HSD BAHAN
1 Mandor OH 250,000
2 Kepala tukang OH 185,000
3 Tukang Listrik OH 150,000
4 Tukang kayu OH 150,000
5 Tukang batu OH 150,000
6 Tukang besi OH 150,000
7 Tukang cat OH 150,000
8 Tukang las OH 200,000
9 Pekerja OH 100,000
10 Pembantu Juru ukur OH 80,000
11 Juru Ukur OH 80,000
12 Tukang Aluminium OH 150,000
NO. URAIAN SAT HARGA
(Rp.)
HSD PERALATAN
-
1 Mandor OH -
2 Kepala tukang OH -
3 Tukang OH -
4 Tukang kayu OH -
5 Tukang batu OH -
6 Tukang besi OH -
7 Tukang cat OH -
8 Tukang las OH -
9 Pekerja OH -
10 Pembantu Juru ukur OH -
11 Juru Ukur OH -
H. Syofyandi Syafei
Direktur
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
6.1 1 m2 - Pembersihan
a. Tenaga : - Pekerja 0.100 OH 100,000.00 10,000.00
- Mandor 0.050 OH 250,000.00 12,500.00 Rp 22,500.00
Rp 22,500.00
PUPR.2016/A.3.2.1.11
3.1 1 m3 - Pondasi sumuran, diameter 100 cm
a. Tenaga : - Pekerja 2.400 OH 100,000.00 240,000.00
- Tukang batu 0.800 OH 150,000.00 120,000.00
- Kepala tukang 0.080 OH 185,000.00 14,800.00
- Mandor 0.119 OH 250,000.00 29,750.00 Rp 404,550.00
PUPR.2016/A.4.4.1.23
4.1 1 m2 - Dinding Roster Bata, 1 PC : 4 PP
a. Tenaga : - Pekerja 0.300 OH 100,000.00 30,000.00
- Tukang batu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.015 OH 250,000.00 3,750.00 50,600.00
PUPR.2016/A.4.4.1.23 *)
4.2 1 m2 - Dinding Roster Keramik 30cm, 1 PC : 4 PP
a. Tenaga : - Pekerja 0.300 OH 100,000.00 30,000.00
- Tukang batu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.015 OH 250,000.00 3,750.00 50,600.00
PUPR.2016/A.4.4.1.23 *)
5.1 1 m2 - Dinding Glassblok 20cm, 1 PC : 4 PP
a. Tenaga : - Pekerja 0.300 OH 100,000.00 30,000.00
- Tukang batu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.015 OH 250,000.00 3,750.00 50,600.00
4.13.4 1 m2 - PLAT ; LANTAI ; ATAP beton bertulang + BEKISTING + PERANCAH (WIREMESH M10)
- Campuran beton K-225
a. Bahan : - Semen / PC 44.538 kg 2,500.00 111,344.54
- Pasir beton 0.050 m3 225,000.00 11,217.86
- Koral beton 0.078 m3 350,000.00 27,144.44
- Air 21.500 ltr 130.00 2,795.00
b. Tenaga : - Pekerja 0.132 OH 100,000.00 13,200.00
- Tukang batu 0.020 OH 150,000.00 3,075.00
- Kepala tukang 0.002 OH 185,000.00 370.00
- Mandor 0.006 OH 250,000.00 1,500.00
c. Alat : - Beton Mixer 0.020 unit/hr 275,000.00 5,500.00 Rp 176,146.84
- Bekisting beton
a. Bahan : - Kayu hutan balok 0.020 m3 4,600,000.00 92,000.00
- Paku 0.250 kg 24,000.00 6,000.00
- Plywood 0.350 lbr 175,000.00 61,250.00
- Minyak bekisting 0.200 ltr 8,100.00 1,620.00
b. Tenaga : - Pekerja 0.200 OH 100,000.00 20,000.00
- Tukang kayu 0.500 OH 150,000.00 75,000.00
- Kepala tukang 0.050 OH 185,000.00 9,250.00
- Mandor 0.010 OH 250,000.00 2,500.00 Rp 267,620.00
- Perancah beton
a. Bahan : - Kayu hutan balok 0.056 m3 4,600,000.00 257,600.00
- Paku 0.140 kg 24,000.00 3,360.00
b. Tenaga : - Pekerja 0.125 OH 100,000.00 12,500.00
- Tukang kayu 0.300 OH 150,000.00 45,000.00
- Kepala tukang 0.030 OH 185,000.00 5,550.00
- Mandor 0.006 OH 250,000.00 1,500.00 Rp 325,510.00
HSP Rp 1,108,761.00
- Pembesian beton
a. Bahan : - Besi beton 115.500 kg 18,200.00 2,102,100.00
- Bendrat 1.650 kg 28,000.00 46,200.00
b. Tenaga : - Pekerja 0.770 OH 100,000.00 77,000.00
- Tukang besi 0.770 OH 150,000.00 115,500.00
- Kepala tukang 0.0770 OH 185,000.00 14,245.00
- Mandor 0.0440 OH 250,000.00 11,000.00 Rp 2,366,045.00
- Bekisting beton
a. Bahan : - Kayu hutan papan 0.268 m3 5,175,000.00 1,386,900.00
- Paku 3.350 kg 24,000.00 80,400.00
- Minyak bekisting 1.675 ltr 8,100.00 13,567.50
b. Tenaga : - Pekerja 5.528 OH 100,000.00 552,750.00
- Tukang kayu 2.764 OH 150,000.00 414,562.50
- Kepala tukang 0.276 OH 185,000.00 51,129.38
- Mandor 0.276 OH 250,000.00 69,093.75 Rp 2,568,403.13
HSP Rp 6,510,223.00
- Pembesian beton
a. Bahan : - Besi beton 178.500 kg 18,200.00 3,248,700.00
- Bendrat 2.550 kg 28,000.00 71,400.00
b. Tenaga : - Pekerja 1.190 OH 100,000.00 119,000.00
- Tukang besi 1.190 OH 150,000.00 178,500.00
- Kepala tukang 0.1190 OH 185,000.00 22,015.00
- Mandor 0.0680 OH 250,000.00 17,000.00 Rp 3,656,615.00
- Bekisting beton
a. Bahan : - Kayu hutan papan 0.268 m3 5,175,000.00 1,386,900.00
- Paku 3.350 kg 24,000.00 80,400.00
- Minyak bekisting 1.675 ltr 8,100.00 13,567.50
b. Tenaga : - Pekerja 5.528 OH 100,000.00 552,750.00
- Tukang kayu 2.764 OH 150,000.00 414,562.50
- Kepala tukang 0.276 OH 185,000.00 51,129.38
- Mandor 0.276 OH 250,000.00 69,093.75 Rp 2,568,403.13
HSP Rp 7,800,793.00
- Pembesian beton
a. Bahan : - Besi beton 140.175 kg 18,200.00 2,551,185.00
- Bendrat 2.003 kg 28,000.00 56,070.00
b. Tenaga : - Pekerja 0.934 OH 100,000.00 93,450.00
- Tukang besi 0.934 OH 150,000.00 140,175.00
- Kepala tukang 0.0935 OH 185,000.00 17,288.25
- Mandor 0.0534 OH 250,000.00 13,350.00 Rp 2,871,518.25
- Bekisting beton
a. Bahan : - Kayu hutan papan 0.200 m3 5,175,000.00 1,035,000.00
- Paku 2.500 kg 24,000.00 60,000.00
- Minyak bekisting 1.250 ltr 8,100.00 10,125.00
b. Tenaga : - Pekerja 4.125 OH 100,000.00 412,500.00
- Tukang kayu 2.063 OH 150,000.00 309,375.00
- Kepala tukang 0.206 OH 185,000.00 38,156.25
- Mandor 0.206 OH 250,000.00 51,562.50 Rp 1,916,718.75
HSP Rp 6,364,012.00
- Pembesian beton
a. Bahan : - Besi beton 129.150 kg 18,200.00 2,350,530.00
- Bendrat 1.845 kg 28,000.00 51,660.00
b. Tenaga : - Pekerja 0.861 OH 100,000.00 86,100.00
- Tukang besi 0.861 OH 150,000.00 129,150.00
- Kepala tukang 0.0861 OH 185,000.00 15,928.50
- Mandor 0.0492 OH 250,000.00 12,300.00 Rp 2,645,668.50
- Pembesian beton
a. Bahan : - Besi beton 105.000 kg 18,200.00 1,911,000.00
- Bendrat 1.500 kg 28,000.00 42,000.00
b. Tenaga : - Pekerja 0.700 OH 100,000.00 70,000.00
