REKAPITULASI

RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN GEDUNG DAN FASILITAS BALAI NIKAH DAN MANASIK HAJI KEC. LALABATA
LOKASI : KEC. LALABATA, KAB. SOPPENG
INSTANSI : KEMENTRIAN AGAMA
KOTA/KAB : KAB. SOPPENG
PROVINSI : SULAWESI SELATAN
TAHUN ANGGARAN
: 2016

NO URAIAN PEKERJAAN TOTAL HARGA

I PEKERJAAN PERSIAPAN Rp 9,000,000.00


II PEKERJAAN TANAH, PASIR DAN LANTAI KERJA Rp 84,015,559.25
III PEKERJAAN PONDASI Rp 46,240,226.59
IV PEKERJAAN STRUKTUR BETON Rp 72,668,580.29
V PEKERJAAN PASANGAN DINDING Rp 58,997,818.46
VI PEKERJAAN TEGEL KERAMIK Rp 77,780,291.43
VII PEK.KUSEN, PINTU, DAN JENDELA KAYU KLS I Rp 57,981,278.36
VIII PEKERJAAN PLAFOND Rp 37,865,988.70
IX PEKERJAAN KUDA-KUDA DAN ATAP Rp 113,265,273.86
X PEKERJAAN PENGECATAN Rp 15,047,156.28
XI PEKERJAAN INSTALASI LISTRIK Rp 11,751,050.00
XII PEKERJAAN PLAMBING / SANITASI Rp 30,544,571.67
XIII PEKERJAAN SALURAN KELILING Rp 21,540,268.73
XIV PEKERJAAN SERBA-SERBI Rp 7,024,008.31
XV PEKERJAAN PAGAR BELAKANG
I PEKERJAAN PEMBONGKARAN PAGAR Rp 1,500,000.00
II PEKERJAAN PONDASI BETON TELAPAK (POER) PAGAR Rp 22,207,139.53
III PEKERJAAN STRUKTUR BETON PAGAR Rp 13,527,718.86
IV PEKERJAAN PASANGAN DINDING PAGAR Rp 14,452,148.31
V PEKERJAAN PENGECATAN DINDING PAGAR Rp 1,864,008.09
Jumlah Rp 697,273,086.70

REAL COST Rp. 697,273,086.70

PPN 10 % Rp. 69,727,308.67

IMB Rp. 3,000,000.00

TOTAL Rp. 770,000,395.37

DIBULATKAN Rp. 770,000,000.00

Terbilang : Tujuh Ratus Tujuh Puluh Juta Rupiah

Soppeng, Maret 2016


Diketahui, Konsultan Perencana
PEJABAT PEMBUAT KOMITMEN CV. DACON

Hj. NURAHMI, SE MUH. FAISAL


NIP : 19670321 198903 2002 Team Leader

Diperiksa, Disetujui,
KEPALA DINAS PEKERJAAN UMUM KUASA PENGGUNA ANGGARAN

Ir. A. RISAL, MT Dr. H. HUZAEMAH, MAg


NIP : 19621231 199303 1025 NIP : 19621231 199303 1025
RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN : PEMBANGUNAN GEDUNG DAN FASILITAS BALAI NIKAH DAN MANASIK HAJI KEC. LALABATA
LOKASI : KEC. LALABATA, KAB. SOPPENG
INSTANSI : KEMENTRIAN AGAMA
KOTA/KAB : KAB. SOPPENG
PROVINSI : SULAWESI SELATAN
TAHUN ANGGARAN : 2016

HARGA SAT. JML.HARGA TOTAL HARGA


NO URAIAN PEKERJAAN SAT VOLUME KODE
(RP) (RP) (RP)
I PEKERJAAN PERSIAPAN
I.1 PEKERJAAN PERSIAPAN
1 Pengukuran / pas Bouwplank Ls 1.000 - 750,000.00 750,000.00
2 Perancah / Kasteling kerja Ls 1.000 - 2,250,000.00 2,250,000.00
3 Dokumentasi, Laporan Ls 1.000 - 1,000,000.00 1,000,000.00
4 Pekerjaan Direksi Keet Ls 1.000 - 5,000,000.00 5,000,000.00
9,000,000.00
II PEKERJAAN TANAH, PASIR DAN LANTAI KERJA
II.1 PEKERJAAN TANAH, PASIR DAN LANTAI KERJA
1 Pek. Galian Tanah Pondasi m3 89.987 A.1 60,000.00 5,399,208.00
2 Pekerjaan Urugan tanah Kembali m3 29.996 A.2 20,000.00 599,912.00
3 Pekerjaan Urugan pasir dibawah lantai & Selasar t= 10 cm m3 29.025 A.3 220,800.00 6,408,720.00
4 Pekerjaan Urugan Tanah dibawah lantai & Halaman m3 286.866 A.4 176,400.00 50,603,127.12
5 Pek. Urugan Pasir dibawah Pondasi Garis = 5 cm m3 7.080 A.3 220,800.00 1,563,264.00
6 Pekerjaan Rabat Lantai Tbl = 7 cm m3 20.318 F. 1 956,876.00 19,441,328.13
84,015,559.25
III PEKERJAAN PONDASI
III.1 PONDASI BATU GUNUNG/ BATU KALI
1 Pekerjaan Pas.Batu kosong m3 25.488 B.1 455,673.00 11,614,193.42
2 Pekerjaan Pas.Pondasi batu gunung/Batu Kali 1: 5 m3 47.082 B.2 735,441.00 34,626,033.16
46,240,226.59
IV PEKERJAAN STRUKTUR BETON
IV.1 PEKERJAAN SLOEF BETON
1 Pekerjaan Beton Sloef 15 x 20 cm m3 4.248 F.3 4,345,728.32 18,460,653.90
IV.2 PEKERJAAN KOLOM BETON
1 Pekerjaan Beton Kolom 15 x 15 cm m3 3.398 F.5 5,914,803.32 20,095,544.27
2 Pekerjaan Beton Kolom 20 x 20 cm m3 0.880 F.5 5,914,803.32 5,205,026.92
IV.3 PEKERJAAN RINGBALK BETON
1 Pekerjaan Ringbalk 15 x 15 cm m3 3.186 F.4 5,865,278.32 18,686,776.72
2 Pekerjaan Balok (Balok Teras) 15 x 25 cm m3 0.319 F.4 5,865,278.32 1,869,557.46
IV.4 PEKERJAAN PLAT BETON
1 Pek. Plat Konsol Teras Tbl = 10 cm m3 0.627 F.6 4,046,060.42 2,537,891.40
2 Pek. Plat Konsol di atas kusen Tbl = 10 cm m3 1.271 F.6 4,046,060.42 5,142,542.79
IV PEKERJAAN PONDASI BETON TELAPAK (POER)
1 Pek. Rabat Beton Lantai Kerja Pondasi Telapak (POER) m3 0.072 F. 1 956,876.00 68,895.07
2 Pek. Beton Pondasi Telapak (Poer) 0. 5 x 0. 5 x 0,15 Meter m3 0.150 F.2 4,011,278.32 601,691.75
72,668,580.29
V PEKERJAAN PASANGAN DINDING
V.1 PEKERJAAN DINDING 1Pc : 4 Ps
1 Pekerjaan Pasangan Dinding Batu Bata (1/2 Bata) m2 209.400 C.2 105,708.25 22,135,307.55
2 Pekerjaan Plesteran Dinding tebal 1.5 cm m2 392.438 D.2 52,971.00 20,787,806.81
3 Pekerjaan Profil Beton Keliling Bangunan m' 62.000 - 35,000.00 2,170,000.00
4 Pekerjaan Penebalan Dinding Ls 1.000 - 1,500,000.00 1,500,000.00
V.2 PEKERJAAN FINISHING DINDING
1 Pekerjaan Acian m2 392.438 D.3 31,609.38 12,404,704.10
58,997,818.46
HARGA SAT. JML.HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOLUME KODE
(RP) (RP) (RP)

