WORK ORDER

Number : 25/WO/MKT/MNB/IV/2021
Revision : 00
Project : BG. ASL 56
Owner : PT. KARUNIA SAMUDERA LINES PT. MERANTI NUSA BAHARI
Reference : 74/PEN/MKT-MNB/IV/2021 (Rev. 00) Integrity , Trustworthy , Synergy

No Item Volume

I PELAYANAN UMUM
a Docking / Undocking 1 Ls
b Asistensi naik/ turun dock, termasuk persiapan ganjal 1 Ls
c Asistensi dengan mooring Boat 1 Ls
d Sewa dock selama tongkang dalam perbaikan 12 Hari
e Fasilitas sandar sesudah docking (sewa sandar) 3 Hari
f Disediakan Tempat penyimpanan logistik selama perbaikan 1 Ls
g Penggunaan alat angkat (<1 Ton) 1 Ls
II PERAWATAN BADAN KAPAL (Supplai Material by Owner)
a Sekrap Bagian Bawah Air 1392 m2
b Sandblasting Bottom Sampai Waterline (S.A 2.0) 1392 m2
c Sandblasting Top Side (S.A 2.0) 742 m2
d Cuci Air Tawar 2134 m2
e Pengecatan Bagian Bawah Air (1x primer,1x sealer,1 xAF) 1392 m2
f Pengecatan Top Side (1x primer,1x top coat) 742 m2
g Pemasangan Zinc Anode 45 bh
h Pengecatan Draft Mark, Nama Kapal 1 Ls
III REPLATING
III.1 Replating Plate sideboard dan Rumah Winch (Marine Grade A)
a Estimasi Replating Plate Marine Non Klass 0 Kg
III.2 Replating Plate hull, Bottom dan Main deck
a Plate Class BKI 0 Kg
IV TANGKI - TANGKI (Tentative, Sesuai arahan dari Owner Representative)
a Buka dan Tutup Kembali Manhole 16 pcs
b Bongkar Semen dan Penyemenan Kembali 16 pcs
c Ganti Karet Manhole 16 pcs
d Dilakukan Freegas Sebelum Pemeriksaan Kedalam Tangki 16 Tank
e Air Test tangki 2 Tank
V LAPORAN DAN GAMBAR
a Dibuatkan laporan pengedockan dan gambar bukaan kulit sesuai posisi replating 1 set

Note : Balikpapan, 17 April 2021


PT. Meranti Nusa Bahari

Wimba Prambada
General Manager
MKT-FM-001/Rev.00/2 Sept 15/Orange Page 1 of 14
WORK ORDER
Number : 25/WO/MKT/MNB/IV/2021
Revision : 00
Project : BG. ASL 56
Owner : PT. KARUNIA SAMUDERA LINES PT. MERANTI NUSA BAHARI
Reference : 74/PEN/MKT-MNB/IV/2021 (Rev. 00) Integrity , Trustworthy , Synergy

No Item Volume

JR Rev. 00 Additional Work By OS (16/04/2021)


I REPLATING
I.1 Bottom Plat
- Lajur D SB , Fr 0/1 - 1/2 , Plat KI uk. 1500 x 2000 x 12 mm 282.6 Kg
- Lajur D PS , Fr 0/1 - 1/2 , Plat KI uk. 1000 x 2000 x 12 mm 188.4 Kg
- Lajur C - D SB , Fr 29/30 - 30/31 , Plat KI uk. 1000 x 1500 x 12 mm 117.75 Kg
- Lajur D PS , Fr 31/32-32/33 , Plat KI uk. 1000 x 1500 x 12 mm 117.75 Kg
I.2 Corner
a Buritan SB
- Plat KI , Uk.3000 x 1800 x 12 mm 508.68 Kg
- Roundbar Uk.2" x 3000 mm 47.73 Kg
b Buritan PS
- Plat KI , Uk.3000 x 1800 x 12 mm 508.68 Kg
- Roundbar Uk.2" x 4000 mm 63.64 Kg
I.3 Internal Tank
a Tank 8 PS
- Stanchion Web , Siku Press Uk. (400+100) x 10 x 2000 mm 94.2 Kg
- Bracket , Siku Press Uk. (400+100) x 10 x 800 mm 37.68 Kg
- Long Side , Besi Siku Uk. (120+120) x 10 x 1200 mm 27.1296 Kg
- Long Deck , Besi Siku Uk. (120+120) x 10 x 1200 mm 27.1296 Kg
- Long Bottom , Besi Siku Uk. (120+120) x 10 x 1000 mm 22.608 Kg
b Tank 8 SB
- Stanchion Web , Siku Press Uk. (400+100) x 10 x 2000 mm 94.2 Kg
- Bracket , Siku Press Uk. (400+100) x 10 x 800 mm 37.68 Kg
- Long Side , Besi Siku Uk. (120+120) x 10 x 1200 mm 27.1296 Kg
- Long Bottom , Besi Siku Uk. (120+120) x 10 x 1000 mm 22.608 Kg
II LAIN-LAIN
a Cleaning Deck ( Sisa Batu Bara ) 1 Ls

