Ø 15 cm @Rp. 11,250.00 / M'
22 Buis Beton 1/2 Ø 20 cm @Rp. 17,790.00 / M'
23 Buis Beton 1/2 Ø 30 cm @Rp. 20,090.00 / M'
24 Buis Beton Ø 15 cm @Rp. 19,240.00 / M'
25 Buis Beton Ø 20 cm @Rp. 27,350.00 / M'
26 Buis Beton Ø 30 cm @Rp. 56,270.00 / M'
27 Buis Beton Ø 40 cm @Rp. 63,400.00 / M'
28 Buis Beton Ø 50 cm @Rp. 95,950.00 / M'
29 Buis Beton Ø 60 cm @Rp. 136,000.00 / M'
30 Buis Beton Ø 80 cm @Rp. 201,100.00 / M'
31 Buis Beton Ø 100 cm @Rp. 345,820.00 / M'
32 Bodeam 30 x 60 cm @Rp. 25,300.00 / Bh
33 Pipa PVC Tipe AW Ø 1/2" @Rp. 5,540.00 / M'
34 Pipa PVC Tipe AW Ø 3/4" @Rp. 7,440.00 / M'
35 Pipa PVC Tipe AW Ø 1" @Rp. 13,620.00 / M'
36 Pipa PVC Tipe AW Ø 1 1/2" @Rp. 19,670.00 / M'
37 Pipa PVC Tipe AW Ø 2" @Rp. 23,190.00 / M'
38 Pipa PVC Tipe AW Ø 2 1/2" @Rp. 26,620.00 / M'
39 Pipa PVC Tipe AW Ø 3" @Rp. 29,840.00 / M'
40 Pipa PVC Tipe AW Ø 4" @Rp. 49,920.00 / M'
41 Pipa Besi Hitam Ø 1/2" @Rp. 14,770.00 / M'
42 Pipa Besi Hitam Ø 3/4" @Rp. 20,140.00 / M'
43 Pipa Besi Hitam Ø 1" @Rp. 29,520.00 / M'
44 Pipa Besi Hitam Ø 1 1/2" @Rp. 37,580.00 / M'
45 Pipa Besi Hitam Ø 2" @Rp. 47,600.00 / M'
46 Pipa Besi Hitam Ø 2 1/2" @Rp. 50,220.00 / M'
47 Pipa Galvanis Ø 1/2" @Rp. 14,770.00 / M'
48 Pipa Galvanis Ø 3/4" @Rp. 20,140.00 / M'
49 Pipa Galvanis Ø 1" @Rp. 29,520.00 / M'
50 Pipa Galvanis Ø 1 1/4" @Rp. 33,560.00 / M'
51 Pipa Galvanis Ø 1 1/2" @Rp. 37,580.00 / M'
52 Pipa Galvanis Ø 2" @Rp. 47,600.00 / M'
53 Pipa Galvanis Ø 2 1/2" @Rp. 52,440.00 / M'
Fitting Pipa AW Ø 1" yang terdiri dari :
54 Fitting Knee AW 1" @Rp. 5,230.00 / Bh
55 Fitting Tee AW 1" @Rp. 7,150.00 / Bh
56 Fitting Socht AW 1" @Rp. 4,680.00 / Bh
1 2 3 4

57 Bocht LL-D 1" @Rp. 24,750.00 / Bh


58 Union Socht 1" @Rp. 7,430.00 / Bh
59 D-Nipple 1" @Rp. 18,150.00 / Bh
K LISTRIK / ACSESORIES
1 Lampu TL 1 x 20 W Lengkap Kotak @Rp. 54,450.00 / Set
2 Lampu TL 1 x 40 W Lengkap Kotak @Rp. 60,500.00 / Set
3 Lampu TL 2 x 20 W Lengkap Kotak @Rp. 163,350.00 / Set
4 Lampu TL 2 x 40 W Lengkap Kotak @Rp. 183,920.00 / Set
5 Lampu TL Bambu 1 x 20 W Lengkap @Rp. 108,900.00 / Set
6 Lampu TL Bambu 1 x 40 W Lengkap @Rp. 123,420.00 / Set
7 Lampu XL 5 W + Fitting @Rp. 25,410.00 / Set
8 Lampu XL 8 W + Fitting @Rp. 27,230.00 / Set
9 Lampu XL 10 W + Fitting @Rp. 29,040.00 / Set
10 Lampu XL 14 W + Fitting @Rp. 33,280.00 / Set
11 Lampu XL 18 W + Fitting @Rp. 33,880.00 / Set
12 Lampu XL 24 W + Fitting @Rp. 38,720.00 / Set
13 Lampu Downlight 5 W lengkap @Rp. 54,450.00 / Set
14 Lampu Pijar 5 w + Fitting @Rp. 8,250.00 / Set
15 Lampu Pijar 10 w + Fitting @Rp. 8,800.00 / Set
16 Lampu Pijar 15 w + Fitting @Rp. 9,350.00 / Set
17 Lampu Pijar 20 w + Fitting @Rp. 9,900.00 / Set
18 Lampu Pijar 25 w + Fitting @Rp. 10,450.00 / Set
19 Lampu Pijar 40 w + Fitting @Rp. 11,550.00 / Set
20 Stop Kontak tanam @Rp. 10,290.00 / Bh
21 Saklar tunggal @Rp. 14,520.00 / Bh
22 Saklar ganda @Rp. 15,730.00 / Bh
23 Saklar Triple @Rp. 18,150.00 / Bh
24 Zekring box 1 grup @Rp. 26,620.00 / Unit
25 Zekring box 2 grup @Rp. 31,350.00 / Unit
26 Zekring box 3 grup @Rp. 38,500.00 / Unit
27 Zekring box 4 grup @Rp. 46,200.00 / Unit
28 MCB 2 Ampere @Rp. 35,200.00 / Unit
29 MCB 4 Ampere @Rp. 42,900.00 / Unit
30 MCB 6 Ampere @Rp. 67,760.00 / Unit
31 MCB 8 Ampere @Rp. 99,220.00 / Unit
32 Kabel Listrik NYA Ø 1,5 mm @Rp. 1,120.00 / M'
33 Kabel Listrik NYA Ø 2,5 mm @Rp. 1,930.00 / M'
34 Kabel Listrik NYA Ø 4 mm @Rp. 8,250.00 / M'
35 Kabel Listrik NYM 2 Ø 1,5 mm @Rp. 4,020.00 / M'
36 Kabel Listrik NYM 2 Ø 2,5 mm @Rp. 9,900.00 / M'
37 Kabel Listrik NYM 2 Ø 4 mm @Rp. 15,970.00 / M'
38 Instalasi Listrik titik api / Lampu nyala @Rp. 101,750.00 / Ttk
Medan, Maret 2008

Diketahui Oleh : Dibuat oleh : TIM TEKNIS


Kepala Dinas Penataan Ruang dan 1. Ir. Jeremias Sinaga, MAP (………….)
Permukiman Prov. Sumatera Utara
2. Ir. Herimas (………….)

