KEGIATAN : PERENCANAAN PEMBANGUNAN GEDUNG KANTOR DINAS PEKERJAAN UMUM KOTA MAKASSAR
LOKASI : KOTA MAKASSAR
SUMBER DANA : APBN TAHUN 2011
LANTAI 1
I Lobby
1 Counter reception 70x220x110 1.00 unit Rp 2,541,000.00 2,541,000
Multiplek 18 mm lapis HPL, kaca 10mm, stainless steel hairlines -
2 Kursi reception ( dengan logo BNN di embossed ) 2.00 unit Rp 650,000.00 1,300,000
3 Back drop counter 9.30 m2 Rp 1,500,000.00 13,950,000
Multiplek 18 mm lapis HPL, kaca duco, stainless steel hairlines -
4 Logo BNN 1.00 unit Rp 36,050.00 36,050
Stainless stell hairlines+cutting stiker -
6 Sofa three seater 1.00 set Rp 17,500,000.00 17,500,000
Rangka kayu solid, busa density 32, artificial leather(oscar),kaki stainless stell -
7 Cofee table 50x900x45 1.00 unit Rp 1,500,000.00 1,500,000
Multiplek 18 mm lapis HPL+ kaca 8 mm+spacer stainless stell -
8 Meja sudut 45x45x45 2.00 unit Rp 250,000.00 500,000
Multiplek 18 mm lapis HPL+ kaca 8 mm+spacer stainless stell
Total I 37,327,050
total II 29,098,000
IV R. Makan
1 Meja makan ø80x75 1.00 unit Rp 2,500,000.00 2,500,000
multiplek lapis HPL, support leg powder coating -
2 kursi makan 4.00 unit Rp 250,000.00 1,000,000
total IV 3,500,000
LANTAI 2
total V 29,098,000
ENGINEERING ESTIMATE
KEGIATAN : PERENCANAAN PEMBANGUNAN GEDUNG KANTOR DINAS PEKERJAAN UMUM KOTA MAKASSAR
LOKASI : KOTA MAKASSAR
SUMBER DANA : APBN TAHUN 2011
total VI 42,658,000
VIII R. Arsip
1 Meja kerja 60x120x75 (dengan plat stainless stell di gravire ) 2.00 unit Rp 1,044,000.00 2,088,000
Multiplek 18 mm lapis HPL+ handle stainless stell -
2 Kursi kerja ( dengan logo BNN di embossed ) 2.00 unit Rp 650,000.00 1,300,000
3 Panel Workstation 160x120 1.00 unit Rp 1,728,000.00 1,728,000
Frame aluminium powder coating, panel fabric 2 colour -
B. BAHAN
C. PERALATAN
B. BAHAN
C. PERALATAN
B. BAHAN
Pasir Urug 1.200 Rp. 160,000.00 Rp. 192,000.00
C. PERALATAN
B. BAHAN
Tanah Timbunan 1.200 Rp. 115,000.00 Rp. 138,000.00
C. PERALATAN
B. BAHAN
Batu belah m³ 1.200 Rp. 172,000.00 Rp. 206,400.00
Pasir urug m³ 0.432 Rp. 160,000.00 Rp. 69,120.00
C. PERALATAN
B. BAHAN
Batu belah m³ 1.200 Rp. 172,000.00 Rp. 206,400.00
Semen Portland kg 163.000 Rp. 1,320.00 215,160.00
Pasir Pasang m³ 0.520 Rp. 160,000.00 Rp. 83,200.00
C. PERALATAN
Membuat 1 m3 Beton Mutu fc' = 14.5 MPa (K-175), Slump (12 ± 2) cm, w/c : 0.66
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
PC (1 zak = 50 kg) kg 326.000 Rp 1,320.00 Rp 430,320.00
Pasir Beton kg 760.000 Rp 114.29 Rp 86,857.14
A. Bahan
Kerikil (Maksimum 30 mm) kg 1029.000 Rp 277.78 Rp 285,833.33
Air ltr 215.000 Rp 50.00 Rp 10,750.00
Jumlah Harga Bahan Rp 813,760.48
Pekerja Org/Hr 1.650 Rp 97,500.00 Rp 160,875.00
Tukang Batu Org/Hr 0.275 Rp 110,000.00 Rp 30,250.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.028 Rp 125,000.00 Rp 3,500.00
Mandor Org/Hr 0.083 Rp 120,000.00 Rp 9,960.00
Jumlah Harga Tenaga Kerja Rp 204,585.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 1,018,345.48
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 101,834.55
