HARGA SATUAN
NO UPAH DAN BAHAN SATUAN
( Rp. )
1 2 3 4
1 IMB m2 16,000.00
Bahan Pasangan
1 Batu Kali Belah 15-20 cm M³ 240,000.00
2 Batu Kali Alam M³ 226,000.00
3 Kerikil Pecah 5/7 cm M³ 418,000.00
4 Kerikil 5/7 cm (Stone Crusher) M³ 560,000.00
5 Kerikil Pecah 3/5 cm M³ 500,000.00
6 Kerikil 3/5 cm (Stone Crusher) M³ 535,000.00
7 Kerikil Pecah 2/3 cm M³ 565,000.00
8 Kerikil 2/3 cm (Stone Crusher) M³ 735,000.00
9 Kerikil Alam 0,5/1 Cm M³ 530,000.00
10 Kerikil Alam 2/3 M³ 560,000.00
11 Kerikil Sungai - Riyalti M³ 350,000.00
12 Kerikil Beton (Maks 3 cm) M³ 340,000.00
13 Kerikil Pecah 1/2 cm M³ 791,000.00
14 Batu Kali Keping / Tempel M³ 283,000.00
15 Kerikil Alam 5/7 M³ 226,000.00
16 Kerikil Alam 3/5 M³ 238,000.00
17 Kerikil Alam 2/3 Cm M³ 339,000.00
18 Agregate Kasar (Stone Crusher) M³ 792,000.00
19 Agregate Halus (Stone Crusher) M³ 905,000.00
20 Agregate Klas B (20% Agg.Hls:80% Agg.Ksr) M³ 679,000.00
21 Batu Apung Kg 249,000.00
22 Batu Bata Kelas I (Press) Buah 950.00
23 Batu Bata Kelas II (Lokal) Buah 850.00
24 Bata ringan/Hebel, 10X20X60 m3 1,600,000.00
25 Bata ringan/Hebel, 10X20X60 bh 19,000.00
26 Pasir Beton ( Pasir Hodo ) M³ 350,000.00
27 Pasir Pasang M³ 220,000.00
28 Pasir Urug M³ 190,000.00
29 Sirtu M³ 237,000.00
30 Tanah Urug biasa M³ 121,000.00
31 Tanah Urug Pilihan M³ 192,000.00
32 Tanah Liat (TL) M³ 57,000.00
Bahan Atap
1 Sirap Kalimantan Bh 2,800.00
2 Genteng Lokal Bh 1,800.00
3 Genteng Beton /Pres Bh 6,800.00
4 Genteng Karang Pilang/ Kodok Bh 5,500.00
5 Genteng Pejaten Sudah di cat Bh 3,800.00
6 Genteng Kaca Bh 28,000.00
7 Genteng Keramik / 25bh Bh 17,000.00
8 Genteng Keramik Glazur / 15bh Bh 15,000.00
9 Genteng Kanmuri Full Flat, Natural Bh 18,000.00
10 Genteng Karang Pilang Type Keramik Bh 9,700.00
11 Genteng Bubungan Lokal Bh 6,800.00
12 Genteng Bubungan Beton Bh 7,800.00
13 Genteng Bubungan Silang Bh 6,500.00
14 Genteng Bubungan Pejaten Bh 8,700.00
15 Genteng Bubungan Keramik / 4bh Bh 30,600.00
16 Genteng Bubungan Keramik Glazur / 4bh Bh 16,000.00
17 Bubungan Genteng kanmuri Full Flat, Natura Bh 34,000.00
18 Bubungan Karang Pilang/ Kodok Bh 13,000.00
19 Genteng Metal roof 0,25 mm (Lapis Butiran) Lbr 60,000.00
20 Bubungan Metal Roof (Lapis Butiran) M' 65,000.00
21 Genteng Metal roof 0,3 mm (Lapis Butiran) Lbr 82,000.00
22 Bubungan Metal Roof (Lapis Butiran) M' 85,000.00
23 Genteng Metal roof 0,25 mm (Tanpa Lapis Butiran) Sakura Lbr 40,000.00
24 Bubungan Metal (Tanpa Lapis Butiran) M' 42,000.00
25 Atap bitumen gelombang H : 3,0 mm lbr 192,500.00
26 Paku fiser bitumen bh 1,500.00
27 Nok / Ridge Onduline Lbr 1,500.00
28 Sekrup / Paku bh 12,500.00
29 Asbes Type Genteng (tyluq) Lembar 67,800.00
30 Ijuk Atap kg 28,000.00
31 Asbes Gelombang Kecil 92 x 180 cm Lembar 68,000.00
32 Asbes Gelombang Besar 105 x 240 cm Lembar 198,000.00
33 Bubungan Asbes Gelombang Kecil 92 cm Lembar 53,000.00
34 Bubungan Asbes Gelombang Besar 105 cm Lembar 85,000.00
35 Seng.Glb Besar BJL.S 20 Lembar 67,000.00
36 Seng.Glb Besar BJL.S 25 Lembar 78,000.00
37 Seng.Glb Besar BJL.S 30 Lembar 84,000.00
38 Seng.Glb Kecil BJL.S 20 Lembar 74,000.00
39 Seng Plat BJL.S 18 lebar 90 cm M' 48,000.00
40 Seng Plat BJL.S 20 lebar 90 cm M' 74,000.00
41 Seng Plat BJL.S 25 lebar 90 cm M' 103,000.00
42 Seng Plat BJL.S 28 lebar 90 cm M' 115,000.00
43 Seng Plat BJL.S 30 lebar 90 cm M' 130,000.00
44 Seng Spandek 0.25 mm lebar 80 cm M' 60,000.00
45 Seng Spandek 0.3 mm lebar 80 cm M' 70,000.00
46 Seng Spandek 0.35 mm lebar 80 cm M' 94,000.00
47 Seng Spandek 0.4 mm lebar 80 cm M' 104,000.00
48 Seng Spandek 0.25 mm lebar 80 cm, Warna M' 75,000.00
49 Seng Spandek 0.3 mm lebar 80 cm, Warna M' 87,000.00
50 Seng Spandek 0.35 mm lebar 80 cm, Warna M' 94,000.00
51 Seng Spandek 4 mm lebar 80 cm, Warna M' 103,000.00
52 Atap Roof Fiber Glass Lbr 125,000.00
53 Rangka Atap Roof Fiber Glass M² 266,000.00
54 Plastik Aerator M² 6,000.00
55 Atap Polycarbonat Lbr 203,000.00
56 Atap Trimdeck 0.40 TCT (Spandek) M² 90,000.00
57 Bubungan Trimdeck 0.40 TCT (Spandek) M' 51,000.00
58 Alumunium Foil M² 11,000.00
59 Karet Talang M' 91,000.00
60 Atap Polycarbonate (210 x 1180 cm) Lembar 418,000.00
61 GRC Board bergelombang m2 89,800.00
62 Profil C 75.100 M' 19,000.00
63 Profil C 75.75 M' 14,000.00
64 Profil C 80.100 M' 22,000.00
65 Profil C 80.75 M' 17,000.00
66 Reng U 0.55 M' 8,000.00
67 Reng U 0.45 M' 6,000.00
68 Baut Truss Bh 500.00
69 Baut Reng Bh 400.00
Bahan Cetak
1 Lubang Angin 10x20 Cm Bh 14,000.00
2 Lubang Angin 20x20 Cm Bh 15,000.00
3 Lubang Angin 20x30 Cm Bh 20,000.00
4 Buis Beton Dia. 10 Cm Bh,L= 0,5M 50,000.00
5 Buis Beton Dia. 20 Cm Bh,L= 0,5M 75,000.00
6 Buis Beton Dia. 30 Cm Bh,L= 0,5M 90,000.00
7 Buis Beton Dia. 40 Cm Bh,L= 0,5M 110,000.00
8 Buis Beton Dia. 50 Cm Bh,L= 0,5M 125,000.00
9 Buis Beton Dia. 60 Cm Bh,L= 0,5M 130,000.00
10 Buis Beton Dia. 80 Cm Bh,L= 0,5M 150,000.00
11 Penutup Buis Beton Dia. 80 Cm Bh 175,000.00
12 Batako 10 x 20 x 40 Cm Bh 4,000.00
13 Paving Blok Persegi (t = 8 cm) M2 80,000.00
14 Paving Blok Persegi (t = 6 cm) M2 65,000.00
15 Paving Blok Persegi (t = 8 cm), Press M2 165,000.00
16 Paving Blok Tiga Berlian M2 197,800.00
17 Batu paras/Palimanan M2 243,000.00
18 Batu Sisir/ Bergaris, hitam M2 260,000.00
19 Lubang Angin Keramik 20 x 20 cm Bh 43,000.00
20 Lubang Angin Keramik 30 x 30 cm Bh 54,000.00
21 Glass Block Bh 55,000.00
22 Roster Terawang (15 X 20 ) Bh 17,000.00
23 Roster 30 x 30 m2 218,700.00
24 Wall Line GRC + Rangka Hollow (Terpasang) M2 1,100,000.00
25 Conblock tipe segi-empat abu-abu 8 cm, K-300 m2 126,800.00
26 Conblock tipe segi-enam abu-abu 8 cm, K-300 m2 121,200.00
27 Kisi-kisi 50x100 mm UPVC Motif Kayu m1 131,700.00
28 Kanstein m1 81,200.00
Bahan Lantai
1 Tegel Abu-abu 20 x 20 M² 62,500.00
2 Tegel Bergaris Abu 20 x 20 Cm M² 73,500.00
3 Tegel Warna 20 x 20 Cm M² 79,500.00
4 Tegel Bergaris Warna 20 x 20 Cm M² 79,500.00
5 Tegel Traso Klas I 30 x 30 M² 84,800.00
6 Tegel Traso Klas II 30 x 30 M² 82,000.00
7 Granite Kw I M² 450,000.00
8 Granite Kw II M² 380,000.00
9 Geotextile m2 312,500.00
10 Drainagecell m2 675,000.00
11 Hospital plint 60 x 10 x 4 Buah 81,200.00
12 Stepnose tangga 10x40 cm Buah 31,200.00
13 Karpet kg 25,000.00
14 grassblock tebal 8 cm m2 140,000.00
15 Lantai conwood deck 12" T-lock + Pengecetan M² 770,000.00
Bahan Besi
1 Besi Beton Ulir Kg 19,000.00
2 Besi Beton polos Kg 16,000.00
3 Rangka Plafond Metal Furing m2 250,000.00
4 Rangka Plafond Besi Hollow, (galvanis) m2 200,000.00
5 Plat baja tebal 8 mm 4 feet x 8 feet lbr 1,240,000.00
6 plat baja 15x9x9,2 cm m1 312,500.00
7 Plat stainless steel m2 1,562,500.00
8 Pull Handle ex. Dekson type 01 bh 1,553,700.00
9 Lock Case ex. Dekson bh 906,200.00
10 Lever Handle ex. Dekson bh 750,000.00
11 Engsel Floor hange Dexson bh 1,743,700.00
12 Door Closer ex dekson bh 655,000.00
13 Slide Handle ex. Dekson bh 1,250,000.00
14 Engsel sliding bh 448,700.00
15 Pintu plat baja tebal 5,5 mm lapis timah hitam ex. Bostinco bh 18,750,000.00
16 Flush bolt ex. Dekson bh 100,000.00
17 Engsel kupu ex. Dekson bh 102,500.00
18 Plat timbah hitam 3 m m2 693,700.00
19 Besi Profil (Siku), kanal C Kg 30,000.00
20 Besi Baja IWF Kg 30,000.00
21 Pipa Black Steel Kg 35,000.00
22 Spaner Kg 35,000.00
23 Curtain Wall + kaca templet 8 mm m2 2,150,000.00
24 Kusen Alumunium Natural M' 93,000.00
25 Kusen Alumunium Warna M' 105,000.00
26 Daun pintu/jendela alumunium + kaca 5 mm, Complit (natural) m2 1,000,000.00
27 Daun pintu/jendela alumunium + kaca 5 mm, Complit (warna) m2 1,050,000.00
28 Daun pintu/jendela alumunium + kaca 8 mm, Complit (natural) m2 1,100,000.00
29 Daun pintu/jendela alumunium + kaca 8 mm, Complit (warna) m2 1,150,000.00
30 Alumunium Strip M' 57,000.00
31 Alumunium "T" M' 14,000.00
32 Kawat f 4 mm M' 8,000.00
33 Profil kaca Alumunium M' 90,000.00
34 Kawat Ikat Beton Kg 33,000.00
35 Kawat Nyamuk Besi M² 28,000.00
36 Kawat Saringan Pasir M² 34,000.00
37 Kawat Duri 50/Rol 95,000.00
38 Kawat Bronjong digalvanisir Kg 39,000.00
39 Kawat Las Kotak 160,000.00
40 Besi Strip Tebal 5 mm Kg 34,000.00
41 Besi Strip Tebal 3 x 2 mm Kg 25,000.00
42 Besi Strip Tebal 2 x 2 mm Kg 22,000.00
43 Besi Stainles Diameter 2" M' 90,000.00
44 Besi Stainles Diameter 1" M' 50,000.00
45 Besi Stainles Diameter 1/2" M' 30,000.00
46 Daun Pintu Roling door alumunium M² 600,000.00
47 Rangka Roling door alumunium M' 300,000.00
48 Pintu Harmonika, Complet M² 1,750,000.00
49 Sunscreen alluminium M² 500,000.00
50 Alluminium Composit Panel (ACP) 0,30 mm, (Interior) M² 550,000.00
51 Alluminium Composit Panel (ACP) 0,30 mm,(Exterior) M² 770,000.00
52 Wood Panel Composit (WPC) tebal 15mm M² 442,000.00
53 Pintu WCP, Complit Unit 1,500,000.00
54 sealent tube 25,000.00
55 Kawat Gerawang M² 22,000.00
56 Besi Hollow 100 x 50 Zincromate L = 6m M' 58,800.00
57 Besi Hollow 40 x 40 Zincromate L = 6m M' 25,000.00
58 Besi Hollow 40 x 20 Zincromate L = 6m M' 12,000.00
59 Besi Hollow 40 x 40 Stenlistail L = 6m M' 100,000.00
60 Besi Hollow 20 x 20 Stenlistail L = 6m M' 38,000.00
61 Pipa 2" black steel di cat duco m1 68,700.00
62 Pipa 1"black steel dicat duco m1 43,700.00
63 Galvanis Steel 3/4" m1 42,700.00
64 Besi Stainless Ø 3/4' m1 93,700.00
65 Hollow 5x5 cm m1 31,200.00
66 Syntetic Grass m2 131,200.00
67 WPC 5x5 cm m1 225,500.00
68 WPC 10x5 cm m1 347,800.00
69 WPC 15x5 cm m1 481,200.00
70 WPC 20x5 cm m1 573,300.00
71 WPC Panel W15 x H2,5 cm m1 281,200.00
72 WPC door type 02 include kaca 5 mm bh 2,812,500.00
73 WPC door type 03 include kaca 5 mm bh 4,437,500.00
74 WPC door type 04b include kaca 5 mm bh 2,312,500.00
75 WPC door type 04c include kaca 5 mm bh 1,937,500.00
76 WPC door type 06 uk. 2,2 x 0,8 m bh 2,187,500.00
77 WPC door type 08 uk. 1.1 x 0,6 m bh 1,625,000.00
78 WPC door type 09 uk. 2,2 x 1,5 m bh 3,125,000.00
79 WPC door type 10 uk. 2,2 x 0,9 m bh 2,375,000.00
80 WPC door type 11 uk. 2,2 x 1,3 m bh 4,250,000.00
81 Kalsiboard rangka alumunium set 750,000.00
82 Besi Hollow / Square Bars 20 x 40 x 1.5 mm M' 21,400.00
