METODE KERJA PONDASI ​BORED PILE

SEBUAH. TEKNIS DATA : C. URUTAN KARYA :


SEBUAH. PEKERJAAN PERSIAPAN
1. NAMA PROYEK :
1. UKUR DAN TENTUKAN POSISI TITIK - TITIK BORE PILE DI SITUS
2. JUMLAH TITIK PONDASI :
2. BUAT PABRIKASI KERANJANG BESI BORE PILE
3. DIAMETER BORED PILE :
3. BUAT SHEDULE PENGECORAN BORED PILE DAN TERUS
4. KEDALAMAN BORE PILE :
DIKENDALIKAN
5. MUTU BETON :
4. FORMAT BUAT UNTUK PEMANTAUAN LAPORAN BORE PILE
6. MUTU BESI UNTUK SPIRAL :
7. MUTU BESI UNTUK TULANGAN POKOK :
B. PEKERJAAN BORED PILE
8. VOLUME BETON PEK. TTK BORED PILE :
1. SET ALAT PADA POSISI TITIK YANG AKAN DI BOR
9. BERAT KERANJANG :
2. BILA KONDISI LAPISAN TANAH BAIK
- BOR SAMPAI KEDALAMAN 6 m SAJA
CASING DAN PASANG 6 m
B. PERALATAN YANG DIGUNAKAN :

1. CRANE LAYANAN
2. KELLY
3. MESIN AUGER
4. GENSET DIESEL
5. PIPA CASING DIA. 0.8 M, PANJANG = 16 M
6. MEMBERSIHKAN BUCKET
7. PIPA TREMIE
8. THEODLITE
9. READY MIX (TRUCK MIXER)
10. TREMIE PIPA CONE

3. BILA KONDISI LAPISAN TANAH JELEK


- GUNAKAN FULL CASING UNTUK
MENCEGAH KELONGSORAN TANAH
PADA SAAT PROSES MEMBOSANKAN
- MASUKKAN FULL CASING KEDALAM
PROSES SEBELUM LUBANG BOR
PENGEBORAN DIMULAI DENGAN ALAT
BANTU VIBRO HAMMER

GENSET

5-6M
CASING PENUH SEMENTARA
METODE KERJA PONDASI ​BORED PILE

4. KEMUDIAN DILANJUTKAN DENGAN PROSES PENGEBORAN SAMPAI 6. BERSIHKAN LUMPUR PADA DASAR LUBANG BOR DENGAN
KEDALAMAN YANG DIKEHENDAKI PEMBERSIHAN BUCKET
5. LIHAT APAKAH KEDALAMAN YANG DIKEHENDAKI SUDAH TERCAPAI 7. SELAMA PROSES BERLANGSUNG, CATAT:
- KEDALAMAN MUKA AIR TANAH
- JENIS LAPISAN TANAH BERIKUT DEDALAMAN DAN KETEBALAN
DARI LAPISAN TANAH
8. BUAT LAPORAN HARIAN BORE PILE

SEMENTARA
KASING 6 M CASING PENUH SEMENTARA
ELEV. - 6.00 ELEV. - 6.00 (BILA DIPERLUKAN)

MEMBERSIHKAN BUCKET
METODE KERJA PONDASI ​BORED PILE

D. PEKERJAAN BETON

1. PESAN BETON K - 400., SLUMP 18 +/- 2 CM, KE BATCHING 3. PASANG PIPA TREMI BILA TERDAPAT MUKA AIR TANAH DALAM LUBANG BOR
RENCANA 4. JIKA TIDAK ADA AIR TANAH PENGGUNAAN PIPATREMIC TIDAK MUTLAK
2. PASANG KERANJANG BESI DIPERLUKAN (CUKUP PAKAI CORONG)

PIPA TREMI

ELEV. - 6.00 KERANJANG PEMBESIAN KERANJANG PEMBESIAN

PENUH SEMENTARA PENUH SEMENTARA


CASING DIA. 80 cm L = 16 M. CASING DIA. 80 cm L = 16 M.
METODE KERJA PONDASI ​BORED PILE

5. PROSES PENGECORAN PONDASI ​BORE PILE 6. SEGERA SETELAH PENGECORAN SLESAI, TARIKTEMPORARY CASING
SELAMA PROSES BERLANGSUNG, CEK VOLUME ADAKAH DARI LUBANG BOR
TEORITIC PER LUBANG SUDAH SESUAI DENGAN VOLUME 7. PEKERJAAN BOR SELESAI
BETON YANG DIKIRIM / DICOR KEDALAM LUBANG

ADA

CASING PENUH SEMENTARA


PIPA TREMI

KERANJANG BESI

PENUH SEMENTARA
SELUBUNG
DASAR
METODE YAYASAN BORED PILE

8. BILA BATAS PENGECORAN AKHIR PONDASI ​BORE PILE TERLETAK


DIKEDALAMAN TERTENTU DARI MUKA TANAH STRUKTUR PONDASI ​BORED PILE
- ISI VOLUME LUBANG TERSEBUT DENGAN PASIR SEBUAH. METODE URUTAN BORED PILE AND COR
DENGAN DASAR PERTIMBANGAN K 3

PENGISIAN PASIR

OVER POUR AKAN 1,25 M


POTONG

BORE PILE 13 M
DIA. 80cm
METODE FLOW CHART PEKERJAAN BORED PILE
METODE PEKERJAAN BORED PILE

MULAILAH

UITZET
A. SEBELUM PENGEBORAN DIBUAT TEST-
PIT TERLEBIH DAHULU DAN SEGALA
SESUATU
STEL BESI ASPAL BONGKAR /
SURVEI PEKERJAAN (RANJANG) KAKU. PAV
MENGATUR ALAT

