II BAHAN PEREKAT
1 Semen (50) Kg tiga roda zak Rp 72,000 Rp 72,000 Rp 72,000 Rp 72,000 Rp 72,000 Rp 72,000
2 Semen Warna kg Rp 4,500 Rp 3,600 Rp 3,900 Rp 4,000 Rp 3,800 Rp 3,800
IV BAHAN KAYU
1 Kayu Klas I m3 Rp 3,600,000 Rp 3,600,000 Rp 3,300,000 Rp 3,400,000 Rp 3,350,000 Rp 3,300,000
2 Kayu Klas II m3 Rp 2,800,000 Rp 2,800,000 Rp 2,600,000 Rp 2,700,000 Rp 2,150,000 Rp 2,070,000
3 Kayu Klas III m3 Rp 1,900,000 Rp 1,900,000 Rp 1,900,000 Rp 1,900,000 Rp 1,850,000 Rp 1,770,000
4 Kayu Klas IV m3
5 Dolken dia 8 s/d 10 cm btg Rp 510,000 Rp 550,000 Rp 510,000 Rp 400,000 Rp 490,000 Rp 440,000
V BAHAN ALMUNIUM
1 Kusen Almunium p=6m btg Rp 751,000 Rp 731,000 Rp 721,000 Rp 721,000 Rp 701,000 Rp 701,000
2 Rangka Jendela Almunium p=6m btg Rp 166,000 Rp 164,000 Rp 161,000 Rp 161,000 Rp 159,000 Rp 159,000
3 Rangka Pintu Almunium p=6m m' Rp 181,000 Rp 179,000 Rp 179,000 Rp 176,000 Rp 171,000 Rp 171,000
4 Kusen & Pintu PVC Toilet almunium unit Rp 350,000 Rp 325,000 Rp 325,000 Rp 350,000 Rp 345,000 Rp 345,000
5 Engsel 4x3 psg Rp 36,000 Rp 26,000 Rp 25,000 Rp 16,000 Rp 28,000 Rp 28,000
6 Handle pintu set Rp 361,000 Rp 361,000 Rp 351,000 Rp 351,000 Rp 346,000 Rp 346,000
7 Selinder set Rp 129,000 Rp 129,000 Rp 126,000 Rp 126,000 Rp 121,000 Rp 121,000
8 Door Stoper set Rp 531,000 Rp 531,000 Rp 526,000 Rp 526,000 Rp 521,000 Rp 521,000
HARGA / ZONA - KECAMATAN DALAM WILAYAH KABUPATE
No Nama Bahan Keterangan Satuan ZONA A ZONA B
Sausu Balinggi Torue Parigi Selatan Parigi Barat Parigi
1 2 3 4 5 6 7 8 9 10
9 Door Closer set Rp 116,000 Rp 116,000 Rp 111,000 Rp 111,000 Rp 106,000 Rp 106,000
10 Slot Tanam set Rp 301,000 Rp 301,000 Rp 296,000 Rp 296,000 Rp 291,000 Rp 291,000
11 Kait Angin bh Rp 12,000 Rp 12,000 Rp 11,000 Rp 11,000 Rp 10,500 Rp 10,500
12 Grendel uk . Sedang bh Rp 11,000 Rp 8,000 Rp 7,000 Rp 11,000 Rp 12,000 Rp 12,000
VI BAHAN PELAPIS
1 Triplek t.3 mm uk. 120x240 cm Lbr Rp 54,000 Rp 54,000 Rp 54,000 Rp 54,000 Rp 54,000 Rp 54,000
2 Triplek t.4 mm uk. 120x240 cm Lbr Rp 64,000 Rp 63,000 Rp 63,000 Rp 63,000 Rp 62,000 Rp 62,000
3 Triplek t.9 mm uk. 120x240 cm Lbr
IX BAHAN KACA
1 Kaca Polos 3 mm uk.122x152 cm Lbr Rp 135,000 Rp 135,000 Rp 130,000 Rp 130,000 Rp 128,000 Rp 128,000
2 Kaca Polos 5 mm uk.122x152 cm Lbr Rp 160,000 Rp 157,000 Rp 155,000 Rp 153,000 Rp 150,000 Rp 150,000
3 Kaca Polos 8 mm uk.122x152 cm Lbr Rp 230,000 Rp 230,000 Rp 225,000 Rp 225,000 Rp 223,000 Rp 223,000
XI BAHAN FINISHING
1 Cat Kayu/Besi kg Rp 51,000 Rp 51,000 Rp 51,000 Rp 57,000 Rp 55,000 Rp 55,000
2 Plamir Kayu kg Rp 11,000 Rp 11,000 Rp 10,500 Rp 11,000 Rp 11,000 Rp 11,000
3 Meni Kayu kg Rp 31,000 Rp 26,000 Rp 23,000 Rp 37,000 Rp 36,000 Rp 36,000
4 Wood Filler kg
5 Thinner Ltr
6 Amplas Kayu Lbr
7 Kwas Cat bh Rp 11,000 Rp 11,000 Rp 9,000 Rp 6,000 Rp 6,500 Rp 6,500
8 Cat Tembok KW 1 kg Rp 71,000 Rp 71,000 Rp 69,000 Rp - Rp 67,000 Rp 67,000
9 Cat Tembok KW 2 kg Rp 66,000 Rp 66,000 Rp 65,000 Rp 65,000 Rp 63,000 Rp 63,000
10 Plamir Tembok kg Rp 31,000 Rp 21,000 Rp 19,000 Rp 19,000 Rp 18,000 Rp 18,000
11 Lem kayu kg Rp 21,000 Rp 21,000 Rp 21,000 Rp 19,000 Rp 34,000 Rp 34,000
12 Seal Tape uk. Besar bh Rp 15,000 Rp 15,000 Rp 14,000 Rp 14,000 Rp 13,000 Rp 13,000
13 Minyak Bekesting Ltr Rp 22,000 Rp 22,000 Rp 21,000 Rp 21,000 Rp 20,000 Rp 20,000
XV PERALATAN ELEKTRIKAL
1 Box Panel PVC isi 4 MCB bh
2 MCB 6 A bh Rp 59,500 Rp 59,500 Rp 58,500 Rp 58,500 Rp 57,500 Rp 57,500
3 MCB 4 A bh Rp 39,500 Rp 39,500 Rp 38,500 Rp 38,500 Rp 37,500 Rp 37,500
4 Kabel NYM 2x2,5 mm2 merk sigeru roll Rp 1,020,000 Rp 1,020,000 Rp 1,010,000 Rp 1,010,000 Rp 1,000,000 Rp 1,000,000
5 Kabel NYM 3x2,5 mm2 merk sigeru roll Rp 1,370,000 Rp 1,370,000 Rp 1,320,000 Rp 1,320,000 Rp 1,270,000 Rp 1,270,000
6 Kabel Telephone 4x0.5 mm roll Rp 250,000 Rp 250,000 Rp 245,000 Rp 245,000 Rp 240,000 Rp 240,000
7 Isolasi uk. Kecil bh Rp 12,000 Rp 12,000 Rp 11,000 Rp 11,000 Rp 105,000 Rp 105,000
8 Saklar Tunggal broco/panasonic bh Rp 20,500 Rp 19,500 Rp 18,500 Rp 18,500 Rp 18,500 Rp 18,500
9 Salar Ganda bh Rp 20,500 Rp 20,500 Rp 20,500 Rp 28,500 Rp 27,500 Rp 27,500
10 Stop Kontak 2 lubang bh Rp 34,500 Rp 34,500 Rp 32,500 Rp 28,500 Rp 30,500 Rp 30,500
11 Outlet TV bh Rp 52,500 Rp 52,500 Rp 50,500 Rp 50,500 Rp 48,500 Rp 50,500
12 Outlet Telephone bh Rp 50,500 Rp 50,500 Rp 48,500 Rp 48,500 Rp 46,500 Rp 46,500
13 Down light/PLC 13 w bh
14 Fitting Plafond + Lampu SL bh
15 Lampu TL 2 x 18 watt grille bh Rp 250,000 Rp 250,000 Rp 247,000 Rp 247,000 Rp 242,000 Rp 242,000
16 Lampu TL 2 x 36 watt grille bh Rp 362,000 Rp 362,000 Rp 275,000 Rp 275,000 Rp 252,000 Rp 252,000
II Bahan Perekat
1 Semen (50} Kg Semen Indonesia zak Rp 81,900
2 Semen Warna Semen Indonesia kg Rp 9,450
IV Bahan Kayu
1 Kayu klas I Jati m3 Rp 5,000,000
2 Kayu Klas II Kamper m3 Rp 2,250,000
3 Kayu Klas III Meranti m3 Rp 1,750,000
4 Kayu klas IV Terentang m3 Rp 1,500,000
5 Dolken Kayu Dia. 8-10Cm p. 4m btg Rp 11,000
V Bahan Alumunium
1 Kusen Alumunium 3"Alexindo m‘ Rp 74,300
2 Rangka Jandela Alumunium Alexindo m' Rp 71,300
3 Rangka Pintu Alumunium Alexindo m' Rp 78,125
4 Kusen Dan Pintu Pvc Toilet Maspion unit Rp 1,500,000
5 Engsel 3" Ex Bos bh Rp 32,500
6 Handle Pintu type HRE 75.01 ex. Cisa bh Rp 500,000
7 Silinder type 08510 ex Cisa bh Rp 190,000
8 Door Stoper bh Rp 95,000
9 Door Closer bh Rp 250,000
10 Slot Tanam bh Rp 65,000
11 Kait Angin bh Rp 15,000
12 Grendel bh Rp 15,000
VI Bahan Pelapis
1 Tripleks T. 3 Mm uk. 120 x 240 cm Lbr Rp 56,000
2 Tripleks T. 4 Mm uk. 120 x 240 cm Lbr Rp 90,000
3 Tripleks T. 9 Mm uk. 120 x 240 cm Lbr Rp 145,000
VII Bahan Lantai Dan Dinding Keramik Bahan Lantai dan Dinding Keramik
1 Keramik30/30 ex. Masterina m2 Rp 66,150
2 Granit Tile 40/40 Ex. Granitotile m2 Rp 195,800
3 Plin Keramik 10/30 Cm ex Roman bh Rp 3,500
4 Plin Granit Tile 10/40 Cm ex Granito bh Rp 10,000
IX
Bahan Kaca
1 Kaca Polos 3 Mm m2 Rp 175,000
2 Kacapolos 5 Mm m2 Rp 215,000
3 Kaca Polos 8 Mm m2 Rp 415,000
XI Bahan Finishing
1 Washtafel LW 240 CJ ax, Toto, komplit kren & acc unit Rp 620,000
2 Klosed Duduk CW 600J/ SW 660 J koomplit & Acc unit Rp 3,200,000
3 Koset Jongkok type CE 6 ex Toto unit Rp 750,000
4 Urinenoir type U 57 M ex Toto unit Rp 2,148,500
5 Bak Air Fiber Glass uk, 55 x 55 x 60 cm bh Rp 950,000
6 Shower Spray Type THX 20 NBPIV ex. Toto unit Rp 220,000
7 Shower Set typeTX 423 SZ ex. Toto unit Rp 1,300,000
8 Floor Drain TXlB ex Toto bh Rp 99,750
9 Tempat Sabun S11 N ex. Toto bh Rp 110,000
T 30 AR13MV7N ex.Toto bh
10 Kran Zink Rp 355,000
11 Kitchenzink Hwaco 1L unit Rp 1,525,000
12 Kran Dinding type T23 AR13NV7N ex. Toto bh Rp 99,750
XIII Bahan Partisi Dinding
XV Peralatan Elektrikal
II BAHAN PEREKAT
1 Semen (Kg) Semen Indonesia zak Rp 79,000.00
2 Semen Warna Semen Indonesia kg Rp 21,000.00
IV BAHAN KAYU
1 Kayu Kelas I Jati m3 Rp 5,200,000.00
2 Kayu Kelas II Kamper m3 Rp 3,000,000.00
3 Kayu Kelas III Meranti m3 Rp 2,200,000.00
4 Kayu Kelas IV Terentang n3 Rp 1,700,000.00
5 Dolken dia 8 s/d 10 mm p = 4 meter btg Rp 20,000.00
V BAHAN ALUMINIUM
1 Kusen Aluminium 3", Alexindo m' Rp 200,000.00
2 Rangka Jendela Aluminium Alexindo m' Rp 83,500.00
3 Rangka Pintu Aluminium Alexindo m' Rp 120,500.00
4 Kusen & Pintu PVC Toilet Maspion unit Rp 1,220,000.00
5 Engsel 3", Ex Boss bh Rp 20,000.00
6 Handle Pintu Type HRE 75.01 Ex Cisa bh Rp 151,300.00
7 Selinder Type 08510 Ex Cisa bh Rp 87,000.00
8 Door Stoper bh Rp 59,000.00
9 Door Closer bh Rp 376,500.00
10 Slot Tanam bh Rp 75,000.00
11 Kait Angin bh Rp 19,000.00
12 Grendel bh Rp 18,000.00
VI BAHAN PELAPIS
1 Tripleks t = 3 mm Uk 120 x 240 cm lbr Rp 65,000.00
2 Tripleks t = 4 mm Uk 120 x 240 cm lbr Rp 80,500.00
3 Tripleks t = 9 mm Uk 120 x 240 cm lbr Rp 145,000.00
IX BAHAN KACA
1 Kaca Polos 3 mm m2 Rp 120,000.00
2 Kaca Polos 5 mm m2 Rp 160,000.00
3 Kaca Polos 8 mm m2 Rp 190,000.00
XV PERALATAN ELEKTRIKAL
1 Box Panel PVC isi 4 MCB Legran bh Rp 255,000.00
2 MCB 4 A Legran bh Rp 92,000.00
3 MCB 6 A Legran bh Rp 80,000.00
4 Kabel NYM 2 x 2,5 mm2 m' Rp 15,000.00
5 Kabel NYM 3 x 2,5 mm2 m' Rp 19,500.00
6 Kabel Telephone 4 x 0,5 mm m' Rp 20,000.00
7 Isolasi bh Rp 16,000.00
8 Saklar Tunggal Broco bh Rp 23,000.00
9 Saklar Ganda Broco bh Rp 33,000.00
10 Stop Kontak Broco bh Rp 29,000.00
11 Outlet TV Broco bh Rp 95,000.00
12 Outlet Telephone Broco bh Rp 85,000.00
13 Downlight / PLC 13 W bh Rp 65,000.00
14 Fitting Plafond + Lampu SL Panasonic bh Rp 87,500.00
15 Lampu TL 2 x 18 watt grille Panasonic bh Rp 73,000.00
16 Lampu TL 2 x 36 watt grille Panasonic bh Rp 90,000.00
XVI UPAH KERJA
1 Tukang Besi Konstruksi Org/Hari Rp 98,000.00
2 Tukang Besi Tulangan Org/Hari Rp 98,000.00
3 Kepala Tukang Besi Org/Hari Rp 126,000.00
4 Tukang Kayu Kasar (Plafond, Kuda-kuda/Gording, R.Atap) Org/Hari Rp 98,000.00
5 Tukang Kayu Halus (Kusen) Org/Hari Rp 98,000.00
6 Kepala Tukang Kayu Org/Hari Rp 126,000.00
7 Tukang Batu Kasar Tukang Batu Kasar Org/Hari Rp 98,000.00
8 Tukang Batu Halus Tukang Batu Halus (Bata, Plester, Acian, List2) Org/Hari Rp 98,000.00
9 Kepala Tukang Batu Org/Hari Rp 126,000.00
10 Tukang Cat Biasa Org/Hari Rp 98,000.00
11 Kepala Tukang Cat Org/Hari Rp 126,000.00
12 Tukang Listrik Org/Hari Rp 98,000.00
13 Kepala Tukang Listrik Org/Hari Rp 126,000.00
14 Pekerja Org/Hari Rp 98,000.00
15 Mandor Org/Hari Rp 98,000.00
XVII LAIN-LAIN
1 IMB m2 Rp 15,000.00
Daftar Harga Bahan / Material Konstruksi
Kabupaten Tolitoli Tahun Anggaran 2018 - 2019
KECAMATAN
No Nama Bahan Satuan
Baolan Galang Dakopemean Tolitoli Utara Lampasio Ogodeide
1 2 3 4 5 6 7 8 9
I BATA, BATU, PASIR DAN TANAH
1 Batu Alam / Tempel M2 216,300 216,825 216,825 220,500 216,825 217,875
2 Batu Bata Merah Bh 1,323 1,313 1,313 2,153 1,313 1,617
3 Bata Beton Ringan Bh - - - - - -
4 Batako Bh 3,255 3,234 3,255 3,308 3,360 3,465
5 Batu Quari / Batu Besar / Batu Gunung Keras M3 301,740 280,340 416,850 574,350 521,850 710,850
6 Batu Kali (Besar) M3 301,740 280,340 416,850 574,350 521,850 710,850
7 Batu Kali (Kecil disaring) M3 301,740 280,340 416,850 574,350 521,850 710,850
8 Batu Pecah M3 599,025 572,460 719,775 1,013,775 719,775 824,775
9 Batu Kerikil Sungai (Tidak disaring) M3 332,500 299,156 387,840 488,840 488,840 697,200
10 Agregat Halus / Pasir Pasang M3 200,550 159,411 321,300 478,800 426,300 615,300
11 Kerikil Berpasiran Alami M3 - - - - - -
12 Bahan Timbunan / Pengikat Pilihan M3 129,864 98,098 169,764 123,500 109,914 120,750
13 Urugan Pilihan (Tanah Urug) M3 139,550 103,964 182,175 126,350 119,585 127,901
14 Sirtu M3 196,980 175,980 317,730 475,230 422,730 611,730
15 Tasirtu M3 150,654 129,654 158,718 327,957 292,866 482,979
II PAVING BLOCK
1 Paving Block Kotak Warna K 100 Bh 3,264 3,284 3,519 3,774 3,386 3,519
2 Paving Block Kotak Tidak Warna K 100 Bh 2,703 2,723 2,723 2,927 2,825 2,825
3 Paving Block Persegi Enam Warna K 100 Bh 4,131 4,151 4,386 4,641 4,253 4,386
4 Paving Block Persegi Enam Tidak Warna K 100 Bh 3,621 3,641 3,876 4,131 3,743 3,876