- Tukang besi 0.700 OH 150,000.00 105,000.00
- Kepala tukang 0.0700 OH 185,000.00 12,950.00
- Mandor 0.0400 OH 250,000.00 10,000.00 Rp 2,150,950.00
- Bekisting beton
a. Bahan : - Kayu hutan balok 0.130 m3 4,600,000.00 600,300.00
- Paku 2.175 kg 24,000.00 52,200.00
- Plywood 1.740 lbr 175,000.00 304,500.00
- Minyak bekisting 1.740 ltr 8,100.00 14,094.00
b. Tenaga : - Pekerja 1.740 OH 100,000.00 174,000.00
- Tukang kayu 4.350 OH 150,000.00 652,500.00
- Kepala tukang 0.435 OH 185,000.00 80,475.00
- Mandor 0.087 OH 250,000.00 21,750.00 Rp 1,899,819.00
- Perancah beton
a. Bahan : - Kayu hutan balok 0.244 m3 4,600,000.00 1,120,560.00
- Paku 1.522 kg 24,000.00 36,540.00
b. Tenaga : - Pekerja 1.088 OH 100,000.00 108,750.00
- Tukang kayu 2.610 OH 150,000.00 391,500.00
- Kepala tukang 0.261 OH 185,000.00 48,285.00
- Mandor 0.052 OH 250,000.00 13,050.00 Rp 1,718,685.00
HSP Rp 7,345,229.00
3.8.1 1 m2 - Acian
a. Tenaga : - Pekerja 0.200 OH 100,000.00 20,000.00
- Tukang batu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.010 OH 250,000.00 2,500.00 Rp 39,350.00
8. PEK. LISTRIK
No. Uraian Koefisien Satuan Harga Satuan Jumlah Harga Harga Satuan
(Rp.) (Rp.) Pekerjaan
9.2.2 1 unit - MCB lengkap
MCB lengkap setara schneider 1.000 unit 825,000.00 825,000.00
HSP Rp 825,000.00
HSP Rp 9,847,047.50
HSP Rp 2,216,280.00
HSP Rp 398,031.10
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
8.2.1 1 bh - Wastafel
a. Bahan : - Wastafel setara toto 1.200 bh 471,000.00 565,200.00
- Semen Gresik 6.000 kg 2,500.00 15,000.00
- Pasir pasang 0.010 m3 140,000.00 1,400.00 Rp 581,600.00
PUPR.2016/A.4.5.1.5
3.7.1 1 m2 - Plafond TRIPLEK
a. Tenaga : - Pekerja 0.100 OH 100,000.00 10,000.00
- Tukang kayu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.005 OH 250,000.00 1,250.00 Rp 28,100.00
PUPR.2016/A.4.5.1.7
3.7.1 1 m2 - Plafond GYPSUM
a. Tenaga : - Pekerja 0.100 OH 100,000.00 10,000.00
- Tukang kayu 0.050 OH 150,000.00 7,500.00
- Kepala tukang 0.005 OH 185,000.00 925.00
- Mandor 0.005 OH 250,000.00 1,250.00 Rp 19,675.00
PUPR.2016/A.4.6.1.19
6.11.1 1 m2 - Rangka plafond 50cm, Kayu Meranti
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.300 OH 150,000.00 45,000.00
- Kepala tukang 0.030 OH 185,000.00 5,550.00
- Mandor 0.075 OH 250,000.00 18,750.00 Rp 84,300.00
PUPR.2016/A.4.6.1.19
6.11.1 1 m2 - Rangka plafond 50cm, Kayu Lokal
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.300 OH 150,000.00 45,000.00
- Kepala tukang 0.030 OH 185,000.00 5,550.00
- Mandor 0.075 OH 250,000.00 18,750.00 Rp 84,300.00
PUPR.2016/A.4.5.1.9
3.7.1 1 m1 - List Plafond KAYU PROFIL
a. Tenaga : - Pekerja 0.050 OH 100,000.00 5,000.00
- Tukang batu 0.050 OH 150,000.00 7,500.00
- Kepala tukang 0.005 OH 185,000.00 925.00
- Mandor 0.003 OH 250,000.00 750.00 Rp 14,175.00
PUPR.2016/A.4.5.1.9 *)
3.7.1 1 m1 - List Plafond GYPSUM
a. Tenaga : - Pekerja 0.050 OH 100,000.00 5,000.00
- Tukang batu 0.050 OH 150,000.00 7,500.00
- Kepala tukang 0.005 OH 185,000.00 925.00
- Mandor 0.003 OH 250,000.00 750.00 Rp 14,175.00
PUPR.2016/A.4.5.2.4
3.7.1 1 m1 - Genteng Bubung PALENTONG Kecil
a. Tenaga : - Pekerja 0.400 OH 100,000.00 40,000.00
- Tukang kayu 0.200 OH 150,000.00 30,000.00
- Kepala tukang 0.020 OH 185,000.00 3,700.00
- Mandor 0.002 OH 250,000.00 500.00 Rp 74,200.00
PUPR.2016/A.4.5.2.3
3.7.1 1 m2 - Genteng PALENTONG Besar
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.075 OH 150,000.00 11,250.00
- Kepala tukang 0.008 OH 185,000.00 1,480.00
- Mandor 0.008 OH 250,000.00 2,000.00 Rp 29,730.00
PUPR.2016/A.4.5.2.6
3.7.1 1 m1 - Genteng Bubung PALENTONG Besar
a. Tenaga : - Pekerja 0.400 OH 100,000.00 40,000.00
- Tukang kayu 0.200 OH 150,000.00 30,000.00
- Kepala tukang 0.020 OH 185,000.00 3,700.00
- Mandor 0.002 OH 250,000.00 500.00 Rp 74,200.00
PUPR.2016/A.4.5.2.5
3.7.1 1 m1 - Genteng Bubung GLAZUUR
a. Tenaga : - Pekerja 0.400 OH 100,000.00 40,000.00
- Tukang kayu 0.200 OH 150,000.00 30,000.00
- Kepala tukang 0.020 OH 185,000.00 3,700.00
- Mandor 0.002 OH 250,000.00 500.00 Rp 74,200.00
PUPR.2016/A.4.5.2.2 *)
3.7.1 1 m2 - Genteng ex. AMBULU
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.075 OH 150,000.00 11,250.00
- Kepala tukang 0.008 OH 185,000.00 1,480.00
- Mandor 0.008 OH 250,000.00 2,000.00 Rp 29,730.00
PUPR.2016/A.4.5.2.5 *)
3.7.1 1 m1 - Genteng Bubung ex. AMBULU
a. Tenaga : - Pekerja 0.400 OH 100,000.00 40,000.00
- Tukang kayu 0.200 OH 150,000.00 30,000.00
- Kepala tukang 0.020 OH 185,000.00 3,700.00
- Mandor 0.002 OH 250,000.00 500.00 Rp 74,200.00
PUPR.2016/A.4.5.2.2 *)
3.7.1 1 m2 - Genteng ex. NGLAYUR
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.075 OH 150,000.00 11,250.00
- Kepala tukang 0.008 OH 185,000.00 1,480.00
- Mandor 0.008 OH 250,000.00 2,000.00 Rp 29,730.00
PUPR.2016/A.4.5.2.30 *)
3.7.1 1 m2 - Genteng BETON
a. Tenaga : - Pekerja 0.200 OH 100,000.00 20,000.00
- Tukang kayu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.010 OH 250,000.00 2,500.00 Rp 39,350.00
PUPR.2016/A.4.5.2.35 *)
3.7.1 1 m1 - Genteng Bubung BETON
a. Tenaga : - Pekerja 0.400 OH 100,000.00 40,000.00
- Tukang kayu 0.200 OH 150,000.00 30,000.00
- Kepala tukang 0.020 OH 185,000.00 3,700.00
- Mandor 0.002 OH 250,000.00 500.00 Rp 74,200.00
PUPR.2016/A.4.5.2.32
3.7.1 1 m2 - Genteng METAL (atap pelana)
a. Tenaga : - Pekerja 0.200 OH 100,000.00 20,000.00
- Tukang kayu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.001 OH 250,000.00 250.00 Rp 37,100.00
PUPR.2016/A.4.5.2.33
3.7.1 1 m2 - Genteng METAL (atap jurai)
a. Tenaga : - Pekerja 0.200 OH 100,000.00 20,000.00
- Tukang kayu 0.100 OH 150,000.00 15,000.00
