URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT E01
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 50.0 T/Jam
4. Alat a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 3,163,050,000.0 Rupiah

5 Kapastas tangki aspal Ca 30,000.00 liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 316,305,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.16275 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 308,863.09 Rupiah
W

b. Asuransi, dll = 0.002 x B F 4,217.40 Rupiah


W

Biaya Pasti per Jam = (E+F) G 313,080.49 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H1 202,500.00 Rupiah
Bahan Bakar Pemanasan Material = 12 ltr x Ms H2 3,780,000.00 Rupiah Khusus AMP
dan aspal (Oil Heater)
Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 270,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 219,150.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 184,511


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 369,022.50 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 57,502.38 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 5,104,710.73 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 5,417,791.23 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan bakar Batubara 500.00 Rp/kg

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER E02
2. Tenaga Pw 47.0 HP
3. Kapasitas Cp 6.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,400.0 Jam
c. Harga Alat B 664,290,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 66,429,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 98,052.36 Rupiah
W

b. Asuransi, dll = 0.002 x B F 948.99 Rupiah


W

Biaya Pasti per Jam = (E+F) G 99,001.34 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 63,450.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 68,667.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 29,656


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 83,036.25 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 286,001.12 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 385,002.46 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.


A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER E03
2. Tenaga Pw 4.0 HP
3. Kapasitas Cp 850.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 217,800,000 Rupiah

5 Kapastas tangki aspal Ca 850 Liter

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 21,780,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 25,854.79 Rupiah
W

b. Asuransi, dll = 0.002 x B F 217.80 Rupiah


W

Biaya Pasti per Jam = (E+F) G 26,072.59 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 4,320.00 Rupiah


Bahan Bakar Pemanas Aspal = 1/1000 *Ca*Ms H3 7,650.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,870.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 9,529 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 13,612.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 81,173.31 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 107,245.90 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER 100-150 HP E04
2. Tenaga Pw 155.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 2,262,700,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 226,270,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 268,602.55 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,262.70 Rupiah


W

Biaya Pasti per Jam = (E+F) G 270,865.25 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 167,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 188,712.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 98,993


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 141,418.75 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 637,716.44 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 908,581.69 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M E05
2. Tenaga Pw 80.0 HP
3. Kapasitas Cp 5,000.0 CPM/(L/m)
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 141,570,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 14,157,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 16,805.61 Rupiah
W

b. Asuransi, dll = 0.002 x B F 141.57 Rupiah


W

Biaya Pasti per Jam = (E+F) G 16,947.18 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 86,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 97,400.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 6,194


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 8,848.13 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 240,033.88 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 256,981.06 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 20.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 68,340,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 6,834,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.57619 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 23,626.11 Rupiah
W

b. Asuransi, dll = 0.002 x B F 91.12 Rupiah


W

Biaya Pasti per Jam = (E+F) G 23,717.23 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 25,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 15,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 3,987 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 7,973.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 21,428.57 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 87,888.07 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 111,605.31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 21,428.57 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,500.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CRANE 10-15 TON E07
2. Tenaga Pw 138.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,379,400,000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 137,940,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 163,747.01 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,379.40000 Rupiah


W

Biaya Pasti per Jam = (E+F) G 165,126.41 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 140,760.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 86,250.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 60348.75 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 86,212.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 21,428.57 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 408,999.82 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 574,126.23 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 21,428.57 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,500.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3.5 TON E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 6.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 397,727,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 39,772,700 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 47,213.72 Rupiah
W

b. Asuransi, dll = 0.002 x B F 397.73 Rupiah


W

Biaya Pasti per Jam = (E+F) G 47,611.45 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 108,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 121,750.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 17,401


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 24,857.94 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 313,200.56 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 360,812.01 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 TON E09
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 544,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 54,450,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 64,636.98 Rupiah
W

b. Asuransi, dll = 0.002 x B F 544.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 65,181.48 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 205,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 231,325.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 23,822 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 34,031.25 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 535,570.19 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 600,751.67 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 80.0 HP
3. Kapasitas Cp 0.50 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,101,100,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 110,110,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 130,710.33 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,101.10 Rupiah


W

Biaya Pasti per Jam = (E+F) G 131,811.43 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 86,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 97,400.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 48,173 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 68,818.75 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 341,983.94 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 473,795.37 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 E11
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 272,250,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 27,225,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 32,318.49 Rupiah
W

b. Asuransi, dll = 0.002 x B F 272.25 Rupiah


W

Biaya Pasti per Jam = (E+F) G 32,590.74 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 205,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 231,325.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 11,911 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 17,015.63 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 506,643.63 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 539,234.36 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR SET E12
2. Tenaga Pw 180.0 HP
3. Kapasitas Cp 135.0 KVA
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 232,320,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 23,232,000 Rupiah
2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -
(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 27,578.44 Rupiah
W

b. Asuransi, dll = 0.002 x B F 232.3200 Rupiah


W

Biaya Pasti per Jam = (E+F) G 27,810.76 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 194,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 219,150.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 10164 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 14,520.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 479,426.06 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 507,236.83 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 135.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 2,178,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 217,800,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 258,547.91 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,178.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 260,725.91 Rupiah


C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 145,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 164,362.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 95,288 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 136,125.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 582,767.06 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 843,492.97 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TRACK LOADER 75-100 HP E14
2. Tenaga Pw 70.0 HP
3. Kapasitas Cp 0.8 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,029,105,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 102,910,500 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 122,163.89 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,029.11 Rupiah


W

Biaya Pasti per Jam = (E+F) G 123,192.99 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 75,600.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 85,225.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 45,023 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 64,319.06 Rupiah


perbaikan = W
4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah
5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 311,359.47 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 434,552.46 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15
2. Tenaga Pw 105.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,179,750,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 117,975,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 140,046.79 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,179.75 Rupiah


W

Biaya Pasti per Jam = (E+F) G 141,226.54 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 113,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 127,837.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 51,614 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 73,734.38 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 407,778.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 549,004.54 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan THREE WHEEL ROLLER 6-8 T E16
2. Tenaga Pw 55.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 435,600,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 43,560,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 51,709.58 Rupiah
W

b. Asuransi, dll = 0.002 x B F 435.60 Rupiah


W

Biaya Pasti per Jam = (E+F) G 52,145.18 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 59,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 66,962.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 19,058 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 27,225.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 213,837.06 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 265,982.25 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT


No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 604,395,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 60,439,500 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 71,747.05 Rupiah
W

b. Asuransi, dll = 0.002 x B F 604.40 Rupiah


W

Biaya Pasti per Jam = (E+F) G 72,351.44 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 54,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 60,875.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 26,442 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 37,774.69 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 220,284.03 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 292,635.47 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T. E18
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 637,065,000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 63,706,500 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 75,625.26 Rupiah
W

b. Asuransi, dll = 0.002 x B F 637.07 Rupiah


W

Biaya Pasti per Jam = (E+F) G 76,262.33 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 64,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 73,050.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 27,872 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 39,816.56 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 246,730.22 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 322,992.55 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19
2. Tenaga Pw 75.0 HP
3. Kapasitas Cp 7.000 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 711,480,000 Rupiah