83 Besi Hollow / Square Bars 40 x 40 x 1.5 mm M' 28,600.00
84 Besi Hollow / Square Bars 40 x 60 x 1.5 mm M' 35,700.00
85 Besi Hollow / Square Bars 60 x 80 x 1.5 mm M' 50,000.00
86 Besi Hollow / Square Bars 60 x 100 x 1.5 mm M' 57,200.00
87 Rangka Hollow 5 x 100 mm m1 137,500.00
88 pengelasan cm1 1,200.00
89 Steel Frame Hollow Galvanis 150x40x3 mm m1 31,200.00
90 Alumunium 4" Dark Gray ex. YKK m1 206,200.00
91 Kunci Pintu Alumunium Bh 220,000.00
92 Textile Tape M' 34,000.00
93 Siku Pintu Otomatis Bh 550,000.00
94 Karet Kaca Set 140,000.00
95 Besi Plat 3 mm Lembar 1,695,000.00
96 Besi Plat 2 mm Lembar 1,244,000.00
97 Pintu kawat harmonika + Besi Siku M² 249,000.00
98 Plat baja, ukuran 120 x 240 cm Kg 23,000.00
99 Jarum Keras Bh 98,000.00
100 Pintu Jeruji Besi Rangka besi siku 40.40.4 + Asisories M² 536,000.00
101 Pintu Besi Pagar M² 480,000.00
102 Pagar Besi M² 452,000.00
103 Pintu Besi Pagar (dia. 16 mm) M² 900,000.00
104 Pagar Besi (dia. 16 mm) M² 800,000.00
105 Pagar Besi Pipa GI M² 792,000.00
106 Pintu Pagar Besi Pipa GI M² 848,000.00
107 Baut Sekrup Anti Karat Bh 1,900.00
108 Ventilasi Siku M2 249,000.00
109 Mata Kater Bh 84,000.00
110 Roda Pintu Dorong Bh 56,000.00
111 Mesin Bor Listirk Unit 1,334,000.00
112 Wiremesh M6/ (34,76)kg Kg 36,000.00
113 Wiremesh M8/ (61,79)kg Kg 65,000.00
114 Wiremesh M10/ (96,54)kg Kg 104,000.00
115 Bondek tebal 0.65 mm M2 108,000.00
116 Bondek tebal 0.70 mm M2 119,000.00
117 Bondek tebal 0.75 mm M2 122,000.00
118 Bondek tebal 1.00 mm M2 203,000.00
Bahan Langit-Langit
1 Eternit 100 x 100 Cm Lembar 26,000.00
2 Triplek 120 x 240 x 2 mm Lembar 53,000.00
3 Triplek 120 x 240 x 3 mm Lembar 66,000.00
4 Triplek 120 x 240 x 4 mm Lembar 102,000.00
5 Triplek 120 x 240 x 6 mm Lembar 105,000.00
6 Triplek 120 x 240 x 9 mm Lembar 158,000.00
7 Triplek 120 x 240 x 12 mm Lembar 237,000.00
8 Triplek 120 x 240 x 18 mm Lembar 328,000.00
9 Calsiboard 1200 x 240 x 3.5 mm Lembar 134,000.00
10 Calsiboard 1200 x 240 x 6 mm Lembar 221,000.00
11 Gypsum board 1200 x 2400 x 9 mm M2 95,000.00
12 PVC/ Shunda Plafond, 1.2 mm, Putih Polos M2 240,000.00
13 PVC/ Shunda Plafond, 1.2 mm, Warna M2 270,000.00
14 Plafond Akustik 600 x 600 M2 150,000.00
15 Plafond Papan Kayu Kls II, 2 cm M2 75,000.00
16 Formika Putih 120 x 240 mm Lembar 192,000.00
17 Formika Warna 120 x 240 mm Lembar 260,000.00
18 Mega Teakwood 120 x 240 x 3 mm Lembar 215,000.00
19 List Gypsum M' 23,000.00
20 List Plafond Gypsum Type I M' 52,000.00
21 List Plafond Gypsum Type II M' 39,000.00
22 List Plafond Shadow Line, aluminium 0.30 mm M' 5,200.00
23 Lem Kayu Kg 50,000.00
24 Lem Kg 50,000.00
25 Lem vinyl/perquete Kg 50,000.00
26 Lem Gypsum Kg 29,000.00
27 List Plafond Shadow Line, aluminium 0.30 mm M' 5,200.00
28 Kasiplank (0.8 x 20) M' 20,000.00
29 Top Cross Rail 250FX btg 30,000.00
30 Furring Chanel PN 205 btg 85,000.00
31 Furring Chanel PN 208 bh 2,600.00
32 Suspension Spring Clip 223SS bh 5,200.00
33 4 mm Soft Galv Suspension Rod PN 225 bh 5,250.00
34 Angle Bracket PN 220 bh 2,000.00
35 Wall Angle 252FX bh 4,200.00
36 Paper Tape roll 30,000.00
37 Steel Tape roll 131,200.00
38 UB Cote Read Mix kg 160,000.00
39 Papan WPC teval 7 mm lbr 328,900.00
Bahan Kaca
1 Kaca Nako 5 mm M² 141,000.00
2 Kaca Polos 3 mm M² 113,000.00
3 Kaca Polos 5 mm M² 141,000.00
4 Kaca Polos 8 mm M² 185,000.00
5 Kaca Buram (ES) 5 mm Komplit M² 215,000.00
6 Kaca Riben 3 mm M² 136,000.00
7 Kaca Riben 5 mm M² 164,000.00
8 Kaca Cermin 5 mm M² 169,000.00
9 Acrilic 2mm Bening 2mmx122cmx244cm Lembar 452,400.00
10 Kaca Tempreat 8 mm, Polos M² 1,000,000.00
11 Kaca Tempreat 10 mm, Polos m2 1,250,000.00
12 Kaca Tempreat 12 mm, Polos M² 1,500,000.00
13 Kaca Tempreat 8 mm, Warna M² 1,100,000.00
14 Kaca Tempreat 12 mm, Warna M² 1,800,000.00
15 Kaca Lengkung 10 mm, Polos M² 2,000,000.00
16 Kaca Lengkung 12 mm, Polos M² 2,500,000.00
Bahan Finishing
1 Amplas Lembar 8,700.00
2 Plamir Kayu Kg 28,000.00
3 Spritus Liter 28,000.00
4 Dempul Kg 35,000.00
5 Batu Apung Kg 249,000.00
6 Soda api Liter 66,000.00
7 Sabun Kg 20,000.00
8 Minyak Cat Liter 20,000.00
9 Residu Liter 25,000.00
10 Minyak Bekisting Liter 18,000.00
11 Meni Besi Kg 34,000.00
12 Meni Kayu Kg 34,000.00
13 Cat Kayu Mutu Menengah Kg 71,000.00
14 Cat Kayu Mutu Tinggi Kg 85,000.00
15 Cat Tembok Mutu Tinggi, (Interior) Kg 60,000.00
16 Cat Tembok Mutu Tinggi, (Exterior) Kg 125,000.00
17 Cat Tembok Mutu Menengah, (Interior) Kg 30,000.00
18 Cat Tembok Mutu Menengah, (Exterior) Kg 55,000.00
19 Cat Besi Kg 70,000.00
20 Cat Genteng Kg 42,000.00
21 Plamir Tembok/ Plafond Kg 49,000.00
22 Teer Kg 36,000.00
23 Politur Liter 35,000.00
24 Politur Jadi Liter 36,000.00
25 Minyak Cat A Spesial Liter 38,000.00
26 Cat Marka Jalan Scalato Kg 103,000.00
27 Cat Marka Jalan Biasa Kg 91,000.00
28 Cat Zigromeat Kg 125,000.00
29 Vernis Ltr 36,000.00
30 Kuas 5 Cm Bh 28,000.00
31 Rol Cat Bh 35,000.00
32 Glassbeads Kg -
33 Roadline thener Ltr -
34 Cat Roadline paint Ltr -
35 Water Proofing Kg 65,000.00
36 Floor hardener 3 Kg/m2 m2 43,700.00
37 Cat Epoxy m2 68,700.00
38 ceramic stepnoosing 100 x 200 mm m1 159,300.00
39 Grooe line 2 cm m2 25,000.00
40 Floor hardener 7 Kg/m2 m2 56,200.00
41 Fiber Bakar m2 106,200.00
42 Cat tembok dulux Watersilt Pro Kg 118,700.00
Bahan Pengunci
1 kunci pintu mutu menengah Bh 164,000.00
2 kunci pintu mutu tinggi Bh 555,000.00
3 Yale 1 Slag Bh 103,000.00
4 Yale 2 Slag Bh 164,000.00
5 Kuda Terbang 1 Slag Bh 114,000.00
6 Kuda Terbang 2 Slag Bh 136,000.00
7 Royal Stel 85,000.00
8 Haag Angin Besar Stel 13,000.00
9 Haag Angin Kecil Stel 9,000.00
10 Grendel Besar Bh 23,000.00
11 Grendel Kecil Bh 13,000.00
12 Engsel Nylon Pas 20,000.00
13 Engsel H (biasa) Pas 16,000.00
14 Expagnolet Bh 103,000.00
15 Kunci Silinder Bh 63,000.00
16 Pegangan Pintu KW I Bh 260,000.00
17 Door Holder Bh -
18 Door Closer Bh 243,000.00
19 Door Stoper Bh 65,000.00
20 Kunci Selot Besar Bh 90,000.00
21 Kunci Selot Kecil Bh 70,000.00
22 Rel Pintu Dorong M' 42,000.00
23 Lubang Pintu Intip (Door Viewer) Bh 88,000.00
Bahan Sanitaire
1 Closet Duduk Biasa Bh 826,000.00
2 Closet Jongkok Teraso Bh 125,000.00
3 Closet Jongkok Porselin Bh 250,000.00
4 Wastapel (KW 1 Super) Bh 2,375,000.00
5 Wastapel Biasa Bh 481,000.00
6 Urinoir Porselin (KW 1 Super) Bh 2,726,000.00
7 Pembatas urinoir ex. TOTO A 100 bh 1,375,000.00
8 Kitchen Sink Stainless Steel ex. TOTO bh 2,156,200.00
9 Closet Duduk (KW 1 Super) Bh 3,659,000.00
10 Saringan Air Besi Bh 114,000.00
11 Saringan Air Plastik Bh 26,000.00
12 Bak Cuci Piring Teraso Bh 390,000.00
13 Bak Cuci Piring Logam, 1 lubang Bh 520,000.00
14 Bak Cuci Piring Logam, 2 lubang Bh 650,000.00
15 Resesvoir Fybg Kapasitas 1 M3 Bh 3,886,000.00
16 Septictank Kapasitas 1 M3 + peresapan Bh 5,350,000.00
17 Septictank Kapasitas 2 M3 + peresapan Bh 7,645,000.00
18 Bak Fiberglass Kap 0.5 M3 Bh 521,000.00
19 Bak Fiberglass Kap 1.0 M3 Bh 1,244,000.00
20 Bak Mandi Plastik Kap. 0,5 M3 Bh 520,000.00
21 Bak Mandi Teraso 50 x 50 cm Bh 481,000.00
22 Bak Mandi Poseslin KW I Bh 470,000.00
23 Kran Shower bh 362,500.00
24 Kran Air 1/2" Bh 18,000.00
25 Kran Air 3/4" Bh 21,000.00
26 Floor Drain ex. TOTO TX 1 BV 3 bh 396,200.00
27 Floor Drain Bh 25,000.00
28 Roof Drain Metal Bh 45,000.00
29 Seal Tape Bh 6,000.00
30 Lem Pipa Kg 79,000.00
31 Klep 3/4" Bh 35,000.00
32 Plampung Air Otomatis Bh 155,000.00
33 Tandon Air Fyberglass Kapasitas 500 Liter vertikal Bh 1,425,000.00
34 Tandon Air Fyberglass Kapasitas 1000 Liter vertikal Bh 2,091,000.00
35 Tandon Air Fyberglass Kapasitas 2000 Liter vertikal Bh 10,154,000.00
36 Tandon Air Fyberglass Kapasitas 3000 Liter vertikal Bh 13,684,000.00
37 Tandon Air Fyberglass Kapasitas 4000 Liter vertikal Bh 19,904,000.00
38 Tandon Air Fyberglass Kapasitas 5000 Liter vertikal Bh 21,961,000.00
39 Tandon Air Fyberglass Kapasitas 1000 Liter horisontal Bh 39,808,000.00
40 Tandon Air Fyberglass Kapasitas 2000 Liter horisontal Bh 55,076,000.00
41 Tandon Air Fyberglass Kapasitas 3000 Liter horisontal Bh 65,707,000.00
42 Tandon Air Fyberglass Kapasitas 4000 Liter horisontal Bh 76,439,000.00
43 Wastapel Merk Ina (KW I Super) Bh 2,373,000.00
44 Tempat Sabun (KW I) Bh 68,000.00
45 Cermin + Acessories (Antik) Bh 130,000.00
46 Gantungan Handuk + Acessories Bh 170,000.00
47 Shower spray ex. TOTO TX 403 SBPIV bh 812,500.00
48 Shower ex. TOTO TR 309 SZ bh 562,500.00
49 Paper Holder ex. TOTO TIPE TS116R bh 593,700.00
50 soap holder ex. TOTO S 156N bh 156,200.00
51 hand railing stainless steel ex. TOTO TX 3A2 bh 937,500.00
52 Shower Splay + Acessories Bh 452,000.00
53 Shower Set + Acessories Bh 700,000.00
54 Hand Dryer + Acessories Bh 1,470,000.00
55 Gantungan Baju + Acessories Bh 243,000.00
56 Water Drain + Acesories Bh 68,000.00
57 Pintu Fiber Glass (Wc) Bh 848,000.00
58 Pembuatan dan Pemasangan Pintu jeruji besi Ø12mm + Rangka kosen besi siku M2 1,555,000.00
59 40.40.4 complit
60 Bath Tub Bh 6,786,000.00
61 Kitchen Sink 1 Bowl GS 5844 bh 1,562,500.00
62 Kran + asesories + Seal Tape set 687,500.00
63 Kitchen Sink Single Bowl Zenit Ris 1B 1D 86 with Kitchen Tap My 1 By TEKA bh 3,875,000.00
64 Mirror 100x120 cm bh 270,000.00
65 Siku alumunium m1 81,200.00
66 Spoel hoek bh 11,000,000.00
67 Kran Air Antik Bh 66,000.00
68 Kran Zink Bh 400,000.00
69 Kitchenzink Bh 350,000.00
70 Kran Dinding Bh 215,000.00
71 sumur pompa tangan terpasang Bh 1,753,000.00
Bahan Paku
1 Paku panjang 1 - 5 Cm Kg 33,000.00
2 Paku panjang 5 - 7 Cm Kg 28,000.00
3 Paku panjang 7 - 10 Cm Kg 28,000.00
4 Paku panjang 10 - 12 Cm Kg 28,000.00
5 Paku Sekrup Kg 35,000.00
6 Paku Seng Kg 45,000.00
7 Paku Asbes Kg 45,000.00
8 Skrup/Piles 1,5 Cm Doos Kecil 35,000.00
9 Skrup/Piles 2,0 Cm Doos Kecil 35,000.00
10 Paku Sumbat Bh 38,000.00
11 Baut Mur Bh 5,000.00
12 Mur baut 12 mm Bh 6,000.00
13 Mur baut 16 mm Bh 7,000.00
14 Baut Mur 18 mm Bh 8,000.00
15 Baut Mur 22 mm Bh 10,000.00
16 Besi Beugel U + Baut Mur Bh 39,000.00
17 Besi Beugel Plat + Baut Mur Bh 39,000.00