- Kepala tukang 0.010 OH 185,000.00 1,850.00
- Mandor 0.001 OH 250,000.00 250.00 Rp 37,100.00
PUPR.2016/A.4.5.2.1 *)
6.6.9 1 m2 - Pasang Genteng lama
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.075 OH 150,000.00 11,250.00
- Kepala tukang 0.0075 OH 185,000.00 1,387.50
- Mandor 0.0080 OH 250,000.00 2,000.00 Rp 29,637.50
Rp 29,638.00
PUPR.2016/A.4.5.2.7
6.7.1 1 m2 - FIBREGLASS Datar
a. Tenaga : - Pekerja 0.140 OH 100,000.00 14,000.00
- Tukang kayu 0.067 OH 150,000.00 10,050.00
- Kepala tukang 0.007 OH 185,000.00 1,295.00
- Mandor 0.007 OH 250,000.00 1,750.00 Rp 27,095.00
PUPR.2016/A.4.5.2.7
6.7.2 1 m2 - FIBREGLASS Gelombang
a. Tenaga : - Pekerja 0.140 OH 100,000.00 14,000.00
- Tukang kayu 0.067 OH 150,000.00 10,050.00
- Kepala tukang 0.007 OH 185,000.00 1,295.00
- Mandor 0.007 OH 250,000.00 1,750.00 Rp 27,095.00
PUPR.2016/A.4.5.2.10
6.7.2 1 m2 - ASBES Gelombang besar
a. Tenaga : - Pekerja 0.140 OH 100,000.00 14,000.00
- Tukang kayu 0.075 OH 150,000.00 11,250.00
- Kepala tukang 0.007 OH 185,000.00 1,295.00
- Mandor 0.007 OH 250,000.00 1,750.00 Rp 28,295.00
PUPR.2016/A.4.5.2.39
6.7.2 1 m2 - SENG Gelombang
a. Tenaga : - Pekerja 0.120 OH 100,000.00 12,000.00
- Tukang kayu 0.060 OH 150,000.00 9,000.00
- Kepala tukang 0.006 OH 185,000.00 1,110.00
- Mandor 0.006 OH 250,000.00 1,500.00 Rp 23,610.00
PUPR.2016/A.4.5.2.40
6.7.2 1 m1 - SENG Bubung
a. Tenaga : - Pekerja 0.150 OH 100,000.00 15,000.00
- Tukang kayu 0.070 OH 150,000.00 10,500.00
- Kepala tukang 0.007 OH 185,000.00 1,295.00
- Mandor 0.006 OH 250,000.00 1,500.00 Rp 28,295.00
SNI 7393:2008-6.18-T
6.9.1 1 m1 - Talang seng
a. Bahan : - Seng plat 1.050 lbr 67,000.00 70,350.00
- Paku 0.015 kg 24,000.00 360.00
- Kayu hutan papan 0.002 m3 5,175,000.00 8,797.50 Rp 79,507.50
PEK. PERSIAPAN
1 m1 - Uitset / Pengukuran Rp -
1 m1 - Profil Melintang Galian Tanah Rp -
1 m1 - Bouwplank Rp -
1 m2 - Direksi keet / Los Kerja / Gudang Rp -
1 bh - Papan nama proyek, 60x90 cm Rp -
1 m1 - Pagar proyek (seng BJLS) Rp -
1 m2 - Pembersihan Rp -
1 m2 - Pemotongan perdu Rp -
1 btg - Pemotongan pohon Rp -
1 m3 - Pembongkaran beton bertulang Rp -
1 m3 - Pembongkaran dinding bata Rp -
1 m2 - Pembongkaran dinding bata Rp -
1 m2 - Pembongkaran plesteran Rp -
1 m3 - Pengangkutan MATERIAL horisontal Rp 27,900
1 m3 - Pengangkutan MATERIAL ke lantai 2 Rp 67,900
1 vol - Pekerjaan LT.2, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 2 Rp 67,900
1 vol - Pekerjaan LT.3, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 3 Rp 151,648
1 vol - Pekerjaan LT.4, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 4 Rp 153,679
1 vol - Pekerjaan LT.5, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 5 Rp 36,249
1 vol - Pekerjaan LT.6, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 6 Rp 37,340
1 vol - Pekerjaan LT.7, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 7 Rp 38,557
1 vol - Pekerjaan LT.8, TENAGA atau ALAT BANTU ANGKUT BAHAN ke lantai 8 Rp 39,462
PEK. TANAH
1 m3 - Galian TANAH BIASA, kedalaman s.d 1 meter #N/A
1 m3 - Galian TANAH BIASA, kedalaman 1 s.d 2 meter #N/A
1 m3 - Galian TANAH KERAS, kedalaman s.d 1 meter Rp 124,200
1 m3 - Galian TANAH BERBATU, kedalaman s.d 1 meter Rp 194,206
1 m3 - Galian TANAH BERBATU, kedalaman 1 s.d 2 meter Rp 215,625
1 m3 - Galian TANAH LUMPUR, kedalaman s.d 1 meter Rp 150,938
1 m3 - Galian TANAH PASIR, kedalaman s.d 1 meter Rp 94,875
1 m3 - Urugan TANAH BARU #N/A
1 m3 - Urugan PASIR #N/A
1 m3 - Urugan Tanah Pasir/TRASS Rp 146,338
1 m3 - Urugan Tanah Padat/Tanah Gunung Rp 164,335
1 m3 - Pengangkutan / pembuangan TANAH Rp 40,825
1 m3 - Urugan tanah kembali #N/A
1 m3 - Pemadatan TANAH Rp 71,875
1 m3 - Pemadatan PASIR Rp 14,375
PEK. PONDASI
1 m3 - Batu kosong dan Pasir urug #N/A
1 m3 - Pondasi batu kali, 1 PC : 3 PP Rp 1,412,229
1 m3 - Pondasi batu kali, 1 PC : 5 PP Rp 1,231,978
1 m3 - Pondasi batu kali, 1 PC : 6 PP Rp 1,180,090
1 m3 - Pondasi batu kali, 1 PC : 8 PP #N/A
1 m3 - Pondasi sumuran, diameter 100 cm #N/A
PEK. PLESTERAN
1 m2 - Plesteran, 1 PC : 3 PP Rp 93,938
1 m2 - Plesteran, 1 PC : 4 PP #N/A
1 m2 - Plesteran, 1 PC : 5 PP Rp 86,969
1 m2 - Plesteran, 1 PC : 6 PP Rp 84,922
1 m1 - Plesteran Skoning 10cm, 1 PC : 3 PP Rp 91,391
1 m2 - Plesteran Ciprat, 1 PC : 2 PP Rp 71,519
1 m2 - Plesteran Beton, 1 PC : 2 PP Rp 100,493
1 m2 - Plesteran Lantai, 1 PC : 5 PP Rp 53,280
1 m2 - Acian #N/A
1 m2 - Siar / Setrik Pasangan Bata Merah #N/A
1 m2 - Siar / Setrik Pasangan Batu Kali Rp 92,351
1 m2 - Rangka Atap Genteng Keramik, Usuk 5/7 + Reng 2/3, Kayu Meranti Rp 136,367
1 m2 - Rangka Atap Genteng Keramik, Usuk 5/7 + Reng 2/3, Kayu Lokal Rp 132,319
1 m2 - Rangka Atap Genteng Beton, Usuk 5/7 + Reng 3/5, Kayu Kruing Rp 252,469
1 m2 - Rangka Atap Genteng Beton, Usuk 5/7 + Reng 3/5, Kayu Meranti Rp 157,895
1 m2 - Rangka Atap Genteng Beton, Usuk 5/7 + Reng 3/5, Kayu Lokal Rp 152,950
1 m2 - Usuk + Reng, Baja Ringan Rp 333,593
1 m2 - Usuk, Kayu Kruing Rp 158,470
1 m2 - Usuk, Kayu Meranti Rp 96,888
1 m2 - Usuk, Kayu Lokal Rp 93,668
1 m2 - Reng 2/3, Kayu Kruing Rp 55,315
1 m2 - Reng 2/3, Kayu Meranti Rp 39,480
1 m2 - Reng 2/3, Kayu Lokal Rp 38,652
1 m2 - Reng 3/5, Kayu Kruing Rp 91,023
1 m2 - Reng 3/5, Kayu Meranti Rp 59,352
1 m2 - Reng 3/5, Kayu Lokal Rp 57,696
1 m2 - Pasang Usuk lama Rp 19,608
1 m1 - Papan Reuter Rp 41,469
1 m1 - Papan Kompres Rp 62,112
1 m1 - Lisplank 3/30, Kayu Kruing Rp 137,828
1 m1 - Lisplank 3/30, Kayu Meranti Rp 106,203
1 m1 - Lisplank 3/30, Kayu Lokal Rp 99,878
1 m1 - Lisplank 3/20, Kayu Kruing Rp 137,667
1 m1 - Lisplank 3/20, Kayu Meranti Rp 106,617
