Anda di halaman 1dari 55

ENGINEERING ESTIMATE

KEGIATAN : PERENCANAAN PEMBANGUNAN GEDUNG KANTOR DINAS PEKERJAAN UMUM KOTA MAKASSAR
LOKASI : KOTA MAKASSAR
SUMBER DANA : APBN TAHUN 2011

No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah

LANTAI 1
I Lobby
1 Counter reception 70x220x110 1.00 unit Rp 2,541,000.00 2,541,000
Multiplek 18 mm lapis HPL, kaca 10mm, stainless steel hairlines -
2 Kursi reception ( dengan logo BNN di embossed ) 2.00 unit Rp 650,000.00 1,300,000
3 Back drop counter 9.30 m2 Rp 1,500,000.00 13,950,000
Multiplek 18 mm lapis HPL, kaca duco, stainless steel hairlines -
4 Logo BNN 1.00 unit Rp 36,050.00 36,050
Stainless stell hairlines+cutting stiker -
6 Sofa three seater 1.00 set Rp 17,500,000.00 17,500,000
Rangka kayu solid, busa density 32, artificial leather(oscar),kaki stainless stell -
7 Cofee table 50x900x45 1.00 unit Rp 1,500,000.00 1,500,000
Multiplek 18 mm lapis HPL+ kaca 8 mm+spacer stainless stell -
8 Meja sudut 45x45x45 2.00 unit Rp 250,000.00 500,000
Multiplek 18 mm lapis HPL+ kaca 8 mm+spacer stainless stell

Total I 37,327,050

II Ruang Eselon IVA & Staff


1 Meja kerja 70x140x75 (dengan plat stainless stell di gravire ) 2.00 unit Rp 1,617,000.00 3,234,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
2 meja samping 60x120x75 2.00 unit Rp 1,188,000.00 2,376,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
3 kursi kerja ( dengan logo BNN di embossed ) 2.00 unit Rp 1,100,000.00 2,200,000
4 Kursi hadap ( dengan logo BNN di embossed ) 4.00 unit Rp 650,000.00 2,600,000
5 Meja kerja 60x120x75 (dengan plat stainless stell di gravire ) 4.00 unit Rp 1,188,000.00 4,752,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
6 Kursi kerja ( dengan logo BNN di embossed ) 4.00 unit Rp 1,100,000.00 4,400,000
7 Panel Workstation 160x120 2.00 unit Rp 3,168,000.00 6,336,000
Frame aluminium powder coating, panel fabric 2 colour -
8 Credenza 40x200x75 (dengan plat stainless stell di gravire ) 2.00 unit Rp 1,600,000.00 3,200,000
Multiplek 18 mm lapis HPL+ handle stainless stell

total II 29,098,000

III Ruang Penjangkauan dan tim penyuluh


1 Meja rapat 150x300x75 2.00 unit Rp 7,425,000.00 14,850,000
multiplek lapis HPL, inlay stainless steel -
2 Kursi kerja ( dengan logo BNN di embossed ) 16.00 unit Rp 1,500,000.00 24,000,000

total III 38,850,000

IV R. Makan
1 Meja makan ø80x75 1.00 unit Rp 2,500,000.00 2,500,000
multiplek lapis HPL, support leg powder coating -
2 kursi makan 4.00 unit Rp 250,000.00 1,000,000

total IV 3,500,000

LANTAI 2

V Ruang Eselon IVA & Staff


1 Meja kerja 70x140x75 (dengan plat stainless stell di gravire ) 2.00 unit Rp 1,617,000.00 3,234,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
2 meja samping 60x120x75 2.00 unit Rp 1,188,000.00 2,376,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
3 kursi kerja ( dengan logo BNN di embossed ) 2.00 unit Rp 1,100,000.00 2,200,000
4 Kursi hadap ( dengan logo BNN di embossed ) 4.00 unit Rp 650,000.00 2,600,000
5 Meja kerja 60x120x75 (dengan plat stainless stell di gravire ) 4.00 unit Rp 1,188,000.00 4,752,000
Multiplek 18 mm lapis HPL+ handle stainless stell Rp - -
6 Kursi kerja ( dengan logo BNN di embossed ) 4.00 unit Rp 1,100,000.00 4,400,000
7 Panel Workstation 160x120 2.00 unit Rp 3,168,000.00 6,336,000
Frame aluminium powder coating, panel fabric 2 colour Rp - -
8 Credenza 40x200x75 (dengan plat stainless stell di gravire ) 2.00 unit Rp 1,600,000.00 3,200,000
Multiplek 18 mm lapis HPL+ handle stainless stell

total V 29,098,000
ENGINEERING ESTIMATE

KEGIATAN : PERENCANAAN PEMBANGUNAN GEDUNG KANTOR DINAS PEKERJAAN UMUM KOTA MAKASSAR
LOKASI : KOTA MAKASSAR
SUMBER DANA : APBN TAHUN 2011

No Uraian Pekerjaan Volume Satuan Harga Satuan Jumlah

VI Ruang Eselon IIIA -


1 Meja kerja 90x180x75 (dengan plat stainless stell di gravire ) 1.00 unit Rp 2,970,000.00 2,970,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
2 meja samping 60x120x75 1.00 unit Rp 1,188,000.00 1,188,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
3 kursi kerja ( dengan logo BNN di embossed ) 1.00 unit Rp 1,100,000.00 1,100,000
4 Kursi hadap ( dengan logo BNN di embossed ) 2.00 unit Rp 650,000.00 1,300,000
5 Sofa single seater 2.00 set Rp 7,500,000.00 15,000,000
Rangka kayu solid, busa density 32, artificial leather(oscar),kaki stainless stell -
6 Sofa three seater 1.00 set Rp 17,500,000.00 17,500,000
Rangka kayu solid, busa density 32, artificial leather(oscar),kaki stainless stell -
7 Cofee table 50x100x45 1.00 unit Rp 1,500,000.00 1,500,000
Multiplek 18 mm lapis HPL+ kaca 8 mm+spacer stainless stell -
8 Meja sudut 50x50x45 2.00 unit Rp 250,000.00 500,000
Multiplek 18 mm lapis HPL+ kaca 8 mm+spacer stainless stell -
9 Credenza 40x200x75 (dengan plat stainless stell di gravire ) 1.00 unit Rp 1,600,000.00 1,600,000
Multiplek 18 mm lapis HPL+ handle stainless stell -

total VI 42,658,000

VII Ruang Rapat


1 Meja rapat 120x350x75 1.00 unit Rp 6,125,000.00 6,125,000
multiplek lapis HPL, inlay stainless steel -
2 kursi rapat ( dengan logo BNN di embossed ) 10.00 unit Rp 650,000.00 6,500,000

Total VII 12,625,000

VIII R. Arsip
1 Meja kerja 60x120x75 (dengan plat stainless stell di gravire ) 2.00 unit Rp 1,044,000.00 2,088,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
2 Kursi kerja ( dengan logo BNN di embossed ) 2.00 unit Rp 650,000.00 1,300,000
3 Panel Workstation 160x120 1.00 unit Rp 1,728,000.00 1,728,000
Frame aluminium powder coating, panel fabric 2 colour -

total VIII 5,116,000


TOTAL PEKERJAAN FURNITURE 198,272,050
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
A.2.3.1. HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1 (Pek. Galian tanah 1 m3)


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (RP.)
A. TENAGA
Pekerja L.01 oh 0.750 Rp. 97,500.00 Rp. 73,125.00
Mandor L.04 oh 0.025 Rp. 120,000.00 Rp. 3,000.00

JUMLAH TENAGA KERJA 76,125.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah harga tenaga, bahan dan peralatan (A + B + C ) Rp. 76,125.00


E. Over Head & Profit (Maksimum 15%) 10% x D Rp. 7,612.50
F. Harga Satuan Pekerjaan ( D + E ) Rp. 83,737.50

A.2.3.1.9 (Pek. Urugan tanah bekas galian 1 m3)


Pengurungan kembali 1 m3 galian dihitung 1/3 kali dari koefisien pekerjaan galian
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (RP.)
A. TENAGA
Pekerja L.01 oh 0.500 Rp. 97,500.00 Rp. 48,750.00
Mandor L.04 oh 0.050 Rp. 120,000.00 Rp. 6,000.00

JUMLAH TENAGA KERJA 54,750.00

B. BAHAN

JUMLAH HARGA BAHAN -

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah harga tenaga, bahan dan peralatan (A + B + C ) Rp. 54,750.00


E. Over Head & Profit (Maksimum 15%) 10% x D Rp. 5,475.00
F. Harga Satuan Pekerjaan ( D + E ) Rp. 60,225.00
A.2.3.1.11 (Pek. Urugan pasir 1 m3)
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (RP.)
A. TENAGA
Pekerja L.01 oh 0.300 Rp. 97,500.00 Rp. 29,250.00
Mandor L.04 oh 0.010 Rp. 120,000.00 Rp. 1,200.00

JUMLAH TENAGA KERJA 30,450.00

B. BAHAN
Pasir Urug 1.200 Rp. 160,000.00 Rp. 192,000.00

JUMLAH HARGA BAHAN 192,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah harga tenaga, bahan dan peralatan (A + B + C ) Rp. 222,450.00


E. Over Head & Profit (Maksimum 15%) 10% x D Rp. 22,245.00
F. Harga Satuan Pekerjaan ( D + E ) Rp. 244,695.00

A.2.3.1.12 (Pek. Timbunan Pilihan 1 m3)


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (RP.)
A. TENAGA
Pekerja L.01 oh 0.300 Rp. 97,500.00 Rp. 29,250.00
Mandor L.04 oh 0.010 Rp. 120,000.00 Rp. 1,200.00

JUMLAH TENAGA KERJA 30,450.00

B. BAHAN
Tanah Timbunan 1.200 Rp. 115,000.00 Rp. 138,000.00

JUMLAH HARGA BAHAN 138,000.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah harga tenaga, bahan dan peralatan (A + B + C ) Rp. 168,450.00


E. Over Head & Profit (Maksimum 15%) 10% x D Rp. 16,845.00
F. Harga Satuan Pekerjaan ( D + E ) Rp. 185,295.00
A.3.2.1.9 (Pek. Pas. Batu kosong 1M3)
HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (RP.)
A. TENAGA
Pekerja L.01 oh 0.780 Rp. 97,500.00 Rp. 76,050.00
Tukang L.02 oh 0.390 Rp. 110,000.00 Rp. 42,900.00
Kepala Tukang L.03 oh 0.039 Rp. 125,000.00 Rp. 4,875.00
Mandor L.04 oh 0.039 Rp. 120,000.00 Rp. 4,680.00

JUMLAH TENAGA KERJA 128,505.00

B. BAHAN
Batu belah m³ 1.200 Rp. 172,000.00 Rp. 206,400.00
Pasir urug m³ 0.432 Rp. 160,000.00 Rp. 69,120.00

JUMLAH HARGA BAHAN 275,520.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah harga tenaga, bahan dan peralatan (A + B + C ) Rp. 404,025.00


E. Over Head & Profit (Maksimum 15%) 10% x D Rp. 40,402.50
F. Harga Satuan Pekerjaan ( D + E ) Rp. 444,427.50

A.3.2.1.2 (Pek. Pas. Batu Gunung 1M3 campuran 1 SP : 4 PP)


HARGA SATUAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN
(Rp.) (RP.)
A. TENAGA
Pekerja L.01 oh 1.500 Rp. 97,500.00 Rp. 146,250.00
Tukang L.02 oh 0.750 Rp. 110,000.00 Rp. 82,500.00
Kepala Tukang L.03 oh 0.075 Rp. 125,000.00 Rp. 9,375.00
Mandor L.04 oh 0.075 Rp. 120,000.00 Rp. 9,000.00

JUMLAH TENAGA KERJA 247,125.00

B. BAHAN
Batu belah m³ 1.200 Rp. 172,000.00 Rp. 206,400.00
Semen Portland kg 163.000 Rp. 1,320.00 215,160.00
Pasir Pasang m³ 0.520 Rp. 160,000.00 Rp. 83,200.00

JUMLAH HARGA BAHAN 504,760.00

C. PERALATAN

JUMLAH HARGA PERALATAN -

D. Jumlah harga tenaga, bahan dan peralatan (A + B + C ) Rp. 751,885.00


E. Over Head & Profit (Maksimum 15%) 10% x D Rp. 75,188.50
F. Harga Satuan Pekerjaan ( D + E ) Rp. 827,073.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BETON
Membuat 1 m3 Beton Mutu fc' = 7.4 MPa (K-100), Slump (12 ± 2) cm, w/c : 0.87
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN/UPAH JUMLAH HARGA
PC (1 zak = 50 kg) kg 247.000 Rp 1,320.00 Rp 326,040.00
Pasir Beton kg 869.000 Rp 114.29 Rp 99,314.29
A. Bahan
Kerikil (Maksimum 30 mm) kg 999.000 Rp 277.78 Rp 277,500.00
Air ltr 215.000 Rp 50.00 Rp 10,750.00
Jumlah Harga Bahan Rp 713,604.29
Pekerja Org/Hr 1.650 Rp 97,500.00 Rp 160,875.00
Tukang Batu Org/Hr 0.275 Rp 110,000.00 Rp 30,250.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.028 Rp 125,000.00 Rp 3,500.00
Mandor Org/Hr 0.083 Rp 120,000.00 Rp 9,960.00
Jumlah Harga Tenaga Kerja Rp 204,585.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 918,189.29
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 91,818.93
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 1,010,008.21

Membuat 1 m3 Beton Mutu fc' = 14.5 MPa (K-175), Slump (12 ± 2) cm, w/c : 0.66
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
PC (1 zak = 50 kg) kg 326.000 Rp 1,320.00 Rp 430,320.00
Pasir Beton kg 760.000 Rp 114.29 Rp 86,857.14
A. Bahan
Kerikil (Maksimum 30 mm) kg 1029.000 Rp 277.78 Rp 285,833.33
Air ltr 215.000 Rp 50.00 Rp 10,750.00
Jumlah Harga Bahan Rp 813,760.48
Pekerja Org/Hr 1.650 Rp 97,500.00 Rp 160,875.00
Tukang Batu Org/Hr 0.275 Rp 110,000.00 Rp 30,250.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.028 Rp 125,000.00 Rp 3,500.00
Mandor Org/Hr 0.083 Rp 120,000.00 Rp 9,960.00
Jumlah Harga Tenaga Kerja Rp 204,585.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 1,018,345.48
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 101,834.55
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 1,120,180.02
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BETON
Pembesian Per 1 kg Besi Polos
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Besi Beton Polos kg 1.050 Rp 13,000.00 Rp 13,650.00
A. Bahan
Kawat Beton kg 0.015 Rp 22,400.00 Rp 336.00
Jumlah Harga Bahan Rp 13,986.00
Pekerja Org/Hr 0.007 Rp 97,500.00 Rp 682.50
Tukang Besi Org/Hr 0.007 Rp 110,000.00 Rp 770.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.001 Rp 125,000.00 Rp 87.50
Mandor Org/Hr 0.000 Rp 120,000.00 Rp 48.00
Jumlah Harga Tenaga Kerja Rp 1,588.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 15,574.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 1,557.40
F. HARGA SATUAN PEKERJAAN PER- Kg ( D + E ) Rp 17,131.40

Memasang 1 m2 Begisting Untuk Sloof


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kayu Kelas III m3 0.045 Rp 1,950,000.00 Rp 87,750.00
A. Bahan Paku 5 - 12 cm kg 0.300 Rp 20,500.00 Rp 6,150.00
Minyak Begisting ltr 0.100 Rp 9,000.00 Rp 900.00
Jumlah Harga Bahan Rp 94,800.00
Pekerja Org/Hr 0.520 Rp 97,500.00 Rp 50,700.00
Tukang Kayu Org/Hr 0.260 Rp 110,000.00 Rp 28,600.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.026 Rp 125,000.00 Rp 3,250.00
Mandor Org/Hr 0.026 Rp 120,000.00 Rp 3,120.00
Jumlah Harga Tenaga Kerja Rp 85,670.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 180,470.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 18,047.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 198,517.00
2x Pakai Rp 99,258.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BETON
Memasang 1 m2 Begisting Untuk Kolom
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kayu Kelas III m3 0.040 Rp 1,950,000.00 Rp 78,000.00
Paku 5 - 12 cm kg 0.400 Rp 20,500.00 Rp 8,200.00
Minyak Begisting ltr 0.200 Rp 9,000.00 Rp 1,800.00
A. Bahan
Balok Kayu Kelas II m3 0.015 Rp 1,950,000.00 Rp 29,250.00
Plywood t = 9 mm lbr 0.350 Rp 148,000.00 Rp 51,800.00
Dolken Kayu Gelam dia. 8-10 cm/4 m btg 2.000 Rp 45,000.00 Rp 90,000.00
Jumlah Harga Bahan Rp 259,050.00
Pekerja Org/Hr 0.660 Rp 97,500.00 Rp 64,350.00
Tukang Kayu Org/Hr 0.330 Rp 110,000.00 Rp 36,300.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.033 Rp 125,000.00 Rp 4,125.00
Mandor Org/Hr 0.033 Rp 120,000.00 Rp 3,960.00
Jumlah Harga Tenaga Kerja Rp 108,735.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 367,785.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 36,778.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 404,563.50
2x Pakai Rp 202,281.75