18 Paku Calsiboth Kg 35,000.00
19 Paku Baja Kg 85,000.00
20 Angker Kusen Bh 5,000.00
21 Paku Sekrup 5 cm Kg 35,000.00
22 Paku Sekrup 10 cm Kg 35,000.00
23 Paku Sekrup 1- 2,5 cm Kg 35,000.00
24 Skrup Fixer Bh 22,000.00
25 Ramset/ Dinabolt Kg 75,000.00
Bahan Tambahan
1 Flux Oil Ltr 40,000.00
2 Minyak pelumas Ltr 47,000.00
3 Olie SAE 100 Ltr 37,000.00
4 Olie SAE 30 Ltr 50,000.00
5 Olie SAE 40 Ltr 62,000.00
6 Olie SAE 90 Ltr 74,000.00
7 Sambungan Rumah 1" Set 3,090,000.00
8 Sambungan Rumah 1/2" Set 1,854,000.00
9 Sambungan Rumah 3/4" Set 2,162,000.00
10 Aspal (AC) Kg 11,500.00
11 Kayu Bakar M³ 197,000.00
12 Sewa Stamper Hari 169,800.00
13 Sewa Alat Bor Hari 205,000.00
14 Sewa Genset Hari 410,000.00
15 Sewa Mesin Las Hari 410,000.00
16 Aspal Emulsi Kg 8,700.00
17 Alat Bantu Bina Marga Set 3,392,800.00
18 Alat Bantu Pengairan Set 3,392,800.00
19 Minyak tanah Ltr 4,700.00
20 Solar Ltr 6,500.00
21 Bensin Ltr 6,500.00
22 Pertalite Ltr 7,800.00
23 Pertamax Ltr 9,500.00
24 Pagar BRC tinggi 1,20 m M' 118,000.00
25 Tiang BRC dia. 1,5 Buah 67,000.00
26 Three Colour Btg 45,000.00
27 Mesin Las Unit 16,964,000.00
28 Bor Listrik Unit 1,131,000.00
29 Mesin Pemotong Besi Bh 1,131,000.00
30 KWH Listrik Kwh 1,500.00
31 Mata Bor Bh 56,000.00
32 Pelicin/Lubrican Kg 120,000.00
33 Alat Bantu Penyetelan (Trucker) Set 113,000.00
34 Alat batu pekerja Ls 11,000.00
35 Blower Bh 540,000.00
36 Excause Van Bh 540,000.00
37 #REF! M3 600,000.00
37 Lataston Lapis Aus (HRS-WC) (gradasi senjang/semi senjang) Ton 1,600,000.00
38 Lapis Resap Pengikat - Aspal Cair (Prime Coat) Liter 12,500.00
39 Bahan anti pengelupasan (Aditif) Kg 56,000.00
Bahan Pipa
1 Pipa PVC ½" m 7,400.00
2 ¾" m 9,000.00
3 1" m 11,400.00
4 1 1/4" m 18,400.00
5 1½" m 23,900.00
6 2" m 35,500.00
7 2,5" m 45,600.00
8 3" m 65,100.00
9 4" m 94,900.00
10 5" m 149,800.00
11 6" m 197,900.00
12 8" m 307,900.00
13 10" m 437,500.00
14 12" m 625,100.00
15 14" m 879,500.00
16 16" m 1,099,400.00
Bahan Pipa
1 Pipa PVC ½" m 8,200.00
2 ¾" m 15,000.00
3 1" m 18,700.00
4 1 1/4" m 21,000.00
5 1½" m 28,000.00
6 2" m 41,000.00
7 2,5" m 60,000.00
8 3" m 83,000.00
9 4" m 121,000.00
10 6" m 255,000.00
11 8" m 415,000.00
12 10" m 668,000.00
Jenis Barang
1 Flange Socket PVC 1,5" Bh 137,000.00
2 2" Bh 177,000.00
3 3" Bh 253,000.00
4 4" Bh 292,000.00
5 6" Bh 674,000.00
6 8" Bh 1,185,000.00
7 10" Bh 2,658,000.00
8 12" Bh 5,121,000.00
1 Pengadaan pompa Submersible type Centrifugal kapasitas 3 Ltr/Dtk, H 100, 3 Phase Unit 44,557,000.00
2 Pengadaan pompa Submersible type Centrifugal kapasitas 5 Ltr/Dtk, H 120, 3 Phase Unit 57,925,000.00
3 Kontrol Panel Auto Unit 9,270,000.00
4 Pengadaan Kabel NYYHY Ø 4 x 2,5 mm m 44,000.00
5 Pengadaan Kabel NYYHY Ø 3 x 0,75 mm m 31,000.00
6 Pengadaan Water Level Control (WLC) Bh 42,000.00
7 Pengadaan Cord Holder (Pengikat Kabel) Bungkus 91,000.00
8 Pengadaan Pipa Pelindung Kabel m 31,000.00
9 Pemasangan dan Set Up Pompa Set 3,605,000.00
10 Kawat Sling 12 mm m 28,000.00
11 8 mm m 22,000.00
12 6 mm m 21,000.00
13 Pemasangan Kawat Sling 12 mm m 9,000.00
14 8 mm m 8,000.00
15 6 mm m 6,000.00
16 Stelan seling 12 mm Bh 536,000.00
17 8 mm Bh 381,000.00
18 6 mm Bh 137,000.00
19 Pengunci seling 12 mm Bh 72,000.00
20 8 mm Bh 52,000.00
21 6 mm Bh 33,000.00
22 Angker Besi 22 mm Bh 21,000.00
23 Pekerjaan Snai Pipa Bh 5,500.00
24 Coupling GI 1/2" Bh 12,000.00
PEKERJAAN PERSIAPAN
SNI.1 1 M2 Pembersihan Lapangan dan perataan
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
B BAHAN
C MATERIAL
Jumlah ( A + B + C ) 16,750.00
Keuntungan & Overhead 10 % 1,675.00
Jumlah ……………………… 18,425.00
Jumlah ( A + B + C ) 75,735.00
Keuntungan & Overhead 10 % 7,573.50
Jumlah ……………………… 83,308.50
Jumlah ( A + B + C ) 216,750.00
Keuntungan & Overhead 10 % 21,675.00
Jumlah ……………………… 238,425.00
C PERALATAN
Jumlah ( A + B + C ) 378,352.25
Keuntungan & Overhead 10 % 37,835.23
Jumlah ……………………… 416,187.48
C PERALATAN
Jumlah ( A + B + C ) 756,704.50
Keuntungan & Overhead 10 % 75,670.45
Jumlah ……………………… 832,374.95
C PERALATAN
Jumlah ( A + B + C ) 28,175.00
Keuntungan & Overhead 10 % 2,817.50
Jumlah ……………………… 30,992.50
C PERALATAN
Jumlah ( A + B + C ) 10,945.00
Keuntungan & Overhead 10 % 1,094.50
Jumlah ……………………… 12,039.50
C PERALATAN
Jumlah ( A + B + C ) 78,375.00
Keuntungan & Overhead 10 % 7,837.50
Jumlah ……………………… 86,212.50
SNI.10.b 1 M3 Galian Tanah Biasa sedalam 0.5 - 1 M' - Dengan mengunakan alat berat
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.750 OH Pekerja 100,000.00 75,000.00
0.025 OH Mandor 135,000.00 3,375.00
B BAHAN
C PERALATAN
0.010 Jam Alat Berat Galian dan keprasan 678,000.00 6,780.00
Jumlah ( A + B + C ) 85,155.00
Keuntungan & Overhead 10 % 8,515.50
Jumlah ……………………… 93,670.50
C PERALATAN
Jumlah ( A + B + C ) 96,075.00
Keuntungan & Overhead 10 % 9,607.50
Jumlah ……………………… 105,682.50
SNI.11.b 1 M3 Galian Tanah Biasa sedalam 2 M' - Dengan mengunakan alat berat
Koefisen satuan Uraian Harga satuan Jumlah harga
A TENAGA
0.900 OH Pekerja 100,000.00 90,000.00
0.045 OH Mandor 135,000.00 6,075.00
B BAHAN
C PERALATAN
0.010 Jam Alat Berat Galian dan keprasan 678,000.00 6,780.00
Jumlah ( A + B + C ) 102,855.00
Keuntungan & Overhead 10 % 10,285.50
Jumlah ……………………… 113,140.50
C PERALATAN
Jumlah ( A + B + C ) 114,045.00
Keuntungan & Overhead 10 % 11,404.50
Jumlah ……………………… 125,449.50
C PERALATAN
Jumlah ( A + B + C ) 104,320.00
Keuntungan & Overhead 10 % 10,432.00
Jumlah ……………………… 114,752.00
C PERALATAN
Jumlah ( A + B + C ) 158,100.00
Keuntungan & Overhead 10 % 15,810.00
Jumlah ……………………… 173,910.00
C PERALATAN
Jumlah ( A + B + C ) 126,075.00
Keuntungan & Overhead 10 % 12,607.50
Jumlah ……………………… 138,682.50
C PERALATAN
Jumlah ( A + B + C ) 5,675.00
Keuntungan & Overhead 10 % 567.50
Jumlah ……………………… 6,242.50
C PERALATAN
Jumlah ( A + B + C ) 28,375.00
Keuntungan & Overhead 10 % 2,837.50
Jumlah ……………………… 31,212.50
C PERALATAN
Jumlah ( A + B + C ) 56,750.00
Keuntungan & Overhead 10 % 5,675.00
Jumlah ……………………… 62,425.00
Jumlah ( A + B + C ) 201,950.00
Keuntungan & Overhead 10 % 20,195.00
Jumlah ……………………… 222,145.00
Jumlah ( A + B + C ) 173,575.00
Keuntungan & Overhead 10 % 17,357.50
Jumlah ……………………… 190,932.50
SNI.21 1 M3 Urug dengan pasir urug
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.200 M³ Pasir Urug 190,000.00 228,000.00
B TENAGA
0.300 OH Pekerja 100,000.00 30,000.00
0.010 OH Mandor 135,000.00 1,350.00
C PERALATAN
Jumlah ( A + B + C ) 259,350.00
Keuntungan & Overhead 10 % 25,935.00
Jumlah ……………………… 285,285.00
Jumlah ( A + B + C ) 312,775.00
Keuntungan & Overhead 10 % 31,277.50
Jumlah ……………………… 344,052.50
Jumlah ( A + B + C ) 495,045.00
Keuntungan & Overhead 10 % 49,504.50
Jumlah ……………………… 544,549.50
Jumlah ( A + B + C ) 929,625.00
Keuntungan & Overhead 10 % 92,962.50
Jumlah ……………………… 1,022,587.50
Jumlah ( A + B + C ) 889,005.00
Keuntungan & Overhead 10 % 88,900.50
Jumlah ……………………… 977,905.50
Jumlah ( A + B + C ) 860,445.00
Keuntungan & Overhead 10 % 86,044.50
Jumlah ……………………… 946,489.50
SNI.26 1 M3 Pasangan Pondasi Sumuran Ø100 cm
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.450 M³ Batu Kali Belah 15/20 cm 240,000.00 108,000.00
194.000 Kg Semen 1,700.00 329,800.00
0.312 M³ Pasir beton 350,000.00 109,200.00
0.468 M³ Kerikil 565,000.00 264,420.00
B TENAGA
0.800 OH Tukang Batu 135,000.00 108,000.00
0.080 OH Kepala Tukang Batu 150,000.00 12,000.00
2.400 OH Pekerja 100,000.00 240,000.00
0.119 OH Mandor 135,000.00 16,065.00
C PERALATAN
Jumlah ( A + B + C ) 1,187,485.00
Keuntungan & Overhead 10 % 118,748.50
Jumlah ……………………… 1,306,233.50
Jumlah ( A + B + C ) 505,365.00
Keuntungan & Overhead 10 % 50,536.50
Jumlah ……………………… 555,901.50
Jumlah ( A + B + C ) 535,365.00
Keuntungan & Overhead 10 % 53,536.50
Jumlah ……………………… 588,901.50
Jumlah ( A + B + C ) 685,365.00
Keuntungan & Overhead 10 % 68,536.50
Jumlah ……………………… 753,901.50
SNI.28 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 3 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
14.370 Kg Semen 1,700.00 24,429.00
0.040 M³ Pasir Pasang 220,000.00 8,800.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN
Jumlah ( A + B + C ) 146,754.00
Keuntungan & Overhead 10 % 14,675.40
Jumlah ……………………… 161,429.40
SNI.29.a 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 4 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
11.500 Kg Semen 1,700.00 19,550.00
0.043 M³ Pasir Pasang 220,000.00 9,460.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN
Jumlah ( A + B + C ) 142,535.00
Keuntungan & Overhead 10 % 14,253.50
Jumlah ……………………… 156,788.50
SNI.29.b 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 5 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
9.680 Kg Semen 1,700.00 16,456.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN
Jumlah ( A + B + C ) 139,881.00
Keuntungan & Overhead 10 % 13,988.10
Jumlah ……………………… 153,869.10
SNI.29.c 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 6 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
8.320 Kg Semen 1,700.00 14,144.00
0.049 M³ Pasir Pasang 220,000.00 10,780.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN
Jumlah ( A + B + C ) 138,449.00
Keuntungan & Overhead 10 % 13,844.90
Jumlah ……………………… 152,293.90
SNI.29.d 1 m2 Pas Bata Merah ukuran (5x11x22) cm tebal 1/2 bata, spesi 1 PC : 8 PP
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
70.000 Biji Bata Merah 950.00 66,500.00
6.500 Kg Semen 1,700.00 11,050.00
0.050 M³ Pasir Pasang 220,000.00 11,000.00
B TENAGA
0.100 OH Tukang Batu 135,000.00 13,500.00
0.010 OH Kepala Tukang 150,000.00 1,500.00
0.300 OH Pekerja 100,000.00 30,000.00
0.015 OH Mandor 135,000.00 2,025.00
C PERALATAN
Jumlah ( A + B + C ) 135,575.00
Keuntungan & Overhead 10 % 13,557.50
Jumlah ……………………… 149,132.50
Jumlah ( A + B + C ) 303,085.00
Keuntungan & Overhead 10 % 30,308.50
Jumlah ……………………… 333,393.50
Jumlah ( A + B + C ) 292,645.00
Keuntungan & Overhead 10 % 29,264.50
Jumlah ……………………… 321,909.50
