Anda di halaman 1dari 5

RINCIAN ANGGARAN PURNAMA ANGGREK 4

NO URAIAN PEKERJAAN
Pekerjaan
VOLUME SATUAN / VOLUME HARGA SATUAN SPESIFIKASI
A LANTAI 1

1 Pintu Sliding 1 Unit IDR 4,680,000.00 5 mm

2 Jendela Buka 3 1 Unit IDR 5,700,000.00 8 mm

3 Jendela Dapur Buka 3 1 Unit IDR 1,825,000.00 5 mm


LANTAI 2
B.

1 Pintu Sliding Void 1 Unit IDR 6,700,000.00 8 mm

2 Jendela Kamar Buka 2 1 Unit IDR 1,986,000.00 5mm

3 Jendela Kamar Buka 1 1 Unit IDR 972,000.00 5 mm

4 Jendela Kamar Buka 3 1 Unit IDR 4,275,000.00 8 mm

5 Jendela Bawah Meja Buka 3 1 Unit IDR 2,916,000.00 5 mm

6 Pintu sliding kamar utama buka 2 1 Unit IDR 6,700,000.00 8 mm

7 Jendela Wc Kamar anak 1 Unit IDR 600,000.00 5 mm

8 Jendela Wc Kamar Utama 1 Unit IDR 600,000.00 5 mm


C. LANTAI 3

1 Jendela Lantai Buka 1 1 Unit IDR 999,000.00 5 mm

2 Jendela Lantai Buka 2 1 Unit IDR 1,165,000.00 5 mm


D

1 Relling Tangga Lt 1 ke Lt2 14.95 IDR 850,000.00 IDR 12,707,500.00 8 mm


2 Relling Tangga Lt 2 ke Lt 3 7.7 IDR 850,000.00 IDR 6,545,000.00 8 mm

E KERJAAN TAMBAHAN

1 Meja Wastafel Kamar Utama 1.2 IDR 1,800,000.00 IDR 2,160,000.00


2 Meja Wastafel Kamar Anak 2 IDR 1,800,000.00 IDR 3,600,000.00
3 Pintu Gudang Lantai 1 Buka 1 1 Unit IDR 2,800,000.00 5 mm
4 Jendela Gudang Buka 2 Lt 1 Unit IDR 1,986,000.00 5 mm
5 Topi Topi Pintu Sliiding 4 IDR 350,000.00 IDR 1,400,000.00

TOTAL SUB PEKERJAAN IDR 70,316,500.00


PEMBUATAN MEJA LESEHAN

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0.150 135,000.00 20,250.00
Tukang Kayu L.03 OH 0.050 135,000.00 6,750.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.010 165,000.00 1,650.00
JUMLAH TENAGA KERJA 30,250.00
B BAHAN
Kayu Multiplek 9 mm Kpg 0.2 180000 36,000.00
Kayu Reng 4x6 Btg 0.3 18000 5,760.00
Amplas 100 Kotak 0.1 100000 10,000.00
Amplas 400 Kotak 0.1 100000 10,000.00
Sekrup Gypsum 1,5" Kotak 0.1 70000 7,000.00
Isi Paku Tembak Kotak 0.1 65000 6,500.00
Lem Fox Putih Unit 0.5 22,000.00 9,900.00
JUMLAH HARGA BAHAN 85,160.00
C FINISHING
Cat Vernish 0.5 72000 36,000.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 151,410.00
E Overhead & Provit 10% x D 15,141.00

F Harga Satuan Pekerjaan ( D + E ) w

PEMBUATAN MEJA LIPAT JATI BELANDA

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0.200 135,000.00 27,000.00
Tukang Kayu L.03 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.010 165,000.00 1,650.00
JUMLAH TENAGA KERJA 43,750.00
B BAHAN
Kayu Jati Belanda Btg 4.5 18000 81,000.00
Kayu Balok Jati Belanda Btg 1.5 27000 40,500.00
Amplas 100 Kotak 0.1 100000 10,000.00
Amplas 400 Kotak 0.1 100000 10,000.00
Sekrup Gypsum 1,5" Kotak 0.1 70000 7,000.00
Isi Paku Tembak Kotak 0.1 65000 6,500.00
Lem Fox Putih Unit 0.5 22,000.00 11,000.00
Lem Korea Bh 0.5 10,000.00 5,000.00
JUMLAH HARGA BAHAN 171,000.00
C FINISHING
Cat Vernish 0.5 72000 36,000.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 250,750.00
E Overhead & Provit 15% x D 25,075.00
F Harga Satuan Pekerjaan ( D + E ) 275,825.00

