Anda di halaman 1dari 88

POLITEKNIK NEGERI SRIWIJAYA

Jalan Srijaya Negara Bukit Besar, Palembang 30139


Telepon 0711-353414 Faksimili 0711-355918
Laman : http//www.polsri.ac.id, Pos El : info@polisriwijaya.ac.id

DESAIN INTERIOR

RENOVASI KANTIN FASUM

POLITEKNIK SRIWIJAYA PALEMBANG

RAB
( RENCANA ANGGARAN BIAYA)
POLITEKNIK NEGERI SRIWIJAYA
Jalan Srijaya Negara Bukit Besar, Palembang 30139
Telepon 0711-353414 Faksimili 0711-355918
Laman : http//www.polsri.ac.id, Pos El :
info@polisriwijaya.ac.id

RENCANA ANGGARAN BIAYA (RAB)

No Uraian Pekerjaan Biaya

1 RENOVASI INTERIOR KANTIN FASILITAS UMUM 199,634,000.00

2 RENOVASI INTERIOR KANTIN DAN BOTH JUALAN KANTI 199,241,000.00

Total 398,875,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : RENOVASI INTERIOR KANTIN FASILITAS UMUM


POLITEKNIK NEGERI SRIWIJAYA
TAHUN : 2023
LOKASI : POLITEKNIK SRIWIJAYA

SUB JUMLAH Jumlah Harga


NO. JENIS PEKERJAAN
(Rp.) (Rp.)

A RENOVASI INTERIOR KANTIN FASILITAS UMUM Rp 179,851,098.00


I PEKERJAAN PERSIAPAN Rp 10,460,178.00
II PEKERJAAN LANGIT-LANGIT (PLAFOND) Rp 13,877,280.00
III PEKERJAAN INSTALASI LISTRIK Rp 9,288,350.00
IV PEKERJAAN FINISHING Rp 28,067,030.00
V PEKERJAAN LAIN-LAIN Rp 39,500,000.00
VII PENGADAAN MEUBELAIR Rp 77,908,260.00
VII PEKERJAAN AKHIR Rp 750,000.00

JUMLAH TOTAL Rp 179,851,098.00


PPN 11 % Rp 19,783,620.78
JUMLAH TOTAL FISIK Rp 199,634,718.78
DIBULATKAN Rp 199,634,000.00
Terbilang
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : RENOVASI INTERIOR KANTIN FASILITAS UMUM
POLITEKNIK NEGERI SRIWIJAYA
TAHUN : 2023
LOKASI : SRIJAYA NEGARA

Harga Satuan Jumlah Harga


NO. JENIS PEKERJAAN Analisa Volume
(Rp,) (Rp,)
A RENOVASI INTERIOR KANTIN FASILITAS UMUM
I PEKERJAAN PERSIAPAN A.4.1.1
1 Pengangkutan Barang Asset Polsri Taksiran 1.00 Ls Rp 5,000,000.00 Rp 5,000,000.00
2 Pekerjaan Pemasangan Skafolding An.2.2.1.19 10.00 m2 Rp 55,000.00 Rp 550,000.00
3 Pekerjaan pengikisan cat lama A.4.7.1.1. 204.00 m2 Rp 24,069.50 Rp 4,910,178.00
Sub Total I Rp 10,460,178.00

II PEKERJAAN LANGIT-LANGIT (PLAFOND) A.4.4.1


1 Pekerjaan pengecatan Plafon Lama A.4.2.1.21 384.00 m2 Rp 36,138.75 Rp 13,877,280.00
Sub Total II Rp 13,877,280.00

III PEKERJAAN INSTALASI LISTRIK


1 Pekerjaan Pemasangan titik nyala Lampu Taksir 6 8.00 Titik Rp 401,298.25 Rp 3,210,390.00
2 Pekerjaan Pemasangan titik nyala stop kontak Taksir 7 8.00 Titik Rp 443,215.75 Rp 3,545,730.00
3 Pekerjaan Lampu downlight 18 watt HDB&HDU 8.00 Bh Rp 59,800.00 Rp 478,400.00
4 Pekerjaan Saklar Double 10 A HDB&HDU 4.00 Bh Rp 44,720.00 Rp 178,880.00
5 Pekerjaan Saklar Tunggal 10 A HDB&HDU 4.00 Bh Rp 29,380.00 Rp 117,520.00
6 Pekerjaan Stop kontak 13 A HDB&HDU 4.00 Bh Rp 40,170.00 Rp 160,680.00
7 Pekerjaan Pemasangan titik nyala stop kontak Ac Taksir 7 2.00 Titik Rp 443,215.75 Rp 886,430.00
8 Pekerjaan Stop kontak AC HDB&HDU 4.00 Bh Rp 100,360.00 Rp 401,440.00
9 Pekerjaan Pasang MCB HDB&HDU 4.00 set Rp 77,220.00 Rp 308,880.00

Sub Total V Rp 9,288,350.00

IV PEKERJAAN FINISHING A.4.7.1


1 Pekerjaan Pengecatan Kolom Interior A.4.7.1.10. 204.00 m2 Rp 47,733.05 Rp 9,737,540.00
1 Pekerjaan Pengecatan Dinding Interior A.4.7.1.10. 384.00 m2 Rp 47,733.05 Rp 18,329,490.00
Sub Total VI Rp 28,067,030.00

V PEKERJAAN LAIN-LAIN
1 Kipas Angin Tornado Taksir 7 6.00 bh Rp 1,500,000.00 Rp 9,000,000.00
2 Pekerjaan pemasangan exhausted fan dinding Taksir 8 4.00 bh Rp 1,150,000.00 Rp 4,600,000.00
3 Rak Display backdrop Kasir Kios ( 5 Unit) Taksir 9 14.00 m2 Rp 1,850,000.00 Rp 25,900,000.00
Sub Total VII Rp 39,500,000.00

VI PENGADAAN MEUBELAIR
1 Pintu Kaca dan Frame Taksir 7 2.00 Unit Rp 2,500,000.00 Rp 5,000,000.00
2 Meja Makan Kantin Taksir 8 24.00 bh Rp 2,650,000.00 Rp 63,600,000.00
3 rak buku & backdrop tv Taksir 9 4.00 m2 Rp 1,850,000.00 Rp 7,400,000.00
5 Sekat Ruang Asset Taksir 10 12.00 m2 Rp 159,021.85 Rp 1,908,260.00
Sub Total VIII Rp 77,908,260.00

VII PEKERJAAN AKHIR


1 Pembersihan akhir LS 1.00 Ls Rp 750,000.00 Rp 750,000.00
Sub Total IX Rp 750,000.00

JUMLAH TOTAL Rp 179,851,098.00


REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : RENOVASI INTERIOR KANTIN DAN BOTH JUALAN KANTIN FASILITAS UMUM
POLITEKNIK NEGERI SRIWIJAYA
TAHUN : 2023
LOKASI : POLITEKNIK SRIWIJAYA

SUB JUMLAH Jumlah Harga


NO. JENIS PEKERJAAN
(Rp.) (Rp.)

B RENOVASI INTERIOR KANTIN DAN BOTH JUALAN KANTIN FASILITAS UMUM Rp 179,497,242.00
I PEKERJAAN PERSIAPAN Rp 4,810,662.00
II PEKERJAAN LANGIT-LANGIT (PLAFOND) Rp 3,931,900.00
III PEKERJAAN KUSEN PINTU Rp 42,480,000.00
IV PEKERJAAN LANTAI DAN SANITASI Rp 36,007,550.00
V PEKERJAAN BOOTH JUALAN Rp 35,489,340.00
VI PEKERJAAN FINISHING Rp 8,019,150.00
VII PEKERJAAN INSTALASI LISTRIK Rp 19,913,640.00
VIII PENGADAAN MEUBELAIR Rp 28,095,000.00
IX PEKERJAAN AKHIR Rp 750,000.00

JUMLAH TOTAL Rp 179,497,242.00


PPN 11 % Rp 19,744,696.62
JUMLAH TOTAL FISIK Rp 199,241,938.62
DIBULATKAN Rp 199,241,000.00
Terbilang
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : RENOVASI INTERIOR KANTIN DAN BOTH JUALAN KANTIN FASILITAS UMUM
POLITEKNIK NEGERI SRIWIJAYA
TAHUN : 2023
LOKASI : SRIJAYA NEGARA

Harga Satuan Jumlah Harga


NO. JENIS PEKERJAAN Analisa Volume
(Rp,) (Rp,)
A RENOVASI INTERIOR KANTIN DAN BOTH JUALAN KANTIN FASILITAS UMUM
I PEKERJAAN PERSIAPAN A.4.1.1
1 Pekerjaan Pemasangan Alat Bantu Skafolding An.2.2.1.19 4.00 m2 Rp 55,000.00 Rp 220,000.00
2 Pekerjaan pembongkaran keramik An.2.2.1.13 8.00 m2 Rp 15,927.50 Rp 127,420.00
3 Pekerjaan pengikisan cat lama A.4.7.1.1. 95.20 m2 Rp 24,069.50 Rp 2,291,416.40
1 Pekerjaan pengikisan cat Lantai lama A.4.7.1.7. 32.00 m2 Rp 67,869.55 Rp 2,171,825.60
Sub Total I Rp 4,810,662.00

II PEKERJAAN LANGIT-LANGIT (PLAFOND) A.4.4.1


1 Pekerjaan pengecatan Plafon Lama A.4.2.1.21 108.80 m2 Rp 36,138.75 Rp 3,931,900.00
Sub Total II Rp 3,931,900.00

III PEKERJAAN KUSEN PINTU HDB&HDU


1 Pintu Rooling door Almunium HDB&HDU 53.10 M2 Rp 800,000.00 Rp 42,480,000.00
Sub Total III Rp 42,480,000.00

IV PEKERJAAN LANTAI DAN SANITASI A.4.4.3


1 Bobokan Lantai Bangunan An.2.2.1.13 40.00 M' Rp 15,927.50 Rp 637,100.00
2 Bobokan Dinding Bangunan An.2.2.1.14 40.00 M' Rp 29,727.50 Rp 1,189,100.00
3 Pekerjaan Pemasangan lantai keramik polish (putih) Uk. 40 cm x 40 cm An.4.4.3.4. 12.00 M2 Rp 251,366.61 Rp 3,016,400.00
4 Pekerjaan Saluran Pipa Air Bersih 1/2 inc A.5.1.1.19. 8.00 M' Rp 30,949.38 Rp 247,600.00
5 Pasangan Kran Air A.5.1.1.19. 8.00 Unit Rp 87,434.50 Rp 699,480.00
5 Pekerjaan Sanitair Air Cuci Piring An.5.1.1.15. 8.00 Unit Rp 208,956.44 Rp 1,671,650.00
6 Tempat Cuci Piring A.5.1.1.12. 1.00 Unit Rp 3,215,486.25 Rp 3,215,490.00
7 Pekerjaan Instalasi Pipa Air Bersih 1/2 inc A.5.1.1.19. 67.00 M' Rp 87,434.50 Rp 5,858,110.00
8 Pemasangan Tedmon 550 Litter 2.00 Unit Rp 2,735,100.00 Rp 5,470,200.00
7 Pemasangan Pompa Air (Jet Pump + Automatic) 1.00 Unit Rp 1,200,000.00 Rp 1,200,000.00
8 Pekerjaan Pemasangan plint keramik ukuran 10 cm x 40 cm polish An.4.4.3.7. 24.00 M' Rp 54,267.60 Rp 1,302,420.00
9 ManHole 60x60 An.4.4.3.7. 10.00 M' Rp 1,150,000.00 Rp 11,500,000.00
Sub Total IV Rp 36,007,550.00

V PEKERJAAN BOOTH JUALAN


1 Pengadaan Both Jualan ls 8.00 Bh Rp 3,550,000.00 Rp 28,400,000.00
2 Pekerjaan Pemasangan titik nyala Lampu Taksir 6 8.00 Titik Rp 401,298.25 Rp 3,210,390.00
3 Pekerjaan Pemasangan titik nyala stop kontak Taksir 7 4.00 Titik Rp 443,215.75 Rp 1,772,860.00
4 Pekerjaan Lampu downlight 18 watt HDB&HDU 8.00 Bh Rp 59,800.00 Rp 478,400.00
5 Pekerjaan Saklar Double 10 A HDB&HDU 2.00 Bh Rp 44,720.00 Rp 89,440.00
6 Pekerjaan Saklar Tunggal 10 A HDB&HDU 2.00 Bh Rp 29,380.00 Rp 58,760.00
7 Pekerjaan Stop kontak 13 A HDB&HDU 4.00 Bh Rp 40,170.00 Rp 160,680.00
8 Pekerjaan Pemasangan titik nyala stop kontak Ac Taksir 7 2.00 Titik Rp 443,215.75 Rp 886,430.00
9 Pekerjaan Stop kontak AC HDB&HDU 2.00 Bh Rp 100,360.00 Rp 200,720.00
10 Pekerjaan Pasang MCB HDB&HDU 3.00 set Rp 77,220.00 Rp 231,660.00

Sub Total V Rp 35,489,340.00

VI PEKERJAAN FINISHING A.4.7.1


1 Pekerjaan Pengecatan Kolom Interior A.4.7.1.10. 72.00 m2 Rp 47,733.05 Rp 3,436,780.00
1 Pekerjaan Pengecatan Dinding Interior A.4.7.1.10. 96.00 m2 Rp 47,733.05 Rp 4,582,370.00
Sub Total VI Rp 8,019,150.00

VII PEKERJAAN INSTALASI LISTRIK


1 Pekerjaan Pemasangan titik nyala Lampu Taksir 6 8.00 Titik Rp 401,298.25 Rp 3,210,390.00
2 Pekerjaan Pemasangan titik nyala stop kontak Taksir 7 8.00 Titik Rp 443,215.75 Rp 3,545,730.00
3 Pekerjaan Lampu downlight 18 watt HDB&HDU 8.00 Bh Rp 59,800.00 Rp 478,400.00
4 Pekerjaan Saklar Double 10 A HDB&HDU 8.00 Bh Rp 44,720.00 Rp 357,760.00
5 Pekerjaan Stop kontak 13 A HDB&HDU 8.00 Bh Rp 40,170.00 Rp 321,360.00
2 Pekerjaan pemasangan exhausted fan dinding LS 8.00 bh Rp 1,500,000.00 Rp 12,000,000.00
Sub Total VII Rp 19,913,640.00
Harga Satuan Jumlah Harga
NO. JENIS PEKERJAAN Analisa Volume
(Rp,) (Rp,)
VIII PENGADAAN MEUBELAIR
1 set meja Jualan Booth LS 8.00 m Rp 650,000.00 Rp 5,200,000.00
2 Maubeler Meja Cuci Piring Kios Jualan LS 8.00 bh Rp 850,000.00 Rp 6,800,000.00
3 Rak Display backdrop Kasir Kios (3 Unit) LS 8.70 m2 Rp 1,850,000.00 Rp 16,095,000.00
Sub Total VIII Rp 28,095,000.00

IX PEKERJAAN AKHIR
1 Pembersihan akhir 1.00 Ls Rp 750,000.00 Rp 750,000.00
Sub Total IX Rp 750,000.00

JUMLAH TOTAL Rp 179,497,242.00


RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : renovasi interior ruang rapar utama
TAHUN : 2023
LOKASI : SRIWIJAYA NEGARA

Harga Satuan Jumlah Harga


NO. JENIS PEKERJAAN Analisa Volume
(Rp,) (Rp,)
B. RENOVASI RUANG RAPAT
I PEKERJAAN BETON A.4.1.1

II PEKERJAAN PEMASANGAN DAN PLESTERAN DINDING A.4.4.1


2 Pekerjaan Pemasangan 1 m2 dinding glass block 20x20 campuran 1 SP : 4 PP An.4.4.1.8 2.00 m2 Rp 958,055.80 Rp 1,916,110.00
3 Pekerjaan. Pemasangan dinding terawang (roster) campuran 1 SP : 4 PP A.4.4.1.23 0.72 m2 Rp 465,568.30 Rp 335,210.00
Sub Total II Rp 2,251,320.00

IV PEKERJAAN LANGIT-LANGIT (PLAFOND) A.4.4.1


1 Pekerjaan pemasangan Rangka Plafond Besi Hollow 40.40.2 A.4.2.1.21 48.00 m2 Rp 140,837.63 Rp 6,760,210.00
2 Pekerjaan Pemasangan 1 m2 langit-langit Plafond PVC + List sambung + List Profil 8 cm Taksir 8 48.00 m2 Rp 202,900.25 Rp 9,739,210.00
Sub Total IV Rp 16,499,420.00
Harga Satuan Jumlah Harga
NO. JENIS PEKERJAAN Analisa Volume
(Rp,) (Rp,)

V PEKERJAAN KUSEN PINTU HDB&HDU


1 Pekerjaan Pembuatan dan pemasangan Kusen dan Pintu besi, Bouvenli + aksesoris lengkap (Type P1) HDB&HDU 4.00 Bh Rp 6,208,125.00 Rp 24,832,500.00
Sub Total V Rp 24,832,500.00

VI PEKERJAAN LANTAI A.4.4.3


1 Pekerjaan Pemasangan lantai keramik polish (putih) Uk. 40 cm x 40 cm An.4.4.3.4. 48.00 m2 Rp 251,366.61 Rp 12,065,600.00
2 Pekerjaan Pemasangan lantai keramik unpolish (warna) ukuran 40 cm x 40 cm An.4.4.3.5. 81.32 m2 Rp 188,464.48 Rp 15,325,930.00
3 Pekerjaan Pemasangan plint keramik ukuran 10 cm x 40 cm polish An.4.4.3.7. 111.84 m' Rp 54,267.60 Rp 6,069,290.00
4 Pekerjaan Pemasangan plint keramik ukuran 10 cm x 40 cm unpolish An.4.4.3.8. 48.00 m' Rp 49,776.95 Rp 2,389,290.00
Sub Total VI Rp 35,850,110.00

VII PEKERJAAN INSTALASI LISTRIK


1 Pekerjaan Pemasangan titik nyala Lampu Taksir 6 21.00 Titik Rp 401,298.25 Rp 8,427,260.00
2 Pekerjaan Pemasangan titik nyala stop kontak Taksir 7 8.00 Titik Rp 443,215.75 Rp 3,545,730.00
3 Pekerjaan Lampu downlight 18 watt HDB&HDU 21.00 Bh Rp 59,800.00 Rp 1,255,800.00
4 Pekerjaan Saklar Double 10 A HDB&HDU 5.00 Bh Rp 44,720.00 Rp 223,600.00
5 Pekerjaan Saklar Tunggal 10 A HDB&HDU 1.00 Bh Rp 29,380.00 Rp 29,380.00
6 Pekerjaan Stop kontak 13 A HDB&HDU 8.00 Bh Rp 40,170.00 Rp 321,360.00
7 Pekerjaan Pemasangan titik nyala stop kontak Ac Taksir 7 8.00 Titik Rp 443,215.75 Rp 3,545,730.00
8 Pekerjaan Stop kontak AC HDB&HDU 8.00 Bh Rp 100,360.00 Rp 802,880.00
9 Pekerjaan Pasang MCB HDB&HDU 3.00 set Rp 77,220.00 Rp 231,660.00
10 Pekerjaan Panarikan kabel antar Ruangan dan anatar gedung Instalasi MCB + upah HDB&HDU 20.00 m Rp 20,800.00 Rp 416,000.00

Sub Total VII Rp 18,799,400.00

VIII PEKERJAAN FINISHING A.4.7.1


1 Pekerjaan Pengecatan Dinding Interior A.4.7.1.10. 328.14 m2 Rp 47,733.05 Rp 15,663,120.00
2 Pekerjaan Pengecatan Dinding Eksterior (Weather Sheld) Warna Terang An. 4.7.1.11. 356.70 m2 Rp 57,271.15 Rp 20,428,620.00
Sub Total VIII Rp 36,091,740.00

IX PEKERJAAN LAIN-LAIN
1 Pekerjaan Pagar Depan Teras Hollow HDB&HDU 25.20 m2 Rp 1,200,000.00 Rp 30,240,000.00
2 Pekerjaan Pengecatan Pagar Hollow A.4.7.1.16. 25.20 m2 Rp 51,865.00 Rp 1,307,000.00
Sub Total IX Rp 31,547,000.00

X PEKERJAAN AKHIR
1 Laporan dan Dokumentasi 1.00 Ls Rp 3,000,000.00 Rp 3,000,000.00
2 Pembersihan Akhir Lapangan 1.00 Ls Rp 2,500,000.00 Rp 2,500,000.00
3 Alat Bantu 1.00 Ls Rp 10,000,000.00 Rp 10,000,000.00
4 Biaya K3 1.00 Ls Rp 1,000,000.00 Rp 1,000,000.00
Sub Total X Rp 16,500,000.00

