2 Memasang Panel Unit (Box MCB 8 Group inbow) 1.00 unit 350,000.00 1,050,000.00 350,000.00 1,050,000.00
3 Memasang Kabel Power (NYM 3x2,5 mm) 140.00 m1 15,000.00 35,000.00 2,100,000.00 4,900,000.00
4 Instalasi titik Lampu (Kabel NYM 3x1,5 mm2) 35.00 titik 100,000.00 185,000.00 3,500,000.00 6,475,000.00
8 Memasang Saklar Tunggal setara Broco 8.00 buah 25,000.00 25,000.00 200,000.00 200,000.00
9 Memasang Saklar Ganda setara Broco 7.00 buah 25,000.00 35,000.00 175,000.00 245,000.00
10 Memasang Stop Kontak setara Broco 24.00 buah 25,000.00 25,000.00 600,000.00 600,000.00
PEKERJAAN PERSIAPAN
1 1 Ls Pembersihan Lokasi Lahan sebelum dan sesudah pekerjaan
1.000 Ls Biaya Langsir material, pembersihan lahan @ Rp. 650,000.00 = Rp 650,000.00
Sub total : = Rp 650,000.00
Total upah+bahan : = Rp 650,000.00
PEKERJAAN TANAH
1 1 m3 Galian Untuk Tanah Keras
Upah An. SNI ( Revisi ) 6.4.1
1.000 Oh Pekerja @ Rp. 95,000.00 = Rp 95,000.00
0.032 Oh Mandor @ Rp. 110,000.00 = Rp 3,520.00
Sub total : = Rp 98,520.00
Total upah+bahan : = Rp 98,520.00
2 1 m3 Urugan kembali
Upah An. SNI ( Revisi ) 6.9.1
0.250 Oh Pekerja @ Rp. 95,000.00 = Rp 23,750.00
0.008 Oh Mandor @ Rp. 110,000.00 = Rp 880.00
Sub total : = Rp 24,630.00
Total upah+bahan : = Rp 24,630.00
PEKERJAAN PONDASI
1 1 m2 Pasangan Pondasi Rollag bata merah tebal 1 bata, 1 Pc : 4 Ps
Bahan An. SNI ( Revisi ) 6.4.1
140.000 Bh Bata merah @ Rp. 750.00 = Rp 105,000.00
26.550 Kg Semen portland @ Rp. 2,100.00 = Rp 55,755.00
0.093 m3 Pasir pasang @ Rp. 255,000.00 = Rp 23,715.00
Sub total : = Rp 184,470.00
Upah An. SNI ( Revisi ) 6.4.2
0.650 Oh Pekerja @ Rp. 95,000.00 = Rp 61,750.00
0.200 Oh Tukang batu @ Rp. 100,000.00 = Rp 20,000.00
0.020 Oh Kepala tukang @ Rp. 105,000.00 = Rp 2,100.00
0.030 Oh Mandor @ Rp. 110,000.00 = Rp 3,300.00
Sub total : = Rp 87,150.00
Total upah+bahan : = Rp 271,620.00
PEKERJAAN STRUKTUR
D.1. PEKERJAAN STRUKTUR PLAT TOPI-TOPI
1 1 m2 Pasang bekisting untuk lantai
Bahan An. SNI ( Revisi ) 6.32.1
0.040 m3 Kayu terentang/Meranti (MC) @ Rp. 3,000,000.00 = Rp 120,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp. 12,500.00 = Rp 5,000.00
0.200 Ltr Minyak bekisting @ Rp. 6,800.00 = Rp 1,360.00
0.015 m3 Kayu Perancah @ Rp. 3,000,000.00 = Rp 45,000.00
0.350 Lbr Plywood Tebal 9 mm uk 120 x 90 cm @ Rp. 92,500.00 = Rp 32,375.00
6.000 Btg Dolken kayu diameter 8 -10 /400 cm @ Rp. 22,500.00 = Rp 135,000.00
Sub total : = Rp 338,735.00
Dipakai 2x = Rp 169,367.50
Upah An. SNI ( Revisi ) 6.32.2
0.320 Oh Pekerja @ Rp. 95,000.00 = Rp 30,400.00
0.330 Oh Tukang kayu @ Rp. 105,000.00 = Rp 34,650.00
