Tongkang
Tongkang
MAYOR ITEM :
1. SPUN PILE
2. SILT SCREEN
3. PCI Girder
4. SSP
5. PRECAST
6. BESI
7. SUBKON BAMBU DAN MATRAS
RENCANA PROGRES BULANAN
BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7 BULAN KE-8 BULAN KE-9 KETERANGA
NO URAIAN PEKERJAAN
N
MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU
KE-1 KE-2 KE-3 KE-4 KE-5 KE-6 KE-7 KE-8 KE-9 KE-10 KE-11 KE-12 KE-13 KE-14 KE-15 KE-16 KE-17 KE-18 KE-19 KE-20 KE-21 KE-22 KE-23 KE-24 KE-25 KE-26 KE-27 KE-28 KE-29 KE-30 KE-31 KE-32 KE-33 KE-34 KE-35 KE-36
II.1.3 PEKERJAAN BANGUNAN STRUKTUR DERMAGA
1 Pekerja a n Ponda s i Ti a ng Pa nca ng
1,1 Penga da a n Ti a ng Pa nca ng Pi pa Ba ja , (Di a . 812 mm, T = 14 mm) 306 306 237 237
270 Feet 230 Feet
1,2 Pema nca nga n Ti a ng Pa nca ng Ba ja @ La ut 63 63 63 63 63 63 63 63 39
Tongka ng 270 Feet 270 Feet
2 Pekerja a n Beton Bertul a ng Pra ceta k (Penga da a n Pema s a nga n) Produksi Pengiriman 1 Pengiriman 2 Pengiriman 3
180 Feet 180 Feet 180 Feet
2 Pekerja a n Beton Bertul a ng Pra ceta k (Pema s a nga n) Pemasangan Per hari 16 Pcs
230 Feet
3 Pekerja a n Beton Bertul a ng Ins i tu Dengan Asumsi Kesiapan Pile Cap
230 Feet
4 Pekerja a n La i n-La i n (Fender, Bol l a rd, Hydra nt)
Barge
Dimesi Kapasitas LOA Depth Jumlah Pemakaian Harga Sewa Biaya
No. Area Item Pekerjaan Jenis Alat / Kode Kode Alat Status Keterangan
(Feet) (ton) (meter) (meter) (unit) (bulan) (Rp.) (Rp.)
1 Dermaga Pancang, Stok, Pengecoran dll Tongkang D1 270 6.000 79 x 22 4-5m 1 3 774.782.609 2.324.347.826,09 Subkont Kedalaman Seabed - 6,5 m
Service/Suplay SSP dan Precast Tongkang D3 230 4000 69 x 17,5 4m 1 3 660.000.000 1.980.000.000,00 Rental Kedalaman Seabed - 6,5 m
Service/Suplay Precast Tongkang D4 180 2000 60 x 17 3-4m 1 3 450.000.000 1.350.000.000,00 Rental Kedalaman Seabed - 6,5 m
Ponton Segmental S1 5x5 6 6 80.000.000 2.880.000.000,00 Rental Kedalaman Seabed - 6,5 m
2 Trestle Tongkang Pancang 180 Feet Tongkang T1 180 2000 60 x 17 4-5m 1 2 450.000.000 900.000.000,00 Rental Kedalaman Seabed - 4-6 m
Tongkang Erection 180 Feet Tongkang T2 180 2000 60 x 17 3-4m 1 1 450.000.000 450.000.000,00 Subkont Kedalaman Seabed - 4-6 m
Tongkang Pengiriman 180 Feet Tongkang T3 180 2000 60 x 17 4m 1 1 450.000.000 450.000.000,00 Subkont Kedalaman Seabed - 4-6 m
Tongkang Servis Besi dan Pengecoran 120Tongkang
Feet T4 120 1500 4m 1 3 344.347.826 1.033.043.478,26 Rental Kedalaman Seabed - 4-6 m
Ponton Segmental S2 5x5 6 6 80.000.000 2.880.000.000,00 Rental Kedalaman Seabed - 4-6 m
14.247.391.304,35
1 Asumsi Per Bulan 200 Jam
2 Belum Termasuk BBM dan Mob & Demob
3 Belum termasuk kru
Crane
Dimesi Kapasitas LOA Depth Jumlah Pemakaian Harga Sewa Biaya
No. Area Item Pekerjaan Jenis Alat / Kode Kode Alat Status Keterangan
(Feet) (ton) (meter) (meter) (unit) (bulan) (Rp.) (Rp.)