5 Paving Block Tiga Berlian Warna K 100 Bh 3,366 3,386 3,386 3,417 3,488 3,488
6 Paving Block Tiga Berlian Tidak Warna K 100 Bh 3,060 3,080 3,080 3,080 3,182 3,182
7 Paving Block (Biasa) Bh 2,162 2,193 2,193 2,193 2,295 2,295
VI BAHAN ALMUNIUM
1 Kusen Almunium Warna Cokelat M1 11,025 11,078 11,130 11,340 11,256 11,288
2 Kusen Almunium Warna Silver M1 95,025 95,078 95,130 95,340 95,256 95,288
3 Kusen Almunium Warna Putih M1 116,025 116,078 116,130 116,340 116,256 116,288
4 Kusen & Pintu PVC toilet M2 1,002,500 1,003,000 1,005,000 1,010,000 1,004,500 1,004,500
5 Kunci Tanam Bh 137,655 138,180 138,338 138,600 137,655 137,655
6 Engsel Jendela Bh 19,300 19,300 19,300 19,400 19,300 19,300
7 Engsel Pintu Bh 33,600 33,600 33,600 33,700 33,600 33,600
8 Grendel Jendela Bh 5,565 6,090 6,248 6,510 5,565 5,565
9 Grendel Pintu Bh 11,655 11,655 11,655 11,760 11,655 11,655
10 Handle Pintu Bh 250,100 250,100 250,100 250,200 250,100 250,100
11 Selinder Bh 52,605 53,130 53,288 53,550 52,500 52,500
12 Door Stoper Bh 26,355 26,880 27,038 27,300 26,250 26,250
13 Door Closer Bh 193,043 193,568 193,725 193,988 192,938 192,938
14 Slot Tanam Bh 52,605 53,130 53,288 53,550 52,605 52,605
15 Kait Angin Bh 15,750 15,750 15,750 15,750 15,750 15,750
16 Grendel Bh 11,100 11,100 11,100 11,200 11,100 1,100
17 Gembok/ Penggantung Psg 23,600 24,100 24,250 24,500 23,600 23,600
X BAHAN KACA
1 Kaca Bening 2 mm M2 86,100 86,625 87,150 87,360 86,625 87,150
2 Kaca Bening 3 mm M2 105,000 105,000 105,000 106,365 105,000 105,000
3 Kaca Bening 5 mm M2 139,650 140,175 140,700 140,910 140,175 140,700
4 Kaca ES 5 mm M2 192,675 193,200 193,725 193,935 193,200 193,725
5 Kaca Raybent 3 mm M2 103,425 103,950 104,475 104,685 103,950 104,475
6 Kaca Raybent 5 mm M2 132,300 132,300 132,300 133,665 132,300 132,300
XV PERALATAN ELEKTRIKAL
1 Box Panel PVC isi 4 MCB Bh 34,125 34,125 34,125 34,125 34,125 34,125
2 Box Panel PVC isi 2 Group Bh 10,920 11,130 11,183 10,920 10,920 11,025
3 MCB 6 A Bh 31,500 31,500 31,500 31,500 31,500 31,500
4 MCB 4 A Bh 31,500 31,500 31,500 31,500 31,500 31,500
5 Kabel NYM 2 x 2.5 mm2 M1 9,818 10,028 10,080 9,818 9,818 9,923
6 Kabel NYM 3 x 2.5 mm2 M1 14,490 14,700 14,753 14,490 14,490 14,595
7 Kabel Telephone 4 x 0.5 mm2 M1 3,675 3,885 3,938 3,675 3,675 3,780
8 Isolasi Bh 8,085 8,085 8,085 8,085 8,085 8,085
9 Saklar Tunggal Bh 13,755 13,965 14,018 13,755 13,860 13,860
10 Saklar Ganda Bh 19,898 20,108 20,160 20,423 19,898 20,003
11 Stop Kontak Bh 15,908 16,118 16,170 16,433 15,908 16,013
12 Outlet TV Bh 50,768 50,978 51,030 51,293 50,768 50,873
13 Outlet Telephone Bh 49,875 50,085 50,138 50,400 49,875 49,980
14 Down Light/PLC 13 W Bh 82,268 82,478 82,530 82,793 82,268 82,373
15 Fitting Plafond + Lampu SL Bh 36,089 36,299 36,351 36,614 36,089 36,194
16 Lampu TL 2 x 18 watt grille Bh 68,250 68,250 68,250 68,355 68,250 68,250
17 Lampu TL 2 x 36 watt grille Bh 61,950 62,160 62,213 62,475 61,950 62,055
18 Lampu Pijar 40 watt Bh 9,450 9,660 9,713 9,975 9,450 9,555
19 Lampu SL 18 watt Bh 34,560 34,650 34,650 34,755 34,650 34,650
20 Fitting Tanam Bh 39,375 39,585 39,638 39,900 39,375 39,480
21 Fitting Tempel Bh 10,500 10,710 10,763 11,025 10,500 10,605
22 Mangkok Listrik Bh 14,858 15,068 15,120 15,383 14,858 14,963
23 Klem Kabel Bh 11,235 11,235 11,235 11,340 11,235 11,235
XV PIPA GIP
1 Pipa GIP (SNI) 2" M1 79,380 79,695 80,220 80,430 80,325 80,357
2 Pipa GIP (SNI) 3" M1 129,150 129,675 130,200 130,410 130,305 130,368
3 Pipa GIP (SNI) 4" M1 186,270 186,795 187,320 187,635 187,425 187,509
4 Pipa GIP (SNI) 6" M1 286,755 287,280 287,805 288,120 287,910 288,005
5 Pipa GIP (SNI) 8" M1 519,750 520,275 520,590 520,800 520,590 520,706
6 Pipa GIP (SNI) 10" M1 918,225 918,750 918,960 919,275 919,065 919,086
7 Pipa GIP (SNI) 12" M1 2,347,695 2,348,220 2,348,535 2,348,745 2,348,640 2,348,672
XIX ASESORIS GI
1 Bend Steel All Flanged 900 12" Bh 1,765,680 1,765,890 1,766,205 1,766,415 1,766,205 1,766,289
2 Bend Steel All Flanged 900 10" 1,283,625 1,283,940 1,284,150 1,284,465 1,284,255 1,284,287
3 Bend Steel All Flanged 900 8" 588,945 589,260 589,470 589,785 589,575 589,607
4 Bend Steel All Flanged 900 6" 444,780 444,990 445,305 445,515 445,305 445,379
5 Bend Steel All Flanged 900 4" 250,215 250,425 250,740 250,950 250,740 250,824
6 Bend Steel All Flanged 900 3" 196,455 196,665 196,980 197,190 196,980 197,033
7 Bend Steel All Flanged 900 2" 134,820 135,030 135,345 135,555 135,345 135,440
8 Bend Steel All Flanged 900 1" 14,805 15,015 15,330 15,540 15,330 15,404
9 Bend Steel All Flanged 450 12" 1,606,605 1,606,815 1,607,130 1,607,340 1,607,130 1,607,214
10 Bend Steel All Flanged 450 10" 1,219,995 1,220,310 1,220,520 1,220,835 1,220,625 1,220,657
11 Bend Steel All Flanged 450 8" 605,850 606,060 606,375 606,585 606,375 606,470
12 Bend Steel All Flanged 450 6" 398,580 398,895 399,105 399,420 399,210 399,242
13 Bend Steel All Flanged 450 4" 250,215 250,425 250,740 250,950 250,740 250,824
14 Bend Steel All Flanged 450 3" 205,275 205,590 205,800 206,115 205,905 205,947
15 Bend Steel All Flanged 450 2" 139,020 139,335 139,545 139,860 139,650 139,682
16 Bend Steel All Flanged 450 1" 16,485 16,695 17,010 17,220 17,010 17,105
17 Bend Steel All Flanged 22.50 12" 1,606,605 1,606,815 1,607,130 1,607,340 1,607,130 1,607,214
18 Bend Steel All Flanged 22.50 10" 1,219,995 1,220,310 1,220,520 1,220,835 1,220,625 1,220,657
19 Bend Steel All Flanged 22.50 8" 693,945 694,260 694,470 694,785 694,575 694,596
20 Bend Steel All Flanged 22.50 6" 458,010 458,220 458,535 458,745 458,535 458,630
21 Bend Steel All Flanged 22.50 4" 333,480 333,690 334,005 334,215 334,005 334,079
22 Bend Steel All Flanged 22.50 3" 205,275 205,590 205,800 206,115 205,905 205,947
23 Bend Steel All Flanged 22.50 2" 139,020 139,335 139,545 139,860 139,650 139,682
24 Bend Steel All Flanged 22.50 1" 16,485 16,695 17,010 17,220 17,010 17,105
25 Gate Valve Double Flange 12" 9,877,665 9,887,875 9,878,190 9,878,400 9,878,190 9,878,285
26 Gate Valve Double Flange 10" 7,762,755 7,762,965 7,763,280 7,763,490 7,763,280 7,763,333
27 Gate Valve Double Flange 8" 4,252,920 4,253,235 4,253,445 4,253,760 4,253,550 4,253,582
28 Gate Valve Double Flange 6" 2,766,015 2,766,225 2,766,540 2,766,750 2,766,540 2,766,614
29 Gate Valve Double Flange 4" 1,567,650 1,567,965 1,568,175 1,568,490 1,568,280 1,568,312
30 Gate Valve Double Flange 3" 1,419,285 1,419,495 1,419,810 1,420,020 1,419,810 1,419,905
31 Gate Valve Double Flange 2" 990,045 990,360 990,570 990,885 990,675 990,675
32 Stop kran 2" 506,835 507,045 507,360 507,570 507,360 507,423
33 Kran 3/4" 32,865 32,865 32,865 32,865 32,865 32,865
34 Kran 1/2" 27,510 27,510 27,510 27,510 27,510 27,563
35 Tee All Flanged 12" 2,316,825 2,317,140 2,317,350 2,317,665 2,317,455 2,317,466
36 Tee All Flanged 10" 1,325,100 1,325,310 1,325,625 1,325,835 1,325,625 1,325,699
37 Tee All Flanged 8" 860,160 860,475 860,685 861,000 860,790 860,790
38 Tee All Flanged 6" 589,470 589,680 589,995 590,205 589,995 590,048
39 Tee All Flanged 4" 361,620 361,830 362,145 362,355 362,145 362,219
40 Tee All Flanged 3" 284,970 285,285 285,495 285,810 285,600 285,642
41 Tee All Flanged 2" 197,190 197,400 197,715 197,925 197,715 197,778
42 Giboult Joint untuk Pipa GIP 12" 1,493,310 1,493,625 1,493,835 1,494,150 1,493,940 1,493,961
43 Giboult Joint untuk Pipa GIP 10" 1,120,350 1,120,560 1,120,875 1,121,085 1,120,875 1,120,938
44 Giboult Joint untuk Pipa GIP 8" 949,095 949,410 949,620 949,935 949,725 949,736
45 Giboult Joint untuk Pipa GIP 6" 772,905 773,220 773,430 773,745 773,535 773,577
46 Giboult Joint untuk Pipa GIP 4" 416,850 417,060 417,375 417,585 417,375 417,470
47 Giboult Joint untuk Pipa GIP 3" 289,275 289,590 289,800 290,115 289,905 289,916
48 Giboult Joint untuk Pipa GIP 2" 241,395 241,605 241,920 242,130 241,920 241,983
49 Flange Steel 12" 408,030 408,345 408,555 408,870 408,660 408,692
50 Flange Steel 10" 403,725 403,935 404,250 404,460 404,250 404,345
51 Flange Steel 8" 269,535 269,850 270,060 270,375 270,165 270,197
52 Flange Steel 6" 174,300 174,615 174,825 175,140 174,930 174,962
53 Flange Steel 4" 108,360 108,675 108,885 109,200 108,990 109,001
54 Flange Steel 3" 66,045 66,360 66,570 66,885 66,675 66,686
55 Flange Steel 2" 57,225 57,540 57,750 58,065 57,855 57,876
56 Clamp Sadle 10" x 1/2" GI 242,865 242,865 243,180 243,390 243,180 243,254
57 Clamp Sadle 8" x 1/2" GI 123,060 123,060 123,270 123,585 123,375 123,417
58 Clamp Sadle 6" x 1/2" GI 65,205 65,205 65,415 65,730 65,520 65,520
59 Clamp Sadle 4" x 1/2" GI 38,850 38,850 39,165 39,375 39,165 39,218
60 Clamp Sadle 3" x 1/2" GI 32,025 32,025 32,340 32,550 32,340 32,424
61 Clamp Sadle 2" x 1/2" GI 25,725 25,725 25,935 26,250 26,040 26,061
62 Striner GI 12" 2,317,245 2,317,455 2,317,770 2,317,980 2,317,770 2,317,883
63 Striner GI 10" 896,805 897,120 897,330 897,645 897,435 897,446
64 Striner GI 8" 504,420 504,735 504,945 505,260 505,050 505,050
65 Striner GI 6" 276,885 277,095 277,410 277,620 277,484 277,515
66 Baut Mur 5/8 8,610 8,610 8,610 8,610 8,684 8,610
XX ASESORIS HDPE
1 Stub Flange HDPE 12" Bh 2,444,820 2,445,135 2,445,345 2,445,660 2,445,450 2,445,513
2 Stub Flange HDPE 10" Bh 1,674,855 1,675,170 1,675,380 1,675,695 1,675,485 1,675,538
3 Stub Flange HDPE 8" Bh 1,223,250 1,223,460 1,223,775 1,223,985 1,223,880 1,223,922
4 Stub Flange HDPE 6" Bh 851,340 851,655 851,865 852,180 851,970 852,033
5 Stub Flange HDPE 4" Bh 453,180 453,390 453,705 453,915 453,810 453,842
6 Stub Flange HDPE Ø 3" BH 384,090 384,300 384,615 384,825 384,720 384,731
7 Stub Flange HDPE Ø 2" BH 235,410 235,725 235,935 236,250 236,040 236,135
8 Bend PE Ø 12" x 45° BH 1,767,360 1,767,570 1,767,885 1,768,095 1,767,990 1,768,011
9 Bend PE Ø 10" x 45° BH 673,575 673,785 674,100 674,310 674,205 674,205
10 Bend PE Ø 8" x 45° BH 335,055 335,370 335,580 335,895 335,685 335,759
11 Bend PE Ø 6" x 45° BH 197,295 197,610 197,820 198,135 197,925 198,009
12 Bend PE Ø 4" x 45° BH 87,465 87,675 57,990 88,200 88,095 88,106
13 Bend PE Ø 3" x 45° BH 60,690 60,900 61,215 61,425 61,320 61,352
14 Bend PE Ø 2" x 45° BH 34,020 34,230 34,545 34,755 34,650 34,671
15 Reducer HDPE Ø 12" x 10" BH 1,596,420 1,596,735 1,596,945 1,597,260 1,597,050 1,597,113
16 Reducer HDPE Ø 10" x 8" BH 556,080 556,290 556,605 556,815 556,710 556,710
17 Reducer HDPE Ø 8" x 6" BH 321,825 322,035 322,350 322,560 322,455 322,497
18 Reducer HDPE Ø 6" x 4" BH 184,275 184,590 184,800 185,115 184,905 184,979
19 Reducer HDPE Ø 4" x 3" BH 82,005 82,215 82,530 82,740 82,635 82,667
20 Reducer HDPE Ø 3" x 2" BH 76,545 76,755 77,070 77,280 77,175 77,186
21 Reducer HDPE Ø 2" x 1" BH 47,775 47,985 48,300 48,510 48,405 48,426
22 Tee PE Ø 12" BH 4,653,075 4,653,390 4,653,600 4,653,915 4,653,705 4,653,779
23 Tee PE Ø 10" BH 1,480,395 1,480,605 1,480,920 1,481,130 1,481,025 1,481,036
24 Tee PE Ø 8" BH 900,900 901,110 901,425 901,635 901,530 901,541
