Anda di halaman 1dari 21

REKAP PENAWARAN HARGA

PROYEK : RUKO HIDAYATULLAH


OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEKERJAAN
I PEK. PANCANG Rp. 646,840,000
II PEK. LANTAI SATU Rp. 1,158,705,997
III PEK. LANTAI DUA Rp. 1,538,923,910
IV PEK. LANTAI TIGA Rp. 1,411,614,421
V PEK. LANTAI EMPAT Rp. 1,335,852,721
VI PEK. LANTAI LIMA Rp. 1,317,739,648
VII PEK. LANTAI ATAP Rp. 401,330,442

SUB TOTAL Rp. 7,164,167,140


RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI SATU

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PEK. PONDASI ATAU PEMANCANGAN
1 Pondasi Dalam (Hydraulik Pile dia 250 mm)
Mob Demob Alat Pancang Ls 1.00 Rp 25,000,000 Rp 25,000,000
Mini Pile dia 250 x 250 mm ex Asumsi 24 m m 2088.00 Rp 250,000 Rp 522,000,000
Pemancangan Tiang m 2088.00 Rp 45,000 Rp 93,960,000
Bobok Kepala Tiang Pancang Titik 84.00 Rp 70,000 Rp 5,880,000

SUB TOTAL PEK. LAIN - LAIN 646,840,000


REKAP PENAWARAN HARGA
PROYEK : RUKO HIDAYATULLAH
OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEK. LANTAI 1


I. PEK. BETON BERTULANG Rp. 747,678,363
II. PEK. DINDING Rp. 162,932,368
III. PEK. LANTAI & DINDING KERAMIK Rp. 40,467,937
IV. PEK. KUSEN PINTU & JENDELA Rp. 24,801,488
V. PEK. PLAFOND Rp. 28,933,429
VI. PEK. CAT Rp. 56,928,080
VII. PEK. TANGGA Rp. 16,512,279
VIII. PEK. MEKANIKAL & ELETRIKAL Rp. 24,221,564
IX. PEK. SANITARY Rp. 5,490,492
IX. PEK. LAIN - LAIN Rp. 50,739,998

Rp. 1,158,705,997
RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI SATU

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PEK. TANAH
1 Galian pondasi m3 44.41 46,000 Rp 2,042,688
2 Pasir Urug kembali m3 12.76 22,050 Rp 281,452
3 Buang tanah bekas galian m3 44.41 12,660 Rp 562,183
4 Pasir urug Pemadatan t = 100 mm m3 24.45 57,500 Rp 1,405,594
5 Lantai kerja t = 50 mm m3 1.27 147,810 Rp 187,534
6 urugan lokasi m3 161.43 139,510 Rp 22,520,485

A.II PONDASI FOOT PLAT


1 Pile Cap P1 Uk. 175x125x50 cm
Beton K 300 m3 4.38 1,671,060 Rp 7,310,888
Besi D19 - 10 kg 994.58 12,030 Rp 11,964,797
Bekisting m2 12.00 187,670 Rp 2,252,040

2 Pile Cap P2 Uk. 175x75x40 cm


Beton K 300 m3 1.58 1,671,060 Rp 2,631,920
Besi D19 - 10 kg 451.58 12,030 Rp 5,432,447
Bekisting m2 6.00 187,670 Rp 1,126,020

3 Pile Cap P3 Uk. 175x125x50 cm


Beton K 300 m3 4.38 1,671,060 Rp 7,310,888
Besi D19 - 10 kg 994.58 12,030 Rp 11,964,797
Bekisting m2 12.00 187,670 Rp 2,252,040

4 Pile Cap P4 Uk. 175x75x40 cm


Beton K 300 m3 1.58 1,671,060 Rp 2,631,920
Besi D19 - 10 kg 451.58 12,030 Rp 5,432,447
Bekisting m2 6.00 187,670 Rp 1,126,020

A.III KOLOM PEDESTAL


1 Kolom Uk. 500 x 500
Beton K 300 m3 10.63 1,671,060 Rp 17,755,013
Besi D19 kg 1538.70 12,030 Rp 18,510,561
Besi Ø 10 Sengkang kg 472.01 12,030 Rp 5,678,220
Bekisting multiplek 9 mm m2 10.63 362,210 Rp 3,848,481

2 Kolom Sayap Pada P1 dan P3


Beton K 300 m3 10.63 1,671,060 Rp 17,755,013
Besi D19 kg 205.16 12,030 Rp 2,468,075
Bekisting multiplek 9 mm m2 10.63 362,210 Rp 3,848,481

A.IV SLOOF
1 SLOOF S1 Uk. 300 x 500
Beton K 300 m3 27.27 1,671,060 Rp 45,564,793
Besi D 19 kg 4053.69 12,030 Rp 48,765,939
Besi Ø 10 kg 224.32 12,030 Rp 2,698,528
Besi Ø 8 Sengkang kg 992.52 12,030 Rp 11,940,001
Bekisting batako m2 181.78 202,420 Rp 36,795,908

2 SLOOF S2 Uk. 150 x 200


Beton K 300 m3 0.06 1,671,060 Rp 100,264
Besi Ø 12 kg 14.21 12,030 Rp 170,922
Besi Ø 10 Sengkang kg 6.20 12,030 Rp 74,586
Bekisting batako m2 0.80 202,420 Rp 161,936
A.V PLAT LANTAI
1 Beton K 300 m3 27.53 1,671,060 Rp 46,011,207
Besi Ø 10 Kg 1584.04 12,030 Rp 19,056,047
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI SATU