B. BIAYA PASTI PER JAM KERJA BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 71,148,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 84,458.98 Rupiah
W

b. Asuransi, dll = 0.002 x B F 711.48 Rupiah


W

Biaya Pasti per Jam = (E+F) G 85,170.46 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 81,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 91,312.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 31,127 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 44,467.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 289,099.31 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 374,269.78 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR E20
2. Tenaga Pw 5.5 HP
3. Kapasitas Cp 25.0 -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 34,848,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 3,484,800 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 9,894.17 Rupiah
W

b. Asuransi, dll = 0.002 x B F 69.70 Rupiah


W

Biaya Pasti per Jam = (E+F) G 9,963.87 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 7,425.00 Rupiah


2. Pelumas = (2.5%-3%) x Pw x Mp I 8,035.50 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 2,178 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 6,098.40 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 64,928.96 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 74,892.83 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan STONE CRUSHER E21
2. Tenaga Pw 220.0 HP
3. Kapasitas Cp 50.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,143,450,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 114,345,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 135,737.65 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,143.45 Rupiah


W

Biaya Pasti per Jam = (E+F) G 136,881.10 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 237,600.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 267,850.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 50,026 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 71,465.63 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 2 Orang / Jam ) x U2 M 38,334.92 Rupiah
Biaya Operasi per Jam = (H+I+K+L+M) P 687,301.09 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 824,182.19 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm E22
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 32,670,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 3,267,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.40211 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 5,911.69 Rupiah
W

b. Asuransi, dll = 0.002 x B F 32.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 5,944.36 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 6,480.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 7,305.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 1,429 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 2,041.88 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 58,448.25 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 64,392.61 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 239,580,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 23,958,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 28,440.27 Rupiah
W

b. Asuransi, dll = 0.002 x B F 239.5800 Rupiah


W

Biaya Pasti per Jam = (E+F) G 28,679.85 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 108,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 121,750.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 10,481.6250 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 14,973.75 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 296,397.44 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 325,077.29 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.


A. URAIAN PERALATAN
1. Jenis Peralatan JACK HAMMER E26
2. Tenaga Pw 0.0 HP
3. Kapasitas Cp 1,330.000 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 48,097,500 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 4,809,750 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 5,709.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 48.10 Rupiah


W

Biaya Pasti per Jam = (E+F) G 5,757.70 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 0.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 0.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 2,104 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 3,006.09 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 46,302.42 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 52,060.12 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE PUMP E28
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 8.00 M3
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 290,400,000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 29,040,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 30,005.09 Rupiah
W

b. Asuransi, dll = 0.002 x B F 290.40 Rupiah


W

Biaya Pasti per Jam = (E+F) G 30,295.49 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 108,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 121,750.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 12,705 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 18,150.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 22,024.60 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 19,167.46 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 301,797.06 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 332,092.56 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 22,024.60 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 19,167.46 Rp./Jam
4. Bahan Bakar Bensin Mb 9,900.00 Liter
5. Bahan Bakar Solar Ms 9,000.00 Liter
6. Minyak Pelumas Mp 48,700.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TRAILER 20 TON E29
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 20.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 600,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 60,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 61,993.99 Rupiah
W
b. Asuransi, dll = 0.002 x B F 600.00 Rupiah
W

Biaya Pasti per Jam = (E+F) G 62,593.99 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 178,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 109,375.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 26,250 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 37,500.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 21,428.57 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 387,053.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 449,647.56 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 21,428.57 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,500.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan PILE DRIVER + HAMMER E30
2. Tenaga Pw 25.0 HP
3. Kapasitas Cp 2.50 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 400,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 40,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 47,483.55 Rupiah
W

b. Asuransi, dll = 0.002 x B F 400.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 47,883.55 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 25,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 15,625.00 Rupiah


Biaya bengkel (6.25% dan 8.75%) x B J 17,500 Rupiah
W

3. Perawatan dan (12,5 % - 17,5 %) x B K 25,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 21,428.57 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 119,053.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 166,937.12 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 21,428.57 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,500.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CRANE ON TRACK 35 TON E31
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 35.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,650,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 165,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 170,483.48 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,650.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 172,133.48 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 127,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 78,125.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 72,188 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 103,125.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 21,428.57 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 416,366.07 Rupiah


D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 588,499.55 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 21,428.57 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,500.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WELDING SET #REF!
2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 250.00 Amp
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 50,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 5,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 5.94 Rupiah
W

b. Asuransi, dll = 0.002 x B F 0.05 Rupiah


W

Biaya Pasti per Jam = (E+F) G 5.99 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 40,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 25,000.00 Rupiah

Biaya bengkel (6.25% dan 8.75%) x B J 2 Rupiah


W

3. Perawatan dan (12,5 % - 17,5 %) x B K 2,382.188 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 21,428.57 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 14,000.00 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 103,612.95 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 103,618.93 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 21,428.57 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,000.00 Rp./Jam
4. Bahan Bakar Bensin Mb 9,500.00 Liter
5. Bahan Bakar Solar Ms 8,500.00 Liter
6. Minyak Pelumas Mp 25,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
TENAGA KAPASITAS HARGA ALAT YANG DIPAKAI
ALAT ALAT ALAT JAM
UMUR KERJA HARGA
ALAT 1 TAHUN ALAT

(HP) - (Tahun) (Tahun) (Jam) (Rp.)