Jumlah ( A + B + C ) 103,725.00
Keuntungan & Overhead 10 % 10,372.50
Jumlah ……………………… 114,097.50
Jumlah ( A + B + C ) 213,254.00
Keuntungan & Overhead 10 % 21,325.40
Jumlah ……………………… 234,579.40
Jumlah ( A + B + C ) 41,875.00
Keuntungan & Overhead 10 % 4,187.50
Jumlah ……………………… 46,062.50
Jumlah ( A + B + C ) 77,525.00
Keuntungan & Overhead 10 % 7,752.50
Jumlah ……………………… 85,277.50
Jumlah ( A + B + C ) 74,394.00
Keuntungan & Overhead 10 % 7,439.40
Jumlah ……………………… 81,833.40
Jumlah ( A + B + C ) 67,943.00
Keuntungan & Overhead 10 % 6,794.30
Jumlah ……………………… 74,737.30
Jumlah ( A + B + C ) 32,688.60
Keuntungan & Overhead 10 % 3,268.86
Jumlah ……………………… 35,957.46
Jumlah ( A + B + C ) 72,777.00
Keuntungan & Overhead 10 % 7,277.70
Jumlah ……………………… 80,054.70
Jumlah ( A + B + C ) 70,413.00
Keuntungan & Overhead 10 % 7,041.30
Jumlah ……………………… 77,454.30
Jumlah ( A + B + C ) 69,057.80
Keuntungan & Overhead 10 % 6,905.78
Jumlah ……………………… 75,963.58
Jumlah ( A + B + C ) 67,972.20
Keuntungan & Overhead 10 % 6,797.22
Jumlah ……………………… 74,769.42
Jumlah ( A + B + C ) 67,376.20
Keuntungan & Overhead 10 % 6,737.62
Jumlah ……………………… 74,113.82
Jumlah ( A + B + C ) 66,780.20
Keuntungan & Overhead 10 % 6,678.02
Jumlah ……………………… 73,458.22
Jumlah ( A + B + C ) 82,200.60
Keuntungan & Overhead 10 % 8,220.06
Jumlah ……………………… 90,420.66
Jumlah ( A + B + C ) 93,226.00
Keuntungan & Overhead 10 % 9,322.60
Jumlah ……………………… 102,548.60
Jumlah ( A + B + C ) 55,689.00
Keuntungan & Overhead 10 % 5,568.90
Jumlah ……………………… 61,257.90
Jumlah ( A + B + C ) 72,250.00
Keuntungan & Overhead 10 % 7,225.00
Jumlah ……………………… 79,475.00
Jumlah ( A + B + C ) 176,608.33
Keuntungan & Overhead 10 % 17,660.83
Jumlah ……………………… 194,269.17
Jumlah ( A + B + C ) 265,625.00
Keuntungan & Overhead 10 % 26,562.50
Jumlah ……………………… 292,187.50
Jumlah ( A + B + C ) 708,750.00
Keuntungan & Overhead 10 % 70,875.00
Jumlah ……………………… 779,625.00
Jumlah ( A + B + C ) 2,298,202.50
Keuntungan & Overhead 10 % 229,820.25
Jumlah ……………………… 2,528,022.75
SNI.41.4 Memasang Kitchen Sink Single Bowl Zenit Ris 1B 1D 86 with Kitchen Tap My 1 By TEKA
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 bh Kitchen Sink Single Bowl Zenit Ris 1B 1D 3,875,000.00 3,875,000.00
1.000 set Kran + asesories + Seal Tape 687,500.00 687,500.00
B TENAGA
0.300 OH Tukang Batu 135,000.00 40,500.00
0.030 OH Kepala Tukang Batu 150,000.00 4,500.00
0.030 OH Pekerja 100,000.00 3,000.00
0.002 OH Mandor 135,000.00 202.50
C PERALATAN
Jumlah ( A + B + C ) 4,610,702.50
Keuntungan & Overhead 10 % 461,070.25
Jumlah ……………………… 5,071,772.75
Jumlah ( A + B + C ) 318,202.50
Keuntungan & Overhead 10 % 31,820.25
Jumlah ……………………… 350,022.75
Jumlah ( A + B + C ) 193,975.00
Keuntungan & Overhead 10 % 19,397.50
Jumlah ……………………… 213,372.50
Jumlah ( A + B + C ) 223,975.00
Keuntungan & Overhead 10 % 22,397.50
Jumlah ……………………… 246,372.50
Jumlah ( A + B + C ) 263,975.00
Keuntungan & Overhead 10 % 26,397.50
Jumlah ……………………… 290,372.50
Jumlah ( A + B + C ) 306,100.00
Keuntungan & Overhead 10 % 30,610.00
Jumlah ……………………… 336,710.00
Jumlah ( A + B + C ) 316,100.00
Keuntungan & Overhead 10 % 31,610.00
Jumlah ……………………… 347,710.00
Jumlah ( A + B + C ) 356,100.00
Keuntungan & Overhead 10 % 35,610.00
Jumlah ……………………… 391,710.00
PEKERJAAN LANTAI & DINDING
SNI.46 1 M2 Pas. Lantai Tegel Abu-abu
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.000 m2 Tegel Abu-abu 62,500.00 62,500.00
11.870 kg PC 1,700.00 20,179.00
0.045 M³ Pasir Pasang 220,000.00 9,900.00
B TENAGA
0.035 OH Tukang Batu 135,000.00 4,725.00
0.013 OH Kepala Tukang 150,000.00 1,950.00
0.120 OH Pekerja 100,000.00 12,000.00
0.014 OH Mandor 135,000.00 1,890.00
C PERALATAN
Jumlah ( A + B + C ) 113,144.00
Keuntungan & Overhead 10 % 11,314.40
Jumlah ……………………… 124,458.40
Jumlah ( A + B + C ) 525,659.00
Keuntungan & Overhead 10 % 52,565.90
Jumlah ……………………… 578,224.90
Jumlah ( A + B + C ) 455,659.00
Keuntungan & Overhead 10 % 45,565.90
Jumlah ……………………… 501,224.90
Jumlah ( A + B + C ) 277,010.00
Keuntungan & Overhead 10 % 27,701.00
Jumlah ……………………… 304,711.00
Jumlah ( A + B + C ) 262,310.00
Keuntungan & Overhead 10 % 26,231.00
Jumlah ……………………… 288,541.00
Jumlah ( A + B + C ) 316,910.00
Keuntungan & Overhead 10 % 31,691.00
Jumlah ……………………… 348,601.00
Jumlah ( A + B + C ) 294,470.00
Keuntungan & Overhead 10 % 29,447.00
Jumlah ……………………… 323,917.00
Jumlah ( A + B + C ) 504,808.00
Keuntungan & Overhead 10 % 50,480.80
Jumlah ……………………… 555,288.80
Jumlah ( A + B + C ) 294,470.00
Keuntungan & Overhead 10 % 29,447.00
Jumlah ……………………… 323,917.00
Jumlah ( A + B + C ) 354,195.00
Keuntungan & Overhead 10 % 35,419.50
Jumlah ……………………… 389,614.50
Jumlah ( A + B + C ) 327,945.00
Keuntungan & Overhead 10 % 32,794.50
Jumlah ……………………… 360,739.50
Jumlah ( A + B + C ) 339,495.00
Keuntungan & Overhead 10 % 33,949.50
Jumlah ……………………… 373,444.50
Jumlah ( A + B + C ) 225,520.00
Keuntungan & Overhead 10 % 22,552.00
Jumlah ……………………… 248,072.00
Jumlah ( A + B + C ) 313,270.00
Keuntungan & Overhead 10 % 31,327.00
Jumlah ……………………… 344,597.00
Jumlah ( A + B + C ) 154,720.00
Keuntungan & Overhead 10 % 15,472.00
Jumlah ……………………… 170,192.00
Jumlah ( A + B + C ) 161,020.00
Keuntungan & Overhead 10 % 16,102.00
Jumlah ……………………… 177,122.00
Jumlah ( A + B + C ) 410,050.00
Keuntungan & Overhead 10 % 41,005.00
Jumlah ……………………… 451,055.00
Jumlah ( A + B + C ) 440,900.00
Keuntungan & Overhead 10 % 44,090.00
Jumlah ……………………… 484,990.00
Jumlah ( A + B + C ) 205,975.50
Keuntungan & Overhead 10 % 20,597.55
Jumlah ……………………… 226,573.05
Jumlah ( A + B + C ) 291,825.50
Keuntungan & Overhead 10 % 29,182.55
Jumlah ……………………… 321,008.05
Jumlah ( A + B + C ) 190,825.50
Keuntungan & Overhead 10 % 19,082.55
Jumlah ……………………… 209,908.05
Jumlah ( A + B + C ) 324,953.50
Keuntungan & Overhead 10 % 32,495.35
Jumlah ……………………… 357,448.85
Jumlah ( A + B + C ) 1,151,550.00
Keuntungan & Overhead 10 % 115,155.00
Jumlah ……………………… 1,266,705.00
Jumlah ( A + B + C ) 41,875.00
Keuntungan & Overhead 10 % 4,187.50
Jumlah ……………………… 46,062.50
Jumlah ( A + B + C ) 165,313.00
Keuntungan & Overhead 10 % 16,531.30
Jumlah ……………………… 181,844.30
Jumlah ( A + B + C ) 105,965.50
Keuntungan & Overhead 10 % 10,596.55
Jumlah ……………………… 116,562.05
Jumlah ( A + B + C ) 127,965.00
Keuntungan & Overhead 10 % 12,796.50
Jumlah ……………………… 140,761.50
Jumlah ( A + B + C ) 255,496.00
Keuntungan & Overhead 10 % 25,549.60
Jumlah ……………………… 281,045.60
Jumlah ( A + B + C ) 368,261.00
Keuntungan & Overhead 10 % 36,826.10
Jumlah ……………………… 405,087.10
Jumlah ( A + B + C ) 228,675.00
Keuntungan & Overhead 10 % 22,867.50
Jumlah ……………………… 251,542.50
Jumlah ( A + B + C ) 223,075.00
Keuntungan & Overhead 10 % 22,307.50
Jumlah ……………………… 245,382.50
Jumlah ( A + B + C ) 178,614.00
Keuntungan & Overhead 10 % 17,861.40
Jumlah ……………………… 196,475.40
SNI.102 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 200
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m3 Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,748,175.00
Keuntungan & Overhead 10 % 774,817.50
Jumlah ……………………… 8,522,992.50
SNI.103 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 200
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m3 Koral beton 735,000.00 757,785.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.840 OH Tukang besi 135,000.00 113,400.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.213 OH Mandor 135,000.00 28,755.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,276,655.00
Keuntungan & Overhead 10 % 627,665.50
Jumlah ……………………… 6,904,320.50
SNI.104 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 200
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
352.000 Kg Semen portland 1,700.00 598,400.00
0.731 m 3
Pasir beton 350,000.00 255,850.00
1.031 m 3
Koral beton 735,000.00 757,785.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,810,775.00
Keuntungan & Overhead 10 % 681,077.50
Jumlah ……………………… 7,491,852.50
SNI.106 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m 3
Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,322,710.00
Keuntungan & Overhead 10 % 432,271.00
Jumlah ……………………… 4,754,981.00
SNI.108 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m 3
Pasir beton 350,000.00 266,000.00
1.029 m 3
Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,067,060.00
Keuntungan & Overhead 10 % 506,706.00
Jumlah ……………………… 5,573,766.00
SNI.109 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,512,160.00
Keuntungan & Overhead 10 % 551,216.00
Jumlah ……………………… 6,063,376.00
SNI.110 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,402,360.00
Keuntungan & Overhead 10 % 640,236.00
Jumlah ……………………… 7,042,596.00
SNI.111 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,480,555.00
Keuntungan & Overhead 10 % 648,055.50
Jumlah ……………………… 7,128,610.50
SNI.112 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,925,655.00
Keuntungan & Overhead 10 % 692,565.50
Jumlah ……………………… 7,618,220.50
SNI.113 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,815,855.00
Keuntungan & Overhead 10 % 781,585.50
Jumlah ……………………… 8,597,440.50
SNI.114 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,377,355.00
Keuntungan & Overhead 10 % 637,735.50
Jumlah ……………………… 7,015,090.50
SNI.115 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m 3
Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,822,455.00
Keuntungan & Overhead 10 % 682,245.50
Jumlah ……………………… 7,504,700.50
SNI.116 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.192 OH Kepala Tukang 150,000.00 28,800.00
0.245 OH Mandor 135,000.00 33,075.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,712,655.00
Keuntungan & Overhead 10 % 771,265.50
Jumlah ……………………… 8,483,920.50
SNI.117 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.840 OH Tukang besi 135,000.00 113,400.00
0.136 OH Kepala Tukang 150,000.00 20,400.00
0.213 OH Mandor 135,000.00 28,755.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,241,135.00