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
Besi Ø 8 Kg 158.43 12,030 Rp 1,905,956
2 Plastik Cor m2 244.45 7,700 Rp 1,882,274

A.VI PEKERJAAN KONSTRUKSI BAJA

1 Kolom K2
Kolom WF Uk. 400 x 400 x 13 x 21 Kg 15050.00 20,000 Rp 301,000,000
Stel & pasang angkur (1 titik 10 angkur 19 mm panjang 500 mm) Titik 250.00 70,000 Rp 17,500,000
Baut HTB Ø 22 Kolom Buah 250.00 35,000 Rp 8,750,000
Cat WF m2 140.00 50,000 Rp 7,000,000

2 Mob Demob anggota dan peralatan kerja Ls 1.00 40,000,000 Rp 40,000,000

SUB TOTAL PEK. PONDASI Rp 747,678,363


B. PEK. DINDING
1 Pas. Dinding bata ringan uk. 100x200x600 m2 474.80 172,200 Rp 81,760,560
2 Plesteran 1 : 5 m2 949.60 51,380 Rp 48,790,448
3 Acian m2 949.60 34,100 Rp 32,381,360

SUB TOTAL PEK. DINDING Rp 162,932,368


C. PEK. LANTAI & DINDING KERAMIK
1 Pas. Keramik 40x40 setara Roman m2 240.45 127,290 Rp 30,607,033
2 Plint Lantai uk. 15 x 60 ( Unpolished ) m1 159.36 41,900 Rp 6,677,184
3 Pas Keramik Lantai Kamar Mandi m2 4.00 137,290 Rp 549,160
4 Pas Keramik Dinding Kamar Mandi M2 16.00 164,660 Rp 2,634,560

SUB TOTAL PEK. LANTAI Rp 40,467,937


D. PEK. KUSEN PINTU & JENDELA
1 Pintu Harmonika m2 19.60 616,180 Rp 12,077,128
2 Pintu Kamar Solid Wood unit 4.00 2,000,000 Rp 8,000,000
3 Pintu Kamar Mandi unit 2.00 750,000 Rp 1,500,000
4 Jendela + Kusen Alumunium Unit 2.00 1,612,180 Rp 3,224,360

SUB TOTAL PEK. KUSEN PINTU & JENDELA Rp 24,801,488


E. PEK. PLAFOND
1 Pasangan Gypsumboard 9 mm m2 240.45 105,040 Rp 25,256,994
2 List Gypsum Plafond m 159.36 23,070 Rp 3,676,435

SUB TOTAL PEK. PLAFOND Rp 28,933,429


F. PEK. CAT
1 Cat dinding interior Ex Vinilex m2 668.80 44,960 Rp 30,069,248
2 Cat dinding exterior Ex Vinilex m2 312.16 51,410 Rp 16,048,146
3 Cat Plafond m2 240.45 44,960 Rp 10,810,686

SUB TOTAL PEK. CAT Rp 56,928,080


G. PEK. TANGGA
1 Beton K 300 m3 1.57 1,671,060 Rp 2,622,227
2 Besi Ø 12 kg 144.60 12,030 Rp 1,739,482
3 Besi Ø 10 kg 51.05 12,030 Rp 614,091
4 Bekisting Multiplek 9 mm m2 9.49 338,460 Rp 3,212,662
5 Pas. Keramik ( Pholised ) Untred m2 6.40 127,290 Rp 814,656
6 Pas. Keramik ( Pholised ) Optred m2 4.00 127,290 Rp 509,160
7 Reilling Tangga, Rangka Stainless, Hand Reilling kayu bengkirai m1 7.00 1,000,000 Rp 7,000,000
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI SATU

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
SUB TOTAL PEK. TANGGA Rp 16,512,279
H. PEK. MEKANIKAL & ELETRIKAL
1 Instalasi pipa air bersih 1/2 " + Fitting m1 46.02 28,400 Rp 1,306,968
2 Instalasi pipa air kotor 4" ke septick tank m1 5.00 170,980 Rp 854,900
3 Instalasi pipa air bekas 3" ke saluran m1 88.36 112,260 Rp 9,919,294
4 Instalasi pipa ke TORN 1 1/2 " + Fitting m1 4.00 55,740 Rp 222,960
5 Instalasi pipa air hujan 3" + Fitting m1 4.00 112,260 Rp 449,040
6 Fitting dan material bantu ls 1.00 1,100,000 Rp 1,100,000
7 Instalasi lampu penerangan ttk 13.00 260,403 Rp 3,385,239
8 Instalasi stop kontak ttk 6.00 281,853 Rp 1,691,118
9 Instalasi saklar ttk 10.00 69,355 Rp 693,550
10 Lampu TL 2x20 Watt bh 4.00 505,505 Rp 2,022,020
11 Lampu XL 10 watt bh 9.00 69,355 Rp 624,195
12 Saklar Tunggal bh 6.00 40,755 Rp 244,530
13 Saklar Ganda bh 4.00 69,355 Rp 277,420
14 Stop kontak bh 6.00 55,055 Rp 330,330
15 Box Sekring ls 1.00 1,100,000 Rp 1,100,000
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL Rp 24,221,564
I. PEK. SANITARY
1 Closet Duduk unit 2.00 1,959,670 Rp 3,919,340
2 Jet washer unit 2.00 29,711 Rp 59,422
3 Kran Buah 2.00 59,060 Rp 118,120
4 Floor Drain Buah 2.00 87,450 Rp 174,900
5 Wastafel + kran unit 1.00 1,218,710 Rp 1,218,710

SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL Rp 5,490,492


J. PEK. LAIN - LAIN
1 Bor air kedalam ± 20 meter + pipa & accessories ls 1.00 5,000,000 Rp 5,000,000
2 Pompa air ex. Sanyo ( Otomatis ) unit 1.00 7,500,000 Rp 7,500,000
3 Bak kontrol rumah pompa unit 1.00 550,000 Rp 550,000
4 Septik Tank unit 1.00 15,000,000 Rp 15,000,000
5 Kran Luar bh 2.00 59,060 Rp 118,120
6 Pekerjaan Paving Halaman parkir m2 78.40 201,270 Rp 15,779,568
7 Bak Kontrol Pembuangan unit 2.00 599,700 Rp 1,199,400
8 Sumur Resapan Air Hujan unit 1.00 765,730 Rp 765,730
9 Pipa PVC 3" ke Saluran m 11.00 112,260 Rp 1,234,860
10 Pipa PVC 3" air hujan m 32.00 112,260 Rp 3,592,320
SUB TOTAL PEK. LAIN - LAIN Rp 50,739,998
REKAP PENAWARAN HARGA
PROYEK : RUKO HIDAYATULLAH
OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEK. LANTAI 2


I. PEK. BETON BERTULANG Rp. 1,178,432,501
II. PEK. DINDING Rp. 177,372,541
III. PEK. LANTAI & DINDING KERAMIK Rp. 41,488,621
IV. PEK. KUSEN PINTU & JENDELA Rp. 11,421,450
V. PEK. PLAFOND Rp. 29,495,414
VI. PEK. CAT Rp. 52,072,400
VII. PEK. TANGGA Rp. 16,512,279
VIII. PEK. MEKANIKAL & ELETRIKAL Rp. 18,763,494
IX. PEK. SANITARY Rp. 2,252,661
IX. PEK. LAIN - LAIN Rp. 11,112,549

Rp. 1,538,923,910
RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI DUA

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PLAT LANTAI -
1 Beton K 300 m3 27.53 1,671,060 Rp 46,011,207
Besi Ø 10 Kg 1584.04 12,030 Rp 19,056,047
Besi Ø 8 Kg 158.43 12,030 Rp 1,905,956
2 Pemasangan Bondek m2 229.45 165,000 Rp 37,859,448
-
A.II PEKERJAAN KONSTRUKSI BAJA -
-
1 Kolom K2
Kolom WF Uk. 400 x 400 x 13 x 21 Kg 17200.00 20,000 Rp 344,000,000
Baut HTB Ø 22 Kolom Buah 250.00 35,000 Rp 8,750,000
Cat WF m2 160.00 50,000 Rp 8,000,000

2 Balok B1
Balok Induk WF Uk. 350 x 350 x 12 x 19 Kg 25383.36 20,000 Rp 507,667,200
Baut HTB Ø 22 Sambungan Kolom dengan WF Buah 1920.00 35,000 Rp 67,200,000
Plat Penahan 12 mm Kg 810.69 35,000 Rp 28,374,092
Cat WF m2 259.39 50,000 Rp 12,969,600
-
3 Balok B2
Balok Anak WF Uk. 175 x 175 x 7,5 x 11 Kg 2297.14 20,000 Rp 45,942,880
Baut HTB Ø 10 Sambungan Balok Anak dengan Balok Induk Buah 568.00 70,000 Rp 39,760,000
Plat Penahan 12 mm Kg 255.60 35,000 Rp 8,945,972
Cat WF m2 39.80 50,000 Rp 1,990,100
-
SUB TOTAL PEK. PONDASI - Rp 1,178,432,501
B. PEK. DINDING -
1 Pas. Dinding bata ringan uk. 100x200x600 m2 516.88 172,200 Rp 89,006,736
2 Plesteran 1 : 5 m2 1033.76 51,380 Rp 53,114,589
3 Acian m2 1033.76 34,100 Rp 35,251,216
-
SUB TOTAL PEK. DINDING - Rp 177,372,541
C. PEK. LANTAI & DINDING KERAMIK -
1 Pas. Keramik 40x40 setara Roman m2 240.45 127,290 Rp 30,607,033
2 Plint Lantai uk. 15 x 60 ( Unpolished ) m1 183.72 41,900 Rp 7,697,868
3 Pas Keramik Lantai Kamar Mandi m2 4.00 137,290 Rp 549,160
4 Pas Keramik Dinding Kamar Mandi M2 16.00 164,660 Rp 2,634,560
-
SUB TOTAL PEK. LANTAI - Rp 41,488,621
D. PEK. KUSEN PINTU & JENDELA -
1 Pintu Kamar Solid Wood unit 5.00 2,000,000 Rp 10,000,000
2 Pintu Kamar Mandi unit 1.00 750,000 Rp 750,000
3 Jendela + Kusen Alumunium Unit 5.00 134,290 Rp 671,450
-
SUB TOTAL PEK. KUSEN PINTU & JENDELA - Rp 11,421,450
E. PEK. PLAFOND -
1 Pasangan Gypsumboard 9 mm m2 240.45 105,040 Rp 25,256,994
2 List Gypsum Plafond m 183.72 23,070 Rp 4,238,420
-
SUB TOTAL PEK. PLAFOND - Rp 29,495,414
F. PEK. CAT -
1 Cat dinding interior Ex Vinilex m2 560.80 44,960 Rp 25,213,568
2 Cat dinding exterior Ex Vinilex m2 312.16 51,410 Rp 16,048,146
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI DUA

