RENCANA KEGIATAN DAN ANGGARAN SEKOLAH T.P.

2021/2022
SUMBER DANA : KOMITE SEKOLAH

A INSENTIF
1 GURU TIDAK TETAP: 3 Orang x Rp 500.000 x 12 Bulan 18,000,000
2 TENAGA ADMINISTRASI : 1 Orang x Rp 400.000 x 10 Bulan 4,000,000
B PEMBANGUNAN/INVESTASI
1 PENGADAAN MEJA DAN KURSI SISWA : 30 Psg x Rp 700.000 21,000,000
2 SEWA ANGKUT 2,800,000
C KEGIATAN KESISWAAN
1 BIAYA KEGIATAN OSIS
a. Kegiatan Porseni 7,620,000
b. Kegiatan Paskibra 6,335,000
c. Kegiatan Pramuka 6,335,000
d. Kegiatan PMR 6,335,000
e. Kegiatan Sosial 1 TAHUN 3,600,000
f. Kegiatan LDK 7,760,000
g. Kegiatan Raker OSIS 6,810,000
2 PENGHARGAAN SISWA BERPRESTASI
10 Kelas x Rp 450.000 + 7 Kelas x Rp 450.000 7,650,000
3 PENGHARGAAN JUARA LOMBA KELAS
Rp 700.000 x 2 semester 1,400,000
4 PENGHARGAAN NILAI UJIAN TERTINGGI 450,000
D BIAYA PELAKSANAAN ASESMEN KOMPETENSI MINIMAL (AKM)
1 Sewa Wifi gladi bersih 3 hari x Rp 2.500.000 7,500,000
2 Sewa Wifi pelaksanaan AKM 5 hari x Rp 2.500.000 12,500,000
D OPERASIONAL KOMITE
Transpor Rapat pengurus dan pihak sekolah : 8 org x Rp 100.000 x 1 kali 800,000
Konsumsi(snack) Rapat pengurus dan pihak sekolah : 8 org x Rp 15.000 x 1 kali 120,000
Konsumsi(snack) rapat orang tua siswa : 100 org x Rp 15.000 1,500,000
Insentif Pengelola administrasi dan keuangan : Rp 40.000 x 12 bln 480,000
Penggandaan undangan, laporan, dan program : 5 lbr x 250exp x Rp 350 437,500
ATK dan Penggandaan Laporan pertanggung Jawaban 167,500
TOTAL 123,600,000

JUMLAH SISWA : 242

SISWA DIBEBASKAN DARI PEMBAYARAN :


BERSAUDARA DAN TIDAK MAMPU : 36 PENANGGUNG 206

JUMLAH PENANGGUNG : 206


BEBAN PENANGGUNG PERTAHUN : Rp 123.600.000 /206 ORANG 600,000

BEBAN PER BULAN 50,000

Menyetujui : Mengetahui : Langgikima, 26 Juli 2021


Ketua Komite, Kepala SMAN 1 Langgikima, Ketua Tim Penyusun,

LA ODE HAIRA, S.IP. SURASDIN, S.Pd.,M.M. AMRIN, S.Pd.


NIP 19730908 200012 1 003 NIP 1984
1
2
3
4
5
6

1
2
3
4
5
6
7
8
9
10

1
2
3
4
5
6
7
8
9
10

1
2
3
4
5
6
7
8
9
10

1
2
3
4
5
6
7
8
9
10

1
2
3
4
5
6
7
8
9
10
OPERASIONAL KOMIITE
Transpor Rapat pengurus dan pihak sekolah : 10 org x Rp 100.000 x 2 kali
Konsumsi(snack) Rapat pengurus dan pihak sekolah : 10 org x Rp 15.000 x 2 kali
Konsumsi(snack) rapat orang tua siswa : 200 org x Rp 15.000
Insentif Pengelola administrasi dan keuangan : Rp 100.000 x 12 bln
Penggandaan undangan, laporan, dan program : 6 lbr x 200exp x Rp 350
ATK dan Penggandaan Laporan pertanggung Jawaban
JUMLAH

PASKIBRA
Konsumsi Guru
Snack Guru
Konsumsi Panitia Siswa
Snack Panitia Siswa
Konsumsi Peserta
Snack Peserta
Spanduk
ID Card
Transpor Guru
Transpor Panitia

PRAMUKA
Konsumsi Guru
Snack Guru
Konsumsi Panitia Siswa
Snack Panitia Siswa
Konsumsi Peserta
Snack Peserta
Spanduk
ID Card
Transpor Guru
Transpor Panitia

PMR
Konsumsi Guru
Snack Guru
Konsumsi Panitia Siswa
Snack Panitia Siswa
Konsumsi Peserta
Snack Peserta
Spanduk
ID Card
Transpor Guru
Transpor Panitia

LDK
Konsumsi Guru
Snack Guru
Konsumsi Panitia Siswa
Snack Panitia Siswa
Konsumsi Peserta
Snack Peserta
Spanduk
ID Card
Transpor Guru
Transpor Panitia

Porseni
Hadiah lomba
Ballpoint
Buku
Snack panitia guru
Snack panitia siswa

RAKER
Konsumsi Guru
Snack Guru
Konsumsi Panitia Siswa
Snack Panitia Siswa
Konsumsi Peserta
Snack Peserta
Spanduk
ID Card
Transpor Guru
Transpor Panitia
2,000,000
300,000
2,000,000
1,200,000
420,000
180,000
6,100,000

