NO NAMA ALAT DAFTAR HARGA (RUPIAH)

1 BACKHOE LOADER 426F2 Rp1,081,500,000


2 BULDOZER
3 WHEEL LOADER
4 WHEEL TRACTOR- SCRAPER
5 COLD PLANER PM620 Rp4,595,971,755.00
6 EXCAVATOR
7 MOTOR GRADER
8 PAVER ASPAL
9 ROAD RECLAIMER
10 TANDEM ROLLER CB34B Rp892,237,500.00
11 COMPACT TRACK LOADER
12 SKID STEER LOADER
13 TRACK LOADER
14 TRUK ARTIKULASI
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan BACKHOE LOADER 426F2 E01
2. Tenaga Pw 93.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 1,081,500,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 108,150,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 229,500.49 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,163.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 231,663.49 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (11%) x Pw x Ms H 190,380.30 Rupiah

2. Pelumas = (0,3%) x Pw x Mp I 16,740.00 Rupiah

Biaya bengkel (2,5%) x B J 27,037.50


W

3. Perawatan dan (7,7 %) x B K 83,275.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 373,302.81 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 604,966.30 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER CB34B E02
2. Tenaga Pw 49.0 HP
3. Kapasitas Cp 4.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 892,237,500 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 89,223,750 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 94,668.95 Rupiah
W

b. Asuransi, dll = 0.002 x B F 892.24 Rupiah


W

Biaya Pasti per Jam = (E+F) G 95,561.19 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (11%) x Pw x Ms H 100,307.90 Rupiah

2. Pelumas = (0,3%) x Pw x Mp I 8,820.00 Rupiah

Biaya bengkel (2,5%) x B J 11,152.97


W

3. Perawatan dan (7,7 %) x B K 34,351.14 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 210,501.52 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 306,062.71 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan BACKHOE LOADER 426F2 E01
2. Tenaga Pw 93.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 1,081,500,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 108,150,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 229,500.49 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,163.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 231,663.49 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (13,5%) x Pw x Ms H 233,648.55 Rupiah 13.5

2. Pelumas = (2,75%) x Pw x Mp I 153,450.00 Rupiah 2.75

Biaya bengkel (7,5%) x B J 81,112.50 7.5


W

3. Perawatan dan (15 %) x B K 162,225.00 Rupiah 15


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 686,305.56 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 917,969.05 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER CB34B E02
2. Tenaga Pw 49.0 HP
3. Kapasitas Cp 4.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 892,237,500 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 89,223,750 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23578 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 94,668.95 Rupiah
W

b. Asuransi, dll = 0.002 x B F 892.24 Rupiah


W

Biaya Pasti per Jam = (E+F) G 95,561.19 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (13,5%) x Pw x Ms H 123,105.15 Rupiah 13.5

2. Pelumas = (2,75%) x Pw x Mp I 80,850.00 Rupiah 2.75

Biaya bengkel (7,5%) x B J 33,458.91 7.5


W

3. Perawatan dan (15 %) x B K 66,917.81 Rupiah 15


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 30,066.21 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 25,803.30 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 360,201.38 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 455,762.57 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5.75 % / Tahun
2. Upah Operator / Sopir U1 30,066.21 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,803.30 Rp./Jam
4. Bahan Bakar Bensin Mb 10,000.00 Liter
5. Bahan Bakar Solar Ms 18,610.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan