Anda di halaman 1dari 34

ITEM PEMBAYARAN No. 9.1.

(4)
JENIS PEKERJAAN Dump Truck 3 - 4 M3
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN

1. Jenis Peralatan DUMP TRUCK 3-4 M3 (E08)


2. Tenaga Pw 115.0 HP
3. Kapasitas Cp 6.0 Ton
4. Umur Ekonomis A 6.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,667 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 20,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 24,797.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 240.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 25,037.60 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 146,625.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 15,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 231,910.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 256,948.31 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(5)
JENIS PEKERJAAN Truk Bak Datar 3 - 4 ton
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 (E11)


2. Tenaga Pw 115.0 HP
3. Kapasitas Cp 4.0 M3
4. Umur Ekonomis A 6.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,667 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 20,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 24,797.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 240.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 25,037.60 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 146,625.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 15,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 231,910.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 256,948.31 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(6)
JENIS PEKERJAAN Truk Tangki 3000 - 4500 Liter
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan WATER TANKER 3000-4500 L. (E23)


2. Tenaga Pw 115.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Umur Ekonomis A 8.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,250 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 22,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.18744 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 30,365.93 Rupiah
W

b. Asuransi, dll = 0.002 x B F 360.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 30,725.93 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 146,625.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 22,500.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 239,410.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 270,136.65 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(7)
JENIS PEKERJAAN Bulldozer 100 - 150 PK
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan BULLDOZER 100-150 PK (E04)


2. Tenaga Pw 100.0 PK
3. Kapasitas Cp - -
4. Umur Ekonomis A 8.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,250 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C ### Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.18744 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 269,919.39 Rupiah
W

b. Asuransi, dll = 0.002 x B F 3,200.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 273,119.39 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 127,500.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 40,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 200,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 391,785.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 664,905.10 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(8)
JENIS PEKERJAAN Motor Grader min 100 PK
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan MOTOR GRADER >100 PK (E13)


2. Tenaga Pw 115.0 PK
3. Kapasitas Cp - -
4. Umur Ekonomis A 8.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,250 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C ### Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.18744 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 175,447.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,080.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 177,527.60 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 146,625.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 130,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 346,910.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 524,438.31 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(9)
JENIS PEKERJAAN Loader Roda Karet 1.0 - 1.6 M3
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 (E15)


2. Tenaga Pw 115.0 HP
3. Kapasitas Cp 1.5 M3
4. Umur Ekonomis A 8.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,250 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C ### Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.18744 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 168,699.62 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,000.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 170,699.62 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 146,625.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 46,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 125,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 341,910.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 512,610.33 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(10)
JENIS PEKERJAAN Loader Roda Berantai 75 - 100 PK
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan TRACK LOADER 75-100 PK (E14)


2. Tenaga Pw 95.0 PK
3. Kapasitas Cp 1.5 M3
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C ### Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 142,450.64 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,200.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 143,650.64 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 121,125.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 38,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 75,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 258,410.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 402,061.35 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(11)
JENIS PEKERJAAN Alat Penggali (Excavator) 80 - 140 PK
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan EXCAVATOR 80-140 PK (E10)


2. Tenaga Pw 80.0 PK
3. Kapasitas Cp 0.5 M3
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C ### Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 142,450.64 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,200.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 143,650.64 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 102,000.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 32,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 75,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 233,285.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 376,936.35 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(12)
JENIS PEKERJAAN Crane 10 - 15 Ton
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan CRANE 10-15 TON (E07)


2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 25.0 Ton
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 95,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 112,773.42 Rupiah
W

b. Asuransi, dll = 0.002 x B F 950.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 113,723.42 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 191,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 60,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 59,375.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 334,910.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 448,634.14 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(13)
JENIS PEKERJAAN Penggilas Roda Besi 6 - 9 Ton
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan STEEL WHEEL ROLLER 6-9 T. (E16)


2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 8.0 Ton
4. Umur Ekonomis A 10.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,000 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 85,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.16275 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 124,500.23 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,700.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 126,200.23 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 51,000.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 16,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 106,250.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 197,535.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 323,735.94 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(14)
JENIS PEKERJAAN Penggilas Bervibrasi 5 - 8 Ton
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. (E19)