35,000 15 525,000
15,000 30 450,000
25,000 14 350,000
10,000 28 280,000
25,000 30 750,000
10,000 60 600,000
150,000 1 150,000
50,000 44 2,200,000
50,000 15 750,000
20,000 14 280,000
6,335,000

35,000 15 525,000
15,000 30 450,000
25,000 14 350,000
10,000 28 280,000
25,000 30 750,000
10,000 60 600,000
150,000 1 150,000
50,000 44 2,200,000
50,000 15 750,000
20,000 14 280,000
6,335,000

35,000 15 525,000
15,000 30 450,000
25,000 14 350,000
10,000 28 280,000
25,000 30 750,000
10,000 60 600,000
150,000 1 150,000
50,000 44 2,200,000
50,000 15 750,000
20,000 14 280,000
6,335,000

35,000 15 525,000
15,000 30 450,000
25,000 14 350,000
10,000 28 280,000
25,000 45 1,125,000
10,000 90 900,000
150,000 1 150,000
50,000 59 2,950,000
50,000 15 750,000
20,000 14 280,000
7,760,000

30 lsn 30,000 900,000


30 lsn 98,000 2,940,000
112 dos 15,000 1,680,000
210 dos 10,000 2,100,000
7,620,000

35,000 15 525,000
15,000 30 450,000
25,000 14 350,000
10,000 28 280,000
25,000 35 875,000
10,000 70 700,000
150,000 1 150,000
50,000 49 2,450,000
50,000 15 750,000
20,000 14 280,000
6,810,000
RENCANA ANGGARAN BIAYA (RAB)
PERBAIKAN JAMBAN SISWA, PENYEDIAAN AIR BERSIH, DAN PENYEDIAAN
WASHTAPEL TIAP RUANGAN
NO URAIAN JML SAT HARGA SAT JUMLAH
1 Tower 4 mtr 1 bh 4,500,000 4,500,000
2 Semen 5 sak 85,000 425,000
3 Pasir ret 800,000 -
4 Tandon 1200 ltr 1 bh 1,400,000 1,400,000
5 Pipa 1 1/2 60 btg 80,000 4,800,000
6 Pipa 3/4 8 btg 40,000 320,000
7 Sok T 1 1/2 ke 1/2 12 bh 12,000 144,000
8 Sok lurus 1 1/2 ke 1/2 4 bh 12,000 48,000
9 Sok lurus 3/4 ke 1 1/2 1 bh 15,000 15,000
10 Sok T 1 1/2 4 bh 12,000 48,000
11 Sok L 1 1/2 3 bh 12,000 36,000
12 washtapel 13 bh 450,000 5,850,000
13 Lem pipa 1 klg 60,000 60,000
14 Kran 1/2 15 bh 50,000 750,000
15 Sok drat dalam 1/2 16 bh 6,000 96,000
16 Seltip 1 bh 13,000 13,000
17 Mesin air 1 bh 2,500,000 2,500,000
18 Klep 1 bh 65,000 65,000
19 Sok L 3/4 14 bh 10,000 140,000
20 Gergaji besi 1 bh 90,000 90,000
21 Sewa angkutan 1 kl 3,000,000 3,000,000
22 Upah kerja pemasangan Washtapel dan tower 1 pkt 3,000,000 3,000,000
23 Sumur bor 1 bh 15,000,000 15,000,000
JUMLAH 42,300,000
Terbilang : Lima Puluh Juta Dua Ratus Delapan Puluh Lima Ribu Rupiah

Langgikima, 7 Juni 2021


Kepala SMAN 1 Langgikima,

SURASDIN, S.Pd.,M.M.
Pembina Tk. I, IV/b
NIP 19730908 200012 1 003
Tower 4 mtr 1 bh 5,000,000 5,000,000
Semen 8 sak 85,000 680,000
Pasir 1 ret 800,000 800,000
Tandon 1200 ltr 1 bh 1,500,000 1,750,000
Pipa 1 1/2 60 btg 79,000 4,500,000
Pipa 3/4 8 btg 40,000 320,000
Sok T 1 1/2 ke 1/2 12 bh 12,500 180,000
Sok lurus 1 1/2 ke 1/2 4 bh 12,500 50,000
Sok lurus 3/4 ke 1 1/2 1 bh 15,000 15,000
Sok T 1 1/2 4 bh 12,500 50,000
Sok L 1 1/2 3 bh 12,500 37,500
washtapel 13 bh 450,000 5,850,000
Lem pipa 1 klg 60,000 60,000
Kran 1/2 15 bh 52,000 525,000
Sok drat dalam 1/2 16 bh 7,500 120,000
Seltip 3 bh 13,000 39,000
Mesin air 1 bh 750,000 750,000
Klep 1 bh 65,000 65,000
Sok L 3/4 14 bh 10,000 140,000
Gergaji besi 1 bh 90,000 90,000
Sewa angkutan 1 kl 2,500,000 2,500,000
Upah kerja pemasangan Wa 1 pkt 3,500,000 3,500,000
Sumur bor 1 bh 15,000,000 15,000,000