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
3 Cat Plafond m2 240.45 44,960 Rp 10,810,686
-
SUB TOTAL PEK. CAT - Rp 52,072,400
G. PEK. TANGGA -
1 Beton K 300 m3 1.57 1,671,060 Rp 2,622,227
2 Besi Ø 12 kg 144.60 12,030 Rp 1,739,482
3 Besi Ø 10 kg 51.05 12,030 Rp 614,091
4 Bekisting Multiplek 9 mm m2 9.49 338,460 Rp 3,212,662
5 Pas. Keramik ( Pholised ) Untred m2 6.40 127,290 Rp 814,656
6 Pas. Keramik ( Pholised ) Optred m2 4.00 127,290 Rp 509,160
7 Reilling Tangga, Rangka Stainless, Hand Reilling kayu bengkirai m1 7.00 1,000,000 Rp 7,000,000
-
SUB TOTAL PEK. TANGGA - Rp 16,512,279
H. PEK. MEKANIKAL & ELETRIKAL -
1 Instalasi pipa air bersih 1/2 " + Fitting m1 13.84 28,400 Rp 393,056
2 Instalasi pipa air kotor 4" ke septick tank m1 5.00 170,980 Rp 854,900
3 Instalasi pipa air bekas 3" ke saluran m1 11.00 112,260 Rp 1,234,860
4 Instalasi pipa ke TORN 1 1/2 " + Fitting m1 4.00 55,740 Rp 222,960
5 Instalasi pipa air hujan 3" + Fitting m1 32.00 112,260 Rp 3,592,320
6 Fitting dan material bantu ls 1.00 1,100,000 Rp 1,100,000
7 Instalasi lampu penerangan ttk 10.00 260,403 Rp 2,604,030
8 Instalasi stop kontak ttk 6.00 281,853 Rp 1,691,118
9 Instalasi saklar ttk 10.00 281,853 Rp 2,818,530
10 Lampu TL 2x20 Watt bh 4.00 505,505 Rp 2,022,020
11 Lampu XL 10 watt bh 6.00 69,355 Rp 416,130
12 Saklar Tunggal bh 6.00 40,755 Rp 244,530
13 Saklar Ganda bh 2.00 69,355 Rp 138,710
14 Stop kontak bh 6.00 55,055 Rp 330,330
15 Box Sekring ls 1.00 1,100,000 Rp 1,100,000
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 18,763,494
I. PEK. SANITARY
1 Closet Duduk unit 1.00 1,959,670 Rp 1,959,670
2 Jet washer unit 1.00 29,711 Rp 29,711
3 Kran Buah 1.00 59,060 Rp 59,060
4 Floor Drain Buah 1.00 87,450 Rp 87,450
5 Kitchen Zink + kran unit 1.00 116,770 Rp 116,770
-
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 2,252,661
J. PEK. LAIN - LAIN -
1 Meja Dapur m2 6.65 1,671,060 Rp 11,112,549

SUB TOTAL PEK. LAIN - LAIN Rp 11,112,549


REKAP PENAWARAN HARGA
PROYEK : RUKO HIDAYATULLAH
OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEK. LANTAI 3


I. PEK. BETON BERTULANG Rp. 1,158,552,501
II. PEK. DINDING Rp. 112,611,386
III. PEK. LANTAI & DINDING KERAMIK Rp. 37,060,629
IV. PEK. KUSEN PINTU & JENDELA Rp. 1,152,870
V. PEK. PLAFOND Rp. 27,057,377
VI. PEK. CAT Rp. 40,893,545
VII. PEK. TANGGA Rp. 16,512,279
VIII. PEK. MEKANIKAL & ELETRIKAL Rp. 15,637,943
IX. PEK. SANITARY Rp. 2,135,891

Rp. 1,411,614,421
RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI TIGA

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PLAT LANTAI -
1 Beton K 300 m3 27.53 1,671,060 Rp 46,011,207
Besi Ø 10 Kg 1584.04 12,030 Rp 19,056,047
Besi Ø 8 Kg 158.43 12,030 Rp 1,905,956
2 Pemasangan Bondek m2 229.45 165,000 Rp 37,859,448
-
A.II PEKERJAAN KONSTRUKSI BAJA -
-
1 Kolom K2
Kolom WF Uk. 400 x 400 x 13 x 21 Kg 17200.00 20,000 Rp 344,000,000
Baut HTB Ø 22 Kolom Buah 250.00 35,000 Rp 8,750,000
Cat WF m2 160.00 50,000 Rp 8,000,000