3. H. Sugiarto Bharata, ST (………….)

4. Ali Muhar, ST (………….)


Ir. H. Syafruddin Siregar, MSi
Pembina Utama Muda 5. Sekula Karokaro, ST (………….)
NIP. 400025884
6. Ebenser Saragih, SE (………….)

7. Sahat Hasudungan, ST (………….)

8. Ir. Tanogara Siahaan (………….)

9. Ali Fauzen, ST (………….)

10. Naimul Ahmad R. ST (………….)

11. Chandra, ST (………….)


REKAPITULASI ANALISA

NO ANALISA URAIAN HARGA

Pekerjaan Persiapan
1 Anl. 6.1 1 M' Pagar sementara dari kayu tinggi 2 meter Rp. 230,172.50
2 Anl. 6.2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter Rp. 228,780.00
3 Anl. 6.3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter Rp. 109,523.75
4 Anl. 6.4 1 M' Pengukuran dan pemasangan bouwlank Rp. 86,777.50
5 Anl. 6.5 1 M² Pembuatan kantor sementara dengan lantai plesteran Rp. 13,282,016.70
6 Anl. 6.6 1 M² Pembuatan gudang semen dan alat - alat Rp. 281,159.00
7 Anl. 6.7 1 M² Pembuatan rumah jaga/ konstruksi kayu Rp. 615,282.40
8 Anl. 6.8 1 M² Membersihkan Lapangan dan peralatan Rp. 18,750.00
9 Anl. 6.9 1 M² Pembuatan bedeng buruh Rp. 948,098.90
10 Anl. 6.10 1 M² Pembuatan bak adukan ukuran (40 x 50 x 20) cm Rp. 60,602.50
11 Anl. 6.11 1 M² Pembuatan Stegger dari bambu ukuran (40 x 50 x 20) cm Rp. 176,250.00
12 Anl. 6.12 1 M² Pembuatan jalan sementara Rp. 148,000.00
13 Anl. 6.13 1 M³ Bongkaran beton bertulang Rp. 724,975.00
14 Anl. 6.14 1 M³ Bongkaran dinding tembok bata merah Rp. 543,750.00
15 Anl. 6.15 1 M' Pasang pagar kawat jaring galvanis, tinggi 1,00 m Rp. 113,852.30
16 Anl. 6.16 1 M' Pasang pagar beton pracetak (5 x 50 x 213) cm Rp. 501,820.00

Pekerjaan Tanah
17 Anl. 6.1 1 M³ Galian tanah biasa sedalam 1 meter Rp. 47,000.00
18 Anl. 6.2 1 M³ Galian tanah biasa sedalam 2 meter Rp. 61,805.00
19 Anl. 6.3 1 M³ Galian tanah biasa sedalam 3 meter Rp. 86,362.50
20 Anl. 6.4 1 M³ Galian tanah keras sedalam 1 meter Rp. 73,350.00
21 Anl. 6.5 1 M³ Galian tanah cadas sedalam 1 meter Rp. 146,875.00
22 Anl. 6.6 1 M³ Galian tanah lumpur sedalam 1 meter Rp. 96,825.00
23 Anl. 6.7 1 M³ Pekerjaan Stripping setinggi 1 meter Rp. 5,875.00
24 Anl. 6.8 1 M³ Pembuangan tanah sejauh 150 meter Rp. 60,512.50
25 Anl. 6.9 1 M³ Urugan kembali Rp. 22,525.00
26 Anl. 6.10 1 M³ Pemadatan tanah Rp. 58,750.00
27 Anl. 6.11 1 M³ Urugan pasir Rp. 188,625.00
28 Anl. 6.12 1 M³ Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL Rp. 212,775.50
29 Anl. 6.13 1 M³ Lapisan pudel campuran 1 Kp : 5 TL Rp. 204,650.00
30 Anl. 6.14 1 M³ Utugan Tanah Rp. 206,625.00
31 Anl. 6.15 1 M³ Urugan sirtu Rp. 230,625.00
32 Anl. 6.16 1 M² Pembuatan jalan sementara, tebal 25 cm Rp. 123,525.00

Pekerjaan Pondasi
33 Anl. 6.1 1 M³ Pasangan pondasi batu kali, 1 Pc : 1 Ps Rp. 1,053,635.00
34 Anl. 6.2 1 M³ Pasang pondasi batu kali 1 Pc : 2 Ps Rp. 908,580.00
35 Anl. 6.3 1 M³ Pasang pondasi batu kali, 1 Pc : 2,5 Ps Rp. 1,053,635.00
36 Anl. 6.4 1 M³ Pasang pondasi batu kali, Pc : 3 Ps Rp. 832,950.00
37 Anl. 6.5 1 M³ Pasang pondasi batu kali, 1 Pc : 4 Ps. Rp. 787,625.00
38 Anl. 6.6 1 M³ Pasang pondasi batu kali, 1 Pc : 5 Ps Rp. 756,185.00
39 Anl. 6.7 1 M³ Pasang pondasi batu kali, 1 Pc : 6 Ps Rp. 734,090.00
40 Anl. 6.8 1 M³ Pasang pondasi batu kali, Pc : 8 Ps Rp. 697,690.00
41 Anl. 6.9 1 M³ Pasang pondasi batu kali, 1 Kp : 1 Sm : 1 Ps Rp. 505,204.20
42 Anl. 6.10 1 M³ Pasang pondasi batu kali, 1 Kp : 1 SM : 2 Ps Rp. 483,270.40
43 Anl. 6.11 1 M³ Pasang pondasi batu kosong Rp. 426,675.00
44 Anl. 6.12 1 M³ Pasang pondasi sumuran diameter 100 Cm Rp. 936,300.00
45 Anl. 6.13 1 M³ Pembuatan tiang pancang (40 x 40) Cm, beton bertulang Rp. 1,368,715.00
46 Anl. 6.14 1 M³ Pembuatan tiang pancang (35 x 35) Cm, beton bertulang Rp. 1,067,940.00
NO ANALISA URAIAN HARGA

