DAFTAR ANALISA HARGA SATUAN RSD GUNUNG JATI KOTA CIREBON TAHUN 2023

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)

40 ABK-I.603 Pekerjaan Pemasangan Instalasi Kabel AC 1.00 unit 97,384.00 18,869.00 - 116,253.00

1.000 OH Pekerja 97,000.00 97,000.00 97,000.00


UPAH

0.003 OH Kepala Tukang 128,000.00 384.00 384.00

1.000 m Kabel NYM 3x2,5mm 18,733.00 18,733.00 18,733.00


BAHAN

0.016 bh Isolasi 8,500.00 136.00 136.00


ALAT

JUMLAH : (A) 116,253.00


KEUNTUNGAN 10% : (B) = 10% x (A) 11,625.30
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 127,878.30

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
Pekerjaan Pemasangan Instalasi Pipa AC
300 ABK-IX.598 1.00 ttk 422,500.00 547,520.00 - 970,020.00
Central LG VRV (10 PK)
1.000 OH Pekerja 200,000.00 200,000.00 200,000.00
0.890 OH Kepala Tukang 250,000.00 222,500.00 222,500.00
UPAH

1.000 m Pipa 3/8 & 7/8 " 547,520.00 547,520.00 547,520.00


BAHAN
ALAT

JUMLAH : (A) 970,020.00


KEUNTUNGAN 10% : (B) = 10% x (A) 97,002.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1,067,022.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
Pekerjaan Pemasangan Instalasi Pipa AC
301 ABK-IX.597 1.00 ttk 422,500.00 750,000.00 - 1,172,500.00
Central LG VRV (15 PK)
1.000 OH Pekerja 200,000.00 200,000.00 200,000.00
UPAH

0.890 OH Tukang Listrik 250,000.00 222,500.00 222,500.00


ALAT BAHAN

1.000 m Pipa 5/8 & 1 1/8 " 750,000.00 750,000.00 750,000.00

JUMLAH : (A) 1,172,500.00


KEUNTUNGAN 10% : (B) = 10% x (A) 117,250.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1,289,750.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
Pekerjaan Pemasangan MCCB 3 Phase 40
309 ABK-IX.608 1.00 ttk 512,000.00 1,388,500.00 128,000.00 2,028,500.00
Ampere
2.000 OH Tukang Listrik 128,000.00 256,000.00 256,000.00
1.000 OH Kepala Tukang 128,000.00 128,000.00 128,000.00
1.000 OH Mandor 128,000.00 128,000.00 128,000.00

1.000 bh MCCB 3 Phase 40 Ampere 1,100,000.00 1,100,000.00 1,100,000.00


BAHAN

1.000 bh Isolasi 8,500.00 8,500.00 8,500.00


1.000 unit Mobilisasi 280,000.00 280,000.00 280,000.00
BAHAN
1.000 pcs Sarung Tangan Safety 30,000.00 30,000.00 30,000.00
1.000 bh Tang Kombinasi 68,500.00 68,500.00 68,500.00
ALAT

1.000 bh Obeng Plus (+) 29,500.00 29,500.00 29,500.00

JUMLAH : (A) 2,028,500.00


KEUNTUNGAN 10% : (B) 202,850.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 2,231,350.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
Pekerjaan Pemasangan MCCB 3 Phase 32
310 ABK-IX.609 1.00 ttk 512,000.00 1,288,500.00 128,000.00 1,928,500.00
Ampere
2.000 OH Tukang Listrik 128,000.00 256,000.00 256,000.00
1.000 OH Kepala Tukang 128,000.00 128,000.00 128,000.00
1.000 OH Mandor 128,000.00 128,000.00 128,000.00

1.000 bh MCCB 3 Phase 32 Ampere 1,000,000.00 1,000,000.00 1,000,000.00


BAHAN

1.000 bh Isolasi 8,500.00 8,500.00 8,500.00


1.000 unit Mobilisasi 280,000.00 280,000.00 280,000.00

1.000 pcs Sarung Tangan Safety 30,000.00 30,000.00 30,000.00


1.000 bh Tang Kombinasi 68,500.00 68,500.00 68,500.00
ALAT

1.000 bh Obeng Plus (+) 29,500.00 29,500.00 29,500.00

JUMLAH : (A) 1,928,500.00


KEUNTUNGAN 10% : (B) 192,850.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 2,121,350.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
Pekerjaan Pemasangan MCB 1 Phase 16
311 ABK-IX.610 1.00 ttk 217,600.00 93,500.00 128,000.00 456,300.00
Ampere
1.000 OH Tukang Listrik 128,000.00 128,000.00 128,000.00
0.700 OH Kepala Tukang 128,000.00 89,600.00 89,600.00
UPAH