2 Balok B1
Balok Induk WF Uk. 350 x 350 x 12 x 19 Kg 25383.36 20,000 Rp 507,667,200
Baut HTB Ø 22 Sambungan Kolom dengan WF Buah 1920.00 35,000 Rp 67,200,000
Plat Penahan 12 mm Kg 810.69 35,000 Rp 28,374,092
Cat WF m2 259.39 50,000 Rp 12,969,600
-
3 Balok B2
Balok Anak WF Uk. 175 x 175 x 7,5 x 11 Kg 2297.14 20,000 Rp 45,942,880
Baut HTB Ø 10 Sambungan Balok Anak dengan Balok Induk Buah 568.00 35,000 Rp 19,880,000
Plat Penahan 12 mm Kg 255.60 35,000 Rp 8,945,972
Cat WF m2 39.80 50,000 Rp 1,990,100
-
SUB TOTAL PEK. PONDASI - Rp 1,158,552,501
B. PEK. DINDING -
1 Pas. Dinding bata ringan uk. 100x200x600 m2 328.16 172,200 Rp 56,509,152
2 Plesteran 1 : 5 m2 656.32 51,380 Rp 33,721,722
3 Acian m2 656.32 34,100 Rp 22,380,512
-
SUB TOTAL PEK. DINDING - Rp 112,611,386
C. PEK. LANTAI & DINDING KERAMIK -
1 Pas. Keramik 40x40 setara Roman m2 240.45 127,290 Rp 30,607,033
2 Plint Lantai uk. 15 x 60 ( Unpolished ) m1 78.04 41,900 Rp 3,269,876
3 Pas Keramik Lantai Kamar Mandi m2 4.00 137,290 Rp 549,160
4 Pas Keramik Dinding Kamar Mandi M2 16.00 164,660 Rp 2,634,560
-
SUB TOTAL PEK. LANTAI - Rp 37,060,629
D. PEK. KUSEN PINTU & JENDELA -
1 Pintu Kamar Mandi unit 1.00 750,000 Rp 750,000
2 Jendela + Kusen Alumunium Unit 3.00 134,290 Rp 402,870
-
SUB TOTAL PEK. KUSEN PINTU & JENDELA - Rp 1,152,870
E. PEK. PLAFOND -
1 Pasangan Gypsumboard 9 mm m2 240.45 105,040 Rp 25,256,994
2 List Gypsum Plafond m 78.04 23,070 Rp 1,800,383
-
SUB TOTAL PEK. PLAFOND - Rp 27,057,377
F. PEK. CAT -
1 Cat dinding interior Ex Vinilex m2 312.16 44,960 Rp 14,034,714
2 Cat dinding exterior Ex Vinilex m2 312.16 51,410 Rp 16,048,146
3 Cat Plafond m2 240.45 44,960 Rp 10,810,686
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI TIGA

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
-
SUB TOTAL PEK. CAT - Rp 40,893,545
G. PEK. TANGGA -
1 Beton K 300 m3 1.57 1,671,060 Rp 2,622,227
2 Besi Ø 12 kg 144.60 12,030 Rp 1,739,482
3 Besi Ø 10 kg 51.05 12,030 Rp 614,091
4 Bekisting Multiplek 9 mm m2 9.49 338,460 Rp 3,212,662
5 Pas. Keramik ( Pholised ) Untred m2 6.40 127,290 Rp 814,656
6 Pas. Keramik ( Pholised ) Optred m2 4.00 127,290 Rp 509,160
7 Reilling Tangga, Rangka Stainless, Hand Reilling kayu bengkirai m1 7.00 1,000,000 Rp 7,000,000
-
SUB TOTAL PEK. TANGGA - Rp 16,512,279
H. PEK. MEKANIKAL & ELETRIKAL -
1 Instalasi pipa air bersih 1/2 " + Fitting m1 13.84 28,400 Rp 393,056
2 Instalasi pipa air kotor 4" ke septick tank m1 5.00 170,980 Rp 854,900
3 Instalasi pipa air bekas 3" ke saluran m1 11.00 112,260 Rp 1,234,860
4 Instalasi pipa ke TORN 1 1/2 " + Fitting m1 4.00 55,740 Rp 222,960
5 Instalasi pipa air hujan 3" + Fitting m1 32.00 112,260 Rp 3,592,320
6 Fitting dan material bantu ls 1.00 1,100,000 Rp 1,100,000
7 Instalasi lampu penerangan ttk 6.00 260,403 Rp 1,562,418
8 Instalasi stop kontak ttk 2.00 281,853 Rp 563,706
9 Instalasi saklar ttk 6.00 281,853 Rp 1,691,118
10 Lampu TL 2x20 Watt bh 6.00 505,505 Rp 3,033,030
11 Saklar Tunggal bh 1.00 40,755 Rp 40,755
12 Saklar Ganda bh 2.00 69,355 Rp 138,710
13 Stop kontak bh 2.00 55,055 Rp 110,110
14 Box Sekring ls 1.00 1,100,000 Rp 1,100,000
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 15,637,943
I. PEK. SANITARY
1 Closet Duduk unit 1.00 1,959,670 Rp 1,959,670
2 Jet washer unit 1.00 29,711 Rp 29,711
3 Kran Buah 1.00 59,060 Rp 59,060
4 Floor Drain Buah 1.00 87,450 Rp 87,450
-
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 2,135,891
REKAP PENAWARAN HARGA
PROYEK : RUKO HIDAYATULLAH
OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEK. LANTAI 4


I. PEK. BETON BERTULANG Rp. 1,082,790,801
II. PEK. DINDING Rp. 112,611,386
III. PEK. LANTAI & DINDING KERAMIK Rp. 37,060,629
IV. PEK. KUSEN PINTU & JENDELA Rp. 1,152,870
V. PEK. PLAFOND Rp. 27,057,377
VI. PEK. CAT Rp. 40,893,545
VII. PEK. TANGGA Rp. 16,512,279
VIII. PEK. MEKANIKAL & ELETRIKAL Rp. 15,637,943
IX. PEK. SANITARY Rp. 2,135,891