VI PEKERJAAN TEGEL KERAMIK

VI.1 PEKERJAAN TEGEL LANTAI KERAMIK


1 Pekerjaan Tegel Lantai Keramik Warna (60 / 60) m2 193.938 G.2 314,055.00 60,907,041.56
2 Pekerjaan Tegel Lantai Keramik Warna Motif (60 / 60) Teras m2 9.000 G.2 314,055.00 2,826,495.00
3 Pek. Tegel Lantai Keramik Warna Kamar mandi & T. Wudhu (25 / 25) m2 5.313 G.1 158,755.00 843,385.94
4 Pekerjaan Tegel Dinding Keramik Warna Kamar mandi & T. Wudhu (25 / 40)
m2 21.600 G.3 229,706.75 4,961,665.80
5 Pekerjaan Pas. Keramik Motif Batu Alam m2 25.000 G.4 329,668.13 8,241,703.13
77,780,291.43
VII PEK.KUSEN, PINTU, DAN JENDELA KAYU KLS I
VII.1 PEKERJAAN KUSEN
1 Pekerjaan Kusen Pintu dan Jendela Kayu Kls I m3 1.270 E.1 12,879,875.00 16,354,221.28
2 Pekerjaan Daun Pintu Panel Kayu Kls I m2 24.432 E.2 739,500.00 18,067,168.20
3 Pekerjaan Daun Jendela Kaca Kayu Kls I m2 21.341 E.3 516,450.00 11,021,456.16
4 Pekerjaan Pasangan Kaca Mati T = 5 mm m2 13.779 L.6 158,362.50 2,182,045.22
5 Pintu Km/wc Aluminium Spanrill BH 2.000 H.BHN 900,000.00 1,800,000.00
VII.2 PEKERJAAN GANTUNGAN PINTU
1 Pekerjaan Pasangan Kunci Pintu Bh 12.000 L.1 228,250.00 2,739,000.00
2 Pekerjaan Pasangan Engsel Pintu Bh 39.000 L.2 56,112.50 2,188,387.50
3 Pekerjaan Pasangan Engsel Jendela Bh 40.000 L.3 40,575.00 1,623,000.00
4 Pekerjaan Pasangan Grendel Jendela Bh 20.000 L.4 28,075.00 561,500.00
5 Pekerjaan Pasangan Hak Angin Kait-kait Jendela Bh 40.000 L.5 36,112.50 1,444,500.00
57,981,278.36
VIII PEKERJAAN PLAFOND
VIII.1 PEKERJAAN RANGKA & PLAFOND
1 Pekerjaan Pas. Rangka Plafond Hollow m2 266.347 - 98,200.00 26,155,226.30
2 Pekerjaan Pas. Plafond Gipsum m2 213.563 I.2 43,832.00 9,360,871.50
3 Pekerjaan Pas. Plafond Calsiboard m2 52.784 I.1 44,519.00 2,349,890.90
37,865,988.70
IX PEKERJAAN KUDA-KUDA DAN ATAP
IX.1 PEKERJAAN KUDA-KUDA
1 Pekerjaan Pas. Rangka Atap (Kap kuda-kuda) Baja Ringan m2 317.350 - 213,500.00 67,754,225.00
2 Pekerjaan Pas. Listplank GRC Plat m' 88.440 E.4 58,364.34 5,161,742.61
IX.2 PEKERJAAN ATAP
1 Pekerjaan Pas. Atap Genteng Metal m2 317.350 H.1 115,725.00 36,725,328.75
2 Pek. Pas. Bubungan Dan Talang Jurai m' 59.950 H.2 60,450.00 3,623,977.50
113,265,273.86
X PEKERJAAN PENGECATAN
X.1 PEKERJAAN PENGECATAN DINDING
1 Pekerjaan Pengecatan Dinding Bangunan m2 392.438 M.1 15,858.50 6,223,470.09
X.2 PEKERJAAN PENGECATAN KAYU
1 Pekerjaan Pengecatan Kusen Pintu dan Jendela m2 67.720 M.3 32,210.00 2,181,261.20
2 Pekerjaan Pengecatan Daun Pintu m2 48.863 M.3 32,210.00 1,573,883.67
3 Pekerjaan Pengecatan Daun Jendela Kayu m2 8.536 M.3 32,210.00 274,954.87
4 Pekerjaan Pengecatan Listplank m2 17.688 M.3 32,210.00 569,730.48
X.3 PEKERJAAN PENGECATAN PLAFOND
1 Pekerjaan Pengecatan Plafon m2 266.347 M.2 15,858.50 4,223,855.97
15,047,156.28
HARGA SAT. JML.HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOLUME KODE
(RP) (RP) (RP)

XI PEKERJAAN INSTALASI LISTRIK

XI.1 SAMBUNGAN INSTALASI LISTRIK


1 Titik Nyala Ttk 22.000 J.1 190,400.00 4,188,800.00
2 MCB 3 Group Bh 1.000 J.5 186,750.00 186,750.00
XI.2 PEKERJAAN PAS. LAMPU DAN SAKLAR
1 Lampu Pijar Sumpit 9 watt Bh 7.000 H.Bah 36,000.00 252,000.00
3 Lampu Pijar Sumpit 18 watt Bh 10.000 H.Bah 41,250.00 412,500.00
3 Lampu Pijar Sumpit 20 watt Bh 5.000 H.Bah 57,000.00 285,000.00
4 Pasangan Saklar Ganda Bh 9.000 J.4 104,437.50 939,937.50
5 Pasangan Saklar Tunggal Bh 6.000 J.3 101,437.50 608,625.00
6 Pasangan Stop Kontak Bh 16.000 J.2 106,437.50 1,703,000.00
7 Pasangan Down light Bh 22.000 J.6 30,656.25 674,437.50
8 Penambahan Daya Listrik ls 1.000 - 2,500,000.00 2,500,000.00
11,751,050.00
XII PEKERJAAN PLAMBING / SANITASI
XII.1 PEKERJAAN PAS. KLOSET
1 Pasangan Kloset Duduk Bh 2.000 K.1 2,509,575.00 5,019,150.00
XII.2 PEKERJAAN PAS. ASSESORI PELENGKAP
1 Pekerjaan Pasangan Kran Air Bh 2.000 K.4 68,915.00 137,830.00
2 Pekerjaan Pasangan Kran Air Doble Bh 2.000 - 150,000.00 300,000.00
3 Pekerjaan Pasangan Shower Bh 2.000 - 250,000.00 500,000.00
4 Pekerjaan Pasangan Kran Air Leher Angsa Bh 1.000 - 75,000.00 75,000.00
5 Pekerjaan Pasangan Flor Drain Bh 3.000 K.3 48,750.00 146,250.00
6 Pekerjaan Pasangan Tempat Sabun Bh 2.000 K.8 64,450.00 128,900.00
7 Pekerjaan Pasangan Wastafel Zink Aluminium Dapur Bh 1.000 K.2 564,025.00 564,025.00
XII.3 PEKERJAAN PAS. PIPA PVC
1 Pekerjaan Pasangan Pipa Air Bersih 3/4" m' 40.000 K.5 17,082.50 683,300.00
2 Pekerjaan Pasangan Pipa Pembuangan Padat dia. 3" m' 36.000 K.7 82,715.00 2,977,740.00
3 Pekerjaan Pasangan Pipa Pembuangan Cair dia. 2" m' 44.000 K.6 44,675.83 1,965,736.67
4 Pekerjaan Septicktank Unit 1.000 - 2,500,000.00 2,500,000.00
5 Pekerjaan Sumur Bor + Pompa Air + Accessories ls 1.000 - 15,000,000.00 15,000,000.00
30,544,571.67
XIII PEKERJAAN SALURAN KELILING
XIII.1 PEKERJAAN TANAH, PASIR DAN LANTAI KERJA
1 Pek. Galian Tanah Saluran m3 4.422 A.1 60,000.00 265,320.00
2 Pekerjaan Urugan pasir dibawah Lantai Saluran t= 5 cm m3 1.843 A.3 220,800.00 406,824.00
3 Pekerjaan Rabat Lantai Tbl = 5 cm m3 1.843 F. 1 956,876.00 1,763,044.03
XIII.2 PONDASI BATU GUNUNG
1 Pekerjaan Pas.Pondasi Rollag 1/2 Bata m2 126.400 B.3 108,624.38 13,730,121.00
2 Pekerjaan Plesteran Dinding Saluran tebal 1.5 cm m2 63.200 D.2 52,971.00 3,347,767.20
3 Pekerjaan Acian Dinding Dan Lantai Saluran m2 63.200 D.3 31,609.38 1,997,712.50
21,540,268.73
XIV PEKERJAAN SERBA-SERBI
XIV.1 PEKERJAAN PLAT BETON MEJA DAPUR
1 Pekerjaan Pasangan Batu Bata m2 0.495 C.1 108,624.38 53,769.07
2 Pekerjaan Pelesteran m3 0.990 D.1 54,631.00 54,084.69
3 Pekerjaan Acian m2 0.990 D.3 31,609.38 31,293.28
4 Pekerjaan Plat Beton Meja Dapur m2 0.146 F.6 4,046,060.42 589,713.31
5 Keramik Lantai Meja Dapur 25x25 cm m2 1.325 G.1 158,755.00 210,350.38
6 Keramik Dinding Meja Dapur 25x40 cm m2 1.458 G.2 229,706.75 334,797.59
XIV.2 PEKERJAAN AKHIR
1 Pekerjaan Papan Nama Kantor (Bahan Stenlis Steel) Ls 1.000 - 3,750,000.00 3,750,000.00
2 Pembersihan Akhir Ls 1.000 - 2,000,000.00 2,000,000.00
7,024,008.31
HARGA SAT. JML.HARGA TOTAL HARGA
NO URAIAN PEKERJAAN SAT VOLUME KODE
(RP) (RP) (RP)
XV PEKERJAAN PAGAR BELAKANG
I PEKERJAAN PEMBONGKARAN PAGAR
1 Pek. Pembobokan Pondasi Lama ls 1.000 - 500,000.00 500,000.00
2 Pekerjaan Pembongkaran pagar lama ls 1.000 - 1,000,000.00 1,000,000.00
1,500,000.00
II PEKERJAAN PONDASI BETON TELAPAK (POER) PAGAR
1 Pekerjaan Pas. Pondasi Batu kali/gunung m3 28.600 B.2 735,441.00 21,033,612.60
2 Pek. Rabat Beton Lantai Kerja Pondasi Telapak (POER) m3 0.126 F. 1 956,876.00 120,566.38
3 Pek. Beton Pondasi Telapak (Poer) 0. 5 x 0. 5 x 0,15 Meter m3 0.263 F.2 4,011,278.32 1,052,960.56
22,207,139.53
III PEKERJAAN STRUKTUR BETON PAGAR
1 Pekerjaan Beton Sloef 15 x 20 cm m3 0.825 F.3 4,345,728.32 3,585,225.86
2 Pekerjaan Beton Kolom 20 x 20 cm m3 1.408 F.5 5,914,803.32 8,328,043.07
3 Pekerjaan Ringbalk 10 x 15 cm m3 0.413 F.7 3,913,818.00 1,614,449.93
13,527,718.86
IV PEKERJAAN PASANGAN DINDING PAGAR
1 Pekerjaan Pasangan Dinding Batu Bata m2 42.670 C.2 105,708.25 4,510,571.03
2 Pekerjaan Plesteran Dinding tebal 1.5 cm m2 85.340 D.2 52,971.00 4,520,545.14
3 Pekerjaan Plesteran Sloof, Kolom, Ringbalk m2 32.200 D.2 52,971.00 1,705,666.20
4 Pekerjaan Acian Sloof, Dinding, Kolom Dan Ringbalk m2 117.540 D.3 31,609.38 3,715,365.94
14,452,148.31
V PEKERJAAN PENGECATAN DINDING PAGAR
1 Pekerjaan Pengecatan Dinding Pagar, kolom, Ringbalk & sloof m2 117.540 M.1 15,858.50 1,864,008.09
1,864,008.09
ANALISA HARGA SATUAN DAN TENAGA KERJA