No. JENIS PERALATAN KODE
ALAT

HP Cp B A W B
1 2 2a 3 4 5 6 7 8

1. ASPHALT MIXING PLANT E01 150.0 50.0 T/Jam 3,163,050,000 10.0 1,500.0 3,163,050,000
2. ASPHALT FINISHER E02 47.0 6.0 Ton 664,290,000 6.0 1,400.0 664,290,000
3. ASPHALT SPRAYER E03 4.0 850.0 Liter 217,800,000 5.0 2,000.0 217,800,000
4. BULLDOZER 100-150 HP E04 155.0 - - 2,262,700,000 5.0 2,000.0 2,262,700,000
5. COMPRESSOR 4000-6500 L\M E05 80.0 5,000.0 CPM/(L/m) 141,570,000 5.0 2,000.0 141,570,000
6. CONCRETE MIXER 0.3-0.6 M3 E06 20.0 500.0 Liter 68,340,000 2.0 1,500.0 68,340,000
7. CRANE 10-15 TON E07 138.0 15.0 Ton 1,379,400,000 5.0 2,000.0 1,379,400,000
8. DUMP TRUCK 3.5 TON E08 100.0 6.0 Ton 397,727,000 5.0 2,000.0 397,727,000
9. DUMP TRUCK 10 TON E09 190.0 8.0 Ton 544,500,000 5.0 2,000.0 544,500,000
10. EXCAVATOR 80-140 HP E10 80.0 0.5 M3 1,101,100,000 5.0 2,000.0 1,101,100,000
11. FLAT BED TRUCK 3-4 M3 E11 190.0 10.0 ton 272,250,000 5.0 2,000.0 272,250,000
12. GENERATOR SET E12 180.0 135.0 KVA 232,320,000 5.0 2,000.0 232,320,000
13. MOTOR GRADER >100 HP E13 135.0 - - 2,178,000,000 5.0 2,000.0 2,178,000,000
14. TRACK LOADER 75-100 HP E14 70.0 0.8 M3 1,029,105,000 5.0 2,000.0 1,029,105,000
15. WHEEL LOADER 1.0-1.6 M3 E15 105.0 1.5 M3 1,179,750,000 5.0 2,000.0 1,179,750,000
16. THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 435,600,000 5.0 2,000.0 435,600,000
17. TANDEM ROLLER 6-8 T. E17 50.0 8.0 Ton 604,395,000 5.0 2,000.0 604,395,000
18. TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton 637,065,000 5.0 2,000.0 637,065,000
19. VIBRATORY ROLLER 5-8 T. E19 75.0 7.0 Ton 711,480,000 5.0 2,000.0 711,480,000
20. CONCRETE VIBRATOR E20 5.5 - - 34,848,000 4.0 1,000.0 34,848,000
21. STONE CRUSHER E21 220.0 50.0 T/Jam 1,143,450,000 5.0 2,000.0 1,143,450,000
22. WATER PUMP 70-100 mm E22 6.0 - - 32,670,000 3.0 2,000.0 32,670,000
23. WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 239,580,000 5.0 2,000.0 239,580,000
24. #REF! E24 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
25. #REF! E25 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
26. JACK HAMMER E26 0.0 1,330.0 1,330.0 48,097,500 5.0 2,000.0 48,097,500
27. #REF! E27 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
28. CONCRETE PUMP E28 100.0 8.00 M3 290,400,000 6.0 2,000.0 290,400,000
29. TRAILER 20 TON E29 175.0 20.00 Ton 600,000,000 6.0 2,000.0 600,000,000
30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 400,000,000 5.0 2,000.0 400,000,000
31. CRANE ON TRACK 35 TON E31 125.0 35.00 Ton 1,650,000,000 6.0 2,000.0 1,650,000,000
32. #REF! E32 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
33. #REF! E33 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
34. #REF! E34 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
KETERANGAN : 1 Tingkat Suku Bunga = 10.00
2 Upah Operator / Sopir / Mekanik = 22,025
3 Upah Pembantu Operator/Sopir/Mekanik = 19,167
4 Harga Bahan Bakar Bensin = 9,900
5 Harga Bahan Bakar Solar = 9,000
6 Minyak Pelumas = 48,700
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas A
TENAGA KAPASITAS HARGA ALAT YANG DIPAKAI
ALAT ALAT ALAT JAM

UMUR KERJA HARGA


ALAT 1 TAHUN ALAT

(HP) - (Tahun) (Tahun) (Jam) (Rp.)


No. JENIS PERALATAN KODE
ALAT

HP Cp B A W B
1 2 2a 3 4 5 6 7 8

35. TRONTON E35 150.0 15.0 Ton 455,400,000 10.0 1,500.0 455,400,000
36. COLD MILLING MACHINE E37 248.0 1,000.0 m 100 5.0 2,000.0 100
37. ROCK DRILL BREAKER E36 3.0 - - 100 10.0 1,500.0 100
38. COLD RECYCLER E38 900.0 2,200.0 M 100 5.0 2,000.0 100
39. HOT RECYCLER E39 400.0 3.0 M 100 5.0 2,000.0 100
40. AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 100 4.0 1,000.0 100
41. ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 225,000,000 5.0 2,000.0 225,000,000
42. SLIP FORM PAVER E42 105.0 2.5 M 100 6.0 2,000.0 100
43. CONCRETE PAN MIXER E43 134.0 600.0 Liter 100 10.0 1,500.0 100
44. CONCRETE BREAKER E44 290.0 20.0 m3/jam 100 5.0 2,000.0 100
45. ASPAHLT TANKER E45 190.0 4,000.0 liter 100 6.0 2,000.0 100
46. CEMENT TANKER E46 190.0 4,000.0 liter 100 6.0 2,000.0 100
47. CONDRETE MIXER (350) E47 20.0 350.0 liter 100 2.0 2,000.0 100
48. VIBRATING RAMMER E48 4.2 80.0 KG 100 4.0 1,000.0 100
49. TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 100 5.0 2,000.0 100
50. BORE PILE MACHINE E50 125.0 60.0 CM 100 10.0 1,500.0 100
51. CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 100 5.0 2,000.0 100
52. BLENDING EQUIPMENT E52 50.0 30.0 Ton 175,000,000 10.0 1,500.0 175,000,000
53. ASPHALT LIQUID MIXER E34a #REF! #REF! #REF! #REF! #REF! #REF! #REF!
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
KETERANGAN : 1 Tingkat Suku Bunga = 10.00
2 Upah Operator / Sopir / Mekanik = 22,025
3 Upah Pembantu Operator/Sopir/Mekanik = 19,167
4 Harga Bahan Bakar Bensin = 9,900
5 Harga Bahan Bakar Solar = 9,000
6 Minyak Pelumas = 48,700
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas A
9 AMP , Aspal Sprayer, Aspal Distribusi ditambah bahan bakar untuk pemanasan Aspal = 1/1000 x Kapas
4018883.62177606
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (I)

NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PE


SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP
ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK
MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA
MODAL
(Rp.) - (Rp.) (Rp.) (Rp.) % % (Rp.) - (Rp.)
f1 x HP x
i(1+i)^A (B - C) x D 0.002 x B 12 2.5 Harga BBM 0.0625 (g1 x B')
(10% X B) ----------- ----------- ----------- (e1 + e2) s/d s/d + s/d -----
(1+i)^A-1 W W 15 3 f2 x HP x 0.0875 W
Harga Olie
C D e1 e2 E f1 f2 F g1 G
9 10 11 12 13 14 15 16 17 18

