METODE

PENGGALIAN
KHUSUS

PROYEK PEMBANGUNAN GRAMEDIA WORLD -


PALEMBANG
PERENCANAAN PENGGALIAN & DEWATERING

Excavator PC 200 : unit


Dump truk kap. 9 m3 : unit
Dozer : unit
Jarak buangan tanah : km
Waktu pelaksanaan : hari
Pompa air : unit
Protector : Ls

Excavation
Bouwplank Board
Remainder

Elev - 0.66
m

EXCAVATION
Bouwplank Patok
DEWATERING
Elev.
m

Excavation for BASEMENT DEWATERING


Apabila diperlukan / sesuai kondisi lapangan
PROYEK PEMBANGUNAN GRAMEDIA WORLD -
PALEMBANG
METODE
PONDASI
BORED PILE
METODE KERJA PONDASI BORED PILE

A. DATA TEKNIS : C. TAHAPAN :


A. PEKERJAAN PERSIAPAN
1. NAMA PROYEK :
1. UKUR DAN TENTUKAN POSISI TITIK – TITIK BORE PILE DI SITE
2. JUMLAH TITIK PONDASI :
2. BUAT PABRIKASI KERANJANG BESI BORE PILE
3. DIAMETER BORED PILE :
3. BUAT SHEDULE PENGECORAN BORED PILE DAN TERUS
4. KEDALAMAN BORE PILE :
DIKENDALIKAN
5. MUTU BETON :
4. BUAT FORMAT UNTUK MONITORING REPORT BORE PILE
6. MUTU BESI UNTUK SPIRAL :
7. MUTU BESI UNTUK TULANGAN POKOK :
B. PEKERJAAN BORED PILE
8. VOLUME BETON PEK. TTK BORED PILE :
1. SET ALAT PADA POSISI TITIK YANG AKAN DI BOR
9. BERAT KERANJANG :
2. BILA KONDISI LAPISAN TANAH BAIK
- BOR SAMPAI KEDALAMAN 6 m SAJA
DAN PASANG CASING 6 m
B. PERALATAN :
1. SERVICE CRANE
2. KELLY
3. AUGER MACHINE
4. DIESEL GENSET
5. PIPE CASING
6. CLEANING BUCKET
7. PIPE TREMIE
8. THEODLITE
9. READY MIX (TRUCK MIXER)
10. TREMIE PIPE CONE 3. BILA KONDISI LAPISAN TANAH JELEK
- GUNAKAN FULL CASING UNTUK
MENCEGAH KELONGSORAN TANAH
PADA SAAT PROSES BORING
- MASUKKAN FULL CASING KEDALAM
LUBANG BOR SEBELUM PROSES
PENGEBORAN DIMULAI DENGAN ALAT
BANTU VIBRO HAMMER

GENSET

5–6M
TEMPORARY FULL CASING
METODE KERJA PONDASI BORED PILE
4. KEMUDIAN DILANJUTKAN DENGAN PROSES PENGEBORAN SAMPAI 6. BERSIHKAN LUMPUR PADA DASAR LUBANG BOR DENGAN
KEDALAMAN YANG DIKEHENDAKI BUCKET CLEANING
5. CHECK APAKAH KEDALAMAN YANG DIKEHENDAKI SUDAH TERCAPAI 7. SELAMA PROSES BERLANGSUNG, CATAT :
- KEDALAMAN MUKA AIR TANAH
- JENIS LAPISAN TANAH BERIKUT DEDALAMAN DAN KETEBALAN
DARI LAPISAN TANAH
8. BUAT LAPORAN HARIAN BORE PILE

TEMPORARY
CASING 6 M TEMPORARY FULL CASING
ELEV. – 6.00 ELEV. – 6.00
(BILA DIPERLUKAN)

CLEANING BUCKET
METODE KERJA PONDASI BORED PILE

D. CONCRETE WORK
3. PASANG PIPA TREMI BILA TERDAPAT MUKA AIR TANAH DALAM LUBANG BOR
4. JIKA TIDAK ADA AIR TANAH PENGGUNAAN PIPATREMIC TIDAK MUTLAK
1. PERSIAPAN PEMESANAN BETON DIPERLUKAN (CUKUP PAKAI CORONG)
2. PASANG KERANJANG BESI

PIPA TREMI

ELEV. – 6.00 KERANJANG PEMBESIAN KERANJANG PEMBESIAN

TEMPORARY FULL TEMPORARY FULL


CASING DIA. 80 cm L=16 M CASING DIA. 80 cm L=16 M
METODE KERJA PONDASI BORED PILE
5. PROSES PENGECORAN PONDASI BORE PILE 6. SEGERA SETELAH PENGECORAN SELESAI, ANGKAT TEMPORARY CASING
SELAMA PROSES BERLANGSUNG, CHECK APAKAH VOLUME DARI LUBANG BOR
TEORITIC PER LUBANG SUDAH SESUAI DENGAN VOLUME 7. PEKERJAAN BOR SELESAI
BETON YANG DICOR KEDALAM LUBANG

EXISTING

TEMPORARY FULL CASING


PIPA TREMI

KERANJANG BESI

TEMPORARY FULL
CASING
DASAR
METODE OF BORED PILE FOUNDATION

8. BILA BATAS PENGECORAN AKHIR PONDASI BORE PILE TERLETAK


DIKEDALAMAN TERTENTU DARI MUKA TANAH STRUKTUR PONDASI BORED PILE
- ISI VOLUME LUBANG TERSEBUT DENGAN PASIR A. METHODE URUTAN BORED PILE AND COR
DENGAN DASAR PERTIMBANGAN K 3

SAND FILLING

OVER POUR WILL 1.25 M


BE CUT OFF

BORE PILE 13 M
DIA. 80cm