A. PEKERJAAN TANAH
A.1 MENGGALI 1 M3 TANAH
Tenaga
0.750 org/hr Pekerja @ Rp. 75,000.00 Rp. 56,250.00
0.025 org/hr Mandor @ Rp. 150,000.00 Rp. 3,750.00
Rp. 60,000.00
Rp. 60,000.00
A.2 MENGURUG KEMBALI 1 M3 GALIAN 13 DARI GALIAN
Tenaga
0.250 org/hr Pekerja @ Rp. 75,000.00 Rp. 18,750.00
0.008 org/hr Mandor @ Rp. 150,000.00 Rp. 1,250.00
Rp. 20,000.00
Rp. 20,000.00
A.3 MENGURUG 1 M3 PASIR URUG
Bahan
1.200 M3 Pasir urug @ Rp. 164,000.00 Rp. 196,800.00
Rp. 196,800.00
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.010 org/hr Mandor @ Rp. 150,000.00 Rp. 1,500.00
Rp. 24,000.00
Total Jumlah Rp. 220,800.00
A.4 MENGURUG 1 M3 TANAH URUG
Bahan
1.200 M3 Tanah Urug @ Rp. 127,000.00 Rp. 152,400.00
Rp. 152,400.00
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.010 org/hr Mandor @ Rp. 150,000.00 Rp. 1,500.00
Rp. 24,000.00
Total Jumlah Rp. 176,400.00

B. PEKERJAAN PONDASI
B.1 MEMEASANG 1 M3 BATU KOSONG (AANSTAMPING)
Bahan
1.200 M3 Batu Belah 15 / 20 cm @ Rp. 230,500.00 Rp. 276,600.00
0.432 M3 Pasir Urug @ Rp. 164,000.00 Rp. 70,848.00
Rp. 347,448.00
Tenaga
0.780 org/hr Pekerja @ Rp. 75,000.00 Rp. 58,500.00
0.390 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 39,000.00
0.039 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 4,875.00
0.039 org/hr Mandor @ Rp. 150,000.00 Rp. 5,850.00
Rp. 108,225.00
Total Jumlah Rp. 455,673.00
B.2 MEMASANG 1 M3 PONDASI BATU BELAH, CAMPURAN 1 PC : 5 PP
Bahan
1.200 M3 Batu Belah 15 cm / 20 cm @ Rp. 230,500.00 Rp. 276,600.00
136.000 Kg Semen Portland @ Rp. 1,187.50 Rp. 161,500.00
0.544 M3 Pasir Pasang @ Rp. 164,000.00 Rp. 89,216.00
Rp. 527,316.00
Tenaga
1.500 org/hr Pekerja @ Rp. 75,000.00 Rp. 112,500.00
0.750 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 75,000.00
0.075 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 9,375.00
0.075 org/hr Mandor @ Rp. 150,000.00 Rp. 11,250.00
Rp. 208,125.00
Total Jumlah Rp. 735,441.00
B.3 MEMASANG 1 M2 PASANGAN PONDASI BATU BATA (ROLAG) TEBAL 1/2 BATA, 1 PC : 3 PS
Bahan
70.000 Bh Batu Bata Standard @ Rp. 700.00 Rp. 49,000.00
14.370 Kg Semen Portland @ Rp. 1,187.50 Rp. 17,064.38
0.040 M3 Pasir Pasang @ Rp. 164,000.00 Rp. 6,560.00
Rp. 72,624.38
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.015 org/hr Mandor @ Rp. 150,000.00 Rp. 2,250.00
Rp. 36,000.00
Total Jumlah Rp. 108,624.38

C. PEKERJAAN DINDING
C.1 MEMASANG 1 M2 BATA MERAH UKURAN (5 X 11 X 22) CM TEBAL 1/2 BATA, CAMPURAN SPESI 1 PC : 3 PS
Bahan
70.000 M3 Batu Bata Standard @ Rp. 700.00 Rp. 49,000.00
14.370 Kg Semen Portland @ Rp. 1,187.50 Rp. 17,064.38
0.040 M3 Pasir Pasang @ Rp. 164,000.00 Rp. 6,560.00
Rp. 72,624.38
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.015 org/hr Mandor @ Rp. 150,000.00 Rp. 2,250.00
Rp. 36,000.00
Total Jumlah Rp. 108,624.38
C.2 MEMASANG 1 M2 BATA MERAH UKURAN (5 X 11 X 22) CM TEBAL 1/2 BATA, CAMPURAN SPESI 1 PC : 4 PS
Bahan
70.000 buah Batu Bata Standard @ Rp. 700.00 Rp. 49,000.00
11.500 Kg Semen Portland @ Rp. 1,187.50 Rp. 13,656.25
0.043 M3 Pasir Pasang @ Rp. 164,000.00 Rp. 7,052.00
Rp. 69,708.25
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.015 org/hr Mandor @ Rp. 150,000.00 Rp. 2,250.00
Rp. 36,000.00
Total Jumlah Rp. 105,708.25

