Anda di halaman 1dari 61

URAIAN ANALISA ALAT

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT LB400 E01
2. Tenaga Pw 294 HP
3. Kapasitas Cp 60 T/h
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 3,000,000,000.00 Rupiah
5. Kapasitas tangki aspal Ca 30,000.0

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 300,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 311,815.98 Rupiah
W

b. Asuransi, dll = 0.002 x B F 3,000.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 314,815.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H1 229,320.00 Rupiah
Bahan Bakar Pelumas Material = 12 ltr x Ms H2 78,000.00 Rupiah
dan aspal (oil heater)
Bahan Bakar Pelumas Aspal =1/1000*Ca*Ms H3 195,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 257,250.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 131,250


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 187,500.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.29 Rupiah
6 Pembantu Operator = ( 3 Orang / Jam ) x U2 M 21.43 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,078,350.71 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,393,166.69 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 18,571 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER CAT AP 255 E02
2. Tenaga Pw 72.4 HP
3. Kapasitas Cp 10 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 1,732,900,000.00 Rupiah
5. Kapasitas tangki aspal Ca 30,000.0

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 173,290,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 189,595.06 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,824.11 Rupiah


W

Biaya Pasti per Jam = (E+F) G 191,419.16 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 56,472.00 Rupiah
Bahan Bakar Pelumas Material = 12 ltr x Ms H2 85,200.00 Rupiah
dan aspal (oil heater)
Bahan Bakar Pelumas Aspal =1/1000*Ca*Ms H3 213,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 63,350.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 79,805


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 114,006.58 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.40 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9.02 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 611,851.61 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 803,270.77 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,857 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,143 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER DONGFENG C.4 E03
2. Tenaga Pw 40 HP
3. Kapasitas Cp 850 Liter
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 309,517,000.00 Rupiah
5. Kapasitas tangki aspal Ca 30,000.0

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 30,951,700.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 33,863.98 Rupiah
W

b. Asuransi, dll = 0.002 x B F 325.81 Rupiah


W

Biaya Pasti per Jam = (E+F) G 34,189.79 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 31,200.00 Rupiah
Bahan Bakar Pelumas Material = 12 ltr x Ms H2 85,200.00 Rupiah
dan aspal (oil heater)
Bahan Bakar Pelumas Aspal =1/1000*Ca*Ms H3 213,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 35,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 14,254


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 20,362.96 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.02 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 6.77 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 399,032.82 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 433,222.61 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan BULLDOZER KOMATSU D31Ex-22 E04
2. Tenaga Pw 75 HP
3. Kapasitas Cp 5.4 m3
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 1,514,700,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 151,470,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 157,435.89 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,514.70 Rupiah


W

Biaya Pasti per Jam = (E+F) G 158,950.59 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 58,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,625.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 66,268


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 94,668.75 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 8.57 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 6.43 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 285,076.88 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 444,027.46 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR ATLAS XAS97 Dd E05
2. Tenaga Pw 75 HP
3. Kapasitas Cp 180 CFM
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,600 Jam
c. Harga Alat B 263,240,175.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 26,324,017.50 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 34,201.04 Rupiah
W

b. Asuransi, dll = 0.002 x B F 329.05 Rupiah


W

Biaya Pasti per Jam = (E+F) G 34,530.09 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 58,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,625.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 14,396


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 20,565.64 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.82 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.04 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 159,104.44 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 193,634.53 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 15,714 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CRANE KATO SR-700L E06
2. Tenaga Pw 138 HP
3. Kapasitas Cp 0.9 m3
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 8,642,800,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 864,280,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 945,601.10 Rupiah
W

b. Asuransi, dll = 0.002 x B F 9,097.68 Rupiah


W

Biaya Pasti per Jam = (E+F) G 954,698.78 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 107,640.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 120,750.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 398,024


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 568,605.26 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 7.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 6.02 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,195,032.48 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 2,149,731.26 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 11,429 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan GRADER HIDROMEK MG330 E07
2. Tenaga Pw 50 HP
3. Kapasitas Cp 17.975 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 1,859,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 185,900,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 227,319.96 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,187.06 Rupiah


W

Biaya Pasti per Jam = (E+F) G 229,507.02 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 39,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 43,750.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 95,684


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 136,691.18 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 8.40 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.56 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 315,140.97 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 544,647.99 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR TAKEUCHI TB 150C E08
2. Tenaga Pw 50 HP
3. Kapasitas Cp 4.730 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 6,747,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 674,700,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 738,183.30 Rupiah
W

b. Asuransi, dll = 0.002 x B F 7,102.11 Rupiah


W

Biaya Pasti per Jam = (E+F) G 745,285.40 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 39,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 43,750.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 310,717


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 443,881.58 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.02 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.52 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 837,365.23 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,582,650.63 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER KAWASAKI 50Z5 E09
2. Tenaga Pw 35 HP
3. Kapasitas Cp 7.560 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 1,073,600,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 107,360,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 117,461.63 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,130.11 Rupiah


W

Biaya Pasti per Jam = (E+F) G 118,591.73 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 27,300.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 30,625.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 49,442


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 70,631.58 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.02 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.52 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 178,015.23 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 296,606.96 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan JACK HAMMER SAKAI R2H-2K static E10
2. Tenaga Pw 80 HP
3. Kapasitas Cp 0.266 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 34,351,812.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 3,435,181.20 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 4,760.64 Rupiah
W

b. Asuransi, dll = 0.002 x B F 45.80 Rupiah


W

Biaya Pasti per Jam = (E+F) G 4,806.44 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 78,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 84,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 1,431


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 4,007.71 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.62 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 167,456.18 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 172,262.62 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 11,429 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan THREE WHEELS ROLLER SAKAI R2H-2K E11
2. Tenaga Pw 40 HP
3. Kapasitas Cp 13.995 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 963,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 96,300,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 117,756.39 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,132.94 Rupiah


W

Biaya Pasti per Jam = (E+F) G 118,889.33 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 31,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 35,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 49,566


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 70,808.82 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 186,593.49 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 305,482.82 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATOR ROLLER SLDG Single Drum E12
2. Tenaga Pw 45 HP
3. Kapasitas Cp 14 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 741,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 74,100,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 90,610.05 Rupiah
W

b. Asuransi, dll = 0.002 x B F 871.76 Rupiah


W

Biaya Pasti per Jam = (E+F) G 91,481.82 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 35,100.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 39,375.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 38,140


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 54,485.29 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.50 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10.08 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 167,120.59 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 258,602.41 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,857 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,143 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER SAKAI TS205 E13
2. Tenaga Pw 40 HP
3. Kapasitas Cp 10.5 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 1,004,090,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 100,409,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 122,780.90 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,181.28 Rupiah


W

Biaya Pasti per Jam = (E+F) G 123,962.19 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 31,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 35,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 51,681