Keuntungan & Overhead 10 % 624,113.50
Jumlah ……………………… 6,865,248.50
SNI.118 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 175
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
326.000 Kg Semen portland 1,700.00 554,200.00
0.760 m3 Pasir beton 350,000.00 266,000.00
1.029 m3 Koral beton 735,000.00 756,315.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,775,255.00
Keuntungan & Overhead 10 % 677,525.50
Jumlah ……………………… 7,452,780.50
SNI.120 1 M3 Pekerjaan Pondasi Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
1.500 kg Paku 5 cm - 12 cm 28,000.00 42,000.00
0.400 Ltr Minyak bekisting 18,000.00 7,200.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,281,640.00
Keuntungan & Overhead 10 % 428,164.00
Jumlah ……………………… 4,709,804.00
SNI.122 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,025,990.00
Keuntungan & Overhead 10 % 502,599.00
Jumlah ……………………… 5,528,589.00
SNI.123 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m 3
Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,471,090.00
Keuntungan & Overhead 10 % 547,109.00
Jumlah ……………………… 6,018,199.00
SNI.124 1 M3 Pekerjaan Sloof Beton Bertulang ( 200 Kg Besi + Bekisting) M-K 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m 3
Pasir beton 350,000.00 279,650.00
1.017 m 3
Koral beton 735,000.00 747,495.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.243 OH Pekerja 100,000.00 324,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.400 OH Tukang besi 135,000.00 189,000.00
0.185 OH Kepala Tukang 150,000.00 27,750.00
0.238 OH Mandor 135,000.00 32,130.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,361,290.00
Keuntungan & Overhead 10 % 636,129.00
Jumlah ……………………… 6,997,419.00
SNI.125 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.088 OH Tukang besi 135,000.00 11,812.50
0.061 OH Kepala Tukang 150,000.00 9,112.50
0.170 OH Mandor 135,000.00 22,950.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,315,285.00
Keuntungan & Overhead 10 % 631,528.50
Jumlah ……………………… 6,946,813.50
SNI.126 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.105 OH Tukang besi 135,000.00 14,175.00
0.063 OH Kepala Tukang 150,000.00 9,375.00
0.171 OH Mandor 135,000.00 23,085.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,735,545.00
Keuntungan & Overhead 10 % 673,554.50
Jumlah ……………………… 7,409,099.50
SNI.127 1 M3 Pekerjaan Kolom Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.140 OH Tukang besi 135,000.00 18,900.00
0.066 OH Kepala Tukang 150,000.00 9,900.00
0.173 OH Mandor 135,000.00 23,355.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,576,065.00
Keuntungan & Overhead 10 % 757,606.50
Jumlah ……………………… 8,333,671.50
SNI.128 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.088 OH Tukang besi 135,000.00 11,812.50
0.061 OH Kepala Tukang 150,000.00 9,112.50
0.170 OH Mandor 135,000.00 22,950.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,212,085.00
Keuntungan & Overhead 10 % 621,208.50
Jumlah ……………………… 6,833,293.50
SNI.129 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.105 OH Tukang besi 135,000.00 14,175.00
0.063 OH Kepala Tukang 150,000.00 9,375.00
0.171 OH Mandor 135,000.00 23,085.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,632,345.00
Keuntungan & Overhead 10 % 663,234.50
Jumlah ……………………… 7,295,579.50
SNI.130 1 M3 Pekerjaan Balok Beton Bertulang ( 200 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
200.000 Kg Besi Beton polos 16,000.00 3,200,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.383 OH Pekerja 100,000.00 338,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.140 OH Tukang besi 135,000.00 18,900.00
0.066 OH Kepala Tukang 150,000.00 9,900.00
0.173 OH Mandor 135,000.00 23,355.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 7,472,865.00
Keuntungan & Overhead 10 % 747,286.50
Jumlah ……………………… 8,220,151.50
SNI.131 1 M3 Pekerjaan Lantai Beton Bertulang ( 120 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
120.000 Kg Besi Beton polos 16,000.00 1,920,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.823 OH Pekerja 100,000.00 282,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.084 OH Tukang besi 135,000.00 11,340.00
0.060 OH Kepala Tukang 150,000.00 9,060.00
0.170 OH Mandor 135,000.00 22,923.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,080,833.00
Keuntungan & Overhead 10 % 608,083.30
Jumlah ……………………… 6,688,916.30
SNI.132 1 M3 Pekerjaan Lantai Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 150
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m 3
Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
299.000 Kg Semen portland 1,700.00 508,300.00
0.799 m3 Pasir beton 350,000.00 279,650.00
1.017 m3 Koral beton 735,000.00 747,495.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.105 OH Tukang besi 135,000.00 14,175.00
0.063 OH Kepala Tukang 150,000.00 9,375.00
0.171 OH Mandor 135,000.00 23,085.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,585,145.00
Keuntungan & Overhead 10 % 658,514.50
Jumlah ……………………… 7,243,659.50
SNI.136 1 M3 Pekerjaan Sloof Beton Bertulang ( 125 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m 3
Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.718 OH Pekerja 100,000.00 271,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.132 OH Kepala Tukang 150,000.00 19,875.00
0.208 OH Mandor 135,000.00 28,080.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 4,671,695.00
Keuntungan & Overhead 10 % 467,169.50
Jumlah ……………………… 5,138,864.50
SNI.137 1 M3 Pekerjaan Sloof Beton Bertulang ( 150 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.150 OH Kepala Tukang 150,000.00 22,500.00
0.218 OH Mandor 135,000.00 29,430.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,116,795.00
Keuntungan & Overhead 10 % 511,679.50
Jumlah ……………………… 5,628,474.50
SNI.138 1 M3 Pekerjaan Sloof Beton Bertulang ( 175 Kg Besi + Bekisting) M-K 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.270 m3 Kayu Kelas III (papan) 2,600,000.00 702,000.00
2.000 kg Paku 5 cm - 12 cm 28,000.00 56,000.00
0.600 Ltr Minyak bekisting 18,000.00 10,800.00
175.000 Kg Besi Beton polos 16,000.00 2,800,000.00
3.000 Kg Kawat beton 33,000.00 99,000.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.068 OH Pekerja 100,000.00 306,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.260 OH Tukang kayu 135,000.00 35,100.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.167 OH Kepala Tukang 150,000.00 25,125.00
0.228 OH Mandor 135,000.00 30,780.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,561,895.00
Keuntungan & Overhead 10 % 556,189.50
Jumlah ……………………… 6,118,084.50
SNI.139 1 M3 Pekerjaan Kolom Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,085,190.00
Keuntungan & Overhead 10 % 608,519.00
Jumlah ……………………… 6,693,709.00
SNI.140 1 M3 Pekerjaan Kolom Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,530,290.00
Keuntungan & Overhead 10 % 653,029.00
Jumlah ……………………… 7,183,319.00
SNI.141 1 M3 Pekerjaan Kolom Beton Bertulang ( 175 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu Kelas III 2,600,000.00 832,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi Beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.120 m3 Kayu balok kelas II 3,640,000.00 436,800.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
32.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 352,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.208 OH Pekerja 100,000.00 320,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,975,390.00
Keuntungan & Overhead 10 % 697,539.00
Jumlah ……………………… 7,672,929.00
SNI.142 1 M3 Pekerjaan Balok Beton Bertulang ( 125 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m3 Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
125.000 Kg Besi Beton polos 16,000.00 2,000,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.858 OH Pekerja 100,000.00 285,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.875 OH Tukang besi 135,000.00 118,125.00
0.139 OH Kepala Tukang 150,000.00 20,925.00
0.215 OH Mandor 135,000.00 29,025.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,981,990.00
Keuntungan & Overhead 10 % 598,199.00
Jumlah ……………………… 6,580,189.00
SNI.143 1 M3 Pekerjaan Balok Beton Bertulang ( 150 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi Beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.033 OH Pekerja 100,000.00 303,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.050 OH Tukang besi 135,000.00 141,750.00
0.157 OH Kepala Tukang 150,000.00 23,550.00
0.225 OH Mandor 135,000.00 30,375.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,427,090.00
Keuntungan & Overhead 10 % 642,709.00
Jumlah ……………………… 7,069,799.00
SNI.144 1 M3 Pekerjaan Balok Beton Bertulang ( 175 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.320 m 3
Kayu terentang kelas III 2,600,000.00 832,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
175.000 Kg Besi Beton polos 16,000.00 2,800,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 Koral beton 735,000.00 543,900.00
0.140 m3 Kayu balok kelas II 3,640,000.00 509,600.00
2.800 Lbr Kawat beton 158,000.00 442,400.00
16.000 Btg Dolken dia 8 cm - 4 m 11,000.00 176,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
3.208 OH Pekerja 100,000.00 320,800.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
1.225 OH Tukang besi 135,000.00 165,375.00
0.175 OH Kepala Tukang 150,000.00 26,175.00
0.235 OH Mandor 135,000.00 31,725.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,872,190.00
Keuntungan & Overhead 10 % 687,219.00
Jumlah ……………………… 7,559,409.00
SNI.145 1 M3 Pekerjaan Lantai Beton Bertulang ( 110 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
110.000 Kg Besi Beton polos 16,000.00 1,760,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m 3
Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.753 OH Pekerja 100,000.00 275,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.770 OH Tukang besi 135,000.00 103,950.00