JUMLAH TOTAL Rp 182,371,490.00


Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG

Data Rencana :
Panjang a (Pa) = 37.00 M'
Panjang (P) = 35.00 M'
Panjang (P1) = 8.00 M'
Panjang (P2) = 8.00 M'
Panjang (P3) = 3.00 M'
Panjang (P4) = 8.00 M'
Panjang (P5) = 8.00 M'
Lebar (L) = 18.00 M'
Lebar 1 (L1) = 9.00 M'
Lebar 2 (L2) = 7.00 M'
Lebar 3 (L3) = 2.00 M'
Lebar 3 (L4) = 0.80 M'
Lebar a1' (La1') = 6.10 M'
Lebar 2' (La2') = 6.10 M'
Tinggi rencana (Tr) = 6.40 M'
900
PEMBANGUNAN GEDUNG BERTINGKAT 2 LANTAI
700 200 Tinggi rencana1 (Tr1) = 4.00 M'
Tinggi rencana 2 (Tr2) = 4.00 M'
K1

K1

K1

K2

10

LANTAI 2
400
800

K1

K1

K2

I. PEKERJAAN BETON
2.1. Pekerjaan Kolom
400

a. Pekerjaan Kolom UtamaUk 40/40 cm (k1)


Tinggi 1' (T1') = 4.00 M'
K1

K1

K1

K2

Lebar 1 Kolom (L1) = 0.40 M'


400

Lebar 2 Kolom (L2) = 0.40 M'


Jumlah kolom = 26.00 Ttk
800

K1

K1

K2

7
400

a. Bekesting
Panjang bekesting = 104.00
K1

K1

K1

K2

Bekesting 2x Pakai
3500
300

300

Luas pekerjaan Bekesting = 83.20 M2


K1

K1

K1

K2

b. Beton Mutu F'c=21,7 Mpa


400

Volume Beton = 16.64 M3


800

K1

K1

K2

c. Pembesian
400

Besi utama 12 D 16
K1

K1

K1

K2

Panjang besi D 16 mm = 4.33 M'


panjang bengkokan 5d = 0.08 M'
400

Jumlah besi per kolom = 12.00 Btg


800

K1

K1

K2

= Ttk
2

Jumlah Kolom 26.00


Panjang besi yang dibutuhkan = 1,350.96 M'
400
K1

K1

K1

K2

Besi Cincin Ø 8 - 15
1

350 350 200


Panjang kolom = 4.00 M'
C
D

A
B

Jumlah balok = 26.00 Ttk


Jarak cincin 15 cm = 0.15 M'
Jumlah Cincin = 694.33 Btg
Panjang besi Ø 8 mm = 1.65 M'
Panjang besi yang dibutuhkan = 1,145.65 M'
(K1) KOLOM UTAMA (40/40)
TUMPUAN LAPANGAN Total Kebutuhan material
Luas Bekesting = 83.20 M2
Volume Beton = 16.64 M3
Panjang Butuh Besi D 16 mm = 1,350.96 M'
Berat Besi D 16 mm per m = 1.58 Kg/m

TULANGAN 12D16 TULANGAN 12D16


Berat Besi D 16 mm = 2,134.52 Kg
CINCIN Ø8-15 CINCIN Ø8-15 Panjang Butuh Besi Ø 8 mm = 1,145.65 M'
BETON MUTU F'c = 21,7 Mpa Berat Besi Ø 8 mm per m = 0.37 Kg/m
Berat Besi Ø 8 mm = 426.75 Kg
Total Berat Besi = 2,561.27 Kg
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
b. Pekerjaan Kolom Teras Uk 30/30 cm (K2)
Tinggi 1' (T1') = 4.00 M'
Lebar 1 Kolom (L1) = 0.30 M'
(K2) KOLOM TERAS (30/30)
TUMPUAN LAPANGAN
Lebar 2 Kolom (L2) = 0.30 M'
Jumlah kolom = 10.00 Unit

a. Bekesting
Panjang bekesting = 40.00 M'
TULANGAN 8D13 TULANGAN 8D13 Bekesting 2x Pakai
CINCIN Ø8-15 CINCIN Ø8-15
Luas pekerjaan Bekesting = 24.00 M2
BETON MUTU F'c = 21,7 Mpa

b. Beton Mutu F'c=21,7 Mpa


Volume Beton = 3.60 M3

c. Pembesian
Besi utama 8 D 13
Panjang besi D 16 mm = 4.32 M'
panjang bengkokan 5d = 0.07 M'
Jumlah besi per kolom = 8.00 Btg
Jumlah Kolom = 10.00 Unit
Panjang besi yang dibutuhkan = 345.20 M'

Besi Cincin Ø 8 - 15
Panjang kolom = 4.00 M'
Jumlah balok = 10.00 Unit
Jarak cincin 15 cm = 0.15 M'
Jumlah Cincin = 267.67 Btg
Panjang besi Ø 8 mm = 1.25 M'
Panjang besi yang dibutuhkan = 334.58 M'

Total Kebutuhan material


Luas Bekesting = 24.00 M2
Volume Beton = 3.60 M3
Panjang Butuh Besi D 13 mm = 345.20 M'
Berat Besi D 13 mm per m = 1.04 Kg/m
Berat Besi D 13 mm = 359.01 Kg
Panjang Butuh Besi Ø 8 mm = 334.58 M'
Berat Besi Ø 8 mm per m = 0.37 Kg/m
Berat Besi Ø 8 mm = 124.63 Kg
Total Berat Besi = 483.64 Kg

1.2. Pekerjaan Ring balok


a. Pekerjaan Ring balok Uk 20/30 cm (RB 2)
Panjang (P) = M'
(RB2) RING BALOK 2 (20/30) Jumlah = Unit
TUMPUAN LAPANGAN TUMPUAN
Lebar = 9.00 M'
Jumlah = 6.00 Unit
Lebar Balok (Lb) = 0.20 M'
Tinggi Balok (Tb) = 0.30 M'
TULANGAN 6D10 TULANGAN 6D10 TULANGAN 6D10 Jumlah = 1.00 ruang
CINCIN Ø8-15 CINCIN Ø8-15 CINCIN Ø8-15
BETON MUTU F'c = 21,7 Mpa

a. Bekesting
Panjang bekesting = 54.00 M'
Panjang bekesting dikurng lebar kolom = 49.80 M'
Bekesting 2x Pakai
Luas pekerjaan Bekesting = 39.84 M2

b. Beton Mutu F'c=21,7 Mpa


Volume Beton = 1.92 M3
Tinggi Balok (Tb) dikurang tinggi plat lanatai
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
c. Pembesian
Besi utama 6 D 10
Panjang besi D 10 mm = 56.45 M'
panjang overlap 40d = 0.40 M'
Jumlah Overlap = 6.00 Btg
panjang bengkokan 5d = 0.05 M'
Jumlah besi per balok = 6.00 Btg
Panjang besi yang dibutuhkan = 338.70 M'

Besi Cincin Ø 8 - 15
Panjang balok = 49.80 M'
Jarak cincin 20 cm = 0.15 M'
Jumlah Cincin = 333.00 Btg
Panjang besi Ø 6 mm = 1.05 M'
Panjang besi yang dibutuhkan = 349.65 M'

Total Kebutuhan material


Luas Bekesting = 39.84 M2
Volume Beton = 1.92 M3
Panjang Butuh Besi Ø 10 mm = 338.70 M'
Berat Besi Ø 10 mm per m = 0.62 Kg/m
Berat Besi Ø 10 mm = 208.87 Kg
Panjang Butuh Besi Ø 8 mm = 349.65 M'
Berat Besi Ø 8 mm per m = 0.37 Kg/m
Berat Besi Ø 8 mm = 130.24 Kg
Total Berat Besi = 339.11 Kg

b Pekerjaan Ring balok Uk 20/40 cm (RB 1)


Panjang (P) = 35.00 M'
Jumlah = 2.00 Unit
Panjang (P) = 35.00 M'
(RB1) RING BALOK 1 (20/40) Jumlah = 1.00 Unit
TUMPUAN LAPANGAN TUMPUAN
Lebar Balok (Lb) = 0.20 M'
Tinggi Balok (Tb) = 0.40 M'
Jumlah = 1.00 ruang

a. Bekesting
TULANGAN 6D13 TULANGAN 6D13 TULANGAN 6D13
CINCIN Ø8-15 CINCIN Ø8-15 CINCIN Ø8-15 Panjang bekesting = 105.00 M'
BETON MUTU F'c = 21,7 Mpa
Panjang bekesting dikurng lebar kolom = 95.10 M'
Bekesting 2x Pakai
Luas pekerjaan Bekesting = 95.10 M2

b. Beton Mutu F'c=21,7 Mpa


Volume Beton = 7.61 M3
Tinggi Balok (Tb) dikurang tinggi plat lanatai

c. Pembesian
Besi utama 6 D 13
Panjang besi D 13 mm = 108.19 M'
panjang overlap 40d = 0.52 M'
Jumlah Overlap = 6.00 Btg
panjang bengkokan 5d = 0.07 M'
Jumlah besi per balok = 6.00 Btg
Panjang besi yang dibutuhkan = 649.11 M'

Besi Cincin Ø 8 - 15
Panjang balok = 95.10 M'
Jarak cincin 20 cm = 0.15 M'
Jumlah Cincin = 635.00 Btg
Panjang besi Ø 6 mm = 1.25 M'
Panjang besi yang dibutuhkan = 793.75 M'
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
Total Kebutuhan material
Luas Bekesting = 95.10 M2
Volume Beton = 7.61 M3
Panjang Butuh Besi Ø 13 mm = 649.11 M'
Berat Besi Ø 13 mm per m = 1.04 Kg/m
Berat Besi Ø 13 mm = 675.07 Kg
Panjang Butuh Besi Ø 8 mm = 793.75 M'
Berat Besi Ø 8 mm per m = 0.37 Kg/m
900 Berat Besi Ø 8 mm = 295.67 Kg
Total Berat Besi = 970.75 Kg
700 200

10
1.3. Pekerjaan Balok Literal/balok diatas kusen pintu dan jendela Uk 12/15 cm

400
BL

BL

Panjang balok = 32.00 M'


800

Lebar balok = 0.12 M'


9
Tinggi balok = 0.15 M'
400
BL

BL

Jumlah balok = 2.00 Unit


8

a. Bekesting
400
BL

BL

Panjang bekesting = 64.00 M'


800

Panjang bekesting dikurng lebar kolom = 56.80 M'


400

Bekesting 2x Pakai
BL

BL

Luas pekerjaan Bekesting = 17.04 M2


6
3500
300

300

b. Beton Mutu F'c=21,7 Mpa


5

Volume Beton = 1.02 M3


400
BL

BL

c. Pembesian
800

Besi utama 4 Ø 10
400
BL

BL

Panjang besi Ø 10 mm = 64.30 M'


panjang bengkokan 5d = 0.05 M'
3

Jumlah besi per kolom = 6.00 Btg


400
BL

BL

Panjang besi yang dibutuhkan = 385.80 M'


800

Besi Cincin Ø 8 - 15
400
BL

BL

Panjang balok L1 = 56.80 M'


Jarak cincin 15 cm = 0.15 M'
1

Jumlah Cincin = 378.67 Btg


350 350 200
C
D

A
B

Panjang besi Ø 8 mm = 0.59 M'


Panjang besi yang dibutuhkan = 223.41 M'

(BL) BALOK LITERAL (12/15)


Total Kebutuhan material
TUMPUAN LAPANGAN TUMPUAN
Luas Bekesting = 17.04 M2
Volume Beton = 1.02 M3
Panjang Butuh Besi Ø 10 mm = 385.80 M'
Berat Besi Ø 10 mm per m = 0.62 Kg/m
TULANGAN 6Ø10 TULANGAN 6Ø10 TULANGAN 6Ø10 Berat Besi Ø 10 mm = 237.91 Kg
CINCIN Ø8-15 CINCIN Ø8-15 CINCIN Ø8-15
BETON MUTU F'c = 21,7 Mpa Panjang Butuh Besi Ø 8 mm = 223.41 M'
Berat Besi Ø 8 mm per m = 0.37 Kg/m
Berat Besi Ø 8 mm = 83.22 Kg
Total Berat Besi = 321.13 Kg

1.4. Pekerjaan Balok dan kolom Tebeng Layar Uk 12/12 cm


Panjang balok = 5.40 M'
Lebar balok = 0.12 M'
Tinggi balok = 0.12 M'
Jumlah balok = 4.00 Unit

Tinggi kolom = 2.66 M'


Lebar 1 (L1) kolom = 0.12 M'
Lebar 2 (L2) kolom = 0.12 M'
Jumlah balok = 2.00 Unit

Bekesting
Panjang bekesting = 26.92 M'
Luas pekerjaan Bekesting = 6.46 M2

Beton Mutu F'c=21,7 Mpa


Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
Volume Beton = 0.39 M3
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG

Pembesian
Besi utama 4 Ø 10
Panjang besi Ø 10 mm = 27.52 M'
panjang bengkokan 5d = 0.05 M'
Jumlah besi per kolom = 4.00 Btg
Panjang besi yang dibutuhkan = 110.08 M'

Besi Cincin Ø 8 - 15
Panjang balok L1 = 26.92 M'
Jarak cincin 15 cm = 0.15 M'
Jumlah Cincin = 180.47 Btg
Panjang besi Ø 8 mm = 0.33 M'
Panjang besi yang dibutuhkan = 59.55 M'

Total Kebutuhan material


Luas Bekesting = 6.46 M2
Volume Beton = 0.39 M3
Panjang Butuh Besi Ø 10 mm = 110.08 M'
Berat Besi Ø 10 mm per m = 0.62 Kg/m
Berat Besi Ø 10 mm = 67.88 Kg
Panjang Butuh Besi Ø 8 mm = 59.55 M'
Berat Besi Ø 8 mm per m = 0.37 Kg/m
Berat Besi Ø 8 mm = 22.18 Kg
Total Berat Besi = 90.07 Kg

II. PEKERJAAN PEMASANGANDAN PLESTERAN DINDING


2.1. Pekerjaan Pemasangan dinding bata merah cm tebal 1/2 batu campuran 1 SP : 4 PP
Dinding
Panjang (P) = 31.40 M'
Jumlah = 1.00 Unit
Panjang (P) = 28.40 M'
Jumlah = 1.00 Unit
Total Panjang (P) = 59.80 M'
Tinggi 1' (T1') = 3.45 M'

Lebar = 6.20 M'


Jumlah = 6.00 Unit
Total Panjang (P) = 37.20 M'
Tinggi 1' (T1') = 3.55 M'
Luas pekerjaan pemasangan dinding = 338.37 M2

Tebeng Layar
Lebar 1 (L1) = 10.88 M'
Tinggi (T) = 2.60 M'
Jumlah = 2.00 Unit
Luas pekerjaan pemasangan Tebeng layar = 28.29 M2

Dikurang Pasangan Pintu dan Jendela


Pekerjaan glass block = 2.00 M2
Type P1 = 10.80 M2
Type J2 = 8.10 M2
Type J3 = 36.00 M2
Luas Pasangan Pintu dan Jendela = 56.90 M2

Total Luas pekerjaan pemasangan dinding bata lubang = 309.76 M2

2.2. Pekerjaan Pemasangan 1 m2 dinding glass block 20x20 campuran 1 SP : 4 PP


Panjang (P) = 0.20 M'
Lebar (L) = 0.20 M'
Jumlah = 50.00 Unit

Luas pekerjaan pemasangan dinding terawang (roster) = 2.00 M2


Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG

2.3. Pekerjaan. Pemasangan dinding terawang (roster) campuran 1 SP : 4 PP


Panjang (P) = 0.60 M'
Lebar (L) = 0.40 M'
Tinggi roster = 0.18 M'
Jumlah = 4.00 Unit

Luas pekerjaan pemasangan dinding terawang (roster) = 0.72 M2

2.4. Pekerjaan Plesteran campuran 1 SP : 4 PP tebal 15 mm


Sama dengan luas pasangan dinding dikali 2
Tebal plesteran = 0.02 M'
Untuk tebeng layar dikali 1
Ditambah luas Kolom Utama dan Praktis
Luas pekerjaan plesteran = 590.51 M2

III. PEKERJAAN PENUTUP ATAP


900 3.1. Pekerjaan pemasangan Rangka Atap
Panjanga a (Pa) = 37.00 M'
700 200

Lebar a1 (La1) = 6.10 M'


10

Lebar a2 (La2) = 6.10 M'


400

Luas Pemasangan Rangka Atap = 451.40 M2


800

3.2. Pekerjaan Pemasangan 1 m2 Atap Zincalume (t.0,35 mm)


400

Panjang a (Pa) + Overlap = 37.10 M'


8

Lebar a1 (La1) + Overlap = 6.20 M'


400

Lebar a2 (La2) + Overlap = 6.20 M'


800

Luas Pemasangan Penutup Atap = 460.04 M2


7
400

3.3. Pekerjaan Pemasangan 1 m' nok aluminium


6

Panjang Atap (Pa) = 37.10 M'


3600
400

400

Panjang Pemasangan Bubungan/ Nok Atap = 37.10 M'


5

3.4. Pekerjaan pemasangan Lisplank kalsiplank


400

Panjang a (Pa) = 37.00 M'


800

Lebar a1 (La1) = 6.10 M'


400

Lebar a2 (La2) = 6.10 M'


Tinggi Lisplank = 0.20 M'
3

Panjang Pemasangan Lisplank = 98.40 M'


400

Luas Lisplank = 19.68 M2


800

2
400

3.5. Pekerjaan pemasangan Rangka Atap Teras Depaan dan Belakang Lanatai 1
Panjanga a (Pa) = 42.00 M'
1

350 350 200 Lebar a1 (La1) = 1.40 M'


Jumlah = 2.00 Unit
C
D

A
B

Luas Pemasangan Rangka Atap = 117.60 M2

3.6. Pekerjaan Pemasangan 1 m2 Atap Zincalume (t.0,35 mm)


Panjang a (Pa) + Overlap = 42.10 M'
Lebar a1 (La1) + Overlap = 1.50 M'
Jumlah = 2.00 Unit
Luas Pemasangan Penutup Atap = 147.35 M2

3.7. Pekerjaan pemasangan Lisplank kalsiplank


Panjang a (Pa) = 43.40 M'
Jumlah = 2.00 M'
Tinggi Lisplank = 0.20 M'
Panjang Pemasangan Lisplank = 86.80 M'
Luas Lisplank = 17.36 M2

IV. PEKERJAAN LANGIT-LANGIT (PLAFOND)


4.1. Pekerjaan pemasangan Rangka Plafond Besi Hollow 40.40.2
a Ruang Dalam Kelas
Panjang (P) = 7.88 M'
Lebar 1 (L1) = 6.88 M'
Jumlah ruang = 4.00 Ruang
Luas pemasangan Ruang kelas = 216.86 M2
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
b Ruang Dalam Kelas
Panjang (P) = 2.88 M'
Lebar 1 (L1) = 6.88 M'
Jumlah ruang = 1.00 Ruang
Luas pemasangan Ruang kelas = 19.81 M2

c Teras Depan
Panjang (P) = 35.00 M'
Lebar 1 (L1) = 3.30 M'
Luas pemasangan Teras Depan = 115.50 M2

d Teras Belakang
Panjang (P) = 35.00 M'
Lebar 1 (L1) = 1.00 M'
Luas pemasangan Teras Belakang = 35.00 M2

e Teras Samping Kiri dan Kanan


Lebar a1' (La1') = 6.10 M'
Lebar 2' (La2') = 6.10 M'
Lebar 1 (L1) = 1.00 M'
Jumlah Teras = 2.00 Unit
Luas pemasangan Teras Samping = 24.40 M2

Luas pemasangan pemasangan Rangka Plafond Besi


= 411.57 M2
Hollow 40.20.2

Pekerjaan Pemasangan 1 m2 langit-langit Plafond PVC + List sambung + List Profil 8


4.2.
cm
Luas pemasangan kalsiboard sama dengan luas pemasangan Rangka Plafond
Luas pemasangan kalsiboard = 411.57 M2

V. PEKERJAAN KAYU KUSEN PINTU DAN JENDELA


Pekerjaan Pembuatan dan pemasangan Kusen dan Pintu besi, Bouvenli + aksesoris
5.1.
lengkap (Type P1)
Tinggi Kusen (H) = 2.70 M'
Lebar Kusen = 1.00 M'
Jumlah Kusen Pintu = 4.00 Bh
Luas Kusen Pintu = 10.80 M2

Pekerjaan Pembuatan dan pemasangan Kusen Jendela Aluminium Ventilasi +


5.2.
Sealent (Type J2)
Tinggi Kusen (H) = 1.50 M'
Lebar Kusen = 1.35 M'
Jumlah Kusen Pintu = 4.00 Bh
Luas Kusen Jendela = 8.10 M2

Pekerjaan Pembuatan dan pemasangan Kusen Jendela Aluminium Ventilasi +


5.3.
Sealent (Type J3)
Tinggi Kusen (H) = 1.50 M'
Lebar Kusen = 2.00 M'
Jumlah Kusen Pintu = 12.00 Bh
Luas Kusen Jendela = 36.00 M2