D. PEKERJAAN PLESTERAN
D.1 MEMASANG 1 M2 PLESTERAN 1 PC : 3 PP, TEBAL 15 MM
Bahan
7.776 Kg Semen Portland @ Rp. 1,187.50 Rp. 9,234.00
0.023 m3 Pasir Pasang @ Rp. 164,000.00 Rp. 3,772.00
Rp. 13,006.00
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.150 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 15,000.00
0.015 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,875.00
0.015 org/hr Mandor @ Rp. 150,000.00 Rp. 2,250.00
Rp. 41,625.00
Total Jumlah Rp. 54,631.00
D.2 MEMASANG 1 M2 PLESTERAN 1 PC : 4 PP, TEBAL 15 MM
Bahan
6.240 Kg Semen Portland @ Rp. 1,187.50 Rp. 7,410.00
0.024 m3 Pasir Pasang @ Rp. 164,000.00 Rp. 3,936.00
Rp. 11,346.00
Tenaga
0.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 22,500.00
0.150 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 15,000.00
0.015 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,875.00
0.015 org/hr Mandor @ Rp. 150,000.00 Rp. 2,250.00
Rp. 41,625.00
Total Jumlah Rp. 52,971.00
D.3 MEMASANG 1 M2 ACIAN
Bahan
3.250 Kg Semen (PC) @ Rp. 1,187.50 Rp. 3,859.38
Rp. 3,859.38

Tenaga
0.200 org/hr Pekerja @ Rp. 75,000.00 Rp. 15,000.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.010 org/hr Mandor @ Rp. 150,000.00 Rp. 1,500.00
Rp. 27,750.00
Total Jumlah Rp. 31,609.38