2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 8.0 Ton
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 2,000 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 60,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 85,177.12 Rupiah
W

b. Asuransi, dll = 0.002 x B F 600.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 85,777.12 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 76,500.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 24,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 37,500.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 162,285.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 248,062.83 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(15)
JENIS PEKERJAAN Pemadat Bervibrasi 1.5 - 3.0 PK
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan VIBRATORY COMPACTOR (E25)


2. Tenaga Pw 4.0 HP
3. Kapasitas Cp 0.200 Ton
4. Umur Ekonomis A 6.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 667 Jam Alat Baru
6. Harga Alat B 35,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 3,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.22961 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 10,848.95 Rupiah
W

b. Asuransi, dll = 0.002 x B F 105.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 10,953.95 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 5,100.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 1,600.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 6,562.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 37,548.21 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 48,502.16 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(16)
JENIS PEKERJAAN Penggilas Roda Karet 8 - 10 Ton
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan TIRE ROLLER 8-10 T. (E18)


2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 10.0 Ton
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,800 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C ### Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 131,898.74 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,111.11 Rupiah


W

Biaya Pasti per Jam = (E+F) G 133,009.85 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 76,500.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 24,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 69,444.44 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 194,230.16 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 327,240.01 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(17)
JENIS PEKERJAAN Kompresor 4000 - 6500 Ltr/mnt
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan COMPRESSOR 4000-6500 L\M (E05)


2. Tenaga Pw 70.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 8.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,250 Jam Alat Baru
6. Harga Alat B ### Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 10,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.18744 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 13,495.97 Rupiah
W

b. Asuransi, dll = 0.002 x B F 160.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 13,655.97 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 89,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 28,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 10,000.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 151,535.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 165,191.68 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(18)
JENIS PEKERJAAN Mesin Pengaduk Beton ( Molen ) 0.3 - 0.6 M3
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 (E06)


2. Tenaga Pw 30.0 HP
3. Kapasitas Cp 500.0 Liter
4. Umur Ekonomis A 5.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,600 Jam Alat Baru
6. Harga Alat B 15,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 1,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 2,225.79 Rupiah
W

b. Asuransi, dll = 0.002 x B F 18.75 Rupiah


W

Biaya Pasti per Jam = (E+F) G 2,244.54 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 38,250.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 12,000.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 1,171.88 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 75,707.59 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 77,952.13 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(19)
JENIS PEKERJAAN Pompa Air 70 - 100 mm
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan WATER PUMP 70-100 mm (E22)


2. Tenaga Pw 8.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,000 Jam Alat Baru
6. Harga Alat B 7,000,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 1,987.47 Rupiah
W

b. Asuransi, dll = 0.002 x B F 14.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 2,001.47 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 10,200.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 3,200.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 875.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 38,560.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 40,562.18 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
ITEM PEMBAYARAN No. 9.1.(20)
JENIS PEKERJAAN Jack Hammer
SATUAN PEMBAYARAN Jam URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

A. URAIAN PERALATAN

1. Jenis Peralatan JACK HAMMER E26


2. Tenaga Pw 3.0 HP
3. Kapasitas Cp - -
4. Umur Ekonomis A 4.0 Tahun Alat Baru
5. Jam Operasi Dalam 1 Tahun W 1,000 Jam Alat Baru
6. Harga Alat B 12,500,000 Rupiah Alat Baru

B. BIAYA PASTI PER JAM KERJA

1. Nilai Sisa Alat = 10 % x Harga Alat Baru C 1,250,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.31547 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal (B-C)xD E 3,549.05 Rupiah
W

b. Asuransi, dll = 0.002 x B F 25.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 3,574.05 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (0.125-0.175 Ltr/HP/Jam) x Pw x M H 3,825.00 Rupiah

2. Pelumas = (0.01-0.02 Ltr/HP/Jam) x Pw x Mp I 1,200.00 Rupiah

3. Perawatan dan (12,5 % - 17,5 %) x B K 1,562.50 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 17,142.86 Rupiah


5. Pembantu Operator= ( 1 Orang / Jam ) x U2 M 7,142.86 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 30,873.21 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 34,447.26 Rupiah