Pekerjaan Dinding
47 Anl. 6.1 1 m² Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps Rp. 390,527.00
48 Anl. 6.2 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 2 Ps Rp. 367,350.00
49 Anl. 6.3 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 3 Ps Rp. 355,495.00
50 Anl. 6.4 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 4 Ps Rp. 341,815.00
51 Anl. 6.5 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 5 Ps Rp. 310,360.00
52 Anl. 6.6 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 6 Ps Rp. 343,360.00
53 Anl. 6.7 1 m² Pasangan bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Ps Rp. 141,874.50
54 Anl. 6.8 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 1 Ps Rp. 188,465.00
55 Anl. 6.9 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 2 Ps Rp. 178,725.00
56 Anl. 6.10 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Ps Rp. 172,843.00
57 Anl. 6.11 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps Rp. 169,620.00
58 Anl. 6.12 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 5 Ps Rp. 167,602.00
59 Anl. 6.13 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 6 Ps Rp. 166,758.00
60 Anl. 6.14 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 8 Ps Rp. 164,475.00
61 Anl. 6.15 1 m² Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Kp : 10 Ps Rp. 161,675.00
62 Anl. 6.16 1 m² Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 1 Ps Rp. 148,196.76
63 Anl. 6.17 1 m² Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 2 Ps Rp. 150,520.66
64 Anl. 6.18 1 m² Pasangan dinding holowblock (HB.20) Rp. 632,807.50
65 Anl. 6.19 1 m² Pasangan dinding holowblock (HB.15) Rp. 513,962.50
66 Anl. 6.20 1 m² Pasangan dinding holowblock (HB.10) Rp. 613,492.50
67 Anl. 6.21 1 m² Pasangan dinding Conblock (CB.20) Rp. 248,392.50
68 Anl. 6.22 1 m² Pasangan dinding Conblock (CB.15) Rp. 194,002.10
69 Anl. 6.23 1 m² Pasangan dinding Conblock (CB.10) Rp. 136,911.70
70 Anl. 6.24 1 m² Pasang dinding lantai Rp. 232,300.00
71 Anl. 6.25 1 m² Pasang dinding Roster / Terawang Rp. 346,320.00
72 Anl. 6.26 1 m² Pasang bata berongga ukuran ( 5 x 10 x 20 ) cm Rp. 315,535.00
73 Anl. 6.27 1 m² Pasang dinding anyaman bambu, rangka kayu Rp. 132,151.00

Pekerjaan Plesteran

74 Anl. 6.1 1 M² Plesteran 1 Pc : 1 Ps, tebal 15 mm Rp. 68,033.00


75 Anl. 6.2 1 M² Plesteran 1 Pc : 2 Ps, tebal 15 mm Rp. 62,933.00
76 Anl. 6.3 1 M² Plesteran 1 Pc : 3 Ps, tebal 15 mm Rp. 60,607.00
77 Anl. 6.4 1 M² Plesteran 1 Pc : 4 Ps, tebal 15 mm Rp. 59,080.00
78 Anl. 6.5 1 M² Plesteran 1 Pc : 5 Ps, tebal 15 mm Rp. 58,378.00
79 Anl. 6.6 1 M² Plesteran 1 Pc : 6 Ps, tebal 15 mm Rp. 57,747.00
80 Anl. 6.7 1 M² Plesteran 1 Pc : 8 Ps, tebal 15 mm Rp. 56,892.00
81 Anl. 6.8 1 M² Plesteran 1 Pc : 2 Ps, tebal 20 mm Rp. 86,274.50
82 Anl. 6.9 1 M² Plesteran 1 Pc : 3 Ps, tebal 20 mm Rp. 82,197.50
83 Anl. 6.10 1 M² Plesteran 1 Pc : 4 Ps, tebal 20 mm Rp. 79,759.50
84 Anl. 6.11 1 M² Plesteran 1 Pc : 5 Ps, tebal 20 mm Rp. 77,813.50
85 Anl. 6.12 1 M² Plesteran 1 Pc : 6 Ps, tebal 20 mm Rp. 76,873.50
86 Anl. 6.13 1 M² Plesteran 1 Pc : 2 Ps, tebal 25 mm Rp. 90,332.50
87 Anl. 6.14 1 M² Plesteran 1 Pc : 3 Ps, tebal 25 mm Rp. 91,000.00
88 Anl. 6.15 1 M² Plesteran 1 Pc : 4 Ps, tebal 25 mm Rp. 88,617.00
89 Anl. 6.16 1 M² Plesteran 1 Pc : 5 Ps, tebal 25 mm Rp. 86,726.00
90 Anl. 6.17 1 M² Plesteran 1 Pc : 2 Ps, tebal 30 mm Rp. 111,260.00
91 Anl. 6.18 1 M² Plesteran 1 Pc : 3 Ps, tebal 30 mm Rp. 106,020.00
92 Anl. 6.19 1 M² Plesteran 1 Pc : 4 Ps, tebal 30 mm Rp. 102,937.00
93 Anl. 6.2 1 M² Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm Rp. 79,065.00
94 Anl. 6.21 1 M² Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm Rp. 76,738.00
95 Anl. 6.22 1 M² Plesteran Skoning 1 Pc : 2 Ps Rp. 18,680.00
96 Anl. 6.23 1 M² Plesteran Ciprat, 1 Pc : 2 Ps, tebal 10 mm Rp. 54,413.00
97 Anl. 6.24 1 M² Plesteran Siar adukan, 1 Pc : 2 Ps Rp. 38,238.00
NO ANALISA URAIAN HARGA

