NO. URAIAN PEKERJAAN VOL. SAT HARGA SATUAN JUMLAH HARGA


Rp. Rp.
1 2 3 4 5 6

A Cat dinding bagian kiri


1 Kupas cat tembok 36.50 m2 18,300.00 667,950.00
2 Cat Dinding exterior 217.35 m2 42,800.00 9,302,580.00
3 Cat Listplank 23.60 m2 42,800.00 1,010,080.00
4 Cat plafond 34.80 m2 36,400.00 1,266,720.00
5 Cat list plafond 58.00 m. 8,600.00 498,800.00

B Cat dinding bagian kanan


1 Kupas/kerok dinding cat 36.50 m2 18,300.00 667,950.00
2 Cat Dinding exterior 217.35 m2 43,000.00 9,346,050.00
3 Cat Listplank 23.60 m2 43,000.00 1,014,800.00
4 Cat plafond 34.80 m2 36,400.00 1,266,720.00
5 Cat list plafond 58.00 m. 12,500.00 725,000.00

C Cat dinding bagian belakang


1 Cat Dinding exterior 378.00 m2 43,000.00 16,254,000.00
2 Cat Listplank 39.20 m2 43,000.00 1,685,600.00
3 Cat plafond 58.80 m2 36,400.00 2,140,320.00
4 Cat list plafond 98.00 m. 12,500.00 1,225,000.00

D Pekerjaan Dak Beton Ruang Sidang


1 Pembersihan dak beton 240.00 m2 14,500.00 3,480,000.00
2 Coating dak beton 240.00 m2 112,500.00 27,000,000.00

E Ruang Kerja TU
1 Bongkara partisi Ruang TU 28.00 m2 18,500.00 518,000.00
2 Pasang plint keramik 28.00 m' 67,600.00 1,892,800.00
3 Cat dinding 168.00 m2 36,400.00 6,115,200.00

F Pekerjaan Lain-lain
1 Pembersihan akhir 1.00 lot 1,750,000.00 1,750,000.00
2 Sewa Steger 1.00 ls 1,900,000.00 1,900,000.00

Jumlah 89,727,570.00
PPN 10% 8,972,757.00
Jumlah Total 98,700,327.00
Dibulatkan 98,700,000.00

Demikian penawaran yang kami ajukan, atas perhatian dan kerja samanya, kami ucapkan terima kasih

* Apabila didapati perubahan ukuran, gambar/spesifikasi bahan bangunan yang ada di lapangan tidak sesuai
dengan rencana kami, maka dilakukan penawaran ulang.

Hormat Kami,