0.900 OH Mandor 128,000.00 115,200.00 115,200.00


BAHAN

1.000 bh MCB 1 Phase 16 Ampere 93,500.00 93,500.00 93,500.00

1.000 pcs Sarung Tangan Safety 30,000.00 30,000.00 30,000.00


1.000 bh Tang Kombinasi 68,500.00 68,500.00 68,500.00
ALAT

1.000 bh Obeng Plus (+) 29,500.00 29,500.00 29,500.00

JUMLAH : (A) 554,300.00


KEUNTUNGAN 10% : (B) 55,430.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 609,730.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
312 ABK-IX.606 Pekerjaan Pemasangan Panel 1.00 unit 592,800.00 1,353,500.00 119,910.00 2,066,210.00
4.000 OH Pekerja 97,000.00 388,000.00 388,000.00
0.600 OH Tukang Listrik 128,000.00 76,800.00 76,800.00
UPAH

0.500 OH Kepala Tukang 128,000.00 64,000.00 64,000.00


0.500 OH Mandor 128,000.00 64,000.00 64,000.00

1.000 unit Pemasangan Panel 850,000.00 850,000.00 850,000.00


BAHAN

1.000 bh Dynabol 12mm 3,500.00 3,500.00 3,500.00


1.000 unit Mobilisasi 500,000.00 500,000.00 500,000.00

1.000 bh Kunci Pas Ring 12mm 30,000.00 30,000.00 30,000.00


ALAT

1.000 bh Palu Besi 89,910.00 89,910.00 89,910.00

JUMLAH : (A) 2,066,210.00


KEUNTUNGAN 10% : (B) 206,621.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 2,272,831.00
HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
313 ABK-IX.607 Pemasangan Kabel Tray 400x100mm 1.00 ttk 2,100,000.00 1,393,500.00 119,910.00 3,613,410.00
6.000 OH Pekerja 250,000.00 1,500,000.00 1,500,000.00
1.000 OH Kepala Tukang 300,000.00 300,000.00 300,000.00
UPAH

1.000 OH Mandor 300,000.00 300,000.00 300,000.00

1.000 m Kabel Tray 400x100 890,000.00 890,000.00 890,000.00


BAHAN

1.000 bh Dynabolt 12mm 3,500.00 3,500.00 3,500.00


1.000 unit Mobilisasi 500,000.00 500,000.00 500,000.00

1.000 bh Kunci Pas Ring 12mm 30,000.00 30,000.00 30,000.00


ALAT

1.000 bh Palu Besi 89,910.00 89,910.00 89,910.00

JUMLAH : (A) 3,613,410.00


KEUNTUNGAN 10% : (B) 361,341.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 3,974,751.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
314 ABK-IX.543 Pengisian Freon R410 A 1.00 can 107,240.00 5,750,000.00 808,271.00 6,665,511.00
1.000 OH Pekerja 97,000.00 97,000.00 97,000.00
UPAH

0.080 OH Kepala Tukang 128,000.00 10,240.00 10,240.00


BAHAN

1.000 can Freon R410 A DUPONT 5,750,000.00 5,750,000.00 5,750,000.00

0.900 bh Manipol 809,190.00 728,271.00 728,271.00


ALAT

0.800 bh Kunci Inggris 100,000.00 80,000.00 80,000.00

JUMLAH : (A) 6,665,511.00


KEUNTUNGAN 10% : (B) 666,551.10
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 7,332,062.10

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
315 ABK-IX.614 Pemasangan Planum Suply Indor AHU 1.00 ttk 320,000.00 5,142,880.00 - 5,462,880.00
2.000 OH Pekerja 100,000.00 200,000.00 200,000.00
UPAH

0.800 OH Kepala Tukang 150,000.00 120,000.00 120,000.00

1.000 unit Planum Suplay Indor AHU 3,642,880.00 3,642,880.00 3,642,880.00


BAHAN

1.000 unit Mobilisasi 1,500,000.00 1,500,000.00 1,500,000.00


ALAT

JUMLAH : (A) 5,462,880.00


KEUNTUNGAN 10% : (B) 546,288.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 6,009,168.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)

316 ABK-IX.615 Pemasangan Planum Suplay Indor 10 PK 1.00 ttk 320,000.00 3,524,000.00 - 3,844,000.00

2.000 OH Pekerja 100,000.00 200,000.00 200,000.00


UPAH

0.800 OH Kepala Tukang 150,000.00 120,000.00 120,000.00

1.000 unit Planum Suplay Indor 10 PK 2,024,000.00 2,024,000.00 2,024,000.00


BAHAN

1.000 unit Mobilisasi 1,500,000.00 1,500,000.00 1,500,000.00


ALAT

JUMLAH : (A) 3,844,000.00


KEUNTUNGAN 10% : (B) 384,400.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 4,228,400.00
HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
317 ABK-IX.616 Pemasangan Planum Return AHU 1.00 ttk 320,000.00 3,928,800.00 - 4,248,800.00
2.000 OH Pekerja 100,000.00 200,000.00 200,000.00
UPAH

0.800 OH Kepala Tukang 150,000.00 120,000.00 120,000.00

1.000 unit Planum Return AHU 2,428,800.00 2,428,800.00 2,428,800.00


BAHAN

1.000 unit Mobilisasi 1,500,000.00 1,500,000.00 1,500,000.00


ALAT

JUMLAH : (A) 4,248,800.00


KEUNTUNGAN 10% : (B) 424,880.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 4,673,680.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)

