Anda di halaman 1dari 158

HARGA SATUAN UPAH DAN BAHAN MATERIAL

LOKASI : KABUPATEN DOMPU


TAHUN ANGGARAN : 2020

HARGA SATUAN
NO UPAH DAN BAHAN SATUAN
( Rp. )
1 2 3 4

Upah Tenaga Kerja


1 Pekerja OH 100,000.00
2 Tukang Batu OH 135,000.00
3 Kepala Tukang Batu OH 150,000.00
4 Tukang Kayu OH 135,000.00
5 Kepala Tukang Kayu OH 150,000.00
6 Tukang Besi Beton OH 135,000.00
7 Kepala Tukang Besi Beton OH 150,000.00
8 Tukang alumnium OH 135,000.00
9 Kepala Tukang alumunium OH 150,000.00
10 Tukang Las OH 135,000.00
11 Kepala Tukang Las OH 150,000.00
12 Tukang Politur OH 135,000.00
13 Tukang Cat OH 135,000.00
14 Kepala Tukang Cat OH 150,000.00
15 Pemecah Batu OH 100,000.00
16 Penggergaji OH 100,000.00
17 Mandor pengisi Bronjong OH 135,000.00
18 pengisi Bronjong OH 110,000.00
19 Penganyam Bronjong OH 130,000.00
20 Kepala Penganyam Bronjong OH 150,000.00
21 Mandor OH 135,000.00
22 Sopir OH 150,000.00
23 Pembantu Sopir OH 110,000.00
24 Mekanik OH 135,000.00
25 Pembantu Mekanik OH 100,000.00
26 Operator Alat Ringan OH 120,000.00
27 Operator Alat Berat OH 150,000.00
28 Pembantu Operator OH 110,000.00
29 Pemasak Aspal OH 100,000.00
30 Penunjuk Jalan OH 127,000.00
31 Tukang Pipa OH 135,000.00
32 Tukang Bor OH 120,000.00
33 Tukang Listrik OH 120,000.00
34 Kepala Tukang Listrik OH 150,000.00
35 Penjaga Malam OH 100,000.00
36 Penggosok Tegel OH 100,000.00
37 Kepala Tukang Politur OH 150,000.00
38 Kepala Tukang Pipa OH 150,000.00
39 Tukang Cor OH 160,000.00
40 Pekerja Cor OH 110,000.00

1 IMB m2 16,000.00

Bahan Pasangan
1 Batu Kali Belah 15-20 cm M³ 240,000.00
2 Batu Kali Alam M³ 226,000.00
3 Kerikil Pecah 5/7 cm M³ 418,000.00
4 Kerikil 5/7 cm (Stone Crusher) M³ 560,000.00
5 Kerikil Pecah 3/5 cm M³ 500,000.00
6 Kerikil 3/5 cm (Stone Crusher) M³ 535,000.00
7 Kerikil Pecah 2/3 cm M³ 565,000.00
8 Kerikil 2/3 cm (Stone Crusher) M³ 735,000.00
9 Kerikil Alam 0,5/1 Cm M³ 530,000.00
10 Kerikil Alam 2/3 M³ 560,000.00
11 Kerikil Sungai - Riyalti M³ 350,000.00
12 Kerikil Beton (Maks 3 cm) M³ 340,000.00
13 Kerikil Pecah 1/2 cm M³ 791,000.00
14 Batu Kali Keping / Tempel M³ 283,000.00
15 Kerikil Alam 5/7 M³ 226,000.00
16 Kerikil Alam 3/5 M³ 238,000.00
17 Kerikil Alam 2/3 Cm M³ 339,000.00
18 Agregate Kasar (Stone Crusher) M³ 792,000.00
19 Agregate Halus (Stone Crusher) M³ 905,000.00
20 Agregate Klas B (20% Agg.Hls:80% Agg.Ksr) M³ 679,000.00
21 Batu Apung Kg 249,000.00
22 Batu Bata Kelas I (Press) Buah 950.00
23 Batu Bata Kelas II (Lokal) Buah 850.00
24 Bata ringan/Hebel, 10X20X60 m3 1,600,000.00
25 Bata ringan/Hebel, 10X20X60 bh 19,000.00
26 Pasir Beton ( Pasir Hodo ) M³ 350,000.00
27 Pasir Pasang M³ 220,000.00
28 Pasir Urug M³ 190,000.00
29 Sirtu M³ 237,000.00
30 Tanah Urug biasa M³ 121,000.00
31 Tanah Urug Pilihan M³ 192,000.00
32 Tanah Liat (TL) M³ 57,000.00

Bahan Pengikat campuran/Semen


1 Semen Merah (SM) Kg 15,000.00
2 Semen Warna Kg 15,000.00
3 PC. Merk Tiga Roda Kg 1,700.00
4 PC. Merk Gresik Kg 1,700.00
5 PC. Merk Tonasa Kg 1,700.00
6 PC. Merk Holcim Kg 1,700.00
7 PC. Merk Basuwa Kg 1,650.00
8 PC. Merk Padang Kg 1,650.00
9 Semen Warna Butiran Halus Kg 15,700.00
10 Semen Warna Butiran Kasar Kg 15,700.00
11 Ornamen terawang custom m2 937,500.00
12 Semen-MU 380 (Plesteran) 40kg Kg 4,500.00
13 Semen-MU 200 (acian) 40kg Kg 5,000.00

1 Rumput Gebalan M² 38,000.00


2 Kapur Gamping/Labur Kg 5,000.00
3 Kapur Biasa Kg 2,000.00
4 Fuller (Abu Bati) Kg 4,000.00

1 Air kerja Liter 250.00


2 Strorox - 100 Kg 37,000.00
3 Dinding Hollow Block (HB 20) Bh 1,500.00
4 Dinding Hollow Block (HB 15) Bh 1,300.00
5 Dinding Hollow Block (HB 10) Bh 1,100.00
6 Fuller Kg 3,800.00

Bahan Atap
1 Sirap Kalimantan Bh 2,800.00
2 Genteng Lokal Bh 1,800.00
3 Genteng Beton /Pres Bh 6,800.00
4 Genteng Karang Pilang/ Kodok Bh 5,500.00
5 Genteng Pejaten Sudah di cat Bh 3,800.00
6 Genteng Kaca Bh 28,000.00
7 Genteng Keramik / 25bh Bh 17,000.00
8 Genteng Keramik Glazur / 15bh Bh 15,000.00
9 Genteng Kanmuri Full Flat, Natural Bh 18,000.00
10 Genteng Karang Pilang Type Keramik Bh 9,700.00
11 Genteng Bubungan Lokal Bh 6,800.00
12 Genteng Bubungan Beton Bh 7,800.00
13 Genteng Bubungan Silang Bh 6,500.00
14 Genteng Bubungan Pejaten Bh 8,700.00
15 Genteng Bubungan Keramik / 4bh Bh 30,600.00
16 Genteng Bubungan Keramik Glazur / 4bh Bh 16,000.00
17 Bubungan Genteng kanmuri Full Flat, Natura Bh 34,000.00
18 Bubungan Karang Pilang/ Kodok Bh 13,000.00
19 Genteng Metal roof 0,25 mm (Lapis Butiran) Lbr 60,000.00
20 Bubungan Metal Roof (Lapis Butiran) M' 65,000.00
21 Genteng Metal roof 0,3 mm (Lapis Butiran) Lbr 82,000.00
22 Bubungan Metal Roof (Lapis Butiran) M' 85,000.00
23 Genteng Metal roof 0,25 mm (Tanpa Lapis Butiran) Sakura Lbr 40,000.00
24 Bubungan Metal (Tanpa Lapis Butiran) M' 42,000.00
25 Atap bitumen gelombang H : 3,0 mm lbr 192,500.00
26 Paku fiser bitumen bh 1,500.00
27 Nok / Ridge Onduline Lbr 1,500.00
28 Sekrup / Paku bh 12,500.00
29 Asbes Type Genteng (tyluq) Lembar 67,800.00
30 Ijuk Atap kg 28,000.00
31 Asbes Gelombang Kecil 92 x 180 cm Lembar 68,000.00
32 Asbes Gelombang Besar 105 x 240 cm Lembar 198,000.00
33 Bubungan Asbes Gelombang Kecil 92 cm Lembar 53,000.00
34 Bubungan Asbes Gelombang Besar 105 cm Lembar 85,000.00
35 Seng.Glb Besar BJL.S 20 Lembar 67,000.00
36 Seng.Glb Besar BJL.S 25 Lembar 78,000.00
37 Seng.Glb Besar BJL.S 30 Lembar 84,000.00
38 Seng.Glb Kecil BJL.S 20 Lembar 74,000.00
39 Seng Plat BJL.S 18 lebar 90 cm M' 48,000.00
40 Seng Plat BJL.S 20 lebar 90 cm M' 74,000.00
41 Seng Plat BJL.S 25 lebar 90 cm M' 103,000.00
42 Seng Plat BJL.S 28 lebar 90 cm M' 115,000.00
43 Seng Plat BJL.S 30 lebar 90 cm M' 130,000.00
44 Seng Spandek 0.25 mm lebar 80 cm M' 60,000.00
45 Seng Spandek 0.3 mm lebar 80 cm M' 70,000.00
46 Seng Spandek 0.35 mm lebar 80 cm M' 94,000.00
47 Seng Spandek 0.4 mm lebar 80 cm M' 104,000.00
48 Seng Spandek 0.25 mm lebar 80 cm, Warna M' 75,000.00
49 Seng Spandek 0.3 mm lebar 80 cm, Warna M' 87,000.00
50 Seng Spandek 0.35 mm lebar 80 cm, Warna M' 94,000.00
51 Seng Spandek 4 mm lebar 80 cm, Warna M' 103,000.00
52 Atap Roof Fiber Glass Lbr 125,000.00
53 Rangka Atap Roof Fiber Glass M² 266,000.00
54 Plastik Aerator M² 6,000.00
55 Atap Polycarbonat Lbr 203,000.00
56 Atap Trimdeck 0.40 TCT (Spandek) M² 90,000.00
57 Bubungan Trimdeck 0.40 TCT (Spandek) M' 51,000.00
58 Alumunium Foil M² 11,000.00
59 Karet Talang M' 91,000.00
60 Atap Polycarbonate (210 x 1180 cm) Lembar 418,000.00
61 GRC Board bergelombang m2 89,800.00
62 Profil C 75.100 M' 19,000.00
63 Profil C 75.75 M' 14,000.00
64 Profil C 80.100 M' 22,000.00
65 Profil C 80.75 M' 17,000.00
66 Reng U 0.55 M' 8,000.00
67 Reng U 0.45 M' 6,000.00
68 Baut Truss Bh 500.00
69 Baut Reng Bh 400.00

Bahan Kayu dan Bambu


1 Papan Kayu Klas I M³ 5,476,000.00 Lokal
2 Papan Kayu Klas II M³ 3,730,000.00 Lokal
3 Papan Kayu Klas III M³ 2,600,000.00 Lokal
4 Balok Kayu Klas I M³ 5,345,000.00 Lokal
5 Balok Kayu Klas II M³ 3,640,000.00 Lokal
6 Balok Kayu Klas III M³ 2,600,000.00 Lokal
7 Dolken / Perancah Dia. 7 Cm - 4 m Batang 11,000.00 Lokal
8 Papan Kayu Begisting M³ 3,261,100.00 Lokal
9 Balok Kayu Begisting M³ 3,181,600.00 Lokal

1 Lumbersering Kayu Kelas I M³ 3,711,800.00


2 Lumbersering Kayu Kelas II M³ 3,149,300.00
3 List Plafond M' 8,500.00
4 List Plafond 2/4 Profil M' 9,000.00
5 List Plafond 4/4 Profil M' 14,000.00
6 Papan Nama Bh 200,000.00
7 Bambu (Dia 12.5 cm, P 6 m) Btg 39,700.00
8 Bambu (Dia 10 cm, P 6 m) Btg 34,000.00
9 Bambu (Dia 7 cm, P 6 m) Btg 27,200.00
10 Bedek Kulitan M² 56,500.00
11 Bedek Biasa M² 31,300.00
12 Bedek Pagar M² 34,000.00
13 Bilik Bambu M² 47,500.00

Bahan Cetak
1 Lubang Angin 10x20 Cm Bh 14,000.00
2 Lubang Angin 20x20 Cm Bh 15,000.00
3 Lubang Angin 20x30 Cm Bh 20,000.00
4 Buis Beton Dia. 10 Cm Bh,L= 0,5M 50,000.00
5 Buis Beton Dia. 20 Cm Bh,L= 0,5M 75,000.00
6 Buis Beton Dia. 30 Cm Bh,L= 0,5M 90,000.00
7 Buis Beton Dia. 40 Cm Bh,L= 0,5M 110,000.00
8 Buis Beton Dia. 50 Cm Bh,L= 0,5M 125,000.00
9 Buis Beton Dia. 60 Cm Bh,L= 0,5M 130,000.00
10 Buis Beton Dia. 80 Cm Bh,L= 0,5M 150,000.00
11 Penutup Buis Beton Dia. 80 Cm Bh 175,000.00
12 Batako 10 x 20 x 40 Cm Bh 4,000.00
13 Paving Blok Persegi (t = 8 cm) M2 80,000.00
14 Paving Blok Persegi (t = 6 cm) M2 65,000.00
15 Paving Blok Persegi (t = 8 cm), Press M2 165,000.00
16 Paving Blok Tiga Berlian M2 197,800.00
17 Batu paras/Palimanan M2 243,000.00
18 Batu Sisir/ Bergaris, hitam M2 260,000.00
19 Lubang Angin Keramik 20 x 20 cm Bh 43,000.00
20 Lubang Angin Keramik 30 x 30 cm Bh 54,000.00
21 Glass Block Bh 55,000.00
22 Roster Terawang (15 X 20 ) Bh 17,000.00
23 Roster 30 x 30 m2 218,700.00
24 Wall Line GRC + Rangka Hollow (Terpasang) M2 1,100,000.00
25 Conblock tipe segi-empat abu-abu 8 cm, K-300 m2 126,800.00
26 Conblock tipe segi-enam abu-abu 8 cm, K-300 m2 121,200.00
27 Kisi-kisi 50x100 mm UPVC Motif Kayu m1 131,700.00
28 Kanstein m1 81,200.00

Bahan Lantai
1 Tegel Abu-abu 20 x 20 M² 62,500.00
2 Tegel Bergaris Abu 20 x 20 Cm M² 73,500.00
3 Tegel Warna 20 x 20 Cm M² 79,500.00
4 Tegel Bergaris Warna 20 x 20 Cm M² 79,500.00
5 Tegel Traso Klas I 30 x 30 M² 84,800.00
6 Tegel Traso Klas II 30 x 30 M² 82,000.00
7 Granite Kw I M² 450,000.00
8 Granite Kw II M² 380,000.00
9 Geotextile m2 312,500.00
10 Drainagecell m2 675,000.00
11 Hospital plint 60 x 10 x 4 Buah 81,200.00
12 Stepnose tangga 10x40 cm Buah 31,200.00
13 Karpet kg 25,000.00
14 grassblock tebal 8 cm m2 140,000.00
15 Lantai conwood deck 12" T-lock + Pengecetan M² 770,000.00

1 Keramik Dinding Kw I (Motif) M² 135,000.00


2 Keramik Dinding Kw II (Motif) M² 110,000.00
3 Keramik Dinding Kw I (Polos) M² 121,000.00
4 Keramik Dinding Kw II (Polos) M² 88,000.00

1 Keramik Lantai Kualitas I (Motif) M² 121,000.00


2 Keramik Lantai Kualitas II (Motif) M² 99,000.00
3 Keramik Lantai Kualitas I (Polos) M² 83,000.00
4 Keramik Lantai Kualitas II (Polos) M² 69,000.00

1 Keramik cutting Motif M² 160,000.00


2 Lantai Marmer M² 335,000.00
3 Lantai Vinyl Bh 16,800.00
4 Lantai parquete (dreamwood) Bh 26,300.00
5 Beton grid Pracetak K225, ( 5x40x240) M3 230,000.00
6 Porselin Kualitas I (Polos) M² 102,700.00
7 Plint Keramik Bh 13,000.00
8 Plint Granite Bh 30,000.00
9 Coral sikat Kg 9,000.00
10 Coral sikat, Warna Kg 15,000.00
11 Dinding Kalsiplank 8" Jati+ Rangka Holow + Pengecetan M² 715,000.00
12 Dinding Bahan HPL, Motif Lembar 220,000.00
13 Dinding Bahan HPL, Polos Lembar 190,000.00
14 HPL m3 68,700.00
15 Kapur Sirih Kg 25,000.00
16 Wall Paper m3 156,200.00
17 Perekat Kg 25,000.00
18 Kanstin m2 75,000.00

Bahan Besi
1 Besi Beton Ulir Kg 19,000.00
2 Besi Beton polos Kg 16,000.00
3 Rangka Plafond Metal Furing m2 250,000.00
4 Rangka Plafond Besi Hollow, (galvanis) m2 200,000.00
5 Plat baja tebal 8 mm 4 feet x 8 feet lbr 1,240,000.00
6 plat baja 15x9x9,2 cm m1 312,500.00
7 Plat stainless steel m2 1,562,500.00
8 Pull Handle ex. Dekson type 01 bh 1,553,700.00
9 Lock Case ex. Dekson bh 906,200.00
10 Lever Handle ex. Dekson bh 750,000.00
11 Engsel Floor hange Dexson bh 1,743,700.00
12 Door Closer ex dekson bh 655,000.00
13 Slide Handle ex. Dekson bh 1,250,000.00
14 Engsel sliding bh 448,700.00
15 Pintu plat baja tebal 5,5 mm lapis timah hitam ex. Bostinco bh 18,750,000.00
16 Flush bolt ex. Dekson bh 100,000.00
17 Engsel kupu ex. Dekson bh 102,500.00
18 Plat timbah hitam 3 m m2 693,700.00
19 Besi Profil (Siku), kanal C Kg 30,000.00
20 Besi Baja IWF Kg 30,000.00
21 Pipa Black Steel Kg 35,000.00
22 Spaner Kg 35,000.00
23 Curtain Wall + kaca templet 8 mm m2 2,150,000.00
24 Kusen Alumunium Natural M' 93,000.00
25 Kusen Alumunium Warna M' 105,000.00
26 Daun pintu/jendela alumunium + kaca 5 mm, Complit (natural) m2 1,000,000.00
27 Daun pintu/jendela alumunium + kaca 5 mm, Complit (warna) m2 1,050,000.00
28 Daun pintu/jendela alumunium + kaca 8 mm, Complit (natural) m2 1,100,000.00
29 Daun pintu/jendela alumunium + kaca 8 mm, Complit (warna) m2 1,150,000.00
30 Alumunium Strip M' 57,000.00
31 Alumunium "T" M' 14,000.00
32 Kawat f 4 mm M' 8,000.00
33 Profil kaca Alumunium M' 90,000.00
34 Kawat Ikat Beton Kg 33,000.00
35 Kawat Nyamuk Besi M² 28,000.00
36 Kawat Saringan Pasir M² 34,000.00
37 Kawat Duri 50/Rol 95,000.00
38 Kawat Bronjong digalvanisir Kg 39,000.00
39 Kawat Las Kotak 160,000.00
40 Besi Strip Tebal 5 mm Kg 34,000.00
41 Besi Strip Tebal 3 x 2 mm Kg 25,000.00
42 Besi Strip Tebal 2 x 2 mm Kg 22,000.00
43 Besi Stainles Diameter 2" M' 90,000.00
44 Besi Stainles Diameter 1" M' 50,000.00
45 Besi Stainles Diameter 1/2" M' 30,000.00
46 Daun Pintu Roling door alumunium M² 600,000.00
47 Rangka Roling door alumunium M' 300,000.00
48 Pintu Harmonika, Complet M² 1,750,000.00
49 Sunscreen alluminium M² 500,000.00
50 Alluminium Composit Panel (ACP) 0,30 mm, (Interior) M² 550,000.00
51 Alluminium Composit Panel (ACP) 0,30 mm,(Exterior) M² 770,000.00
52 Wood Panel Composit (WPC) tebal 15mm M² 442,000.00
53 Pintu WCP, Complit Unit 1,500,000.00
54 sealent tube 25,000.00
55 Kawat Gerawang M² 22,000.00
56 Besi Hollow 100 x 50 Zincromate L = 6m M' 58,800.00
57 Besi Hollow 40 x 40 Zincromate L = 6m M' 25,000.00
58 Besi Hollow 40 x 20 Zincromate L = 6m M' 12,000.00
59 Besi Hollow 40 x 40 Stenlistail L = 6m M' 100,000.00
60 Besi Hollow 20 x 20 Stenlistail L = 6m M' 38,000.00
61 Pipa 2" black steel di cat duco m1 68,700.00
62 Pipa 1"black steel dicat duco m1 43,700.00
63 Galvanis Steel 3/4" m1 42,700.00
64 Besi Stainless Ø 3/4' m1 93,700.00
65 Hollow 5x5 cm m1 31,200.00
66 Syntetic Grass m2 131,200.00
67 WPC 5x5 cm m1 225,500.00
68 WPC 10x5 cm m1 347,800.00
69 WPC 15x5 cm m1 481,200.00
70 WPC 20x5 cm m1 573,300.00
71 WPC Panel W15 x H2,5 cm m1 281,200.00
72 WPC door type 02 include kaca 5 mm bh 2,812,500.00
73 WPC door type 03 include kaca 5 mm bh 4,437,500.00
74 WPC door type 04b include kaca 5 mm bh 2,312,500.00
75 WPC door type 04c include kaca 5 mm bh 1,937,500.00
76 WPC door type 06 uk. 2,2 x 0,8 m bh 2,187,500.00
77 WPC door type 08 uk. 1.1 x 0,6 m bh 1,625,000.00
78 WPC door type 09 uk. 2,2 x 1,5 m bh 3,125,000.00
79 WPC door type 10 uk. 2,2 x 0,9 m bh 2,375,000.00
80 WPC door type 11 uk. 2,2 x 1,3 m bh 4,250,000.00
81 Kalsiboard rangka alumunium set 750,000.00
82 Besi Hollow / Square Bars 20 x 40 x 1.5 mm M' 21,400.00
83 Besi Hollow / Square Bars 40 x 40 x 1.5 mm M' 28,600.00
84 Besi Hollow / Square Bars 40 x 60 x 1.5 mm M' 35,700.00
85 Besi Hollow / Square Bars 60 x 80 x 1.5 mm M' 50,000.00
86 Besi Hollow / Square Bars 60 x 100 x 1.5 mm M' 57,200.00
87 Rangka Hollow 5 x 100 mm m1 137,500.00
88 pengelasan cm1 1,200.00
89 Steel Frame Hollow Galvanis 150x40x3 mm m1 31,200.00
90 Alumunium 4" Dark Gray ex. YKK m1 206,200.00
91 Kunci Pintu Alumunium Bh 220,000.00
92 Textile Tape M' 34,000.00
93 Siku Pintu Otomatis Bh 550,000.00
94 Karet Kaca Set 140,000.00
95 Besi Plat 3 mm Lembar 1,695,000.00
96 Besi Plat 2 mm Lembar 1,244,000.00
97 Pintu kawat harmonika + Besi Siku M² 249,000.00
98 Plat baja, ukuran 120 x 240 cm Kg 23,000.00
99 Jarum Keras Bh 98,000.00
100 Pintu Jeruji Besi Rangka besi siku 40.40.4 + Asisories M² 536,000.00
101 Pintu Besi Pagar M² 480,000.00
102 Pagar Besi M² 452,000.00
103 Pintu Besi Pagar (dia. 16 mm) M² 900,000.00
104 Pagar Besi (dia. 16 mm) M² 800,000.00
105 Pagar Besi Pipa GI M² 792,000.00
106 Pintu Pagar Besi Pipa GI M² 848,000.00
107 Baut Sekrup Anti Karat Bh 1,900.00
108 Ventilasi Siku M2 249,000.00
109 Mata Kater Bh 84,000.00
110 Roda Pintu Dorong Bh 56,000.00
111 Mesin Bor Listirk Unit 1,334,000.00
112 Wiremesh M6/ (34,76)kg Kg 36,000.00
113 Wiremesh M8/ (61,79)kg Kg 65,000.00
114 Wiremesh M10/ (96,54)kg Kg 104,000.00
115 Bondek tebal 0.65 mm M2 108,000.00
116 Bondek tebal 0.70 mm M2 119,000.00
117 Bondek tebal 0.75 mm M2 122,000.00
118 Bondek tebal 1.00 mm M2 203,000.00

Bahan Langit-Langit
1 Eternit 100 x 100 Cm Lembar 26,000.00
2 Triplek 120 x 240 x 2 mm Lembar 53,000.00
3 Triplek 120 x 240 x 3 mm Lembar 66,000.00
4 Triplek 120 x 240 x 4 mm Lembar 102,000.00
5 Triplek 120 x 240 x 6 mm Lembar 105,000.00
6 Triplek 120 x 240 x 9 mm Lembar 158,000.00
7 Triplek 120 x 240 x 12 mm Lembar 237,000.00
8 Triplek 120 x 240 x 18 mm Lembar 328,000.00
9 Calsiboard 1200 x 240 x 3.5 mm Lembar 134,000.00
10 Calsiboard 1200 x 240 x 6 mm Lembar 221,000.00
11 Gypsum board 1200 x 2400 x 9 mm M2 95,000.00
12 PVC/ Shunda Plafond, 1.2 mm, Putih Polos M2 240,000.00
13 PVC/ Shunda Plafond, 1.2 mm, Warna M2 270,000.00
14 Plafond Akustik 600 x 600 M2 150,000.00
15 Plafond Papan Kayu Kls II, 2 cm M2 75,000.00
16 Formika Putih 120 x 240 mm Lembar 192,000.00
17 Formika Warna 120 x 240 mm Lembar 260,000.00
18 Mega Teakwood 120 x 240 x 3 mm Lembar 215,000.00
19 List Gypsum M' 23,000.00
20 List Plafond Gypsum Type I M' 52,000.00
21 List Plafond Gypsum Type II M' 39,000.00
22 List Plafond Shadow Line, aluminium 0.30 mm M' 5,200.00
23 Lem Kayu Kg 50,000.00
24 Lem Kg 50,000.00
25 Lem vinyl/perquete Kg 50,000.00
26 Lem Gypsum Kg 29,000.00
27 List Plafond Shadow Line, aluminium 0.30 mm M' 5,200.00
28 Kasiplank (0.8 x 20) M' 20,000.00
29 Top Cross Rail 250FX btg 30,000.00
30 Furring Chanel PN 205 btg 85,000.00
31 Furring Chanel PN 208 bh 2,600.00
32 Suspension Spring Clip 223SS bh 5,200.00
33 4 mm Soft Galv Suspension Rod PN 225 bh 5,250.00
34 Angle Bracket PN 220 bh 2,000.00
35 Wall Angle 252FX bh 4,200.00
36 Paper Tape roll 30,000.00
37 Steel Tape roll 131,200.00
38 UB Cote Read Mix kg 160,000.00
39 Papan WPC teval 7 mm lbr 328,900.00

Bahan Kaca
1 Kaca Nako 5 mm M² 141,000.00
2 Kaca Polos 3 mm M² 113,000.00
3 Kaca Polos 5 mm M² 141,000.00
4 Kaca Polos 8 mm M² 185,000.00
5 Kaca Buram (ES) 5 mm Komplit M² 215,000.00
6 Kaca Riben 3 mm M² 136,000.00
7 Kaca Riben 5 mm M² 164,000.00
8 Kaca Cermin 5 mm M² 169,000.00
9 Acrilic 2mm Bening 2mmx122cmx244cm Lembar 452,400.00
10 Kaca Tempreat 8 mm, Polos M² 1,000,000.00
11 Kaca Tempreat 10 mm, Polos m2 1,250,000.00
12 Kaca Tempreat 12 mm, Polos M² 1,500,000.00
13 Kaca Tempreat 8 mm, Warna M² 1,100,000.00
14 Kaca Tempreat 12 mm, Warna M² 1,800,000.00
15 Kaca Lengkung 10 mm, Polos M² 2,000,000.00
16 Kaca Lengkung 12 mm, Polos M² 2,500,000.00

Bahan Finishing
1 Amplas Lembar 8,700.00
2 Plamir Kayu Kg 28,000.00
3 Spritus Liter 28,000.00
4 Dempul Kg 35,000.00
5 Batu Apung Kg 249,000.00
6 Soda api Liter 66,000.00
7 Sabun Kg 20,000.00
8 Minyak Cat Liter 20,000.00
9 Residu Liter 25,000.00
10 Minyak Bekisting Liter 18,000.00
11 Meni Besi Kg 34,000.00
12 Meni Kayu Kg 34,000.00
13 Cat Kayu Mutu Menengah Kg 71,000.00
14 Cat Kayu Mutu Tinggi Kg 85,000.00
15 Cat Tembok Mutu Tinggi, (Interior) Kg 60,000.00
16 Cat Tembok Mutu Tinggi, (Exterior) Kg 125,000.00
17 Cat Tembok Mutu Menengah, (Interior) Kg 30,000.00
18 Cat Tembok Mutu Menengah, (Exterior) Kg 55,000.00
19 Cat Besi Kg 70,000.00
20 Cat Genteng Kg 42,000.00
21 Plamir Tembok/ Plafond Kg 49,000.00
22 Teer Kg 36,000.00
23 Politur Liter 35,000.00
24 Politur Jadi Liter 36,000.00
25 Minyak Cat A Spesial Liter 38,000.00
26 Cat Marka Jalan Scalato Kg 103,000.00
27 Cat Marka Jalan Biasa Kg 91,000.00
28 Cat Zigromeat Kg 125,000.00
29 Vernis Ltr 36,000.00
30 Kuas 5 Cm Bh 28,000.00
31 Rol Cat Bh 35,000.00
32 Glassbeads Kg -
33 Roadline thener Ltr -
34 Cat Roadline paint Ltr -
35 Water Proofing Kg 65,000.00
36 Floor hardener 3 Kg/m2 m2 43,700.00
37 Cat Epoxy m2 68,700.00
38 ceramic stepnoosing 100 x 200 mm m1 159,300.00
39 Grooe line 2 cm m2 25,000.00
40 Floor hardener 7 Kg/m2 m2 56,200.00
41 Fiber Bakar m2 106,200.00
42 Cat tembok dulux Watersilt Pro Kg 118,700.00

Bahan Pengunci
1 kunci pintu mutu menengah Bh 164,000.00
2 kunci pintu mutu tinggi Bh 555,000.00
3 Yale 1 Slag Bh 103,000.00
4 Yale 2 Slag Bh 164,000.00
5 Kuda Terbang 1 Slag Bh 114,000.00
6 Kuda Terbang 2 Slag Bh 136,000.00
7 Royal Stel 85,000.00
8 Haag Angin Besar Stel 13,000.00
9 Haag Angin Kecil Stel 9,000.00
10 Grendel Besar Bh 23,000.00
11 Grendel Kecil Bh 13,000.00
12 Engsel Nylon Pas 20,000.00
13 Engsel H (biasa) Pas 16,000.00
14 Expagnolet Bh 103,000.00
15 Kunci Silinder Bh 63,000.00
16 Pegangan Pintu KW I Bh 260,000.00
17 Door Holder Bh -
18 Door Closer Bh 243,000.00
19 Door Stoper Bh 65,000.00
20 Kunci Selot Besar Bh 90,000.00
21 Kunci Selot Kecil Bh 70,000.00
22 Rel Pintu Dorong M' 42,000.00
23 Lubang Pintu Intip (Door Viewer) Bh 88,000.00

Bahan Sanitaire
1 Closet Duduk Biasa Bh 826,000.00
2 Closet Jongkok Teraso Bh 125,000.00
3 Closet Jongkok Porselin Bh 250,000.00
4 Wastapel (KW 1 Super) Bh 2,375,000.00
5 Wastapel Biasa Bh 481,000.00
6 Urinoir Porselin (KW 1 Super) Bh 2,726,000.00
7 Pembatas urinoir ex. TOTO A 100 bh 1,375,000.00
8 Kitchen Sink Stainless Steel ex. TOTO bh 2,156,200.00
9 Closet Duduk (KW 1 Super) Bh 3,659,000.00
10 Saringan Air Besi Bh 114,000.00
11 Saringan Air Plastik Bh 26,000.00
12 Bak Cuci Piring Teraso Bh 390,000.00
13 Bak Cuci Piring Logam, 1 lubang Bh 520,000.00
14 Bak Cuci Piring Logam, 2 lubang Bh 650,000.00
15 Resesvoir Fybg Kapasitas 1 M3 Bh 3,886,000.00
16 Septictank Kapasitas 1 M3 + peresapan Bh 5,350,000.00
17 Septictank Kapasitas 2 M3 + peresapan Bh 7,645,000.00
18 Bak Fiberglass Kap 0.5 M3 Bh 521,000.00
19 Bak Fiberglass Kap 1.0 M3 Bh 1,244,000.00
20 Bak Mandi Plastik Kap. 0,5 M3 Bh 520,000.00
21 Bak Mandi Teraso 50 x 50 cm Bh 481,000.00
22 Bak Mandi Poseslin KW I Bh 470,000.00
23 Kran Shower bh 362,500.00
24 Kran Air 1/2" Bh 18,000.00
25 Kran Air 3/4" Bh 21,000.00
26 Floor Drain ex. TOTO TX 1 BV 3 bh 396,200.00
27 Floor Drain Bh 25,000.00
28 Roof Drain Metal Bh 45,000.00
29 Seal Tape Bh 6,000.00
30 Lem Pipa Kg 79,000.00
31 Klep 3/4" Bh 35,000.00
32 Plampung Air Otomatis Bh 155,000.00
33 Tandon Air Fyberglass Kapasitas 500 Liter vertikal Bh 1,425,000.00
34 Tandon Air Fyberglass Kapasitas 1000 Liter vertikal Bh 2,091,000.00
35 Tandon Air Fyberglass Kapasitas 2000 Liter vertikal Bh 10,154,000.00
36 Tandon Air Fyberglass Kapasitas 3000 Liter vertikal Bh 13,684,000.00
37 Tandon Air Fyberglass Kapasitas 4000 Liter vertikal Bh 19,904,000.00
38 Tandon Air Fyberglass Kapasitas 5000 Liter vertikal Bh 21,961,000.00
39 Tandon Air Fyberglass Kapasitas 1000 Liter horisontal Bh 39,808,000.00
40 Tandon Air Fyberglass Kapasitas 2000 Liter horisontal Bh 55,076,000.00
41 Tandon Air Fyberglass Kapasitas 3000 Liter horisontal Bh 65,707,000.00
42 Tandon Air Fyberglass Kapasitas 4000 Liter horisontal Bh 76,439,000.00
43 Wastapel Merk Ina (KW I Super) Bh 2,373,000.00
44 Tempat Sabun (KW I) Bh 68,000.00
45 Cermin + Acessories (Antik) Bh 130,000.00
46 Gantungan Handuk + Acessories Bh 170,000.00
47 Shower spray ex. TOTO TX 403 SBPIV bh 812,500.00
48 Shower ex. TOTO TR 309 SZ bh 562,500.00
49 Paper Holder ex. TOTO TIPE TS116R bh 593,700.00
50 soap holder ex. TOTO S 156N bh 156,200.00
51 hand railing stainless steel ex. TOTO TX 3A2 bh 937,500.00
52 Shower Splay + Acessories Bh 452,000.00
53 Shower Set + Acessories Bh 700,000.00
54 Hand Dryer + Acessories Bh 1,470,000.00
55 Gantungan Baju + Acessories Bh 243,000.00
56 Water Drain + Acesories Bh 68,000.00
57 Pintu Fiber Glass (Wc) Bh 848,000.00
58 Pembuatan dan Pemasangan Pintu jeruji besi Ø12mm + Rangka kosen besi siku M2 1,555,000.00
59 40.40.4 complit
60 Bath Tub Bh 6,786,000.00
61 Kitchen Sink 1 Bowl GS 5844 bh 1,562,500.00
62 Kran + asesories + Seal Tape set 687,500.00
63 Kitchen Sink Single Bowl Zenit Ris 1B 1D 86 with Kitchen Tap My 1 By TEKA bh 3,875,000.00
64 Mirror 100x120 cm bh 270,000.00
65 Siku alumunium m1 81,200.00
66 Spoel hoek bh 11,000,000.00
67 Kran Air Antik Bh 66,000.00
68 Kran Zink Bh 400,000.00
69 Kitchenzink Bh 350,000.00
70 Kran Dinding Bh 215,000.00
71 sumur pompa tangan terpasang Bh 1,753,000.00

Bahan Paku
1 Paku panjang 1 - 5 Cm Kg 33,000.00
2 Paku panjang 5 - 7 Cm Kg 28,000.00
3 Paku panjang 7 - 10 Cm Kg 28,000.00
4 Paku panjang 10 - 12 Cm Kg 28,000.00
5 Paku Sekrup Kg 35,000.00
6 Paku Seng Kg 45,000.00
7 Paku Asbes Kg 45,000.00
8 Skrup/Piles 1,5 Cm Doos Kecil 35,000.00
9 Skrup/Piles 2,0 Cm Doos Kecil 35,000.00
10 Paku Sumbat Bh 38,000.00
11 Baut Mur Bh 5,000.00
12 Mur baut 12 mm Bh 6,000.00
13 Mur baut 16 mm Bh 7,000.00
14 Baut Mur 18 mm Bh 8,000.00
15 Baut Mur 22 mm Bh 10,000.00
16 Besi Beugel U + Baut Mur Bh 39,000.00
17 Besi Beugel Plat + Baut Mur Bh 39,000.00
18 Paku Calsiboth Kg 35,000.00
19 Paku Baja Kg 85,000.00
20 Angker Kusen Bh 5,000.00
21 Paku Sekrup 5 cm Kg 35,000.00
22 Paku Sekrup 10 cm Kg 35,000.00
23 Paku Sekrup 1- 2,5 cm Kg 35,000.00
24 Skrup Fixer Bh 22,000.00
25 Ramset/ Dinabolt Kg 75,000.00

Bahan Instalasi Listrik


1 Titik Lampu Bh 282,000.00
2 Stop Kontak Tanam Bh 209,000.00
3 Stop Kontak Luar Bh 226,000.00
4 Stop kontak dinding 200 W bh 22,900.00
5 Saklar Double Bh 37,900.00
6 Saklar Tunggal Bh 29,900.00
7 Zekering Boxes 1 Group Bh 419,000.00
8 Zekering Boxes 2 Group Bh 566,000.00
9 Zekering Boxes 3 Group Bh 701,000.00
10 Lampu Philip 18 W Bh 60,000.00
11 Lampu Philip 14 W Bh 49,000.00
12 Lampu Philip 5 W Bh 34,000.00
13 Lampu Pijar 25 W Bh 20,000.00
14 Lampu TL 40 W Bh 96,000.00
15 Lampu TL 2 x 18 W Bh 94,000.00
16 Lampu TL 2 x 36 W Bh 160,000.00
17 Lampu TL 2 x 40 W Bh 164,000.00
18 Lampu LED 2 x 14 W Bh 190,000.00
19 Lampu RMI TL LED T8 2 x 18 W bh 752,800.00
20 Lampu Sorot (Sejenis Mercury) Bh 701,000.00
21 Kabel NYA 2,5 mm Roll/50 300,000.00
22 Kabel NGA 2 x 2,5 mm Roll/50 576,000.00
23 Kabel NYM 3 x 2,5 mm Roll/50 704,000.00
24 Kabel NYM 3 x 1,5 mm Roll/50 576,000.00
25 Kabel NYM 2 x 2,5 mm Roll/50 576,000.00
26 Kabel NYM 2 x 1,5 mm Roll/50 396,000.00
27 Kabel NYM 4 x 6 mm Roll/50 1,645,000.00
28 Kabel NYY 4 x 10 mm² m1 58,700.00
29 Kabel NYY 4 x 50 mm m1 380,000.00
30 Kabel BCC 10 mm² m1 12,500.00
31 Kabel NYM 3 x 4 mm 2 m1 22,000.00
32 Kabel NYM 3 x 2.5 mm2 m1 15,400.00
33 Kabel NYM 2 x 2.5 mm 2 m1 11,000.00
34 Kabel NYY 4 x 25 mm2 m1 187,000.00
35 Kabel tray 400 mm x 100 mm m1 141,200.00
36 TeeTray 400 mm x 100 mm bh 575,300.00
37 El Bow Tray 400 mm x 100 mm bh 513,500.00
38 Kabel Ladder 400 mm x 100 mm m1 103,200.00
39 Kabel ITC 2x2x0.6 m1 6,000.00
40 Kabel BC 50 mm M' 50,000.00
41 Kabel BC 35 mm M' 40,000.00
42 Outlet telepon bh 56,400.00
43 Box Uk. 30 x 20 x 20 cm (tebal 2mm) bh 192,500.00
44 PABX Kap 4 lines, 16 Extension bh 16,500,000.00
45 MDF Telephone bh 2,750,000.00
46 Hand single Telephone unit 302,500.00
47 NYMHY 3x1,5mm m1 11,500.00
48 Sound terminal box unit 1,100,000.00
49 Ceiling Speaker bh 137,500.00
50 Attenuator 30W ZV-303 bh 162,800.00
51 Dynamic Microphone bh 269,800.00
52 CD Player CD-2011 R unit 2,200,000.00
53 Rack cabinet set 11,000,000.00
54 Remote Microphone w/Keypad Zone Selector bh 6,390,400.00
55 Power amplifier 240 W with 5 zone Selector system bh 5,500,000.00
56 Battery backup 2x1000 VA unit 3,598,200.00
57 Air terminal R-150 unit 10,450,000.00
58 Kabel NYY 1x70 mm2 for down conductor m1 123,200.00
59 Connecting Sleeve bh 418,000.00
60 Schoen cable CU 50 bh 22,000.00
61 Kabel conductor BC 70 mm² untuk gounding m1 58,900.00
62 Splitzen tembaga murni 3/4" bh 946,000.00
63 Timah kg 742,500.00
64 Pembuatan sumur grounding unit 2,750,000.00
65 Tarikan besi Ø10 mm kg 15,600.00
66 Fiting Lampu Bh 21,000.00
67 Fiting Lampu Tanam Dia. 4 " Bh 40,000.00
68 Fiting Lampu Tanam Dia. 3 " Bh 30,000.00
69 Box Panel 3 Phase, Comlite (80x120x25) Set 12,000,000.00
70 Box Panel 3 Phase, Comlite (50x70x20) Set 5,850,000.00
71 Box Panel 3 Phase, (30x40x15) Bh 1,100,000.00
72 Box Panel PVC 4 MCB, (40x60x20) Bh 390,000.00
73 MCB 6 A Bh 70,000.00
74 MCB 4 A Bh 66,000.00
75 Pemasukan Daya listrk KWH 2,500.00
76 Pemasangan Daya listrk VA 1,500.00
77 AC (Air Conditioner) Kapasiitas 2.5 PK Unit 19,243,900.00
78 AC (Air Conditioner) Kapasiitas 2 PK Unit 14,803,000.00
79 AC (Air Conditioner) Kapasiitas 1 1/2 PK Unit 11,102,200.00
80 AC (Air Conditioner) Kapasiitas 1 PK Unit 8,881,800.00
81 AC (Air Conditioner) Kapasiitas 1/2 PK Unit 4,440,900.00
82 Pipa refigerant 1/4 " m1 62,500.00
83 Pipa refigerant 3/8 " m1 62,500.00
84 Pipa refigerant 5/8" m1 106,250.00
85 Insulasi m' 25,000.00
86 Pas pengisap debu ruangan (Blower) + asisories complit Bh 166,000.00
87 Pas Lampu darurat + asisories complit Bh 154,000.00
88 Kabel Telepone 4 x 0.5 mm M' 30,000.00
89 Isolasi Bh 12,000.00
90 Outle TV Bh 50,000.00
91 Outle Telephone Bh 50,000.00
92 Dow ligth / PCL 13 W Bh 130,000.00
93 Dow ligth / PCL 8 W Bh 110,000.00
94 Dow ligth / LED 14 W Bh 152,000.00
95 Dow ligth / LED 7 W Bh 95,000.00
96 Dow ligth / LED 3 W Bh 40,000.00
97 Down Light Ø 6", LED 10.5 W bh 279,100.00
98 Down Light Ø 6", LED 7 W bh 192,800.00
99 Barret LED 18 W 1100 lm 6500 K bh 488,100.00
100 Lampu Tempel / LED 14 W Bh 250,000.00
101 Lampu spot light/ LED 7 W Bh 300,000.00
102 Lampu strip light/ LED 7 W M' 38,000.00
103 Electroda Cooper dia. 1 inci M' 340,000.00
104 Lampu Sorot taman spot light (LED), 10 watt Bh 300,000.00
105 Lampu taman Tanam (LED), 8 watt Bh 260,000.00
106 Bollard Lighting (LED), 9 watt Bh 3,575,000.00
107 Fire Detector, Sprinkler + Accessories (Hose Nozzle) 1,5" + Pipa GI + Pemasangan Bh 1,200,000.00
108 Pipa Conduit PVC dia. 20 mm2 M' 2,500.00
109 Exhaust Fan 472 CMH 12 W bh 302,500.00
110 Exshaust Fan 353 CFM/ 34 W bh 343,700.00
111 Wall Type Exshaust Fan 2500 CMH bh 1,068,700.00
112 Orbit Fan 60 Watt bh 710,000.00
113 Pemasangan Penangkal Petir + Arde (Radius min. 50 m) Unit 15,000,000.00
114 Pemasangan Penangkal Petir + Arde (Radius min. 25 m) Unit 12,500,000.00
115 Box panel uk (600 x 400 x 250) type wall mounted unit 2,108,200.00
116 MCCB 80 A 3~ 3P 25 kA bh 1,332,500.00
117 MCCB 40 A 3~ 3P 50 kA bh 1,853,700.00
118 MCCB 40 A 3~ 3P 18 kA bh 1,051,100.00
119 MCCB 40A / 3P / 10kA bh 701,800.00
120 MCB 16A / 1P / 10kA bh 161,700.00
121 MCB 10A / 1P / 10kA bh 161,700.00
122 Lampu Indikator bh 27,500.00
123 Fuse Lamp 2A bh 27,500.00
124 Bus Bar system Cu 5x(20x5mm) ls 935,000.00
125 Sepatu kabel+ Sleeve+ Cable tie ls 165,000.00
126 Grounding kabel BCC 35 mm2 ls 935,000.00
127 Wiring + Pemasangan ls 550,000.00
128 Inbowdoos seng bh 11,000.00
129 Kabel UTP Cat 6 m1 11,000.00
130 Outlet LAN bh 9,700.00
131 Optical terminal box unit 1,375,000.00
132 Switch Hub Utama 8 Port Manageable unit 17,242,500.00
133 Patch panel 8 port unit 1,650,000.00
134 Walmount Rack 12U unit 3,520,000.00
135 Material bantu ringan ls 5,000.00
136 Material bantu sedang ls 10,000.00
137 Material bantu T dos,klem,dll ls 18,700.00
138 Plat beton, tebal 80 mm, Tulangan # P8 - 150 m3 3,500,000.00
139 Lampu Sorot LED 100 W bh 1,105,000.00
140 Lampu Gantung LED 70 W bh 715,000.00
141 Stop Kontak / MCB bh 100,000.00
142 Stop Kontak AC bh 57,000.00

Pekerjaan Vegetasi Tanaman


1 Lempengan Rumput M² 7,350.00
2 Sirih Gading Bh 15,000.00
3 Bakung Lele Bh 10,500.00
4 Tanam perdu Bakung Lele tinggi 0,25 - 0,3 meter Bh 21,800.00
5 Tanam perdu Pisang Hias tinggi 0,7 - 0,8 meter Bh 15,600.00
6 Adam Hawa Bh 35,000.00
7 Sikas (tinggi ± 50 cm) Bh 980,000.00
8 Pucuk Merah (tinggi ± 60 - 70 cm) Bh 150,000.00
9 Pisang Hias (tinggi ± 50 - 100 cm) Bh 140,000.00
10 Palem Phoenix (tinggi ± 80 - 100 cm) Bh 280,000.00
11 Pandan Bali (tinggi ± 80 - 100 cm) Bh 1,050,000.00
12 Bugenvil (tinggi ± 80 - 100 cm) Bh 412,500.00
13 Ketappang Kencana (tinggi ± 200 cm) Bh 400,000.00
14 Palem Putri (tinggi ± 200 - 300 cm) Bh 750,000.00
15 Palem Kuning (tinggi ± 150 - 200 cm) Bh 750,000.00
16 Tabebuya Kuning tinggi 4 meter Bh 1,500,000.00
17 Tanam Pohon Palem raja tinggi 3 meter Bh 1,250,000.00
18 Tanam Pohon Kamboja tinggi 5 meter Bh 1,875,000.00
19 Tanam Pohon Pisang Kipas tinggi 1,5 meter Bh 125,000.00
20 Tanam perdu Honje Merah tinggi 0,7 - 0,8 meter Bh 18,700.00
21 Pohon Damar (Agathis dammara) Tinggi 4m Bh 831,200.00
22 Pohon Pulai (alstonia scholaris) Tinggi 6m Bh 1,187,500.00
23 Pohon Kasia Jawa (Cassia javanica) Tinggi 4m Bh 562,500.00
24 Pohon Kayu Kamper (Cinnamamum camphara) Tinggi 6m Bh 875,000.00
25 Pohon Flamboyan (Delonix regia) Tinggi 7m Bh 1,187,500.00
26 Pohon Biola Cantik (Ficus lyrata) Tinggi 6m Bh 812,500.00
27 Pohon Beringin Bodi (Ficus religiosa) Tinggi 6m Bh 1,062,500.00
28 Pohon Sosis (Kigelia pinnata) Tinggi 7m Bh 1,062,500.00
29 Pohon Bungur (Lagerstroemia speciasa) Tinggi 5m Bh 875,000.00
30 Pohon Flamboyan Kuning (Peltophorum pterocarpum) Tinggi 6m Bh 543,700.00
31 Pohon Kamboja Putih (Plumeria obtusa) Tinggi 5m Bh 1,462,500.00
32 Pohon Parahiba (Schizolobium parahyba) Tinggi 7m Bh 937,500.00
33 Pohon Tabebuya Pink (Tabebuia rosea) Tinggi 4m Bh 675,000.00
34 Pohon Bambu Kuning (Bambusa vulgaris) Tinggi 2,5m Bh 187,500.00
35 Pohon Pakis Monyet (Cibotium barometz) Tinggi 0,8m Bh 106,200.00
36 Pohon Palem Kol (Licualis grandis) Tinggi 1,5m Bh 156,200.00
37 Pohon Palem Sadeng (Livistona rotundifolia) Tinggi 3m Bh 1,875,000.00
38 Pohon Palem Kurma (Phoenix sylvestris) Tinggi 2m Bh 1,750,000.00
39 Pohon Pisang Kipas (Ravenala madagascariensis) Tinggi 1,5m Bh 562,500.00
40 Semak Agave (Agave angustifolia) Tinggi 300-400 mm Bh 100,000.00
41 Semak Paku Sarang Burung (Asplenium nidus) Tinggi 250-300mm Bh 62,500.00
42 Semak Fox Tail Agave (Agave attenuata) Tinggi 200-300 mm Bh 52,500.00
43 Semak Giant Arum (Typhonodarum lindleyanum) Tinggi 1500-2500 mm Bh 312,500.00
44 Semak Spineless (Spineless Yucca) Tinggi 800 mm Bh 168,700.00
45 Semak Sente (Alocosia macrorrhiza) Tinggi 700-800mm Bh 93,700.00
46 Semak Honje Merah (Alpinia purpurata) Tinggi 700-800mm Bh 18,700.00
47 Semak Kacang Emas (Arachis pintai) Tinggi 50-100mm Bh 21,200.00
48 Semak Bromelia Merah (Bromelia sp.) Tinggi 150-200mm Bh 43,700.00
49 Semak Pisang Hias (Calathea lutea) Tinggi 700-800mm Bh 43,700.00
50 Semak Kalatea Belang (Calathea zebrina) Tinggi 250-300mm Bh 18,700.00
51 Semak Bunga Pagoda (Cleorodendrum paniculatum) Tinggi 700-800mm Bh 87,500.00
52 Semak hanjuang Merah (Cordyline frusticosa) Tinggi 700-800mm Bh 18,700.00
53 Semak Pacing Merah (Costus woodsonii) Tinggi 400-500mm Bh 12,500.00
54 Semak Sirih Gading (Epipremnum aureum) Tinggi 300-500mm Bh 72,500.00
55 Semak Heliconia Bunga Pink (Heliconia chartacea) Tinggi 400-500mm Bh 9,300.00
56 Semak Bakung Lele (Hymenocallis littoralis) Tinggi 250-300mm Bh 12,500.00
57 Semak Pakis Kelabang (Nephrolepis exaltata) Tinggi 250-300mm Bh 25,000.00
58 Semak Alang Mini (Ophiopogon japonicus "dwarf") Tinggi 100-150mm Bh 18,700.00
59 Semak Aralia (Osmoxylon lineare) Tinggi 400-500mm Bh 9,300.00
60 Semak Pandan Pigmi (Pandanus pygmaeus) Tinggi 250-300mm Bh 25,000.00
61 Semak Daun Philo "Burle Marx" (Philadendron "Burle Marx") Tinggi 200-250mm Bh 31,200.00
62 Semak Daun Philo Besar (Philadendron sellaum) Tinggi 500-600mm Bh 37,500.00
63 Semak Daun Philo Xenadu (Philadendron xenadu) Tinggi 300-400mm Bh 46,200.00
64 Semak Cendrawasih (Phyllanthus myrtifolius) Tinggi 300-400mm Bh 11,200.00
65 Semak Melati Jepang (Pseuderanthemum reticulatum) Tinggi 400-500mm Bh 10,600.00
66 Semak kembang Air Mancur Merah (Russelia equisetiformis) Tinggi 400-500mm Bh 27,500.00
67 Semak Wali Songo Var. (Schefflera arbaricola) Tinggi 400-500mm Bh 43,700.00
68 Semak Lee Kuan Yew (Vernonia elliptica) Tinggi 300-500mm Bh 8,100.00
69 Semak Lili Brazil (Dianella tasmanica) Tinggi 250-300 Bh 12,500.00
70 Semak Opiopagon Hijau (Ophiopagon jaburan) Tinggi 300-400mm Bh 18,700.00
71 Semak Kembang Coklat (Zephyranthes candida) Tinggi 100-150 Bh 25,000.00
72 Semak Rumput Manila (Zoysia matrella) M² 62,500.00
73 Tanaman Cemara Bh 150,000.00
74 Tanaman Karambosa hijau Bh 120,000.00
75 Tanaman Karambosa Karigata Bh 135,000.00
76 Tanaman Batang Merah Bh 25,000.00
77 Tanaman Erpah Bh 65,000.00
78 Kembang pukul sembilan Bh 420,000.00
79 Kembang rumput kuning Bh 10,500.00
80 Bunga Agave Bh 725,000.00
81 Bunga Andong Bh 42,000.00
82 Bunga Asoka Bh 150,000.00
83 Bunga Brokoli Bh 52,500.00
84 Bunga Kembang Puring Bh 125,000.00
85 Bunga Lidah mertua mini Bh 52,500.00
86 Bunga Lidah Rumpun mertua mini Bh 787,500.00
87 Bunga Puring kerupuk Bh 262,500.00
88 Bunga Rumpun sansevieria Bh 21,000.00
89 Bunga Soft india Bh 780,500.00
90 Bunga Kembang sepatu Bh 260,000.00
91 Pupuk daun dan kembang Zak 157,500.00
92 Pupuk kandang kg 31,200.00
93 Insektisida / Furadan kg 30,000.00