VI. PEKERJAAN LANTAI


6.1. Pekerjaan Pemasangan lantai keramik polish (putih) Uk. 40 cm x 40 cm
a Panjang (P) = 7.88 M'
Lebar 1 (L1) = 6.60 M'
Jumlah ruang = 4.00 Ruang
Luas pekerjaan pemasangan lantai keramik putih Uk.
= 208.03 M2
40 x 40 cm
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
Pekerjaan Pemasangan Dinding keramik polish (putih) Uk. 40 cm x 40 cm
c
(Podium)
Panjang (P) = 6.80 M'
Tinggi = 0.20 M'
Jumlah ruang = 4.00 Ruang
Luas pekerjaan pemasangan lantai keramik putih Uk.
= 5.44 M2
40 x 40 cm

Total Luas pekerjaan pemasangan lantai keramik putih


= 213.47 M2
Uk. 40 x 40 cm

6.2. Pekerjaan Pemasangan lantai keramik unpolish (warna) ukuran 40 cm x 40 cm


a Ruang Tangga
Panjang (P) = 2.88 M'
Lebar 2 (L2) = 1.50 M'
Luas pekerjaan pemasangan lantai keramik warna Uk.
= 4.32 M2
40 x 40 cm

b Teras Depan
Panjang (P) = 35.00 M'
Lebar 2 (L2) = 2.20 M'
Luas pekerjaan pemasangan lantai keramik warna Uk.
= 77.00 M2
40 x 40 cm

Total Luas pekerjaan pemasangan lantai keramik


= 81.32 M2
warna Uk. 40 x 40 cm

6.3. Pekerjaan Pemasangan plint keramik ukuran 10 cm x 40 cm polish


a Panjang (P) = 7.88 M'
Jumlah = 2.00 Unit
Lebar 1 (L1) = 6.60 M'
Jumlah = 2.00 Unit
Jumlah ruang = 4.00 Ruang
Dikurangi pasangan Kusen pintu
Jumlah Pintu = 4.00 M'
Lebar Kusen pintu = 1.00 M'
Panjang Pek. Pemasangan plint keramik polish ukuran
= 111.84 M'
10 cm x 40 cm

6.4. Pekerjaan Pemasangan plint keramik ukuran 10 cm x 40 cm unpolish


Panjang (P) = 52.00 M'
Dikurangi pasangan Kusen pintu
Jumlah Pintu = 4.00 M'
Lebar Kusen pintu = 1.00 M'
Panjang Pek. Pemasangan plint keramik unpolish
= 48.00 M'
ukuran 10 cm x 40 cm

VII. PEKERJAAN INSTALASI LISTRIK


7.1. Pekerjaan Pemasangan titik nyala Lampu = 21.00 Titik
7.2. Pekerjaan Pemasangan titik nyala stop kontak = 8.00 Titik
7.3. Pekerjaan Lampu downlight 18 watt = 21.00 Titik
7.4. Pekerjaan Saklar Double 10 A = 5.00 Bh
7.5. Pekerjaan Saklar Tunggal 10 A = 1.00 Bh
7.6. Pekerjaan Stop kontak 13 A = 8.00 Bh
7.7. Pekerjaan Pemasangan titik nyala stop kontak Ac = 8.00 Titik
7.8. Pekerjaan Stop kontak AC = 8.00 Bh
7.9. Pekerjaan Pasang MCB = 3.00 Set
Pekerjaan Panarikan kabel antar Ruangan dan anatar
7.10. = 20.00 M'
gedung Instalasi MCB + upah
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG
VIII. PEKERJAAN FINISHING
8.1. Pekerjaan Pengecatan Dinding Interior
Dinding
Panjang (P) = 7.88 M'
Jumlah = 2.00 Unit
Lebar 1 (L1) = 5.80 M'
Jumlah = 2.00 Unit
Tinggi 1' (T1') = 3.50 M'
Jumlah Ruang = 4.00 Ruang
Luas Pengecatan Dinding Interior = 383.04 M2

Dikurang Pasangan Pintu dan Jendela


Type P1 = 10.80 M2
Type J2 = 8.10 M2
Type J3 = 36.00 M2
Luas Pasangan Pintu dan Jendela = 54.90 M2

Total Luas pekerjaan Pengecatan Dinding Interior = 328.14 M2

8.2. Pekerjaan Pengecatan Dinding Eksterior (Weather Sheld) Warna Terang


Dinding
Panjang (P) = 35.00 M'
Jumlah = 2.00 Unit
Lebar 1 (L1) = 7.00 M'
Jumlah = 4.00 Unit
Tinggi 1' (T1') = 3.50 M'
Luas PengecatanEksterior (Weather Sheld) Warna
= 343.00 M2
Terang

Tebeng Layar
Lebar 1 (L1) = 11.00 M'
Tinggi (T) = 2.60 M'
Jumlah = 2.00 Unit
Luas pekerjaan pemasangan Tebeng layar = 28.60 M2

Kolom Teras
Lebar 30x 30 = 1.20 M'
Tingg = 3.50 M'
Jumlah = 10.00 Unit
Luas pengecatankolom teras sama dengan plesteran
= 42.00 M2
kolom

Dikurang Pasangan Pintu dan Jendela


Pekerjaan glass block = 2.00 M2
Type P1 = 10.80 M2
Type J2 = 8.10 M2
Type J3 = 36.00 M2
Luas Pasangan Pintu dan Jendela = 56.90 M2

Total Luas pekerjaan Pengecatan Dinding Eksterior


= 356.70 M2
(Weather Sheld) Warna Terang

8.3. Pekerjaan pengecatan Lisplank Kalsiplank


Sama dengan Luas Pasangan Lisplangk
Luas pekerjaan pengecatan Lisplank = 37.04 M2

IX. PEKERJAAN LAIN-LAIN


9.1. Pekerjaan Pagar Depan Teras Hollow
Panjang = 21.00 M'
Tinggi = 1.20 M'
Luas Pagar Depan Teras = 25.20 M2

9.2. Pekerjaan Pengecatan Pagar Hollow


Panjang = 21.00 M2
Tinggi = 1.20 M2
Luas Pagar Depan Teras = 25.20 M'
Take Of Sheet
Kegiatan RENOVASI INTERIOR RUANG DIREKTUR POLSRI PALEMBANG

X. PEKERJAAN AKHIR
10.1. Laporan dan Dokumentasi = 1.00 Ls
10.2. Pembersihan Akhir Lapangan = 1.00 Ls
10.3. Alat Bantu = 1.00 Ls
10.4. Biaya K3 = 1.00 Ls
DHSP
DAFTAR HARGA SATUAN PEKERJAAN
TAHUN 2022 - KOTA PALEMBANG

ANALISA JENIS PEKERJAAN SATUAN HARGA (RP)


A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
A.2.2.1.2 Pembuatan 1 m2 pagar sementara dari seng gelombang tinggi 2 meter m2 484,209.80
A.2.2.1.4 Pengukuran dan Pemasangan 1 m' Bouwplank m 84,523.85
A.2.2.1.5 Pembuatan 1 m2 kantor sementara lantai plesteran m2 1,759,336.70
A.2.2.1.7 Pembuatan 1 m2 gudang semen dan peralatan m2 1,306,751.90
A.2.2.1.8 Pembuatan 1 m2 bedeng pekerja m2 1,367,650.15
A.2.2.1.9 Pembersihan dan perataan lapangan 1 m2 m2 24,437.50
A.2.2.1.10 Pembuatan 1 m2 Steger/perancah dari bambu m2 626,570.60
A.2.2.1.11 Pembuatan 1 buah kotak adukan ukuran 40cm x 50cm x 25cm bh 190,895.40
A.2.2.1.13 Pembongkaran 1m3 beton bertulang m3 1,981,783.50
A.2.2.1.14 Pembongkaran 1m3 dinding tembok bata m3 990,891.75
A.2.2.1.15 Pembuatan 1 m2 pagar kawat jaring galvanis panjang 240 cm m2 59,335.29
An.2.2.1.12 Pemasangan 1 unit scafolding (sewa) unit 46,442.75
An.2.2.1.13 Pembongkaran 1 m2 Lantai Keramik m2 15,927.50
An.2.2.1.14 Pembongkaran 1 m2 Dinding Bata m2 29,727.50
An.2.2.1.15 Pembongkaran 1 m2 Plesteran m2 29,727.50
An.2.2.1.16 Pembongkaran 1 m2 Atap Genteng m2 4,887.50
An.2.2.1.17 Pembongkaran 1 m2 Atap Seng/Asbes m2 11,649.50
An.2.2.1.18 Pembongkaran 1 m2 Rangka Atap Kuda-kuda Kayu m2 45,137.50
An.2.2.1.19 Pembongkaran 1 m2 Plafond + rangka m2 9,775.00
An.2.2.1.20 Pembongkaran 1 m3 Pasangan Batu Kali m3 520,375.00
An.2.2.1.21 Pembongkaran 1 m2 Kusen Pintu m2 159,275.00
An.2.2.1.22 Pembongkaran 1 m2 Daun Pintu m2 159,275.00
An.2.2.1.23 Pembongkaran 1 m2 Rabat Beton m2 7,538.25
An.2.2.1.24 Pembongkaran 1 m2 Kaso & Reng Kayu m2 19,966.88
An.2.2.1.25 Pembersihan Akhir Lapangan 1 m2 m2 18,328.13

A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1 Menggali 1 m3 tanah biasa sedalam 1 m m3 108,818.75
A.2.3.1.2 Menggali 1 m3 tanah biasa sedalam 2 m m3 133,773.75
A.2.3.1.3 Menggali 1 m3 tanah keras sedalam 1 m m3 144,808.00
A.2.3.1.6 Menggali 1 m3 tanah lumpur sedalam 1 m m3 175,173.75
A.2.3.1.7 Pengerjaan stripping 1 m2 tanah tebing setinggi 1 m m2 7,963.75
A.2.3.1.8 Pembuangan 1 m3 tanah sejauh 30 meter m3 47,667.50
A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah m3 79,637.50
A.2.3.1.10 Pemadatan tanah 1 m3 tanah (per 20 cm) m3 79,637.50
A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug m3 188,427.50
A.2.3.1.14 Pengurugan 1 m3 sirtu padat m3 158,498.75
A.2.3.1.15. Pengurugan 1 m3 tanah urug m3 147,458.75

A.3.2.1 HARGA SATUAN PEKERJAAN PONDASI


A.3.2.1.1 Pemasangan 1 m3 pondasi batu kali campuran 1 SP: 3 PP m3 1,454,800.60
A.3.2.1.2 Pemasangan 1 m3 pondasi batu kali campuran 1 SP: 4 PP m3 1,394,617.65
An.3.2.1.19 Pemasangan 1 m3 pondasi batu bata (5x11x22) cm campuran 1 SP : 4 PP m3 1,419,013.64
An.3.2.1.20 Pemasangan 1 m3 pondasi batu bata (5x11x22) cm campuran 1 SP: 3 PP m3 1,473,195.81
An.3.2.1.21 1 m2 pasang cerucup gelam untuk pondasi (p.1,5m-20 cm) m2 129,720.00
An.3.2.1.22 Pemasangan 1 m3 Rollag batu bata merah (5x11x22) cm campuran 1 SP : 4 PP m3 1,742,330.50

A.4.1.1 HARGA SATUAN PEKERJAAN BETON


A.4.1.1.2 Membuat 1 m3 beton mutu F'c=9,8 Mpa m3 1,286,962.95
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu F'c=7,4 Mpa, slump (3-6) cm, w/c=0,87 m3 1,222,215.56
A.4.1.1.5 Membuat 1 m3 beton mutu F'c=14,5 Mpa, slump (120±20) mm m3 1,370,382.37
A.4.1.1.7 Membuat 1 m3 beton mutu F'c=19,3 Mpa m3 1,446,457.06
A.4.1.1.8 Membuat 1 m3 beton mutu F'c=21,7 Mpa m3 1,464,511.78
A.4.1.1.10 Membuat 1 m3 beton mutu F'c=26,4 Mpa m3 1,505,009.47
A.4.1.1.12 Membuat 1 m3 beton mutu F'c=31,2 Mpa m3 1,554,092.74
A.4.1.1.17 Pembesian 1 kg dengan besi polos atau besi ulir kg 19,194.08
A.4.1.1.19 Pemasangan 1 kg jaring kawat baja (wiremesh) kg 15,790.65
A.4.1.1.20 Pemasangan 1 m2 bekesting untuk pondasi m2 235,888.00
A.4.1.1.21 Pemasangan 1 m2 bekesting untuk sloof m2 248,825.50
A.4.1.1.22 Pemasangan 1 m2 bekesting untuk kolom m2 413,367.50
A.4.1.1.23 Pemasangan 1 m2 bekesting untuk balok m2 421,130.00
A.4.1.1.24 Pemasangan 1 m2 bekesting untuk lantai m2 478,687.50
A.4.1.1.25 Pemasangan 1 m2 bekesting untuk dinding m2 419,200.00
A.4.1.1.26 Pemasangan 1 m2 bekesting untuk tangga m2 336,315.00
A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton m2 95,600.00
A.4.1.1.35 Membuat 1 m' kolom praktis beton bertulang (11x11) cm m 96,783.79
A.4.1.1.36 Membuat 1 m' ring balok beton bertulang (10x15) cm m 117,186.21

II - 23
ANALISA JENIS PEKERJAAN SATUAN HARGA (RP)

A.4.2.1 HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM


A.4.2.1.1 Pemasangan 1 kg besi profil kg 47,121.25
A.4.2.1.2 Pemasangan 1 kg rangka kuda-kuda baja IWF kg 43,153.75
A.4.2.1.3 Pengerjaan 100 kg pekerjaan perakitan kg 89,763.25
A.4.2.1.4 Pembuatan 1 m2 pintu besi plat baja tebal 2 mm rangkap, rangka baja siku m2 1,010,936.25
A.4.2.1.5 Pengerjaan 10 cm pengelasan dengan las listrik cm 25,972.75
A.4.2.1.8 Pemasangan 1 m2 pintu lipat (folding door) bahan plastik/PVCt. 0,8 mm m2 (1,146,906.50)
A.4.2.1.11 Pemasangan 1 m kusen pintu aluminium m 112,594.78
A.4.2.1.12 Pemasangan 1 m2 pintu aluminium strip lebar 8 cm m2 1,008,867.00
A.4.2.1.13 Pemasangan 1 m2 pintu kaca rangka aluminium m2 1,440,360.05
A.4.2.1.15 Pemasangan 1 m2 terali besi strip (2x3) mm m2 810,081.17
A.4.2.1.18 Pemasangan 1 m' talang datar/jurai seng bjls 28 lebar 90 cm m 190,297.98
Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60x120cm, dinding
A.4.2.1.20 m2 140,837.63
partisi
A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 40x40.2mm, modul 60x60cm, plafon m2 181,993.25

A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 2
A.4.4.1.1 m2 345,899.30
PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 3
A.4.4.1.2 m2 329,874.51
PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 4
A.4.4.1.3 m2 319,374.09
PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1
A.4.4.1.7 m2 167,876.31
SP : 2 PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1
A.4.4.1.8 160,456.79
SP : 3 PP
Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1
A.4.4.1.9 m2 156,098.70
SP : 4 PP
A.4.4.1.23 Pemasangan 1 m2 dinding terawang (roster) 12x11x24 campuran 1 SP : 4 PP m2 465,568.30
An.4.4.1.6 Pemasangan 1 m2 dinding roster keramik 30x30 campuran 1 SP : 4 PP m2 1,234,292.70
An.4.4.1.7 Pemasangan 1 m2 dinding roster keramik 20x20 campuran 1 SP : 4 PP m2 1,317,143.30
An.4.4.1.8 Pemasangan 1 m2 dinding glass block 20x20 campuran 1 SP : 4 PP m2 958,055.80

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2 Pemasangan 1 m2 plesteran 1 SP : 2 PP tebal 15 mm m2 95,938.44
A.4.4.2.3 Pemasangan 1 m2 plesteran 1 SP : 3 PP tebal 15 mm m2 92,294.71
A.4.4.2.4 Pemasangan 1 m2 plesteran 1 SP : 4 PP tebal 15 mm m2 89,861.32
A.4.4.2.13 Pemasangan 1 m2 plesteran 1 SP : 1 PP tebal 20 mm m2 128,378.69
A.4.4.2.14 Pemasangan 1 m2 plesteran 1 SP : 3 PP tebal 20 mm m2 102,305.95
A.4.4.2.15 Pemasangan 1 m2 plesteran 1 SP : 4 PP tebal 20 mm m2 120,240.60
A.4.4.2.19 Pemasangan 1 m2 berapen 1 SP : 5 PP tebal 15 mm m2 50,968.98
A.4.4.2.20 Pemasangan 1 m' plesteran skonig 1 SP : 3 PP lebar 10 cm m' 96,785.15
A.4.4.2.23 Pemasangan 1 m2 plesteran ciprat 1 SP : 2 PP m2 73,374.65
A.4.4.2.26 Pemasangan 1 m2 finishing siar pasangan batu kali campuran 1 SP : 2 PP m2 88,029.60
A.4.4.2.27 Pemasangan 1 m2 acian m2 55,699.10

A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


A.4.4.3.35 Pemasangan 1 m2 lantai keramik putih ukuran 30 cm x 30 cm m2 371,584.73
A.4.4.3.36 Pemasangan 1 m2 lantai keramik KM/WC ukuran 20 cm x 20 cm m2 302,122.49
A.4.4.3.38 Pemasangan 1 m2 lantai keramik warna ukuran 30 cm x 30 cm m2 292,388.14
An.4.4.3.4. Pemasangan 1 m2 lantai keramik polish (putih) ukuran 40 cm x 40 cm m2 251,366.61
An.4.4.3.5. Pemasangan 1 m2 lantai keramik Unpolish ukuran 40 cm x 40 cm m2 188,464.48
An.4.4.3.6. Pemasangan 1 m' plint keramik ukuran 10 cm x 30 cm m' 57,447.89
An.4.4.3.7. Pemasangan 1 m' plint keramik ukuran 10 cm x 40 cm polish (putih) m' 56,062.42
An.4.4.3.8. Pemasangan 1 m' plint keramik ukuran 10 cm x 40 cm unpolish m' 49,776.95
An.4.4.3.9. Pemasangan 1 m2 dinding keramik warna ukuran 20 cm x 25cm m2 249,765.47
An.4.4.3.10. Pemasangan 1 m2 dinding keramik putih ukuran 20 cm x 25 cm m2 249,765.47
An.4.4.3.11. Pemasangan 1 m2 dinding batu palimanan + anti lumut (vernis) m2 479,083.82
An.4.4.3.12. Pemasangan 1 m' Step nosing Keramik 10 x 60 cm m' 103,293.16

A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


A.4.5.1.1 Pemasangan 1 m2 langit-langit asbes semen (tebal 4 mm, 5 mm, 6 mm) m2 101,886.55
Pemasangan 1 m2 langit-langit triplek ukuran (120 x 240) cm (tebal 3 mm, 4 mm, 6
A.4.5.1.5 m2 72,712.78
mm)
Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm (tebal 9
A.4.5.1.7 m2 75,897.70
mm)
A.4.5.1.9 Pemasangan 1 m' list langit-langit kayu profil m 39,077.18
An.4.5.1.5 Pemasangan 1 m' list langit-langit gypsum profil m 33,909.44
An.4.5.1.6 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120 x 240 x 9) mm (tebal 3,5 mm) m 69,021.85
A.4.5.1.9a Pemasangan 1 m' list langit-langit kayu profil lebar 4 cm m 22,140.41

II - 24
ANALISA JENIS PEKERJAAN SATUAN HARGA (RP)
A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
A.4.5.2.11 Pemasangan 1 m2 atap asbes gelombang 0.92 m x 1.80 m x 5 mm m2 130,710.15
A.4.5.2.22 Pemasangan 1 m' nok asbes m 107,423.80
A.4.5.2.32 Pemasangan 1 m2 genteng metal Ukuran 80 X 77 Atap m2 150,416.55
A.4.5.2.37 Pemasangan 1 m' nok genteng metal m 107,927.50
A.4.5.2.39 Pemasangan 1 m2 atap seng gelombang m2 83,446.30
A.4.5.2.40 Pemasangan 1 m' nok atap seng m 53,376.10
A.4.5.2.41 Pemasangan 1 m2 Atap Zincalume (t.0,35 mm) m2 163,971.60
A.4.5.2.42 Pemasangan 1 m' nok aluminium m 111,271.70
A.4.5.2.43 Pemasangan 1 m2 aluminium foil m2 48,093.00

