No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Excavator Cartepillar CAT320D E01
2. Tenaga Pw 140,0 HP
3. Kapasitas Cp 1,0 m3
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.300.000.000 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 130.000.000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 138.876,89 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.300,00 Rupiah


W

Biaya Pasti per Jam = ( E+F) G 140.176,89 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar (13,5%) x Pw x Ms H 448.875,00 Rupiah

2. Pelumas (2,75%) x Pw x Mp I 362.269,60 Rupiah

Biaya bengkel (8,75%) x B J 56.875,00


W

3. Perawatan dan (15%) x B K 97.500,00 Rupiah


perbaikan = W

4. Operator ( 1 Orang / Jam ) x U1 L 28.666,67 Rupiah


5. Pembantu Operator ( 3 Orang / Jam ) x U2 M 64.571,43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 1.058.757,70 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 1.198.934,59 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6,00 % / Tahun
2. Upah Operator / Sopir U1 28.666,67 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 21.523,81 Rp./Jam
4. Bahan Bakar Bensin Mb 18.000,00 Liter
5. Bahan Bakar Solar Ms 23.750,00 Liter
6. Minyak Pelumas Mp 94.096,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Model:320D
Max. Digging Radius:8900 mm
Max.Digging Depth :5160 mm
Max.Digging Height: 8930 mm
Engine Model:CAT C6.4 ACERT
Net Power :103kw/2000rpm
Backet Capacity:1.0 m3
Travel Speed:3.5-5.7km/h
Ground Clearance:450mm
Tail Swing Radius:2750mm
Track Gauge:2200mm
Shoe Size:600mm
Engine Oil Capacity:30L
Displacement:6.4 L
Swing Speed:11.5rpm
Operating weight:20330kg
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan Wheel loader Caterpillar 908K E01
2. Tenaga Pw 68,4 HP
3. Kapasitas Cp 1,1 m3
4. Alat Baru : a. Umur Ekonomis A 5,0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2.000,0 Jam
c. Harga Alat B 1.469.400.636 Rupiah
5.

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 146.940.064 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0,23740 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 156.973,69 Rupiah
W

b. Asuransi, dll = 0,002 x B F 1.469,40 Rupiah


W

Biaya Pasti per Jam = ( E+F) G 158.443,09 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar (13,5%) x Pw x Ms H 219.275,44 Rupiah

2. Pelumas (2,75%) x Pw x Mp I 176.968,70 Rupiah

Biaya bengkel (8,75%) x B J 64.286,28


W

3. Perawatan dan (15%) x B K 110.205,05 Rupiah


perbaikan = W

4. Operator ( 1 Orang / Jam ) x U1 L 28.666,67 Rupiah


5. Pembantu Operator ( 3 Orang / Jam ) x U2 M 64.571,43 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 663.973,56 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 822.416,65 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 6,00 % / Tahun
2. Upah Operator / Sopir U1 28.666,67 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 21.523,81 Rp./Jam
4. Bahan Bakar Bensin Mb 18.000,00 Liter
5. Bahan Bakar Solar Ms 23.750,00 Liter
6. Minyak Pelumas Mp 94.096,00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
Pelumas 1 liter = Rp. 94.096