Bahan Tambahan
1 Flux Oil Ltr 40,000.00
2 Minyak pelumas Ltr 47,000.00
3 Olie SAE 100 Ltr 37,000.00
4 Olie SAE 30 Ltr 50,000.00
5 Olie SAE 40 Ltr 62,000.00
6 Olie SAE 90 Ltr 74,000.00
7 Sambungan Rumah 1" Set 3,090,000.00
8 Sambungan Rumah 1/2" Set 1,854,000.00
9 Sambungan Rumah 3/4" Set 2,162,000.00
10 Aspal (AC) Kg 11,500.00
11 Kayu Bakar M³ 197,000.00
12 Sewa Stamper Hari 169,800.00
13 Sewa Alat Bor Hari 205,000.00
14 Sewa Genset Hari 410,000.00
15 Sewa Mesin Las Hari 410,000.00
16 Aspal Emulsi Kg 8,700.00
17 Alat Bantu Bina Marga Set 3,392,800.00
18 Alat Bantu Pengairan Set 3,392,800.00
19 Minyak tanah Ltr 4,700.00
20 Solar Ltr 6,500.00
21 Bensin Ltr 6,500.00
22 Pertalite Ltr 7,800.00
23 Pertamax Ltr 9,500.00
24 Pagar BRC tinggi 1,20 m M' 118,000.00
25 Tiang BRC dia. 1,5 Buah 67,000.00
26 Three Colour Btg 45,000.00
27 Mesin Las Unit 16,964,000.00
28 Bor Listrik Unit 1,131,000.00
29 Mesin Pemotong Besi Bh 1,131,000.00
30 KWH Listrik Kwh 1,500.00
31 Mata Bor Bh 56,000.00
32 Pelicin/Lubrican Kg 120,000.00
33 Alat Bantu Penyetelan (Trucker) Set 113,000.00
34 Alat batu pekerja Ls 11,000.00
35 Blower Bh 540,000.00
36 Excause Van Bh 540,000.00
37 #REF! M3 600,000.00
37 Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton 1,600,000.00
38 Lapis Resap Pengikat - Aspal Cair (Prime Coat) Liter 12,500.00
39 Bahan anti pengelupasan (Aditif) Kg 56,000.00

1 Pengeboran air + Pipa Casing Ø 6'' m 1,074,000.00


2 Pengeboran air + Pipa Casing Ø 4'' m 848,000.00
3 Pengeboran air + Pipa Casing Ø 3'' m 395,000.00
4 Pengeboran air + Pipa Casing Ø 2.5'' m 198,000.00
5 Mesin disel 6.5 . HP + Pompa Ebara ØINT 3'' OUT 3'' Unit 28,782,000.00
6 Mesin Pompa air 5 . HP Pompa ØINT OUT 2'' Unit 8,863,000.00
7 Mesin disel+Pompa Outo matis Jet pam ØINT OUT1.5'' - 30 Complit Unit 25,904,000.00
8 Mesin disel+Pompa Outo matis ( setara sanyo ) ØINT 1''- 20 Complit Unit 23,313,000.00
9 Mesin pompa air 5 . PK /type Hoda Unit 7,351,000.00
10 Mesin pompa air 8 . PK /type Hoda Unit 9,613,000.00
11 Slang Veleksibel Ø2.'' m 42,000.00
12 Slang Veleksibel Ø2.5.'' m 59,000.00
13 Slang Veleksibel Ø3.'' m 76,000.00
14 Mesin Jet Pump Kap. 250 watt Unit 3,700,000.00
15 Mesin Pompa Tekan Kap. 150 watt Unit 1,128,000.00
16 Sand Filter 520 ltr/mnt, (31.2 m3/jam), 2Hp - 3Hp, V 900 watt Unit 15,108,000.00
17 Sand Filter, (24.9 m3/jam), 2Hp - 3Hp, V 800 watt Unit 13,195,000.00
18 Tulisan Papan Nama, (Staenlis) - t = 1 cm + Pemasangan cm 17,000.00
19 Tulisan Papan Nama, (Galvanil) - t = 1 cm + Pemasangan cm 12,000.00
20 Tulisan Papan Nama, (Fiber) - t = 1 cm cm 7,000.00
21 Tulisan Papan Nama/ Logo, (Akrilik + lampu LED) - t = 1 cm cm 22,500.00

1 Genzet Outomatis zellent complit asisories 50 PK + pemasangan Unit 203,568,000.00


2 Pompa Ebara ØINT 3'' OUT 3'' Bh 8,651,000.00
3 Sewa Molen Kpst 0.3 m3 Hari 282,000.00
4 Mobilisasi Alat berat Km 282,000.00
5 Alat Berat Galian dan keprasan Jam 678,000.00
6 Alat berat Pemadatan Jam 622,000.00
7 Penatahalaman dan pembuatan taman + Bunga m2 168,000.00
8 Contaner ( tong sampah ). 2.5 X 3 x 1.5 m Bh 29,065,000.00
9 Alat bantu (Sewa Cren Kpst 7 ton) Hari 14,136,000.00
10 Mesin kompresor Bh 2,500,000.00

HARGA BAHAN MATERIAL TIDAK BERTEKANAN

Bahan Pipa
1 Pipa PVC ½" m 7,400.00
2 ¾" m 9,000.00
3 1" m 11,400.00
4 1 1/4" m 18,400.00
5 1½" m 23,900.00
6 2" m 35,500.00
7 2,5" m 45,600.00
8 3" m 65,100.00
9 4" m 94,900.00
10 5" m 149,800.00
11 6" m 197,900.00
12 8" m 307,900.00
13 10" m 437,500.00
14 12" m 625,100.00
15 14" m 879,500.00
16 16" m 1,099,400.00

1 Pipa GI 1/2" m 23,300.00


2 3/4" m 30,000.00
3 1" m 46,000.00
4 1 1/4" m 60,800.00
5 1½" m 69,700.00
6 2" m 95,200.00
7 2½" m 121,400.00
8 3" m 156,600.00
9 4" m 226,800.00
10 5" m 305,400.00
11 6" m 363,500.00
12 8" m 644,100.00

HARGA BAHAN MATERIAL BERTEKANAN

Bahan Pipa
1 Pipa PVC ½" m 8,200.00
2 ¾" m 15,000.00
3 1" m 18,700.00
4 1 1/4" m 21,000.00
5 1½" m 28,000.00
6 2" m 41,000.00
7 2,5" m 60,000.00
8 3" m 83,000.00
9 4" m 121,000.00
10 6" m 255,000.00
11 8" m 415,000.00
12 10" m 668,000.00

1 Pipa GI Medium 1/2" m 31,000.00


2 3/4" m 39,000.00
3 1" m 64,000.00
4 1 1/4" m 89,000.00
5 1½" m 102,000.00
6 2" m 109,000.00
7 2½" m 151,000.00
8 3" m 180,000.00
9 4" m 254,000.00
10 6" m 405,000.00
11 8" m 625,000.00

1 Pipa HDPE 1/2" m 8,000.00


2 1" m 18,000.00
3 1½" m 39,000.00
4 2" m 54,000.00
5 2.5" m 86,000.00
6 3" m 124,000.00
7 4" m 185,000.00
8 6" m 388,000.00
9 8" m 450,000.00

Jenis Barang
1 Flange Socket PVC 1,5" Bh 137,000.00
2 2" Bh 177,000.00
3 3" Bh 253,000.00
4 4" Bh 292,000.00
5 6" Bh 674,000.00
6 8" Bh 1,185,000.00
7 10" Bh 2,658,000.00
8 12" Bh 5,121,000.00

1 Flange Spigot PVC 1,5" Bh 126,000.00


2 2" Bh 177,000.00
3 2,5" Bh 221,000.00
4 3" Bh 253,000.00
5 4" Bh 292,000.00
6 6" Bh 578,000.00
7 8" Bh 1,007,000.00
8 10" Bh 2,440,000.00
9 12" Bh 4,821,000.00

1 Bend PVC RR/SP/S-12,5 1"x90° Bh 55,000.00


2 Bend PVC RR/SP/S-12,6 3/4"x90° Bh 52,000.00
3 ½"x90° Bh 49,000.00
4 Bend PVC RR/SP/S-12,5 1½"x90° Bh 73,000.00
5 2"x90° Bh 108,000.00
6 3"x90° Bh 178,000.00
7 4"x90° Bh 253,000.00
8 6"x90° Bh 530,000.00
9 8"x90° Bh 954,000.00
10 10"x90° Bh 1,679,000.00
11 12"x90° Bh 2,905,000.00

1 Bend PVC RR/SP/S-12,5 1,5"x45° Bh 82,000.00


2 2"x45° Bh 94,000.00
3 3"x45° Bh 159,000.00
4 4"x45° Bh 223,000.00
5 6"x45° Bh 482,000.00
6 8"x45° Bh 824,000.00
7 10"x45° Bh 1,532,000.00
8 12"x45° Bh 2,622,000.00
1 Bend PVC RR/SP/S-12,5 2"x22,5° Bh 82,000.00
2 3"x22,5° Bh 147,000.00
3 4"x22,5° Bh 206,000.00
4 6"x22,5° Bh 400,000.00
5 8"x22,5° Bh 694,000.00
6 10"x22,5° Bh 1,267,000.00
7 12"x22,5° Bh 2,116,000.00

1 Bend GI All Flange 1½"x45° Bh 257,000.00


2 2"x45° Bh 301,000.00
3 2,5"x45° Bh 333,000.00
4 3"x45° Bh 355,000.00
5 4"x45° Bh 475,000.00
6 6"x45° Bh 763,000.00
7 8"x45° Bh 1,182,000.00

1 Bend GI All Flange 1½"x90° Bh 292,000.00


2 2"x90° Bh 318,000.00
3 2,5"x90° Bh 350,000.00
4 3"x90° Bh 369,000.00
5 4"x90° Bh 498,000.00
6 6"x90° Bh 805,000.00
7 8"x90° Bh 1,259,000.00

1 Bend GI All Flange 1½"x22,5° Bh 222,000.00


2 2"x22,5° Bh 285,000.00
3 2,5"x22,5° Bh 323,000.00
4 3"x22,5° Bh 341,000.00
5 4"x22,5° Bh 451,000.00
6 6"x22,5° Bh 720,000.00
7 8"x22,5° Bh 1,104,000.00

1 Bend Drat GI 1½"x45° Bh 257,000.00


2 2"x45° Bh 301,000.00
3 2,5"x45° Bh 328,000.00
4 3"x45° Bh 355,000.00
5 4"x45° Bh 475,000.00
6 6"x45° Bh 763,000.00
7 8"x45° Bh 1,181,000.00

1 Bend Drat GI 3/4"x90° Bh 7,500.00


2 1"x90° Bh 196,000.00
3 Bend Drat GI/Knee GI ½"x90° Bh 4,500.00
4 Long Bend Female dan Male GI ½"x90° Bh 5,500.00
5 Bend Drat GI 1½"x90° Bh 239,000.00
6 2"x90° Bh 278,000.00
7 2,5"x90° Bh 318,000.00
8 3"x90° Bh 369,000.00
9 4"x90° Bh 498,000.00
10 6"x90° Bh 805,000.00
11 8"x90° Bh 1,259,000.00

1 Sock Drat GI ½" Bh 6,000.00


2 ¾" Bh 6,500.00
3 1" Bh 9,000.00
4 1½" Bh 18,000.00
5 2" Bh 25,000.00
6 2½" Bh 46,000.00
7 3" Bh 67,000.00
8 4" Bh 112,000.00
9 6" Bh 344,000.00
10 8" Bh 602,000.00

1 Sock PVC Drat Luar ½" Bh 5,000.00


2 ¾" Bh 7,500.00
3 1" Bh 12,000.00
4 1½" Bh 17,000.00
5 2" Bh 23,000.00
6 2½" Bh 46,000.00
7 3" Bh 64,000.00
8 4" Bh 81,000.00
9 6" Bh 157,000.00
10 8" Bh 315,000.00
1 Tee All Socket PVC / RR 1"x½" Bh 37,000.00
2 1"x1" Bh 75,000.00
3 1½"x½" Bh 79,000.00
4 1½"x3/4" Bh 92,000.00
5 1½"x1" Bh 117,000.00
6 1½"x1½" Bh 155,000.00
7 2"x 1" Bh 180,000.00
8 2"x2" Bh 194,000.00
9 3"x1" Bh 232,000.00
10 3"x2" Bh 270,000.00
11 3"x3" Bh 336,000.00
12 4"x2" Bh 412,000.00
13 4"x3" Bh 472,000.00
14 4"x4" Bh 513,000.00
15 6"x2" Bh 648,000.00
16 6"x3" Bh 737,000.00
17 6"x4" Bh 790,000.00
18 6"x6" Bh 954,000.00
19 8"x3" Bh 1,679,000.00
20 8"x4" Bh 1,614,000.00
21 8"x6" Bh 1,974,000.00
22 8"x8" Bh 2,180,000.00
23 10"x6" Bh 5,611,000.00
24 10"x8" Bh 6,565,000.00
25 10"x10" Bh 7,334,000.00

1 Reduser All Socket PVC / RR 1½"x1" Bh 83,000.00


2 ½"x1" Bh 37,000.00
3 1" x 3/4" Bh 41,000.00
4 1" x 1 1/4" Bh 49,000.00
5 2"x1" Bh 100,000.00
6 2"x1½" Bh 117,000.00
7 2"x2" Bh 152,000.00
8 3"x1" Bh 155,000.00
9 3"x2" Bh 164,000.00
10 4"x2" Bh 259,000.00
11 4"x3" Bh 265,000.00
12 6"x2" Bh 412,000.00
13 6"x3" Bh 419,000.00
14 6"x4" Bh 482,000.00
15 8"x3" Bh 960,000.00
16 8"x4" Bh 913,000.00
17 8"x6" Bh 860,000.00
18 10"x6" Bh 1,437,000.00
19 10"x8" Bh 1,296,000.00
20 12"x10" Bh 5,392,000.00

1 Dop GI ½" Bh 5,500.00


2 1" Bh 16,000.00
3 1½" Bh 26,000.00
4 2" Bh 79,000.00
5 3" Bh 159,000.00
6 4" Bh 196,000.00

1 Gilbout Joint CI 2" Bh 147,000.00


2 3" Bh 182,000.00
3 4" Bh 265,000.00
4 6" Bh 447,000.00
5 8" Bh 853,000.00
6 10" Bh 984,000.00
7 12" Bh 1,355,000.00
8 14" Bh 2,004,000.00
9 16" Bh 2,209,000.00

1 Flange Las 2" Bh 76,000.00


2 2,5" Bh 83,000.00
3 3" Bh 88,000.00
4 4" Bh 111,000.00
5 6" Bh 188,000.00
6 8" Bh 177,000.00
7 10" Bh 412,000.00
8 12" Bh 447,000.00
9 16" Bh 883,000.00

1 Gate Valve CI 1½" Bh 498,000.00


2 2" Bh 659,000.00
3 2,5" Bh 864,000.00
4 3" Bh 996,000.00
5 4" Bh 1,326,000.00
6 6" Bh 2,209,000.00
7 8" Bh 3,842,000.00
8 10" Bh 5,511,000.00
9 12" Bh 7,867,000.00
10 16" Bh 1,768,000.00

1 Clamp Sadel CI 1½"x½" Bh 32,000.00


2 2"x ½" Bh 55,000.00
3 2"x 3/4" Bh 58,000.00
4 2"x 1" Bh 60,000.00
5 3"x ½" Bh 64,000.00
6 4"x ½" Bh 74,000.00
7 4"x 2" Bh 100,000.00
8 6"x½" Bh 118,000.00
9 6"x 1" Bh 124,000.00
10 6"x 2" Bh 137,000.00
11 8"x 2" Bh 689,000.00
12 8"x 3" Bh 763,000.00

1 Hidran Umum Fiberglass 1000 lt Bh 5,619,000.00


2 2000 lt Bh 8,303,000.00
3 3000 lt Bh 11,113,000.00

1 Profile Tank 2200 lt Bh 5,304,000.00


1 Water Meter 1/2" Bh 334,000.00
2 3/4" Bh 530,000.00
3 1" Bh 1,002,000.00
4 2" Bh 1,503,000.00
5 3" Bh 2,098,000.00
6 4" Bh 2,688,000.00
7 6" Bh 3,418,000.00

1 Manometer 1/2" Bh 238,000.00

1 Stop Kran 1/2" Bh 57,000.00


2 3/4" Bh 89,000.00
3 1" Bh 221,000.00
4 1½" Bh 397,000.00
5 2" Bh 584,000.00
6 3" Bh 940,000.00
7 4" Bh 1,231,000.00
8 6" Bh 1,867,000.00

1 Streetbox 2" Bh 100,000.00


2 3" Bh 100,000.00
3 4" Bh 132,000.00
4 6" Bh 132,000.00
5 8" Bh 238,000.00

1 Chek Valve 1,5" Bh 344,000.00


2 2" Bh 583,000.00
3 2,5" Bh 842,000.00
4 3" Bh 1,007,000.00
5 4" Bh 1,538,000.00
6 6" Bh 2,811,000.00
7 8" Bh 3,447,000.00

1 Valve socket 1 1/4" Bh 68,000.00


2 1" Bh 58,000.00
3 2" Bh 79,000.00

1 Singel Air Valve ½" Bh 355,000.00


2 ¾" Bh 531,000.00
3 1" Bh 706,000.00
4 2" Bh 1,153,000.00
5 3" Bh 1,568,000.00

1 Tee GI All Flange 1½"x¾" Bh 139,000.00


2 1½"x1" Bh 169,000.00
3 1½"x1½" Bh 198,000.00
4 2"x1½" Bh 245,000.00
5 2"x2" Bh 344,000.00
6 2½"x2" Bh 370,000.00
7 2½"x2½" Bh 399,000.00
8 3"x2" Bh 411,000.00
9 3"x3" Bh 454,000.00
10 4"x2" Bh 482,000.00
11 4"x3" Bh 535,000.00
12 4"x4" Bh 587,000.00
13 6"x2" Bh 662,000.00
14 6"x3" Bh 746,000.00
15 6"x4" Bh 863,000.00
16 6"x6" Bh 908,000.00
17 8"x3" Bh 1,151,000.00
18 8"x4" Bh 1,205,000.00
19 8"x6" Bh 1,252,000.00
20 8"x8" Bh 1,418,000.00
21 Tee GI 1/2" x 1/2" Bh 5,000.00
22 1" x 1/2" Bh 24,000.00
23 1" x 1 " Bh 58,000.00
24 1,5" x 1,5 " Bh 79,000.00
25 2" x 2" Bh 95,000.00

1 Packing Rubber 8" Bh 101,000.00


2 6" Bh 78,000.00
3 4" Bh 54,000.00
4 3" Bh 36,000.00
5 2,5" Bh 31,000.00
6 2" Bh 22,000.00
7 1,5" Bh 16,000.00

1 Socket PVC ½" Bh 16,100.00


2 1" Bh 16,600.00
3 1½" Bh 17,500.00
4 2" Bh 23,200.00
5 2½" Bh 36,200.00
6 3" Bh 49,100.00
7 4" Bh 81,800.00
8 6" Bh 159,100.00
9 8" Bh 472,700.00

1 Socket PVC Drat Dalam ½" Bh 16,000.00


2 1" Bh 16,000.00
3 1½" Bh 17,000.00
4 2" Bh 23,000.00
5 2½" Bh 36,000.00
6 3" Bh 49,000.00
7 4" Bh 81,000.00
8 6" Bh 159,000.00
9 8" Bh 472,000.00

1 Dop PVC 1" Bh 17,000.00


2 1½" Bh 26,000.00
3 2" Bh 35,000.00
4 3" Bh 56,000.00
5 4" Bh 88,000.00
6 6" Bh 170,000.00
7 8" Bh 507,000.00

1 Stud Flange 1,5" Bh 99,000.00


2 2" Bh 113,000.00
3 3" Bh 128,000.00
4 4" Bh 142,000.00
5 6" Bh 331,000.00
6 8" Bh 659,000.00

1 Reduser HDPE 2" x 1" Bh 103,000.00


2 2" x 1.5" Bh 132,000.00
3 3" x 2" Bh 201,000.00
4 3" x 1,5" Bh 169,000.00
5 2" x 4" Bh 338,000.00
6 4" x 3" Bh 392,000.00
7 6" x 2" Bh 682,000.00
8 6" x 3" Bh 545,000.00
9 6" x 4" Bh 477,000.00
1 Tee Coupling HDPE 1,5" x 1" Bh 302,000.00
2 1" x 1" Bh 154,000.00
3 1" x 1/2" Bh 149,000.00

1 Tee HDPE 1,5" x 1,5" Bh 278,000.00


2 2" x 1" Bh 329,000.00
3 2" x 1,5" Bh 344,000.00
4 2" x 2" Bh 359,000.00
5 2" x 3" Bh 389,000.00
6 2" x 4" Bh 516,000.00
7 3" x 4" Bh 595,000.00
8 3" x 3" Bh 405,000.00
9 4" x 4" Bh 802,000.00
10 6" x 4" Bh 917,000.00
11 6" x 3" Bh 691,000.00
12 8" x 2" Bh 2,042,000.00

1 Reduser GI 1,5" x 2" Bh 153,000.00


2 2" x 3" Bh 180,000.00
3 2,5" x 2" Bh 211,000.00
4 2,5" x 3" Bh 238,000.00
5 2" x 4" Bh 285,000.00
6 3" x 4" Bh 291,000.00
7 4" x 6" Bh 530,000.00
8 1 1/2" x 1 1/4 Bh 159,000.00
9 1 1/2" x 1 Bh 127,000.00

1 Bend HDPE 1,5"x90° Bh 107,000.00


2 2"x90° Bh 164,000.00
3 3"x90° Bh 259,000.00
4 4"x90° Bh 590,000.00
5 6"x90° Bh 808,000.00
6 8"x90° Bh 1,849,000.00

1 Bend HDPE 1,5"x45° Bh 85,000.00


2 2"x45° Bh 148,000.00
3 3"x45° Bh 245,000.00
4 4"x45° Bh 567,000.00
5 6"x45° Bh 766,000.00
6 8"x45° Bh 1,772,000.00

1 Dop HDPE 1" Bh 103,000.00


2 1,5" Bh 164,000.00
3 2" Bh 193,000.00
4 3" Bh 35,000.00
5 4" Bh 375,000.00
6 6" Bh 675,000.00

1 Konektor HDPE 1" Bh 106,000.00


2 1,5" Bh 169,000.00
3 2" Bh 212,000.00
4 3" Bh 318,000.00
5 4" Bh 424,000.00

1 Male Elbow HDPE 2" Bh 162,000.00

1 Male Adaptor HDPE (Drat Luar) 3" Bh 106,000.00


2 2" Bh 101,000.00
3 1,5" Bh 77,000.00
4 1" Bh 55,000.00
5 1/2" Bh 43,000.00

1 Female Adaptor HDPE (Drat Dalam) 3" Bh 118,000.00


2 2" Bh 113,000.00
3 1,5" Bh 84,000.00
4 1" Bh 62,000.00
5 1/2" Bh 50,000.00

1 Pengadaan pompa Submersible type Centrifugal kapasitas 3 Ltr/Dtk, H 100, 3 Phase Unit 44,557,000.00
2 Pengadaan pompa Submersible type Centrifugal kapasitas 5 Ltr/Dtk, H 120, 3 Phase Unit 57,925,000.00
3 Kontrol Panel Auto Unit 9,270,000.00
4 Pengadaan Kabel NYYHY Ø 4 x 2,5 mm m 44,000.00
5 Pengadaan Kabel NYYHY Ø 3 x 0,75 mm m 31,000.00
6 Pengadaan Water Level Control (WLC) Bh 42,000.00
7 Pengadaan Cord Holder (Pengikat Kabel) Bungkus 91,000.00
8 Pengadaan Pipa Pelindung Kabel m 31,000.00
9 Pemasangan dan Set Up Pompa Set 3,605,000.00
10 Kawat Sling 12 mm m 28,000.00
11 8 mm m 22,000.00
12 6 mm m 21,000.00
13 Pemasangan Kawat Sling 12 mm m 9,000.00
14 8 mm m 8,000.00
15 6 mm m 6,000.00
16 Stelan seling 12 mm Bh 536,000.00
17 8 mm Bh 381,000.00
18 6 mm Bh 137,000.00
19 Pengunci seling 12 mm Bh 72,000.00
20 8 mm Bh 52,000.00
21 6 mm Bh 33,000.00
22 Angker Besi 22 mm Bh 21,000.00
23 Pekerjaan Snai Pipa Bh 5,500.00
24 Coupling GI 1/2" Bh 12,000.00

1 Verlop Ring water Tank Ø 2" 3/4" x 1/2" Bh 62,000.00


2 1" x 3/4" Bh 88,000.00
3 1,5" x 1" Bh 120,000.00

1 Double Nepel GI 3" Bh 49,000.00


2 2,5" Bh 34,000.00
3 2" Bh 29,000.00
4 1,5" Bh 26,000.00
5 1" Bh 21,000.00
6 1/2" Bh 18,000.00
7 Water Mur 1,5" Bh 90,000.00
8 Double Nepel PVC 1/2" Bh 6,500.00
9 Knee PVC drat dalam 1/2" Bh 9,500.00
10 Knee PVC 1/2" Bh 5,000.00
11 Tap Kran Bh 31,000.00
12 Plugh Kran 1/2" 1/2" Bh 66,000.00
13 Box Water Meter Bh 65,000.00
14 Pemasangan Meteran Air 1/2" Unit 26,000.00
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN PERSIAPAN
SNI.1 1 M2 Pembersihan Lapangan dan perataan
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
B BAHAN

C MATERIAL

Jumlah ( A + B + C ) 16,750.00
Keuntungan & Overhead 10 % 1,675.00
Jumlah ……………………… 18,425.00

SNI.2 1 M Pengukuran dan Pemasangan Bouwplank


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.012 M³ Balok Kayu Klas III 2,600,000.00 31,200.00
0.007 M³ Papan Kayu Klas III 2,600,000.00 18,200.00
0.020 Kg Paku 2" - 5" 33,000.00 660.00
B TENAGA
0.100 OH Pekerja 100,000.00 10,000.00
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.005 OH Mandor 135,000.00 675.00
C PERALATAN

Jumlah ( A + B + C ) 75,735.00
Keuntungan & Overhead 10 % 7,573.50
Jumlah ……………………… 83,308.50

SNI.3 1 Bh Pembuatan Papan nama Proyek 0,8 x 1,2 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 Bh Papan Nama 200,000.00 200,000.00
B TENAGA
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
C PERALATAN

Jumlah ( A + B + C ) 216,750.00
Keuntungan & Overhead 10 % 21,675.00
Jumlah ……………………… 238,425.00

SNI.4a 1 m2 Pagar Pengaman Lokasi Dari seng gelombang tinggi 2m


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.200 OH Pekerja 100,000.00 20,000.00
0.400 OH Tk Kayu 135,000.00 54,000.00
0.020 OH Kp Tukang 150,000.00 3,000.00
0.020 OH Mandor 135,000.00 2,700.00
B BAHAN
1.250 Btg Dolken 11,000.00 13,750.00
2.500 Kg Semen Pc 1,700.00 4,250.00
1.200 Lbr Seng gelombang 67,000.00 80,400.00
0.005 m3 Pasir 220,000.00 1,100.00
0.009 m3 Kerikil 339,000.00 3,051.00
0.072 m3 Kayu 5/7 2,600,000.00 187,200.00
0.060 Kg Paku 5 - 7 cm 28,000.00 1,680.00
C PERALATAN
-
Jumlah ( A + B + C ) 371,131.00
Keuntungan & Overhead 10 % 37,113.10
Jumlah ……………………… 408,244.10
SNI.4b 1 m2 Pagar Pengaman Lokasi Dari seng gelombang tinggi 2m
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.150 m3 Pekerja 100,000.00 15,000.00
0.300 m3 Tk Kayu 135,000.00 40,500.00
0.015 m3 Kp Tukang 150,000.00 2,250.00
0.015 m3 Mandor 135,000.00 2,025.00
B BAHAN
1.250 Btg Dolken 11,000.00 13,750.00
1.200 Lbr Seng gelombang 67,000.00 80,400.00
0.072 m3 Kayu 5/7 2,600,000.00 187,200.00
0.060 Kg Paku 5 - 7 cm 28,000.00 1,680.00
0 PERALATAN
-
Jumlah ( A + B + C ) 342,805.00
Keuntungan & Overhead 10 % 34,280.50
Jumlah ……………………… 377,085.50

SNI.5 1 m2 . Pembuatan Direksiket/Kantor sementara


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
1.000 OH Pekerja 100,000.00 100,000.00
1.000 OH Tk Kayu 135,000.00 135,000.00
0.300 OH Kp Tukang 150,000.00 45,000.00
0.050 OH Mandor 28,000.00 1,400.00
B BAHAN
0.168 m3 Kayu 5/7 2,600,000.00 436,800.00
0.080 kg Paku 5 - 7 cm 28,000.00 2,240.00
0.250 lbr seng gelombang 67,000.00 16,750.00
0.046 lbr Triplek 5mm 105,000.00 4,830.00
30.500 kg semen Pc 1,700.00 51,850.00
0.200 m3 Pasir 220,000.00 44,000.00
0.150 m3 Kerikil 339,000.00 50,850.00
30.000 bh Bata merah 850.00 25,500.00
C PERALATAN
-
Jumlah ( A + B + C ) 914,220.00
Keuntungan & Overhead 10 % 91,422.00
Jumlah ……………………… 1,005,642.00

PEKERJAAN PEMBONGKARAN BANGUNAN LAMA


SNI.6 1 M2 Pembongkaran Dinding Tembok Bata Merah Lama
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
3.334 OH Pekerja 100,000.00 333,350.00
0.333 OH Mandor 135,000.00 45,002.25
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 378,352.25
Keuntungan & Overhead 10 % 37,835.23
Jumlah ……………………… 416,187.48

SNI.7 1 M3 Pembongkaran Beton Bertulang Lama


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
6.667 OH Pekerja 100,000.00 666,700.00
0.667 OH Mandor 135,000.00 90,004.50
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 756,704.50
Keuntungan & Overhead 10 % 75,670.45
Jumlah ……………………… 832,374.95

SNI.8 1 m2 Bongkar Usuk + Reng Untuk Dipakai Kembali


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.200 OH Pekerja 100,000.00 20,000.00
0.050 OH Tukang Kayu 135,000.00 6,750.00
0.005 OH Kepala Tukang Kayu 150,000.00 750.00
0.005 OH Mandor 135,000.00 675.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 28,175.00
Keuntungan & Overhead 10 % 2,817.50
Jumlah ……………………… 30,992.50

SNI.9 1 M2 Pembongkaran Atap Seng Gelombang


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.100 OH Pekerja 100,000.00 10,000.00
0.007 OH Mandor 135,000.00 945.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 10,945.00
Keuntungan & Overhead 10 % 1,094.50
Jumlah ……………………… 12,039.50

PEKERJAAN TANAH DAN PASIR


SNI.10.a 1 M3 Galian Tanah Biasa sedalam 0.5 - 1 M' - Dengan manual
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.750 OH Pekerja 100,000.00 75,000.00
0.025 OH Mandor 135,000.00 3,375.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 78,375.00
Keuntungan & Overhead 10 % 7,837.50
Jumlah ……………………… 86,212.50

SNI.10.b 1 M3 Galian Tanah Biasa sedalam 0.5 - 1 M' - Dengan mengunakan alat berat
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.750 OH Pekerja 100,000.00 75,000.00
0.025 OH Mandor 135,000.00 3,375.00
B BAHAN

C PERALATAN
0.010 Jam Alat Berat Galian dan keprasan 678,000.00 6,780.00

Jumlah ( A + B + C ) 85,155.00
Keuntungan & Overhead 10 % 8,515.50
Jumlah ……………………… 93,670.50

SNI.11.a 1 M3 Galian Tanah Biasa sedalam 2 M', Dengan Manual


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.900 OH Pekerja 100,000.00 90,000.00
0.045 OH Mandor 135,000.00 6,075.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 96,075.00
Keuntungan & Overhead 10 % 9,607.50
Jumlah ……………………… 105,682.50

SNI.11.b 1 M3 Galian Tanah Biasa sedalam 2 M' - Dengan mengunakan alat berat
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.900 OH Pekerja 100,000.00 90,000.00
0.045 OH Mandor 135,000.00 6,075.00
B BAHAN

C PERALATAN
0.010 Jam Alat Berat Galian dan keprasan 678,000.00 6,780.00

Jumlah ( A + B + C ) 102,855.00
Keuntungan & Overhead 10 % 10,285.50
Jumlah ……………………… 113,140.50

SNI.12 1 M3 Galian Tanah Biasa sedalam 3 M'


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
1.050 OH Pekerja 100,000.00 105,000.00
0.067 OH Mandor 135,000.00 9,045.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 114,045.00
Keuntungan & Overhead 10 % 11,404.50
Jumlah ……………………… 125,449.50

SNI.13 1 M3 Galian Tanah Keras sedalam 1 M'


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
1.000 OH Pekerja 100,000.00 100,000.00
0.032 OH Mandor 135,000.00 4,320.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 104,320.00
Keuntungan & Overhead 10 % 10,432.00
Jumlah ……………………… 114,752.00

SNI.14 1 M3 Galian Tanah Cadas sedalam 1 M'


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
1.500 OH Pekerja 100,000.00 150,000.00
0.060 OH Mandor 135,000.00 8,100.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 158,100.00
Keuntungan & Overhead 10 % 15,810.00
Jumlah ……………………… 173,910.00

SNI.15 1 M3 Galian Tanah Lumpur sedalam 1 M'


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
1.200 OH Pekerja 100,000.00 120,000.00
0.045 OH Mandor 135,000.00 6,075.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 126,075.00
Keuntungan & Overhead 10 % 12,607.50
Jumlah ……………………… 138,682.50

SNI.16 1 M2 Pekerjaan Stripping tanah Tebing setinggi 1 M'


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.050 OH Pekerja 100,000.00 5,000.00
0.005 OH Mandor 135,000.00 675.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 5,675.00
Keuntungan & Overhead 10 % 567.50
Jumlah ……………………… 6,242.50

SNI.17 1 M3 Urugan Kembali Tanah galian


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.250 OH Pekerja 100,000.00 25,000.00
0.025 OH Mandor 135,000.00 3,375.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 28,375.00
Keuntungan & Overhead 10 % 2,837.50
Jumlah ……………………… 31,212.50

SNI.18 1 M3 Pemadatan Tanah Per 20 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.500 OH Pekerja 100,000.00 50,000.00
0.050 OH Mandor 135,000.00 6,750.00
B BAHAN

C PERALATAN

Jumlah ( A + B + C ) 56,750.00
Keuntungan & Overhead 10 % 5,675.00
Jumlah ……………………… 62,425.00

SNI.19 1 M3 Urugan Tanah (dipadatkan)


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Tanah Urug 121,000.00 145,200.00
B TENAGA
0.500 OH Pekerja 100,000.00 50,000.00
0.050 OH Mandor 135,000.00 6,750.00
C PERALATAN

Jumlah ( A + B + C ) 201,950.00
Keuntungan & Overhead 10 % 20,195.00
Jumlah ……………………… 222,145.00

SNI.20 1 M3 Urugan Tanah Biasa tampa pemadatan


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Tanah Urug 121,000.00 145,200.00
B TENAGA
0.250 OH Pekerja 100,000.00 25,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN

Jumlah ( A + B + C ) 173,575.00
Keuntungan & Overhead 10 % 17,357.50
Jumlah ……………………… 190,932.50
SNI.21 1 M3 Urug dengan pasir urug
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Pasir Urug 190,000.00 228,000.00
B TENAGA
0.300 OH Pekerja 100,000.00 30,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 259,350.00
Keuntungan & Overhead 10 % 25,935.00
Jumlah ……………………… 285,285.00

SNI.22 1 M3 Urugan Sirtu/ Material Pilihan padat


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Sirtu 237,000.00 284,400.00
B TENAGA
0.250 OH Pekerja 100,000.00 25,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN

Jumlah ( A + B + C ) 312,775.00
Keuntungan & Overhead 10 % 31,277.50
Jumlah ……………………… 344,052.50

PEKERJAAN PASANGAN, PLESTERAN DAN LANTAI


SNI.23 1 M3 Pasangan Batu Kosong ( anstamping )
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Batu Kali Alam 226,000.00 271,200.00
0.432 M³ Pasir Urug 190,000.00 82,080.00
B TENAGA
0.390 OH Tukang Batu 135,000.00 52,650.00
0.039 OH Kepala Tukang Batu 150,000.00 5,850.00
0.780 OH Pekerja 100,000.00 78,000.00
0.039 OH Mandor 135,000.00 5,265.00
C PERALATAN

Jumlah ( A + B + C ) 495,045.00
Keuntungan & Overhead 10 % 49,504.50
Jumlah ……………………… 544,549.50

SNI.24 1 M3 Pasangan Batu Kali 1 Pc : 4 Psr


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Batu Kali Belah 15/20 cm 240,000.00 288,000.00
163.000 Kg Semen 1,700.00 277,100.00
0.520 M³ Pasir Pasang 220,000.00 114,400.00
B TENAGA
0.600 OH Tukang Batu 135,000.00 81,000.00
0.060 OH Kepala Tukang Batu 150,000.00 9,000.00
1.500 OH Pekerja 100,000.00 150,000.00
0.075 OH Mandor 135,000.00 10,125.00
C PERALATAN

Jumlah ( A + B + C ) 929,625.00
Keuntungan & Overhead 10 % 92,962.50
Jumlah ……………………… 1,022,587.50

SNI.25.a 1 M3 Pasangan Batu Kali 1 Pc : 5 Psr


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Batu Kali Belah 15/20 cm 240,000.00 288,000.00
136.000 Kg Semen 1,700.00 231,200.00
0.544 M³ Pasir Pasang 220,000.00 119,680.00
B TENAGA
0.600 OH Tukang Batu 135,000.00 81,000.00
0.060 OH Kepala Tukang Batu 150,000.00 9,000.00
1.500 OH Pekerja 100,000.00 150,000.00
0.075 OH Mandor 135,000.00 10,125.00
C PERALATAN

Jumlah ( A + B + C ) 889,005.00
Keuntungan & Overhead 10 % 88,900.50
Jumlah ……………………… 977,905.50

SNI.25.b 1 M3 Pasangan Batu Kali 1 Pc : 6 Psr


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Batu Kali Belah 15/20 cm 240,000.00 288,000.00
117.000 Kg Semen 1,700.00 198,900.00
0.561 M³ Pasir Pasang 220,000.00 123,420.00
B TENAGA
0.600 OH Tukang Batu 135,000.00 81,000.00
0.060 OH Kepala Tukang Batu 150,000.00 9,000.00
1.500 OH Pekerja 100,000.00 150,000.00
0.075 OH Mandor 135,000.00 10,125.00
C PERALATAN

Jumlah ( A + B + C ) 860,445.00
Keuntungan & Overhead 10 % 86,044.50
Jumlah ……………………… 946,489.50
SNI.26 1 M3 Pasangan Pondasi Sumuran Ø100 cm
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.450 M³ Batu Kali Belah 15/20 cm 240,000.00 108,000.00
194.000 Kg Semen 1,700.00 329,800.00
0.312 M³ Pasir beton 350,000.00 109,200.00
0.468 M³ Kerikil 565,000.00 264,420.00
B TENAGA
0.800 OH Tukang Batu 135,000.00 108,000.00
0.080 OH Kepala Tukang Batu 150,000.00 12,000.00
2.400 OH Pekerja 100,000.00 240,000.00
0.119 OH Mandor 135,000.00 16,065.00
C PERALATAN

Jumlah ( A + B + C ) 1,187,485.00
Keuntungan & Overhead 10 % 118,748.50
Jumlah ……………………… 1,306,233.50

SNI.27 1 M2 Pasangan Dinding bata berongga / roster (10 x 20)


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
30.000 Bh Roster 14,000.00 420,000.00
14.000 Kg Semen 1,700.00 23,800.00
0.032 M³ Pasir Pasang 220,000.00 7,040.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 505,365.00
Keuntungan & Overhead 10 % 50,536.50
Jumlah ……………………… 555,901.50

SNI.27.b 1 M2 Pasangan Dinding bata berongga / roster (20 x 20)


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
30.000 Bh Roster 15,000.00 450,000.00
14.000 Kg Semen 1,700.00 23,800.00
0.032 M³ Pasir Pasang 220,000.00 7,040.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 535,365.00
Keuntungan & Overhead 10 % 53,536.50
Jumlah ……………………… 588,901.50

SNI.27.c 1 M2 Pasangan Dinding bata berongga / roster (30 x 30)


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
30.000 Bh Roster 20,000.00 600,000.00
14.000 Kg Semen 1,700.00 23,800.00
0.032 M³ Pasir Pasang 220,000.00 7,040.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 685,365.00
Keuntungan & Overhead 10 % 68,536.50
Jumlah ……………………… 753,901.50

SNI.28 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 3 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
14.370 Kg Semen 1,700.00 24,429.00
0.040 M³ Pasir Pasang 220,000.00 8,800.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 146,754.00
Keuntungan & Overhead 10 % 14,675.40
Jumlah ……………………… 161,429.40

SNI.29.a 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 4 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
11.500 Kg Semen 1,700.00 19,550.00
0.043 M³ Pasir Pasang 220,000.00 9,460.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 142,535.00
Keuntungan & Overhead 10 % 14,253.50
Jumlah ……………………… 156,788.50

SNI.29.b 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 5 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
9.680 Kg Semen 1,700.00 16,456.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 139,881.00
Keuntungan & Overhead 10 % 13,988.10
Jumlah ……………………… 153,869.10

SNI.29.c 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 6 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
8.320 Kg Semen 1,700.00 14,144.00
0.049 M³ Pasir Pasang 220,000.00 10,780.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 138,449.00
Keuntungan & Overhead 10 % 13,844.90
Jumlah ……………………… 152,293.90

SNI.29.d 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 8 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
6.500 Kg Semen 1,700.00 11,050.00
0.050 M³ Pasir Pasang 220,000.00 11,000.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 135,575.00
Keuntungan & Overhead 10 % 13,557.50
Jumlah ……………………… 149,132.50

SNI.29.R Pemasangan 1 m2 dinding bata ringan tebal 10 X 20 X 60 cm + dengan mortar


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
8.400 Biji Bata ringan/Hebel, 10X20X60 19,000.00 159,600.00
0.063 Kg Mortar siap pakai 5,000.00 316.00
B TENAGA
1.300 OH Tukang Batu 135,000.00 175,500.00
0.130 OH Kepala Tukang 150,000.00 19,500.00
0.671 OH Pekerja 100,000.00 67,100.00
0.003 OH Mandor 135,000.00 405.00
C PERALATAN
0.100 Ls Alat bantu 11,000.00 1,100.00
Jumlah ( A + B + C ) 423,521.00
Keuntungan & Overhead 10 % 42,352.10
Jumlah ……………………… 465,873.10

SNI.30 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1 bata, spesi 1 PC : 3 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
140.000 Biji Bata Merah 950.00 133,000.00
32.950 Kg Semen 1,700.00 56,015.00
0.091 M³ Pasir Pasang 220,000.00 20,020.00
B TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00
0.600 OH Pekerja 100,000.00 60,000.00
0.030 OH Mandor 135,000.00 4,050.00
C PERALATAN

Jumlah ( A + B + C ) 303,085.00
Keuntungan & Overhead 10 % 30,308.50
Jumlah ……………………… 333,393.50

SNI.31 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1 bata, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
140.000 Biji Bata Merah 950.00 133,000.00
26.550 Kg Semen 1,700.00 45,135.00
0.093 M³ Pasir Pasang 220,000.00 20,460.00
B TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00
0.600 OH Pekerja 100,000.00 60,000.00
0.030 OH Mandor 135,000.00 4,050.00
C PERALATAN

Jumlah ( A + B + C ) 292,645.00
Keuntungan & Overhead 10 % 29,264.50
Jumlah ……………………… 321,909.50

SNI.32 1 M2 Pasangan Dinding Batako 1 Pc : 4 Psr


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
12.500 Biji Batako 4,000.00 50,000.00
5.750 Kg Semen 1,700.00 9,775.00
0.022 M³ Pasir Pasang 220,000.00 4,730.00
B TENAGA
0.080 OH Tukang Batu 135,000.00 10,800.00
0.008 OH Kepala Tukang 150,000.00 1,200.00
0.256 OH Pekerja 100,000.00 25,600.00
0.012 OH Mandor 135,000.00 1,620.00
C PERALATAN

Jumlah ( A + B + C ) 103,725.00
Keuntungan & Overhead 10 % 10,372.50
Jumlah ……………………… 114,097.50

SNI.33 1 M2 Pasangan Rollag 1 Bata Merah 1 Pc : 3 Ps


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
140.000 Biji Bata Merah 950.00 133,000.00
14.370 Kg Semen 1,700.00 24,429.00
0.040 M³ Pasir Pasang 220,000.00 8,800.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 213,254.00
Keuntungan & Overhead 10 % 21,325.40
Jumlah ……………………… 234,579.40

SNI.34.a 1 M2 Acian halus dengan Pc


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
3.250 Kg Semen Pc 1,700.00 5,525.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 41,875.00
Keuntungan & Overhead 10 % 4,187.50
Jumlah ……………………… 46,062.50

SNI.34.b 1 M2 Plesteran + Acian halus dinding bata ringan/Hebel


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
6.240 Kg Semen-MU 380 , 40 Kg 4,500.00 28,080.00
3.250 Kg Semen-MU 200 , 40 Kg 5,000.00 16,250.00
B TENAGA
0.250 OH Tukang Batu 135,000.00 33,750.00
0.025 OH Kepala Tukang Batu 150,000.00 3,750.00
0.500 OH Pekerja 100,000.00 50,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN
0.100 Ls Alat bantu 11,000.00 1,100.00
Jumlah ( A + B + C ) 136,305.00
Keuntungan & Overhead 10 % 13,630.50
Jumlah ……………………… 149,935.50

SNI.34.c 1 M2 Plesteran dinding bata ringan/Hebel


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
6.240 Kg Semen-MU 380 , 40 Kg 4,500.00 28,080.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN
0.100 Ls Mandor 11,000.00 1,100.00
Jumlah ( A + B + C ) 83,705.00
Keuntungan & Overhead 10 % 8,370.50
Jumlah ……………………… 92,075.50

SNI.34.d 1 M2 Plesteran Beton 1 PC : 2 Ps Tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
9.300 Kg Semen Pc 1,700.00 15,810.00
0.018 M3 Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang Batu 150,000.00 3,000.00
0.260 OH Pekerja 100,000.00 26,000.00
0.013 OH Mandor 135,000.00 1,755.00
C PERALATAN

Jumlah ( A + B + C ) 77,525.00
Keuntungan & Overhead 10 % 7,752.50
Jumlah ……………………… 85,277.50

SNI.34.e 1 M2 Plesteran Beton 1 PC : 3 Ps Tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
7.070 Kg Semen Pc 1,700.00 12,019.00
0.021 M3 Pasir Pasang 220,000.00 4,620.00
B TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang Batu 150,000.00 3,000.00
0.260 OH Pekerja 100,000.00 26,000.00
0.013 OH Mandor 135,000.00 1,755.00
C PERALATAN

Jumlah ( A + B + C ) 74,394.00
Keuntungan & Overhead 10 % 7,439.40
Jumlah ……………………… 81,833.40

SNI.35.a 1 M2 Siar Pas batu Kali


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
6.340 Kg Semen 1,700.00 10,778.00
0.012 m3 Pasir Pasang 220,000.00 2,640.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 67,943.00
Keuntungan & Overhead 10 % 6,794.30
Jumlah ……………………… 74,737.30

SNI.35.b 1 m2 Finishing Siar pasangan bata merah


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
3.108 Kg Semen Portland 1,700.00 5,283.60
B TENAGA
0.075 OH Tukang Batu 135,000.00 10,125.00
0.008 OH Kepala Tukang Batu 150,000.00 1,200.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
C PERALATAN

Jumlah ( A + B + C ) 32,688.60
Keuntungan & Overhead 10 % 3,268.86
Jumlah ……………………… 35,957.46

SNI.36 1 m2 Plesteran 1 Pc : 3 Pp tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
7.760 Kg Semen Portland 1,700.00 13,192.00
0.023 m3 Pasir Pasang 220,000.00 5,060.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 72,777.00
Keuntungan & Overhead 10 % 7,277.70
Jumlah ……………………… 80,054.70

SNI.37.a 1 m2 Plesteran 1 Pc : 4 Pp tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
6.240 Kg Semen Portland 1,700.00 10,608.00
0.024 m3 Pasir Pasang 220,000.00 5,280.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 70,413.00
Keuntungan & Overhead 10 % 7,041.30
Jumlah ……………………… 77,454.30

SNI.37.b 1 m2 Plesteran 1 Pc : 5 Pp tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
5.184 Kg Semen Portland 1,700.00 8,812.80
0.026 m3 Pasir Pasang 220,000.00 5,720.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 69,057.80
Keuntungan & Overhead 10 % 6,905.78
Jumlah ……………………… 75,963.58

SNI.37.c 1 m2 Plesteran 1 Pc : 6 Pp tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
4.416 Kg Semen Portland 1,700.00 7,507.20
0.027 m3 Pasir Pasang 220,000.00 5,940.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 67,972.20
Keuntungan & Overhead 10 % 6,797.22
Jumlah ……………………… 74,769.42

SNI.37.d 1 m2 Plesteran 1 Pc : 7 Pp tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
3.936 Kg Semen Portland 1,700.00 6,691.20
0.028 m3 Pasir Pasang 220,000.00 6,160.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 67,376.20
Keuntungan & Overhead 10 % 6,737.62
Jumlah ……………………… 74,113.82

SNI.37.e 1 m2 Plesteran 1 Pc : 8 Pp tebal 15 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
3.456 Kg Semen Portland 1,700.00 5,875.20
0.029 m3 Pasir Pasang 220,000.00 6,380.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang Batu 150,000.00 2,250.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 66,780.20
Keuntungan & Overhead 10 % 6,678.02
Jumlah ……………………… 73,458.22

SNI.38 1 m2 Plesteran 1 Pc : 3 Pp tebal 20 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
10.368 Kg Semen Portland 1,700.00 17,625.60
0.031 m3 Pasir Pasang 220,000.00 6,820.00
B TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang Batu 150,000.00 3,000.00
0.260 OH Pekerja 100,000.00 26,000.00
0.013 OH Mandor 135,000.00 1,755.00
C PERALATAN

Jumlah ( A + B + C ) 82,200.60
Keuntungan & Overhead 10 % 8,220.06
Jumlah ……………………… 90,420.66

SNI.39 1 m2 Plesteran 1 Pc : 4 Pp tebal 20 mm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
8.680 Kg Semen Portland 1,700.00 14,756.00
0.025 m3 Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang Batu 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.022 OH Mandor 135,000.00 2,970.00
C PERALATAN

Jumlah ( A + B + C ) 93,226.00
Keuntungan & Overhead 10 % 9,322.60
Jumlah ……………………… 102,548.60

SNI.40.a 1 m2 Plesteran Ciprat 1 Pc : 2 Pp


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
4.320 Kg Semen Portland 1,700.00 7,344.00
0.006 m3 Pasir Pasang 220,000.00 1,320.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 55,689.00
Keuntungan & Overhead 10 % 5,568.90
Jumlah ……………………… 61,257.90

SNI.40.b 1 m1 Plesteran Skoning / Benangan 1 Pc : 3 Pp, lebar 10 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.500 Kg Semen Portland 1,700.00 850.00
0.013 m3 Pasir Pasang 220,000.00 2,860.00
B TENAGA
0.400 OH Tukang Batu 135,000.00 54,000.00
0.040 OH Kepala Tukang Batu 150,000.00 6,000.00
0.080 OH Pekerja 100,000.00 8,000.00
0.004 OH Mandor 135,000.00 540.00
C PERALATAN