25 Tee PE Ø 6" BH 567,210 567,525 5,644,735 568,050 567,840 567,893
26 Tee PE Ø 4" BH 258,300 258,615 258,825 259,140 258,930 258,983
27 Tee PE Ø 3" BH 178,395 178,605 178,920 179,130 179,025 179,036
28 Tee PE Ø 2" BH 64,785 65,100 65,310 65,625 65,415 65,468
P
II BAHAN PEREKAT P
1 Semen (50) Kg Semen Indonesia zak Rp ### N
75,500.00
2 Semen Warna Semen Indonesia kg Rp 22,900.00
###
IV BAHAN KAYU
1 Kayu Klas I m3 Rp 3,615,000.00
###
2 Kayu Klas II Kamper m3 Rp 2,349,000.00
###
3 Kayu Klas III Meranti m3 Rp 2,149,000.00
###
4 Kayu Klas IV Terentang m3 Rp 1,200,000.00
###
5 Dolken dia 8 s/d 10cm p. 4m btg Rp 20,500.00
###
V BAHAN ALMUNIUM
1 Kusen Almunium 3" Alexindo m' Rp ###
298,900.00
2 Rangka Jendela Almunium Alexindo m' Rp ###
172,000.00
3 Rangka Pintu Almunium Alexindo m' Rp ###
235,000.00
4 Kusen & Pintu PVC Toilet Maspion unit Rp ###
418,700.00
5 Engsel 3", ex Bos bh Rp ###
45,100.00
6 Handle pintu type HRE 75.01 ex. Cisa bh Rp ###
433,000.00
7 Selinder type 08510 ex. Cisa bh Rp ###
124,000.00
8 Door Stoper bh Rp ###
460,000.00
9 Door Closer bh Rp ###
391,000.00
10 Slot Tanam bh Rp ###
124,000.00
11 Kait Angin bh Rp ###
46,000.00
12 Grendel bh Rp 35,100.00
###
VI BAHAN PELAPIS
1 Triplek t.3 mm uk. 120x240 cm Lbr Rp 59,600.00
###
2 Triplek t.4 mm uk. 120x240 cm Lbr Rp 82,100.00
###
3 Triplek t.9 mm uk. 120x240 cm Lbr Rp 151,000.00
###
VII BAHAN LANTAI & DINDING KERAMIK
1 Keramik 30/30 m2 Rp 54,000.00
###
2 Granite Tile 40/40 m2 Rp 185,000.00
###
3 Plint Keramik 10/30cm bh Rp 15,000.00
###
4 Plint Granite Tile 10/40cm bh Rp 38,000.00
###
IX BAHAN KACA
1 Kaca Polos 3 mm m2 Rp 180,900.00
###
2 Kaca Polos 5 mm m2 Rp 206,400.00
###
3 Kaca Polos 8 mm m 2
Rp 360,000.00
###
XI BAHAN FINISHING
1 Cat Kayu/Besi ex.SEIV kg Rp 64,500.00
###
2 Plamir Kayu kg Rp 40,500.00
###
3 Meni Kayu ex.Nippon kg Rp 40,500.00
###
4 Wood Filler Impra kg Rp 64,900.00
###
5 Thinner ND IMPALA Ltr Rp 35,800.00
###
6 Amplas Kayu Lbr Rp 10,000.00
###
7 Kwas Cat bh Rp 13,300.00
###
8 Cat Tembok KW 1 ex. Dulax; warna standar kg Rp 44,350.00
###
9 Cat Tembok KW 2 ex. Vinilex; warna standar kg Rp 22,788.00
###
10 Plamir Tembok kg Rp 14,540.00
###
11 Lem kayu kg Rp 58,300.00
###
12 Seal Tape bh Rp 11,500.00
###
13 Minyak Bekesting Ltr Rp 15,800.00
###
XV PERALATAN ELEKTRIKAL
1 Box Panel PVC isi 4 MCB Legran bh Rp 45,100.00
###
2 MCB 6 A Legran bh Rp 54,000.00
###
3 MCB 4 A Legran bh Rp 61,000.00
###
4 Kabel NYM 2x2,5 mm2 m' Rp 8,675.00
###
5 Kabel NYM 3x2,5 mm2 m' Rp 12,525.00
###
6 Kabel Telephone 4x0.5 mm m' Rp 5,000.00
###
7 Isolasi bh Rp 13,000.00
###
8 Saklar Tunggal Broco bh Rp 19,100.00
###
9 Salar Ganda Broco bh Rp 34,100.00
###
10 Stop Kontak Broco bh Rp 27,100.00
###
11 Outlet TV Broco bh Rp 44,000.00
###
12 Outlet Telephone Broco bh Rp 51,000.00
###
13 Down Light/PLC 13 w bh Rp 58,000.00
###
14 Fitting Plafond + Lampu SL Panasonic bh Rp 13,000.00
###
15 Lampu TL 2 x 18 watt grille Panasonic bh Rp 213,000.00
###
16 Lampu TL 2 x 36 watt grille Panasonic bh Rp 213,000.00
###
XVI UPAH PEKERJA
1 Tukang Besi Konstruksi org/hari Rp 125,000.00
###
2 Tukang Besi Tulangan org/hari Rp 125,000.00
###
3 Kepala Tukang Besi org/hari Rp 150,000.00
###
4 Tukang Kayu Kasar (Plafond, Kuda/Gording R. Atap) org/hari Rp 125,000.00
###
5 Tukang Kayu Halus Kusen org/hari Rp 125,000.00
###
6 Kepala Tukang Kayu org/hari Rp 150,000.00
###
7 Tukang Batu Kasar Tukang Batu Kasar org/hari Rp 125,000.00
###
8 Tukang Batu Halus Tukang Batu Halus (Bata,Plester,Acian List2) org/hari Rp 125,000.00
###
9 Kepala Tukang Batu org/hari Rp 150,000.00
###
10 Tukang Cat Biasa org/hari Rp 125,000.00
###
11 Kapala Tukang Cat org/hari Rp 150,000.00
###
12 Tukang Listrik org/hari Rp 125,000.00
###
13 Kepala Tukang Listrik org/hari Rp 150,000.00
###
14 Pekerja org/hari Rp 80,000.00
###
15 Mandor org/hari Rp 125,000.00
###
XVII LAIN-LAIN
1 IMB m2 ###
DAFTAR HARGA BAHAN PAN UPAH
Provinsi : Sulawesi Tengah
Kota/Kabupaten : Kabupaten Morowali
Tahun : 2018
No. SK
Ditetapkan Oleh : Bupati Morowali
Nama : Taslim
Ditetapkan di : Bungku
Tanggal ........./September/2018
II Bahan Perekat
1 Semen (50} Kg Semen Indonesia zak Rp 109,000
2 Semen Warna Semen Indonesia kg Rp 30,000
IV Bahan Kayu
1 Kayu klas I Jati m3 Rp 4,500,000
2 Kayu Klas II Kamper m3 Rp 3,500,000
3 Kayu Klas III Meranti m3 Rp 2,700,000
4 Kayu klas IV Terentang m3 Rp 1,800,000
5 Dolken Kayu Dia. 8-10Cm p. 4m btg Rp 20,500
V Bahan Alumunium
1 Kusen Alumunium 3"Alexindo m‘ Rp 139,000
2 Rangka Jandela Alumunium Alexindo m' Rp 84,500
3 Rangka Pintu Alumunium Alexindo m' Rp 265,000
4 Kusen Dan Pintu Pvc Toilet Maspion unit Rp 885,000
5 Engsel 3" Ex Bos bh Rp 101,400
6 Handle Pintu type HRE 75.01 ex. Cisa bh Rp 355,000
7 Silinder type 08510 ex Cisa bh Rp 285,000
8 Door Stoper bh Rp 122,000
9 Door Closer bh Rp 368,000
10 Slot Tanam bh Rp 148,000
11 Kait Angin bh Rp 130,000
12 Grendel bh Rp 35,000
VI Bahan Pelapis
1 Tripleks T. 3 Mm uk. 120 x 240 cm Lbr Rp 80,000
2 Tripleks T. 4 Mm uk. 120 x 240 cm Lbr Rp 90,000
3 Tripleks T. 9 Mm uk. 120 x 240 cm Lbr Rp 130,000
VII Bahan Lantai Dan Dinding Keramik Bahan Lantai dan Dinding Keramik
1 Keramik30/30 ex. Masterina m2 Rp 120,000
2 Granit Tile 40/40 Ex. Granitotile m 2
Rp 275,000
3 Plin Keramik 10/30 Cm ex Roman bh Rp 3.333
4 Plin Granit Tile 10/40 Cm ex Granito bh Rp 11,458
IX
Bahan Kaca
1 Kaca Polos 3 Mm m2 Rp 155,000
2 Kacapolos 5 Mm m2 Rp 225,000
3 Kaca Polos 8 Mm m 2
Rp 270,000
XI Bahan Finishing
1 Washtafel LW 240 CJ ax, Toto, komplit kren & acc unit Rp 1,200,000
2 Klosed Duduk CW 600J/ SW 660 J koomplit & Acc unit Rp 2,400,000
3 Koset Jongkok type CE 6 ex Toto unit Rp 327,000
4 Urinenoir type U 57 M ex Toto unit Rp 1,105,000
5 Bak Air Fiber Glass uk, 55 x 55 x 60 cm bh Rp 380,000
6 Shower Spray Type THX 20 NBPIV ex. Toto unit Rp 300,000
7 Shower Set typeTX 423 SZ ex. Toto unit Rp 720,000
8 Floor Drain TXlB ex Toto bh Rp 60,000
9 Tempat Sabun S11 N ex. Toto bh Rp 85,000
T 30 AR13MV7N ex.Toto bh
10 Kran Zink Rp 345,000
11 Kitchenzink Hwaco 1L unit Rp 320,000
12 Kran Dinding type T23 AR13NV7N ex. Toto bh Rp 140,000
XIII Bahan Partisi Dinding
I. UPAH
1.1 Pekerja 1 Hari 70,000 88,000 61,000 67,100 67,100 69,000 69,000 95,000 75,000 6,100 70,000 88,000 61,000 67,100 67,100 75,000
1.2 Tukang 2 Hari 100,000 137,500 70,000 77,000 77,000 128,500 128,500 128,500 7,000 100,000 137,500 65,000 71,500 71,500 90,000
1.3 Kepala Tukang 10 Hari 125,000 165,000 80,000 88,000 88,000 128,500 128,500 128,500 8,000 125,000 165,000 67,000 73,700 73,700 105,000
1.4 Mandor 3 Hari 150,000 192,500 87,000 95,700 95,700 128,500 128,500 145,000 128,500 8,700 150,000 192,500 68,750 75,625 75,625 110,000
1.5 Operator 4 Jam 35,000 55,000 82,500 90,750 90,750 55,000 90,750 8,250 35,000 55,000 82,500 90,750 90,750
1.6 Pembantu Operator 5 Jam 25,000 38,500 20,000 22,000 22,000 38,500 22,000 2,000 25,000 38,500 20,000 22,000 22,000
1.7 Sopir / Driver 6 Hari 125,000 192,500 100,000 110,000 110,000 192,500 110,000 10,000 125,000 192,500 100,000 110,000 110,000
1.8 Pembantu Sopir / Kernet 7 Hari 65,000 78,650 65,000 71,500 71,500 78,650 71,500 6,500 65,000 78,650 65,000 71,500 71,500
1.9 Juru Ukur 11 Hari 250,000 330,000 160,000 176,000 176,000 330,000 176,000 16,000 250,000 330,000 160,000 176,000 176,000
1.10 Pembantu Juru Ukur 12 Hari 70,000 88,000 65,000 71,500 71,500 88,000 71,500 6,500 70,000 88,000 65,000 71,500 71,500
II. BAHAN
2.1 Pasir Pasang 1 M3 90,909 150,000 113,636 113,636 113,636 127,000 127,000 142,000 127,000 On Site 155,036 226,594 90,000 90,000 90,000 110,000
2.2 Batu Kali 2 M3 204,545 400,000 207,000 207,000 207,000 213,000 213,000 241,000 213,000 On Site 250,318 456,482 115,300 115,300 115,300 140,000
2.3 Agregat Kasar/Kerikil Sungai 3 M3 159,091 315,000 138,000 142,000 142,000 170,000 170,000 104,000 104,000 On Site 159,091 285,000 127,000 127,000 127,000 145,000
2.4 Tanah Urug 4 M3 100,000 135,000 57,500 57,500 57,500 81,000 81,000 90,000 90,000 Quary 100,000 135,000 57,500 66,220 66,220 80,000
2.5 Semen / PC (50kg) 6 Zak 68,182 100,000 70,000 75,000 75,000 60,000 75,000 72,000 72,000 On Site 85,800 103,818 59,000 70,000 70,000 62,000
2.6 Besi Beton 7 Kg 15,000 24,000 12,096 15,000 15,000 15,000 15,000 On Site 15,000 24,000 13,135 15,000 15,000
2.7 Kawat Beton 8 Kg 20,000 24,200 23,364 23,364 23,364 25,000 25,000 25,000 On Site 20,000 24,200 20,000 20,000 20,000 25,000
2.8 Sirtu 10 M3 159,091 315,000 138,000 140,000 140,000 84,000 140,000 142,000 140,000 On Site 159,091 285,000 115,000 115,000 115,000
2.9 Paku 11 Kg 18,873 22,836 20,000 20,000 20,000 20,000 20,000 22,000 22,000 On Site 18,873 22,836 20,000 20,000 20,000
2.10 Kayu Daerah (Papan/Balok) 12 M3 2,050,909 2,481,600 1,800,000 1,900,000 1,900,000 2,100,000 1,900,000 On Site 2,050,909 2,481,600 1,450,000 1,450,000 1,450,000
2.11 Kayu Kelas II M3 2,272,727 3,000,000 2,122,727 2,122,727 2,600,000 2,000,000 On Site 2,272,727 3,000,000 2,272,727 2,272,727 4,500,000
2.12 Bensin 13 LITER 9,091 13,000 10,000 10,000 10,000 10,000 10,000 On Site 9,091 13,000 10,000 10,000 10,000
2.13 Solar 14 LITER 9,091 14,500 13,000 13,000 13,000 13,000 13,000 On Site 9,091 14,500 13,000 13,000 13,000
2.14 Minyak Pelumas / Olie 15 LITER 40,909 60,000 30,000 40,909 40,909 40,909 40,909 On Site 40,909 60,000 30,000 40,909 40,909
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 323,636 425,000 356,000 370,000 370,000 370,000 370,000 On Site 323,636 425,000 356,000 370,000 370,000
2.16 Bronjong Pabrikasi, 3 mm 16 Bh 385,455 500,000 On Site 385,455 500,000
2.17 Triplex Tebal 3mm 17 Lbr 62,500 75,625 120,000 120,000 120,000 54,000 54,000 On Site 62,500 75,625 120,000 120,000 120,000 56,000
2.18 Pipa GIP 3" ( 6 m) 21 m 129,091 166,500 151,364 151,364 151,364 460,000 151,364 151,364 On Site 129,091 166,500 151,364 151,364 151,364
2.19 Pipa GIP 4" ( 6 m) m 227,273 320,000 318,182 318,182 318,182 625,000 318,182 318,182 On Site 227,273 320,000 318,182 318,182 318,182
2.20 Pipa Pvc 6'' (6 m) m 168,182 210,000 143,636 168,182 168,182 260,000 168,182 168,182 On Site 168,182 210,000 143,636 168,182 168,182
2.21 Pipa Pvc 2" ( 4 m) m 35,455 45,000 27,273 35,455 35,455 80,000 80,000 80,000 On Site 35,455 45,000 27,273 27,273 27,273 42,500
2.22 Pipa Pvc 4" ( 4 m) m 104,545 150,000 102,273 104,545 104,545 130,000 130,000 100,083 130,000 On Site 104,545 34,000 102,273 104,545 104,545 150,000
2.23 Pipa Pvc 3" ( 4 m) m 69,091 110,000 75,000 75,000 75,000 160,000 160,000 160,000 On Site 69,091 110,000 75,000 75,000 75,000 110,000
2.24 Pipa Pvc 3/4" ( 4 m) m 19,091 34,000 22,727 22,727 22,727 29,000 29,000 38,333 38,000 On Site 19,091 34,000 22,727 22,727 22,727 32,000
2.25 Pipa Pvc 3" ( 6 m) m 74,561 74,561 74,561 180,000 180,000 164,083 164,000 On Site SHB 2015 73,168 73,168 73,168
2.26 Pipa PVC 4" ( 6 m) m 112,118 112,118 112,118 190,000 190,000 192,083 190,000 On Site SHB 2015 110,023 110,023 110,023