E. PEKERJAAN KAYU
E.1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN KUSEN JENDELA , KAYU Kls I
Bahan
1.100 M3 Balok Kayu Kls .I @ Rp. 9,000,000.00 Rp. 9,900,000.00
1.250 Kg Paku 10 cm @ Rp. 19,500.00 Rp. 24,375.00
1.000 Kg Lem Kayu @ Rp. 15,500.00 Rp. 15,500.00
Rp. 9,939,875.00
Tenaga
7.000 org/hr Pekerja @ Rp. 75,000.00 Rp. 525,000.00
21.000 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 2,100,000.00
2.100 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 262,500.00
0.350 org/hr Mandor @ Rp. 150,000.00 Rp. 52,500.00
Rp. 2,940,000.00
Total Jumlah Rp. 12,879,875.00
E.2 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANAEL, KAYU Kls I
Bahan
0.040 m3 Papan Kayu Kls I @ Rp. 9,200,000.00 Rp. 368,000.00
0.500 Kg Lem Kayu @ Rp. 15,500.00 Rp. 7,750.00
Rp. 375,750.00
Tenaga
1.000 org/hr Pekerja @ Rp. 75,000.00 Rp. 75,000.00
2.500 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 250,000.00
0.250 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 31,250.00
0.050 org/hr Mandor @ Rp. 150,000.00 Rp. 7,500.00
Rp. 363,750.00
Total Jumlah Rp. 739,500.00
E.3 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU Kls I
Bahan
0.024 M3 Papan Kayu Kls .I @ Rp. 9,200,000.00 Rp. 220,800.00
0.300 Kg Lem Kayu @ Rp. 15,500.00 Rp. 4,650.00
Rp. 225,450.00
Tenaga
0.800 org/hr Pekerja @ Rp. 75,000.00 Rp. 60,000.00
2.000 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 200,000.00
0.200 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 25,000.00
0.040 org/hr Mandor @ Rp. 150,000.00 Rp. 6,000.00
Rp. 291,000.00
Total Jumlah Rp. 516,450.00
E.4 MEMASANG 1 M1 LISPLANK GRC PLAT
Bahan
0.410 Lbr GRC Plat @ Rp. 65,000.00 Rp. 26,639.34
0.050 Kg Paku @ Rp. 19,500.00 Rp. 975.00
Rp. 27,614.34
Tenaga
0.100 org/hr Pekerja @ Rp. 75,000.00 Rp. 7,500.00
0.200 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 20,000.00
0.020 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 2,500.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 30,750.00
Total Jumlah Rp. 58,364.34
F. PEKERJAAN BETON
F. 1 MEMBUAT 1 M3 LANTAI KERJA BETON MUTU F'c = 7,4 MPa (K 100), SLUMP (3 - 6) CM, W/C = 0,87
Bahan
230.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 273,125.00
893.000 Kg PB (Pasir Beton) @ Rp. 187.00 Rp. 166,991.00
1027.000 Kg KR (Maksimum 30 mm) @ Rp. 380.00 Rp. 390,260.00
200.000 Liter Air @ Rp. 25.00 Rp. 5,000.00
Rp. 835,376.00
Tenaga
1.200 org/hr Pekerja @ Rp. 75,000.00 Rp. 90,000.00
0.200 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 20,000.00
0.020 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 2,500.00
0.060 org/hr Mandor @ Rp. 150,000.00 Rp. 9,000.00
Rp. 121,500.00
Total Jumlah Rp. 956,876.00
F.2 MEMBUAT 1 M3 PONDASI BETON BERTULANG (150 KG BESI + BEKESTING)
Bahan
0.200 m3 Kayu Kelas III @ Rp. 2,925,000.00 Rp. 585,000.00
1.500 Kg Paku 5 cm - 12 cm @ Rp. 19,500.00 Rp. 29,250.00
0.400 Lt Minyak bekisting @ Rp. 27,500.00 Rp. 11,000.00
157.500 Kg Besi Beton Polos @ Rp. 11,397.61 Rp. 1,795,123.32
2.250 Kg Kawat Beton @ Rp. 22,500.00 Rp. 50,625.00
336.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 399,000.00
0.540 m3 PB (Pasir Beton) @ Rp. 187,000.00 Rp. 100,980.00
0.810 m3 KR (Maksimum 30 mm) @ Rp. 380,000.00 Rp. 307,800.00
Rp. 3,278,778.32
Tenaga
5.300 OH Pekerja @ Rp. 75,000.00 Rp. 397,500.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.300 OH Tukang kayu @ Rp. 100,000.00 Rp. 130,000.00
1.050 OH Tukang besi @ Rp. 100,000.00 Rp. 105,000.00
0.262 OH Kepala Tukang @ Rp. 125,000.00 Rp. 32,750.00
0.265 OH Mandor @ Rp. 150,000.00 Rp. 39,750.00
Rp. 732,500.00
Total Jumlah Rp. 4,011,278.32
F.3 Membuat 1 m3 Sloof Beton Bertulang ( 150 kg Besi + Bekisting )
Bahan
0.270 m3 Kayu Kelas III @ Rp. 2,925,000.00 Rp. 789,750.00
2.000 Kg Paku 5 cm - 12 cm @ Rp. 19,500.00 Rp. 39,000.00
0.600 Lt Minyak bekisting @ Rp. 27,500.00 Rp. 16,500.00
157.500 Kg Besi Beton Polos @ Rp. 11,397.61 Rp. 1,795,123.32
3.000 Kg Kawat Beton @ Rp. 22,500.00 Rp. 67,500.00
336.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 399,000.00
0.540 m3 PB (Pasir Beton) @ Rp. 187,000.00 Rp. 100,980.00
0.810 m3 KR (Maksimum 30 mm) @ Rp. 380,000.00 Rp. 307,800.00
Rp. 3,515,653.32
Tenaga
5.650 OH Pekerja @ Rp. 75,000.00 Rp. 423,750.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.560 OH Tukang kayu @ Rp. 100,000.00 Rp. 156,000.00
1.400 OH Tukang besi @ Rp. 100,000.00 Rp. 140,000.00
0.323 OH Kepala Tukang @ Rp. 125,000.00 Rp. 40,375.00
0.283 OH Mandor @ Rp. 150,000.00 Rp. 42,450.00
Rp. 830,075.00
Total Jumlah Rp. 4,345,728.32
F.4 Membuat 1 m3 Balok Beton Bertulang ( 150 kg Besi + Bekisting )
Bahan
0.320 m3 Kayu Kelas III @ Rp. 2,925,000.00 Rp. 936,000.00
3.200 Kg Paku 5 cm - 12 cm @ Rp. 19,500.00 Rp. 62,400.00
1.600 Lt Minyak bekisting @ Rp. 27,500.00 Rp. 44,000.00
157.500 Kg Besi Beton Polos @ Rp. 11,397.61 Rp. 1,795,123.32
3.000 Kg Kawat Beton @ Rp. 22,500.00 Rp. 67,500.00
336.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 399,000.00
0.540 m3 PB (Pasir Beton) @ Rp. 187,000.00 Rp. 100,980.00
0.810 m3 KR (Maksimum 30 mm) @ Rp. 380,000.00 Rp. 307,800.00
0.140 m3 Kayu Kelas II Balok @ Rp. 4,100,000.00 Rp. 574,000.00
2.800 Lbr Plywood 9 mm @ Rp. 131,000.00 Rp. 366,800.00
16.000 Btg Dolken kayu galam Ø 8-10/4 m @ Rp. 19,600.00 Rp. 313,600.00
Rp. 4,967,203.32
Tenaga
6.350 OH Pekerja @ Rp. 75,000.00 Rp. 476,250.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.650 OH Tukang kayu @ Rp. 100,000.00 Rp. 165,000.00
1.400 OH Tukang besi @ Rp. 100,000.00 Rp. 140,000.00
0.333 OH Kepala Tukang @ Rp. 125,000.00 Rp. 41,625.00
0.318 OH Mandor @ Rp. 150,000.00 Rp. 47,700.00
Rp. 898,075.00
Total Jumlah Rp. 5,865,278.32
F.5 Membuat 1 m3 Kolom Beton Bertulang ( 150 kg Besi + Bekisting )
Bahan
0.320 m3 Kayu Kelas III @ Rp. 2,925,000.00 Rp. 936,000.00
3.200 Kg Paku 5 cm - 12 cm @ Rp. 19,500.00 Rp. 62,400.00
1.600 Lt Minyak bekisting @ Rp. 27,500.00 Rp. 44,000.00
157.500 Kg Besi Beton Polos @ Rp. 11,397.61 Rp. 1,795,123.32
2.250 Kg Kawat Beton @ Rp. 22,500.00 Rp. 50,625.00
336.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 399,000.00
0.540 m3 PB (Pasir Beton) @ Rp. 187,000.00 Rp. 100,980.00
0.810 m3 KR (Maksimum 30 mm) @ Rp. 380,000.00 Rp. 307,800.00
0.120 m3 Kayu Kelas II Balok @ Rp. 4,100,000.00 Rp. 492,000.00
2.800 Lbr Plywood 9 mm @ Rp. 131,000.00 Rp. 366,800.00
32.000 Btg Dolken kayu galam Ø 8-10/4 m @ Rp. 19,600.00 Rp. 627,200.00
Rp. 5,181,928.32
Tenaga
5.300 OH Pekerja @ Rp. 75,000.00 Rp. 397,500.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.300 OH Tukang kayu @ Rp. 100,000.00 Rp. 130,000.00
1.050 OH Tukang besi @ Rp. 100,000.00 Rp. 105,000.00
0.265 OH Kepala Tukang @ Rp. 125,000.00 Rp. 33,125.00
0.265 OH Mandor @ Rp. 150,000.00 Rp. 39,750.00
Rp. 732,875.00
Total Jumlah Rp. 5,914,803.32
F.6 MEMBUAT 1 M3 PLAT MEJA BETON BERTULANG (50 KG BESI + BEKESTING)
Bahan
0.100 m3 Kayu Kelas III @ Rp. 2,925,000.00 Rp. 292,500.00
3.200 Kg Paku 5 cm - 12 cm @ Rp. 19,500.00 Rp. 62,400.00
1.600 Lt Minyak bekisting @ Rp. 27,500.00 Rp. 44,000.00
50.000 Kg Besi Beton Polos @ Rp. 11,397.61 Rp. 569,880.42
2.250 Kg Kawat Beton @ Rp. 22,500.00 Rp. 50,625.00
336.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 399,000.00
0.540 m3 PB (Pasir Beton) @ Rp. 187,000.00 Rp. 100,980.00
0.810 m3 KR (Maksimum 30 mm) @ Rp. 380,000.00 Rp. 307,800.00
0.120 m3 Kayu Kelas II Balok @ Rp. 4,100,000.00 Rp. 492,000.00
2.800 Lbr Plywood 9 mm @ Rp. 131,000.00 Rp. 366,800.00
32.000 Btg Dolken kayu galam Ø 8-10/4 m @ Rp. 19,600.00 Rp. 627,200.00
Rp. 3,313,185.42
Tenaga
5.300 OH Pekerja @ Rp. 75,000.00 Rp. 397,500.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.300 OH Tukang kayu @ Rp. 100,000.00 Rp. 130,000.00
1.050 OH Tukang besi @ Rp. 100,000.00 Rp. 105,000.00
0.265 OH Kepala Tukang @ Rp. 125,000.00 Rp. 33,125.00
0.265 OH Mandor @ Rp. 150,000.00 Rp. 39,750.00
Rp. 732,875.00
Total Jumlah Rp. 4,046,060.42
F.7 Membuat 1 m3 Ringbalk Beton Bertulang ( 120 kg Besi + Bekisting )
Bahan
0.270 m3 Kayu Kelas III @ Rp. 2,925,000.00 Rp. 789,750.00
2.000 Kg Paku 5 cm - 12 cm @ Rp. 19,500.00 Rp. 39,000.00
0.600 Lt Minyak bekisting @ Rp. 27,500.00 Rp. 16,500.00
120.000 Kg Besi Beton Polos @ Rp. 11,397.61 Rp. 1,367,713.00
2.800 Kg Kawat Beton @ Rp. 22,500.00 Rp. 63,000.00
336.000 Kg PC (Semen Portland) @ Rp. 1,187.50 Rp. 399,000.00
0.540 m3 PB (Pasir Beton) @ Rp. 187,000.00 Rp. 100,980.00
0.810 m3 KR (Maksimum 30 mm) @ Rp. 380,000.00 Rp. 307,800.00
Rp. 3,083,743.00
Tenaga
5.650 OH Pekerja @ Rp. 75,000.00 Rp. 423,750.00
0.275 OH Tukang Batu @ Rp. 100,000.00 Rp. 27,500.00
1.560 OH Tukang kayu @ Rp. 100,000.00 Rp. 156,000.00
1.400 OH Tukang besi @ Rp. 100,000.00 Rp. 140,000.00
0.323 OH Kepala Tukang @ Rp. 125,000.00 Rp. 40,375.00
0.283 OH Mandor @ Rp. 150,000.00 Rp. 42,450.00
Rp. 830,075.00
Total Jumlah Rp. 3,913,818.00