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 73,830.15 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 191,729.74 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 315,691.92 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR CAT SILENT C18 E14
2. Tenaga Pw 250 kW
3. Kapasitas Cp 650 kVA
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,300 Jam
c. Harga Alat B 1,336,456,780.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 133,645,678.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 213,706.96 Rupiah
W

b. Asuransi, dll = 0.002 x B F 2,056.09 Rupiah


W

Biaya Pasti per Jam = (E+F) G 215,763.05 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 243,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 262,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 64,253


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 179,907.64 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.89 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 9.89 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 750,430.15 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 966,193.20 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 12,857 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 TON SCAHMAN MANUAL E15
2. Tenaga Pw 150 HP
3. Kapasitas Cp 10 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 647,168,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 64,716,800.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 79,136.20 Rupiah
W

b. Asuransi, dll = 0.002 x B F 761.37 Rupiah


W

Biaya Pasti per Jam = (E+F) G 79,897.58 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 117,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 131,250.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 33,310


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 47,585.88 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 12.61 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10.08 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 329,168.69 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 409,066.27 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 21,429 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,143 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3,5 TON SINOTRUCK HOWO E16
2. Tenaga Pw 150 HP
3. Kapasitas Cp 3.5 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 117,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,700,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 14,306.85 Rupiah
W

b. Asuransi, dll = 0.002 x B F 137.65 Rupiah


W

Biaya Pasti per Jam = (E+F) G 14,444.50 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 117,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 131,250.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 6,022


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 8,602.94 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.92 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 262,894.33 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 277,338.83 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 18,571 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TRUCK TRAILER CHENGDA SCD 9400P E17
2. Tenaga Pw 150 HP
3. Kapasitas Cp 60 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 305,500,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 30,550,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 42,337.68 Rupiah
W

b. Asuransi, dll = 0.002 x B F 407.33 Rupiah


W

Biaya Pasti per Jam = (E+F) G 42,745.01 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 146,250.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 157,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 12,729


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 35,641.67 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 11.90 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10.48 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 352,143.21 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 394,888.23 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,857 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 15,714 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER YUJIE JS500 E18
2. Tenaga Pw 50 HP
3. Kapasitas Cp 800 Liter
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 202,800,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 20,280,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 24,798.54 Rupiah
W

b. Asuransi, dll = 0.002 x B F 238.59 Rupiah


W

Biaya Pasti per Jam = (E+F) G 25,037.13 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 39,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 43,750.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 10,438


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 14,911.76 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 8.40 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.56 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 108,115.97 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 133,153.10 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan STONE CHRUSER JINGTAI PF1315 E19
2. Tenaga Pw 80 HP
3. Kapasitas Cp 250 T/Jam
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 546,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 54,600,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 59,737.38 Rupiah
W

b. Asuransi, dll = 0.002 x B F 574.74 Rupiah


W

Biaya Pasti per Jam = (E+F) G 60,312.11 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 62,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 70,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 25,145


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 35,921.05 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.02 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.52 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 193,482.33 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 253,794.44 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANK JIANGSU 1000 LITER E20
2. Tenaga Pw 76 kW
3. Kapasitas Cp 1,000 Liter
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 13,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1,300,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,801.60 Rupiah
W

b. Asuransi, dll = 0.002 x B F 17.33 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,818.94 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 74,100.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 79,800.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 542


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 1,516.67 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 11.43 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.57 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 155,978.33 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 157,797.27 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP WASINEX 0,75kW VFWI E21
2. Tenaga Pw 80 kW
3. Kapasitas Cp 3 Liter
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 3,588,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 358,800.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 497.24 Rupiah
W

b. Asuransi, dll = 0.002 x B F 4.78 Rupiah


W

Biaya Pasti per Jam = (E+F) G 502.03 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 78,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 84,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 150


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 418.60 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.62 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 162,585.24 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 163,087.27 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 11,429 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan PIPE BORING MACHINE XZ320E E22
2. Tenaga Pw 80 HP
3. Kapasitas Cp 320 Liter
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 3,380,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 338,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 413,309.02 Rupiah
W

b. Asuransi, dll = 0.002 x B F 3,976.47 Rupiah


W

Biaya Pasti per Jam = (E+F) G 417,285.49 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 62,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 70,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 173,971


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 248,529.41 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 554,918.49 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 972,203.98 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan FLATBED TRUCK DONGFENG E23
2. Tenaga Pw 150 HP
3. Kapasitas Cp 24.9 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 1,040,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 104,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 144,128.27 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,386.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 145,514.94 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 146,250.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 157,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 43,333


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 121,333.33 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.62 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 468,433.81 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 613,948.75 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 11,429 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT LIQUID MIXER BLS E24
2. Tenaga Pw 80 HP
3. Kapasitas Cp 5,000 Liter
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 117,000,000.00 Rupiah
5. Kapasitas tangki aspal Ca 30,000.0

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,700,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 16,214.43 Rupiah
W

b. Asuransi, dll = 0.002 x B F 156.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 16,370.43 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 78,000.00 Rupiah
Bahan Bakar Pelumas Material = 12 ltr x Ms H2 85,200.00 Rupiah
dan aspal (oil heater)
Bahan Bakar Pelumas Aspal =1/1000*Ca*Ms H3 213,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 84,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 4,875


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 13,650.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.57 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 478,743.10 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 495,113.53 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WELDING SET MACHINE BX1-250C E25
2. Tenaga Pw 80 kW
3. Kapasitas Cp 250 Amp
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 1,170,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 117,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 162.14 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1.56 Rupiah


W

Biaya Pasti per Jam = (E+F) G 163.70 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 78,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 84,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 49


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 136.50 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.62 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 162,202.39 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 162,366.10 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 11,429 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan BACKHOE LOADER KOMATSU WB97R E26
2. Tenaga Pw 40 HP
3. Kapasitas Cp 7 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 4,540,625,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 454,062,500.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 555,231.15 Rupiah
W

b. Asuransi, dll = 0.002 x B F 5,341.91 Rupiah


W

Biaya Pasti per Jam = (E+F) G 560,573.06 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 31,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 35,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 233,709


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 333,869.49 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 633,796.61 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,194,369.67 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER BOMAG BW174 AD-2AM E27
2. Tenaga Pw 75 HP
3. Kapasitas Cp 10 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 4,578,720,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 457,872,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 559,889.43 Rupiah
W

b. Asuransi, dll = 0.002 x B F 5,386.73 Rupiah


W

Biaya Pasti per Jam = (E+F) G 565,276.16 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 58,500.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 65,625.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 235,669


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 336,670.59 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10.08 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 696,485.17 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,261,761.33 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,143 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan HYDRAULIC EXCAVATOR VOLVO EW145B E28
2. Tenaga Pw 45 HP
3. Kapasitas Cp 13.1 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 1,679,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 167,900,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 205,309.42 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,975.29 Rupiah