1 m1 - Lisplank 3/20, Kayu Lokal Rp 100,407
1 m1 - Kalsiplank 30 Rp 90,219
1 m1 - Kalsiplank 20 Rp 80,876
1 m2 - Atap ondulin tile Rp 182,793
1 m2 - Atap Metalroof Rp 135,183
1 m2 - Atap Onduvilla Rp 339,883
1 m2 - Atap PVC Genteng Rp 286,983
1 m2 - Atap UPVC Double Layer Rp -
1 m2 - Atap UPVC Single Layer Rp -
1 m2 - Genteng Keramik ex. Ambulu Rp 126,190
1 m1 - Genteng Keramik bubung ex. Ambulu Rp -
1 m2 - Genteng Keramik ex. Nglayur Rp 111,815
1 m1 - Genteng Keramik bubung ex. Nglayur Rp 160,057
1 m2 - Genteng beton Rp 133,803
1 m1 - Genteng bubung beton Rp 173,857
1 m2 - Genteng keramik glazuur Rp 291,790
1 m1 - Genteng bubung keramik glazuur Rp 219,857
1 m2 - Pasang Genteng lama Rp 34,190
1 m2 - Fiberglass datar Rp 83,599
1 m2 - Fiberglass gelombang Rp 156,049
1 m2 - Polycarbonate, rangka hollow Rp 961,475
1 m2 - Asbes gelombang kecil Rp 75,929
1 m1 - Nok stel gelombang kecil Rp 77,688
JENIS PEKERJAAN HSP
PEK. LISTRIK
1 unit - Pasang Daya 1300 VA Rp -
1 unit - Pasang Daya 900 VA Rp -
1 VA - Pasang Daya Rp -
1 unit - Pasang baru listrik (Jaminan + Instalasi 3 titik) Rp -
1 bh - Sekring kas Rp 132,000
1 unit - MCB lengkap #N/A
1 unit - Arde Rp 103,000
1 ttk - Instalasi listrik #N/A
1 bh - Saklar tunggal #N/A
1 bh - Saklar ganda #N/A
1 bh - Stop kontak #N/A
1 bh - Fitting lampu Rp 17,000
1 bh - Kap downlight kecil Rp 63,000
1 bh - Kap downlight besar Rp 86,000
1 bh - Lampu HE 18 W Rp 57,000
1 bh - Lampu TL 1x20 W + reflektor Rp 145,000
1 bh - Lampu TL 1x40 W + reflektor Rp 253,000
1 m1 - Kabel NYY Rp 12,000
1 m1 - Kabel NYM Rp 10,500
1 m1 - Kabel NYA Rp 7,100
PEK. PENGECATAN
1 m2 - Pengecatan kayu lama Rp 46,653
1 m2 - Pengecatan kayu baru Rp 53,446
1 m2 - Pengecatan dinding atau plafond lama Rp 24,572
1 m2 - Pengecatan dinding atau plafond baru Rp 32,540
1 m2 - Cat meni Rp 47,639
1 m2 - Pengecatan besi atau baja Rp 39,123
1 m2 - Pengecatan weathershield Rp 48,836
1 m2 - Pengecatan waterproof Rp 39,176
1 m2 - Pengecatan tekstur Rp 39,176
1 m2 - waterbased wood finishing Rp 74,437
DAFTAR KUANTITAS DAN HARGA
BILL OF QUANTITY ( BQ )
B PEKERJAAN TANAH
1 1 m3 Galian Tanah biasa sedalam 1 meter 86.93 m3 93,438.00 8,122,565.34
2 1 m3 Galian Tanah biasa sedalam 2 meter 24.00 m3 116,438.00 2,794,512.00
3 1 m3 Urugan kembali 110.93 m3 71,875.00 7,973,093.75
4 1 m3 Urugan tanah baru 106.20 m3 146,395.00 15,547,149.00
5 1 m1 Pekerjaan Galian Strouss Ø30m 32.00 m1 112,125.60 3,588,019.20
C PEKERJAAN PONDASI
1 1 m3 Pekerjaan Pondasi Strouss Ø30m 2.27 m3 112,125.60 254,525.11
2 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps (lokal) 52.16 m3 1,109,043.00 57,847,682.88
3 1 m3 Pasang Anstampeng Batu Kali (lokal) 13.04 m3 1,109,043.00 14,461,920.72
4 1 m3 Urugan Sirtu Padat (lokal) 4.35 m3 215,000.00 935,250.00
5 1 m3 Pondasi Tapak (100x100x20) Mutu Beton k-275 3.20 m3 1,447,333.00 4,631,465.60
6 1 m2 Pondasi Rollag 8.40 m2 640,165.00 5,377,386.00
D PEKERJAAN PASANGAN
1 1 m2 Pas Dinding Bata Batako 407.10 m2 186,283.00 75,835,809.30
2 1 m2 Pasang Paving K 250 abu-abu 187.89 m2 253,575.00 47,644,206.75
3 1 m2 Pasang Dinding Partisi 8.05 m2 145,000.00 1,167,250.00
E PEKERJAAN BETON
1 1 m3 Membuat sloof beton bertulang (15 x 20) cm (besi Ø 12 dan besi Ø10) 3.09 m3 8,970,912.00 27,720,118.08
2 1 m3 Membuat kolom struktur beton bertulang (30 x 30) cm (besi Ø 16 dan besi Ø10) 10.98 m3 7,486,756.00 82,204,580.88
3 1 m3 Membuat kolom struktur beton bertulang (15 x 15) cm (besi Ø 12 dan besi Ø10) 2.68 m3 7,486,756.00 20,064,506.08
4 1 m3 Membuat ring balok beton bertulang (15 x 20) cm (besi Ø 12 dan besi Ø10) 3.90 m3 7,486,756.00 29,198,348.40
5 1 m3 Membuat balok struktur beton bertulang (20 x 30) cm (besi Ø 16 dan besi Ø10) 5.07 m3 7,486,756.00 37,957,852.92
6 1 m3 Membuat balok latei (besi Ø 10 dan besi Ø8) 1.24 m3 7,486,756.00 9,283,577.44
7 1 m3 Membuat Lantai Beton Mutu K-250 (besi Ø10) 15.98 m3 1,275,075.00 20,375,698.50
8 1 m3 Membuat Plat Leuvel tebal 10cm(besi Ø 10 dan besi Ø8) 0.65 m3 1,275,075.00 828,798.75
F PEKERJAAN PLESTERAN DAN ACIAN
1 1 m2 Plesteran 1 Pc : 4 Ps, tebal 20 mm 982.98 m2 89,683.00 88,156,595.34
2 1 m2 Acian 982.98 m2 54,596.00 53,666,776.08
3 1 m1 Benangan 215.95 m1 500.00 107,975.00
G PEKERJAAN PLAFOND
1 1 m2 Pasang Rangka Plafond Hollow Galvanis modul 60x120 333.60 m2 143,319.00 47,811,218.40
2 1 m2 Pasang langit-langit gypsum board, ( 120 X 240 X 9 ) mm 333.60 m2 57,098.00 19,047,892.80
3 1 m1 Pasang List Plafond Gypsum 222.33 m1 57,098.00 12,694,598.34
H PEKERJAAN ATAP
1 1 m2 pasang rangka atap hollow galvanis 268.62 m2 143,319.00 38,498,349.78
2 1 m2 pasang atap genteng metal multiroof 268.62 m2 78,833.00 21,176,120.46
3 1 m1 pasang bubung atap genteng metal multiroof 8.70 m1 158,528.00 1,379,193.60
4 1 m1 pasang lisplank 2/20 cm 88.50 m1 99,878.00 8,839,203.00
5 1 m2 Pasang Kanopi UPVC Ecoroof Balkon 37.73 m2 176,640.00 6,664,627.20
6 1 m2 Pasang Kanopi UPVC Ecoroof Selasar 22.50 m2 176,640.00 3,974,400.00
I PEKERJAAN LANTAI
1 1 m2 Pasang Lantai Keramik L1 60 x 60 (Granit) warna putih setara roman,platinum 95.49 m2 455,682.00 43,513,074.18
2 1 m1 Plin Keramik L1 (Granit) 10x60 hitam polos 100.72 m1 151,737.00 15,283,709.32
3 1 m2 Pasang Lantai Keramik L2 60 x 60 (Granit) warna putih setara roman,platinum 69.05 m2 455,682.00 31,464,842.10
4 1 m1 Plin Keramik L2 (Granit) 10x60 hitam polos 121.60 m1 151,737.00 18,451,219.20
5 1 m2 Pasang Lantai Keramik Asrama 60 x 60 (Granit) warna putih setara roman,platinum 45.00 m2 455,682.00 20,505,690.00
6 1 m1 Plin Keramik Asrama (Granit) 10x60 hitam polos 54.00 m1 151,737.00 8,193,798.00