Rp. 1,335,852,721
RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI EMPAT

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PLAT LANTAI -
1 Beton K 300 m3 27.53 1,671,060 Rp 46,011,207
Besi Ø 10 Kg 1584.04 12,030 Rp 19,056,047
Besi Ø 8 Kg 158.43 12,030 Rp 1,905,956
2 Pemasangan Bondek m2 229.45 165,000 Rp 37,859,448
-
A.II PEKERJAAN KONSTRUKSI BAJA -
-
1 Kolom K2
Kolom WF Uk. 400 x 400 x 13 x 21 Kg 13072.00 20,000 Rp 261,440,000
Baut HTB Ø 22 Kolom Buah 152.00 35,000 Rp 5,320,000
Cat WF m2 121.60 50,000 Rp 6,080,000

2 Kolom K3
Kolom WF Uk. 350 x 350 x 12 x 19 Kg 3288.00 20,000 Rp 65,760,000
Baut HTB Ø 22 Kolom Buah 48.00 35,000 Rp 1,680,000
Cat WF m2 38.40 50,000 Rp 1,920,000

3 Balok B1
Balok Induk WF Uk. 350 x 350 x 12 x 19 Kg 17788.08 20,000 Rp 355,761,600
Baut HTB Ø 22 Sambungan Kolom dengan WF Buah 1344.00 35,000 Rp 47,040,000
Plat Penahan 12 mm Kg 578.33 35,000 Rp 20,241,390
Cat WF m2 259.39 50,000 Rp 12,969,600
-
4 Balok B2
Balok Anak WF Uk. 175 x 175 x 7,5 x 11 Kg 2297.14 20,000 Rp 45,942,880
Baut HTB Ø 10 Sambungan Balok Anak dengan Balok Induk Buah 568.00 35,000 Rp 19,880,000
Plat Penahan 12 mm Kg 255.60 35,000 Rp 8,945,972
Cat WF m2 259.39 50,000 Rp 12,969,600

5 Balok B3
Balok Induk WF Uk. 250 x 250 x 9 x 14 Kg 3991.68 20,000 Rp 79,833,600
Baut HTB Ø 22 Sambungan Kolom dengan WF Buah 576.00 35,000 Rp 20,160,000
Plat Penahan 12 mm Kg 232.36 35,000 Rp 8,132,702
Cat WF m2 77.62 50,000 Rp 3,880,800
-
SUB TOTAL PEK. PONDASI - Rp 1,082,790,801
B. PEK. DINDING -
1 Pas. Dinding bata ringan uk. 100x200x600 m2 328.16 172,200 Rp 56,509,152
2 Plesteran 1 : 5 m2 656.32 51,380 Rp 33,721,722
3 Acian m2 656.32 34,100 Rp 22,380,512
-
SUB TOTAL PEK. DINDING - Rp 112,611,386
C. PEK. LANTAI & DINDING KERAMIK -
1 Pas. Keramik 40x40 setara Roman m2 240.45 127,290 Rp 30,607,033
2 Plint Lantai uk. 15 x 60 ( Unpolished ) m1 78.04 41,900 Rp 3,269,876
3 Pas Keramik Lantai Kamar Mandi m2 4.00 137,290 Rp 549,160
4 Pas Keramik Dinding Kamar Mandi M2 16.00 164,660 Rp 2,634,560
-
SUB TOTAL PEK. LANTAI - Rp 37,060,629
D. PEK. KUSEN PINTU & JENDELA -
1 Pintu Kamar Mandi unit 1.00 750,000 Rp 750,000
2 Jendela + Kusen Alumunium Unit 3.00 134,290 Rp 402,870
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI EMPAT

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga

-
SUB TOTAL PEK. KUSEN PINTU & JENDELA - Rp 1,152,870
E. PEK. PLAFOND -
1 Pasangan Gypsumboard 9 mm m2 240.45 105,040 Rp 25,256,994
2 List Gypsum Plafond m 78.04 23,070 Rp 1,800,383
-
SUB TOTAL PEK. PLAFOND - Rp 27,057,377
F. PEK. CAT -
1 Cat dinding interior Ex Vinilex m2 312.16 44,960 Rp 14,034,714
2 Cat dinding exterior Ex Vinilex m2 312.16 51,410 Rp 16,048,146
3 Cat Plafond m2 240.45 44,960 Rp 10,810,686
-
SUB TOTAL PEK. CAT - Rp 40,893,545
G. PEK. TANGGA -
1 Beton K 300 m3 1.57 1,671,060 Rp 2,622,227
2 Besi Ø 12 kg 144.60 12,030 Rp 1,739,482
3 Besi Ø 10 kg 51.05 12,030 Rp 614,091
4 Bekisting Multiplek 9 mm m2 9.49 338,460 Rp 3,212,662
5 Pas. Keramik ( Pholised ) Untred m2 6.40 127,290 Rp 814,656
6 Pas. Keramik ( Pholised ) Optred m2 4.00 127,290 Rp 509,160
7 Reilling Tangga, Rangka Stainless, Hand Reilling kayu bengkirai m1 7.00 1,000,000 Rp 7,000,000
-
SUB TOTAL PEK. TANGGA - Rp 16,512,279
H. PEK. MEKANIKAL & ELETRIKAL -
1 Instalasi pipa air bersih 1/2 " + Fitting m1 13.84 28,400 Rp 393,056
2 Instalasi pipa air kotor 4" ke septick tank m1 5.00 170,980 Rp 854,900
3 Instalasi pipa air bekas 3" ke saluran m1 11.00 112,260 Rp 1,234,860
4 Instalasi pipa ke TORN 1 1/2 " + Fitting m1 4.00 55,740 Rp 222,960
5 Instalasi pipa air hujan 3" + Fitting m1 32.00 112,260 Rp 3,592,320
6 Fitting dan material bantu ls 1.00 1,100,000 Rp 1,100,000
7 Instalasi lampu penerangan ttk 6.00 260,403 Rp 1,562,418
8 Instalasi stop kontak ttk 2.00 281,853 Rp 563,706
9 Instalasi saklar ttk 6.00 281,853 Rp 1,691,118
10 Lampu TL 2x20 Watt bh 6.00 505,505 Rp 3,033,030
11 Saklar Tunggal bh 1.00 40,755 Rp 40,755
12 Saklar Ganda bh 2.00 69,355 Rp 138,710
13 Stop kontak bh 2.00 55,055 Rp 110,110
ls 1.00 1,100,000 Rp 1,100,000
14 Box Sekring
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 15,637,943
I. PEK. SANITARY
1 Closet Duduk unit 1.00 1,959,670 Rp 1,959,670
2 Jet washer unit 1.00 29,711 Rp 29,711
3 Kran Buah 1.00 59,060 Rp 59,060
4 Floor Drain Buah 1.00 87,450 Rp 87,450
-
REKAP PENAWARAN HARGA
PROYEK : RUKO HIDAYATULLAH
OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEK. LANTAI 5


