Anda di halaman 1dari 20

Gambar Alat

Crane 10-15 Ton


URAIAN ANALISA

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Crane 10-15 Ton
2 Tenaga Pw 138.00 HP
3 Kapasitas Cp 15.00 T/Jam
4 Alat a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 750,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 75,000,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 3,375,020.96 Rupiah

(0.002dll
b. Asuransi, x B)/W
= F 750.00 Rupiah

Biaya Pasti per Jam = E + F G 3,375,770.96 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 231,840.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 17,250,000.00 Rupiah

3 Biaya ((6.25%
bengkel dan 8.73%) x B)/W J 23,437.50 Rupiah

4 Biaya ((12.5%
perbaikandan 17.5%) x B)/W K 4,687,500.00 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 22,219,920.36 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T 25,595,691.31 Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga i 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

No. URAIAN KODE KOEF. SATUAN KET.

A URAIAN PERALATAN
1 Jenis Peralatan Track Loader 75-100 Hp
2 Tenaga Pw 75.00 HP
3 Kapasitas Cp 0.80 T/Jam
4 Alat a. Umur Ekonomis A 6.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 30,305,163,330.00 Rupiah

B BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 3,030,516,333.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C) x Modal
a. Biaya Pengembalian D)/W = E 136,373,311.96 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 30,305.16 Rupiah

Biaya PaE + F G 136,403,617.13 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 126,000.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 93,750.00 Rupiah

3 Biaya ((6.25%
bengkel dan 8.73%) x B)/W J 947,036.35 Rupiah

4 Biaya ((12.5%
perbaikandan 17.5%) x B)/W K 1,894,072.71 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 3,088,001.92 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T 139,491,619.05 Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga i 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Stone Crusher
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 60.00 T/Jam
4 Alat a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 17,232,000,000.00 Rupiah

B BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 1,723,200,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 77,544,481.49 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 17,232.00 Rupiah

Biaya Pasti per Jam = E + F G 77,561,713.49 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 168,000.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 125,000.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 538,500.00 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 1,077,000.00 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 1,935,642.86 Rupiah

D TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T 79,497,356.35 Rupiah

E LAIN - LAIN
1 Tingkat Suku Bunga i 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Concrete Pump
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 8.00 T/Jam
4 Alat a. Umur Ekonomis A 6.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 1,680,520,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 168,052,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 7,562,344.27 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 1,680.52 Rupiah

Biaya Pasti per Jam = E + F G 7,564,024.79 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 168,000.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 125,000.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 52,516.25 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 105,032.50 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 477,691.61 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T 8,041,716.40 Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga I 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Tronton
2 Tenaga Pw 608.00 HP
3 Kapasitas Cp 15.0 T/Jam
4 Alat a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.00 Jam
c. Harga Alat B 900,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 90,000,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 5,400,000.00 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 1,200.00 Rupiah

Biaya Pasti per Jam = E + F G 5,401,200.00 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 1,276,800.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 912,000.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 52,380.00 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 105,000.00 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 38,571.43 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 2,399,037.14 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga I 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Slip Form Paver
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 2.5 T/Jam
4 Alat a. Umur Ekonomis A 6.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 1,600,700,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 160,070,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 7,203,154.07 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 1,600.70 Rupiah

Biaya Pasti per Jam = E + F G 7,204,754.77 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 252,000.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 187,500.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 50,021.88 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 100,043.75 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 616,708.48 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T Rupiah


E. LAIN - LAIN
1 Tingkat Suku Bunga i 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Truck Mixer (Agitator)
2 Tenaga Pw 280.00 HP
3 Kapasitas Cp 5.0 T/Jam
4 Alat a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 600,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 60,000,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 2,700,016.76 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 600.00 Rupiah

Biaya Pasti per Jam = E + F G 2,700,616.76 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 470,400.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 350,000.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 18,750.00 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 37,500.00 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 14,285.71 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 905,221.43 Rupiah


D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga i 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg

URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Breaker
2 Tenaga Pw 138.00 HP
3 Kapasitas Cp 3.0 T/Jam
4 Alat a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 175,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 17,500,000.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 787,504.89 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 175.00 Rupiah

Biaya Pasti per Jam = E + F G 787,679.89 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 231,840.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 172,500.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 5,468.75 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 10,937.50 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah
Biaya Operasi per Jam (H+I+J+K+L+M) P 447,889.11 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga I 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Bat 0 Rp/kg

URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1 Jenis Peralatan Stresing Jack
2 Tenaga Pw 70.00 HP
3 Kapasitas Cp 15.0 T/Jam
4 Alat a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,800.00 Jam
c. Harga Alat B 979,447,760.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1 Nilai Sis=10% x B C 97,944,776.00 Rupiah

(i x (1+i)^A )/((1+i)^A−1)
Faktor
Angsur
2 D
an
Modal
= 10.00

3 Biaya Pasti per Jam:


((B −C)
a. Biaya Pengembalian x D)/W
Modal E 4,897,269.21 Rupiah

(0.002 dll
b. Asuransi, x B)/W
= F 1,088.28 Rupiah

Biaya Pasti per Jam = E + F G 4,898,357.48 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1 Bahan Bakar = (12% - 15%) x Pw x Ms H1 117,600.00 Rupiah

2 Pelumas = (2.5% - 3%) x Pa x Mp I 87,500.00 Rupiah

3 ((6.25% dan 8.73%)


Biaya bengkel x B)/W J 34,008.60 Rupiah

4 ((12.5% dan 17.5%)


Biaya perbaikan x B)/W K 6,801,720.56 Rupiah

5 Operator= ( 1 Orang/Jam ) x U1 L 14,285.71 Rupiah


6 Pembantu
= ( 3 Orang/Jam ) x U2 M 12,857.14 Rupiah

Biaya Operasi per Jam (H+I+J+K+L+M) P 7,067,972.02 Rupiah

D. TOTAL BIAYA SEWA ALAT/JAM = ( G + P ) T 11,966,329.50 Rupiah

E. LAIN - LAIN
1 Tingkat Suku Bunga I 10.00 % /Tahun
2 Upah Operator/Sopir U1 14,285.71 Rp/Jam
3 Upah Pembantu Operator/ Pmb. Sopir U2 12,857.14 Rp/Jam
4 Bahan Bakar Bensin Mb 15,000.00 Rp/liter
5 Bahan Bakar Solar Ms 14,000.00 Rp/liter
6 Minyak Pelumas Mp 50,000.00 Rp/liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan Bakar Batubara Rp/kg
TENAGA
KAPASITAS
HARGAALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM
ALAT ALAT ALAT JAM SISAPENGEMBALIAN
BIAYA
ASURANSITOTAL
UMUR KERJA HARGA ALAT MODAL PENGEMBALIAN
DAN BIAYA
ALAT 1 TAHUNALAT MODALLAIN-LAIN
PASTI/JAM

(HP) - (Tahun) (Tahun) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.) (Rp.)


JENIS
No. PERALATAN
KODE
ALAT i(1+i)^A (B-C) x D
0.002 x B
(10% x B) ( e1 + e2 )
(1+i)^A-1 W W

HP Cp B A W B C D e1 e2 E
1 2 2n 3 4 5 6.0 7.0 8 9 10 11 12 13

1 Crane 10 E01 138 15.0 ### 5.0 2000.0 ### ### 10.00 ### 750.00 ###
2 Track ko E02 75 0.00 ### 5.0 2000.0 ### ### 0.00 ### ### ###
3 Stone Cr E03 220 60.00 ### 5.0 2000.0 ### ### 10.00 ### ### ###
4 Concret E04 100 8.00 ### 6.0 2000.0 ### ### 10.00 ### ### ###
5 Tronton E05 608 15.0 ### 10.0 1500.0 ### ### 10.00 ### ### ###

6 Slip For E06 150 2.5 ### 6.0 2000.0 ### ### 10.00 ### ### ###
7 Truck Mi E07 280 5.0 ### 5.0 2000.0 ### ### 10.00 ### 600.00 ###
8 Breaker E08 138 3.0 ### 5.0 2000.0 ### ### 10.00 ### 175.00 ###
9 Stresing E09 70 15.0 ### 5.0 1800.0 ### ### 10.00 ### ### ###