7 1 m2 Pas. Lantai Keramik Teras Matt 40 x 40 Asrama, L1 & Balkon 82.15 m2 183,806.00 15,099,662.90
8 1 m1 Plin Keramik Teras Asrama, L1 dan Balkon (Granit) 10x40 hitam polos 26.80 m1 151,737.00 4,066,551.60
9 1 m2 Pasang Lantai Keramik Km/Wc Matt 25 x 25 warna/motif setara roman,platinum 23.56 m2 288,828.00 6,804,787.68
10 1 m2 Pasang Keramik Dinding Km/Wc 25 x 40 warna/motif setara roman,platinum 44.40 m2 345,273.00 15,330,121.20
L PEKERJAAN LISTRIK
1 1 bh MCB Box setara schneider 4.00 buah 825,000.00 3,300,000.00
2 1 unit Panel Pompa setara submersible 1.00 unit 9,847,047.50 9,847,047.50
3 1 unit Panel Utama setara submersible 1.00 unit 3,200,000.00 3,200,000.00
4 1 m1 Kabel Feeder 4 x16 setara heliax 20.00 m1 235,000.00 4,700,000.00
5 1 m1 Kabel Leeder 3 x 4 setara heliax 20.00 m1 125,000.00 2,500,000.00
6 1 Titik Instalasi Lampu dan stop kontak 87.00 titik 230,000.00 20,010,000.00
7 1 bh Pek. Stop Kontak setara panasonic 36.00 buah 25,500.00 918,000.00
8 1 bh Skaklar tunggal setara panasonic 14.00 buah 28,000.00 392,000.00
9 1 bh Skaklar Ganda setara panasonic 3.00 buah 34,000.00 102,000.00
10 1 bh Pek. Lampu DL setara philips meson lengkap 34.00 buah 235,000.00 7,990,000.00
11 1 bh Pek. Lampu Pijar setara philips 3.00 buah 62,500.00 187,500.00
12 Penambahan Daya Listrik 1.00 ls 9,800,000.00 9,800,000.00
13 1 bh Lampu sorot Plakat 12 wat 3.00 buah 425,000.00 1,275,000.00
M PEKERJAAN SANITASI
1 1 m1 pipa PVC diameter 3" (AW) Air Supply 30.00 m1 118,764.00 3,562,920.00
2 1 m1 pipa PVC diameter 4" (AW) Air Supply 30.00 m1 157,404.00 4,722,120.00
3 1 m1 pipa PVC diameter 3/4" (AW) Air Supply 40.00 m1 41,000.00 1,640,000.00
4 1 bh shower head 1 set setara classic 5.00 buah 365,000.00 1,825,000.00
5 1 bh Avur Stainless 5.00 buah 122,015.00 610,075.00
6 1 bh Kran Air Stainless 5.00 buah 145,763.00 728,815.00
7 1 unit Pasang septictank ukuran 3 x 1.5 x 1.75. 1.00 unit 5,259,737.00 5,259,737.00
8 1 unit - Peresapan (Ø=1 m ; d= 2 m) 1.00 unit 3,483,212.00 3,483,212.00
9 1 bh Closed Duduk Porselin setara toto 3.00 buah 2,742,963.00 8,228,889.00
10 1 bh Closed Jongkok setara toto 2.00 buah 800,573.00 1,601,146.00
11 1 bh Wastafel setara toto 1.00 buah 1,106,128.00 1,106,128.00
12 1 unit Pekerjaan Zinc Dapur Bolzano 2 Lubang 1.00 unit 1,200,000.00 1,200,000.00
13 Filter penyaring air bersih 1.00 set 350,000.00 350,000.00
14 1 bh Pompa air listrik 1.00 bh 1,307,838.00 1,307,838.00
JUMLAH 1,258,030,494.59
PPN 11% 138,383,354.40
TOTAL + PPN 1,396,413,848.99
DIBULATKAN 1,396,413,000.00
H. Syofyandi Syafei
Direktur
REKAPITULASI BQ
NO URAIAN JUMLAH
TOTAL Rp 1,257,201,695.84
DIBULATKAN Rp 1,395,493,000.00
Terbilang :
H. Syofyandi Syafei
Direktur
A. BIAYA UMUM K3
1 ALAT PELINDUNG DIRI
1.1 Topi Pelindung (Safety Helmet) Bh 10.00 50,000.00 500,000.00
1.2 Pelindung Pernafasan Dan Mulut (Masker) Bh 10.00 5,000.00 50,000.00
1.3 Sepatu Boots Karet Psg 10.00 125,000.00 1,250,000.00
1.4 Rompi Keselamatan Bh 10.00 65,000.00 650,000.00
4 RAMBU-RAMBU
4.1 Rambu Informasi (Larangan, Petunjuk, Peringatan) Bh 3.00 250,000.00 750,000.00
4.2 Kerucut Lalu Lintas (Traffic Cone) Bh 2.00 85,000.00 170,000.00
5 PERSONIL K3
5.1 Ahli K3 OB 1.00 1,500,000.00 1,500,000.00
5.2 Petugas K3 OB 1.00 1,250,000.00 1,250,000.00
8,770,000.00
Penawar : PT. Belka Ceria Persada
Surat Penawar :
Nama Tender : Renovasi Pos PGA Dukono, Maluku Utara
Satuan Kerja : Pusat Vulkanologi Dan Mitigasi Bencana Geologi
Instansi : Kementrian ESDM
Lokasi Pekerjaan
Waktu Pelaksanaan
:
:
Pos Pengamatan Gunung Api Dukono - Halmahera ( Kab. )
150 ( seratus lima puluh ) hari kalender
KURVA S PENGIRIMAN MATERIAL KE LOKASI
Tahun Anggaran : APBN TA.2023 PEKERJAAN DAN PEKERJAAN FISIK LAPANGAN
BOBOT BULAN BULAN KE - 1 BULAN KE - 2 BULAN KE - 3 BULAN KE - 4 BULAN KE - 5
NO URAIAN PEKERJAAN VOLUME SAT KET.
KONTRAK % MINGGU 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A PEKERJAAN PERSIAPAN
100.00%
1 1 m1 Pengukuran dan Pemasangan Bouwplank 6.60 m1 0.0002 4.0 0.00006 0.00006 0.00006 0.00006
100.00%
2 1 m2 Membersihkan lapangan 177.00 m2 0.0036 4.0 0.00091 0.00091 0.00091 0.00091
3 1 m2 Bongkaran Dinding tembok bata merah 136.15 m2 0.0140 4.0 0.00350 0.00350 0.00350 0.00350
4 1 m2 Pembuatan Direksi Keet 10.00 m2 0.0122 4.0 0.00305 0.00305 0.00305 0.00305
5 1 m2 Pembuatan gudang alat-alat kantor 9.00 m2 0.0110 4.0 0.00274 0.00274 0.00274 0.00274
6 1 unit Papan Nama ukuran 80x120 1.00 unit 0.0004 4.0 0.00009 0.00009 0.00009 0.00009
7 1 m2 Bongkaran Atap+Rangka+penutup Atap 153.82 m2 0.0061 4.0 0.00153 0.00153 0.00153 0.00153
8 1 m3 Bongkaran Kolom dan Balok Beton existing 2.48 m3 0.0034 4.0 0.00085 0.00085 0.00085 0.00085 95.04%
9 1 m2 Bongkaran rangka dan penutup gypsum 168.30 m2 0.0033 4.0 0.00084 0.00084 0.00084 0.00084
10 1 m2 Bongkaran Keramik 168.30 m2 0.0029 4.0 0.00072 0.00072 0.00072 0.00072
11 1 m2 Bongkar Kusen Eksisting 35.55 m2 0.0004 4.0 0.00011 0.00011 0.00011 0.00011
12 Biaya Umum Keselamatan dan Kesehatan Kerja (K3) 1.00 ls 0.0070 4.0 0.00174 0.00174 0.00174 0.00174
E PEKERJAAN BETON
1 1 m3 Membuat sloof beton bertulang (15 x 20) cm (besi Ø 12 dan besi Ø10) 3.09 m3 0.0220 4.0 0.00551 0.00551 0.00551 0.00551
2 1 m3 Membuat kolom struktur beton bertulang (30 x 30) cm (besi Ø 16 dan besi Ø10) 10.98 m3 0.0653 4.0 0.01634 0.01634 0.01634 0.01634
3 1 m3 Membuat kolom struktur beton bertulang (15 x 15) cm (besi Ø 12 dan besi Ø10) 2.68 m3 0.0159 4.0 0.00399 0.00399 0.00399 0.00399
4 1 m3 Membuat ring balok beton bertulang (15 x 20) cm (besi Ø 12 dan besi Ø10) 3.90 m3 0.0232 4.0 0.00580 0.00580 0.00580 0.00580