G. PEK. PENUTUP LANTAI DAN DINDING


G.1 MEMASANG 1 M2 LANTAI KERAMIK UKURAN (25 X 25) CM WARNA
Bahan
16.000 Bh Tegel keramik 25 x 25 cm warna @ Rp. 2,500.00 Rp. 40,000.00
9.600 Kg Semen portland @ Rp. 1,187.50 Rp. 11,400.00
0.045 m3 Pasir pasang @ Rp. 164,000.00 Rp. 7,380.00
1.500 Kg Semen warna @ Rp. 1,900.00 Rp. 2,850.00
Rp. 61,630.00
Tenaga
0.700 org/hr Pekerja @ Rp. 75,000.00 Rp. 52,500.00
0.350 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 35,000.00
0.035 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 4,375.00
0.035 org/hr Mandor @ Rp. 150,000.00 Rp. 5,250.00
Rp. 97,125.00
Total Jumlah Rp. 158,755.00
G.2 MEMASANG 1 M2 DINDING KERAMIK UKURAN (25 X 40) CM WARNA
Bahan
10.500 Bh keramik 25 x 40 cm warna @ Rp. 8,300.00 Rp. 87,150.00
9.300 Kg Semen portland @ Rp. 1,187.50 Rp. 11,043.75
0.018 m3 Pasir pasang @ Rp. 164,000.00 Rp. 2,952.00
1.940 Kg Semen warna @ Rp. 1,900.00 Rp. 3,686.00
Rp. 104,831.75
Tenaga
0.900 org/hr Pekerja @ Rp. 75,000.00 Rp. 67,500.00
0.450 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 45,000.00
0.045 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 5,625.00
0.045 org/hr Mandor @ Rp. 150,000.00 Rp. 6,750.00
Rp. 124,875.00
Total Jumlah Rp. 229,706.75
G.3 MEMASANG 1 M2 LANTAI KERAMIK UKURAN (60 X 60) CM WARNA
Bahan
3.100 Bh Tegel keramik 60 x 60 cm warna @ Rp. 63,000.00 Rp. 195,300.00
9.600 Kg Semen portland @ Rp. 1,187.50 Rp. 11,400.00
0.045 m3 Pasir pasang @ Rp. 164,000.00 Rp. 7,380.00
1.500 Kg Semen warna @ Rp. 1,900.00 Rp. 2,850.00
Rp. 216,930.00
Tenaga
0.700 org/hr Pekerja @ Rp. 75,000.00 Rp. 52,500.00
0.350 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 35,000.00
0.035 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 4,375.00
0.035 org/hr Mandor @ Rp. 150,000.00 Rp. 5,250.00
Rp. 97,125.00
Total Jumlah Rp. 314,055.00
G.4 MEMASANG 1 M2 PASANGAN BATU TEMPEL BERGARIS (BERMOTIF MINIMALIS)
Bahan
1.100 M2 Batu Tempel 10 x 20 Bergaris (Minimalis)
@ Rp. 193,500.00 Rp. 212,850.00
11.750 Kg Semen Portland @ Rp. 1,187.50 Rp. 13,953.13
0.035 M3 Pasir Pasangan @ Rp. 164,000.00 Rp. 5,740.00
Rp. 232,543.13
Tenaga
0.700 org/hr Pekerja @ Rp. 75,000.00 Rp. 52,500.00
0.350 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 35,000.00
0.035 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 4,375.00
0.035 org/hr Mandor @ Rp. 150,000.00 Rp. 5,250.00
Rp. 97,125.00
Total Jumlah Rp. 329,668.13
H. PEKERJAAN ATAP
H.1 MEMASANG 1 M2 ATAP GENTENG METAL
Bahan
1.650 Lbr Atap Genteng Metal @ Rp. 50,500.00 Rp. 83,325.00
10.000 Bj Sekrup Flesshing @ Rp. 600.00 Rp. 6,000.00
Rp. 89,325.00
Tenaga
0.200 org/hr Pekerja @ Rp. 75,000.00 Rp. 15,000.00
0.100 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,250.00
0.001 org/hr Mandor @ Rp. 150,000.00 Rp. 150.00
Rp. 26,400.00
Total Jumlah Rp. 115,725.00

H.2 MEMASANG 1 M' ATAP NOK METAL


Bahan
1.020 lbr Nok Genteng Metal @ Rp. 27,500.00 Rp. 28,050.00
10.000 Bj Sekrup Flesshing @ Rp. 600.00 Rp. 6,000.00
Rp. 34,050.00
Tenaga
0.200 org/hr Pekerja @ Rp. 75,000.00 Rp. 15,000.00
0.100 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,250.00
0.001 org/hr Mandor @ Rp. 150,000.00 Rp. 150.00
Rp. 26,400.00
Total Jumlah Rp. 60,450.00

I. PEKERJAAN LANGIT-LANGIT
I.1 1 m2 PASANGAN LANGIT-LANGIT CALSIBOARD
Bahan
0.364 Lbr Calsiboard @ Rp. 71,000.00 Rp. 25,844.00
8.000 Bj Sekrup Flesshing @ Rp. 600.00 Rp. 4,800.00
Rp. 30,644.00
Tenaga
0.100 org/hr Pekerja @ Rp. 75,000.00 Rp. 7,500.00
0.050 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 5,000.00
0.005 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 625.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 13,875.00
Jumlah 1 m2 Rp. 44,519.00

I.2 1 m2 PASANGAN LANGIT-LANGIT GYPSUM BOARD UKURAN (1200 X 2400 X 9) MM


Bahan
0.364 Lbr Gypsum Board @ Rp. 75,500.00 Rp. 27,482.00
0.110 Kg Paku Biasa 2" - 5" @ Rp. 22,500.00 Rp. 2,475.00
Rp. 29,957.00
Tenaga
0.100 org/hr Pekerja @ Rp. 75,000.00 Rp. 7,500.00
0.050 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 5,000.00
0.005 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 625.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 13,875.00
Jumlah 1 m2 Rp. 43,832.00

J. PEKERJAAN LISTRIK
J.1 MEMASANG 1 TITIK INSTALASI LISTRIK
Bahan
2.000 m' Pipa Listrik @ Rp. 1,656.25 Rp. 3,312.50
7.500 m' Kabel @ Rp. 8,070.00 Rp. 60,525.00
Rp. 63,837.50
Upah
0.250 Upah Supl. List @ Rp. 506,250.00 Rp. 126,562.50
Rp. 126,562.50 Rp. 190,400.00

J.2 MEMASANG 1 BH STOP KONTAK


Bahan
1.000 Bh Stop Kontak @ Rp. 30,500.00 Rp. 30,500.00
Rp. 30,500.00
Upah
0.150 Upah Supl. List @ Rp. 506,250.00 Rp. 75,937.50
Rp. 75,937.50 Rp. 106,437.50

J.3 MEMASANG 1 BH SAKLAR TUNGGAL


Bahan
1.000 Bh Saklar Tunggal @ Rp. 25,500.00 Rp. 25,500.00
Rp. 25,500.00
Upah
0.150 Upah Supl. List @ Rp. 506,250.00 Rp. 75,937.50
Rp. 75,937.50 Rp. 101,437.50

J.4 MEMASANG 1 BH SAKLAR GANDA


Bahan
1.000 Bh Saklar Ganda @ Rp. 28,500.00 Rp. 28,500.00
Rp. 28,500.00
Upah
0.150 Upah Supl. List @ Rp. 506,250.00 Rp. 75,937.50
Rp. 75,937.50 Rp. 104,437.50

J.5 MEMASANG 1 BH SEKRING CASS LOKAL


Bahan
1.000 Bh Sekring Cass Lokal @ Rp. 85,500.00 Rp. 85,500.00
Rp. 85,500.00
Upah
0.200 Upah Supl. List @ Rp. 506,250.00 Rp. 101,250.00
Rp. 101,250.00 Rp. 186,750.00

J.6 MEMASANG 1 BH DAUN LIGHT


Bahan
1.000 Bh Down Light @ Rp. 18,000.00 Rp. 18,000.00
Rp. 18,000.00
Upah
0.025 Upah Supl. List @ Rp. 506,250.00 Rp. 12,656.25
Rp. 12,656.25 Rp. 30,656.25

K. PEKERJAAN SANITASI
K.1 MEMASANG 1 BUAH KLOSET DUDUK / MONOBLOK
Bahan
1.000 Bh Kloset Duduk @ Rp. 2,007,500.00 Rp. 2,007,500.00
0.060 6% HB Perlengkapan 6 % H. Bahan @ Rp. 2,007,500.00 Rp. 120,450.00
Rp. 2,127,950.00
Tenaga
3.300 org/hr Pekerja @ Rp. 75,000.00 Rp. 247,500.00
1.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 110,000.00
0.001 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 125.00
0.160 org/hr Mandor @ Rp. 150,000.00 Rp. 24,000.00
Rp. 381,625.00
Jumlah 1 Bh Rp. 2,509,575.00
K.2 MEMASANG 1 BUAH BAK CUCI PIRING STAINLES STEEL
Bahan
1.000 Bh bak cuci stainles steel @ Rp. 458,500.00 Rp. 458,500.00
1.000 Set Water drain + asesories @ Rp. 69,300.00 Rp. 69,300.00
Rp. 527,800.00
Tenaga
0.030 org/hr Pekerja @ Rp. 75,000.00 Rp. 2,250.00
0.300 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 30,000.00
0.030 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 3,750.00
0.0015 org/hr Mandor @ Rp. 150,000.00 Rp. 225.00
Rp. 36,225.00
Jumlah 1 Bh Rp. 564,025.00

