Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
I PEKERJAAN PERSIAPAN
II PEKERJAAN DERMAGA
IV PEKERJAAN JALAN
A. Jalan Lingkungan
B. Jalan Pelabuhan
Jumlah
Pembulatan
PPN 10%
Jumlah Total
OREKSI ARITMATIKA
470,800,000.00
12,617,257,000.00
618,207,000.00
23,064,535,000.00
12,948,096,000.00
10,116,439,000.00
36,770,799,000.00
36,770,790,000.00
3,677,079,000.00
40,447,869,000.00
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
10,000,000.00 10,000,000.00
10,000,000.00 10,000,000.00
10,000,000.00 10,000,000.00
50,000,000.00 50,000,000.00
50,000,000.00 50,000,000.00
Sub Total Pekerjaan Pendahuluan 130,000,000.00
5,000,000.00 5,000,000.00
550,000.00 5,500,000.00
450,000.00 4,500,000.00
2,400,000.00 12,000,000.00
5,000,000.00 5,000,000.00
5,000,000.00 15,000,000.00
5,000,000.00 15,000,000.00
500,000.00 25,000,000.00
125,000.00 2,500,000.00
650,000.00 3,250,000.00
45,000.00 2,250,000.00
750,000.00 11,250,000.00
1,050,000.00 52,500,000.00
5,000,000.00 50,000,000.00
150,000.00 7,500,000.00
50,000,000.00 50,000,000.00
2,000,000.00 2,000,000.00
150,000.00 2,700,000.00
1,500,000.00 7,500,000.00
1,500,000.00 7,500,000.00
1,500,000.00 7,500,000.00
1,500,000.00 7,500,000.00
1,500,000.00 7,500,000.00
1,500,000.00 7,500,000.00
5,000,000.00 20,000,000.00
1,500,000.00 1,500,000.00
500,000.00 1,000,000.00
550,000.00 550,000.00
450,000.00 1,800,000.00
Sub Total Pekerjaan Pekerjaan SMK3 340,800,000.00
TOTAL PEKERJAAN PERSIAPAN 470,800,000.00
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
95,000.00 355,680.00
350,000.00 145,600.00
65,000.00 54,080.00
850,000.00 530,400.00
75,000.00 221,625.00
3,500,000.00 10,342,500.00
310,000.00 3,666,990.00
1,450,000.00 17,139,000.00
215,000.00 3,628,125.00
8,500,000.00 26,679,375.00
175,000.00 2,197,125.00
3,500,000.00 4,725,000.00
Sub.Total Pek. Struktur : 69,685,500.00
145,000.00 100,038,400.00
4,500,000.00 6,912,000.00
4,500,000.00 14,175,000.00
550,000.00 227,700,000.00
450,000.00 69,340,500.00
4,500,000.00 25,312,500.00
450,000.00 49,500,000.00
Sub.Total Pek. Penggantian Atap : 492,978,400.00
150,000,000.00 3,000,000,000.00
10,000,000.00 20,000,000.00
25,000,000.00 500,000,000.00
10,000,000.00 20,000,000.00
150,000,000.00 300,000,000.00
950,000.00 1,900,000.00
550,000.00 2,200,000.00
1,050,000.00 8,400,000.00
35,000,000.00 420,000,000.00
3,000,000.00 360,000,000.00
105,000,000.00 840,000,000.00
2,500,000.00 10,000,000.00
450,000,000.00 450,000,000.00
15,000,000.00 15,000,000.00
450,000.00 450,000.00
56,000.00 11,379,200.00
95,000.00 27,307,353.38
550,000.00 1,053,968,025.00
215,000.00 107,500,000.00
195,000.00 97,500,000.00
750,000.00 357,815,700.00
Sub.Total Pek. Paving : 1,670,920,278.38
95,000.00 1,979,752.50
350,000.00 1,326,150.00
1,450,000.00 2,747,025.00
450,000.00 3,888,000.00
850,000.00 8,588,400.00
3,500,000.00 6,630,750.00
450,000.00 104,917,410.00
5,700,000.00 5,681,988.00
8,500,000.00 1,083,750.00