Note : Balikpapan, 17 April 2021


PT. Meranti Nusa Bahari

Wimba Prambada

MKT-FM-001/Rev.00/2 Sept 15/Orange Page 2 of 14


WORK ORDER
Number : 25/WO/MKT/MNB/IV/2021
Revision : 00
Project : BG. ASL 56
Owner : PT. KARUNIA SAMUDERA LINES PT. MERANTI NUSA BAHARI
Reference : 74/PEN/MKT-MNB/IV/2021 (Rev. 00) Integrity , Trustworthy , Synergy

No Item Volume
General Manager

MKT-FM-001/Rev.00/2 Sept 15/Orange Page 3 of 14


Project Name : Sesuai WO
Owner : Sesuai WO
Status Docking: Sesuai WO PT. MERANTI NUSA BAHARI
Class :- Integrity , Trustworthy , Synergy
Number : Sesuai WO

Jetty Area Docking Eletrical : Volts Phase


In Out Indocking Undocking Install Release
Tgl : Tgl : Tgl : Tgl : Tgl : Tgl :

Month
Date

Fitter
Helper
Welder
Man Power

Maintenance
Blasting

Cleaning

Total Man Power

Weather

Note :
- Tanggal terhitung sesuai terbitnya WO (Kapal di atas dock)
- 1 Nozzel / 3 Orang
- √ = proses / selesai
- X = cancel
- Weather ( H = Hujan, G = Gerimis, M = Mendung, C = Cerah )

Page 4
Paraf Kapro
Replating

Paraf Suv
Progres project Devisi Replating
Nama Pekerja Cutting Fit Up Welding Test QC
No Item Volume Fitter Helper Welder Tanggal Tanggal Tanggal Tanggal

II PERAWATAN BADAN KAPAL (Material Cat Dan Zinc Anode By Owner)


g Pemasangan Zinc Anode 45 bh

JR Rev. 00 Additional Work By OS (16/04/2021)


I REPLATING
I.1 Bottom Plat
- Lajur D SB , Fr 0/1 - 1/2 , Plat KI uk. 1500 x 2000 x 12 mm 282.6 Kg
- Lajur D PS , Fr 0/1 - 1/2 , Plat KI uk. 1000 x 2000 x 12 mm 188.4 Kg
- Lajur C - D SB , Fr 29/30 - 30/31 , Plat KI uk. 1000 x 1500 x 12 mm 117.75 Kg
- Lajur D PS , Fr 31/32-32/33 , Plat KI uk. 1000 x 1500 x 12 mm 117.75 Kg
I.2 Corner
a Buritan SB
- Plat KI , Uk.3000 x 1800 x 12 mm 508.68 Kg
- Roundbar Uk.2" x 3000 mm 47.73 Kg
b Buritan PS
- Plat KI , Uk.3000 x 1800 x 12 mm 508.68 Kg
- Roundbar Uk.2" x 4000 mm 63.64 Kg
I.3 Internal Tank
a Tank 8 PS
- Stanchion Web , Siku Press Uk. (400+100) x 10 x 2000 mm 94.2 Kg
- Bracket , Siku Press Uk. (400+100) x 10 x 800 mm 37.68 Kg
- Long Side , Besi Siku Uk. (120+120) x 10 x 1200 mm 27.1296 Kg
- Long Deck , Besi Siku Uk. (120+120) x 10 x 1200 mm 27.1296 Kg
- Long Bottom , Besi Siku Uk. (120+120) x 10 x 1000 mm 22.608 Kg
b Tank 8 SB
- Stanchion Web , Siku Press Uk. (400+100) x 10 x 2000 mm 94.2 Kg
- Bracket , Siku Press Uk. (400+100) x 10 x 800 mm 37.68 Kg
- Long Side , Besi Siku Uk. (120+120) x 10 x 1200 mm 27.1296 Kg
- Long Bottom , Besi Siku Uk. (120+120) x 10 x 1000 mm 22.608 Kg

