PROYEK GEDUNG IBU DAN ANAK RS. HASAN SADIKIN JV PP-ADHI
BANDUNG - JAWA BARAT
TOTAL TOTAL JUMLAH TEST BIAYA TEST
NO. VENDOR/SUPPLIER MUTU DIAMETER PENDATANGAN PENDATANGAN (2 TARIK & 1 TARIK+TEKUK / TOTAL BIAYA DALAM KG DALAM TON TEKUK) SAMPLE 1 Master Steel (MS) BJTS-420B D10 431.586,564 431,587 3 Rp 400.000 Rp 1.200.000 2 Master Steel (MS) BJTS-420B D13 411.306,576 411,307 3 Rp 400.000 Rp 1.200.000 3 Delcoprima (DP) BJTS-420B D16 144.405,936 144,406 3 Rp 400.000 Rp 1.200.000 4 Master Steel (MS) BJTS-420B D19 419.939,352 419,939 3 Rp 400.000 Rp 1.200.000 5 Master Steel (MS) BJTS-420B D22 467.330,208 467,330 3 Rp 500.000 Rp 1.500.000 6 Master Steel (MS) BJTS-420B D25 419.314,284 419,314 3 Rp 500.000 Rp 1.500.000 7 Master Steel (MS) BJTS-420B D32 267.418,680 267,419 3 Rp 500.000 Rp 1.500.000 TOTAL Rp 9.300.000 BIAYA LAPORAN Rp 500.000 GRAND TOTAL Rp 9.800.000
NOTE : - Rencana lokasi pengujian di Laboratorium Kampus Polban Bandung - Pendaftaran dan membawa sample uji/specimen - Pelunasan pembayaran saat pendaftaran - Menunggu jadwal dan antrian pengujian