Jumlah ( A + B + C ) 72,250.00
Keuntungan & Overhead 10 % 7,225.00
Jumlah ……………………… 79,475.00

SNI.41 Pasang Kanstin Cetak 600x150x250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.667 m1 Kanstein 81,200.00 135,333.33
0.008 m3 Pasir pasang 220,000.00 1,650.00
0.750 kg PC 1,700.00 1,275.00
0.050 m3 Pasir urug 190,000.00 9,500.00
B TENAGA
0.050 OH Tukang Batu 135,000.00 6,750.00
0.005 OH Kepala Tukang Batu 150,000.00 750.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 176,608.33
Keuntungan & Overhead 10 % 17,660.83
Jumlah ……………………… 194,269.17

SNI.41.1 Lapisan Geotextile


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Geotextile 312,500.00 250,000.00
B TENAGA
0.050 OH Upang pasang 312,500.00 15,625.00
C PERALATAN

Jumlah ( A + B + C ) 265,625.00
Keuntungan & Overhead 10 % 26,562.50
Jumlah ……………………… 292,187.50

SNI.41.2 Lapisan Drainagecell


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Drainagecell 675,000.00 675,000.00
B TENAGA
0.050 OH Upang pasang 675,000.00 33,750.00
C PERALATAN

Jumlah ( A + B + C ) 708,750.00
Keuntungan & Overhead 10 % 70,875.00
Jumlah ……………………… 779,625.00

SNI.41.3 Memasang Kitchen Sink 1 Bowl GS 5844


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 bh Kitchen Sink 1 Bowl GS 5844 1,562,500.00 1,562,500.00
1.000 set Kran + asesories + Seal Tape 687,500.00 687,500.00
B TENAGA
0.300 OH Tukang Batu 135,000.00 40,500.00
0.030 OH Kepala Tukang Batu 150,000.00 4,500.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
C PERALATAN

Jumlah ( A + B + C ) 2,298,202.50
Keuntungan & Overhead 10 % 229,820.25
Jumlah ……………………… 2,528,022.75

SNI.41.4 Memasang Kitchen Sink Single Bowl Zenit Ris 1B 1D 86 with Kitchen Tap My 1 By TEKA
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 bh Kitchen Sink Single Bowl Zenit Ris 1B 1D 3,875,000.00 3,875,000.00
1.000 set Kran + asesories + Seal Tape 687,500.00 687,500.00
B TENAGA
0.300 OH Tukang Batu 135,000.00 40,500.00
0.030 OH Kepala Tukang Batu 150,000.00 4,500.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
C PERALATAN

Jumlah ( A + B + C ) 4,610,702.50
Keuntungan & Overhead 10 % 461,070.25
Jumlah ……………………… 5,071,772.75

SNI.41.5 Memasang Mirror 100x120 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 bh Mirror 100x120 cm 270,000.00 270,000.00
B TENAGA
0.300 OH Tukang Batu 135,000.00 40,500.00
0.030 OH Kepala Tukang Batu 150,000.00 4,500.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
C PERALATAN

Jumlah ( A + B + C ) 318,202.50
Keuntungan & Overhead 10 % 31,820.25
Jumlah ……………………… 350,022.75

SNI.42.a 1 m1 Pasang Buis beton Ø20 cm, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.000 Bh Buis Beton Dia. 20 Cm 75,000.00 150,000.00
1.250 Kg Semen 1,700.00 2,125.00
0.025 M³ Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 193,975.00
Keuntungan & Overhead 10 % 19,397.50
Jumlah ……………………… 213,372.50

SNI.42.b 1 m1 Pasang Buis beton Ø 30 cm, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.000 Bh Buis Beton Dia. 30 Cm 90,000.00 180,000.00
1.250 Kg Semen 1,700.00 2,125.00
0.025 M³ Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 223,975.00
Keuntungan & Overhead 10 % 22,397.50
Jumlah ……………………… 246,372.50

SNI.42.c 1 m1 Pasang Buis beton Ø 40 cm, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.000 Bh Buis Beton Dia. 40 Cm 110,000.00 220,000.00
1.250 Kg Semen 1,700.00 2,125.00
0.025 M³ Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 263,975.00
Keuntungan & Overhead 10 % 26,397.50
Jumlah ……………………… 290,372.50

SNI.43 1 m1 Pasang Buis beton Ø 50 cm, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.000 Bh Buis Beton Dia. 50 Cm 125,000.00 250,000.00
2.500 Kg Semen 1,700.00 4,250.00
0.025 M³ Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 150,000.00 30,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 306,100.00
Keuntungan & Overhead 10 % 30,610.00
Jumlah ……………………… 336,710.00

SNI.44 1 m1 Pasang Buis beton Ø 60 cm, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.000 Bh Buis Beton Dia. 60 Cm 130,000.00 260,000.00
2.500 Kg Semen 1,700.00 4,250.00
0.025 M³ Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 150,000.00 30,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 316,100.00
Keuntungan & Overhead 10 % 31,610.00
Jumlah ……………………… 347,710.00

SNI.45 1 m1 Pasang Buis beton Ø 80 cm, spesi 1 PC : 4 PP


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.000 Bh Buis Beton Dia. 80 Cm 150,000.00 300,000.00
2.500 Kg Semen 1,700.00 4,250.00
0.025 M³ Pasir Pasang 220,000.00 5,500.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.200 OH Pekerja 150,000.00 30,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 356,100.00
Keuntungan & Overhead 10 % 35,610.00
Jumlah ……………………… 391,710.00
PEKERJAAN LANTAI & DINDING
SNI.46 1 M2 Pas. Lantai Tegel Abu-abu
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Tegel Abu-abu 62,500.00 62,500.00
11.870 kg PC 1,700.00 20,179.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.035 OH Tukang Batu 135,000.00 4,725.00
0.013 OH Kepala Tukang 150,000.00 1,950.00
0.120 OH Pekerja 100,000.00 12,000.00
0.014 OH Mandor 135,000.00 1,890.00
C PERALATAN

Jumlah ( A + B + C ) 113,144.00
Keuntungan & Overhead 10 % 11,314.40
Jumlah ……………………… 124,458.40

SNI.47.a 1 M2 Pas. Lantai Granite Kw I


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Granite Kw I 450,000.00 450,000.00
11.870 kg PC 1,700.00 20,179.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.125 OH Tukang Batu 135,000.00 16,875.00
0.013 OH Kepala Tukang 150,000.00 1,950.00
0.250 OH Pekerja 100,000.00 25,000.00
0.013 OH Mandor 135,000.00 1,755.00
C PERALATAN

Jumlah ( A + B + C ) 525,659.00
Keuntungan & Overhead 10 % 52,565.90
Jumlah ……………………… 578,224.90

SNI.47.b 1 M2 Pas. Lantai Granite Kw II


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Granite Kw II 380,000.00 380,000.00
11.870 kg PC 1,700.00 20,179.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.125 OH Tukang Batu 135,000.00 16,875.00
0.013 OH Kepala Tukang 150,000.00 1,950.00
0.250 OH Pekerja 100,000.00 25,000.00
0.013 OH Mandor 135,000.00 1,755.00
C PERALATAN

Jumlah ( A + B + C ) 455,659.00
Keuntungan & Overhead 10 % 45,565.90
Jumlah ……………………… 501,224.90

SNI.48 1 M2 Pasangan Lantai Keramik ( KW I Polos )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Lantai Kualitas I (Polos) 83,000.00 87,150.00
14.150 Kg PC 1,700.00 24,055.00
2.000 Kg Semen Warna 15,000.00 30,000.00
0.039 M³ Pasir Pasang 220,000.00 8,580.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 277,010.00
Keuntungan & Overhead 10 % 27,701.00
Jumlah ……………………… 304,711.00

SNI.49 1 M2 Pasangan Lantai Keramik ( KW II Polos )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Lantai Kualitas II (Polos) 69,000.00 72,450.00
14.150 Kg PC 1,700.00 24,055.00
2.000 Kg Semen Warna 15,000.00 30,000.00
0.039 M³ Pasir Pasang 220,000.00 8,580.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 262,310.00
Keuntungan & Overhead 10 % 26,231.00
Jumlah ……………………… 288,541.00

SNI.50 1 M2 Pasangan Lantai Keramik ( KW I Motif )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Lantai Kualitas I (Motif) 121,000.00 127,050.00
14.150 Kg PC 1,700.00 24,055.00
2.000 Kg Semen Warna 15,000.00 30,000.00
0.039 M³ Pasir Pasang 220,000.00 8,580.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 316,910.00
Keuntungan & Overhead 10 % 31,691.00
Jumlah ……………………… 348,601.00

SNI.51 1 M2 Pasangan Lantai Keramik ( KW II Motif )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Lantai Kualitas II (Motif) 99,000.00 103,950.00
14.150 Kg PC 1,700.00 24,055.00
2.000 Kg Semen Warna 15,000.00 30,000.00
0.042 M³ Pasir Pasang 220,000.00 9,240.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 294,470.00
Keuntungan & Overhead 10 % 29,447.00
Jumlah ……………………… 323,917.00

SNI.52 1 M2 Pasangan Lantai Marmer


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Lantai Marmer 335,000.00 351,750.00
8.190 Kg PC 1,700.00 13,923.00
0.134 Kg Semen Warna 15,000.00 2,010.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 504,808.00
Keuntungan & Overhead 10 % 50,480.80
Jumlah ……………………… 555,288.80

SNI.52.a 1 M2 Pasangan Lantai Keramik Anti Slip


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Lantai Anti Slip Kualitas II 99,000.00 103,950.00
14.150 Kg PC 1,700.00 24,055.00
2.000 Kg Semen Warna 15,000.00 30,000.00
0.042 M³ Pasir Pasang 220,000.00 9,240.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 294,470.00
Keuntungan & Overhead 10 % 29,447.00
Jumlah ……………………… 323,917.00

SNI.53 1 M2 Pasangan dinding keramik ( Kw I Motif )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Dinding Kw I (Motif) 135,000.00 141,750.00
9.300 Kg PC 1,700.00 15,810.00
1.940 Kg Semen Warna 15,000.00 29,100.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.900 OH Pekerja 100,000.00 90,000.00
0.045 OH Mandor 135,000.00 6,075.00
C PERALATAN

Jumlah ( A + B + C ) 354,195.00
Keuntungan & Overhead 10 % 35,419.50
Jumlah ……………………… 389,614.50

SNI.54 1 M2 Pas. Dinding Keramik ( Kw II Motf )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Dinding Kw II (Motif) 110,000.00 115,500.00
9.300 Kg PC 1,700.00 15,810.00
1.940 Kg Semen Warna 15,000.00 29,100.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.900 OH Pekerja 100,000.00 90,000.00
0.045 OH Mandor 135,000.00 6,075.00
C PERALATAN

Jumlah ( A + B + C ) 327,945.00
Keuntungan & Overhead 10 % 32,794.50
Jumlah ……………………… 360,739.50

SNI.55 1 M2 Pas. Dinding Keramik ( Kw I polos )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik 10 x 20 cm 121,000.00 127,050.00
9.300 Kg PC 1,700.00 15,810.00
1.940 Kg Semen Warna 15,000.00 29,100.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.900 OH Pekerja 100,000.00 90,000.00
0.045 OH Mandor 135,000.00 6,075.00
C PERALATAN

Jumlah ( A + B + C ) 339,495.00
Keuntungan & Overhead 10 % 33,949.50
Jumlah ……………………… 373,444.50

SNI.56 1 M2 Pas. Dinding Keramik ( Kw II Polos )


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik Dinding Kw II (Polos) 88,000.00 92,400.00
9.300 Kg PC 1,700.00 15,810.00
1.940 Kg Semen Warna 15,000.00 29,100.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
C PERALATAN

Jumlah ( A + B + C ) 225,520.00
Keuntungan & Overhead 10 % 22,552.00
Jumlah ……………………… 248,072.00

SNI.57.a 1 M2 Pas. Lantai Keramik Cating Motif


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Keramik cutting Motif 160,000.00 168,000.00
9.300 Kg PC 1,700.00 15,810.00
2.750 Kg Semen Warna 15,000.00 41,250.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
C PERALATAN

Jumlah ( A + B + C ) 313,270.00
Keuntungan & Overhead 10 % 31,327.00
Jumlah ……………………… 344,597.00

SNI.57.b 1 M2 Pas. Lantai Coral Sikat


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 Kg Coral sikat 9,000.00 9,450.00
9.300 Kg PC 1,700.00 15,810.00
2.750 Kg Semen Warna 15,000.00 41,250.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
C PERALATAN

Jumlah ( A + B + C ) 154,720.00
Keuntungan & Overhead 10 % 15,472.00
Jumlah ……………………… 170,192.00

SNI.57.c 1 M2 Pas. Lantai Coral Sikat, Warna


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 Kg Coral sikat, Warna 15,000.00 15,750.00
9.300 Kg PC 1,700.00 15,810.00
2.750 Kg Semen Warna 15,000.00 41,250.00
0.018 M³ Pasir Pasang 220,000.00 3,960.00
B TENAGA
0.450 OH Tukang Batu 135,000.00 60,750.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
C PERALATAN

Jumlah ( A + B + C ) 161,020.00
Keuntungan & Overhead 10 % 16,102.00
Jumlah ……………………… 177,122.00

SNI.58 1 M2 Pas. Dinding batu paras/Palimanan


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Batu paras/Palimanan 243,000.00 255,150.00
11.750 Kg PC 1,700.00 19,975.00
0.035 M³ Pasir Pasang 220,000.00 7,700.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 410,050.00
Keuntungan & Overhead 10 % 41,005.00
Jumlah ……………………… 451,055.00

SNI.59 1 M2 Pas. Dinding batu tempel hitam bergaris


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.100 m2 Batu Sisir/ Bergaris, hitam 260,000.00 286,000.00
11.750 Kg PC 1,700.00 19,975.00
0.035 M³ Pasir Pasang 220,000.00 7,700.00
B TENAGA
0.350 OH Tukang Batu 135,000.00 47,250.00
0.035 OH Kepala Tukang 150,000.00 5,250.00
0.700 OH Pekerja 100,000.00 70,000.00
0.035 OH Mandor 135,000.00 4,725.00
C PERALATAN

Jumlah ( A + B + C ) 440,900.00
Keuntungan & Overhead 10 % 44,090.00
Jumlah ……………………… 484,990.00

SNI.60.B 1 M2 Pas. Paving Blok bata . T 8 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.010 m2 Paving Blok Persegi (t = 8 cm) 80,000.00 80,800.00
B TENAGA
0.500 OH Tukang Batu 135,000.00 67,500.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.500 OH Pekerja 100,000.00 50,000.00
0.001 OH Mandor 135,000.00 175.50
C PERALATAN

Jumlah ( A + B + C ) 205,975.50
Keuntungan & Overhead 10 % 20,597.55
Jumlah ……………………… 226,573.05

SNI.60.P 1 M2 Pas. Paving Blok bata . T 8 cm, Press


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.010 m2 Paving Blok Persegi (t = 8 cm), Press 165,000.00 166,650.00
B TENAGA
0.500 OH Tukang Batu 135,000.00 67,500.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.500 OH Pekerja 100,000.00 50,000.00
0.001 OH Mandor 135,000.00 175.50
C PERALATAN

Jumlah ( A + B + C ) 291,825.50
Keuntungan & Overhead 10 % 29,182.55
Jumlah ……………………… 321,008.05

SNI.61 1 M2 Pas. Paving Blok bata . T 6 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.010 m2 Paving Blok Persegi (t = 6 cm) 65,000.00 65,650.00
B TENAGA
0.500 OH Tukang Batu 135,000.00 67,500.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.500 OH Pekerja 100,000.00 50,000.00
0.001 OH Mandor 135,000.00 175.50
C PERALATAN

Jumlah ( A + B + C ) 190,825.50
Keuntungan & Overhead 10 % 19,082.55
Jumlah ……………………… 209,908.05

SNI.62 1 M2 Pas. Paving Blok persegi/berlian


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.010 m2 Paving Blok Tiga Berlian 197,800.00 199,778.00
B TENAGA
0.500 OH Tukang Batu 135,000.00 67,500.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.500 OH Pekerja 100,000.00 50,000.00
0.001 OH Mandor 135,000.00 175.50
C PERALATAN

Jumlah ( A + B + C ) 324,953.50
Keuntungan & Overhead 10 % 32,495.35
Jumlah ……………………… 357,448.85

SNI.62.1 1 m2 Memasang ornamen terawang custom bahan GRC


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Ornamen terawang custom 937,500.00 984,375.00
11.000 kg Portland Cement 1,700.00 18,700.00
0.035 m3 Pasir Pasang 220,000.00 7,700.00
B TENAGA
0.750 OH Tukang Batu 135,000.00 101,250.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN

Jumlah ( A + B + C ) 1,151,550.00
Keuntungan & Overhead 10 % 115,155.00
Jumlah ……………………… 1,266,705.00

SNI.62.2 1 m2 Memasang acian motif tali air


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
3.250 kg Portland Cement 1,700.00 5,525.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN

Jumlah ( A + B + C ) 41,875.00
Keuntungan & Overhead 10 % 4,187.50
Jumlah ……………………… 46,062.50

SNI.62.3 1 m Memasang plint ukuran (60 x 10x 4 ) cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.700 Buah Hospital plint 60 x 10 x 4 81,200.00 138,040.00
1.140 kg Portland Cement 1,700.00 1,938.00
0.003 m3 Pasir Pasang 220,000.00 660.00
0.100 kg Semen warna 15,000.00 1,500.00
B TENAGA
0.090 OH Tukang Batu 135,000.00 12,150.00
0.009 OH Kepala Tukang 150,000.00 1,350.00
0.090 OH Pekerja 100,000.00 9,000.00
0.005 OH Mandor 135,000.00 675.00
C PERALATAN

Jumlah ( A + B + C ) 165,313.00
Keuntungan & Overhead 10 % 16,531.30
Jumlah ……………………… 181,844.30

SNI.62.4 1 m Memasang stepnose tangga ukuran (10 x 40) cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
2.650 Buah Stepnose tangga 10x40 cm 31,200.00 82,680.00
1.140 kg Portland Cement 1,700.00 1,938.00
0.003 m3 Pasir Pasang 220,000.00 660.00
0.100 kg Semen warna 15,000.00 1,500.00
B TENAGA
0.010 OH Tukang Batu 135,000.00 1,350.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.003 OH Mandor 135,000.00 337.50
C PERALATAN

Jumlah ( A + B + C ) 105,965.50
Keuntungan & Overhead 10 % 10,596.55
Jumlah ……………………… 116,562.05

SNI.62.5 1 m2 Memasang lantai karpet


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.050 m2 Karpet 25,000.00 26,250.00
0.350 kg Lem 50,000.00 17,500.00
B TENAGA
0.470 OH Tukang Kayu 135,000.00 63,450.00
0.017 OH Kepala Tukang 150,000.00 2,550.00
0.170 OH Pekerja 100,000.00 17,000.00
0.009 OH Mandor 135,000.00 1,215.00
C PERALATAN

Jumlah ( A + B + C ) 127,965.00
Keuntungan & Overhead 10 % 12,796.50
Jumlah ……………………… 140,761.50

SNI.62.6 1 m2 Memasang lantai vinyl ukuran (30 x 30) cm KL I


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
11.870 Buah Vinyl 16,800.00 199,416.00
0.350 kg Lem vinyl 50,000.00 17,500.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
C PERALATAN

Jumlah ( A + B + C ) 255,496.00
Keuntungan & Overhead 10 % 25,549.60
Jumlah ……………………… 281,045.60

SNI.62.7 1 m2 Memasang lantai parquete ukuran (30 x 30) cm KL I


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
11.870 Buah Lantai parquete (dreamwood) 26,300.00 312,181.00
0.350 kg Lem perquete 50,000.00 17,500.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
C PERALATAN

Jumlah ( A + B + C ) 368,261.00
Keuntungan & Overhead 10 % 36,826.10
Jumlah ……………………… 405,087.10

SNI.62.W 1 m2 Pasang conblock tipe segi-empat warna 8 cm, K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Conblock tipe segi-empat abu-abu 8 cm, 126,800.00 126,800.00
0.050 m3 Pasir urug 220,000.00 11,000.00
B TENAGA
0.250 OH Tukang Batu 135,000.00 33,750.00
0.025 OH Kepala Tukang 150,000.00 3,750.00
0.500 OH Pekerja 100,000.00 50,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN

Jumlah ( A + B + C ) 228,675.00
Keuntungan & Overhead 10 % 22,867.50
Jumlah ……………………… 251,542.50

SNI.62.A 1 m2 Pasang conblock tipe segi-empat abu-abu 8 cm, K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Conblock tipe segi-enam abu-abu 8 cm, K 121,200.00 121,200.00
0.050 m3 Pasir urug 220,000.00 11,000.00
B TENAGA
0.250 OH Tukang Batu 135,000.00 33,750.00
0.025 OH Kepala Tukang 150,000.00 3,750.00
0.500 OH Pekerja 100,000.00 50,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN

Jumlah ( A + B + C ) 223,075.00
Keuntungan & Overhead 10 % 22,307.50
Jumlah ……………………… 245,382.50

SNI.62.7 1 m Pasang kansten beton


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.667 m2 Kanstin 75,000.00 125,000.00
2.670 m3 Semen 1,700.00 4,539.00
0.030 m3 Batu kali 240,000.00 7,200.00
0.050 m3 pasir urug 190,000.00 9,500.00
B TENAGA
0.150 OH Tukang Batu 135,000.00 20,250.00
0.025 OH Kepala Tukang 150,000.00 3,750.00
0.050 OH Pekerja 100,000.00 5,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN

Jumlah ( A + B + C ) 178,614.00
Keuntungan & Overhead 10 % 17,861.40
Jumlah ……………………… 196,475.40

SNI.62.8 1 m2 Pasang grassblocksegi 8 tebal 8 cm


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 grassblock tebal 8 cm 140,000.00 140,000.00
0.050 m3 Pasir urug 190,000.00 9,500.00
B TENAGA
0.250 OH Tukang Batu 135,000.00 33,750.00
0.025 OH Kepala Tukang 150,000.00 3,750.00
0.500 OH Pekerja 100,000.00 50,000.00
0.025 OH Mandor 135,000.00 3,375.00
C PERALATAN
Jumlah ( A + B + C ) 240,375.00
Keuntungan & Overhead 10 % 24,037.50
Jumlah ……………………… 264,412.50
PEKERJAAN KONSTRUKSI BETON
SNI.63.a 1 M3 Membuat Beton Dengan Mutu K-300
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
413.000 Kg Semen 1,700.00 702,100.00
1.021 M³ Kerikil Pecah 2/3 735,000.00 750,435.00
0.681 M³ Pasir Beton 350,000.00 238,350.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,993,620.00
Keuntungan & Overhead 10 % 199,362.00
Jumlah ……………………… 2,192,982.00

SNI.64.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 130 Kg Besi + Bekisting) M-K300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
130.000 Kg Besi beton ulir 19,000.00 2,470,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.753 OH Pekerja 100,000.00 275,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.910 OH Tukang besi 135,000.00 122,850.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.210 OH Mandor 135,000.00 28,350.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,916,100.00
Keuntungan & Overhead 10 % 491,610.00
Jumlah ……………………… 5,407,710.00

SNI.65.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m 3
Pasir beton 350,000.00 238,350.00
1.021 m 3
Koral beton 735,000.00 750,435.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,332,180.00
Keuntungan & Overhead 10 % 533,218.00
Jumlah ……………………… 5,865,398.00

SNI.66.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,556,430.00
Keuntungan & Overhead 10 % 555,643.00
Jumlah ……………………… 6,112,073.00

SNI.67.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,076,530.00
Keuntungan & Overhead 10 % 607,653.00
Jumlah ……………………… 6,684,183.00

SNI.68.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m 3
Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,116,730.00
Keuntungan & Overhead 10 % 711,673.00
Jumlah ……………………… 7,828,403.00

SNI.69.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,490,025.00
Keuntungan & Overhead 10 % 749,002.50
Jumlah ……………………… 8,239,027.50

SNI.70.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,530,225.00
Keuntungan & Overhead 10 % 853,022.50
Jumlah ……………………… 9,383,247.50

SNI.71.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
250.000 Kg Besi beton ulir 19,000.00 4,750,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.733 OH Pekerja 100,000.00 373,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.750 OH Tukang besi 135,000.00 236,250.00
0.227 OH Kepala Tukang 150,000.00 34,050.00
0.265 OH Mandor 135,000.00 35,775.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 9,570,425.00
Keuntungan & Overhead 10 % 957,042.50
Jumlah ……………………… 10,527,467.50

SNI.72.a 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,866,725.00
Keuntungan & Overhead 10 % 686,672.50
Jumlah ……………………… 7,553,397.50

SNI.73.a 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,386,825.00
Keuntungan & Overhead 10 % 738,682.50
Jumlah ……………………… 8,125,507.50

SNI.74.a 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m 3
Pasir beton 350,000.00 238,350.00
1.021 m 3
Koral beton 735,000.00 750,435.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,427,025.00
Keuntungan & Overhead 10 % 842,702.50
Jumlah ……………………… 9,269,727.50

SNI.75.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m 3
Koral beton 735,000.00 750,435.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,819,525.00
Keuntungan & Overhead 10 % 681,952.50
Jumlah ……………………… 7,501,477.50

SNI.76.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-300


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
413.000 Kg Semen portland 1,700.00 702,100.00
0.681 m3 Pasir beton 350,000.00 238,350.00
1.021 m3 Koral beton 735,000.00 750,435.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,339,625.00
Keuntungan & Overhead 10 % 733,962.50
Jumlah ……………………… 8,073,587.50

SNI.63.b 1 M3 Membuat Beton Dengan Mutu K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
406.000 Kg Semen 1,700.00 690,200.00
1.026 M³ Kerikil Pecah 2/3 735,000.00 754,110.00
0.684 M³ Pasir Beton 350,000.00 239,400.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,986,445.00
Keuntungan & Overhead 10 % 198,644.50
Jumlah ……………………… 2,185,089.50

SNI.64.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 130 Kg Besi + Bekisting) M-K275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
130.000 Kg Besi beton ulir 19,000.00 2,470,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m 3
Koral beton 735,000.00 754,110.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.753 OH Pekerja 100,000.00 275,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.910 OH Tukang besi 135,000.00 122,850.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.210 OH Mandor 135,000.00 28,350.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,908,925.00
Keuntungan & Overhead 10 % 490,892.50
Jumlah ……………………… 5,399,817.50

SNI.65.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,325,005.00
Keuntungan & Overhead 10 % 532,500.50
Jumlah ……………………… 5,857,505.50

SNI.66.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,549,255.00
Keuntungan & Overhead 10 % 554,925.50
Jumlah ……………………… 6,104,180.50

SNI.67.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,069,355.00
Keuntungan & Overhead 10 % 606,935.50
Jumlah ……………………… 6,676,290.50

SNI.68.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,109,555.00
Keuntungan & Overhead 10 % 710,955.50
Jumlah ……………………… 7,820,510.50

SNI.69.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m 3
Pasir beton 350,000.00 239,400.00
1.026 m 3
Koral beton 735,000.00 754,110.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,482,850.00
Keuntungan & Overhead 10 % 748,285.00
Jumlah ……………………… 8,231,135.00

SNI.70.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,523,050.00
Keuntungan & Overhead 10 % 852,305.00
Jumlah ……………………… 9,375,355.00

SNI.71.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1 0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
2 3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
250.000 Kg Besi beton ulir 19,000.00 4,750,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.733 OH Pekerja 100,000.00 373,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.750 OH Tukang besi 135,000.00 236,250.00
0.227 OH Kepala Tukang 150,000.00 34,050.00
0.265 OH Mandor 135,000.00 35,775.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 9,563,250.00
Keuntungan & Overhead 10 % 956,325.00
Jumlah ……………………… 10,519,575.00

SNI.72.b 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m 3
Pasir beton 350,000.00 239,400.00
1.026 m 3
Koral beton 735,000.00 754,110.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,859,550.00
Keuntungan & Overhead 10 % 685,955.00
Jumlah ……………………… 7,545,505.00

SNI.73.b 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m 3
Koral beton 735,000.00 754,110.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,379,650.00
Keuntungan & Overhead 10 % 737,965.00
Jumlah ……………………… 8,117,615.00

SNI.74.b 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m3 Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,419,850.00
Keuntungan & Overhead 10 % 841,985.00
Jumlah ……………………… 9,261,835.00

SNI.75.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m 3
Pasir beton 350,000.00 239,400.00
1.026 m3 Koral beton 735,000.00 754,110.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,812,350.00
Keuntungan & Overhead 10 % 681,235.00
Jumlah ……………………… 7,493,585.00

SNI.76.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-275


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
406.000 Kg Semen portland 1,700.00 690,200.00
0.684 m 3
Pasir beton 350,000.00 239,400.00
1.026 m 3
Koral beton 735,000.00 754,110.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,332,450.00
Keuntungan & Overhead 10 % 733,245.00
Jumlah ……………………… 8,065,695.00

SNI.77.a 1 M3 Membuat Beton Dengan Mutu K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
384.000 Kg Semen 1,700.00 652,800.00
1.039 M³ Kerikil Pecah 2/3 735,000.00 763,665.00
0.692 M³ Pasir Beton 350,000.00 242,200.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,961,400.00
Keuntungan & Overhead 10 % 196,140.00
Jumlah ……………………… 2,157,540.00

SNI.78.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 130 Kg Besi + Bekisting) M-K250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
130.000 Kg Besi beton ulir 19,000.00 2,470,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m 3
Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.753 OH Pekerja 100,000.00 275,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.910 OH Tukang besi 135,000.00 122,850.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.210 OH Mandor 135,000.00 28,350.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,883,880.00
Keuntungan & Overhead 10 % 488,388.00
Jumlah ……………………… 5,372,268.00

SNI.79.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,299,960.00
Keuntungan & Overhead 10 % 529,996.00
Jumlah ……………………… 5,829,956.00

SNI.80.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m 3
Pasir beton 350,000.00 242,200.00
1.039 m 3
Koral beton 735,000.00 763,665.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,524,210.00
Keuntungan & Overhead 10 % 552,421.00
Jumlah ……………………… 6,076,631.00

SNI.81.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,044,310.00
Keuntungan & Overhead 10 % 604,431.00
Jumlah ……………………… 6,648,741.00

SNI.82.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m 3
Koral beton 735,000.00 763,665.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,084,510.00
Keuntungan & Overhead 10 % 708,451.00
Jumlah ……………………… 7,792,961.00

SNI.83.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,457,805.00
Keuntungan & Overhead 10 % 745,780.50
Jumlah ……………………… 8,203,585.50
SNI.84.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-250
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,498,005.00
Keuntungan & Overhead 10 % 849,800.50
Jumlah ……………………… 9,347,805.50

SNI.85.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
250.000 Kg Besi beton ulir 19,000.00 4,750,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.733 OH Pekerja 100,000.00 373,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.750 OH Tukang besi 135,000.00 236,250.00
0.227 OH Kepala Tukang 150,000.00 34,050.00
0.265 OH Mandor 135,000.00 35,775.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 9,538,205.00
Keuntungan & Overhead 10 % 953,820.50
Jumlah ……………………… 10,492,025.50

SNI.86.a 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,834,505.00
Keuntungan & Overhead 10 % 683,450.50
Jumlah ……………………… 7,517,955.50

SNI.87.a 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,354,605.00
Keuntungan & Overhead 10 % 735,460.50
Jumlah ……………………… 8,090,065.50

SNI.88.a 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,394,805.00
Keuntungan & Overhead 10 % 839,480.50
Jumlah ……………………… 9,234,285.50

SNI.89.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,787,305.00
Keuntungan & Overhead 10 % 678,730.50
Jumlah ……………………… 7,466,035.50

SNI.90.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-250


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
384.000 Kg Semen portland 1,700.00 652,800.00
0.692 m3 Pasir beton 350,000.00 242,200.00
1.039 m3 Koral beton 735,000.00 763,665.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,307,405.00
Keuntungan & Overhead 10 % 730,740.50
Jumlah ……………………… 8,038,145.50

SNI.77.b 1 M3 Membuat Beton Dengan Mutu K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
371.000 Kg Semen 1,700.00 630,700.00
1.047 M³ Kerikil Pecah 2/3 735,000.00 769,545.00
0.698 M³ Pasir Beton 350,000.00 244,300.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,947,280.00
Keuntungan & Overhead 10 % 194,728.00
Jumlah ……………………… 2,142,008.00

SNI.78.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,765,740.00
Keuntungan & Overhead 10 % 476,574.00
Jumlah ……………………… 5,242,314.00

SNI.79.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m 3
Pasir beton 350,000.00 244,300.00
1.047 m 3
Koral beton 735,000.00 769,545.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,285,840.00
Keuntungan & Overhead 10 % 528,584.00
Jumlah ……………………… 5,814,424.00

SNI.80.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,510,090.00
Keuntungan & Overhead 10 % 551,009.00
Jumlah ……………………… 6,061,099.00

SNI.81.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,030,190.00
Keuntungan & Overhead 10 % 603,019.00
Jumlah ……………………… 6,633,209.00

SNI.82.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m 3
Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,070,390.00
Keuntungan & Overhead 10 % 707,039.00
Jumlah ……………………… 7,777,429.00

SNI.83.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,443,685.00
Keuntungan & Overhead 10 % 744,368.50
Jumlah ……………………… 8,188,053.50

SNI.84.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,483,885.00
Keuntungan & Overhead 10 % 848,388.50
Jumlah ……………………… 9,332,273.50

SNI.85.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
250.000 Kg Besi beton ulir 19,000.00 4,750,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.733 OH Pekerja 100,000.00 373,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.750 OH Tukang besi 135,000.00 236,250.00
0.227 OH Kepala Tukang 150,000.00 34,050.00
0.265 OH Mandor 135,000.00 35,775.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 9,524,085.00
Keuntungan & Overhead 10 % 952,408.50
Jumlah ……………………… 10,476,493.50

SNI.86.b 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,820,385.00
Keuntungan & Overhead 10 % 682,038.50
Jumlah ……………………… 7,502,423.50

SNI.87.b 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,340,485.00
Keuntungan & Overhead 10 % 734,048.50
Jumlah ……………………… 8,074,533.50

SNI.88.b 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton ulir 19,000.00 3,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m 3
Pasir beton 350,000.00 244,300.00
1.047 m 3
Koral beton 735,000.00 769,545.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 8,380,685.00
Keuntungan & Overhead 10 % 838,068.50
Jumlah ……………………… 9,218,753.50

SNI.89.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton ulir 19,000.00 2,375,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m 3
Koral beton 735,000.00 769,545.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,773,185.00
Keuntungan & Overhead 10 % 677,318.50
Jumlah ……………………… 7,450,503.50

SNI.90.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,293,285.00
Keuntungan & Overhead 10 % 729,328.50
Jumlah ……………………… 8,022,613.50

SNI.91 1 M3 Membuat Beton Dengan Mutu K-200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
352.000 Kg Semen 1,700.00 598,400.00
1.031 M³ Kerikil Pecah 2/3 735,000.00 757,785.00
0.731 M³ Pasir Beton 350,000.00 255,850.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,914,770.00
Keuntungan & Overhead 10 % 191,477.00
Jumlah ……………………… 2,106,247.00

SNI.92 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,358,230.00
Keuntungan & Overhead 10 % 435,823.00
Jumlah ……………………… 4,794,053.00

SNI.93 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,803,330.00
Keuntungan & Overhead 10 % 480,333.00
Jumlah ……………………… 5,283,663.00

SNI.94 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,102,580.00
Keuntungan & Overhead 10 % 510,258.00
Jumlah ……………………… 5,612,838.00

SNI.95 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,547,680.00
Keuntungan & Overhead 10 % 554,768.00
Jumlah ……………………… 6,102,448.00

SNI.96 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,437,880.00
Keuntungan & Overhead 10 % 643,788.00
Jumlah ……………………… 7,081,668.00

SNI.97 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,516,075.00
Keuntungan & Overhead 10 % 651,607.50
Jumlah ……………………… 7,167,682.50

SNI.98 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,961,175.00
Keuntungan & Overhead 10 % 696,117.50
Jumlah ……………………… 7,657,292.50

SNI.99 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,851,375.00
Keuntungan & Overhead 10 % 785,137.50
Jumlah ……………………… 8,636,512.50

SNI.100 1 M3 Pekerjaan Balok Beton Bertulang ( 120 Kg Besi + Bekisting) M-K-200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.840 OH Tukang besi 135,000.00 113,400.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.213 OH Mandor 135,000.00 28,755.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,323,855.00
Keuntungan & Overhead 10 % 632,385.50
Jumlah ……………………… 6,956,240.50

SNI.101 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-200


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,412,875.00
Keuntungan & Overhead 10 % 641,287.50
Jumlah ……………………… 7,054,162.50

SNI.102 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 200
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,748,175.00
Keuntungan & Overhead 10 % 774,817.50
Jumlah ……………………… 8,522,992.50

SNI.103 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 200
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.840 OH Tukang besi 135,000.00 113,400.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.213 OH Mandor 135,000.00 28,755.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,276,655.00
Keuntungan & Overhead 10 % 627,665.50
Jumlah ……………………… 6,904,320.50

SNI.104 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 200
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,810,775.00
Keuntungan & Overhead 10 % 681,077.50
Jumlah ……………………… 7,491,852.50

SNI.105 1 M3 Membuat Beton Dengan Mutu K- 175


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
326.000 Kg Semen 1,700.00 554,200.00
1.029 M³ Kerikil Pecah 2/3 735,000.00 756,315.00
0.760 M³ Pasir Beton 350,000.00 266,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,879,250.00
Keuntungan & Overhead 10 % 187,925.00
Jumlah ……………………… 2,067,175.00

SNI.106 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m 3
Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,322,710.00
Keuntungan & Overhead 10 % 432,271.00
Jumlah ……………………… 4,754,981.00

SNI.107 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M- K 175


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,767,810.00
Keuntungan & Overhead 10 % 476,781.00
Jumlah ……………………… 5,244,591.00

SNI.108 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m 3
Pasir beton 350,000.00 266,000.00
1.029 m 3
Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,067,060.00
Keuntungan & Overhead 10 % 506,706.00
Jumlah ……………………… 5,573,766.00

SNI.109 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,512,160.00
Keuntungan & Overhead 10 % 551,216.00
Jumlah ……………………… 6,063,376.00

SNI.110 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,402,360.00
Keuntungan & Overhead 10 % 640,236.00
Jumlah ……………………… 7,042,596.00

SNI.111 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,480,555.00
Keuntungan & Overhead 10 % 648,055.50
Jumlah ……………………… 7,128,610.50

SNI.112 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,925,655.00
Keuntungan & Overhead 10 % 692,565.50
Jumlah ……………………… 7,618,220.50

SNI.113 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,815,855.00
Keuntungan & Overhead 10 % 781,585.50
Jumlah ……………………… 8,597,440.50

SNI.114 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,377,355.00
Keuntungan & Overhead 10 % 637,735.50
Jumlah ……………………… 7,015,090.50

SNI.115 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m 3
Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,822,455.00
Keuntungan & Overhead 10 % 682,245.50
Jumlah ……………………… 7,504,700.50

SNI.116 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,712,655.00
Keuntungan & Overhead 10 % 771,265.50
Jumlah ……………………… 8,483,920.50

SNI.117 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.840 OH Tukang besi 135,000.00 113,400.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.213 OH Mandor 135,000.00 28,755.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,241,135.00
Keuntungan & Overhead 10 % 624,113.50
Jumlah ……………………… 6,865,248.50

SNI.118 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,775,255.00
Keuntungan & Overhead 10 % 677,525.50
Jumlah ……………………… 7,452,780.50

SNI.119 1 M3 Membuat Beton Dengan Mutu K- 150


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
299.000 Kg Semen 1,700.00 508,300.00
1.017 M³ Kerikil Pecah 2/3 735,000.00 747,495.00
0.799 M³ Pasir Beton 350,000.00 279,650.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,838,180.00
Keuntungan & Overhead 10 % 183,818.00
Jumlah ……………………… 2,021,998.00

SNI.120 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,281,640.00
Keuntungan & Overhead 10 % 428,164.00
Jumlah ……………………… 4,709,804.00

SNI.121 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M- K 150


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m 3
Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,726,740.00
Keuntungan & Overhead 10 % 472,674.00
Jumlah ……………………… 5,199,414.00

SNI.122 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,025,990.00
Keuntungan & Overhead 10 % 502,599.00
Jumlah ……………………… 5,528,589.00

SNI.123 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m 3
Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,471,090.00
Keuntungan & Overhead 10 % 547,109.00
Jumlah ……………………… 6,018,199.00

SNI.124 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m 3
Pasir beton 350,000.00 279,650.00
1.017 m 3
Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,361,290.00
Keuntungan & Overhead 10 % 636,129.00
Jumlah ……………………… 6,997,419.00

SNI.125 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.088 OH Tukang besi 135,000.00 11,812.50
0.061 OH Kepala Tukang 150,000.00 9,112.50
0.170 OH Mandor 135,000.00 22,950.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,315,285.00
Keuntungan & Overhead 10 % 631,528.50
Jumlah ……………………… 6,946,813.50

SNI.126 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.105 OH Tukang besi 135,000.00 14,175.00
0.063 OH Kepala Tukang 150,000.00 9,375.00
0.171 OH Mandor 135,000.00 23,085.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,735,545.00
Keuntungan & Overhead 10 % 673,554.50
Jumlah ……………………… 7,409,099.50
SNI.127 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.140 OH Tukang besi 135,000.00 18,900.00
0.066 OH Kepala Tukang 150,000.00 9,900.00
0.173 OH Mandor 135,000.00 23,355.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,576,065.00
Keuntungan & Overhead 10 % 757,606.50
Jumlah ……………………… 8,333,671.50

SNI.128 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.088 OH Tukang besi 135,000.00 11,812.50
0.061 OH Kepala Tukang 150,000.00 9,112.50
0.170 OH Mandor 135,000.00 22,950.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,212,085.00
Keuntungan & Overhead 10 % 621,208.50
Jumlah ……………………… 6,833,293.50

SNI.129 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.105 OH Tukang besi 135,000.00 14,175.00
0.063 OH Kepala Tukang 150,000.00 9,375.00
0.171 OH Mandor 135,000.00 23,085.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,632,345.00
Keuntungan & Overhead 10 % 663,234.50
Jumlah ……………………… 7,295,579.50

SNI.130 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.140 OH Tukang besi 135,000.00 18,900.00
0.066 OH Kepala Tukang 150,000.00 9,900.00
0.173 OH Mandor 135,000.00 23,355.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,472,865.00
Keuntungan & Overhead 10 % 747,286.50
Jumlah ……………………… 8,220,151.50

SNI.131 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.084 OH Tukang besi 135,000.00 11,340.00
0.060 OH Kepala Tukang 150,000.00 9,060.00
0.170 OH Mandor 135,000.00 22,923.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,080,833.00
Keuntungan & Overhead 10 % 608,083.30
Jumlah ……………………… 6,688,916.30

SNI.132 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.105 OH Tukang besi 135,000.00 14,175.00
0.063 OH Kepala Tukang 150,000.00 9,375.00
0.171 OH Mandor 135,000.00 23,085.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,585,145.00
Keuntungan & Overhead 10 % 658,514.50
Jumlah ……………………… 7,243,659.50

SNI.133 1 M3 Membuat Beton Dengan Mutu K- 125


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
247.000 Kg Semen 1,700.00 419,900.00
0.740 M³ Kerikil Pecah 2/3 735,000.00 543,900.00
0.621 M³ Pasir Beton 350,000.00 217,350.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,483,885.00
Keuntungan & Overhead 10 % 148,388.50
Jumlah ……………………… 1,632,273.50
SNI.134 1 M3 Pekerjaan Pondasi Beton Bertulang ( 110 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
110.000 Kg Besi Beton polos 16,000.00 1,760,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.613 OH Pekerja 100,000.00 261,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.770 OH Tukang besi 135,000.00 103,950.00
0.122 OH Kepala Tukang 150,000.00 18,300.00
0.202 OH Mandor 135,000.00 27,270.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 3,660,285.00
Keuntungan & Overhead 10 % 366,028.50
Jumlah ……………………… 4,026,313.50

SNI.135 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M- K 125


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 3,927,345.00
Keuntungan & Overhead 10 % 392,734.50
Jumlah ……………………… 4,320,079.50

SNI.136 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,671,695.00
Keuntungan & Overhead 10 % 467,169.50
Jumlah ……………………… 5,138,864.50

SNI.137 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,116,795.00
Keuntungan & Overhead 10 % 511,679.50
Jumlah ……………………… 5,628,474.50

SNI.138 1 M3 Pekerjaan Sloof Beton Bertulang ( 175 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
175.000 Kg Besi Beton polos 16,000.00 2,800,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.068 OH Pekerja 100,000.00 306,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.167 OH Kepala Tukang 150,000.00 25,125.00
0.228 OH Mandor 135,000.00 30,780.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,561,895.00
Keuntungan & Overhead 10 % 556,189.50
Jumlah ……………………… 6,118,084.50

SNI.139 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,085,190.00
Keuntungan & Overhead 10 % 608,519.00
Jumlah ……………………… 6,693,709.00

SNI.140 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,530,290.00
Keuntungan & Overhead 10 % 653,029.00
Jumlah ……………………… 7,183,319.00

SNI.141 1 M3 Pekerjaan Kolom Beton Bertulang ( 175 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi Beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.208 OH Pekerja 100,000.00 320,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,975,390.00
Keuntungan & Overhead 10 % 697,539.00
Jumlah ……………………… 7,672,929.00

SNI.142 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,981,990.00
Keuntungan & Overhead 10 % 598,199.00
Jumlah ……………………… 6,580,189.00

SNI.143 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,427,090.00
Keuntungan & Overhead 10 % 642,709.00
Jumlah ……………………… 7,069,799.00

SNI.144 1 M3 Pekerjaan Balok Beton Bertulang ( 175 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi Beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.208 OH Pekerja 100,000.00 320,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,872,190.00
Keuntungan & Overhead 10 % 687,219.00
Jumlah ……………………… 7,559,409.00

SNI.145 1 M3 Pekerjaan Lantai Beton Bertulang ( 110 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
110.000 Kg Besi Beton polos 16,000.00 1,760,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.753 OH Pekerja 100,000.00 275,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.770 OH Tukang besi 135,000.00 103,950.00
0.129 OH Kepala Tukang 150,000.00 19,350.00
0.209 OH Mandor 135,000.00 28,215.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,667,730.00
Keuntungan & Overhead 10 % 566,773.00
Jumlah ……………………… 6,234,503.00

SNI.146 1 M3 Pekerjaan Lantai Beton Bertulang ( 130 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
130.000 Kg Besi Beton polos 16,000.00 2,080,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.910 OH Tukang besi 135,000.00 122,850.00
0.143 OH Kepala Tukang 150,000.00 21,450.00
0.217 OH Mandor 135,000.00 29,295.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,023,810.00
Keuntungan & Overhead 10 % 602,381.00
Jumlah ……………………… 6,626,191.00

SNI.147 1 M3 Pekerjaan Dinding Beton Bertulang ( 150 Kg Besi + Bekisting) M - K 225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu Kelas III 2,600,000.00 624,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
14.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 154,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,183,285.00
Keuntungan & Overhead 10 % 718,328.50
Jumlah ……………………… 7,901,613.50

SNI.148 1 M3 Pekerjaan Tangga Beton Bertulang ( 175 Kg Besi + Bekisting) M - K - 225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi beton ulir 19,000.00 3,325,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m 3
Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.208 OH Pekerja 100,000.00 320,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,860,585.00
Keuntungan & Overhead 10 % 786,058.50
Jumlah ……………………… 8,646,643.50

SNI.149 1 M3 Pekerjaan Tangga Beton Bertulang ( 150 Kg Besi + Bekisting) M - K - 225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton ulir 19,000.00 2,850,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m 3
Pasir beton 350,000.00 244,300.00
1.047 m 3
Koral beton 735,000.00 769,545.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,340,485.00
Keuntungan & Overhead 10 % 734,048.50
Jumlah ……………………… 8,074,533.50

SNI.150 1 M3 Pekerjaan Tangga Beton Bertulang ( 130 Kg Besi + Bekisting) M - K - 225


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
130.000 Kg Besi beton ulir 19,000.00 2,470,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
371.000 Kg Semen portland 1,700.00 630,700.00
0.698 m3 Pasir beton 350,000.00 244,300.00
1.047 m3 Koral beton 735,000.00 769,545.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.910 OH Tukang besi 135,000.00 122,850.00
0.143 OH Kepala Tukang 150,000.00 21,450.00
0.217 OH Mandor 135,000.00 29,295.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,924,405.00
Keuntungan & Overhead 10 % 692,440.50
Jumlah ……………………… 7,616,845.50

SNI.151 1 M2 Lantai Kerja Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr (Tebal = 5 Cm)


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
10.000 Kg Semen 1,700.00 17,000.00
0.044 M³ Batu Kerikil 565,000.00 24,860.00
0.026 M³ Pasir Beton 350,000.00 9,100.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.020 OH Tukang Batu 135,000.00 2,700.00
0.002 OH Kepala Tukang 150,000.00 300.00
1.150 OH Pekerja 100,000.00 115,000.00
0.006 OH Mandor 135,000.00 810.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 294,020.00
Keuntungan & Overhead 10 % 29,402.00
Jumlah ……………………… 323,422.00

SNI.152 1 M3 Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
200.000 Kg Semen 1,700.00 340,000.00
0.862 M³ Batu Kerikil 565,000.00 487,030.00
0.522 M³ Pasir Beton 350,000.00 182,700.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.250 OH Tukang Batu 135,000.00 33,750.00
0.220 OH Kepala Tukang 150,000.00 33,000.00
1.320 OH Pekerja 100,000.00 132,000.00
0.013 OH Mandor 135,000.00 1,782.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,334,512.00
Keuntungan & Overhead 10 % 133,451.20
Jumlah ……………………… 1,467,963.20

SNI.153 1 M3 Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr


Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
247.000 Kg Semen 1,700.00 419,900.00
0.740 M³ Batu Kerikil 565,000.00 418,100.00
0.621 M³ Pasir Beton 350,000.00 217,350.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
0.189 OH Tukang Batu 135,000.00 25,515.00
0.019 OH Kepala Tukang 150,000.00 2,850.00
1.323 OH Pekerja 100,000.00 132,300.00
0.132 OH Mandor 135,000.00 17,820.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 1,358,085.00
Keuntungan & Overhead 10 % 135,808.50
Jumlah ……………………… 1,493,893.50

SNI.154 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.200 m3 Kayu Kelas III (papan) 2,600,000.00 520,000.00
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00

2.893 OH Pekerja 100,000.00 289,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
Jumlah ( A + B + C ) 4,642,395.00
Keuntungan & Overhead 10 % 464,239.50
Jumlah ……………………… 5,106,634.50

SNI.155 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi beton polos 16,000.00 3,200,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00

3.243 OH Pekerja 100,000.00 324,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
Jumlah ( A + B + C ) 5,756,945.00
Keuntungan & Overhead 10 % 575,694.50
Jumlah ……………………… 6,332,639.50

SNI.156 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00

2.893 OH Pekerja 100,000.00 289,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
Jumlah ( A + B + C ) 4,866,745.00
Keuntungan & Overhead 10 % 486,674.50
Jumlah ……………………… 5,353,419.50

SNI.157 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00

2.718 OH Pekerja 100,000.00 271,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
Jumlah ( A + B + C ) 4,421,645.00
Keuntungan & Overhead 10 % 442,164.50
Jumlah ……………………… 4,863,809.50

SNI.158 1 M3 Pekerjaan Sloof Beton Bertulang ( 120 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
120.000 Kg Besi beton polos 16,000.00 1,920,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00

2.683 OH Pekerja 100,000.00 268,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.840 OH Tukang besi 135,000.00 113,400.00
0.129 OH Kepala Tukang 150,000.00 19,350.00
0.206 OH Mandor 135,000.00 27,810.00
Jumlah ( A + B + C ) 4,332,625.00
Keuntungan & Overhead 10 % 433,262.50
Jumlah ……………………… 4,765,887.50

SNI.159 1 M3 Pekerjaan Sloof Beton Bertulang ( 100 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
100.000 Kg Besi beton polos 16,000.00 1,600,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00

2.543 OH Pekerja 100,000.00 254,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.700 OH Tukang besi 135,000.00 94,500.00
0.115 OH Kepala Tukang 150,000.00 17,250.00
0.198 OH Mandor 135,000.00 26,730.00
Jumlah ( A + B + C ) 3,976,545.00
Keuntungan & Overhead 10 % 397,654.50
Jumlah ……………………… 4,374,199.50

SNI.160 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00

3.383 OH Pekerja 100,000.00 338,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
Jumlah ( A + B + C ) 7,170,440.00
Keuntungan & Overhead 10 % 717,044.00
Jumlah ……………………… 7,887,484.00

SNI.161 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00

3.033 OH Pekerja 100,000.00 303,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
Jumlah ( A + B + C ) 6,280,240.00
Keuntungan & Overhead 10 % 628,024.00
Jumlah ……………………… 6,908,264.00

SNI.162 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00

2.858 OH Pekerja 100,000.00 285,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
Jumlah ( A + B + C ) 5,835,140.00
Keuntungan & Overhead 10 % 583,514.00
Jumlah ……………………… 6,418,654.00

SNI.163 1 M3 Pekerjaan Lantai Beton Bertulang ( 175 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 565,000.00 418,100.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00