4.6.1 HARGA SATUAN PEKERJAAN KAYU


A.4.6.1.2 Pembuatan dan Pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II m3 11,523,230.00
A.4.6.1.5 Pembuatan dan pemasangan 1 m2 daun pintu panel kayu klas II m2 1,015,277.50
A.4.6.1.6 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca Kayu Kelas II m2 761,714.00
Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup (lebar
A.4.6.1.7 m2 739,692.65
sampai 90 cm)
A.4.6.1.10 Pemasangan 1 m2 jalusi kusen, kayu kelas II m2 918,338.25
A.4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 meter m3 9,721,778.00
A.4.6.1.15 Pemasangan 1 m3 konstruksi gordeng, kayu kelas II m3 10,149,411.25
A.4.6.1.16 Pemasangan 1 m2 rangka atap genteng keramik, kayu kelas II m2 323,178.75
A.4.6.1.19 Pemasangan 1 m2 rangka langit-langit (50x100) cm, kayu kelas III m2 151,472.25
A.4.6.1.20 Pemasangan 1 m2 rangka langit-langit (60x60) cm, III m2 147,717.50
A.4.6.1.21 Pemasangan 1 m' lisplank ukuran (3x20) cm, kayu kelas II m' 118,041.75
A.4.6.1.22 Pemasangan 1 m' lisplank ukuran (3x30) cm, kayu kelas II m 119,122.75
A.4.6.1.23 Pemasangan 1 m2 rangka dinding pemisah (60x120) cm kayu kelas III m2 211,324.00
A.4.6.1.25 Pemasangan 1 m2 rangka dinding pemisah plywood rangkap, rangka kayu kelas II m2 357,972.00
A.4.6.1.26 Pemasangan 1 m2 dinding lambrisering dari papan kayu kelas II m2 509,294.75
A.4.6.1.27 Pemasangan 1 m2 dinding lambrisering dari plywood ukuran (120x240) cm m2 57,965.75
An.4.6.1.17 Pemasangan 1 m' kalsiplank m 83,674.00

A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA


A.4.6.2.2 Pemasangan 1 buah kunci tanam biasa bh 316,393.75
A.4.6.2.3 Pemasangan 1 buah kunci kamar mandi bh 342,533.25
A.4.6.2.4 Pemasangan 1 buah kunci silinder bh 342,533.25
A.4.6.2.5 Pemasangan 1 buah engsel pintu biasa 4" bh 92,745.20
A.4.6.2.6 Pemasangan 1 buah engsel jendela 3" bh 64,046.38
A.4.6.2.8 Pemasangan 1 buah spring knip bh 86,655.38
A.4.6.2.9 Pemasangan 1 buah kait angin bh 68,057.00
A.4.6.2.10 Pemasangan 1 buah door closer bh 723,988.25
A.4.6.2.11 Pemasangan 1 buah kunci slot bh 114,867.75
A.4.6.2 .12 Pemasangan 1 buah Door handle bh 258,583.25
A.4.6.2 .13 Pemasangan 1 buah door stop bh 158,613.75
A.4.6.2 .17 Pemasangan 1 m2 kaca tebal 5 mm m2 190,966.70
A.4.6.2 .18 Pemasangan 1 m2 kaca tebal 8 mm m2 289,786.78
A.4.6.2 .19 Pemasangan 1 m2 kaca tebal 12 mm m2 846,115.38
A.4.6.2 .23 Pemasangan 1 m2 kaca patri tebal 5 mm m2 2,822,019.50

A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama m2 24,069.50
1 m2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat
A.4.7.1.4. m2 67,606.20
penutup)
A.4.7.1.6. Pelaburan 1 m2 bidang kayu dengan teak oil m2 57,825.45
A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur m2 67,869.55
A.4.7.1.8. Pelaburan 1 m2 bidang kayu dengan cat residu dan ter m2 17,451.25
A.4.7.1.9. Pelaburan 1 m2 bidang kayu dengan vernis m2 65,314.25
Pengecatan 1 m2 tembok baru untuk interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis
A.4.7.1.10. m2 47,733.05
cat penutup)
A.4.7.1.11. Pengecatan 1 m2 tembok lama (1 lapis cat dasar, 2 lapis cat penutup) m2 36,138.75
A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi m2 51,865.00
An. 4.7.1.10. Pengecatan 1 m2 permukaan baja galvanis secara manual sistem 1 lapis cat m2 50,107.80
Pengecatan 1 m2 tembok baru untuk exterior ( 1 lapis plamir, 1 lapis cat dasar, 2
An. 4.7.1.11. m2 57,271.15
lapis cat penutup)
An. 4.7.1.12. Pengecatan 1 m2 plafond (2 lapis cat penutup) m2 19,972.05

II - 25
ANALISA JENIS PEKERJAAN SATUAN HARGA (RP)
A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.1. Pemasangan 1 buah closed duduk bh 3,941,082.20
A.5.1.1.2. Pemasangan 1 buah closed jongkok bh 935,964.30
A.5.1.1.4. Pemasangan 1 buah urinoir bh 4,003,244.30
A.5.1.1.5. Pemasangan 1 buah wastafel bh 1,634,745.70
A.5.1.1.6. Pemasangan 1 buah bathcuip porselen bh 7,465,955.25
A.5.1.1.7. Pemasangan 1 buah bak fibreglass Uk. 70x70x66cm bh 1,326,410.00
A.5.1.1.12. Pemasangan 1 buah bak cuci piring stainlessteel bh 3,215,486.25
A.5.1.1.14. Pemasangan 1 buah floor drain stainless steel bh 364,118.75
A.5.1.1.18. Pemasangan 1 m' pipa galvanis diameter 1/2" m 82,127.25
A.5.1.1.19. Pemasangan 1 buah kran diameter 1/2" atau 3/4" bh 87,434.50
A.5.1.1.20. Pemasangan 1 m' pipa galvanis diameter 3/4" m 110,970.21
A.5.1.1.25. Pemasangan 1 m' pipa PVC tipe AW diameter 1/2" m 30,949.38
A.5.1.1.26. Pemasangan 1 m' pipa PVC tipe AW diameter 3/4" m 35,374.00
A.5.1.1.27. Pemasangan 1 m' pipa PVC tipe AW diameter 1" m 34,706.25
An.5.1.1.13. Pemasangan 1 m' pipa PVC tipe DW diameter 11/2" m 65,093.45
An.5.1.1.14. Pemasangan 1 m' pipa PVC tipe DW diameter 3" m 137,522.75
An.5.1.1.15. Pemasangan 1 m' pipa PVC tipe DW diameter 4" m 208,956.44
An.5.1.1.16. Pemasangan 1 m' pipa beton diameter 40 cm m 771,784.09

Taksir HARGA SATUAN PEKERJAAN LAIN-LAIN


Pemasangan 1 m2 rangka atap baja ringan SNI dihitung dan desain dengan program
Taksir 1 m2 256,213.34
khusus oleh Vendor
Taksir 2 Pemasangan 1 m2 paving blok persegi panjang t. 8 cm mutu K200 m2 258,908.13
Taksir 3 Pemasangan 1 m2 paving blok persegi panjang warna t. 8 cm mutu K200 m2 286,738.13
Taksir 4 Pemasangan 1 m2 paving blok segienam t. 8 cm mutu K200 m2 276,848.13
Taksir 5 Pemasangan 1 m2 paving blok segienam warna t. 8 cm mutu K200 m2 306,633.13
Taksir 6 Pemasangan 1 titik nyala Lampu titik 401,298.25
Taksir 7 Pemasangan 1 titik nyala stop kontak titik 443,215.75
Taksir 8 Pemasangan 1 M2 Plafond PVC m2 202,900.25
Taksir 9 Pemasangan Kusen dan jendela alumunium kaca (bag. depan) J3 unit 4,606,233.25
Taksir 10 Pemasangan Kusen dan jendela alumunium kaca (bag. depan) J2 unit 3,064,230.50
Taksir 11 Pemasangan Kusen dan jendela alumunium kaca (bag. depan) J1 unit 1,829,550.25
Taksir 12 Pemasangan Kusen dan jendela alumunium kaca (bag. BELAKANG) B3 unit 1,794,500.50
Taksir 13 Pemasangan Kusen dan jendela alumunium kaca (bag. BELAKANG) B2 unit 1,350,712.00
Pekerjaan Pembuatan dan pemasangan Kusen dan Pintu besi, Bouvenli + aksesoris
Taksir 14 unit 6,208,125.00
lengkap (P1)
Taksir 15 Pekerjaan Pengeboran Tanah dan Pengecoran Beton Pondasi Bored Pile m' 460,000.00
Taksir 16 Mobilisasi dan Demolisai Alat Bored Pile Ls 11,500,000.00
Taksir 17 Pekerjaan Pemecahan Kepala Bored Pile ( Max 1 Meter Dia 40 Cm) Perbuah Ls 287,500.00
A.4.1.1.8 a Membuat 1 m3 beton Untuk Pengecoran Bored Pile mutu F'c=21,7 Mpa m3 1,162,757.53
A.4.1.1.17 a Pembesian 10 kg dengan besi polos atau besi ulir Untuk Pengecoran Bored Pile kg 16,710.08

II - 26
HDB & HDU
DAFTAR HARGA SATUAN BAHAN DAN UPAH
TAHUN 2022 - KOTA PALEMBANG

HARGA DASAR (Rp)


No. JENIS BAHAN SATUAN KETERANGAN
I. HARGA DASAR BAHAN
1. SEMEN Semen PC Zak 73,600.00 1 zak @ 50 kg
Semen PC kg 1,472.00
Floor hardener kg 9,000.00
Semen instan Zak 168,600.00 semen utk perekat bata ringan; 1 Zak @ 40 Kg
Semen putih kg 2,535.00
Cornis Zak 106,800.00 setara A+; 1 zak @ 20 kg
Cornis kg 5,340.00

2. PASIR Pasir Beton / Pasang m3 145,000.00


Pasir Beton / Pasang kg 103.57 BJ 1400 kg/m3
Pasir Urug m3 105,000.00
Pasir Urug kg 75.00 BJ 1400 kg/m3

3. BATU KALI Batu kali m3 475,000.00


PEMBANGUNAN GEDUNG BERTINGKAT m3 490,000.00
Batu koral kg 362.96 BJ 1350 kg/m3
Batu split m3 475,000.00
Batu split kg 351.85 BJ 1350 kg/m3

4. BATU BATA Batu bata merah bh 800.00 uk. 5x11x22 cm


Batu bata ringan / hebel bh 3,200.00 uk. 36x20x7,5

5. TANAH Tanah urug / bahan tanah timbunan m3 78,000.00


Tanah Sirtu m3 86,000.00

6. LAIN-LAIN Aspal kg 13,500.00

II. BAHAN PENUTUP ATAP


1. SENG BJLS Seng gelombang uk. 5' kpg 65,500.00 uk. 0,8 x 1,50 m
Seng gelombang uk. 7' kpg 91,500.00 uk. 0,8 x 2,1 m
Seng gelombang uk. 10' kpg 137,200.00 uk. 0,8 x 3,0 m
Seng polos m 46,000.00 lebar 88 cm

2. ASBES Asbes gelombang 5' kpg 103,400.00 lebar 105 cm


Nok asbes bh 58,400.00 panjang 1.00 cm; satu pasang

3. GENTENG KERAMIK Keramik warna natural bh 13,300.00 setara Kanmuri; 1m 2 @ 14 bh


Keramik warna special bh 22,700.00 setara Kanmuri; 1m 2 @ 14 bh
Nok keramik warna natural bh 33,800.00 setara Kanmuri; 1m @ 3,9 bh
Nok Keramik warna special bh 52,200.00 setara Kanmuri; 1m @ 3,9 bh

4. GENTENG METAL Genteng metal uk. 2x4 (0.25mm) lbr 124,700.00 setara Multiroof; 1m2 @ 1,3 lbr
Genteng metal uk. 2x4 (0.3mm) lbr 51,600.00 1 m2 @ 1,62 lbr
Genteng metal berpasir 2x5 (0,45mm) lbr 138,600.00 setara Multiroof; 1m2 @ 1,3 lbr
Nok genteng metal bh 30,400.00
Nok genteng metal berpasir bh 56,700.00

5. GENTENG TANAH LIAT Genteng tanah liat bh 2,400.00 1 m2 @ 17,5 bh


Nok genteng tanah liat bh 6,800.00 1 m @ 3,5 bh

6. POLYCARBONATE Polycarbonate m2 71,200.00 1 roll @ 5mm x 2,1m x 11,8m

7. ATAP ZINCALUME Atap Zincalume (t.0,35 mm) m' 92,000.00 uk.lebar 105 cm
Atap Zincalume warna (t. 0,35 mm) m' 105,700.00 uk.lebar 105 cm
Atap Alkan (t.0,35 mm) m' 70,600.00 uk. Lebar 105 cm
Nok Zincalume 0,30 m' 40,400.00 uk. 300x60
Atap Zincalume warna (t.022mm) lbr 70,600.00 uk. 1600 mm x 740 mm, setara soka
Atap Zincalume warna (t.045mm) m' 131,200.00 setara bluecsoope; uk.lebar 105 cm

8. ATAP BITUMEN Atap bitumen motif gelombang lbr 217,100.00 uk. 200x95x9,3 cm
Atap bitumen motif genteng lbr 61,300.00 uk. 105x40x9,3 cm
Nok atap bitumen bh 105,700.00 uk. 100cm x 50 cm

9. LAIN-LAIN Aluminium foil m2 12,800.00


Kalsiplank btg 68,900.00
Karpet talang m` 14,800.00 lebar 55 cm

III BAHAN KAYU


1. MERAWAN, KULIM Papan m3 5,000,000.00 Kayu Klas II
Balok kayu m3 5,000,000.00 Kayu Klas II

2. MERANTI Papan m3 3,000,000.00 Kayu klas III


Balok kayu m3 3,000,000.00 Kayu klas III

4. RACUK Papan m3 2,250,000.00


Balok kayu m3 2,250,000.00 Kayu klas
Papan racuk t.20 cm kpg 45,000.00 uk 2/25 1m3 = 50 kpg

3. LAIN-LAIN Gelam 6-8 cm pj. 4m btg 11,900.00


Gelam 8-10 cm pj. 4m btg 14,200.00
Gelam 10-12 cm pj. 4m btg 17,800.00
Bambu dia.6-8/ 600cm btg 41,500.00 p. 6 m

I - 28
HARGA DASAR (Rp)
No. JENIS BAHAN SATUAN KETERANGAN

IV BAHAN PENUTUP DINDING/LANTAI


1. KERAMIK PUTIH 20 x 25 kotak 94,000.00 1 kotak @ 20 kpg
buah 4,700.00
30 x 30 kotak 147,000.00 1 kotak @ 11 kpg
buah 13,363.64
40 x 40 kotak 131,500.00 1 kotak @ 6 kpg
buah 21,916.67
50x50 kotak 150,000.00 1 kotak @ 4 kpg
buah 37,500.00

2. KERAMIK 20 x 25 kotak 95,000.00 1 kotak @ 20 kpg


WARNA/TEKSTUR bh 4,750.00
20 x 20 (KM/WC) kotak 90,000.00 1 kotak @ 25 kpg
bh 3,600.00
30 x 30 (tekstur) kotak 70,000.00 1 kotak @ 11 kpg
bh 6,363.64
30 x 30 kotak 105,000.00 1 kotak @ 11 kpg
bh 9,545.45
33,5x33,5 (tekstur) kotak 125,000.00 1 kotak @ 9 kpg
bh 13,888.89
40 x 40 kotak 65,200.00 1 kotak @ 6 kpg
bh 10,866.67
40 x 40 (Anti slip) kotak 82,000.00 1 kotak @ 6 kpg
bh 13,666.67
50x50 kotak 135,000.00 1 kotak @ 4 kpg
bh 33,750.00
50x50 (tekstur) kotak 176,000.00 1 kotak @ 4 kpg
bh 44,000.00
30x50 ktk 208,000.00 1 kotak @ 3 kpg
bh 69,333.33

3. GRANITE TILE 60 x 60 kotak 385,000.00 Homogeneus tile (Helium); 1 kotak @ 3 kpg


bh 128,333.33
Homogeneus tile (happana llappato); 1 kotak @
60 x 60 (tekstur) kotak 650,000.00
3 kpg
bh 216,666.67
80 x 80 kotak 825,000.00 Homogeneus tile GMA26; 1 kotak @ 3 kpg
bh 275,000.00
80 x 80 (tekstur) kotak 1,050,000.00 Homogeneus tile polished; 1 kotak @ 3 kpg
bh 350,000.00
Granite Pola uk. 1,2 x 1,2 m ls 563,300.00 setara Indecor
Step nosing 30 x 60 bh 126,000.00 1 kotak @ 50 kpg
Step nosing 20 x 60 bh 78,500.00 1 kotak @ 33 kpg
Step nosing Keramik 10 x 60 bh 32,700.00 @ 1 kpg

4. BATU ALAM Batu candi uk. 10x20 m2 230,900.00


Granit alam m2 2,374,200.00
Andesit bintik bakar uk. 15x30 m2 237,400.00
Andesit bintik bakar uk. 10 x 20 m2 203,600.00
Palimanan uk. 10x20 m2 217,200.00
Palimanan uk. 15x30 m2 244,500.00
Lempeng (kecil) m2 135,900.00
Lempeng (besar) m2 176,900.00
Andesit + bevel m2 264,700.00 uk. 15x30

5. LAIN-LAIN Karpet biasa m2 27,200.00 bahan bludru


Karpet tebal 4 - 4,5mm m2 133,000.00 setara rainbow tipe crown; lebar 3,95 - 4 m
Karpet t. 4- 6 mm m2 322,300.00 setara rainbow tipe carprice; lebar 3,95 - 4 m
Lantai vinyl 3 mm m2 305,100.00 setara Gaimaru; 1ktk@ 3,3m2
Lantai Laminate t=0,8 mm m2 296,800.00 setara krisbow 1 ktk@1,897m2
Lapis foam Lantai laminate m 23,700.00 uk. 1,2 m x 1 m
Plint laminate m 135,300.00 P. 2,4 m ; L. 10 cm
Adaptation laminate m 108,600.00 P. 2,4 m
Wallpaper m2 115,100.00 setara Royal Mansion; uk. 1 rol @ 10m x 53 cm
Nat keramik kg 27,000.00 setara AM
Aluminium Composite Panel (ACP) tipe
m2 346,000.00 setara seven untuk interior ; uk. 1,22 m x 2,44 m
PE untuk dalam
Aluminium Composite Panel (ACP) tipe
m2 447,500.00 setara seven untuk eksterior ; uk. 1,22 m x 2,44 m
PVDF untuk luar

V BAHAN CETAK
1. BUIS BETON Buis beton dia. 100cm m 1,096,100.00 d0=100 cm; d1=120cm
Buis beton dia. 80cm m 983,700.00 d0=80 cm; d1=100cm
Buis beton dia. 60cm m 702,600.00 d0=60 cm; d1=75cm
Buis beton dia. 40cm m 505,900.00 d0=40 cm; d1=48cm
Buis beton dia. 30cm m 387,800.00 d0=30 cm; d1=38cm
Buis beton dia. 20cm m 281,100.00 d0=20 cm; d1=25cm

2. ROSTER Roster keramik uk.30x30 bh 89,600.00


Roster keramik uk. 20x20 bh 42,700.00
Roster terawang bh 10,900.00 uk. 10x20
Roster beton bh 16,300.00 uk. 25x25

3. GLASS BLOK Glass block uk. 20x20 bh 28,500.00

I - 29
HARGA DASAR (Rp)
No. JENIS BAHAN SATUAN KETERANGAN

4. PAGAR BETON Panel beton lebar 50 bh 195,900.00 uk. 50x240


Panel beton lebar 40 bh 163,200.00 uk. 40x240
Kolom beton pracetak m 118,700.00 uk. 16x17
Pagar catur t. 60 bh 23,700.00

5. PAVING BLOK Segi enam t. 6 cm bh 4,600.00 1 m2 @ 37 bh; K 300


Persegi panjang t. 6 cm bh 3,400.00 1 m2 @ 44 bh; K 300
Segi enam t.8 cm bh 5,000.00 1 m2 @ 37 bh; K 300
Persegi panjang t. 8 cm bh 3,850.00 1 m2 @ 44 bh; K 300
Segi enam warna t. 6 cm bh 5,300.00 1 m2 @ 37 bh; K 300
Persegi panjang warna t. 6 cm bh 3,950.00 1 m2 @ 44 bh; K 300
Segi enam warna t.8 cm bh 5,700.00 1 m2 @ 37 bh; K 300
Persegi panjang warna t. 8 cm bh 4,400.00 1 m2 @ 44 bh; K 300

6. KANSTEIN Uk. 60x30x20/12 bh 129,400.00


Uk. 60x30x10/15 bh 71,000.00
Uk.40x20x10/13 bh 44,500.00
Uk. 60x35x18/21 bh 92,600.00 standar K.250
7. BATACO BETON Bataco uk. 20x40 bh 3,200.00

Jendela kaca dan kusen UPVC (uk. 1


8. JENDELA UPVC bh 2,041,800.00 dua daun jendela
m x 1,2 m)
Jendela kaca dan kusen UPVC (uk. 0.6
bh 1,365,200.00 satu daun jendela
m x 1,5 m)