W

Biaya Pasti per Jam = (E+F) G 207,284.72 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 35,100.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 39,375.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 86,419


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 123,455.88 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.50 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10.08 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 284,370.59 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 491,655.30 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,857 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 17,143 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER NIIGATA NF220 E29
2. Tenaga Pw 45 HP
3. Kapasitas Cp 12.2 Gal
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,900 Jam
c. Harga Alat B 4,000,000,000.00 Rupiah
5. Kapasitas tangki aspal Ca 30,000.0

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 400,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 437,636.46 Rupiah
W

b. Asuransi, dll = 0.002 x B F 4,210.53 Rupiah


W

Biaya Pasti per Jam = (E+F) G 441,846.99 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 35,100.00 Rupiah
Bahan Bakar Pelumas Material = 12 ltr x Ms H2 85,200.00 Rupiah
dan aspal (oil heater)
Bahan Bakar Pelumas Aspal =1/1000*Ca*Ms H3 213,000.00

2. Pelumas = (2.5%-3%) x Pw x Mp I 39,375.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 184,211


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 263,157.89 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.02 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.52 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 820,059.96 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,261,906.95 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan TRACKED EXCAVATOR JCB JS205 E30
2. Tenaga Pw 40 HP
3. Kapasitas Cp 20.5 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 1,403,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 140,300,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 171,559.93 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,650.59 Rupiah


W

Biaya Pasti per Jam = (E+F) G 173,210.52 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 31,200.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 35,000.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 72,213


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 103,161.76 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 241,593.49 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 414,804.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan LANDFILL COMPACTOR BOMAG BC462RB E31
2. Tenaga Pw 50 HP
3. Kapasitas Cp 21.3 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,700 Jam
c. Harga Alat B 4,933,500,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 493,350,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 603,272.21 Rupiah
W

b. Asuransi, dll = 0.002 x B F 5,804.12 Rupiah


W

Biaya Pasti per Jam = (E+F) G 609,076.32 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 39,000.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 43,750.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 253,930


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 362,757.35 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.08 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.40 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 699,455.99 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,308,532.31 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 14,286 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan WEED BOAT A.BERKENHEGER 6550 E32
2. Tenaga Pw 50 HP
3. Kapasitas Cp 14.5 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 13,950,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1,395,000,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,933,259.06 Rupiah
W

b. Asuransi, dll = 0.002 x B F 18,600.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,951,859.06 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 48,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 52,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 581,250


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 1,627,500.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 11.43 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.57 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 2,310,020.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 4,261,879.06 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 17,143 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,857 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT CUTTER ATLAS COPCO 350 E33
2. Tenaga Pw 90 HP
3. Kapasitas Cp 216 lbs
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 43,873,363.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 4,387,336.30 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 6,080.18 Rupiah
W

b. Asuransi, dll = 0.002 x B F 58.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 6,138.68 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 87,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 94,500.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 1,828


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 5,118.56 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 9.52 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 7.62 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 189,213.76 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 195,352.44 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 14,286 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 11,429 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan SLIPFORM PAVER WIRTGEN SP25 E34
2. Tenaga Pw 57 HP
3. Kapasitas Cp 13.6 Ton
4. Alat a. Umur Ekonomis A 5 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500 Jam
c. Harga Alat B 6,006,000,000.00 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 600,600,000.00 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.23097 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 832,340.78 Rupiah
W

b. Asuransi, dll = 0.002 x B F 8,008.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 840,348.78 Rupiah

C. BIAYA OPERASI PER JAM KERJA


1. Bahan Bakar = (12%-15%) x Pw x Ms H 55,575.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 59,850.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 250,250


W
4. Biaya perbaikan (12,5 % - 17,5 %) x B K 700,700.00 Rupiah
W
5 Operator = ( 1 Orang / Jam ) x U1 L 10.48 Rupiah
6 Pembantu Operator = ( 1 Orang / Jam ) x U2 M 8.10 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 1,066,393.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 1,906,742.35 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 5 % / Tahun
2. Upah Operator / Sopir U1 15,714 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 12,143 Rp./Jam
4. Bahan Bakar Bensin Mb 7,100 Rp./liter
5. Bahan Bakar Solar Ms 6,500 Rp./liter
6. Minyak Pelumas Mp 35,000 Rp./liter
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (I)

TENAGA KAPASITAS HARGA ALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PER JAM KERJA TOTAL
ALAT ALAT ALAT JAM SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP PERBAIKAN dan PERAWATAN UPAH TOTAL BIAYA
UMUR KERJA HARGA ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK OPERATOR PEMBANTU BIAYA SEWA ALAT
ALAT 1 TAHUN ALAT MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
MODAL / SOPIR / JAM JAM KERJA
(HP) - (Tahun) (Tahun) (Jam) (Rp.) (Rp.) - (Rp.) (Rp.) (Rp.) % % (Rp.) - (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
No. JENIS PERALATAN KODE f1 x HP x Orang Orang
ALAT i(1+i)^A (B - C) x D 0.002 x B 12 2.5 Harga BBM 0.0625 (g1 x B') 0.125 (g1 x B') Per Per DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA
(10% X B) ----------- ----------- ----------- (e1 + e2) s/d s/d + s/d ----- s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J
(1+i)^A-1 W W 15 3 f2 x HP x 0.0875 W 0.175 W = =
Harga Olie Rp130,000.0 Rp100,000.0 No. URAIAN KO
HP Cp B A W B C D e1 e2 E f1 f2 F g1 G g1 G H I J K L DE
1 2a 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 17 18 19 20 21 22 23