Memasang 1 m2 Begisting Untuk Balok


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kayu Kelas III m3 0.040 Rp 1,950,000.00 Rp 78,000.00
Paku 5 - 12 cm kg 0.400 Rp 20,500.00 Rp 8,200.00
Minyak Begisting ltr 0.200 Rp 9,000.00 Rp 1,800.00
A. Bahan
Balok Kayu Kelas II m3 0.018 Rp 1,950,000.00 Rp 35,100.00
Plywood t = 9 mm lbr 0.350 Rp 148,000.00 Rp 51,800.00
Dolken Kayu Gelam dia. 8-10 cm/4 m btg 2.000 Rp 45,000.00 Rp 90,000.00
Jumlah Harga Bahan Rp 264,900.00
Pekerja Org/Hr 0.660 Rp 97,500.00 Rp 64,350.00
Tukang Kayu Org/Hr 0.330 Rp 110,000.00 Rp 36,300.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.033 Rp 125,000.00 Rp 4,125.00
Mandor Org/Hr 0.033 Rp 120,000.00 Rp 3,960.00
Jumlah Harga Tenaga Kerja Rp 108,735.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 373,635.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 37,363.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 410,998.50
2x Pakai Rp 205,499.25
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BETON
Memasang 1 m2 Bekisting Untuk Plat & DAK
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kayu Kelas III m3 0.040 Rp 1,950,000.00 Rp 78,000.00
Paku 5 - 12 cm kg 0.400 Rp 20,500.00 Rp 8,200.00
Minyak Begisting ltr 0.200 Rp 9,000.00 Rp 1,800.00
A. Bahan
Balok Kayu Kelas III m3 0.015 Rp 1,950,000.00 Rp 29,250.00
Plywood t = 9 mm lbr 0.350 Rp 148,000.00 Rp 51,800.00
Dolken Kayu Gelam dia. 8-10 cm/4 m btg 6.000 Rp 45,000.00 Rp 270,000.00
Jumlah Harga Bahan Rp 439,050.00
Pekerja Org/Hr 0.660 Rp 97,500.00 Rp 64,350.00
Tukang Kayu Org/Hr 0.330 Rp 110,000.00 Rp 36,300.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.033 Rp 125,000.00 Rp 4,125.00
Mandor Org/Hr 0.033 Rp 120,000.00 Rp 3,960.00
Jumlah Harga Tenaga Kerja Rp 108,735.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 547,785.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 54,778.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 602,563.50
2x Pakai Rp 301,281.75
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN DINDING PASANGAN

Memasang 1 m2 Dinding Bata Merah uk. 22 x 11 x 5 cm, 1/2 Bata, Campuran 1 Pc : 4 Pp


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN/UPAH JUMLAH HARGA
Bata Merah bh 70.0000 Rp 700.00 Rp 49,000.00
A. Bahan PC (1 zak = 50 kg) kg 11.5000 Rp 1,320.00 Rp 15,180.00
Pasir Pasang m3 0.0430 Rp 160,000.00 Rp 6,880.00
Jumlah Harga Bahan Rp 71,060.00
Pekerja Org/Hr 0.3000 Rp 97,500.00 Rp 29,250.00
Tukang Batu Org/Hr 0.1000 Rp 110,000.00 Rp 11,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0100 Rp 125,000.00 Rp 1,250.00
Mandor Org/Hr 0.0150 Rp 120,000.00 Rp 1,800.00
Jumlah Harga Tenaga Kerja Rp 43,300.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 114,360.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 11,436.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 125,796.00

Memasang 1 m2 Dinding Batu alam


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN/UPAH JUMLAH HARGA
Batu alam bh 1.10 Rp 220,000.00 Rp 242,000.00
A. Bahan PC (1 zak = 50 kg) kg 11.75 Rp 1,320.00 Rp 15,510.00
Pasir Pasang m3 0.035 Rp 160,000.00 Rp 5,600.00
Jumlah Harga Bahan Rp 263,110.00
Pekerja Org/Hr 0.7000 Rp 97,500.00 Rp 68,250.00
Tukang Batu Org/Hr 0.3500 Rp 110,000.00 Rp 38,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0350 Rp 125,000.00 Rp 4,375.00
Mandor Org/Hr 0.0350 Rp 120,000.00 Rp 4,200.00
Jumlah Harga Tenaga Kerja Rp 115,325.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 378,435.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 37,843.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 416,278.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN PLESTERAN
Memasang 1 m2 Plesteran Dinding 1 Pc : 3 Pp, Tebal 2 cm
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
PC (1 zak = 50 kg) kg 10.3680 Rp 1,320.00 Rp 13,685.76
A. Bahan
Pasir Pasang m3 0.0310 Rp 160,000.00 Rp 4,960.00
Jumlah Harga Bahan Rp 18,645.76
Pekerja Org/Hr 0.2600 Rp 97,500.00 Rp 25,350.00
Tukang Batu Org/Hr 0.2000 Rp 110,000.00 Rp 22,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0200 Rp 125,000.00 Rp 2,500.00
Mandor Org/Hr 0.0130 Rp 120,000.00 Rp 1,560.00
Jumlah Harga Tenaga Kerja Rp 51,410.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 70,055.76
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 7,005.58
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 77,061.34
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN KUDA-KUDA
Pekerjaan 1m2 Kuda-kuda Rangka Atap Baja Ringan
KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Main Truss C 75.75 m' 3.500 Rp 14,500.00 Rp 50,750.00
Roof Button/Reng R 32 - 0,45 m' 3.000 Rp 8,500.00 Rp 25,500.00
A.. Bahan Screw 6 x 20 Biji 20.000 Rp 500.00 Rp 10,000.00
Screw 4 x 16 Biji 8.000 Rp 450.00 Rp 3,600.00
Dynabolt 12-120 Biji 2.000 Rp 3,500.00 Rp 7,000.00
Jumlah Harga Bahan Rp 96,850.00
Pekerja Org/Hr 0.300 Rp 97,500.00 Rp 29,250.00
Tukang Kayu Org/Hr 0.300 Rp 110,000.00 Rp 33,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.030 Rp 125,000.00 Rp 3,750.00
Mandor Org/Hr 0.030 Rp 120,000.00 Rp 3,600.00
Jumlah Harga Tenaga Kerja Rp 69,600.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 166,450.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 16,645.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 183,095.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN ATAP

Memasang 1 m2 Atap Spandek Gelombang T. 0,35 mm


KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Spandek Warna T. 0,35 mm m2 1.0500 Rp 52,000.00 Rp 54,600.00
A.. Bahan
Paku sekrup kg 0.0200 Rp 38,700.00 Rp 774.00
Jumlah Harga Bahan Rp 55,374.00
Pekerja Org/Hr 0.120 Rp 97,500.00 Rp 11,700.00
Tukang Kayu Org/Hr 0.060 Rp 110,000.00 Rp 6,600.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.006 Rp 125,000.00 Rp 750.00
Mandor Org/Hr 0.006 Rp 120,000.00 Rp 720.00
Jumlah Harga Tenaga Kerja Rp 19,770.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 75,144.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 7,514.40
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 82,658.40

Memasang 1 m' nok atap spandek


KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Seng Plat BJLS 0,30 mm, L.50 cm m' 1.1000 Rp 19,500.00 Rp 21,450.00
A.. Bahan
Paku sekrup kg 0.0400 Rp 38,700.00 Rp 1,548.00
Jumlah Harga Bahan Rp 22,998.00
Pekerja Org/Hr 0.150 Rp 97,500.00 Rp 14,625.00
Tukang Kayu Org/Hr 0.070 Rp 110,000.00 Rp 7,700.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.007 Rp 125,000.00 Rp 875.00
Mandor Org/Hr 0.006 Rp 120,000.00 Rp 720.00
Jumlah Harga Tenaga Kerja Rp 23,920.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 46,918.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 4,691.80
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 51,609.80

Memasang 1 m' Listplank Kalsiplank L. 20 cm


KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kalsiplank m' 1.1000 Rp 27,000.00 Rp 29,700.00
A. Bahan
Paku / Sekrup kg 0.1700 Rp 38,700.00 Rp 6,579.00
Jumlah Harga Bahan Rp 36,279.00
Pekerja Org/Hr 0.1000 Rp 97,500.00 Rp 9,750.00
Tukang Kayu Org/Hr 0.0200 Rp 110,000.00 Rp 2,200.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0020 Rp 125,000.00 Rp 250.00
Mandor Org/Hr 0.0050 Rp 120,000.00 Rp 600.00
Jumlah Harga Tenaga Kerja Rp 12,800.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 49,079.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 4,907.90
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 53,986.90
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN PLAFOND

Memasang 1 m2 Plafond Kalsiboard t = 3,5 mm ukuran 120 x 240 cm


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kalsiboard 120 x 240 x 3,5 mm lbr 0.3640 Rp 75,000.00 Rp 27,300.00
A. Bahan Plester Roll 0.2500 Rp 15,000.00 Rp 3,750.00
Paku / Sekrup kg 0.1100 Rp 38,700.00 Rp 4,257.00
Jumlah Harga Bahan Rp 35,307.00
Pekerja Org/Hr 0.1000 Rp 97,500.00 Rp 9,750.00
Tukang Kayu Org/Hr 0.0500 Rp 110,000.00 Rp 5,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0050 Rp 125,000.00 Rp 625.00
Mandor Org/Hr 0.0050 Rp 120,000.00 Rp 600.00
Jumlah Harga Tenaga Kerja Rp 16,475.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 51,782.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 5,178.20
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 56,960.20

Memasang 1 m' List Profil Plafond Kayu 5 Cm


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
List Profil kayu m' 1.0500 Rp 4,250.00 Rp 4,462.50
A. Bahan
Paku kg 0.0100 Rp 39,000.00 Rp 390.00
Jumlah Harga Bahan Rp 4,852.50
Pekerja Org/Hr 0.0500 Rp 97,500.00 Rp 4,875.00
Tukang Kayu Org/Hr 0.0500 Rp 110,000.00 Rp 5,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0050 Rp 125,000.00 Rp 625.00
Mandor Org/Hr 0.0030 Rp 120,000.00 Rp 360.00
Jumlah Harga Tenaga Kerja Rp 11,360.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 16,212.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,621.25
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 17,833.75
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN KERAMIK

Memasang 1 m2 Lantai Keramik 40 x 40 (Halus)


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Keramik 40 x 40 halus Bh 6.6300 Rp 10,833.33 71,825.00
PC (1 zak = 50 kg) kg 9.8000 Rp 1,320.00 12,936.00
A. Bahan
Pasir Pasang m3 0.0450 Rp 160,000.00 7,200.00
Semen Warna kg 1.3000 Rp 20,500.00 26,650.00
Jumlah Harga Bahan 118,611.00
Pekerja Org/Hr 0.7000 Rp 97,500.00 68,250.00
Tukang Batu Org/Hr 0.3500 Rp 110,000.00 38,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0350 Rp 125,000.00 4,375.00
Mandor Org/Hr 0.0350 Rp 120,000.00 4,200.00
Jumlah Harga Tenaga Kerja 115,325.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 233,936.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 23,393.60
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 257,329.60

Memasang 1 m2 Lantai Keramik 40 x 40 (Kasar)

KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA

Keramik 40 x 40 kasar Bh 6.6300 Rp 13,166.67 87,295.00


PC (1 zak = 50 kg) kg 9.8000 Rp 1,320.00 12,936.00
A. Bahan
Pasir Pasang m3 0.0450 Rp 160,000.00 7,200.00
Semen Warna kg 1.3000 Rp 20,500.00 26,650.00
Jumlah Harga Bahan 134,081.00
Pekerja Org/Hr 0.7000 Rp 97,500.00 68,250.00
Tukang Batu Org/Hr 0.3500 Rp 110,000.00 38,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0350 Rp 125,000.00 4,375.00
Mandor Org/Hr 0.0350 Rp 120,000.00 4,200.00
Jumlah Harga Tenaga Kerja 115,325.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 249,406.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 24,940.60
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 274,346.60
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN KERAMIK
Memasang 1 m2 Lantai Keramik 30 x 30 (Kasar)
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Keramik 30 x 30 kasar bh 11.8700 Rp 6,545.45 77,694.55
PC (1 zak = 50 kg) kg 10.0000 Rp 1,320.00 13,200.00
A. Bahan
Pasir Pasang m3 0.0450 Rp 160,000.00 7,200.00
Semen Warna kg 1.5000 Rp 20,500.00 30,750.00
Jumlah Harga Bahan 128,844.55
Pekerja Org/Hr 0.7000 Rp 97,500.00 68,250.00
Tukang Batu Org/Hr 0.3500 Rp 110,000.00 38,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0350 Rp 125,000.00 4,375.00
Mandor Org/Hr 0.0350 Rp 120,000.00 4,200.00
Jumlah Harga Tenaga Kerja 115,325.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 244,169.55
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 24,416.95
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 268,586.50

Memasang 1 m2 Lantai Keramik 30 x 30 (Halus)


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Keramik 30 x 30 halus bh 11.8700 Rp 5,272.73 62,587.27
PC (1 zak = 50 kg) kg 10.0000 Rp 1,320.00 13,200.00
A. Bahan
Pasir Pasang m3 0.0450 Rp 160,000.00 7,200.00
Semen Warna kg 1.5000 Rp 20,500.00 30,750.00
Jumlah Harga Bahan 113,737.27
Pekerja Org/Hr 0.7000 Rp 97,500.00 68,250.00
Tukang Batu Org/Hr 0.3500 Rp 110,000.00 38,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0350 Rp 125,000.00 4,375.00
Mandor Org/Hr 0.0350 Rp 120,000.00 4,200.00
Jumlah Harga Tenaga Kerja 115,325.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 229,062.27
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 22,906.23
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 251,968.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN KERAMIK
Memasang 1 m2 Dinding Keramik 25 x 40
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Keramik 25 x 40 bh 10.0000 Rp 8,150.00 81,500.00
PC (1 zak = 50 kg) Kg 9.3000 Rp 1,320.00 12,276.00
A. Bahan
Pasir Pasang m3 0.0180 Rp 160,000.00 2,880.00
Semen Warna kg 1.9400 Rp 20,500.00 39,770.00
Jumlah Harga Bahan 136,426.00
Pekerja Org/Hr 0.9000 Rp 97,500.00 87,750.00
Tukang Batu Org/Hr 0.4500 Rp 110,000.00 49,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0450 Rp 125,000.00 5,625.00
Mandor Org/Hr 0.0450 Rp 120,000.00 5,400.00
Jumlah Harga Tenaga Kerja 148,275.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 284,701.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 28,470.10
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 313,171.10

Memasang 1 m2 Pas. Batu alam


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Batu alam bh 95.2400 Rp 2,309.95 220,000.00
A. Bahan PC (1 zak = 50 kg) Kg 9.0000 Rp 1,320.00 11,880.00
Pasir Pasang m3 0.0180 Rp 160,000.00 2,880.00
Jumlah Harga Bahan 234,760.00
Pekerja Org/Hr 0.9000 Rp 97,500.00 87,750.00
Tukang Batu Org/Hr 0.4500 Rp 110,000.00 49,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0450 Rp 125,000.00 5,625.00
Mandor Org/Hr 0.0450 Rp 120,000.00 5,400.00
Jumlah Harga Tenaga Kerja 148,275.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 383,035.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 38,303.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 421,338.50
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BESI & ALUMUNIUM

Memasang 1 m2 Pasangan Clading Allucopan


HARGA BAHAN /
KEBUTUHAN KODE SAT INDEKS JUMLAH HARGA
UPAH

Aluminium Composite Panel (Alucopan) M2 1.100 Rp 300,000.00 Rp 330,000.00


Sealant Corning Set 0.3000 Rp 120,000.00 Rp 36,000.00
Besi Siku 50.50.5 m¹ 1.0000 Rp 15,840.00 Rp 15,840.00
A. Bahan
Hollow Alumunium m¹ 2.1000 Rp 12,320.00 Rp 25,872.00
Bracket + Dinabolt Set 1.0000 Rp 15,000.00 Rp 15,000.00
Aksesoris & Alat Bantu % 0.0100 Rp 422,712.00 Rp 4,227.12
Jumlah Harga Bahan 426,939.12
Pekerja Org/Hr 0.4200 Rp 97,500.00 Rp 40,950.00
Tukang Kayu Org/Hr 0.8000 Rp 110,000.00 Rp 88,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.4000 Rp 125,000.00 Rp 50,000.00
Mandor Org/Hr 0.4000 Rp - Rp -
Jumlah Harga Tenaga Kerja 178,950.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 605,889.12
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10 % x D Rp 60,588.91
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 666,478.03
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BESI & ALUMUNIUM