316,305,000 0.16275 308,863.09 4,217.40 313,080.49 0.1500 0.0300 4,201,650.00 0.0875 184,511
66,429,000 0.22961 98,052.36 948.99 99,001.34 0.1500 0.0300 132,117.00 0.0625 29,655.80
21,780,000 0.26380 25,854.79 217.80 26,072.59 0.1200 0.0250 9,190.00 0.0875 9,528.75
226,270,000 0.26380 268,602.55 2,262.70 270,865.25 0.1200 0.0250 356,112.50 0.0875 98,993.13
14,157,000 0.26380 16,805.61 141.57 16,947.18 0.1200 0.0250 183,800.00 0.0875 6,193.69
6,834,000 0.57619 23,626.11 91.12 23,717.23 0.1500 0.0300 56,220.00 0.0875 3,986.50
137,940,000 0.26380 163,747.01 1,379.40 165,126.41 0.1200 0.0250 317,055.00 0.0875 60,348.75
39,772,700 0.26380 47,213.72 397.73 47,611.45 0.1200 0.0250 229,750.00 0.0875 17,400.56
54,450,000 0.26380 64,636.98 544.50 65,181.48 0.1200 0.0250 436,525.00 0.0875 23,821.88
110,110,000 0.26380 130,710.33 1,101.10 131,811.43 0.1200 0.0250 183,800.00 0.0875 48,173.13
27,225,000 0.26380 32,318.49 272.25 32,590.74 0.1200 0.0250 436,525.00 0.0875 11,910.94
23,232,000 0.26380 27,578.44 232.32 27,810.76 0.1200 0.0250 413,550.00 0.0875 10,164.00
217,800,000 0.26380 258,547.91 2,178.00 260,725.91 0.1200 0.0250 310,162.50 0.0875 95,287.50
102,910,500 0.26380 122,163.89 1,029.11 123,192.99 0.1200 0.0250 160,825.00 0.0875 45,023.34
117,975,000 0.26380 140,046.79 1,179.75 141,226.54 0.1200 0.0250 241,237.50 0.0875 51,614.06
43,560,000 0.26380 51,709.58 435.60 52,145.18 0.1200 0.0250 126,362.50 0.0875 19,057.50
60,439,500 0.26380 71,747.05 604.40 72,351.44 0.1200 0.0250 114,875.00 0.0875 26,442.28
63,706,500 0.26380 75,625.26 637.07 76,262.33 0.1200 0.0250 137,850.00 0.0875 27,871.59
71,148,000 0.26380 84,458.98 711.48 85,170.46 0.1200 0.0250 172,312.50 0.0875 31,127.25
3,484,800 0.31547 9,894.17 69.70 9,963.87 0.1500 0.0300 15,460.50 0.0625 2,178.00
114,345,000 0.26380 135,737.65 1,143.45 136,881.10 0.1200 0.0250 505,450.00 0.0875 50,025.94
3,267,000 0.40211 5,911.69 32.67 5,944.36 0.1200 0.0250 13,785.00 0.0875 1,429.31
23,958,000 0.26380 28,440.27 239.58 28,679.85 0.1200 0.0250 229,750.00 0.0875 10,481.63
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
4,809,750 0.26380 5,709.60 48.10 5,757.70 0.1200 0.0250 0.00 0.0875 2,104.27
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
29,040,000 0.22961 30,005.09 290.40 30,295.49 0.1200 0.0250 229,750.00 0.0875 12,705.00
60,000,000 0.22961 61,993.99 600.00 62,593.99 0.1200 0.0250 402,062.50 0.0875 26,250.00
40,000,000 0.26380 47,483.55 400.00 47,883.55 0.1200 0.0250 57,437.50 0.0875 17,500.00
165,000,000 0.22961 170,483.48 1,650.00 172,133.48 0.1200 0.0250 287,187.50 0.0875 72,187.50
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
% per-tahun
Rupiah per-orang/jam
Rupiah per-orang/jam
Rupiah per-liter
Rupiah per-liter
Rupiah per-liter
asi Biaya Pekerjaan
sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (II)

NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PE


SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP

ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK


MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA
MODAL
(Rp.) - (Rp.) (Rp.) (Rp.) Lt/HP/Jam Ltr/HP/Jam (Rp.) - (Rp.)
f1 x HP x
i(1+i)^A (B - C) x D 0.002 x B 0.125 0.01 Harga BBM 0.0625 (g1 x B')
(10% X B) ----------- ----------- ----------- (e1 + e2) s/d s/d + s/d -----
(1+i)^A-1 W W 0.175 0.02 f2 x HP x 0.0875 W
Harga Olie
C D e1 e2 E f1 f2 F g1 G
9 10 11 12 13 14 15 16 17 18

45,540,000 0.16275 44,468.55 607.20 45,075.75 0.1500 0.0300 421,650.00 0.0875 26,565.00
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 569,780.00 0.0875 0.00
10 0.16275 0.01 0.00 0.01 0.1500 0.0300 8,433.00 0.0875 0.01
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 2,067,750.00 0.0875 0.00
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 919,000.00 0.0875 0.00
10 0.31547 0.03 0.00 0.03 0.1500 0.0300 323,265.00 0.0625 0.01
22,500,000 0.26380 26,709.49 225.00 26,934.49 0.1200 0.0250 264,212.50 0.0875 9,843.75
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 241,237.50 0.0875 0.00
10 0.16275 0.01 0.00 0.01 0.1500 0.0300 376,674.00 0.0875 0.01
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 666,275.00 0.0875 0.00
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 472,525.00 0.0875 0.00
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 436,525.00 0.0875 0.00
10 0.57619 0.03 0.00 0.03 0.1200 0.0250 45,950.00 0.0875 0.00
10 0.31547 0.03 0.00 0.03 0.1500 0.0300 11,806.20 0.0625 0.01
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 505,450.00 0.0875 0.00
10 0.16275 0.01 0.00 0.01 0.1500 0.0300 351,375.00 0.0875 0.01
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 459,500.00 0.0875 0.00
17,500,000 0.16275 17,088.27 233.33 17,321.60 0.1500 0.0300 140,550.00 0.0875 10,208.33
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

