II Pekerjaan Pondasi
1 Balok ulin 10x10 batang 8 Rp240,000
2 Paku ulin kg 1 Rp30,000
3 Gergaji buah 2 Rp55,000
IV Pekerjaan Lantai
Teras
1 Kayu meranti batang 1 Rp25,000
2 Papan meranti lembar 3 Rp35,000
3 Paku reng kg 0,5 Rp25,000
Ruangan
1 Kayu meranti batang 3 Rp25,000
2 Papan meranti batang 13 Rp35,000
3 Paku reng kg 1 Rp25,000
VI Pekerjaan Listrik
1 Lampu 14 watt buah 2 Rp30,000
2 Stop Kontak buah 1 Rp15,000
3 Saklar buah 2 Rp15,000
4 Fitting buah 2 Rp5,000
5 Kabel (100 m) roll 1 Rp200,000
IX Pekerjaan Finishing
1 Karpet m 25 Rp20,000
2 Jam dinding buah 1 Rp75,000
X Gaji Pekerja
1 Tukang hari/orang 5 Rp100,000
2 Pembantu tukang hari/orang 5 Rp65,000
3 Uang makan pekerja hari/2 orang 5 Rp20,000
JUMLAH HARGA
SATUAN
Rp50,000
Rp10,000
Rp60,000
Rp1,920,000
Rp30,000
Rp110,000
Rp2,060,000
Rp1,995,000
Rp50,000
Rp1,000,000
Rp3,045,000
Rp25,000
Rp105,000
Rp12,500
Rp142,500
Rp75,000
Rp455,000
Rp25,000
Rp555,000
Rp697,500
Rp3,300,000
Rp1,680,000
Rp175,000
Rp125,000
Rp25,000
Rp25,000
Rp25,000
Rp5,355,000
Rp60,000
Rp15,000
Rp30,000
Rp10,000
Rp200,000
Rp315,000
Rp600,000
Rp200,000
Rp45,000
Rp25,000
Rp870,000
Rp15,000
Rp30,000
Rp300,000
Rp65,000
Rp410,000
Rp500,000
Rp75,000
Rp575,000
Rp500,000
Rp325,000
Rp100,000
Rp925,000
Rp14,312,500
Rp1,431,250
Rp15,743,750