318 ABK-IX.617 Pemasangan Planum Return Indor 10 PK 1.00 ttk 320,000.00 2,920,000.00 - 3,240,000.00

2.000 OH Pekerja 100,000.00 200,000.00 200,000.00


UPAH

0.800 OH Kepala Tukang 150,000.00 120,000.00 120,000.00

1.000 unit Planum Return Indor 10 PK 1,420,000.00 1,420,000.00 1,420,000.00


BAHAN

1.000 unit Mobilisasi 1,500,000.00 1,500,000.00 1,500,000.00


ALAT

JUMLAH : (A) 3,240,000.00


KEUNTUNGAN 10% : (B) 324,000.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 3,564,000.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
319 ABK-IX.618 Pemasangan Ducting 700x300 1.00 m 296,400.00 1,458,000.00 - 1,754,400.00
2.000 OH Pekerja 97,000.00 194,000.00 194,000.00
UPAH

0.800 OH Kepala Tukang 128,000.00 102,400.00 102,400.00

1.000 m Ducting 700x300 608,000.00 608,000.00 608,000.00


BAHAN

1.000 unit Mobilisasi 850,000.00 850,000.00 850,000.00


ALAT

JUMLAH : (A) 1,754,400.00


KEUNTUNGAN 10% : (B) 175,440.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1,929,840.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
320 ABK-IX.619 Pemasangan Ducting 500x300 1.00 bh 296,400.00 1,400,000.00 - 1,696,400.00
2.000 OH Pekerja 97,000.00 194,000.00 194,000.00
UPAH

0.800 OH Kepala Tukang 128,000.00 102,400.00 102,400.00

1.000 m Ducting 500x300 550,000.00 550,000.00 550,000.00


BAHAN

1.000 unit Mobilisasi 850,000.00 850,000.00 850,000.00


ALAT

JUMLAH : (A) 1,696,400.00


KEUNTUNGAN 10% : (B) 169,640.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1,866,040.00
HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
321 ABK-IX.620 Pemasangan Difuser 300x300 1.00 bh 393,400.00 1,150,000.00 - 1,543,400.00
3.000 OH Pekerja 97,000.00 291,000.00 291,000.00
UPAH

0.800 OH Kepala Tukang 128,000.00 102,400.00 102,400.00

1.000 bh Difuser 300x300 300,000.00 300,000.00 300,000.00


BAHAN

1.000 unit Mobilisasi 850,000.00 850,000.00 850,000.00


ALAT

JUMLAH : (A) 1,543,400.00


KEUNTUNGAN 10% : (B) 154,340.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1,697,740.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)

322 ABK-IX.621 Pemasangan Box Suplay Ducting AHU 1.00 bh 393,400.00 1,050,000.00 - 1,443,400.00

3.000 OH Pekerja 97,000.00 291,000.00 291,000.00


UPAH

0.800 OH Kepala Tukang 128,000.00 102,400.00 102,400.00

1.000 bh Box Suplay Ducting AHU 200,000.00 200,000.00 200,000.00


BAHAN

1.000 unit Mobilisasi 850,000.00 850,000.00 850,000.00


ALAT

JUMLAH : (A) 1,443,400.00


KEUNTUNGAN 10% : (B) 144,340.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1,587,740.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
323 ABK-IX.622 Pemasangan Bak Drain AHU 1.00 bh 490,400.00 4,158,400.00 - 4,648,800.00
4.000 OH Pekerja 97,000.00 388,000.00 388,000.00
UPAH

0.800 OH Kepala Tukang 128,000.00 102,400.00 102,400.00

1.000 bh Bak Drain AHU 3,238,400.00 3,238,400.00 3,238,400.00


BAHAN

1.000 unit Mobilisasi 850,000.00 850,000.00 850,000.00


1.000 bh Sealent Dextone 70,000.00 70,000.00 70,000.00
ALAT

JUMLAH : (A) 4,648,800.00


KEUNTUNGAN 10% : (B) 464,880.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 5,113,680.00

HARGA SATUAN
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp) JUMLAH HARGA (Rp)
(Rp)
324 ABK-IX.623 Pemasangan Bak Drain Indor 10 PK 1.00 bh 490,400.00 2,342,080.00 - 2,832,480.00
4.000 OH Pekerja 97,000.00 388,000.00 388,000.00
UPAH

0.800 OH Kepala Tukang 128,000.00 102,400.00 102,400.00

1.000 bh Bak Drain Indor 10 PK 1,422,080.00 1,422,080.00 1,422,080.00


BAHAN

1.000 unit Mobilisasi 850,000.00 850,000.00 850,000.00


1.000 bh Sealent Dextone 70,000.00 70,000.00 70,000.00
ALAT

JUMLAH : (A) 2,832,480.00


KEUNTUNGAN 10% : (B) 283,248.00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 3,115,728.00