Pekerjaan Kayu
98 Anl 6.1 1 M³ Pasang kusen pintu dan jendela kayu jati Rp. 30,270,000.00
99 Anl 6.2 1 M³ Pasang kusen pintu dan jendela kayu damar laut Rp. 14,542,500.00
100 Anl 6.3 1 M³ Pasang kusen pintu dan jendela kayu meranti Rp. 11,440,500.00
101 Anl 6.4 1 M³ Pasang kusen pintu dan jendela kayu damar laut Rp. 14,872,500.00
102 Anl 6.5 1 M³ Pasang pintu klamp kayu meranti batu Rp. 549,800.00
103 Anl 6.6 1 M³ Pasang pintu klamp kayu jati Rp. 1,080,059.84
104 Anl 6.7 1 M² Pasang pintu panel kayu jati Rp. 1,389,009.84
105 Anl 6.8 1 M² Pasang pintu panel kayu meranti batu Rp. 896,250.00
106 Anl 6.9 1 M² Pasang pintu dan jendela kaca panel kayu jati Rp. 1,400,655.40
107 Anl 6.10 1 M² Pasang pintu dan jendela kaca panel kayu meranti batu Rp. 885,125.00
108 Anl 6.11 1 M² Pasang pintu dan jendela kaca panel kayu meranti Rp. 748,625.00
109 Anl 6.12 1 M² Pasang pintu dan jendela jalusi kayu jati Rp. 2,190,184.16
110 Anl 6.13 1 M² Pasang pintu dan jendela jalusi kayu meranti batu Rp. 1,282,500.00
111 Anl 6.14 1 M² Pasang pintu plywood rangka, rangka kayu jati Rp. 931,377.02
112 Anl 6.15 1 M² Pasang pintu plywood rangka, rangka kayu meranti batu Rp. 642,680.00
113 Anl 6.16 1 M² Pasang jalusi mati kusen kayu jati Rp. 1,833,341.40
114 Anl 6.17 1 M² Pasang jalusi mati kusen kayu damar laut Rp. 966,075.00
115 Anl 6.18 1 M² Pasang pintu plywood rangka, rangka kayu meranti Rp. 458,390.00
116 Anl 6.19 1 M² Pasang pintu teakwood rangka, rangka kayu jati Rp. 938,767.02
117 Anl 6.20 1 M² Pasang pintu teakwood rangka, rangka kayu meranti batu Rp. 650,070.00
118 Anl 6.21 1 M² Pasang pintu plywood & formika, rangka kayu jati Rp. 1,133,437.02
119 Anl 6.22 1 M² Pasang pintu plywood & formika, rangka kayu meranti batu Rp. 844,740.00
120 Anl 6.23 1 M² Psg. pintu plywood & formika, rangka kayu damar laut (divermis) Rp. 742,710.00
121 Anl 6.24 1 M³ Pasang konstruksi kuda-kuda kayu damar laut Rp. 12,892,600.00
122 Anl 6.25 1 M³ Pasang konstruksi kuda-kuda kayu meranti Rp. 8,355,100.00
123 Anl 6.26 1 M² Pasang kaso + reng genteng kodok kayu meranti Rp. 92,775.00
124 Anl 6.27 1 M² Pasang kaso + reng genteng kodok kayu damar laut Rp. 142,275.00
125 Anl 6.28 1 M² Pasang kaso + reng genteng monier kayu jati Rp. 365,025.00
126 Anl 6.29 1 M² Pasang kaso + reng genteng monier kayu damar laut Rp. 160,975.00
127 Anl 6.30 1 M² Pasang kaso + reng genteng beton kayu damar laut Rp. 160,975.00
128 Anl 6.31 1 M² Pasang kaso + reng atap sirap kayu damar laut Rp. 1,579,200.00
129 Anl 6.32 1 M² Pasang kaso + reng atap sirap kayu meranti Rp. 898,575.00
130 Anl 6.33 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, kayu jati Rp. 358,275.00
131 Anl 6,34.A 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, damar laut Rp. 183,375.00
132 Anl 6,34.B 1 M² Pasang rangka langit-langit (1.00 x 1.00) m, Kayu meranti Rp. 133,875.00
133 Anl 6.35 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu jati Rp. 734,512.50
134 Anl 6.36 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu damar laut Rp. 340,987.50
135 Anl 6.37 1 M² Pasang rangka langit-langit (30 x 30) cm, kayu meranti Rp. 229,612.50
136 Anl 6.38 1 M' Pasang lisplang ukuran (3 x 20) cm, kayu meranti Rp. 84,945.00
137 Anl 6.39 1 M' Pasang lisplang ukuran (3 x 20) cm, kayu meranti batu Rp. 112,275.00
138 Anl 6.40 1 M' Pasang lisplang ukuran (3 x 30) cm, kayu jati Rp. 314,223.84
139 Anl 6.41 1 M' Pasang lisplang ukuran (3 x 30) cm, kayu meranti batu Rp. 152,200.00
140 Anl 6.42 1 M' Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti batu Rp. 206,392.50
141 Anl 6.43 1 M' Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti batu Rp. 116,955.00
142 Anl 6.44 1 M' Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti Rp. 83,415.00
143 Anl 6.45 1 M' Pasang rangka dinding pemisah, kayu damar laut Rp. 352,125.00
144 Anl 6.46 1 M' Pasang rangka dinding pemisah, kayu meranti Rp. 244,387.50
145 Anl 6.47 1 M² Psg. dinding pemisah teakwood rangka, rangka kayu damar laut Rp. 340,950.00
146 Anl 6.48 1 M² Pasang dinding pemisah double plywood, rangka kayu damar laut Rp. 377,739.00
147 Anl 6.49 1 M² Pasang dinding lambrizering dari papan meranti Rp. 433,500.00
148 Anl 6.50 1 M² Pasang plywood tebal 4 mm, untuk dinding Rp. 36,770.50
149 Anl 6.51 1 M' Pasang list plafond kayu profil Rp. 18,892.00
NO ANALISA URAIAN HARGA

Pekerjaan Beton
150 Anl 6.1 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr Rp. 859,800.00
151 Anl 6.2 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr Rp. 829,750.00
152 Anl 6.3 1 M³ Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr Rp. 811,800.00
153 Anl 6.4 1 M³ Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 Cm Rp. 52,420.00
154 Anl 6.5 1 M³ Membuat beton 1 Pc : 2 Ps : 3 Kr Rp. 860,950.00
155 Anl 6.6 1 M³ Membuat beton 1 Pc : 2 Ps : 4 Kr Rp. 941,560.00
156 Anl 6.7 1 M³ Membuat beton 1 Pc : 2 Ps : 2,5 Kr Rp. 1,032,180.00
157 Anl 6.8 1 M³ Membuat beton 1 Pc : 1,5 Ps : 3 Kr Rp. 962,636.00
158 Anl 6.9 1 M³ Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr Rp. 1,070,052.00
159 Anl 6.10 1 M³ Membuat beton 1 Pc : 1 Ps : 2 Kr Rp. 1,161,616.00
160 Anl 6.11 1 M³ Membuat tiang pancang prestressed beton Rp. 1,150,250.00
161 Anl 6.12 1 M³ Membuat beton 1 Pc : 2 Ps : 3 Kr Rp. 1,231,200.00
162 Anl 6.13 1 M³ Membuat beton 1 Pc : 2 Ps : 4 Kr Rp. 1,171,800.00
163 Anl 6.14 1 M³ Membuat beton 1 Pc : 1,5 Ps : 3 Kr Rp. 1,258,950.00
164 Anl 6.15 1 M³ Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr Rp. 1,317,150.00
165 Anl 6.16 1 M³ Membuat beton 1 Pc : 1 Ps : 1 Kr Rp. 1,556,350.00
166 Anl 6.17 1 M³ Membuat beton kedap air dengan strorox - 100 Rp. 1,300,750.00
167 Anl 6.18 1 M' Memasang PVC Waterstop lebar 150 mm Rp. 31,300.00
168 Anl 6.19 1 M' Memasang PVC Waterstop lebar 200 mm Rp. 37,375.00
169 Anl 6.20 1 M' Memasang PVC Waterstop lebar 230 mm Rp. 92,100.00
170 Anl 6.21 1 M' Memasang PVC Waterstop lebar 250 mm Rp. 97,525.00
171 Anl 6.22 1 M' Memasang PVC Waterstop lebar 300 mm Rp. 115,775.00
172 Anl 6.23 1 Kg Pembesian dengan Besi polos Rp. 24,092.50
173 Anl 6.24 1 M² Kabel Presstressed polos / strands Rp. 23,195.00
174 Anl 6.25 1 M² Pasang bekisting untuk pondasi Rp. 204,375.00
175 Anl 6.26 1 M² Pasang bekisting untuk sloof Rp. 219,912.50
176 Anl 6.27 1 M² Pasang bekisting untuk kolom Rp. 344,799.50
177 Anl 6.28 1 M² Pasang bekisting untuk balok Rp. 356,122.00
178 Anl 6.29 1 M² Pasang bekisting untuk lantai Rp. 423,799.50
179 Anl 6.30 1 M² Pasang bekisting untuk dinding Rp. 370,512.00
180 Anl 6.31 1 M² Pasang bekisting untuk tangga Rp. 315,274.50
181 Anl 6.32 1 M³ Pasang beton dengan mutu K 225 Rp. 1,695,450.00
182 Anl 6.33 1 M³ Pasang beton dengan mutu K 275 Rp. 1,673,800.00
183 Anl 6.34 1 M² Pasang jembatan cor Rp. 126,938.00
184 Anl 6.35 1 M³ Membuat pondasi beton bertulang (150 kg besi + bekisting) Rp. 5,218,500.00
185 Anl 6.36 1 M³ Membuat sloof beton bertulang (200 kg besi + bekisting) Rp. 6,675,725.00
186 Anl 6.37 1 M³ Membuat kolom beton bertulang (300 kg besi + bekisting) Rp. 11,028,395.00
187 Anl 6.38 1 M³ Membuat balok beton bertulang (200 kg besi + bekisting) Rp. 8,254,096.00
188 Anl 6.39 1 M³ Membuat balok beton bertulang (150 kg besi + bekisting) Rp. 7,432,546.00
189 Anl 6.40 1 M³ Membuat dinding beton bertulang (150 kg besi + bekisting) Rp. 7,108,646.00
190 Anl 6.41 1 M³ Membuat tangga beton bertulang (150 kg besi + bekisting) Rp. 7,727,512.50
191 Anl 6.42 1 M' Membuat kolom penguat beton bertulang (11 x 11) cm Rp. 99,430.00
192 Anl 6.43 1 M' Membuat ring balok beton bertulang (10 x 15) cm Rp. 121,707.50

