Kegiatan Pengembangan Fasilitas Sarana Dan Prasarana Yayasan PAUD
Pembangunan Yayasan Paud Pekerjaan urugan Tanah Timbunan & Pagar Batas Tanah Lokasi Area Yayasan Paud Tahun 2021
NO. URAIAN PEKERJAAN VOLUME SAT. HARGA SATUAN BIAYA
1 4 5 6 7 I PEKERJAAN PENDAHULUAN 1 Pemasangan bowplank 76.00 M1 77,593.12 5,897,077.12 Sub Total I 5,897,077.12 II PEKERJAAN TANAH 3 Urugan Tanah / pasir urug 630.00 M3 98,000.00 61,740,000.00 Sub Total II 61,740,000.00 III PEKERJAAN BETON Pondasi Foot plat (Utk Tiang steel BRC) 0.6 m x 0,6 m x 1 2.40 M3 4,750,000.00 11,400,000.00 0,5 cm x 30 Bh 2 Sloof beton 20/35 4.51 M3 4,350,000.00 19,618,500.00 Sub Total III 31,018,500.00 IV PEKERJAAN PASANGAN PAGAR BATAS TANAH Pekerjaan Fabrikasi, erection & instalasai Pagar BRC + 1 76.00 M1 450,000.00 34,200,000.00 Tiang pagar Sub Total IV 34,200,000.00 TOTAL ANGGARAN ( I - IV) 132,855,577.12 DIBULATKAN