VI BAHAN BESI /BAJA /ALUMINIUM /BAJA RINGAN

1. BESI BETON Besi beton kg 13,500.00 1 batang @ 12 m


Kawat beton kg 23,700.00
uk. 2,1 m x 5,4 m; jarak150mm x150mm (6mm)
Wiremesh kg 12,200.00
berat 34,76 kg
Besi strip tebal 5mm kg 19,600.00
2. BAJA Baja WF, IWF, H kg 16,600.00
Baja Siku, CNP kg 11,600.00
Kawat las kg 41,500.00 setara Niko; 1 ktk @ 2 kg
Rangka besi siku 40.40.4mm m 18,800.00
3. ALUMINIUM Profil daun pintu kaca m 74,700.00 setara CA; warna silver; panjang 6 m
Profil kusen 3" m 45,500.00 setara CA; warna silver; panjang 6 m
Profil kusen 4" m 63,800.00 setara CA; warna silver; panjang 6 m
Aluminium strip m 44,800.00 setara CA; warna silver; panjang 6 m
Alimunium Composite m2 344,300.00
4. BAJA RINGAN Profil C channel 100.75 btg 160,300.00 Tegangan leleh minimum 550 MPa;p. 6 m
m 23,400.00
Profil C channel 80.75 btg 130,600.00 Tegangan leleh minimum 550 MPa;p. 6 m
21,800.00
Profil C channel 75.75 btg 116,300.00 Tegangan leleh minimum 550 Mpa;p. 6 m
19,400.00
Profil C channel 75.65 btg 104,500.00 Tegangan leleh minimum 550 Mpa;p. 6 m
17,400.00
Reng R.40.45 btg 53,400.00 Tegangan leleh minimum 550 Mpa;p. 6 m
8,900.00
Screw truss 12x 3/4 bh 200.00
Dynabolt dia 12 mm (10 - 15) cm bh 16,000.00
Talang Jurai dalam m 32,100.00 panjang 6 m

5. PINTU BESI Folding Gate t.0,4 mm m2 813,200.00 min. 7 m2; finish cat standar
Folding Gate t.0,6mm m2 915,800.00 min. 7 m2; finish cat standar
Folding Gate t.0,8mm (jumbo) m2 1,132,500.00 min. 7 m2; finish cat standar
Rolling door aluminum t.0,8 mm m2 848,800.00 min. 6 m2; panjang + 50 cm
Rolling door besi t.± 0,4 mm m2 441,000.00 min. 6 m2; panjang + 50 cm; finish cat standar
Rolling door galvanum t.± 0,4 mm m2 468,300.00 min. 6 m2; panjang + 50 cm

PEGANGAN TANGGA Pegangan tangga stainless kombinasi


6. m'
STAINLESS acylic (3/4", 1" & 2") 1,085,600.00
Pegangan tangga stainless (3/4" & 2") m' 1,356,900.00

7. LAIN-LAIN Kawat jaring galvanis lbr 263,500.00 uk. 2,4 m x 3 m


Kawat duri roll 306,900.00 1 rol @ 60m
Pintu KM/WC Aluminium warna - frame
Aluminium 0,75mm ; coating powder 60 micron;
louver (incl. kusen, lever handle bh 1,287,400.00
uk. 80cm x 200cm; setara solidoor-starmas
stainless steel, engsel aluminium)
Pintu Aluminium warna - 5 mm ice
Akuminium 0,75mm ; coating powder 60 micron;
glass (incl. kusen, lever handle bh 4,497,300.00
uk. 90cm x 215cm; setara solidoor-starmas
stainless steel, engsel aluminium)
Pintu KM/WC Aluminium warna urat
kayu - frame louver (incl. kusen, lever Aluminium 0,75mm ; coating powder 60 micron;
bh 4,883,700.00
handle stainless steel, engsel uk. 80cm x 200cm; setara solidoor-starmas
aluminium)
Pekerjaan Pembuatan dan
Akuminium 0,75mm ; coating powder 60 micron;
pemasangan Kusen dan Pintu besi, bh 6,208,125.00
uk. 90cm x 215cm; setara solidoor-starmas
Bouvenli + aksesoris lengkap (P1)
Pembuatan dan Pemasangan 1 lobang
Lbg 1,356,000.00
terali besi strip (2x3) mm Type DP4
Pagar besi hollow m2 1,200,000.00

I - 30
HARGA DASAR (Rp)
No. JENIS BAHAN SATUAN KETERANGAN
VII. BAHAN PIPA
1. PIPA PVC Pipa PVC AW 1/2" btg 28,500.00 1 batang @ 4 m
Pipa PVC AW 3/4" btg 38,000.00 1 batang @ 4 m
Pipa PVC AW 1" btg 49,900.00 1 batang @ 4 m
Pipa PVC AW 3" btg 219,600.00 1 batang @ 4 m
Pipa PVC AW 4" btg 379,900.00 1 batang @ 4 m
Pipa PVC DW 1½" btg 54,600.00 1 batang @ 4 m
Pipa PVC DW 3" btg 124,600.00 1 batang @ 4 m
Pipa PVC DW 4" btg 197,100.00 1 batang @ 4 m

2. PIPA GALVANIS Pipa galvanis 1/2" t.1,9-2,3 mm btg 219,600.00 1 btg @ 6m


Pipa galvanis 3/4" t.1,9-2,3 mm btg 267,100.00 1 btg @ 6m

3. LAIN-LAIN Lem pipa btl 12,000.00 1 btl @ 400 gram


Assesoris PVC m' 5,900.00

VIII. BAHAN LANGIT-LANGIT


1. PLYWOOD Plywood 3 mm lbr 79,800.00
Plywood 4 mm lbr 84,300.00
Plywood 6 mm lbr 139,600.00
Plywood 9 mm lbr 172,100.00
Plywood 12 mm lbr 219,600.00

2. SOFT BOARD Gypsum 9 mm uk. 1,2 x 2,4 m kpg 90,500.00

3. HARD BOARD kalsiboard 3,5mm kpg 65,000.00


Kalsiplank papan kalsiboard kpg 77,200.00
Kalsiplank tekstur kayu btg 68,900.00
4. PLAFOND PVC Plafond PVC m2 100,900.00 50,450
Plafond PVC + pasang + List PVC (30
m2 326,500.00 setara Shunda plafond
cm x 60 Cm )
Ornamen PVC unit 1,780,600.00 Uk. 1,2m x 1,2m

5. LIST PLAFOND List plafond 1x4 btg 13,700.00 1 batang @ 3,8 m


List plafond besar 10 cm btg 67,000.00 1 batang @ 3,8 m
List gypsum kecil btg 17,800.00 1 batang @ 1,7 m
List gypsum sedang btg 20,200.00 1 batang @ 1,7 m
List PVC btg 95,000.00 1 batang @ 4 m

6. LAIN-LAIN Skrup gypsum 1" dus 102,100.00 1 kotak @ 1000


Lakban gypsum roll 24,300.00
Paku plywood kg 29,700.00
Hollow galvanis 20x40X0,25 mm m 12,650.00 1 btg @ 4 m
Hollow galvanis 40x40x0,25 mm m 10,125.00 1 btg @ 4 m

IX. BAHAN FINISHING


1. KAYU Menie kayu kg 28,500.00
Plamir kayu kg 21,400.00
Cat dasar kg 71,200.00
Cat penutup kg 64,100.00
Teak Oil ltr 65,300.00
Politur ltr 51,000.00
Residu/Ter ltr 5,900.00
Dempul kayu kg 38,200.00
Vernis ltr 38,000.00

2. BESI Menie kg 60,700.00


Cat penutup liter 77,300.00

3. TEMBOK Cat tembok eksterior liter 109,200.00


Cat tembok interior kg 33,200.00
Plamir dinding/kayu kg 21,400.00
Cat dasar/sealer interior kg 51,000.00
Cat dasar/sealer eksterior kg 51,000.00
Cat antibocor kg 60,500.00

4. THINNER Thinner liter 39,200.00


Thinner A liter 36,800.00
5. LAIN-LAIN Kuas 1" bh 11,900.00
Kuas 1 1/2" bh 17,800.00
Kuas 2" bh 23,700.00
Kuas 3" bh 35,600.00
Kuas 4" bh 47,500.00
Kuas roll bh 37,400.00
Baki cat bh 43,300.00
Coating batu alam liter 76,000.00
X. BAHAN KACA
1. KACA POLOS Kaca polos 3 mm m2 108,600.00
Kaca polos 5 mm m2 123,300.00
Kaca polos 8 mm m2 197,300.00
Kaca polos 10 mm m2 271,300.00
Kaca polos 12 mm m2 623,200.00

2. KACA RYBEN/HITAM Kaca polos 3 mm m2 102,100.00


Kaca polos 5 mm m2 98,500.00

I - 31
HARGA DASAR (Rp)
No. JENIS BAHAN SATUAN KETERANGAN

3. LAIN-LAIN Sunblast polos m2 197,100.00 lebar 120 cm


Kaca film m2 88,400.00 lebar 120 cm
Kaca patri 5 mm m2 2,196,100.00
Lem kaca btl 87,800.00
Jendela nako (rangka + kaca 5mm ) m2 385,800.00
Jendela nako m2 326,500.00
XI BAHAN INSTALASI LISTRIK
1. KABEL LISTRIK NYM 2 x 1,5 mm m 10,100.00 setara Supreme; 1 roll @ 50 m
NYM 2 x 2,5 mm m 16,000.00 setara Supreme; 1 roll @ 50 m
NYM 3 x 2,5 mm m 17,800.00 setara Supreme; 1 roll @ 50 m
NYA 2,5 mm m 6,200.00 setara Supreme; 1 roll @ 100 m

2. SAKELAR Saklar tunggal bh 22,600.00


Saklar seri bh 34,400.00

3. STOP KONTAK Stop kontak bh 30,900.00


Stop kontak AC bh 77,200.00

4. LAMPU Downlight 4" bh 103,900.00


Lampu SL 18 watt bh 46,000.00
Lampu LED bh 69,400.00 setara Panasonic
Lampu T5 p. 60 cm bh 92,000.00
Lampu TL RAM 2 x 18 watt bh 284,900.00 setara Philips; 2 x 28 watt
Lampu Taman t. 1m bh 948,500.00 besi tempa (wrougt iron)

5. LAIN-LAIN Pipa listrik btg 15,400.00 setara clipsal; 1 btg @ 3 meter


T dus, L bh 5,000.00
Isolasi bh 12,500.00
Klem kabel bks 16,000.00 1 bks @ 50 pcs
Mangkok inbow bh 5,900.00
Fitting bh 16,100.00
Klem pipa bh 950.00
Fleksibel m 4,700.00
MCB 10A 1PHASE bh 59,400.00 setara Schneider

XII. BAHAN PENGUNCI DAN PENGGANTUNG


1. KUNCI TANAM Kunci tanam stainless bh 207,700.00
Kunci tanam biasa bh 184,000.00
Kunci tanam kecil bh 89,000.00
Kunci bulat (KM/WC) bh 160,300.00
Handle pintu stainless steel bh 504,500.00
Cylinder kunci bh 207,700.00
Rambuncis/grendel jendela bh 39,900.00

2. ENGSEL/GRENDEL Engsel 3" stainless steel ktk 54,000.00


Engsel 3" biasa ktk 36,600.00
Engsel 4" stainless steel ktk 84,200.00
Engsel 4" biasa ktk 52,000.00 Invisible Hinge IHP 202 Stainless Sus 304
Engsel tanam set 1,050,000.00
Grendel 2" stainless steel bh 31,500.00
Grendel 3" bh 25,000.00 paloma
Grendel 8 " bh 90,500.00
Grendel 12 " bh 265,000.00
Grendel tanam bh 140,000.00

3. LAIN-LAIN Gembok bh 62,300.00


Door closer bh 534,000.00
Door stop bh 118,000.00
Door holder bh 129,300.00
Kait angin bh 29,200.00 Invisible Hinge IHP 202 Stainless Sus 304
Spring knip ktk 30,900.00
Pull Handle biasa bh 314,600.00
Kunci slot bh 61,700.00 paloma
Casement 16" bh 155,000.00
Casement 8" bh 57,700.00

XIII. BAHAN SANITAIR


1. CLOSED Closed jongkok porselen bh 387,000.00
Closed duduk bh 2,663,800.00 setara American Standard
Closed duduk/monoblok bh 2,552,300.00

2. JET SHOWER Jet shower bh 343,400.00 setara Toto


Jet shower bh 161,300.00 setara Onda
Jet Pump 200 Watt bh 900,000.00 setara Sanyo
3. KRAN TEMBOK Kran air 1/2 - 3/4" bh 247,300.00 Basin Faucet W 5L
Kran air 1/2 - 3/4" bh 50,600.00

4. WASTAFEL Wastafel bh 890,300.00


Siphon stainless bh 290,800.00 setara Toto THX1A-3N
kran wastafel Tl2-065W. bh 332,400.00
Stop kran 3/4" bh 93,200.00
Selang Flexsibel p.40 cm bh 77,200.00 setara Onda

5. URINOIR Urinoir bh 2,433,500.00


Pembatas Urinoir bh 1,017,300.00

I - 32
HARGA DASAR (Rp)
No. JENIS BAHAN SATUAN KETERANGAN

6. BATHUBE Bathube uk. 820x470 bh 5,290,900.00


Septictank Uk 2 X 2 X 1 m unit 6,885,200.00
7. PENAMPUNG AIR Penampung air fiber kap. 250L unit 529,400.00
Penampung air fiber kap. 550 L unit 1,187,100.00
Penampung air fiber kap. 900 L unit 1,483,900.00
Penampung air fiber kap. 1200 L unit 1,602,600.00
Penampung air fiber kap. 3000 L unit 5,494,500.00
Penampung air stainless kap. 550 L unit 2,735,100.00
Penampung air stainless kap. 1100 L unit 5,282,600.00
Penampung air stainless kap. 2000 L unit 7,597,400.00
Tower besi tinggi 2 m unit 2,400,000.00
8. LAIN-LAIN Bak Air fiberglass uk. 70x70x66cm bh 777,500.00
Bak Air Marble uk. 56x56 cm bh 842,800.00
Bak Air Marble uk. 66x66 cm bh 1,483,900.00
Kitchen siknk stainless steel bh 2,421,700.00 Uk. 820 x 470
Waterdrain + asesories bh 314,600.00
Floor drain stainless steel bh 296,700.00
Floor drain plastik bh 39,300.00
Sealtape bh 4,200.00
Pintu KM/WC PVC bh 890,300.00
Pelampung 1/2" bh 202,400.00
Pelampung 3/4" bh 305,400.00
Kaca cermin Wastafel bh 300,000.00
XIV. BAHAN PENGIKAT
1. PAKU Paku bermacam ukuran kg 26,100.00
Beton ktk 61,100.00 1 ktk @ 50 buah
Paku seng kg 46,300.00
Paku atap bitumen bh 1,200.00 p. 70 mm
Skrup fixer bh 800.00 1 kotak @ 100 pcs
Paku hak panj.15 cm kg 23,700.00
2. LEM Lem kayu kg 39,200.00
Lem serba guna kg 109,200.00
Sealent tube 35,600.00
Paku skrup kg 65,300.00
XV. LAIN-LAIN
1 Amplas lbr 9,500.00
2 Diamond wheel 4 Universal Turbo (740) bh 116,900.00 setara Bosch
3 Tali Ijuk kg 41,500.00
4 Air ltr 40.00
5 Minyak Bekesting ltr 12,700.00
6 Minyak Pelumas ltr 41,500.00
7 Solar ltr 11,600.00
8 Soda api kg 47,500.00
9 Sewa alat las jam 41,500.00
10 Sewa scafolding unit 53,400.00 1 bulan
11 Sewa molen unit/hari 712,300.00
12 Karung goni lbr 11,900.00 Uk. 75 cm x 110 cm
13 Plastik m2 4,900.00 1 roll @ 20m x 1,2m
14 Geotekstil m2 26,100.00
15 Ijuk kg 21,200.00 berat jenis =2,524

HARGA DASAR UPAH


1 Pekerja OH 120,000.00
2 Tukang OH 160,000.00
3 Kepala Tukang OH 180,000.00
4 Mandor OH 185,000.00
5 Operator OH 165,000.00
6 Pembantu Operator OH 85,000.00
7 Sopir/ Driver OH 105,000.00
8 Pembantu Sopir OH 85,000.00
9 Mekanik OH 135,000.00
10 Pemasang Mekanik OH 85,000.00
11 Pemasak Aspal OH 110,000.00
12 Pekerja Tidak Terlatih OH 120,000.00
13 Penjaga Pompa OH 1,500,000.00
14 Pembantu Penjaga Pompa OH 1,000,000.00
15 Penjaga Alat Berat OH 1,500,000.00
16 Pembantu Penjaga Alat Berat OH 1,000,000.00

I - 33
ANALISA SATUAN
A.2.2.1. HARGA SATUAN PEKERJAAN PERSIAPAN

A.2.2.1.4 Pengukuran dan Pemasangan 1 m' Bouwplank


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang Kayu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 30,725.00
B BAHAN
Kayu Balok 5/7 m3 0.012 2,250,000.00 27,000.00
Paku 2"-3" Kg 0.020 1,200.00 24.00
Kayu papan 3/20 m3 0.007 2,250,000.00 15,750.00
JUMLAH TENAGA BAHAN 42,774.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 73,499.00


### E. Overhead & Profit 15% x D 11,024.85
F. Harga Satuan Pekerjaan (D+E) 84,523.85

An.2.2.1.25 Pembersihan Akhir Lapangan 1 m2


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.075 120,000.00 9,000.00
Tukang Kayu L.02 OH - 160,000.00 -
Kepala Tukang L.03 OH - 180,000.00 -
Mandor L.04 OH 0.038 185,000.00 6,937.50
JUMLAH TENAGA KERJA 15,937.50
B BAHAN
-
-
JUMLAH TENAGA BAHAN -
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 15,937.50


E. Overhead & Profit 15% x D 2,390.63
F. Harga Satuan Pekerjaan (D+E) 18,328.13
Untuk peR m2

A.2.2.1 - 1
A.2.3.1. HARGA SATUAN PEKERJAAN TANAH

A.2.3.1.1 Menggali 1 m3 tanah biasa sedalam 1 m


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.750 120,000.00 90,000.00
Mandor L.04 OH 0.025 185,000.00 4,625.00
JUMLAH TENAGA KERJA 94,625.00
B BAHAN
-
JUMLAH TENAGA BAHAN -
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 94,625.00


E. Overhead & Profit 15% x D 14,193.75
F. Harga Satuan Pekerjaan (D+E) 108,818.75

PEMBANGUNAN GEDUNG BERTINGKAT 2 LANTAI

A.2.3.1.9 Pengurugan kembali 1 m3 galian tanah


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.500 120,000.00 60,000.00
Mandor L.04 OH 0.050 185,000.00 9,250.00
JUMLAH TENAGA KERJA 69,250.00
B BAHAN
-
JUMLAH TENAGA BAHAN -
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 69,250.00


E. Overhead & Profit 15% x D 10,387.50
F. Harga Satuan Pekerjaan (D+E) 79,637.50
* pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian

A.2.3.1.11 Pengurugan 1 m3 dengan pasir urug


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Mandor L.04 OH 0.010 185,000.00 1,850.00
JUMLAH TENAGA KERJA 37,850.00
B BAHAN
Pasir urug m3 1.200 105,000.00 126,000.00
-
JUMLAH TENAGA BAHAN 126,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 163,850.00


E. Overhead & Profit 15% x D 24,577.50
F. Harga Satuan Pekerjaan (D+E) 188,427.50

A.2.3.1 - 1
A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
An.3.2.1.21 1 m2 pasang cerucup gelam untuk pondasi (p.1,5m-20 cm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 160,000.00 -
Kepala Tukang L.03 OH 0.030 180,000.00 5,400.00
Mandor L.04 OH 185,000.00 -
JUMLAH TENAGA KERJA 41,400.00
B BAHAN
Gelam dia.6-8 btg 6.000 11,900.00 71,400.00
JUMLAH TENAGA BAHAN 71,400.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 112,800.00


E. Overhead & Profit 15% x D 16,920.00
F. Harga Satuan Pekerjaan (D+E) 129,720.00

An.3.2.1.22 Pemasangan 1 m3 Rollag batu bata merah (5x11x22) cm campuran 1 SP : 4 PP


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 3.000 120,000.00 360,000.00
Tukang Batu L.02 OH 1.500 160,000.00 240,000.00
Kepala Tukang L.03 OH 0.150 180,000.00 27,000.00
Mandor L.04 OH 0.150 185,000.00 27,750.00
JUMLAH TENAGA KERJA 654,750.00
B BAHAN
Batu bata bh 770.000 800.00 616,000.00
Sement Portland kg 125.000 1,472.00 184,000.00
Pasir Pasang m3 0.416 145,000.00 60,320.00
JUMLAH TENAGA BAHAN 860,320.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,515,070.00


