METODE KERJA PEMASANGAN COVER CONVEYOR AREA 31B

GAMBARAN UMUM
GAMBARAN UMUM

METODE INI MENJELASKAN LANGKAH LANGKAH PELAKSANAAN PEKERJAAN


PEMASANGAN COVER TRAY 31B EX FEEDER

AREA KERJA
METODE KERJA PEMASANGAN COVER CONVEYOR AREA 31B

PROSES TAHAP PERTAMA


LANGKAH – 1

PROSES PEMASANGAN SCAFFOLDING


PERSIAPAN AKSES PEKERJAAN

- LANGKAH PERTAMA LAKUKAN TOOLBOX MEETING ATAU BREAFING PAGI SEBELUM BEKERJA
SCAFFOLDING
- LAKUKAN PENJELASAN METODE KERJA DAN RA

- MOBILISASI MATERIAL DAN ALAT

- PASTIKAN MATERIAL DAN ALAT KERJA DIBERSIHKAN SEBELUM MASUK KE AREA PRODUKSI

- PASTIKAN ALAT KERJA ATAU TOOLS DALAM TAGING HIJAU

- LIFTING MATERIAL SCAFFOLDING SECARA MANUAL

- INSTAL SCAFFOLDING UNTUK AKSES PEKERJAAN KETINGGIAN

- PASANG BRACING, JOIN PINT, TANGGA, CATWALK DENGAN BENAR & PASTIKAN DALAM

KONDISI PROPER/TERKUNCI

- UNTUK SCAFFOLDING LEBIH DARI 2 BAY, PASANG SUPPORT BRACING

- PASANG BARICADE & SIGN BOARD UNTUK MEMBATASI AREA

- SETELAH SCAFFOLDING SELESAI DI INSTAL, LAKUKAN TAGGING SCAFFOLDING

- PASTIKAN SCAFFOLDING DI TAGGING HIJAU

- SPV DAN HSE WAJIB MENGECEK DAN MENGAWASI

- PASTIKAN PEKERJA SUDAH TENSI DARAH SEBELUM BEKERJA KETINGGIAN

- COVER AREA KERJA UNTUK MENGHINDARI KONTAMINASI KE AREA PRODUKSI


METODE KERJA PEMASANGAN COVER CONVEYOR AREA 31B

PROSES TAHAP KEDUA


LANGKAH – 2

PROSES PEMASANGAN COVER CONVEYOR RANGKA COVER


• PEMASANGAN COVER CONVEYOR
HOLLOW ZINC
TCOVER CONVEYOR
PLASITIK FIBER TEBAL 1. SIAPKAN MATERIAL DAN ALAT KERJA

2. PASTIKAN ALAT KERJA SUDAH DI CEK DAN DI INSPEKSI SECARA BERKALA

3. SETELAH MATERIAL READY LANGSIR MATERIAL KE AREA KERJA MENGGUNAKAN GEROBAK

4. PASTIKAN PEKERJA MENGGUNAKAN SARUNNG TANGAN

5. SETELAH MATERIAL DAN ALAT DI LANGSIR KE AREA KERJA POTONG HOLLO ZINCALUME
CONVEYOR
SESUAI KEBUTUHAN MENGGUNAKAN GUNTING

6. ANGKAT MATERIAL SECARA MANUAL DAN PASANG MENGGUNAKAN PAKU RIPPET

7. PASTIKAN MENGGUNAKAN SARUNG TANGAN

8. SETELAH PEKERJAAN SELESAI LAKUKAN HOUSKEEPING AREA

9. PASTIKAN SPV DAN HSE MENGAWASI SAMPAI PEKERJAAN SELESAI DAN HOUSKEEPING

AREA SELESAI

10. SPV WAJIB MELAKUKAN PENGECEKAN KEMBALI UNTUK PEMASANGAN COVER APAKAH

SUDAH TEPAT/KUAT