1. ASPHALT MIXING PLANT LB400 E01 294.0 60.0 T/h Rp 3,000,000,000 5.0 2,000 Rp 3,000,000,000 Rp 300,000,000 0.20030 270,405.13 3,000.00 273,405.13 0.1200 0.0250 3,762,570.00 0.0875 131,250 0.1250 187,500.00 18,571.43 28,571.43 1,077,385.98 443,065.98 Pek. Berat 1 ASPHALT MIXING PLANT LB400 E01
2. ASPHALT FINISHER CAT AP 255 E02 72.4 10.0 T/Jam Rp 1,732,900,000 5.0 1,900 Rp 1,732,900,000 Rp 173,290,000 0.20030 164,415.81 1,824.11 166,239.92 0.1200 0.0250 3,059,822.00 0.0875 79,805 0.1250 114,006.58 17,857.14 34,285.71 611,265.27 269,399.66 Pek. Berat 2 ASPHALT FINISHER CAT AP 255 E02
3. ASPHALT SPRAYER DONGFENG C.4 E03 40.0 850.0 Liter Rp 309,517,000 5.0 1,900 Rp 309,517,000 Rp 30,951,700 0.20030 29,366.66 325.81 29,692.47 0.1200 0.0250 66,200.00 0.0875 14,254 0.1250 20,362.96 17,142.86 25,714.29 398,915.60 48,118.05 Pek. Berat 3 ASPHALT SPRAYER DONGFENG C.4 E03
4. BULLDOZER KOMATSU D31Ex-22 E04 75.0 5.4 m3 Rp 1,514,700,000 5.0 2,000 Rp 1,514,700,000 Rp 151,470,000 0.20030 136,527.55 1,514.70 138,042.25 0.1200 0.0250 124,125.00 0.0875 66,268 0.1250 94,668.75 17,142.86 12,857.14 284,590.29 223,704.01 Pek. Berat 4 BULLDOZER KOMATSU D31Ex-22 E04
5. COMPRESSOR ATLAS XAS97 Dd E05 75.0 180.0 CFM Rp 263,240,175 5.0 1,600 Rp 263,240,175 Rp 26,324,018 0.20030 29,658.96 329.05 29,988.01 0.1200 0.0250 124,125.00 0.0875 14,396 0.1250 20,565.64 15,714.29 12,857.14 158,984.14 48,596.99 Pek. Berat 5 COMPRESSOR ATLAS XAS97 Dd E05
6. CRANE KATO SR-700L E06 138.0 0.9 m3 Rp 8,642,800,000 5.0 1,900 Rp 8,642,800,000 Rp 864,280,000 0.20030 820,020.18 9,097.68 829,117.86 0.1200 0.0250 228,390.00 0.0875 398,024 0.1250 568,605.26 14,285.71 11,428.57 1,192,186.47 1,343,624.78 Pek. Berat 6 CRANE KATO SR-700L E06
7. GRADER HIDROMEK MG330 E07 50.0 18.0 Ton Rp 1,859,000,000 5.0 1,700 Rp 1,859,000,000 Rp 185,900,000 0.20030 197,130.65 2,187.06 199,317.70 0.1200 0.0250 82,750.00 0.0875 95,684 0.1250 136,691.18 14,285.71 12,857.14 314,444.08 323,003.79 Pek. Berat 7 GRADER HIDROMEK MG330 E07
8. EXCAVATOR TAKEUCHI TB 150C E08 50.0 4.7 Ton Rp 6,747,000,000 5.0 1,900 Rp 6,747,000,000 Rp 674,700,000 0.20030 640,148.58 7,102.11 647,250.68 0.1200 0.0250 82,750.00 0.0875 310,717 0.1250 443,881.58 17,142.86 14,285.71 835,137.51 1,048,900.40 Pek. Berat 8 EXCAVATOR TAKEUCHI TB 150C E08
9. WHEEL LOADER KAWASAKI 50Z5 E09 35.0 7.6 Ton Rp 1,073,600,000 5.0 1,900 Rp 1,073,600,000 Rp 107,360,000 0.20030 101,862.09 1,130.11 102,992.19 0.1200 0.0250 57,925.00 0.0875 49,442 0.1250 70,631.58 17,142.86 14,285.71 177,646.84 166,903.73 Pek. Berat 9 WHEEL LOADER KAWASAKI 50Z5 E09
10. JACK HAMMER SAKAI R2H-2K static E10 80.0 0.3 Ton Rp 34,351,812 5.0 1,500 Rp 34,351,812 Rp 3,435,181 0.20030 4,128.40 45.80 4,174.21 0.1500 0.0300 162,000.00 0.0625 1,431 0.1750 4,007.71 14,285.71 11,428.57 84,557.00 6,191.97 Pek. Ringan 10 JACK HAMMER SAKAI R2H-2K static E10
11. THREE WHEELS ROLLER SAKAI R2H-2K E11 40.0 14.0 Ton Rp 963,000,000 5.0 1,700 Rp 963,000,000 Rp 96,300,000 0.20030 102,117.70 1,132.94 103,250.65 0.1200 0.0250 66,200.00 0.0875 49,566 0.1250 70,808.82 17,142.86 14,285.71 186,222.27 167,322.56 Pek. Berat 11 THREE WHEELS ROLLER SAKAI R2H-2K E11
12. VIBRATOR ROLLER SLDG Single Drum E12 45.0 14.0 Ton Rp 741,000,000 5.0 1,700 Rp 741,000,000 Rp 74,100,000 0.20030 78,576.55 871.76 79,448.32 0.1200 0.0250 74,475.00 0.0875 38,140 0.1250 54,485.29 17,857.14 17,142.86 166,828.58 128,749.76 Pek. Berat 12 VIBRATOR ROLLER SLDG Single Drum E12
13. TIRE ROLLER SAKAI TS205 E13 40.0 10.5 Ton Rp 1,004,090,000 5.0 1,700 Rp 1,004,090,000 Rp 100,409,000 0.20030 106,474.94 1,181.28 107,656.22 0.1200 0.0250 66,200.00 0.0875 51,681 0.1250 73,830.15 17,142.86 14,285.71 191,343.47 174,462.01 Pek. Berat 13 TIRE ROLLER SAKAI TS205 E13
14. GENERATOR CAT SILENT C18 E14 250.0 650.0 kVA Rp 1,336,456,780 5.0 1,300 Rp 1,336,456,780 Rp 133,645,678 0.20030 185,325.53 2,056.09 187,381.61 0.1500 0.0300 506,250.00 0.0625 64,253 0.1750 179,907.64 12,857.14 12,857.14 724,069.14 277,959.69 Pek. Ringan 14 GENERATOR CAT SILENT C18 E14
15. DUMP TRUCK 10 TON SCAHMAN MANUAL E15 150.0 10.0 Ton Rp 647,168,000 5.0 1,700 Rp 647,168,000 Rp 64,716,800 0.20030 68,626.49 761.37 69,387.86 0.1200 0.0250 248,250.00 0.0875 33,310 0.1250 47,585.88 21,428.57 17,142.86 328,908.95 112,446.32 Pek. Berat 15 DUMP TRUCK 10 TON SCAHMAN MANUAL E15
16. DUMP TRUCK 3,5 TON SINOTRUCK HOWO E16 150.0 3.5 Ton Rp 117,000,000 5.0 1,700 Rp 117,000,000 Rp 11,700,000 0.20030 12,406.82 137.65 12,544.47 0.1200 0.0250 248,250.00 0.0875 6,022 0.1250 8,602.94 18,571.43 14,285.71 262,832.14 20,328.91 Pek. Berat 16 DUMP TRUCK 3,5 TON SINOTRUCK HOWO E16
17. TRUCK TRAILER CHENGDA SCD 9400P E17 150.0 60.0 Ton Rp 305,500,000 5.0 1,500 Rp 305,500,000 Rp 30,550,000 0.20030 36,715.01 407.33 37,122.34 0.1500 0.0300 303,750.00 0.0625 12,729 0.1750 35,641.67 17,857.14 15,714.29 346,902.35 55,066.85 Pek. Ringan 17 TRUCK TRAILER CHENGDA SCD 9400P E17
18. CONCRETE MIXER YUJIE JS500 E18 50.0 800.0 Liter Rp 202,800,000 5.0 1,700 Rp 202,800,000 Rp 20,280,000 0.20030 21,505.16 238.59 21,743.75 0.1200 0.0250 82,750.00 0.0875 10,438 0.1250 14,911.76 14,285.71 12,857.14 108,025.72 35,236.78 Pek. Berat 18 CONCRETE MIXER YUJIE JS500 E18