E. Overhead & Profit 15% x D 227,260.50
F. Harga Satuan Pekerjaan (D+E) 1,742,330.50

A.3.2.1 - 1
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu F'c=7,4 Mpa, slump (3-6) cm, w/c=0,87
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 120,000.00 198,000.00
Tukang Batu L.02 OH 0.275 160,000.00 44,000.00
Kepala Tukang L.03 OH 0.028 180,000.00 5,040.00
Mandor L.04 OH 0.083 185,000.00 15,355.00
JUMLAH TENAGA KERJA 262,395.00
B BAHAN
Semen Portland kg 230.000 1,472.00 338,560.00
Pasir Beton kg 893.000 103.57 92,489.29
Kerikil (Maks. 30mm) kg 1027.000 351.85 361,351.85
Air Liter 200.000 40.00 8,000.00
JUMLAH TENAGA BAHAN 800,401.14
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,062,796.14


### E. Overhead & Profit 15% x D 159,419.42
F. Harga Satuan Pekerjaan (D+E) 1,222,215.56

A.4.1.1.5 Membuat 1 m3 beton mutu F'c=14,5 Mpa, slump (120±20) mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 120,000.00 198,000.00
Tukang Batu L.02 OH 0.275 160,000.00 44,000.00
Kepala Tukang L.03 OH 0.028 180,000.00 5,040.00
Mandor L.04 OH 0.083 185,000.00 15,355.00
JUMLAH TENAGA KERJA 262,395.00
B BAHAN
Semen Portland kg 326.000 1,472.00 479,872.00
Pasir Beton kg 760.000 103.57 78,714.29
Kerikil (Maks. 30mm) kg 1029.000 351.85 362,055.56
Air Liter 215.000 40.00 8,600.00
JUMLAH TENAGA BAHAN 929,241.84
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,191,636.84


E. Overhead & Profit 15% x D 178,745.53
F. Harga Satuan Pekerjaan (D+E) 1,370,382.37
CATATAN :
Bobot isi pasir = 1.400 kg/m³; Bobot isi kerikil = 1.350 kg/m³, Buckling factor pasir = 20 %
A.4.1.1 - 1
A.4.1.1.7 Membuat 1 m3 beton mutu F'c=19,3 Mpa
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 120,000.00 198,000.00
Tukang Batu L.02 OH 0.275 160,000.00 44,000.00
Kepala Tukang L.03 OH 0.028 180,000.00 5,040.00
Mandor L.04 OH 0.083 185,000.00 15,355.00
JUMLAH TENAGA KERJA 262,395.00
B BAHAN
Semen Portland kg 371.000 1,472.00 546,112.00
Pasir Beton kg 698.000 103.57 72,292.86
Kerikil (Maks. 30mm) kg 1047.000 351.85 368,388.89
Air Liter 215.000 40.00 8,600.00
JUMLAH TENAGA BAHAN 995,393.75
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,257,788.75


E. Overhead & Profit 15% x D 188,668.31
F. Harga Satuan Pekerjaan (D+E) 1,446,457.06

A.4.1.1.8 Membuat 1 m3 beton mutu F'c=21,7 Mpa


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 120,000.00 198,000.00
Tukang Batu L.02 OH 0.275 160,000.00 44,000.00
Kepala Tukang L.03 OH 0.028 180,000.00 5,040.00
Mandor L.04 OH 0.083 185,000.00 15,355.00
JUMLAH TENAGA KERJA 262,395.00
B BAHAN
Semen Portland kg 384.000 1,472.00 565,248.00
Pasir Beton kg 692.000 103.57 71,671.43
Kerikil (Maks. 30mm) kg 1039.000 351.85 365,574.07
Air Liter 215.000 40.00 8,600.00
JUMLAH TENAGA BAHAN 1,011,093.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,273,488.50


E. Overhead & Profit 15% x D 191,023.28
F. Harga Satuan Pekerjaan (D+E) 1,464,511.78

A.4.1.1.10 Membuat 1 m3 beton mutu F'c=26,4 Mpa


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.650 120,000.00 198,000.00
Tukang Batu L.02 OH 0.275 160,000.00 44,000.00
Kepala Tukang L.03 OH 0.028 180,000.00 5,040.00
Mandor L.04 OH 0.083 185,000.00 15,355.00
JUMLAH TENAGA KERJA 262,395.00
B BAHAN
Semen Portland kg 413.000 1,472.00 607,936.00
Pasir Beton kg 681.000 103.57 70,532.14
Kerikil (Maks. 30mm) kg 1021.000 351.85 359,240.74
Air Liter 215.000 40.00 8,600.00
JUMLAH TENAGA BAHAN 1,046,308.88
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,308,703.88


E. Overhead & Profit 15% x D 196,305.58
F. Harga Satuan Pekerjaan (D+E) 1,505,009.47
A.4.1.1 - 2
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.070 120,000.00 8,400.00
Tukang Batu L.02 OH 0.070 160,000.00 11,200.00
Kepala Tukang L.03 OH 0.007 180,000.00 1,260.00
Mandor L.04 OH 0.004 185,000.00 740.00
JUMLAH TENAGA KERJA 21,600.00
B BAHAN
Besi beton (polos/ulir) kg 10.500 13,500.00 141,750.00
Kawat beton kg 0.150 23,700.00 3,555.00
JUMLAH TENAGA BAHAN 145,305.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 166,905.00


E. Overhead & Profit 15% x D 25,035.75
F. Harga Satuan Pekerjaan (D+E) 191,940.75
1 kg 19,194.08

A.4.1.1.20 Pemasangan 1 m2 bekesting untuk pondasi


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.520 120,000.00 62,400.00
Tukang Kayu L.02 OH 0.260 160,000.00 41,600.00
Kepala Tukang L.03 OH 0.026 180,000.00 4,680.00
Mandor L.04 OH 0.026 185,000.00 4,810.00
JUMLAH TENAGA KERJA 113,490.00
B BAHAN
Kayu m3 0.040 2,250,000.00 90,000.00
Paku 5-10 cm kg 0.300 1,200.00 360.00
Minyak bekesting Liter 0.100 12,700.00 1,270.00
JUMLAH TENAGA BAHAN 91,630.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 205,120.00


E. Overhead & Profit 15% x D 30,768.00
F. Harga Satuan Pekerjaan (D+E) 235,888.00

A.4.1.1.21 Pemasangan 1 m2 bekesting untuk sloof


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.520 120,000.00 62,400.00
Tukang Kayu L.02 OH 0.260 160,000.00 41,600.00
Kepala Tukang L.03 OH 0.026 180,000.00 4,680.00
Mandor L.04 OH 0.026 185,000.00 4,810.00
JUMLAH TENAGA KERJA 113,490.00
B BAHAN
Kayu m3 0.045 2,250,000.00 101,250.00
Paku 5-10 cm kg 0.300 1,200.00 360.00
Minyak bekesting Liter 0.100 12,700.00 1,270.00
JUMLAH TENAGA BAHAN 102,880.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 216,370.00


E. Overhead & Profit 15% x D 32,455.50
F. Harga Satuan Pekerjaan (D+E) 248,825.50
A.4.1.1 - 3
A.4.1.1.22 Pemasangan 1 m2 bekesting untuk kolom
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang Kayu L.02 OH 0.330 160,000.00 52,800.00
Kepala Tukang L.03 OH 0.033 180,000.00 5,940.00
Mandor L.04 OH 0.033 185,000.00 6,105.00
JUMLAH TENAGA KERJA 144,045.00
B BAHAN
Kayu m3 0.040 2,250,000.00 90,000.00
Paku 5-12 cm kg 0.400 1,200.00 480.00
Minyak bekesting Liter 0.200 12,700.00 2,540.00
Balok kayu m3 0.015 2,250,000.00 33,750.00
Plywood tebal 9 mm Lbr 0.350 172,100.00 60,235.00
Dolken Kayu Ø8-10cm p.4m Batang 2.000 14,200.00 28,400.00
JUMLAH TENAGA BAHAN 215,405.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 359,450.00


E. Overhead & Profit 15% x D 53,917.50
F. Harga Satuan Pekerjaan (D+E) 413,367.50

A.4.1.1.23 Pemasangan 1 m2 bekesting untuk balok


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang Kayu L.02 OH 0.330 160,000.00 52,800.00
Kepala Tukang L.03 OH 0.033 180,000.00 5,940.00
Mandor L.04 OH 0.033 185,000.00 6,105.00
JUMLAH TENAGA KERJA 144,045.00
B BAHAN
Kayu m3 0.040 2,250,000.00 90,000.00
Paku 5-12 cm kg 0.400 1,200.00 480.00
Minyak bekesting Liter 0.200 12,700.00 2,540.00
Balok m3 0.018 2,250,000.00 40,500.00
Plywood tebal 9 mm Lbr 0.350 172,100.00 60,235.00
Dolken Kayu Ø8-10cm p.4m Batang 2.000 14,200.00 28,400.00
JUMLAH TENAGA BAHAN 222,155.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 366,200.00


E. Overhead & Profit 15% x D 54,930.00
F. Harga Satuan Pekerjaan (D+E) 421,130.00
A.4.1.1 - 4
A.4.1.1.24 Pemasangan 1 m2 bekesting untuk lantai
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang Kayu L.02 OH 0.330 160,000.00 52,800.00
Kepala Tukang L.03 OH 0.033 180,000.00 5,940.00
Mandor L.04 OH 0.033 185,000.00 6,105.00
JUMLAH TENAGA KERJA 144,045.00
B BAHAN
Kayu m3 0.040 2,250,000.00 90,000.00
Paku 5-12 cm kg 0.400 1,200.00 480.00
Minyak bekesting Liter 0.200 12,700.00 2,540.00
Balok m3 0.015 2,250,000.00 33,750.00
Plywood tebal 9 mm Lbr 0.350 172,100.00 60,235.00
Dolken Kayu Ø8-10cm p.4m Batang 6.000 14,200.00 85,200.00
JUMLAH TENAGA BAHAN 272,205.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 416,250.00


E. Overhead & Profit 15% x D 62,437.50
F. Harga Satuan Pekerjaan (D+E) 478,687.50

A.4.1.1.26 Pemasangan 1 m2 bekesting untuk tangga


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.660 120,000.00 79,200.00
Tukang Kayu L.02 OH 0.330 160,000.00 52,800.00
Kepala Tukang L.03 OH 0.033 180,000.00 5,940.00
Mandor L.04 OH 0.033 185,000.00 6,105.00
JUMLAH TENAGA KERJA 144,045.00
B BAHAN
Kayu m3 0.030 2,250,000.00 67,500.00
Paku 5-12 cm kg 0.400 1,200.00 480.00
Minyak bekesting Liter 0.150 12,700.00 1,905.00
Balok m3 0.015 2,250,000.00 33,750.00
Plywood tebal 9 mm Lbr 0.350 172,100.00 60,235.00
Dolken Kayu Ø8-10cm p.4m Batang 2.000 14,200.00 28,400.00
JUMLAH TENAGA BAHAN 192,270.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 336,315.00


E. Overhead & Profit 15% x D
F. Harga Satuan Pekerjaan (D+E) 336,315.00
A.4.1.1 - 5
A.4.1.1.27 Pemasangan 1 m2 jembatan untuk pengecoran beton
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 120,000.00 18,000.00
Tukang Kayu L.02 OH 0.050 160,000.00 8,000.00
Kepala Tukang L.03 OH 0.005 180,000.00 900.00
Mandor L.04 OH 0.008 185,000.00 1,480.00
JUMLAH TENAGA KERJA 28,380.00
B BAHAN
Kayu kelas (papan) m3 0.026 2,250,000.00 59,400.00
Paku 5-12 cm kg 0.600 1,200.00 720.00
Dolken Kayu Ø8-10cm p.4m Batang 0.500 14,200.00 7,100.00
JUMLAH TENAGA BAHAN 67,220.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 95,600.00


E. Overhead & Profit 15% x D
F. Harga Satuan Pekerjaan (D+E) 95,600.00

A.4.1.1.35 Membuat 1 m' kolom praktis beton bertulang (11x11) cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.180 120,000.00 21,600.00
Tukang Batu L.02 OH 0.020 160,000.00 3,200.00
Tukang Kayu L.02 OH 0.020 160,000.00 3,200.00
Tukang Besi L.02 OH 0.020 160,000.00 3,200.00
Kepala Tukang L.03 OH 0.006 180,000.00 1,080.00
Mandor L.04 OH 0.009 185,000.00 1,665.00
JUMLAH TENAGA KERJA 33,945.00
B BAHAN
Kayu kelas m3 0.002 2,250,000.00 4,500.00
Paku 5-12 cm kg 0.010 1,200.00 12.00
Minyak bekesting Liter 0.100 12,700.00 1,270.00
Besi beton polos kg 3.000 13,500.00 40,500.00
Kawat beton kg 0.450 23,700.00 10,665.00
Sement Portland kg 4.000 1,472.00 5,888.00
Pasir Beton m3 0.006 103.57 0.62
Kerikil kg 0.009 351.85 3.17
JUMLAH TENAGA BAHAN 62,838.79
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 96,783.79


E. Overhead & Profit 15% x D
F. Harga Satuan Pekerjaan (D+E) 96,783.79
A.4.1.1 - 6
A.4.1.1.36 Membuat 1 m' ring balok beton bertulang (10x15) cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.297 120,000.00 35,640.00
Tukang Batu L.02 OH 0.033 160,000.00 5,280.00
Tukang Kayu L.02 OH 0.033 160,000.00 5,280.00
Tukang Besi L.02 OH 0.003 160,000.00 480.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 51,255.00
B BAHAN
Kayu kelas m3 0.003 2,250,000.00 6,750.00
Paku 5-12 cm kg 0.020 1,200.00 24.00
Minyak bekesting Liter 0.100 12,700.00 1,270.00
Besi beton polos kg 3.600 13,500.00 48,600.00
Kawat beton kg 0.050 23,700.00 1,185.00
Sement Portland kg 5.500 1,472.00 8,096.00
Pasir Beton m3 0.009 103.57 0.93
Kerikil kg 0.015 351.85 5.28
JUMLAH TENAGA BAHAN 65,931.21
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 117,186.21


E. Overhead & Profit 15% x D
F. Harga Satuan Pekerjaan (D+E) 117,186.21
A.4.1.1 - 7
A.4.1.1. HARGA SATUAN PEKERJAAN BETON
A.4.1.1.8 a Membuat 1 m3 beton Untuk Pengecoran Bored Pile mutu F'c=21,7 Mpa
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH
Tukang Batu L.02 OH
Kepala Tukang L.03 OH
Mandor L.04 OH
JUMLAH TENAGA KERJA -
B BAHAN
Semen Portland kg 384.000 1,472.00 565,248.00
Pasir Beton kg 692.000 103.57 71,671.43
Kerikil (Maks. 30mm) kg 1039.000 351.85 365,574.07
Air Liter 215.000 40.00 8,600.00
JUMLAH TENAGA BAHAN 1,011,093.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) PEMBANGUNAN GEDUNG BERTINGKAT 2 L 1,011,093.50


E. Overhead & Profit 15% x D 151,664.03
F. Harga Satuan Pekerjaan (D+E) 1,162,757.53

A.4.1.1.17 a Pembesian 10 kg dengan besi polos atau besi ulir Untuk Pengecoran Bored Pile
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.161 -
Tukang Batu L.02 OH 0.402 -
Kepala Tukang L.03 OH 0.016 -
Mandor L.04 OH
JUMLAH TENAGA KERJA -
B BAHAN
Besi beton (polos/ulir) kg 10.500 13,500.00 141,750.00
Kawat beton kg 0.150 23,700.00 3,555.00
JUMLAH TENAGA BAHAN 145,305.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 145,305.00


E. Overhead & Profit 15% x D 21,795.75
F. Harga Satuan Pekerjaan (D+E) 167,100.75
1 kg 16,710.08

AN .4.1.1 - 1
A.4.2.1. HARGA SATUAN PEKERJAAN BESI & ALUMINIUM

A.4.2.1.21 Pemasangan 1 m2 rangka besi hollow 40x40.2mm, modul 60x60cm, plafon


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 120,000.00 42,000.00
Tukang Besi L.02 OH 0.350 160,000.00 56,000.00
Kepala Tukang L.03 OH 0.035 180,000.00 6,300.00
Mandor L.04 OH 0.018 185,000.00 3,330.00
JUMLAH TENAGA KERJA 107,630.00
B BAHAN
Rangka metal hollow 40.20.2 mm m' 4.000 10,125.00 40,500.00
Assesoris (perkuatan, las dll) Ls 100%xrangka 10,125.00
JUMLAH TENAGA BAHAN 50,625.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 158,255.00


E. Overhead & Profit 15% x D 23,738.25
F. Harga Satuan Pekerjaan (D+E) 181,993.25

A.4.2.1 - 1
A.4.4.1. HARGA SATUAN PEKERJAAN PASANGAN DINDING

A.4.4.1.1 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 2 PP


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 120,000.00 72,000.00
Tukang Batu L.02 OH 0.200 160,000.00 32,000.00
Kepala Tukang L.03 OH 0.020 180,000.00 3,600.00
Mandor L.04 OH 0.030 185,000.00 5,550.00
JUMLAH TENAGA KERJA 113,150.00
B BAHAN
Bata merah bh 140.000 800.00 112,000.00
Semen Portland kg 43.500 1,472.00 64,032.00
Pasir pasang m3 0.080 145,000.00 11,600.00
JUMLAH TENAGA BAHAN 187,632.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) PEMBANGUNAN GEDUNG BERTINGKAT 2 L 300,782.00


### E. Overhead & Profit 15% x D 45,117.30
F. Harga Satuan Pekerjaan (D+E) 345,899.30

A.4.4.1.2 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 3 PP


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 120,000.00 72,000.00
Tukang Batu L.02 OH 0.200 160,000.00 32,000.00
Kepala Tukang L.03 OH 0.020 180,000.00 3,600.00
Mandor L.04 OH 0.030 185,000.00 5,550.00
JUMLAH TENAGA KERJA 113,150.00
B BAHAN
Bata merah bh 140.000 800.00 112,000.00
Semen Portland kg 32.950 1,472.00 48,502.40
Pasir pasang m3 0.091 145,000.00 13,195.00
JUMLAH TENAGA BAHAN 173,697.40
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 286,847.40


E. Overhead & Profit 15% x D 43,027.11
F. Harga Satuan Pekerjaan (D+E) 329,874.51
A.4.4.1.3 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1 SP : 4 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.600 120,000.00 72,000.00
Tukang Batu L.02 OH 0.200 160,000.00 32,000.00
Kepala Tukang L.03 OH 0.020 180,000.00 3,600.00
Mandor L.04 OH 0.030 185,000.00 5,550.00
JUMLAH TENAGA KERJA 113,150.00
B BAHAN
Bata merah bh 140.000 800.00 112,000.00
Semen Portland kg 26.550 1,472.00 39,081.60
Pasir pasang m3 0.093 145,000.00 13,485.00
JUMLAH TENAGA BAHAN 164,566.60
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 277,716.60


### E. Overhead & Profit 15% x D 41,657.49
F. Harga Satuan Pekerjaan (D+E) 319,374.09

A.4.4.1 - 1
A.4.4.1.7 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 SP : 2 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Bata merah bh 70.000 800.00 56,000.00
Semen Portland kg 18.950 1,472.00 27,894.40
Pasir pasang m3 0.038 145,000.00 5,510.00
JUMLAH TENAGA BAHAN 89,404.40
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 145,979.40


### E. Overhead & Profit 15% x D 21,896.91
F. Harga Satuan Pekerjaan (D+E) 167,876.31
A.4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 SP : 3 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Bata merah bh 70.000 800.00 56,000.00
Semen Portland kg 14.370 1,472.00 21,152.64
Pasir pasang m3 0.040 145,000.00 5,800.00
JUMLAH TENAGA BAHAN 82,952.64
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 139,527.64


E. Overhead & Profit 15% x D 20,929.15
F. Harga Satuan Pekerjaan (D+E) 160,456.79

A.4.4.1.9 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 SP : 4 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Bata merah bh 70.000 800.00 56,000.00
Semen Portland kg 11.500 1,472.00 16,928.00
Pasir pasang m3 0.043 145,000.00 6,235.00
JUMLAH TENAGA BAHAN 79,163.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 135,738.00


### E. Overhead & Profit 15% x D 20,360.70
F. Harga Satuan Pekerjaan (D+E) 156,098.70
A.4.4.1.23 Pemasangan 1 m2 dinding terawang (roster) 12x11x24 campuran 1 SP : 4 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Bata rooster bh 30.000 10,900.00 327,000.00
Semen Portland kg 11.000 1,472.00 16,192.00
Pasir pasang m3 0.035 145,000.00 5,075.00
JUMLAH TENAGA BAHAN 348,267.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 404,842.00