0.033 Oh Kepala tukang @ Rp. 105,000.00 = Rp 3,465.00
0.006 Oh Mandor @ Rp. 110,000.00 = Rp 660.00
Sub total : = Rp 69,175.00
Total upah+bahan : = Rp 407,910.00
3 1 m2 Pemasangan Acian
Bahan A.4.4.2.27
3.250 Kg Semen portland @ Rp. 2,100.00 = Rp 6,825.00
Sub total : = Rp 6,825.00
Upah A.4.4.2.27
0.200 Oh Pekerja @ Rp. 95,000.00 = Rp 19,000.00
0.100 Oh Tukang batu @ Rp. 100,000.00 = Rp 10,000.00
0.010 Oh Kepala tukang @ Rp. 105,000.00 = Rp 1,050.00
0.010 Oh Mandor @ Rp. 110,000.00 = Rp 1,100.00
Sub total : = Rp 31,150.00
Total upah+bahan : = Rp 37,975.00
PEKERJAAN PENUTUP LANTAI DAN DINDING
1 1 m2 Pasang lantai Keramik uk.50x50, polished
Bahan An. SNI ( Revisi ) 6.47.1
1.050 m2 Keramik uk.50x50, polished @ Rp. 132,000.00 = Rp 138,600.00
7.454 Kg Semen portland @ Rp. 2,100.00 = Rp 15,653.19
0.042 m3 Pasir pasang @ Rp. 255,000.00 = Rp 10,710.00
0.300 Kg Semen warna @ Rp. 3,000.00 = Rp 900.00
Sub total : = Rp 165,863.19
Upah An. SNI ( Revisi ) 6.47.2
0.240 Oh Pekerja @ Rp. 95,000.00 = Rp 22,800.00
0.120 Oh Tukang batu @ Rp. 100,000.00 = Rp 12,000.00
0.012 Oh Kepala tukang @ Rp. 105,000.00 = Rp 1,260.00
0.013 Oh Mandor @ Rp. 110,000.00 = Rp 1,375.00
Sub total : = Rp 37,435.00
Total upah+bahan : = Rp 203,298.19
PEKERJAAN PLAFOND
1 1 m2 Pemasangan Rangka Besi Hollow Galvanis 40.40.0,3 mm; Modul 60x60 cm dinding plafond
Bahan PUPR28-2016 (A.4.2.1.21)
4.000 m' Hollow galvanis uk.40x40x0,3 mm @ Rp. 15,000.00 = Rp 60,000.00
1.000 **) Assesoris (perkuatan; las dll) = Rp 60,000.00
**) 100% x rangka Sub total : = Rp 120,000.00
Upah PUPR28-2016 (A.4.2.1.21)
0.350 OH Pekerja @ Rp. 95,000.00 = Rp 33,250.00
0.350 OH Tukang Besi @ Rp. 100,000.00 = Rp 35,000.00
0.035 OH Kepala Tukang @ Rp. 105,000.00 = Rp 3,675.00
0.018 OH Mandor @ Rp. 110,000.00 = Rp 1,980.00
Sub total : = Rp 73,905.00
Total upah+bahan : = Rp 193,905.00
2 1 m2 Pasang langit-langit gypsum board, tebal 9 mm
Bahan An. SNI ( Revisi ) 6.24.1
0.364 Lbr Gypsum tebal 9 mm @ Rp. 87,000.00 = Rp 31,668.00
0.110 Kg Paku sekrup @ Rp. 15,000.00 = Rp 1,650.00
Sub total : = Rp 33,318.00
Upah An. SNI ( Revisi ) 6.24.2
0.100 Oh Pekerja @ Rp. 95,000.00 = Rp 9,500.00
0.050 Oh Tukang kayu @ Rp. 105,000.00 = Rp 5,250.00
0.005 Oh Kepala tukang @ Rp. 105,000.00 = Rp 525.00
0.005 Oh Mandor @ Rp. 110,000.00 = Rp 550.00
Sub total : = Rp 15,825.00
Total upah+bahan : = Rp 49,143.00
PEKERJAAN PARTISI
1 1 m2 Pemasangan Rangka Hollow galvanis uk.40x40x0,3 mm; Modul 60x120 cm dinding partisi
Bahan PUPR28-2016 (A.4.2.1.20)
3.5000 m' Hollow galvanis uk.40x40x0,3 mm @ Rp. 15,000.00 = Rp 52,500.00
1.0000 **) Assesoris (perkuatan; las dll) = Rp 52,500.00