5 1 m3 Membuat balok struktur beton bertulang (20 x 30) cm (besi Ø 16 dan besi Ø10) 5.07 m3 0.0302 4.0 0.00754 0.00754 0.00754 0.00754 70.43%
6 1 m3 Membuat balok latei (besi Ø 10 dan besi Ø8) 1.24 m3 0.0074 4.0 0.00184 0.00184 0.00184 0.00184
7 1 m3 Membuat Lantai Beton Mutu K-250 (besi Ø10) 15.98 m3 0.0162 4.0 0.00405 0.00405 0.00405 0.00405
8 1 m3 Membuat Plat Leuvel tebal 10cm(besi Ø 10 dan besi Ø8) 0.65 m3 0.0007 4.0 0.00016 0.00016 0.00016 0.00016
G PEKERJAAN PLAFOND
61.76%
1 1 m2 Pasang Rangka Plafond Hollow Galvanis modul 60x120 333.60 m2 0.0380 4.0 0.00950 0.00950 0.00950 0.00950
2 1 m2 Pasang langit-langit gypsum board, ( 120 X 240 X 9 ) mm 333.60 m2 0.0151 4.0 0.00379 0.00379 0.00379 0.00379 60.00%
3 1 m1 Pasang List Plafond Gypsum 222.33 m1 0.0101 4.0 0.00252 0.00252 0.00252 0.00252
H PEKERJAAN ATAP
1 1 m2 pasang rangka atap hollow galvanis 268.62 m2 0.0306 4.0 0.00765 0.00765 0.00765 0.00765
2 1 m2 pasang atap genteng metal multiroof 268.62 m2 0.0168 4.0 0.00421 0.00421 0.00421 0.00421
3 1 m1 pasang bubung atap genteng metal multiroof 8.70 m1 0.0011 4.0 0.00027 0.00027 0.00027 0.00027
4 1 m1 pasang lisplank 2/20 cm 88.50 m1 0.0070 4.0 0.00176 0.00176 0.00176 0.00176
5 1 m2 Pasang Kanopi UPVC Ecoroof Balkon 37.73 m2 0.0053 4.0 0.00132 0.00132 0.00132 0.00132
6 1 m2 Pasang Kanopi UPVC Ecoroof Selasar 22.50 m2 0.0032 4.0 0.00079 0.00079 0.00079 0.00079
52.94%
44.12%
40.00%
37.12%
30.12%
23.11%
20.00%
16.11%
13.70%
11.28%
8.87%
6.45%
4.84%
3.23%
1.61%
0.00%
61.76%
60.00%
52.94%
I PEKERJAAN LANTAI
1 1 m2 Pasang Lantai Keramik L1 60 x 60 (Granit) warna putih setara roman,platinum 95.49 m2 0.0346 4.0 0.00865 0.00865 0.00865 0.00865
2 1 m1 Plin Keramik L1 (Granit) 10x60 hitam polos 100.72 m1 0.0121 4.0 0.00304 0.00304 0.00304 0.00304
3 1 m2 Pasang Lantai Keramik L2 60 x 60 (Granit) warna putih setara roman,platinum 69.05 m2 0.0250 4.0 0.00625 0.00625 0.00625 0.00625
4 1 m1 Plin Keramik L2 (Granit) 10x60 hitam polos 121.60 m1 0.0147 4.0 0.00367 0.00367 0.00367 0.00367
5 1 m2 Pasang Lantai Keramik Asrama 60 x 60 (Granit) warna putih setara roman,platinum 45.00 m2 0.0163 4.0 0.00407 0.00407 0.00407 0.00407
6 1 m1 Plin Keramik Asrama (Granit) 10x60 hitam polos 54.00 m1 0.0065 4.0 0.00163 0.00163 0.00163 0.00163
7 1 m2 Pas. Lantai Keramik Teras Matt 40 x 40 Asrama, L1 & Balkon 82.15 m2 0.0120 4.0 0.00300 0.00300 0.00300 0.00300
8 1 m1 Plin Keramik Teras Asrama, L1 dan Balkon (Granit) 10x40 hitam polos 26.80 m1 0.0032 4.0 0.00081 0.00081 0.00081 0.00081
9 1 m2 Pasang Lantai Keramik Km/Wc Matt 25 x 25 warna/motif setara roman,platinum 23.56 m2 0.0054 4.0 0.00135 0.00135 0.00135 0.00135
10 1 m2 Pasang Keramik Dinding Km/Wc 25 x 40 warna/motif setara roman,platinum 44.40 m2 0.0122 4.0 44.12% 0.00305 0.00305 0.00305 0.00305
K PEKERJAAN PENGECATAN
1 1 m2 Pengecatan Tembok Baru setara Catylac 982.98 m2 0.0254 4.0 0.00636 0.00636 0.00636 0.00636
2 1 m2 Pengecatan Tembok Lama setara Catylac 276.50 m2 0.0054 4.0 0.00135 0.00135 0.00135 0.00135
3 1 m2 pengecatan plafond baru setara Ceiling 403.75 m2 0.0104 4.0 0.00261 0.00261 0.00261 0.00261
4 1 m2 pengecatan lisplank setara Propan 88.50 m2 0.0023 4.0 30.12% 0.00057 0.00057 0.00057 0.00057
L PEKERJAAN LISTRIK
1 1 bh MCB Box setara schneider 4.00 buah 0.0026 2.0 0.00131 0.00131
2 1 unit Panel Pompa setara submersible 1.00 unit 0.0078 2.0 0.00391 0.00391
3 1 unit Panel Utama setara submersible 1.00 unit 0.0025 2.0 0.00127 0.00127
4 1 m1 Kabel Feeder 4 x16 setara heliax 20.00 m1 0.0037 2.0 0.00187 0.00187
5 1 m1 Kabel Leeder 3 x 4 setara heliax 20.00 m1 0.0020 2.0 0.00099 0.00099
6 1 Titik Instalasi Lampu dan stop kontak 87.00 titik 0.0159 2.0 0.00795 0.00795
7 1 bh Pek. Stop Kontak setara panasonic 36.00 buah 0.0007 2.0 23.11% 0.00036 0.00036
8 1 bh Skaklar tunggal setara panasonic 14.00 buah 0.0003 2.0 0.00016 0.00016
9 1 bh Skaklar Ganda setara panasonic 3.00 buah 0.0001 2.0 0.00004 0.00004
10 1 bh Pek. Lampu DL setara philips meson lengkap 34.00 buah 0.0064 2.0 0.00318 0.00318 20.00%
11 1 bh Pek. Lampu Pijar setara philips 3.00 buah 0.0001 2.0 0.00007 0.00007
12 Penambahan Daya Listrik 1.00 ls 0.0078 2.0 0.00389 0.00389
13 1 bh Lampu sorot Plakat 12 wat 3.00 buah 0.0010 2.0 0.00051 0.00051
M PEKERJAAN SANITASI
1 1 m1 pipa PVC diameter 3" (AW) Air Supply 30.00 m1 0.0028 2.0 16.11% 0.00142 0.00142
2 1 m1 pipa PVC diameter 4" (AW) Air Supply 30.00 m1 0.0038 2.0 0.00188 0.00188
3 1 m1 pipa PVC diameter 3/4" (AW) Air Supply 40.00 m1 0.0013 2.0 0.00065 0.00065
4 1 bh shower head 1 set setara classic 5.00 buah 0.0015 2.0 13.70% 0.00073 0.00073
5 1 bh Avur Stainless 5.00 buah 0.0005 2.0 0.00024 0.00024
6 1 bh Kran Air Stainless 5.00 buah 0.0006 2.0 0.00029 0.00029
7 1 unit Pasang septictank ukuran 3 x 1.5 x 1.75. 1.00 unit 0.0042 2.0 11.28% 0.00209 0.00209
8 1 unit - Peresapan (Ø=1 m ; d= 2 m) 1.00 unit 0.0028 2.0 0.00138 0.00138
9 1 bh Closed Duduk Porselin setara toto 3.00 buah 0.0065 2.0 0.00327 0.00327
10 1 bh Closed Jongkok setara toto 2.00 buah 0.0013 2.0 8.87% 0.00064 0.00064
11 1 bh Wastafel setara toto 1.00 buah 0.0009 2.0 0.00044 0.00044
12 1 unit Pekerjaan Zinc Dapur Bolzano 2 Lubang 1.00 unit 0.0010 2.0 0.00048 0.00048
13 Filter penyaring air bersih 1.00 set 0.0003 2.0 6.45% 0.00014 0.00014
14 1 bh Pompa air listrik 1.00 bh 0.0010 2.0 0.00052 0.00052
4.84%
N PEKERJAAN LAIN - LAIN
1 1 m2 pasang pagar besi hollow 4x4 railling Tangga 4.24 m2 0.0009 2.0 3.23% 0.00043 0.00043
2 1 m2 pasang pembatas balkon pagar besi hollow 4x4 21.12 m2 0.0043 2.0 0.00215 0.00215
3 1 m2 Stainless kaca temperd 10mm balkon depan 4.28 m2 0.0096 2.0 1.61% 0.00480 0.00480