Pekerjaan Penutup Atap


193 Anl 6.1 1 M² Pasang atap genteng palentong kecil Rp. 70,600.00
194 Anl 6.2 1 M² Pasang atap genteng kodok / glazzur Rp. 83,100.00
195 Anl 6.3 1 M² Pasang atap genteng palentong super / besar Rp. 74,060.00
196 Anl 6.4 1 M² Pasang genteng bubung palentong Rp. 139,780.00
197 Anl 6.5 1 M² Pasang bubung genteng kodok glazzuur Rp. 140,830.00
198 Anl 6.6 1 M² Pasang bubung genteng palentong besar Rp. 143,990.00
199 Anl 6.7 1 M² Pasang roof light fiberglass ( 180 x 90 ) cm Rp. 55,059.00
NO ANALISA URAIAN HARGA

200 Anl 6.8 1 M² Pasang atap asbes gelombang ( 2,70 x 0,92 m ) x 5 mm Rp. 78,914.50
201 Anl 6.9 1 M² Pasang atap asbes gelombang ( 2,40 x 0,92 m ) x 5 mm Rp. 79,360.00
202 Anl 6.10 1 M² M² Pasang atap asbes gelombang ( 2,10 x 0,92 m ) x 5 mm Rp. 84,112.00
203 Anl 6.11 1 M² Pasang atap asbes gelombang ( 1,80 x 0,92 m ) x 5 mm Rp. 82,987.50
204 Anl 6.12 1 M² Pasang atap asbes gelombang ( 2,40 x 1,05 m ) x 4 mm Rp. 78,433.50
205 Anl 6.13 1 M² Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm Rp. 76,360.00
206 Anl 6.14 1 M² Pasang atap asbes gelombang ( 1,80 x 1,05 m ) x 4 mm Rp. 64,953.00
207 Anl 6.15 1 M² Pasang atap asbes gelombang ( 2,70 x 1,08 m ) x 6 mm Rp. 51,889.40
208 Anl 6.16 1 M² Pasang atap asbes gelombang ( 2,4 x 1,08 m ) x 6 mm Rp. 87,091.50
209 Anl 6.17 1 M² Pasang atap asbes gelombang ( 2,1 x 1,08 m ) x 6 mm Rp. 88,345.50
210 Anl 6.18 1 M² Pasang atap asbes gelombang ( 1,80 x 1,08 m ) x 6 mm Rp. 88,388.40
211 Anl 6.19 1 M' Pasang bubung stel gelombang 0,92 m Rp. 79,276.00
212 Anl 6.20 1 M' Pasang nok stel gelombang 1,05 m Rp. 86,839.00
213 Anl 6.21 1 M' Pasang nok stel gelombang 1,08 m Rp. 90,705.50
214 Anl 6.22 1 M' Pasang nok paten 1,05 m Rp. 76,432.00
215 Anl 6.23 1 M' Pasang nok paten 1,05 m Rp. 69,400.00
216 Anl 6.24 1 M' Pasang nok paten 1,08 m Rp. 83,812.00
217 Anl 6.25 1 M' Pasang nok stel rata 0,92 m Rp. 77,298.00
218 Anl 6.26 1 M' Pasang nok stel rata 1,05 m Rp. 65,535.00
219 Anl 6.27 1 M² Pasang atap genteng beton Rp. 104,460.00
220 Anl 6.28 1 M² Pasang atap genteng aspal Rp. 186,856.00
221 Anl 6.29 1 M² Pasang atap genteng metal / multi roof Rp. 107,262.60
222 Anl 6.30 1 M² Pasang atap sirap Rp. 124,650.00
223 Anl 6.31 1 M' Pasang nok genteng beton Rp. 153,040.00
224 Anl 6.32 1 M' Pasang nok genteng aspal Rp. 112,115.00
225 Anl 6.33 1 M' Pasang nok genteng metal Rp. 98,179.00
226 Anl 6.34 1 M' Pasang nok sirap Rp. 141,580.00
227 Anl 6.35 1 M' Pasang atap seng gelombang Rp. 65,698.00
228 Anl 6.36 1 M' Pasang atap nok seng Rp. 62,900.00
229 Anl 6.37 1 M' Pasang atap aluminium Rp. 162,460.60
230 Anl 6.38 1 M' Pasang nok aluminium Rp. 107,471.20
231 Anl 6.39 1 M² Pasang aluminium foil / sisalation Rp. 105,710.00