3.208 OH Pekerja 100,000.00 320,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
Jumlah ( A + B + C ) 6,574,940.00
Keuntungan & Overhead 10 % 657,494.00
Jumlah ……………………… 7,232,434.00

SNI.164 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00

3.033 OH Pekerja 100,000.00 303,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
Jumlah ( A + B + C ) 6,129,840.00
Keuntungan & Overhead 10 % 612,984.00
Jumlah ……………………… 6,742,824.00

SNI.164.a2lp 1 M3 Pekerjaan Lantai Beton Bertulang ( 100 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


100.000 Kg Besi beton polos 16,000.00 1,600,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 565,000.00 418,100.00

2.683 OH Pekerja 100,000.00 268,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.700 OH Tukang besi 135,000.00 94,500.00
0.122 OH Kepala Tukang 150,000.00 18,300.00
0.205 OH Mandor 135,000.00 27,675.00
Jumlah ( A + B + C ) 3,208,440.00
Keuntungan & Overhead 10 % 320,844.00
Jumlah ……………………… 3,529,284.00

SNI.164.b1lp 1 M3 Pekerjaan Lantai Beton Bertulang ( 100 Kg Besi ) BT, 1 Pc : 2 Ps : 3 Kr


100.000 Kg Besi beton polos 16,000.00 1,600,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00

0.200 OH Tenaga 2,729,600.00 545,920.00


Jumlah ( A + B + C ) 3,275,520.00
Keuntungan & Overhead 10 % 327,552.00
Jumlah ……………………… 3,603,072.00

SNI.164.c1lp 1 M3 Pekerjaan Lantai Beton Bertulang ( 75 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


75.000 Kg Besi beton polos 16,000.00 1,200,000.00
1.125 Kg Kawat beton 33,000.00 37,125.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 565,000.00 418,100.00

0.200 OH Tenaga 2,292,475.00 458,495.00


Jumlah ( A + B + C ) 2,750,970.00
Keuntungan & Overhead 10 % 275,097.00
Jumlah ……………………… 3,026,067.00
SNI.164.1lp.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 100 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr
0.120 m3 Kayu terentang 2,600,000.00 312,000.00
1.600 Kg Paku biasa 2 " - 5 " 28,000.00 44,800.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
100.000 Kg Besi beton polos 16,000.00 1,600,000.00
1.125 Kg Kawat beton 33,000.00 37,125.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.080 m3 Kayu balok kelas II 3,640,000.00 291,200.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
12.000 Btg Dolken dia 8 cm - 4 m 11,000.00 132,000.00

2.683 OH Pekerja 100,000.00 268,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.700 OH Tukang besi 135,000.00 94,500.00
0.122 OH Kepala Tukang 150,000.00 18,300.00
0.205 OH Mandor 135,000.00 27,675.00
Jumlah ( A + B + C ) 4,422,515.00
Keuntungan & Overhead 10 % 442,251.50
Jumlah ……………………… 4,864,766.50

SNI.164.1lp.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 75 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.120 m3 Kayu terentang 2,600,000.00 312,000.00
1.600 Kg Paku biasa 2 " - 5 " 28,000.00 44,800.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
75.000 Kg Besi beton polos 16,000.00 1,200,000.00
1.125 Kg Kawat beton 33,000.00 37,125.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 565,000.00 418,100.00
0.080 m3 Kayu balok kelas II 3,640,000.00 291,200.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
12.000 Btg Dolken dia 8 cm - 4 m 11,000.00 132,000.00

2.508 OH Pekerja 100,000.00 250,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.525 OH Tukang besi 135,000.00 70,875.00
0.105 OH Kepala Tukang 150,000.00 15,675.00
0.195 OH Mandor 135,000.00 26,325.00
Jumlah ( A + B + C ) 3,977,415.00
Keuntungan & Overhead 10 % 397,741.50
Jumlah ……………………… 4,375,156.50

SNI.165 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00

3.383 OH Pekerja 100,000.00 338,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
Jumlah ( A + B + C ) 7,067,240.00
Keuntungan & Overhead 10 % 706,724.00
Jumlah ……………………… 7,773,964.00

SNI.166 1 M3 Pekerjaan Balok Beton Bertulang (175 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00

3.208 OH Pekerja 100,000.00 320,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
Jumlah ( A + B + C ) 6,622,140.00
Keuntungan & Overhead 10 % 662,214.00
Jumlah ……………………… 7,284,354.00

SNI.167 1 M3 Pekerjaan Balok Beton Bertulang (150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kayu balok kelas II 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00

3.033 OH Pekerja 100,000.00 303,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
Jumlah ( A + B + C ) 6,177,040.00
Keuntungan & Overhead 10 % 617,704.00
Jumlah ……………………… 6,794,744.00

SNI.168 1 M3 Pekerjaan Balok Beton Bertulang (125 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kayu balok kelas II 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00

2.858 OH Pekerja 100,000.00 285,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
Jumlah ( A + B + C ) 5,731,940.00
Keuntungan & Overhead 10 % 573,194.00
Jumlah ……………………… 6,305,134.00

SNI.169 1 M3 Pekerjaan Balok Beton Bertulang (110 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
110.000 Kg Besi beton polos 16,000.00 1,760,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 565,000.00 418,100.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kayu balok kelas II 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00

2.753 OH Pekerja 100,000.00 275,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.770 OH Tukang besi 135,000.00 103,950.00
0.129 OH Kepala Tukang 150,000.00 19,350.00
0.209 OH Mandor 135,000.00 28,215.00
Jumlah ( A + B + C ) 5,464,880.00
Keuntungan & Overhead 10 % 546,488.00
Jumlah ……………………… 6,011,368.00

SNI.170 1 M3 Pek Dinding Plat Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr
0.240 m3 Kayu Kelas III 2,600,000.00 624,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
14.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 154,000.00

3.033 OH Pekerja 100,000.00 303,300.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
Jumlah ( A + B + C ) 6,019,840.00
Keuntungan & Overhead 10 % 601,984.00
Jumlah ……………………… 6,621,824.00

SNI.171 1 M3 Pek Tangga Beton Bertulang ( 175 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr


0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 565,000.00 418,100.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00

3.208 OH Pekerja 100,000.00 320,800.00


0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
Jumlah ( A + B + C ) 6,622,140.00
Keuntungan & Overhead 10 % 662,214.00
Jumlah ……………………… 7,284,354.00

SNI.172 1 M' Pekerjaan Kolom Penguat Beton Bertulang ( 11 x 11 cm )


0.002 m3 Kayu Klas III 2,600,000.00 5,200.00
0.010 Kg Paku 5 cm - 12 cm 28,000.00 280.00
0.800 Ltr Minyak bekisting 18,000.00 14,400.00
3.000 Kg Besi beton polos 16,000.00 48,000.00
0.450 Kg Kawat beton 33,000.00 14,850.00
4.000 Kg Semen portland 1,700.00 6,800.00
0.006 m3 Pasir beton 350,000.00 2,100.00
0.009 m3 KR/Koral beton 565,000.00 5,085.00

0.180 OH Pekerja 100,000.00 18,000.00


0.020 OH Tukang batu 135,000.00 2,700.00
0.020 OH Tukang kayu 135,000.00 2,700.00
0.020 OH Tukang besi 135,000.00 2,700.00
0.006 OH Kepala Tukang 150,000.00 900.00
0.009 OH Mandor 135,000.00 1,215.00
Jumlah ( A + B + C ) 124,930.00
Keuntungan & Overhead 10 % 12,493.00
Jumlah ……………………… 137,423.00

SNI.173 1 M' Pekerjaan Ring Balok Beton Bertulang ( 10 x 15 cm )


0.003 m3 Kayu Klas III 2,600,000.00 7,800.00
0.020 Kg Paku 5 cm - 12 cm 28,000.00 560.00
0.800 Ltr Minyak bekisting 18,000.00 14,400.00
3.600 Kg Besi beton polos 16,000.00 57,600.00
0.050 Kg Kawat beton 33,000.00 1,650.00
5.500 Kg Semen portland 1,700.00 9,350.00
0.009 m3 Pasir beton 350,000.00 3,150.00
0.015 m3 KR/Koral beton 565,000.00 8,475.00

0.297 OH Pekerja 100,000.00 29,700.00


0.033 OH Tukang batu 135,000.00 4,455.00
0.033 OH Tukang kayu 135,000.00 4,455.00
0.033 OH Tukang besi 135,000.00 4,455.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.015 OH Mandor 135,000.00 2,025.00
Jumlah ( A + B + C ) 149,575.00
Keuntungan & Overhead 10 % 14,957.50
Jumlah ……………………… 164,532.50

SNI.154.a 1 M2 Pekerjaan Bekisting Pondasi


0.040 m3 Kayu Kelas III (papan) 2,600,000.00 104,000.00
0.300 kg Paku 5 cm - 12 cm 28,000.00 8,400.00
0.100 Ltr Minyak bekisting 18,000.00 1,800.00

0.520 OH Pekerja 100,000.00 52,000.00


0.260 OH Tukang kayu 135,000.00 35,100.00
0.026 OH Kepala Tukang 150,000.00 3,900.00
0.026 OH Mandor 135,000.00 3,510.00
Jumlah ( A + B + C ) 208,710.00
Keuntungan & Overhead 10 % 20,871.00
Jumlah ……………………… 229,581.00

SNI.155.a 1 M2 Pekerjaan Bekisting Sloof


0.045 m3 Kayu Kelas III (papan) 2,600,000.00 117,000.00
0.300 kg Paku 5 cm - 12 cm 28,000.00 8,400.00
0.100 Ltr Minyak bekisting 18,000.00 1,800.00

0.520 OH Pekerja 100,000.00 52,000.00


0.260 OH Tukang kayu 135,000.00 35,100.00
0.026 OH Kepala Tukang 150,000.00 3,900.00
0.026 OH Mandor 135,000.00 3,510.00
Jumlah ( A + B + C ) 221,710.00
Keuntungan & Overhead 10 % 22,171.00
Jumlah ……………………… 243,881.00

SNI.160.a 1 M2 Pekerjaan Bekisting Kolom


0.040 m3 Kayu Kelas III 2,600,000.00 104,000.00
0.400 Kg Paku 5 cm - 12 cm 28,000.00 11,200.00
0.200 Ltr Minyak bekisting 18,000.00 3,600.00
0.015 m 3
Kayu balok kelas II 3,640,000.00 54,600.00
0.350 Lbr Plywood tebal 9 mm 158,000.00 55,300.00
2.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 22,000.00

0.660 OH Pekerja 100,000.00 66,000.00


0.330 OH Tukang kayu 135,000.00 44,550.00
0.033 OH Kepala Tukang 150,000.00 4,950.00
0.033 OH Mandor 135,000.00 4,455.00
Jumlah ( A + B + C ) 370,655.00
Keuntungan & Overhead 10 % 37,065.50
Jumlah ……………………… 407,720.50

SNI.163.a 1 M2 Pekerjaan Bekisting Lantai


0.040 m3 Kayu terentang 2,600,000.00 104,000.00
0.400 Kg Paku biasa 2 " - 5 " 28,000.00 11,200.00
0.200 Ltr Minyak bekisting 18,000.00 3,600.00
0.015 m3 Kayu balok kelas II 3,640,000.00 54,600.00
0.350 Lbr Plywood tebal 9 mm 158,000.00 55,300.00
6.000 Btg Dolken dia 8 cm - 4 m 11,000.00 66,000.00

0.660 OH Pekerja 100,000.00 66,000.00


0.330 OH Tukang kayu 135,000.00 44,550.00
0.033 OH Kepala Tukang 150,000.00 4,950.00
0.033 OH Mandor 135,000.00 4,455.00
Jumlah ( A + B + C ) 414,655.00
Keuntungan & Overhead 10 % 41,465.50
Jumlah ……………………… 456,120.50

SNI.165.a 1 M2 Pekerjaan Bekisting Balok


0.040 m3 Kayu terentang kelas III 2,600,000.00 104,000.00
0.400 Kg Paku biasa 2 " - 5 " 28,000.00 11,200.00
0.200 Ltr Minyak bekisting 18,000.00 3,600.00
0.018 m 3
Kayu balok kelas II 3,640,000.00 65,520.00
0.350 Lbr Plywood tebal 9 mm 158,000.00 55,300.00
2.000 Btg Dolken dia 8 cm - 4 m 11,000.00 22,000.00

0.660 OH Pekerja 100,000.00 66,000.00


0.330 OH Tukang kayu 135,000.00 44,550.00
0.033 OH Kepala Tukang 150,000.00 4,950.00
0.033 OH Mandor 135,000.00 4,455.00
Jumlah ( A + B + C ) 381,575.00
Keuntungan & Overhead 10 % 38,157.50
Jumlah ……………………… 419,732.50

SNI.170.a 1 M2 Pek Bekisting Dinding Plat


0.030 m3 Kayu Kelas III 2,600,000.00 78,000.00
0.400 Kg Paku 5 cm - 12 cm 28,000.00 11,200.00
0.200 Ltr Minyak bekisting 18,000.00 3,600.00
0.020 m3 Kayu balok kelas II 3,640,000.00 72,800.00
0.350 Lbr Plywood tebal 9 mm 158,000.00 55,300.00
3.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 33,000.00

0.660 OH Pekerja 100,000.00 66,000.00


0.330 OH Tukang kayu 135,000.00 44,550.00
0.033 OH Kepala Tukang 150,000.00 4,950.00
0.033 OH Mandor 135,000.00 4,455.00
Jumlah ( A + B + C ) 373,855.00
Keuntungan & Overhead 10 % 37,385.50
Jumlah ……………………… 411,240.50

SNI.171.a 1 M2 Pek Bekisting Tangga


0.030 m3 Kayu terentang kelas III 2,600,000.00 78,000.00
0.400 Kg Paku biasa 2 " - 5 " 28,000.00 11,200.00
0.150 Ltr Minyak bekisting 18,000.00 2,700.00
0.015 m3 Kayu balok kelas II 3,640,000.00 54,600.00
0.350 Lbr Plywood tebal 9 mm 158,000.00 55,300.00
2.000 Btg Dolken dia 8 cm - 4 m 11,000.00 22,000.00

0.660 OH Pekerja 100,000.00 66,000.00


0.330 OH Tukang kayu 135,000.00 44,550.00
0.033 OH Kepala Tukang 150,000.00 4,950.00
0.033 OH Mandor 135,000.00 4,455.00
Jumlah ( A + B + C ) 343,755.00
Keuntungan & Overhead 10 % 34,375.50
Jumlah ……………………… 378,130.50

SNI.173.1 10 Kg Pembesian dengan Besi Polos


10.500 Kg Besi beton polos 16,000.00 168,000.00
0.150 Kg Kawat beton 33,000.00 4,950.00

0.070 OH Pekerja 100,000.00 7,000.00


0.070 OH Tukang besi 135,000.00 9,450.00
0.007 OH Kepala Tukang 150,000.00 1,050.00
0.004 OH Mandor 135,000.00 540.00
Jumlah ( A + B + C ) 190,990.00
Keuntungan & Overhead 10 % 19,099.00
Jumlah ……………………… 210,089.00
Jumlah 1 Kg Pembesian besi polos 21,008.90

SNI.173.2 10 Kg Pembesian dengan Besi Ulir


10.500 Kg Besi beton ulir 19,000.00 199,500.00
0.150 Kg Kawat beton 33,000.00 4,950.00

0.070 OH Pekerja 100,000.00 7,000.00


0.070 OH Tukang besi 135,000.00 9,450.00
0.007 OH Kepala Tukang 150,000.00 1,050.00
0.004 OH Mandor 135,000.00 540.00
Jumlah ( A + B + C ) 222,490.00
Keuntungan & Overhead 10 % 22,249.00
Jumlah ……………………… 244,739.00
Jumlah 1 Kg Pembesian besi ulir 24,473.90

SNI.173.3a Memasang 1 M2 Jaring Kawat Baja / Wiremesh 6 mm


1.020 Kg Jaring Kawat Baja/ Wiremesh 6 mm 36,000.00 36,720.00
0.050 Kg Kawat beton 33,000.00 1,650.00

0.025 OH Pekerja 100,000.00 2,500.00


0.025 OH Tukang besi 135,000.00 3,375.00
0.002 OH Kepala Tukang 150,000.00 300.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 44,680.00
Keuntungan & Overhead 10 % 4,468.00
Jumlah ……………………… 49,148.00

SNI.173.3b Memasang 1 M2 Jaring Kawat Baja / Wiremesh 8 mm


1.020 Kg Jaring Kawat Baja/ Wiremesh 8 mm 65,000.00 66,300.00
0.050 Kg Kawat beton 33,000.00 1,650.00

0.025 OH Pekerja 100,000.00 2,500.00


0.025 OH Tukang besi 135,000.00 3,375.00
0.002 OH Kepala Tukang 150,000.00 300.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 74,260.00
Keuntungan & Overhead 10 % 7,426.00
Jumlah ……………………… 81,686.00

SNI.173.3c Memasang 1 M2 Jaring Kawat Baja / Wiremesh 10 mm


1.020 Kg Jaring Kawat Baja/ Wiremesh 10 mm 104,000.00 106,080.00
0.050 Kg Kawat beton 33,000.00 1,650.00

0.025 OH Pekerja 100,000.00 2,500.00


0.025 OH Tukang besi 135,000.00 3,375.00
0.002 OH Kepala Tukang 150,000.00 300.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 114,040.00
Keuntungan & Overhead 10 % 11,404.00
Jumlah ……………………… 125,444.00

SNI.173.4a Memasang 1 M Plat lantai sistem Bondex 0.65 mm


1.030 M2 Plat Bondex tebal 0.65 mm 108,000.00 111,240.00
0.040 M3 Kayu terentang kelas III 2,600,000.00 104,000.00
0.100 Kg Paku biasa 2 " - 5 " 28,000.00 2,800.00
0.004 M3 Kayu balok kelas II 3,640,000.00 14,560.00
0.090 Lbr Plywood 9 mm 158,000.00 14,220.00
1.500 Btg Dolken dia 8 cm - 4 m 11,000.00 16,500.00

0.170 OH Pekerja 100,000.00 17,000.00


0.080 OH Tukang kayu 135,000.00 10,800.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 293,970.00
Keuntungan & Overhead 10 % 29,397.00
Jumlah ……………………… 323,367.00

SNI.173.4b Memasang 1 M Plat lantai sistem Bondex 0.70 mm


1.030 M2 Plat Bondex tebal 0.70 mm 119,000.00 122,570.00
0.040 M3 Kayu terentang kelas III 2,600,000.00 104,000.00
0.100 Kg Paku biasa 2 " - 5 " 28,000.00 2,800.00
0.004 M3 Kayu balok kelas II 3,640,000.00 14,560.00
0.090 Lbr Plywood 9 mm 158,000.00 14,220.00
1.500 Btg Dolken dia 8 cm - 4 m 11,000.00 16,500.00

0.170 OH Pekerja 100,000.00 17,000.00


0.080 OH Tukang kayu 135,000.00 10,800.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 305,300.00
Keuntungan & Overhead 10 % 30,530.00
Jumlah ……………………… 335,830.00

SNI.173.4c Memasang 1 M Plat lantai sistem Bondex 0.75 mm


1.030 M2 Plat Bondex tebal 0.75 mm 122,000.00 125,660.00
0.040 M3 Kayu terentang kelas III 2,600,000.00 104,000.00
0.100 Kg Paku biasa 2 " - 5 " 28,000.00 2,800.00
0.004 M3 Kayu balok kelas II 3,640,000.00 14,560.00
0.090 Lbr Plywood 9 mm 158,000.00 14,220.00
1.500 Btg Dolken dia 8 cm - 4 m 11,000.00 16,500.00

0.170 OH Pekerja 100,000.00 17,000.00


0.080 OH Tukang kayu 135,000.00 10,800.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 308,390.00
Keuntungan & Overhead 10 % 30,839.00
Jumlah ……………………… 339,229.00
SNI.173.4d Memasang 1 M Plat lantai sistem Bondex 0.100 mm
1.030 M2 Plat Bondex tebal 0.100 mm 203,000.00 209,090.00
0.040 M3 Kayu terentang kelas III 2,600,000.00 104,000.00
0.100 Kg Paku biasa 2 " - 5 " 28,000.00 2,800.00
0.004 M3 Kayu balok kelas II 3,640,000.00 14,560.00
0.090 Lbr Plywood 9 mm 158,000.00 14,220.00
1.500 Btg Dolken dia 8 cm - 4 m 11,000.00 16,500.00

0.170 OH Pekerja 100,000.00 17,000.00


0.080 OH Tukang kayu 135,000.00 10,800.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 391,820.00
Keuntungan & Overhead 10 % 39,182.00
Jumlah ……………………… 431,002.00

PEKERJAAN KAYU
SNI.174 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3
BAHAN
0.012 M³ Kayu Klas II 3,640,000.00 43,680.00
0.150 Kg Paku 7 - 12 cm 28,000.00 4,200.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 73,555.00
Keuntungan & Overhead 10 % 7,355.50
Jumlah ……………………… 80,910.50

SNI.174.a 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3 ( Expose )


BAHAN
0.012 M³ Kayu Klas II 3,640,000.00 43,680.00
0.150 Kg Paku 7 - 12 cm 28,000.00 4,200.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 93,892.50
Keuntungan & Overhead 10 % 9,389.25
Jumlah ……………………… 103,281.75

SNI.175 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 3/4


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.150 Kg Paku 7 - 12 cm 28,000.00 4,200.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 80,835.00
Keuntungan & Overhead 10 % 8,083.50
Jumlah ……………………… 88,918.50

SNI.175.a 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 3/4 ( Expose )


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.150 Kg Paku 7 - 12 cm 28,000.00 4,200.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 101,172.50
Keuntungan & Overhead 10 % 10,117.25
Jumlah ……………………… 111,289.75

SNI.176.a 1 M2 Mengerjakan / Memasang Usuk 5/7 cm


BAHAN
0.010 M³ Kayu Klas II 3,640,000.00 35,672.00
0.105 Kg Paku 7 - 12 cm 28,000.00 2,940.00
TENAGA
0.070 OH Tukang Kayu 135,000.00 9,450.00
0.007 OH Kepala Tukang Kayu 150,000.00 1,050.00
0.070 OH Pekerja 100,000.00 7,000.00
0.003 OH Mandor 135,000.00 472.50
Jumlah ( A + B + C ) 56,584.50
Keuntungan & Overhead 10 % 5,658.45
Jumlah ……………………… 62,242.95

SNI.176.b 1 M2 Mengerjakan / Memasang Kembali Usuk 5/7 cm


BAHAN
0.105 Kg Paku 7 - 12 cm 28,000.00 2,940.00
TENAGA
0.070 OH Tukang Kayu 135,000.00 9,450.00
0.007 OH Kepala Tukang Kayu 150,000.00 1,050.00
0.070 OH Pekerja 100,000.00 7,000.00
0.003 OH Mandor 135,000.00 472.50
Jumlah ( A + B + C ) 20,912.50
Keuntungan & Overhead 10 % 2,091.25
Jumlah ……………………… 23,003.75
SNI.176.c 1 M2 Mengerjakan / Memasang Reng 3/4 cm
BAHAN
0.004 M³ Kayu Klas II 3,640,000.00 15,288.00
0.045 Kg Paku 7 - 12 cm 28,000.00 1,260.00
TENAGA
0.030 OH Tukang Kayu 135,000.00 4,050.00
0.003 OH Kepala Tukang Kayu 150,000.00 450.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
Jumlah ( A + B + C ) 24,250.50
Keuntungan & Overhead 10 % 2,425.05
Jumlah ……………………… 26,675.55

SNI.176.d 1 M2 Mengerjakan / Memasang Kembali Usuk 5/7 cm


BAHAN
0.045 Kg Paku 7 - 12 cm 28,000.00 1,260.00
TENAGA
0.030 OH Tukang Kayu 135,000.00 4,050.00
0.003 OH Kepala Tukang Kayu 150,000.00 450.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
Jumlah ( A + B + C ) 8,962.50
Keuntungan & Overhead 10 % 896.25
Jumlah ……………………… 9,858.75

SNI.177 1 M' Pekerjaan Papan Lisplank Satu Lapis, Kisi-Kisi 3/20 Kayu Klas II
BAHAN
0.007 M³ Papan Kayu Klas II 3,730,000.00 26,856.00
0.050 Kg Paku 7 - 12 cm 28,000.00 1,400.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 69,681.00
Keuntungan & Overhead 10 % 6,968.10
Jumlah ……………………… 76,649.10

SNI.178 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 3/20 ) Kayu Klas II
BAHAN
0.015 M³ Papan Kayu Klas II 3,730,000.00 54,085.00
0.060 Kg Paku 7 - 12 cm 28,000.00 1,680.00
TENAGA
0.250 OH Tukang Kayu 135,000.00 33,750.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.150 OH Pekerja 100,000.00 15,000.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 118,390.00
Keuntungan & Overhead 10 % 11,839.00
Jumlah ……………………… 130,229.00

SNI.179 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II
BAHAN
0.009 M³ Papan Kayu Klas II 3,730,000.00 32,078.00
0.050 Kg Paku 7 - 12 cm 28,000.00 1,400.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 80,978.00
Keuntungan & Overhead 10 % 8,097.80
Jumlah ……………………… 89,075.80

SNI.179.a 1 M' Memasang Kembali Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 47,500.00
Keuntungan & Overhead 10 % 4,750.00
Jumlah ……………………… 52,250.00

SNI.180 1 M' Pekerjaan Papan Reuter (2/20)


BAHAN
0.004 M³ Papan Kayu Klas II 3,730,000.00 16,412.00
0.025 Kg Paku 7 - 12 cm 28,000.00 700.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 48,862.00
Keuntungan & Overhead 10 % 4,886.20
Jumlah ……………………… 53,748.20

SNI.181 1 M' Mengerjakan Talang Karet


BAHAN
0.019 M³ Papan Kayu Klas II 3,730,000.00 70,870.00
0.015 Kg Paku Biasa 1cm - 2,5 cm 28,000.00 420.00
1.050 M' Karet Talang 91,000.00 95,550.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 216,975.00
Keuntungan & Overhead 10 % 21,697.50
Jumlah ……………………… 238,672.50

SNI.182.a 1 M' Mengerjakan Talang datar/ jurai Seng BjLs 20


BAHAN
0.019 M³ Papan Kayu Klas II 3,730,000.00 70,870.00
0.015 Kg Paku Biasa 1cm - 2,5 cm 28,000.00 420.00
1.050 M' Seng Plat BjLs 20 74,000.00 77,700.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 199,125.00
Keuntungan & Overhead 10 % 19,912.50
Jumlah ……………………… 219,037.50

SNI.182.b 1 M' Mengerjakan Talang 1/2 lingkaran Seng BjLs 20


BAHAN
0.500 Kg Besi strip 34,000.00 17,000.00
0.015 Kg Paku Biasa 1cm - 2,5 cm 28,000.00 420.00
1.050 M' Seng Plat BjLs 20 74,000.00 77,700.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 156,200.00
Keuntungan & Overhead 10 % 15,620.00
Jumlah ……………………… 171,820.00

SNI.183 1 M3 Pekerjaan Kayu Kuda - Kuda, Gording Kayu Klas II


BAHAN
1.100 M³ Kayu Klas II 3,640,000.00 4,004,000.00
15.000 Kg Besi Strip 34,000.00 510,000.00
3.000 Kg Paku 7 - 12 cm 28,000.00 84,000.00
TENAGA
7.200 OH Tukang Kayu 135,000.00 972,000.00
0.720 OH Kepala Tukang Kayu 150,000.00 108,000.00
2.400 OH Pekerja 100,000.00 240,000.00
0.120 OH Mandor 135,000.00 16,200.00
Jumlah ( A + B + C ) 5,934,200.00
Keuntungan & Overhead 10 % 593,420.00
Jumlah ……………………… 6,527,620.00

SNI.184 1 M3 Pekerjaan Kayu Kuda - Kuda, Gording Kayu Klas II (Expose)


BAHAN
1.100 M³ Kayu Klas II 3,640,000.00 4,004,000.00
15.000 Kg Besi Strip 34,000.00 510,000.00
0.800 Kg Paku 7 - 12 cm 28,000.00 22,400.00
TENAGA
14.000 OH Tukang Kayu 135,000.00 1,890,000.00
1.400 OH Kepala Tukang Kayu 150,000.00 210,000.00
6.000 OH Pekerja 100,000.00 600,000.00
0.300 OH Mandor 135,000.00 40,500.00
Jumlah ( A + B + C ) 7,276,900.00
Keuntungan & Overhead 10 % 727,690.00
Jumlah ……………………… 8,004,590.00

SNI.185 1 M3 Pekerjaan Kayu Konsol, Tiang Kayu Klas II


BAHAN
1.200 M³ Kayu Klas II 3,640,000.00 4,368,000.00
0.800 Kg Paku 7 - 12 cm 28,000.00 22,400.00
TENAGA
1.500 OH Tukang Kayu 135,000.00 202,500.00
5.000 OH Kepala Tukang Kayu 150,000.00 750,000.00
15.000 OH Pekerja 100,000.00 1,500,000.00
0.200 OH Mandor 135,000.00 27,000.00
Jumlah ( A + B + C ) 6,869,900.00
Keuntungan & Overhead 10 % 686,990.00
Jumlah ……………………… 7,556,890.00

SNI.186 1 M' Pasang Kasiplank ukuran (0.8x20), 1 Lapis


BAHAN
1.100 M' Kasi plank 20,000.00 22,000.00
0.050 Kg Paku 5 cm - 10 cm 28,000.00 1,400.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 64,075.00
Keuntungan & Overhead 10 % 6,407.50
Jumlah ……………………… 70,482.50

SNI.187 1 M' Pasang Kasiplank ukuran (0.8x20), 2 Lapis


BAHAN
1.650 M' Kasi plank 20,000.00 33,000.00
0.075 Kg Paku 5 cm - 10 cm 28,000.00 2,100.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 96,112.50
Keuntungan & Overhead 10 % 9,611.25
Jumlah ……………………… 105,723.75

SNI.188 1 M3 Pekerjaan Kayu Konsol, Tiang Kayu Klas II (Expose)


BAHAN
1.200 M³ Kayu Klas II 3,640,000.00 4,368,000.00
0.800 Kg Paku 7 - 12 cm 28,000.00 22,400.00
TENAGA
1.600 OH Tukang Kayu 135,000.00 216,000.00
6.000 OH Kepala Tukang Kayu 150,000.00 900,000.00
16.000 OH Pekerja 100,000.00 1,600,000.00
0.300 OH Mandor 135,000.00 40,500.00
Jumlah ( A + B + C ) 7,146,900.00
Keuntungan & Overhead 10 % 714,690.00
Jumlah ……………………… 7,861,590.00
SNI.189 1 M3 Pekerjaan Kayu Kusen Pintu dan Jendela
BAHAN
1.200 M³ Kayu Klas II 3,640,000.00 4,368,000.00
1.000 Kg Lem Kayu 50,000.00 50,000.00
1.250 Kg Paku 7 - 12 cm 28,000.00 35,000.00
TENAGA
18.000 OH Tukang Kayu 135,000.00 2,430,000.00
2.000 OH Kepala Tukang Kayu 150,000.00 300,000.00
6.000 OH Pekerja 100,000.00 600,000.00
0.300 OH Mandor 135,000.00 40,500.00
Jumlah ( A + B + C ) 7,823,500.00
Keuntungan & Overhead 10 % 782,350.00
Jumlah ……………………… 8,605,850.00

SNI.190 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca 3 mm


BAHAN
0.024 M³ Papan Kayu Klas II 3,730,000.00 89,520.00
0.030 Kg Paku 28,000.00 840.00
0.300 Kg Lem Kayu 50,000.00 15,000.00
1.000 M² Kaca 3 mm 113,000.00 113,000.00
TENAGA
2.000 OH Tukang Kayu 135,000.00 270,000.00
0.200 OH Kepala Tukang Kayu 150,000.00 30,000.00
0.800 OH Pekerja 100,000.00 80,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 603,760.00
Keuntungan & Overhead 10 % 60,376.00
Jumlah ……………………… 664,136.00

SNI.191 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca 5 mm


BAHAN
0.024 M³ Papan Kayu Klas II 3,730,000.00 89,520.00
0.030 Kg Paku 28,000.00 840.00
0.300 Kg Lem Kayu 50,000.00 15,000.00
1.000 M² Kaca 5 mm 141,000.00 141,000.00
TENAGA
2.000 OH Tukang Kayu 135,000.00 270,000.00
0.200 OH Kepala Tukang Kayu 150,000.00 30,000.00
0.800 OH Pekerja 100,000.00 80,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 631,760.00
Keuntungan & Overhead 10 % 63,176.00
Jumlah ……………………… 694,936.00

SNI.192 1 M2 Pekerjaan Memasang Kaca Mati 3 mm Pintu / Jendela


BAHAN
0.020 Kg Paku 28,000.00 560.00
1.100 M² Kaca 3 mm 113,000.00 124,300.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 148,961.25
Keuntungan & Overhead 10 % 14,896.13
Jumlah ……………………… 163,857.38

SNI.193 1 M2 Pekerjaan Memasang Kaca Mati 5 mm Pintu / Jendela


BAHAN
0.020 Kg Paku 28,000.00 560.00
1.100 M² Kaca 5 mm 141,000.00 155,100.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 179,761.25
Keuntungan & Overhead 10 % 17,976.13
Jumlah ……………………… 197,737.38

SNI.193.8 1 M2 Pekerjaan Memasang Kaca Mati 8 mm Pintu / Jendela


BAHAN
0.020 Kg Paku 28,000.00 560.00
1.100 M² Kaca 8 mm 185,000.00 203,500.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 228,161.25
Keuntungan & Overhead 10 % 22,816.13
Jumlah ……………………… 250,977.38

SNI.194 1 M2 Pekerjaan Memasang Alumunium strip 8 mm


BAHAN
12.500 M² Alumunium Strip 57,000.00 712,500.00
0.050 m sealent 275.00 13.75
TENAGA
0.150 OH Tukang alumunium 135,000.00 20,250.00
0.015 OH Kepala Tukang alumunium 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 736,615.00
Keuntungan & Overhead 10 % 73,661.50
Jumlah ……………………… 810,276.50

SNI.195 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca Tempered 8 mm


BAHAN
0.024 M³ Papan Kayu Klas II 3,730,000.00 89,520.00
0.030 Kg Paku 28,000.00 840.00
0.300 Kg Lem Kayu 50,000.00 15,000.00
1.000 M² Kaca Tempered 8 mm Polos 1,000,000.00 1,000,000.00
TENAGA
2.000 OH Tukang Kayu 135,000.00 270,000.00
0.200 OH Kepala Tukang Kayu 150,000.00 30,000.00
0.800 OH Pekerja 100,000.00 80,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 1,490,760.00
Keuntungan & Overhead 10 % 149,076.00
Jumlah ……………………… 1,639,836.00

SNI.195.a 1 M2 Pekerjaan Memasang Kaca Cermin 5 mm


BAHAN
1.100 M² Kaca Cermin 5 mm 169,000.00 185,900.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 210,001.25
Keuntungan & Overhead 10 % 21,000.13
Jumlah ……………………… 231,001.38

SNI.196 1 M2 Pekerjaan Memasang Glass Blok


BAHAN
25.000 bh Glas Blok 20 x 20 cm 55,000.00 1,375,000.00
TENAGA
0.165 OH Tukang batu 135,000.00 22,275.00
0.017 OH Kepala Tukang batu 150,000.00 2,475.00
0.017 OH Pekerja 100,000.00 1,650.00
0.001 OH Mandor 135,000.00 108.00
Jumlah ( A + B + C ) 1,401,508.00
Keuntungan & Overhead 10 % 140,150.80
Jumlah ……………………… 1,541,658.80

SNI.197 1 M2 Pekerjaan Memasang Kaca Mati Riben 5 mm Pintu / Jendela


BAHAN
0.020 Kg Paku 28,000.00 560.00
1.100 M² Kaca Ryben 5 mm 164,000.00 180,400.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 205,061.25
Keuntungan & Overhead 10 % 20,506.13
Jumlah ……………………… 225,567.38

SNI.197.a 1 M2 Pekerjaan Memasang Kaca Mati Buram 5 mm Pintu / Jendela


BAHAN
0.020 Kg Paku 28,000.00 560.00
1.100 M² Kaca Buram 5 mm 215,000.00 236,500.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 261,161.25
Keuntungan & Overhead 10 % 26,116.13
Jumlah ……………………… 287,277.38

SNI.198 1 M2 Pekerjaan Memasang Kaca Mati Tempered 8 mm Pintu / Jendela


BAHAN
0.020 Kg Paku 28,000.00 560.00
1.100 M² Kaca Tempered 8mm 1,000,000.00 1,100,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 1,124,661.25
Keuntungan & Overhead 10 % 112,466.13
Jumlah ……………………… 1,237,127.38

SNI199 1 M2 Pekerjaan Daun Pintu / Jendela Panil dan Krepyak Kayu Klas II
BAHAN
0.140 M³ Papan Kayu Klas II 3,730,000.00 522,200.00
0.050 Kg Paku 1- 3 Cm 28,000.00 1,400.00
TENAGA
1.500 OH Tukang Kayu 135,000.00 202,500.00
0.150 OH Kepala Tukang Kayu 150,000.00 22,500.00
1.000 OH Pekerja 100,000.00 100,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 855,350.00
Keuntungan & Overhead 10 % 85,535.00
Jumlah ……………………… 940,885.00

SNI.200 1 M2 Pekerjaan Daun Pintu Panil dan Krepyak Kayu Klas II Lap. Formika
BAHAN
0.080 M³ Papan Kayu Klas II 3,730,000.00 298,400.00
0.050 Kg Paku 1- 3 Cm 28,000.00 1,400.00
0.500 Lbr Formika 192,000.00 96,000.00
TENAGA
1.500 OH Tukang Kayu 135,000.00 202,500.00
0.150 OH Kepala Tukang Kayu 150,000.00 22,500.00
1.000 OH Pekerja 100,000.00 100,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 727,550.00
Keuntungan & Overhead 10 % 72,755.00
Jumlah ……………………… 800,305.00

SNI.201 1 M2 Pekerjaan Ram Jalusi


BAHAN
0.060 M³ Papan Kayu Klas II 3,730,000.00 223,800.00
TENAGA
3.000 OH Tukang Kayu 135,000.00 405,000.00
0.300 OH Kepala Tukang Kayu 150,000.00 45,000.00
1.000 OH Pekerja 100,000.00 100,000.00
0.500 OH Mandor 135,000.00 67,500.00
Jumlah ( A + B + C ) 841,300.00
Keuntungan & Overhead 10 % 84,130.00
Jumlah ……………………… 925,430.00

SNI.202 1 M2 Pekerjaan Ram Jalusi Mati Kusen


BAHAN
0.060 M³ Papan Kayu Klas II 3,730,000.00 223,800.00
0.150 Kg Paku 1/2" - 1" 33,000.00 4,950.00
TENAGA
2.000 OH Tukang Kayu 135,000.00 270,000.00
0.200 OH Kepala Tukang Kayu 150,000.00 30,000.00
0.500 OH Pekerja 100,000.00 50,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 582,125.00
Keuntungan & Overhead 10 % 58,212.50
Jumlah ……………………… 640,337.50

SNI.203 1 M2 Pekerjaan Jendela Nako/ Tralis


BAHAN
1.100 M² Jendela Nako 141,000.00 155,100.00
10.000 Kg Paku 1/2" - 1" 33,000.00 330,000.00
7.000 M Besi Strip 34,000.00 238,000.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 773,235.00
Keuntungan & Overhead 10 % 77,323.50
Jumlah ……………………… 850,558.50

SNI.204 1 M2 Mengerjakan Daun Pintu Double Teakwood 3 mm


BAHAN
0.025 M³ Papan Kayu Klas II 3,730,000.00 93,250.00
1.000 Lbr Teakwood 120x240x3 mm 215,000.00 215,000.00
0.300 Kg Lem Kayu 50,000.00 15,000.00
0.030 Kg Paku 1/2" - 1" 33,000.00 990.00
TENAGA
2.000 OH Tukang Kayu 135,000.00 270,000.00
0.200 OH Kepala Tukang Kayu 150,000.00 30,000.00
0.800 OH Pekerja 100,000.00 80,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 709,640.00
Keuntungan & Overhead 10 % 70,964.00
Jumlah ……………………… 780,604.00

SNI.206 1 M2 Pekerjaan Pintu Double Tripleks 3 mm


BAHAN
0.025 M³ Papan Kayu Klas II 3,730,000.00 93,250.00
2.000 Lbr Tripleks 120x240x3 mm 66,000.00 132,000.00
0.300 Kg Lem Kayu 50,000.00 15,000.00
0.030 Kg Paku 1/2" - 1" 33,000.00 990.00
TENAGA
2.000 OH Tukang Kayu 135,000.00 270,000.00
0.040 OH Kepala Tukang Kayu 150,000.00 6,000.00
2.000 OH Pekerja 100,000.00 200,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 722,640.00
Keuntungan & Overhead 10 % 72,264.00
Jumlah ……………………… 794,904.00

SNI.208 1 M2 Pekerjaan Pintu Teakwood Lapis Formika


BAHAN
0.025 M³ Papan Kayu Klas II 3,730,000.00 93,250.00
0.500 Lbr Formika 192,000.00 96,000.00
1.000 Lbr Teakwood 120x240x3 mm 215,000.00 215,000.00
0.800 Kg Lem Kayu 50,000.00 40,000.00
0.030 Kg Paku 1/2" - 1" 33,000.00 990.00
TENAGA
2.500 OH Tukang Kayu 135,000.00 337,500.00
0.250 OH Kepala Tukang Kayu 150,000.00 37,500.00
0.800 OH Pekerja 100,000.00 80,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 905,640.00
Keuntungan & Overhead 10 % 90,564.00
Jumlah ……………………… 996,204.00

SNI.209 1 M2 Pekerjaan Pintu Triplek Lapis Formika


BAHAN
0.025 M³ Papan Kayu Klas II 3,730,000.00 93,250.00
0.500 Lbr Formika 192,000.00 96,000.00
1.000 Lbr Tripleks 120x240x3 mm 66,000.00 66,000.00
0.300 Ltr Lem Kayu 50,000.00 15,000.00
0.030 Kg Paku 1/2" - 1" 33,000.00 990.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.040 OH Kepala Tukang Kayu 150,000.00 6,000.00
2.000 OH Pekerja 100,000.00 200,000.00
0.040 OH Mandor 135,000.00 5,400.00
Jumlah ( A + B + C ) 509,640.00
Keuntungan & Overhead 10 % 50,964.00
Jumlah ……………………… 560,604.00

SNI.210 1 M2 Pekerjaan Pasang Kawat Gerawang


BAHAN
1.100 Lbr Kawat Gerawang 22,000.00 24,200.00
0.020 Kg Paku 1/2" - 1" 33,000.00 660.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.001 OH Mandor 135,000.00 67.50
Jumlah ( A + B + C ) 49,927.50
Keuntungan & Overhead 10 % 4,992.75
Jumlah ……………………… 54,920.25

SNI.211 1 M2 Pekerjaan Pasang Jeruji Besi Pintu


BAHAN
1.000 M2 Jeruji Pintu Besi 536,000.00 536,000.00
TENAGA
0.500 OH Tukang Las 135,000.00 67,500.00
0.050 OH Kepala Tukang 150,000.00 7,500.00
0.500 OH Pekerja 100,000.00 50,000.00
0.005 OH Mandor 135,000.00 708.75
Jumlah ( A + B + C ) 661,708.75
Keuntungan & Overhead 10 % 66,170.88
Jumlah ……………………… 727,879.63

SNI.212 1 M2 Pekerjaan Pasang Kawat Duri


BAHAN
0.175 Rol Kawat Duri 95,000.00 16,625.00
0.150 Kg Kawat Ikat Beton 33,000.00 4,950.00
TENAGA
0.650 OH Tukang Besi 135,000.00 87,750.00
0.065 OH Kepala Tukang 150,000.00 9,750.00
0.650 OH Pekerja 100,000.00 65,000.00
0.032 OH Mandor 135,000.00 4,320.00
Jumlah ( A + B + C ) 188,395.00
Keuntungan & Overhead 10 % 18,839.50
Jumlah ……………………… 207,234.50

SNI.213 1 M2 Pekerjaan Pagar besi Hollow (stenlistail)


BAHAN
6.000 M' Besi hollow 40 x 40 mm 100,000.00 600,000.00
11.000 M' Besi hollow 40 x 20 mm 38,000.00 418,000.00
TENAGA
1.050 OH Tukang Besi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.005 OH Mandor 135,000.00 708.75
Jumlah ( A + B + C ) 1,281,208.75
Keuntungan & Overhead 10 % 128,120.88
Jumlah ……………………… 1,409,329.63

SNI.214 1 M2 Pekerjaan Pagar besi Hollow


BAHAN
6.000 M' Besi hollow 40 x 40 mm 25,000.00 150,000.00
11.000 M' Besi hollow 40 x 20 mm 12,000.00 132,000.00
TENAGA
1.050 OH Tukang Besi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.005 OH Mandor 135,000.00 708.75
Jumlah ( A + B + C ) 545,208.75
Keuntungan & Overhead 10 % 54,520.88
Jumlah ……………………… 599,729.63

SNI.214.1 1 M2 Pekerjaan Pagar/ Dinding besi Hollow 100 x 50 mm


BAHAN
11.000 M' Besi hollow 100 x 50 mm 58,800.00 646,800.00
TENAGA
1.050 OH Tukang Besi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.005 OH Mandor 135,000.00 708.75
Jumlah ( A + B + C ) 910,008.75
Keuntungan & Overhead 10 % 91,000.88
Jumlah ……………………… 1,001,009.63

SNI.214.A 1 M2 Pekerjaan Pintu Pagar besi (dia. 16 mm)


BAHAN
1.000 M2 Pintu Besi Pagar (dia. 16 mm) 900,000.00 900,000.00
TENAGA
1.050 OH Tukang Besi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.005 OH Mandor 135,000.00 708.75
Jumlah ( A + B + C ) 1,163,208.75
Keuntungan & Overhead 10 % 116,320.88
Jumlah ……………………… 1,279,529.63

SNI.214.B 1 M2 Pekerjaan Pagar besi (dia. 16 mm)


BAHAN
1.000 M2 Pagar Besi (dia. 16 mm) 800,000.00 800,000.00
TENAGA
1.050 OH Tukang Besi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.005 OH Mandor 135,000.00 708.75
Jumlah ( A + B + C ) 1,063,208.75
Keuntungan & Overhead 10 % 106,320.88
Jumlah ……………………… 1,169,529.63
PEKERJAAN ATAP
SNI.215 1 M2 Pekerjaan Atap Genteng Lokal
BAHAN
26.000 Bh Genteng Lokal 1,800.00 46,800.00
TENAGA
0.075 OH Tukang Kayu 135,000.00 10,125.00
0.008 OH Kepala Tukang Kayu 150,000.00 1,200.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 74,205.00
Keuntungan & Overhead 10 % 7,420.50
Jumlah ……………………… 81,625.50

SNI.216 1 M2 Pekerjaan Bubungan Genteng Lokal


BAHAN
6.000 Bh Bubungan Genteng Lokal 6,800.00 40,800.00
8.000 Kg Pc 1,700.00 13,600.00
0.032 M³ Pasir 220,000.00 7,040.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.002 OH Mandor 135,000.00 270.00
Jumlah ( A + B + C ) 131,710.00
Keuntungan & Overhead 10 % 13,171.00
Jumlah ……………………… 144,881.00

SNI.217 1 M2 Pekerjaan Atap Genteng Pejaten Bali


BAHAN
25.000 Bh Genteng Pejaten 3,800.00 95,000.00
TENAGA
0.075 OH Tukang Kayu 135,000.00 10,125.00
0.008 OH Kepala Tukang Kayu 150,000.00 1,200.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 122,405.00
Keuntungan & Overhead 10 % 12,240.50
Jumlah ……………………… 134,645.50

SNI.217,a 1m² Pasang Atap Genteng Bitumen Monoleyer model gelombang ex. Onduline
BAHAN
0.878 lbr Atap bitumen gelombang H : 3,0 mm 192,500.00 168,988.55
15.802 bh Paku fiser bitumen 1,500.00 23,702.29
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 227,825.84
Keuntungan & Overhead 10 % 22,782.58
Jumlah ……………………… 250,608.42

SNI.218 1 M2 Pekerjaan Bubungan Genteng Pejaten Bali


BAHAN
5.000 Bh Bubungan Genteng Pejaten 8,700.00 43,500.00
8.000 Kg Semen Portland 1,700.00 13,600.00
0.032 M³ Pasir 220,000.00 7,040.00
TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.020 OH Kepala Tukang Batu 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.002 OH Mandor 135,000.00 270.00
Jumlah ( A + B + C ) 134,410.00
Keuntungan & Overhead 10 % 13,441.00
Jumlah ……………………… 147,851.00

SNI.218.a 1 m Pemasangan nok bitumen Monolayer


BAHAN
72.760 Lbr Nok / Ridge Onduline 1,500.00 109,140.00
1.200 bh Sekrup / Paku 12,500.00 15,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.250 OH Pekerja 100,000.00 25,000.00
0.013 OH Mandor 135,000.00 1,755.00
Jumlah ( A + B + C ) 173,395.00
Keuntungan & Overhead 10 % 17,339.50
Jumlah ……………………… 190,734.50

SNI.219.0.25 1 M2 Pekerjaan Atap Trimdeck 0.25 TCT (Spandek)


BAHAN
1.100 M2 Penutup Atap Trimdeck 60,000.00 66,000.00
12.000 Bh Paku Mata Bor Tahan Karat 1,900.00 22,800.00
0.001 Unit Mesin Bor Baut 1,334,000.00 1,334.00
TENAGA
0.500 OH Tukang Besi 135,000.00 67,500.00
0.050 OH Kepala Tukang Besi 150,000.00 7,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 176,484.00
Keuntungan & Overhead 10 % 17,648.40
Jumlah ……………………… 194,132.40
SNI.219.0.30 1 M2 Pekerjaan Atap Trimdeck 0.30 TCT (Spandek)
BAHAN
1.100 M2 Penutup Atap Trimdeck 70,000.00 77,000.00
12.000 Bh Paku Mata Bor Tahan Karat 1,900.00 22,800.00
0.001 Unit Mesin Bor Baut 1,334,000.00 1,334.00
TENAGA
0.500 OH Tukang Besi 135,000.00 67,500.00
0.050 OH Kepala Tukang Besi 150,000.00 7,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 187,484.00
Keuntungan & Overhead 10 % 18,748.40
Jumlah ……………………… 206,232.40

SNI.219.0.35 1 M2 Pekerjaan Atap Trimdeck 0.35 TCT (Spandek)


BAHAN
1.100 M2 Penutup Atap Trimdeck 94,000.00 103,400.00
12.000 Bh Paku Mata Bor Tahan Karat 1,900.00 22,800.00
0.001 Unit Mesin Bor Baut 1,334,000.00 1,334.00
TENAGA
0.500 OH Tukang Besi 135,000.00 67,500.00
0.050 OH Kepala Tukang Besi 150,000.00 7,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 213,884.00
Keuntungan & Overhead 10 % 21,388.40
Jumlah ……………………… 235,272.40

SNI.220 1 M' Pekerjaan Memasang Bubungan Trimdeck 0.35 TCT (Spandek)


BAHAN
1.100 M2 Bubungan Atap Trimdeck 51,000.00 56,100.00
5.460 Bh Paku Mata Bor Tahan Karat 1,900.00 10,374.00
TENAGA
0.055 OH Tukang Besi 135,000.00 7,425.00
0.006 OH Kepala Tukang Besi 150,000.00 825.00
0.200 OH Pekerja 100,000.00 20,000.00
0.002 OH Mandor 135,000.00 270.00
Jumlah ( A + B + C ) 94,994.00
Keuntungan & Overhead 10 % 9,499.40
Jumlah ……………………… 104,493.40

SNI.221.a 1 M2 Pekerjaan Atap Genteng Kodok


BAHAN
25.000 Bh Genteng Kodok 5,500.00 137,500.00
TENAGA
0.075 OH Tukang Kayu 135,000.00 10,125.00
0.008 OH Kepala Tukang Kayu 150,000.00 1,200.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 164,905.00
Keuntungan & Overhead 10 % 16,490.50
Jumlah ……………………… 181,395.50

SNI.221.b 1 M2 Pekerjaan Atap Genteng kanmuri full flat


BAHAN
11.500 Bh Genteng Kanmuri 18,000.00 207,000.00
TENAGA
0.075 OH Tukang Kayu 135,000.00 10,125.00
0.008 OH Kepala Tukang Kayu 150,000.00 1,200.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 234,405.00
Keuntungan & Overhead 10 % 23,440.50
Jumlah ……………………… 257,845.50

SNI.222.a 1 M2 Pekerjaan Bubungan Genteng Kodok


BAHAN
5.000 Bh Bubungan Genteng Kodok 6,500.00 32,500.00
8.000 Kg Semen Portland 1,700.00 13,600.00
0.032 M³ Pasir 220,000.00 7,040.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.002 OH Mandor 135,000.00 270.00
Jumlah ( A + B + C ) 123,410.00
Keuntungan & Overhead 10 % 12,341.00
Jumlah ……………………… 135,751.00