B. PENGEBORAN DIBUAT DALAM 2 (DUA)


TAHAPAN YANG BERBEDA YAITU: GALIAN
- DAERAH SEBUAH 1,50 - 2,00 M
- DAERAH B
PENGEBORAN
MENGGUNAKAN 1 (SATU) UNIT ALAT
BOR DAN 1 (SATU) UNIT SERVICE
CRANE
CASSING + VERTICALITY
+ MASUK BESI RANJANG
C. PEMBUATAN (RANJANG) PEMBESIAN
DISESUAIKAN LOKASI STOCK PILE
COR
C. CAPASITAS PRODUKSI KURANG LEBIH
2 - 3 TITIK / HARI
TUTUP KEMBALI
BEKAS LUBANG

SELESAI
METODE PEKERJAAN BENTONITE

A. DATA TEKNIS SEBAGAI BERIKUT:


- DIA. 60 cm
- L = 11 - 18 m
- 1 m3 = 60 kg SEMUA BENTONITE +
300 kg SEMEN

B. PENENTUAN TITIK BOR

B. PENGEBORAN SESUAIKAN PEIL


KEDALAMAN YANG DITENTUKAN

B. COR YAITU:
- TUANGKAN SEMUA SEMEN
BENTONITE (DESAIN SESUAI MIX)
KEDALAM BUCKET COR / POMPA
BETON KEMUDIAN LUAPANNYA
DIALIRKAN KE TANGKI BENTONIT
- SETELAH SEMEN BENTONITE
MASUKKAN KEDALAM LUBANG
SAMPAI MELUAP DAN SEHINGGA
SEHINGGA DIDAPATKAN
KAPASTIAN BAHWA LUBANG
TELAH SELANJUTNYA SEGERA PIPA
TREMIE DAN CASING DICABUT
ARTINYA BAHWA PEMBUATAN
BENTONITE PILE
TELAH SELESAI
METODE PEKERJAAN JEMBATAN
( PERINTAHKAN KE BAWAH )

A. BONGKAR ASPAL / RIGIT PAV DAN GALIAN TANAH


DAN PEMOTONGAN KEPALA BORED PILE

B. PENGUKURAN UNTUK MENENTUKAN PEIL DAN COR CAPPING BEAM


BUAT / PASANG BEKISTING YAITU TERDIRI: COR (PLAT JEMBATAN
- PEMADATAN TANAH
- PAS. LANTAI KERJA
- PAS. MULTIPLEX 12 mm
MULTIPLEX 12 mm
(BILA TIDAK TERGALI MAKA MENGGUNAKAN LT. KERJA
BATACO BEKISTING)
TUMPUKAN BORED
C. STEL PEMBESIAN SESUAI GBR / BISTAT

C. PENGECORAN YAITU SETELAH PEMBERSIHAN


DAN PENENTUAN PEIL
METODE PEMANCANGAN SHEET PILE

MULAILAH

UITZET

A. PEMANCANGAN DIBUAT DALAM 2 TAHAP BERSAMAAN


YAITU SISI KIRI DAN KANAN (LIHAT GAMBAR)
DENGAN MENGGUNKAN 2 ALAT YAITU MASING-MASING KEDALAMAN ASPAL BONGKAR /
MENGATUR ALAT
SHEET PILE KAKU. PAV
1 UNIT DRIVE PILING DAN 1 UNIT SERVICE CRANE
PENGIRIMAN DARI TOKO KERJA DISESUAIKAN
DENGAN HASIL PEMANCANGAN DILAPANGAN GALIAN
(KARENA STOCK PILE TERBATAS) 1,50 - 2,00 M

B. SEBELUM PANCANG LEBIH DAHULU DIBUAT


TEST-PIT DAN GUIDE BEAM SEPANJANG BALOK PANDUAN PASANG
RETAINNING WALL SEBAGAI REFERENSI
(HARUS KOKOH / KUAT) UNTUK CEK
TERHADAP VERTIKAL / HORIZONTAL SHEET PILE UP

C. CAPASITAS PRODUKSI KURANG LEBIH 4 - 5 TITIK / HARI


DAN HARUS ADA DATA KALENDERING PEMANCANGAN

TUTUP KEMBALI
BEKAS LUBANG

SELESAI
FLOW CHART PEKERJAAN
UNDERPASS CAWANG
MULAILAH

PERSIAPAN

PELEBARAN JALAN KOORDINASI DENGAN INSTANSI TERKAIT


MANAJEMEN LALU LINTAS
PADA TROTOAR / PENEBANGAN / JARINGAN / PIPA / GAS / DLL
PEMINDAHAN POHON

GALIAN
MANAJEMEN LALU LINTAS
1,50 - 2,00 M

YA TIDAK
YA / TIDAK

PEKERJAAN TUMPUKAN BORED Tumpukan LEMBAR PEKERJAAN

CAPPING BEAM
PEIR / ABUTMENT JEMBATAN

LEMPENG & OPRIT JEMBATAN

SELESAI
FLOW CHART PEKERJAAN
UNDERPASS TOMANG
MULAILAH

PERSIAPAN

PELEBARAN JALAN KOORDINASI DENGAN INSTANSI TERKAIT


MANAJEMEN LALU LINTAS
PADA TROTOAR / PENEBANGAN / JARINGAN / PIPA / GAS / DLL
PEMINDAHAN POHON

GALIAN
MANAJEMEN LALU LINTAS
1,50 - 2,00 M

YA TIDAK
YA / TIDAK

PEKERJAAN TUMPUKAN BORED Tumpukan LEMBAR PEKERJAAN

CAPPING BEAM
PEIR / ABUTMENT JEMBATAN

LEMPENG & OPRIT JEMBATAN

SELESAI