1 Dermaga Crawel Crane 200 Ton Crawler Crane CD1 200 8,83 x 7,22 1 3 482.500.000,00 1.447.500.000,00 Rental Kedalaman Seabed - 6,5 m
Crawel Crane 180 Ton Crawler Crane CD2 180 8,155 x 6,682 1 3 450.000.000,00 1.350.000.000,00 Subkont Kedalaman Seabed - 6,5 m
Crawel Crane 180 Ton Crawler Crane CD3 180 8,155 x 6,682 1 3 450.000.000,00 1.350.000.000,00 Rental Kedalaman Seabed - 6,5 m
2 Trestle Crawel Crane 200 Ton (Erection) Crawler Crane CT1 200 8,83 x 7,22 1 1 482.500.000,00 482.500.000,00 Subkont Kedalaman Seabed - 4-6 m
Crawel Crane 180 Ton (Servis) Crawler Crane CT2 180 8,155 x 6,682 1 1 377.500.000,00 377.500.000,00 Rental Kedalaman Seabed - 4-6 m
Crawel Crane 80 Ton Servis Crawler Crane CT3 80 7,76 x 6,16 1 2 197.500.000,00 395.000.000,00 Subkont Kedalaman Seabed - 4-6 m
Crawel Crane 60 Ton Pancang Crawler Crane CT4 60 7,76 x 6,16 1 2 142.500.000,00 285.000.000,00 Subkont Kedalaman Seabed - 4-6 m
3 Pelabuhan Kendal Stock Yard, Pengecoran, dll Mobile Crane MCK1 80/100 6,22 x 4,9 1 6 197.500.000,00 1.185.000.000,00 Rental Kedalaman Seabed - 4-6 m
Keterangan : 6.872.500.000,00
1 Asumsi Per Bulan 200 Jam
2 Belum Termasuk BBM dan Mob & Demob
3 Belum termasuk tim lifting (SPV dan Rigger)
185 jt bln/300 jam
Angkutan
Keterangan :
1 Belum Termasuk BBM dan Mob & Demob 22.844.391.304,35
Spun Pile
Loading 948,68 Ton 2,2 Hari
Berlayar
Kendal - Batang 51 Km 0,2 Hari
Unloading 948,68 Ton 2,2 Hari
Batang - Kendal 0,2 Hari
4,9 Hari
5,0 Hari
SSP
Loading 1266 Ton 4,1 Hari
Berlayar
Cilegon - Batang 517 Km 2,4 Hari
Unloading 1266 Ton 2,1 Hari
Batang - Cilegon 517 Km Hari
8,6 Hari
9,0 Hari
Kebutuhan Alat
Pemancangan Baja
Volume Pekerjaan 8145 m
Jumlah Titik 181 Titik
Target Rencana 3 Titik/Hari 6 Titik/Hari Asumsi per hari 6 Batang Perhari
Jumlah Hari 60 Hari 30 Hari
SCH Pemasaran : 2,5 Bulan (75 hari)
Panjang Pipa Rencana
BOQ Penyambungan 362 Bh terhadap BOQ
Panjang 1 Pipa 15 m
Berat Per m 276 Kg Berat Perbatang 8.273 Ton (Panjang Boom 48,8 - 51,8) Crane 120 Ton
Total Berat 2.246.228 Kg 35 m = 7,5 Ton
2.246 Ton Aman !!!
Jumlah Muatan
Pipa SSP 204 Batang Asumsi Panjang 22,5 m
306 Batang Asumsi Panjang 15 m
Crawel Crane 200 Ton 1 Unit
Total Berat 1471 Ton
Total Kebutuhan
Tongkang 270 Feet 1 Unit 3 Bulan By Subkon
Tongkang Pengiriman 230 Feet 1 Unit 3 Bulan Rental
Tongkang Pengiriman 180 Feet 1 Unit 3 Bulan Rental
Crawel Crane 200 Ton 1 Unit 3 Bulan By Subkon
Crawel Crane 180 Ton 1 Unit 3 Bulan Rental
Crawel Crane 180 Ton 1 Unit 3 Bulan Rental
Erection Girder
Volume Pekerjaan 102 Batang
Target Rencana 4 Batang/hari
Jumlah Hari 26 Hari
Total Kebutuhan
Tongkang Pancang 180 Feet 1 Unit 2 Bulan By Subkon
Tongkang Erection 180 Feet 1 Unit 1 Bulan By Subkon
Tongkang Pengiriman 180 Feet 1 Unit 1 Bulan Rental
Tongkang Servis Besi dan Pengecoran 120 Feet 1 Unit 3 Bulan Rental