3,750,000.00 5,328,281.25
1,450,000.00 652,500.00
1,500,000.00 1,484,358.75
450,000.00 2,160,000.00
56,000.00 107,520.00
215,000.00 198,146,150.00
105,000.00 48,384,525.00
4,500,000.00 18,000,000.00
3,500,000.00 14,000,000.00
2,050,000.00 16,400,000.00
1,850,000.00 12,950,000.00
1,500,000.00 12,000,000.00
95,000.00 13,680,000.00
125,000.00 800,000.00
65,000.00 3,510,000.00
65,000.00 1,170,000.00
1,500,000.00 4,417,713.00
215,500.00 39,193,416.00
1,510,000.00 6,040,000.00
1,450,000.00 5,800,000.00
1,650,000.00 4,950,000.00
150,000.00 1,650,000.00
5,000,000.00 5,000,000.00
125,000.00 1,250,000.00
250,000.00 1,500,000.00
95,000.00 7,980,000.00
65,000.00 115,440.00
350,000.00 155,400.00
1,450,000.00 1,287,600.00
850,000.00 1,509,600.00
3,500,000.00 1,596,000.00
450,000.00 11,130,210.00
5,700,000.00 2,685,042.00
3,750,000.00 1,282,500.00
4,500,000.00 616,500.00
4,500,000.00 448,560.00
550,000.00 188,100.00
450,000.00 5,310,000.00
1,450,000.00 1,046,900.00
215,000.00 30,305,952.80
105,000.00 7,400,290.80
95,000.00 950,000.00
65,000.00 585,000.00
450,000.00 2,092,500.00
5,700,000.00 1,026,000.00
3,750,000.00 675,000.00
215,000.00 96,750.00
215,000.00 3,870,000.00
1,100,000.00 495,000.00
210,000.00 1,260,000.00
175,000.00 350,000.00
65,000.00 214,500.00
450,000.00 2,092,500.00
5,700,000.00 384,750.00
3,750,000.00 675,000.00
450,000.00 742,500.00
1,100,000.00 242,000.00
JUMLAH SUB TOTAL PEKERJAAN BARU : 644,227,285.10
35,000.00 2,178,750.00
210,000.00 13,072,500.00
350,000.00 145,250,000.00
550,000.00 6,050,000.00
175,000.00 9,800,000.00
450,000.00 7,200,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
1,200,000.00 1,200,000.00
2,100,000.00 8,400,000.00
65,000.00 7,049,900.00
550,000.00 5,500,000.00
100,000.00 8,134,500.00
550,000.00 298,265,000.00
JUMLAH SUB TOTAL PEKERJAAN TAMAN : 514,350,650.00
455,000.00 1,255,800.00
95,000.00 2,956,400.00
35,000.00 522,900.00
215,000.00 13,381,600.00
750,000.00 46,680,000.00
125,000.00 1,164,000.00
145,000.00 139,200.00
215,000.00 619,200.00
135,000.00 297,000.00
215,000.00 412,800.00
550,000.00 11,000,000.00
125,000.00 1,875,000.00
JUMLAH SUB TOTAL PEKERJAAN AMPHITHEATER : 80,303,900.00
65,000.00 1,612,000.00
95,000.00 666,900.00
210,000.00 1,916,460.00
550,000.00 12,548,250.00
JUMLAH SUB TOTAL PEKERJAAN POT BUNGA : 16,743,610.00
450,000.00 450,000.00
65,000.00 37,440,000.00
850,000.00 897,600,000.00
215,000.00 18,812,500.00
125,000.00 100,000,000.00
65,000.00 23,400,000.00
850,000.00 561,000,000.00
1,450,000.00 58,000,000.00
210,000.00 134,400,000.00
654,000.00 87,636,000.00
550,000.00 402,325,000.00
Sub.Total Pek. Tanggulan : 2,321,063,500.00
10,500,000.00 777,000,000.00
-
-
-
-
-
-
-
155,000.00 55,800.00
95,000.00 130,245.00
235,000.00 644,370.00
215,000.00 3,655,000.00
Sub.Total Pek. Lain-lain : 781,485,415.00
215,000.00 1,207,440.00
650,000.00 2,822,976.00
350,000.00 1,365,000.00
95,000.00 661,200.00