III. A L A T.
3.1 Excavator 1 Jam 642,000 794,475 612,195 628,298 628,298 686,344 642,000 794,475 612,195 628,298 628,298
3.2 Dump Trcuk 5 Ton 2 Jam 347,750 423,720 329,696 364,181 364,181 366,503 347,750 423,720 329,696 364,181 364,181
3.3 Concrette Mixer 3 Jam 42,800 55,908 45,112 56,884 56,884 57,581 42,800 55,908 45,112 56,884 56,884
3.4 Pompa Sentrifugal 4 Jam 14,980 22,363 14,902 26,958 26,958 27,052 14,980 22,363 14,902 26,958 26,958
3.5 Stamper Jam 13,910 20,009 13,776 25,892 25,892 26,124 13,910 20,009 13,776 25,892 25,892
Harga Kabupaten/Kota.
No. Uraian
Kab. SIGI Sat.
( Rp ) CATATAN KET
HPS 2018
1 2 3 19 20 21
I. UPAH
1.1 Pekerja 1 Hari 75,000 6,100
1.2 Tukang 2 Hari 90,000 6,500
1.3 Kepala Tukang 10 Hari 105,000 6,700
1.4 Mandor 3 Hari 110,000 6,875
1.5 Operator 4 Jam 90,750 8,250
1.6 Pembantu Operator 5 Jam 22,000 2,000
1.7 Sopir / Driver 6 Hari 110,000 10,000
1.8 Pembantu Sopir / Kernet 7 Hari 71,500 6,500
1.9 Juru Ukur 11 Hari 176,000 16,000
1.10 Pembantu Juru Ukur 12 Hari 71,500 6,500
II. BAHAN
2.1 Pasir Pasang 1 M3 110,000 On Site
2.2 Batu Kali 2 M3 140,000 On Site
2.3 Agregat Kasar/Kerikil Sungai 3 M3 145,000 On Site
2.4 Tanah Urug 4 M3 80,000 Quary
2.5 Semen / PC (50kg) 6 Zak 70,000 On Site
2.6 Besi Beton 7 Kg 15,000 On Site
2.7 Kawat Beton 8 Kg 25,000 On Site
2.8 Sirtu 10 M3 115,000 On Site
2.9 Paku 11 Kg 20,000 On Site
2.10 Kayu Daerah (Papan/Balok) 12 M3 1,450,000 On Site
2.11 Kayu Kelas II M3 On Site
2.12 Bensin 13 LITER 10,000 On Site
2.13 Solar 14 LITER 13,000 On Site
2.14 Minyak Pelumas / Olie 15 LITER 40,909 On Site
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 370,000 On Site
2.16 Bronjong Pabrikasi, 3 mm 16 Bh On Site
2.17 Triplex Tebal 3mm 17 Lbr 120,000 On Site
2.18 Pipa GIP 3" ( 6 m) 21 m 151,364 On Site
2.19 Pipa GIP 4" ( 6 m) m 318,182 On Site
2.20 Pipa Pvc 6'' (6 m) m 168,182 On Site
2.21 Pipa Pvc 2" ( 4 m) m 42,500 On Site
2.22 Pipa Pvc 4" ( 4 m) m 150,000 On Site
2.23 Pipa Pvc 3" ( 4 m) m 110,000 On Site
2.24 Pipa Pvc 3/4" ( 4 m) m 32,000 On Site
2.25 Pipa Pvc 3" ( 6 m) m 73,168 On Site SHB 2015
2.26 Pipa PVC 4" ( 6 m) m 110,023 On Site SHB 2015
III. A L A T.
3.1 Excavator 1 Jam 686,344
I. UPAH
1.1 Pekerja 1 Hari 75,000 99,000 70,500 77,550 77,550 97,000 97,000 98,000 97,000 7,050 HASIL RAPAT 90,000 118,800 78,700 84,996 84,996 85,000
1.2 Tukang 2 Hari 110,000 148,500 90,500 99,550 99,550 97,000 105,000 98,000 98,000 9,050 132,000 178,200 110,000 118,800 118,800 100,000
1.3 Kepala Tukang 10 Hari 135,000 176,000 100,000 110,000 110,000 126,000 120,000 126,000 120,000 10,000 162,000 211,200 125,900 135,972 135,972 150,000
1.4 Mandor 3 Hari 160,000 203,500 101,000 111,100 111,100 97,000 125,000 98,000 97,000 10,100 HASIL RAPAT 192,000 244,200 141,500 152,820 152,820 125,000
1.5 Operator 4 Jam 50,000 82,500 82,500 90,750 90,750 90,750 90,750 90,750 90,750 8,250 60,000 99,000 82,500 89,100 89,100
1.6 Pembantu Operator 5 Jam 25,000 38,500 20,000 22,000 22,000 22,000 22,000 22,000 22,000 2,000 30,000 46,200 20,000 21,600 21,600
1.7 Sopir / Driver 6 Hari 125,000 192,500 100,000 110,000 110,000 110,000 110,000 110,000 110,000 10,000 150,000 231,000 100,000 108,000 108,000
1.8 Pembantu Sopir / Kernet 7 Hari 65,000 78,650 65,000 71,500 71,500 71,500 71,500 71,500 71,500 6,500 78,000 94,380 65,000 70,200 70,200
1.9 Juru Ukur 11 Hari 250,000 330,000 160,000 176,000 176,000 176,000 176,000 176,000 176,000 16,000 300,000 396,000 160,000 172,800 172,800
1.10 Pembantu Juru Ukur 12 Hari 75,000 99,000 65,000 71,500 71,500 71,500 71,500 71,500 71,500 6,500 90,000 118,800 65,000 70,200 70,200
II. BAHAN
2.1 Pasir Pasang 1 M3 227,273 300,000 160,000 160,000 160,000 190,000 165,000 156,750 148,913 On Site 227,273 360,000 160,000 160,000 160,000 283,333
2.2 Batu Kali 2 M3 295,455 350,000 276,818 276,818 276,818 212,000 276,818 262,977 249,828 On Site HASIL RAPAT 295,455 420,000 284,545 284,545 284,545 300,000
2.3 Agregat Kasar/Kerikil Sungai 3 M3 281,818 325,000 296,454 296,454 296,454 230,000 296,454 281,631 267,549 On Site HASIL RAPAT 281,818 390,000 265,936 265,936 265,936 283,333
2.4 Tanah Urug 4 M3 100,000 135,000 57,500 57,500 57,500 90,000 90,000 85,500 81,225 Quary HASIL RAPAT 100,000 162,000 57,500 57,500 57,500 115,000
2.5 Semen / PC (50kg) 6 Zak 72,727 100,000 76,364 76,364 76,364 65,000 87,000 80,000 80,000 On Site HASIL RAPAT 72,727 120,000 88,182 88,182 88,182 75,000
2.6 Besi Beton 7 Kg 15,000 24,000 14,520 15,000 15,000 15,600 15,600 14,100 14,100 On Site 15,000 28,800 14,821 15,000 15,000
2.7 Kawat Beton 8 Kg 22,727 27,500 25,000 25,000 25,000 30,000 30,000 31,000 31,000 On Site 22,727 33,000 25,850 25,850 25,850 25,000
2.8 Sirtu 10 M3 281,818 325,000 173,500 175,000 175,000 130,000 175,000 138,000 138,000 On Site 281,818 390,000 175,000 175,000 175,000 250,000
2.9 Paku 11 Kg 18,182 22,000 18,000 18,000 18,000 22,950 22,950 24,000 24,000 On Site 18,182 26,400 19,800 19,800 19,800 25,000
2.10 Kayu Daerah (Papan/Balok) 12 M3 2,272,727 2,625,000 2,386,364 2,386,364 2,386,364 2,210,000 2,386,364 On Site 2,272,727 3,150,000 1,555,000 1,555,000 1,555,000 1,750,000
2.11 Kayu Kelas II M3 2,454,545 3,000,000 2,454,545 2,454,545 2,860,000 2,454,545 2,200,000 2,200,000 On Site 2,454,545 3,600,000 2,454,545 2,454,545
2.12 Bensin 13 LITER 9,091 13,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000 On Site 9,091 15,600 10,000 10,000 10,000
2.13 Solar 14 LITER 9,091 14,500 13,000 13,000 13,000 13,000 13,000 13,000 13,000 On Site 9,091 17,400 13,000 13,000 13,000
2.14 Minyak Pelumas / Olie 15 LITER 40,909 60,000 30,000 40,909 40,909 40,909 40,909 40,909 40,909 On Site 40,909 72,000 30,000 40,909 40,909
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 323,636 400,000 356,000 370,000 370,000 370,000 370,000 370,000 370,000 On Site 323,636 480,000 356,000 370,000 370,000
2.16 Bronjong Pabrikasi, 3 mm 16 Bh 385,455 470,000 On Site 385,455 564,000
2.17 Triplex Tebal 3mm 17 Lbr 109,091 132,000 120,000 120,000 120,000 143,000 143,000 65,000 65,000 On Site T = 9 MM 109,091 158,400 120,000 120,000 120,000
2.18 Pipa GIP 3" ( 6 m) 21 m 129,091 166,500 151,364 151,364 151,364 151,364 151,364 On Site 129,091 199,800 151,364 129,091 129,091
2.19 Pipa GIP 4" ( 6 m) m 227,273 320,000 318,182 318,182 318,182 318,182 318,182 On Site 227,273 384,000 318,182 318,182 318,182
2.20 Pipa Pvc 6'' (6 m) m 168,182 570,000 143,636 168,182 168,182 168,182 168,182 On Site 168,182 252,000 143,636 168,182 168,182
2.21 Pipa Pvc 2" ( 4 m) m 35,455 45,000 27,273 35,455 35,455 35,455 35,455 29,800 29,800 On Site 35,455 54,000 27,273 35,455 35,455
2.22 Pipa Pvc 4" ( 4 m) m 104,545 150,000 102,273 104,545 104,545 93,000 104,545 95,500 95,500 On Site 104,545 180,000 102,273 104,545 104,545
2.23 Pipa Pvc 3" ( 4 m) m 69,091 110,000 75,000 75,000 75,000 55,575 75,000 57,100 57,100 On Site 69,091 132,000 75,000 75,000 75,000
2.24 Pipa Pvc 3/4" ( 4 m) m 19,091 34,000 22,727 22,727 22,727 15,000 22,727 8,600 8,600 On Site 19,091 40,800 22,727 22,727 22,727
2.25 Pipa Pvc 3" ( 6 m) m 76,652 76,652 76,652 76,652 On Site SHB 2015 76,652 76,652
2.26 Pipa PVC 4" ( 6 m) m 115,262 115,262 115,262 115,262 On Site SHB 2015 115,262 115,262
III. A L A T.
3.1 Excavator 1 Jam 642,000 794,475 612,195 628,298 628,298 686,344 686,344 686,344 642,000 794,475 612,195 628,298 628,298
3.2 Dump Trcuk 5 Ton 2 Jam 347,750 423,720 329,696 364,181 364,181 366,503 366,503 366,503 347,750 423,720 329,696 364,181 364,181
3.3 Concrette Mixer 3 Jam 42,800 55,908 45,112 56,884 56,884 57,581 57,581 57,581 42,800 55,908 45,112 56,884 56,884
3.4 Pompa Sentrifugal 4 Jam 14,980 22,363 14,902 26,958 26,958 27,052 27,052 27,052 14,980 22,363 14,902 26,958 26,958
3.5 Stamper Jam 13,910 20,009 13,776 25,892 25,892 26,124 26,124 26,124 13,910 20,009 13,776 25,892 25,892
Harga Kabupaten/Kota.