E. LAIN - LAIN

1. Tingkat Suku Bunga i 10.00 % / Tahun


2. Upah Operator / Sopir U1 17,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 7,142.86 Rp./Jam
4. Bahan Bakar Bensin Mb 10,750.00 Liter
5. Bahan Bakar Solar Ms 10,200.00 Liter
6. Minyak Pelumas Mp 40,000.00 Liter

File : 606275468.xls
Analisa EI-94

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(4) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Dump Truck 3 - 4 M3 TOTAL HARGA (Rp.) : 0.00
DUMP TRUCK 3-4 M3 % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E08)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. DUMP TRUCK 3-4 M3 jam 1.0000 256,948.31 256,948.31


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 256,948.31


E. OVERHEAD & PROFIT 10.0 % x D 25,694.83
F. HARGA SATUAN PEKERJAAN ( D + E ) 282,643.14
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-95

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(5) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Truk Bak Datar 3 - 4 ton TOTAL HARGA (Rp.) : 0.00
FLAT BED TRUCK 3-4 M3 % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E11)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. FLAT BED TRUCK 3-4 M3 jam 1.0000 256,948.31 256,948.31


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 256,948.31


E. OVERHEAD & PROFIT 10.0 % x D 25,694.83
F. HARGA SATUAN PEKERJAAN ( D + E ) 282,643.14
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-96

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(6) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Truk Tangki 3000 - 4500 Liter TOTAL HARGA (Rp.) : 0.00
WATER TANKER 3000-4500 L. % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E23)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. WATER TANKER 3000-4500 L jam 1.0000 270,136.65 270,136.65


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 270,136.65


E. OVERHEAD & PROFIT 10.0 % x D 27,013.66
F. HARGA SATUAN PEKERJAAN ( D + E ) 297,150.31
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-97

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(7) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Bulldozer 100 - 150 PK TOTAL HARGA (Rp.) : 0.00
BULLDOZER 100-150 PK % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E04)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. BULLDOZER 100-150 PK jam 1.0000 664,905.10 664,905.10


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 664,905.10


E. OVERHEAD & PROFIT 10.0 % x D 66,490.51
F. HARGA SATUAN PEKERJAAN ( D + E ) 731,395.61
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-98

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(8) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Motor Grader min 100 PK TOTAL HARGA (Rp.) : 0.00
MOTOR GRADER >100 PK % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E13)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. MOTOR GRADER >100 PK jam 1.0000 524,438.31 524,438.31


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 524,438.31


E. OVERHEAD & PROFIT 10.0 % x D 52,443.83
F. HARGA SATUAN PEKERJAAN ( D + E ) 576,882.15
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-99

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(9) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Loader Roda Karet 1.0 - 1.6 M3 TOTAL HARGA (Rp.) : 0.00
WHEEL LOADER 1.0-1.6 M3 % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E15)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. WHEEL LOADER 1.0-1.6 M3 jam 1.0000 512,610.33 512,610.33


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 512,610.33


E. OVERHEAD & PROFIT 10.0 % x D 51,261.03
F. HARGA SATUAN PEKERJAAN ( D + E ) 563,871.36
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-910

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(10) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Loader Roda Berantai 75 - 100 PK TOTAL HARGA (Rp.) : 0.00
TRACK LOADER 75-100 PK % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E14)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. TRACK LOADER 75-100 PK jam 1.0000 402,061.35 402,061.35


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 402,061.35


E. OVERHEAD & PROFIT 10.0 % x D 40,206.14
F. HARGA SATUAN PEKERJAAN ( D + E ) 442,267.49
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-911

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(11) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Alat Penggali (Excavator) 80 - 140 P TOTAL HARGA (Rp.) : 0.00
EXCAVATOR 80-140 PK % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E10)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. EXCAVATOR 80-140 PK jam 1.0000 376,936.35 376,936.35


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 376,936.35


E. OVERHEAD & PROFIT 10.0 % x D 37,693.64
F. HARGA SATUAN PEKERJAAN ( D + E ) 414,629.99
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-912

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(12) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Crane 10 - 15 Ton TOTAL HARGA (Rp.) : 0.00
CRANE 10-15 TON % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E07)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. CRANE 10-15 TON jam 1.0000 448,634.14 448,634.14