I. PEK. BETON BERTULANG Rp. 1,016,682,501
II. PEK. DINDING Rp. 126,118,163
III. PEK. LANTAI & DINDING KERAMIK Rp. 73,753,359
IV. PEK. KUSEN PINTU & JENDELA Rp. 1,152,870
V. PEK. PLAFOND Rp. 27,057,377
VI. PEK. CAT Rp. 40,893,545
VII. PEK. TANGGA Rp. 16,512,279
VIII. PEK. MEKANIKAL & ELETRIKAL Rp. 13,433,663
IX. PEK. SANITARY Rp. 2,135,891

Rp. 1,317,739,648
RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI LIMA

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PLAT LANTAI -
1 Beton K 300 m3 27.53 1,671,060 Rp 46,011,207
Besi Ø 10 Kg 1584.04 12,030 Rp 19,056,047
Besi Ø 8 Kg 158.43 12,030 Rp 1,905,956
2 Pemasangan Bondek m2 229.45 165,000 Rp 37,859,448
-
A.II PEKERJAAN KONSTRUKSI BAJA -
-
1 Kolom K2
Kolom WF Uk. 350 x 350 x 12 x 19 Kg 10412.00 20,000 Rp 208,240,000
Baut HTB Ø 22 Kolom Buah 152.00 35,000 Rp 5,320,000
Cat WF m2 106.40 50,000 Rp 5,320,000

2 Balok B1
Balok Induk WF Uk. 350 x 350 x 12 x 19 Kg 25383.36 20,000 Rp 507,667,200
Baut HTB Ø 22 Sambungan Kolom dengan WF Buah 1920.00 35,000 Rp 67,200,000
Plat Penahan 12 mm Kg 810.69 35,000 Rp 28,374,092
Cat WF m2 259.39 50,000 Rp 12,969,600
-
3 Balok B2
Balok Anak WF Uk. 175 x 175 x 7,5 x 11 Kg 2297.14 20,000 Rp 45,942,880
Baut HTB Ø 10 Sambungan Balok Anak dengan Balok Induk Buah 568.00 35,000 Rp 19,880,000
Plat Penahan 12 mm Kg 255.60 35,000 Rp 8,945,972
Cat WF m2 39.80 50,000 Rp 1,990,100
-
SUB TOTAL PEK. PONDASI - Rp 1,016,682,501
B. PEK. DINDING -
1 Pas. Dinding bata ringan uk. 100x200x600 m2 367.52 172,200 Rp 63,286,944
2 Plesteran 1 : 5 m2 735.04 51,380 Rp 37,766,355
3 Acian m2 735.04 34,100 Rp 25,064,864
-
SUB TOTAL PEK. DINDING - Rp 126,118,163
C. PEK. LANTAI & DINDING KERAMIK -
1 Pas. Keramik 40x40 setara Roman m2 240.45 127,290 Rp 30,607,033
2 Plint Lantai uk. 15 x 60 ( Unpolished ) m1 78.04 41,900 Rp 3,269,876
3 Pas Keramik Lantai Kamar Mandi m2 4.00 137,290 Rp 549,160
4 Pas Keramik Dinding Kamar Mandi M2 16.00 164,660 Rp 2,634,560
5 Waterproofing Dak Beton Atap m2 78.40 297,060 Rp 23,289,466
6 Plesteran 1 : 5 Dak Beton m2 156.80 51,380 Rp 8,056,384
7 Acian Dak Beton m2 156.80 34,100 Rp 5,346,880
-
SUB TOTAL PEK. LANTAI - Rp 73,753,359
D. PEK. KUSEN PINTU & JENDELA -
1 Pintu Kamar Mandi unit 1.00 750,000 Rp 750,000
2 Jendela + Kusen Alumunium Unit 3.00 134,290 Rp 402,870
-
SUB TOTAL PEK. KUSEN PINTU & JENDELA - Rp 1,152,870
E. PEK. PLAFOND -
1 Pasangan Gypsumboard 9 mm m2 240.45 105,040 Rp 25,256,994
2 List Gypsum Plafond m 78.04 23,070 Rp 1,800,383
-
SUB TOTAL PEK. PLAFOND - Rp 27,057,377
F. PEK. CAT -
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI LIMA