SNI.222.b 1 M2 Pekerjaan Bubungan Genteng kanmuri full flat


BAHAN
5.000 Bh Bubungan Genteng kanmuri 34,000.00 170,000.00
8.000 Kg Semen Portland 1,700.00 13,600.00
0.032 M³ Pasir 220,000.00 7,040.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.002 OH Mandor 135,000.00 270.00
Jumlah ( A + B + C ) 260,910.00
Keuntungan & Overhead 10 % 26,091.00
Jumlah ……………………… 287,001.00
SNI.223 1 M2 Pekerjaan Atap Seng Gelombang BJLS 20
BAHAN
0.900 Lbr Seng BJLS 20 mm 74,000.00 66,600.00
0.070 Kg Paku Seng 45,000.00 3,150.00
TENAGA
0.015 OH Tukang Kayu 135,000.00 2,025.00
0.150 OH Kepala Tukang Kayu 150,000.00 22,500.00
0.150 OH Pekerja 100,000.00 15,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 116,025.00
Keuntungan & Overhead 10 % 11,602.50
Jumlah ……………………… 127,627.50

SNI.224 1 M' Memasang Bubungan Seng BJLS 20


BAHAN
0.900 Lbr Seng BJLS 20 mm 48,000.00 43,200.00
0.070 Kg Paku Seng 45,000.00 3,150.00
TENAGA
0.015 OH Tukang Kayu 135,000.00 2,025.00
0.150 OH Kepala Tukang Kayu 150,000.00 22,500.00
0.150 OH Pekerja 100,000.00 15,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 92,625.00
Keuntungan & Overhead 10 % 9,262.50
Jumlah ……………………… 101,887.50

SNI.225 1 M2 Pekerjaan Atap Asbes Gelombang Kecil


BAHAN
0.750 Lbr Asbes Gelombang Kecil 68,000.00 51,000.00
0.120 Kg Paku Asbes 45,000.00 5,400.00
TENAGA
0.070 OH Tukang Kayu 135,000.00 9,450.00
0.070 OH Kepala Tukang Kayu 150,000.00 10,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.007 OH Mandor 135,000.00 945.00
Jumlah ( A + B + C ) 91,295.00
Keuntungan & Overhead 10 % 9,129.50
Jumlah ……………………… 100,424.50

SNI.226 1 M' Memasang Bubungan Asbes Gelombang Kecil


BAHAN
1.000 Lbr Bubungan Asbes Gelombang Kecil 53,000.00 53,000.00
0.120 Kg Paku Asbes 45,000.00 5,400.00
TENAGA
0.067 OH Tukang Kayu 135,000.00 9,045.00
0.007 OH Kepala Tukang Kayu 150,000.00 1,050.00
0.140 OH Pekerja 100,000.00 14,000.00
0.007 OH Mandor 135,000.00 945.00
Jumlah ( A + B + C ) 83,440.00
Keuntungan & Overhead 10 % 8,344.00
Jumlah ……………………… 91,784.00

SNI.227 1 m2 Mengerjakan atap genteng Metalroof ( Tebal 2.5 mm ) lapisan butiran


BAHAN
1.500 Lbr Genteng metal roof 60,000.00 90,000.00
0.200 kg Paku biasa 1/2"=1" 33,000.00 6,600.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 125,735.00
Keuntungan & Overhead 10 % 12,573.50
Jumlah ……………………… 138,308.50

SNI.228 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 2.5 mm ) lap. Butiran
BAHAN
1.100 m' Bubungan Genteng metal roof 65,000.00 71,500.00
0.050 kg Paku biasa 1/2"=1" 33,000.00 1,650.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 102,285.00
Keuntungan & Overhead 10 % 10,228.50
Jumlah ……………………… 112,513.50

SNI.229.a 1 m2 Mengerjakan atap genteng Metalroof ( Tebal 3 mm ) lapisan butiran


BAHAN
1.500 Lbr Genteng metal roof 82,000.00 123,000.00
0.200 kg Paku biasa 1/2"=1" 33,000.00 6,600.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 158,735.00
Keuntungan & Overhead 10 % 15,873.50
Jumlah ……………………… 174,608.50

SNI.229.b 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 3 mm ) lap. Butiran
BAHAN
1.100 m' Bubungan Genteng metal roof 85,000.00 93,500.00
0.050 kg Paku biasa 1/2"=1" 33,000.00 1,650.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 124,285.00
Keuntungan & Overhead 10 % 12,428.50
Jumlah ……………………… 136,713.50

SNI.230 1 m2 Mengerjakan atap genteng Metal ( Tebal 2.5 mm ) Sakura


BAHAN
1.660 Lbr Genteng Metal anti karat (sakura) 40,000.00 66,400.00
0.200 kg Paku biasa 1/2"=1" 33,000.00 6,600.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 102,135.00
Keuntungan & Overhead 10 % 10,213.50
Jumlah ……………………… 112,348.50

SNI.231 1 m' Mengerjakan bubungan Genteng Metal ( Tebal 2.5 mm )


BAHAN
1.100 m' Bubungan Genteng Metal anti karat 42,000.00 46,200.00
0.050 kg Paku biasa 1/2"=1" 33,000.00 1,650.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 76,985.00
Keuntungan & Overhead 10 % 7,698.50
Jumlah ……………………… 84,683.50

SNI.232 1 m2 Mengerjakan Plafond Gypsum Board, tebal 9 mm + rangka kayu


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.020 Kg Paku Panjang 4-6 Cm 28,000.00 560.00
0.364 Lbr Gypsum Board Tebal 9 mm 95,000.00 34,580.00
0.110 kg Paku Sekrup 35,000.00 3,850.00
TENAGA
0.300 OH Tukang 135,000.00 40,500.00
0.030 OH Kepala tukang 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 156,300.00
Keuntungan & Overhead 10 % 15,630.00
Jumlah ……………………… 171,930.00

SNI.233.a 1 m' Mengerjakan List Plafond Gypsum Board Type I


BAHAN
1.050 m' List Gypsum Type I 52,000.00 54,600.00
0.064 kg Lem Gypsum 29,000.00 1,856.00
TENAGA
0.021 OH Tukang 135,000.00 2,835.00
0.002 OH Kepala tukang 150,000.00 315.00
0.021 OH Pekerja 100,000.00 2,100.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 61,841.00
Keuntungan & Overhead 10 % 6,184.10
Jumlah ……………………… 68,025.10

SNI.233.b 1 m' Mengerjakan List Plafond Gypsum Board Type II


BAHAN
1.050 m' List Gypsum Type II 39,000.00 40,950.00
0.064 kg Lem Gypsum 29,000.00 1,856.00
TENAGA
0.021 OH Tukang 135,000.00 2,835.00
0.002 OH Kepala tukang 150,000.00 315.00
0.021 OH Pekerja 100,000.00 2,100.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 48,191.00
Keuntungan & Overhead 10 % 4,819.10
Jumlah ……………………… 53,010.10

SNI.234 1 m2 Mengerjakan Plafond Gypsum Rangka Hollow 40x40 Zincromate


BAHAN
2.750 M' Besi Holow 40x40 zincromate 25,000.00 68,750.00
1.100 M2 Gypsum Board Tebal 9 mm 95,000.00 104,500.00
0.110 kg Paku Sekrup 35,000.00 3,850.00
0.064 kg Lem Gypsum 29,000.00 1,856.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala tukang 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 224,968.50
Keuntungan & Overhead 10 % 22,496.85
Jumlah ……………………… 247,465.35
SNI.234.a 1 m2 Memasang langit-langit WPC , rangka metal furing
BAHAN
0.250 btg Top Cross Rail 250FX 30,000.00 7,500.00
0.370 btg Furring Chanel PN 205 85,000.00 31,450.00
1.700 bh Furring Chanel PN 208 2,600.00 4,420.00
0.810 bh Suspension Spring Clip 223SS 5,200.00 4,212.00
0.810 bh 4 mm Soft Galv Suspension Rod PN 225 5,250.00 4,252.50
0.810 bh Angle Bracket PN 220 2,000.00 1,620.00
0.810 bh Wall Angle 252FX 4,200.00 3,402.00
0.050 roll Paper Tape 30,000.00 1,500.00
0.075 roll Steel Tape 131,200.00 9,840.00
0.003 kg UB Cote Read Mix 160,000.00 480.00
1.754 lbr Papan WPC teval 7 mm 328,900.00 577,017.54
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.075 OH Kepala tukang 150,000.00 11,250.00
0.780 OH Pekerja 100,000.00 78,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 809,194.04
Keuntungan & Overhead 10 % 80,919.40
Jumlah ……………………… 890,113.45

SNI.234.b 1 m2 Pasang Atap Kaca Laminasi / Laminated 12 mm rangka hollow


BAHAN
4.400 m1 Rangka Hollow 5 x 100 mm 137,500.00 605,000.00
1.050 m2 Kaca Laminated 12 mm 1,500,000.00 1,575,000.00
TENAGA
0.800 OH Tukang Besi 135,000.00 108,000.00
0.080 OH Kepala tukang Besi 150,000.00 12,000.00
0.080 OH Pekerja 100,000.00 8,000.00
0.004 OH Mandor 135,000.00 540.00
Jumlah ( A + B + C ) 2,308,540.00
Keuntungan & Overhead 10 % 230,854.00
Jumlah ……………………… 2,539,394.00

SNI.234.c 1 m2 Pasang Kaca Tempered Clear T=10


BAHAN
1.100 m2 Kaca Tempered Clear T=10 1,250,000.00 1,375,000.00
TENAGA
0.800 OH Tukang Kayu 135,000.00 108,000.00
0.080 OH Kepala tukang Kayu 150,000.00 12,000.00
0.080 OH Pekerja 100,000.00 8,000.00
0.004 OH Mandor 135,000.00 540.00
Jumlah ( A + B + C ) 1,503,540.00
Keuntungan & Overhead 10 % 150,354.00
Jumlah ……………………… 1,653,894.00

SNI.234.d 1 m2 Pasang Atap Kanopi GRC gelombang


BAHAN
1.050 m2 GRC Board bergelombang 89,800.00 94,290.00
TENAGA
0.800 OH Tukang Kayu 135,000.00 108,000.00
0.080 OH Kepala tukang Kayu 150,000.00 12,000.00
0.080 OH Pekerja 100,000.00 8,000.00
0.004 OH Mandor 135,000.00 540.00
Jumlah ( A + B + C ) 222,830.00
Keuntungan & Overhead 10 % 22,283.00
Jumlah ……………………… 245,113.00

SNI.234.SP.1 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Putih polos
BAHAN
2.750 M' Besi Holow 40x40 zincromate 25,000.00 68,750.00
1.300 M2 PVC/ Shunda Plafond, 1.2 mm, Putih Polo 240,000.00 312,000.00
0.170 kg Paku Sekrup 35,000.00 5,950.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala tukang 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 432,712.50
Keuntungan & Overhead 10 % 43,271.25
Jumlah ……………………… 475,983.75

SNI.234.SP.2 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Warna


BAHAN
2.750 M' Besi Holow 40x40 zincromate 25,000.00 68,750.00
1.300 M2 PVC/ Shunda Plafond, 1.2 mm, Warna 270,000.00 351,000.00
0.170 kg Paku Sekrup 35,000.00 5,950.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala tukang 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 471,712.50
Keuntungan & Overhead 10 % 47,171.25
Jumlah ……………………… 518,883.75

SNI.234.AQ 1 m2 Mengerjakan Plafond Akustik Rangka Alumunium


BAHAN
3.600 M' Rangka Alumunium "T" 14,000.00 50,400.00
1.300 Lbr Plafond Akustik 600 x 600 150,000.00 195,000.00
0.150 kg Kawat f 4 mm 8,000.00 1,200.00
1.050 kg Ramset/ Dinabolt 75,000.00 78,750.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala tukang 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 371,362.50
Keuntungan & Overhead 10 % 37,136.25
Jumlah ……………………… 408,498.75

SNI.235.a 1 M2 Pekerjaan Plafond Tripleks 3 mm + Rangka kayu


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.020 Kg Paku Panjang 4-6 Cm 28,000.00 560.00
0.015 Kg Paku Panjang 1-3 Cm 33,000.00 495.00
0.375 Lbr Tripleks 3 mm 66,000.00 24,750.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 143,115.00
Keuntungan & Overhead 10 % 14,311.50
Jumlah ……………………… 157,426.50

SNI.235.b 1 M2 Pekerjaan Plafond Tripleks 5 mm + Rangka kayu


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.020 Kg Paku Panjang 4-6 Cm 28,000.00 560.00
0.015 Kg Paku Panjang 1-3 Cm 33,000.00 495.00
0.375 Lbr Tripleks 5 mm 105,000.00 39,375.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 157,740.00
Keuntungan & Overhead 10 % 15,774.00
Jumlah ……………………… 173,514.00

SNI.235.c 1 M2 Pekerjaan Rangka Langit-langit


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.020 Kg Paku Panjang 7-10 Cm 28,000.00 560.00
TENAGA
0.230 OH Tukang Kayu 135,000.00 31,050.00
0.023 OH Kepala Tukang Kayu 150,000.00 3,450.00
0.170 OH Pekerja 100,000.00 17,000.00
0.008 OH Mandor 135,000.00 1,035.00
Jumlah ( A + B + C ) 104,055.00
Keuntungan & Overhead 10 % 10,405.50
Jumlah ……………………… 114,460.50

SNI.235.d 1 M2 Pekerjaan Plafond Tripleks 5 mm


BAHAN
0.015 Kg Paku Panjang 1-5 Cm 33,000.00 495.00
0.375 Lbr Tripleks 5 mm 105,000.00 39,375.00
TENAGA
0.070 OH Tukang Kayu 135,000.00 9,450.00
0.007 OH Kepala Tukang Kayu 150,000.00 1,050.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 315.00
Jumlah ( A + B + C ) 53,685.00
Keuntungan & Overhead 10 % 5,368.50
Jumlah ……………………… 59,053.50

SNI.236.a 1 M2 Pekerjaan Plafond Miring Tripleks 3 mm + Rangka kayu


BAHAN
0.015 Kg Paku Panjang 1-3 Cm 33,000.00 495.00
0.007 M³ Kayu Klas II 3,640,000.00 25,480.00
0.375 Lbr Tripleks 3 mm 66,000.00 24,750.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 117,075.00
Keuntungan & Overhead 10 % 11,707.50
Jumlah ……………………… 128,782.50

SNI.236.b 1 M2 Pekerjaan Plafond Miring Tripleks 5 mm + Rangka kayu


BAHAN
0.015 Kg Paku Panjang 1-3 Cm 33,000.00 495.00
0.007 M³ Kayu Klas II 3,640,000.00 25,480.00
0.375 Lbr Tripleks 5 mm 105,000.00 39,375.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 131,700.00
Keuntungan & Overhead 10 % 13,170.00
Jumlah ……………………… 144,870.00
SNI.237.a 1 M2 Pekerjaan Dinding Double Tripleks 3 mm + Rangka kayu
BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.020 Kg Paku Panjang 4-6 Cm 28,000.00 560.00
0.030 Kg Paku Panjang 1-3 Cm 33,000.00 990.00
0.750 Lbr Tripleks 3 mm 66,000.00 49,500.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 168,360.00
Keuntungan & Overhead 10 % 16,836.00
Jumlah ……………………… 185,196.00

SNI.237.b 1 M2 Pekerjaan Dinding Double Tripleks 5 mm + Rangka kayu


BAHAN
0.014 M³ Kayu Klas II 3,640,000.00 50,960.00
0.020 Kg Paku Panjang 4-6 Cm 28,000.00 560.00
0.030 Kg Paku Panjang 1-3 Cm 33,000.00 990.00
0.750 Lbr Tripleks 5 mm 105,000.00 78,750.00
TENAGA
0.300 OH Tukang Kayu 135,000.00 40,500.00
0.030 OH Kepala Tukang Kayu 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 197,610.00
Keuntungan & Overhead 10 % 19,761.00
Jumlah ……………………… 217,371.00

SNI.238 1 M' Pekerjaan List Plafond Kayu Profil 4/4 cm


BAHAN
1.050 M³ List Profil 4/4 cm 14,000.00 14,700.00
0.010 Kg Paku Panjang 1-3 Cm 33,000.00 330.00
TENAGA
0.050 OH Tukang Kayu 135,000.00 6,750.00
0.005 OH Kepala Tukang Kayu 150,000.00 750.00
0.050 OH Pekerja 100,000.00 5,000.00
0.003 OH Mandor 135,000.00 405.00
Jumlah ( A + B + C ) 27,935.00
Keuntungan & Overhead 10 % 2,793.50
Jumlah ……………………… 30,728.50

SNI.239 1 M' Pekerjaan List Plafond Kayu Profil 2/4 cm


BAHAN
1.050 M³ List Profil 2/4 cm 9,000.00 9,450.00
0.010 Kg Paku Panjang 1-3 Cm 33,000.00 330.00
TENAGA
0.050 OH Tukang Kayu 135,000.00 6,750.00
0.005 OH Kepala Tukang Kayu 150,000.00 750.00
0.050 OH Pekerja 100,000.00 5,000.00
0.003 OH Mandor 135,000.00 405.00
Jumlah ( A + B + C ) 22,685.00
Keuntungan & Overhead 10 % 2,268.50
Jumlah ……………………… 24,953.50

PEKERJAAN ALUMUNIUM dan BESI


SNI.240 Memasang 1 Kg Besi Profil
BAHAN
1.150 M³ Besi Profil 30,000.00 34,500.00
TENAGA
0.060 OH Tukang Las Konstruksi 135,000.00 8,100.00
0.006 OH Kepala Tukang 150,000.00 900.00
0.060 OH Pekerja 100,000.00 6,000.00
0.003 OH Mandor 135,000.00 405.00
Jumlah ( A + B + C ) 49,905.00
Keuntungan & Overhead 10 % 4,990.50
Jumlah ……………………… 54,895.50

SNI.241.1 Memasang 1 Kg Rangka Kuda-kuda Baja IWF


BAHAN
1.150 M³ Besi Baja IWF 30,000.00 34,500.00
TENAGA
0.060 OH Tukang Las Konstruksi 135,000.00 8,100.00
0.006 OH Kepala Tukang 150,000.00 900.00
0.060 OH Pekerja 100,000.00 6,000.00
0.003 OH Mandor 135,000.00 405.00
Jumlah ( A + B + C ) 49,905.00
Keuntungan & Overhead 10 % 4,990.50
Jumlah ……………………… 54,895.50

SNI.241.a Memasang 1 Kg Rangka Kanal - C


BAHAN
1.150 M³ Besi Kanal C 30,000.00 34,500.00
TENAGA
0.060 OH Tukang Las Konstruksi 135,000.00 8,100.00
0.006 OH Kepala Tukang 150,000.00 900.00
0.060 OH Pekerja 100,000.00 6,000.00
0.003 OH Mandor 135,000.00 405.00
Jumlah ( A + B + C ) 49,905.00
Keuntungan & Overhead 10 % 4,990.50
Jumlah ……………………… 54,895.50
SNI.241.b Pasang 1 m Handrail dan Railing
BAHAN
2.650 m1 Pipa 2" black steel di cat duco 68,700.00 182,055.00
4.400 m1 Pipa 1"black steel dicat duco 43,700.00 192,280.00
10% Harga (Perlengkapan) 56,200.00 5,620.00
TENAGA
0.250 OH Tukang Las Konstruksi 135,000.00 33,750.00
0.115 OH Kepala Tukang 150,000.00 17,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 121.50
Jumlah ( A + B + C ) 432,576.50
Keuntungan & Overhead 10 % 43,257.65
Jumlah ……………………… 475,834.15

SNI.241.c Pasang 1 m Galvanis Steel 3/4"


BAHAN
1.100 m1 Galvanis Steel 3/4" 42,700.00 46,970.00
15% Harga (Perlengkapan) 42,700.00 6,405.00
TENAGA
0.150 OH Tukang Las Konstruksi 135,000.00 20,250.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.150 OH Pekerja 100,000.00 15,000.00
0.001 OH Mandor 135,000.00 121.50
Jumlah ( A + B + C ) 90,996.50
Keuntungan & Overhead 10 % 9,099.65
Jumlah ……………………… 100,096.15

SNI.241.d Pasang 1 m Railing Stainless


BAHAN
8.075 m1 Besi Stainless Ø 3/4' 93,700.00 756,627.50
TENAGA
0.250 OH Tukang Las Konstruksi 135,000.00 33,750.00
0.115 OH Kepala Tukang 150,000.00 17,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 121.50
Jumlah ( A + B + C ) 809,249.00
Keuntungan & Overhead 10 % 80,924.90
Jumlah ……………………… 890,173.90

SNI.241.e Pasang 1 m Tangga Hollow 5x5 cm


BAHAN
8.075 m1 Hollow 5x5 cm 31,200.00 251,940.00
TENAGA
0.250 OH Tukang Las Konstruksi 135,000.00 33,750.00
0.115 OH Kepala Tukang 150,000.00 17,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 121.50
Jumlah ( A + B + C ) 304,561.50
Keuntungan & Overhead 10 % 30,456.15
Jumlah ……………………… 335,017.65

SNI.241.1 1 m2 Pasang Syntetic Grass


BAHAN
1.000 m2 Syntetic Grass 131,200.00 131,200.00
TENAGA
1.000 ls Biaya pasang / Alat bantu 13,120.00 13,120.00
Jumlah ( A + B + C ) 144,320.00
Keuntungan & Overhead 10 % 14,432.00
Jumlah ……………………… 158,752.00

SNI.241.2 1 m Pasang WPC 5x5 cm


BAHAN
1.000 m1 WPC 5x5 cm 225,500.00 225,500.00
TENAGA
1.000 ls Biaya pasang / Alat bantu 22,550.00 22,550.00
Jumlah ( A + B + C ) 248,050.00
Keuntungan & Overhead 10 % 24,805.00
Jumlah ……………………… 272,855.00

SNI.241.3 1 m Pasang WPC 10x5 cm


BAHAN
1.000 m1 WPC 10x5 cm 347,800.00 347,800.00
TENAGA
1.000 ls Biaya pasang / Alat bantu 34,780.00 34,780.00
Jumlah ( A + B + C ) 382,580.00
Keuntungan & Overhead 10 % 38,258.00
Jumlah ……………………… 420,838.00

SNI.241.4 1 m Pasang WPC 15x5 cm


BAHAN
1.000 m1 WPC 15x5 cm 481,200.00 481,200.00
TENAGA
1.000 ls Biaya pasang / Alat bantu 48,120.00 48,120.00
Jumlah ( A + B + C ) 529,320.00
Keuntungan & Overhead 10 % 52,932.00
Jumlah ……………………… 582,252.00

SNI.241.5 1 m Pasang WPC 20x5 cm


BAHAN
1.000 m1 WPC 20x5 cm 573,300.00 573,300.00
TENAGA
1.000 ls Biaya pasang / Alat bantu 57,330.00 57,330.00
Jumlah ( A + B + C ) 630,630.00
Keuntungan & Overhead 10 % 63,063.00
Jumlah ……………………… 693,693.00

SNI.241.6 1 m Pasang WPC Panel W15 x H2,5 cm


BAHAN
1.000 m1 WPC Panel W15 x H2,5 cm 281,200.00 281,200.00
TENAGA
1.000 ls Biaya pasang / Alat bantu 28,120.00 28,120.00
Jumlah ( A + B + C ) 309,320.00
Keuntungan & Overhead 10 % 30,932.00
Jumlah ……………………… 340,252.00

SNI.241.7 1 m2 Pasang Floor hardener 3 Kg/m2


BAHAN
1.000 m2 Floor hardener 3 Kg/m2 43,700.00 43,700.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.020 OH Mandor 135,000.00 2,700.00
Jumlah ( A + B + C ) 116,400.00
Keuntungan & Overhead 10 % 11,640.00
Jumlah ……………………… 128,040.00

SNI.241.8 1 m2 Pasang Efoxy waterbased flooring non slip anti abrasion


BAHAN
1.000 m2 Cat Epoxy 68,700.00 68,700.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.020 OH Mandor 135,000.00 2,700.00
Jumlah ( A + B + C ) 141,400.00
Keuntungan & Overhead 10 % 14,140.00
Jumlah ……………………… 155,540.00

SNI.241.9 1 m2 Pasang Floor hardener 3 Kg/m2 + ceramic stepnoosing 100 x 200 mm


BAHAN
1.000 m2 Floor hardener 3 Kg/m2 43,700.00 43,700.00
2.500 m1 ceramic stepnoosing 100 x 200 mm 159,300.00 398,250.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.020 OH Mandor 135,000.00 2,700.00
Jumlah ( A + B + C ) 514,650.00
Keuntungan & Overhead 10 % 51,465.00
Jumlah ……………………… 566,115.00

SNI.241.10 1 m2 Pasang Floor hardener 7 Kg/m2 + grove line 2 cm


BAHAN
1.000 m2 Floor hardener 7 Kg/m2 56,200.00 56,200.00
4.000 m2 Grooe line 2 cm 25,000.00 100,000.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala Tukang 150,000.00 3,000.00
0.400 OH Pekerja 100,000.00 40,000.00
0.020 OH Mandor 135,000.00 2,700.00
Jumlah ( A + B + C ) 228,900.00
Keuntungan & Overhead 10 % 22,890.00
Jumlah ……………………… 251,790.00

SNI.241.11 Pasang GRC Rosters 300x300x150


BAHAN
1.000 m2 Roster 30 x 30 218,700.00 218,700.00
4% Biaya Perlengkapan 218,700.00 8,748.00
0.045 kg PC 1,700.00 76.50
TENAGA
1.000 ls Upah Pasang 75,000.00 75,000.00
Jumlah ( A + B + C ) 302,524.50
Keuntungan & Overhead 10 % 30,252.45
Jumlah ……………………… 332,776.95

SNI.241.12 Pasang Kisi-kisi 50x100 mm UPVC Motif Kayu


BAHAN
10.000 m1 Kisi-kisi 50x100 mm UPVC Motif Kayu 131,700.00 1,317,000.00
4% Biaya Perlengkapan 131,700.00 5,268.00
TENAGA
1.000 ls Upah Pasang 55,000.00 55,000.00
Jumlah ( A + B + C ) 1,377,268.00
Keuntungan & Overhead 10 % 137,726.80
Jumlah ……………………… 1,514,994.80

SNI.242 Mengerjakan 100 kg pekerjaan perakitan


BAHAN
1.000 Ltr Solar 6,500.00 6,500.00
0.100 Ltr Minyak pelumas 47,000.00 4,700.00
0.800 jam Sewa Alat 410,000.00 328,000.00
TENAGA
0.100 OH Tukang Besi konstruksi 135,000.00 13,500.00
0.001 OH Kepala Tukang 150,000.00 150.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 363,525.00
Keuntungan & Overhead 10 % 36,352.50
Jumlah ……………………… 399,877.50

SNI.243 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
BAHAN
15.000 Kg Besi siku 30,000.00 450,000.00
32.800 Kg Besi plat baja 2 mm 22,000.00 721,600.00
0.050 Kg kawat las 160,000.00 8,000.00
TENAGA
1.050 OH Tukang Las Konstruksi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.052 OH Mandor 135,000.00 7,020.00
Jumlah ( A + B + C ) 1,449,120.00
Keuntungan & Overhead 10 % 144,912.00
Jumlah ……………………… 1,594,032.00

SNI.244 Mengerjakan 10 cm pengelasan dengan las listrik


BAHAN
0.300 Ltr Solar 6,500.00 1,950.00
0.040 Ltr Minyak pelumas 47,000.00 1,880.00
0.400 kg Kawat las listrik 160,000.00 64,000.00
0.170 jam Sewa Alat 410,000.00 69,700.00
TENAGA
0.020 OH Tukang Besi konstruksi 135,000.00 2,700.00
0.002 OH Kepala Tukang 150,000.00 300.00
0.040 OH Pekerja 100,000.00 4,000.00
0.002 OH Mandor 135,000.00 270.00
Jumlah ( A + B + C ) 144,800.00
Keuntungan & Overhead 10 % 14,480.00
Jumlah ……………………… 159,280.00

SNI.245 Memasang 1 m2 rolling door alluminium


BAHAN
1.000 M2 Rolling door alluminium 600,000.00 600,000.00
TENAGA
1.000 OH Tukang Alumunium 135,000.00 135,000.00
0.100 OH Kepala Tukang 150,000.00 15,000.00
1.000 OH Pekerja 100,000.00 100,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 856,750.00
Keuntungan & Overhead 10 % 85,675.00
Jumlah ……………………… 942,425.00

SNI.246 Memasang 1 m2 sunscreen alluminium


BAHAN
1.000 M2 Sunscreen alluminium 500,000.00 500,000.00
TENAGA
0.800 OH Tukang Alumunium 135,000.00 108,000.00
0.080 OH Kepala Tukang 150,000.00 12,000.00
0.080 OH Pekerja 100,000.00 8,000.00
0.004 OH Mandor 135,000.00 540.00
Jumlah ( A + B + C ) 628,540.00
Keuntungan & Overhead 10 % 62,854.00
Jumlah ……………………… 691,394.00

SNI.247 Memasang 1 m kusen pintu alluminium Natural


BAHAN
1.100 m Kusen Alumunium Natural 93,000.00 102,300.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.043 OH Tukang Alumunium 135,000.00 5,805.00
0.004 OH Kepala Tukang 150,000.00 645.00
0.043 OH Pekerja 100,000.00 4,300.00
0.002 OH Mandor 135,000.00 290.25
Jumlah ( A + B + C ) 158,840.25
Keuntungan & Overhead 10 % 15,884.03
Jumlah ……………………… 174,724.28

SNI.247.a Memasang 1 m2 Dinding kusen alluminium Natural + Kaca polos 8 mm


BAHAN
4.400 m Kusen Alumunium Natural 93,000.00 409,200.00
1.100 m2 Kaca Polos 8 mm 185,000.00 203,500.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 680,023.75
Keuntungan & Overhead 10 % 68,002.38
Jumlah ……………………… 748,026.13

SNI.247.b Memasang 1 m2 Dinding kusen alluminium Natural + Kaca temreat 8 mm, polos
BAHAN
4.400 m Kusen Alumunium Natural 93,000.00 409,200.00
1.100 m2 Kaca Tempreat 8 mm, Polos 1,000,000.00 1,100,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,576,523.75
Keuntungan & Overhead 10 % 157,652.38
Jumlah ……………………… 1,734,176.13

SNI.247.c Memasang 1 m2 Dinding kusen alluminium Natural + Kaca temreat 8 mm, warna
BAHAN
4.400 m Kusen Alumunium Natural 93,000.00 409,200.00
1.100 m2 Kaca Tempreat 8 mm, Warna 1,100,000.00 1,210,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,686,523.75
Keuntungan & Overhead 10 % 168,652.38
Jumlah ……………………… 1,855,176.13

SNI.248 Memasang 1 m kusen pintu alluminium Warna


BAHAN
1.100 m Kusen Alumunium Warna 105,000.00 115,500.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.043 OH Tukang Alumunium 135,000.00 5,805.00
0.004 OH Kepala Tukang 150,000.00 645.00
0.043 OH Pekerja 100,000.00 4,300.00
0.002 OH Mandor 135,000.00 290.25
Jumlah ( A + B + C ) 172,040.25
Keuntungan & Overhead 10 % 17,204.03
Jumlah ……………………… 189,244.28

SNI.248.a Memasang 1 m2 Dinding kusen alluminium Warna + Kaca polos 8 mm


BAHAN
4.400 m Kusen Alumunium Warna 105,000.00 462,000.00
1.100 m2 Kaca Polos 8 mm 185,000.00 203,500.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.043 OH Tukang Alumunium 135,000.00 5,805.00
0.004 OH Kepala Tukang 150,000.00 645.00
0.043 OH Pekerja 100,000.00 4,300.00
0.002 OH Mandor 135,000.00 290.25
Jumlah ( A + B + C ) 722,040.25
Keuntungan & Overhead 10 % 72,204.03
Jumlah ……………………… 794,244.28

SNI.248.b Memasang 1 m2 Dinding kusen alluminium Warna + Kaca temreat 8 mm, polos
BAHAN
4.400 m Kusen Alumunium Warna 105,000.00 462,000.00
1.100 m2 Kaca Tempreat 8 mm, Polos 1,000,000.00 1,100,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.043 OH Tukang Alumunium 135,000.00 5,805.00
0.004 OH Kepala Tukang 150,000.00 645.00
0.043 OH Pekerja 100,000.00 4,300.00
0.002 OH Mandor 135,000.00 290.25
Jumlah ( A + B + C ) 1,618,540.25
Keuntungan & Overhead 10 % 161,854.03
Jumlah ……………………… 1,780,394.28

SNI.248.c Memasang 1 m2 Dinding kusen alluminium Warna + Kaca temreat 8 mm, warna
BAHAN
4.400 m Kusen Alumunium Warna 105,000.00 462,000.00
1.100 m2 Kaca Tempreat 8 mm, Warna 1,100,000.00 1,210,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,739,323.75
Keuntungan & Overhead 10 % 173,932.38
Jumlah ……………………… 1,913,256.13

SNI.248.12 Memasang 1 m2 Besi Hollow + Kaca temreat 12 mm, warna


BAHAN
4.400 m Besi Hollow 25,000.00 110,000.00
1.100 m2 Kaca Tempreat 12 mm, Warna 1,800,000.00 1,980,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 2,157,323.75
Keuntungan & Overhead 10 % 215,732.38
Jumlah ……………………… 2,373,056.13

SNI.248.T8p Memasang 1 m2 Kaca temreat 8 mm, polos


BAHAN
1.100 m2 Kaca Tempreat 8 mm, Polos 1,000,000.00 1,100,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,123,323.75
Keuntungan & Overhead 10 % 112,332.38
Jumlah ……………………… 1,235,656.13

SNI.248.T8w Memasang 1 m2 Kaca temreat 8 mm, Warna


BAHAN
1.100 m2 Kaca Tempreat 8 mm, Warna 1,100,000.00 1,210,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,233,323.75
Keuntungan & Overhead 10 % 123,332.38
Jumlah ……………………… 1,356,656.13

SNI.248.5p Memasang 1 m2 Kaca mati 5 mm, polos


BAHAN
1.100 m2 Kaca 5 mm, Polos 141,000.00 155,100.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 178,423.75
Keuntungan & Overhead 10 % 17,842.38
Jumlah ……………………… 196,266.13

SNI.248.8p Memasang 1 m2 Kaca mati 8 mm, polos


BAHAN
1.100 m2 Kaca 8 mm, Polos 185,000.00 203,500.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 226,823.75
Keuntungan & Overhead 10 % 22,682.38
Jumlah ……………………… 249,506.13

SNI.248.R Memasang 1 m2 Kaca mati Riben 5 mm


BAHAN
1.100 m2 Kaca Riben 5 mm 164,000.00 180,400.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 203,723.75
Keuntungan & Overhead 10 % 20,372.38
Jumlah ……………………… 224,096.13

SNI.248.B/E Memasang 1 m2 Kaca mati Buram/Es 5 mm


BAHAN
1.100 m2 Kaca Buram/Es 5 mm 215,000.00 236,500.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 259,823.75
Keuntungan & Overhead 10 % 25,982.38
Jumlah ……………………… 285,806.13

SNI.249 Memasang 1 m2 pintu alluminium strip


BAHAN
4.400 m Kusen Alumunium Natural 93,000.00 409,200.00
8.750 m' alluminium strip 57,000.00 498,750.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 929,773.75
Keuntungan & Overhead 10 % 92,977.38
Jumlah ……………………… 1,022,751.13

SNI.249.a Pasang 1 Buah Cermin ex. TOTO TS 119 AS5


BAHAN
1.100 m2 Kaca Cermin 5 mm 169,000.00 185,900.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 210,001.25
Keuntungan & Overhead 10 % 21,000.13
Jumlah ……………………… 231,001.38

SNI.249.b Pasang 1 Buah Kaca Laminasi tebal 12 mm


BAHAN
1.100 m2 Laminasi tebal 12 mm 1,500,000.00 1,650,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 1,674,101.25
Keuntungan & Overhead 10 % 167,410.13
Jumlah ……………………… 1,841,511.38

SNI.249.c Pasang 1 m2 kaca green glass 12 mm


BAHAN
1.100 m2 Kaca green glass 12 mm 1,800,000.00 1,980,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 2,005,080.00
Keuntungan & Overhead 10 % 200,508.00
Jumlah ……………………… 2,205,588.00

SNI.249.d Pasang 1 m2 kaca green glass tebal 8 mm


BAHAN
1.100 m2 Kaca temperet 8 mm 1,100,000.00 1,210,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 1,235,080.00
Keuntungan & Overhead 10 % 123,508.00
Jumlah ……………………… 1,358,588.00

SNI.249.e Pasang 1 bh Pintu Engineering door / WPC


TENAGA
1.500 OH Tukang 135,000.00 202,500.00
0.075 OH Kepala Tukang 150,000.00 11,250.00
0.750 OH Pekerja 100,000.00 75,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 289,087.50
Keuntungan & Overhead 10 % 28,908.75
Jumlah ……………………… 317,996.25

SNI.249.f Pasang 1 bh Pintu Green glass


TENAGA
2.500 OH Tukang 135,000.00 337,500.00
0.075 OH Kepala Tukang 150,000.00 11,250.00
0.075 OH Pekerja 100,000.00 7,500.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 356,587.50
Keuntungan & Overhead 10 % 35,658.75
Jumlah ……………………… 392,246.25

SNI.249.g Pasang 1 bh Pintu siku alumunium powder coating


BAHAN
1.000 m1 Siku alumunium 81,200.00 81,200.00
TENAGA
0.500 OH Tukang 135,000.00 67,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 70,675.00
Keuntungan & Overhead 10 % 7,067.50
Jumlah ……………………… 77,742.50

SNI.249.1 Pemasangan 1 m1 Kusen plat baja uk. 15x9x0,2 cm


BAHAN
1.000 m1 plat baja 15x9x9,2 cm 312,500.00 312,500.00
15.000 cm1 pengelasan 1,200.00 18,000.00
TENAGA
0.800 OH Tukang 135,000.00 108,000.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 461,330.00
Keuntungan & Overhead 10 % 46,133.00
Jumlah ……………………… 507,463.00

SNI.249.2 Pemasangan 1 m1 Kusen Steel Frame Hollow Galvanis 150x40x3 mm


BAHAN
1.050 m1 Steel Frame Hollow Galvanis 150x40x3 m 31,200.00 32,760.00
1.000 ls Alat bantu 11,000.00 11,000.00
TENAGA
0.080 OH Tukang 135,000.00 10,800.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 77,390.00
Keuntungan & Overhead 10 % 7,739.00
Jumlah ……………………… 85,129.00

SNI.249.3 Pemasangan 1 m1 Kusen alumunium 4" YKK finishing powder coating


BAHAN
1.000 m1 Alumunium 4" Dark Gray ex. YKK 206,200.00 206,200.00
2.000 bh Sekrup 1,900.00 3,800.00
TENAGA
0.080 OH Tukang 135,000.00 10,800.00
0.045 OH Kepala Tukang 150,000.00 6,750.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,080.00
Jumlah ( A + B + C ) 243,630.00
Keuntungan & Overhead 10 % 24,363.00
Jumlah ……………………… 267,993.00

SNI.249.4a Mengerjakan 1 Unit pintu double UGD type P-01


BAHAN
4.920 m2 Kaca green glass 12 mm 1,500,000.00 7,380,000.00
1.000 m2 Plat stainless steel 1,562,500.00 1,562,500.00
2.000 bh Pull Handle ex. Dekson type 01 1,553,700.00 3,107,400.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
2.000 bh Engsel Floor hange Dexson 1,743,700.00 3,487,400.00
1.050 m2 Kaca green glass 8 mm 1,000,000.00 1,050,000.00
TENAGA
10.200 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 2,733,528.60
2.000 bh Pasang Daun Pintu 392,246.25 784,492.50
Jumlah ( A + B + C ) 21,011,521.10
Keuntungan & Overhead 10 % 2,101,152.11
Jumlah ……………………… 23,112,673.21

SNI.249.4b Mengerjakan 1 Unit pintu type P-02


BAHAN
2.000 bh WPC door type 02 include kaca 5 mm 2,812,500.00 5,625,000.00
0.720 m2 Plate stainless steel 1,562,500.00 1,125,000.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
2.000 bh Lever Handle ex. Dekson 750,000.00 1,500,000.00
6.000 bh Engsel kupu ex. Dekson 102,500.00 615,000.00
2.000 bh Door Closer ex dekson 655,000.00 1,310,000.00
TENAGA
6.200 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,661,556.60
2.000 bh Pasang Daun Pintu 317,996.25 635,992.50
Jumlah ( A + B + C ) 13,378,749.10
Keuntungan & Overhead 10 % 1,337,874.91
Jumlah ……………………… 14,716,624.01

SNI.249.4c Mengerjakan 1 Unit pintu type P-03


BAHAN
1.000 bh WPC door type 03 include kaca 5 mm 4,437,500.00 4,437,500.00
0.520 m2 Plate stainless steel 1,562,500.00 812,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
6.000 bh Engsel kupu ex. Dekson 102,500.00 615,000.00
1.000 bh Door Closer ex dekson 655,000.00 655,000.00
TENAGA
5.700 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,527,560.10
1.500 bh Pasang Daun Pintu 317,996.25 476,994.38
Jumlah ( A + B + C ) 10,180,754.48
Keuntungan & Overhead 10 % 1,018,075.45
Jumlah ……………………… 11,198,829.92

SNI.249.4d Mengerjakan 1 Unit pintu type P-04A


BAHAN
1.000 bh WPC door type 02 include kaca 5 mm 2,812,500.00 2,812,500.00
0.360 m2 Plate stainless steel 1,562,500.00 562,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
3.000 bh Engsel kupu ex. Dekson 102,500.00 307,500.00
1.000 bh Door Closer ex dekson 655,000.00 655,000.00
TENAGA
5.300 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,420,362.90
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 7,732,059.15
Keuntungan & Overhead 10 % 773,205.92
Jumlah ……………………… 8,505,265.07

SNI.249.4e Mengerjakan 1 Unit pintu type P-04B


BAHAN
1.000 bh WPC door type 04b include kaca 5 mm 2,312,500.00 2,312,500.00
0.360 m2 Plate stainless steel 1,562,500.00 562,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
3.000 bh Engsel kupu ex. Dekson 102,500.00 307,500.00
1.000 bh Door Closer ex dekson 655,000.00 655,000.00
TENAGA
5.300 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,420,362.90
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 7,232,059.15
Keuntungan & Overhead 10 % 723,205.92
Jumlah ……………………… 7,955,265.07

SNI.249.4f Mengerjakan 1 Unit pintu type P-04C


BAHAN
1.000 bh WPC door type 04c include kaca 5 mm 1,937,500.00 1,937,500.00
0.280 m2 Plate stainless steel 1,562,500.00 437,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
3.000 bh Engsel kupu ex. Dekson 102,500.00 307,500.00
1.000 bh Door Closer ex dekson 655,000.00 655,000.00
TENAGA
5.100 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,366,764.30
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 6,678,460.55
Keuntungan & Overhead 10 % 667,846.06
Jumlah ……………………… 7,346,306.60

SNI.249.4g Mengerjakan 1 Unit pintu type P-05


BAHAN
1.000 bh WPC door type 06 uk. 2,2 x 0,8 m 2,187,500.00 2,187,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
3.000 bh Engsel kupu ex. Dekson 102,500.00 307,500.00
TENAGA
5.200 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,393,563.60
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 5,862,759.85
Keuntungan & Overhead 10 % 586,275.99
Jumlah ……………………… 6,449,035.84

SNI.249.4h Mengerjakan 1 Unit pintu type P-06


BAHAN
1.000 bh WPC door type 06 uk. 2,2 x 0,8 m 2,187,500.00 2,187,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
3.000 bh Engsel kupu ex. Dekson 102,500.00 307,500.00
0.400 m2 Kaca es 215,000.00 86,000.00
TENAGA
7.100 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,902,750.30
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 6,457,946.55
Keuntungan & Overhead 10 % 645,794.66
Jumlah ……………………… 7,103,741.21

SNI.249.4i Mengerjakan 1 Unit pintu type P-07


BAHAN
1.000 bh WPC door type 06 uk. 2,2 x 0,8 m 2,187,500.00 2,187,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
3.000 bh Engsel kupu ex. Dekson 102,500.00 307,500.00
0.450 m2 Kaca es 215,000.00 96,750.00
TENAGA
7.100 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,902,750.30
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 6,468,696.55
Keuntungan & Overhead 10 % 646,869.66
Jumlah ……………………… 7,115,566.21

SNI.249.4j Mengerjakan 1 Unit pintu type P-08


BAHAN
1.000 bh WPC door type 08 uk. 1.1 x 0,6 m 1,625,000.00 1,625,000.00
2.000 bh Engsel kupu ex. Dekson 102,500.00 205,000.00
TENAGA
3.400 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 911,176.20
1.000 bh Pasang Daun Pintu 317,996.25 317,996.25
Jumlah ( A + B + C ) 3,059,172.45
Keuntungan & Overhead 10 % 305,917.25
Jumlah ……………………… 3,365,089.70

SNI.249.4k Mengerjakan 1 Unit pintu type P-09


BAHAN
1.000 bh WPC door type 09 uk. 2,2 x 1,5 m 3,125,000.00 3,125,000.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Slide Handle ex. Dekson 1,250,000.00 1,250,000.00
1.000 bh Engsel sliding 448,700.00 448,700.00
TENAGA
5.900 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,581,158.70
1.450 bh Pasang Daun Pintu 317,996.25 461,094.56
Jumlah ( A + B + C ) 7,772,153.26
Keuntungan & Overhead 10 % 777,215.33
Jumlah ……………………… 8,549,368.59

SNI.249.4l Mengerjakan 1 Unit pintu type P-10


BAHAN
1.000 bh WPC door type 10 uk. 2,2 x 0,9 m 2,375,000.00 2,375,000.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Slide Handle ex. Dekson 1,250,000.00 1,250,000.00
1.000 bh Engsel sliding 448,700.00 448,700.00
TENAGA
5.300 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,420,362.90
1.450 bh Pasang Daun Pintu 317,996.25 461,094.56
Jumlah ( A + B + C ) 6,861,357.46
Keuntungan & Overhead 10 % 686,135.75
Jumlah ……………………… 7,547,493.21

SNI.249.4m Mengerjakan 1 Unit pintu type P-11


BAHAN
1.000 bh Pintu plat baja tebal 5,5 mm lapis timah h 18,750,000.00 18,750,000.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
5.000 bh Flush bolt ex. Dekson 100,000.00 500,000.00
15.000 bh Engsel kupu ex. Dekson 102,500.00 1,537,500.00
TENAGA
8.700 m1 Pasang kusen pintu plat baja uk. 15x9x0,2 507,463.00 4,414,928.10
1.450 bh Pasang Daun Pintu 317,996.25 461,094.56
Jumlah ( A + B + C ) 27,319,722.66
Keuntungan & Overhead 10 % 2,731,972.27
Jumlah ……………………… 30,051,694.93

SNI.249.4n Mengerjakan 1 Unit pintu type P-12


BAHAN
1.000 bh WPC door type 11 uk. 2,2 x 1,3 m 4,250,000.00 4,250,000.00
0.520 m2 Plate stainless steel 1,562,500.00 812,500.00
1.000 bh Lock Case ex. Dekson 906,200.00 906,200.00
1.000 bh Lever Handle ex. Dekson 750,000.00 750,000.00
6.000 bh Engsel kupu ex. Dekson 102,500.00 615,000.00
1.000 bh Door Closer ex dekson 655,000.00 655,000.00
TENAGA
5.700 m1 Pasang kusen pintu alumunium 4" finishin 267,993.00 1,527,560.10
1.500 bh Pasang Daun Pintu 317,996.25 476,994.38
Jumlah ( A + B + C ) 9,993,254.48
Keuntungan & Overhead 10 % 999,325.45
Jumlah ……………………… 10,992,579.92

SNI.249.4o Mengerjakan 1 Unit pintu type P-S


BAHAN
1.000 set Kalsiboard rangka alumunium 750,000.00 750,000.00
2.000 bh Engsel kupu ex. Dekson 102,500.00 205,000.00
TENAGA
3.800 m1 Pasang kusen pintu siku alumunium finish 81,200.00 308,560.00
1.500 bh Pasang Daun Pintu 158,998.13 238,497.19
Jumlah ( A + B + C ) 1,502,057.19
Keuntungan & Overhead 10 % 150,205.72
Jumlah ……………………… 1,652,262.91

SNI.250.N5 Memasang 1 m2 Daun pintu kaca 5 mm rangka alluminium, (natural)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 5 1,000,000.00 1,000,000.00
mm, Complit (natural)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,021,823.75
Keuntungan & Overhead 10 % 102,182.38
Jumlah ……………………… 1,124,006.13

SNI.250.N8 Memasang 1 m2 Daun pintu kaca 8 mm rangka alluminium, (natural)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 8 1,100,000.00 1,100,000.00
mm, Complit (natural)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,121,823.75
Keuntungan & Overhead 10 % 112,182.38
Jumlah ……………………… 1,234,006.13

SNI.250.W5 Memasang 1 m2 Daun pintu kaca 5 mm rangka alluminium, (warna)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 5 1,050,000.00 1,050,000.00
mm, Complit (warna)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,071,823.75
Keuntungan & Overhead 10 % 107,182.38
Jumlah ……………………… 1,179,006.13

SNI.250.W8 Memasang 1 m2 Daun pintu kaca 8 mm rangka alluminium, (warna)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 1,150,000.00 1,150,000.00
8 mm, Complit (warna)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,171,823.75
Keuntungan & Overhead 10 % 117,182.38
Jumlah ……………………… 1,289,006.13

SNI.251.N Memasang 1 m2 jendela kaca 5 mm rangka alluminium, (natural)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 5 1,000,000.00 1,000,000.00
mm, Complit (natural)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,021,823.75
Keuntungan & Overhead 10 % 102,182.38
Jumlah ……………………… 1,124,006.13

SNI.251.N8 Memasang 1 m2 jendela kaca 8 mm rangka alluminium, (natural)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 8 1,100,000.00 1,100,000.00
mm, Complit (natural)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,121,823.75
Keuntungan & Overhead 10 % 112,182.38
Jumlah ……………………… 1,234,006.13

SNI.251.W Memasang 1 m2 jendela kaca 5 mm rangka alluminium, (warna)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 5 1,050,000.00 1,050,000.00
mm, Complit (warna)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,071,823.75
Keuntungan & Overhead 10 % 107,182.38
Jumlah ……………………… 1,179,006.13

SNI.251.W8 Memasang 1 m2 jendela kaca 8 mm rangka alluminium, (warna)


BAHAN
1.000 M2 Daun pintu/jendela alumunium + kaca 8 1,150,000.00 1,150,000.00
mm, Complit (warna)
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,171,823.75
Keuntungan & Overhead 10 % 117,182.38
Jumlah ……………………… 1,289,006.13

SNI.251.75.a 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 75.100


BAHAN
4.260 M1 Profil C 75.100 19,000.00 80,940.00
4.930 M1 Reng U 0.45 6,000.00 29,580.00
14.000 Bh Baut Truss 500.00 7,000.00
11.000 Bh Baut Reng 400.00 4,400.00
TENAGA
0.400 OH Tukang Alumunium 135,000.00 54,000.00
0.040 OH Kepala Tukang 150,000.00 6,000.00
0.140 OH Pekerja 100,000.00 14,000.00
0.070 OH Mandor 135,000.00 9,450.00
Jumlah ( A + B + C ) 205,370.00
Keuntungan & Overhead 10 % 20,537.00
Jumlah ……………………… 225,907.00

SNI.251.75.b 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 75.75


BAHAN
4.260 M1 Profil C 75.75 14,000.00 59,640.00
4.930 M1 Reng U 0.45 6,000.00 29,580.00
14.000 Bh Baut Truss 500.00 7,000.00
11.000 Bh Baut Reng 400.00 4,400.00
TENAGA
0.400 OH Tukang Alumunium 135,000.00 54,000.00
0.040 OH Kepala Tukang 150,000.00 6,000.00
0.140 OH Pekerja 100,000.00 14,000.00
0.070 OH Mandor 135,000.00 9,450.00
Jumlah ( A + B + C ) 184,070.00
Keuntungan & Overhead 10 % 18,407.00
Jumlah ……………………… 202,477.00
SNI.251.75.c 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) Usuk C 75
BAHAN
4.260 M1 Profil C 75.75 14,000.00 59,640.00
14.000 Bh Baut Truss 500.00 7,000.00
TENAGA
0.280 OH Tukang Alumunium 135,000.00 37,800.00
0.028 OH Kepala Tukang 150,000.00 4,200.00
0.098 OH Pekerja 100,000.00 9,800.00
0.049 OH Mandor 135,000.00 6,615.00
Jumlah ( A + B + C ) 125,055.00
Keuntungan & Overhead 10 % 12,505.50
Jumlah ……………………… 137,560.50

SNI.251.75.d 1 M2 Rangka Reng Aluzing Aluminium (Baja ringan) Reng U 0.45


BAHAN
4.930 M1 Reng U 0.45 6,000.00 29,580.00
11.000 Bh Baut Reng 400.00 4,400.00
TENAGA
0.120 OH Tukang Alumunium 135,000.00 16,200.00
0.012 OH Kepala Tukang 150,000.00 1,800.00
0.042 OH Pekerja 100,000.00 4,200.00
0.021 OH Mandor 135,000.00 2,835.00
Jumlah ( A + B + C ) 59,015.00
Keuntungan & Overhead 10 % 5,901.50
Jumlah ……………………… 64,916.50

SNI.251.80.a 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 80.100


BAHAN
4.260 M1 Profil C 80.100 22,000.00 93,720.00
4.930 M1 Reng U 0.45 6,000.00 29,580.00
14.000 Bh Baut Truss 500.00 7,000.00
11.000 Bh Baut Reng 400.00 4,400.00
TENAGA
0.400 OH Tukang Alumunium 135,000.00 54,000.00
0.040 OH Kepala Tukang 150,000.00 6,000.00
0.140 OH Pekerja 100,000.00 14,000.00
0.070 OH Mandor 135,000.00 9,450.00
Jumlah ( A + B + C ) 218,150.00
Keuntungan & Overhead 10 % 21,815.00
Jumlah ……………………… 239,965.00