19. STONE CHRUSER JINGTAI PF1315 E19 80.0 250.0 T/Jam Rp 546,000,000 5.0 1,900 Rp 546,000,000 Rp 54,600,000 0.20030 51,803.93 574.74 52,378.67 0.1200 0.0250 132,400.00 0.0875 25,145 0.1250 35,921.05 17,142.86 14,285.71 193,286.85 84,882.11 Pek. Berat 19 STONE CHRUSER JINGTAI PF1315 E19
20. WATER TANK JIANGSU 1000 LITER E20 76.0 1,000.0 Liter Rp 13,000,000 5.0 1,500 Rp 13,000,000 Rp 1,300,000 0.20030 1,562.34 17.33 1,579.67 0.1500 0.0300 153,900.00 0.0625 542 0.1750 1,516.67 17,142.86 12,857.14 155,736.27 2,343.27 Pek. Ringan 20 WATER TANK JIANGSU 1000 LITER E20
21. WATER PUMP WASINEX 0,75kW VFWI E21 80.0 3.0 Liter Rp 3,588,000 5.0 1,500 Rp 3,588,000 Rp 358,800 0.20030 431.21 4.78 435.99 0.1500 0.0300 162,000.00 0.0625 150 0.1750 418.60 14,285.71 11,428.57 162,506.81 646.74 Pek. Ringan 21 WATER PUMP WASINEX 0,75kW VFWI E21
22. PIPE BORING MACHINE XZ320E E22 80.0 320.0 Liter Rp 3,380,000,000 5.0 1,700 Rp 3,380,000,000 Rp 338,000,000 0.20030 358,419.36 3,976.47 362,395.83 0.1200 0.0250 132,400.00 0.0875 173,971 0.1250 248,529.41 17,142.86 14,285.71 553,661.96 587,279.61 Pek. Berat 22 PIPE BORING MACHINE XZ320E E22
23. FLATBED TRUCK DONGFENG E23 150.0 24.9 Ton Rp 1,040,000,000 5.0 1,500 Rp 1,040,000,000 Rp 104,000,000 0.20030 124,987.26 1,386.67 126,373.93 0.1500 0.0300 303,750.00 0.0625 43,333 0.1750 121,333.33 14,285.71 11,428.57 450,651.61 187,461.61 Pek. Ringan 23 FLATBED TRUCK DONGFENG E23
24. ASPHALT LIQUID MIXER BLS E24 80.0 5,000.0 Liter Rp 117,000,000 5.0 1,500 Rp 117,000,000 Rp 11,700,000 0.20030 14,061.07 156.00 14,217.07 0.1500 0.0300 162,000.00 0.0625 4,875 0.1750 13,650.00 14,285.71 12,857.14 476,726.43 21,089.43 Pek. Ringan 24 ASPHALT LIQUID MIXER BLS E24
25. WELDING SET MACHINE BX1-250C E25 80.0 250.0 Amp Rp 1,170,000 5.0 1,500 Rp 1,170,000 Rp 117,000 0.20030 140.61 1.56 142.17 0.1500 0.0300 162,000.00 0.0625 49 0.1750 136.50 14,285.71 1,471.00 162,165.26 210.89 Pek. Ringan 25 WELDING SET MACHINE BX1-250C E25
26. BACKHOE LOADER KOMATSU WB97R E26 40.0 7.0 Ton Rp 4,540,625,000 5.0 1,700 Rp 4,540,625,000 Rp 454,062,500 0.20030 481,493.46 5,341.91 486,835.37 0.1200 0.0250 66,200.00 0.0875 233,709 0.1250 333,869.49 17,142.86 14,285.71 632,114.97 788,939.79 Pek. Berat 26 BACKHOE LOADER KOMATSU WB97R E26
27. TANDEM ROLLER BOMAG BW174 AD-2AM E27 75.0 10.0 Ton Rp 4,578,720,000 5.0 1,700 Rp 4,578,720,000 Rp 457,872,000 0.20030 485,533.10 5,386.73 490,919.83 0.1200 0.0250 124,125.00 0.0875 235,669 0.1250 336,670.59 17,142.86 17,142.86 694,787.89 795,558.84 Pek. Berat 27 TANDEM ROLLER BOMAG BW174 AD-2AM E27
28. HYDRAULIC EXCAVATOR VOLVO EW145B E28 45.0 13.1 Ton Rp 1,679,000,000 5.0 1,700 Rp 1,679,000,000 Rp 167,900,000 0.20030 178,043.22 1,975.29 180,018.52 0.1200 0.0250 74,475.00 0.0875 86,419 0.1250 123,455.88 17,857.14 17,142.86 283,735.01 291,728.54 Pek. Berat 28 HYDRAULIC EXCAVATOR VOLVO EW145B E28
29. ASPHALT FINISHER NIIGATA NF220 E29 45.0 12.2 Gal Rp 4,000,000,000 5.0 1,900 Rp 4,000,000,000 Rp 400,000,000 0.20030 379,515.98 4,210.53 383,726.51 0.1200 0.0250 74,475.00 0.0875 184,211 0.1250 263,157.89 17,142.86 14,285.71 818,732.51 621,846.99 Pek. Berat 29 ASPHALT FINISHER NIIGATA NF220 E29
30. TRACKED EXCAVATOR JCB JS205 E30 40.0 20.5 Ton Rp 1,403,000,000 5.0 1,700 Rp 1,403,000,000 Rp 140,300,000 0.20030 148,775.84 1,650.59 150,426.43 0.1200 0.0250 66,200.00 0.0875 72,213 0.1250 103,161.76 17,142.86 14,285.71 241,061.10 243,773.16 Pek. Berat 30 TRACKED EXCAVATOR JCB JS205 E30
31. LANDFILL COMPACTOR BOMAG BC462RB E31 50.0 21.3 Ton Rp 4,933,500,000 5.0 1,700 Rp 4,933,500,000 Rp 493,350,000 0.20030 523,154.41 5,804.12 528,958.52 0.1200 0.0250 82,750.00 0.0875 253,930 0.1250 362,757.35 17,142.86 14,285.71 697,630.44 857,202.35 Pek. Berat 31 LANDFILL COMPACTOR BOMAG BC462RB E31
32. WEED BOAT A.BERKENHEGER 6550 E32 50.0 14.5 Ton Rp 13,950,000,000 5.0 1,500 Rp 13,950,000,000 Rp 1,395,000,000 0.20030 1,676,511.84 18,600.00 1,695,111.84 0.1500 0.0300 101,250.00 0.0625 581,250 0.1750 1,627,500.00 17,142.86 12,857.14 2,071,709.06 2,514,509.06 Pek. Ringan 32 WEED BOAT A.BERKENHEGER 6550 E32
33. ASPHALT CUTTER ATLAS COPCO 350 E33 90.0 216.0 lbs Rp 43,873,363 5.0 1,500 Rp 43,873,363 Rp 4,387,336 0.20030 5,272.70 58.50 5,331.20 0.1500 0.0300 182,250.00 0.0625 1,828 0.1750 5,118.56 14,285.71 11,428.57 188,447.18 7,908.24 Pek. Ringan 33 ASPHALT CUTTER ATLAS COPCO 350 E33
34. SLIPFORM PAVER WIRTGEN SP25 E34 57.0 13.6 Ton Rp 6,006,000,000 5.0 1,500 Rp 6,006,000,000 Rp 600,600,000 0.20030 721,801.44 8,008.00 729,809.44 0.1500 0.0300 115,425.00 0.0625 250,250 0.1750 700,700.00 15,714.29 12,142.86 963,781.78 1,082,590.78 Pek. Ringan 34 SLIPFORM PAVER WIRTGEN SP25 E34
KETERANGAN : 1 Tingkat Suku Bunga = 5% per-tahun
2 Upah Operator / Sopir / Mekanik = 130,000 Rupiah per-orang/jam
3 Upah Pembantu Operator/Sopir/Mekanik = 100,000 Rupiah per-orang/jam
4 Harga Bahan Bakar Bensin = 7,500 Rupiah per-liter
5 Harga Bahan Bakar Solar = 6,500 Rupiah per-liter
6 Minyak Pelumas = 35,000 Rupiah per-liter
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (II)
URAIAN ANALISA HARGA SATUAN