Memasang 1 m2 Rangka Hollow 1 x 40/40 modul 60 x 60 cm Untuk Plafond


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Besi Hollow 40/40 Galvanish m' 4.0000 Rp 6,750.00 27,000.00
A. Bahan
Asesoris % 1.0000 Rp 6,750.00 6,750.00
Jumlah Harga Bahan 33,750.00
Pekerja Org/Hr 0.3500 Rp 97,500.00 34,125.00
Tukang Besi Org/Hr 0.3500 Rp 110,000.00 38,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0350 Rp 125,000.00 4,375.00
Mandor Org/Hr 0.0180 Rp 120,000.00 2,160.00
Jumlah Harga Tenaga Kerja 79,160.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 112,910.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 11,291.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 124,201.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN INSTALASI LISTRIK

Pekerjaan Pemasangan Jaringan Lampu


KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Kabel NYY 2 X 2,5 mm 12.000 m' Rp 5,665.00 Rp 67,980.00
Klem Kabel no.10 20.000 bh Rp 515.00 Rp 10,300.00
A. BAHAN Pipa pvc 5/8" 1.000 btg Rp 14,300.00 Rp 14,300.00
Isolasi 4.000 roll Rp 1,545.00 Rp 6,180.00
Tee dos 5/8" 1.000 bh Rp 2,060.00 Rp 2,060.00
JUMLAH HARGA SATUAN Rp 100,820.00
pekerja 0.500 org/hr Rp 97,500.00 Rp 48,750.00
B. TENAGA KERJA
Tukang Instalasi 0.500 org/hr Rp 110,000.00 Rp 55,000.00
JUM LAH HARGA TENAGA KERJA Rp 103,750.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 204,570.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 20,457.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 225,027.00

Pekerjaan Pasang Instalasi Stop Kontak


KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Kabel NYY 2 X 2,5 mm 12.000 m' Rp 5,665.00 Rp 67,980.00
Klem Kabel no.10 20.000 bh Rp 515.00 Rp 10,300.00
A. BAHAN Pipa pvc 5/8" 2.000 btg Rp 14,300.00 Rp 28,600.00
Isolasi 1.000 roll Rp 1,545.00 Rp 1,545.00
Tee dos 5/8" 1.000 bh Rp 2,060.00 Rp 2,060.00
JUMLAH HARGA SATUAN Rp 110,485.00
pekerja 0.500 org/hr Rp 97,500.00 Rp 48,750.00
B. TENAGA KERJA
Tukang Instalasi 0.500 org/hr Rp 110,000.00 Rp 55,000.00
JUM LAH HARGA TENAGA KERJA Rp 103,750.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 171,730.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 17,173.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 188,903.00
1 Bh Lampu LED Philips 20 Watt
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Lampu LED Philips 20 Watt 1.000 bh Rp 100,000.00 Rp 100,000.00
A. BAHAN

JUMLAH HARGA SATUAN Rp 100,000.00


B. UPAH KERJA Ongkos Pasang Lampu 0.350 bh Rp 100,000.00 Rp 35,000.00
JUM LAH HARGA TENAGA KERJA Rp 35,000.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 135,000.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 13,500.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 148,500.00

1 Bh Saklar Tunggal
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A.BAHAN Saklar tunggal 1.000 bh Rp 22,886.60 Rp 22,887.00
JUMLAH HARGA SATUAN Rp 22,887.00
B. UPAH KERJA Ongkos Pasang Saklar 0.350 bh Rp 22,886.60 Rp 8,010.00
JUM LAH HARGA TENAGA KERJA Rp 8,010.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 30,897.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 3,089.70
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 33,986.70

1 Bh Saklar Ganda
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A.BAHAN Saklar ganda 2 gang 1.000 bh Rp 34,113.60 Rp 34,114.00
JUMLAH HARGA SATUAN Rp 34,114.00
B. UPAH KERJA Ongkos Pasang Saklar 0.350 bh Rp 34,113.60 Rp 11,940.00
JUM LAH HARGA TENAGA KERJA Rp 11,940.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 46,054.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 4,605.40
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 50,659.40

1 Bh Stop Kontak
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A.BAHAN stop kontak 1 phase 1.000 bh Rp 28,551.60 Rp 28,552.00
JUMLAH HARGA SATUAN Rp 28,552.00
B. UPAH KERJA Ongkos Pasang Stop Kontak 1.000 bh Rp 5,000.00 Rp 5,000.00
JUM LAH HARGA TENAGA KERJA Rp 5,000.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 33,552.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 3,355.20
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 36,907.20
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN PLAMBING
Pipa PVC AW Diameter 1/2 " / m'
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Pipa PVC AW Dia 1/2 " 1.200 m' Rp 5,000.00 Rp 6,000.00
A. BAHAN
Perlengkapan dari harga pipa 35.000 % Rp 5,000.00 Rp 1,750.00
JUMLAH HARGA SATUAN Rp 7,750.00
Pekerja 0.036 Oh Rp 97,500.00 Rp 3,510.00
Tukang batu 0.060 Oh Rp 110,000.00 Rp 6,600.00
B. TENAGA KERJA
Kepala tukang 0.006 Oh Rp 125,000.00 Rp 750.00
Mandor 0.002 Oh Rp 120,000.00 Rp 216.00
JUM LAH HARGA TENAGA KERJA Rp 11,076.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 18,826.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,882.60
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 20,708.60

Pipa PVC AW Diameter 2" / m'


KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Pipa PVC Type AW dia 2" 1.200 m' Rp 22,000.00 Rp 26,400.00
A. BAHAN
Perlengkapan dari harga pipa 35.000 % Rp 22,000.00 Rp 7,700.00
JUMLAH HARGA SATUAN Rp 34,100.00
Pekerja 0.054 Oh Rp 97,500.00 Rp 5,265.00
Tukang batu 0.090 Oh Rp 110,000.00 Rp 9,900.00
B. TENAGA KERJA
Kepala tukang 0.009 Oh Rp 125,000.00 Rp 1,125.00
Mandor 0.003 Oh Rp 120,000.00 Rp 324.00
JUM LAH HARGA TENAGA KERJA Rp 16,614.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 50,714.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 5,071.40
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 55,785.40

Pipa PVC AW Diameter 3" / m'


KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Pipa PVC Type AW dia 3" 1.200 m' Rp 37,000.00 Rp 44,400.00
A. BAHAN
Perlengkapan dari harga pipa 35.000 % Rp 37,000.00 Rp 12,950.00
JUMLAH HARGA SATUAN Rp 57,350.00
Pekerja 0.081 Oh Rp 97,500.00 Rp 7,897.50
Tukang batu 0.135 Oh Rp 110,000.00 Rp 14,850.00
B. TENAGA KERJA
Kepala tukang 0.014 Oh Rp 125,000.00 Rp 1,687.50
Mandor 0.004 Oh Rp 120,000.00 Rp 492.00
JUM LAH HARGA TENAGA KERJA Rp 24,927.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 82,277.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 8,227.70
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 90,504.70
Memasang 1 buah kran ø 3/4" atau 1/2"
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Kran air stainless 1.0000 Bh Rp 75,000.00 Rp 75,000.00
A. BAHAN
Rol TBA 0.0250 % Rp 75,000.00 Rp 1,875.00
JUMLAH HARGA SATUAN Rp 76,875.00
Pekerja 0.010 Oh Rp 97,500.00 Rp 975.00
Tukang batu 0.100 Oh Rp 110,000.00 Rp 11,000.00
B. TENAGA KERJA
Kepala tukang 0.010 Oh Rp 125,000.00 Rp 1,250.00
Mandor 0.005 Oh Rp 120,000.00 Rp 600.00
JUM LAH HARGA TENAGA KERJA Rp 13,825.00
C. PERLATAN - - 0
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 90,700.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 9,070.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 99,770.00

Memasang 1 buah Floor Drain 3"


KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A. BAHAN Floor Drain 1.000 bh Rp 65,000.00 Rp 65,000.00
JUMLAH HARGA SATUAN Rp 65,000.00
B. UPAH KERJA Ongkos Pasang 1.000 ls Rp 5,000.00 Rp 5,000.00
JUM LAH HARGA TENAGA KERJA Rp 5,000.00
C. PERLATAN - - 0
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 70,000.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 7,000.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 77,000.00

Memasang 1 buah klosed Jongkok


KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Klosed Jongkok 1.0000 Bh Rp 388,000.00 Rp 388,000.00
PC (1 zak = 50 kg) 6.0000 Kg Rp 1,320.00 Rp 7,920.00
A. BAHAN Pasir Pasang 0.0100 M3 Rp 160,000.00 Rp 1,600.00
Bata Merah 7.0000 Bh Rp 700.00 Rp 4,900.00

JUMLAH HARGA SATUAN Rp 402,420.00


Pekerja 1.000 Oh Rp 97,500.00 Rp 97,500.00
Tukang batu 1.500 Oh Rp 110,000.00 Rp 165,000.00
B. TENAGA KERJA
Kepala tukang 0.150 Oh Rp 125,000.00 Rp 18,750.00
Mandor 0.005 Oh Rp 120,000.00 Rp 600.00
JUM LAH HARGA TENAGA KERJA Rp 281,850.00
C. PERLATAN - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 684,270.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 68,427.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 752,697.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN KACA DAN GANTUNGAN

Memasang 1 m2 Kaca Clear/Bening/Polos T.5 mm


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kaca Clear 5 mm m2 1.1000 Rp 168,000.00 Rp 184,800.00
A. Bahan
Sealent kg 0.0500 Rp 12,875.00 Rp 643.75
Jumlah Harga Bahan Rp 185,443.75
Pekerja Org/Hr 0.0150 Rp 97,500.00 Rp 1,462.50
Tukang Kayu Org/Hr 0.1500 Rp 110,000.00 Rp 16,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0150 Rp 125,000.00 Rp 1,875.00
Mandor Org/Hr 0.0008 Rp 120,000.00 Rp 96.00
Jumlah Harga Tenaga Kerja Rp 19,933.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 205,377.25
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 20,537.73
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 225,914.98

Memasang 1 Buah Engsel Pintu


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Engsel Pintu Buah 1.0000 Rp 8,500.00 Rp 8,500.00
A. Bahan

Jumlah Harga Bahan Rp 8,500.00


Pekerja Org/Hr 0.0150 Rp 97,500.00 Rp 1,462.50
Tukang Kayu Org/Hr 0.1500 Rp 110,000.00 Rp 16,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0150 Rp 125,000.00 Rp 1,875.00
Mandor Org/Hr 0.0008 Rp 120,000.00 Rp 96.00
Jumlah Harga Tenaga Kerja Rp 19,933.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 28,433.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 2,843.35
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 31,276.85

Memasang 1 Buah Engsel Jendela


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Engsel Jendela Buah 1.0000 Rp 6,250.00 Rp 6,250.00
A. Bahan

Jumlah Harga Bahan Rp 6,250.00


Pekerja Org/Hr 0.0100 Rp 97,500.00 Rp 975.00
Tukang Kayu Org/Hr 0.1000 Rp 110,000.00 Rp 11,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0100 Rp 125,000.00 Rp 1,250.00
Mandor Org/Hr 0.0005 Rp 120,000.00 Rp 60.00
Jumlah Harga Tenaga Kerja Rp 13,285.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 19,535.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,953.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 21,488.50
Memasang Kunci Pintu
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Kunci Pintu Bh 1.0000 Rp 140,000.00 Rp 140,000.00
A. Bahan

Jumlah Harga Bahan Rp 140,000.00


Pekerja Org/Hr 0.0100 Rp 97,500.00 Rp 975.00
Tukang Kayu Org/Hr 0.5000 Rp 110,000.00 Rp 55,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0500 Rp 125,000.00 Rp 6,250.00
Mandor Org/Hr 0.0050 Rp 120,000.00 Rp 600.00
Jumlah Harga Tenaga Kerja Rp 62,825.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 202,825.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 20,282.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 223,107.50

Memasang Grendel Pintu & Jendela


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Grendel Bh 1.0000 Rp 17,000.00 Rp 17,000.00
A. Bahan

Jumlah Harga Bahan Rp 17,000.00


Pekerja Org/Hr 0.0150 Rp 97,500.00 Rp 1,462.50
Tukang Kayu Org/Hr 0.1500 Rp 110,000.00 Rp 16,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0150 Rp 125,000.00 Rp 1,875.00
Mandor Org/Hr 0.0008 Rp 120,000.00 Rp 96.00
Jumlah Harga Tenaga Kerja Rp 19,933.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 36,933.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 3,693.35
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 40,626.85

Memasang 1 Buah Hak Angin


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
A. Bahan Hak Angin Buah 1.0000 Rp 7,500.00 Rp 7,500.00
Jumlah Harga Bahan Rp 7,500.00
Pekerja Org/Hr 0.0150 Rp 97,500.00 Rp 1,462.50
Tukang Kayu Org/Hr 0.1500 Rp 110,000.00 Rp 16,500.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.0150 Rp 125,000.00 Rp 1,875.00
Mandor Org/Hr 0.0080 Rp 120,000.00 Rp 960.00
Jumlah Harga Tenaga Kerja Rp 20,797.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 28,297.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 2,829.75
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 31,127.25
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN KAYU
Pekerjaan 1m3 Pemasangan Kusen Kayu Kls I
KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Balok kayu klas I m3 1.1000 Rp 10,354,000.00 Rp 11,389,400.00
A. Bahan Lem kg 1.0000 Rp 21,000.00 Rp 21,000.00
Paku biasa 7-10 cm kg 1.2500 Rp 20,500.00 Rp 25,625.00
Jumlah Harga Bahan Rp 11,436,025.00
Pekerja Org/Hr 7.000 Rp 97,500.00 Rp 682,500.00
Tukang Kayu Org/Hr 21.000 Rp 110,000.00 Rp 2,310,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 2.100 Rp 125,000.00 Rp 262,500.00
Mandor Org/Hr 0.350 Rp 120,000.00 Rp 42,000.00
Jumlah Harga Tenaga Kerja Rp 3,297,000.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 14,733,025.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,473,302.50
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 16,206,327.50

Pekerjaan 1m2 Daun Pintu Kayu klas II


KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Papan Kayu Kls II m3 0.0400 Rp 3,510,000.00 Rp 140,400.00
A.. Bahan Lem kg 0.5000 Rp 21,000.00 Rp 10,500.00

Jumlah Harga Bahan Rp 150,900.00


Pekerja Org/Hr 1.000 Rp 97,500.00 Rp 97,500.00
Tukang Kayu Org/Hr 3.000 Rp 110,000.00 Rp 330,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.300 Rp 125,000.00 Rp 37,500.00
Mandor Org/Hr 0.050 Rp 120,000.00 Rp 6,000.00
Jumlah Harga Tenaga Kerja Rp 471,000.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 621,900.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 62,190.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 684,090.00

Pekerjaan 1m2 Daun Jendela Kayu Kls II


KEBUTUHAN SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Papan Kayu Kls II m3 0.0240 Rp 3,510,000.00 Rp 84,240.00
A.. Bahan
Lem kg 0.3000 Rp 21,000.00 Rp 6,300.00
Jumlah Harga Bahan Rp 90,540.00
Pekerja Org/Hr 0.800 Rp 97,500.00 Rp 78,000.00
Tukang Kayu Org/Hr 2.400 Rp 110,000.00 Rp 264,000.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.240 Rp 125,000.00 Rp 30,000.00
Mandor Org/Hr 0.040 Rp 120,000.00 Rp 4,800.00
Jumlah Harga Tenaga Kerja Rp 376,800.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+C) Rp 467,340.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 46,734.00
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 514,074.00
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN PENGECATAN

Mengecat 1 m2 Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Indoor
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Plamir kg 0.1000 Rp 3,500.00 350.00
A.Bahan Cat Dasar kg 0.1000 Rp 16,810.00 1,681.00
Cat Penutup 2x kg 0.2600 Rp 27,500.00 7,150.00
Jumlah Harga Bahan 9,181.00
Pekerja Org/Hr 0.0200 Rp 97,500.00 1,950.00
Tukang Cat Org/Hr 0.0630 Rp 110,000.00 6,930.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0063 Rp 125,000.00 787.50
Mandor Org/Hr 0.0030 Rp 120,000.00 360.00
Jumlah Harga Tenaga Kerja 10,027.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 19,208.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,920.85
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 21,129.35

