BILL OF QUANTITY ( BQ )

RENCANA ANGGARAN BIAYA


PEKERJAAN : BRANDING DAN PEMBATAS PARKIRAN LAPANGAN FUTSAL
LOKASI :
VOLUME HARGA JUMLAH HARGA
NO JENIS PEKERJAAN SATUAN

I PEKERJAAN PERSIAPAN 2.000.000


1 PEK. PEMBONGKARAN, PEMBERSIHAN DAN MOBILISASI 1,00 LS 2.000.000 2.000.000

II PEKERJAAN BRANDING SISI LAPANGAN 48.108.762


1 PEK. RANGKA HOLOW 4 X 4 *GALVANIS 1.042,84 KG 19.509 20.344.766
2 PEK. HMR LAPISAN VINYL *INSTALASI PAKU RIVET 107,30 M2 75.689 8.121.430
3 PEK. VINYL KOREA *INSTALASI LEM FOX KUNING 107,30 M2 67.559 7.249.081
4 PEK. LAPISAN CAT ANTI KARAT RANGKA HOLOW 111,36 M2 65.090 7.248.422
5 PEK. PASANG ENGSEL KUPU-KUPU 3'' STEINSTEEL 87,00 BH 27.472 2.390.064
6 PEK. PASANG HAK ANGIN 58,00 BH 17.500 1.015.000
7 PEK. ANGKUR DAN STRIP KAKI-KAKI 116,00 BH 15.000 1.740.000

III PEKERJAAN PEMBATAS PARKIRAN 22.920.531


1 PEK. RANGKA TULANGAN PIPA 3 INCH 451,44 KG 19.509 8.807.143
2 PEK. RANGKA HOLOW 4 X 4 *GALVANIS 176,40 KG 19.509 3.441.388
3 PEK. PLATSEET (SENGPLAT GALVALUME ) TBL 0.40 MM 48,00 M2 61.500 2.952.000
4 PEK. STICKER PRINTING 48,00 M2 140.000 6.720.000
5 PEK. BETON DAN ANGKUR 1,00 LS 1.000.000 1.000.000

REAL COAST : 73.029.293


PPN 11% : 8.033.222
GRAND TOTAL : 81.062.515
DIBULATKAN : 81.000.000

TERBILANG : DELAPAN PULUH SATU JUTA RUPIAH,

MAKASSAR, 21 FEBRUARI 2024

HORMAT KAMI,
CV. ALAM RAYA ABADI PERKASA

NUR ALAM
DIREKTUR