K.3 MEMASANG1 BUAH FLOOR DRAIN


Bahan
1.000 Bh Floor Drain @ Rp. 36,000.00 Rp. 36,000.00
Rp. 36,000.00
Upah
0.010 org/hr Pekerja @ Rp. 75,000.00 Rp. 750.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 12,750.00
Jumlah 1 Bh Rp. 48,750.00
K.4 MEMASANG 1 BUAH KRAN AIR DIAMETER 3/4'' ATAU 1/2''
Bahan
1.000 Bh Kran Air @ Rp. 56,000.00 Rp. 56,000.00
0.025 Tube Seal Tape @ Rp. 6,600.00 Rp. 165.00
Rp. 56,165.00
Upah
0.010 org/hr Pekerja @ Rp. 75,000.00 Rp. 750.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 12,750.00
Jumlah 1 Bh Rp. 68,915.00

K.5 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3/4''


Bahan
1.200 m' Pipa PVC @ Rp. 4,750.00 Rp. 5,700.00
0.350 35% HBPerlengkapan @ Rp. 4,750.00 Rp. 1,662.50
Rp. 7,362.50
Upah
0.036 org/hr Pekerja @ Rp. 75,000.00 Rp. 2,700.00
0.060 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 6,000.00
0.006 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 750.00
0.0018 org/hr Mandor @ Rp. 150,000.00 Rp. 270.00
Rp. 9,720.00
Rp. 17,082.50
K.6 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 2''
Bahan
1.200 m' Pipa PVC @ Rp. 19,416.67 Rp. 23,300.00
0.350 35% HBPerlengkapan @ Rp. 19,416.67 Rp. 6,795.83
Rp. 30,095.83
Upah
0.054 org/hr Pekerja @ Rp. 75,000.00 Rp. 4,050.00
0.090 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 9,000.00
0.009 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,125.00
0.0027 org/hr Mandor @ Rp. 150,000.00 Rp. 405.00
Rp. 14,580.00
Rp. 44,675.83
K.7 MEMASANG 1 M' PIPA PVC TIPE AW DIAMETER 3''
Bahan
1.200 m' Pipa PVC @ Rp. 39,250.00 Rp. 47,100.00
0.350 35% HBPerlengkapan @ Rp. 39,250.00 Rp. 13,737.50
Rp. 60,837.50
Upah
0.081 org/hr Pekerja @ Rp. 75,000.00 Rp. 6,075.00
0.135 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 13,500.00
0.0135 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,687.50
0.0041 org/hr Mandor @ Rp. 150,000.00 Rp. 615.00
Rp. 21,877.50
Rp. 82,715.00

K.8 1 BH TEMPAT SABUN


Bahan
1.000 Bh Tempat Sabun @ Rp. 51,700.00 Rp. 51,700.00
Rp. 51,700.00
Upah
0.010 org/hr Pekerja @ Rp. 75,000.00 Rp. 750.00
0.100 org/hr Tukang Batu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Batu @ Rp. 125,000.00 Rp. 1,250.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 12,750.00
Rp. 64,450.00

L. PEKERJAAN KUNCI / KACA


L.1 PASANGAN 1 BUAH KUNCI TANAM BIASA
Bahan
1.000 Bh Kunci Tanam Biasa @ Rp. 175,500.00 Rp. 175,500.00
Rp. 175,500.00
Upah
0.010 org/hr Pekerja @ Rp. 75,000.00 Rp. 750.00
0.500 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 50,000.00
0.010 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,250.00
0.005 org/hr Mandor @ Rp. 150,000.00 Rp. 750.00
Rp. 52,750.00
Rp. 228,250.00

L.2 PASANG 1 BUAH ENGSEL PINTU


Bahan
1.000 Bh Engsel Pintu @ Rp. 38,000.00 Rp. 38,000.00
Rp. 38,000.00
Upah
0.015 org/hr Pekerja @ Rp. 75,000.00 Rp. 1,125.00
0.150 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 15,000.00
0.015 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,875.00
0.00075 org/hr Mandor @ Rp. 150,000.00 Rp. 112.50
Rp. 18,112.50
Engsel Pintu Rp. 56,112.50

L.3 PASANG 1 BUAH ENGSEL JENDELA


Bahan
1.000 Bh Engsel Jendela @ Rp. 28,500.00 Rp. 28,500.00
Rp. 28,500.00
Upah
0.010 org/hr Pekerja @ Rp. 75,000.00 Rp. 750.00
0.100 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,250.00
0.0005 org/hr Mandor @ Rp. 150,000.00 Rp. 75.00
Rp. 12,075.00
Engsel Pintu Rp. 40,575.00
L.4 1 Bh. GRENDEL PINTU DAN JENDELA
Bahan
1.000 Bh Grendel Pintu @ Rp. 20,000.00 Rp. 20,000.00
1.000 Bh Grendel Jendela @ Rp. 16,000.00 Rp. 16,000.00
Rp. 20,000.00
Rp. 16,000.00
Upah
0.010 org/hr Pekerja @ Rp. 75,000.00 Rp. 750.00
0.100 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 10,000.00
0.010 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,250.00
0.001 org/hr Mandor @ Rp. 150,000.00 Rp. 75.00
Rp. 12,075.00
Grendel Pintu Rp. 32,075.00
Grendel Jendela Rp. 28,075.00

L.5 PASANG 1 BUAH KAIT ANGIN


Bahan
1.000 Bh Hak angin (kait-Kait) Jendela @ Rp. 18,000.00 Rp. 18,000.00
Rp. 18,000.00
Upah
0.015 org/hr Pekerja @ Rp. 75,000.00 Rp. 1,125.00
0.150 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 15,000.00
0.015 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,875.00
0.00075 org/hr Mandor @ Rp. 150,000.00 Rp. 112.50
Rp. 18,112.50
Hak angin (kait-Kait) Jendela Rp. 36,112.50

L.6 PASANGAN 1 M2 KACA, TEBAL 5 mm


Bahan
1.100 M2 Kaca 5 mm @ Rp. 127,500.00 Rp. 140,250.00
Rp. 140,250.00
Tenaga
0.015 org/hr Pekerja @ Rp. 75,000.00 Rp. 1,125.00
0.150 org/hr Tukang Kayu @ Rp. 100,000.00 Rp. 15,000.00
0.015 org/hr Kepala Tukang Kayu @ Rp. 125,000.00 Rp. 1,875.00
0.00075 org/hr Mandor @ Rp. 150,000.00 Rp. 112.50
Rp. 18,112.50
Total Jumlah Rp. 158,362.50

M. PEKERJAAN CAT
M.1 PENGECETAN 1 M2 TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
Bahan
0.100 Kg Plamir @ Rp. 8,000.00 Rp. 800.00
0.100 Kg Cat dasar @ Rp. 12,600.00 Rp. 1,260.00
0.260 Kg Cat penutup 2 kali @ Rp. 18,600.00 Rp. 4,836.00
Rp. 6,896.00
Tenaga
0.020 org/hr Pekerja @ Rp. 75,000.00 Rp. 1,500.00
0.063 org/hr Tukang Cat @ Rp. 100,000.00 Rp. 6,300.00
0.0063 org/hr Kepala Tukang Cat @ Rp. 125,000.00 Rp. 787.50
0.0025 org/hr Mandor @ Rp. 150,000.00 Rp. 375.00
Rp. 8,962.50
Total Jumlah Rp. 15,858.50
M.2 PENGECETAN 1 M2 PLAFON BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
Bahan
0.100 Kg Plamir @ Rp. 8,000.00 Rp. 800.00
0.100 Kg Cat dasar @ Rp. 12,600.00 Rp. 1,260.00
0.260 Kg Cat penutup 2 kali @ Rp. 18,600.00 Rp. 4,836.00
Rp. 6,896.00
Tenaga
0.020 org/hr Pekerja @ Rp. 75,000.00 Rp. 1,500.00
0.063 org/hr Tukang Cat @ Rp. 100,000.00 Rp. 6,300.00
0.0063 org/hr Kepala Tukang Cat @ Rp. 125,000.00 Rp. 787.50
0.0025 org/hr Mandor @ Rp. 150,000.00 Rp. 375.00
Rp. 8,962.50
Total Jumlah Rp. 15,858.50