No. Uraian
Kab. Banggai
Sat.
SHB 2019
CATATAN KET
HPS 2018 HPS 2019
1 2 3 37 38 39
I. UPAH
1.1 Pekerja 1 Hari 85,000 95,000 90,000 6,296
1.2 Tukang 2 Hari 120,000 110,000 100,000 8,800
1.3 Kepala Tukang 10 Hari 130,000 165,000 130,000 10,072
1.4 Mandor 3 Hari 152,820 165,000 130,000 11,320
1.5 Operator 4 Jam 89,100 89,100 6,600
1.6 Pembantu Operator 5 Jam 21,600 21,600 1,600
1.7 Sopir / Driver 6 Hari 108,000 108,000 8,000
1.8 Pembantu Sopir / Kernet 7 Hari 70,200 70,200 5,200
1.9 Juru Ukur 11 Hari 172,800 172,800 12,800
1.10 Pembantu Juru Ukur 12 Hari 70,200 70,200 5,200
II. BAHAN
2.1 Pasir Pasang 1 M3 160,000 348,300 160,000 On Site
2.2 Batu Kali 2 M3 285,000 348,300 285,000 On Site
2.3 Agregat Kasar/Kerikil Sungai 3 M3 265,936 348,300 250,000 On Site
2.4 Tanah Urug 4 M3 80,000 120,000 100,000 Quary
2.5 Semen / PC (50kg) 6 Zak 75,000 81,900 80,000 On Site
2.6 Besi Beton 7 Kg 15,000 12,150 12,150 On Site
2.7 Kawat Beton 8 Kg 25,850 25,000 25,000 On Site
2.8 Sirtu 10 M3 180,000 250,000 180,000 On Site
2.9 Paku 11 Kg 19,800 25,000 25,000 On Site
2.10 Kayu Daerah (Papan/Balok) 12 M3 1,555,000 On Site
2.11 Kayu Kelas II M3 2,250,000 On Site
2.12 Bensin 13 LITER 10,000 10,000 On Site
2.13 Solar 14 LITER 13,000 13,000 On Site
2.14 Minyak Pelumas / Olie 15 LITER 40,909 40,909 On Site
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 370,000 370,000 On Site
2.16 Bronjong Pabrikasi, 3 mm 16 Bh On Site
2.17 Triplex Tebal 3mm 17 Lbr On Site
2.18 Pipa GIP 3" ( 6 m) 21 m 129,091 129,091 On Site
2.19 Pipa GIP 4" ( 6 m) m 318,182 318,182 On Site
2.20 Pipa Pvc 6'' (6 m) m 168,182 168,182 On Site
2.21 Pipa Pvc 2" ( 4 m) m 35,455 35,455 On Site
2.22 Pipa Pvc 4" ( 4 m) m 104,545 104,545 On Site
2.23 Pipa Pvc 3" ( 4 m) m 75,000 75,000 On Site
2.24 Pipa Pvc 3/4" ( 4 m) m 22,727 22,727 On Site
2.25 Pipa Pvc 3" ( 6 m) m 76,652 76,652 On Site SHB 2015
2.26 Pipa PVC 4" ( 6 m) m 115,262 115,262 On Site SHB 2015
III. A L A T.
3.1 Excavator 1 Jam 686,344 686,344
I. UPAH
1.1 Pekerja 1 Hari 70,000 88,000 61,000 70,000 72,000 90,000 118,800 64,000 68,480 70,000 95,000 95,000
1.2 Tukang 2 Hari 100,000 137,500 65,000 100,000 105,000 132,000 178,200 90,000 99,000 100,000 110,000 110,000
1.3 Kepala Tukang 10 Hari 125,000 165,000 67,000 125,000 125,000 162,000 211,200 100,000 110,000 110,000 115,000 115,000
1.4 Mandor 3 Hari 150,000 192,500 68,750 150,000 150,000 192,000 244,200 110,000 121,000 121,000 125,000 125,000
1.5 Operator 4 Jam 35,000 55,000 82,500 82,500 82,500 60,000 99,000 82,500 90,750 90,750 115,000 110,000
1.6 Pembantu Operator 5 Jam 25,000 38,500 20,000 25,000 25,000 30,000 46,200 20,000 22,000 22,000 50,000 71,500
1.7 Sopir / Driver 6 Hari 125,000 192,500 100,000 125,000 125,000 150,000 231,000 100,000 110,000 110,000 110,000 176,000
1.8 Pembantu Sopir / Kernet 7 Hari 65,000 78,650 65,000 65,000 65,000 78,000 94,380 65,000 71,500 71,500 71,500 71,500
1.9 Juru Ukur 11 Hari 250,000 330,000 160,000 250,000 250,000 300,000 396,000 160,000 176,000 176,000 176,000 176,000
1.10 Pembantu Juru Ukur 12 Hari 70,000 88,000 65,000 70,000 70,000 90,000 118,800 65,000 71,500 71,500 71,500 71,500
II. BAHAN
2.1 Pasir Pasang 1 M3 98,182 145,000 90,000 90,000 100,000 On Site 155,036 226,594 92,114 92,114 100,000 146,000 146,000 150,000 142,500
2.2 Batu Kali 2 M3 136,364 185,000 115,300 136,364 150,000 On Site 250,318 456,482 305,932 305,932 305,932 262,000 320,000 280,340 266,323
2.3 Agregat Kasar/Kerikil Sungai 3 M3 136,364 185,000 127,000 136,364 136,364 On Site 159,091 285,000 268,418 268,418 268,418 545,200 268,418 299,156 284,198
2.4 Tanah Urug 4 M3 62,727 75,900 57,500 57,500 57,500 Quary 100,000 135,000 57,500 57,500 57,500 76,000 76,000 103,964 98,766
2.5 Semen / PC (50kg) 6 Zak 52,727 63,800 59,000 58,000 58,000 On Site 85,800 103,818 73,977 73,977 73,977 84,000 84,000 84,000 75,000
2.6 Besi Beton 7 Kg 15,000 24,000 13,135 15,000 15,000 On Site 15,000 24,000 12,290 15,000 15,000 17,720 17,720 12,923 12,277
2.7 Kawat Beton 8 Kg 18,182 24,200 20,000 22,000 22,000 On Site 20,000 24,200 19,568 19,568 19,568 17,720 19,568 20,880 19,836
2.8 Sirtu 10 M3 136,364 185,000 115,000 136,364 136,364 On Site 159,091 285,000 101,468 110,000 110,000 167,000 167,000 175,980 167,181
2.9 Paku 11 Kg 18,873 22,836 20,000 20,760 20,760 On Site 18,873 22,836 18,566 18,566 18,566 15,200 18,566 15,960 14,364
2.10 Kayu Daerah (Papan/Balok) 12 M3 1,454,545 2,000,000 1,450,000 1,454,545 1,454,545 On Site 2,050,909 2,481,600 1,902,409 1,902,409 1,902,409 1,500,000 1,902,409 -
2.11 Kayu Kelas II M3 2,272,727 3,000,000 2,272,727 2,272,727 On Site 2,272,727 3,000,000 2,272,727 2,272,727 2,100,000 2,272,727 2,730,000 2,730,000
2.12 Bensin 13 LITER 9,091 13,000 10,000 10,000 10,000 On Site 9,091 13,000 10,000 10,000 10,000 10,000 10,000 10,000 10,000
2.13 Solar 14 LITER 9,091 14,500 13,000 13,000 13,000 On Site 9,091 14,500 13,000 13,000 13,000 13,000 13,000 13,000 13,000
2.14 Minyak Pelumas / Olie 15 LITER 40,909 60,000 30,000 40,909 40,909 On Site 40,909 60,000 30,000 40,909 40,909 40,909 40,909 40,909 40,909
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 323,636 400,000 356,000 356,000 356,000 On Site 323,636 425,000 356,000 370,000 370,000 370,000 370,000 370,000 370,000
2.16 Bronjong Pabrikasi, 3 mm 16 Bh 385,455 470,000 - On Site 385,455 500,000
2.17 Triplex Tebal 3mm 17 Lbr 50,000 60,000 49,000 49,000 On Site 62,500 75,625 134,750 134,750 134,750 112,750 134,750 54,863 52,120
2.18 Pipa GIP 3" ( 6 m) 21 m 129,091 166,500 151,364 151,364 151,364 On Site 129,091 166,500 303,600 303,600 303,600 274,500 303,600 129,675 129,675
2.19 Pipa GIP 4" ( 6 m) m 227,273 320,000 318,182 318,182 318,182 On Site 227,273 320,000 318,182 318,182 318,182 178,400 318,182 186,795 177,455
2.20 Pipa Pvc 6'' (6 m) m 165,455 205,400 143,636 165,455 165,455 On Site 168,182 210,000 143,636 168,182 168,182 170,000 168,182 166,635 158,303
2.21 Pipa Pvc 2" ( 4 m) m 35,455 45,000 27,273 35,455 35,455 On Site 35,455 45,000 27,273 35,455 35,455 28,400 35,455 28,455 27,032
2.22 Pipa Pvc 4" ( 4 m) m 103,409 146,250 102,273 103,409 103,409 On Site 104,545 150,000 102,273 104,545 104,545 82,000 104,545 80,745 76,708
2.23 Pipa Pvc 3" ( 4 m) m 67,955 107,250 75,000 75,000 75,000 On Site 69,091 110,000 75,000 75,000 75,000 55,800 75,000 54,915 52,169
2.24 Pipa Pvc 3/4" ( 4 m) m 17,727 32,500 22,727 22,727 22,727 On Site 19,091 34,000 22,727 22,727 22,727 26,800 22,727 7,035 6,683
2.25 Pipa Pvc 3" ( 6 m) m 69,683 69,683 69,683 On Site 73,864 73,864 73,864 55,600 73,864 -
2.26 Pipa PVC 4" ( 6 m) m 104,783 104,783 104,783 On Site 111,070 111,070 111,070 87,900 111,070 166,635 158,303
III. A L A T.
3.1 Excavator 1 Jam 642,000 794,475 612,195 628,298 628,298 642,000 794,475 612,195 628,298 686,344 686,344
3.2 Dump Trcuk 5 Ton 2 Jam 347,750 423,720 329,696 364,181 364,181 347,750 423,720 329,696 364,181 366,503 366,503
3.3 Concrette Mixer 3 Jam 42,800 55,908 45,112 56,884 56,884 42,800 55,908 45,112 56,884 57,581 57,581
3.4 Pompa Sentrifugal 4 Jam 14,980 22,363 14,902 26,958 26,958 14,980 22,363 14,902 26,958 27,052 27,052
3.5 Stamper Jam 13,910 20,009 13,776 25,892 25,892 13,910 20,009 13,776 25,892 26,124 26,124
Harga Kabupaten/Kota.
No.
Kab. Toli-toli Uraian Sat.