Mengecat 1 m2 Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Outdoor
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Plamir kg 0.1000 Rp 3,500.00
A.Bahan Cat Dasar kg 0.1000 Rp 16,810.00 1,681.00
Cat Wathershield kg 0.2600 Rp 50,000.00 13,000.00
Jumlah Harga Bahan 14,681.00
Pekerja Org/Hr 0.0200 Rp 97,500.00 1,950.00
Tukang Cat Org/Hr 0.0630 Rp 110,000.00 6,930.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0063 Rp 125,000.00 787.50
Mandor Org/Hr 0.0030 Rp 120,000.00 360.00
Jumlah Harga Tenaga Kerja 10,027.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 24,708.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 2,470.85
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 27,179.35
Mengecat 1 m2 Plafond Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Plamir kg 0.1000 Rp 3,500.00 350.00
Cat Dasar kg 0.1500 Rp 16,810.00 2,521.50
A.Bahan
Cat Penutup kg 0.1800 Rp 27,500.00 4,950.00
Jumlah Harga Bahan 7,821.50
Pekerja Org/Hr 0.0800 Rp 97,500.00 7,800.00
Tukang Cat Org/Hr 0.0600 Rp 110,000.00 6,600.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0063 Rp 125,000.00 787.50
Mandor Org/Hr 0.0040 Rp 120,000.00 480.00
Jumlah Harga Tenaga Kerja 15,667.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 23,489.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 2,348.90
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 25,837.90

Mengecat 1 m2 Kayu Baru (1 Lapis Cat Dasar, 2 Lapis Cat Penutup)


KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Cat meni kg 0.2000 Rp 25,000.00 5,000.00
Cat dasar kg 0.1700 Rp 24,200.00 4,114.00
Cat Penutup 2 kali kg 0.2600 Rp 60,000.00 15,600.00
A.Bahan
Kuas bh 0.0100 Rp 20,000.00 200.00
Pengencer kg 0.0300 Rp 16,800.00 504.00
Amplas lbr 0.2000 Rp 5,500.00 1,100.00
Jumlah Harga Bahan 26,518.00
Pekerja Org/Hr 0.0700 Rp 97,500.00 6,825.00
Tukang Cat Org/Hr 0.0090 Rp 110,000.00 990.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0060 Rp 125,000.00 750.00
Mandor Org/Hr 0.0030 Rp 120,000.00 360.00
Jumlah Harga Tenaga Kerja 8,925.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 35,443.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 3,544.30
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 38,987.30
RENCANA ANGGARAN BIAYA (RAB)

No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

I. PEKERJAAN PERSIAPAN Rp. 1,650,000.00


1. Pembersihan Lokasi 1.000 Ls Rp. 500,000.00 Rp. 500,000.00
2. Papan Pengenal Kegiatan 1.000 Ls Rp. 150,000.00 Rp. 150,000.00
3. Pengukuran dan Pemasangan Bouwplank 1.000 Ls Rp. 1,000,000.00 Rp. 1,000,000.00
SUB JUMLAH, I Rp. 1,650,000.00
II. PEKERJAAN RUAS. 01. Rp. 117,393,986.52
A. Pek Jalan Beton
1. Pasir Perata 13.500 m3 Rp. 244,695.00 Rp. 3,303,382.50
2. Bekisting/mall 45.000 m2 Rp. 99,258.50 Rp. 4,466,632.50
3. Beton K-175 74.250 m3 Rp. 1,120,180.02 Rp. 83,173,366.49
4. Gorong-Gorong d.40 / 1 m 4.000 m1 Rp. 195,000.00 Rp. 780,000.00
SUB JUMLAH, II.A Rp. 91,723,381.49
B. Pekerjaan Talud 01.
1. Galian Tanah 7.650 m3 83,737.50 Rp. 640,591.88
2. Pasir urug t.5 cm 0.600 m3 Rp. 244,695.00 Rp. 146,817.00
3. Pas. Batu gunung 1:4 14.550 m3 Rp. 827,073.50 Rp. 12,033,919.43
4. Plesteran 1:3 t.2 cm 39.900 m2 Rp. 77,061.34 Rp. 3,074,747.31
5. Timbunan Pilihan 1.875 m3 Rp. 185,295.00 Rp. 347,428.13
SUB JUMLAH, II.B Rp. 16,243,503.73
C. Pekerjaan Talud 02.
1. Galian Tanah 4.201 m3 Rp. 83,737.50 Rp. 351,787.94
2. Pasir urug t.5 cm 0.300 m3 Rp. 244,695.00 Rp. 73,408.50
3. Pas. Batu gunung 1:4 8.494 m3 Rp. 827,073.50 Rp. 7,024,955.54
4. Plesteran 1:3 t.2 cm 23.400 m3 Rp. 77,061.34 Rp. 1,803,235.26
5. Timbunan Pilihan 0.938 m2 Rp. 185,295.00 Rp. 173,714.06
SUB JUMLAH, II.C Rp. 9,427,101.30

III PEKERJAAN RUAS. 02. Rp. 25,952,049.21


A. Pek Jalan Beton
1. Pasir Perata 2.070 m3 Rp. 244,695.00 Rp. 506,518.65
2. Bekisting/mall 6.900 m2 Rp. 99,258.50 Rp. 684,883.65
3. Beton K-175 11.385 m3 Rp. 1,120,180.02 Rp. 12,753,249.53
SUB JUMLAH, II.A Rp. 13,944,651.83
B. PEKERJAAN TALUD
1. Galian Tanah 4.973 m3 Rp. 83,737.50 Rp. 416,384.72
2. Pasir urug t.5 cm 0.553 m3 Rp. 244,695.00 Rp. 135,193.99
3. Pas. Batu gunung 1:4 11.180 m3 Rp. 827,073.50 Rp. 9,246,681.73
4. Plesteran 1:3 t.2 cm 20.540 m2 Rp. 77,061.34 Rp. 1,582,839.84
5. Timbunan Pilihan 3.380 m3 Rp. 185,295.00 Rp. 626,297.10
SUB JUMLAH, II.B Rp. 12,007,397.38
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)

No. ITEM PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 1,650,000.00


II. PEKERJAAN RUAS. 01. Rp. 117,393,986.52
III. PEKERJAAN RUAS. 02. Rp. 25,952,049.21

JUMLAH REAL COST Rp. 144,996,035.72


PPN 10% Rp. 14,499,603.57
SUB TOTAL Rp. 159,495,639.30
DIBULATKAN Rp. 159,495,000.00
###
Terbilang:Seratus Limah Puluh Sembilan Juta Empat Ratus Sembilan Puluh Limah Rupiah
HARGA SATUAN DASAR (HSD) TENAGA KERJA

DAFTAR UPAH TENAGA KERJA

No. Jenis Pekerja Sat. Harga ( Rp )


1 Mandor Org/Hr Rp 120,000.00
2 Kepala Tukang Org/Hr Rp 125,000.00
3 Tukang Org/Hr Rp 110,000.00
4 Tukang Kayu Org/Hr Rp 110,000.00
5 Tukang Batu Org/Hr Rp 110,000.00
6 Tukang Cat Org/Hr Rp 110,000.00
7 Tukang Listrik Org/Hr Rp 110,000.00
8 Tukang Pipa Org/Hr Rp 110,000.00
9 Tukang Besi Org/Hr Rp 110,000.00
10 Pekerja Org/Hr Rp 97,500.00
HARGA SATUAN DASAR (HSD) BAHAN
###
DAFTAR HARGA BAHAN ###

NO. JENIS BAHAN SATUAN HARGA


1 Pasir Urug m3 Rp 160,000.00
2 Tanah Timbunan Pilihan m3 Rp 115,000.00
3 Pasir Pasang m3 Rp 160,000.00
4 Pasir Beton m3 Rp 160,000.00
5 Batu belah/gunung m3 Rp 172,000.00
6 Batu Pecah (chipping 1-2 Cm) m3 Rp 375,000.00
7 Sirtu Sungai m3 Rp 205,000.00
8 Sirtu Saring m3 Rp 160,000.00
9 Bata Merah bh Rp 700.00
10 Roster beton Bh Rp 25,000.00
11 PC (1 zak = 50 Kg) zak Rp 66,000.00
12 PC (1 zak = 40 Kg) zak Rp 55,000.00
13 Semen warna kg Rp 20,500.00
14 Besi Beton Polos kg Rp 13,000.00
15 Besi Beton Ulir kg Rp 13,300.00
16 Besi Siku
30.30.3 btg Rp 52,800.00
40.40.4 btg Rp 63,360.00
50.50.5 btg Rp 95,040.00
17 Bracket besi siku 70x70 @200mm kg Rp 15,000.00
18 Baja tralis kg Rp 20,394.00
19 Kawat las Listrik kg Rp 36,050.00
20 Kawat las Stainlest kg Rp 39,655.00
21 Hollow Galvanis 4/4 kg Rp 5,948.25
22 Besi strep 4/0,4 kg Rp 21,527.00
23 Kawat Beton kg Rp 22,400.00
24 Minyak Begisting ltr Rp 9,000.00
25 Cat Meni kg Rp 25,000.00
26 Cat Dasar kayu/besi kg Rp 24,200.00
27 Cat Dasar Tembok kg Rp 16,810.00
28 Cat tembok kg Rp 27,500.00
29 Cat Tipe Exterior kg Rp 50,000.00
30 Cat Plapond (metrolith) kg Rp 27,500.00
31 Cat Seng kg Rp 27,000.00
32 Cat Plitur/Vernis ltr Rp 56,650.00
33 Cat Kayu/besi kg Rp 60,000.00
34 Dempul kg Rp 22,500.00
35 Plamir tembok Interior ( Skim Coat A PLUS ) kg Rp 3,500.00
36 Waterproofing kg Rp 65,000.00
37 Kaca Clear/Bening t = 5 mm m2 Rp 168,000.00
38 Kaca Clear/Bening t = 8 mm Ukuran Non Standar m2 Rp 260,000.00
39 Kaca t = 8 mm Jenis Panasap Glass Warna Blue Green m2 Rp 586,500.00
40 Kaca Ryben t = 5 mm m2 Rp 190,000.00
41 Kaca Tempered 10 mm m2 Rp 470,000.00
42 Kaca Tempered 12 mm m2 Rp 529,000.00
43 Kayu Klas 1 ( Papan ) m3 Rp 13,260,000.00
44 Kayu Klas 1 ( Balok ) m3 Rp 10,354,000.00
45 Kayu Kelas II (Papan) m3 Rp 3,510,000.00
46 Kayu Kelas II (balok) m3 Rp 3,199,000.00
47 Kayu Kelas III ( Balok ) m3 Rp 1,950,000.00
48 Kayu Kelas III ( Papan ) m3 Rp 1,950,000.00
49 Kayu Kumia ( Balok ) m3 Rp 7,517,000.00
50 Kayu Kumia ( Papan ) m3 Rp 6,318,000.00
51 Dolken Kayu Gelam dia. 8 - 10 cm / 4 m btg Rp 45,000.00
52 Plin Multiplek 1.2 mm + HPL m' Rp 25,750.00
53 Lambrasering t=9mm m3 Rp 3,950,000.00
54 Tripleks 4mm lbr Rp 80,000.00
55 Multipleks t = 6 mm lbr Rp 116,000.00
HARGA SATUAN DASAR (HSD) BAHAN
###
DAFTAR HARGA BAHAN ###

NO. JENIS BAHAN SATUAN HARGA


56 Multipleks t = 9 mm lbr Rp 148,000.00
57 Gypsumboard 120 x 240 x 9 mm lbr Rp 77,000.00
HARGA SATUAN DASAR (HSD) BAHAN
###
DAFTAR HARGA BAHAN ###

NO. JENIS BAHAN SATUAN HARGA


58 Kalsibord 3,5 mm lbr Rp 78,000.00
59 HPL Urat Kayu lbr Rp 185,000.00
60 Lem Kayu kg Rp 21,000.00
61 List Gypsum m' Rp 66,500.00
62 List Profil kayu 5/5 m' Rp 4,250.00
63 Pintu Pabrikasi Type Groovy Bh Rp 1,200,000.00
64 Seng Gelombang BWG 31" -bjls 0,25 mm lbr Rp 67,500.00
65 Seng Plat 0,35 lbr Rp 56,000.00
66 Seng Plat BJLS 0,30 mm, Lebar 50 cm m' Rp 19,500.00
67 Atap Fiber transparan (Datar) lbr Rp 470,000.00
68 Atap Spandek Warna T. 0,35 mm m2 Rp 52,000.00
69 Atap Lengkung Trimdek T. 0,4 mm m2 Rp 121,000.00
70 Atap Genteng Metal Roof T. 0,25 mm setara Sakura Roof ) lbr Rp 39,000.00
71 Nok Genteng Metal Roof bh Rp 38,000.00
72 Karet Pelapis Atap m2 Rp 11,200.00
73 Paku Biasa kg Rp 20,500.00
74 Paku seng kg Rp 30,000.00
75 Paku atap spandek bj Rp 2,200.00
76 Paku 5 - 12 cm kg Rp 20,500.00
77 Paku Beton kg Rp 39,000.00
78 Paku / Sekrup kg Rp 38,700.00
79 plester Roll Rp 15,000.00
80 Hag Angin Pasang Rp 15,000.00
81 Sekrup Fixer bh Rp 500.00
82 Engsel pintu Pasang Rp 17,000.00
83 Engsel Jendela Pasang Rp 12,500.00
84 Engsel Jendela Casement 16" bh Rp 72,000.00
85 Grendel Pintu bh Rp 39,000.00
86 Grendel Jendela bh Rp 17,000.00
87 Kunci Pintu bh Rp 140,000.00
88 Rel Pintu Henderson J-3 untuk Pintu Lebar 750 mm - 900 mm Set Rp 380,000.00
89 Rel Pintu Henderson J-4 untuk Pintu Lebar 950 mm - 1.050 mm Set Rp 445,000.00
90 Rel Pintu Henderson J-5 untuk Pintu Lebar 1.050 mm - 1.200 mm Set Rp 490,000.00
91 Rel Pintu Henderson J-4 untuk Pintu Lebar 1.200 mm - 1.500 mm Set Rp 617,500.00
92 Ijuk kg Rp 56,650.00
93 Keramik 60 x 60 Granito Halus m2 Rp 160,000.00
94 Keramik 60 x 60 Granito Kasar m2 Rp 212,000.00
95 Keramik 40 x 40 Halus m2 Rp 65,000.00
96 Keramik 40 x 40 Kasar m2 Rp 79,000.00
97 Keramik 40 x 40 Motif Batu Alam m2 Rp 77,000.00
97 Keramik 30 x 30 Halus m2 Rp 58,000.00
98 Keramik 30 x 30 Kasar m2 Rp 72,000.00
99 Keramik 30 x 30 Motif Batu Alam m2 Rp 73,000.00
100 Keramik 25 x 40 warna m2 Rp 81,500.00
101 Step Nosing Bh Rp 20,000.00
102 Batu alam m2 Rp 220,000.00
103 Roster Keramik 25 x 25 cm bh Rp 41,200.00
104 Roster Beton 10 x 40 cm bh Rp 20,000.00
105 Roster Beton 15 x 70 cm bh Rp 35,000.00
106 Roster Beton 15 x 30 cm bh Rp 25,000.00
107 Bingkai Pintu / Jendela Aliminium (Profil Aluminium) 4" m' Rp 95,000.00
108 Aluminium Strip m' Rp 30,000.00
109 Karet Kusen m' Rp 5,000.00
110 Sealent tube Rp 12,875.00
111 Tarikan Pintu Aliminium bh Rp 36,000.00
112 Paving 21 x 10,5 x 8 cm K-300 m2 Rp 95,000.00
113 Kansteen K225 15x25x40 cm bh Rp 35,020.00
HARGA SATUAN DASAR (HSD) BAHAN
###
DAFTAR HARGA BAHAN ###