Noted :
Paraf Kapro
Replating

Paraf Suv
Progres project Devisi Replating
Nama Pekerja Cutting Fit Up Welding Test QC
No Item Volume Fitter Helper Welder Tanggal Tanggal Tanggal Tanggal
Maintenance

Paraf Kapro
Laporan Devisi Maintenance

Paraf suv
Release Repair Test QC Install
Nama Pekerja
No Item Volume Tanggal Tanggal Tanggal Tanggal

IV TANGKI - TANGKI (Tentative, Sesuai arahan dari Owner Representative)


a Buka dan Tutup Kembali Manhole 16 pcs
b Bongkar Semen dan Penyemenan Kembali 16 pcs
c Ganti Karet Manhole 16 pcs
d Dilakukan Freegas Sebelum Pemeriksaan Kedalam Tangki 16 Tank
e Air Test tangki 2 Tank

JR Rev. 00 Additional Work By OS (16/04/2021)


II LAIN-LAIN
a Cleaning Deck ( Sisa Batu Bara ) 1 Ls
Maintenance

Paraf Kapro
Laporan Devisi Maintenance

Paraf suv
Release Repair Test QC Install
Nama Pekerja
No Item Volume Tanggal Tanggal Tanggal Tanggal
B&P

On Proses
Progres project Devisi Blasting dan Painting
Blasting Primer Sealer AF/Top Coat

Pinish
No Item Volume Jam / Tanggal Jam / Tanggal Jam / Tanggal Jam / Tanggal

II PERAWATAN BADAN KAPAL (Supplai Material by Owner)


a Sekrap Bagian Bawah Air 1392 m2
b Sandblasting Bottom Sampai Waterline (S.A 2.0) 1392 m2
c Sandblasting Top Side (S.A 2.0) 742 m2
d Cuci Air Tawar 2134 m2
e Pengecatan Bagian Bawah Air (1x primer,1x sealer,1 xAF) 1392 m2
f Pengecatan Top Side (1x primer,1x top coat) 742 m2
h Pengecatan Draft Mark, Nama Kapal 1 Ls
B&P

On Proses
Progres project Devisi Blasting dan Painting
Blasting Primer Sealer AF/Top Coat

Pinish
No Item Volume Jam / Tanggal Jam / Tanggal Jam / Tanggal Jam / Tanggal
Laporan Devisi General Support (Team Docking)
Project Indocking Dimensi kapal
Nama Kapal : BG YAMADA 01 Loa : 82.29 M
Owner : PT. BINATANG MANUNGGAL PRATAMA Bmld : 21.94 M
Date : 26 April 2021 Hmld : 4.87 M

Man power Equitment


1. General Support : Orang 1. Excavator : Unit 8. AirBag : Pcs
2. Operator Winch : Orang 2. Loader : Unit 9. Batu Ganjal : Buah
3. Operator Alat Berat : Orang 3. Manitau : Unit 10. Balok Ganjal : Buah
4. Sefety : Orang 4. Winch : Unit 11.
5. Logistic : Orang 5. Generator : Unit 12.
6. Head project : Orang 6. Mooring boat : Unit 13.
Total Man Power : Orang 7. Kompressor : Unit 14.

Mulai proses Selesai Kalkulasi Waktu


No Item
(Jam) (Jam) (Jam)

I PROSES INDOCKING

II KENDALA INDOCKING

Dibuat Mengetahui Approved

Supervisor Head Project Manager Produksi


Laporan Devisi General Support (Team Docking)
Project Undocking Dimensi kapal
Nama Kapal : BG YAMADA 01 Loa : 82.29 M
Owner : PT. BINATANG MANUNGGAL PRATAMA Bmld : 21.94 M
Date : Hmld : 4.87 M

Man power Equitment


1. General Support : Orang 1. Excavator : Unit 8. AirBag : Pcs
2. Operator Winch : Orang 2. Loader : Unit 9.
3. Operator Alat Berat : Orang 3. Manitau : Unit 10.
4. Sefety : Orang 4. Winch : Unit 11.
5. Logistic : Orang 5. Generator : Unit 12.
6. Head project : Orang 6. Mooring boat : Unit 13.
Total Man Power : Orang 7. Kompressor : Unit 14.

Mulai proses Selesai kalkulasi waktu


No Item
(Jam) (Jam) (Jam)

I PROSES UNDOCKING

II KENDALA UNDOCKING

Dibuat Mengetahui Approved

Supervisor Head Project Manager Produksi