Pekerjaan Lantai dan Dinding


232 Anl 6.1 1 M² 1 M² Pasang lantai ubin granito ukuran 40 x 40 cm Rp. 395,773.70
233 Anl 6.2 1 M² 1 M² Pasang lantai ubin granito ukuran 30 x 30 cm Rp. 387,803.70
234 Anl 6.3 1 M² 1 M² Pasang lantai ubin teralux marmer ukuran 60 x 60 cm Rp. 373,588.80
235 Anl 6.4 1 M² 1 M² Pasang lantai ubin teralux marmer ukuran 40 x 40 cm Rp. 437,067.50
236 Anl 6.5 1 M² 1 M² Pasang lantai ubin teralux marmer ukuran 30 x 30 cm Rp. 482,642.60
237 Anl 6.6 1 M' 1 M' Pasang plint ubin granito ukuran 10 x 40 cm Rp. 234,923.00
238 Anl 6.7 1 M' 1 M' Pasang plint ubin granito ukuran 10 x 30 cm Rp. 202,369.00
239 Anl 6.8 1 M' 1 M' Pasang plint ubin teralux marmer ukuran 10 x 60 cm Rp. 220,985.50
240 Anl 6.9 1 M' 1 M' Pasang plint ubin teralux marmer ukuran 10 x 40 cm Rp. 181,895.50
241 Anl 6.10 1 M' 1 M' Pasang plint ubin teralux marmer ukuran 10 x 30 cm Rp. 163,707.70
242 Anl 6.11 1 M² 1 M² Pasang lantai keramik artistik 10 x 20 cm Rp. 247,562.00
243 Anl 6.12 1 M² 1 M² Pasang lantai keramik artistik 10 x 10 cm Rp. 207,562.00
244 Anl 6.13 1 M² 1 M² Pasang lantai keramik artistik ukuran 5 x 20 cm Rp. 250,562.00
245 Anl 6.14 1 M' 1 M' Pasang plint keramik artistik ukuran 10 x 20 cm Rp. 37,095.50
246 Anl 6.15 1 M' 1 M' Pasang plint keramik artistik ukuran 10 x 10 cm Rp. 37,495.50
247 Anl 6,16.A 1 M' 1 M' Pasang plint keramik ukuran 10 x 20 cm Rp. 33,125.50
248 Anl 6,16.B 1 M' 1 M' Pasang plint keramik ukuran 10 x 30 cm Rp. 40,802.90
249 Anl 6,16.C 1 M' 1 M' Pasang plint keramik ukuran 10 x 40 cm Rp. 41,300.50
250 Anl 6.17 1 M' 1 M' Pasang plint vinyil tanpa adukan Rp. 54,297.00
251 Anl 6.18 1 M² 1 M² Pasang lantai keramik 10 x 20 cm Rp. 220,062.00
NO ANALISA URAIAN HARGA

252 Anl 6.19 1 M² Pasang lantai keramik 15 x 15 cm Rp. 221,162.00


253 Anl 6.20 1 M² Pasang lantai keramik 20 x 20 cm Rp. 221,812.00
254 Anl 6.21 1 M² Pasang lantai keramik 20 x 25 cm Rp. 222,562.00
255 Anl 6.22 1 M² Pasang lantai keramik 25 x 25 cm Rp. 221,482.00
256 Anl 6.23 1 M² Pasang lantai keramik 30 x 30 cm Rp. 221,500.40
257 Anl 6.24 1 M² Pasang lantai keramik 30 x 30 cm anti slip Rp. 229,506.80
258 Anl 6.25 1 M² Pasang lantai keramik 40 x 40 cm Rp. 220,062.00
259 Anl 6.26 1 M² Pasang lantai mosaik 30 x 30 cm, ex lokal Rp. 332,185.00
260 Anl 6.27 1 M² Pasang lantai marmer Rp. 440,737.44
261 Anl 6.28 1 M² Pasang lantai karpet 100% wool Rp. 151,765.00
262 Anl 6.29 1 M² Pasang lantai karpet 80% wool, 20% nylon Rp. 154,075.00
263 Anl 6.30 1 M² Pasang lantai karpet Rp. 157,540.00
264 Anl 6.31 1 M² Pasang lantai parquet jati Rp. 542,302.50
265 Anl 6.32 1 M² Pasang dinding porselin 11 x 11 cm, putih Rp. 275,470.00
266 Anl 6.33 1 M² Pasang dinding porselin 11 x 11 cm, warna Rp. 187,075.00
267 Anl 6.34 1 M² Pasang dinding porselin 15 x 15 cm, putih Rp. 268,290.00
268 Anl 6.35 1 M² Pasang dinding porselin 15 x 15 cm, warna Rp. 279,090.00
269 Anl 6.36 1 M² Pasang dinding keramik artistik 10 x 20 cm Rp. 340,790.00
270 Anl 6.37 1 M² Pasang dinding keramik artistik 5 x 20 cm Rp. 255,790.00
271 Anl 6.38 1 M² Pasang dinding keramik 10 x 20 cm Rp. 225,290.00
272 Anl 6.39 1 M² Pasang dinding keramik 15 x 15 cm Rp. 227,790.00
273 Anl 6.40 1 M² Pasang dinding keramik 20 x 20 cm Rp. 174,540.00
274 Anl 6.41 1 M² Pasang dinding keramik 20 x 25 cm Rp. 227,790.00
275 Anl 6.42 1 M² Pasang dinding marmer Rp. 485,565.40
276 Anl 6.43 1 M² Pasang dinding bata pelapis 7 x 3 x 20 cm Rp. 299,191.00
277 Anl 6.44 1 M² Pasang dinding batu poros Rp. 271,139.00
278 Anl 6.45 1 M² Pasang dinding batu tempel hitam Rp. 260,450.00
279 Anl 6.46 1 M² Pasang lantai vinyl karet 30 x 30 cm KL I Rp. 165,067.50
280 Anl 6.47 1 M² Pasang lantai vinyl karet 30 x 30 cm KL II Rp. 157,111.50
281 Anl 6.48 1 M² Pasang lantai vinyl asbes 30 x 30 cm Rp. 147,719.00
282 Anl 6.49 1 M² Pasang lantai vinyl motif kembang 30 x 30 cm Rp. 161,089.50
283 Anl 6.50 1 M² Pasang wall corvering lebar 50 cm Rp. 185,337.50
284 Anl 6.51 1 M² Plint kayu Jati 2 x 10 cm Rp. 91,718.16
285 Anl 6.52 1 M² Plint kayu Meranti batu 2 x 10 cm Rp. 56,367.50