M.3 PENGECETAN 1 M2 BIDANG KAYU BARU (1 LAPIS PLAMIR), 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP
Bahan
0.200 Kg Cat Meni @ Rp. 17,000.00 Rp. 3,400.00
0.150 Kg Plamir @ Rp. 8,000.00 Rp. 1,200.00
0.170 Kg Cat dasar @ Rp. 22,500.00 Rp. 3,825.00
0.260 Kg Cat penutup 2 kali @ Rp. 63,500.00 Rp. 16,510.00
Rp. 24,935.00
Tenaga
0.070 org/hr Pekerja @ Rp. 75,000.00 Rp. 5,250.00
0.009 org/hr Tukang Cat @ Rp. 100,000.00 Rp. 900.00
0.006 org/hr Kepala Tukang Cat @ Rp. 125,000.00 Rp. 750.00
0.0025 org/hr Mandor @ Rp. 150,000.00 Rp. 375.00
Rp. 7,275.00
Total Jumlah Rp. 32,210.00
A. DAFTAR HARGA BAHAN BANGUNAN

NO JENIS BAHAN BANGUNAN SATUAN HARGA

1 2 3 4
A BAHAN DASAR
1 Batu
- Batu belah 15 /20 cm m3 @ Rp 230,500.00
- Krikil 0.5 - 2 cm m3 @ Rp 380,000.00
- Krikil 0.5 - 2 cm kg @ Rp 380.00
- Batu Merah Standart Klas I Biji @ Rp 700.00
2 Pasir dan Tanah
- Pasir Beton m3 @ Rp 187,000.00
- Pasir Beton kg @ Rp 187.00
- Pasir Pasangan m3 @ Rp 164,000.00
- Pasir Urug m3 @ Rp 164,000.00
- Tanah Urug m3 @ Rp 127,000.00
-Air Liter @ Rp 25.00
3 Semen Portland
Semen 50 Kg (Tonasa) P.C Zak @ Rp 59,375.00
Semen 50 Kg (Tonasa) P.C Kg @ Rp 1,187.50
Semen warna Kg @ Rp 1,900.00

B BAHAN BESI
1 Besi Beton Biasa U.24 Dia. 08 - 19 mm Kg @ Rp 11,397.61
2 Paku biasa 5 - 12 cm Kg @ Rp 19,500.00
3 Sekrup Flesshing Bj @ Rp 600.00
4 Kawat Ikat Beton Kg @ Rp 22,500.00
5 Lispalak GRC Plat Lbr @ Rp 65,000.00
C BAHAN KAYU
1 Kayu Kls.I Bayam (Balok) M3 @ Rp 9,000,000.00
2 Kayu Kls.I Bayam (Papan) M3 @ Rp 9,200,000.00
3 Kayu Kls.II (Balok) M3 @ Rp 4,100,000.00
4 Kayu Kls.III (Papan) M3 @ Rp 2,925,000.00
5 Dolken Kayu M' @ Rp 19,600.00
D BAHAN FINISHING
1 Cat Tembok Kg @ Rp 18,600.00
2 Cat Tembok ( cat dasar) Kg @ Rp 12,600.00
2 Cat Kayu / Besi Avian Kg @ Rp 63,500.00
4 Cat Kayu Dasar Kg @ Rp 22,500.00
3 Plamur Kg @ Rp 8,000.00
5 Lem Fox Kg @ Rp 15,500.00
6 cat meni Kg @ Rp 17,000.00
7 minyak bekesting Ltr @ Rp 27,500.00
E BAHAN PERPIPAAN
1 Pipa PVC dia. 3/4 Inch - 4 m Maspion m' @ Rp 4,750.00
2 Pipa PVC dia. 3 Inch - 4 m Maspion m' @ Rp 39,250.00
3 Pipa PVC dia. 2 Inch - 4 m Maspion m' @ Rp 19,416.67
4 Kloset Duduk American Standart (Setara) Buah @ Rp 2,007,500.00
5 Westaffel Zink Aluminium Merek KIA Tipe EX Buah @ Rp 458,500.00
7 Kran Air Buah @ Rp 56,000.00
8 Floor Drain Buah @ Rp 36,000.00
9 seal Tape Buah @ Rp 6,600.00
11 Tempat Sabun Keramik Buah @ Rp 51,700.00
Pintu Km/wc Aluminium Spanrill Buah @ Rp 900,000.00

F BAHAN LANGIT-LANGIT/ ATAP


1 Calsiboard T= 4 mm Lbr @ Rp 71,000.00
3 Gypsum Board Jayabord Setara Lbr @ Rp 75,500.00
2 Pliwood 9 mm Lbr @ Rp 131,000.00
3 Atap Genteng Metal ex. Surya roof Lbr @ Rp 50,500.00
4 Nok Genteng Metal ex. Surya roof Bj @ Rp 27,500.00
9 Rangka Plafon m2 @ Rp 98,200.00
12 Rangka Channel 75/100, 75/75 dan top span m2 @ Rp 213,500.00

G BAHAN KACA
1 Kaca Polos 5 mm m2 @ Rp 127,500.00
H BAHAN KERAMIK / BATU TEMPEL
7 Keramik Lantai Warna 60 x 60 cm Bh @ Rp 63,000.00
Keramik Lantai Warna 25 x 25 cm Bh @ Rp 2,500.00
Keramik Lantai Warna 25 x 40 cm Bh @ Rp 8,300.00
4 Batu Tempel Minimalis m2 @ Rp 193,500.00
I BAHAN PENGGANTUNG
1 Kunci Pintu 2 slag putar SES set @ Rp 175,500.00
2 Engsel Pintu Bh @ Rp 38,000.00
3 Engsel Jendela Bh @ Rp 28,500.00
4 Grendel Pintu Bh @ Rp 20,000.00
5 Grendel Jendela Bh @ Rp 16,000.00
6 Hak Angin Kait-Kait Jendela Bh @ Rp 18,000.00
J BAHAN INSTALASI LISTRIK
1 Sekring unit @ Rp 85,500.00
2 Lampu Pijar Sumpit 26 watt Sinyoku bh @ Rp 72,750.00
3 Lampu Pijar Sumpit 20 watt Sinyoku bh @ Rp 41,250.00
4 Lampu Pijar Sumpit 9 watt Sinyoku bh @ Rp 36,000.00
5 Stop Kontak Panasonik bh @ Rp 30,500.00
6 Saklar Tunggal Panasonik bh @ Rp 25,500.00
7 Saklar Ganda Panasonik bh @ Rp 28,500.00
8 Pipa Union untuk Listrik m' @ Rp 1,656.25
9 Kabel listrik NYY 2 X 2,5 mm m' @ Rp 8,070.00
10 Lampu Down Light Bh @ Rp 18,000.00
B. DAFTAR HARGA UPAH KERJA
NO U R A I A N SATUAN HARGA

Pekerja Org / Hari @ Rp 75,000.00


TUKANG
Tukang Kayu Org / Hari @ Rp 100,000.00
Tukang Batu Org / Hari @ Rp 100,000.00
Tukang Cat Org / Hari @ Rp 100,000.00
Tukang Listrik Org / Hari @ Rp 100,000.00
Tukang Pipa Org / Hari @ Rp 100,000.00
Tukang Besi Org / Hari @ Rp 100,000.00
KEPALA TUKANG
Kepala Tukang Kayu Org / Hari @ Rp 125,000.00
Kepala Tukang Batu Org / Hari @ Rp 125,000.00
Kepala Tukang Listrik Org / Hari @ Rp 125,000.00
Kepala Tukang Cat Org / Hari @ Rp 125,000.00
Kepala Tukang Pipa Org / Hari @ Rp 125,000.00
Kepala Tukang Besi Org / Hari @ Rp 125,000.00
Mandor Org / Hari @ Rp 150,000.00