PERKERASAN JALAN UTAMA

Panjang Lebar Jalan Tinggi Perkerasan Kubikasi Keterangan material koef Batu belah Agregat A Agregat B Satuan
227.93 m 12 m 0.2 m 547.032 m3 Agregat A 1.27 694.73 m3
227.93 m 12 m 0.2 m 547.032 m3 Agregat B 1.27 694.73 m3
44.389 m 8m 0.2 m 71.0224 m3 Agregat A 1.27 90.20 m3
44.389 m 8m 0.2 m 71.0224 m3 Agregat B ± 1.27 90.20 m3
633.006 202.68 m 8m 0.1 m 162.144 m3 Agregat A 1.27 205.92 m3
202.68 m 8m 0.1 m 162.144 m3 Agregat B 1.27 205.92 m3
158.007 m 8m 0.2 m 252.8112 m3 Agregat A 1.27 321.07 m3
158.007 m 8m 0.2 m 252.8112 m3 Agregat B 1.27 321.07 m3
TOTAL AGREGAT 1311.92 1311.92 m3

Keterangan
Di area material keras jadi memerlukan pengeresan yang tidak cukup banyak

CUT N FILL
PT ABADI OGAN CEMERLANG

Output dari desain jalan cut 51942.33 Bcm


no Pekerjaan Total Volume Plan Area
1 CUT 20,000.00 bcm 0.79 ha

KEBUTUHAN ALAT
Productivity EH DAY DISTANCE Prod DT TOTAL DT
No Jenis TOTAL DAY MONTH
BCM/HR HOURS BCM/DAY M BCM/HR UNIT
1 EXA CLASS 20 TON 90 7 630 15.87 0.5 500 40 3.00
2 EXA CLASS 20 TON 90 7 630 15.87 0.5 500 40 3.00

TARGET PENGERJAAN 30 HARI


ALAT PRODUKSI UTAMA
PILIHAN ALAT YANG DIGUNAKAN N (BANYAK) BCM / (HOUR) BCM / (DAY) Waktu Pengerjaan
1 EXCA CLASS 20 TON 2
180.00 1260.00 15.87 day
2 DT CLASS 30 TON 6
SUPPORT
ALAT N (BANYAK)
1 EXCA CLASS 20 TON 1
1 DOZZER 1
1 COMPACT 1
1 GRADER 1

Alat Yang Digunakan


Exca 20 ton 1 Unit 2 Alat produksi , 1 Alat support
Dozzer 1 Unit 1 fleet
Compactor 1 Unit 1 fleet
Grader 1 Unit fleksibel ke dua arah kerja

Perbaikan Tanah Geotextile jalan UTAMA


Area yang harus di perbaiki

Panjang Lebar Luasan


227.93 m 15 m 3418.95 m2
44.389 m 12 m 532.67 m2
158.007 m 12 m 1896.08 m2
Total 5847.70 m2
PERKERASAN Dari stock pile ke jalan STBM

Panjang Lebar Jalan Tinggi Perkerasan Kubikasi Keterangan material koef Batu belah Agregat A Agregat B Satuan
272.104 m 12 m 0.2 m 653.0496 m3 Agregat A 1.27 829.37 m3
272.104 m 12 m 0.2 m 653.0496 m3 Agregat B 1.27 829.37 m3
TOTAL AGREGAT 829.37 829.37 m3

GEOTEXTILE JALAN MENUJU STOCKPILE STBM


GEOTEXTILE
Panjang Lebar
272.104 m 15.0 m 4081.56 m2

2141.30
no Pekerjaan Total Volume Plan Area
1 CUT 22,000.00 bcm 0.79

KEBUTUHAN ALAT
Productivity EH
No Jenis
BCM/HR HOURS
1 EXA CLASS 20 TON 90 7
2 EXA CLASS 20 TON 90 7

TARGET PENGERJAAN 30 HARI


ALAT PRODUKSI UTAMA
PILIHAN ALAT YANG DIGUNAKAN N (BANYAK) BCM / (HOUR)
1 EXCA CLASS 20 TON 2
180.00
2 DT CLASS 30 TON 6
SUPPORT
ALAT N (BANYAK)
1 EXCA CLASS 20 TON 1
1 DOZZER 1
1 COMPACT 1
1 GRADER 1

Alat Yang Digunakan


Exca 20 ton 1 Unit
Dozzer 1 Unit
Compactor 1 Unit
Grader 1 Unit
PT ABADI OGAN CEMERLANG

ha

DAY DISTANCE Prod DT


TOTAL DAY MONTH
BCM/DAY M BCM/HR
630 17.46 0.6 500 40
630 17.46 0.6 500 40

ALAT PRODUKSI UTAMA


BCM / (DAY) Waktu Pengerjaan

1260.00 17.46 day

Alat Yang Digunakan


2 Alat produksi , 1 Alat support
1 fleet
1 fleet
fleksibel ke dua arah kerja
TOTAL DT
UNIT
3.00
3.00
ANALISA DAN REVIEW PENAWARAN ITEM CUT N FILL

Biaya total =(𝑗𝑎𝑚 𝑘𝑒𝑟𝑗𝑎 𝑥 ℎ𝑎𝑟𝑔𝑎 𝑠𝑒𝑤𝑎 𝑎𝑙𝑎𝑡)+(𝑓𝑢𝑒𝑙 𝑐𝑜𝑛𝑠𝑢𝑚𝑡𝑖𝑜𝑛 𝑥 𝐻𝑎𝑟𝑔𝑎 𝑠𝑜𝑙𝑎𝑙 𝐼𝑛𝑑𝑢𝑠𝑡𝑟𝑖 𝑥 𝑗𝑎𝑚 𝑒𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑘𝑒𝑟𝑗𝑎)

Harga Sewa Alat


No Jenis Alat Jam Efective Kerja Fuel Consumtion Harga Solar Industri Biaya total
Per jam
1 Excavaotor 122.22 jam Rp 280,000.00 18 Liter/jam Rp 21,000.00 Rp 80,420,760.00
2 Excavaotor 122.22 jam Rp 280,000.00 18 Liter/jam Rp 21,000.00 Rp 80,420,760.00
3 Dozzer 122.22 jam Rp 400,000.00 34 Liter/jam Rp 21,000.00 Rp 136,153,080.00
4 Vibro 122.22 jam Rp 350,000.00 13 Liter/jam Rp 21,000.00 Rp 76,143,060.00
5 Grade 122.22 jam Rp 350,000.00 13 Liter/jam Rp 21,000.00 Rp 76,143,060.00
6 DT 122.22 jam Rp 250,000.00 10 Liter/jam Rp 21,000.00 Rp 56,221,200.00
7 DT 122.22 jam Rp 250,000.00 10 Liter/jam Rp 21,000.00 Rp 56,221,200.00
8 DT 122.22 jam Rp 250,000.00 10 Liter/jam Rp 21,000.00 Rp 56,221,200.00
9 DT 122.22 jam Rp 250,000.00 10 Liter/jam Rp 21,000.00 Rp 56,221,200.00
10 DT 122.22 jam Rp 250,000.00 10 Liter/jam Rp 21,000.00 Rp 56,221,200.00
TOTAL BIAYA Rp 730,386,720.00

NO COST MAN POWER JUMLAH 1 BULAN / ORANG BIAYA


1 ENGINEER 1.00 Rp 15,000,000.00 Rp 15,000,000.00
2 SURVEYOR 2.00 Rp 8,000,000.00 Rp 16,000,000.00
3 FOREMAN 2.00 Rp 6,000,000.00 Rp 12,000,000.00
JUMLAH Rp 43,000,000.00

Biaya oprasional 18 hari Rp 1,000,000.00


JUMLAH Rp 18,000,000.00

ANALISA RINCIAN BIAYA ACTUAL

Total Baya Cut n fill 22000 Bcm Rp 791,386,720.00


Biaya per-bcm Rp 35,972.12

Estimasi keuntungan kontraktor

profit kontraktor 20.06%


Dari nilai total penawaran sebesar Rp. 990.000.000