NO. JENIS BAHAN SATUAN HARGA


114 Plat Alumunium Untuk Pintu Tebal 2 mm m2 Rp 65,000.00
115 Plat Stainlist 2 mm Lembar Rp 1,600,000.00
116 Plat Stainlist 20 x 2 mm m' Rp 12,000.00
117 Plat Besi t = 1,5 mm m2 Rp 91,700.00
118 Plat Besi t = 5 mm kg Rp 12,360.00
119 Besi Strip kg Rp 12,360.00
120 Slot bh Rp 25,750.00
121 Kisi-Kisi Alumunium m' Rp 21,115.00
122 Besi Hollow 50/100 m' Rp 32,000.00
123 Besi Hollow 80/80 m' Rp 36,050.00
124 Besi Hollow 40 x 60 x 1,10 mm m' Rp 21,500.00
125 Besi Hollow 50 x 50 x 1,10 mm m' Rp 21,500.00
126 Besi Hollow 40 x 40 x 2 mm untuk partisi m' Rp 25,000.00
127 Besi Hollow 40 x 40 x 0,80 mm m' Rp 12,320.00
128 Besi Hollow 20 x 40 x 0,60 mm m' Rp 7,500.00
129 Besi Hollow 40 x 40 Galvanis u/Plafond m' Rp 6,750.00
130 Besi Hollow 20 x 40 Galvanis u/ Plafond m' Rp 5,625.00
131 Besi Profil Kg Rp 13,800.00
132 Handle Stainless bh Rp 275,000.00
133 Handle Pintu swing aluminium bh Rp 70,000.00
134 Kloset Duduk + Accesories lengkap bh Rp 2,150,000.00
135 Kloset Jongkok setara TOTO bh Rp 388,000.00
136 Door Closer bh Rp 128,750.00
137 Urinoir Toto U57 + Accesories Lengkap bh Rp 2,640,000.00
138 Wastafel Sekualitas Toto bh Rp 1,850,000.00
139 Cucipiring Stainlessteel bh Rp 350,000.00
140 Kran Air dia. 1/2" bh Rp 43,869.76
141 Kran Leher Angsa dia. 1/2" bh Rp 149,350.00
142 Kran Air Wastafel Stainlist Sekualitas Toto dia. 1/2" bh Rp 320,000.00
143 stop Kran 1/2 - 1" bh Rp 56,332.76
144 Floor Drain Stainles bh Rp 65,000.00
145 Roof Drain Stainles 4" bh Rp 200,000.00
146 Waterdrain bh Rp 180,000.00
147 Tangki Air Fiber 1,3 m3 + Accessories bh Rp 1,500,000.00
148 Kaca Cermin 5 mm m2 Rp 97,850.00
149 Cermin Hias Ukuran 60 x 200 Cm Bh Rp 350,000.00
150 Exhaust fan Celling 10" putih Bh Rp 313,000.00
151 Kalsiboard 1200 x 2400 x 3,5 mm lbr Rp 75,000.00
152 Kalsiplank L= 20 cm m' Rp 18,000.00
153 Kalsiplank L= 30 cm m' Rp 27,000.00
154 Kuas bh Rp 20,000.00
155 Amplas lbr Rp 5,500.00
156 Minyak Cat ltr Rp 16,800.00
157 Dempul kg Rp 15,500.00
158 Kawat ram 5 cm m2 Rp 77,250.00
159 Pengelasan listrik cm Rp 3,434.88
160 Main Truss C 75.75 m' Rp 14,500.00
161 Roof Button/Reng R 33 - 0,45 m' Rp 8,500.00
162 Screw 6 x 20 Biji Rp 500.00
163 Screw 4 x 16 Biji Rp 450.00
164 Joint Las cm Rp 1,030.00
165 Logo + Tulisan Sthenlish cm Rp 15,000.00
166 Baut dia. 6 mm bh Rp 15,000.00
167 Baut dia. 80 mm bh Rp 35,000.00
HARGA SATUAN DASAR (HSD) BAHAN
###
DAFTAR HARGA BAHAN ###

NO. JENIS BAHAN SATUAN HARGA


168 Baut Kaca dia. 20 mm bh Rp 56,650.00
169 Dyna Bolt dia. 12 - 120 bh Rp 3,500.00
170 Elektroda kg Rp 25,750.00
171 Aluminium Composite Panel (Alucopan) M2 Rp 300,000.00
172 Kawat las RB dia.2.6 kg Rp 3,000.00
173 Bracket + Dynabolt Set Rp 15,000.00
174 Mur+Baut M 10x70 Bh Rp 5,000.00
175 Sealent Corning set Rp 120,000.00
176 Sticker Sandblast M2 Rp 75,000.00
177 Membran 3 mm m2 Rp 17,000.00
178 Air ltr Rp 50.00
HARGA SATUAN DASAR (HSD) BAHAN

SATUAN /
NO JENIS BARANG / JASA HARGA SATUAN
UNIT

BAHAN KABEL
. Kabel NYM 2x2.5 mm m' Rp 5,665.00
. Kabel NYM 2x3.5 mm m' Rp 9,630.50
. Kabel NYY 2 x 1,5 mm Roll Rp 600,716.60
. Kabel NYY 2 x2,5 mm Roll Rp 812,587.60
. Kabel NYY 2 x 4 mm Roll Rp 340,126.60
. Kabel NYFGBY 4 x 10 mm m' Rp 79,310.00
. Kabel NYY 4 x 25 mm m' Rp 160,680.00
. Kabel NYFGBY 4 x 25 mm m' Rp 180,250.00
. Kawat BC 70 mm m' Rp 77,250.00
. Kawat BC 50 mm m' Rp 56,650.00
. Kawat BC 10 mm m' Rp 17,510.00
. Tray Kabel 300 x 100 mm lengkap dengan asesories m' Rp 360,500.00
. Tray Kabel 200 x 100 mm lengkap dengan asesories m' Rp 257,500.00

BAHAN PIPA ###


. Pipa Galvanis medium Ø 1/2" m' Rp 21,250.00
. Pipa Galvanis medium Ø 3/4" m' Rp 23,091.67
. Pipa Galvanis medium Ø 1" m' Rp 34,778.33
. Pipa Galvanis medium Ø 1 1/4 m' Rp 51,495.83
. Pipa Galvanis medium Ø 1 1/2" m' Rp 38,500.00
. Pipa Galvanis medium Ø 2" m' Rp 78,894.17
. Pipa Galvanis medium Ø 2 1/2" m' Rp 123,193.33
. Pipa Galvanis medium Ø 3" m' Rp 121,082.50
. Pipa PVC AW Dia 1/2 " m' Rp 5,000.00
. Pipa PVC AW Dia 3/4 " m' Rp 7,000.00
. Pipa PVC AW dia 1" m' Rp 11,000.00
. Pipa PVC AW dia 1 1/2" m' Rp 16,000.00
. Pipa PVC Type AW dia 2" m' Rp 22,000.00
. Pipa PVC Type AW dia 2 1/2" m' Rp 29,000.00
. Pipa PVC Type AW dia 3" m' Rp 37,000.00
. Pipa PVC Type AW dia 4" m' Rp 60,000.00
. Pipa pvc 5/8" btg Rp 14,300.00
. Pipa pvc 3/4" btg Rp 18,700.00
. Tongkat Tembaga + Pipa Gip dia. 1,5" Bh Rp 2,000,000.00
SATUAN /
NO JENIS BARANG / JASA HARGA SATUAN
UNIT
BAHAN LISTRIK
. RMI 2x20 bh Rp 294,580.00
. RMI 2x36 W bh Rp 351,230.00
. Master LED 4w-20w GU 5.3 12v bh Rp 190,000.00
. Downlight besar 23 W bh Rp 87,550.00
. Downlight Kecil 10 W bh Rp 72,100.00
. Lampu Sorot LED 50 Watt Unit Rp 750,000.00
. Lampu Baret + TL bulat 22 watt + batt bh Rp 489,250.00
. Lampu SL 9 watt philips bh Rp 57,783.00
. Lampu 18 watt philips bh Rp 38,000.00
. Lampu 23 watt philips bh Rp 44,000.00
. Lampu LED Philips 14 Watt bh Rp 45,000.00
. Lampu LED Philips 18 Watt bh Rp 70,000.00
. Lampu LED Philips 20 Watt bh Rp 100,000.00
. Lampu Downlight LED Philips 18 Watt bh Rp 155,000.00
. Lampu TL 1 x 20 Watt bh Rp 113,300.00
. Lampu TL 2 x 20 Watt setara philips bh Rp 236,900.00
. Stop Kontak 1 phase bh Rp 28,551.60
. Stop Kontak Khusus AC bh Rp 70,000.00
. Saklar Tunggal bh Rp 22,886.60
. Saklar Ganda 2 Gang bh Rp 34,113.60
. Pipa konduit high impact 20 mm ljr Rp 15,450.00
. Klem bh Rp 515.00
. Klem Besi bh Rp 1,545.00
. Inbow dos bh Rp 772.50
. Las dop bh Rp 772.50
. Isolasi bh Rp 1,545.00
. Tee dos 5/8" bh Rp 2,060.00
. Panel box lengkap bh Rp 550,000.00
. Lokal zakering case 2 group automatis Rp 85,201.60
. MCB bh Rp 100,000.00
. Arde/Pentanahan Titik Rp 600,000.00
SATUAN /
NO JENIS BARANG / JASA HARGA SATUAN
UNIT
BAHAN MEKANIKAL
. Floating Valve Ø 1 " (Katup Pelampung) bh Rp 180,250.00
. Header Ø 4" Ls Rp 159,650.00
. Clean Out dia 3" stainless bh Rp 33,990.00
. Clean Out dia 4" stainless bh Rp 46,350.00
. Stop Kran dia 3/4" bh Rp 39,140.00
. Stop Kran dia 1" bh Rp 53,869.00
. Stop Kran dia 1 1/4" bh Rp 77,250.00
. Stop Kran dia 1 1/2" bh Rp 77,250.00
. Stop Kran dia 2" bh Rp 128,750.00
. Stop Kran dia 2 1/2" bh Rp 133,900.00
. Rol TBA bh Rp 4,635.00
. Roof Drain Ø 3" bh Rp 36,050.00
. Roof Drain Ø 4" bh Rp 46,350.00
. Talang Air Segi Empat Batang Rp 55,000.00
. kran air Stainless bh Rp 75,000.00
RENCANA ANGGARAN BIAYA

PEKERJAAN : REHABILITASI PERUMAHAN DOKTER PKM CAKKURIDI


PEMILIK : DINAS KESEHATAN KAB. SOPPENG
TAHUN : 2018

No. URAIAN PEKERJAAN Volume HARGA SATUAN JUMLAH

I. PEKERJAAN PERSIAPAN JUMLAH Rp. 2,000,000.00


1. Pengukuran dan Pemasangan Bouwplank 1.000 Ls Rp. 500,000.00 Rp. 500,000.00
3. Papan Proyek 1.000 Ls Rp. 250,000.00 Rp. 250,000.00
4. Air kerja 1.000 Ls Rp. 500,000.00 Rp. 500,000.00
5. Listrik kerja 1.000 Ls Rp. 750,000.00 Rp. 750,000.00

II. PEKERJAAN RUMAH DOKTER (2 UNIT)


A. PEKERJAAN STRUKTUR JUMLAH Rp. 170,792,281.01
1. STRUKTUR PONDASI & SLOEF Rp. 66,078,485.24
1.1 1.1.1 Pondasi Batu Gunung Rp. 39,045,806.54
1.1.1.1 Galian tanah 49.386 m3 Rp. 83,737.50 Rp. 4,135,460.18
1.1.1.2 Urugan pasir bawah pondasi 5.484 m3 Rp. 244,695.00 Rp. 1,341,907.38
1.1.1.3 Pas. Batu kosong 16.452 m3 Rp. 444,427.50 Rp. 7,311,721.23
1.1.1.4 Pas. Batu kali campuran 1 : 4 30.848 m3 Rp. 827,073.50 Rp. 25,513,149.79
1.1.1.5 Urugan tanah bekas galian 12.347 m3 Rp. 60,225.00 Rp. 743,567.96

1.2 Sloef Rp. 16,779,578.70


1.2.1 Sloef ukuran 15/20
a Bekisting 18.280 m2 Rp. 99,258.50 Rp. 1,814,445.38
b Pembesian 604.611 Kg Rp. 17,131.40 Rp. 10,357,832.89
c Beton K. 175 4.113 m3 Rp. 1,120,180.02 Rp. 4,607,300.44

1.3 Urugan Rp. 10,253,100.00


1.4.1 Timbunan Pilihan dibawah lantai 41.600 m3 Rp. 185,295.00 Rp. 7,708,272.00
1.4.2 Pasir urug dibawah lantai, T. 5 Cm 10.400 m3 Rp. 244,695.00 Rp. 2,544,828.00

2 Struktur Kolom & Ringbalk SUB JUMLAH 2 Rp. 48,137,885.67


2.1 Kolom 26,463,826.11
2.1.1 Kolom ukuran 20/20, ###
a Bekisting 16.940 m2 Rp. 202,281.75 Rp. 3,426,652.85
b Pembesian 401.016 Kg Rp. 17,131.40 Rp. 6,869,965.50
c Beton K. 175 3.388 m3 Rp. 1,120,180.02 Rp. 3,795,169.92
2.1.1 Kolom Praktis ukuran 11/15, ###
a Bekisting 16.016 m2 Rp. 202,281.75 Rp. 3,239,744.51
b Pembesian 400.154 Kg Rp. 17,131.40 Rp. 6,855,191.38
c Beton K. 175 2.033 m3 Rp. 1,120,180.02 Rp. 2,277,101.95

2.2 Ringbalk & Kuda-Kuda Beton Rp. 19,293,746.48


2.2.1 Ringbalk Ukuran 11/15 ###
a Bekisting 16.643 m2 Rp. 205,499.25 Rp. 3,420,021.27
b Pembesian 687.180 Kg Rp. 17,131.40 Rp. 11,772,354.08
c Beton K. 175 3.661 m3 Rp. 1,120,180.02 Rp. 4,101,371.13

2.3 Dak Beton Rp. 2,380,313.08


2.3.1 Dak Beton, T 10 cm
a Bekisting 2.500 m2 Rp. 301,281.75 Rp. 753,204.38
b Pembesian 45.938 Kg Rp. 17,131.40 Rp. 786,973.69
c Beton K. 175 0.750 m3 Rp. 1,120,180.02 Rp. 840,135.02

3 Struktur Atap SUB JUMLAH 3 Rp. 56,575,910.10


3.1 Rangka Atap Baja Ringan 179.550 m2 Rp. 183,095.00 Rp. 32,874,707.25
3.2 Atap genteng Metal 179.550 m2 Rp. 90,190.00 Rp. 16,193,614.50
3.3 Karet Pelapis Atap 179.550 m2 Rp. 15,485.00 Rp. 2,780,331.75
3.4 Nok Genteng Metal 18.000 m1 Rp. 86,485.00 Rp. 1,556,730.00
3.5 List Plant Kalsiplank 65.400 m1 Rp. 48,479.00 Rp. 3,170,526.60

B. PEK. FINISHING ARSITEKTUR JUMLAH Rp. 297,292,123.78

1.1 Pekerjaan Lantai Rp. 46,952,257.85


1.1.1 Rabat beton sebagai lantai kerja T. 7 cm 8.475 m3 Rp. 1,010,008.21 Rp. 8,559,819.62
1.1.2 Lantai Keramik 60x60 Homogeneous (Setara Granit) 99.890 m2 Rp. 329,747.00 Rp. 32,938,427.83
1.1.3 Lantai Keramik 40 x 40 cm Kasar (Teras) 8.750 m2 Rp. 274,346.60 Rp. 2,400,532.75
1.1.4 Lantai Keramik 40 x 40 cm Kasar (KM/WC) 11.130 m2 Rp. 274,346.60 Rp. 3,053,477.66
No. URAIAN PEKERJAAN Volume HARGA SATUAN JUMLAH

1.2 Pekerjaan Dinding Rp. 150,437,537.09


1.2.1 Pas. Bata merah 1/2 batu camp. 1 : 3 (Transraam) 38.640 m2 Rp. 115,868.40 Rp. 4,477,154.98
1.2.2 Pas. Bata merah 1/2 batu camp. 1 : 4 466.560 m2 Rp. 125,796.00 Rp. 58,691,381.76
1.2.3 Plesteran camp. 1 : 3 (Transraam) 77.280 m2 Rp. 61,569.32 Rp. 4,758,077.05
1.2.4 Plesteran camp. 1 : 4 933.120 m2 Rp. 59,701.80 Rp. 55,708,943.62
1.2.5 Pas. Keramik Dinding 40 x 40 Cm Motif Batu Alam 17.090 m2 Rp. 280,146.00 Rp. 4,787,695.14
1.2.6 Pas. Keramik dinding KM/WC 25 x 40, T. 150 Cm 34.500 m2 Rp. 313,171.10 Rp. 10,804,402.95
1.2.7 Acian 311.040 m2 Rp. 36,040.00 Rp. 11,209,881.60

1.3 Pekerjaan Plafond Rp. 22,022,564.97


1.3.1 Rangka Hollow 127.770 m2 Rp. 124,201.00 Rp. 15,869,161.77
1.3.2 Plafond Gypsumboard 9 mm 127.770 m2 Rp. 48,160.00 Rp. 6,153,403.20

1.4 Pekerjaan Pintu lengkap kusen dan accesories Rp. 52,944,476.06


1.4.1 Type P1 8.000 bh Rp. 14,935,881.34
1.4.1.1 Pek. Kusen Pintu Kayu Kls I 0.031 m3 Rp. 16,206,327.50 Rp. 505,637.42
1.4.1.2 Pek. Daun Pintu Kayu Kls II 1.365 m2 Rp. 684,090.00 Rp. 933,782.85
1.4.1.3 Engsel Pintu 3.000 bh Rp. 31,276.85 Rp. 93,830.55
1.4.1.4 Grendel 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.1.5 Handle Pintu 1.000 psg Rp. 70,000.00 Rp. 70,000.00
1.4.1.6 Kunci Pintu 2 x putar Setara Yale 1.000 bh Rp. 223,107.50 Rp. 223,107.50
Rp. 1,866,985.17