0.129 OH Kepala Tukang 150,000.00 19,350.00
0.209 OH Mandor 135,000.00 28,215.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 5,667,730.00
Keuntungan & Overhead 10 % 566,773.00
Jumlah ……………………… 6,234,503.00
SNI.146 1 M3 Pekerjaan Lantai Beton Bertulang ( 130 Kg Besi + Bekisting) M-K- 125
Koefisen satuan Uraian Harga satuan Jumlah harga
A BAHAN
0.240 m3 Kayu terentang 2,600,000.00 624,000.00
3.200 Kg Paku biasa 2 " - 5 " 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
130.000 Kg Besi Beton polos 16,000.00 2,080,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m 3
Koral beton 735,000.00 543,900.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
24.000 Btg Dolken dia 8 cm - 4 m 11,000.00 264,000.00
215.000 Ltr Air kerja 250.00 53,750.00
B TENAGA
2.893 OH Pekerja 100,000.00 289,300.00
0.189 OH Tukang batu 135,000.00 25,515.00
0.330 OH Tukang kayu 135,000.00 44,550.00
0.910 OH Tukang besi 135,000.00 122,850.00
0.143 OH Kepala Tukang 150,000.00 21,450.00
0.217 OH Mandor 135,000.00 29,295.00
C PERALATAN
0.250 Hri Sewa Molen Kpst 0.3 m3 282,000.00 70,500.00
Jumlah ( A + B + C ) 6,023,810.00
Keuntungan & Overhead 10 % 602,381.00
Jumlah ……………………… 6,626,191.00
SNI.170 1 M3 Pek Dinding Plat Beton Bertulang ( 150 Kg Besi + Bekisting) BT, 1 Pc : 2 Ps : 3 Kr
0.240 m3 Kayu Kelas III 2,600,000.00 624,000.00
3.200 Kg Paku 5 cm - 12 cm 28,000.00 89,600.00
1.600 Ltr Minyak bekisting 18,000.00 28,800.00
150.000 Kg Besi beton polos 16,000.00 2,400,000.00
2.250 Kg Kawat beton 33,000.00 74,250.00
247.000 Kg Semen portland 1,700.00 419,900.00
0.621 m3 Pasir beton 350,000.00 217,350.00
0.740 m3 KR/Koral beton 565,000.00 418,100.00
0.160 m3 Kayu balok kelas II 3,640,000.00 582,400.00
2.800 Lbr Plywood tebal 9 mm 158,000.00 442,400.00
14.000 Btg Dolken kayu galam f (8-10) cm, 4 m 11,000.00 154,000.00
PEKERJAAN KAYU
SNI.174 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3
BAHAN
0.012 M³ Kayu Klas II 3,640,000.00 43,680.00
0.150 Kg Paku 7 - 12 cm 28,000.00 4,200.00
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 73,555.00
Keuntungan & Overhead 10 % 7,355.50
Jumlah ……………………… 80,910.50
SNI.177 1 M' Pekerjaan Papan Lisplank Satu Lapis, Kisi-Kisi 3/20 Kayu Klas II
BAHAN
0.007 M³ Papan Kayu Klas II 3,730,000.00 26,856.00
0.050 Kg Paku 7 - 12 cm 28,000.00 1,400.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 69,681.00
Keuntungan & Overhead 10 % 6,968.10
Jumlah ……………………… 76,649.10
SNI.178 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 3/20 ) Kayu Klas II
BAHAN
0.015 M³ Papan Kayu Klas II 3,730,000.00 54,085.00
0.060 Kg Paku 7 - 12 cm 28,000.00 1,680.00
TENAGA
0.250 OH Tukang Kayu 135,000.00 33,750.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.150 OH Pekerja 100,000.00 15,000.00
0.075 OH Mandor 135,000.00 10,125.00
Jumlah ( A + B + C ) 118,390.00
Keuntungan & Overhead 10 % 11,839.00
Jumlah ……………………… 130,229.00
SNI.179 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II
BAHAN
0.009 M³ Papan Kayu Klas II 3,730,000.00 32,078.00
0.050 Kg Paku 7 - 12 cm 28,000.00 1,400.00
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 80,978.00
Keuntungan & Overhead 10 % 8,097.80
Jumlah ……………………… 89,075.80
SNI.179.a 1 M' Memasang Kembali Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II
TENAGA
0.200 OH Tukang Kayu 135,000.00 27,000.00
0.025 OH Kepala Tukang Kayu 150,000.00 3,750.00
0.100 OH Pekerja 100,000.00 10,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 47,500.00
Keuntungan & Overhead 10 % 4,750.00
Jumlah ……………………… 52,250.00
SNI199 1 M2 Pekerjaan Daun Pintu / Jendela Panil dan Krepyak Kayu Klas II
BAHAN
0.140 M³ Papan Kayu Klas II 3,730,000.00 522,200.00
0.050 Kg Paku 1- 3 Cm 28,000.00 1,400.00
TENAGA
1.500 OH Tukang Kayu 135,000.00 202,500.00
0.150 OH Kepala Tukang Kayu 150,000.00 22,500.00
1.000 OH Pekerja 100,000.00 100,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 855,350.00
Keuntungan & Overhead 10 % 85,535.00
Jumlah ……………………… 940,885.00
SNI.200 1 M2 Pekerjaan Daun Pintu Panil dan Krepyak Kayu Klas II Lap. Formika
BAHAN
0.080 M³ Papan Kayu Klas II 3,730,000.00 298,400.00
0.050 Kg Paku 1- 3 Cm 28,000.00 1,400.00
0.500 Lbr Formika 192,000.00 96,000.00
TENAGA
1.500 OH Tukang Kayu 135,000.00 202,500.00
0.150 OH Kepala Tukang Kayu 150,000.00 22,500.00
1.000 OH Pekerja 100,000.00 100,000.00
0.050 OH Mandor 135,000.00 6,750.00
Jumlah ( A + B + C ) 727,550.00
Keuntungan & Overhead 10 % 72,755.00
Jumlah ……………………… 800,305.00
SNI.217,a 1m² Pasang Atap Genteng Bitumen Monoleyer model gelombang ex. Onduline
BAHAN
0.878 lbr Atap bitumen gelombang H : 3,0 mm 192,500.00 168,988.55
15.802 bh Paku fiser bitumen 1,500.00 23,702.29
TENAGA
0.100 OH Tukang Kayu 135,000.00 13,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.200 OH Pekerja 100,000.00 20,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 227,825.84
Keuntungan & Overhead 10 % 22,782.58
Jumlah ……………………… 250,608.42
SNI.228 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 2.5 mm ) lap. Butiran
BAHAN
1.100 m' Bubungan Genteng metal roof 65,000.00 71,500.00
0.050 kg Paku biasa 1/2"=1" 33,000.00 1,650.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 102,285.00
Keuntungan & Overhead 10 % 10,228.50
Jumlah ……………………… 112,513.50
SNI.229.b 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 3 mm ) lap. Butiran
BAHAN
1.100 m' Bubungan Genteng metal roof 85,000.00 93,500.00
0.050 kg Paku biasa 1/2"=1" 33,000.00 1,650.00
TENAGA
0.100 OH Tukang 135,000.00 13,500.00
0.010 OH Kepala tukang 150,000.00 1,500.00
0.140 OH Pekerja 100,000.00 14,000.00
0.001 OH Mandor 135,000.00 135.00
Jumlah ( A + B + C ) 124,285.00
Keuntungan & Overhead 10 % 12,428.50
Jumlah ……………………… 136,713.50
SNI.234.SP.1 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Putih polos
BAHAN
2.750 M' Besi Holow 40x40 zincromate 25,000.00 68,750.00
1.300 M2 PVC/ Shunda Plafond, 1.2 mm, Putih Polo 240,000.00 312,000.00
0.170 kg Paku Sekrup 35,000.00 5,950.00
TENAGA
0.200 OH Tukang 135,000.00 27,000.00
0.020 OH Kepala tukang 150,000.00 3,000.00
0.150 OH Pekerja 100,000.00 15,000.00
0.008 OH Mandor 135,000.00 1,012.50
Jumlah ( A + B + C ) 432,712.50
Keuntungan & Overhead 10 % 43,271.25
Jumlah ……………………… 475,983.75
SNI.243 Membuat 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
BAHAN
15.000 Kg Besi siku 30,000.00 450,000.00
32.800 Kg Besi plat baja 2 mm 22,000.00 721,600.00
0.050 Kg kawat las 160,000.00 8,000.00
TENAGA
1.050 OH Tukang Las Konstruksi 135,000.00 141,750.00
0.105 OH Kepala Tukang 150,000.00 15,750.00
1.050 OH Pekerja 100,000.00 105,000.00
0.052 OH Mandor 135,000.00 7,020.00
Jumlah ( A + B + C ) 1,449,120.00
Keuntungan & Overhead 10 % 144,912.00
Jumlah ……………………… 1,594,032.00
SNI.247.b Memasang 1 m2 Dinding kusen alluminium Natural + Kaca temreat 8 mm, polos
BAHAN
4.400 m Kusen Alumunium Natural 93,000.00 409,200.00
1.100 m2 Kaca Tempreat 8 mm, Polos 1,000,000.00 1,100,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,576,523.75
Keuntungan & Overhead 10 % 157,652.38
Jumlah ……………………… 1,734,176.13
SNI.247.c Memasang 1 m2 Dinding kusen alluminium Natural + Kaca temreat 8 mm, warna
BAHAN
4.400 m Kusen Alumunium Natural 93,000.00 409,200.00
1.100 m2 Kaca Tempreat 8 mm, Warna 1,100,000.00 1,210,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,686,523.75
Keuntungan & Overhead 10 % 168,652.38
Jumlah ……………………… 1,855,176.13
SNI.248.b Memasang 1 m2 Dinding kusen alluminium Warna + Kaca temreat 8 mm, polos
BAHAN
4.400 m Kusen Alumunium Warna 105,000.00 462,000.00
1.100 m2 Kaca Tempreat 8 mm, Polos 1,000,000.00 1,100,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.043 OH Tukang Alumunium 135,000.00 5,805.00
0.004 OH Kepala Tukang 150,000.00 645.00
0.043 OH Pekerja 100,000.00 4,300.00
0.002 OH Mandor 135,000.00 290.25
Jumlah ( A + B + C ) 1,618,540.25
Keuntungan & Overhead 10 % 161,854.03
Jumlah ……………………… 1,780,394.28
SNI.248.c Memasang 1 m2 Dinding kusen alluminium Warna + Kaca temreat 8 mm, warna
BAHAN
4.400 m Kusen Alumunium Warna 105,000.00 462,000.00
1.100 m2 Kaca Tempreat 8 mm, Warna 1,100,000.00 1,210,000.00
2.000 bh Skrup fixer 22,000.00 44,000.00
0.060 tube Sealant 25,000.00 1,500.00
TENAGA
0.085 OH Tukang Alumunium 135,000.00 11,475.00
0.009 OH Kepala Tukang 150,000.00 1,275.00
0.085 OH Pekerja 100,000.00 8,500.00
0.004 OH Mandor 135,000.00 573.75
Jumlah ( A + B + C ) 1,739,323.75
Keuntungan & Overhead 10 % 173,932.38
Jumlah ……………………… 1,913,256.13
PEKERJAAN PENGECATAN/FINISING
SNI.252 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Eksterior)
BAHAN
0.260 Kg Cat Tembok 125,000.00 32,500.00
0.100 Kg Plamir Tembok 49,000.00 4,900.00
0.100 Kg Cat Dasar 125,000.00 12,500.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 61,687.50
Keuntungan & Overhead 10 % 6,168.75
Jumlah ……………………… 67,856.25
SNI.252.e 1 m² Pengecatan Tembok Baru anti bakteri ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup anti bakteri)
BAHAN
0.100 Kg Plamir 49,000.00 4,900.00
0.100 Kg Cat Dasar 125,000.00 12,500.00
0.100 Lbr Ampelas 8,700.00 870.00
0.360 Kg Cat Tembok berbahan anti bakteri 125,000.00 45,000.00
TENAGA
0.063 OH Tukang Cat 135,000.00 8,505.00
0.006 OH Kepala Tukang Cat 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 75,057.50
Keuntungan & Overhead 10 % 7,505.75
Jumlah ……………………… 82,563.25
SNI.252.f 1 m² Memasang pelapis tembok dengan plat timbal hitam tebal 3 mm rangka hollow
BAHAN
1.100 m2 Plat timbah hitam 3 m 693,700.00 763,070.00
1.100 m2 Triplek rebal 6 mm 105,000.00 115,500.00
6.400 m1 Hollow 40 x 40 tebal 1 mm 25,000.00 160,000.00
4.400 m1 Hollow 20 x 40 tebal 1 mm 12,000.00 52,800.00
10.000 cm Pengelasan 1,200.00 12,000.00
TENAGA
0.063 OH Tukang Besi 135,000.00 8,505.00
0.006 OH Kepala Tukang Besi 150,000.00 945.00
0.020 OH Pekerja 100,000.00 2,000.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 1,115,157.50
Keuntungan & Overhead 10 % 111,515.75
Jumlah ……………………… 1,226,673.25