CATATAN KET
1 2 3 56 57
I. UPAH
1.1 Pekerja 1 Hari 4,480 Hasil Rapat
1.2 Tukang 2 Hari 9,000 Hasil Rapat
1.3 Kepala Tukang 10 Hari 10,000 Hasil Rapat
1.4 Mandor 3 Hari 11,000 Hasil Rapat
1.5 Operator 4 Jam 8,250
1.6 Pembantu Operator 5 Jam 2,000
1.7 Sopir / Driver 6 Hari 10,000
1.8 Pembantu Sopir / Kernet 7 Hari 6,500
1.9 Juru Ukur 11 Hari 16,000
1.10 Pembantu Juru Ukur 12 Hari 6,500
II. BAHAN
2.1 Pasir Pasang 1 M3 On Site
2.2 Batu Kali 2 M3 On Site
2.3 Agregat Kasar/Kerikil Sungai 3 M3 On Site SPLIT
2.4 Tanah Urug 4 M3 Quary
2.5 Semen / PC (50kg) 6 Zak On Site
2.6 Besi Beton 7 Kg On Site HSIL RAPAT
2.7 Kawat Beton 8 Kg On Site
2.8 Sirtu 10 M3 On Site
2.9 Paku 11 Kg On Site
2.10 Kayu Daerah (Papan/Balok) 12 M3 On Site
2.11 Kayu Kelas II M3 On Site
2.12 Bensin 13 LITER On Site
2.13 Solar 14 LITER On Site
2.14 Minyak Pelumas / Olie 15 LITER On Site
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh On Site
2.16 Bronjong Pabrikasi, 3 mm 16 Bh On Site
2.17 Triplex Tebal 3mm 17 Lbr On Site T = 9 mm
2.18 Pipa GIP 3" ( 6 m) 21 m On Site
2.19 Pipa GIP 4" ( 6 m) m On Site
2.20 Pipa Pvc 6'' (6 m) m On Site
2.21 Pipa Pvc 2" ( 4 m) m On Site
2.22 Pipa Pvc 4" ( 4 m) m On Site
2.23 Pipa Pvc 3" ( 4 m) m On Site
2.24 Pipa Pvc 3/4" ( 4 m) m On Site
2.25 Pipa Pvc 3" ( 6 m) m On Site
2.26 Pipa PVC 4" ( 6 m) m On Site
III. A L A T.
3.1 Excavator 1 Jam
I. UPAH
1.1 Pekerja 1 Hari 90,000 118,800 77,000 84,700 84,700 80,000 84,700 100,000 85,000 7,700 90,000 125,000 70,500 70,500 70,500 90,000
1.2 Tukang 2 Hari 132,000 178,200 82,500 90,750 90,750 100,000 100,000 120,000 110,000 8,250 132,000 178,200 75,700 75,700 75,700 100,000
1.3 Kepala Tukang 10 Hari 162,000 211,200 99,000 108,900 108,900 150,000 108,900 150,000 135,000 9,900 162,000 211,200 99,000 99,000 99,000 120,000
1.4 Mandor 3 Hari 192,000 244,200 93,500 102,850 102,850 85,000 115,000 100,000 85,000 9,350 192,000 244,200 93,500 93,500 93,500 100,000
1.5 Operator 4 Jam 60,000 99,000 100,000 110,000 110,000 99,000 110,000 10,000 60,000 99,000 82,500 82,500 82,500
1.6 Pembantu Operator 5 Jam 30,000 46,200 50,000 55,000 55,000 46,200 46,200 5,000 30,000 46,200 20,000 20,000 20,000
1.7 Sopir / Driver 6 Hari 150,000 231,000 100,000 110,000 110,000 100,000 10,000 150,000 231,000 100,000 100,000 100,000
1.8 Pembantu Sopir / Kernet 7 Hari 78,000 94,380 50,000 55,000 55,000 65,000 5,000 78,000 94,380 65,000 65,000 65,000
1.9 Juru Ukur 11 Hari 300,000 396,000 100,000 110,000 110,000 160,000 10,000 300,000 396,000 160,000 160,000 160,000
1.10 Pembantu Juru Ukur 12 Hari 90,000 118,800 50,000 55,000 55,000 65,000 5,000 90,000 126,000 65,000 65,000 65,000
II. BAHAN
2.1 Pasir Pasang 1 M3 250,000 360,000 150,000 250,000 250,000 150,000 250,000 200,000 185,000 On Site 250,000 360,000 157,500 250,000 250,000 168,960
2.2 Batu Kali 2 M3 325,000 420,000 125,000 325,000 325,000 180,000 325,000 330,000 315,000 On Site 325,000 420,000 197,950 325,000 325,000 184,800
2.3 Agregat Kasar/Kerikil Sungai 3 M3 310,000 390,000 220,500 310,000 310,000 180,000 310,000 330,000 320,000 On Site 310,000 390,000 220,500 310,000 310,000 174,400
2.4 Tanah Urug 4 M3 110,000 720,000 100,000 100,000 100,000 80,000 100,000 80,000 80,000 Quary 110,000 162,000 100,000 110,000 110,000 79,200
2.5 Semen / PC (50kg) 6 Zak 80,000 162,000 85,000 85,000 85,000 85,000 85,000 109,000 106,000 On Site 80,000 120,000 90,000 95,000 95,000 79,200
2.6 Besi Beton 7 Kg 16,500 28,800 9,971 9,971 9,971 13,697 13,697 On Site 16,500 28,800 9,971 9,971 9,971
2.7 Kawat Beton 8 Kg 25,000 33,000 44,100 44,100 44,100 22,000 44,100 30,000 30,000 On Site 25,000 33,000 44,100 44,100 44,100 24,400
2.8 Sirtu 10 M3 310,000 390,000 129,150 129,150 129,150 136,000 130,000 200,000 200,000 On Site 310,000 390,000 129,150 129,150 129,150 168,960
2.9 Paku 11 Kg 20,000 26,400 29,400 29,400 29,400 20,000 29,400 30,000 30,000 On Site 20,000 31,000 29,400 29,400 29,400 22,000
2.10 Kayu Daerah (Papan/Balok) 12 M3 2,500,000 3,150,000 1,550,000 1,550,000 1,550,000 1,600,000 1,550,000 - On Site 2,500,000 3,150,000 1,911,000 1,911,000 1,911,000 1,698,000
2.11 Kayu Kelas II M3 2,700,000 3,600,000 2,700,000 2,700,000 2,700,000 2,700,000 On Site 2,700,000 3,600,000 2,700,000 2,700,000
2.12 Bensin 13 LITER 10,000 15,600 10,000 10,000 10,000 10,000 10,000 10,000 On Site 10,000 15,600 10,000 10,000 10,000
2.13 Solar 14 LITER 10,000 17,400 13,000 10,000 10,000 10,000 10,000 13,000 On Site 10,000 17,400 13,000 13,000 13,000
2.14 Minyak Pelumas / Olie 15 LITER 45,000 72,000 30,000 45,000 45,000 45,000 45,000 45,000 On Site 45,000 72,000 30,000 45,000 45,000
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 356,000 480,000 356,000 370,000 370,000 370,000 370,000 370,000 On Site 356,000 480,000 356,000 356,000 356,000
2.16 Bronjong Pabrikasi, 3 mm 16 Bh 424,000 564,000 - On Site 424,000 564,000
2.17 Triplex Tebal 3mm 17 Lbr 120,000 158,000 134,750 134,750 134,750 58,500 80,000 On Site 120,000 158,400 134,750 134,750 134,750
2.18 Pipa GIP 3" ( 6 m) 21 m 142,000 199,800 303,600 303,600 303,600 303,600 303,600 On Site 142,000 199,800 303,600 303,600 303,600
2.19 Pipa GIP 4" ( 6 m) m 250,000 384,000 318,182 318,182 318,182 318,182 318,182 On Site 250,000 384,000 318,182 318,182 318,182
2.20 Pipa Pvc 6'' (6 m) m 185,000 252,000 143,636 185,000 185,000 185,000 185,000 On Site 185,000 252,000 143,636 185,000 185,000
2.21 Pipa Pvc 2" ( 4 m) m 39,000 54,000 27,273 39,000 39,000 28,000 39,000 36,250 36,250 On Site 39,000 54,000 27,273 39,000 39,000 24,750
2.22 Pipa Pvc 4" ( 4 m) m 115,000 180,000 102,273 115,000 115,000 66,000 115,000 115,000 On Site 115,000 180,000 102,273 115,000 115,000 71,500
2.23 Pipa Pvc 3" ( 4 m) m 76,000 132,000 75,000 76,000 76,000 76,000 76,000 On Site 76,000 132,000 75,000 76,000 76,000
2.24 Pipa Pvc 3/4" ( 4 m) m 21,000 40,800 22,727 22,727 22,727 14,000 14,000 14,000 On Site 21,000 40,800 22,727 22,727 22,727 9,625
2.25 Pipa Pvc 3" ( 6 m) m 83,620 83,620 83,620 83,620 83,620 On Site SHB 2015 83,620 83,620 83,620 44,000
2.26 Pipa PVC 4" ( 6 m) m 125,740 125,740 125,740 125,740 125,740 On Site SHB 2015 125,740 125,740 125,740
III. A L A T.
3.1 Excavator 1 Jam 642,000 794,475 612,195 628,298 628,298 686,344 686,344 686,344 642,000 794,475 612,195 628,298 628,298
3.2 Dump Trcuk 5 Ton 2 Jam 347,750 423,720 329,696 364,181 364,181 366,503 366,503 366,503 347,750 423,720 329,696 364,181 364,181
3.3 Concrette Mixer 3 Jam 42,800 55,908 45,112 56,884 56,884 57,581 57,581 57,581 42,800 55,908 45,112 56,884 56,884
3.4 Pompa Sentrifugal 4 Jam 14,980 22,363 14,902 26,958 26,958 27,052 27,052 27,052 14,980 22,363 14,902 26,958 26,958
3.5 Stamper Jam 13,910 20,009 13,776 25,892 25,892 26,124 26,124 26,124 13,910 20,009 13,776 25,892 25,892
Harga Kabupaten/Kota.
No. Uraian
Kab. Morowali UtaraSat.
( Rp ) CATATAN KET
HPS 2018
1 2 3 73 74 75
I. UPAH
1.1 Pekerja 1 Hari 90,000
1.2 Tukang 2 Hari 100,000
1.3 Kepala Tukang 10 Hari 120,000
1.4 Mandor 3 Hari 100,000
1.5 Operator 4 Jam 82,500
1.6 Pembantu Operator 5 Jam 20,000
1.7 Sopir / Driver 6 Hari 100,000
1.8 Pembantu Sopir / Kernet 7 Hari 65,000
1.9 Juru Ukur 11 Hari 160,000
1.10 Pembantu Juru Ukur 12 Hari 65,000
II. BAHAN
2.1 Pasir Pasang 1 M3 168,960 On Site
2.2 Batu Kali 2 M3 325,000 On Site
2.3 Agregat Kasar/Kerikil Sungai 3 M3 310,000 On Site
2.4 Tanah Urug 4 M3 110,000 Quary
2.5 Semen / PC (50kg) 6 Zak 95,000 On Site
2.6 Besi Beton 7 Kg 15,000 On Site
2.7 Kawat Beton 8 Kg 44,100 On Site
2.8 Sirtu 10 M3 135,000 On Site
2.9 Paku 11 Kg 29,400 On Site
2.10 Kayu Daerah (Papan/Balok) 12 M3 1,911,000 On Site
2.11 Kayu Kelas II M3 On Site
2.12 Bensin 13 LITER 10,000 On Site
2.13 Solar 14 LITER 13,000 On Site
2.14 Minyak Pelumas / Olie 15 LITER 45,000 On Site
2.15 Bronjong Pabrikasi, 2.7 mm 16 Bh 356,000 On Site
2.16 Bronjong Pabrikasi, 3 mm 16 Bh On Site
2.17 Triplex Tebal 3mm 17 Lbr 134,750 On Site
2.18 Pipa GIP 3" ( 6 m) 21 m 303,600 On Site
2.19 Pipa GIP 4" ( 6 m) m 318,182 On Site
2.20 Pipa Pvc 6'' (6 m) m 185,000 On Site
2.21 Pipa Pvc 2" ( 4 m) m 39,000 On Site
2.22 Pipa Pvc 4" ( 4 m) m 115,000 On Site
2.23 Pipa Pvc 3" ( 4 m) m 76,000 On Site
2.24 Pipa Pvc 3/4" ( 4 m) m 22,727 On Site
2.25 Pipa Pvc 3" ( 6 m) m 83,620 On Site SHB 2015
2.26 Pipa PVC 4" ( 6 m) m 125,740 On Site SHB 2015
III. A L A T.
3.1 Excavator 1 Jam 686,344
I. UPAH
Pekerja 1.1 Pekerja 1 Hari 80,000 78,000 6,600
Tukang 1.2 Tukang 2 Hari 125,000 120,000 7,000
Kepala Tukang 1.3 Kepala Tukang 10 Hari 150,000 140,000 8,000
Mandor 1.4 M a n d o r 3 Hari 125,000 120,000 9,350
Operator 1.5 Operator 4 Jam 90,750 90,750 8,250
Pembantu Operator 1.6 Pembantu Operator 5 Jam 22,000 22,000 2,000
Sopir / Driver 1.7 Sopir / Driver 6 Hari 110,000 110,000 10,000
Pembantu Sopir / Kernet 1.8 Pembantu Sopir / Kernet 7 Hari 71,500 71,500 6,500
Juru Ukur 1.9 Juru Ukur 9 Hari 176,000 176,000 16,000
Pembantu Juru Ukur 1.10 Pembantu Juru Ukur 11 Hari 71,500 71,500 6,500
II. BAHAN
2.1 Pasir Pasang 1 M3 263,700 220,000 On Site
DILOKASI
2.2 Batu Kali / Batu Gunung 2 M3 250,000 250,000 On Site
2.3 Agregat Kasar/Kerikil Sungai 3 M3 305,200 305,200 On Site
2.4 Tanah Urug 4 M3 145,500 140,000 Quary
2.5 Semen / PC (50kg) 6 Zak 75,500 75,500 On Site
2.6 Besi Beton 7 Kg 13,800 13,800 On Site
2.7 Kawat Beton 8 Kg 27,100 27,100 On Site
2.8 S i r t u 10 M3 263,700 200,000 On Site
2.9 P a k u 11 Kg 32,200 32,200 On Site
2.10 Kayu Daerah (Papan/Balok) 12 M3 On Site
2.11 Kayu Kelas II M3 2,349,000 2,135,400 On Site
2.12 B e n s i n 13 LITER 10,000 On Site
2.13 S o l a r 14 LITER 13,000 On Site
2.14 Minyak Pelumas / Olie 15 LITER 40,909 On Site
2.15 Bronjong Pabrikasi, 2,7 mm 16 Bh 370,000 On Site
2.16 Bronjong Pabrikasi, 3 mm Bh On Site
2.17 Triplex Tebal 3mm 17 Lbr 59,600 On Site
2.18 Pipa GIP 3" ( 6 m) 21 m 151,364 On Site
2.19 Pipa GIP 4" ( 6 m) m 318,182 On Site
2.20 Pipa Pvc 6'' (6 m) m 168,182 On Site
2.21 Pipa Pvc 2" ( 4 m) m 27,675 27,675 On Site
2.22 Pipa Pvc 4" ( 4 m) m 90,225 90,225 On Site
2.23 Pipa Pvc 3" ( 4 m) m 54,450 54,450 On Site
2.24 Pipa Pvc 3/4" ( 4 m) m 9,175 9,175 On Site
2.25 Pipa Pvc 3" ( 6 m) m On Site
2.26 Pipa PVC 4" ( 6 m) m On Site
III. A L A T.
3.1 Excavator 1 Jam 686,344
Min Max HPS 2015 HPS 2016 HPS 2017 HPS 2018 Min Max HPS 2015 HPS 2016 HPS 2017 HPS 2018
1 2 3 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
I. UPAH
1.1 Pekerja 1 Hari 75,000 99,000 51,000 58,650 60,000 80,000 80,000 7,650 99,000 130,680 86,570 87,000
1.2 Tukang 2 Hari 110,000 148,500 70,500 81,075 85,000 85,000 85,000 10,575 145,200 196,020 121,000 121,000
1.3 Kepala Tukang 10 Hari 135,000 176,000 72,000 82,800 86,000 110,000 110,000 10,800 178,200 232,320 138,490 139,000
1.4 M a n d o r 3 Hari 160,000 203,500 73,000 83,950 86,500 95,000 95,000 10,950 211,200 268,620 155,650 156,000
1.5 Operator 4 Jam 50,000 82,500 82,500 94,875 95,000 95,000 12,375 66,000 108,900 90,750 91,000
1.6 Pembantu Operator 5 Jam 25,000 38,500 20,000 23,000 23,000 23,000 3,000 33,000 50,820 22,000 22,000
1.7 Sopir / Driver 6 Hari 125,000 192,500 100,000 115,000 115,000 115,000 15,000 165,000 254,100 110,000 110,000
1.8 Pembantu Sopir / Kernet 7 Hari 65,000 78,650 65,000 74,750 75,000 75,000 9,750 85,800 103,818 71,500 71,500
1.9 Juru Ukur 9 Hari 250,000 330,000 160,000 184,000 184,000 184,000 24,000 330,000 435,600 176,000 176,000
1.10 Pembantu Juru Ukur 11 Hari 75,000 99,000 65,000 74,750 75,000 75,000 9,750 99,000 130,680 71,500 71,500
II. BAHAN
2.1 Pasir Pasang 1 M3 227,273 360,000 134,500 134,500 134,500 185,000 185,000 On Site 250,000 396,000 200,000 200,000 On Site
2.2 Batu Kali / Batu Gunung 2 M3 295,455 420,000 157,000 160,000 160,000 147,000 160,000 On Site 325,000 462,000 325,000 325,000 On Site
2.3 Agregat Kasar/Kerikil Sungai 3 M3 281,818 390,000 186,200 186,200 186,200 203,000 203,000 On Site 310,000 429,000 310,000 310,000 On Site
2.4 Tanah Urug 4 M3 100,000 162,000 57,500 57,500 57,500 81,000 81,000 Quary 110,000 178,200 70,000 70,000 Quary
2.5 Semen / PC (50kg) 6 Zak 72,727 120,000 90,000 90,000 90,000 69,000 69,000 On Site 80,000 132,000 92,000 92,000 On Site
2.6 Besi Beton 7 Kg 15,000 28,800 15,000 15,000 15,000 15,000 On Site 16,500 31,680 16,500 16,500 On Site
2.7 Kawat Beton 8 Kg 22,727 33,000 31,900 31,900 31,900 34,000 34,000 On Site 25,000 36,300 26,000 26,000 On Site
2.8 S i r t u 10 M3 281,818 390,000 134,500 135,000 135,000 185,000 185,000 On Site 310,000 429,000 220,000 220,000 On Site
2.9 P a k u 11 Kg 18,182 26,400 15,000 18,182 18,500 26,000 26,000 On Site 20,000 29,040 30,000 30,000 On Site
2.10 Kayu Daerah (Papan/Balok) 12 M3 2,272,727 3,150,000 1,883,000 1,883,000 1,900,000 3,000,000 3,000,000 On Site 2,500,000 3,465,000 1,900,000 1,900,000 On Site
2.11 Kayu Kelas II M3 2,454,545 3,600,000 2,454,545 2,460,000 On Site 2,700,000 3,960,000 2,700,000 2,700,000 On Site
2.12 B e n s i n 13 LITER 9,091 15,600 10,000 10,000 10,000 10,000 On Site 10,000 17,160 10,000 10,000 On Site
2.13 S o l a r 14 LITER 9,091 17,400 13,000 13,000 13,000 13,000 On Site 10,000 19,140 13,000 13,000 On Site
2.14 Minyak Pelumas / Olie 15 LITER 40,909 72,000 30,000 40,909 40,909 40,909 On Site 45,000 79,200 45,000 45,000 On Site
2.15 Bronjong Pabrikasi, 2,7 mm 16 Bh 323,636 480,000 356,000 370,000 370,000 370,000 On Site 356,000 528,000 370,000 370,000 On Site
2.16 Bronjong Pabrikasi, 3 mm Bh 385,455 564,000 - On Site 424,000 620,400 On Site
2.17 Triplex Tebal 3mm 17 Lbr 109,091 158,400 67,245 67,245 67,245 56,000 67,245 On Site 120,000 174,240 120,000 120,000 On Site
2.18 Pipa GIP 3" ( 6 m) 21 m 129,091 199,800 151,364 151,364 151,364 151,364 On Site 142,000 219,780 151,364 151,364 On Site
2.19 Pipa GIP 4" ( 6 m) m 227,273 384,000 318,182 318,182 318,182 318,182 On Site 250,000 422,400 318,182 318,182 On Site
2.20 Pipa Pvc 6'' (6 m) m 168,182 252,000 143,636 168,182 168,182 168,182 On Site 185,000 277,200 185,000 185,000 On Site
2.21 Pipa Pvc 2" ( 4 m) m 35,455 54,000 27,273 35,455 35,455 81,250 81,250 On Site 39,000 59,400 39,000 39,000 On Site
2.22 Pipa Pvc 4" ( 4 m) m 104,545 180,000 102,273 104,545 104,545 159,000 159,000 On Site 115,000 198,000 115,000 115,000 On Site
2.23 Pipa Pvc 3" ( 4 m) m 69,091 132,000 75,000 75,000 75,000 118,000 118,000 On Site 76,000 145,200 76,000 76,000 On Site