**) 100% x rangka Sub total : = Rp 105,000.00
Upah PUPR28-2016 (A.4.2.1.20)
0.2500 OH Pekerja @ Rp. 95,000.00 = Rp 23,750.00
0.2500 OH Tukang Besi @ Rp. 100,000.00 = Rp 25,000.00
0.0250 OH Kepala Tukang @ Rp. 105,000.00 = Rp 2,625.00
0.0130 OH Mandor @ Rp. 110,000.00 = Rp 1,430.00
Sub total : = Rp 52,805.00
Total upah+bahan : = Rp 157,805.00
PEKERJAAN PENGECATAN
1 1 m2 Pengecatan Interior tembok baru (Ngamplas, 1x cat dasar, 2x cat penutup)
Bahan An. SNI ( Revisi ) 6.14.1
0.100 Kg Plamir @ Rp. 35,000.00 = Rp 3,500.00
0.250 Lbr Ampelas @ Rp. 3,000.00 = Rp 750.00
0.020 Bh Kuwas / roll @ Rp. 14,000.00 = Rp 280.00
0.100 Kg Cat dasar @ Rp. 32,500.00 = Rp 3,250.00
0.260 Kg Cat interior penutup 2x @ Rp. 45,000.00 = Rp 11,700.00
Sub total : = Rp 19,480.00
Upah An. SNI ( Revisi ) 6.14.2
0.020 Oh Pekerja @ Rp. 95,000.00 = Rp 1,900.00
0.063 Oh Tukang cat @ Rp. 100,000.00 = Rp 6,300.00
0.006 Oh Kepala tukang @ Rp. 105,000.00 = Rp 661.50
0.003 Oh Mandor @ Rp. 110,000.00 = Rp 275.00
Sub total : = Rp 9,136.50
Total upah+bahan : = Rp 28,616.50
PEKERJAAN SANITASI
1 1 buah Memasang Closet duduk setara TOTO SW53JP
Bahan An. SNI ( Revisi ) 6.1.1
1.000 Bh Closet duduk setara TOTO SW53JP @ Rp. 2,250,000.00 = Rp 2,250,000.00
6.000 % Perlengkapan Closet = Rp 135,000.00
Sub total : = Rp 2,385,000.00
Upah An. SNI ( Revisi ) 6.1.2
3.300 Oh Pekerja @ Rp. 95,000.00 = Rp 313,500.00
1.100 Oh Tukang batu @ Rp. 100,000.00 = Rp 110,000.00
0.001 Oh Kepala tukang @ Rp. 105,000.00 = Rp 105.00
0.160 Oh Mandor @ Rp. 110,000.00 = Rp 17,600.00
Sub total : = Rp 441,205.00
Total upah+bahan : = Rp 2,826,205.00
2 1 buah Memasang Shower Spray With Stop Valve (White)
Bahan An. SNI ( Revisi ) 6.35.1
@ Rp. 550,000.00 = Rp 550,000.00
1.000 Bh Shower Spray With Stop Valve (White)
0.025 Bh Seal tape @ Rp. 5,000.00 = Rp 125.00
Sub total : = Rp 550,125.00
Upah An. SNI ( Revisi ) 6.35.2
0.010 Oh Pekerja @ Rp. 95,000.00 = Rp 950.00
0.100 Oh Tukang batu @ Rp. 100,000.00 = Rp 10,000.00
0.010 Oh Kepala tukang @ Rp. 105,000.00 = Rp 1,050.00
0.005 Oh Mandor @ Rp. 110,000.00 = Rp 550.00
Sub total : = Rp 12,550.00
Total upah+bahan : = Rp 562,675.00
14 1 Unit Memasang pompa hisap air otomatis setara Shimizu PS 230 BIT
Bahan
Pompa hisap air otomatis setara Shimizu
1.0000 bh @ Rp. 840,000.00 = Rp 840,000.00
PS 230 BIT
5.0000 % Perlengkapan instalasi = Rp 42,000.00
Sub total : = Rp 882,000.00
Upah
0.5000 Oh Pekerja @ Rp. 95,000.00 = Rp 47,500.00
0.5000 Oh Tukang batu @ Rp. 100,000.00 = Rp 50,000.00
0.1000 Oh Kepala tukang @ Rp. 105,000.00 = Rp 10,500.00
0.0100 Oh Mandor @ Rp. 110,000.00 = Rp 1,100.00
