RENCANA UJI MATERIAL BESI

PROYEK GEDUNG IBU DAN ANAK RS. HASAN SADIKIN JV PP-ADHI

BANDUNG - JAWA BARAT

TOTAL TOTAL JUMLAH TEST BIAYA TEST


NO. VENDOR/SUPPLIER MUTU DIAMETER PENDATANGAN PENDATANGAN (2 TARIK & 1 TARIK+TEKUK / TOTAL BIAYA
DALAM KG DALAM TON TEKUK) SAMPLE
1 Master Steel (MS) BJTS-420B D10 431.586,564 431,587 3 Rp 400.000 Rp 1.200.000
2 Master Steel (MS) BJTS-420B D13 411.306,576 411,307 3 Rp 400.000 Rp 1.200.000
3 Delcoprima (DP) BJTS-420B D16 144.405,936 144,406 3 Rp 400.000 Rp 1.200.000
4 Master Steel (MS) BJTS-420B D19 419.939,352 419,939 3 Rp 400.000 Rp 1.200.000
5 Master Steel (MS) BJTS-420B D22 467.330,208 467,330 3 Rp 500.000 Rp 1.500.000
6 Master Steel (MS) BJTS-420B D25 419.314,284 419,314 3 Rp 500.000 Rp 1.500.000
7 Master Steel (MS) BJTS-420B D32 267.418,680 267,419 3 Rp 500.000 Rp 1.500.000
TOTAL Rp 9.300.000
BIAYA LAPORAN Rp 500.000
GRAND TOTAL Rp 9.800.000

NOTE :
- Rencana lokasi pengujian di Laboratorium Kampus Polban Bandung
- Pendaftaran dan membawa sample uji/specimen
- Pelunasan pembayaran saat pendaftaran
- Menunggu jadwal dan antrian pengujian

Disetujui Oleh, Dibuat Oleh,

Hari Nugraha Ibnu Mubarok


SEM QC Officer