jenis pekerjaan : pekerjaan galian untuk saluran


satuan pembayaran : m3

No. URAIAN KODE KOEFISIEN SATUAN


I. ASUMSI
1. mengunakan alat berat
2. lokasi pekerjaan : sepanjang jalan
3. kondisi jalan: ringan/baik sekali
4. jam kerja efektif per hari Tk 7.00 Jam
5. faktor pengembangan bahan Tk 1.20

II. URUTAN KERJA


1. penggalian dilakukan dengan menggunakan excavator
selanjutnya excavator menuangkan material
2. hasil galian ke dalam dump truck
dum truck membuang material hasil galian ke luar
3. lokasi jalan sejauh L 1.00 Km
4. sekelompok pekerja akan merapikan hasil galian

III. PEMAKAIAN BAHAN, ALAT, DAN TENAGA


1. BAHAN
tidak ada bahan yang diperlukan

2. ALAT
a. EXCAVATOR
Kapasitas Bucket KB 0.50 m3
Faktor Bucket fb 0.90
Faktor Efisiensi Alat fe 0.83

Waktu Siklus
- menggali Wg 0.25 menit
- memuat Wp1 0.25 menit
- putar Wp2 0.25 menit
- buang Wb 0.25 menit
CT1 1.00 menit

KP = KB x 60/CT x FK KP1 24.9 m3/jam

Koefisien Alat/m3 = 1:KP1 0.04016 jam

b. DUMP TRUCK
Kapasitas Muat C 4.00 m3
Faktor Efisiensi alat fe 0.83
Kecepatan Angkut V1 40.00 Km/jam
Kecepatan Balik V2 60.00 Km/jam

Waktu Siklus
- waktu tempuh isi = (L:V1) x 60 t1 1.50 menit
- waktu tempuh kosong = (L:V2) x 60 t2 1.00 menit
- waktu muat = (C:KP1) x 60 t3 9.64 menit
- lain-lain t4 3.50 menit
CT2 15.64 menit

KP = C x 60/CT x FK KP2 12.74 m3/jam

koefisien alat/m3 = 1:KP2 0.08 jam

c. ALAT BANTU
diperlukan alat-alat bantu kecil 1.00 LS
- sekop
- keranjang + sapu

3. TENAGA
Produksi menentukan :
EXCAVATOR KP1 24.9 m3/jam
produksi galian/hari = Tk x KP1 KPt 174.3 m3
Kebutuhan tenaga :
- pekerja P 2.00 orang
- mandor M 1.00 orang

koefisien tenaga/m3
- pekerja = (Tk x P) : KPt 0.08032 jam
- mandor = (Tk x M) : KPt 0.04016 jam

4. HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


Lihat perhitungan

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam Perekaman Analisa
MASING-MASING HARGA SATUAN
didapat harga satuan pekerjaan
Rp. /m3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : m3
KETERANGAN
Lump Sum
DAFTAR HARGA DASAR UPAH

No. Tenaga Kerja Harga dasar/OH Jam kerja efektif harga dasar/jam
(Rp.) (jam) (Rp.)
1. pekerja Rp 70,000.00 7 Rp 10,000.00
2. tukang Rp 90,000.00 7 Rp 12,857.14
3. kepala tukang Rp 96,500.00 7 Rp 13,785.71
4. mandor Rp 100,000.00 7 Rp 14,285.71
5. operator Rp 95,000.00 7 Rp 13,571.43
6. pembantu operator Rp 75,000.00 7 Rp 10,714.29
7. supir Rp 70,000.00 7 Rp 10,000.00
8. pembantu supir Rp 60,000.00 7 Rp 8,571.43
9. mekanik Rp 65,000.00 7 Rp 9,285.71
10. pembantu mekanik Rp 60,000.00 7 Rp 8,571.43
ANALISA
Jenis pekerjaan : pekerjaan galian untuk saluran
satuan pembayaran : m3

PERKIRAAN Harga satuan


No. KOMPONEN SATUAN
KUANTITAS (Rp.)
A. TENAGA
1. Pekerja jam 0.1071 Rp 10,000.00
2. Mandor jam 0.0535 Rp 14,285.71
jumlah harga tenaga
B. BAHAN

jumlah harga bahan


C. PERALATAN
1. Excavator jam 0.0535 Rp 1,048,900.40
2. Dump Truck jam 0.1135 Rp 112,446.32
3. Alat Bantu LS 1 Rp 500.00
jumlah harga peralatan
D. JUMLAH HARGA TENAGA, BAHAN, DAN PERALATAN
(A+B+C)
E. OVERHEAD & PROFIT (15% x D)
F. HARGA SATUAN PEKERJAAN (D+E)
Jumlah harga
(Rp.)