KET :
1 Tingkat Suku Bunga = 10,00 %Per Tahun
2 Upah Operator /Sopir /Mekanik = 14,286
Rupiah Per Orang
3 Upah Pembantu Operator/Sopir/Me12,857
Rupiah Per Orang/Jam
4 Harga Bahan Bakar Bensin = 15,000
Rupiah Per Liter
5 Harga Bahan Bakar Solar = ###
Rupiah Per Liter
6 Minyak Pelumas = ###
Rupiah Per Liter
7 Pajak Pertambahan Nilai (PPN) di Perhitungkan Pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, Biaya Bahan Bakar ditambah (untuk pemanasan material) Sebesar : 12 Liter x (kapasitas AMP Riil = 0,7 x Kapasitas AM
9 AMP Aspal Sprayer, Aspal Distribusi ditambah Bahan Bakar Untuk Pemanasan Aspal = 1/1000 x Kapasitas Tangki Aspal x Harga Baha
0.0
BIAYA OPERASI PER JAM KERJA TOTAL
BAHAN BAKAR & PELUMAS WORKSHOP Pebaikan dan Perawatan UPAH TOTAL BIAYA
BAHANMINYAK OPERATOR PEMBANTU BIAYASEWA ALAT
BAKARPELUMASBIAYA KOEF. BIAYA KOEF. BIAYA /SOPIR OPERATOR OPERASI PER
/SOPIR /JAMJAM KERJA
% % (Rp.) - (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
f1 x HP x 1 Orang 1 Orang
12 2.5 Harga BBM0.0625 (g1 x B') 0.125 (g1 x B') Per Per
s/d s/d + s/d s/d Jam Kerja
Jam Kerja
F+G+H+E I +J
15 3 f2 x HP x 0.0875 W 0.175 W = =
Harga Olie Rp0.0 Rp0.0
f1 f2 F g1 G g1 G H I J K L
14 15 16 17 18 17 18.00 19 20 21.00 22.00 23

### ### ### 0.0875 32812.5 0.125 ### ### 12,857 ### ### Pek. Berat
0.00 ### ### 0.0875 1E+06 0.125 ### ### 12,857 ### ### Pek. Berat
### ### ### 0.0875 753900 0.125 ### ### 12,857 ### ### Pek. Berat
### ### ### 0.0875 73523 0.125 ### ### 12,857 ### ### Pek. Berat
### ### ### 0.0875 52500 0.175 ### ### 12,857 ### ### Pek. Ringan

Pek. Berat

### ### ### 0.0875 70031 0.125 ### ### 12,857 ### ###
### ### ### 0.0875 26250 0.125 ### ### 12,857 ### ### Pek. Berat
### ### ### 0.0875 7656.25 0.125 ### ### 12,857 ### ### Pek. Berat
### ### ### 0.0875 47612 0.125 ### ### 12,857 ### ### Pek. Berat

s AMP Riil = 0,7 x Kapasitas AMP/Jam) x Harga BBM Solar


pasitas Tangki Aspal x Harga Bahan Bakar Solar
TENAGA
KAPASITAS
HARGAALAT YANG DIPAKAI NILAI
ALAT ALAT ALAT JAM SISA
UMUR KERJA HARGA ALAT
ALAT 1 TAHUNALAT

(HP) - (Tahun) (Tahun) (Jam) (Rp.) (Rp.)


JENIS
No. PERALATAN
KODE
ALAT i(1+i)^A
(10% x B)
(1+i)^A-1

HP Cp B A W B C
1 2 2n 3 4 5 6.0 7.0 8 9

1 #REF! E01 138 #REF! #REF! 5.0 2000.0 #REF! #REF!


2 Track ko E02 75 #REF! #REF! 5.0 2000.0 #REF! #REF!
3 #REF! E03 220 #REF! #REF! 5.0 2000.0 #REF! #REF!
4 #REF! E04 100 #REF! #REF! 6.0 2000.0 #REF! #REF!
5 #REF! E05 608 #REF! #REF! 10.0 1500.0 #REF! #REF!
6 #REF! E06 150 #REF! #REF! 6.0 2000.0 #REF! #REF!
7 #REF! E07 280 #REF! #REF! 5.0 2000.0 #REF! #REF!
8 #REF! E08 138 #REF! #REF! 5.0 2000.0 #REF! #REF!
9 #REF! E09 70 #REF! #REF! 5.0 1800.0 #REF! #REF!

KET :
1 Tingkat Suku Bunga = 10,00 %Per Tahun
2 Upah Operator /Sopir /Mekanik = #REF!
Rupiah Per Orang
3 Upah Pembantu Operator/Sopir/Me#REF!
Rupiah Per Orang/Jam
4 Harga Bahan Bakar Bensin = #REF!
Rupiah Per Liter
5 Harga Bahan Bakar Solar = #REF!
Rupiah Per Liter
6 Minyak Pelumas = #REF!
Rupiah Per Liter
7 Pajak Pertambahan Nilai (PPN) di Perhitungkan Pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, Biaya Bahan Bakar ditambah (untuk pemanasan material) Sebesar : 12 Liter
FAKTORBIAYA PASTI PER JAM BIAYA OPERASI PER JAM KERJA
PENGEMBALIAN
BIAYA
ASURANSI TOTAL
BAHAN BAKAR & PELUMASWORKSHOPPebaikan dan Perawatan
MODAL
PENGEMBALIAN
DAN BIAYABAHANMINYAK
MODAL
LAIN-LAIN
PASTI/JAM
BAKARPELUMASBIAYA KOEF. BIAYA KOEF.