SNI.254 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Eksterior
BAHAN
0.200 Kg Cat Tembok 125,000.00 25,000.00
0.120 Kg Cat Dasar 125,000.00 15,000.00
TENAGA
0.042 OH Tukang Cat 135,000.00 5,670.00
0.004 OH Kepala Tukang Cat 150,000.00 630.00
0.028 OH Pekerja 100,000.00 2,800.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 49,437.50
Keuntungan & Overhead 10 % 4,943.75
Jumlah ……………………… 54,381.25
SNI.254.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Interior
BAHAN
0.200 Kg Cat Tembok 60,000.00 12,000.00
0.120 Kg Cat Dasar 60,000.00 7,200.00
TENAGA
0.042 OH Tukang Cat 135,000.00 5,670.00
0.004 OH Kepala Tukang Cat 150,000.00 630.00
0.028 OH Pekerja 100,000.00 2,800.00
0.003 OH Mandor 135,000.00 337.50
Jumlah ( A + B + C ) 28,637.50
Keuntungan & Overhead 10 % 2,863.75
Jumlah ……………………… 31,501.25
PEKERJAAN PAS.KUNCI
SNI.265.a 1 Bh. Pasang Kunci Tanam Biasa
BAHAN
1.000 bh Kunci tanam biasa 114,000.00 114,000.00
TENAGA
0.500 OH Tukang Kayu 135,000.00 67,500.00
0.010 OH Kepala Tukang Kayu 150,000.00 1,500.00
0.010 OH Pekerja 100,000.00 1,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 184,675.00
Keuntungan & Overhead 10 % 18,467.50
Jumlah ……………………… 203,142.50
SNI.IL.6e 1 bh Attenuator
BAHAN
1.000 bh Attenuator 30W ZV-303 162,800.00 162,800.00
1.000 ls Material bantu 10,000.00 10,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 217,475.00
Keuntungan & Overhead 10 % 21,747.50
Jumlah ……………………… 239,200.00
SNI.IL.7 1 unit Air terminal R-150 Early Streamer Emmission (ESE) technology
BAHAN
1.000 unit Air terminal R-150 10,450,000.00 10,450,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang listrik 120,000.00 24,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 10,499,675.00
Keuntungan & Overhead 10 % 1,049,967.50
Jumlah ……………………… 11,549,600.00
SNI.IL.7d 1 m' Pipa galvanis Ø 2.5" dudukan untuk air terminal + las
BAHAN
1.000 m1 Pipa galvanis Ø 2.5" 121,400.00 121,400.00
1.000 ls Perlengkapan (35% dari harga bahan) 42,490.00 42,490.00
TENAGA
0.180 OH Tukang Batu 135,000.00 24,300.00
0.108 OH Pekerja 100,000.00 10,800.00
0.018 OH Kepala Tukang batu 150,000.00 2,700.00
0.005 OH Mandor 135,000.00 729.00
Jumlah ( A + B + C ) 202,419.00
Keuntungan & Overhead 10 % 20,241.90
Jumlah ……………………… 222,650.00
SNI.IL.7g 1 bh Splitzen tembaga murni 3/4"( bukan lapisan ) untuk ground rod
BAHAN
1.000 bh Splitzen tembaga murni 3/4" 946,000.00 946,000.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 998,675.00
Keuntungan & Overhead 10 % 99,867.50
Jumlah ……………………… 1,098,500.00
SNI.IL.7h 1 Kg Timah
BAHAN
1.000 kg Timah 742,500.00 742,500.00
1.000 ls Material bantu 5,000.00 5,000.00
TENAGA
0.200 OH Tukang Batu 135,000.00 27,000.00
0.200 OH Pekerja 100,000.00 20,000.00
0.005 OH Mandor 135,000.00 675.00
Jumlah ( A + B + C ) 795,175.00
Keuntungan & Overhead 10 % 79,517.50
Jumlah ……………………… 874,650.00
SNI.IL.7i 1 m' Pipa PVC 3/4" for Kabel NYY 1x50 mm2
BAHAN
1.000 m1 Pipa PVC 3/4" for Kabel NYY 1x50 mm2 9,000.00 9,000.00
1.000 ls Perlengkapan (35% dari harga bahan) 3,150.00 3,150.00
TENAGA
0.060 OH Tukang Batu 135,000.00 8,100.00
0.036 OH Pekerja 100,000.00 3,600.00
0.006 OH Kepala tukang batu 150,000.00 900.00
0.002 OH Mandor 135,000.00 243.00
Jumlah ( A + B + C ) 24,993.00
Keuntungan & Overhead 10 % 2,499.30
Jumlah ……………………… 27,450.00
PEKERJAAN SANITAIR
SNI.283.B Memasang 1 Bh Kloset Duduk Biasa
BAHAN
1.000 Bh Kloset Duduk biasa 826,000.00 826,000.00
6% Harga Kloset Perlengkapan 49,560.00
TENAGA
1.100 OH Tukang Batu 135,000.00 148,500.00
0.001 OH Kepala Tukang Batu 150,000.00 150.00
3.300 OH Pekerja 100,000.00 330,000.00
0.160 OH Mandor 135,000.00 21,600.00
Jumlah ( A + B + C ) 1,375,810.00
Keuntungan & Overhead 10 % 137,581.00
Jumlah ……………………… 1,513,391.00
PEKERJAAN TAMBAHAN
SNI.Ls.1 1 M' Biaya Pengeboran air + Pipa Casing Ø 6''
1.000 m' Biaya Pengeboran air 1,074,000.00 1,074,000.00
1.000 m' Pipa PVC dia 6" 197,900.00 197,900.00
Perlengkapan (35 % x harga pipa) 69,265.00
1.000 Ls Biaya pemasangan sebesar 15% dari 29,685.00 29,685.00
harga material
Jumlah ( A + B + C ) 1,370,850.00
Keuntungan & Overhead 10 % 137,085.00
Jumlah ……………………… 1,507,935.00
Jumlah ( A + B + C ) 990,350.00
Keuntungan & Overhead 10 % 99,035.00
Jumlah ……………………… 1,089,385.00
Jumlah ( A + B + C ) 492,650.00
Keuntungan & Overhead 10 % 49,265.00
Jumlah ……………………… 541,915.00
Jumlah ( A + B + C ) 266,400.00
Keuntungan & Overhead 10 % 26,640.00
Jumlah ……………………… 293,040.00
SNI.Ls.5 1 Bh' Mesin tenaga disel YEP-3 + Pompa Ebra Ø Q3'' ( setara Yanmar )
1.000 zet Mesin tenaga disel 6.5 Pk YEP-3 + 28,782,000.00 28,782,000.00
Pompa Ebra Ø Q3'' ( setara Yanmar )
SNI.Ls.6 1 Bh' Pompa Submersible type Centrifugal kapasitas 3 Ltr/Dtk, H 100, 3 Phase
1.000 zet Pompa Submersible type Centrifugal 44,557,000.00 44,557,000.00
kapasitas 3 Ltr/Dtk, H 100, 3 Phase
Jumlah ( A + B + C ) 44,557,000.00
Keuntungan & Overhead 10 % 4,455,700.00
Jumlah ……………………… 49,012,700.00
SNI.Ls.7 1 Bh' Mesin tenaga Listerik disel + Pompa Outo matis Jet pam - 30 Complit pemasangan
1.000 zet Mesin disel+Pompa Outo matis Jet pam 25,904,000.00 25,904,000.00
ØINT OUT1.5'' - 30 Complit
Jumlah ( A + B + C ) 25,904,000.00
Keuntungan & Overhead 10 % 2,590,400.00
Jumlah ……………………… 28,494,400.00
SNI.Ls.8 1 Bh' Mesin tenaga disel + Pompa Outo matis ( setara sanyo ) ØINT 1''- 25 Complit pemasangan
1.000 zet Mesin disel+Pompa Outo matis ( setara 23,313,000.00 23,313,000.00
sanyo ) ØINT 1''- 20 Complit
Jumlah ( A + B + C ) 23,313,000.00
Keuntungan & Overhead 10 % 2,331,300.00
Jumlah ……………………… 25,644,300.00
REKAP ANALISA
NO URAIAN PEKERJAAN HARGA SATUAN
PEKERJAAN PERSIAPAN
SNI.1 1 M2 Pembersihan Lapangan dan perataan 18,425.000
SNI.2 1 M Pengukuran dan Pemasangan Bouwplank 83,308.500
SNI.3 1 Bh Pembuatan Papan nama Proyek 0,8 x 1,2 cm 238,425.000
SNI.4a 1 m2 Pagar Pengaman Lokasi Dari seng gelombang tinggi 2m 408,244.100
SNI.4b 1 m2 Pagar Pengaman Lokasi Dari seng gelombang tinggi 2m 377,085.500
SNI.5 1 m2 . Pembuatan Direksiket/Kantor sementara 1,005,642.000
SNI.147 1 M3 Pekerjaan Dinding Beton Bertulang ( 150 Kg Besi + Bekisting) M - K 225 7,901,613.500
SNI.148 1 M3 Pekerjaan Tangga Beton Bertulang ( 175 Kg Besi + Bekisting) M - K - 225 8,646,643.500
SNI.149 1 M3 Pekerjaan Tangga Beton Bertulang ( 150 Kg Besi + Bekisting) M - K - 225 8,074,533.500
SNI.150 1 M3 Pekerjaan Tangga Beton Bertulang ( 130 Kg Besi + Bekisting) M - K - 225 7,616,845.500
PEKERJAAN KAYU
SNI.174 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3 80,910.500
SNI.174.a 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 2/3 ( Expose ) 103,281.750
SNI.175 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 3/4 88,918.500
SNI.175.a 1 M2 Mengerjakan / Memasang Usuk 5/7, Reng 3/4 ( Expose ) 111,289.750
SNI.176.a 1 M2 Mengerjakan / Memasang Usuk 5/7 cm 62,242.950
SNI.176.b 1 M2 Mengerjakan / Memasang Kembali Usuk 5/7 cm 23,003.750
SNI.176.c 1 M2 Mengerjakan / Memasang Reng 3/4 cm 26,675.550
SNI.176.d 1 M2 Mengerjakan / Memasang Kembali Usuk 5/7 cm 9,858.750
SNI.177 1 M' Pekerjaan Papan Lisplank Satu Lapis, Kisi-Kisi 3/20 Kayu Klas II 76,649.100
SNI.178 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 3/20 ) Kayu Klas II 130,229.000
SNI.179 1 M' Pekerjaan Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II 89,075.800
SNI.179.a 1 M' Memasang Kembali Papan Lisplank Dua Lapis ( 2 x 2/20 ) Kayu Klas II 52,250.000
SNI.180 1 M' Pekerjaan Papan Reuter (2/20) 53,748.200
SNI.181 1 M' Mengerjakan Talang Karet 238,672.500
SNI.182.a 1 M' Mengerjakan Talang datar/ jurai Seng BjLs 20 219,037.500
SNI.182.b 1 M' Mengerjakan Talang 1/2 lingkaran Seng BjLs 20 171,820.000
SNI.183 1 M3 Pekerjaan Kayu Kuda - Kuda, Gording Kayu Klas II 6,527,620.000
SNI.184 1 M3 Pekerjaan Kayu Kuda - Kuda, Gording Kayu Klas II (Expose) 8,004,590.000
SNI.185 1 M3 Pekerjaan Kayu Konsol, Tiang Kayu Klas II 7,556,890.000
SNI.186 1 M' Pasang Kasiplank ukuran (0.8x20), 1 Lapis 70,482.500
SNI.187 1 M' Pasang Kasiplank ukuran (0.8x20), 2 Lapis 105,723.750
SNI.188 1 M3 Pekerjaan Kayu Konsol, Tiang Kayu Klas II (Expose) 7,861,590.000
SNI.189 1 M3 Pekerjaan Kayu Kusen Pintu dan Jendela 8,605,850.000
SNI.190 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca 3 mm 664,136.000
SNI.191 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca 5 mm 694,936.000
SNI.192 1 M2 Pekerjaan Memasang Kaca Mati 3 mm Pintu / Jendela 163,857.375
SNI.193 1 M2 Pekerjaan Memasang Kaca Mati 5 mm Pintu / Jendela 197,737.375
SNI.193.8 1 M2 Pekerjaan Memasang Kaca Mati 8 mm Pintu / Jendela 250,977.375
SNI.194 1 M2 Pekerjaan Memasang Alumunium strip 8 mm 810,276.500
SNI.195 1 M2 Pekerjaan Daun Pintu dan Jendela Kaca Tempered 8 mm 1,639,836.000
SNI.195.a 1 M2 Pekerjaan Memasang Kaca Cermin 5 mm 231,001.375
SNI.196 1 M2 Pekerjaan Memasang Glass Blok 1,541,658.800
SNI.197 1 M2 Pekerjaan Memasang Kaca Mati Riben 5 mm Pintu / Jendela 225,567.375
SNI.197.a 1 M2 Pekerjaan Memasang Kaca Mati Buram 5 mm Pintu / Jendela 287,277.375
SNI.198 1 M2 Pekerjaan Memasang Kaca Mati Tempered 8 mm Pintu / Jendela 1,237,127.375
SNI199 1 M2 Pekerjaan Daun Pintu / Jendela Panil dan Krepyak Kayu Klas II 940,885.000
SNI.200 1 M2 Pekerjaan Daun Pintu Panil dan Krepyak Kayu Klas II Lap. Formika 800,305.000
SNI.201 1 M2 Pekerjaan Ram Jalusi 925,430.000
SNI.202 1 M2 Pekerjaan Ram Jalusi Mati Kusen 640,337.500
SNI.203 1 M2 Pekerjaan Jendela Nako/ Tralis 850,558.500
SNI.204 1 M2 Mengerjakan Daun Pintu Double Teakwood 3 mm 780,604.000
SNI.206 1 M2 Pekerjaan Pintu Double Tripleks 3 mm 794,904.000
SNI.208 1 M2 Pekerjaan Pintu Teakwood Lapis Formika 996,204.000
SNI.209 1 M2 Pekerjaan Pintu Triplek Lapis Formika 560,604.000
SNI.210 1 M2 Pekerjaan Pasang Kawat Gerawang 54,920.250
SNI.211 1 M2 Pekerjaan Pasang Jeruji Besi Pintu 727,879.625
SNI.212 1 M2 Pekerjaan Pasang Kawat Duri 207,234.500
SNI.213 1 M2 Pekerjaan Pagar besi Hollow (stenlistail) 1,409,329.625