Rp 1,071.00
Rp 764.29
Rp 1,835.29

Rp 56,116.17
Rp 12,762.66
Rp 500.00
Rp 69,378.83

Rp 71,214.11
Rp 10,682.12
Rp 81,896.23
RENCANA ANGGARAN BIAYA

HARGA SATUAN
No. URAIAN SATUAN PERKIRAAN KUANTITAS (Rp.)
a b c d e
pekerjaan galian untuk Selokan Drainase
1. dan saluran air m3 21 Rp 29,216.78

PPN 10%
Jumlah Total
Dibulatkan
TERBILANG : ENAM RATUS TUJUH PULUH LIMA RIBU RUPIAH
JUMLAH HARGA
(Rp.)
f = (d x e)

Rp 613,552.38

Rp 61,355.24
Rp 674,907.62
Rp 675,000.00
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN

Jumlah harga
No.Devisi Uraian pekerjaan
(Rp)
1 Umum Rp -
2 Drainase Rp -
3 Pekerjaan Tanah Rp 5,814,632.48
4 Pelebaran Perkerasan & Bahu Jalan Rp -
5 Perkerasan Berbutir & Beton Semen Rp -
6 Perkerasan Aspal Rp -
7 Struktur Rp -
8 Pengembalian Kondisi & Pekerjaan Minor Rp -
9 Pekerjaan Harian Rp -
10 Pekerjaan Pemeliharaan Rp -
Daftar Kuantitas & Harga

No. Mata
Pembayaran

1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
1.13
1.14
1.15
1.16
1.17
1.18
1.19
1.20
1.21

2.1
2.2
2.3
2.4

3.1
3.2
3.3
3.4

4.1
4.2

5.1
5.2
5.3
5.4
5.5
5.6

6.1
6.2
6.3
6.4
6.5
6.6
6.7

7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
7.13
7.14
7.15
7.16

8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8

9.1
10.1
10.2
ftar Kuantitas & Harga

Uraian Satuan

DEVISI I - UMUM
Ringkasan Pekerjaan
Mobilisasi
Kantor Lapangan dan Pelayanan
Fasilitas dan Pelayanan Pengujian
Transportasi dan Pananganan
Pembayaran dan Sertifikat Bulanan
Pembayaran Sementara
Manajemen dan Keselamatan Lalu Lintas
Kajian Teknis Rekayasa Lapangan
Standar Rujukan
Bahan dan Penyimpanan
Jadwal Pelaksanaan
Prosedur Perintah Perubahan Variasi
Penutupan Kontrak
Dokumen Rekaman Kegiatan Proyek
Pekerjaan Pembersihan
Pengamanan Lingkungan Hidup
Relokasi Utilitas dan Pelayanan yang ada
Keselamatan dan Kesehatan Kerja (K3)
Pengujian Pengeboran
Manajemen Mutu
Jumlah Harga Pekerjaan DEVISI 1
DEVISI 2 - DRAINASE
Selokan dan Saluran Air
Pasangan Batu Dengan Mortar
Gorong-gorong dan Drainase Beton
Drainase Porous
Jumlah Harga Pekerjaan DEVISI 2
DEVISI 3 - PEKERJAAN TANAH
Galian m3
Timbunan m3
Penyiapan Badan Jalan
Pengupasan Perkerasan Lama dan Dicampur Kembali
Jumlah Harga Pekerjaan DEVISI 3
DEVISI 4 - PELEBARAN PERKERASAN DAN BAHU JALAN
Pelebaran Perkerasan
Bahu Jalan
Jumlah Harga Pekerjaan DEVISI 4
DEVISI 5 - PEKERASAN BERBUTIR DAN PEKERJAAN BETON SEMEN
Lapis Pondasi Agregat
Lapis Pondasi Jalan Tanpa Penutup Aspal
Perkerasan Beton Semen
Lapis Pondasi Semen Tanah
Lapis Beton Semen Pondasi dan Pondasi Bawah (CTB & CTSB)
Lapis Pondasi Agregat dengan Cement Treated Base (CTB)
Jumlah Harga Pekerjaan DEVISI 5
DEVISI 6 - PERKERASAN ASPAL
Lapis Resap Pengikat dan Lapis Perekat
Laburan Aspal Satu Lapis (Burtu) dan Laburan Aspal Dua Lapis (Burda)
Campuran Aspal Panas
Lasbutag dan Latasbusir
Campuran Aspal Dingin
Lapis Perata Penetrasi Macadam
Pemeliharaan dengan Laburan Aspal
Jumlah Harga Pekerjaan DEVISI 6
DEVISI 7 - STRUKTUR
Beton
Beton Pratekan
Baja Tulangan
Baja Struktur
Pemasangan Jembatan Rangka Baja
Pondasi Tiang
Pondasi Sumuran
Adukan Semen
Pasangan Batu
Pasangan Batu Kosong dan Bronjong
Sambungan Ekspansi (Expansion Joint)
Perletakan (Bearing)
Sandaran (Railing)
Papan Nama Jembatan
Pembongkaran Struktur
Drainase Lantai Jembatan Pipa Cucuran
Jumlah Harga Pekerjaan DEVISI 7
DEVISI 8 - PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
Pengembalian Kondisi Perkerasan Lama
Pengembalian Kondisi Bahu Jalan Lama Pada Perkerasan Berpenutup Aspal
Pengembalian Kondisi Selokan, Saluran Air, Galian, Timbunan dan Penghijauan
Perlengkapan Jalan dan Pengatur Lalu Lintas
Pengembalian Kondisi Jembatan
Kerb Pracetak Pemisah Jalan (Concrete Barrier)
Penerangan Jalan dan Pekerjaan Elektrikal
Pagar Pemisah Pedestriasn
Jumlah Harga Pekerjaan DEVISI 8
DEVISI 9 - PEKERJAAN HARIAN
Pekerjaan Harian
Jumlah Harga Pekerjaan DEVISI 9
DEVISI 10 - PEKERJAAN PEMELIHARAAN RUTIN
Pemeliharaan Rutin Perkerasan, Bahu Jalan, Drainase, Perlengkapan Jalan dan Jembatan
Pemeliharaan Jalan Samping dan Jembatan
Jumlah Harga Pekerjaan DEVISI 10
Perkiraan Harga Satuan Jumlah Harga
Kuantitas (Rp) (Rp)

21 Rp 81,896.23 Rp 1,719,820.88
50 Rp 81,896.23 Rp 4,094,811.61

Rp 5,814,632.48
ANALISA K3

No. Jenis Peralatan Satuan Harga


1 Helmet Buah Rp 55,000.00
2 Rompi Buah Rp 100,000.00
3 Sepatu Buah Rp 25,000.00
4 Dll Buah Rp -
Total Rp 180,000.00
Periode Konstruksi Hari 180.00
Jam Pemakaian Jam 8.00
Koefisien jam 125
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI
% TERHADAP TOTAL BIAYA PROYEK