% per-tahun
Rupiah per-orang/jam
Rupiah per-orang/jam
Rupiah per-liter
Rupiah per-liter
Rupiah per-liter
asi Biaya Pekerjaan
sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
manasan Aspal = 1/1000 x Kapasitas tangki aspal x harga bahan bakar solar ( lihat E 01 , E 03, E 41)
BIAYA OPERASI PER JAM KERJA TOTAL No. URA
PERBAIKAN dan PERAWATAN UPAH TOTAL BIAYA
OPERATOR PEMBANTU BIAYA SEWA ALAT
KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
/ SOPIR / JAM JAM KERJA 1
- (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET. 2
1 Orang 1 Orang 3
0.125 (g1 x B') Per Per 4
s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J 5
0.175 W = = 6
Rp22,024.6 Rp19,167.5 7
g1 G H I J K L 8
17 18 19 20 21 22 23 9
10
0.1750 369,022.50 22,024.60 57,502.38 5,104,710.73 5,417,791.23 Pek. Ringan 11
0.1750 83,036.25 22,024.60 19,167.46 286,001.12 385,002.46 Pek. Ringan 12
0.1250 13,612.50 22,024.60 19,167.46 81,173.31 107,245.90 Pek. Berat 13
0.1250 141,418.75 22,024.60 19,167.46 637,716.44 908,581.69 Pek. Berat 14
0.1250 8,848.13 22,024.60 19,167.46 240,033.88 256,981.06 Pek. Berat 15
0.1750 7,973.00 22,024.60 19,167.46 109,371.56 133,088.80 Pek. Ringan 16
0.1250 86,212.50 22,024.60 19,167.46 504,808.31 669,934.72 Pek. Berat 17
0.1250 24,857.94 22,024.60 19,167.46 313,200.56 360,812.01 Pek. Berat 18
0.1250 34,031.25 22,024.60 19,167.46 535,570.19 600,751.67 Pek. Berat 19
0.1250 68,818.75 22,024.60 19,167.46 341,983.94 473,795.37 Pek. Berat 20
0.1250 17,015.63 22,024.60 19,167.46 506,643.63 539,234.36 Pek. Berat 21
0.1250 14,520.00 22,024.60 19,167.46 479,426.06 507,236.83 Pek. Berat 22
0.1250 136,125.00 22,024.60 19,167.46 582,767.06 843,492.97 Pek. Berat 23
0.1250 64,319.06 22,024.60 19,167.46 311,359.47 434,552.46 Pek. Berat 24
0.1250 73,734.38 22,024.60 19,167.46 407,778.00 549,004.54 Pek. Berat 25
0.1250 27,225.00 22,024.60 19,167.46 213,837.06 265,982.25 Pek. Berat 26
0.1250 37,774.69 22,024.60 19,167.46 220,284.03 292,635.47 Pek. Berat 27
0.1250 39,816.56 22,024.60 19,167.46 246,730.22 322,992.55 Pek. Berat 28
0.1250 44,467.50 22,024.60 19,167.46 289,099.31 374,269.78 Pek. Berat 29
0.1750 6,098.40 22,024.60 19,167.46 64,928.96 74,892.83 Pek. Ringan 30
0.1250 71,465.63 22,024.60 38,334.92 687,301.09 824,182.19 Pek. Berat 31
0.1250 2,041.88 22,024.60 19,167.46 58,448.25 64,392.61 Pek. Berat 32
0.1250 14,973.75 22,024.60 19,167.46 296,397.44 325,077.29 Pek. Berat 33
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF! 34
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF! 35
0.1250 3,006.09 22,024.60 19,167.46 46,302.42 52,060.12 Pek. Berat 36
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF! 37
0.1250 18,150.00 22,024.60 19,167.46 301,797.06 332,092.56 Pek. Berat 38
0.1250 37,500.00 22,024.60 19,167.46 507,004.56 569,598.56 Pek. Berat 39
0.1250 25,000.00 22,024.60 19,167.46 141,129.56 189,013.11 Pek. Berat 40
0.1250 103,125.00 22,024.60 19,167.46 503,692.06 675,825.54 Pek. Berat 41
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF! 42
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF! 43
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF! 44
45
46
47
48
49
50
51
52
53

BIAYA OPERASI PER JAM KERJA TOTAL


PERBAIKAN & PERAWATAN UPAH TOTAL BIAYA

OPERATOR PEMBANTU BIAYA SEWA ALAT


KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
/ SOPIR / JAM JAM KERJA
- (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
1 Orang 1 Orang
0.125 (g1 x B') Per Per
s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J
0.175 W = =
Rp22,024.6 Rp19,167.5
g1 G H I J K L
17 18 19 20 21 22 23

0.1750 53,130.00 22,024.60 57,502.38 580,871.98 625,947.74 Pek. Ringan


0.1250 0.01 22,024.60 57,502.38 649,306.99 649,307.01 Pek. Berat
0.1750 0.01 22,024.60 57,502.38 87,960.00 87,960.01 Pek. Ringan
0.1250 0.01 22,024.60 57,502.38 2,147,276.99 2,147,277.01 Pek. Berat
0.1250 0.01 22,024.60 57,502.38 998,526.99 998,527.01 Pek. Berat
0.1750 0.02 22,024.60 57,502.38 402,792.01 402,792.04 Pek. Ringan
0.1250 14,062.50 22,024.60 57,502.38 367,645.73 394,580.23 Pek. Berat
0.1250 0.01 22,024.60 57,502.38 320,764.49 320,764.51 Pek. Berat
0.1750 0.01 22,024.60 57,502.38 456,201.00 456,201.01 Pek. Ringan
0.1250 0.01 22,024.60 57,502.38 745,801.99 745,802.01 Pek. Berat
0.1250 0.01 22,024.60 19,167.46 513,717.07 513,717.08 Pek. Berat
0.1250 0.01 22,024.60 19,167.46 477,717.07 477,717.08 Pek. Berat
0.1250 0.01 22,024.60 19,167.46 87,142.07 87,142.10 Pek. Berat
0.1750 0.02 22,024.60 19,167.46 52,998.29 52,998.32 Pek. Ringan
0.1250 0.01 22,024.60 19,167.46 546,642.07 546,642.09 Pek. Berat
0.1750 0.01 22,024.60 19,167.46 392,567.08 392,567.09 Pek. Ringan
0.1250 0.01 22,024.60 19,167.46 500,692.07 500,692.09 Pek. Berat
0.1750 20,416.67 22,024.60 19,167.46 212,367.06 229,688.66 Pek. Ringan
#REF! #REF! 22,024.60 19,167.46 #REF! #REF! #REF!
DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA
URAIAN KO HP KAP. HARGA SEWA KET.
DE ALAT ALAT/JAM
(di luar PPN)