SNI.214 1 M2 Pekerjaan Pagar besi Hollow 599,729.625
SNI.214.1 1 M2 Pekerjaan Pagar/ Dinding besi Hollow 100 x 50 mm 1,001,009.625
SNI.214.A 1 M2 Pekerjaan Pintu Pagar besi (dia. 16 mm) 1,279,529.625
SNI.214.B 1 M2 Pekerjaan Pagar besi (dia. 16 mm) 1,169,529.625
PEKERJAAN ATAP
SNI.215 1 M2 Pekerjaan Atap Genteng Lokal 81,625.500
SNI.216 1 M2 Pekerjaan Bubungan Genteng Lokal 144,881.000
SNI.217 1 M2 Pekerjaan Atap Genteng Pejaten Bali 134,645.500
SNI.217,a 1m² Pasang Atap Genteng Bitumen Monoleyer model gelombang ex. Onduline 250,608.424
SNI.218 1 M2 Pekerjaan Bubungan Genteng Pejaten Bali 147,851.000
SNI.218.a 1 m Pemasangan nok bitumen Monolayer 190,734.500
SNI.219.0.25 1 M2 Pekerjaan Atap Trimdeck 0.25 TCT (Spandek) 194,132.400
SNI.219.0.30 1 M2 Pekerjaan Atap Trimdeck 0.30 TCT (Spandek) 206,232.400
SNI.219.0.35 1 M2 Pekerjaan Atap Trimdeck 0.35 TCT (Spandek) 235,272.400
SNI.220 1 M' Pekerjaan Memasang Bubungan Trimdeck 0.35 TCT (Spandek) 104,493.400
SNI.221.a 1 M2 Pekerjaan Atap Genteng Kodok 181,395.500
SNI.221.b 1 M2 Pekerjaan Atap Genteng kanmuri full flat 257,845.500
SNI.222.a 1 M2 Pekerjaan Bubungan Genteng Kodok 135,751.000
SNI.222.b 1 M2 Pekerjaan Bubungan Genteng kanmuri full flat 287,001.000
SNI.223 1 M2 Pekerjaan Atap Seng Gelombang BJLS 20 127,627.500
SNI.224 1 M' Memasang Bubungan Seng BJLS 20 101,887.500
SNI.225 1 M2 Pekerjaan Atap Asbes Gelombang Kecil 100,424.500
SNI.226 1 M' Memasang Bubungan Asbes Gelombang Kecil 91,784.000
SNI.227 1 m2 Mengerjakan atap genteng Metalroof ( Tebal 2.5 mm ) lapisan butiran 138,308.500
SNI.228 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 2.5 mm ) lap. Butiran 112,513.500
SNI.229.a 1 m2 Mengerjakan atap genteng Metalroof ( Tebal 3 mm ) lapisan butiran 174,608.500
SNI.229.b 1 m' Mengerjakan bubungan Genteng Metal roof ( Tebal 3 mm ) lap. Butiran 136,713.500
SNI.230 1 m2 Mengerjakan atap genteng Metal ( Tebal 2.5 mm ) Sakura 112,348.500
SNI.231 1 m' Mengerjakan bubungan Genteng Metal ( Tebal 2.5 mm ) 84,683.500
SNI.232 1 m2 Mengerjakan Plafond Gypsum Board, tebal 9 mm + rangka kayu 171,930.000
SNI.233.a 1 m' Mengerjakan List Plafond Gypsum Board Type I 68,025.100
SNI.233.b 1 m' Mengerjakan List Plafond Gypsum Board Type II 53,010.100
SNI.234 1 m2 Mengerjakan Plafond Gypsum Rangka Hollow 40x40 Zincromate 247,465.350
SNI.234.a 1 m2 Memasang langit-langit WPC , rangka metal furing 890,113.448
SNI.234.b 1 m2 Pasang Atap Kaca Laminasi / Laminated 12 mm rangka hollow 2,539,394.000
SNI.234.c 1 m2 Pasang Kaca Tempered Clear T=10 1,653,894.000
SNI.234.d 1 m2 Pasang Atap Kanopi GRC gelombang 245,113.000
SNI.234.SP.1 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Putih polos 475,983.750
SNI.234.SP.2 1 m2 Mengerjakan PVC/Sunda Plafond Rangka Hollow 40x40 Zincromate, Warna 518,883.750
SNI.234.AQ 1 m2 Mengerjakan Plafond Akustik Rangka Alumunium 408,498.750
SNI.235.a 1 M2 Pekerjaan Plafond Tripleks 3 mm + Rangka kayu 157,426.500
SNI.235.b 1 M2 Pekerjaan Plafond Tripleks 5 mm + Rangka kayu 173,514.000
SNI.235.c 1 M2 Pekerjaan Rangka Langit-langit 114,460.500
SNI.235.d 1 M2 Pekerjaan Plafond Tripleks 5 mm 59,053.500
SNI.236.a 1 M2 Pekerjaan Plafond Miring Tripleks 3 mm + Rangka kayu 128,782.500
SNI.236.b 1 M2 Pekerjaan Plafond Miring Tripleks 5 mm + Rangka kayu 144,870.000
SNI.237.a 1 M2 Pekerjaan Dinding Double Tripleks 3 mm + Rangka kayu 185,196.000
SNI.237.b 1 M2 Pekerjaan Dinding Double Tripleks 5 mm + Rangka kayu 217,371.000
SNI.238 1 M' Pekerjaan List Plafond Kayu Profil 4/4 cm 30,728.500
SNI.239 1 M' Pekerjaan List Plafond Kayu Profil 2/4 cm 24,953.500
PEKERJAAN PENGECATAN/FINISING
SNI.252 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Eksterior) 67,856.250
SNI.252.a 1 M2 Pekerjaan Cat Tembok Baru 1 x Dasar, 2 x Cat, (Interior) 42,116.250
SNI.252.b 1 M2 Pekerjaan Cat Plafond Baru 1 x Dasar, 2 x Cat 65,065.000
SNI.252.c 1 M2 Pekerjaan Cat Dak Beton, (Water Proofing/ Sunscreen) 31,556.250
SNI.252.d 1 M2 Pekerjaan Cat Dak Beton, (Water Proofing/ Sunscreen) 241,502.250
SNI.252.e 1 m² Pengecatan Tembok Baru anti bakteri ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup anti bakteri 82,563.250
SNI.252.f 1 m² Memasang pelapis tembok dengan plat timbal hitam tebal 3 mm rangka hollow 1,226,673.250
SNI.252.g 1 m² Measang pelapis tembak dengan HPL 109,150.250
SNI.252.h 1 m² Pemasangan Wall Paper 182,366.250
SNI.252.i 1 m2 Pengecatan Cat Tekstur Fin. Kamprot Halus 507,966.250
SNI.253 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Berjamur ) - Lama, Eksterior 90,103.750
SNI.253.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Berjamur ) - Lama, Interior 68,653.750
SNI.254 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Eksterior 54,381.250
SNI.254.a 1 M2 Pekerjaan Cat Tembok 1 x Cat ( Tembok Tak Berjamur ) - Lama, Interior 31,501.250
SNI.254.b 1 M2 Pekerjaan Cat Plafond Lama 1 x Dasar, 2 x Cat 57,035.000
SNI.255 1 M2 Pekerjaan cat Genteng 68,853.400
SNI.256 1 M2 Pekerjaan Cat Kayu 1 x Meni, 2 x Cat 60,524.750
SNI.257 1 M2 Pekerjaan Cat Kayu, 1 x Cat 54,238.250
SNI.258 1 M2 Pekerjaan Cat paving Blok 38,557.200
SNI.259 1 M2 Mendempul dan Menggosok Kayu 17,630.250
SNI.260 1 M2 Pekerjaan Politur 2 Kali 51,567.450
SNI.261 1 M2 Mengecat Besi 1 x Meni, 2 x Cat 65,285.000
SNI.262 1 M2 Mengecat Atap Seng Gelombang 47,451.800
SNI.263 1 M2 Pekerjaan Pelaburan Bidang Kayu dengan Teak Oil 22,294.250
SNI.264 1 M2 Mengeter Kayu 2x 37,301.000
PEKERJAAN KUNCI
SNI.265.a 1 Bh. Pasang Kunci Tanam Biasa 203,142.500
SNI.265.b 1 Bh. Pasang Kunci Tanam Mutu Menengah 258,142.500
SNI.265.c 1 Bh. Pasang Kunci Tanam Mutu Tinggi 688,242.500
SNI.266 1 Bh. Pasang Kunci Tanam Kamar Mandi 189,296.250
SNI.267 1 Bh. Pasang Engsel Pintu 48,511.375
SNI.268 1 Bh. Pasang Engsel Jendela 35,274.250
SNI.268.1 1 Bh. Pasang Grendel Besar 42,974.250
SNI.268.2 1 Bh. Pasang Grendel Kecil 31,974.250
SNI.269 1 Bh. Pasang Kait Angin Besar 40,811.375
SNI.270 1 Bh. Pasang Kait Angin Kecil 98,271.250
SNI.271 1 Bh. Pasang Kunci Selot Besar 116,674.250
SNI.272 1 Bh. Pasang Kunci Selot Kecil 112,348.500
SNI.273 1 Bh. Pasang Beugel U 44,661.375
SNI.274 1 Bh. Pasang Beugel Plat 44,661.375
SNI.275 1 Bh. Pasang Angker Dia 12 MM 7,261.375
SNI.276.a 1 Bh. Pas. Baut Mur 7,261.375
SNI.276.b 1 Bh. Pas. Baut Mur 12 mm 8,361.375
SNI.276.c 1 Bh. Pas. Baut Mur 16 mm 9,461.375
SNI.276.d 1 Bh. Pas. Baut Mur 18 mm 10,561.375
SNI.276.e 1 Bh. Pas. Baut Mur 22 mm 12,761.375
SNI.278.a 1 Bh. Pasang Door Closer 355,337.125
SNI.278.b 1 Bh. Pasang Door Stoper 159,537.125
SNI.279 1 Bh. Pasang Pegangan Pintu/ Door Holder, (Pull Handle) 374,037.125
SNI.280 1 Bh. Pasang Kunci Silender 157,337.125
SNI.281 1 Bh. Pasang Rel Pintu Dorong 134,237.125
SNI.282 1 Bh. Pasang Pintu Feber glass (Wc) 1,020,837.125
PEKERJAAN SANITAIR
SNI.283.B Memasang 1 Bh Kloset Duduk Biasa 1,513,391.000
SNI.283.K Memasang 1 Bh Kloset Duduk (KW 1 Super) 4,816,669.000
SNI.283.a Memasang 1 Bh Kloset Jongkok Porselon 892,650.000
SNI.283.b Memasang 1 Bh Kloset Jongkok Teraso 557,040.000
SNI.284 Memasang 1 Bh Wastafel Biasa 993,157.000
SNI.285 Memasang 1 Bh Wastafel (KW 1 Super) 3,326,565.000
SNI.286 Memasang 1 buah Urinoir ex. TOTO U 57 M 3,482,006.000
SNI.286.a Memasang 1 bh Pembatas Urinoir ex. TOTO A 100 1,530,842.500
SNI.286.b Memasang 1 buah Kitchen Sink Stainless Steel ex. TOTO 2,654,324.200
SNI.286.1 Memasang 1 Bh Bak Cuci Piring Logam, 1 lubang 699,822.750
SNI.286.2 Memasang 1 Bh Bak Cuci Piring Logam, 2 lubang 842,822.750
SNI.287 Memasang 1 Bh Bak Mandi Teraso 913,000.000
SNI.288 Memasang 1 Bh Bak Mandi Fiberglass 1,380,643.000
SNI.289 Memasang 1 Bh Bak Mandi Plastik 1,379,345.000
SNI.290 Memasang 1 Bh Kran Dia. 3/4" atau 1/2" 38,307.500
SNI.290.a Memasang 1 bh Kran ex. TOTO T2613 417,257.500
SNI.291 Memasang 1 Bh Floor Drain 45,842.500
SNI.291.a Memasang 1 bh Floor Drain ex. TOTO TX 1 BV 3 454,162.500
SNI.292 Memasang 1 Bh Saringan Air Besi 143,742.500
SNI.292.1 Memasang 1 bh Shower spray ex. TOTO TX 403 SBPIV 912,257.500
SNI.292.2 Memasang 1 bh Spoel hoek 12,210,082.500
SNI.292.3 Memasang 1 bh shower ex. TOTO TR 309 SZ 637,257.500
SNI.292.4 Memasang 1 bh Paper Holder ex. TOTO TIPE TS116R 671,412.500
SNI.292.5 Memasang 1 bh soap holder ex. TOTO S 156N 190,162.500
SNI.292.6 Memasang 1 bh hand railing stainless steel ex. TOTO TX 3A2 1,049,592.500
SNI.293.a Memasang 1 Bh Tandon Air kap. 500 Liter 1,585,842.500
SNI.293.b Memasang 1 Bh Tandon Air kap. 1000 Liter 2,318,442.500
SNI.294.V Memasang 1 m' Pipa PVC AW dia 1/2" 25,116.300
SNI.295.V Memasang 1 m' Pipa PVC AW dia 3/4" 27,492.300
SNI.296.V Memasang 1 m' Pipa PVC AW dia 1" 31,056.300
SNI.297.V Memasang 1 m' Pipa PVC AW dia 1.5" 49,618.800
SNI.298.Va Memasang 1 m' Pipa PVC AW dia 2" 66,844.800
SNI.298.Vb Memasang 1 m' Pipa PVC AW dia 3" 110,800.800
SNI.298.Vc Memasang 1 m' Pipa PVC AW dia 4" 155,053.800
SNI.294.G Memasang 1 m' Pipa GI dia 1/2" 63,549.842
SNI.295.G Memasang 1 m' Pipa GI dia 3/4" 70,919.842
SNI.296.G Memasang 1 m' Pipa GI dia 1" 88,519.842
SNI.297.G Memasang 1 m' Pipa GI dia 1.5" 114,589.842
SNI.298.Ga Memasang 1 m' Pipa GI dia 2" 142,639.842
SNI.298.Gb Memasang 1 m' Pipa GI dia 3" 210,179.842
SNI.298.Gc Memasang 1 m' Pipa GI dia 4" 287,399.842
0 0 0.000
PEKERJAAN TAMBAHAN
SNI.Ls.1 1 M' Biaya Pengeboran air + Pipa Casing Ø 6'' 1,507,935.000
SNI.Ls.2 1 M' Biaya Pengeboran air + Pipa Casing Ø 4'' 1,089,385.000
SNI.Ls.3 1 M' Biaya Pengeboran air + Pipa Casing Ø 3'' 541,915.000
SNI.Ls.4 1 M' Biaya Pengeboran air + Pipa Casing Ø 2.5'' 293,040.000
SNI.Ls.5 1 Bh' Mesin tenaga disel YEP-3 + Pompa Ebra Ø Q3'' ( setara Yanmar ) 37,992,240.000
SNI.Ls.6 1 Bh' Pompa Submersible type Centrifugal kapasitas 3 Ltr/Dtk, H 100, 3 Phase 49,012,700.000
SNI.Ls.7 1 Bh' Mesin tenaga Listerik disel + Pompa Outo matis Jet pam - 30 Complit pemasangan 28,494,400.000
SNI.Ls.8 1 Bh' Mesin tenaga disel + Pompa Outo matis ( setara sanyo ) ØINT 1''- 25 Complit pemasangan 25,644,300.000