E. Overhead & Profit 15% x D 60,726.30
F. Harga Satuan Pekerjaan (D+E) 465,568.30

An.4.4.1.6 Pemasangan 1 m2 dinding roster keramik 30x30 campuran 1 SP : 4 PP


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Rooster keramik 30x30cm bh 11.110 89,600.00 995,456.00
Semen Portland kg 11.000 1,472.00 16,192.00
Pasir pasang m3 0.035 145,000.00 5,075.00
JUMLAH TENAGA BAHAN 1,016,723.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,073,298.00


E. Overhead & Profit 15% x D 160,994.70
F. Harga Satuan Pekerjaan (D+E) 1,234,292.70
A.4.4.1 - 1
An.4.4.1.7 Pemasangan 1 m2 dinding roster keramik 20x20 campuran 1 SP : 4 PP
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Rooster keramik 20x20cm bh 25.000 42,700.00 1,067,500.00
Semen Portland kg 11.000 1,472.00 16,192.00
Pasir pasang m3 0.035 145,000.00 5,075.00
JUMLAH TENAGA BAHAN 1,088,767.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,145,342.00


E. Overhead & Profit 15% x D 171,801.30
F. Harga Satuan Pekerjaan (D+E) 1,317,143.30

An.4.4.1.8 Pemasangan 1 m2 dinding glass block 20x20 campuran 1 SP : 4 PP


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 56,575.00
B BAHAN
Glass block bh 26.500 28,500.00 755,250.00
Semen Portland kg 11.000 1,472.00 16,192.00
Pasir pasang m3 0.035 145,000.00 5,075.00
JUMLAH TENAGA BAHAN 776,517.00
C. PERALATAN
JUMLAH TENAGA ALAT

D. Jumlah (A+B+C) 833,092.00


E. Overhead & Profit 15% x D 124,963.80
F. Harga Satuan Pekerjaan (D+E) 958,055.80
A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN

A.4.4.2.4 Pemasangan 1 m2 plesteran 1 SP : 4 PP tebal 15 mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang Batu L.02 OH 0.150 160,000.00 24,000.00
Kepala Tukang L.03 OH 0.015 180,000.00 2,700.00
Mandor L.04 OH 0.015 185,000.00 2,775.00
JUMLAH TENAGA KERJA 65,475.00
B BAHAN
Semen Portland kg 6.240 1,472.00 9,185.28
Pasir pasang m3 0.024 145,000.00 3,480.00
JUMLAH TENAGA BAHAN 12,665.28
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 78,140.28


### E. Overhead & Profit 15% x D 11,721.04
F. Harga Satuan Pekerjaan (D+E) 89,861.32

A.4.4.2 - 1
A.4.4.3. HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

An.4.4.3.4. Pemasangan 1 m2 lantai keramik polish (putih) ukuran 40 cm x 40 cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 120,000.00 30,000.00
Tukang Batu L.02 OH 0.125 160,000.00 20,000.00
Kepala Tukang L.03 OH 0.013 180,000.00 2,340.00
Mandor L.04 OH 0.013 185,000.00 2,405.00
JUMLAH TENAGA KERJA 54,745.00
B BAHAN
Keramik 40x40 (putih) bh 6.630 21,916.67 145,307.50
Semen Portland kg 10.000 1,472.00 14,720.00
Pasir pasang kg 0.045 103.57 4.66
Semen warna kg 1.500 2,535.00 3,802.50
JUMLAH TENAGA BAHAN 163,834.66
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 218,579.66


### E. Overhead & Profit 15% x D 32,786.95
F. Harga Satuan Pekerjaan (D+E) 251,366.61

An.4.4.3.5. Pemasangan 1 m2 lantai keramik Unpolish ukuran 40 cm x 40 cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 120,000.00 30,000.00
Tukang Batu L.02 OH 0.125 160,000.00 20,000.00
Kepala Tukang L.03 OH 0.013 180,000.00 2,340.00
Mandor L.04 OH 0.013 185,000.00 2,405.00
JUMLAH TENAGA KERJA 54,745.00
B BAHAN
Keramik 40x40 warna bh 6.630 13,666.67 90,610.00
Semen Portland kg 10.000 1,472.00 14,720.00
Pasir pasang kg 0.045 103.57 4.66
Semen warna kg 1.500 2,535.00 3,802.50
JUMLAH TENAGA BAHAN 109,137.16
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 163,882.16


### E. Overhead & Profit 15% x D 24,582.32
F. Harga Satuan Pekerjaan (D+E) 188,464.48

A.4.4.3 - 1
An.4.4.3.8. Pemasangan 1 m' plint keramik ukuran 10 cm x 40 cm unpolish
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 120,000.00 10,800.00
Tukang Batu L.02 OH 0.090 160,000.00 14,400.00
Kepala Tukang L.03 OH 0.035 180,000.00 6,300.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 32,425.00
B BAHAN
Plint keramik bh 2.650 3,416.67 9,054.17
Semen Portland kg 1.140 1,472.00 1,678.08
Pasir pasang kg 0.003 103.57 0.31
Semen warna kg 0.050 2,535.00 126.75
JUMLAH TENAGA BAHAN 10,859.31
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 43,284.31


E. Overhead & Profit 15% x D 6,492.65
F. Harga Satuan Pekerjaan (D+E) 49,776.95

An.4.4.3.8. Pemasangan 1 m' Step nosing Keramik 10 x 60 cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.090 120,000.00 10,800.00
Tukang Batu L.02 OH 0.090 160,000.00 14,400.00
Kepala Tukang L.03 OH 0.035 180,000.00 6,300.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 32,425.00
B BAHAN
Step nosing Keramik 10 x 60 bh 1.700 32,700.00 55,590.00
Semen Portland kg 1.140 1,472.00 1,678.08
Pasir pasang kg 0.003 103.57 0.31
Semen warna kg 0.050 2,535.00 126.75
JUMLAH TENAGA BAHAN 57,395.14
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 89,820.14


E. Overhead & Profit - 13,473.02
F. Harga Satuan Pekerjaan (D+E) 103,293.16

An.4.4.3.9. Pemasangan 1 m2 lantai keramik polish (putih) ukuran 40 cm x 40 cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.250 120,000.00 30,000.00
Tukang Batu L.02 OH 0.125 160,000.00 20,000.00
Kepala Tukang L.03 OH 0.013 180,000.00 2,340.00
Mandor L.04 OH 0.013 185,000.00 2,405.00
JUMLAH TENAGA KERJA 54,745.00
B BAHAN
Keramik 40x40 (putih) bh 6.630 385,000.00 2,552,550.00
Semen Portland kg 10.000 1,472.00 14,720.00
Pasir pasang kg 0.045 103.57 4.66
Semen warna kg 1.500 2,535.00 3,802.50
JUMLAH TENAGA BAHAN 2,571,077.16
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,625,822.16


### E. Overhead & Profit 120,000.00 393,873.32
F. Harga Satuan Pekerjaan (D+E) 3,019,695.48
A.4.5.1. HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)
A.4.5.1.9 Pemasangan 1 m' list langit-langit kayu profil
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 120,000.00 6,000.00
Tukang Batu L.02 OH 0.050 160,000.00 8,000.00
Kepala Tukang L.03 OH 0.005 180,000.00 900.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 15,455.00
B BAHAN
List kayu profil m 1.050 17,631.58 18,513.16
Paku kg 0.010 1,200.00 12.00
JUMLAH TENAGA BAHAN 18,525.16
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 33,980.16


### E. Overhead & Profit 15% x D 5,097.02
F. Harga Satuan Pekerjaan (D+E) 39,077.18

An.4.5.1.6 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120 x 240 x 9) mm (tebal 3,5 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang Batu L.02 OH 0.050 160,000.00 8,000.00
Kepala Tukang L.03 OH 0.005 180,000.00 900.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 21,825.00
B BAHAN
Kalsiboard Lembar 0.364 65,000.00 23,660.00
Paku skrup kg 0.110 102,100.00 11,231.00
Cornis kg 0.300 5,340.00 1,602.00
Lakban gypsum roll 0.070 24,300.00 1,701.00
JUMLAH TENAGA BAHAN 38,194.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 60,019.00


### E. Overhead & Profit 15% x D 9,002.85
F. Harga Satuan Pekerjaan (D+E) 69,021.85
A.4.5.1 - 2
A.4.5.1.9a Pemasangan 1 m' list langit-langit kayu profil lebar 4 cm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 120,000.00 6,000.00
Tukang Batu L.02 OH 0.050 160,000.00 8,000.00
Kepala Tukang L.03 OH 0.005 180,000.00 900.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 15,455.00
B BAHAN
List kayu profil m 1.050 3,605.26 3,785.53
Paku kg 0.010 1,200.00 12.00
JUMLAH TENAGA BAHAN 3,797.53
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 19,252.53


E. Overhead & Profit 15% x D 2,887.88
F. Harga Satuan Pekerjaan (D+E) 22,140.41
An.4.5.1.6 Pemasangan 1 m2 langit-langit kalsiboard ukuran (120 x 240 x 9) mm (tebal 3,5 mm)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 - -
Tukang Batu L.02 OH 0.050 - -
Kepala Tukang L.03 OH 0.005 - -
Mandor L.04 OH 0.005 - -
JUMLAH TENAGA KERJA -
B BAHAN
Kalsiboard Lembar 0.364 950.00 345.80
Paku skrup kg 0.110 - -
Cornis kg 0.300 - -
Lakban gypsum roll 0.070 36,600.00 2,562.00
JUMLAH TENAGA BAHAN 2,907.80
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,907.80


### E. Overhead & Profit - -
F. Harga Satuan Pekerjaan (D+E) 2,907.80
A.4.5.1 - 2
A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP

A.4.5.2.41 Pemasangan 1 m2 Atap Zincalume (t.0,35 mm)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 120,000.00 18,000.00
Tukang Kayu L.02 OH 0.075 160,000.00 12,000.00
Kepala Tukang L.03 OH 0.080 180,000.00 14,400.00
Mandor L.04 OH 0.006 185,000.00 1,110.00
JUMLAH TENAGA KERJA 45,510.00
B BAHAN
Atap Zincalume (t.0,35 mm) Lbr 1.050 92,000.00 96,600.00
Paku hak panj.15 cm kg 0.020 23,700.00 474.00
JUMLAH TENAGA BAHAN 97,074.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 142,584.00


### E. Overhead & Profit 15% x D 21,387.60
F. Harga Satuan Pekerjaan (D+E) 163,971.60

A.4.5.2.42 Pemasangan 1 m' nok aluminium


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang Kayu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.100 180,000.00 18,000.00
Mandor L.04 OH 0.050 185,000.00 9,250.00
JUMLAH TENAGA KERJA 55,250.00
B BAHAN
Nok standar 40x18 Bh 1.200 33,800.00 40,560.00
Paku hak panj.15 cm kg 0.040 23,700.00 948.00
JUMLAH TENAGA BAHAN 41,508.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 96,758.00


### E. Overhead & Profit 15% x D 14,513.70
F. Harga Satuan Pekerjaan (D+E) 111,271.70
A.4.5.2 - 1
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU

An.4.6.1.17 Pemasangan 1 m' kalsiplank


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang Kayu L.02 OH 0.200 160,000.00 32,000.00
Kepala Tukang L.03 OH 0.020 180,000.00 3,600.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 48,525.00
B BAHAN
Kalsiplank btg 0.3500 68,900.00 24,115.00
Paku kg 0.100 1,200.00 120.00
JUMLAH TENAGA BAHAN 24,235.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 72,760.00


### E. Overhead & Profit 15% x D 10,914.00
F. Harga Satuan Pekerjaan (D+E) 83,674.00
A.4.6.1 - 1
A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI DAN KACA

A.4.6.2.2 Pemasangan 1 buah kunci tanam biasa


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang Kayu L.02 OH 0.500 160,000.00 80,000.00
Kepala Tukang L.03 OH 0.050 180,000.00 9,000.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 91,125.00
B BAHAN
Kunci tanam biasa bh 1.000 184,000.00 184,000.00
JUMLAH TENAGA BAHAN 184,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 275,125.00


### E. Overhead & Profit 15% x D 41,268.75
F. Harga Satuan Pekerjaan (D+E) 316,393.75

A.4.6.2.3 Pemasangan 1 buah kunci kamar mandi


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.005 120,000.00 600.00
Tukang Kayu L.02 OH 0.500 160,000.00 80,000.00
Kepala Tukang L.03 OH 0.050 180,000.00 9,000.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 90,155.00
B BAHAN
Kunci Tanam KM bh 1.000 207,700.00 207,700.00
JUMLAH TENAGA BAHAN 207,700.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 297,855.00


### E. Overhead & Profit 15% x D 44,678.25
F. Harga Satuan Pekerjaan (D+E) 342,533.25

A.4.6.2.4 Pemasangan 1 buah kunci silinder


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.005 120,000.00 600.00
Tukang Kayu L.02 OH 0.500 160,000.00 80,000.00
Kepala Tukang L.03 OH 0.050 180,000.00 9,000.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 90,155.00
B BAHAN
Kunci bulat ex. SES bh 1.000 207,700.00 207,700.00
JUMLAH TENAGA BAHAN 207,700.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 297,855.00


### E. Overhead & Profit 15% x D 44,678.25
F. Harga Satuan Pekerjaan (D+E) 342,533.25

A.4.6.2 - 1
A.4.6.2.5 Pemasangan 1 buah engsel pintu biasa 4"
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 120,000.00 1,800.00
Tukang Kayu L.02 OH 0.150 160,000.00 24,000.00
Kepala Tukang L.03 OH 0.015 180,000.00 2,700.00
Mandor L.04 OH 0.0008 185,000.00 148.00
JUMLAH TENAGA KERJA 28,648.00
B BAHAN
Engsel 4" biasa bh 1.000 52,000.00 52,000.00
JUMLAH TENAGA BAHAN 52,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 80,648.00


### E. Overhead & Profit 15% x D 12,097.20
F. Harga Satuan Pekerjaan (D+E) 92,745.20

A.4.6.2.6 Pemasangan 1 buah engsel jendela 3"


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang Kayu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.0005 185,000.00 92.50
JUMLAH TENAGA KERJA 19,092.50
B BAHAN
Engsel 3" biasa bh 1.000 36,600.00 36,600.00
JUMLAH TENAGA BAHAN 36,600.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 55,692.50


### E. Overhead & Profit 15% x D 8,353.88
F. Harga Satuan Pekerjaan (D+E) 64,046.38

A.4.6.2.8 Pemasangan 1 buah spring knip


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang Kayu L.02 OH 0.200 160,000.00 32,000.00
Kepala Tukang L.03 OH 0.002 180,000.00 360.00
Mandor L.04 OH 0.0005 185,000.00 92.50
JUMLAH TENAGA KERJA 44,452.50
B BAHAN
Spring knip bh 1.000 30,900.00 30,900.00
JUMLAH TENAGA BAHAN 30,900.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 75,352.50


### E. Overhead & Profit 15% x D 11,302.88
F. Harga Satuan Pekerjaan (D+E) 86,655.38

A.4.6.2 - 2
A.4.6.2.9 Pemasangan 1 buah kait angin
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 120,000.00 1,800.00
Tukang Kayu L.02 OH 0.150 160,000.00 24,000.00
Kepala Tukang L.03 OH 0.015 180,000.00 2,700.00
Mandor L.04 OH 0.0080 185,000.00 1,480.00
JUMLAH TENAGA KERJA 29,980.00
B BAHAN
Kait angin stainless stell bh 1.000 29,200.00 29,200.00
JUMLAH TENAGA BAHAN 29,200.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 59,180.00


### E. Overhead & Profit 15% x D 8,877.00
F. Harga Satuan Pekerjaan (D+E) 68,057.00

A.4.6.2.10 Pemasangan 1 buah door closer


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 120,000.00 6,000.00
Tukang Kayu L.02 OH 0.500 160,000.00 80,000.00
Kepala Tukang L.03 OH 0.050 180,000.00 9,000.00
Mandor L.04 OH 0.0030 185,000.00 555.00
JUMLAH TENAGA KERJA 95,555.00
B BAHAN
Door closer kw 2 bh 1.000 534,000.00 534,000.00
JUMLAH TENAGA BAHAN 534,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 629,555.00


### E. Overhead & Profit 15% x D 94,433.25
F. Harga Satuan Pekerjaan (D+E) 723,988.25

A.4.6.2.11 Pemasangan 1 buah kunci slot


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 120,000.00 2,400.00
Tukang Kayu L.02 OH 0.200 160,000.00 32,000.00
Kepala Tukang L.03 OH 0.020 180,000.00 3,600.00
Mandor L.04 OH 0.0010 185,000.00 185.00
JUMLAH TENAGA KERJA 38,185.00
B BAHAN
Kunci slot stainless stell bh 1.000 61,700.00 61,700.00
JUMLAH TENAGA BAHAN 61,700.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 99,885.00


### E. Overhead & Profit 15% x D 14,982.75
F. Harga Satuan Pekerjaan (D+E) 114,867.75

A.4.6.2 - 3
A.4.6.2 .12 Pemasangan 1 buah Door handle
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.050 120,000.00 6,000.00
Tukang Kayu L.02 OH 0.500 160,000.00 80,000.00
Kepala Tukang L.03 OH 0.050 180,000.00 9,000.00
Mandor L.04 OH 0.0030 185,000.00 555.00
JUMLAH TENAGA KERJA 95,555.00
B BAHAN
Door handle bh 1.000 129,300.00 129,300.00
JUMLAH TENAGA BAHAN 129,300.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 224,855.00


### E. Overhead & Profit 15% x D 33,728.25
F. Harga Satuan Pekerjaan (D+E) 258,583.25

A.4.6.2 .13 Pemasangan 1 buah door stop


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang Kayu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.0050 185,000.00 925.00
JUMLAH TENAGA KERJA 19,925.00
B BAHAN
Door stop bh 1.000 118,000.00 118,000.00
JUMLAH TENAGA BAHAN 118,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 137,925.00


### E. Overhead & Profit 15% x D 20,688.75
F. Harga Satuan Pekerjaan (D+E) 158,613.75

A.4.6.2 .17 Pemasangan 1 m2 kaca tebal 5 mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.015 120,000.00 1,800.00
Tukang Kaca L.02 OH 0.150 160,000.00 24,000.00
Kepala Tukang L.03 OH 0.015 180,000.00 2,700.00
Mandor L.04 OH 0.0008 185,000.00 148.00
JUMLAH TENAGA KERJA 28,648.00
B BAHAN
Kaca tebal 5 mm m2 1.100 123,300.00 135,630.00
Sealent bh 0.050 35,600.00 1,780.00
JUMLAH TENAGA BAHAN 137,410.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 166,058.00


### E. Overhead & Profit 15% x D 24,908.70
F. Harga Satuan Pekerjaan (D+E) 190,966.70

A.4.6.2 - 4
A.4.6.2 .18 Pemasangan 1 m2 kaca tebal 8 mm
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.017 120,000.00 2,040.00
Tukang Kayu L.02 OH 0.170 160,000.00 27,200.00
Kepala Tukang L.03 OH 0.017 180,000.00 3,060.00
Mandor L.04 OH 0.0009 185,000.00 166.50
JUMLAH TENAGA KERJA 32,466.50
B BAHAN
Kaca tebal 8 mm m2 1.100 197,300.00 217,030.00
Sealent bh 0.070 35,600.00 2,492.00
JUMLAH TENAGA BAHAN 219,522.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 251,988.50


### E. Overhead & Profit 15% x D 37,798.28
F. Harga Satuan Pekerjaan (D+E) 289,786.78

A.4.6.2 .19 Pemasangan 1 m2 kaca tebal 12 mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.025 120,000.00 3,000.00
Tukang Kayu L.02 OH 0.250 160,000.00 40,000.00
Kepala Tukang L.03 OH 0.025 180,000.00 4,500.00
Mandor L.04 OH 0.0013 185,000.00 240.50
JUMLAH TENAGA KERJA 47,740.50
B BAHAN
Kaca tebal 12 mm m2 1.100 623,200.00 685,520.00
Sealent bh 0.070 35,600.00 2,492.00
JUMLAH TENAGA BAHAN 688,012.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 735,752.50


### E. Overhead & Profit 15% x D 110,362.88
F. Harga Satuan Pekerjaan (D+E) 846,115.38

A.4.6.2 .23 Pemasangan 1 m2 kaca patri tebal 5 mm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.075 120,000.00 9,000.00
Tukang Kayu L.02 OH 0.150 160,000.00 24,000.00
Kepala Tukang L.03 OH 0.015 180,000.00 2,700.00
Mandor L.04 OH 0.0040 185,000.00 740.00
JUMLAH TENAGA KERJA 36,440.00
B BAHAN
Kaca patri 5 mm m2 1.100 2,196,100.00 2,415,710.00
Sealent bh 0.050 35,600.00 1,780.00
JUMLAH TENAGA BAHAN 2,417,490.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 2,453,930.00


