GAMBARAN UMUM
GAMBARAN UMUM
METODE INI MENJELASKAN LANGKAH LANGKAH ERECTION BAJA JEMBATAN DUCTING DI AREA
CRT MENGGUNAKAN ROUGH TERRAIN CRANE CAP 10T
AREA KERJA
METODE ERECTION BAJA JEMBATAN DUCTING AREA CRT
LANGKAH PERTAMA
LANGAKAH KE - 1
- LANGKAH PERTAMA LAKUKAN TOOLBOX MEETING ATAU BREAFING PAGI SEBELUM BEKERJA
PROSES PEMASANGAN SUPPPORT PIPA
- MOBILISASI MATERIAL DAN ALAT
- PASANG BARICADE UNTUK MEMBATASI AREA SUPAYA TIDAK SEMBARANG ORANG LEWAT
LANGKAH KEDUA
LANGKAH KE - 2
PROSES PEMASANGAN ASIBA DAN LIFELINE
- PEMASANGAN ASIBA DAN LIFELINE UNTUK AKSES
LIFELINE
1. LANGSIR ASIBA DAN LIFE LINE KE AREA
DI INSTAL SEBELUMNYA
3. PASANG ASIBA TERLEBIH DAHULU DAN PASTIKAN DIIKAT DAN TIDAK BERGESER UNTUK
LANGKAH KETIGA
LANGKAH KE - 3
PROSES FABRIKASI BAJA
- SELANJUTNYA FABRIKASI BAJA
A. PASTIKAN AREA FABRIKASI JAUH DARI BAHAN MUDAH TERBAKAR SEPERTI CAT, THINER
MINIMAL 15M
B. PASTIKAN MENGGUNAKAN APD LENGKAP SEPERTI FACE SHEILD, KEDOK LAS, SARUNG
WEBING SLING 3T
METODE ERECTION BAJA JEMBATAN DUCTING AREA CRT
LANGKAH KEEMPAT
- PASIR
- KERIKIL
- BAJA/BESI
BAJA/BESI
PASIR
4,17 14,6
KERIKIL 7,57
METODE ERECTION BAJA JEMBATAN DUCTING AREA CRT
LANGKAH KELIMA
LANGKAH KE - 5
PROSIS ERECTION BAJA
- SELANJUTNYA PERSIAPAN ERECTION BAJA
- KARENA JANGKAUAN RADIUS JAUH DARI POSISI JALAN, MAKA PERLU MENGGUNAKAN MOBILE
WEBING SLING 3T 7. PASTIKAN AREA AMAN DARI PEKERJAAN LAIN SAAT ERECTION
8. SETELAH WEBING SLING DIIKAT DENGAN KUAT, CANTOLKAN HOOK KE WEBINGSLING YANG
SUDAH DIIKAT
10. SAAT PENGANGKATAN BAJA, BOOM ROUGH CRANE HARUS MELEWATI ATAS KABEL JANGAN
11. LAKUKAN SECARA PERLAHAN SESUAI DENGAN URUTAN/SKEMA BAJA YANG HARUS
DIPASANG
LANGKAH KEENAM
4 3
7
5 ASIBA 2
1
METODE ERECTION BAJA JEMBATAN DUCTING AREA CRT
LAMPIRAN
LAMPIRAN
LOAD CHART
METODE ERECTION BAJA JEMBATAN DUCTING AREA CRT
LANGKAH KEEMPAT
LANGKAH KE - 4
PROSES PEMASANGAN CHAINBLOCK
- PEMASANGAN CHAINBLOCK
1. PERSIAPKAN ALAT DAN MATERIAL (CHAINBLOCK)
2. LANGSIR CHAINBLOCK KE AREA KERJA
3. SETELAH SCAFFOLDING SELESAI TERINSTAL
4. ANGKAT MANUAL CHAINBLOCK KE ATAS SCAFFOLDING
5. PASTIKAN AREA BAWAH SCAFFOLDING TIDAK ADA PEKERJA LAIN
6. PASANGKAN CAHAINBLOCK KE BAJA EXISTING DENGAN PERLAHAN, LAKUKAN DENGAN HATI-
HATI. UTAMAKAN KESELAMATAN
7. SETELAH TERPASANG DENGAN KUAT PASTIKAN RANTAI TIDAK MACET
8. SETELAH SELESAI MEMASANG CHAINBLOCK, TURUNKAN HOOK CHAINBLOCK UNTUK
DIKAITKAN KE BAJA YANG SUDAH DIIKAT WEBING SLING
9. SELANJUTNYA FLANGE PIPA BISA DILEPAS