Pekerjaan Kunci dan Kaca


286 Anl 6.1 1 Bh pasang kunci tanam antik Rp. 320,025.00
287 Anl 6.2 1 Bh pasang kunci tanam biasa Rp. 273,375.00
288 Anl 6.3 1 Bh pasang kunci tanam kamar mandi Rp. 131,377.50
289 Anl 6.4 1 Bh pasang kunci silinder Rp. 110,783.75
290 Anl 6.5 1 Bh pasang engsel pintu Rp. 61,381.25
291 Anl 6.6 1 Bh pasang engsel jendela kupu-kupu Rp. 35,087.50
292 Anl 6.7 1 Bh pasang engsel angin Rp. 61,800.00
293 Anl 6.8 1 Bh pasang spring knip Rp. 35,461.25
294 Anl 6.9 1 Bh pasang kait angin Rp. 51,381.25
296 Anl 6.10 1 Bh pasang door closer Rp. 197,687.50
296 Anl 6.11 1 Bh pasang kunci selot Rp. 62,405.00
297 Anl 6.12 1 Bh pasang pegangan pintu / door holder Rp. 200,947.50
298 Anl 6.13 1 Bh pasang door stop Rp. 55,707.50
299 Anl 6.14 1 Bh pasang rel pintu dorong Rp. 265,855.00
300 Anl 6.15 1 Bh pasang kunci lemari Rp. 56,308.75
301 Anl 6.16 1 M² pasang kaca, tebal 3 mm Rp. 122,213.25
302 Anl 6.17 1 M² pasang kaca, tebal 5 mm Rp. 219,756.25
303 Anl 6.18 1 M² pasang kaca, tebal 8 mm Rp. 284,567.00
NO ANALISA URAIAN HARGA

304 Anl 6.19 1 M² pasang kaca buram, tebal 5 mm Rp. 151,674.75


305 Anl 6.20 1 M² pasang kaca cermin, tebal 5 mm Rp. 205,126.25
306 Anl 6.21 1 M² pasang kaca cermin, tebal 8 mm Rp. 313,607.00
307 Anl 6.22 1 M² pasang kaca "wireglass" , tebal 5 mm Rp. 193,631.25
308 Anl 6.23 1 M² pasang kaca patri, tebal 5 mm Rp. 230,308.75
309 Anl 6.24 1 M² pasang kaca Reyben, tebal 5 mm Rp. 274,756.25

Pekerjaan Pengecatan
310 Anl 6.1 1 M² Mengikis/ mengerok permukaan cat tembok lama Rp. 16,042.50
311 Anl 6.2 1 M² Mencuci bidang permukaan tembok yang pernah di cat Rp. 15,952.00
312 Anl 6.3 1 M² Mengerok karat cat lama permukaan baja dengan cara manual Rp. 15,952.00
313 Anl 6.4 1 M² Menyabun permukaan tembok lama Rp. 15,952.00
314 Anl 6.5 1 M² Mendempul dan menggosok kayu Rp. 18,107.70
315 Anl 6.6 1 M² Pengecatan bidang kayu lama Rp. 30,378.20
316 Anl 6.7 1 M² Cat bidang kayu baru 1 lps plamir, 1 lps cat dasar, 2 lps cat minyak Rp. 41,283.50
317 Anl 6.8 1 M² Cat bidang kayu baru 1 lps plamir, 1 lps cat dasar, 3lps cat minyak Rp. 45,868.20
318 Anl 6.9 1 M² Peleburan kayu dengan politur Rp. 40,449.16
319 Anl 6.10 1 M² Peleburan kayu dengan residu Rp. 14,200.00
320 Anl 6.11 1 M² Peleburan bidang kayu dan vernis Rp. 51,179.50
321 Anl 6.12 1 M² Cat tembok baru 1 lps. plamir, 1 lps. cat dasar, 2 lps. cat penutup Rp. 47,850.00
322 Anl 6.13 1 M² Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup ) Rp. 39,712.50
323 Anl 6.14 1 M² Pemasangan wall paper Rp. 78,449.50
324 Anl 6.15 1 M² Pengecatan permukaan baja dengan meni besi Rp. 12,391.00
325 Anl 6.16 1 M² Pengecatan permukaan baja dengan meni besi dan perancah Rp. 72,293.50
326 Anl 6.17 1 M² Pengecatan permukaan baja lapis seng (galbani) secara manual
sistem 1 lapis cat konvensional dengan tebal 200 um. Rp. 45,849.00
327 Anl 6.18 1 M² Pengecatan permukaan baja lapis seng (galbani) secara manual
sistem 3 lapis cat konvensional dengan tebal 200 um. Rp. 259,391.10
328 Anl 6.19 1 M² Pengecatan permukaan baja lapis seng (galbani) secara semprot
(airless spray) dgn sistem 1 lapis cat konvensional dgn t = 200 um. Rp. 215,250.00

Pekerjaan Sanitasi
329 Anl 6.1 1 Bh Memasang kloset duduk/monoblok Rp. 2,652,996.00
330 Anl 6.2 1 Bh Memasang kloset jongkok porselen Rp. 613,080.00
331 Anl 6.3 1 Bh Memasang kloset jongkok teraso Rp. 908,700.00
332 Anl 6.4 1 Bh Memasang urinoir Rp. 934,652.00
333 Anl 6.5 1 Bh Memasang wastafel Rp. 978,062.00
334 Anl 6.6 1 Bh Memasang bak mandi teraso volume 0,30 m³ Rp. 545,550.00
335 Anl 6.7 1 Bh Memasang bak mandi fibreglass volume 0,30 m³ Rp. 502,520.00
336 Anl 6.8 1 Bh Memasang bak mandi batu bata volume 0,30 m³ Rp. 1,234,400.00
337 Anl 6.9 1 Bh Memasang badkip porselin Rp. 4,047,500.00
338 Anl 6.10 1 Bh Memasang bak mandi beton volume 1 m³ air Rp. 5,586,017.00
339 Anl 6.11 1 Bh Memasang bak fibreglass volume 1 m³ air Rp. 1,470,780.00
340 Anl 6.12 1 Bh Memasang 1 m' pipa beton, diameter 30 cm - 100 cm Rp. 245,627.00
341 Anl 6.13 1 Bh Memasang bak kontrol pas. bt bata uk. (30 x 30) cm tinggi 35 cm Rp. 800,138.00
342 Anl 6.14 1 Bh Memasang bak kontrol pas. bt bata uk. (45 x 45) cm tinggi 50 cm Rp. 769,543.00
343 Anl 6.15 1 Bh Memasang bak kontrol pas. bt bata uk. (60 x 60) cm tinggi 65 cm Rp. 1,175,859.70
344 Anl 6.16 1 M' Memasang pipa galvanis diameter ½" Rp. 47,868.50
345 Anl 6.17 1 M' Memasang pipa galvanis diameter 3/4" Rp. 56,192.00
346 Anl 6.18 1 M' Memasang pipa galvanis diameter 1" Rp. 70,731.00
347 Anl 6.19 1 M' Memasang pipa galvanis diameter 1 ½" Rp. 99,694.00
348 Anl 6.20 1 M' Memasang pipa galvanis diameter 2" Rp. 115,225.00
349 Anl 6.21 1 M' Memasang pipa galvanis diameter 3" Rp. 133,097.00
350 Anl 6.22 1 M' Memasang pipa PVC tipe AW diameter ½" Rp. 22,402.00
351 Anl 6.23 1 M' Memasang pipa PVC tipe AW diameter ¾" Rp. 25,347.00
352 Anl 6.24 1 M' Memasang pipa PVC tipe AW diameter 1" Rp. 34,926.00
NO ANALISA URAIAN HARGA