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
1 Cat dinding interior Ex Vinilex m2 312.16 44,960 Rp 14,034,714
2 Cat dinding exterior Ex Vinilex m2 312.16 51,410 Rp 16,048,146
3 Cat Plafond m2 240.45 44,960 Rp 10,810,686
-
SUB TOTAL PEK. CAT - Rp 40,893,545
G. PEK. TANGGA -
1 Beton K 300 m3 1.57 1,671,060 Rp 2,622,227
2 Besi Ø 12 kg 144.60 12,030 Rp 1,739,482
3 Besi Ø 10 kg 51.05 12,030 Rp 614,091
4 Bekisting Multiplek 9 mm m2 9.49 338,460 Rp 3,212,662
5 Pas. Keramik ( Pholised ) Untred m2 6.40 127,290 Rp 814,656
6 Pas. Keramik ( Pholised ) Optred m2 4.00 127,290 Rp 509,160
7 Reilling Tangga, Rangka Stainless, Hand Reilling kayu bengkirai m1 7.00 1,000,000 Rp 7,000,000
-
SUB TOTAL PEK. TANGGA - Rp 16,512,279
H. PEK. MEKANIKAL & ELETRIKAL -
1 Instalasi pipa air bersih 1/2 " + Fitting m1 13.84 28,400 Rp 393,056
2 Instalasi pipa air kotor 4" ke septick tank m1 5.00 170,980 Rp 854,900
3 Instalasi pipa air bekas 3" ke saluran m1 11.00 55,740 Rp 613,140
4 Instalasi pipa ke TORN 1 1/2 " + Fitting m1 4.00 112,260 Rp 449,040
5 Instalasi pipa air hujan 3" + Fitting m1 32.00 55,740 Rp 1,783,680
6 Fitting dan material bantu ls 1.00 1,100,000 Rp 1,100,000
7 Instalasi lampu penerangan ttk 6.00 260,403 Rp 1,562,418
8 Instalasi stop kontak ttk 2.00 281,853 Rp 563,706
9 Instalasi saklar ttk 6.00 281,853 Rp 1,691,118
10 Lampu TL 2x20 Watt bh 6.00 505,505 Rp 3,033,030
11 Saklar Tunggal bh 1.00 40,755 Rp 40,755
12 Saklar Ganda bh 2.00 69,355 Rp 138,710
13 Stop kontak bh 2.00 55,055 Rp 110,110
14 Box Sekring ls 1.00 1,100,000 Rp 1,100,000
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 13,433,663
I. PEK. SANITARY
1 Closet Duduk unit 1.00 1,959,670 Rp 1,959,670
2 Jet washer unit 1.00 29,711 Rp 29,711
3 Kran Buah 1.00 59,060 Rp 59,060
4 Floor Drain Buah 1.00 87,450 Rp 87,450
-
SUB TOTAL PEK. MEKANIKAL & ELEKTRIKAL - Rp 2,135,891
REKAP PENAWARAN HARGA
PROYEK : RUKO HIDAYATULLAH
OWNER :
LOKASI : SAMARINDA
TAHUN : APRIL 2021

REKAP PEK. LANTAI DAK


I. PEK. BETON BERTULANG Rp. 377,626,658
II. PEK. BETON ATAP Rp. 23,703,785

Rp. 401,330,442
RAB RUKO HIDAYATULLAH
KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI ATAP

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga
A. PEK. BETON BERTULANG
A.I PLAT LANTAI ATAP -
1 Beton K 300 m3 19.29 1,671,060 Rp 32,228,732
Besi Ø 10 Kg 1041.47 12,030 Rp 12,528,831
Besi Ø 8 Kg 75.57 12,030 Rp 909,064
2 Pemasangan Bondek m2 160.72 175,000 Rp 28,126,000
-
A.II PEKERJAAN KONSTRUKSI BAJA -

1 Balok B1
Balok Induk WF Uk. 250 x 250 x 9 x 14 Kg 8943.84 20,000 Rp 178,876,800
Baut HTB Ø 22 Sambungan Kolom dengan WF Buah 1152.00 35,000 Rp 40,320,000
Plat Penahan 12 mm Kg 485.38 35,000 Rp 16,988,310
Cat WF m2 173.91 50,000 Rp 8,695,400
-
2 Balok B2
Balok Anak WF Uk. 175 x 175 x 7,5 x 11 Kg 1656.40 20,000 Rp 33,128,000
Baut HTB Ø 10 Sambungan Balok Anak dengan Balok Induk Buah 480.00 35,000 Rp 16,800,000
Plat Penahan 12 mm Kg 216.87 35,000 Rp 7,590,521
Cat WF m2 28.70 50,000 Rp 1,435,000
-
SUB TOTAL PEK. PONDASI - Rp 377,626,658
B PEK. BETON ATAP -
1 Plesteran 1 : 5 m2 240.45 51,380 Rp 12,354,383
2 Acian m1 78.04 34,100 Rp 2,661,164
3 Waterproofing Beton Atap m2 4.00 297,060 Rp 1,188,238
4 Tandon air stainless 1000 L Unit 3.00 2,500,000 Rp 7,500,000

SUB TOTAL PEK. LANTAI - Rp 23,703,785


KOTA SAMARINDA
OWNER :
LOKASI : SAMARINDA
TAHUN : 2021
LANTAI : LANTAI ATAP

Harga Jumlah
No Uraian Pekerjaan Sat Volume
Satuan Harga

Anda mungkin juga menyukai