- (Rp.) (Rp.) (Rp.) % % (Rp.) - (Rp.) -


f1 x HP x
i(1+i)^A(B-C) x D
0.002 x B 12 2.5 Harga BBM0.0625 (g1 x B') 0.125
(10% x B) ( e1 + e2 ) s / d s/d + s/d s/d
(1+i)^A-1 W W 15 3 f2 x HP x 0.0875 W 0.175
Harga Olie
D e1 e2 E f1 f2 F g1 G g1
10 11 12 13 14 15 16 17 18 17

#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.175
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125
#REF! #REF! #REF! #REF! #REF! #REF! #REF! 0.0875 #REF! 0.125

pitulasi Biaya Pekerjaan


erial) Sebesar : 12 Liter x (kapasitas AMP Riil = 0,7 x Kapasitas AMP/Jam) x Harga BBM Solar
I PER JAM KERJA TOTAL
baikan dan Perawatan UPAH TOTAL BIAYA
OPERATOR PEMBANTU BIAYASEWA ALAT
BIAYA /SOPIR OPERATOR OPERASI PER
/SOPIR /JAMJAM KERJA
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
1 Orang 1 Orang
(g1 x B') Per Per
Jam Kerja
Jam Kerja
F+G+H+E I +J
W = =
Rp0.0 Rp0.0
G H I J K L
18.00 19 20 21.00 22.00 23

#REF! #REF! #REF! #REF! #REF!Pek. Berat


#REF! #REF! #REF! #REF! #REF!Pek. Berat
#REF! #REF! #REF! #REF! #REF!Pek. Berat
#REF! #REF! #REF! #REF! #REF!Pek. Berat
#REF! #REF! #REF! #REF! #REF!Pek. Ringan
#REF! #REF! #REF! #REF! #REF!Pek. Berat
#REF! #REF! #REF! #REF! #REF!Pek. Berat
#REF! #REF! #REF! #REF! #REF!Pek. Berat
#REF! #REF! #REF! #REF! #REF!Pek. Berat

BBM Solar
kecepatan rencana = 50 km/jam
e maks = 10%
lebar jln = 2*3,75 m (tanpa median)
kemiringan melintang total = 2%
20˚
dit : rencanakan alinyemen horizontal trase di atas dan di belok kanan
jawab 7.471698 112.041331
Tahap 1 4.807692
Rmin = VR^2/127(em+fm)
Rmin = 50²/127(0.1+0.1335) = 84.30424 m 0.1335
Tahap II
jadi R yang direncanakan harus lebih besar dari 84.30424 m
direncanakan R = 573 m 0.026
Tahap III
Metode AASTHO 71600.00%
dari tabel metode AASTHO diperoleh e = 0.026 dan Ls' = 30 m
karena e = 2.6% < 3%,maka bentuk lengkung yang digunakan adalah Full Circle
Tahap IV
Ls1 = 0.022 V^3/R.C = 0.022 50^3/286.2 = 4.81
rumus Mod. SHORTT
Ls2 = 0.022 V^3/R.C-2.727 V.e/C = 0.22 50^3/286.2-2.727*50*0.026/2 = 3.04
Rumus SHORTT
Lr = V*t/3.6 = 50*2/3.6= 27.8
Tahap V
Ls' = 30 > Ls1 = 4.81
Ls' = 30 > Ls2 = 3.04
Ls' = 30 > LR = 27.8
jadi Ls yang digunakan adalah Ls'
Tahap VI
Tc = R tg1/2B = 573 tg 10˚ = 101.04 m
Ec = Tc tg1/4B = 101.04 tg 5˚ = 8.84 m
Lc = 0.01745.B.R = 0.01745*20*573 = 199.98 m
Tahap VII
Data lengkung untuk lengkung busur lingkaran sederhana tersebut diatas :
V = 50 km/jam
B = 20˚
R = 573 m
Tc = 101.04 m
Lc = 199.98 m
e = 2.6 %
Ec = 8.84 m
Ls' = 30 m
0,153 60^2/127

27.77778