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 1,120,180.02
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN BETON
Pembesian Per 1 kg Besi Polos
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Besi Beton Polos kg 1.050 Rp 13,000.00 Rp 13,650.00
A. Bahan
Kawat Beton kg 0.015 Rp 22,400.00 Rp 336.00
Jumlah Harga Bahan Rp 13,986.00
Pekerja Org/Hr 0.007 Rp 97,500.00 Rp 682.50
Tukang Besi Org/Hr 0.007 Rp 110,000.00 Rp 770.00
B. Tenaga Kerja
Kepala Tukang Org/Hr 0.001 Rp 125,000.00 Rp 87.50
Mandor Org/Hr 0.000 Rp 120,000.00 Rp 48.00
Jumlah Harga Tenaga Kerja Rp 1,588.00
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 15,574.00
E. Over Head & Profit (Maksimum 15%) 10% x D Rp 1,557.40
F. HARGA SATUAN PEKERJAAN PER- Kg ( D + E ) Rp 17,131.40
1 Bh Saklar Tunggal
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A.BAHAN Saklar tunggal 1.000 bh Rp 22,886.60 Rp 22,887.00
JUMLAH HARGA SATUAN Rp 22,887.00
B. UPAH KERJA Ongkos Pasang Saklar 0.350 bh Rp 22,886.60 Rp 8,010.00
JUM LAH HARGA TENAGA KERJA Rp 8,010.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 30,897.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 3,089.70
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 33,986.70
1 Bh Saklar Ganda
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A.BAHAN Saklar ganda 2 gang 1.000 bh Rp 34,113.60 Rp 34,114.00
JUMLAH HARGA SATUAN Rp 34,114.00
B. UPAH KERJA Ongkos Pasang Saklar 0.350 bh Rp 34,113.60 Rp 11,940.00
JUM LAH HARGA TENAGA KERJA Rp 11,940.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 46,054.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 4,605.40
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 50,659.40
1 Bh Stop Kontak
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
A.BAHAN stop kontak 1 phase 1.000 bh Rp 28,551.60 Rp 28,552.00
JUMLAH HARGA SATUAN Rp 28,552.00
B. UPAH KERJA Ongkos Pasang Stop Kontak 1.000 bh Rp 5,000.00 Rp 5,000.00
JUM LAH HARGA TENAGA KERJA Rp 5,000.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 33,552.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 3,355.20
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 36,907.20
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
PEKERJAAN PLAMBING
Pipa PVC AW Diameter 1/2 " / m'
KEBUTUHAN KODE INDEKS SATUAN HARGA BAHAN JUMLAH HARGA
Pipa PVC AW Dia 1/2 " 1.200 m' Rp 5,000.00 Rp 6,000.00
A. BAHAN
Perlengkapan dari harga pipa 35.000 % Rp 5,000.00 Rp 1,750.00
JUMLAH HARGA SATUAN Rp 7,750.00
Pekerja 0.036 Oh Rp 97,500.00 Rp 3,510.00
Tukang batu 0.060 Oh Rp 110,000.00 Rp 6,600.00
B. TENAGA KERJA
Kepala tukang 0.006 Oh Rp 125,000.00 Rp 750.00
Mandor 0.002 Oh Rp 120,000.00 Rp 216.00
JUM LAH HARGA TENAGA KERJA Rp 11,076.00
C. PERLATAN - - -
JUMLAH HARGA PERALATAN Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 18,826.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,882.60
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 20,708.60
Mengecat 1 m2 Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Indoor