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 448,634.14


E. OVERHEAD & PROFIT 10.0 % x D 44,863.41
F. HARGA SATUAN PEKERJAAN ( D + E ) 493,497.55
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-913

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(13) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Penggilas Roda Besi 6 - 9 Ton TOTAL HARGA (Rp.) : 0.00
STEEL WHEEL ROLLER 6-9 T. % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E16)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. STEEL WHEEL ROLLER 6-9 T jam 1.0000 323,735.94 323,735.94


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 323,735.94


E. OVERHEAD & PROFIT 10.0 % x D 32,373.59
F. HARGA SATUAN PEKERJAAN ( D + E ) 356,109.54
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-914

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(14) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Penggilas Bervibrasi 5 - 8 Ton TOTAL HARGA (Rp.) : 0.00
VIBRATORY ROLLER 5-8 T. % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E19)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. VIBRATORY ROLLER 5-8 T. jam 1.0000 248,062.83 248,062.83


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 248,062.83


E. OVERHEAD & PROFIT 10.0 % x D 24,806.28
F. HARGA SATUAN PEKERJAAN ( D + E ) 272,869.11
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-915

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(15) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Pemadat Bervibrasi 1.5 - 3.0 PK TOTAL HARGA (Rp.) : 0.00
VIBRATORY COMPACTOR % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E25)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. VIBRATORY COMPACTOR jam 1.0000 48,502.16 48,502.16


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 48,502.16


E. OVERHEAD & PROFIT 10.0 % x D 4,850.22
F. HARGA SATUAN PEKERJAAN ( D + E ) 53,352.38
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-916

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(16) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Penggilas Roda Karet 8 - 10 Ton TOTAL HARGA (Rp.) : 0.00
TIRE ROLLER 8-10 T. % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E18)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. TIRE ROLLER 8-10 T. jam 1.0000 327,240.01 327,240.01


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 327,240.01


E. OVERHEAD & PROFIT 10.0 % x D 32,724.00
F. HARGA SATUAN PEKERJAAN ( D + E ) 359,964.01
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-917

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(17) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Kompresor 4000 - 6500 Ltr/mnt TOTAL HARGA (Rp.) : 0.00
COMPRESSOR 4000-6500 L\M % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E05)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. COMPRESSOR 4000-6500 L\ jam 1.0000 165,191.68 165,191.68


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 165,191.68


E. OVERHEAD & PROFIT 10.0 % x D 16,519.17
F. HARGA SATUAN PEKERJAAN ( D + E ) 181,710.85
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-918

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(18) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Mesin Pengaduk Beton ( Molen ) 0.3 TOTAL HARGA (Rp.) : 0.00
CONCRETE MIXER 0.3-0.6 M3 % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E06)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. CONCRETE MIXER 0.3-0.6 M jam 1.0000 77,952.13 77,952.13


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 77,952.13


E. OVERHEAD & PROFIT 10.0 % x D 7,795.21
F. HARGA SATUAN PEKERJAAN ( D + E ) 85,747.34
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-919

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(19) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Pompa Air 70 - 100 mm TOTAL HARGA (Rp.) : 0.00
WATER PUMP 70-100 mm % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam (E22)

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. WATER PUMP 70-100 mm jam 1.0000 40,562.18 40,562.18


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 40,562.18


E. OVERHEAD & PROFIT 10.0 % x D 4,056.22
F. HARGA SATUAN PEKERJAAN ( D + E ) 44,618.40
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.

File : 606275468.xls
Analisa EI-920

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

KETERANGAN

PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROP / KAB / KODYA :
ITEM PEMBAYARAN NO.9.1.(20) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN Jack Hammer TOTAL HARGA (Rp.) : 0.00
JACK HAMMER % THD. BIAYA PROYEK : 0.00
SATUAN PEMBAYARAN Jam E26

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. PEKERJA

1. - - - -
2. - - - -

B. BAHAN

1. - - - -
2. - - - -

C. ALAT

1. JACK HAMMER jam 1.0000 34,447.26 34,447.26


2. - jam - - -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 34,447.26


E. OVERHEAD & PROFIT 10.0 % x D 3,444.73
F. HARGA SATUAN PEKERJAAN ( D + E ) 37,891.99
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor
mata pembayaran.
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.