353 Anl 6.25 1 M' Memasang pipa PVC tipe AW diameter 1 ½" Rp. 44,303.50
354 Anl 6.26 1 M' Memasang pipa PVC tipe AW diameter 2" Rp. 56,667.00
355 Anl 6.27 1 M' Memasang pipa PVC tipe AW diameter 2 ½" Rp. 55,076.00
356 Anl 6.28 1 M' Memasang pipa PVC tipe AW diameter 3" Rp. 77,344.50
357 Anl 6.29 1 M' Memasang pipa PVC tipe AW diameter 4" Rp. 108,468.50
358 Anl 6.30 1 Bh Memasang bak cuci piring stainles steel Rp. 534,462.50
358 Anl 6.31 1 Bh Memasang bak cuci piring teraso Rp. 416,437.50
359 Anl 6.32 1 Bh Memasang kran diameter ¾" atau ½" Rp. 48,039.25
360 Anl 6.33 1 Bh Memasang Floor drain Rp. 33,375.00

Pekerjaan Besi dan Aluminium


361 Anl 6.1 1 Kg 1 Kg Pasang rangka atap baja Rp. 27,430.30
362 Anl 6.2 1 M² 1 M² Pasang pintu besi baja Rp. 994,600.00
363 Anl 6.3 1 M² 1 M² Pasang jendela besi Rp. 626,438.75
364 Anl 6.4 1 M² 1 M² Pasang pintu gulung besi Rp. 1,147,900.00
365 Anl 6.5 1 M² 1 M² Pasang pintu lipat Rp. 1,116,480.00
366 Anl 6.6 1 M² 1 M² Pasang pintu Sunscreen alluminium Rp. 490,700.00
367 Anl 6.7 1 M² 1 M² Pasang Rolling door Rp. 812,510.00
368 Anl 6.8 1 M² 1 M² Pasang pintu alluminium Rp. 829,160.00
369 Anl 6.9 1 M² 1 M² Pasang Venetions blinds Rp. 225,527.50
370 Anl 6.10 1 M² 1 M² Pasang Vertikals blinds Rp. 237,627.50
371 Anl 6.11 1 M² 1 M² Pasang teralis besi Rp. 332,655.00
372 Anl 6.12 1 M² 1 M² Pasang kawat harmonika Rp. 62,312.50
373 Anl 6.13 1 M² 1 M² Pasang kawat nyamuk Rp. 49,530.50
374 Anl 6.14 1 M² 1 M² Pasang kawat kassa Rp. 51,664.50
375 Anl 6.15 1 M² 1 M² Pasang kawat burung Rp. 50,333.50
376 Anl 6.16 1 M² 1 M² Pasang jendela nako dan teralis Rp. 293,181.00
377 Anl 6.17 1 M' 1 M' Pasang talang datar, seng bjls 35 Rp. 193,501.25
278 Anl 6.18 1 M' 1 M' Pasang talang miring, seng bjls 35 Rp. 243,886.75
379 Anl 6.19 1 M' 1 M' Pasang talang ½ lingkaran D-10 cm, seng bjls 35 Rp. 198,133.75
380 Anl 6.20 1 M' 1 M' Pasang talang ½ lingkaran D-10 cm, seng bjls 30 Rp. 194,668.75

Pekerjaan Langit - langit ( Plafond )


381 Anl 6.1 1 M² Langit - langit asbes ( 1,00 x 1,00 ) m tebal 6 mm Rp. 34,055.50
382 Anl 6.2 1 M² Langit - langit asbes ( 1,00 x 1,00 ) m tebal 5 mm Rp. 30,876.50
383 Anl 6.3 1 M² Langit - langit asbes ( 1,00 x 1,00 ) m tebal 4 mm Rp. 27,697.50
384 Anl 6.4 1 M² Langit - langit asbes ( 1,00 x 1,00 ) m tebal 3,5 mm Rp. 25,277.50
385 Anl 6.5 1 M² Langit - langit akustik ( 30 x 30 ) cm Rp. 125,435.00
386 Anl 6.6 1 M² Langit - langit akustik ( 30 x 60 ) cm Rp. 122,931.00
387 Anl 6.7 1 M² Langit - langit akustik ( 60 x 120 ) cm Rp. 126,360.00
388 Anl 6.8 1 M² Langit - langit plywood ( 30 x 60 ) cm, tebal 4 mm Rp. 43,343.70
389 Anl 6.9 1 M² Langit - langit plywood ( 30 x 60 ) cm, tebal 6 mm Rp. 52,689.30
390 Anl 6.10 1 M² Langit - langit plywood ( 60 x 120 ) cm, tebal 4 mm Rp. 44,122.50
391 Anl 6.11 1 M² Langit - langit plywood ( 60 x 120 ) cm, tebal 6 mm Rp. 53,857.50
392 Anl 6.12 1 M² Langit - langit teakwood ( 30 x 60 ) cm, tebal 4 mm Rp. 44,254.50
393 Anl 6.13 1 M² Langit - langit teakwood ( 60 x 120 ) cm, tebal 4 mm Rp. 45,071.25
394 Anl 6.14 1 M² Langit - langit lat kayu jati Rp. 700,686.56
395 Anl 6.15 1 M² Langit - langit lat kayu ramin Rp. 122,180.00
396 Anl 6.16 1 M² Langit - langit lat papan rider Rp. 437,180.00
397 Anl 6.17 1 M² Langit - langit soft board Rp. 97,161.50
398 Anl 6.18 1 M² Langit - langit akustik 60 x 120 cm + rangka alluminium Rp. 237,619.00
399 Anl 6.19 1 M' List Langit - langit Kayu profil 3" Rp. 34,646.00
400 Anl 6.20 1 M² Langit - langit asbes (1,00 x 1,00) m, rangka kayu meranti Rp. 148,860.00
401 Anl 6.21 1 M² Langit - langit plywood 4 mm + rangka kayu meranti Rp. 184,616.30
402 Anl 6.22 1 M² Langit - langit akustik ( 30 x 60 ) cm + rangka kayu meranti Rp. 262,286.00
NO ANALISA URAIAN HARGA

403 Anl 6.23 1 M² Langit - langit akustik ( 30 x 30 ) cm + rangka kayu borneo Rp. 278,477.50
404 Anl 6,24.A 1 M² Langit - langit gypsum board, tebal 9 mm Rp. 63,735.00
405 Anl 6,24.B 1 M² Langit - langit gypsum board, tebal 6 mm Rp. 45,535.00
406 Anl 6,24.C 1 M² Langit - langit gypsum board, tebal 12 mm Rp. 77,687.50