1.4.2 Type PJ 1 2.000 bh Rp. 6,013,842.41


1.4.2.1 Pek. Kusen Pintu dan Jendela Kayu Kls I 0.051 m3 Rp. 16,206,327.50 Rp. 821,660.80
1.4.2.2 Pek. Daun Pintu Kayu Kls II 1.755 m2 Rp. 684,090.00 Rp. 1,200,577.95
1.4.2.3 Pek. Daun Jendela Kaca Kayu Kls II 0.800 m2 Rp. 514,074.00 Rp. 411,259.20
1.4.2.4 Engsel Pintu 3.000 bh Rp. 31,276.85 Rp. 93,830.55
1.4.2.5 Engsel Jendela 2.000 bh Rp. 21,488.50 Rp. 42,977.00
1.4.2.6 Grendel Pintu 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.2.7 Grendel Jendela 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.2.8 Haag Angin 2.000 bh Rp. 31,127.25 Rp. 62,254.50
1.4.2.9 Handle Pintu 1.000 psg Rp. 70,000.00 Rp. 70,000.00
1.4.2.10 Kunci Pintu 2 x putar Setara Yale 1.000 bh Rp. 223,107.50 Rp. 223,107.50
Rp. 3,006,921.20

1.4.3 Type PJ 2 2.000 bh Rp. 7,717,987.83


1.4.3.1 Pek. Kusen Pintu dan Jendela Kayu Kls I 0.069 m3 Rp. 16,206,327.50 Rp. 1,116,615.96
1.4.3.2 Pek. Daun Pintu Kayu Kls II 1.755 m2 Rp. 684,090.00 Rp. 1,200,577.95
1.4.3.3 Pek. Daun Jendela Kaca Kayu Kls II 1.600 m2 Rp. 514,074.00 Rp. 822,518.40
1.4.3.4 Engsel Pintu 3.000 bh Rp. 31,276.85 Rp. 93,830.55
1.4.3.5 Engsel Jendela 4.000 bh Rp. 21,488.50 Rp. 85,954.00
1.4.3.6 Grendel Pintu 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.3.7 Grendel Jendela 2.000 bh Rp. 40,626.85 Rp. 81,253.70
1.4.3.8 Haag Angin 4.000 bh Rp. 31,127.25 Rp. 124,509.00
1.4.3.9 Handle Pintu 1.000 psg Rp. 70,000.00 Rp. 70,000.00
1.4.3.10 Kunci Pintu 2 x putar Setara Yale 1.000 bh Rp. 223,107.50 Rp. 223,107.50
Rp. 3,858,993.91

1.4.4 Type P2 (KM/WC) 4.000 bh Rp. 4,417,580.48


1.4.4.1 Pintu Aluminium 1.000 bh Rp. 854,754.73 Rp. 854,754.73
1.4.4.2 Kaca Mati 5 mm 0.200 m2 Rp. 225,914.98 Rp. 45,183.00
1.4.4.3 Engsel Pintu 3.000 bh Rp. 31,276.85 Rp. 93,830.55
1.4.4.4 Grendel Buncis 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.4.5 Handle Pintu 1.000 psg Rp. 70,000.00 Rp. 70,000.00
Rp. 1,104,395.12

1.4.5 Type J1 4.000 bh Rp. 6,152,917.51


1.4.5.1 Pek. Kusen Jendela Kayu Kls I 0.038 m3 Rp. 16,206,327.50 Rp. 610,978.55
1.4.5.2 Pek. Daun Jendela Kaca Kayu Kls I 1.520 m2 Rp. 514,074.00 Rp. 781,392.48
1.4.5.3 Engsel Jendela 2.000 bh Rp. 21,488.50 Rp. 42,977.00
1.4.5.4 Grendel 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.5.5 Haag Angin 2.000 bh Rp. 31,127.25 Rp. 62,254.50
Rp. 1,538,229.38

1.4.6 Type J2 6.000 bh Rp. 10,288,077.20


1.4.6.1 Pek. Kusen Jendela Kayu Kls I 0.037 m3 Rp. 16,206,327.50 Rp. 600,444.43
1.4.6.2 Pek. Daun Jendela Kaca Kayu Kls I 1.600 m2 Rp. 514,074.00 Rp. 822,518.40
1.4.6.3 Engsel Jendela 4.000 bh Rp. 21,488.50 Rp. 85,954.00
1.4.6.4 Grendel 2.000 bh Rp. 40,626.85 Rp. 81,253.70
1.4.6.5 Haag Angin 4.000 bh Rp. 31,127.25 Rp. 124,509.00
Rp. 1,714,679.53
No. URAIAN PEKERJAAN Volume HARGA SATUAN JUMLAH

1.4.7 Type V1 2.000 bh Rp. 3,418,189.29


1.4.7.1 Pek. Kusen Jendela Kayu Kls I 0.044 m3 Rp. 16,206,327.50 Rp. 716,319.68
1.4.7.2 Pek. Daun Jendela Kaca Kayu Kls I 1.080 m2 Rp. 514,074.00 Rp. 555,199.92
1.4.7.3 Engsel Jendela 6.000 bh Rp. 21,488.50 Rp. 128,931.00
1.4.7.4 Grendel 3.000 bh Rp. 40,626.85 Rp. 121,880.55
1.4.7.5 Haag Angin 6.000 bh Rp. 31,127.25 Rp. 186,763.50
Rp. 1,709,094.65

1.5 Pengecatan Rp. 24,935,287.81


1.5.1 Cat Tembok dalam 587.580 m2 Rp. 21,129.35 Rp. 12,415,183.47
1.5.2 Cat Tembok Bagian Luar 311.040 m2 Rp. 27,179.35 Rp. 8,453,865.02
1.5.3 Cat Plafond 127.770 m2 Rp. 25,837.90 Rp. 3,301,308.48
1.5.4 Cat Listplank 19.620 m2 Rp. 38,987.30 Rp. 764,930.83

C. PEKERJAAN ELEKTRIKAL Rp. 18,038,029.20

1 INSTALASI LISTRIK ARUS KUAT Rp. 18,038,029.20


1.1 Instalasi Listrik Bangunan Rp. 12,250,956.00
1.1.1 Penyambungan Listrik Baru 1300 kwh 2.000 Titik Rp. 1,500,000.00 Rp. 3,000,000.00
1.1.2 Pemasangan Jaringan Lampu 26.000 ttk Rp. 225,027.00 Rp. 5,850,702.00
1.1.3 Pemasangan Instalasi stop kontak Biasa 12.000 ttk Rp. 188,903.00 Rp. 2,266,836.00
1.1.4 Pemasangan Instalasi stop kontak Khusus 6.000 ttk Rp. 188,903.00 Rp. 1,133,418.00

1.2 Armature Rp. 5,787,073.20


1.2.1 Down Light Setara Panasonik 26.000 bh Rp. 118,193.00 Rp. 3,073,018.00
1.2.2 Lamp SL 23 W 26.000 bh Rp. 44,000.00 Rp. 1,144,000.00
1.2.3 Saklar Ganda 8.000 bh Rp. 50,659.40 Rp. 405,275.20
1.2.4 Saklar Tunggal 8.000 bh Rp. 33,986.70 Rp. 271,893.60
1.2.5 Stop Kontak Biasa skualitas Panasonik 12.000 bh Rp. 36,907.20 Rp. 442,886.40
1.2.6 Stop Kontak Khusus AC skualitas Panasonik 6.000 bh Rp. 75,000.00 Rp. 450,000.00

D. PEKERJAAN AIR BERSIH Rp. 3,367,418.00

1. INSTALASI AIR Rp. 3,367,418.00


1.1 Instalasi Air Bersih Rp. 3,367,418.00
1.1.1 Pipa PVC AW dia. 1/2" 30.000 m' Rp. 20,708.60 Rp. 621,258.00
1.1.2 Kran Air 1/2 " 8.000 bh Rp. 99,770.00 Rp. 798,160.00
1.1.3 Pasang 1 buah Bak Cuci Piring Stainlessteel 2.000 bh Rp. 974,000.00 Rp. 1,948,000.00

E. PEKERJAAN PLUMBING Rp. 20,934,125.80


1 FIXTURE
1.1 Sanitary Rp. 6,951,394.00
1.1.1 Kloset Jongkok 2.000 bh Rp. 752,697.00 Rp. 1,505,394.00
1.1.2 Kloset Duduk 2.000 bh Rp. 2,723,000.00 Rp. 5,446,000.00

1.2 Instalasi Air Kotor dan air bekas Rp. 13,982,731.80


1.2.1 Pipa PVC AW dia. 2" 58.000 m' Rp. 55,785.40 Rp. 3,235,553.20
1.2.3 Pipa PVC AW dia. 3" Disposal Padat 38.000 m' Rp. 90,504.70 Rp. 3,439,178.60
1.2.4 Floor Drain 3" 4.000 bh Rp. 77,000.00 Rp. 308,000.00
1.2.5 Septiktank dan peresapan 2.000 unit Rp. 3,500,000.00 Rp. 7,000,000.00
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN : REHABILITASI PERUMAHAN DOKTER PKM CAKKURIDI
PEMILIK : DINAS KESEHATAN KAB. SOPPENG
TAHUN ANGGARAN : 2018

No. ITEM PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 2,000,000.00


II. PEKERJAAN RUMAH DOKTER (2 UNIT)
A. PEKERJAAN STRUKTUR Rp. 170,792,281.01
B. PEK. FINISHING ARSITEKTUR Rp. 297,292,123.78
C. PEKERJAAN ELEKTRIKAL Rp. 18,038,029.20
D. PEKERJAAN AIR BERSIH Rp. 3,367,418.00
E. PEKERJAAN PLUMBING Rp. 20,934,125.80

JUMLAH REAL COST Rp. 512,423,977.80


PPN 10% Rp. 51,242,397.78
SUB TOTAL Rp. 563,666,375.58
DIBULATKAN Rp. 563,666,000.00

Terbilang:
ENAM RATUS JUTA RUPIAH

Watansoppeng, 2017

Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,


PEJABAT PEMBUAT KOMITMEN PEJABAT PELAKSANA TEKNIS KEGIATAN KONSULTAN PERENCANA
DINAS KESEHATAN DINAS KESEHATAN CV. BIAS MONARCHY KONSULTAN

SALLANG, SKM, M. Kes SABIRIN, SKM ASUBAN PRASAD, ST


NIP. 19631231 196503 1 151 Nip. 19770717 199603 1 004 Direktur

Diketahui Oleh, Diketahui Oleh,


Plt. KEPALA DINAS KESEHATAN KEPALA DINAS PEKERJAAN UMUM & PENATAAN RUANG
KABUPATEN SOPPENG KABUPATEN SOPPENG

Drs. SARIANTO, M. Si H. ABDILLAH BAUSAD, SST, ST


Nip. 19620424 199103 1 011 NIP . 19620508 198903 1 009
HARGA PERKIRAAN SENDIRI (HPS)

KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA PARIWISATA (DAK)


PEKERJAAN : PEMBANGUNAN PUSAT INFORMASI WISATA (TIC) DAN PERLENGKAPANNYA
PEMILIK : DINAS PARIWISATA KAB. SOPPENG
TAHUN : 2018

No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

I. PEKERJAAN PERSIAPAN JUMLAH Rp. 4,800,000.00


1. Pengukuran dan Pemasangan Bouwplank 1.000 Ls Rp. 550,000.00 Rp. 550,000.00
2. Papan Proyek 1.000 Ls Rp. 250,000.00 Rp. 250,000.00
3. Pembongkaran 1.000 Ls Rp. 4,000,000.00 Rp. 4,000,000.00

II. PEKERJAAN GEDUNG UTAMA


A. PEKERJAAN STRUKTUR JUMLAH Rp. 138,026,938.44
1. STRUKTUR PONDASI & SLOEF SUB JUMLAH 1 Rp. 56,957,764.80
1.1 Pondasi Rp. 28,338,079.97
1.1.1 Pondasi Batu Gunung Rp. 27,105,200.72
1.1.1.1 Galian tanah 29.125 m3 Rp. 83,737.50 Rp. 2,438,854.69
1.1.1.2 Urugan pasir bawah pondasi 2.460 m3 Rp. 244,695.00 Rp. 601,949.70
1.1.1.3 Pas. Batu kosong 7.380 m3 Rp. 444,427.50 Rp. 3,279,874.95
1.1.1.4 Pas. Batu Gunung 1 : 4 24.600 m3 Rp. 827,073.50 Rp. 20,346,008.10
1.1.1.5 Urugan tanah bekas galian 7.281 m3 Rp. 60,225.00 Rp. 438,513.28

1.1.2 Pondasi Batu Bata Untuk Tangga Rp. 1,232,879.25


1.1.2.1 Galian tanah 3.170 m3 Rp. 83,737.50 Rp. 265,447.88
1.1.2.2 Urugan pasir bawah rabat 0.225 m3 Rp. 244,695.00 Rp. 55,056.38
1.1.2.3 Pas. Batu merah camp. 1 : 3 4.00 m2 Rp. 115,868.40 Rp. 463,473.60
1.1.2.4 Plasteran 1 : 3 3.60 m2 Rp. 61,569.32 Rp. 221,649.55
1.1.2.5 Rabat Beton Tangga, T=5 cm 0.225 m3 Rp. 1,010,008.21 Rp. 227,251.85

1.2 1.2.1 Saluran Keliling Bangunan Rp. 6,698,630.57


1.2.1.1 Galian tanah 2.49 m3 Rp. 83,737.50 Rp. 208,506.38
1.2.1.2 Urugan pasir bawah pondasi 1.25 m3 Rp. 244,695.00 Rp. 304,645.28
1.2.1.3 Pas. Batu merah camp. 1 : 3 34.86 m2 Rp. 115,868.40 Rp. 4,039,172.42
1.2.1.4 Plasteran 1 : 3 34.86 m2 Rp. 61,569.32 Rp. 2,146,306.50

1.3 Sloef dan rabat Rp. 12,638,975.13


1.31 Sloef ukuran 18/20
a Bekisting 12.400 m2 Rp. 99,258.50 Rp. 1,230,805.40
b Pembesian 278.888 Kg Rp. 17,131.40 Rp. 4,777,748.74
c Beton K. 175 2.232 m3 Rp. 1,120,180.02 Rp. 2,500,241.81
1.3.2 Pasir Alas Rabat Beton Keliling Bangunan, T= 5 cm 2.490 m3 Rp. 244,695.00 Rp. 609,290.55
1.3.3 Rabat Beton Keliling Bangunan, T=7 cm 3.486 m3 Rp. 1,010,008.21 Rp. 3,520,888.64

1.4. Urugan Rp. 9,282,079.13


1.4.1 Timbunan Tanah Pilihan 44.250 m3 Rp. 185,295.00 Rp. 8,199,303.75
1.4.2 Pasir urug dibawah lantai 4.425 m3 Rp. 244,695.00 Rp. 1,082,775.38

2 Struktur Kolom & Balok SUB JUMLAH 2 Rp. 35,117,471.84


2.1 Kolom Rp. 17,677,049.76
2.1.1 Kolom K1 ukuran 20/20 14
a Bekisting 19.200 m2 Rp. 202,281.75 Rp. 3,883,809.60
b Pembesian 328.104 Kg Rp. 17,131.40 Rp. 5,620,880.87
c Beton K. 175 2.880 m3 Rp. 1,120,180.02 Rp. 3,226,118.47
2.1.2 Kolom K2 ukuran 15/15 14
a Bekisting 2.400 m2 Rp. 202,281.75 Rp. 485,476.20
b Pembesian 38.926 Kg Rp. 17,131.40 Rp. 666,850.02
c Beton K. 175 0.270 m3 Rp. 1,120,180.02 Rp. 302,448.61
2.1.3 Kolom K3 ukuran 60/20
a Bekisting 6.400 m2 Rp. 202,281.75 Rp. 1,294,603.20
b Pembesian 65.464 Kg Rp. 17,131.40 Rp. 1,121,489.97
c Beton K. 175 0.960 m3 Rp. 1,120,180.02 Rp. 1,075,372.82

2.2 Balok, Plat Rp. 17,440,422.08


2.2.1 Balok B1 15/15, Elev. ± 3,11 14
a Bekisting 1.800 m2 Rp. 205,499.25 Rp. 369,898.65
b Pembesian 34.574 Kg Rp. 17,131.40 Rp. 592,307.88
c Beton K. 175 0.180 m3 Rp. 1,120,180.02 Rp. 201,632.40
2.2.2 Balok B2 15/15, Elev. ± 3,69 14
a Bekisting 1.200 m2 Rp. 205,499.25 Rp. 246,599.10
b Pembesian 25.950 Kg Rp. 17,131.40 Rp. 444,566.68
c Beton K. 175 0.180 m3 Rp. 1,120,180.02 Rp. 201,632.40
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