No URAIAN Satuan Vol

A. SEWA TANAH M2 1

B. PERALATAN
Periksa Lembar 1.2-2

C. MOBILISASI FASILITAS KONTRAKTOR 1


1 Base Camp
2 Kantor
3 Barak
4 Bengkel
5 Gudang, dan Lain-lain
6

D. MOBILISASI FASILITAS LABORATORIUM set 1.00


1 Ruang Laboratorium (Sesuai Gambar)

2 Soil & Agregat Testing


Compaction Test
CBR Test
Specific Gravity
Atterberg Limits
Grain Size Analysis
Field Density Test by Sand Cone Methode
Moisture Content
Abrasion of Aggregate by Los Angeles Machine

3 Bituminous Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Reffux Method
Specific Gravity for Coarse Aggregate
Specific Gravity for Fine Aggregate
Mix Air Void Content (Accurate Method)
Core Drill
Metal Thermometer
Accessories an Tolls
Penetration Test
Soeftening Point
Refusal Density Compactor
4 Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine

5 Pendukung (Periksa Fasilitas Laboratorium)

6 Operasional (Periksa Fasilitas Laboratorium)

E MOBILISASI LAINNYA
E.II PEKERJAAN DARURAT LS 1
1 Pekerjaan Jembatan Lama
2 Pemeliharaan Jalan Kerja / Samping
3
4
5
6

E.II Lain-lain Set 1


1 Komunikasi Lapangan Lengkap
2
3
4
5
6

F MANAJEMEN DAN KESELAMATAN LALU LINTAS LS

G DEMOBILISASI LS 1

TOTAL BIAYA MOBILISASI

ITEM PEMBAYARAN NO. : 1.2


JENIS PEKERJAAN : MOBILISASI
% TERHADAP TOTAL BIAYA PROYEK

Kode
No Jenis Alat Alat Satuan

B. PERALATAN
1. ASPHALT MIXING PLANT LB400 E01 Unit
2. ASPHALT FINISHER CAT AP 255 E02 Unit
3. ASPHALT SPRAYER DONGFENG C.4 E03 Unit
4. BULLDOZER KOMATSU D31Ex-22 E04 Unit
5. COMPRESSOR ATLAS XAS97 Dd E05 Unit
6. CRANE KATO SR-700L E06 Unit
7. GRADER HIDROMEK MG330 E07 Unit
8. EXCAVATOR TAKEUCHI TB 150C E08 Unit
9. WHEEL LOADER KAWASAKI 50Z5 E09 Unit
10. JACK HAMMER SAKAI R2H-2K static E10 Unit
11. THREE WHEELS ROLLER SAKAI R2H-2K E11 Unit
12. VIBRATOR ROLLER SLDG Single Drum E12 Unit
13. TIRE ROLLER SAKAI TS205 E13 Unit
14. GENERATOR CAT SILENT C18 E14 Unit
15. DUMP TRUCK 10 TON SCAHMAN MANUAL E15 Unit
16. DUMP TRUCK 3,5 TON SINOTRUCK HOWO E16 Unit
17. TRUCK TRAILER CHENGDA SCD 9400P E17 Unit
18. CONCRETE MIXER YUJIE JS500 E18 Unit
19. STONE CHRUSER JINGTAI PF1315 E19 Unit
20. WATER TANK JIANGSU 1000 LITER E20 Unit
21. WATER PUMP WASINEX 0,75kW VFWI E21 Unit
22. PIPE BORING MACHINE XZ320E E22 Unit
23. FLATBED TRUCK DONGFENG E23 Unit
24. ASPHALT LIQUID MIXER BLS E24 Unit
25. WELDING SET MACHINE BX1-250C E25 Unit
26. BACKHOE LOADER KOMATSU WB97R E26 Unit
27. TANDEM ROLLER BOMAG BW174 AD-2AM E27 Unit
28. HYDRAULIC EXCAVATOR VOLVO EW145B E28 Unit
29. ASPHALT FINISHER NIIGATA NF220 E29 Unit
30. TRACKED EXCAVATOR JCB JS205 E30 Unit
31. LANDFILL COMPACTOR BOMAG BC462RB E31 Unit
32. WEED BOAT A.BERKENHEGER 6550 E32 Unit
33. ASPHALT CUTTER ATLAS COPCO 350 E33 Unit
34. SLIPFORM PAVER WIRTGEN SP25 E34 Unit

Total untuk item B pada Lembar 1


lembar 1.2-1
Harga Jumlah
Satuan Harga
(Rp) (Rp)
500.00 500.00

260,300,000.00

50,000.00 50,000.00

55,940,000.00 55,940,000.00
100,000,000.00 100,000,000.00

5,000,000.00 5,000,000.00

5,000,000.00

78,090,000.00 78,090,000.00

504,380,500.00

lembar 1.2-2
Harga Jumlah
Vol Satuan Harga
(Rp) (Rp)

1 Rp 443,065.98 Rp 443,065.98
1 Rp 269,399.66 Rp 269,399.66
1 Rp 48,118.05 Rp 48,118.05
1 Rp 223,704.01 Rp 223,704.01
1 Rp 48,596.99 Rp 48,596.99
1 Rp 1,343,624.78 Rp 1,343,624.78
1 Rp 323,003.79 Rp 323,003.79
1 Rp 1,048,900.40 Rp 1,048,900.40
1 Rp 166,903.73 Rp 166,903.73
1 Rp 6,191.97 Rp 6,191.97
1 Rp 167,322.56 Rp 167,322.56
1 Rp 128,749.76 Rp 128,749.76
1 Rp 174,462.01 Rp 174,462.01
1 Rp 277,959.69 Rp 277,959.69
1 Rp 112,446.32 Rp 112,446.32
1 Rp 20,328.91 Rp 20,328.91
1 Rp 55,066.85 Rp 55,066.85
1 Rp 35,236.78 Rp 35,236.78
1 Rp 84,882.11 Rp 84,882.11
1 Rp 2,343.27 Rp 2,343.27
1 Rp 646.74 Rp 646.74
1 Rp 587,279.61 Rp 587,279.61
1 Rp 187,461.61 Rp 187,461.61
1 Rp 21,089.43 Rp 21,089.43
1 Rp 210.89 Rp 210.89
1 Rp 788,939.79 Rp 788,939.79
1 Rp 795,558.84 Rp 795,558.84
1 Rp 291,728.54 Rp 291,728.54
1 Rp 621,846.99 Rp 621,846.99
1 Rp 243,773.16 Rp 243,773.16
1 Rp 857,202.35 Rp 857,202.35
1 Rp 2,514,509.06 Rp 2,514,509.06
1 Rp 7,908.24 Rp 7,908.24
1 Rp 1,082,590.78 Rp 1,082,590.78

Rp 12,981,053.66

Anda mungkin juga menyukai