SNI.251.80.b 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 80.75


BAHAN
4.260 M1 Profil C 80.75 17,000.00 72,420.00
4.930 M1 Reng U 0.45 6,000.00 29,580.00
14.000 Bh Baut Truss 500.00 7,000.00
11.000 Bh Baut Reng 400.00 4,400.00
TENAGA
0.400 OH Tukang Alumunium 135,000.00 54,000.00
0.040 OH Kepala Tukang 150,000.00 6,000.00
0.140 OH Pekerja 100,000.00 14,000.00
0.070 OH Mandor 135,000.00 9,450.00
Jumlah ( A + B + C ) 196,850.00
Keuntungan & Overhead 10 % 19,685.00
Jumlah ……………………… 216,535.00

SNI.251.ACP.a 1 M2 Rangka dan Penutup Alluminium Composit Panel (ACP), Interior


BAHAN
6.000 M' Besi Holow 40x40 zincromate 25,000.00 150,000.00
1.100 M2 Alluminium Composit Panel (ACP) 0,30 mm, 550,000.00 605,000.00
0.200 kg Paku Sekrup 35,000.00 7,000.00
0.250 tube Sealant 25,000.00 6,250.00
TENAGA
0.150 OH Tukang 135,000.00 20,250.00
0.015 OH Kepala tukang 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 793,262.50
Keuntungan & Overhead 10 % 79,326.25
Jumlah ……………………… 872,588.75

SNI.251.ACP.b 1 M2 Rangka dan Penutup Alluminium Composit Panel (ACP), Exterior


BAHAN
6.000 M' Besi Holow 40x40 zincromate 25,000.00 150,000.00
1.100 M2 Alluminium Composit Panel (ACP) 0,30 mm, 770,000.00 847,000.00
0.200 kg Paku Sekrup 35,000.00 7,000.00
0.250 tube Sealant 25,000.00 6,250.00
TENAGA
0.150 OH Tukang 135,000.00 20,250.00
0.015 OH Kepala tukang 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 1,035,262.50
Keuntungan & Overhead 10 % 103,526.25
Jumlah ……………………… 1,138,788.75

SNI.251.ACP.c 1 M2 Rangka dan Penutup Wood Panel Composit (WPC), Exterior


BAHAN
6.000 M' Besi Holow 40x40 zincromate 12,000.00 72,000.00
1.100 M2 Wood Panel Composit 442,000.00 486,200.00
0.200 kg Paku Sekrup 35,000.00 7,000.00
0.250 tube Sealant 25,000.00 6,250.00
TENAGA
0.150 OH Tukang 135,000.00 20,250.00
0.015 OH Kepala tukang 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 596,462.50
Keuntungan & Overhead 10 % 59,646.25
Jumlah ……………………… 656,108.75

SNI.251.DG 1 M2 Pekerjaan Dinding Double Gypsum 9 mm + Rangka profil C


BAHAN
4.400 m Profil C 14,000.00 61,600.00
0.050 Kg Paku Sekrup 35,000.00 1,750.00
0.750 Lbr Gypsum board 1200 x 2400 x 9 mm 95,000.00 71,250.00
TENAGA
0.300 OH Tukang 135,000.00 40,500.00
0.030 OH Kepala Tukang 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 200,950.00
Keuntungan & Overhead 10 % 20,095.00
Jumlah ……………………… 221,045.00

SNI.251.DC 1 M2 Pekerjaan Dinding Double Calsiboart 6 mm + Rangka profil C


BAHAN
4.400 m Profil C 14,000.00 61,600.00
0.050 Kg Paku Sekrup 35,000.00 1,750.00
0.750 Lbr Calsiboard 1200 x 240 x 6 mm 221,000.00 165,750.00
TENAGA
0.300 OH Tukang 135,000.00 40,500.00
0.030 OH Kepala Tukang 150,000.00 4,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 295,450.00
Keuntungan & Overhead 10 % 29,545.00
Jumlah ……………………… 324,995.00

PEKERJAAN PENGECATAN/FINISING
SNI.252 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Eksterior)
BAHAN
0.260 Kg Cat Tembok 125,000.00 32,500.00
0.100 Kg Plamir Tembok 49,000.00 4,900.00
0.100 Kg Cat Dasar 125,000.00 12,500.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 61,687.50
Keuntungan & Overhead 10 % 6,168.75
Jumlah ……………………… 67,856.25

SNI.252.a 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Interior)


BAHAN
0.260 Kg Cat Tembok 60,000.00 15,600.00
0.100 Kg Plamir Tembok 49,000.00 4,900.00
0.100 Kg Cat Dasar 60,000.00 6,000.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 38,287.50
Keuntungan & Overhead 10 % 3,828.75
Jumlah ……………………… 42,116.25

SNI.252.b 1 M2 Pekerjaan Cat Plafond Baru 1 x Dasar, 2 x Cat


BAHAN
0.260 Kg Cat Plafond 60,000.00 15,600.00
0.100 Kg Plamir Plafond 49,000.00 4,900.00
0.100 Kg Cat Dasar 60,000.00 6,000.00
TENAGA
0.200 OH Tukang Cat 135,000.00 27,000.00
0.020 OH Kepala Tukang Cat 150,000.00 3,000.00
0.013 OH Pekerja 100,000.00 1,300.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 59,150.00
Keuntungan & Overhead 10 % 5,915.00
Jumlah ……………………… 65,065.00

SNI.252.c 1 M2 Pekerjaan Cat Dak Beton, (Water Proofing/ Sunscreen)


BAHAN
0.260 Kg Cat Dak, (Water Proofing) 65,000.00 16,900.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 28,687.50
Keuntungan & Overhead 10 % 2,868.75
Jumlah ……………………… 31,556.25
SNI.252.d 1 M2 Pekerjaan Cat Dak Beton, (Water Proofing/ Sunscreen)
BAHAN
1.050 m2 Fiber Bakar 106,200.00 111,510.00
1.000 bh Kuas 28,000.00 28,000.00
1.050 m2 Waterproofing 65,000.00 68,250.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 219,547.50
Keuntungan & Overhead 10 % 21,954.75
Jumlah ……………………… 241,502.25

SNI.252.e 1 m² Pengecatan Tembok Baru anti bakteri ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup anti bakteri)
BAHAN
0.100 Kg Plamir 49,000.00 4,900.00
0.100 Kg Cat Dasar 125,000.00 12,500.00
0.100 Lbr Ampelas 8,700.00 870.00
0.360 Kg Cat Tembok berbahan anti bakteri 125,000.00 45,000.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 75,057.50
Keuntungan & Overhead 10 % 7,505.75
Jumlah ……………………… 82,563.25

SNI.252.f 1 m² Memasang pelapis tembok dengan plat timbal hitam tebal 3 mm rangka hollow
BAHAN
1.100 m2 Plat timbah hitam 3 m 693,700.00 763,070.00
1.100 m2 Triplek rebal 6 mm 105,000.00 115,500.00
6.400 m1 Hollow 40 x 40 tebal 1 mm 25,000.00 160,000.00
4.400 m1 Hollow 20 x 40 tebal 1 mm 12,000.00 52,800.00
10.000 cm Pengelasan 1,200.00 12,000.00
TENAGA
0.063 OH Tukang Besi 135,000.00 8,505.00
0.006 OH Kepala Tukang Besi 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 1,115,157.50
Keuntungan & Overhead 10 % 111,515.75
Jumlah ……………………… 1,226,673.25

SNI.252.g 1 m² Measang pelapis tembak dengan HPL


BAHAN
1.200 m3 HPL 68,700.00 82,440.00
0.200 Kg Kapur Sirih 25,000.00 5,000.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 99,227.50
Keuntungan & Overhead 10 % 9,922.75
Jumlah ……………………… 109,150.25

SNI.252.h 1 m² Pemasangan Wall Paper


BAHAN
1.200 m3 Wall Paper 156,200.00 150,000.00
0.200 Kg Perekat 25,000.00 4,000.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 165,787.50
Keuntungan & Overhead 10 % 16,578.75
Jumlah ……………………… 182,366.25

SNI.252.i 1 m2 Pengecatan Cat Tekstur Fin. Kamprot Halus


BAHAN
0.260 kg Cat tembok dulux Watersilt Pro 118,700.00 150,000.00
4.320 kg PC 1,700.00 150,000.00
0.006 m3 Pasir pasang 220,000.00 150,000.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 461,787.50
Keuntungan & Overhead 10 % 46,178.75
Jumlah ……………………… 507,966.25

SNI.253 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Berjamur ) - Lama, Eksterior


0.180 Kg Cat Tembok 125,000.00 22,500.00
0.120 Kg Cat Dasar 125,000.00 15,000.00
0.042 OH Tukang Cat 135,000.00 5,670.00
0.004 OH Kepala Tukang Cat 150,000.00 630.00
0.028 OH Pekerja 100,000.00 2,800.00
0.003 OH Mandor 135,000.00 337.50
46,937.50
1 M2 Pekerjaan Mengikis/ Mengerok Permukaan Cat Tembok Lama
0.050 Kg Soda api 66,000.00 3,300.00
0.150 OH Pekerja 100,000.00 15,000.00
0.003 OH Mandor 135,000.00 337.50
18,637.50
1 M2 Pekerjaan Mencuci Bidang Permukaan Tembok yang pernah di cat
0.050 Kg Sabun 20,000.00 1,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.003 OH Mandor 135,000.00 337.50
16,337.50

Jumlah 1 M2 Cat Tembok 1 x Cat ( I + II + III ) 81,912.50


Jumlah ( A + B + C ) 81,912.50
Keuntungan & Overhead 10 % 8,191.25
Jumlah ……………………… 90,103.75

SNI.253.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Berjamur ) - Lama, Interior


0.180 Kg Cat Tembok 60,000.00 10,800.00
0.120 Kg Cat Dasar 60,000.00 7,200.00
0.042 OH Tukang Cat 135,000.00 5,670.00
0.004 OH Kepala Tukang Cat 150,000.00 630.00
0.028 OH Pekerja 100,000.00 2,800.00
0.003 OH Mandor 135,000.00 337.50
27,437.50
1 M2 Pekerjaan Mengikis/ Mengerok Permukaan Cat Tembok Lama
0.050 Kg Soda api 66,000.00 3,300.00
0.150 OH Pekerja 100,000.00 15,000.00
0.003 OH Mandor 135,000.00 337.50
18,637.50
1 M2 Pekerjaan Mencuci Bidang Permukaan Tembok yang pernah di cat
0.050 Kg Sabun 20,000.00 1,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.003 OH Mandor 135,000.00 337.50
16,337.50

Jumlah 1 M2 Cat Tembok 1 x Cat ( I + II + III ) 62,412.50


Jumlah ( A + B + C ) 62,412.50
Keuntungan & Overhead 10 % 6,241.25
Jumlah ……………………… 68,653.75

SNI.254 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Eksterior
BAHAN
0.200 Kg Cat Tembok 125,000.00 25,000.00
0.120 Kg Cat Dasar 125,000.00 15,000.00
TENAGA
0.042 OH Tukang Cat 135,000.00 5,670.00
0.004 OH Kepala Tukang Cat 150,000.00 630.00
0.028 OH Pekerja 100,000.00 2,800.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 49,437.50
Keuntungan & Overhead 10 % 4,943.75
Jumlah ……………………… 54,381.25

SNI.254.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Interior
BAHAN
0.200 Kg Cat Tembok 60,000.00 12,000.00
0.120 Kg Cat Dasar 60,000.00 7,200.00
TENAGA
0.042 OH Tukang Cat 135,000.00 5,670.00
0.004 OH Kepala Tukang Cat 150,000.00 630.00
0.028 OH Pekerja 100,000.00 2,800.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 28,637.50
Keuntungan & Overhead 10 % 2,863.75
Jumlah ……………………… 31,501.25

SNI.254.b 1 M2 Pekerjaan Cat Plafond Lama 1 x Dasar, 2 x Cat


BAHAN
0.200 Kg Cat Tembok 60,000.00 12,000.00
0.120 Kg Cat Dasar 60,000.00 7,200.00
TENAGA
0.200 OH Tukang Cat 135,000.00 27,000.00
0.020 OH Kepala Tukang Cat 150,000.00 3,000.00
0.013 OH Pekerja 100,000.00 1,300.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 51,850.00
Keuntungan & Overhead 10 % 5,185.00
Jumlah ……………………… 57,035.00

SNI.255 1 M2 Pekerjaan cat Genteng


BAHAN
0.180 Kg Cat Genteng 42,000.00 7,560.00
0.120 Kg Cat Dasar 60,000.00 7,200.00
TENAGA
0.200 OH Tukang Cat 135,000.00 27,000.00
0.020 OH Kepala Tukang Cat 150,000.00 3,000.00
0.167 OH Pekerja 100,000.00 16,700.00
0.008 OH Mandor 135,000.00 1,134.00
Jumlah ( A + B + C ) 62,594.00
Keuntungan & Overhead 10 % 6,259.40
Jumlah ……………………… 68,853.40
SNI.256 1 M2 Pekerjaan Cat Kayu 1 x Meni, 2 x Cat
BAHAN
0.200 Kg Cat Meni 34,000.00 6,800.00
0.260 Kg Cat Kayu 85,000.00 22,100.00
0.170 Kg Cat Dasar 71,000.00 12,070.00
0.150 Kg Plamir Kayu 28,000.00 4,200.00
0.020 Kg Minyak Cat 20,000.00 400.00
TENAGA
0.009 OH Tukang Cat 135,000.00 1,215.00
0.006 OH Kepala Tukang Cat 150,000.00 900.00
0.070 OH Pekerja 100,000.00 7,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 55,022.50
Keuntungan & Overhead 10 % 5,502.25
Jumlah ……………………… 60,524.75

SNI.257 1 M2 Pekerjaan Cat Kayu, 1 x Cat


BAHAN
0.170 Kg Cat Kayu 85,000.00 14,450.00
0.150 Kg Plamir 28,000.00 4,200.00
0.170 Kg Cat Dasar 71,000.00 12,070.00
TENAGA
0.075 OH Tukang Cat 135,000.00 10,125.00
0.008 OH Kepala Tukang Cat 150,000.00 1,125.00
0.070 OH Pekerja 100,000.00 7,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 49,307.50
Keuntungan & Overhead 10 % 4,930.75
Jumlah ……………………… 54,238.25

SNI.258 1 M2 Pekerjaan Cat paving Blok


BAHAN
0.260 Kg Cat Penutup 2 x 42,000.00 10,920.00
TENAGA
0.100 OH Tukang Cat 135,000.00 13,500.00
0.010 OH Kepala Tukang Cat 150,000.00 1,500.00
0.087 OH Pekerja 100,000.00 8,700.00
0.003 OH Mandor 135,000.00 432.00
Jumlah ( A + B + C ) 35,052.00
Keuntungan & Overhead 10 % 3,505.20
Jumlah ……………………… 38,557.20

SNI.259 1 M2 Mendempul dan Menggosok Kayu


BAHAN
0.080 Kg Dempul Jadi 35,000.00 2,800.00
0.020 Kg Minyak Cat 20,000.00 400.00
0.010 Kg Batu Apung 249,000.00 2,490.00
TENAGA
0.040 OH Tukang Cat 135,000.00 5,400.00
0.004 OH Kepala Tukang Cat 150,000.00 600.00
0.040 OH Pekerja 100,000.00 4,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 16,027.50
Keuntungan & Overhead 10 % 1,602.75
Jumlah ……………………… 17,630.25

SNI.260 1 M2 Pekerjaan Politur 2 Kali


BAHAN
0.150 Ltr Politur 35,000.00 5,250.00
0.372 Ltr Politur Jadi 36,000.00 13,392.00
2.000 Lbr Amplas 8,700.00 17,400.00
TENAGA
0.060 OH Tukang Cat 135,000.00 8,100.00
0.016 OH Kepala Tukang Cat 150,000.00 2,400.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 46,879.50
Keuntungan & Overhead 10 % 4,687.95
Jumlah ……………………… 51,567.45

SNI.261 1 M2 Mengecat Besi 1 x Meni, 2 x Cat


BAHAN
0.100 Kg Cat Meni Besi 34,000.00 3,400.00
0.160 Kg Cat Besi 70,000.00 11,200.00
0.270 Ltr Minyak Cat 20,000.00 5,400.00
1.000 Lbr Amplas 20,000.00 20,000.00
0.050 Bh Kuas 20,000.00 1,000.00
TENAGA
0.100 OH Tukang Cat 135,000.00 13,500.00
0.010 OH Kepala Tukang Cat 150,000.00 1,500.00
0.020 OH Pekerja 100,000.00 2,000.00
0.010 OH Mandor 135,000.00 1,350.00
Jumlah ( A + B + C ) 59,350.00
Keuntungan & Overhead 10 % 5,935.00
Jumlah ……………………… 65,285.00

SNI.262 10 M2 Mengecat Atap Seng Gelombang


BAHAN
1.420 Kg Cat Meni Besi 34,000.00 48,280.00
1.000 Kg Cat Besi 70,000.00 70,000.00
0.250 Ltr Minyak Cat 20,000.00 5,000.00
TENAGA
1.200 OH Tukang Cat 135,000.00 162,000.00
0.120 OH Kepala Tukang Cat 150,000.00 18,000.00
1.200 OH Pekerja 100,000.00 120,000.00
0.060 OH Mandor 135,000.00 8,100.00
Jumlah ( A + B + C ) 431,380.00
Keuntungan & Overhead 10 % 43,138.00
Jumlah ……………………… 474,518.00
M2 Mengecat Besi 1 x Meni 47,451.80

SNI.263 1 M2 Pekerjaan Pelaburan Bidang Kayu dengan Teak Oil


BAHAN
0.360 Ltr Teak Oil 18,000.00 6,480.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.040 OH Pekerja 100,000.00 4,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 20,267.50
Keuntungan & Overhead 10 % 2,026.75
Jumlah ……………………… 22,294.25

SNI.264 1 M2 Mengeter Kayu 2x


BAHAN
0.350 Ltr Teer Arang 36,000.00 12,600.00
TENAGA
0.060 OH Tukang Cat 135,000.00 8,100.00
0.016 OH Kepala Tukang Cat 150,000.00 2,400.00
0.100 OH Pekerja 100,000.00 10,000.00
0.006 OH Mandor 135,000.00 810.00
Jumlah ( A + B + C ) 33,910.00
Keuntungan & Overhead 10 % 3,391.00
Jumlah ……………………… 37,301.00

PEKERJAAN PAS.KUNCI
SNI.265.a 1 Bh. Pasang Kunci Tanam Biasa
BAHAN
1.000 bh Kunci tanam biasa 114,000.00 114,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 184,675.00
Keuntungan & Overhead 10 % 18,467.50
Jumlah ……………………… 203,142.50

SNI.265.b 1 Bh. Pasang Kunci Tanam Mutu Menengah


BAHAN
1.000 bh Kunci tanam mutu menengah 164,000.00 164,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 234,675.00
Keuntungan & Overhead 10 % 23,467.50
Jumlah ……………………… 258,142.50

SNI.265.c 1 Bh. Pasang Kunci Tanam Mutu Tinggi


BAHAN
1.000 bh Kunci tanam mutu tinggi 555,000.00 555,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 625,675.00
Keuntungan & Overhead 10 % 62,567.50
Jumlah ……………………… 688,242.50

SNI.266 1 Bh. Pasang Kunci Tanam Kamar Mandi


BAHAN
1.000 bh Kunci tanam biasa 103,000.00 103,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.005 OH Kepala Tukang Kayu 150,000.00 750.00
0.005 OH Pekerja 100,000.00 500.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 172,087.50
Keuntungan & Overhead 10 % 17,208.75
Jumlah ……………………… 189,296.25

SNI.267 1 Bh. Pasang Engsel Pintu


BAHAN
1.000 bh Engsel Pintu 20,000.00 20,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 44,101.25
Keuntungan & Overhead 10 % 4,410.13
Jumlah ……………………… 48,511.38
SNI.268 1 Bh. Pasang Engsel Jendela
BAHAN
1.000 bh Engsel Jendela 16,000.00 16,000.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.001 OH Mandor 135,000.00 67.50
Jumlah ( A + B + C ) 32,067.50
Keuntungan & Overhead 10 % 3,206.75
Jumlah ……………………… 35,274.25

SNI.268.1 1 Bh. Pasang Grendel Besar


BAHAN
1.000 bh Grendel Besar 23,000.00 23,000.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.001 OH Mandor 135,000.00 67.50
Jumlah ( A + B + C ) 39,067.50
Keuntungan & Overhead 10 % 3,906.75
Jumlah ……………………… 42,974.25

SNI.268.2 1 Bh. Pasang Grendel Kecil


BAHAN
1.000 bh Grendel Kecil 13,000.00 13,000.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.001 OH Mandor 135,000.00 67.50
Jumlah ( A + B + C ) 29,067.50
Keuntungan & Overhead 10 % 2,906.75
Jumlah ……………………… 31,974.25
SNI.269 1 Bh. Pasang Kait Angin Besar
BAHAN
1.000 set Kait Angin Besar 13,000.00 13,000.00
TENAGA
0.150 OH Tukang Kayu 135,000.00 20,250.00
0.015 OH Kepala Tukang Kayu 150,000.00 2,250.00
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 37,101.25
Keuntungan & Overhead 10 % 3,710.13
Jumlah ……………………… 40,811.38

SNI.270 1 Bh. Pasang Kait Angin Kecil


BAHAN
1.000 set Kait Angin Kecil 9,000.00 9,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 89,337.50
Keuntungan & Overhead 10 % 8,933.75
Jumlah ……………………… 98,271.25

SNI.271 1 Bh. Pasang Kunci Selot Besar


BAHAN
1.000 bh Kunci Selot Besar 90,000.00 90,000.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.001 OH Mandor 135,000.00 67.50
Jumlah ( A + B + C ) 106,067.50
Keuntungan & Overhead 10 % 10,606.75
Jumlah ……………………… 116,674.25

SNI.272 1 Bh. Pasang Kunci Selot Kecil


BAHAN
1.000 bh Kunci Selot Kecil 70,000.00 70,000.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.020 OH Kepala Tukang Kayu 150,000.00 3,000.00
0.020 OH Pekerja 100,000.00 2,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 102,135.00
Keuntungan & Overhead 10 % 10,213.50
Jumlah ……………………… 112,348.50

SNI.273 1 Bh. Pasang Beugel U


BAHAN
1.000 bh Beugel U 39,000.00 39,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 40,601.25
Keuntungan & Overhead 10 % 4,060.13
Jumlah ……………………… 44,661.38

SNI.274 1 Bh. Pasang Beugel Plat


BAHAN
1.000 bh Beugel U 39,000.00 39,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 40,601.25
Keuntungan & Overhead 10 % 4,060.13
Jumlah ……………………… 44,661.38

SNI.275 1 Bh. Pasang Angker Dia 12 MM


BAHAN
1.000 bh Angkur Dia 12 mm 5,000.00 5,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 6,601.25
Keuntungan & Overhead 10 % 660.13
Jumlah ……………………… 7,261.38

SNI.276.a 1 Bh. Pas. Baut Mur


BAHAN
1.000 bh Baut Mur 5,000.00 5,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 6,601.25
Keuntungan & Overhead 10 % 660.13
Jumlah ……………………… 7,261.38

SNI.276.b 1 Bh. Pas. Baut Mur 12 mm


BAHAN
1.000 bh Paku Sekrup 10 cm 6,000.00 6,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 7,601.25
Keuntungan & Overhead 10 % 760.13
Jumlah ……………………… 8,361.38

SNI.276.c 1 Bh. Pas. Baut Mur 16 mm


BAHAN
1.000 bh Paku Sekrup 1- 2,5 cm 7,000.00 7,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 8,601.25
Keuntungan & Overhead 10 % 860.13
Jumlah ……………………… 9,461.38

SNI.276.d 1 Bh. Pas. Baut Mur 18 mm


BAHAN
1.000 bh Skrup Fixer 8,000.00 8,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 9,601.25
Keuntungan & Overhead 10 % 960.13
Jumlah ……………………… 10,561.38

SNI.276.e 1 Bh. Pas. Baut Mur 22 mm


BAHAN
1.000 bh Baut Mur 22 mm 10,000.00 10,000.00
TENAGA
0.015 OH Pekerja 100,000.00 1,500.00
0.001 OH Mandor 135,000.00 101.25
Jumlah ( A + B + C ) 11,601.25
Keuntungan & Overhead 10 % 1,160.13
Jumlah ……………………… 12,761.38

SNI.278.a 1 Bh. Pasang Door Closer


BAHAN
1.000 bh Door Closer 243,000.00 243,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.000 OH Mandor 135,000.00 33.75
Jumlah ( A + B + C ) 323,033.75
Keuntungan & Overhead 10 % 32,303.38
Jumlah ……………………… 355,337.13

SNI.278.b 1 Bh. Pasang Door Stoper


BAHAN
1.000 bh Door Stoper 65,000.00 65,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.000 OH Mandor 135,000.00 33.75
Jumlah ( A + B + C ) 145,033.75
Keuntungan & Overhead 10 % 14,503.38
Jumlah ……………………… 159,537.13

SNI.279 1 Bh. Pasang Pegangan Pintu/ Door Holder, (Pull Handle)


BAHAN
1.000 bh Pegangan Pintu KW 1 260,000.00 260,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.000 OH Mandor 135,000.00 33.75
Jumlah ( A + B + C ) 340,033.75
Keuntungan & Overhead 10 % 34,003.38
Jumlah ……………………… 374,037.13

SNI.280 1 Bh. Pasang Kunci Silender


BAHAN
1.000 bh Kunci Silinder 63,000.00 63,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.000 OH Mandor 135,000.00 33.75
Jumlah ( A + B + C ) 143,033.75
Keuntungan & Overhead 10 % 14,303.38
Jumlah ……………………… 157,337.13

SNI.281 1 Bh. Pasang Rel Pintu Dorong


BAHAN
1.000 bh Rel Pintu Dorong 42,000.00 42,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.000 OH Mandor 135,000.00 33.75
Jumlah ( A + B + C ) 122,033.75
Keuntungan & Overhead 10 % 12,203.38
Jumlah ……………………… 134,237.13

SNI.282 1 Bh. Pasang Pintu Feber glass (Wc)


BAHAN
1.000 bh Pintu Fiber Glass (Wc) 848,000.00 848,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.050 OH Kepala Tukang Kayu 150,000.00 7,500.00
0.050 OH Pekerja 100,000.00 5,000.00
0.000 OH Mandor 135,000.00 33.75
Jumlah ( A + B + C ) 928,033.75
Keuntungan & Overhead 10 % 92,803.38
Jumlah ……………………… 1,020,837.13

PEKERJAAN INSTALASI LISTRIK


SNI.IL.1 Pekerjaan Panel
BAHAN
1.000 unit Box panel uk (600 x 400 x 250) type wal 2,108,200.00 2,108,200.00
1.000 bh MCCB 80 A 3~ 3P 25 kA 1,332,500.00 1,332,500.00
3.000 bh MCCB 40 A 3~ 3P 50 kA 1,853,700.00 5,561,100.00
3.000 bh MCCB 40 A 3~ 3P 18 kA 1,051,100.00 3,153,300.00
3.000 bh Lampu Indikator 27,500.00 82,500.00
3.000 bh Fuse Lamp 2A 27,500.00 82,500.00
1.000 ls Bus Bar system Cu 5x(20x5mm) 935,000.00 935,000.00
1.000 ls Sepatu kabel+ Sleeve+ Cable tie 165,000.00 165,000.00
1.000 ls Grounding kabel BCC 35 mm2 935,000.00 935,000.00
1.000 ls Wiring + Pemasangan 550,000.00 550,000.00
TENAGA
1.000 Ls Pekerja listrik (3% dari harga bahan) 447,153.00 447,153.00
Jumlah ( A + B + C ) 15,352,253.00
Keuntungan & Overhead 10 % 1,535,225.30
Jumlah ……………………… 16,887,450.00

SNI.IL.1a Panel Daya lantai 01


BAHAN
1.000 unit Box panel uk (600 x 400 x 250) type wal 2,108,200.00 2,108,200.00
1.000 bh MCCB 40A / 3P / 10kA 701,800.00 701,800.00
18.000 bh MCB 16A / 1P / 10kA 161,700.00 2,910,600.00
3.000 bh MCB 10A / 1P / 10kA 161,700.00 485,100.00
3.000 bh Lampu Indikator 27,500.00 82,500.00
3.000 bh Fuse Lamp 2A 27,500.00 82,500.00
1.000 ls Bus Bar system Cu 5x(20x5mm) 935,000.00 935,000.00
1.000 ls Sepatu kabel+ Sleeve+ Cable tie 165,000.00 165,000.00
1.000 ls Wiring + Pemasangan 550,000.00 550,000.00
TENAGA
1.000 Ls Pekerja listrik (3% dari harga bahan) 240,621.00 240,621.00
Jumlah ( A + B + C ) 8,261,321.00
Keuntungan & Overhead 10 % 826,132.10
Jumlah ……………………… 9,087,450.00

SNI.IL.1b Panel Daya lantai 02


BAHAN
1.000 unit Box panel uk (600 x 400 x 250) type wal 2,108,200.00 2,108,200.00
1.000 bh MCCB 40A / 3P / 10kA 701,800.00 701,800.00
9.000 bh MCB 16A / 1P / 10kA 161,700.00 1,455,300.00
10.000 bh MCB 10A / 1P / 10kA 161,700.00 1,617,000.00
3.000 bh Lampu Indikator 27,500.00 82,500.00
3.000 bh Fuse Lamp 2A 27,500.00 82,500.00
1.000 ls Bus Bar system Cu 5x(20x5mm) 935,000.00 935,000.00
1.000 ls Sepatu kabel+ Sleeve+ Cable tie 165,000.00 165,000.00
1.000 ls Wiring + Pemasangan 550,000.00 550,000.00
TENAGA
1.000 Ls Pekerja listrik (3% dari harga bahan) 230,919.00 230,919.00
Jumlah ( A + B + C ) 7,928,219.00
Keuntungan & Overhead 10 % 792,821.90
Jumlah ……………………… 8,721,000.00

SNI.IL.1c Panel AC lantai 01


BAHAN
1.000 unit Box panel uk (600 x 400 x 250) type wal 2,108,200.00 2,108,200.00
1.000 bh MCCB 40A / 3P / 18kA 701,800.00 701,800.00
18.000 bh MCB 10A / 1P / 10kA 161,700.00 2,910,600.00
3.000 bh Lampu Indikator 27,500.00 82,500.00
3.000 bh Fuse Lamp 2A 27,500.00 82,500.00
1.000 ls Bus Bar system Cu 5x(20x5mm) 935,000.00 935,000.00
1.000 ls Sepatu kabel+ Sleeve+ Cable tie 165,000.00 165,000.00
1.000 ls Wiring + Pemasangan 550,000.00 550,000.00
TENAGA
1.000 Ls Pekerja listrik (3% dari harga bahan) 226,068.00 226,068.00
Jumlah ( A + B + C ) 7,761,668.00
Keuntungan & Overhead 10 % 776,166.80
Jumlah ……………………… 8,537,800.00

SNI.IL.2 1 m' NYY 4 x 10 mm² + BCC 10 mm²


BAHAN
1.000 m1 Kabel NYY 4 x 10 mm² 58,700.00 58,700.00
1.000 m1 Kabel BCC 10 mm² 12,500.00 12,500.00
TENAGA
1.000 Ls Pekerja listrik (10% dari harga bahan) 7,120.00 7,120.00
Jumlah ( A + B + C ) 78,320.00
Keuntungan & Overhead 10 % 7,832.00
Jumlah ……………………… 86,150.00
SNI.IL.2a 1 m' Kabel NYM 3 x 2.5 mm2
BAHAN
1.000 m1 Kabel NYM 3 x 2.5 mm2 15,400.00 15,400.00
1.000 Ls Material bantu (1% dari harga bahan) 154.00 154.00
TENAGA
0.100 OH Tukang listrik 120,000.00 12,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 49,304.00
Keuntungan & Overhead 10 % 4,930.40
Jumlah ……………………… 54,200.00

SNI.IL.2b 1 m' Kabel NYY 4 x 25 mm2


BAHAN
1.000 m1 Kabel NYY 4 x 25 mm2 187,000.00 187,000.00
1.000 Ls Material bantu (1% dari harga bahan) 1,870.00 1,870.00
TENAGA
0.100 OH Tukang listrik 120,000.00 12,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 222,620.00
Keuntungan & Overhead 10 % 22,262.00
Jumlah ……………………… 244,850.00

SNI.IL.3 1 Titik instalasi Penerangan Kabel NYM 2 x 2.5 mm


BAHAN
10.000 m1 Kabel NYM 2 x 2.5 mm 11,000.00 110,000.00
10.000 m1 Pipa PVC 20mm² 2,500.00 25,000.00
1.000 ls Material bantu T doos, sock, lem 18,700.00 18,700.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 180,325.00
Keuntungan & Overhead 10 % 18,032.50
Jumlah ……………………… 198,350.00
SNI.IL.3a 1 Titik instalasi Penerangan Kabel NYM 3 x 2.5 mm
BAHAN
10.000 m1 Kabel NYM 3 x 2.5 mm 15,400.00 154,000.00
10.000 m1 Pipa PVC 20mm² 2,500.00 25,000.00
1.000 ls Material bantu T doos, sock, lem 18,700.00 18,700.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 224,325.00
Keuntungan & Overhead 10 % 22,432.50
Jumlah ……………………… 246,750.00

SNI.IL.3b 1 Titik instalasi stop kontak


BAHAN
10.000 m1 Kabel NYM 2 x 2.5 mm 11,000.00 110,000.00
10.000 m1 Pipa PVC 20mm² 2,500.00 25,000.00
1.000 ls Material bantu T doos, sock, lem 18,700.00 18,700.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 180,325.00
Keuntungan & Overhead 10 % 18,032.50
Jumlah ……………………… 198,350.00

SNI.IL.3c 1 Titik instalasi stop kontak


BAHAN
10.000 m1 Kabel NYM 2 x 2.5 mm 11,000.00 110,000.00
10.000 m1 Pipa PVC 20mm² 2,500.00 25,000.00
1.000 ls Material bantu T doos, sock, lem 18,700.00 18,700.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 180,325.00
Keuntungan & Overhead 10 % 18,032.50
Jumlah ……………………… 198,350.00

SNI.IL.3d 1 Titik instalasi exhaust fan


BAHAN
10.000 m1 Kabel NYM 2 x 2.5 mm 15,400.00 154,000.00
10.000 m1 Pipa PVC 20mm² 2,500.00 25,000.00
1.000 ls Material bantu, sock, lem 18,700.00 18,700.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 224,325.00
Keuntungan & Overhead 10 % 22,432.50
Jumlah ……………………… 246,750.00

SNI.IL.3e 1 bh Lampu RMI TL LED T8 2 x 18 W


BAHAN
1.000 bh Lampu RMI TL LED T8 2 x 18 W 752,800.00 752,800.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 784,425.00
Keuntungan & Overhead 10 % 78,442.50
Jumlah ……………………… 862,850.00

SNI.IL.3f 1 bh Lampu Down Light Ø 6", LED 10.5 W


BAHAN
1.000 bh Lampu Down Light Ø 6", LED 10.5 W 279,100.00 279,100.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 310,725.00
Keuntungan & Overhead 10 % 31,072.50
Jumlah ……………………… 341,750.00

SNI.IL.3g 1 bh Lampu Down Light Ø 6", LED 7 W


BAHAN
1.000 bh Lampu Down Light Ø 6", LED 7 W 192,800.00 192,800.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 224,425.00
Keuntungan & Overhead 10 % 22,442.50
Jumlah ……………………… 246,850.00

SNI.IL.3h 1 bh Lampu Down Light Ø 4", LED 14 W


BAHAN
1.000 bh Fiting Lampu Tanam Dia. 4 " 40,000.00 40,000.00
1.000 bh Dow ligth / LED 14 W 152,000.00 152,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 223,625.00
Keuntungan & Overhead 10 % 22,362.50
Jumlah ……………………… 245,950.00

SNI.IL.3i 1 bh Lampu Down Light Ø 3", LED 7 W


BAHAN
1.000 bh Fiting Lampu Tanam Dia. 3 " 30,000.00 30,000.00
1.000 bh Dow ligth / LED 7 W 95,000.00 95,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 156,625.00
Keuntungan & Overhead 10 % 15,662.50
Jumlah ……………………… 172,250.00

SNI.IL.3j 1 bh Lampu Barret LED 18 W 1100 lm 6500 K


BAHAN
1.000 bh Lampu Barret LED 18 W 1100 lm 6500 K 488,100.00 488,100.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 519,725.00
Keuntungan & Overhead 10 % 51,972.50
Jumlah ……………………… 571,650.00

SNI.IL.3k 1 bh Exhaust Fan 472 CMH 12 W


BAHAN
1.000 bh Exhaust Fan 472 CMH 12 W 302,500.00 302,500.00
1.000 bh Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 334,125.00
Keuntungan & Overhead 10 % 33,412.50
Jumlah ……………………… 367,500.00

SNI.IL.3l Stop Kontak dinding


BAHAN
1.000 bh Stop kontak dinding 200 W 22,900.00 22,900.00
1.000 bh Inbowdoos seng 11,000.00 11,000.00
TENAGA
0.050 OH Tukang listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 45,575.00
Keuntungan & Overhead 10 % 4,557.50
Jumlah ……………………… 50,100.00

SNI.IL.3m Saklar Tunggal


BAHAN
1.000 bh Saklar Tunggal 29,900.00 29,900.00
1.000 bh Inbowdoos seng 11,000.00 11,000.00
TENAGA
0.050 OH Tukang listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 52,575.00
Keuntungan & Overhead 10 % 5,257.50
Jumlah ……………………… 57,800.00

SNI.IL.3n Saklar Double


BAHAN
1.000 bh Saklar Double 37,900.00 37,900.00
1.000 bh Inbowdoos seng 11,000.00 11,000.00
TENAGA
0.050 OH Tukang listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 60,575.00
Keuntungan & Overhead 10 % 6,057.50
Jumlah ……………………… 66,600.00

SNI.IL.4 1 Titik Instalasi Telephone


BAHAN
10.000 m1 Kabel ITC 2x2x0.6 6,000.00 60,000.00
10.000 m1 Pipa PVC 20mm² 2,500.00 25,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 116,625.00
Keuntungan & Overhead 10 % 11,662.50
Jumlah ……………………… 128,250.00
SNI.IL.4a 1 m' Kabel ITC 2 x 2 x 0.6
BAHAN
1.000 m1 Kabel ITC 2x2x0.6 6,000.00 6,000.00
1.000 m1 Pipa PVC 20mm² 2,500.00 2,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.025 OH Tukang listrik 120,000.00 3,000.00
0.025 OH Pekerja 100,000.00 2,500.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 22,375.00
Keuntungan & Overhead 10 % 2,237.50
Jumlah ……………………… 24,600.00

SNI.IL.4b Outlet telepon


BAHAN
1.000 bh Outlet telepon 56,400.00 56,400.00
1.000 bh Inbowdoos seng 11,000.00 11,000.00
TENAGA
0.050 OH Tukang listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 79,075.00
Keuntungan & Overhead 10 % 7,907.50
Jumlah ……………………… 86,950.00

SNI.IL.4c Telephone Terminal Box


BAHAN
1.000 bh Box Uk. 30 x 20 x 20 cm (tebal 2mm) 192,500.00 192,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 242,175.00
Keuntungan & Overhead 10 % 24,217.50
Jumlah ……………………… 266,350.00

SNI.IL.4d PABX Kap 4 lines, 16 Extension


BAHAN
1.000 bh PABX Kap 4 lines, 16 Extension 16,500,000.00 16,500,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 16,549,675.00
Keuntungan & Overhead 10 % 1,654,967.50
Jumlah ……………………… 18,204,600.00

SNI.IL.4e MDF Telephone


BAHAN
1.000 bh MDF Telephone 2,750,000.00 2,750,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 2,799,675.00
Keuntungan & Overhead 10 % 279,967.50
Jumlah ……………………… 3,079,600.00

SNI.IL.4f Hand single Telephone


BAHAN
1.000 unit Hand single Telephone 302,500.00 302,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 352,175.00
Keuntungan & Overhead 10 % 35,217.50
Jumlah ……………………… 387,350.00

SNI.IL.5 1 Titik Instalasi LAN


BAHAN
10.000 m1 Kabel UTP Cat 6 6,000.00 60,000.00
10.000 m1 Pipa conduit PVC 20mm 2,500.00 25,000.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 121,625.00
Keuntungan & Overhead 10 % 12,162.50
Jumlah ……………………… 133,750.00

SNI.IL.5a 1 m' Kabel UTP cat.6


BAHAN
1.000 m1 Kabel UTP Cat 6 11,000.00 11,000.00
1.000 m1 Pipa conduit PVC 20mm 2,500.00 2,500.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.025 OH Tukang listrik 120,000.00 3,000.00
0.025 OH Pekerja 100,000.00 2,500.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 32,375.00
Keuntungan & Overhead 10 % 3,237.50
Jumlah ……………………… 35,600.00

SNI.IL.5b Outlet LAN


BAHAN
1.000 bh Outlet LAN 9,700.00 9,700.00
1.000 bh Inbowdoos seng 11,000.00 11,000.00
TENAGA
0.050 OH Tukang listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 32,375.00
Keuntungan & Overhead 10 % 3,237.50
Jumlah ……………………… 35,600.00

SNI.IL.5c 1 unit Optical terminal box


BAHAN
1.000 unit Optical terminal box 1,375,000.00 1,375,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 1,424,675.00
Keuntungan & Overhead 10 % 142,467.50
Jumlah ……………………… 1,567,100.00

SNI.IL.5d 1 unit Switch Hub Utama 8 Port Manageable


BAHAN
1.000 unit Switch Hub Utama 8 Port Manageable 17,242,500.00 17,242,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 17,292,175.00
Keuntungan & Overhead 10 % 1,729,217.50
Jumlah ……………………… 19,021,350.00

SNI.IL.5e 1 unit Patch panel 8 port


BAHAN
1.000 unit Patch panel 8 port 1,650,000.00 1,650,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 1,699,675.00
Keuntungan & Overhead 10 % 169,967.50
Jumlah ……………………… 1,869,600.00

SNI.IL.5f 1 unit Closed Rack 12U


BAHAN
1.000 unit Walmount Rack 12U 3,520,000.00 3,520,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 3,569,675.00
Keuntungan & Overhead 10 % 356,967.50
Jumlah ……………………… 3,926,600.00

SNI.IL.6 1 Titik Instalasi Ceiling speaker


BAHAN
10.000 m1 NYMHY 3x1,5mm 11,500.00 115,000.00
10.000 m1 Pipa conduit PVC 20mm 2,500.00 25,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 171,625.00
Keuntungan & Overhead 10 % 17,162.50
Jumlah ……………………… 188,750.00

SNI.IL.6a 1 Titik Instalasi attenuator


BAHAN
10.000 m1 NYMHY 3x1,5mm 11,500.00 115,000.00
10.000 m1 Pipa conduit PVC 20mm 2,500.00 25,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.075 OH Tukang listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 171,625.00
Keuntungan & Overhead 10 % 17,162.50
Jumlah ……………………… 188,750.00
SNI.IL.6b 1 unit Sound terminal box
BAHAN
1.000 unit Sound terminal box 1,100,000.00 1,100,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 1,149,675.00
Keuntungan & Overhead 10 % 114,967.50
Jumlah ……………………… 1,264,600.00

SNI.IL.6c 1 m' NYMHY 3x1,5mm


BAHAN
1.000 m1 NYMHY 3x1,5mm 11,500.00 11,500.00
1.000 m1 Pipa conduit PVC 20mm 2,500.00 2,500.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.050 OH Tukang listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 41,750.00
Keuntungan & Overhead 10 % 4,175.00
Jumlah ……………………… 45,900.00

SNI.IL.6d 1 bh Ceiling Speaker


BAHAN
1.000 bh Ceiling Speaker 137,500.00 137,500.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 192,175.00
Keuntungan & Overhead 10 % 19,217.50
Jumlah ……………………… 211,350.00

SNI.IL.6e 1 bh Attenuator
BAHAN
1.000 bh Attenuator 30W ZV-303 162,800.00 162,800.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 217,475.00
Keuntungan & Overhead 10 % 21,747.50
Jumlah ……………………… 239,200.00

SNI.IL.6f 1 bh Dynamic Microphone


BAHAN
1.000 bh Dynamic Microphone 269,800.00 269,800.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 324,475.00
Keuntungan & Overhead 10 % 32,447.50
Jumlah ……………………… 356,900.00

SNI.IL.6g 1unit CD Player CD-2011 R


BAHAN
1.000 unit CD Player CD-2011 R 2,200,000.00 2,200,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 2,249,675.00
Keuntungan & Overhead 10 % 224,967.50
Jumlah ……………………… 2,474,600.00

SNI.IL.6h 1 set Rack cabinet


BAHAN
1.000 set Rack cabinet 11,000,000.00 11,000,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 11,049,675.00
Keuntungan & Overhead 10 % 1,104,967.50
Jumlah ……………………… 12,154,600.00

SNI.IL.6i 1 bh Remote Microphone w/Keypad Zone Selector


BAHAN
1.000 bh Remote Microphone w/Keypad Zone Selec 6,390,400.00 6,390,400.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 6,440,075.00
Keuntungan & Overhead 10 % 644,007.50
Jumlah ……………………… 7,084,050.00

SNI.IL.6j 1 unit Power amplifier 240 W with 5 zone Selector system


BAHAN
1.000 bh Power amplifier 240 W with 5 zone Select 5,500,000.00 5,500,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 5,549,675.00
Keuntungan & Overhead 10 % 554,967.50
Jumlah ……………………… 6,104,600.00

SNI.IL.6k 1 unit Battery backup 2x1000 VA


BAHAN
1.000 unit Battery backup 2x1000 VA 3,598,200.00 3,598,200.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 3,647,875.00
Keuntungan & Overhead 10 % 364,787.50
Jumlah ……………………… 4,012,650.00

SNI.IL.7 1 unit Air terminal R-150 Early Streamer Emmission (ESE) technology
BAHAN
1.000 unit Air terminal R-150 10,450,000.00 10,450,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 10,499,675.00
Keuntungan & Overhead 10 % 1,049,967.50
Jumlah ……………………… 11,549,600.00

SNI.IL.7a 1 m' Kabel NYY 1x70 mm2 for down conductor


BAHAN
1.000 m1 Kabel NYY 1x70 mm2 for down conductor 123,200.00 123,200.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.005 OH Tukang listrik 120,000.00 600.00
0.005 OH Pekerja 100,000.00 500.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 129,975.00
Keuntungan & Overhead 10 % 12,997.50
Jumlah ……………………… 142,950.00

SNI.IL.7b 1 bh Connecting Sleeve


BAHAN
1.000 bh Connecting Sleeve 418,000.00 418,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 467,675.00
Keuntungan & Overhead 10 % 46,767.50
Jumlah ……………………… 514,400.00

SNI.IL.7c 1 bh Schoen cable CU 50


BAHAN
1.000 bh Schoen cable CU 50 22,000.00 22,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 71,675.00
Keuntungan & Overhead 10 % 7,167.50
Jumlah ……………………… 78,800.00

SNI.IL.7d 1 m' Pipa galvanis Ø 2.5" dudukan untuk air terminal + las
BAHAN
1.000 m1 Pipa galvanis Ø 2.5" 121,400.00 121,400.00
1.000 ls Perlengkapan (35% dari harga bahan) 42,490.00 42,490.00
TENAGA
0.180 OH Tukang Batu 135,000.00 24,300.00
0.108 OH Pekerja 100,000.00 10,800.00
0.018 OH Kepala Tukang batu 150,000.00 2,700.00
0.005 OH Mandor 135,000.00 729.00
Jumlah ( A + B + C ) 202,419.00
Keuntungan & Overhead 10 % 20,241.90
Jumlah ……………………… 222,650.00

SNI.IL.7e 1 m' Kabel conductor BC 70 mm² untuk gounding


BAHAN
1.000 m1 Kabel conductor BC 70 mm² untuk gound 58,900.00 58,900.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.005 OH Tukang Batu 135,000.00 675.00
0.005 OH Pekerja 100,000.00 500.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 65,750.00
Keuntungan & Overhead 10 % 6,575.00
Jumlah ……………………… 72,300.00

SNI.IL.7f 1 btg Pipa galvanis 3/4" ( untuk grounding )


BAHAN
1.000 btg Pipa galvanis 3/4" ( untuk grounding ) 30,000.00 30,000.00
1.000 ls Perlengkapan (35% dari harga bahan) 10,500.00 10,500.00
TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 88,175.00
Keuntungan & Overhead 10 % 8,817.50
Jumlah ……………………… 96,950.00

SNI.IL.7g 1 bh Splitzen tembaga murni 3/4"( bukan lapisan ) untuk ground rod
BAHAN
1.000 bh Splitzen tembaga murni 3/4" 946,000.00 946,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 998,675.00
Keuntungan & Overhead 10 % 99,867.50
Jumlah ……………………… 1,098,500.00

SNI.IL.7h 1 Kg Timah
BAHAN
1.000 kg Timah 742,500.00 742,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 795,175.00
Keuntungan & Overhead 10 % 79,517.50
Jumlah ……………………… 874,650.00

SNI.IL.7i 1 m' Pipa PVC 3/4" for Kabel NYY 1x50 mm2
BAHAN
1.000 m1 Pipa PVC 3/4" for Kabel NYY 1x50 mm2 9,000.00 9,000.00
1.000 ls Perlengkapan (35% dari harga bahan) 3,150.00 3,150.00
TENAGA
0.060 OH Tukang Batu 135,000.00 8,100.00
0.036 OH Pekerja 100,000.00 3,600.00
0.006 OH Kepala tukang batu 150,000.00 900.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 24,993.00
Keuntungan & Overhead 10 % 2,499.30
Jumlah ……………………… 27,450.00

SNI.IL.7j 1 unit Pembuatan sumur grounding


BAHAN
1.000 unit Pembuatan sumur grounding 2,750,000.00 2,750,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang Listrik 135,000.00 27,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 2,802,675.00
Keuntungan & Overhead 10 % 280,267.50
Jumlah ……………………… 3,082,900.00

SNI.IL.7k 1 bh Pembuatan bak kontrol grounding 70x70x65 cm

0.366 m3 Galian tanah sampai 1 m 86,212.50 31,521.45


2.513 m2 Pas dinding bata merah 1pc : 6ps 152,293.90 382,638.42
5.025 m2 Plesteran Dinding 1Pc : 6Ps 74,769.42 375,716.34
5.025 m2 Acian 46,062.50 231,464.06
0.740 kg Tarikan besi Ø10 mm 16,000.00 11,846.40
0.039 m3 Plat beton, tebal 80 mm, Tulangan # P8 3,500,000.00 137,200.00
Jumlah ( A + B + C ) 1,170,386.67
Jumlah ……………………… 1,170,350.00

SNI.IL.8 1 m' Kabel tray 400 mm x 100 mm


BAHAN
1.000 m1 Kabel tray 400 mm x 100 mm 141,200.00 141,200.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.050 OH Tukang Listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 163,950.00
Keuntungan & Overhead 10 % 16,395.00
Jumlah ……………………… 180,300.00

SNI.IL.8a 1 pcs TeeTray 400 mm x 100 mm


BAHAN
1.000 bh TeeTray 400 mm x 100 mm 575,300.00 575,300.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.100 OH Tukang Listrik 120,000.00 12,000.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 602,975.00
Keuntungan & Overhead 10 % 60,297.50
Jumlah ……………………… 663,250.00

SNI.IL.8b 1 pcs El Bow Tray 400 mm x 100 mm


BAHAN
1.000 bh El Bow Tray 400 mm x 100 mm 513,500.00 513,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.100 OH Tukang Listrik 120,000.00 12,000.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 541,175.00
Keuntungan & Overhead 10 % 54,117.50
Jumlah ……………………… 595,250.00

SNI.IL.8c 1 m' Kabel Ladder 400 mm x 100 mm


BAHAN
1.000 m1 Kabel Ladder 400 mm x 100 mm 103,200.00 103,200.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.050 OH Tukang Listrik 120,000.00 6,000.00
0.050 OH Pekerja 100,000.00 5,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 125,950.00
Keuntungan & Overhead 10 % 12,595.00
Jumlah ……………………… 138,500.00

SNI.IL.9 Instalasi Power AC NYM 3x2,5mm


BAHAN
15.000 m1 NYM 3x2,5mm 15,400.00 231,000.00
15.000 m1 Pipa PVC 20mm² 2,500.00 37,500.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.075 OH Tukang Listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 305,125.00
Keuntungan & Overhead 10 % 30,512.50
Jumlah ……………………… 335,600.00

SNI.IL.9a Instalasi Power AC NYM 3x4mm


BAHAN
15.000 m1 NYM 3x4mm 22,000.00 330,000.00
15.000 m1 Pipa PVC 20mm² 2,500.00 37,500.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.075 OH Tukang Listrik 120,000.00 9,000.00
0.075 OH Pekerja 100,000.00 7,500.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 404,125.00
Keuntungan & Overhead 10 % 40,412.50
Jumlah ……………………… 444,500.00

SNI.IL.9b 1 unit Unit AC type wall split kap 1/2 PK


BAHAN
1.000 unit Unit AC type wall split kap 1/2 PK 4,440,900.00 4,440,900.00
1.000 ls Material bantu (0.5% dari harga bahan) 22,204.50 22,204.50
TENAGA
1.000 ls Pekerja listrik (0.05% dari harga bahan) 22,315.52 22,315.52
Jumlah ( A + B + C ) 4,485,420.02
Keuntungan & Overhead 10 % 448,542.00
Jumlah ……………………… 4,933,950.00