2.2.3 Ringbalk 15/15, Elev. ± 4,00


a Bekisting 6.460 m2 Rp. 205,499.25 Rp. 1,327,525.16
b Pembesian 209.549 Kg Rp. 17,131.40 Rp. 3,589,875.96
c Beton K. 175 1.454 m3 Rp. 1,120,180.02 Rp. 1,628,181.66
2.2.4 Kuda-Kuda Beton 15/15
a Bekisting 5.295 m2 Rp. 205,499.25 Rp. 1,088,118.53
b Pembesian 114.506 Kg Rp. 17,131.40 Rp. 1,961,650.49
c Beton K. 175 0.794 m3 Rp. 1,120,180.02 Rp. 889,702.98
2.2.5 Dak Beton, T. 5 Cm
a Bekisting 3.120 m2 Rp. 301,281.75 Rp. 939,999.06
b Pembesian 175.910 Kg Rp. 17,131.40 Rp. 3,013,584.57
c Beton K. 175 0.312 m3 Rp. 1,120,180.02 Rp. 349,496.17
2.2.6 Meja Beton Dapur, T. 10 Cm
a Bekisting 1.410 m2 Rp. 205,499.25 Rp. 289,753.94
b Pembesian 8.636 Kg Rp. 17,131.40 Rp. 147,951.05
c Beton K. 175 0.141 m3 Rp. 1,120,180.02 Rp. 157,945.38

3 Struktur Atap SUB JUMLAH 3 Rp. 45,951,701.80


3.1 Rangka Atap Baja Ringan 156.440 m2 Rp. 183,095.00 Rp. 28,643,381.80
3.2 Atap Spandek Warna T. 0,35 mm 156.440 m2 Rp. 82,658.40 Rp. 12,931,080.10
3.4 Jurai Dalam 7.000 m' Rp. 46,950.00 Rp. 328,650.00
3.5 Nok Atap 20.620 m' Rp. 51,609.80 Rp. 1,064,194.08
3.6 Listplank Kalsiplank 55.280 m' Rp. 53,986.90 Rp. 2,984,395.83

B. PEK. FINISHING ARSITEKTUR JUMLAH Rp. 187,651,730.30

1.1 Pekerjaan Lantai Rp. 35,739,215.22


1.1.1 Rabat beton sebagai lantai kerja T 7 cm 6.195 m3 Rp. 1,010,008.21 Rp. 6,257,000.89
1.1.2 Lantai Granit 60x60 Homogeneous (Tekstur Halus) 73.153 m2 Rp. 329,747.00 Rp. 24,121,817.42
1.1.3 Lantai Granit 60x60 Homogeneous (Tekstur Kasar) 6.000 m2 Rp. 384,347.00 Rp. 2,306,082.00
1.1.4 Lantai Keramik 60x60 Homogeneous u/ Meja Beton 1.410 m2 Rp. 329,747.00 Rp. 464,943.27
1.1.5 Keramik Tangga 30x30 Kasar 5.200 m2 Rp. 268,586.50 Rp. 1,396,649.80
1.1.6 Keramik 40 x 40 Kasar (kamar mandi) 4.348 m2 Rp. 274,346.60 Rp. 1,192,721.84

1.2 Pekerjaan Dinding Rp. 74,564,042.47


1.2.1 Pas. Bata merah 1/2 batu camp. 1 : 3 (Transraam) 14.550 m2 Rp. 115,868.40 Rp. 1,685,885.22
1.2.2 Pas. Bata merah 1/2 batu camp. 1 : 4 218.490 m2 Rp. 125,796.00 Rp. 27,485,168.04
1.2.3 Plesteran camp. 1 : 3 (Transraam) 29.100 m2 Rp. 61,569.32 Rp. 1,791,667.21
1.2.4 Plesteran camp. 1 : 4 436.980 m2 Rp. 59,701.80 Rp. 26,088,492.56
1.2.5 Acian Dinding Luar 154.860 m2 Rp. 36,040.00 Rp. 5,581,154.40
1.2.6 Pas. Keramik granit dinding Meja Beton 60x60, T. 60 Cm 2.130 m2 Rp. 331,616.60 Rp. 706,343.36
1.2.7 Pas. Keramik Dinding 40 x 40 Cm 11.960 m2 Rp. 280,146.00 Rp. 3,350,546.16
(Motif Batu Alam Pada Tiang Depan)
1.2.8 Pas. Keramik dinding KM/WC 25 x 40, T. 175 Cm 13.650 m2 Rp. 313,171.10 Rp. 4,274,785.52
1.2.9 Papan Nama Huruf Stainlist, Tinggi 20 Cm 1.000 Ls Rp. 3,600,000.00 Rp. 3,600,000.00
"PUSAT INFORMASI WISATA"

1.3 Pekerjaan Plafond Rp. 25,973,379.54


1.3.1 Rangka Hollow 125.160 m2 Rp. 124,201.00 Rp. 15,544,997.16
1.3.3 Plafond Calsiboard 3,5 mm 125.160 m2 Rp. 56,960.20 Rp. 7,129,138.63
1.3.4 List Plafond Kayu Profil 5 Cm 185.000 m' Rp. 17,833.75 Rp. 3,299,243.75

1.4 Pekerjaan Pintu lengkap kusen dan accesories Rp. 36,709,941.63


1.4.1 Type P1 1.000 bh Rp. 3,168,592.50
1.4.1.1 Kusen Alluminium 7.000 m' Rp. 115,984.50 Rp. 811,891.50
1.4.1.2 Daun Pintu Pabrikasi Lapis HPL 1.000 Bh Rp. 1,225,075.00 Rp. 1,225,075.00
1.4.1.3 Daun Jendela Allumunium + Kaca Ryben T 5 cm 0.350 m2 Rp. 579,535.00 Rp. 202,837.25
1.4.1.4 Engsel Casement 16" 2.000 m2 Rp. 106,310.00 Rp. 212,620.00
1.4.1.5 Engsel Pintu 3.000 bh Rp. 31,276.85 Rp. 93,830.55
1.4.1.6 Engsel Jendela 2.000 bh Rp. 21,488.50 Rp. 42,977.00
1.4.1.7 Grendel Buncis 2.000 bh Rp. 40,626.85 Rp. 81,253.70
1.4.1.8 Handle Pintu Stainlist 1.000 psg Rp. 275,000.00 Rp. 275,000.00
1.4.1.9 Kunci Pintu 2 x putar Setara Yale 1.000 bh Rp. 223,107.50 Rp. 223,107.50
Rp. 3,168,592.50

1.4.2 Type P2 (KM/WC) 1.000 bh Rp. 1,284,816.35


1.4.2.1 Kusen Allumunium 4.400 m' Rp. 115,984.50 Rp. 510,331.80
1.4.2.2 Pintu Aluminium 1.000 m2 Rp. 601,304.00 Rp. 601,304.00
1.4.2.3 Engsel Pintu 2.000 bh Rp. 31,276.85 Rp. 62,553.70
1.4.2.4 Grendel Buncis 1.000 bh Rp. 40,626.85 Rp. 40,626.85
1.4.2.5 Handle Pintu 1.000 psg Rp. 70,000.00 Rp. 70,000.00
Rp. 1,284,816.35
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

1.4.3 Type PJ.1 1.000 bh Rp. 8,707,752.58


1.4.3.1 Kusen Allumunium 16.900 m' Rp. 115,984.50 Rp. 1,960,138.05
1.4.3.2 Daun Pintu Pabrikasi Lapis HPL 2.000 Bh Rp. 1,225,075.00 Rp. 2,450,150.00
1.4.3.3 Daun Jendela Allumunium + Kaca Ryben T 5 cm 2.350 m2 Rp. 579,535.00 Rp. 1,361,907.25
1.4.3.4 Kaca Mati Ryben 5 mm 0.500 m2 Rp. 232,383.75 Rp. 116,191.88
1.4.3.5 Engsel Casement 16" 12.000 bh Rp. 106,310.00 Rp. 1,275,720.00
1.4.3.6 Engsel Pintu 6.000 bh Rp. 31,276.85 Rp. 187,661.10
1.4.3.7 Engsel Jendela 12.000 bh Rp. 21,488.50 Rp. 257,862.00
1.4.3.8 Grendel Buncis 8.000 bh Rp. 40,626.85 Rp. 325,014.80
1.4.3.9 Handle Pintu Stainlist 2.000 psg Rp. 275,000.00 Rp. 550,000.00
1.4.3.10 Kunci Pintu 2 x putar Setara Yale 1.000 bh Rp. 223,107.50 Rp. 223,107.50
Rp. 8,707,752.58

1.4.4 Type PJ.2 1.000 bh Rp. 5,025,013.33


1.4.4.1 Kusen Allumunium 11.600 m' Rp. 115,984.50 Rp. 1,345,420.20
1.4.4.2 Daun Pintu Pabrikasi Lapis HPL 1.000 Bh Rp. 1,225,075.00 Rp. 1,225,075.00
1.4.4.3 Daun Jendela Allumunium + Kaca Ryben T 5 cm 1.420 m2 Rp. 579,535.00 Rp. 822,939.70
1.4.4.4 Kaca Mati Ryben 5 mm 0.300 m2 Rp. 232,383.75 Rp. 69,715.13
1.4.4.5 Engsel Casement 16" 6.000 bh Rp. 106,310.00 Rp. 637,860.00
1.4.4.6 Engsel Pintu 3.000 bh Rp. 31,276.85 Rp. 93,830.55
1.4.4.7 Engsel Jendela 6.000 bh Rp. 21,488.50 Rp. 128,931.00
1.4.4.8 Grendel Buncis 5.000 bh Rp. 40,626.85 Rp. 203,134.25
1.4.4.9 Handle Pintu Stainlist 1.000 psg Rp. 275,000.00 Rp. 275,000.00
1.4.4.10 Kunci Pintu 2 x putar Setara Yale 1.000 bh Rp. 223,107.50 Rp. 223,107.50
Rp. 5,025,013.33

1.4.5 Type V1 2.000 bh Rp. 2,576,321.90


1.4.5.1 Kusen Allumunium 3.500 m' Rp. 115,984.50 Rp. 405,945.75
1.4.5.2 Daun Jendela Allumunium + Kaca Ryben T 5 cm 0.500 m2 Rp. 579,535.00 Rp. 289,767.50
1.4.5.3 Engsel Casement 16" 4.000 bh Rp. 106,310.00 Rp. 425,240.00
1.4.5.4 Engsel Jendela 4.000 bh Rp. 21,488.50 Rp. 85,954.00
1.4.5.5 Grendel Buncis 2.000 bh Rp. 40,626.85 Rp. 81,253.70
Rp. 1,288,160.95

1.4.6 Type V2 Rp. 750,000.00


1.4.6.1 Ventilasi Besi Kotak 4/4 dan 2/4 1.000 Ls Rp. 750,000.00 Rp. 750,000.00

1.4.7 Type J1 3.000 bh Rp. 13,155,461.85


1.4.7.1 Kusen Allumunium 11.400 m' Rp. 115,984.50 Rp. 1,322,223.30
1.4.7.2 Daun Jendela Allumunium + Kaca Ryben T 5 cm 3.000 m2 Rp. 579,535.00 Rp. 1,738,605.00
1.4.7.3 Kaca Mati Ryben 5 mm 0.600 m2 Rp. 232,383.75 Rp. 139,430.25
1.4.7.4 Engsel Casement 16" 8.000 bh Rp. 106,310.00 Rp. 850,480.00
1.4.7.5 Engsel Jendela 8.000 bh Rp. 21,488.50 Rp. 171,908.00
1.4.7.6 Grendel Buncis 4.000 bh Rp. 40,626.85 Rp. 162,507.40
Rp. 4,385,153.95

1.4.8 Type J2 1.000 bh Rp. 2,041,983.13


1.4.8.1 Kusen Allumunium 6.800 m' Rp. 115,984.50 Rp. 788,694.60
1.4.8.2 Daun Jendela Allumunium + Kaca Ryben T 5 cm 1.020 m2 Rp. 579,535.00 Rp. 591,125.70
1.4.8.3 Kaca Mati Ryben 5 mm 0.300 m2 Rp. 232,383.75 Rp. 69,715.13
1.4.8.4 Engsel Casement 16" 4.000 bh Rp. 106,310.00 Rp. 425,240.00
1.4.8.5 Engsel Jendela 4.000 bh Rp. 21,488.50 Rp. 85,954.00
1.4.8.6 Grendel Buncis 2.000 bh Rp. 40,626.85 Rp. 81,253.70
Rp. 2,041,983.13

1.5. Pengecatan Rp. 14,665,151.45


1.5.1 Cat Tembok dalam 311.220 m2 Rp. 21,129.35 Rp. 6,575,876.31
1.5.2 Cat Tembok Bagian Luar 154.860 m2 Rp. 27,179.35 Rp. 4,208,994.14
1.5.3 Cat Plafond 125.160 m2 Rp. 25,837.90 Rp. 3,233,871.56
1.5.4 Cat Listplank 16.580 m2 Rp. 38,987.30 Rp. 646,409.43

C. PEKERJAAN ELEKTRIKAL Rp. 14,560,985.60

1. INSTALASI LISTRIK Rp. 14,560,985.60


1.1 Instalasi listrik utama Rp. 4,965,000.00
1.1.1 Pemasangan Panel/ Box MCB Instalasi 1.000 Set Rp. 565,000.00 Rp. 565,000.00
1.1.2 Penyambungan Listrik Baru 2200 kwh 1.000 Titik Rp. 2,400,000.00 Rp. 2,400,000.00
1.1.3 Penyambungan Jaringan Telepon/Fax 1.000 Titik Rp. 2,000,000.00 Rp. 2,000,000.00
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

1.2 Instalasi Listrik Bangunan Rp. 5,561,710.00


1.2.1 Pemasangan Jaringan Lampu 18.000 ttk Rp. 225,027.00 Rp. 4,050,486.00
1.2.2 Pemasangan Instalasi stop kontak Biasa 5.000 ttk Rp. 188,903.00 Rp. 944,515.00
1.2.3 Pemasangan Instalasi stop kontak Khusus 3.000 ttk Rp. 188,903.00 Rp. 566,709.00

1.3 Armature Rp. 4,034,275.60


1.3.1 Down Light Setara Panasonik 18.000 bh Rp. 118,193.00 Rp. 2,127,474.00
1.3.2 Lampu LED 18 Watt 18.000 bh Rp. 70,000.00 Rp. 1,260,000.00
1.3.3 Saklar Ganda 2.000 bh Rp. 50,659.40 Rp. 101,318.80
1.3.4 Saklar Tunggal 4.000 bh Rp. 33,986.70 Rp. 135,946.80
1.3.5 Stop Kontak Biasa skualitas Panasonik 5.000 bh Rp. 36,907.20 Rp. 184,536.00
1.3.6 Stop Kontak Khusus AC skualitas Panasonik 3.000 bh Rp. 75,000.00 Rp. 225,000.00

D. PEKERJAAN AIR BERSIH Rp. 5,767,690.75

1. INSTALASI AIR Rp. 5,767,690.75


1.1 Instalasi Air Bersih Rp. 5,767,690.75
1.1.1 Pipa PVC AW dia. 1/2" 20.000 m' Rp. 20,708.60 Rp. 414,172.00
1.1.2 Pipa PVC AW dia. 3/4" 4.000 m' Rp. 21,710.00 Rp. 86,840.00
1.1.3 Kran Air Stainless 1/2 " 1.000 bh Rp. 99,770.00 Rp. 99,770.00
1.1.4 Kran Air Leher Angsa Pada Dapur dia. 1/2" 1.000 bh Rp. 166,908.75 Rp. 166,908.75
1.1.5 Bak Reservoir Fiber 1,3 M3 + Dudukan + Instalasi Air 1.000 bh Rp. 5,000,000.00 Rp. 5,000,000.00

E. PEKERJAAN PLUMBING Rp. 5,902,510.60


1. FIXTURE
1.1 Sanitary Rp. 1,726,697.00
1.1.1 Kloset Jongkok 1.000 bh Rp. 752,697.00 Rp. 752,697.00
1.1.2 Pasang 1 buah Bak Cuci Piring Stainlessteel 1.000 bh Rp. 974,000.00 Rp. 974,000.00

1.2 Instalasi Air Kotor dan air bekas Rp. 4,175,813.60


1.2.1 Pipa PVC AW dia. 3" Disposal Padat dan Cair 4.000 m' Rp. 90,504.70 Rp. 362,018.80
1.2.2 Floor Drain Stainless 3" 1.000 bh Rp. 77,000.00 Rp. 77,000.00
1.2.3 Fitting2 dan acsesories 1.000 Ls Rp. 236,794.80 Rp. 236,794.80
1.2.4 Septiktank dan peresapan 1.000 unit Rp. 3,500,000.00 Rp. 3,500,000.00