2.24 Pipa Pvc 3/4" ( 4 m) m 19,091 40,800 22,727 22,727 22,727 45,500 45,500 On Site 21,000 44,880 21,000 21,000 On Site
2.25 Pipa Pvc 3" ( 6 m) m 81,948 90,142 81,948 81,948 81,948 On Site - 94,073 94,073 94,073 On Site -
2.26 Pipa PVC 4" ( 6 m) m 123,225 135,548 123,225 123,225 123,225 On Site - 141,458 141,458 141,458 On Site -
III. A L A T.
3.1 Excavator 1 Jam 642,000 794,475 612,195 628,298 628,298 686,344 642,000 794,475 612,195 628,298 628,298
3.2 Dump Trcuk 5 Ton 2 Jam 347,750 423,720 329,696 364,181 364,181 366,503 347,750 423,720 329,696 364,181 364,181
3.3 Concrette Mixer 3 Jam 42,800 55,908 45,112 56,884 56,884 57,581 42,800 55,908 45,112 56,884 56,884
3.4 Pompa Sentrifugal 4 Jam 14,980 22,363 14,902 26,958 26,958 27,052 14,980 22,363 14,902 26,958 26,958
3.5 Stamper Jam 13,910 20,009 13,776 25,892 25,892 26,124 13,910 20,009 13,776 25,892 25,892
ANALISIS BIAYA OPERASI ALAT BERAT UNTUK GALIAN TANAH, ANGKUTAN DUMP TRUCK DAN PEMADATAN
JENIS ALAT : Excavator, Dump Truck, Buldozer, Roller Vibro, Water Tanker,Concreate Mixer dan Vibrator Roller
SATUAN PEMBAYARAN : Rupiah/jam URAIAN ANALISA HARGA SATUAN
Biaya Pasti per Jam G = (E + F) G Rp/jam 276,868.44 55,373.69 103,825.67 2,076.51 1,038.26 69,217.11 2,353.38 245.72 1,799.64
2. Pelumas x x Mp
= (2.5%-3%) x Pw I Rp/jam 81,818.00 102,272.50 76,704.38 15,340.88 1,022.73 102,272.50 3,068.18 2,045.45 3,068.18 2.50%
x
3. Biaya bengkel = (6,25% - 8,75%) J Rp/jam 62,500.00 12,500.00 23,437.50 468.75 234.38 15,625.00 531.25 55.47 406.25 6.25%
4. Perawatan dan = (12,5%-17,5%) K Rp/jam 125,000.00 25,000.00 46,875.00 937.50 468.75 31,250.00 1,062.50 110.94 812.50 12.50%
perbaikan
5. Operator = (m orang/jam) x U1 M Rp/jam 11,785.71 11,785.71 11,785.71 11,785.71 11,785.71 11,785.71 11,785.71 11,785.71 11,785.71
6. Pembantu operator = (n orang/jam) x U2 L Rp/jam 3,571.43 3,571.43 3,571.43 3,571.43 3,571.43 3,571.43 3,571.43 3,571.43 3,571.43
Biaya Operasi (per Jam) = P Rp/jam 409,475.14 311,129.64 279,374.02 55,504.27 18,642.99 320,504.64 24,699.07 20,689.00 24,324.07
D. BIAYA OPERASI ALAT / JAM = (G + P) S Rp/jam 686,343.59 366,503.33 383,199.68 57,580.78 19,681.25 389,721.75 27,052.45 20,934.72 26,123.71
E. LAIN - LAIN
1. Bahan Bakar Premium (non subsidi) Mb Liter 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00
2. Bahan Bakar Solar (non subsidi) Ms Liter 13,000.00 13,000.00 13,000.00 13,000.00 13,000.00 13,000.00 13,000.00 13,000.00 13,000.00
3. Minyak Pelumas Mp Liter 40,909.00 40,909.00 40,909.00 40,909.00 40,909.00 40,909.00 40,909.00 40,909.00 40,909.00
4. Operator O Jam 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00 82,500.00
5. Pembantu Operator PO Jam 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00 25,000.00
Dina Dina Dina
DI. Tambayoli DI. Tambayoli DI. Toili DI. Moilong DI. Bella DI. Warulamala DI. Bunta DI. Dongin/Tolisu DI. Bakung DI. Dongin/Tolisu DI. Toili DI. Moilong DI. Bella DI. Warulamala DI. Bunta DI. Bakung DI. Gintu DI. Karongkasa DI. Saroso DI. Puna Kiri DI. Gintu DI. Karongkasa DI. Saroso DI. Puna Kiri DI. Ungkaya DI. Karaopa DI. Ungkaya DI. Karaopa
1 2 3
I. UPAH
1.1 Pekerja 1 Hari 100,000 90,000 90,000 100,000 100,000 90,000 80,000 90,000 100,000 100,000 95,000 95,000 95,000 95,000 90,000 80,000 90,000 95,000 70,000 80,000 80,000 100,000 98,000 70,000 80,000 80,000 98,000 135,000 135,000 90,000 90,000 90,000
1.2 Tukang 2 Hari 120,000 100,000 100,000 175,000 175,000 135,000 150,000 125,000 150,000 150,000 135,000 135,000 135,000 135,000 135,000 135,000 125,000 135,000 100,000 125,000 125,000 125,000 98,000 98,000 98,000 98,000 98,000 150,000 150,000 100,000 100,000 100,000
1.3 Kepala Tukang 10 Hari 120,000 120,000 120,000 200,000 200,000 150,000 175,000 150,000 175,000 175,000 165,000 165,000 165,000 165,000 150,000 165,000 150,000 165,000 125,000 150,000 150,000 150,000 126,000 125,000 126,000 126,000 126,000 250,000 250,000 120,000 120,000 120,000
1.4 M a n d o r 3 Hari 120,000 100,000 100,000 200,000 200,000 150,000 125,000 150,000 150,000 200,000 165,000 150,000 165,000 165,000 150,000 125,000 150,000 165,000 75,000 100,000 100,000 100,000 98,000 75,000 98,000 98,000 98,000 200,000 200,000 100,000 100,000 100,000
1.5 Operator Hari - -
1.6 Pembantu Operator Hari - -
1.7 Sopir / Driver 6 Hari - -
1.8 Pembantu Sopir / Kernet 7 Hari - -
1.9 Juru Ukur 9 Hari
1.10 Pembantu Juru Ukur 11 Hari
II. BAHAN
2.1 Semen 1 Zak 105,000 92,000 92,000 89,000 89,000 80,000 80,000 80,000 85,000 81,500 81,900 81,900 81,900 81,900 80,000 80,000 80,000 81,500 80,000 60,000 60,000 75,000 80,500 80,000 60,000 60,000 75,000 78,000 78,000 109,000 109,000 109,000
2.2 Batu Kali 2 M3 250,000 300,000 250,000 246,000 246,000 175,000 150,000 175,000 225,000 180,000 348,300 225,000 246,000 246,000 175,000 150,000 175,000 180,000 100,000 250,000 250,000 120,000 350,000 100,000 250,000 250,000 120,000 170,000 170,000 330,000 330,000 330,000
2.3 Pasir Pasang M3 150,000 300,000 150,000 164,000 164,000 150,000 150,000 150,000 200,000 125,000 348,300 200,000 164,000 164,000 150,000 150,000 150,000 125,000 75,000 200,000 200,000 115,000 138,000 75,000 138,000 138,000 115,000 125,000 125,000 200,000 200,000 200,000
2.4 Batu Pecah / Kerikil 3 M3 -
Batu Split Pecah Mesin 1/2 646,875 204,000 204,000 200,000 200,000 200,000 350,000 425,000 400,000 350,000 204,000 204,000 200,000 200,000 200,000 400,000 150,000 300,000 300,000 350,000 325,000 150,000 300,000 300,000 325,000 350,000 350,000 300,000 300,000 300,000
Batu Split Pecah Mesin 3/5 646,875 400,000
Manual
Pabrikasi
2.5 S i r t u 4 M3 150,000 316,800 145,000 145,000 125,000 150,000 125,000 125,000 125,000 348,300 125,000 145,000 145,000 125,000 150,000 125,000 125,000 75,000 200,000 200,000 115,000 223,500 75,000 200,000 200,000 115,000 72,000 72,000 330,000 330,000 330,000