ASPHALT MIXING PLANT E01 150.0 50.0 T/Jam 3,163,050,000 5,417,791.23 Alat baru
ASPHALT FINISHER E02 47.0 6.0 Ton 664,290,000 385,002.46 Alat baru
ASPHALT SPRAYER E03 4.0 850.0 Liter 217,800,000 107,245.90 Alat baru
BULLDOZER 100-150 HP E04 155.0 - - 2,262,700,000 908,581.69 Alat baru
COMPRESSOR 4000-6500 L\M E05 80.0 5,000.0 CPM/(L/m) 141,570,000 256,981.06 Alat baru
CONCRETE MIXER 0.3-0.6 M3 E06 20.0 500.0 Liter 68,340,000 111,605.31 Alat baru
CRANE 10-15 TON E07 138.0 15.0 Ton 1,379,400,000 574,126.23 Alat baru
DUMP TRUCK 3.5 TON E08 100.0 6.0 Ton 397,727,000 360,812.01 Alat baru
DUMP TRUCK 10 TON E09 190.0 8.0 Ton 544,500,000 600,751.67 Alat baru
EXCAVATOR 80-140 HP E10 80.0 0.5 M3 1,101,100,000 473,795.37 Alat baru
FLAT BED TRUCK 3-4 M3 E11 190.0 10.0 ton 272,250,000 539,234.36 Alat baru
GENERATOR SET E12 180.0 135.0 KVA 232,320,000 507,236.83 Alat baru
MOTOR GRADER >100 HP E13 135.0 - - 2,178,000,000 843,492.97 Alat baru
TRACK LOADER 75-100 HP E14 70.0 0.8 M3 1,029,105,000 434,552.46 Alat baru
WHEEL LOADER 1.0-1.6 M3 E15 105.0 1.5 M3 1,179,750,000 549,004.54 Alat baru
THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 435,600,000 265,982.25 Alat baru
TANDEM ROLLER 6-8 T. E17 50.0 8.0 Ton 604,395,000 292,635.47 Alat baru
TIRE ROLLER 8-10 T. E18 60.0 10.0 Ton 637,065,000 322,992.55 Alat baru
VIBRATORY ROLLER 5-8 T. E19 75.0 7.0 Ton 711,480,000 374,269.78 Alat baru
CONCRETE VIBRATOR E20 5.5 - - 34,848,000 74,892.83 Alat baru
STONE CRUSHER E21 220.0 50.0 T/Jam 1,143,450,000 824,182.19 Alat baru
WATER PUMP 70-100 mm E22 6.0 - - 32,670,000 64,392.61 Alat baru
WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 239,580,000 325,077.29 Alat baru
#REF! E24 #REF! #REF! #REF! #REF! #REF! Alat baru
#REF! E25 #REF! #REF! #REF! #REF! #REF! Alat baru
JACK HAMMER E26 0.0 - - 48,097,500 52,060.12 Alat baru
#REF! E27 #REF! - - #REF! #REF! Alat baru
CONCRETE PUMP E28 100.0 8.00 M3 290,400,000 332,092.56 Alat baru
TRAILER 20 TON E29 175.0 20.00 Ton 600,000,000 449,647.56 Alat baru
PILE DRIVER + HAMMER E30 25.0 2.50 Ton 400,000,000 166,937.12 Alat baru
CRANE ON TRACK 35 TON E31 125.0 35.0 Ton 1,650,000,000 588,499.55 Alat baru
#REF! E32 #REF! #REF! #REF! #REF! #REF! Alat baru
#REF! E33 #REF! #REF! #REF! #REF! #REF! Alat baru
#REF! E34 #REF! #REF! #REF! #REF! #REF! Alat baru
TRONTON E35 150.0 15.0 Ton 455,400,000 625,947.74 Alat baru
COLD MILLING E36 248.0 1,000.0 m 100 649,307.01 Alat baru
ROCK DRILL BREAKER E37 3.0 - - 100 87,960.01 Alat baru
COLD RECYCLER E38 900.0 2.2 M 100 2,147,277.01 Alat baru
HOT RECYCLER E39 400.0 3.0 M 100 998,527.01 Alat baru
AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 100 402,792.04 Alat baru
ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 225,000,000 394,580.23 Alat baru
SLIP FORM PAVER E42 105.0 2.5 M 100 320,764.51 Alat baru
CONCRETE PAN MIXER E43 134.0 600.0 Liter 100 456,201.01 Alat baru
CONCRETE BREAKER E44 290.0 20.0 m3/jam 100 745,802.01 Alat baru
ASPAHLT TANKER E45 190.0 4,000.0 liter 100 513,717.08 Alat baru
CEMENT TANKER E46 190.0 4,000.0 liter 100 477,717.08 Alat baru
CONDRETE MIXER (350) E47 20.0 350.0 liter 100 87,142.10 Alat baru
VIBRATING RAMMER E48 4.2 80.0 KG 100 52,998.32 Alat baru
TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 100 546,642.09 Alat baru
BORE PILE MACHINE E50 125.0 60.0 CM 100 392,567.09 Alat baru
CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 100 500,692.09 Alat baru
BLENDING EQUIPMENT E52 50.0 30.0 Ton 175,000,000 209,272.00 Alat baru
ASPHALT LIQUID MIXER E34a #REF! #REF! #REF! #REF! #REF! Alat baru

T x Te1 x Te2 x Fa
Analisa EI-7.6.12.c

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.6 (12).c


JENIS PEKERJAAN : Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 2.2839 12,428.57 28,386.00


2. Tukang (L02) jam 0.4568 14,000.00 6,395.01
3. Mandor (L03) jam 0.2284 16,000.00 3,654.29

JUMLAH HARGA TENAGA 38,435.30

B. BAHAN

1. Tiang Pancang Beton Ø 400 mm M' 1.0000 600,000.00 600,000.00

JUMLAH HARGA BAHAN 600,000.00

C. PERALATAN

1. Trailer E29 jam 1.6159 449,647.56 726,577.04


2. Crane E07 jam 0.2284 574,126.23 131,126.47
3. Alat Bantu Ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 858,703.50

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,497,138.80


E. OVERHEAD & PROFIT 10.0 % x D 149,713.88
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,646,852.68
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 7.6 (12).c Analisa EI-7.6.12.c
JENIS PEKERJAAN : Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik dan diterima di
lokasi jembatan
2 Lokasi pekerjaan : di setiap jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L 1.50 KM
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Ukuran tiang pancang sesuai kebutuhan (diameter) Uk 400.00 mm
6 Panjang Tiang Pancang p 14.00 M
7 Jarak pabrik ke lokasi Dermaga Ld2 630.00 KM

II. URUTAN KERJA


1 Unit tiang pancang prategang pracetak diangkut dari
pabrik ke lokasi Dermaga menggunakan tronton

2 Memuat & menurunkan dari/ke trailer dengan


menggunakan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tiang Pancang Beton Prategang Pracetak Lengkap (M50) 1.0000 M1
Volume per batang is 1.7584 M3

2. ALAT
2.a TRAILER (E29)
Kapasitas bak sekali muat V 7.00 batang
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 80.00 Km/Jam
Kecepatan rata-rata kosong v2 100.00 Km/Jam
Waktu siklus : Ts1
- Waktu tempuh isi = (Ld2 : v1 ) x 60 T1 472.50 menit
- Waktu tempuh kosong = (Ld2 : v2) x 60 T2 378.00 menit
- Lain-lain (bongkar dan muat) T3 140.00 menit
Ts1 990.50 menit

Kapasitas Produksi / Jam = V x is x Fa x 60 Q1 0.62 M3


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29) 1.6159 Jam

2.b CRANE (E07)


Kapasitas V2 1.00 batang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu memuat dan membongkar T1 10.00 menit
- dan lain-lain ( termasuk mengatur dan menggeser) T2 10.00 menit
Ts2 20.00 menit

Kap. Prod. / jam = V x is x Fa x 60 Q2 4.38 M3


Ts2
Koefisien Alat / m = 1 : Q2 (E07) 0.2284 jam

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi Lumpsum
- Tackle
- Tambang
- Alat kecil lainnya
Berlanjut ke hal. berikut.
ITEM PEMBAYARAN NO. : 7.6 (12).c Analisa EI-7.6.12.c
JENIS PEKERJAAN : Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt 30.65 M3
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 10.00 orang

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.2284 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.4568 jam
- Pekerja = (Tk x P) : Qt (L01) 2.2839 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,646,852.68 / M'


Analisa EI-7.6.18.c

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.6 (18).c


JENIS PEKERJAAN : Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 3.6145 12,428.57 44,922.55


2. Tukang (L02) jam 0.9036 14,000.00 12,650.60
3. Mandor (L03) jam 0.4518 16,000.00 7,228.92

JUMLAH HARGA TENAGA 64,802.07

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Pile Driver & Hammer E30 jam 0.4518 144,152.37 65,129.08