95,000.00 342,000.00
1,450,000.00 522,000.00
1,450,000.00 526,350.00
5,000,000.00 1,980,000.00
350,000.00 3,500,000.00
Total Pekerjaan Pelabuhan Ikan Besar : 12,926,966.00
215,000.00 2,507,760.00
650,000.00 5,863,104.00
350,000.00 336,000.00
95,000.00 205,200.00
95,000.00 114,000.00
1,450,000.00 234,900.00
1,450,000.00 227,287.50
5,000,000.00 783,750.00
350,000.00 14,000,000.00
Total Pekerjaan Pelabuhan Ikan Kecil : 24,272,001.50
100,000.00 819,000.00
550,000.00 30,030,000.00
215,000.00 4,536,500.00
195,000.00 4,114,500.00
1,500,000.00 3,000,000.00
550,000.00 3,300,000.00
10,000,000.00 10,000,000.00
Total Pekerjaan Perapihan Sumpur Jepang : 55,800,000.00
JUMLAH SUB TOTAL PEKERJAAN KESELURUHAN : 12,617,257,505.98
Dibulatkan : 12,617,257,000.00
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
95,000.00 775,912.50
350,000.00 354,375.00
1,450,000.00 1,468,125.00
450,000.00 911,250.00
850,000.00 3,060,000.00
3,500,000.00 2,362,500.00
450,000.00 28,350,000.00
5,700,000.00 2,244,375.00
3,750,000.00 7,593,750.00
1,450,000.00 2,936,250.00
25,000,000.00 24,739,312.50
215,000.00 13,545,000.00
105,000.00 3,307,500.00
4,500,000.00 18,000,000.00
1,445,000.00 58,522,500.00
315,000.00 6,378,750.00
1,500,000.00 210,850,500.00
215,500.00 30,292,188.50
3,000,000.00 15,000,000.00
2,500,000.00 5,000,000.00
3,100,000.00 6,200,000.00
450,000.00 3,150,000.00
10,000,000.00 10,000,000.00
250,000.00 2,250,000.00
450,000.00 1,800,000.00
750,000.00 4,500,000.00
150,000,000.00 150,000,000.00
95,000.00 313,500.00
450,000.00 2,092,500.00
5,700,000.00 384,750.00
3,750,000.00 675,000.00
550,000.00 907,500.00
1,100,000.00 242,000.00
618,207,538.50
618,207,000.00
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
95,000.00 431,041,600.00
850,000.00 2,402,979,580.00
2,500,000.00 1,160,100,000.00
Total Drainase 3,994,121,180.00
95,000.00 531,014,375.00
450,000.00 974,484,000.00
10,000.00 26,945,000.00
125,000.00 455,687,500.00
Total Pekerjaan Tanah 1,988,130,875.00
510,000.00 690,259,500.00
L PEKERJAAN PELEBARAN PERKERASAN DAN BAHU JALAN 690,260,672.77
610,000.00 2,465,299,750.00
TOTAL PEKERJAAN PERKERASAN BERBUTIR 2,465,299,750.00
15,000.00 193,350,000.00
3,050,000.00 3,616,934,000.00
TOTAL PEKERJAAN PERKERASAN ASPAL 3,810,284,000.00
Jumlah (A+B+C+D+E) = 12,948,096,477.77
Dibulatkan 12,948,096,000.00
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
B PEKERJAAN TANAH
Galian Biasa M3 5,094.9
Timbunan Biasa dari galian M 3
1,006.4
Penyiapan Badan Jalan M 2
11,322.0
Pembersihan dan Pengupasan Lahan M2 15,096.0
Total Pekerjaan Tanah
E PERKERASAN ASPAL
Lapis Resap Pengikat - Aspal Cair Liter 8,806.0
Lapis Perekat - Aspal Cair Liter 1,320.9
Laston Lapis Aus (AC-WC) Ton 810.2
Laston Lapis Antara (AC-BC) Ton 1,215.2
Total Pekerjaan Perkerasan Aspal
REKAPITULASI PEKERJAAN
Dibu
OREKSI ARITMATIKA
95,000.00 210,337,600
850,000.00 1,172,594,380
2,500,000.00 566,100,000
1,949,031,980