4 1 set signage nama gedung 1.00 set 0.0052 2.0 0.00258 0.00258 0.00%
% PROGRESS SETIAP MINGGU 0.0161 0.0161 0.0161 0.0161 0.0242 0.0242 0.0242 0.0242 0.0700 0.0700 0.0700 0.0700 0.0882 0.0882 0.0867 0.0867 0.0549 0.0549 0.0496 0.0496
KETERANGAN : % KUMULATIF PROGRESS SETIAP MINGGU 1.61% 3.23% 4.84% 6.45% 8.87% 11.28% 13.70% 16.11% 23.11% 30.12% 37.12% 44.12% 52.94% 61.76% 70.43% 79.10% 84.58% 90.07% 95.04% 100.00%
: FACTORY ORDER
H. Syofyandi Syafei
Direktur
Penawar : PT. Belka Ceria Persada
Surat Penawar : 0
Nama Tender : Renovasi Pos PGA Dukono, Maluku Utara
Satuan Kerja : Pusat Vulkanologi Dan Mitigasi Bencana Geologi
Instansi : Kementrian ESDM
Lokasi Pekerjaan : Pos Pengamatan Gunung Api Dukono - Halmahera ( Kab. )
Waktu Pelaksanaan : 150 ( seratus lima puluh ) hari kalender
Tahun Anggaran : APBN TA.2023 SPESIFIKASI MATERIAL
NO. SPESIFIKASI MATERIAL YANG DITAWARKAN
Kusen alumunium setara alexindo Type P1, 4 " Pintu & Jendela Kusen alumunium setara alexindo PJ1 Bouven Kusen alumunium setara alexindo BV1
Jendela Kusen alumunium setara alexindo J1 Pintu & Jendela Kusen alumunium setara alexindo PJ2 Pintu Kusen alumunium setara alexindo Type P2 & P3
Lantai Keramik L1 60 x 60 (Granit) warna Hitam Lantai Keramik L1 60 x 60 (Granit) warna putih Lantai Keramik Teras Matt 40 x 40
Plin Keramik, L1 dan Balkon (Granit) 10x40 hitam polos MCB Box setara schneider Kabel Feeder 4 x16 setara heliax
Stop Kontak setara panasonic Saklar tunggal setara panasonic Saklar Ganda setara panasonic
Lampu DL setara philips meson lengkap Lampu Pijar setara philips Lampu sorot Plakat 12 wat
shower head 1 set setara classic Kran Air Stainless Closed Duduk Porselin setara toto
Closed Jongkok setara toto Wastafel setara toto Pompa air listrik
Stainless kaca Tempered 10 mm Balkon Kabel NYM 3 x 2,5 mm Kabel NYM 2 x 2,5 mm
Cat Tembok Catylac Interior & Exterior Cat Kayu Wood Stain
REALCOST / REAL MATERIAL
A PEKERJAAN PERSIAPAN
1 1 m1 Pengukuran dan Pemasangan Bouwplank 6.60 m1 19,246.00 127,023.60
2 1 m2 Membersihkan lapangan 177.00 m2 - -
3 1 m2 Bongkaran Dinding tembok bata merah 136.15 m2 - -
4 1 m2 Pembuatan Direksi Keet 10.00 m2 889,920.00 8,899,200.00
5 1 m2 Pembuatan gudang alat-alat kantor 9.00 m2 889,920.00 8,009,280.00
6 1 unit Papan Nama ukuran 80x120 1.00 unit 206,686.00 206,686.00
7 1 m2 Bongkaran Atap+Rangka+penutup Atap 153.82 m2 - -
8 1 m3 Bongkaran Kolom dan Balok Beton existing 0.71 m3 - -
9 1 m2 Bongkaran rangka dan penutup gypsum 111.10 m2 - -
10 1 m2 Bongkaran Keramik 111.10 m2 - -
11 1 m2 Bongkar Kusen Eksisting 35.55 m2 - -
12 Biaya Umum Keselamatan dan Kesehatan Kerja (K3) 1.00 ls 4,823,500.00 4,823,500.00
B PEKERJAAN TANAH
1 1 m3 Galian Tanah biasa sedalam 1 meter 86.93 m3 - -
2 1 m3 Galian Tanah biasa sedalam 2 meter 24.00 m3 - -
3 1 m3 Urugan kembali 110.93 m3 - -
4 1 m3 Urugan tanah baru 106.20 m3 142,200.00 15,101,640.00
5 1 m1 Pekerjaan Galian Strouss Ø30m 32.00 m1 - -
C PEKERJAAN PONDASI
1 1 m3 Pekerjaan Pondasi Strouss Ø30m 2.27 m3 - -
2 1 m3 Pasang Pondasi Batu Kali, 1 Pc : 8 Ps (lokal) 52.16 m3 510,705.00 26,638,372.80
3 1 m3 Pasang Anstampeng Batu Kali (lokal) 13.04 m3 408,564.00 5,327,674.56
4 1 m3 Urugan Sirtu Padat (lokal) 4.35 m3 142,200.00 618,570.00
5 1 m3 Pondasi Tapak (100x100x20) Mutu Beton k-275 3.20 m3 786,009.60 2,515,230.72
6 1 m2 Pondasi Rollag 8.40 m2 364,046.40 3,057,989.76
D PEKERJAAN PASANGAN
1 1 m2 Pas Dinding Bata Batako 407.10 m2 94,062.50 38,292,843.75
2 1 m2 Pasang Paving K 250 abu-abu 187.89 m2 189,000.00 35,511,210.00
3 1 m2 Pasang Dinding Partisi 8.05 m2 166,500.00 1,340,325.00
E PEKERJAAN BETON
1 1 m3 Membuat sloof beton bertulang (15 x 20) cm (besi Ø 12 dan besi Ø10) 3.09 m3 4,352,664.80 13,449,734.23
2 1 m3 Membuat kolom struktur beton bertulang (30 x 30) cm (besi Ø 16 dan besi Ø10) 10.98 m3 3,636,984.80 39,934,093.10
3 1 m3 Membuat kolom struktur beton bertulang (15 x 15) cm (besi Ø 12 dan besi Ø10) 2.68 m3 3,636,984.80 9,747,119.26
4 1 m3 Membuat ring balok beton bertulang (15 x 20) cm (besi Ø 12 dan besi Ø10) 3.90 m3 3,636,984.80 14,184,240.72
5 1 m3 Membuat balok struktur beton bertulang (20 x 30) cm (besi Ø 16 dan besi Ø10) 5.07 m3 3,636,984.80 18,439,512.94
6 1 m3 Membuat balok latei (besi Ø 10 dan besi Ø8) 1.24 m3 3,636,984.80 4,509,861.15
7 1 m3 Membuat Lantai Beton Mutu K-250 (besi Ø10) 15.98 m3 665,667.85 10,637,372.24
8 1 m3 Membuat Plat Leuvel tebal 10cm(besi Ø 10 dan besi Ø8) 0.65 m3 665,667.85 432,684.10
G PEKERJAAN PLAFOND
1 1 m2 Pasang Rangka Plafond Hollow Galvanis modul 60x120 333.60 m2 81,937.50 27,334,350.00
2 1 m2 Pasang langit-langit gypsum board, ( 120 X 240 X 9 ) mm 333.60 m2 68,250.00 22,768,200.00
3 1 m1 Pasang List Plafond Gypsum 222.33 m1 11,476.50 2,551,570.25
H PEKERJAAN ATAP
1 1 m2 pasang rangka atap hollow galvanis 268.62 m2 81,937.50 22,010,051.25
2 1 m2 pasang atap genteng metal multiroof 268.62 m2 46,521.00 12,496,471.02
3 1 m1 pasang bubung atap genteng metal multiroof 8.70 m1 54,445.50 473,675.85
4 1 m1 pasang lisplank 2/20 cm 88.50 m1 20,950.00 1,854,075.00
5 1 m2 Pasang Kanopi UPVC Ecoroof Balkon 37.73 m2 129,903.00 4,901,240.19
6 1 m2 Pasang Kanopi UPVC Ecoroof Selasar 22.50 m2 129,903.00 2,922,817.50
I PEKERJAAN LANTAI
1 1 m2 Pasang Lantai Keramik L1 60 x 60 (Granit) warna putih setara roman,platinum 95.49 m2 173,870.00 16,602,846.30
2 1 m1 Plin Keramik L1 (Granit) 10x60 hitam polos 100.72 m1 27,480.60 2,767,983.43
3 1 m2 Pasang Lantai Keramik L2 60 x 60 (Granit) warna putih setara roman,platinum 69.05 m2 139,096.00 9,604,578.80
