BACK UP VOLUME COR BALOK,PLAT LT.

No. Uraian Pekerjaan P L T titik Volume Sat Keterangan

1 BALOK LT. 3
BI-1A 1.70 0.20 0.35 0.02 0.12 1.00 0.02 m³ Beton K325 Nfa
BI-1 4.48 0.30 0.35 0.02 0.12 1.00 0.37 m³ Beton K325 Nfa
BI-2 52.55 0.30 0.60 0.02 0.12 1.00 9.36 m³ Beton K325 Nfa
BI-3 23.00 0.30 0.65 0.02 0.12 1.00 4.39 m³ Beton K325 Nfa
BA1 35.36 0.20 0.30 0.02 0.12 1.00 2.02 m³ Beton K325 Nfa
BA2 31.16 0.20 0.35 0.02 0.12 1.00 2.08 m³ Beton K325 Nfa
BA4 3.11 0.25 0.55 0.02 0.12 1.00 0.33 m³ Beton K325 Nfa
BA6 35.72 0.25 0.60 0.02 0.12 1.00 5.26 m³ Beton K325 Nfa
BA7 3.15 0.25 0.40 0.02 0.12 1.00 0.22 m³ Beton K325 Nfa
KS1 1.00 0.30 0.35 0.02 0.12 1.00 0.01 m³ Beton K325 Nfa
KS2 1.00 0.25 0.35 0.02 0.12 1.00 (0.01) m³ Beton K325 Nfa

2 PLAT LANTAI LT. 3 26.99 m³ Beton K325 Nfa

NB : Kebutuhan cor balok,plat lt. 3

BALOK LT. 3 24.03 m³


PLAT LT. 3 26.99 m³
SUB TOT. 51.02 m³
BACK UP VOLUME COR BALOK,PLAT RAMP TANGGA DAN KOLOM STRUKTUR LT. 2

No. Uraian Pekerjaan P L T titik Volume Sat Keterangan

3 KOLOM STRUKTUR LT. 2


KOLOM STRUKTUR LT. 2 0.52 0.52 3.30 14.00 12.49 m³ Beton K325 Nfa
4 BALOK TANGGA 1 Beton K325 Nfa
BALOK BT 1 7.87 0.20 0.40 0.12 1.00 0.51 m³ Beton K325 Nfa
BALOK BT 2 6.00 0.25 0.55 0.12 1.00 0.71 m³ Beton K325 Nfa
5 BALOK TANGGA 2 Beton K325 Nfa
BALOK BT 1 2.50 0.20 0.40 0.12 1.00 0.08 m³ Beton K325 Nfa
BALOK BT 2 8.55 0.25 0.55 0.12 1.00 1.06 m³ Beton K325 Nfa
6 PLAT TANGGA 1
PLAT 10.80 5.20 0.12 1.00 6.74 m³ Beton K325 Nfa
ANAK TANGGA 1.75 0.30 0.17 22.00 0.96 m³ Beton K325 Nfa
7 PLAT TANGGA 2
PLAT 9.10 4.53 0.12 1.00 4.94 m³ Beton K325 Nfa
ANAK TANGGA 1.50 0.30 0.17 20.00 0.75 m³ Beton K325 Nfa
8 PILE CAB TANGGA 1 DAN 2 1.75 0.30 0.65 2.00 0.68 m³ Beton K325 Nfa
SLOOF TANGGA 1 DAN 2 1.75 0.30 0.60 2.00 0.63 m³ Beton K325 Nfa

NB : Kebutuhan cor balok, plat tangga 1-2 dan kolom struktur lt. 2

KOLOM STRUKTUR LT. 2 12.49 m³


BALOK TANGGA 1 1.21 m³
BALOK TANGGA 2 1.14 m³
PLAT TANGGA 1 7.70 m³
PLAT TANGGA 2 5.69 m³
SUB TOT. 29.55 m³
Uraian Pekerjaan Volume Satuan Keterangan
COR BALOK DAN PLAT LT. 3 51.02 m3
COR KOLOM STRUKTUR LT. 2 DAN TANGGA 1 -2 29.55 m3
TOTAL : 80.57 m3
GAMBAR AREA COR BALOK, PLAT LT. 3
GAMBAR AREA COR BALOK, PLAT LT. 3


























CATATAN REVISI KETERANGAN M ENG ETA HUI / APP ROVED K OOR DIN ATOR K OOR DIN ATOR J UDUL GAMBAR SKALA PROYEK
R E VIS IONS NOT E             DR AW ING T I T LE S C ALE P R OJ E C T

NO. TGL. DETAIL REVISI PARAF


N O. D ATE DE T A IL O F REVISION S IG NA TURE


M ENG ETA HUI / APP ROVED K OORDIN ATOR D IG AM BAR
          T ANGGAL N O . L EMBAR JU M L A H LBR
        


GAMBAR AREA COR KOLOM LT. 2
GAMBAR AREA COR KOLOM LT. 2

























CATATAN REVISI KETERANGAN MENGETAHUI / APPROVED KOORDINATOR KOORDINATOR JUDUL GAMBAR SKALA PROYEK
R E V I S IO N S NOTE              D RA WIN G TITLE S CA L E P RO J E CT

NO. TGL. DETAIL REVISI PARAF


NO. D ATE D ETA IL O F REVISION S IG NA TU RE

  

MENGETAHUI / APPROVED KOOR DINATOR DIGAMBAR


          TANGGAL NO. LEMBAR J UMLAH LBR
          

  
GAMBAR AREA COR RAMP TANGGA
GAMBAR AREA COR TANGGA 1 dan 2

























CATATAN REVISI KETERANGAN MENGETAHUI / APPROVED KOORDINATOR KOORDINATOR JUDUL GAMBAR SKALA PROYEK
R E V IS I O N S NOTE                      D RA W IN G T IT L E S CA L E PRO JECT

NO. TGL. DETAIL REVISI PARAF


NO. D ATE D ETA IL O F REVISION S IG NA TU RE

  

MENGETAHUI / APPROVED KOORDINATOR DIGAMBAR


              TANGGAL NO. LEMBAR JUMLAH LBR
             

 