2. Alat Bantu Ls 1.0000 150,000.00 150,000.00
3. Pontoon Jam 0.4518 500,000.00 225,903.61

JUMLAH HARGA PERALATAN 441,032.70

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 505,834.76


E. OVERHEAD & PROFIT 10.0 % x D 50,583.48
F. HARGA SATUAN PEKERJAAN ( D + E ) 556,418.24
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 7.6.(18).c Analisa EI-7.6.18.c
JENIS PEKERJAAN : Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Tiang pancang beton diterima di lokasi dermaga
3 Lokasi pekerjaan : di lokasi jembatan
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Panjang Tiang p 6.00 M

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada di
lokasi pemancangan
2 Pile Driver & Hammer berdiri diatas Pontoon

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Pemakaian bahan pada pekerjaan penyiapan
material tiang pancang

2. ALAT

2.a PILE DRIVER & HAMMER (E30)


Kapasitas V1 1.00 Titik
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1 45.00 menit
- Waktu pemancangan sampai kalendering 3 cm T2 60.00 menit
- Waktu penjambungan tiang T3 30.00 menit
Ts1 135.00 menit

Kap. Prod. / jam = V1 x p x Fa x 60 Q1 2.2133 M1


Ts1
Koefisien Alat / m' = 1 : Q1 (E30) 0.4518 Jam

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan Lumpsum
penyambungan
- Rantai/sling baja, dan Lain-Lain

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 15.49 M'
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.4518 jam
- Tukang = ( Tk x Tb ) : Qt (L02) 0.9036 jam
- Pekerja = ( Tk x P ) : Qt (L01) 3.6145 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 7.6.(18).c Analisa EI-7.6.18.c
JENIS PEKERJAAN : Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 400 mm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 556,418.24 / M'


Analisa EI-7.6.12.b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.6 (12).b


JENIS PEKERJAAN : Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm
SATUAN PEMBAYARAN : M'

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 2.3685 12,428.57 29,437.33


2. Tukang (L02) jam 0.4737 14,000.00 6,631.86
3. Mandor (L03) jam 0.2369 16,000.00 3,789.63

JUMLAH HARGA TENAGA 39,858.83

B. BAHAN

1. Tiang Pancang Beton Ø 600 mm M' 1.0000 900,000.00 900,000.00

JUMLAH HARGA BAHAN 900,000.00

C. PERALATAN

1. Trailer E29 jam 1.2646 449,647.56 568,633.77


2. Crane E07 jam 0.2369 574,126.23 135,983.01
3. Alat Bantu Ls 1.0000 1,000.00 1,000.00

JUMLAH HARGA PERALATAN 705,616.78

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,645,475.61


E. OVERHEAD & PROFIT 10.0 % x D 164,547.56
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,810,023.17
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 7.6 (12).b Analisa EI-7.6.12.b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Membeli Tiang Pancang jadi dari Pabrik dan diterima di
lokasi jembatan
2 Lokasi pekerjaan : Dermaga Ulee Lheu
3 Jarak rata-rata Base camp ke lokasi pekerjaan L 1.50 KM
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Ukuran tiang pancang sesuai kebutuhan (diameter) Uk 600.00 mm
6 Panjang Tiang Pancang p 6.00 M
7 Jarak pabrik ke lokasi Dermaga Ld2 450.00 KM

II. URUTAN KERJA


1 Unit tiang pancang prategang pracetak diangkut dari
pabrik ke lokasi Dermaga menggunakan tronton

2 Memuat & menurunkan dari/ke trailer dengan


menggunakan Crane

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tiang Pancang Beton Prategang Pracetak Lengkap (M50) 1.0000 M1
Volume per batang is 1.6956 M3

2. ALAT
2.a TRAILER (E29)
Kapasitas bak sekali muat V 7.00 batang
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 80.00 Km/Jam
Kecepatan rata-rata kosong v2 100.00 Km/Jam
Waktu siklus : Ts1
- Waktu tempuh isi = (Ld2 : v1 ) x 60 T1 337.50 menit
- Waktu tempuh kosong = (Ld2 : v2) x 60 T2 270.00 menit
- Lain-lain (bongkar dan muat) T3 140.00 menit
Ts1 747.50 menit

Kapasitas Produksi / Jam = V x is x Fa x 60 Q1 0.79 M3


Ts1

Koefisien Alat / m3 = 1 : Q1 (E29) 1.2646 Jam

2.b CRANE (E07)


Kapasitas V2 1.00 batang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu memuat dan membongkar T1 10.00 menit
- dan lain-lain ( termasuk mengatur dan menggeser) T2 10.00 menit
Ts2 20.00 menit

Kap. Prod. / jam = V x is x Fa x 60 Q2 4.22 M3


Ts2
Koefisien Alat / m = 1 : Q2 (E07) 0.2369 jam

2.c. ALAT BANTU


Diperlukan alat bantu untuk transportasi Lumpsum
- Tackle
- Tambang
- Alat kecil lainnya
Berlanjut ke hal. berikut.
ITEM PEMBAYARAN NO. : 7.6 (12).b Analisa EI-7.6.12.b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm
SATUAN PEMBAYARAN : M' URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

3. TENAGA
Produksi per hari (unloading) = Q2 x Tk Qt 29.55 M3
Kebutuhan tenaga (di lokasi pekerjaan) :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 10.00 orang

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.2369 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.4737 jam
- Pekerja = (Tk x P) : Qt (L01) 2.3685 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,810,023.17 / M'


Analisa EI-7.6.18.b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.6 (18).b


JENIS PEKERJAAN : Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 4.0161 12,428.57 49,913.94


2. Tukang (L02) jam 1.0040 14,000.00 14,056.22
3. Mandor (L03) jam 0.5020 16,000.00 8,032.13

JUMLAH HARGA TENAGA 72,002.29

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Pile Driver & Hammer E30 jam 0.5020 144,152.37 72,365.65


2. Alat Bantu Ls 1.0000 150,000.00 150,000.00
3. Pontoon Jam 0.5020 500,000.00 251,004.02

JUMLAH HARGA PERALATAN 473,369.66

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 545,371.96


E. OVERHEAD & PROFIT 10.0 % x D 54,537.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 599,909.15
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 7.6.(18).b Analisa EI-7.6.18.b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Tiang pancang beton diterima di lokasi dermaga
3 Lokasi pekerjaan : di lokasi jembatan
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Panjang Tiang p 6.00 M

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada di
lokasi pemancangan
2 Pile Driver & Hammer berdiri diatas Pontoon

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Pemakaian bahan pada pekerjaan penyiapan
material tiang pancang

2. ALAT

2.a PILE DRIVER & HAMMER (E30)


Kapasitas V1 1.00 Titik
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1 45.00 menit
- Waktu pemancangan sampai kalendering 3 cm T2 75.00 menit
- Waktu penjambungan tiang T3 30.00 menit
Ts1 150.00 menit

Kap. Prod. / jam = V1 x p x Fa x 60 Q1 1.9920 M1


Ts1
Koefisien Alat / m' = 1 : Q1 (E30) 0.5020 Jam

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan Lumpsum
penyambungan
- Rantai/sling baja, dan Lain-Lain

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 13.94 M'
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.5020 jam
- Tukang = ( Tk x Tb ) : Qt (L02) 1.0040 jam
- Pekerja = ( Tk x P ) : Qt (L01) 4.0161 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke hal. berikut.