SNI.IL.9c 1 unit Unit AC type wall split kap 1 PK


BAHAN
1.000 unit Unit AC type wall split kap 1 PK 8,881,800.00 8,881,800.00
1.000 ls Material bantu (0.5% dari harga bahan) 44,409.00 44,409.00
TENAGA
1.000 ls Pekerja listrik (0.05% dari harga bahan) 44,631.05 44,631.05
Jumlah ( A + B + C ) 8,970,840.05
Keuntungan & Overhead 10 % 897,084.00
Jumlah ……………………… 9,867,900.00

SNI.IL.9d 1 unit Unit AC type wall split kap 1.5 PK


BAHAN
1.000 unit Unit AC type wall split kap 1.5 PK 11,102,200.00 11,102,200.00
1.000 ls Material bantu (0.5% dari harga bahan) 55,511.00 55,511.00
TENAGA
1.000 ls Pekerja listrik (0.05% dari harga bahan) 55,788.56 55,788.56
Jumlah ( A + B + C ) 11,213,499.56
Keuntungan & Overhead 10 % 1,121,349.96
Jumlah ……………………… 12,334,800.00

SNI.IL.9e 1 unit Unit AC type wall split kap 2 PK


BAHAN
1.000 unit Unit AC wall mounted type kap 2 PK 14,803,000.00 14,803,000.00
1.000 ls Material bantu (0.5% dari harga bahan) 74,015.00 74,015.00
TENAGA
1.000 ls Pekerja listrik (0.05% dari harga bahan) 74,385.08 74,385.08
Jumlah ( A + B + C ) 14,951,400.08
Keuntungan & Overhead 10 % 1,495,140.01
Jumlah ……………………… 16,446,500.00

SNI.IL.9f Unit AC cassette type kap 2.5 PK


BAHAN
1.000 unit Unit AC cassette type kap 2.5 PK 19,243,900.00 19,243,900.00
1.000 ls Material bantu (0.5% dari harga bahan) 96,219.50 96,219.50
TENAGA
1.000 ls Pekerja listrik (0.05% dari harga bahan) 96,700.60 96,700.60
Jumlah ( A + B + C ) 19,436,820.10
Keuntungan & Overhead 10 % 1,943,682.01
Jumlah ……………………… 21,380,500.00

SNI.IL.9g 1m' Pipa refrigrant 3/8" + 5/8"


BAHAN
1.050 m1 Pipa refigerant 3/8 " 62,500.00 65,625.00
1.050 m1 Pipa refigerant 5/8" 106,250.00 111,562.50
1.050 m' Insulasi 25,000.00 26,250.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
1.000 ls Pekerja listrik (1% dari harga bahan) 20,843.75 20,843.75
Jumlah ( A + B + C ) 229,281.25
Keuntungan & Overhead 10 % 22,928.13
Jumlah ……………………… 252,200.00

SNI.IL.9h 1m' Pipa refrigrant 1/4" + 3/8"


BAHAN
1.050 m1 Pipa refigerant 1/4 " 62,500.00 65,625.00
1.050 m1 Pipa refigerant 3/8 " 4,964.33 5,212.54
1.050 m' Insulasi 6,866.83 7,210.17
1.000 ls Material bantu 20,000.00 20,000.00
TENAGA
1.000 ls Pekerja listrik (1% dari harga bahan) 9,804.77 9,804.77
Jumlah ( A + B + C ) 107,852.48
Keuntungan & Overhead 10 % 10,785.25
Jumlah ……………………… 118,600.00

PEKERJAAN SANITAIR
SNI.283.B Memasang 1 Bh Kloset Duduk Biasa
BAHAN
1.000 Bh Kloset Duduk biasa 826,000.00 826,000.00
6% Harga Kloset Perlengkapan 49,560.00
TENAGA
1.100 OH Tukang Batu 135,000.00 148,500.00
0.001 OH Kepala Tukang Batu 150,000.00 150.00
3.300 OH Pekerja 100,000.00 330,000.00
0.160 OH Mandor 135,000.00 21,600.00
Jumlah ( A + B + C ) 1,375,810.00
Keuntungan & Overhead 10 % 137,581.00
Jumlah ……………………… 1,513,391.00

SNI.283.K Memasang 1 Bh Kloset Duduk (KW 1 Super)


BAHAN
1.000 Bh Kloset Duduk (Kw 1 super) 3,659,000.00 3,659,000.00
6% Harga Kloset Perlengkapan 219,540.00
TENAGA
1.100 OH Tukang Batu 135,000.00 148,500.00
0.001 OH Kepala Tukang Batu 150,000.00 150.00
3.300 OH Pekerja 100,000.00 330,000.00
0.160 OH Mandor 135,000.00 21,600.00
Jumlah ( A + B + C ) 4,378,790.00
Keuntungan & Overhead 10 % 437,879.00
Jumlah ……………………… 4,816,669.00

SNI.283.U Memasang 1 Bh Urinoir Porselin (KW 1 Super)


BAHAN
1.000 Bh Kloset Duduk 2,726,000.00 2,726,000.00
6% Harga Kloset Perlengkapan 163,560.00
TENAGA
1.100 OH Tukang Batu 135,000.00 148,500.00
0.001 OH Kepala Tukang Batu 150,000.00 150.00
3.300 OH Pekerja 100,000.00 330,000.00
0.160 OH Mandor 135,000.00 21,600.00
Jumlah ( A + B + C ) 3,389,810.00
Keuntungan & Overhead 10 % 338,981.00
Jumlah ……………………… 3,728,791.00

SNI.283.a Memasang 1 Bh Kloset Jongkok Porselon


BAHAN
1.000 Bh Kloset Jongkok Porselin 250,000.00 250,000.00
6.000 Kg Semen Portland 1,700.00 10,200.00
0.010 M3 Pasir Pasang 220,000.00 2,200.00
TENAGA
1.500 OH Tukang Batu 135,000.00 202,500.00
1.500 OH Kepala Tukang Batu 150,000.00 225,000.00
1.000 OH Pekerja 100,000.00 100,000.00
0.160 OH Mandor 135,000.00 21,600.00
Jumlah ( A + B + C ) 811,500.00
Keuntungan & Overhead 10 % 81,150.00
Jumlah ……………………… 892,650.00

SNI.283.b Memasang 1 Bh Kloset Jongkok Teraso


BAHAN
1.000 Bh Kloset Jongkok Teraso 125,000.00 125,000.00
7.000 Bj Bata merah 950.00 6,650.00
6.000 Kg Semen Portland 1,700.00 10,200.00
0.010 M3 Pasir Pasang 220,000.00 2,200.00
TENAGA
1.500 OH Tukang Batu 135,000.00 202,500.00
0.300 OH Kepala Tukang Batu 150,000.00 45,000.00
1.000 OH Pekerja 100,000.00 100,000.00
0.110 OH Mandor 135,000.00 14,850.00
Jumlah ( A + B + C ) 506,400.00
Keuntungan & Overhead 10 % 50,640.00
Jumlah ……………………… 557,040.00
SNI.284 Memasang 1 Bh Wastafel Biasa
BAHAN
1.000 Bh Wastafel biasa 481,000.00 481,000.00
12% Harga Wastafel Perlengkapan 57,720.00
6.000 Kg Semen Portland 1,700.00 10,200.00
0.010 M3 Pasir Pasang 220,000.00 2,200.00
TENAGA
1.450 OH Tukang Batu 135,000.00 195,750.00
0.150 OH Kepala Tukang Batu 150,000.00 22,500.00
1.200 OH Pekerja 100,000.00 120,000.00
0.100 OH Mandor 135,000.00 13,500.00
Jumlah ( A + B + C ) 902,870.00
Keuntungan & Overhead 10 % 90,287.00
Jumlah ……………………… 993,157.00

SNI.285 Memasang 1 Bh Wastafel (KW 1 Super)


BAHAN
1.000 Bh Wastafel ( Kw 1 Super) 2,375,000.00 2,375,000.00
12% Harga Wastafel Perlengkapan 285,000.00
6.000 Kg Semen Portland 1,700.00 10,200.00
0.010 M3 Pasir Pasang 220,000.00 2,200.00
TENAGA
1.450 OH Tukang Batu 135,000.00 195,750.00
0.150 OH Kepala Tukang Batu 150,000.00 22,500.00
1.200 OH Pekerja 100,000.00 120,000.00
0.100 OH Mandor 135,000.00 13,500.00
Jumlah ( A + B + C ) 3,024,150.00
Keuntungan & Overhead 10 % 302,415.00
Jumlah ……………………… 3,326,565.00

SNI.286 Memasang 1 buah Urinoir ex. TOTO U 57 M


BAHAN
1.000 bh Urinoir 2,726,000.00 2,726,000.00
6% Harga Wastafel Perlengkapan 163,560.00
6.000 Kg Semen Portland 1,700.00 10,200.00
0.010 m3 Pasir Pasang 220,000.00 2,200.00
TENAGA
1.000 OH Tukang Batu 135,000.00 135,000.00
0.100 OH Kepala Tukang Batu 150,000.00 15,000.00
1.000 OH Pekerja 100,000.00 100,000.00
0.100 OH Mandor 135,000.00 13,500.00
Jumlah ( A + B + C ) 3,165,460.00
Keuntungan & Overhead 10 % 316,546.00
Jumlah ……………………… 3,482,006.00

SNI.286.a Memasang 1 bh Pembatas Urinoir ex. TOTO A 100


BAHAN
1.000 bh Pembatas urinoir ex. TOTO A 100 1,375,000.00 1,375,000.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 1,391,675.00
Keuntungan & Overhead 10 % 139,167.50
Jumlah ……………………… 1,530,842.50

SNI.286.b Memasang 1 buah Kitchen Sink Stainless Steel ex. TOTO


BAHAN
1.000 bh Kitchen Sink Stainless Steel ex. TOTO 2,156,200.00 2,156,200.00
6% Harga Wastafel Perlengkapan 129,372.00
TENAGA
0.700 OH Tukang Batu 135,000.00 94,500.00
0.054 OH Kepala Tukang Batu 150,000.00 8,100.00
0.100 OH Pekerja 100,000.00 10,000.00
0.110 OH Mandor 135,000.00 14,850.00
Jumlah ( A + B + C ) 2,413,022.00
Keuntungan & Overhead 10 % 241,302.20
Jumlah ……………………… 2,654,324.20

SNI.286.1 Memasang 1 Bh Bak Cuci Piring Logam, 1 lubang


1.000 Bh Bak Cuci Piring Logam, 1 lubang 520,000.00 520,000.00
1.000 Set Water Drain + Acesories 68,000.00 68,000.00
0.300 OH Tukang Batu 135,000.00 40,500.00
0.030 OH Kepala Tukang Batu 150,000.00 4,500.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
Jumlah ( A + B + C ) 636,202.50
Keuntungan & Overhead 10 % 63,620.25
Jumlah ……………………… 699,822.75

SNI.286.2 Memasang 1 Bh Bak Cuci Piring Logam, 2 lubang


1.000 Bh Bak Cuci Piring Logam, 2 lubang 650,000.00 650,000.00
1.000 Set Water Drain + Acesories 68,000.00 68,000.00
0.300 OH Tukang Batu 135,000.00 40,500.00
0.030 OH Kepala Tukang Batu 150,000.00 4,500.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
Jumlah ( A + B + C ) 766,202.50
Keuntungan & Overhead 10 % 76,620.25
Jumlah ……………………… 842,822.75
SNI.287 Memasang 1 Bh Bak Mandi Teraso
BAHAN
1.000 Bh Bak Teraso 481,000.00 481,000.00
6.000 Kg Semen Portland 1,700.00 10,200.00
0.010 M3 Pasir Pasang 220,000.00 2,200.00
TENAGA
0.750 OH Tukang Batu 135,000.00 101,250.00
0.070 OH Kepala Tukang Batu 150,000.00 10,500.00
2.100 OH Pekerja 100,000.00 210,000.00
0.110 OH Mandor 135,000.00 14,850.00
Jumlah ( A + B + C ) 830,000.00
Keuntungan & Overhead 10 % 83,000.00
Jumlah ……………………… 913,000.00

SNI.288 Memasang 1 Bh Bak Mandi Fiberglass


BAHAN
1.000 Bh Bak Fiberglass 521,000.00 521,000.00
18% Harga Bak Perlengkapan 93,780.00
TENAGA
2.700 OH Tukang Batu 135,000.00 364,500.00
0.540 OH Kepala Tukang Batu 150,000.00 81,000.00
1.800 OH Pekerja 100,000.00 180,000.00
0.110 OH Mandor 135,000.00 14,850.00
Jumlah ( A + B + C ) 1,255,130.00
Keuntungan & Overhead 10 % 125,513.00
Jumlah ……………………… 1,380,643.00

SNI.289 Memasang 1 Bh Bak Mandi Plastik


BAHAN
1.000 Bh Bak Plastik 520,000.00 520,000.00
18% Harga Bak Perlengkapan 93,600.00
TENAGA
2.700 OH Tukang Batu 135,000.00 364,500.00
0.540 OH Kepala Tukang Batu 150,000.00 81,000.00
1.800 OH Pekerja 100,000.00 180,000.00
0.110 OH Mandor 135,000.00 14,850.00
Jumlah ( A + B + C ) 1,253,950.00
Keuntungan & Overhead 10 % 125,395.00
Jumlah ……………………… 1,379,345.00

SNI.290 Memasang 1 Bh Kran Dia. 3/4" atau 1/2"


BAHAN
1.000 Bh Kran Air 18,000.00 18,000.00
0.025 Kg Seal Tape 6,000.00 150.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 34,825.00
Keuntungan & Overhead 10 % 3,482.50
Jumlah ……………………… 38,307.50

SNI.290.a Memasang 1 bh Kran ex. TOTO T2613


BAHAN
1.000 bh Kran Shower 362,500.00 362,500.00
0.025 bh Seal tape 6,000.00 150.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 379,325.00
Keuntungan & Overhead 10 % 37,932.50
Jumlah ……………………… 417,257.50

SNI.291 Memasang 1 Bh Floor Drain


BAHAN
1.000 Bh Floor Drain 25,000.00 25,000.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 41,675.00
Keuntungan & Overhead 10 % 4,167.50
Jumlah ……………………… 45,842.50

SNI.291.a Memasang 1 bh Floor Drain ex. TOTO TX 1 BV 3


BAHAN
1.000 bh Floor Drain ex. TOTO TX 1 BV 3 396,200.00 396,200.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 412,875.00
Keuntungan & Overhead 10 % 41,287.50
Jumlah ……………………… 454,162.50

SNI.292 Memasang 1 Bh Saringan Air Besi


BAHAN
1.000 Bh Saringan Air Besi 114,000.00 114,000.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 130,675.00
Keuntungan & Overhead 10 % 13,067.50
Jumlah ……………………… 143,742.50

SNI.292.1 Memasang 1 bh Shower spray ex. TOTO TX 403 SBPIV


BAHAN
1.000 bh Shower spray ex. TOTO TX 403 SBPIV 812,500.00 812,500.00
0.025 bh Seal tape 6,000.00 150.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 829,325.00
Keuntungan & Overhead 10 % 82,932.50
Jumlah ……………………… 912,257.50

SNI.292.2 Memasang 1 bh Spoel hoek


BAHAN
1.000 bh Spoel hoek 11,000,000.00 11,000,000.00
0.025 bh Seal tape 6,000.00 150.00
TENAGA
0.650 OH Tukang Batu 135,000.00 87,750.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 11,100,075.00
Keuntungan & Overhead 10 % 1,110,007.50
Jumlah ……………………… 12,210,082.50

SNI.292.3 Memasang 1 bh shower ex. TOTO TR 309 SZ


BAHAN
1.000 bh Shower ex. TOTO TR 309 SZ 562,500.00 562,500.00
0.025 bh Seal tape 6,000.00 150.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 579,325.00
Keuntungan & Overhead 10 % 57,932.50
Jumlah ……………………… 637,257.50

SNI.292.4 Memasang 1 bh Paper Holder ex. TOTO TIPE TS116R


BAHAN
1.000 bh Paper Holder ex. TOTO TIPE TS116R 593,700.00 593,700.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 610,375.00
Keuntungan & Overhead 10 % 61,037.50
Jumlah ……………………… 671,412.50

SNI.292.5 Memasang 1 bh soap holder ex. TOTO S 156N


BAHAN
1.000 bh soap holder ex. TOTO S 156N 156,200.00 156,200.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 172,875.00
Keuntungan & Overhead 10 % 17,287.50
Jumlah ……………………… 190,162.50

SNI.292.6 Memasang 1 bh hand railing stainless steel ex. TOTO TX 3A2


BAHAN
1.000 bh hand railing stainless steel ex. TOTO TX 3 937,500.00 937,500.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 954,175.00
Keuntungan & Overhead 10 % 95,417.50
Jumlah ……………………… 1,049,592.50

SNI.293.a Memasang 1 Bh Tandon Air kap. 500 Liter


BAHAN
1.000 Bh Tandon Air Kap. 500 Liter 1,425,000.00 1,425,000.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 1,441,675.00
Keuntungan & Overhead 10 % 144,167.50
Jumlah ……………………… 1,585,842.50

SNI.293.b Memasang 1 Bh Tandon Air kap. 1000 Liter


BAHAN
1.000 Bh Tandon Air Kap. 1000 Liter 2,091,000.00 2,091,000.00
TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang Batu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 2,107,675.00
Keuntungan & Overhead 10 % 210,767.50
Jumlah ……………………… 2,318,442.50

SNI.294.V Memasang 1 m' Pipa PVC AW dia 1/2"


BAHAN
1.000 m' Pipa PVC dia 1/2" 7,400.00 7,400.00
Perlengkapan (35 % x harga pipa) 2,590.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 22,833.00
Keuntungan & Overhead 10 % 2,283.30
Jumlah ……………………… 25,116.30

SNI.295.V Memasang 1 m' Pipa PVC AW dia 3/4"


BAHAN
1.000 m' Pipa PVC dia 3/4" 9,000.00 9,000.00
Perlengkapan (35 % x harga pipa) 3,150.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 24,993.00
Keuntungan & Overhead 10 % 2,499.30
Jumlah ……………………… 27,492.30

SNI.296.V Memasang 1 m' Pipa PVC AW dia 1"


BAHAN
1.000 m' Pipa PVC dia 1" 11,400.00 11,400.00
Perlengkapan (35 % x harga pipa) 3,990.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 28,233.00
Keuntungan & Overhead 10 % 2,823.30
Jumlah ……………………… 31,056.30

SNI.297.V Memasang 1 m' Pipa PVC AW dia 1.5"


BAHAN
1.000 m' Pipa PVC dia 1.5" 23,900.00 23,900.00
Perlengkapan (35 % x harga pipa) 8,365.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 45,108.00
Keuntungan & Overhead 10 % 4,510.80
Jumlah ……………………… 49,618.80

SNI.298.Va Memasang 1 m' Pipa PVC AW dia 2"


BAHAN
1.000 m' Pipa PVC dia 2" 35,500.00 35,500.00
Perlengkapan (35 % x harga pipa) 12,425.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 60,768.00
Keuntungan & Overhead 10 % 6,076.80
Jumlah ……………………… 66,844.80

SNI.298.Va1 Memasang 1 m' Pipa PVC AW dia 2.5"


BAHAN
1.000 m' Pipa PVC dia 2.5" 45,600.00 45,600.00
Perlengkapan (35 % x harga pipa) 15,960.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 74,403.00
Keuntungan & Overhead 10 % 7,440.30
Jumlah ……………………… 81,843.30

SNI.298.Vb Memasang 1 m' Pipa PVC AW dia 3"


BAHAN
1.000 m' Pipa PVC dia 3" 65,100.00 65,100.00
Perlengkapan (35 % x harga pipa) 22,785.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 100,728.00
Keuntungan & Overhead 10 % 10,072.80
Jumlah ……………………… 110,800.80

SNI.298.Vc Memasang 1 m' Pipa PVC AW dia 4"


BAHAN
1.000 m' Pipa PVC dia 4" 94,900.00 94,900.00
Perlengkapan (35 % x harga pipa) 33,215.00
TENAGA
0.060 OH Tukang Pipa 135,000.00 8,100.00
0.006 OH Kepala Tukang Pipa 150,000.00 900.00
0.036 OH Pekerja 100,000.00 3,600.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 140,958.00
Keuntungan & Overhead 10 % 14,095.80
Jumlah ……………………… 155,053.80

SNI.294.G Memasang 1 m' Pipa GI dia 1/2"


BAHAN
1.000 m' Pipa GI dia 1/2" 23,300.00 23,300.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 57,772.58
Keuntungan & Overhead 10 % 5,777.26
Jumlah ……………………… 63,549.84

SNI.295.G Memasang 1 m' Pipa GI dia 3/4"


BAHAN
1.000 m' Pipa GI dia 1/2" 30,000.00 30,000.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 64,472.58
Keuntungan & Overhead 10 % 6,447.26
Jumlah ……………………… 70,919.84

SNI.296.G Memasang 1 m' Pipa GI dia 1"


BAHAN
1.000 m' Pipa GI dia 1" 46,000.00 46,000.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 80,472.58
Keuntungan & Overhead 10 % 8,047.26
Jumlah ……………………… 88,519.84

SNI.297.G Memasang 1 m' Pipa GI dia 1.5"


BAHAN
1.000 m' Pipa GI dia 1.5" 69,700.00 69,700.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 104,172.58
Keuntungan & Overhead 10 % 10,417.26
Jumlah ……………………… 114,589.84

SNI.298.Ga Memasang 1 m' Pipa GI dia 2"


BAHAN
1.000 m' Pipa GI dia 2" 95,200.00 95,200.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 129,672.58
Keuntungan & Overhead 10 % 12,967.26
Jumlah ……………………… 142,639.84
SNI.298.Ga1 Memasang 1 m' Pipa GI dia 2.5"
BAHAN
1.000 m' Pipa GI dia 2.5" 121,400.00 121,400.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 155,872.58
Keuntungan & Overhead 10 % 15,587.26
Jumlah ……………………… 171,459.84

SNI.298.Gb Memasang 1 m' Pipa GI dia 3"


BAHAN
1.000 m' Pipa GI dia 3" 156,600.00 156,600.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 191,072.58
Keuntungan & Overhead 10 % 19,107.26
Jumlah ……………………… 210,179.84

SNI.298.Gc Memasang 1 m' Pipa GI dia 4"


BAHAN
1.000 m' Pipa GI dia 4" 226,800.00 226,800.00
0.167 Bh Seel tipe 6,000.00 1,000.00
TENAGA
0.152 OH Tukang Pipa 135,000.00 20,504.25
0.015 OH Kepala Tukang Pipa 150,000.00 2,280.00
0.091 OH Pekerja 100,000.00 9,113.33
0.012 OH Mandor 135,000.00 1,575.00
Jumlah ( A + B + C ) 261,272.58
Keuntungan & Overhead 10 % 26,127.26
Jumlah ……………………… 287,399.84

PEKERJAAN LAIN - LAIN


SNI.299 1 M' Pagar BRC tinggi 1,20 m
1.000 M' Pagar BRC 118,000.00 118,000.00
2.000 OH Tukang Besi 135,000.00 270,000.00
0.200 OH Kepala Tukang Besi 150,000.00 30,000.00
0.067 OH Pekerja 100,000.00 6,670.00
0.003 OH Mandor 135,000.00 445.50
Jumlah ( A + B + C ) 425,115.50
Keuntungan & Overhead 10 % 42,511.55
Jumlah ……………………… 467,627.05

SNI.300 1 M2 Fabrikasi Besi


2.000 Kg Besi Siku 30,000.00 60,000.00
0.003 Unit Mesin Pemotong Besi 1,131,000.00 3,166.80
0.002 Buah Las Listrik 16,964,000.00 28,278.99
0.002 Unit Mesin Bor 1,131,000.00 2,601.30
0.080 Buah Mata Bor 56,000.00 4,480.00
15.000 KWh Listrik 1,500.00 22,500.00
1.500 OH Tukang Las 135,000.00 202,500.00
0.150 OH Kepala Tukang Las 150,000.00 22,500.00
2.000 OH Pekerja Terlatih 100,000.00 200,000.00
Jumlah ( A + B + C ) 546,027.09
Keuntungan & Overhead 10 % 54,602.71
Jumlah ……………………… 600,629.80

SNI.301.3 3 M3 Kawat Bronjong 3 mm


25.000 Kg Kawat Galvanis Tebal 3 mm 39,000.00 975,000.00
6.000 Bh Dolken/ Perancah 11,000.00 66,000.00
2.000 OH Penganyam 130,000.00 260,000.00
2.600 OH Pekerja Pengayam 100,000.00 260,000.00
0.080 OH Mandor Pengayam 135,000.00 10,800.00
3.000 M3 Batu Kali 226,000.00 678,000.00
4.500 OH Pekerja Pengisi 100,000.00 450,000.00
0.075 OH Mandor Pengisi 135,000.00 10,125.00
Jumlah ( A + B + C ) 2,709,925.00
Keuntungan & Overhead 10 % 270,992.50
Jumlah ……………………… 2,980,917.50

SNI.301.4 3 M3 Kawat Bronjong 4 mm


45.000 Kg Kawat Galvanis Tebal 4 mm 39,000.00 1,755,000.00
6.000 Bh Dolken/ Perancah 11,000.00 66,000.00
2.200 OH Penganyam 130,000.00 286,000.00
2.000 OH Pekerja Pengayam 100,000.00 200,000.00
0.080 OH Mandor Pengayam 135,000.00 10,800.00
3.000 M3 Batu Kali 226,000.00 678,000.00
4.500 OH Pekerja Pengisi 100,000.00 450,000.00
0.075 OH Mandor Pengisi 135,000.00 10,125.00
Jumlah ( A + B + C ) 3,455,925.00
Keuntungan & Overhead 10 % 345,592.50
Jumlah ……………………… 3,801,517.50

SNI.301.5 3 M3 Kawat Bronjong 5 mm


70.000 Kg Kawat Galvanis Tebal 5 mm 39,000.00 2,730,000.00
6.000 Bh Dolken/ Perancah 11,000.00 66,000.00
2.500 OH Penganyam 130,000.00 325,000.00
2.000 OH Pekerja Pengayam 100,000.00 200,000.00
0.080 OH Mandor Pengayam 135,000.00 10,800.00
3.000 M3 Batu Kali 226,000.00 678,000.00
4.500 OH Pekerja Pengisi 100,000.00 450,000.00
0.075 OH Mandor Pengisi 135,000.00 10,125.00
Jumlah ( A + B + C ) 4,469,925.00
Keuntungan & Overhead 10 % 446,992.50
Jumlah ……………………… 4,916,917.50

PEKERJAAN VEGETASI TANAMAN


SNI.302 1 bh Tanam Pohon Kamboja tinggi 5 meter
BAHAN
1.000 bh Tanam Pohon Kamboja tinggi 5 meter 1,875,000.00 1,875,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 kg Insektisida / Furadan 30,000.00 150.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.075 OH Kepala Tukang 150,000.00 11,250.00
0.100 OH Pekerja 100,000.00 10,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 1,928,875.00
Keuntungan & Overhead 10 % 192,887.50
Jumlah ……………………… 2,121,762.50

SNI.302.1 1 bh Tanam Pohon Tabebuya tinggi 4 meter


BAHAN
1.000 bh Tanam Pohon Tabebuya tinggi 4 meter 1,500,000.00 1,500,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 kg Insektisida / Furadan 30,000.00 150.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.075 OH Kepala Tukang 150,000.00 11,250.00
0.100 OH Pekerja 100,000.00 10,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 1,553,875.00
Keuntungan & Overhead 10 % 155,387.50
Jumlah ……………………… 1,709,262.50

SNI.302.2 1 bh Tanam Pohon Palem raja tinggi 3 meter


BAHAN
1.000 bh Tanam Pohon Palem raja tinggi 3 meter 1,250,000.00 1,250,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 kg Insektisida / Furadan 30,000.00 150.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.075 OH Kepala Tukang 150,000.00 11,250.00
0.100 OH Pekerja 100,000.00 10,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 1,303,875.00
Keuntungan & Overhead 10 % 130,387.50
Jumlah ……………………… 1,434,262.50

SNI.302.3 1 bh Tanam Pohon Pisang Kipas tinggi 1,5 meter


BAHAN
1.000 bh Tanam Pohon Pisang Kipas tinggi 1,5 met 125,000.00 125,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 kg Insektisida / Furadan 30,000.00 150.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.075 OH Kepala Tukang 150,000.00 11,250.00
0.100 OH Pekerja 100,000.00 10,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 178,875.00
Keuntungan & Overhead 10 % 17,887.50
Jumlah ……………………… 196,762.50

SNI.302.4 1 bh Tanam perdu Honje Merah tinggi 0,7 - 0,8 meter


BAHAN
1.000 bh Tanam perdu Honje Merah tinggi 0,7 - 0, 18,700.00 18,700.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
TENAGA
0.050 OH Tukang 135,000.00 6,750.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.050 OH Pekerja 100,000.00 5,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 51,675.00
Keuntungan & Overhead 10 % 5,167.50
Jumlah ……………………… 56,842.50

SNI.302.5 1 bh Tanam perdu Bakung Lele tinggi 0,25 - 0,3 meter


BAHAN
1.000 bh Tanam perdu Bakung Lele tinggi 0,25 - 0 21,800.00 21,800.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
TENAGA
0.050 OH Tukang 135,000.00 6,750.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.050 OH Pekerja 100,000.00 5,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 54,775.00
Keuntungan & Overhead 10 % 5,477.50
Jumlah ……………………… 60,252.50

SNI.302.6 1 bh Tanam perdu Pisang Hias tinggi 0,7 - 0,8 meter


BAHAN
1.000 bh Tanam perdu Pisang Hias tinggi 0,7 - 0,8 15,600.00 15,600.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
TENAGA
0.050 OH Tukang 135,000.00 6,750.00
0.015 OH Kepala Tukang 150,000.00 2,250.00
0.050 OH Pekerja 100,000.00 5,000.00
0.025 OH Mandor 135,000.00 3,375.00
Jumlah ( A + B + C ) 48,575.00
Keuntungan & Overhead 10 % 4,857.50
Jumlah ……………………… 53,432.50

SNI.302.a Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Damar (Agathis dammara) Tinggi 831,200.00 831,200.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 kg Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 843,726.00
Keuntungan & Overhead 10 % 84,372.60
Jumlah ……………………… 928,098.60

SNI.302.b Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Pulai (alstonia scholaris) Tinggi 6m 1,187,500.00 1,187,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,200,026.00
Keuntungan & Overhead 10 % 120,002.60
Jumlah ……………………… 1,320,028.60

SNI.302.c Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Kasia Jawa (Cassia javanica) Tingg 562,500.00 562,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 575,026.00
Keuntungan & Overhead 10 % 57,502.60
Jumlah ……………………… 632,528.60

SNI.302.d Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Kayu Kamper (Cinnamamum camph 875,000.00 875,000.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 887,526.00
Keuntungan & Overhead 10 % 88,752.60
Jumlah ……………………… 976,278.60

SNI.302.e Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Flamboyan (Delonix regia) Tinggi 1,187,500.00 1,187,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,200,026.00
Keuntungan & Overhead 10 % 120,002.60
Jumlah ……………………… 1,320,028.60

SNI.302.f Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Biola Cantik (Ficus lyrata) Tinggi 6 812,500.00 812,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 825,026.00
Keuntungan & Overhead 10 % 82,502.60
Jumlah ……………………… 907,528.60

SNI.302.g Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Beringin Bodi (Ficus religiosa) Ting 1,062,500.00 1,062,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,075,026.00
Keuntungan & Overhead 10 % 107,502.60
Jumlah ……………………… 1,182,528.60

SNI.302.h Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Sosis (Kigelia pinnata) Tinggi 7m 1,062,500.00 1,062,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,075,026.00
Keuntungan & Overhead 10 % 107,502.60
Jumlah ……………………… 1,182,528.60

SNI.302.i Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Bungur (Lagerstroemia speciasa) T 875,000.00 875,000.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 887,526.00
Keuntungan & Overhead 10 % 88,752.60
Jumlah ……………………… 976,278.60

SNI.302.j Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Flamboyan Kuning (Peltophorum p 543,700.00 543,700.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 556,226.00
Keuntungan & Overhead 10 % 55,622.60
Jumlah ……………………… 611,848.60

SNI.302.k Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Kamboja Putih (Plumeria obtusa) T 1,462,500.00 1,462,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,475,026.00
Keuntungan & Overhead 10 % 147,502.60
Jumlah ……………………… 1,622,528.60

SNI.302.l Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Parahiba (Schizolobium parahyba) 937,500.00 937,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 950,026.00
Keuntungan & Overhead 10 % 95,002.60
Jumlah ……………………… 1,045,028.60

SNI.302.m Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Tabebuya Pink (Tabebuia rosea) T 675,000.00 675,000.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 687,526.00
Keuntungan & Overhead 10 % 68,752.60
Jumlah ……………………… 756,278.60

SNI.302.n Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Bambu Kuning (Bambusa vulgaris) 187,500.00 187,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 200,026.00
Keuntungan & Overhead 10 % 20,002.60
Jumlah ……………………… 220,028.60

SNI.302.o Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Palem Kuning (Chrysalidacarpus lut 750,000.00 750,000.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 762,526.00
Keuntungan & Overhead 10 % 76,252.60
Jumlah ……………………… 838,778.60

SNI.302.p Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Pakis Monyet (Cibotium barometz) 106,200.00 106,200.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 118,726.00
Keuntungan & Overhead 10 % 11,872.60
Jumlah ……………………… 130,598.60

SNI.302.q Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Palem Kol (Licualis grandis) Tinggi 156,200.00 156,200.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 168,726.00
Keuntungan & Overhead 10 % 16,872.60
Jumlah ……………………… 185,598.60

SNI.302.r Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Palem Sadeng (Livistona rotundifol 1,875,000.00 1,875,000.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,887,526.00
Keuntungan & Overhead 10 % 188,752.60
Jumlah ……………………… 2,076,278.60

SNI.302.s Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Palem Kurma (Phoenix sylvestris) 1,750,000.00 1,750,000.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 1,762,526.00
Keuntungan & Overhead 10 % 176,252.60
Jumlah ……………………… 1,938,778.60

SNI.302.t Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Pisang Kipas (Ravenala madagascar 562,500.00 562,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 575,026.00
Keuntungan & Overhead 10 % 57,502.60
Jumlah ……………………… 632,528.60

SNI.302.u Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm


BAHAN
1.000 bh Pohon Pisang Hias (Strelitzia nicolai) Ting 562,500.00 562,500.00
0.080 kg Pupuk kandang 31,200.00 2,496.00
0.001 ls Insektisida / Furadan 30,000.00 30.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 10,000.00 10,000.00
Jumlah ( A + B + C ) 575,026.00
Keuntungan & Overhead 10 % 57,502.60
Jumlah ……………………… 632,528.60

SNI.302.1a Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Agave (Agave angustifolia) Tingg 100,000.00 1,000,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 1,030,750.00
Keuntungan & Overhead 10 % 103,075.00
Jumlah ……………………… 1,133,825.00

SNI.302.1b Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Paku Sarang Burung (Asplenium n 62,500.00 625,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 655,750.00
Keuntungan & Overhead 10 % 65,575.00
Jumlah ……………………… 721,325.00

SNI.302.1c Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Fox Tail Agave (Agave attenuata) 52,500.00 525,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 555,750.00
Keuntungan & Overhead 10 % 55,575.00
Jumlah ……………………… 611,325.00
SNI.302.1d Tanam semak , lubang polibag 15 x 15 cm
BAHAN
10.000 bh Semak Giant Arum (Typhonodarum lindle 312,500.00 3,125,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 3,155,750.00
Keuntungan & Overhead 10 % 315,575.00
Jumlah ……………………… 3,471,325.00

SNI.302.1e Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Spineless (Spineless Yucca) Tingg 168,700.00 1,687,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 1,717,750.00
Keuntungan & Overhead 10 % 171,775.00
Jumlah ……………………… 1,889,525.00

SNI.302.1f Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Sente (Alocosia macrorrhiza) Tin 93,700.00 937,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 967,750.00
Keuntungan & Overhead 10 % 96,775.00
Jumlah ……………………… 1,064,525.00

SNI.302.1g Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Honje Merah (Alpinia purpurata) 18,700.00 187,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 217,750.00
Keuntungan & Overhead 10 % 21,775.00
Jumlah ……………………… 239,525.00

SNI.302.1h Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Kacang Emas (Arachis pintai) Tin 21,200.00 212,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 242,750.00
Keuntungan & Overhead 10 % 24,275.00
Jumlah ……………………… 267,025.00

SNI.302.1i Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Bromelia Merah (Bromelia sp.) Ti 43,700.00 437,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 467,750.00
Keuntungan & Overhead 10 % 46,775.00
Jumlah ……………………… 514,525.00

SNI.302.1j Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Pisang Hias (Calathea lutea) Ting 43,700.00 437,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 467,750.00
Keuntungan & Overhead 10 % 46,775.00
Jumlah ……………………… 514,525.00

SNI.302.1k Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Kalatea Belang (Calathea zebrina) 18,700.00 187,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 217,750.00
Keuntungan & Overhead 10 % 21,775.00
Jumlah ……………………… 239,525.00

SNI.302.1l Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Bunga Pagoda (Cleorodendrum pan 87,500.00 875,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 905,750.00
Keuntungan & Overhead 10 % 90,575.00
Jumlah ……………………… 996,325.00

SNI.302.1m Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak hanjuang Merah (Cordyline frustic 18,700.00 187,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 217,750.00
Keuntungan & Overhead 10 % 21,775.00
Jumlah ……………………… 239,525.00

SNI.302.1n Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Pacing Merah (Costus woodsonii) 12,500.00 125,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 155,750.00
Keuntungan & Overhead 10 % 15,575.00
Jumlah ……………………… 171,325.00

SNI.302.1o Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Sirih Gading (Epipremnum aureum 72,500.00 725,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 755,750.00
Keuntungan & Overhead 10 % 75,575.00
Jumlah ……………………… 831,325.00

SNI.302.1p Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Heliconia Bunga Pink (Heliconia c 9,300.00 93,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 123,750.00
Keuntungan & Overhead 10 % 12,375.00
Jumlah ……………………… 136,125.00

SNI.302.1q Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Bakung Lele (Hymenocallis littoral 12,500.00 125,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 155,750.00
Keuntungan & Overhead 10 % 15,575.00
Jumlah ……………………… 171,325.00

SNI.302.1r Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Pakis Kelabang (Nephrolepis exalt 25,000.00 250,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 280,750.00
Keuntungan & Overhead 10 % 28,075.00
Jumlah ……………………… 308,825.00

SNI.302.1s Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Alang Mini (Ophiopogon japonicus 18,700.00 187,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 217,750.00
Keuntungan & Overhead 10 % 21,775.00
Jumlah ……………………… 239,525.00

SNI.302.1t Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Aralia (Osmoxylon lineare) Tingg 9,300.00 93,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 123,750.00
Keuntungan & Overhead 10 % 12,375.00
Jumlah ……………………… 136,125.00
SNI.302.1v Tanam semak , lubang polibag 15 x 15 cm
BAHAN
10.000 bh Semak Pandan Pigmi (Pandanus pygmaeu 25,000.00 250,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 280,750.00
Keuntungan & Overhead 10 % 28,075.00
Jumlah ……………………… 308,825.00

SNI.302.1x Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Daun Philo "Burle Marx" (Philaden 31,200.00 312,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 342,750.00
Keuntungan & Overhead 10 % 34,275.00
Jumlah ……………………… 377,025.00

SNI.302.1y Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Daun Philo Besar (Philadendron s 37,500.00 375,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 405,750.00
Keuntungan & Overhead 10 % 40,575.00
Jumlah ……………………… 446,325.00

SNI.302.1z Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Daun Philo Xenadu (Philadendron 46,200.00 462,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 492,750.00
Keuntungan & Overhead 10 % 49,275.00
Jumlah ……………………… 542,025.00

SNI.302.2a Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Cendrawasih (Phyllanthus myrtifol 11,200.00 112,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 142,750.00
Keuntungan & Overhead 10 % 14,275.00
Jumlah ……………………… 157,025.00

SNI.302.2b Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Melati Jepang (Pseuderanthemum 10,600.00 106,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 136,750.00
Keuntungan & Overhead 10 % 13,675.00
Jumlah ……………………… 150,425.00

SNI.302.2c Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak kembang Air Mancur Merah (Russel 27,500.00 275,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 305,750.00
Keuntungan & Overhead 10 % 30,575.00
Jumlah ……………………… 336,325.00

SNI.302.2d Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Wali Songo Var. (Schefflera arbar 43,700.00 437,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 467,750.00
Keuntungan & Overhead 10 % 46,775.00
Jumlah ……………………… 514,525.00

SNI.302.2e Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Lee Kuan Yew (Vernonia elliptica) 8,100.00 81,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 111,750.00
Keuntungan & Overhead 10 % 11,175.00
Jumlah ……………………… 122,925.00

SNI.302.2f Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Lili Brazil (Dianella tasmanica) Tin 12,500.00 125,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 155,750.00
Keuntungan & Overhead 10 % 15,575.00
Jumlah ……………………… 171,325.00

SNI.302.2g Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Opiopagon Hijau (Ophiopagon jab 18,700.00 187,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 217,750.00
Keuntungan & Overhead 10 % 21,775.00
Jumlah ……………………… 239,525.00

SNI.302.2h Tanam semak , lubang polibag 15 x 15 cm


BAHAN
10.000 bh Semak Kembang Coklat (Zephyranthes can 25,000.00 250,000.00
0.500 kg Pupuk kandang 31,200.00 15,600.00
0.005 ls Insektisida / Furadan 30,000.00 150.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 15,000.00 15,000.00
Jumlah ( A + B + C ) 280,750.00
Keuntungan & Overhead 10 % 28,075.00
Jumlah ……………………… 308,825.00

SNI.302.3a Tanam rumput


BAHAN
1.000 m2 Semak Rumput Manila (Zoysia matrella) 62,500.00 62,500.00
0.750 kg Pupuk kandang 31,200.00 23,400.00
TENAGA
1.000 ls Upah tanam vegetasi pohon 5,000.00 5,000.00
Jumlah ( A + B + C ) 90,900.00
Keuntungan & Overhead 10 % 9,090.00
Jumlah ……………………… 99,990.00

PEKERJAAN TAMBAHAN
SNI.Ls.1 1 M' Biaya Pengeboran air + Pipa Casing Ø 6''
1.000 m' Biaya Pengeboran air 1,074,000.00 1,074,000.00
1.000 m' Pipa PVC dia 6" 197,900.00 197,900.00
Perlengkapan (35 % x harga pipa) 69,265.00
1.000 Ls Biaya pemasangan sebesar 15% dari 29,685.00 29,685.00
harga material

Jumlah ( A + B + C ) 1,370,850.00
Keuntungan & Overhead 10 % 137,085.00
Jumlah ……………………… 1,507,935.00

SNI.Ls.2 1 M' Biaya Pengeboran air + Pipa Casing Ø 4''


1.000 m Biaya Pengeboran air 848,000.00 848,000.00
1.000 m' Pipa PVC dia 4" 94,900.00 94,900.00
Perlengkapan (35 % x harga pipa) 33,215.00
1.000 Ls Biaya pemasangan sebesar 15% dari 14,235.00 14,235.00
harga material

Jumlah ( A + B + C ) 990,350.00
Keuntungan & Overhead 10 % 99,035.00
Jumlah ……………………… 1,089,385.00

SNI.Ls.3 1 M' Biaya Pengeboran air + Pipa Casing Ø 3''


1.000 m Biaya Pengeboran air 395,000.00 395,000.00
1.000 m' Pipa PVC dia 3" 65,100.00 65,100.00
Perlengkapan (35 % x harga pipa) 22,785.00
1.000 Ls Biaya pemasangan sebesar 15% dari 9,765.00 9,765.00
harga material

Jumlah ( A + B + C ) 492,650.00
Keuntungan & Overhead 10 % 49,265.00
Jumlah ……………………… 541,915.00

SNI.Ls.4 1 M' Biaya Pengeboran air + Pipa Casing Ø 2.5''


1.000 m Biaya Pengeboran air 198,000.00 198,000.00
1.000 m' Pipa PVC dia 2.5" 45,600.00 45,600.00
Perlengkapan (35 % x harga pipa) 15,960.00
1.000 Ls Biaya pemasangan sebesar 15% dari 6,840.00 6,840.00
harga material

Jumlah ( A + B + C ) 266,400.00
Keuntungan & Overhead 10 % 26,640.00
Jumlah ……………………… 293,040.00

SNI.Ls.5 1 Bh' Mesin tenaga disel YEP-3 + Pompa Ebra Ø Q3'' ( setara Yanmar )
1.000 zet Mesin tenaga disel 6.5 Pk YEP-3 + 28,782,000.00 28,782,000.00
Pompa Ebra Ø Q3'' ( setara Yanmar )

1.000 Ls Biaya Asisories dan Perakitan 20% dari 5,756,400.00 5,756,400.00


harga bahan
Jumlah ( A + B + C ) 34,538,400.00
Keuntungan & Overhead 10 % 3,453,840.00
Jumlah ……………………… 37,992,240.00

SNI.Ls.6 1 Bh' Pompa Submersible type Centrifugal kapasitas 3 Ltr/Dtk, H 100, 3 Phase
1.000 zet Pompa Submersible type Centrifugal 44,557,000.00 44,557,000.00
kapasitas 3 Ltr/Dtk, H 100, 3 Phase

Jumlah ( A + B + C ) 44,557,000.00
Keuntungan & Overhead 10 % 4,455,700.00
Jumlah ……………………… 49,012,700.00

SNI.Ls.7 1 Bh' Mesin tenaga Listerik disel + Pompa Outo matis Jet pam - 30 Complit pemasangan
1.000 zet Mesin disel+Pompa Outo matis Jet pam 25,904,000.00 25,904,000.00
ØINT OUT1.5'' - 30 Complit

Jumlah ( A + B + C ) 25,904,000.00
Keuntungan & Overhead 10 % 2,590,400.00
Jumlah ……………………… 28,494,400.00

SNI.Ls.8 1 Bh' Mesin tenaga disel + Pompa Outo matis ( setara sanyo ) ØINT 1''- 25 Complit pemasangan
1.000 zet Mesin disel+Pompa Outo matis ( setara 23,313,000.00 23,313,000.00
sanyo ) ØINT 1''- 20 Complit

Jumlah ( A + B + C ) 23,313,000.00
Keuntungan & Overhead 10 % 2,331,300.00
Jumlah ……………………… 25,644,300.00
REKAP ANALISA
NO URAIAN PEKERJAAN HARGA SATUAN
PEKERJAAN PERSIAPAN
SNI.1 1 M2 Pembersihan Lapangan dan perataan 18,425.000
SNI.2 1 M Pengukuran dan Pemasangan Bouwplank 83,308.500
SNI.3 1 Bh Pembuatan Papan nama Proyek 0,8 x 1,2 cm 238,425.000
SNI.4a 1 m2 Pagar Pengaman Lokasi Dari seng gelombang tinggi 2m 408,244.100
SNI.4b 1 m2 Pagar Pengaman Lokasi Dari seng gelombang tinggi 2m 377,085.500
SNI.5 1 m2 . Pembuatan Direksiket/Kantor sementara 1,005,642.000

PEKERJAAN PEMBONGKARAN BANGUNAN LAMA


SNI.6 1 M2 Pembongkaran Dinding Tembok Bata Merah Lama 416,187.475
SNI.7 1 M3 Pembongkaran Beton Bertulang Lama 832,374.950
SNI.8 1 m2 Bongkar Usuk + Reng Untuk Dipakai Kembali 30,992.500
SNI.9 1 M2 Pembongkaran Atap Seng Gelombang 12,039.500

PEKERJAAN TANAH DAN PASIR


SNI.10.a 1 M3 Galian Tanah Biasa sedalam 0.5 - 1 M' - Dengan manual 86,212.500
SNI.10.b 1 M3 Galian Tanah Biasa sedalam 0.5 - 1 M' - Dengan mengunakan alat berat 93,670.500
SNI.11.a 1 M3 Galian Tanah Biasa sedalam 2 M', Dengan Manual 105,682.500
SNI.11.b 1 M3 Galian Tanah Biasa sedalam 2 M' - Dengan mengunakan alat berat 113,140.500
SNI.12 1 M3 Galian Tanah Biasa sedalam 3 M' 125,449.500
SNI.13 1 M3 Galian Tanah Keras sedalam 1 M' 114,752.000
SNI.14 1 M3 Galian Tanah Cadas sedalam 1 M' 173,910.000
SNI.15 1 M3 Galian Tanah Lumpur sedalam 1 M' 138,682.500
SNI.16 1 M2 Pekerjaan Stripping tanah Tebing setinggi 1 M' 6,242.500
SNI.17 1 M3 Urugan Kembali Tanah galian 31,212.500
SNI.18 1 M3 Pemadatan Tanah Per 20 cm 62,425.000
SNI.19 1 M3 Urugan Tanah (dipadatkan) 222,145.000
SNI.20 1 M3 Urugan Tanah Biasa tampa pemadatan 190,932.500
SNI.21 1 M3 Urug dengan pasir urug 285,285.000
SNI.22 1 M3 Urugan Sirtu/ Material Pilihan padat 344,052.500

PEKERJAAN PASANGAN, PLESTERAN DAN LANTAI


SNI.23 1 M3 Pasangan Batu Kosong ( anstamping ) 544,549.500
SNI.24 1 M3 Pasangan Batu Kali 1 Pc : 4 Psr 1,022,587.500
SNI.25.a 1 M3 Pasangan Batu Kali 1 Pc : 5 Psr 977,905.500
SNI.25.b 1 M3 Pasangan Batu Kali 1 Pc : 6 Psr 946,489.500
SNI.26 1 M3 Pasangan Pondasi Sumuran Ø100 cm 1,306,233.500
SNI.27 1 M2 Pasangan Dinding bata berongga / roster (10 x 20) 555,901.500
SNI.28 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 3 PP 161,429.400
SNI.29.a 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 4 PP 156,788.500
SNI.29.b 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 5 PP 153,869.100
SNI.29.c 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 6 PP 152,293.900
SNI.29.d 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 8 PP 149,132.500
SNI.29.R Pemasangan 1 m2 dinding bata ringan tebal 10 X 20 X 60 cm + dengan mortar 465,873.100
SNI.30 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1 bata, spesi 1 PC : 3 PP 333,393.500
SNI.31 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1 bata, spesi 1 PC : 4 PP 321,909.500
SNI.32 1 M2 Pasangan Dinding Batako 1 Pc : 4 Psr 114,097.500
SNI.33 1 M2 Pasangan Rollag 1 Bata Merah 1 Pc : 3 Ps 234,579.400
SNI.34.a 1 M2 Acian halus dengan Pc 46,062.500
SNI.34.b 1 M2 Plesteran + Acian halus dinding bata ringan/Hebel 149,935.500
SNI.34.c 1 M2 Plesteran dinding bata ringan/Hebel 92,075.500
SNI.34.d 1 M2 Plesteran Beton 1 PC : 2 Ps Tebal 15 mm 85,277.500
SNI.34.e 1 M2 Plesteran Beton 1 PC : 3 Ps Tebal 15 mm 81,833.400
SNI.35.a 1 M2 Siar Pas batu Kali 74,737.300
SNI.35.b 1 m2 Finishing Siar pasangan bata merah 35,957.460
SNI.36 1 m2 Plesteran 1 Pc : 3 Pp tebal 15 mm 80,054.700
SNI.37.a 1 m2 Plesteran 1 Pc : 4 Pp tebal 15 mm 77,454.300
SNI.37.b 1 m2 Plesteran 1 Pc : 5 Pp tebal 15 mm 75,963.580
SNI.37.c 1 m2 Plesteran 1 Pc : 6 Pp tebal 15 mm 74,769.420
SNI.37.d 1 m2 Plesteran 1 Pc : 7 Pp tebal 15 mm 74,113.820
SNI.37.e 1 m2 Plesteran 1 Pc : 8 Pp tebal 15 mm 73,458.220
SNI.38 1 m2 Plesteran 1 Pc : 3 Pp tebal 20 mm 90,420.660
SNI.39 1 m2 Plesteran 1 Pc : 4 Pp tebal 20 mm 102,548.600
SNI.40.a 1 m2 Plesteran Ciprat 1 Pc : 2 Pp 61,257.900
SNI.40.b 1 m1 Plesteran Skoning / Benangan 1 Pc : 3 Pp, lebar 10 cm 79,475.000
SNI.41 Pasang Kanstin Cetak 600x150x250 194,269.167
SNI.41.1 Lapisan Geotextile 292,187.500
SNI.41.2 Lapisan Drainagecell 779,625.000
SNI.41.3 Memasang Kitchen Sink 1 Bowl GS 5844 2,528,022.750
SNI.41.4 Memasang Kitchen Sink Single Bowl Zenit Ris 1B 1D 86 with Kitchen Tap My 1 By TEKA 5,071,772.750
SNI.41.5 Memasang Mirror 100x120 cm 350,022.750
SNI.42.a 1 m1 Pasang Buis beton Ø20 cm, spesi 1 PC : 4 PP 213,372.500
SNI.42.b 1 m1 Pasang Buis beton Ø 30 cm, spesi 1 PC : 4 PP 246,372.500
SNI.42.c 1 m1 Pasang Buis beton Ø 40 cm, spesi 1 PC : 4 PP 290,372.500
SNI.43 1 m1 Pasang Buis beton Ø 50 cm, spesi 1 PC : 4 PP 336,710.000
SNI.44 1 m1 Pasang Buis beton Ø 60 cm, spesi 1 PC : 4 PP 347,710.000
SNI.45 1 m1 Pasang Buis beton Ø 80 cm, spesi 1 PC : 4 PP 391,710.000
SNI.46 1 M2 Pas. Lantai Tegel Abu-abu 124,458.400
SNI.47.a 1 M2 Pas. Lantai Granite Kw I 578,224.900
SNI.47.b 1 M2 Pas. Lantai Granite Kw II 501,224.900
SNI.48 1 M2 Pasangan Lantai Keramik ( KW I Polos ) 304,711.000
SNI.49 1 M2 Pasangan Lantai Keramik ( KW II Polos ) 288,541.000
SNI.50 1 M2 Pasangan Lantai Keramik ( KW I Motif ) 348,601.000
SNI.51 1 M2 Pasangan Lantai Keramik ( KW II Motif ) 323,917.000
SNI.52 1 M2 Pasangan Lantai Marmer 555,288.800
SNI.52.a 1 M2 Pasangan Lantai Keramik Anti Slip 323,917.000
SNI.53 1 M2 Pasangan dinding keramik ( Kw I Motif ) 389,614.500
SNI.54 1 M2 Pas. Dinding Keramik ( Kw II Motf ) 360,739.500
SNI.55 1 M2 Pas. Dinding Keramik ( Kw I polos ) 373,444.500
SNI.56 1 M2 Pas. Dinding Keramik ( Kw II Polos ) 248,072.000
SNI.57.a 1 M2 Pas. Lantai Keramik Cating Motif 344,597.000
SNI.57.b 1 M2 Pas. Lantai Coral Sikat 170,192.000
SNI.57.c 1 M2 Pas. Lantai Coral Sikat, Warna 177,122.000
SNI.58 1 M2 Pas. Dinding batu paras/Palimanan 451,055.000
SNI.59 1 M2 Pas. Dinding batu tempel hitam bergaris 484,990.000
SNI.60.B 1 M2 Pas. Paving Blok bata . T 8 cm 226,573.050
SNI.60.P 1 M2 Pas. Paving Blok bata . T 8 cm, Press 321,008.050
SNI.61 1 M2 Pas. Paving Blok bata . T 6 cm 209,908.050
SNI.62 1 M2 Pas. Paving Blok persegi/berlian 357,448.850
SNI.62.1 1 m2 Memasang ornamen terawang custom bahan GRC 1,266,705.000
SNI.62.2 1 m2 Memasang acian motif tali air 46,062.500
SNI.62.3 1 m Memasang plint ukuran (60 x 10x 4 ) cm 181,844.300
SNI.62.4 1 m Memasang stepnose tangga ukuran (10 x 40) cm 116,562.050
SNI.62.5 1 m2 Memasang lantai karpet 140,761.500
SNI.62.6 1 m2 Memasang lantai vinyl ukuran (30 x 30) cm KL I 281,045.600
SNI.62.7 1 m2 Memasang lantai parquete ukuran (30 x 30) cm KL I 405,087.100
SNI.62.W 1 m2 Pasang conblock tipe segi-empat warna 8 cm, K-300 251,542.500
SNI.62.A 1 m2 Pasang conblock tipe segi-empat abu-abu 8 cm, K-300 245,382.500
SNI.62.7 1 m Pasang kansten beton 196,475.400
SNI.62.8 1 m2 Pasang grassblocksegi 8 tebal 8 cm 264,412.500

PEKERJAAN KONSTRUKSI BETON


SNI.63.a 1 M3 Membuat Beton Dengan Mutu K-300 2,192,982.000
SNI.64.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 130 Kg Besi + Bekisting) M-K300 5,407,710.000
SNI.65.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K300 5,865,398.000
SNI.66.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K300 6,112,073.000
SNI.67.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K300 6,684,183.000
SNI.68.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K300 7,828,403.000
SNI.69.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-300 8,239,027.500
SNI.70.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-300 9,383,247.500
SNI.71.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-300 10,527,467.500
SNI.72.a 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-300 7,553,397.500
SNI.73.a 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-300 8,125,507.500
SNI.74.a 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-300 9,269,727.500
SNI.75.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-300 7,501,477.500
SNI.76.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-300 8,073,587.500

SNI.63.b 1 M3 Membuat Beton Dengan Mutu K-275 2,185,089.500


SNI.64.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 130 Kg Besi + Bekisting) M-K275 5,399,817.500
SNI.65.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K275 5,857,505.500
SNI.66.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K275 6,104,180.500
SNI.67.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K275 6,676,290.500
SNI.68.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K275 7,820,510.500
SNI.69.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-275 8,231,135.000
SNI.70.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-275 9,375,355.000
SNI.71.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-275 10,519,575.000
SNI.72.b 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-275 7,545,505.000
SNI.73.b 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-275 8,117,615.000
SNI.74.b 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-275 9,261,835.000
SNI.75.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-275 7,493,585.000
SNI.76.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-275 8,065,695.000

SNI.77.a 1 M3 Membuat Beton Dengan Mutu K-250 2,157,540.000


SNI.78.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 130 Kg Besi + Bekisting) M-K250 5,372,268.000
SNI.79.a 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K250 5,829,956.000
SNI.80.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K250 6,076,631.000
SNI.81.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K250 6,648,741.000
SNI.82.a 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K250 7,792,961.000
SNI.83.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-250 8,203,585.500
SNI.84.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-250 9,347,805.500
SNI.85.a 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-250 10,492,025.500
SNI.86.a 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-250 7,517,955.500
SNI.87.a 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-250 8,090,065.500
SNI.88.a 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-250 9,234,285.500
SNI.89.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-250 7,466,035.500
SNI.90.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-250 8,038,145.500

SNI.77.b 1 M3 Membuat Beton Dengan Mutu K-225 2,142,008.000


SNI.78.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K225 5,242,314.000
SNI.79.b 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K225 5,814,424.000
SNI.80.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K225 6,061,099.000
SNI.81.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K225 6,633,209.000
SNI.82.b 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K225 7,777,429.000
SNI.83.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-225 8,188,053.500
SNI.84.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-225 9,332,273.500
SNI.85.b 1 M3 Pekerjaan Kolom Beton Bertulang ( 250 Kg Besi + Bekisting) M-K-225 10,476,493.500
SNI.86.b 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-225 7,502,423.500
SNI.87.b 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-225 8,074,533.500
SNI.88.b 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-225 9,218,753.500
SNI.89.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-225 7,450,503.500
SNI.90.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-225 8,022,613.500

SNI.91 1 M3 Membuat Beton Dengan Mutu K-200 2,106,247.000


SNI.92 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K200 4,794,053.000
SNI.93 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M-K200 5,283,663.000
SNI.94 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K200 5,612,838.000
SNI.95 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K200 6,102,448.000
SNI.96 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K200 7,081,668.000
SNI.97 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-200 7,167,682.500
SNI.98 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K-200 7,657,292.500
SNI.99 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K-200 8,636,512.500
SNI.100 1 M3 Pekerjaan Balok Beton Bertulang ( 120 Kg Besi + Bekisting) M-K-200 6,956,240.500
SNI.101 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K-200 7,054,162.500
SNI.102 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 200 8,522,992.500
SNI.103 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 200 6,904,320.500
SNI.104 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 200 7,491,852.500

SNI.105 1 M3 Membuat Beton Dengan Mutu K- 175 2,067,175.000


SNI.106 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 175 4,754,981.000
SNI.107 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M- K 175 5,244,591.000
SNI.108 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 175 5,573,766.000
SNI.109 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 175 6,063,376.000
SNI.110 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K 175 7,042,596.000
SNI.111 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 175 7,128,610.500
SNI.112 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175 7,618,220.500
SNI.113 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 175 8,597,440.500
SNI.114 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 175 7,015,090.500
SNI.115 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175 7,504,700.500
SNI.116 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 175 8,483,920.500
SNI.117 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 175 6,865,248.500
SNI.118 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175 7,452,780.500

SNI.119 1 M3 Membuat Beton Dengan Mutu K- 150 2,021,998.000


SNI.120 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 150 4,709,804.000
SNI.121 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) M- K 150 5,199,414.000
SNI.122 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 150 5,528,589.000
SNI.123 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 150 6,018,199.000
SNI.124 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K 150 6,997,419.000
SNI.125 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 150 6,946,813.500
SNI.126 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150 7,409,099.500
SNI.127 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 150 8,333,671.500
SNI.128 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 150 6,833,293.500
SNI.129 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150 7,295,579.500
SNI.130 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 150 8,220,151.500
SNI.131 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 150 6,688,916.300
SNI.132 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150 7,243,659.500

SNI.133 1 M3 Membuat Beton Dengan Mutu K- 125 1,632,273.500


SNI.134 1 M3 Pekerjaan Pondasi Beton Bertulang ( 110 Kg Besi + Bekisting) M-K 125 4,026,313.500
SNI.135 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M- K 125 4,320,079.500
SNI.136 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 125 5,138,864.500
SNI.137 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 125 5,628,474.500
SNI.138 1 M3 Pekerjaan Sloof Beton Bertulang ( 175 Kg Besi + Bekisting) M-K 125 6,118,084.500
SNI.139 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 125 6,693,709.000
SNI.140 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 125 7,183,319.000
SNI.141 1 M3 Pekerjaan Kolom Beton Bertulang ( 175 Kg Besi + Bekisting) M-K- 125 7,672,929.000
SNI.142 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 125 6,580,189.000
SNI.143 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 125 7,069,799.000
SNI.144 1 M3 Pekerjaan Balok Beton Bertulang ( 175 Kg Besi + Bekisting) M-K- 125 7,559,409.000
SNI.145 1 M3 Pekerjaan Lantai Beton Bertulang ( 110 Kg Besi + Bekisting) M-K- 125 6,234,503.000
SNI.146 1 M3 Pekerjaan Lantai Beton Bertulang ( 130 Kg Besi + Bekisting) M-K- 125 6,626,191.000

SNI.147 1 M3 Pekerjaan Dinding Beton Bertulang ( 150 Kg Besi + Bekisting) M - K 225 7,901,613.500
SNI.148 1 M3 Pekerjaan Tangga Beton Bertulang ( 175 Kg Besi + Bekisting) M - K - 225 8,646,643.500
SNI.149 1 M3 Pekerjaan Tangga Beton Bertulang ( 150 Kg Besi + Bekisting) M - K - 225 8,074,533.500
SNI.150 1 M3 Pekerjaan Tangga Beton Bertulang ( 130 Kg Besi + Bekisting) M - K - 225 7,616,845.500

SNI.151 1 M2 Lantai Kerja Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr (Tebal = 5 Cm) 323,422.000


SNI.152 1 M3 Beton Tumbuk, 1 Pc : 3 Ps : 5 Kr 1,467,963.200
SNI.153 1 M3 Beton Tumbuk, 1 Pc : 2 Ps : 3 Kr 1,493,893.500
SNI.154 1 M3 Pekerjaan Pondasi Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 5,106,634.500
SNI.154.a 1 M2 Pekerjaan Bekisting Pondasi 229,581.000
SNI.155 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,332,639.500
SNI.155.a 1 M2 Pekerjaan Bekisting Sloof 243,881.000
SNI.156 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 5,353,419.500
SNI.157 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 4,863,809.500
SNI.158 1 M3 Pekerjaan Sloof Beton Bertulang ( 120 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 4,765,887.500
SNI.159 1 M3 Pekerjaan Sloof Beton Bertulang ( 100 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 4,374,199.500
SNI.160 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 7,887,484.000
SNI.160.a 1 M2 Pekerjaan Bekisting Kolom 407,720.500
SNI.161 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,908,264.000
SNI.162 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,418,654.000
SNI.163 1 M3 Pekerjaan Lantai Beton Bertulang ( 175 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 7,232,434.000
SNI.163.a 1 M2 Pekerjaan Bekisting Lantai 456,120.500
SNI.164 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,742,824.000
SNI.164.a2lp 1 M3 Pekerjaan Lantai Beton Bertulang ( 100 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 3,529,284.000
SNI.164.b1lp 1 M3 Pekerjaan Lantai Beton Bertulang ( 100 Kg Besi ) BT, 1 Pc : 2 Ps : 3 Kr 3,603,072.000
SNI.164.c1lp 1 M3 Pekerjaan Lantai Beton Bertulang ( 75 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 3,026,067.000
SNI.164.1lp.a 1 M3 Pekerjaan Lantai Beton Bertulang ( 100 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 4,864,766.500
SNI.164.1lp.b 1 M3 Pekerjaan Lantai Beton Bertulang ( 75 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 4,375,156.500
SNI.165 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 7,773,964.000
SNI.165.a 1 M2 Pekerjaan Bekisting Balok 419,732.500
SNI.166 1 M3 Pekerjaan Balok Beton Bertulang (175 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 7,284,354.000
SNI.167 1 M3 Pekerjaan Balok Beton Bertulang (150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,794,744.000
SNI.168 1 M3 Pekerjaan Balok Beton Bertulang (125 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,305,134.000
SNI.169 1 M3 Pekerjaan Balok Beton Bertulang (110 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,011,368.000
SNI.170 1 M3 Pek Dinding Plat Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 6,621,824.000
SNI.170.a 1 M2 Pek Bekisting Dinding Plat 411,240.500
SNI.171 1 M3 Pek Tangga Beton Bertulang ( 175 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr 7,284,354.000
SNI.171.a 1 M2 Pek Bekisting Tangga 378,130.500
SNI.172 1 M' Pekerjaan Kolom Penguat Beton Bertulang ( 11 x 11 cm ) 137,423.000
SNI.173 1 M' Pekerjaan Ring Balok Beton Bertulang ( 10 x 15 cm ) 164,532.500
SNI.173.1 1 Kg Pembesian dengan Besi Polos 21,008.900
SNI.173.2 1 Kg Pembesian dengan Besi Ulir 24,473.900
SNI.173.3a Memasang 1 M2 Jaring Kawat Baja / Wiremesh 6 mm 49,148.000
SNI.173.3b Memasang 1 M2 Jaring Kawat Baja / Wiremesh 8 mm 81,686.000
SNI.173.3c Memasang 1 M2 Jaring Kawat Baja / Wiremesh 10 mm 125,444.000
SNI.173.4a Memasang 1 M Plat lantai sistem Bondex 0.65 mm 323,367.000
SNI.173.4b Memasang 1 M Plat lantai sistem Bondex 0.70 mm 335,830.000
SNI.173.4c Memasang 1 M Plat lantai sistem Bondex 0.75 mm 339,229.000
SNI.173.4d Memasang 1 M Plat lantai sistem Bondex 0.100 mm 431,002.000

PEKERJAAN KAYU
SNI.174 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3 80,910.500
SNI.174.a 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3 ( Expose ) 103,281.750
SNI.175 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 3/4 88,918.500
SNI.175.a 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 3/4 ( Expose ) 111,289.750
SNI.176.a 1 M2 Mengerjakan / Memasang Usuk 5/7 cm 62,242.950
SNI.176.b 1 M2 Mengerjakan / Memasang Kembali Usuk 5/7 cm 23,003.750
SNI.176.c 1 M2 Mengerjakan / Memasang Reng 3/4 cm 26,675.550
SNI.176.d 1 M2 Mengerjakan / Memasang Kembali Usuk 5/7 cm 9,858.750
SNI.177 1 M' Pekerjaan Papan Lisplank Satu Lapis, Kisi-Kisi 3/20 Kayu Klas II 76,649.100
SNI.178 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 3/20 ) Kayu Klas II 130,229.000
SNI.179 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II 89,075.800
SNI.179.a 1 M' Memasang Kembali Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II 52,250.000
SNI.180 1 M' Pekerjaan Papan Reuter (2/20) 53,748.200
SNI.181 1 M' Mengerjakan Talang Karet 238,672.500
SNI.182.a 1 M' Mengerjakan Talang datar/ jurai Seng BjLs 20 219,037.500
SNI.182.b 1 M' Mengerjakan Talang 1/2 lingkaran Seng BjLs 20 171,820.000
SNI.183 1 M3 Pekerjaan Kayu Kuda - Kuda, Gording Kayu Klas II 6,527,620.000
SNI.184 1 M3 Pekerjaan Kayu Kuda - Kuda, Gording Kayu Klas II (Expose) 8,004,590.000
SNI.185 1 M3 Pekerjaan Kayu Konsol, Tiang Kayu Klas II 7,556,890.000
SNI.186 1 M' Pasang Kasiplank ukuran (0.8x20), 1 Lapis 70,482.500
SNI.187 1 M' Pasang Kasiplank ukuran (0.8x20), 2 Lapis 105,723.750
SNI.188 1 M3 Pekerjaan Kayu Konsol, Tiang Kayu Klas II (Expose) 7,861,590.000
SNI.189 1 M3 Pekerjaan Kayu Kusen Pintu dan Jendela 8,605,850.000
SNI.190 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca 3 mm 664,136.000
SNI.191 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca 5 mm 694,936.000
SNI.192 1 M2 Pekerjaan Memasang Kaca Mati 3 mm Pintu / Jendela 163,857.375
SNI.193 1 M2 Pekerjaan Memasang Kaca Mati 5 mm Pintu / Jendela 197,737.375
SNI.193.8 1 M2 Pekerjaan Memasang Kaca Mati 8 mm Pintu / Jendela 250,977.375
SNI.194 1 M2 Pekerjaan Memasang Alumunium strip 8 mm 810,276.500
SNI.195 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca Tempered 8 mm 1,639,836.000
SNI.195.a 1 M2 Pekerjaan Memasang Kaca Cermin 5 mm 231,001.375
SNI.196 1 M2 Pekerjaan Memasang Glass Blok 1,541,658.800
SNI.197 1 M2 Pekerjaan Memasang Kaca Mati Riben 5 mm Pintu / Jendela 225,567.375
SNI.197.a 1 M2 Pekerjaan Memasang Kaca Mati Buram 5 mm Pintu / Jendela 287,277.375
SNI.198 1 M2 Pekerjaan Memasang Kaca Mati Tempered 8 mm Pintu / Jendela 1,237,127.375
SNI199 1 M2 Pekerjaan Daun Pintu / Jendela Panil dan Krepyak Kayu Klas II 940,885.000
SNI.200 1 M2 Pekerjaan Daun Pintu Panil dan Krepyak Kayu Klas II Lap. Formika 800,305.000
SNI.201 1 M2 Pekerjaan Ram Jalusi 925,430.000
SNI.202 1 M2 Pekerjaan Ram Jalusi Mati Kusen 640,337.500
SNI.203 1 M2 Pekerjaan Jendela Nako/ Tralis 850,558.500
SNI.204 1 M2 Mengerjakan Daun Pintu Double Teakwood 3 mm 780,604.000
SNI.206 1 M2 Pekerjaan Pintu Double Tripleks 3 mm 794,904.000
SNI.208 1 M2 Pekerjaan Pintu Teakwood Lapis Formika 996,204.000
SNI.209 1 M2 Pekerjaan Pintu Triplek Lapis Formika 560,604.000
SNI.210 1 M2 Pekerjaan Pasang Kawat Gerawang 54,920.250
SNI.211 1 M2 Pekerjaan Pasang Jeruji Besi Pintu 727,879.625
SNI.212 1 M2 Pekerjaan Pasang Kawat Duri 207,234.500
SNI.213 1 M2 Pekerjaan Pagar besi Hollow (stenlistail) 1,409,329.625
SNI.214 1 M2 Pekerjaan Pagar besi Hollow 599,729.625
SNI.214.1 1 M2 Pekerjaan Pagar/ Dinding besi Hollow 100 x 50 mm 1,001,009.625
SNI.214.A 1 M2 Pekerjaan Pintu Pagar besi (dia. 16 mm) 1,279,529.625
SNI.214.B 1 M2 Pekerjaan Pagar besi (dia. 16 mm) 1,169,529.625

PEKERJAAN ATAP
SNI.215 1 M2 Pekerjaan Atap Genteng Lokal 81,625.500
SNI.216 1 M2 Pekerjaan Bubungan Genteng Lokal 144,881.000
SNI.217 1 M2 Pekerjaan Atap Genteng Pejaten Bali 134,645.500
SNI.217,a 1m² Pasang Atap Genteng Bitumen Monoleyer model gelombang ex. Onduline 250,608.424
SNI.218 1 M2 Pekerjaan Bubungan Genteng Pejaten Bali 147,851.000
SNI.218.a 1 m Pemasangan nok bitumen Monolayer 190,734.500
SNI.219.0.25 1 M2 Pekerjaan Atap Trimdeck 0.25 TCT (Spandek) 194,132.400
SNI.219.0.30 1 M2 Pekerjaan Atap Trimdeck 0.30 TCT (Spandek) 206,232.400
SNI.219.0.35 1 M2 Pekerjaan Atap Trimdeck 0.35 TCT (Spandek) 235,272.400
SNI.220 1 M' Pekerjaan Memasang Bubungan Trimdeck 0.35 TCT (Spandek) 104,493.400
SNI.221.a 1 M2 Pekerjaan Atap Genteng Kodok 181,395.500
SNI.221.b 1 M2 Pekerjaan Atap Genteng kanmuri full flat 257,845.500
SNI.222.a 1 M2 Pekerjaan Bubungan Genteng Kodok 135,751.000
SNI.222.b 1 M2 Pekerjaan Bubungan Genteng kanmuri full flat 287,001.000
SNI.223 1 M2 Pekerjaan Atap Seng Gelombang BJLS 20 127,627.500
SNI.224 1 M' Memasang Bubungan Seng BJLS 20 101,887.500
SNI.225 1 M2 Pekerjaan Atap Asbes Gelombang Kecil 100,424.500
SNI.226 1 M' Memasang Bubungan Asbes Gelombang Kecil 91,784.000
SNI.227 1 m2 Mengerjakan atap genteng Metalroof ( Tebal 2.5 mm ) lapisan butiran 138,308.500
SNI.228 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 2.5 mm ) lap. Butiran 112,513.500
SNI.229.a 1 m2 Mengerjakan atap genteng Metalroof ( Tebal 3 mm ) lapisan butiran 174,608.500
SNI.229.b 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 3 mm ) lap. Butiran 136,713.500
SNI.230 1 m2 Mengerjakan atap genteng Metal ( Tebal 2.5 mm ) Sakura 112,348.500
SNI.231 1 m' Mengerjakan bubungan Genteng Metal ( Tebal 2.5 mm ) 84,683.500
SNI.232 1 m2 Mengerjakan Plafond Gypsum Board, tebal 9 mm + rangka kayu 171,930.000
SNI.233.a 1 m' Mengerjakan List Plafond Gypsum Board Type I 68,025.100
SNI.233.b 1 m' Mengerjakan List Plafond Gypsum Board Type II 53,010.100
SNI.234 1 m2 Mengerjakan Plafond Gypsum Rangka Hollow 40x40 Zincromate 247,465.350
SNI.234.a 1 m2 Memasang langit-langit WPC , rangka metal furing 890,113.448
SNI.234.b 1 m2 Pasang Atap Kaca Laminasi / Laminated 12 mm rangka hollow 2,539,394.000
SNI.234.c 1 m2 Pasang Kaca Tempered Clear T=10 1,653,894.000
SNI.234.d 1 m2 Pasang Atap Kanopi GRC gelombang 245,113.000
SNI.234.SP.1 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Putih polos 475,983.750
SNI.234.SP.2 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Warna 518,883.750
SNI.234.AQ 1 m2 Mengerjakan Plafond Akustik Rangka Alumunium 408,498.750
SNI.235.a 1 M2 Pekerjaan Plafond Tripleks 3 mm + Rangka kayu 157,426.500
SNI.235.b 1 M2 Pekerjaan Plafond Tripleks 5 mm + Rangka kayu 173,514.000
SNI.235.c 1 M2 Pekerjaan Rangka Langit-langit 114,460.500
SNI.235.d 1 M2 Pekerjaan Plafond Tripleks 5 mm 59,053.500
SNI.236.a 1 M2 Pekerjaan Plafond Miring Tripleks 3 mm + Rangka kayu 128,782.500
SNI.236.b 1 M2 Pekerjaan Plafond Miring Tripleks 5 mm + Rangka kayu 144,870.000
SNI.237.a 1 M2 Pekerjaan Dinding Double Tripleks 3 mm + Rangka kayu 185,196.000
SNI.237.b 1 M2 Pekerjaan Dinding Double Tripleks 5 mm + Rangka kayu 217,371.000
SNI.238 1 M' Pekerjaan List Plafond Kayu Profil 4/4 cm 30,728.500
SNI.239 1 M' Pekerjaan List Plafond Kayu Profil 2/4 cm 24,953.500

PEKERJAAN ALUMUNIUM dan BESI


SNI.240 Memasang 1 Kg Besi Profil 54,895.500
SNI.241.1 Memasang 1 Kg Rangka Kuda-kuda Baja IWF 54,895.500
SNI.241.a Memasang 1 Kg Rangka Kanal - C 54,895.500
SNI.241.b Pasang 1 m Handrail dan Railing 475,834.150
SNI.241.c Pasang 1 m Galvanis Steel 3/4" 100,096.150
SNI.241.d Pasang 1 m Railing Stainless 890,173.900
SNI.241.e Pasang 1 m Tangga Hollow 5x5 cm 335,017.650
SNI.241.1 1 m2 Pasang Syntetic Grass 158,752.000
SNI.241.2 1 m Pasang WPC 5x5 cm 272,855.000
SNI.241.3 1 m Pasang WPC 10x5 cm 420,838.000
SNI.241.4 1 m Pasang WPC 15x5 cm 582,252.000
SNI.241.5 1 m Pasang WPC 20x5 cm 693,693.000
SNI.241.6 1 m Pasang WPC Panel W15 x H2,5 cm 340,252.000
SNI.241.7 1 m2 Pasang Floor hardener 3 Kg/m2 128,040.000
SNI.241.8 1 m2 Pasang Efoxy waterbased flooring non slip anti abrasion 155,540.000
SNI.241.9 1 m2 Pasang Floor hardener 3 Kg/m2 + ceramic stepnoosing 100 x 200 mm 566,115.000
SNI.241.10 1 m2 Pasang Floor hardener 7 Kg/m2 + grove line 2 cm 251,790.000
SNI.241.11 Pasang GRC Rosters 300x300x150 332,776.950
SNI.241.12 Pasang Kisi-kisi 50x100 mm UPVC Motif Kayu 1,514,994.800
SNI.242 Mengerjakan 100 kg pekerjaan perakitan 399,877.500
SNI.243 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku 1,594,032.000
SNI.244 Mengerjakan 10 cm pengelasan dengan las listrik 159,280.000
SNI.245 Memasang 1 m2 rolling door alluminium 942,425.000
SNI.246 Memasang 1 m2 sunscreen alluminium 691,394.000
SNI.247 Memasang 1 m kusen pintu alluminium Natural 174,724.275
SNI.247.a Memasang 1 m2 Dinding kusen alluminium Natural + Kaca polos 8 mm 748,026.125
SNI.247.b Memasang 1 m2 Dinding kusen alluminium Natural + Kaca temreat 8 mm, polos 1,734,176.125
SNI.247.c Memasang 1 m2 Dinding kusen alluminium Natural + Kaca temreat 8 mm, warna 1,855,176.125
SNI.248 Memasang 1 m kusen pintu alluminium Warna 189,244.275
SNI.248.a Memasang 1 m2 Dinding kusen alluminium Warna + Kaca polos 8 mm 794,244.275
SNI.248.b Memasang 1 m2 Dinding kusen alluminium Warna + Kaca temreat 8 mm, polos 1,780,394.275
SNI.248.c Memasang 1 m2 Dinding kusen alluminium Warna + Kaca temreat 8 mm, warna 1,913,256.125
SNI.248.12 Memasang 1 m2 Besi Hollow + Kaca temreat 12 mm, warna 2,373,056.125
SNI.248.T8p Memasang 1 m2 Kaca temreat 8 mm, polos 1,235,656.125
SNI.248.T8w Memasang 1 m2 Kaca temreat 8 mm, Warna 1,356,656.125
SNI.248.5p Memasang 1 m2 Kaca mati 5 mm, polos 196,266.125
SNI.248.8p Memasang 1 m2 Kaca mati 8 mm, polos 249,506.125
SNI.248.R Memasang 1 m2 Kaca mati Riben 5 mm 224,096.125
SNI.248.B/E Memasang 1 m2 Kaca mati Buram/Es 5 mm 285,806.125
SNI.249 Memasang 1 m2 pintu alluminium strip 1,022,751.125
SNI.249.a Pasang 1 Buah Cermin ex. TOTO TS 119 AS5 231,001.375
SNI.249.b Pasang 1 Buah Kaca Laminasi tebal 12 mm 1,841,511.375
SNI.249.c Pasang 1 m2 kaca green glass 12 mm 2,205,588.000
SNI.249.d Pasang 1 m2 kaca green glass tebal 8 mm 1,358,588.000
SNI.249.e Pasang 1 bh Pintu Engineering door / WPC 317,996.250
SNI.249.f Pasang 1 bh Pintu Green glass 392,246.250
SNI.249.g Pasang 1 bh Pintu siku alumunium powder coating 77,742.500
SNI.249.1 Pemasangan 1 m1 Kusen plat baja uk. 15x9x0,2 cm 507,463.000
SNI.249.2 Pemasangan 1 m1 Kusen Steel Frame Hollow Galvanis 150x40x3 mm 85,129.000
SNI.249.3 Pemasangan 1 m1 Kusen alumunium 4" YKK finishing powder coating 267,993.000
SNI.249.4a Mengerjakan 1 Unit pintu double UGD type P-01 23,112,673.210
SNI.249.4b Mengerjakan 1 Unit pintu type P-02 14,716,624.010
SNI.249.4c Mengerjakan 1 Unit pintu type P-03 11,198,829.923
SNI.249.4d Mengerjakan 1 Unit pintu type P-04A 8,505,265.065
SNI.249.4e Mengerjakan 1 Unit pintu type P-04B 7,955,265.065
SNI.249.4f Mengerjakan 1 Unit pintu type P-04C 7,346,306.605
SNI.249.4g Mengerjakan 1 Unit pintu type P-05 6,449,035.835
SNI.249.4h Mengerjakan 1 Unit pintu type P-06 7,103,741.205
SNI.249.4i Mengerjakan 1 Unit pintu type P-07 7,115,566.205
SNI.249.4j Mengerjakan 1 Unit pintu type P-08 3,365,089.695
SNI.249.4k Mengerjakan 1 Unit pintu type P-09 8,549,368.589
SNI.249.4l Mengerjakan 1 Unit pintu type P-10 7,547,493.209
SNI.249.4m Mengerjakan 1 Unit pintu type P-11 30,051,694.929
SNI.249.4n Mengerjakan 1 Unit pintu type P-12 10,992,579.923
SNI.249.4o Mengerjakan 1 Unit pintu type P-S 1,652,262.906
SNI.250.N5 Memasang 1 m2 Daun pintu kaca 5 mm rangka alluminium, (natural) 1,124,006.125
SNI.250.N8 Memasang 1 m2 Daun pintu kaca 8 mm rangka alluminium, (natural) 1,234,006.125
SNI.250.W5 Memasang 1 m2 Daun pintu kaca 5 mm rangka alluminium, (warna) 1,179,006.125
SNI.250.W8 Memasang 1 m2 Daun pintu kaca 8 mm rangka alluminium, (warna) 1,289,006.125
SNI.251.N Memasang 1 m2 jendela kaca 5 mm rangka alluminium, (natural) 1,124,006.125
SNI.251.N8 Memasang 1 m2 jendela kaca 8 mm rangka alluminium, (natural) 1,234,006.125
SNI.251.W Memasang 1 m2 jendela kaca 5 mm rangka alluminium, (warna) 1,179,006.125
SNI.251.W8 Memasang 1 m2 jendela kaca 8 mm rangka alluminium, (warna) 1,289,006.125
SNI.251.75.a 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 75.100 225,907.000
SNI.251.75.b 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 75.75 202,477.000
SNI.251.75.c 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) Usuk C 75 137,560.500
SNI.251.75.d 1 M2 Rangka Reng Aluzing Aluminium (Baja ringan) Reng U 0.45 64,916.500
SNI.251.80.a 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 80.100 239,965.000
SNI.251.80.b 1 M2 Rangka Kuda-kuda Aluzing Aluminium (Baja ringan) C 80.75 216,535.000
SNI.251.ACP.a 1 M2 Rangka dan Penutup Alluminium Composit Panel (ACP), Interior 872,588.750
SNI.251.ACP.b 1 M2 Rangka dan Penutup Alluminium Composit Panel (ACP), Exterior 1,138,788.750
SNI.251.ACP.c 1 M2 Rangka dan Penutup Wood Panel Composit (WPC), Exterior 656,108.750
SNI.251.DG 1 M2 Pekerjaan Dinding Double Gypsum 9 mm + Rangka profil C 221,045.000
SNI.251.DC 1 M2 Pekerjaan Dinding Double Calsiboart 6 mm + Rangka profil C 324,995.000

PEKERJAAN PENGECATAN/FINISING
SNI.252 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Eksterior) 67,856.250
SNI.252.a 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Interior) 42,116.250
SNI.252.b 1 M2 Pekerjaan Cat Plafond Baru 1 x Dasar, 2 x Cat 65,065.000
SNI.252.c 1 M2 Pekerjaan Cat Dak Beton, (Water Proofing/ Sunscreen) 31,556.250
SNI.252.d 1 M2 Pekerjaan Cat Dak Beton, (Water Proofing/ Sunscreen) 241,502.250
SNI.252.e 1 m² Pengecatan Tembok Baru anti bakteri ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup anti bakteri 82,563.250
SNI.252.f 1 m² Memasang pelapis tembok dengan plat timbal hitam tebal 3 mm rangka hollow 1,226,673.250
SNI.252.g 1 m² Measang pelapis tembak dengan HPL 109,150.250
SNI.252.h 1 m² Pemasangan Wall Paper 182,366.250
SNI.252.i 1 m2 Pengecatan Cat Tekstur Fin. Kamprot Halus 507,966.250
SNI.253 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Berjamur ) - Lama, Eksterior 90,103.750
SNI.253.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Berjamur ) - Lama, Interior 68,653.750
SNI.254 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Eksterior 54,381.250
SNI.254.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Interior 31,501.250
SNI.254.b 1 M2 Pekerjaan Cat Plafond Lama 1 x Dasar, 2 x Cat 57,035.000
SNI.255 1 M2 Pekerjaan cat Genteng 68,853.400
SNI.256 1 M2 Pekerjaan Cat Kayu 1 x Meni, 2 x Cat 60,524.750
SNI.257 1 M2 Pekerjaan Cat Kayu, 1 x Cat 54,238.250
SNI.258 1 M2 Pekerjaan Cat paving Blok 38,557.200
SNI.259 1 M2 Mendempul dan Menggosok Kayu 17,630.250
SNI.260 1 M2 Pekerjaan Politur 2 Kali 51,567.450
SNI.261 1 M2 Mengecat Besi 1 x Meni, 2 x Cat 65,285.000
SNI.262 1 M2 Mengecat Atap Seng Gelombang 47,451.800
SNI.263 1 M2 Pekerjaan Pelaburan Bidang Kayu dengan Teak Oil 22,294.250
SNI.264 1 M2 Mengeter Kayu 2x 37,301.000

PEKERJAAN KUNCI
SNI.265.a 1 Bh. Pasang Kunci Tanam Biasa 203,142.500
SNI.265.b 1 Bh. Pasang Kunci Tanam Mutu Menengah 258,142.500
SNI.265.c 1 Bh. Pasang Kunci Tanam Mutu Tinggi 688,242.500
SNI.266 1 Bh. Pasang Kunci Tanam Kamar Mandi 189,296.250
SNI.267 1 Bh. Pasang Engsel Pintu 48,511.375
SNI.268 1 Bh. Pasang Engsel Jendela 35,274.250
SNI.268.1 1 Bh. Pasang Grendel Besar 42,974.250
SNI.268.2 1 Bh. Pasang Grendel Kecil 31,974.250
SNI.269 1 Bh. Pasang Kait Angin Besar 40,811.375
SNI.270 1 Bh. Pasang Kait Angin Kecil 98,271.250
SNI.271 1 Bh. Pasang Kunci Selot Besar 116,674.250
SNI.272 1 Bh. Pasang Kunci Selot Kecil 112,348.500
SNI.273 1 Bh. Pasang Beugel U 44,661.375
SNI.274 1 Bh. Pasang Beugel Plat 44,661.375
SNI.275 1 Bh. Pasang Angker Dia 12 MM 7,261.375
SNI.276.a 1 Bh. Pas. Baut Mur 7,261.375
SNI.276.b 1 Bh. Pas. Baut Mur 12 mm 8,361.375
SNI.276.c 1 Bh. Pas. Baut Mur 16 mm 9,461.375
SNI.276.d 1 Bh. Pas. Baut Mur 18 mm 10,561.375
SNI.276.e 1 Bh. Pas. Baut Mur 22 mm 12,761.375
SNI.278.a 1 Bh. Pasang Door Closer 355,337.125
SNI.278.b 1 Bh. Pasang Door Stoper 159,537.125
SNI.279 1 Bh. Pasang Pegangan Pintu/ Door Holder, (Pull Handle) 374,037.125
SNI.280 1 Bh. Pasang Kunci Silender 157,337.125
SNI.281 1 Bh. Pasang Rel Pintu Dorong 134,237.125
SNI.282 1 Bh. Pasang Pintu Feber glass (Wc) 1,020,837.125

PEKERJAAN INSTALASI LISTRIK


SNI.IL.1 Pekerjaan Panel 16,887,450.000
SNI.IL.1a Panel Daya lantai 01 9,087,450.000
SNI.IL.1b Panel Daya lantai 02 8,721,000.000
SNI.IL.1c Panel AC lantai 01 8,537,800.000
SNI.IL.2 1 m' NYY 4 x 10 mm² + BCC 10 mm² 86,150.000
SNI.IL.2a 1 m' Kabel NYM 3 x 2.5 mm2 54,200.000
SNI.IL.2b 1 m' Kabel NYY 4 x 25 mm2 244,850.000
SNI.IL.3 1 Titik instalasi Penerangan Kabel NYM 2 x 2.5 mm 198,350.000
SNI.IL.3a 1 Titik instalasi Penerangan Kabel NYM 3 x 2.5 mm 246,750.000
SNI.IL.3b 1 Titik instalasi stop kontak 198,350.000
SNI.IL.3c 1 Titik instalasi stop kontak 198,350.000
SNI.IL.3d 1 Titik instalasi exhaust fan 246,750.000
SNI.IL.3e 1 bh Lampu RMI TL LED T8 2 x 18 W 862,850.000
SNI.IL.3f 1 bh Lampu Down Light Ø 6", LED 10.5 W 341,750.000
SNI.IL.3g 1 bh Lampu Down Light Ø 6", LED 7 W 246,850.000
SNI.IL.3h 1 bh Lampu Down Light Ø 4", LED 14 W 245,950.000
SNI.IL.3i 1 bh Lampu Down Light Ø 3", LED 7 W 172,250.000
SNI.IL.3j 1 bh Lampu Barret LED 18 W 1100 lm 6500 K 571,650.000
SNI.IL.3k 1 bh Exhaust Fan 472 CMH 12 W 367,500.000
SNI.IL.3l Stop Kontak dinding 50,100.000
SNI.IL.3m Saklar Tunggal 57,800.000
SNI.IL.3n Saklar Double 66,600.000
SNI.IL.4 1 Titik Instalasi Telephone 128,250.000
SNI.IL.4a 1 m' Kabel ITC 2 x 2 x 0.6 24,600.000
SNI.IL.4b Outlet telepon 86,950.000
SNI.IL.4c Telephone Terminal Box 266,350.000
SNI.IL.4d PABX Kap 4 lines, 16 Extension 18,204,600.000
SNI.IL.4e MDF Telephone 3,079,600.000
SNI.IL.4f Hand single Telephone 387,350.000
SNI.IL.5 1 Titik Instalasi LAN 133,750.000
SNI.IL.5a 1 m' Kabel UTP cat.6 35,600.000
SNI.IL.5b Outlet LAN 35,600.000
SNI.IL.5c 1 unit Optical terminal box 1,567,100.000
SNI.IL.5d 1 unit Switch Hub Utama 8 Port Manageable 19,021,350.000
SNI.IL.5e 1 unit Patch panel 8 port 1,869,600.000
SNI.IL.5f 1 unit Closed Rack 12U 3,926,600.000
SNI.IL.6 1 Titik Instalasi Ceiling speaker 188,750.000
SNI.IL.6a 1 Titik Instalasi attenuator 188,750.000
SNI.IL.6b 1 unit Sound terminal box 1,264,600.000
SNI.IL.6c 1 m' NYMHY 3x1,5mm 45,900.000
SNI.IL.6d 1 bh Ceiling Speaker 211,350.000
SNI.IL.6e 1 bh Attenuator 239,200.000
SNI.IL.6f 1 bh Dynamic Microphone 356,900.000
SNI.IL.6g 1unit CD Player CD-2011 R 2,474,600.000
SNI.IL.6h 1 set Rack cabinet 12,154,600.000
SNI.IL.6i 1 bh Remote Microphone w/Keypad Zone Selector 7,084,050.000
SNI.IL.6j 1 unit Power amplifier 240 W with 5 zone Selector system 6,104,600.000
SNI.IL.6k 1 unit Battery backup 2x1000 VA 4,012,650.000
SNI.IL.7 1 unit Air terminal R-150 Early Streamer Emmission (ESE) technology 11,549,600.000
SNI.IL.7a 1 m' Kabel NYY 1x70 mm2 for down conductor 142,950.000
SNI.IL.7b 1 bh Connecting Sleeve 514,400.000
SNI.IL.7c 1 bh Schoen cable CU 50 78,800.000
SNI.IL.7d 1 m' Pipa galvanis Ø 2.5" dudukan untuk air terminal + las 222,650.000
SNI.IL.7e 1 m' Kabel conductor BC 70 mm² untuk gounding 72,300.000
SNI.IL.7f 1 btg Pipa galvanis 3/4" ( untuk grounding ) 96,950.000
SNI.IL.7g 1 bh Splitzen tembaga murni 3/4"( bukan lapisan ) untuk ground rod 1,098,500.000
SNI.IL.7h 1 Kg Timah 874,650.000
SNI.IL.7i 1 m' Pipa PVC 3/4" for Kabel NYY 1x50 mm2 27,450.000
SNI.IL.7j 1 unit Pembuatan sumur grounding 3,082,900.000
SNI.IL.7k 1 bh Pembuatan bak kontrol grounding 70x70x65 cm 1,170,350.000
SNI.IL.8 1 m' Kabel tray 400 mm x 100 mm 180,300.000
SNI.IL.8a 1 pcs TeeTray 400 mm x 100 mm 663,250.000
SNI.IL.8b 1 pcs El Bow Tray 400 mm x 100 mm 595,250.000
SNI.IL.8c 1 m' Kabel Ladder 400 mm x 100 mm 138,500.000
SNI.IL.9 Instalasi Power AC NYM 3x2,5mm 335,600.000
SNI.IL.9a Instalasi Power AC NYM 3x4mm 444,500.000
SNI.IL.9b 1 unit Unit AC type wall split kap 1/2 PK 4,933,950.000
SNI.IL.9c 1 unit Unit AC type wall split kap 1 PK 9,867,900.000
SNI.IL.9d 1 unit Unit AC type wall split kap 1.5 PK 12,334,800.000
SNI.IL.9e 1 unit Unit AC type wall split kap 2 PK 16,446,500.000
SNI.IL.9f Unit AC cassette type kap 2.5 PK 21,380,500.000
SNI.IL.9g 1m' Pipa refrigrant 3/8" + 5/8" 252,200.000
SNI.IL.9h 1m' Pipa refrigrant 1/4" + 3/8" 118,600.000

PEKERJAAN SANITAIR
SNI.283.B Memasang 1 Bh Kloset Duduk Biasa 1,513,391.000
SNI.283.K Memasang 1 Bh Kloset Duduk (KW 1 Super) 4,816,669.000
SNI.283.a Memasang 1 Bh Kloset Jongkok Porselon 892,650.000
SNI.283.b Memasang 1 Bh Kloset Jongkok Teraso 557,040.000
SNI.284 Memasang 1 Bh Wastafel Biasa 993,157.000
SNI.285 Memasang 1 Bh Wastafel (KW 1 Super) 3,326,565.000
SNI.286 Memasang 1 buah Urinoir ex. TOTO U 57 M 3,482,006.000
SNI.286.a Memasang 1 bh Pembatas Urinoir ex. TOTO A 100 1,530,842.500
SNI.286.b Memasang 1 buah Kitchen Sink Stainless Steel ex. TOTO 2,654,324.200
SNI.286.1 Memasang 1 Bh Bak Cuci Piring Logam, 1 lubang 699,822.750
SNI.286.2 Memasang 1 Bh Bak Cuci Piring Logam, 2 lubang 842,822.750
SNI.287 Memasang 1 Bh Bak Mandi Teraso 913,000.000
SNI.288 Memasang 1 Bh Bak Mandi Fiberglass 1,380,643.000
SNI.289 Memasang 1 Bh Bak Mandi Plastik 1,379,345.000
SNI.290 Memasang 1 Bh Kran Dia. 3/4" atau 1/2" 38,307.500
SNI.290.a Memasang 1 bh Kran ex. TOTO T2613 417,257.500
SNI.291 Memasang 1 Bh Floor Drain 45,842.500
SNI.291.a Memasang 1 bh Floor Drain ex. TOTO TX 1 BV 3 454,162.500
SNI.292 Memasang 1 Bh Saringan Air Besi 143,742.500
SNI.292.1 Memasang 1 bh Shower spray ex. TOTO TX 403 SBPIV 912,257.500
SNI.292.2 Memasang 1 bh Spoel hoek 12,210,082.500
SNI.292.3 Memasang 1 bh shower ex. TOTO TR 309 SZ 637,257.500
SNI.292.4 Memasang 1 bh Paper Holder ex. TOTO TIPE TS116R 671,412.500
SNI.292.5 Memasang 1 bh soap holder ex. TOTO S 156N 190,162.500
SNI.292.6 Memasang 1 bh hand railing stainless steel ex. TOTO TX 3A2 1,049,592.500
SNI.293.a Memasang 1 Bh Tandon Air kap. 500 Liter 1,585,842.500
SNI.293.b Memasang 1 Bh Tandon Air kap. 1000 Liter 2,318,442.500
SNI.294.V Memasang 1 m' Pipa PVC AW dia 1/2" 25,116.300
SNI.295.V Memasang 1 m' Pipa PVC AW dia 3/4" 27,492.300
SNI.296.V Memasang 1 m' Pipa PVC AW dia 1" 31,056.300
SNI.297.V Memasang 1 m' Pipa PVC AW dia 1.5" 49,618.800
SNI.298.Va Memasang 1 m' Pipa PVC AW dia 2" 66,844.800
SNI.298.Vb Memasang 1 m' Pipa PVC AW dia 3" 110,800.800
SNI.298.Vc Memasang 1 m' Pipa PVC AW dia 4" 155,053.800
SNI.294.G Memasang 1 m' Pipa GI dia 1/2" 63,549.842
SNI.295.G Memasang 1 m' Pipa GI dia 3/4" 70,919.842
SNI.296.G Memasang 1 m' Pipa GI dia 1" 88,519.842
SNI.297.G Memasang 1 m' Pipa GI dia 1.5" 114,589.842
SNI.298.Ga Memasang 1 m' Pipa GI dia 2" 142,639.842
SNI.298.Gb Memasang 1 m' Pipa GI dia 3" 210,179.842
SNI.298.Gc Memasang 1 m' Pipa GI dia 4" 287,399.842
0 0 0.000

PEKERJAAN LAIN - LAIN


SNI.299 1 M' Pagar BRC tinggi 1,20 m 467,627.050
SNI.300 1 M2 Fabrikasi Besi 600,629.797
SNI.301.3 3 M3 Kawat Bronjong 3 mm 2,980,917.500
SNI.301.4 3 M3 Kawat Bronjong 4 mm 3,801,517.500
SNI.301.5 3 M3 Kawat Bronjong 5 mm 4,916,917.500

PEKERJAAN VEGETASI TANAMAN


SNI.302 1 bh Tanam Pohon Kamboja tinggi 5 meter 2,121,762.500
SNI.302.1 1 bh Tanam Pohon Tabebuya tinggi 4 meter 1,709,262.500
SNI.302.2 1 bh Tanam Pohon Palem raja tinggi 3 meter 1,434,262.500
SNI.302.3 1 bh Tanam Pohon Pisang Kipas tinggi 1,5 meter 196,762.500
SNI.302.4 1 bh Tanam perdu Honje Merah tinggi 0,7 - 0,8 meter 56,842.500
SNI.302.5 1 bh Tanam perdu Bakung Lele tinggi 0,25 - 0,3 meter 60,252.500
SNI.302.6 1 bh Tanam perdu Pisang Hias tinggi 0,7 - 0,8 meter 53,432.500
SNI.302.a Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 928,098.600
SNI.302.b Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,320,028.600
SNI.302.c Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 632,528.600
SNI.302.d Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 976,278.600
SNI.302.e Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,320,028.600
SNI.302.f Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 907,528.600
SNI.302.g Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,182,528.600
SNI.302.h Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,182,528.600
SNI.302.i Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 976,278.600
SNI.302.j Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 611,848.600
SNI.302.k Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,622,528.600
SNI.302.l Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,045,028.600
SNI.302.m Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 756,278.600
SNI.302.n Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 220,028.600
SNI.302.o Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 838,778.600
SNI.302.p Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 130,598.600
SNI.302.q Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 185,598.600
SNI.302.r Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 2,076,278.600
SNI.302.s Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 1,938,778.600
SNI.302.t Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 632,528.600
SNI.302.u Tanam pelindung tinggi > 2 m, lubang 60 x 60 cm 632,528.600
SNI.302.1a Tanam semak , lubang polibag 15 x 15 cm 1,133,825.000
SNI.302.1b Tanam semak , lubang polibag 15 x 15 cm 721,325.000
SNI.302.1c Tanam semak , lubang polibag 15 x 15 cm 611,325.000
SNI.302.1d Tanam semak , lubang polibag 15 x 15 cm 3,471,325.000
SNI.302.1e Tanam semak , lubang polibag 15 x 15 cm 1,889,525.000
SNI.302.1f Tanam semak , lubang polibag 15 x 15 cm 1,064,525.000
SNI.302.1g Tanam semak , lubang polibag 15 x 15 cm 239,525.000
SNI.302.1h Tanam semak , lubang polibag 15 x 15 cm 267,025.000
SNI.302.1i Tanam semak , lubang polibag 15 x 15 cm 514,525.000
SNI.302.1j Tanam semak , lubang polibag 15 x 15 cm 514,525.000
SNI.302.1k Tanam semak , lubang polibag 15 x 15 cm 239,525.000
SNI.302.1l Tanam semak , lubang polibag 15 x 15 cm 996,325.000
SNI.302.1m Tanam semak , lubang polibag 15 x 15 cm 239,525.000
SNI.302.1n Tanam semak , lubang polibag 15 x 15 cm 171,325.000
SNI.302.1o Tanam semak , lubang polibag 15 x 15 cm 831,325.000
SNI.302.1p Tanam semak , lubang polibag 15 x 15 cm 136,125.000
SNI.302.1q Tanam semak , lubang polibag 15 x 15 cm 171,325.000
SNI.302.1r Tanam semak , lubang polibag 15 x 15 cm 308,825.000
SNI.302.1s Tanam semak , lubang polibag 15 x 15 cm 239,525.000
SNI.302.1t Tanam semak , lubang polibag 15 x 15 cm 136,125.000
SNI.302.1v Tanam semak , lubang polibag 15 x 15 cm 308,825.000
SNI.302.1x Tanam semak , lubang polibag 15 x 15 cm 377,025.000
SNI.302.1y Tanam semak , lubang polibag 15 x 15 cm 446,325.000
SNI.302.1z Tanam semak , lubang polibag 15 x 15 cm 542,025.000
SNI.302.2a Tanam semak , lubang polibag 15 x 15 cm 157,025.000
SNI.302.2b Tanam semak , lubang polibag 15 x 15 cm 150,425.000
SNI.302.2c Tanam semak , lubang polibag 15 x 15 cm 336,325.000
SNI.302.2d Tanam semak , lubang polibag 15 x 15 cm 514,525.000
SNI.302.2e Tanam semak , lubang polibag 15 x 15 cm 122,925.000
SNI.302.2f Tanam semak , lubang polibag 15 x 15 cm 171,325.000
SNI.302.2g Tanam semak , lubang polibag 15 x 15 cm 239,525.000
SNI.302.2h Tanam semak , lubang polibag 15 x 15 cm 308,825.000
SNI.302.3a Tanam rumput 99,990.000

PEKERJAAN TAMBAHAN
SNI.Ls.1 1 M' Biaya Pengeboran air + Pipa Casing Ø 6'' 1,507,935.000
SNI.Ls.2 1 M' Biaya Pengeboran air + Pipa Casing Ø 4'' 1,089,385.000
SNI.Ls.3 1 M' Biaya Pengeboran air + Pipa Casing Ø 3'' 541,915.000
SNI.Ls.4 1 M' Biaya Pengeboran air + Pipa Casing Ø 2.5'' 293,040.000
SNI.Ls.5 1 Bh' Mesin tenaga disel YEP-3 + Pompa Ebra Ø Q3'' ( setara Yanmar ) 37,992,240.000
SNI.Ls.6 1 Bh' Pompa Submersible type Centrifugal kapasitas 3 Ltr/Dtk, H 100, 3 Phase 49,012,700.000
SNI.Ls.7 1 Bh' Mesin tenaga Listerik disel + Pompa Outo matis Jet pam - 30 Complit pemasangan 28,494,400.000
SNI.Ls.8 1 Bh' Mesin tenaga disel + Pompa Outo matis ( setara sanyo ) ØINT 1''- 25 Complit pemasangan 25,644,300.000

Anda mungkin juga menyukai