PEMBUATAN MEJA LIPAT KAYU PAPAN DURIAN


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0.150 135,000.00 20,250.00
Tukang Kayu L.03 OH 0.050 135,000.00 6,750.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.010 165,000.00 1,650.00
JUMLAH TENAGA KERJA 30,250.00
B BAHAN
Kayu Durian Btg 0.6 93000 51,150.00
Kayu Reng 4x6 Btg 0.3 18000 5,760.00
Amplas 100 Kotak 0.1 100000 10,000.00
Amplas 400 Kotak 0.1 100000 10,000.00
Sekrup Gypsum 1,5" Kotak 0.1 70000 7,000.00
Isi Paku Tembak Kotak 0.1 65000 6,500.00
Lem Fox Putih Unit 0.5 22,000.00 11,000.00
JUMLAH HARGA BAHAN 101,410.00
C FINISHING
Cat Vernish 0.5 72000 36,000.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 167,660.00
E Overhead & Provit 15% x D 16,766.00
F Harga Satuan Pekerjaan ( D + E ) 184,426.00
PEMBUATAN MEJA LIPAT KAYU KARET

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0.300 135,000.00 40,500.00
Tukang Kayu L.03 OH 0.050 135,000.00 6,750.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.010 165,000.00 1,650.00
JUMLAH TENAGA KERJA 50,500.00
B BAHAN
Kayu Karet Kpg 0.3 180000 54,000.00
Kayu Reng 4x6 Btg 0.5 18000 8,280.00
Kayu Bulat Btg 0.3 18000 4,500.00
Amplas 100 Kotak 0.1 100000 10,000.00
Amplas 400 Kotak 0.1 100000 10,000.00
Besi 6" Btg 0.2 32000 5,760.00
Sekrup Gypsum 1,5" Kotak 0.1 70000 7,000.00
Isi Paku Tembak Kotak 0.1 65000 6,500.00
Lem Fox Putih Unit 0.5 22,000.00 11,000.00
JUMLAH HARGA BAHAN 117,040.00
C FINISHING
Cat Vernish 0.5 72000 36,000.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 203,540.00
E Overhead & Provit 15% x D 16,283.20

F Harga Satuan Pekerjaan ( D + E ) 219,823.20

PEMBUATAN MEJA LIPAT JATI BELANDA

No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0.300 135,000.00 40,500.00
Tukang Kayu L.03 OH 0.050 135,000.00 6,750.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.010 165,000.00 1,650.00
JUMLAH TENAGA KERJA 50,500.00
B BAHAN
Kayu Jati Belanda Btg 7.0 18000 126,000.00
Kayu Balok Jati Belanda Btg 2.5 27000 67,500.00
Kayu Bulat Btg 0.3 18000 4,500.00
Amplas 100 Kotak 0.1 100000 10,000.00
Amplas 400 Kotak 0.1 100000 10,000.00
Sekrup Gypsum 1,5" Kotak 0.1 70000 7,000.00
Isi Paku Tembak Kotak 0.1 65000 6,500.00
Lem Fox Putih Unit 0.5 22,000.00 11,000.00
Besi 6" Btg 0.2 32,000.00 5,760.00
Lem Korea Bh 0.5 10,000.00 5,000.00
JUMLAH HARGA BAHAN 253,260.00
C FINISHING
Cat Vernish 0.5 72000 36,000.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 339,760.00
E Overhead & Provit 15% x D 23,783.20
F Harga Satuan Pekerjaan ( D + E ) 363,543.20

PEMBUATAN MEJA LIPAT KAYU PAPAN DURIAN


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01 OH 0.350 135,000.00 47,250.00
Tukang Kayu L.03 OH 0.100 135,000.00 13,500.00
Kepala tukang L.03 OH 0.010 160,000.00 1,600.00
Mandor L.04 OH 0.010 165,000.00 1,650.00
JUMLAH TENAGA KERJA 64,000.00
B BAHAN
Kayu Durian Btg 0.6 93000 55,800.00
Kayu Reng 4x6 Btg 0.4 18000 7,560.00
Kayu Bulat Btg 0.3 18000 4,500.00
Amplas 100 Kotak 0.1 100000 10,000.00
Amplas 400 Kotak 0.1 100000 10,000.00
Sekrup Gypsum 1,5" Kotak 0.1 70000 7,000.00
Isi Paku Tembak Kotak 0.1 65000 6,500.00
Lem Fox Putih Unit 0.5 22,000.00 11,000.00
JUMLAH HARGA BAHAN 112,360.00
C FINISHING
Cat Vernish 0.5 72000 36,000.00
JUMLAH HARGA ALAT
D Jumlah (A + B + C) 212,360.00
E Overhead & Provit 15% x D 10,618.00
F Harga Satuan Pekerjaan ( D + E ) 222,978.00

Anda mungkin juga menyukai