Sub total : = Rp 109,100.00
Total upah+bahan : = Rp 991,100.00
15 1 Ls Pembuatan meja beton panjang 2,7 meter di pantry termasuk Kitchen Zink dan finishing Granit
Upah
Pembuatan meja beton panjang 2,7 meter
1.000 Ls di pantry termasuk Kitchen Zink dan @ Rp. 3,000,000.00 = Rp 3,000,000.00
finishing Granit
Sub total : = Rp 3,000,000.00
Total upah+bahan : = Rp 3,000,000.00
b 1 m3 Urugan Kembali
Upah An. SNI ( Revisi ) 6.9.1
0.250 Oh Pekerja @ Rp. 95,000.00 = Rp 23,750.00
0.008 Oh Mandor @ Rp. 110,000.00 = Rp 880.00
Sub total : = Rp 24,630.00
Total upah+bahan : = Rp 98,630.00
c 1 m3 Pasir urug
Bahan An. SNI ( Revisi ) 6.11.1
1.200 m3 Pasir urug @ Rp. 235,000.00 = Rp 282,000.00
Sub total : = Rp 282,000.00
Upah An. SNI ( Revisi ) 6.11.2
0.300 Oh Pekerja @ Rp. 95,000.00 = Rp 28,500.00
0.010 Oh Mandor @ Rp. 110,000.00 = Rp 1,100.00
Sub total : = Rp 29,600.00
Total upah+bahan : = Rp 311,600.00
d 1 m3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr
Bahan An. SNI ( Revisi ) 6.1.1
218.000 Kg Semen portland @ Rp. 2,100.00 = Rp 457,800.00
0.520 m3 Pasir beton @ Rp. 260,000.00 = Rp 135,200.00
0.870 m3 Koral beton @ Rp. 230,000.00 = Rp 200,100.00
Sub total : = Rp 793,100.00
Upah An. SNI ( Revisi ) 6.1.2
1.650 Oh Pekerja @ Rp. 95,000.00 = Rp 156,750.00
0.250 Oh Tukang batu @ Rp. 100,000.00 = Rp 25,000.00
0.025 Oh Kepala tukang @ Rp. 105,000.00 = Rp 2,625.00
0.080 Oh Mandor @ Rp. 110,000.00 = Rp 8,800.00
Sub total : = Rp 193,175.00
Total upah+bahan : = Rp 986,275.00
b 1 m3 Urugan Kembali
Upah An. SNI ( Revisi ) 6.9.1
0.250 Oh Pekerja @ Rp. 95,000.00 = Rp 23,750.00
0.008 Oh Mandor @ Rp. 110,000.00 = Rp 880.00
Sub total : = Rp 24,630.00
Total upah+bahan : = Rp 98,630.00
c 1 m3 Pasir urug
Bahan An. SNI ( Revisi ) 6.11.1
1.200 m3 Pasir urug @ Rp. 235,000.00 = Rp 282,000.00
Sub total : = Rp 282,000.00
Upah An. SNI ( Revisi ) 6.11.2
0.300 Oh Pekerja @ Rp. 95,000.00 = Rp 28,500.00
0.010 Oh Mandor @ Rp. 110,000.00 = Rp 1,100.00
Sub total : = Rp 29,600.00
Total upah+bahan : = Rp 311,600.00
PEKERJAAN ELEKTRIKAL
1 1 Paket Penambahan Daya Listrik dari 2.200 VA menjadi 11.000 VA, termasuk biaya Sertifikat Laik Operasi
bahan
8,800 VA Bea Penyambungan Baru (BP) @ Rp. 500.00 = Rp 4,400,000.00
11,000 VA Uang Jamiman Langganan (UJL) @ Rp. 300.00 = Rp 3,300,000.00
11,000 VA Pembuatan Setrifikat Laik Operasi (SLO) @ Rp. 500.00 = Rp 5,500,000.00
1 buah Materai @ Rp. 10,000.00 = Rp 10,000.00
Sub total : = Rp 13,210,000.00
Upah
11,000 VA Administrasi dan Supervisi Instalasi Listrik @ Rp. 500.00 = Rp 5,500,000.00
Sub total : = Rp 5,500,000.00
Total upah+bahan : = Rp 18,710,000.00
6 1 Buah Pemasangan Lampu Downlight LED 18 watt setara Philips, termasuk rumah lampu uk. 4 inch
Bahan
Lampu Downlight LED 18 watt setara
1.000 buah @ Rp. 235,000.00 = Rp 235,000.00
Philips, termasuk rumah lampu uk. 4 inch
5.000 % Perlengkapan instalasi = Rp 11,750.00
Sub total : = Rp 246,750.00
Upah An. SNI ( Revisi ) 6.4.2
0.166 Oh Pembantu tukang listrik @ Rp. 95,000.00 = Rp 15,770.00
0.166 Oh Tukang listrik @ Rp. 105,000.00 = Rp 17,430.00
0.033 Oh Kepala tukang listrik @ Rp. 110,000.00 = Rp 3,630.00
0.017 Oh Mandor @ Rp. 110,000.00 = Rp 1,826.00
Sub total : = Rp 38,656.00
Total upah+bahan : = Rp 285,406.00
7 1 Buah Pemasangan Lampu Downlight LED 12 watt setara Philips, termasuk rumah lampu uk. 4 inch
Bahan
Lampu Downlight LED 12 watt setara
1.000 buah @ Rp. 215,000.00 = Rp 215,000.00
Philips, termasuk rumah lampu uk. 4 inch
5.000 % Perlengkapan instalasi = Rp 10,750.00
Sub total : = Rp 225,750.00
Upah An. SNI ( Revisi ) 6.4.2
0.166 Oh Pembantu tukang listrik @ Rp. 95,000.00 = Rp 15,770.00
0.166 Oh Tukang listrik @ Rp. 105,000.00 = Rp 17,430.00
0.033 Oh Kepala tukang listrik @ Rp. 110,000.00 = Rp 3,630.00
0.017 Oh Mandor @ Rp. 110,000.00 = Rp 1,826.00
Sub total : = Rp 38,656.00
Total upah+bahan : = Rp 264,406.00
11 1 Titik Pemasangan Instalasi AC (Instalasi Kabel NYM 3x2,5 mm2, MCB dan pipa drain PVC AW)
Bahan
5.000 m Kabel NYM 3x2,5 mm setara Eterna @ Rp. 14,000.00 = Rp 70,000.00
5.000 m Conduit pipa dia. 20 @ Rp. 1,500.00 = Rp 7,500.00
5.000 m Pipa Drain PVC AW dia. 3/4 @ Rp. 42,500.00 = Rp 212,500.00
1.000 buah MCB 10A, 1P setara schneider @ Rp. 88,000.00 = Rp 88,000.00
10.000 % Perlengkapan instalasi = Rp 37,800.00
Sub total : = Rp 415,800.00
Upah
0.750 Oh Pembantu tukang listrik @ Rp. 95,000.00 = Rp 71,250.00
0.500 Oh Tukang listrik @ Rp. 105,000.00 = Rp 52,500.00
0.050 Oh Kepala tukang listrik @ Rp. 110,000.00 = Rp 5,500.00
0.050 Oh Mandor @ Rp. 110,000.00 = Rp 5,500.00
Sub total : = Rp 134,750.00
Total upah+bahan : = Rp 550,550.00
Kab Kendal
No Uraian Satuan Harga Keterangan
(Rp)
UPAH/JASA
1 Pekerja Oh Rp 95,000.00
2 Pembantu tukang listrik Oh Rp 95,000.00
3 Tukang batu Oh Rp 100,000.00
4 Tukang besi Oh Rp 100,000.00
5 Tukang cat Oh Rp 100,000.00
6 Tukang kayu Oh Rp 105,000.00
7 Tukang listrik Oh Rp 105,000.00
8 Kepala Tukang oh Rp 105,000.00
9 Kepala tukang listrik Oh Rp 110,000.00
10 Mandor Oh Rp 110,000.00
11 Biaya Langsir material, pembersihan lahan Ls Rp 650,000.00
12 Sewa Stegger / Scaffolding Set Rp 42,000.00
BAHAN
1 Administrasi dan Supervisi Instalasi Listrik VA Rp 500.00
2 Ampelas Lbr Rp 3,000.00