95,000.00 484,015,500
450,000.00 452,880,000
10,000.00 113,220,000
35,000.00 528,360,000
1,578,475,500
510,000.00 192,474,000
192,474,000
610,000.00 2,417,247,000
2,417,247,000
15,000.00 132,090,000
14,500.00 19,153,050
1,950,000.00 1,579,796,400
1,850,000.00 2,248,171,800
3,979,211,250
REKAPITULASI PEKERJAAN JALAN 10,116,439,730
Dibulatkan 10,116,439,000
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
B Pekerjaan Plaza
1 Pemasangan Bronjong Kawat Galvanis M3 429.8
2 Pemasangan Beton K.250 M3 26.5
3 Pemasangan Wiremesh M8 Kg 1,982.9
5 Gazebo 78.6
6 Pemasangan Batu Andesit M2 176.8
JUMLAH SUB TOTAL PEKERJAAN BEACH W
IV. PEKERJAAN RTH DAN AMPHITHEATER
A Pekerjaan RTH
1 Galian tanah ( Diganti tanah Merah ) T.15cm m3 62.25
2 Pek.Urugan Tanah Merah m3 62.25
3 Pek.Tanam Rumput Gajah Mini m2 415.00
4 Pek.Tanam pohon Peneduh btg 11.00
5 Pek.Kansteen Keliling Taman m1 56.00
6 Pek. Tanam Pohon Palm Ekor Tupai btg 16.00
7 Pek. Mainan Anak Perosotan dari bata set 1.00
8 Pek. Mainan Anak Ayunan Gantung set 1.00
9 Pek. Mainan Anak bar set 1.00
10 Pek. Kursi Taman unit 4.00
11 Pek.Galian tanah m3 108.46
12 Pek. Pot bunga dan tempat duduk unit 10.00
13 Pek.Levelling (urugan pasir t=15cm) m3 81.35
14 Pek.Paving t. 8 cm, filler abu batu 1cm m2 542.30
JUMLAH SUB TOTAL PEKERJAAN TA
B Pekerjaan Amphitheater
1 Pek. Pondasi batu kali base tempat duduk m3 2.76
2 Pek. Dinding Batu bata tempat duduk m2 31.12
3 Pek. Urugan puing untuk mengisi Tempat duduk m3 14.94
4 Pek. Plesteran dan Acian m2 62.24
5 Pek. Lapis Lantai WPC ( Wood Plastic Composite ) m2 62.24
6 Pek. Dinding Batu bata area tangga dari bangunan2 ke arah amphi m2 9.31
7 Pek. Dinding Batu bata Anak tangga dari bangunan m2 0.96
8 Pek. Plesteran dan Acian anak Tangga m2 2.88
9 Pek. Batu Bata Anak Tangga ke Pedestrian m2 2.20
10 Pek. Plesteran dan Acian anak Tangga m2 1.92
11 Pek. Drainage dari Amphitheater ke laut pipa 4' m 20.00
12 Pek. Sub drainage ke kolektor pipa 3" m 15.00
JUMLAH SUB TOTAL PEKERJAAN AMPHITHE
95,000.00 157,795,000
736,000.00 1,718,008,000
81,000.00 502,524,000
65,000.00 38,896,000
2,500,000.00 860,500,000
850,000.00 1,907,400,000
17,307.27 192,368,731
450,000.00 788,832,000
300,365.23 1,011,269,656
JUMLAH SUB TOTAL PEKERJAAN BEACH WALK : 7,177,593,387.31
736,000.00 316,322,286
2,500,000.00 66,294,643
17,307.27 34,318,603
3,000,000.00 235,714,286
300,365.23 53,100,282
JUMLAH SUB TOTAL PEKERJAAN BEACH WALK : 705,750,098.71
35,000.00 2,178,750.00
210,000.00 13,072,500.00
350,000.00 145,250,000.00
550,000.00 6,050,000.00
175,000.00 9,800,000.00
450,000.00 7,200,000.00
750,000.00 750,000.00
1,500,000.00 1,500,000.00
1,200,000.00 1,200,000.00
2,100,000.00 8,400,000.00
65,000.00 7,049,900.00
550,000.00 5,500,000.00
100,000.00 8,134,500.00
550,000.00 298,265,000.00
JUMLAH SUB TOTAL PEKERJAAN TAMAN : 514,350,650.00
455,000.00 1,255,800.00
95,000.00 2,956,400.00
35,000.00 522,900.00
215,000.00 13,381,600.00