2.6 Material Timbunan Biasa / Tanah 6 M3 105,600 100,000 120,000 -
2.7 Bronjong Pabrikasi 2,7 mm 7 Kg - - -
2.8 Besi Beton 8 Kg -
Besi Beton (U-24) 12,650 12,150 -
Besi Beton (U-39) 13,800 18,500 -
Besi Beton Ǿ 6 -
Besi Beton Ǿ 8 -
Besi Beton Ǿ 10 -
Besi Beton Ǿ 12 -
Besi Beton Ǿ 14 -
Besi Beton Ǿ 16 -
2.9 Kawat Beton 10 Kg 28,750 25,000 -
2.10 P a k u 11 Kg 23,000 25,000 -
2.11 Kayu Kelas IV 12 M3 1,575,000 1,500,000 -
2.12 Triplex Tebal 3 mm Lbr 69,000 56,000 -
2.13 Triplex Tebal 4 mm 13 Lbr 97,750 90,000 -
III. A L A T.
3.1 Excavator 1 Jam - -
DI. Wuno DI. Paneki DI. Kekeloe Wuno Paneki Kekeloe Wil. I Wil. II Wil. III Wil. Khusus DI. Sioyong DI. Malonas Sioyong Malonas DI. Dolago DI. Kasimbar DI. Malino DI. Maoti Di. Mepanga Hilir DI. Ongka Atas DI. Tada DI. Torue Zona A Zona B
Sausu Balinggi Torue Parigi Selatan Parigi Barat Parigi Parigi Tengah Parigi Utara
1 2 3 4
I. UPAH
1.1 Pekerja 1 Hari 100,000 85,000 129,000 90,000 70,000 90,000 90,000 90,000 90,000 85,000 80,000 100,000 80,000 100,000 100,000 100,000 80,000 80,000 100,000 95,000 95,000 95,000 95,000 95,000 95,000 95,000 95,000
1.2 Tukang 2 Hari 125,000 125,000 158,000 90,000 10,000 90,000 90,000 100,000 - 135,000 125,000 130,000 100,000 125,000 130,000 125,000 125,000 100,000 150,000 - - - - - - - -
1.3 Kepala Tukang 10 Hari 150,000 125,000 107,800 110,000 130,000 105,000 110,000 120,000 - 140,000 150,000 150,000 125,000 150,000 150,000 150,000 150,000 125,000 170,000 - - - - - - - -
1.4 M a n d o r 3 Hari 125,000 85,000 107,800 150,000 85,000 150,000 150,000 150,000 150,000 135,000 125,000 - 70,000 150,000 - 150,000 - 70,000 150,000 145,000 145,000 145,000 145,000 14,500 145,000 145,000 145,000
1.5 Operator Hari 200,000 - 86,200 150,000 - - 150,000 - - - 40,000 250,000 125,000 40,000 125,000 - 250,000 80,000 - - - - - - - -
1.6 Pembantu Operator Hari 75,000 - 80,000 75,000 - - 75,000 - - - 10,000 100,000 100,000 10,000 100,000 - 100,000 50,000 - - - - - - - -
1.7 Sopir / Driver 6 Hari 100,000 75,000 86,200 100,000 60,000 - 100,000 - - - 20,000 100,000 150,000 20,000 150,000 150,000 100,000 100,000 - - - - - - - -
1.8 Pembantu Sopir / Kernet 7 Hari 75,000 35,000 93,400 - 35,000 - - - - - 30,000 80,000 100,000 30,000 100,000 90,000 80,000 - - - - - - - - -
1.9 Juru Ukur 9 Hari -
1.10 Pembantu Juru Ukur 11 Hari -
II. BAHAN
2.1 Semen 1 Zak 78,800 58,000 62,000 73,600 73,600 71,300 73,600 79,900 345,000 70,000 75,500 65,000 67,000 70,000 65,000 70,000 65,000 67,000 65,000 72,000 72,000 72,000 72,000 72,000 72,000 72,000 72,000
2.2 Batu Kali 2 M3 223,500 550,000 400,000 167,000 167,000 - 167,000 200,000 - 430,000 718,800 130,000 300,000 200,000 130,000 200,000 210,000 300,000 200,000 385,000 349,000 241,000 276,000 267,000 257,000 154,000 131,000
2.3 Pasir Pasang M3 133,500 350,000 450,000 192,000 192,000 126,500 192,500 375,000 805,000 150,000 263,700 50,000 100,000 150,000 50,000 150,000 150,000 100,000 100,000 190,000 200,000 142,000 119,000 127,000 125,000 107,000 131,000
2.4 Batu Pecah / Kerikil 3 M3 346,300 325,000 650,000 178,250 178,250 275,000 450,000 500,000 600,000 - 305,200 200,000 125,000 180,000 200,000 180,000 275,000 125,000 553,000 553,000 539,000 538,000 529,000
Batu Split Pecah Mesin 1/2 - 609,000 585,000 573,000
Batu Split Pecah Mesin 3/5 - 574,000 557,000 545,000
Manual 125,000
Pabrikasi 498,000
2.5 S i r t u 4 M3 133,500 180,000 450,000 138,000 138,000 166,500 178,250 205,000 977,500 140,000 130,000 100,000 150,000 130,000 150,000 175,000 100,000 40,000 199,000 210,000 195,000 183,000 157,000 159,000 165,000 167,000
2.6 Material Timbunan Biasa / Tanah 6 M3 115,000 160,000 250,000 147,000 147,000 55,000 80,000 - - 140,000 145,500 50,000 100,000 120,000 50,000 120,000 125,000 100,000 40,000 130,000 117,000 90,000 87,000 142,000 - 81,000 100,000
2.7 Bronjong Pabrikasi 2,7 mm 7 Kg 409,500 50,000 30,000 30,000 - 365,000 - - - - 350,000 - - - - - - - -
2.8 Besi Beton 8 Kg 12,000 - 112,000 142,000 - - - - - - - - - - -
Besi Beton (U-24) -
Besi Beton (U-39) -
Besi Beton Ǿ 6 28,000 35,000 28,000 35,000 28,000
Besi Beton Ǿ 8 44,000 75,000 44,000 75,000 44,000
Besi Beton Ǿ 10 68,000 65,000 125,000 65,000 125,000 65,000
Besi Beton Ǿ 12 98,000 98,000 - 110,000 98,000 110,000 110,000 - 98,000
Besi Beton Ǿ 14
Besi Beton Ǿ 16
2.9 Kawat Beton 10 Kg 32,500 15,000 8,000 28,000 28,000 28,750 29,900 31,050 40,250 26,000 27,100 25,000 30,000 25,000 25,000 25,000 25,000 30,000 20,000 32,000 27,000 27,000 32,000 30,000 30,000 27,000 32,000
2.10 P a k u 11 Kg 23,100 15,000 6,000 26,450 26,450 24,150 26,450 27,025 33,925 20,000 32,200 25,000 25,000 18,000 25,000 18,000 20,000 25,000 20,000 32,000 22,000 22,000 25,000 24,000 24,000 22,000 31,000
2.11 Kayu Kelas IV 12 M3 1,841,600 1,750,000 1,600,000 - - - - - - 1,800,000 1,200,000 1,900,000 2,500,000 2,100,000 1,900,000 2,100,000 1,850,000 2,500,000 1,700,000 - - - - - - - -
2.12 Triplex Tebal 3 mm Lbr 62,900 52,000 60,000 70,150 70,150 64,400 70,150 75,900 179,000 49,000 59,600 48,000 55,000 52,000 48,000 52,000 57,000 55,000 50,000 54,000 54,000 54,000 54,000 54,000 54,000 53,000 53,000
2.13 Triplex Tebal 4 mm 13 Lbr 84,500 75,000 750,000 98,900 98,900 93,150 98,900 104,650 236,900 78,000 82,100 65,000 90,000 67,000 65,000 67,000 80,000 90,000 60,000 64,000 63,000 63,000 63,000 62,000 62,000 67,000 72,000
-
III. A L A T. -
3.1 Excavator 1 Jam - 540,179 - - - - - - - - - - - - -
3.9 Water Tank 1000 Ml 2 Bh 1,121,200 2,012,500 1,224,750 1,242,000 1,207,600 - - 1,550,000 1,550,000 1,550,000 1,550,000 1,450,000 1,450,000 1,450,000 1,450,000
3.10 Water Tank 500 Ml 3 Bh 1,722,500 1,650,000 2,041,250 2,070,000 2,012,500 - - 925,000 925,000 925,000 955,000 945,000 945,000 945,000 945,000
Zona C
Siniu Ampibabo Toribulu Kasimbar Dolago Maoti Tada Mepanga Hilir Malino Ongka
1 2 3
I. UPAH
1.1 Pekerja 1 Hari 95,000 95,000 95,000 95,000 95,000 95,000 95,000 95,000 95,000 95,000
1.2 Tukang 2 Hari - - - - - - - - - -
1.3 Kepala Tukang 10 Hari - - - - - - - - - -
1.4 M a n d o r 3 Hari 145,000 145,000 145,000 145,000 145,000 145,000 145,000 145,000 145,000 145,000
1.5 Operator Hari - - - -
1.6 Pembantu Operator Hari - - - -
1.7 Sopir / Driver 6 Hari - - - -
1.8 Pembantu Sopir / Kernet 7 Hari - - - -
1.9 Juru Ukur 9 Hari
1.10 Pembantu Juru Ukur 11 Hari
II. BAHAN
2.1 Semen 1 Zak 72,000 72,000 72,000 77,000 72,000 72,000 77,000 77,000 77,000 77,000
2.2 Batu Kali 2 M3 121,000 243,000 310,000 246,000 276,000 276,000 246,000 246,000 246,000 246,000
2.3 Pasir Pasang M3 76,000 138,000 216,000 136,000 119,000 119,000 136,000 136,000 136,000 136,000
2.4 Batu Pecah / Kerikil 3 M3 589,000 609,000 609,000 147,000 183,000 183,000 147,000 147,000 147,000 147,000
Batu Split Pecah Mesin 1/2
Batu Split Pecah Mesin 3/5
Manual
Pabrikasi
2.5 S i r t u 4 M3 112,000 138,000 162,000
2.6 Material Timbunan Biasa / Tanah 6 M3 64,000 135,000 92,000
2.7 Bronjong Pabrikasi 2,7 mm 7 Kg - - - -
2.8 Besi Beton 8 Kg - - - -
Besi Beton (U-24)
Besi Beton (U-39)
Besi Beton Ǿ 6
Besi Beton Ǿ 8
Besi Beton Ǿ 10
Besi Beton Ǿ 12
Besi Beton Ǿ 14
Besi Beton Ǿ 16
2.9 Kawat Beton 10 Kg 32,000 32,000 32,000 32,000 32,000 32,000 32,000 32,000 32,000 32,000
2.10 P a k u 11 Kg 22,000 22,000 37,000 37,000 25,000 25,000 37,000 37,000 37,000 37,000
2.11 Kayu Kelas IV 12 M3 - - - - - - - - - -
2.12 Triplex Tebal 3 mm Lbr 55,000 57,000 59,000 60,000 54,000 54,000 60,000 60,000 60,000 60,000
2.13 Triplex Tebal 4 mm 13 Lbr 72,000 73,000 74,000 75,000 63,000 63,000 75,000 75,000 75,000 75,000
III. A L A T.
3.1 Excavator 1 Jam - - - -
1 2 3
I. UPAH
1.1 Pekerja 1 Hari 80,000 80,000 98,000 98,000 90,000 100,000 90,000 100,000 90,000 115,000 96,000 95,000 70,000 70,000 70,000 - -
1.2 Tukang 2 Hari 120,000 125,000 98,000 98,000 100,000 120,000 100,000 135,000 135,000 150,000 157,000 135,000 85,000 85,000 85,000 - -
1.3 Kepala Tukang 10 Hari 150,000 150,000 126,000 126,000 120,000 130,000 120,000 150,000 150,000 175,000 170,000 165,000 100,000 100,000 100,000 - -
1.4 M a n d o r 3 Hari 100,000 125,000 98,000 98,000 100,000 110,000 100,000 135,000 135,000 150,000 - 165,000 100,000 100,000 100,000 - -
1.5 Operator Hari 150,000 200,000 - - - - - - - 250,000 170,000 - - - - - -
1.6 Pembantu Operator Hari 100,000 100,000 - - - - - - - 100,000 157,000 - - - - - -
1.7 Sopir / Driver 6 Hari 100,000 150,000 - - - - - - - 150,000 157,000 - - - - - -
1.8 Pembantu Sopir / Kernet 7 Hari 100,000 80,000 - - - - - - - 100,000 96,000 - - - - - -
1.9 Juru Ukur 9 Hari -
1.10 Pembantu Juru Ukur 11 Hari -
-
II. BAHAN -
2.1 Semen 1 Zak 70,000 70,000 79,000 80,500 85,000 85,000 109,000 109,000 92,000 85,000 80,000 85,000 80,000 89,000 81,900 75,000 80,000 84,000 84,000 99,000 84,000 81,500 84,000
2.2 Batu Kali 2 M3 125,000 250,000 270,000 350,000 - 330,000 330,000 300,000 150,000 150,000 150,000 150,000 246,000 348,300 200,000 500,000 200,000 280,340 348,600 280,340 301,740 280,340
2.3 Pasir Pasang M3 125,000 250,000 213,000 138,000 - 200,000 330,000 300,000 125,000 100,000 125,000 150,000 164,000 348,300 120,000 150,000 140,000 159,411 342,300 159,411 200,550 159,411
2.4 Batu Pecah / Kerikil 3 M3 350,000 300,000 - 375,000 - 200,000 204,000 400,000 500,000 450,000 299,156 350,569 299,156 599,025 572,460
Batu Split Pecah Mesin 1/2 273,000 325,000 - 300,000 450,000 646,875 400,000 -
Batu Split Pecah Mesin 3/5 248,000 276,000 - 300,000 450,000 646,875 400,000 -
Manual -
Pabrikasi -
2.5 S i r t u 4 M3 95,000 250,000 - 223,500 - 330,000 330,000 316,800 75,000 100,000 80,000 150,000 145,000 348,300 100,000 300,000 100,000 175,980 338,184 175,980 196,980 175,980
2.6 Material Timbunan Biasa / Tanah 6 M3 85,000 150,000 100,000 - - 80,000 80,000 105,600 85,000 75,000 85,000 100,000 123,000 120,000 70,000 350,000 76,000 103,964 130,700 103,964 139,550 103,964
2.7 Bronjong Pabrikasi 2,7 mm 7 Kg 30,000 300,000 - - - - - - 20,000 - 375,000 - - - 65,000 - - -
2.8 Besi Beton 8 Kg 12,500 20,000 - - 120,000 - - 12,750 12,923
Besi Beton (U-24) 14,100 14,500 - 13,697 13,697 12,650 12,150 -
Besi Beton (U-39) 18,200 18,700 - 13,646 13,648 13,800 18,500 -
Besi Beton Ǿ 6 37,000 37,000 30,000 30,000
Besi Beton Ǿ 8 60,000 60,000
Besi Beton Ǿ 10 93,000 93,000 68,000 91,000
Besi Beton Ǿ 12 134,000 134,000 97,000 142,000
Besi Beton Ǿ 14 151,000 151,000 140,000 190,000
Besi Beton Ǿ 16 207,000 207,000 185,000 255,000
2.9 Kawat Beton 10 Kg 30,000 25,000 31,000 35,000 28,000 28,000 30,000 30,000 28,750 20,000 - 30,000 30,000 25,000 20,000 - 23,000 20,880 22,083 20,880 21,413 20,880
2.10 P a k u 11 Kg 30,000 25,000 24,000 26,000 23,000 23,000 30,000 30,000 23,000 20,000 20,000 20,000 20,000 18,000 25,000 18,000 30,000 20,000 20,706 22,032 20,706 - -
2.11 Kayu Kelas IV 12 M3 2,000,000 1,500,000 1,700,000 1,560,000 - - 1,800,000 1,600,000 1,575,000 1,750,000 1,800,000 1,750,000 1,500,000 2,050,000 1,500,000 2,000,000 - - - - - - -
2.12 Triplex Tebal 3 mm Lbr 75,000 55,000 65,000 70,000 65,000 65,000 80,000 80,000 69,000 50,000 - 60,000 65,000 56,000 65,000 50,000 54,250 54,863 55,860 54,863 54,705 54,863
2.13 Triplex Tebal 4 mm 13 Lbr 90,000 80,000 80,500 95,000 84,000 84,000 90,000 90,000 97,750 77,000 - 80,000 95,000 90,000 85,000 80,000 - - - - - -
-
III. A L A T. -
3.1 Excavator 1 Jam - - - - - - - - - - -
3.9 Water Tank 1000 Ml 2 Bh 1,525,000 1,625,000 2,005,000 2,005,000 1,955,000 - 3,150,000 - - - -
3.10 Water Tank 500 Ml 3 Bh 1,325,000 1,425,000 850,000 850,000 1,150,000 - 1,900,000 - - 1,375,500 1,393,875
Dakopemean Toli-toli Utara Lampasio Ogodeide Basidondo Dondo Dampal Utara Dampal Selatan DI. Air Terang DI. Modo Air Terang Modo
1 2 3
I. UPAH
1.1 Pekerja 1 Hari - - - - - - - - 129,000 85,000 85,000
1.2 Tukang 2 Hari - - - - - - - - 158,000 100,000 100,000
1.3 Kepala Tukang 10 Hari - - - - - - - - 107,800 120,000 120,000
1.4 M a n d o r 3 Hari - - - - - - - - 107,800 110,000 110,000
1.5 Operator Hari - - - - - - - - 86,200 - -
1.6 Pembantu Operator Hari - - - - - - - - 80,000 - -
1.7 Sopir / Driver 6 Hari - - - - - - - - 86,200 - -
1.8 Pembantu Sopir / Kernet 7 Hari - - - - - - - - 93,400 - -
1.9 Juru Ukur 9 Hari
1.10 Pembantu Juru Ukur 11 Hari
II. BAHAN
2.1 Semen 1 Zak 89,000 99,000 94,000 109,000 97,000 99,000 89,000 82,505 80,000 85,000 85,000
2.2 Batu Kali 2 M3 416,850 574,350 521,850 710,850 380,100 348,600 423,675 301,350 275,000 275,000 275,000
2.3 Pasir Pasang M3 321,300 478,800 426,300 615,300 373,800 342,300 357,929 268,800 198,000 220,000 220,000
2.4 Batu Pecah / Kerikil 3 M3 719,775 1,013,775 719,775 824,775 877,275 903,525 1,285,710 1,489,710 170,000 176,000
Batu Split Pecah Mesin 1/2 515,000
Batu Split Pecah Mesin 3/5 475,000
Manual
Pabrikasi
2.5 S i r t u 4 M3 317,730 475,230 422,730 611,730 317,772 338,184 259,980 186,480 183,000 176,000
2.6 Material Timbunan Biasa / Tanah 6 M3 182,175 126,350 119,585 127,901 120,158 130,700 124,700 236,261 120,000 85,500 85,500
2.7 Bronjong Pabrikasi 2,7 mm 7 Kg - - - - - - - - 20,000 -
2.8 Besi Beton 8 Kg 13,158 15,198 13,413 14,331 14,178 14,688 14,249 14,249
Besi Beton (U-24) 12,500
Besi Beton (U-39) 24,600
Besi Beton Ǿ 6 31,000
Besi Beton Ǿ 8 52,000
Besi Beton Ǿ 10 80,000
Besi Beton Ǿ 12 11,000
Besi Beton Ǿ 14
Besi Beton Ǿ 16
2.9 Kawat Beton 10 Kg 21,042 21,247 21,192 17,952 18,615 22,083 22,491 22,236 25,000 27,500 27,500
2.10 P a k u 11 Kg - - - - - - - - 13,000 22,032 32,000
2.11 Kayu Kelas IV 12 M3 - - - - - - - - 1,500,000 1,718,750 1,718,750
2.12 Triplex Tebal 3 mm Lbr 55,650 56,175 55,388 55,440 5,808 55,860 55,913 55,965 55,000 50,000 50,000
2.13 Triplex Tebal 4 mm 13 Lbr - - - - - - - - 105,000 85,000 85,000
III. A L A T.
3.1 Excavator 1 Jam - - - - - - - - -
3.10 Water Tank 500 Ml 3 Bh 1,396,500 1,417,500 1,393,875 1,417,500 1,396,500 1,396,500 1,401,750 1,417,500 1,050,000