ITEM PEMBAYARAN NO. : 7.6.(18).b Analisa EI-7.6.18.b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Beton Pratekan Pracetak diameter 600 mm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 599,909.15 / M'


Analisa EI-7.6.8.b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.6 (8).b


JENIS PEKERJAAN : Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : Meter Panjang

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 8.4000 12,428.57 104,400.00


2. Tukang (L02) jam 2.8000 14,000.00 39,200.00
3. Mandor (L03) jam 0.7000 16,000.00 11,200.00

JUMLAH HARGA TENAGA 154,800.00

B. BAHAN

1. Pipa baja M52 Kg 173.9233 28,000.00 4,869,853.63


2. Plat Baja M48 Kg 0.2709 32,000.00 8,670.28

JUMLAH HARGA BAHAN 4,878,523.91

C. PERALATAN

1. Trailer E29 jam 0.0036 449,647.56 1,598.95


2. Crane E07 jam 0.0001 574,126.23 66.29
3. Alat Bantu Ls 1.0000 100.00 100.00

JUMLAH HARGA PERALATAN 1,765.24

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 5,035,089.15


E. OVERHEAD & PROFIT 10.0 % x D 503,508.92
F. HARGA SATUAN PEKERJAAN ( D + E ) 5,538,598.07
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 7.6 (8).b Analisa EI-7.6.8.b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : Meter panjang URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Membeli Tiang Pancang dari Pabrik dan diangkut kelokasi
Lokasi pekerjaan : di lokasi jembatan
2 Jarak rata-rata Pabrik ke lokasi pekerjaan L 600.00 Km
3 Jam kerja efektif per-hari Tk 7.00 jam
4 Ukuran diameter tiang pancang (sesuai keperluan) Uk 600.0 mm

5 Tebal tiang t 12.00 mm


6 Berat per-meter tiang b 173.923 kg
7 Panjang Tiang (sesuai keperluan) p 10.0 M

II. URUTAN KERJA


1 Material tiang pancang baja diterima di base camp
2 Di lokasi pekerjaan dibuatkan sepatu pancang
dan penyambungan pipa
3 Penyambungan pipa dengan las listrik

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Pipa baja tiang pancang (M52) 1.05 M'
Plat Baja (untuk penyambungan) (M48) 0.27 Kg

2. ALAT
2.a. TRAILER (E29)
Kapasitas bak sekali muat V 10.00 batang
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 20 Km/Jam
Kecepatan rata-rata kosong v2 30 Km/Jam
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 1,800.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T2 1,200.00 menit
- Lain-lain (bongkar dan muat) T3 80 menit
Ts1 3,080.00 menit

Kapasitas Produksi / Jam = V x p x Fa x 60 x b Q1 281.2137 Kg


Ts1

Koefisien Alat / kg = 1 : Q1 (E29) 0.003556 Jam

2.b CRANE (E07)


Kapasitas V2 3.00 batang
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu menurunkan T4 10.00 menit Lumpsum
- dan lain-lain ( termasuk mengatur dan menggeser) T5 20.00 menit
Ts2 30.00 menit

Kap. Prod. / jam = V2 x p x Fa x b x 60 Q2 8,661.38 Kg


Ts2

Koefisien Alat / kg = 1 : Q1 (E07) 0.0001 jam


Berlanjut ke hal. berikut.
ITEM PEMBAYARAN NO. : 7.6 (8).b Analisa EI-7.6.8.b
JENIS PEKERJAAN : Penyediaan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : Meter panjang URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.c. ALAT BANTU


Diperlukan alat bantu untuk pek. Tiang Pancang Baja Lumpsum
- Tachkel
- Tambang, seling ,rantai dan Alat kecil lainnya

3. TENAGA Qt 10.00 batang


Produksi Tiang dalam 1 hari Qt 100.00 M
Qt 17,392 Kg
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 12.00 orang

Koefisien Tenaga / kg :
- Mandor = (Tk x M) : Qt (L03) 0.7000 jam
- Tukang = (Tk x Tb) : Qt (L02) 2.8000 jam
- Pekerja = (Tk x P) : Qt (L01) 8.4000 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
Didapat Harga Satuan Pekerjaan :

Rp. 5,538,598.07 / M'


Analisa EI-7.6.14.b

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

ITEM PEMBAYARAN NO. : 7.6 (14)a


JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : M1

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) jam 4.0161 12,428.57 49,913.94


2. Tukang (L02) jam 1.0040 14,000.00 14,056.22
3. Mandor (L03) jam 0.5020 16,000.00 8,032.13

JUMLAH HARGA TENAGA 72,002.29

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Pile Driver Hammer E30 jam 0.5020 144,152.37 72,365.65


2. Alat Bantu Ls 1.0000 150,000.00 150,000.00
3. Pontoon Jam 0.5020 500,000.00 251,004.02

JUMLAH HARGA PERALATAN 473,369.66

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 545,371.96


E. OVERHEAD & PROFIT 10.0 % x D 54,537.20
F. HARGA SATUAN PEKERJAAN ( D + E ) 599,909.15
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 7.6 (14)a Analisa EI-7.6.14.b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk 7.00 jam
4 Panjang Tiang p 6.0 M
5 Pemakaian Kawat las dan alat Las utk penyambungan
termasuk dalam item Penyediaan Tiang Pancang

II. URUTAN KERJA


1 Material Tiang pancang yang telah siap ada dekat
lokasi pemancangan
2 Penyambungan dilakukan pada saat pemancangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Pemakaian bahan pada pekerjaan penyiapan
material tiang pancang

2. ALAT

2.a PILE DRIVER HAMMER (E30)


Kapasitas V1 1.00 Titik
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus
- Waktu penggeseran dan penyetelan tiang T1 45.00 menit
- Waktu pemancangan sampai kalendering 3 cm T2 75.00 menit
- Waktu penjambungan tiang T3 30.00 menit
Ts1 150.00 menit

Kap. Prod. / jam = V1 x p x Fa x 60 Q1 1.99 M1/jam


Ts1
Koefisien Alat / m' = 1 : Q1 (E31) 0.5020 Jam

2.b. ALAT BANTU


Diperlukan alat bantu kecil selama penyetelan dan Lumpsum
penyambungan
- Rantai/sling baja, dan Lain-Lain

3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 13.94 M'
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang

Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.5020 jam
- Tukang = ( Tk x Tb ) : Qt (L02) 1.0040 jam
- Pekerja = ( Tk x P ) : Qt (L01) 4.0161 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.
Berlanjut ke hal. berikut.
ITEM PEMBAYARAN NO. : 7.6 (14)a Analisa EI-7.6.14.b
JENIS PEKERJAAN : Pemancangan Tiang Pancang Baja Diameter 600 mm dengan tebal 12 mm
SATUAN PEMBAYARAN : M1 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 599,909.15 / M'