4 1 m1 Plin Keramik L2 (Granit) 10x60 hitam polos 121.60 m1 27,480.60 3,341,640.96
5 1 m2 Pasang Lantai Keramik Asrama 60 x 60 (Granit) warna putih setara roman,platinum 45.00 m2 139,096.00 6,259,320.00
6 1 m1 Plin Keramik Asrama (Granit) 10x60 hitam polos 54.00 m1 27,480.60 1,483,952.40
7 1 m2 Pas. Lantai Keramik Teras Matt 40 x 40 Asrama, L1 & Balkon 82.15 m2 94,627.10 7,773,616.27
8 1 m1 Plin Keramik Teras Asrama, L1 dan Balkon (Granit) 10x40 hitam polos 26.80 m1 27,480.60 736,480.08
9 1 m2 Pasang Lantai Keramik Km/Wc Matt 25 x 25 warna/motif setara roman,platinum 23.56 m2 85,747.50 2,020,211.10
10 1 m2 Pasang Keramik Dinding Km/Wc 25 x 40 warna/motif setara roman,platinum 44.40 m2 85,747.50 3,807,189.00
K PEKERJAAN PENGECATAN
1 1 m2 Pengecatan Tembok Baru setara Catylac 982.98 m2 17,169.50 16,877,275.11
2 1 m2 Pengecatan Tembok Lama setara Catylac 276.50 m2 17,169.50 4,747,366.75
3 1 m2 pengecatan plafond baru setara Ceiling 403.75 m2 19,409.00 7,836,383.75
4 1 m2 pengecatan lisplank setara Propan 88.50 m2 17,169.50 1,519,500.75
L PEKERJAAN LISTRIK
1 1 bh MCB Box setara schneider 4.00 buah 412,500.00 1,650,000.00
2 1 unit Panel Pompa setara submersible 1.00 unit 3,828,667.50 3,828,667.50
3 1 unit Panel Utama setara submersible 1.00 unit 3,360,000.00 3,360,000.00
4 1 m1 Kabel Feeder 4 x16 setara heliax 20.00 m1 223,250.00 4,465,000.00
5 1 m1 Kabel Leeder 3 x 4 setara heliax 20.00 m1 100,000.00 2,000,000.00
6 1 Titik Instalasi Lampu dan stop kontak 87.00 titik 172,500.00 15,007,500.00
7 1 bh Pek. Stop Kontak setara panasonic 36.00 buah 22,950.00 826,200.00
8 1 bh Skaklar tunggal setara panasonic 14.00 buah 22,950.00 321,300.00
9 1 bh Skaklar Ganda setara panasonic 3.00 buah 25,500.00 76,500.00
10 1 bh Pek. Lampu DL setara philips meson lengkap 34.00 buah 199,750.00 6,791,500.00
11 1 bh Pek. Lampu Pijar setara philips 3.00 buah 53,125.00 159,375.00
12 Penambahan Daya Listrik 1.00 ls 7,840,000.00 7,840,000.00
13 1 bh Lampu sorot Plakat 12 wat 3.00 buah 340,000.00 1,020,000.00
M PEKERJAAN SANITASI
1 1 m1 pipa PVC diameter 3" (AW) Air Supply 30.00 m1 57,120.00 1,713,600.00
2 1 m1 pipa PVC diameter 4" (AW) Air Supply 30.00 m1 84,000.00 2,520,000.00
3 1 m1 pipa PVC diameter 3/4" (AW) Air Supply 40.00 m1 32,800.00 1,312,000.00
4 1 bh shower head 1 set setara classic 5.00 buah 292,000.00 1,460,000.00
5 1 bh Avur Stainless 5.00 buah 69,600.00 348,000.00
6 1 bh Kran Air Stainless 5.00 buah 45,680.00 228,400.00
7 1 unit Pasang septictank ukuran 3 x 1.5 x 1.75. 1.00 unit 4,432,504.00 4,432,504.00
8 1 unit - Peresapan (Ø=1 m ; d= 2 m) 1.00 unit 1,593,234.00 1,593,234.00
9 1 bh Closed Duduk Porselin setara toto 3.00 buah 1,757,500.00 5,272,500.00
10 1 bh Closed Jongkok setara toto 2.00 buah 242,880.00 485,760.00
11 1 bh Wastafel setara toto 1.00 buah 523,620.00 523,620.00
12 1 unit Pekerjaan Zinc Dapur Bolzano 2 Lubang 1.00 unit 900,000.00 900,000.00
13 Filter penyaring air bersih 1.00 set 140,000.00 140,000.00
14 1 bh Pompa air listrik 1.00 bh 709,650.00 709,650.00
JUMLAH 584,071,130.82
OVERHEAD LAPANGAN DAN KANTOR
NO URAIAN PENGELUARAN SAT VOL HARGA JUMLAH TOTAL
REALCOST 584,071,130.819
A. OVERHEAD LAPANGAN Ls
Gaji Site Manager+Uang Makan+Tunjangan bln 5 8,000,000.00 40,000,000.00
Logistik/Admini/Keuangan+Uang Makan+Tunjangan bln 5 6,500,000.00 32,500,000.00
Mess/Kantor/Listrik/PAM/Iuran RT/Keamanan bln 5 1,500,000.00 7,500,000.00
Aira Galon untuk Mess bln 5 200,000.00 1,000,000.00
Aira Galon untuk Lapangan bln 5 200,000.00 1,000,000.00
ATK/Foto Copy/Laporan Harian/Minggu/Bulan bln 5 75,000.000 375,000.00
Uang Saku untuk Perjalanan dua Staf ( Dua Orang ) pp 4 200,000.000 800,000.000
Biaya Makan dalam perjalanan / 2 orang pp 4 150,000.000 600,000.000
Kesehatan ls 1 1,000,000.000 1,000,000.000
Jamuan Lapangan ls 1 1,000,000.000 1,000,000.000
Uang Saku Pengawas bln 5 1,000,000.000 5,000,000.000
Pembelian Alat KerjaTukang Listrik ls 1 1,000,000.000 1,000,000.000
Biaya Tak Terduga Lapangan ls 1 1,500,000.000 1,500,000.000
Pulsa Hand Phone bln 5 200,000.000 1,000,000.000
Listrik, PAM, Iuran Kemanan di Mess bln 5 100,000.000 500,000.000
Ke Amanan di lokasi Kerja ( ORMAS, POLSEK ) ls 1 1,000,000.000 1,000,000.000
Administrasi Tagihan/ Photo Copy ls 1 1,000,000.000 1,000,000.000
Laporan Mingguan, Bulan ( Photo Copy/ Rental dll ) ls 1 250,000.000 250,000.000
Inventaris Motor Second ls 1 5,000,000.000 5,000,000.000
BMM ( Alat kerja dan sepeda motor ) ls 1 1,500,000.000 1,500,000.000
Biaya Pengetikan Tagihan ls 1 500,000.000 500,000.000
Biaya Pemeriksaan Akhir Pekerjaan ls 1 500,000.000 500,000.000
PHO / Serah terima Ke - 1 ls 1 1,000,000.000 1,000,000.000
UPAH HARIAN KERJA LOKAL
Pekerja / 10 orang hari 1500 100,000.000 150,000,000.000
Tukang / 2 Orang hari 300 150,000.000 45,000,000.000
Ekspedisi Material ls 1 50,000,000.000 50,000,000.000
362,605,000.000
B OVERHEAD KANTOR
Gaji Staf Kantor : 2 orang bln 5 3,000,000.000 15,000,000.000
Bantuan Dari Proyek bln 5 2,500,000.000 12,500,000.000
Ucapan Pemenang Lelang ls 1 4,000,000.000 4,000,000.000
Listrik, Tlp, Internet, Iuran bln 5 1,250,000.000 6,250,000.000
ATK dll ls 1 350,000.000 350,000.000
BBM Kantor bln 5 500,000.000 2,500,000.000
Tinta Coumputer ls 1 250,000.000 250,000.000
Service alat kerja ls 1 500,000.000 500,000.000
Sedekah ls 1 4,000,000.000 4,000,000.000
SPJ Kantor ls 1 7,500,000.000 7,500,000.000
PEMBUKTIAN : JL. Plaju No.13,
Kebon Melati, Jakarta Pusat
Transport Bandung - Jakarta ls 1 500,000.000 500,000.000
Biaya Makan minum dll ls 1 500,000.000 500,000.000
3,630,409.8
JUMLAH 1,040,031,945.449
1,248,038,334.539