3 Atap Galvalum tebal 0,4 mm Lbr Rp 62,000.00
4 Bata merah Bh Rp 750.00
5 Batu belah m3 Rp 233,000.00
6 Bea Penyambungan Baru (BP) VA Rp 500.00
7 Besi begel polos dia 6 mm Kg Rp 13,500.00
8 besi beton polos Kg Rp 13,750.00
9 Besi beton polos dia 12 mm Kg Rp 13,500.00
10 Biofilter BF-03 Kapasitas 1000 liter bh Rp 2,300,000.00
11 Box MCB 8 Group inbow setara presto bh Rp 215,000.00
12 Cat dasar Kg Rp 32,500.00
13 Cat dasar kayu Kg Rp 36,000.00
14 Cat eksterior penutup 2x Kg Rp 45,000.00
15 Cat interior penutup 2x Kg Rp 45,000.00
16 Cat penutup kayu Kg Rp 42,000.00
17 Closet duduk setara TOTO SW53JP Bh Rp 2,250,000.00
18 Closet jongkok setara Toto CE7 Bh Rp 310,000.00
19 Conduit pipa dia. 20 m Rp 1,500.00
20 Dolken kayu diameter 8 -10 /400 cm Btg Rp 22,500.00
21 Engsel pintu uk. 4 inch Bh Rp 33,000.00
22 Floor Drain Stainless Steel Bh Rp 145,000.00
23 Genteng Beton Flat bh Rp 8,850.00
24 Grendel stainless steel uk. 3 inch Bh Rp 35,000.00
25 Gypsum tebal 9 mm Lbr Rp 87,000.00
26 Hand Shower setara Onda Bh Rp 161,000.00
27 Hollow galvanis uk.40x40x0,3 mm m' Rp 15,000.00
28 Ijuk kg Rp 13,000.00
29 Insulasi Atap /Alumunium Foil Bubble m2 Rp 14,000.00
30 Jasa anti rayap m2 Rp 40,000.00
31 Kabel NYM 3x1,5 mm setara Eterna m Rp 11,500.00
32 Kabel NYM 3x2,5 mm setara Eterna m Rp 14,000.00
33 Kaca Polos 5 mm m2 Rp 82,000.00
34 Kait angin jendela stainless steel Bh Rp 22,500.00
35 Kalsiplank 200×3000 tebal 8mm Lbr Rp 40,000.00
36 Kawat beton Kg Rp 15,000.00
37 Kayu jati, balok m3 Rp 16,000,000.00
Kab Kendal
No Uraian Satuan Harga Keterangan
(Rp)
38 Kayu jati, papan m3 Rp 16,000,000.00
39 Kayu Perancah m3 Rp 3,000,000.00
40 Kayu terentang/Meranti (MC) m3 Rp 3,000,000.00
Kab Kendal
No Uraian Satuan Harga Keterangan
(Rp)
41 Keramik 30 x 60 cm Polished M2 Rp 115,000.00
42 Keramik uk.30x30, unpolished m2 Rp 88,000.00
43 Keramik uk.50x50, polished m2 Rp 132,000.00
44 Keramik uk.50x50, unpolished m2 Rp 138,000.00
45 Koral beton m3 Rp 230,000.00
46 Kran Dinding bahan stainless setara Onda Bh Rp 73,000.00
47 Kran double/cabang setara Onda Bh Rp 85,000.00
48 Kran wastafel setara TOTO T205MB Bh Rp 230,000.00
49 Kunci tanam termasuk handle Bh Rp 325,000.00
50 Kuwas / roll Bh Rp 14,000.00
Lampu Downlight LED 12 watt setara Philips, termasuk rumah lampu
51 buah Rp 215,000.00
uk. 4 inch
Lampu Downlight LED 18 watt setara Philips, termasuk rumah lampu
52 buah Rp 235,000.00
uk. 4 inch
53 Materai buah Rp 10,000.00
54 MCB 6A, 1P setara schneider bh Rp 83,000.00
55 MCB 10A, 1P setara schneider bh Rp 88,000.00
56 Pipa Drain PVC AW dia. 3/4 bh Rp 42,500.00