MANPOWER SCHEDULE

PEMBANGUNAN DERMAGA IV PELABUHAN PENYEBERANGAN MERAK DAN BAKAUHENI

2019 Total
NO Manpower Description
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec M/M

A DERMAGA IV BAKAUHENI
Manpower
I STAFF
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 12
2 Site Manager 1 1 1 1 1 1 1 1 1 1 1 1 12
3 Quality Engineer 1 1 1 1 1 1 1 1 1 1 1 1 12
4 Quantity Engineer 1 1 1 1 1 1 1 1 1 1 1 1 12
5 Surveyor 2 2 2 2 2 2 2 2 2 2 2 2 24
6 Supervisor 2 2 2 2 2 2 2 2 2 2 2 2 24
7 Drafter 2 2 2 2 2 2 2 2 2 2 2 2 24
8 Logistik 2 2 2 2 2 2 2 2 2 2 2 2 24
9 Adm & Keuangan 2 2 2 2 2 2 2 2 2 2 2 2 24
10 HSE Officer 1 1 1 1 1 1 1 1 1 1 1 1 12

SUB TOTAL 15 15 15 15 15 15 15 15 15 15 15 15 180

II LABOUR
1 Pekerjaan Persiapan 10 10 10 10 15 15 15 10 10 10 5 5 125
2 Pekerjaan Pembongkaran dermaga IV Existing 20 20 30 20 90
3 Pekerjaan Pengerukan dan timbunan batu di kolom dermaga 15 20 35
4 Timbunan area darat 10 15 10 35
5 Pembuatan dinding turap baja, Capping Beam, Pelindung MB, Dudukan Bollard & Fender 15 30 75 80 40 240
6 Pekerjaan Angker Deadmen 20 50 60 40 30 200
7 Pembuatan Dudukan Movable Bridge 20 50 50 20 140
8 Pembuatan Dudukan Hidraulik 25 25 50
9 Pemb. Movable Bridge Hot Div Galavanized Dan Pengecatan (144 M2) 15 15 30
10 Pembuatan Konstruksi Mooring 6 Buah 20 70 50 140
11 Pekerjaan Rigid Pavement & Utilisasi 0
12 Catwalk & Accessories 10 20 20 40 90
13 Mechanical Piping 10 15 15 15 55
14 Electrical 10 15 10 35
SUB TOTAL 30 70 105 115 115 125 125 150 155 130 100 45 1,050

TOTAL MANPOWER
- STAFF 15 15 15 15 15 15 15 15 15 15 15 15 180
- LABOUR 30 70 105 115 115 125 125 150 155 130 100 45 1265
TOTAL 45 85 120 130 130 140 140 165 170 145 115 60 1,445

Page 1 of 2
MANPOWER SCHEDULE

PEMBANGUNAN DERMAGA IV PELABUHAN PENYEBERANGAN MERAK DAN BAKAUHENI

2019 Total
NO Manpower Description
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec M/M

B DERMAGA IV MERAK
Manpower
I STAFF
1 Project Manager 1 1 1 1 1 1 1 1 1 1 1 1 12
2 Site Manager 1 1 1 1 1 1 1 1 1 1 1 1 12
3 Quality Engineer 1 1 1 1 1 1 1 1 1 1 1 1 12
4 Quantity Engineer 1 1 1 1 1 1 1 1 1 1 1 1 12
5 Surveyor 2 2 2 2 2 2 2 2 2 2 2 2 24
6 Supervisor 2 2 2 2 2 2 2 2 2 2 2 2 24
7 Drafter 2 2 2 2 2 2 2 2 2 2 2 2 24
8 Logistik 2 2 2 2 2 2 2 2 2 2 2 2 24
9 Adm & Keuangan 2 2 2 2 2 2 2 2 2 2 2 2 24
10 HSE Officer 1 1 1 1 1 1 1 1 1 1 1 1 12

SUB TOTAL 15 15 15 15 15 15 15 15 15 15 15 15 180

II LABOUR
1 Pekerjaan Persiapan 6 6 6 6 10 10 10 10 10 10 5 5 94
2 Pekerjaan Pembongkaran Dermaga Iv Existing 15 15 20 20 70
3 Pekerjaan Perbaikan Dermaga 10 10 15 15 15 10 75
4 Pembuatan Dudukan Movable Bridge ( 1 Buah) 10 10 10 10 40
5 Konstruksi Dudukan Hidrolik (2 Buah) 10 20 20 20 70
7 Pemb. Konstruksi Mooring (1 Buah) 15 20 10 45
8 Pemb. Konstruksi Breasthing Dolphin (5 Buah) 10 15 15 15 15 15 85
9 Pemb. Konstruksi Pelindung Mb (2 Unit) 10 10 10 30
10 Pemb. Movable Bridge Hot Div Galavanized Dan Pengecatan (144 M2) 10 20 20 15 65
11 Pembuatan Catwalk 10 10 10 10 10 10 10 10 10 90
12 Pembuatan Rumah Kontrol 7 7 7 7 28
13 Pekerjaan Cathodic Protection 5 10 10 5 30
14 Electrical 15 15 15 15 15 75
15 Mechanical Piping 10 10 20 20 20 20 20 120
16 Pemb. Platform 15 15 15 15 15 15 90
17 Pemb. Temporary Jetty 5 5 10 10 10 40

SUB TOTAL 31 51 61 128 142 152 152 95 85 70 65 15 1,047

TOTAL MANPOWER
- STAFF 15 15 15 15 15 15 15 15 15 15 15 15 180
- LABOUR 31 51 61 128 142 152 152 95 85 70 65 15 1047
TOTAL 46 66 76 143 157 167 167 110 100 85 80 30 1,227

Page 2 of 2