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Plamir kg 0.1000 Rp 3,500.00 350.00
A.Bahan Cat Dasar kg 0.1000 Rp 16,810.00 1,681.00
Cat Penutup 2x kg 0.2600 Rp 27,500.00 7,150.00
Jumlah Harga Bahan 9,181.00
Pekerja Org/Hr 0.0200 Rp 97,500.00 1,950.00
Tukang Cat Org/Hr 0.0630 Rp 110,000.00 6,930.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0063 Rp 125,000.00 787.50
Mandor Org/Hr 0.0030 Rp 120,000.00 360.00
Jumlah Harga Tenaga Kerja 10,027.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 19,208.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 1,920.85
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 21,129.35
Mengecat 1 m2 Tembok Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup) Outdoor
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Plamir kg 0.1000 Rp 3,500.00
A.Bahan Cat Dasar kg 0.1000 Rp 16,810.00 1,681.00
Cat Wathershield kg 0.2600 Rp 50,000.00 13,000.00
Jumlah Harga Bahan 14,681.00
Pekerja Org/Hr 0.0200 Rp 97,500.00 1,950.00
Tukang Cat Org/Hr 0.0630 Rp 110,000.00 6,930.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0063 Rp 125,000.00 787.50
Mandor Org/Hr 0.0030 Rp 120,000.00 360.00
Jumlah Harga Tenaga Kerja 10,027.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 24,708.50
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 2,470.85
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 27,179.35
Mengecat 1 m2 Plafond Baru (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
KEBUTUHAN KODE SAT INDEKS HARGA BAHAN / UPAH JUMLAH HARGA
Plamir kg 0.1000 Rp 3,500.00 350.00
Cat Dasar kg 0.1500 Rp 16,810.00 2,521.50
A.Bahan
Cat Penutup kg 0.1800 Rp 27,500.00 4,950.00
Jumlah Harga Bahan 7,821.50
Pekerja Org/Hr 0.0800 Rp 97,500.00 7,800.00
Tukang Cat Org/Hr 0.0600 Rp 110,000.00 6,600.00
B.Tenaga Kerja
Kepala Tukang Org/Hr 0.0063 Rp 125,000.00 787.50
Mandor Org/Hr 0.0040 Rp 120,000.00 480.00
Jumlah Harga Tenaga Kerja 15,667.50
C. Peralatan
Jumlah Harga Peralatan Rp -
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A+B+G) Rp 23,489.00
E. OVERHEAD + PROFIT ( Maksimum 15 % ) 10% x D Rp 2,348.90
F. HARGA SATUAN PEKERJAAN PER- M2 ( D + E ) Rp 25,837.90
SATUAN /
NO JENIS BARANG / JASA HARGA SATUAN
UNIT
BAHAN KABEL
. Kabel NYM 2x2.5 mm m' Rp 5,665.00
. Kabel NYM 2x3.5 mm m' Rp 9,630.50
. Kabel NYY 2 x 1,5 mm Roll Rp 600,716.60
. Kabel NYY 2 x2,5 mm Roll Rp 812,587.60
. Kabel NYY 2 x 4 mm Roll Rp 340,126.60
. Kabel NYFGBY 4 x 10 mm m' Rp 79,310.00
. Kabel NYY 4 x 25 mm m' Rp 160,680.00
. Kabel NYFGBY 4 x 25 mm m' Rp 180,250.00
. Kawat BC 70 mm m' Rp 77,250.00
. Kawat BC 50 mm m' Rp 56,650.00
. Kawat BC 10 mm m' Rp 17,510.00
. Tray Kabel 300 x 100 mm lengkap dengan asesories m' Rp 360,500.00
. Tray Kabel 200 x 100 mm lengkap dengan asesories m' Rp 257,500.00
Terbilang:
ENAM RATUS JUTA RUPIAH
Watansoppeng, 2017
Terbilang: EMPAT RATUS SEMBILAN PULUH SEMBILAN JUTA ENAM RATUS TUJUH PULUH TIGA RIBU
RUPIAH
Terbilang: DUA RATUS EMPAT PULUH SEMBILAN JUTA ENAM RATUS EMPAT PULUH TUJUH RIBU
RUPIAH