III. PENGADAAN BARANG KELENGKAPAN Rp. 56,575,900.00


1. Meja Resepsionis 1.000 Bh Rp. 6,600,000.00 Rp. 6,600,000.00
2. Kursi Kerja Staf 2.000 Bh Rp. 1,305,000.00 Rp. 2,610,000.00
3. Kursi Susun/Rapat (Futura) 3.000 Bh Rp. 517,500.00 Rp. 1,552,500.00
4. Kursi Tunggu (4 Seat/Dudukan) 1.000 Bh Rp. 4,950,000.00 Rp. 4,950,000.00
5. Meja Kerja Staf 1.000 Bh Rp. 1,980,000.00 Rp. 1,980,000.00
6. Rak Buku (Aktiv) 1.000 Bh Rp. 2,340,000.00 Rp. 2,340,000.00
7. Televisi "LG" LED 42" 1.000 Unit Rp. 5,733,000.00 Rp. 5,733,000.00
8. Personal Computer (PC) ALL IN ONE (Lenovo AIO 510-22ISH) 1.000 Unit Rp. 9,752,400.00 Rp. 9,752,400.00
- Processor Intel Corew TMi5-7400T
- Integrated Intel HD Graphics 620
- Memory 4GB DDR4
- Hard Disk 500GB (7200 RPM SATA3)
- HDMI Out, Wifi, Bluetooth 4.0, Keyboard + Mouse
- Monitor 21.5"LED (1920x1080p)
- DOS Operating System
9. Wireless TOA (ZW-G810CU) 1.000 Set Rp. 7,488,000.00 Rp. 7,488,000.00
10. Printer Epson Type L 120 1.000 Unit Rp. 2,030,000.00 Rp. 2,030,000.00
11. Scanner Epson Type DS-360 W 1.000 Unit Rp. 5,340,000.00 Rp. 5,340,000.00
13. Mesin Faximile (Panasonic KX-FT503 CX) 1.000 Unit Rp. 1,800,000.00 Rp. 1,800,000.00
14. Running Text (32 x 224 cm), 14 modul Warna Merah 1.000 Unit Rp. 4,400,000.00 Rp. 4,400,000.00
REKAPITULASI
HARGA PERKIRAAN SENDIRI (HPS)
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA PARIWISATA (DAK)
PEKERJAAN : PEMBANGUNAN PUSAT INFORMASI WISATA (TIC) DAN PERLENGKAPANNYA
PEMILIK : DINAS PARIWISATA KAB. SOPPENG
TAHUN ANGGARAN : 2018

No. ITEM PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 4,800,000.00


II. PEKERJAAN GEDUNG UTAMA
A. PEKERJAAN STRUKTUR Rp. 138,026,938.44
B. PEKERJAAN ARSITEKTUR Rp. 187,651,730.30
C. PEKERJAAN ELEKTRIKAL Rp. 14,560,985.60
D. PEKERJAAN AIR BERSIH Rp. 5,767,690.75
E. PEKERJAAN PLUMBING Rp. 5,902,510.60
III. PENGADAAN BARANG KELENGKAPANNYA Rp. 56,575,900.00

JUMLAH REAL COST Rp. 413,285,755.69


PPN 10% Rp. 41,328,575.57
SUB TOTAL Rp. 454,614,331.26
DIBULATKAN Rp. 454,614,000.00

Terbilang: EMPAT RATUS SEMBILAN PULUH SEMBILAN JUTA ENAM RATUS TUJUH PULUH TIGA RIBU
RUPIAH

Watansoppeng, 16 April 2018

PEJABAT PEMBUAT KOMITMEN


DINAS KEBUDAYAAN DAN PARIWISATA

H. ANDI UNRU MAPPAJANCI, SH


Nip. 19600423 198803 1 003
HARGA PERKIRAAN SENDIRI (HPS)
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA PARIWISATA (DAK)
PEKERJAAN : PEMBANGUNAN GAPURA IDENTITAS/PINTU GERBANG KAWASAN WISATA ALAM (KWA) OMPO
PEMILIK : DINAS PARIWISATA KAB. SOPPENG
TAHUN : 2018

No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

I. PEKERJAAN PERSIAPAN JUMLAH Rp. 850,000.00


1. Pengukuran dan Pemasangan Bouwplank 1.000 Ls Rp. 600,000.00 Rp. 600,000.00
2. Papan Proyek 1.000 Ls Rp. 250,000.00 Rp. 250,000.00

II. PEKERJAAN GAPURA/PINTU GERBANG


A. PEKERJAAN STRUKTUR JUMLAH Rp. 134,985,776.63
1. STRUKTUR PONDASI & SLOEF Rp. 51,724,314.64
1.1 Pondasi Rp. 44,925,284.66
1.1.1 Pondasi Poer PD. 01 Rp. 25,987,181.07
1.1.1.1 Galian tanah 21.320 m3 Rp. 83,737.50 Rp. 1,785,283.50
1.1.1.2 Urugan pasir bawah pondasi Poer 0.750 m3 Rp. 244,695.00 Rp. 183,521.25
1.1.1.3 Lantai Kerja 1.500 m3 Rp. 1,010,008.21 Rp. 1,515,012.32
1.1.1.4 Beton Poer
a Bekisting 11.533 m2 Rp. 170,720.00 Rp. 1,968,970.67
b Pembesian 766.654 Kg Rp. 17,131.40 Rp. 13,133,856.34
c Beton K. 175 6.320 m3 Rp. 1,120,180.02 Rp. 7,079,537.75
1.1.1.5 Urugan tanah bekas galian 5.330 m3 Rp. 60,225.00 Rp. 320,999.25

1.1.2 Pondasi Poer PD. 02 Rp. 9,158,411.15


1.1.1.1 Galian tanah 12.870 m3 Rp. 83,737.50 Rp. 1,077,701.63
1.1.1.2 Urugan pasir bawah pondasi Poer 0.425 m3 Rp. 244,695.00 Rp. 103,995.38
1.1.1.3 Lantai Kerja 0.850 m3 Rp. 1,010,008.21 Rp. 858,506.98
1.1.1.4 Beton Poer
a Bekisting 7.160 m2 Rp. 170,720.00 Rp. 1,222,355.20
b Pembesian 455.077 Kg Rp. 3,250.00 Rp. 1,478,999.34
c Beton K. 175 3.770 m3 Rp. 1,120,180.02 Rp. 4,223,078.69
1.1.1.5 Urugan tanah bekas galian 3.218 m3 Rp. 60,225.00 Rp. 193,773.94

1.1.3 Pondasi Batu Gunung Rp. 9,779,692.44


1.1.3.1 Galian tanah 3.200 m3 Rp. 83,737.50 Rp. 267,960.00
1.1.3.2 Urugan pasir bawah pondasi 0.225 m3 Rp. 244,695.00 Rp. 55,056.38
1.1.3.3 Pas. Batu Gunung campuran 1 : 4 9.860 m3 Rp. 827,073.50 Rp. 8,154,944.71
1.1.3.4 Plasteran Pondasi 1 : 3 20.36 m2 Rp. 61,569.32 Rp. 1,253,551.36
1.1.3.5 Urugan tanah bekas galian 0.800 m3 Rp. 60,225.00 Rp. 48,180.00

1.2 Sloef dan rabat Rp. 3,292,539.90


1.2.1 Sloef ukuran 20/25
a Bekisting 4.300 m2 Rp. 99,258.50 Rp. 426,811.55
b Pembesian 111.046 Kg Rp. 17,131.40 Rp. 1,902,373.53
c Beton K. 175 0.860 m3 Rp. 1,120,180.02 Rp. 963,354.82

1.3 Urugan Rp. 3,506,490.08


1.3.1 Timbunan Tanah 17.940 m3 Rp. 185,295.00 Rp. 3,324,192.30
1.3.2 Pasir urug dibawah lantai, T. 5 Cm 0.745 m3 Rp. 244,695.00 Rp. 182,297.78

2 STRUKTUR KOLOM DAN BALOK SUB JUMLAH 2 Rp. 50,852,918.14


2.1 Kolom 26,945,022.26
2.1.1 Kolom K1, ukuran 30/50
a Bekisting 15.360 m2 Rp. 202,281.75 Rp. 3,107,047.68
b Pembesian 380.683 Kg Rp. 17,131.40 Rp. 6,521,632.06
c Beton K. 175 3.840 m3 Rp. 1,120,180.02 Rp. 4,301,491.29
2.1.2 Kolom K2, ukuran 30/30
a Bekisting 16.427 m2 Rp. 202,281.75 Rp. 3,322,814.88
b Pembesian 382.008 Kg Rp. 17,131.40 Rp. 6,544,330.48
c Beton K. 175 2.810 m3 Rp. 1,120,180.02 Rp. 3,147,705.87

2.2 Balok dan Lantai Beton Rp. 23,907,895.88


2.2.1 Balok B1, Ukuran 15/20, Elev. ±4,40
a Bekisting 10.413 m2 Rp. 205,499.25 Rp. 2,139,932.19
b Pembesian 124.993 Kg Rp. 17,131.40 Rp. 2,141,298.74
c Beton K. 175 0.850 m3 Rp. 1,120,180.02 Rp. 952,153.02
2.2.2 Balok B2, Ukuran 20/60, Elev. ±5,60
a Bekisting 10.267 m2 Rp. 205,499.25 Rp. 2,109,792.30
b Pembesian 257.696 Kg Rp. 17,131.40 Rp. 4,414,691.54
c Beton K. 175 2.640 m3 Rp. 1,120,180.02 Rp. 2,957,275.26
No. URAIAN PEKERJAAN VOLUME HARGA SATUAN JUMLAH

2.2.3 Balok B3, Ukuran 15/20, Elev. ±6,20


a Bekisting 6.875 m2 Rp. 205,499.25 Rp. 1,412,807.34
b Pembesian 141.880 Kg Rp. 17,131.40 Rp. 2,430,594.47
c Beton K. 175 0.750 m3 Rp. 1,120,180.02 Rp. 840,135.02
2.2.4 Balok B4, Ukuran 15/20, Elev. ±6,40
a Bekisting 4.730 m2 Rp. 205,499.25 Rp. 972,011.45
b Pembesian 75.700 Kg Rp. 17,131.40 Rp. 1,296,844.50
c Beton K. 175 0.510 m3 Rp. 1,120,180.02 Rp. 571,291.81
2.2.5 Lantai Beton K. 175 1.490 m3 Rp. 1,120,180.02 Rp. 1,669,068.24

3 STRUKTUR ATAP SUB JUMLAH 3 Rp. 32,408,543.85


3.1 Rangka Kuda-Kuda Kayu Kumia 0.810 m3 Rp. 10,428,900.00 Rp. 8,447,409.00
3.2 Rangka Balok Gording Kayu Kls II 1.080 m3 6,881,300.00 Rp. 7,431,804.00
3.3 Atap Spandek Warna T. 0,35 mm 120.520 m2 Rp. 82,658.40 Rp. 9,961,990.37
3.4 Nok Atap Spandek 21.510 m1 Rp. 51,609.80 Rp. 1,110,126.80
3.5 Jurai Dalam 4.800 m1 Rp. 46,950.00 Rp. 225,360.00
3.6 List Plant Kalsiplank L. 30 Cm 107.920 m1 Rp. 48,479.00 Rp. 5,231,853.68

B. PEK. FINISHING ARSITEKTUR JUMLAH Rp. 64,595,775.35

1.1 Pekerjaan Dinding Rp. 42,897,992.34


1.1.1 Pas. Bata merah 1/2 batu camp. 1 : 4 20.300 m2 Rp. 125,796.00 Rp. 2,553,658.80
1.1.2 Plesteran camp. 1 : 4 40.600 m2 Rp. 59,701.80 Rp. 2,423,893.08
1.1.3 Plesteran Beton camp. 1 : 2 (Kolom & Balok) 100.520 m2 Rp. 64,320.68 Rp. 6,465,514.75
1.1.4 Pas. Keramik Dinding 40 x 40 Cm Motif Kayu 4.550 m2 Rp. 280,146.00 Rp. 1,274,664.30
1.1.5 Acian 141.120 m2 Rp. 36,040.00 Rp. 5,085,964.80
1.1.6 Ralling Besi Hollow 6.400 m2 Rp. 352,460.78 Rp. 2,255,749.01
1.1.7 Ralling Kayu Kumia 11.440 m2 Rp. 520,415.00 Rp. 5,953,547.60
1.1.8 Pemasangan Logo Soppeng (Acrilyc), Tinggi 100 Cm 1.000 Ls Rp. 1,000,000.00 Rp. 1,000,000.00
1.1.9 Papan Nama Huruf Stainlist, Tinggi 10 Cm 1.000 Ls Rp. 1,440,000.00 Rp. 1,440,000.00
"KABUPATEN SOPPENG"
1.1.10 Papan Nama Huruf Stainlist, Tinggi 25 Cm 1.000 Ls Rp. 2,925,000.00 Rp. 2,925,000.00
"SELAMAT DATANG"
1.1.11 Papan Nama Huruf Stainlist, Tinggi 25 Cm 1.000 Ls Rp. 2,700,000.00 Rp. 2,700,000.00
"SELAMAT JALAN"
1.1.12 Papan Nama Huruf Stainlist, Tinggi 25 Cm 1.000 Ls Rp. 1,575,000.00 Rp. 1,575,000.00
"WELCOME"
1.1.13 Papan Nama Huruf Stainlist, Tinggi 25 Cm 1.000 Ls Rp. 1,575,000.00 Rp. 1,575,000.00
"GOODBYE"
1.1.14 Papan Nama Huruf Stainlist, Tinggi 30 Cm 1.000 Ls Rp. 5,670,000.00 Rp. 5,670,000.00
"KAWASAN WISATA ALAM OMPO"

1.2 Pekerjaan Plafond Rp. 14,815,900.62


1.2.1 Rangka Plafond Kayu Kls II 77.010 m2 Rp. 113,739.60 Rp. 8,759,086.60
1.2.2 Plafond Calsiboard 3,5 mm 77.010 m2 Rp. 56,960.20 Rp. 4,386,505.00
1.2.3 List Plafond Profil Kayu 5 Cm 93.660 m' Rp. 17,833.75 Rp. 1,670,309.03

1.3 Pengecatan Rp. 6,881,882.38


1.3.1 Cat Tembok Exterior 141.120 m2 Rp. 27,179.35 Rp. 3,835,549.87
1.3.2 Cat Plafond 77.010 m2 Rp. 25,837.90 Rp. 1,989,776.68
1.3.3 Cat Kayu 27.100 m2 Rp. 38,987.30 Rp. 1,056,555.83

III. PEKERJAAN TAMAN JUMLAH Rp. 4,761,878.09


1. Pas. Casting Bata merah 1/2 batu camp. 1 : 4 12.030 m2 Rp. 125,796.00 Rp. 1,513,325.88
2. Plesteran Campuran 1 : 4 24.060 m2 Rp. 59,701.80 Rp. 1,436,425.31
3. Acian 24.060 m2 Rp. 36,040.00 Rp. 867,122.40
4. Timbunan Tanah 5.100 m3 Rp. 185,295.00 Rp. 945,004.50
REKAPITULASI
HARGA PERKIRAAN SENDIRI (HPS)
KEGIATAN : PENINGKATAN PEMBANGUNAN SARANA DAN PRASARANA PARIWISATA (DAK)
PEKERJAAN : PEMBANGUNAN GAPURA IDENTITAS/PINTU GERBANG KAWASAN WISATA ALAM (KWA) OMPO
PEMILIK : DINAS PARIWISATA KAB. SOPPENG
TAHUN ANGGARAN : 2018

No. ITEM PEKERJAAN JUMLAH HARGA

I. PEKERJAAN PERSIAPAN Rp. 850,000.00


II. PEKERJAAN GAPURA/PINTU GERBANG
A. PEKERJAAN STRUKTUR Rp. 134,985,776.63
B. PEK. FINISHING ARSITEKTUR Rp. 64,595,775.35
III. PEKERJAAN TAMAN Rp. 4,761,878.09

JUMLAH REAL COST Rp. 205,193,430.06


PPN 10% Rp. 20,519,343.01
SUB TOTAL Rp. 225,712,773.07
DIBULATKAN Rp. 225,712,000.00

Terbilang: DUA RATUS EMPAT PULUH SEMBILAN JUTA ENAM RATUS EMPAT PULUH TUJUH RIBU
RUPIAH

Watansoppeng, 16 April 2018

PEJABAT PEMBUAT KOMITMEN


DINAS KEBUDAYAAN DAN PARIWISATA

H. ANDI UNRU MAPPAJANCI, SH


Nip. 19600423 198803 1 003

Anda mungkin juga menyukai