Crawel Crane 200 Ton (Erection) 1 Unit 1 Bulan By Subkon
Crawel Crane 180 Ton (Servis) 1 Unit 1 Bulan Rental
Crawel Crane 80 Ton Servis 1 Unit 2 Bulan By Subkon
Crawel Crane 60 Ton Pancang 1 Unit 2 Bulan By Subkon
DERMAGA
270 FEET
AREAL CRAWEL
CRANE PANCANG
230 FEET
Segmen Segmen
Segmen 1 Segmen 2 Segmen 3 Segmen 4 Segmen 1 Segmen 2 Segmen 3
Susunan Susunan
Layer 4 24 24 24 Layer 5 9 10 8
Layer 3 25 25 25 Layer 4 16 16 16
Layer 2 26 26 26 Layer 3 17 17 17
Layer 1 27 27 27 Layer 2 18 18 18
TOTAL 102 Batang 102 Batang 1 Batang 102 Batang Layer 1 19 19 19
BERAT 422 Ton 422 Ton 205 Ton 422 Ton TOTAL 79 Batang 80 Batang 78 Batang
GT 1471 Ton BERAT 327 Ton 331 Ton 323 Ton
GT 980 Ton
15 m 15 m 15 m
Pengiriman 1 306 Batang 1.266 Ton Waktu Pengiriman Minggu Ke 9
Pengiriman 2 237 Batang 980 Ton Waktu Pengiriman Minggu Ke 13
543 Batang 2.246 Ton
SPUN PILE
BELAKANG DEPAN
Pengiriman
Segmen
Segmen 1 Segmen 2 Segmen 3 Segmen 4 Total 1 2 3
Susunan
Layer 4 Bottom Middle Upper Bottom 84 37 37 10
Layer 1
Girder
Segmen
Segmen 1 Segmen 2 Segmen 3
Susunan
Layer 1 13 1 13 26
TOTAL 13 Batang 1 Unit 13 Unit
BERAT 325 Ton 205 Ton 325 Ton
Segmen
Segmen 1 Segmen 2 Segmen 3
Susunan
Layer 1 13 1 13 27
TOTAL 13 Batang 1 Unit 13 Unit
BERAT 325 Ton 185 Ton 325 Ton
Segmen
Segmen 1 Segmen 2 Segmen 3
Susunan
Layer 1 13 1 13 27
TOTAL 13 Batang 1 Unit 13 Unit
BERAT 325 Ton 185 Ton 325 Ton
Segmen
Segmen 1 Segmen 2 Segmen 3
Susunan
Layer 1 12 1 12 25
TOTAL 12 Batang 1 Unit 12 Unit
BERAT 300 Ton 185 Ton 300 Ton
105
PRECAST
Produksi Perhari
Kg m3 m2 Total Berat 60 Hari
Headstock - precast 168,00 114,29 19.200,22 - 0,90 151,20 5,67 952,11 378,00 3,00 Pcs/Hari
Headstock fender - precast 13,00 574,25 7.465,26 - 1,77 23,01 8,97 116,55 57,53 1,00 Pcs/Hari
Plank Fender Parapet 13,00 1.490,58 19.377,49 - 4,95 64,36 - - 160,89 1,00 Pcs/Hari
Balok B1 - precast layer 1 13,00 336,37 4.372,80 - 1,20 15,56 6,82 88,67 38,90 1,00 Pcs/Hari
Balok B2 - precast layer 1 39,00 336,37 13.118,40 - 1,20 46,68 6,82 266,01 116,71 1,00 Pcs/Hari
Balok B3 - precast layer 1 26,00 345,55 8.984,28 - 1,23 31,86 6,98 181,56 79,66 1,00 Pcs/Hari
Balok B4 - precast layer 1 52,00 278,17 14.464,93 - 0,97 50,39 5,52 287,12 125,97 1,00 Pcs/Hari
Balok B5 - precast layer 1 150,00 385,39 57.808,03 - 1,40 209,48 7,96 1.193,64 523,69 3,00 Pcs/Hari
Balok B6 - precast layer 1 38,00 313,91 11.928,58 - 1,11 42,24 6,33 240,68 105,59 1,00 Pcs/Hari
Deck slab Tipe HS.1 - precast 100,00 4,13 412,93 - 2,53 252,90 16,90 1.690,15 632,25 2,00 Pcs/Hari
Deck slab Tipe HS.2 - precast 50,00 8,45 422,27 - 2,58 129,13 17,22 861,14 322,81 1,00 Pcs/Hari
Deck slab Tipe HS.3 - precast 100,00 3,54 353,67 - 2,10 210,10 14,33 1.433,19 525,25 2,00 Pcs/Hari
Deck slab Tipe HS.4 - precast 28,00 11,69 327,20 - 2,37 66,32 15,94 446,26 165,80 1,00 Pcs/Hari
3.233 Ton