### E. Overhead & Profit 15% x D 368,089.50
F. Harga Satuan Pekerjaan (D+E) 2,822,019.50

A.4.6.2 - 5
A.4.7.1. HARGA SATUAN PEKERJAAN PENGECATAN

A.4.7.1.1. 1 m2 Pengikisan/pengerokan permukaan cat lama


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.150 120,000.00 18,000.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 18,555.00
B BAHAN
Soda api bh 0.050 47,500.00 2,375.00
JUMLAH TENAGA BAHAN 2,375.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 20,930.00


### E. Overhead & Profit 15% x D 3,139.50
F. Harga Satuan Pekerjaan (D+E) 24,069.50

PEMBANGUNAN GEDUNG BERTINGKAT 2 LANTAI


A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.070 120,000.00 8,400.00
Tukang cat L.02 OH 0.009 160,000.00 1,440.00
Kepala tukang L.03 OH 0.006 180,000.00 1,080.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 11,475.00
B BAHAN
Cat menie kg 0.200 60,700.00 12,140.00
Plamir kg 0.150 21,400.00 3,210.00
Cat dasar kg 0.170 51,000.00 8,670.00
Cat penutup kg 0.260 77,300.00 20,098.00
Kuas bh 0.010 11,900.00 119.00
Pengencer kg 0.030 39,200.00 1,176.00
Amplas Lbr 0.200 9,500.00 1,900.00
JUMLAH TENAGA BAHAN 47,313.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 58,788.00


### E. Overhead & Profit 15% x D 8,818.20
F. Harga Satuan Pekerjaan (D+E) 67,606.20

A.4.7.1.10. Pengecatan 1 m2 tembok baru untuk interior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat
penutup)
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 120,000.00 2,400.00
Tukang cat L.02 OH 0.063 160,000.00 10,080.00
Kepala tukang L.03 OH 0.0063 180,000.00 1,134.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 14,169.00
B BAHAN
Plamir L 0.100 21,400.00 2,140.00
Cat dasar Kg 0.100 51,000.00 5,100.00
Cat penutup kg 0.260 77,300.00 20,098.00
JUMLAH TENAGA BAHAN 27,338.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -
D. Jumlah (A+B+C) 41,507.00
### E. Overhead & Profit 15% x D 6,226.05
F. Harga Satuan Pekerjaan (D+E) 47,733.05

A.4.7.1 - 1
Pengecatan 1 m2 tembok baru untuk exterior ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat
An. 4.7.1.11.
penutup)

No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.020 120,000.00 2,400.00
Tukang cat L.02 OH 0.063 160,000.00 10,080.00
Kepala tukang L.03 OH 0.0063 180,000.00 1,134.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 14,169.00
B BAHAN
Plamir L 0.100 21,400.00 2,140.00
Cat dasar Kg 0.100 51,000.00 5,100.00
Cat tembok eksterior L 0.260 109,200.00 28,392.00
JUMLAH TENAGA BAHAN 35,632.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 49,801.00


### E. Overhead & Profit 15% x D 7,470.15
F. Harga Satuan Pekerjaan (D+E) 57,271.15

An. 4.7.1.12. Pengecatan 1 m2 plafond (2 lapis cat penutup)


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.028 120,000.00 3,360.00
Tukang cat L.02 OH 0.042 160,000.00 6,720.00
Kepala tukang L.03 OH 0.0042 180,000.00 756.00
Mandor L.04 OH 0.003 185,000.00 555.00
JUMLAH TENAGA KERJA 11,391.00
B BAHAN
Cat tembok interior Lbr 0.180 33,200.00 5,976.00
JUMLAH TENAGA BAHAN 5,976.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 17,367.00


### E. Overhead & Profit 15% x D 2,605.05
F. Harga Satuan Pekerjaan (D+E) 19,972.05

A.4.7.1 - 2
A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.5.1.1.2. Pemasangan 1 buah closed jongkok
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.000 120,000.00 120,000.00
Tukang batu L.02 OH 1.500 160,000.00 240,000.00
Kepala Tukang L.03 OH 0.150 180,000.00 27,000.00
Mandor L.04 OH 0.160 185,000.00 29,600.00
JUMLAH TENAGA KERJA 416,600.00
B BAHAN
Closed jongkok unit 1.000 387,000.00 387,000.00
Semen Portland kg 6.000 1,472.00 8,832.00
Pasir pasang m3 0.010 145,000.00 1,450.00
JUMLAH TENAGA BAHAN 397,282.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 813,882.00


### E. Overhead & Profit 15% x D 122,082.30
F. Harga Satuan Pekerjaan (D+E) 935,964.30
A.5.1.1.5. Pemasangan 1 buah wastafel
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 1.200 120,000.00 144,000.00
Tukang batu L.02 OH 1.450 160,000.00 232,000.00
Kepala Tukang L.03 OH 0.150 180,000.00 27,000.00
Mandor L.04 OH 0.060 185,000.00 11,100.00
JUMLAH TENAGA KERJA 414,100.00
B BAHAN
Wastafel unit 1.000 890,300.00 890,300.00
Semen Portland kg 6.000 1,472.00 8,832.00
Pasir pasang m3 0.010 145,000.00 1,450.00
Perlengkapan (siphon, kran, stop
% 12.000 106,836.00
kran, flexible)
JUMLAH TENAGA BAHAN 1,007,418.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,421,518.00


### E. Overhead & Profit 15% x D 213,227.70
F. Harga Satuan Pekerjaan (D+E) 1,634,745.70

A.5.1.1.7. Pemasangan 1 buah bak fibreglass Uk. 70x70x66cm


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.300 120,000.00 36,000.00
Tukang batu L.02 OH 0.450 160,000.00 72,000.00
Kepala Tukang L.03 OH 0.045 180,000.00 8,100.00
Mandor L.04 OH 0.900 185,000.00 166,500.00
JUMLAH TENAGA KERJA 282,600.00
B BAHAN
Bak fibreglass unit 1.000 777,500.00 777,500.00
Perlengkapan Ls 12%xbak 93,300.00
JUMLAH TENAGA BAHAN 870,800.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 1,153,400.00


### E. Overhead & Profit 15% x D 173,010.00
F. Harga Satuan Pekerjaan (D+E) 1,326,410.00
A.5.1.1.14. Pemasangan 1 buah floor drain stainless steel
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang batu L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 19,925.00
B BAHAN
Floor drain unit 1.000 296,700.00 296,700.00
JUMLAH TENAGA BAHAN 296,700.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 316,625.00


### E. Overhead & Profit 15% x D 47,493.75
F. Harga Satuan Pekerjaan (D+E) 364,118.75
A.5.1.1.19. Pemasangan 1 buah kran diameter 1/2" atau 3/4"
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.010 120,000.00 1,200.00
Tukang L.02 OH 0.100 160,000.00 16,000.00
Kepala Tukang L.03 OH 0.040 180,000.00 7,200.00
Mandor L.04 OH 0.005 185,000.00 925.00
JUMLAH TENAGA KERJA 25,325.00
B BAHAN
Kran air m 1.000 50,600.00 50,600.00
Sealtape Buah 0.025 4,200.00 105.00
JUMLAH TENAGA BAHAN 50,705.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 76,030.00


### E. Overhead & Profit 15% x D 11,404.50
F. Harga Satuan Pekerjaan (D+E) 87,434.50

A.5.1.1.25. Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.036 120,000.00 4,320.00
Tukang batu L.02 OH 0.060 160,000.00 9,600.00
Kepala Tukang L.03 OH 0.006 180,000.00 1,080.00
Mandor L.04 OH 0.002 185,000.00 370.00
JUMLAH TENAGA KERJA 15,370.00
B BAHAN
Pipa PVC tipe AW 1/2" m 1.200 7,125.00 8,550.00
Perlengkapan Ls 35%xpipa 2,992.50
JUMLAH TENAGA BAHAN 11,542.50
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 26,912.50


### E. Overhead & Profit 15% x D 4,036.88
F. Harga Satuan Pekerjaan (D+E) 30,949.38
A.5.1.1.26. Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.036 120,000.00 4,320.00
Tukang batu L.02 OH 0.060 160,000.00 9,600.00
Kepala Tukang L.03 OH 0.006 180,000.00 1,080.00
Mandor L.04 OH 0.002 185,000.00 370.00
JUMLAH TENAGA KERJA 15,370.00
B BAHAN
Pipa PVC tipe AW 3/4" m 1.200 9,500.00 11,400.00
Perlengkapan Ls 35%xpipa 3,990.00
JUMLAH TENAGA BAHAN 15,390.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 30,760.00


### E. Overhead & Profit 15% x D 4,614.00
F. Harga Satuan Pekerjaan (D+E) 35,374.00
An.5.1.1.14. Pemasangan 1 m' pipa PVC tipe DW diameter 3"
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang batu L.02 OH 0.135 160,000.00 21,600.00
Kepala Tukang L.03 OH 0.0135 180,000.00 2,430.00
Mandor L.04 OH 0.004 185,000.00 740.00
JUMLAH TENAGA KERJA 34,490.00
B BAHAN
Pipa PVC tipe AW 3" m 1.200 54,900.00 65,880.00
Perlengkapan Ls 35%xpipa 19,215.00
JUMLAH TENAGA BAHAN 85,095.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 119,585.00


### E. Overhead & Profit 15% x D 17,937.75
F. Harga Satuan Pekerjaan (D+E) 137,522.75

An.5.1.1.15. Pemasangan 1 m' pipa PVC tipe DW diameter 4"


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.081 120,000.00 9,720.00
Tukang batu L.02 OH 0.135 160,000.00 21,600.00
Kepala Tukang L.03 OH 0.0135 180,000.00 2,430.00
Mandor L.04 OH 0.004 185,000.00 740.00
JUMLAH TENAGA KERJA 34,490.00
B BAHAN
Pipa PVC tipe AW 4" m 1.200 94,975.00 113,970.00
Perlengkapan Ls 35%xpipa 33,241.25
JUMLAH TENAGA BAHAN 147,211.25
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 181,701.25


### E. Overhead & Profit 15% x D 27,255.19
F. Harga Satuan Pekerjaan (D+E) 208,956.44
HARGA SATUAN PEKERJAAN LAIN-LAIN

1
Pemasangan 1 m2 rangka atap baja ringan SNI dihitung dan desain dengan program khusus oleh Vendor
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.200 120,000.00 24,000.00
Tukang L.02 OH 0.450 160,000.00 72,000.00
Kepala Tukang L.03 OH 0.010 180,000.00 1,800.00
Mandor L.04 OH 0.050 185,000.00 9,250.00
JUMLAH TENAGA KERJA 107,050.00
B BAHAN
Profil C 75.75 m 1.778 19,400.00 34,484.21
Reng AZ 0,55mm x 6m m 5.400 8,900.00 48,060.00
Screw bh 38.000 200.00 7,600.00
Dynabolt bh 1.600 16,000.00 25,600.00

JUMLAH TENAGA BAHAN 115,744.21


C. PERALATAN
-
PEMBANGUNAN GEDUNG
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 222,794.21


### E. Overhead & Profit 15% x D 33,419.13
F. Harga Satuan Pekerjaan (D+E) 256,213.34

2. Pemasangan 1 m2 paving blok persegi panjang t. 8 cm mutu K200


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 120,000.00 42,000.00
Tukang L.02 OH 160,000.00 -
Kepala Tukang L.03 OH 180,000.00 -
Mandor L.04 OH 0.018 185,000.00 3,237.50
JUMLAH TENAGA KERJA 45,237.50
B BAHAN
Persegi panjang t. 8 cm bh 44.000 3,850.00 169,400.00
Pasir m3 0.100 105,000.00 10,500.00
JUMLAH TENAGA BAHAN 179,900.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 225,137.50


### E. Overhead & Profit 15% x D 33,770.63
F. Harga Satuan Pekerjaan (D+E) 258,908.13

3. Pemasangan 1 m2 paving blok persegi panjang warna t. 8 cm mutu K200


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 120,000.00 42,000.00
Tukang L.02 OH 160,000.00 -
Kepala Tukang L.03 OH 180,000.00 -
Mandor L.04 OH 0.018 185,000.00 3,237.50
JUMLAH TENAGA KERJA 45,237.50
B BAHAN
Persegi panjang t. 8 cm bh 44.000 4,400.00 193,600.00
Pasir m3 0.100 105,000.00 10,500.00
JUMLAH TENAGA BAHAN 204,100.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 249,337.50


### E. Overhead & Profit 15% x D 37,400.63
F. Harga Satuan Pekerjaan (D+E) 286,738.13

TAKSIR - 1
4. Pemasangan 1 m2 paving blok segienam t. 8 cm mutu K200
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 120,000.00 42,000.00
Tukang L.02 OH 160,000.00 -
Kepala Tukang L.03 OH 180,000.00 -
Mandor L.04 OH 0.018 185,000.00 3,237.50
JUMLAH TENAGA KERJA 45,237.50
B BAHAN
Paving blok segienam t. 8 cm bh 37.000 5,000.00 185,000.00
Pasir m3 0.100 105,000.00 10,500.00
JUMLAH TENAGA BAHAN 195,500.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 240,737.50


### E. Overhead & Profit 15% x D 36,110.63
F. Harga Satuan Pekerjaan (D+E) 276,848.13

5. Pemasangan 1 m2 paving blok segienam warna t. 8 cm mutu K200


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.350 120,000.00 42,000.00
Tukang L.02 OH 160,000.00 -
Kepala Tukang L.03 OH 180,000.00 -
Mandor L.04 OH 0.018 185,000.00 3,237.50
JUMLAH TENAGA KERJA 45,237.50
B BAHAN
Paving blok segienam t. 8 cm bh 37.000 5,700.00 210,900.00
Pasir m3 0.100 105,000.00 10,500.00
JUMLAH TENAGA BAHAN 221,400.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 266,637.50


### E. Overhead & Profit 15% x D 39,995.63
F. Harga Satuan Pekerjaan (D+E) 306,633.13

6. Pemasangan 1 titik nyala Lampu


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 120,000.00 -
Tukang L.02 OH 0.1350 160,000.00 21,600.00
Kepala Tukang L.03 OH 0.0135 180,000.00 2,430.00
Mandor L.04 OH 0.0050 185,000.00 925.00
JUMLAH TENAGA KERJA 24,955.00
B BAHAN
NYM 2 x 2,5 mm2 m 15.000 16,000.00 240,000.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 84,000.00
JUMLAH TENAGA BAHAN 324,000.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 348,955.00


### E. Overhead & Profit 15% x D 52,343.25
F. Harga Satuan Pekerjaan (D+E) 401,298.25

TAKSIR - 2
7. Pemasangan 1 titik nyala stop kontak
No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 120,000.00 -
Tukang L.02 OH 0.1350 160,000.00 21,600.00
Kepala Tukang L.03 OH 0.0135 180,000.00 2,430.00
Mandor L.04 OH 0.0050 185,000.00 925.00
JUMLAH TENAGA KERJA 24,955.00
B BAHAN
NYM 3 x 2,5 mm2 m 15.000 17,800.00 267,000.00
Perlengkapan ( 35% harga conduit,klem,isolasi ) 93,450.00
JUMLAH TENAGA BAHAN 360,450.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 385,405.00


### E. Overhead & Profit 15% x D 57,810.75
F. Harga Satuan Pekerjaan (D+E) 443,215.75

8. Pemasangan 1 M2 Plafond PVC


No. Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp)
A. TENAGA
Pekerja L.01 OH 0.100 120,000.00 12,000.00
Tukang L.02 OH 0.0500 160,000.00 8,000.00
Kepala Tukang L.03 OH 0.0050 180,000.00 900.00
Mandor L.04 OH 0.0050 185,000.00 925.00
JUMLAH TENAGA KERJA 21,825.00
B BAHAN
Bahan PVC L=20 cm M' 1.100 59,600.00 65,560.00
List Profil utk PCV M' 0.350 54,000.00 18,900.00
List Siku utk PVC M' 0.500 46,000.00 23,000.00
List Sambung utk PVC M' 0.650 46,000.00 29,900.00
Lem Silikon Kg 0.150 115,000.00 17,250.00
JUMLAH TENAGA BAHAN 154,610.00
C. PERALATAN
-
JUMLAH TENAGA ALAT -

D. Jumlah (A+B+C) 176,435.00


E. Overhead & Profit 15% x D 26,465.25
F. Harga Satuan Pekerjaan (D+E) 202,900.25

TAKSIR - 3
HARGA SATUAN PEKERJAAN LAIN-LAIN

TAKSIR - 9 Pemasangan Kusen dan jendela alumunium kaca (bag. depan) J3


1 Unit Jendela Type J1 (3 lbg 60 x 90/50) ukuran dalam
Kusen Alumunium silver 4" M1 12.75 63,800.00 813,450.00
Aluminium strip M1 14.88 44,800.00 666,624.00
Kaca polos clear 5 mm M2 1.42 123,300.00 175,332.60
Karet kaca M1 11.88 3,500.00 41,580.00
Casement 16" SET 6.00 155,000.00 930,000.00
Casement 8" SET 6.00 57,700.00 346,200.00
Rambuncis/grendel jendela SET 12.00 39,900.00 478,800.00
Dinabolt dia. 12 mm BH 8.00 16,000.00 128,000.00
Pengisian aduk 3 sisi LS 3.00 35,000.00 105,000.00
3,684,986.60
- Upah pasang 25% acs LS 1.00 921,246.65 921,246.65
4,606,233.25

TAKSIR - 10 Pemasangan Kusen dan jendela alumunium kaca (bag. depan) J2


1 Unit Jendela Type J2 (2 lbg 60 x 90/50) ukuran dalam
Kusen Alumunium silver 4" M1 7.20 63,800.00 459,360.00
Aluminium strip M1 9.92 44,800.00 444,416.00
Kaca polos clear 5 mm M2 0.95 123,300.00 116,888.40
Karet kaca M1 7.92 3,500.00 27,720.00
Casement 16" SET 4.00 155,000.00 620,000.00
Casement 8" SET 4.00 57,700.00 230,800.00
Rambuncis/grendel jendela SET 8.00 39,900.00 319,200.00
Dinabolt dia. 12 mm BH 8.00 16,000.00 128,000.00
Pengisian aduk 3 sisi LS 3.00 35,000.00 105,000.00
2,451,384.40
- Upah pasang 25% acs LS 1.00 612,846.10 612,846.10
3,064,230.50

TAKSIR - 11 Pemasangan Kusen dan jendela alumunium kaca (bag. depan) J1


1 Unit Jendela Type J1 (1 lbg 60 x 90/50) ukuran dalam
Kusen Alumunium silver 4" M1 4.90 63,800.00 312,620.00
Aluminium strip M1 9.92 44,800.00 444,416.00
Kaca polos clear 5 mm M2 0.47 123,300.00 58,444.20
Karet kaca M1 3.96 3,500.00 13,860.00
Casement 16" SET 2.00 155,000.00 310,000.00
Casement 8" SET 2.00 57,700.00 115,400.00
Rambuncis/grendel jendela SET 1.00 39,900.00 39,900.00
Dinabolt dia. 12 mm BH 4.00 16,000.00 64,000.00
Pengisian aduk 3 sisi LS 3.00 35,000.00 105,000.00
1,463,640.20
- Upah pasang 25% acs LS 1.00 365,910.05 365,910.05
1,829,550.25

TAKSIR - 12 Pemasangan Kusen dan jendela alumunium kaca (bag. BELAKANG) B3


1 Unit Jendela Type B3 (3 lbg 60 x 100/50) ukuran dalam
Kusen Alumunium silver 4" M1 5.52 63,800.00 352,176.00
Aluminium strip M1 6.42 44,800.00 287,616.00
Kaca polos clear 5 mm M2 0.65 123,300.00 79,898.40
Karet kaca M1 4.86 3,500.00 17,010.00
Casement 8" SET 6.00 57,700.00 346,200.00
Rambuncis/grendel jendela SET 3.00 39,900.00 119,700.00
Dinabolt dia. 12 mm BH 8.00 16,000.00 128,000.00
Pengisian aduk 3 sisi LS 3.00 35,000.00 105,000.00
1,435,600.40
- Upah pasang 25% acs LS 1.00 358,900.10 358,900.10
1,794,500.50
TAKSIR - 13 Pemasangan Kusen dan jendela alumunium kaca (bag. BELAKANG) B2
1 Unit Jendela Type B2 (2 lbg 60 x 100/50) ukuran dalam
Kusen Alumunium silver 4" M1 4.90 63,800.00 312,620.00
Aluminium strip M1 4.28 44,800.00 191,744.00
Kaca polos clear 5 mm M2 0.43 123,300.00 53,265.60
Karet kaca M1 3.24 3,500.00 11,340.00
Casement 8" SET 4.00 57,700.00 230,800.00
Rambuncis/grendel jendela SET 2.00 39,900.00 79,800.00
Dinabolt dia. 12 mm BH 6.00 16,000.00 96,000.00
Pengisian aduk 3 sisi LS 3.00 35,000.00 105,000.00
1,080,569.60
- Upah pasang 25% acs LS 1.00 270,142.40 270,142.40
1,350,712.00