Anda di halaman 1dari 2

ENGINEERING ESTIMATE (EE)

RENCANA ANGGARAN BIAYA


PROGRAM : PENYEDIAAN PENGEMBANGAN PRASARANA DAN SARANA PERTANIAN/PERKEBUNAN
PEKERJAAN : PEMBUATAN DAM PARIT
DESA : KAMI WANGI
KECAMATAN : TOILI BARAT
KABUPATEN : BANGGAI
PROPINSI : SULAWESI TENGAH
TAHUN ANGGARAN : 2024

NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

A B C D E F
I PEKERJAAN PERSIAPAN

1 Pengukuran Dan Pemasangan Bouwplank ls 1.00 1,000,000.00 1,000,000.00


2 Papan Nama Proyek Bh 1.00 250,000.00 250,000.00
3 Dokumentasi dan Pelaporan Ls 1.00 2,500,000.00 2,500,000.00
J u m l a h I 3,750,000.00
II PEKERJAAN DAM PARIT

A PEKERJAAN PEMBUATAN BAYA-BAYA 14,557,480.62


1 Pek. Galian Tanah M³ 2.35 94,462.50 222,175.80
2 Pas. Pondasi/Kovoran Batu Kali M³ 2.35 694,963.29 1,634,553.66
3 Pas. Dinding Batu Kali M² 7.13 1,259,701.48 8,975,373.02
4 Pek. Plesteran Dinding 1 : 5 M² 28.46 80,711.24 2,297,041.90
5 Pek. Acian Semen M² 28.46 50,187.50 1,428,336.25
B PEKERJAAN PEMBUATAN MERCU 20,068,534.65
1 Pek. Galian Tanah M³ 5.59 94,462.50 528,328.76
2 Pas. Pondasi/Kovoran Batu Kali M³ 5.59 694,963.29 3,886,929.67
3 Pas. Batu Kali Mercu M² 10.37 1,259,701.48 13,063,104.31
4 Pek. Plesteran Mercu 1 : 5 M² 19.79 80,711.24 1,597,081.74
5 Pek. Acian Semen M² 19.79 50,187.50 993,090.18
C PEKERJAAN LANTAI 20,178,592.84
1 Pek. Galian Tanah M³ 7.05 94,462.50 665,960.63
2 Pas. Batu Kali Lantai M³ 11.42 1,271,709.40 14,528,008.19
3 Pek. Plesteran Lantai 1 : 5 M² 38.08 80,711.24 3,073,484.03
4 Pek. Acian Semen Lantai M² 38.08 50,187.50 1,911,140.00
C PEKERJAAN SAYAP 57,258,329.13
1 Pek. Galian Tanah M³ 13.58 94,462.50 1,282,800.75
2 Pas. Pondasi/Kovoran Batu Kali M³ 13.58 694,963.29 9,437,601.46
3 Pas. Dinding Sayap Batu Kali M² 33.95 1,259,701.48 42,766,865.11
4 Pek. Plesteran Sayap 1 : 5 M² 28.81 80,711.24 2,325,210.12
5 Pek. Acian Semen M² 28.81 50,187.50 1,445,851.69
D. PEKERJAAN PINTU AIR & BETON 22,402,322.48
1 Pek.Beton M³ 0.34 7,710,585.11 2,602,322.48
2 Pek.Pintu Penguras M³ 1.00 10,000,000.00 10,000,000.00
3 Pek.Pintu Intek Saluran M³ 1.00 8,000,000.00 8,000,000.00
4 Pek.Pintu Saluran Pembuangan Lumpur M³ 1.00 1,800,000.00 1,800,000.00
J u m l a h II 134,465,259.71
III PEKERJAAN DRAINASE

1 Pek. Galian Tanah M3 33.93 94,462.50 3,205,112.63


2 Pas. Batu Kali Saluran M3 20.48 1,271,709.40 26,043,336.80
3 Pek. Plesteran 1 : 3 M2 95.04 80,711.24 7,670,796.27
4 Pek. Acian Semen M2 95.04 50,187.50 4,769,820.00
J u m l a h VI 41,689,065.70
REKAPITULASI
PROGRAM : PENYEDIAAN PENGEMBANGAN PRASARANA DAN SARANA PERTANIAN/PERKEBUNAN
PEKERJAAN : PEMBUATAN DAM PARIT
DESA : KAMI WANGI
KECAMATAN : TOILI BARAT
KABUPATEN : BANGGAI
PROPINSI : SULAWESI TENGAH
TAHUN ANGGARAN : 2024

NO URAIAN PEKERJAAN JUMLAH HARGA


A B C

I PEKERJAAN PERSIAPAN 3,750,000.00


II PEKERJAAN DAM PARIT 134,465,259.71
III PEKERJAAN DRAINASE 41,689,065.70
REAL COST 179,904,325.41
PPN (11% X REAL COST ) 19,789,475.80
JUMLAH REAL COST + PPN 11% 199,693,801.21
DIBULATKAN 200,000,000.00

Terbilang : Seratus Sembilan Puluh Sembilan Juta Rupiah

Disetujui Oleh : Dibuat Oleh :


Pejabat Pembuat Komitmen (PPK) Fasilitator
Dinas Tanaman Pangan,Hortikultura dan Perkebunan

…………………………………….. …………………………….
NIP…………………………………. Tenaga Teknis

Anda mungkin juga menyukai