750,000.00 46,680,000.00
125,000.00 1,164,000.00
145,000.00 139,200.00
215,000.00 619,200.00
135,000.00 297,000.00
215,000.00 412,800.00
550,000.00 11,000,000.00
125,000.00 1,875,000.00
JUMLAH SUB TOTAL PEKERJAAN AMPHITHEATER : 80,303,900.00
95,000.00 775,912.50
350,000.00 354,375.00
1,450,000.00 1,468,125.00
450,000.00 911,250.00
850,000.00 3,060,000.00
3,500,000.00 2,362,500.00
450,000.00 28,350,000.00
5,700,000.00 2,244,375.00
3,750,000.00 7,593,750.00
1,450,000.00 2,936,250.00
25,000,000.00 24,739,312.50
215,000.00 13,545,000.00
105,000.00 3,307,500.00
4,500,000.00 18,000,000.00
1,445,000.00 58,522,500.00
315,000.00 6,378,750.00
1,500,000.00 210,850,500.00
215,500.00 30,292,188.50
3,000,000.00 15,000,000.00
2,500,000.00 5,000,000.00
3,100,000.00 6,200,000.00
450,000.00 3,150,000.00
10,000,000.00 10,000,000.00
250,000.00 2,250,000.00
450,000.00 1,800,000.00
750,000.00 4,500,000.00
150,000,000.00 150,000,000.00
95,000.00 313,500.00
450,000.00 2,092,500.00
5,700,000.00 384,750.00
3,750,000.00 675,000.00
550,000.00 907,500.00
1,100,000.00 242,000.00
618,207,538.50
KOREKSI ARITMATIKA
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
I PEKERJAAN PERSIAPAN
II PEKERJAAN DERMAGA
IV PEKERJAAN RTH
A. PEKERJAAN RTH
B. PEKERJAAN AMPHITHEATER
Jumlah
Pembulatan
PPN 10%
Jumlah Total
OREKSI ARITMATIKA
470,800,000.00
1,551,200,000.00
7,177,593,387.31
705,750,098.71
514,350,650.00
80,303,900.00
618,207,538.50
11,118,205,574.53
11,118,200,000.00
1,111,820,000.00
12,230,020,000.00
ACTION PLAN PELAKSANAAN KSPN MOROTAI TAHUN 2017
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
B Pekerjaan Plaza
1 Pemasangan Bronjong Kawat Galvanis M3 429.8
2 Pemasangan Beton K.250 M3 26.5
3 Pemasangan Wiremesh M8 Kg 1,982.9
5 Gazebo 78.6
6 Pemasangan Batu Andesit M2 176.8
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKTORAT JENDERAL
PENGEMBANGAN KAWASAN CIPTA KARYA
PERMUKIMAN
Jalan Cipaku V. No. 01 Kebayoran Baru, Jakarta Se
BACK UP OF QUANTITY
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
TOTAL 1,661.00
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
BEACH WALK
0+000 - 0+913 913.00 2.00 0.50 913.00
0+000 - 0+913 913.00 1.50 0.50 684.75
0+000 - 0+913 913.00 1.00 0.50 456.50
TOTAL 2,334.25
PLAZA
Plaza Besar Diameter
Bronjong A 18.00 0.50 254.57 127.29
Bronjong B 17.00 0.50 227.07 113.54
Bronjong C 16.00 0.50 201.14 100.57
Bronjong D 15.00 0.50 176.79 88.39
TOTAL 429.79
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKTORAT
PENGEMBANGAN JENDERAL CIPTA KARYA
Jalan Cipaku V. No. 01KAWASAN
Kebayoran PERMUKIMAN
Baru, Jakarta Se
BACK UP OF QUANTITY
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
TOTAL 598.40
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
BEACH WALK
Lantai Kerja
0+000 - 0+227 227 1.40 0.10 31.78
0+463 - 0+786 323 1.40 0.10 45.22
Plat Lantai
0+000 - 0+913 913 2.00 0.10 182.60
0+913 - 0+953 40 2.00 0.15 12.00
TOTAL 344.20
PLAZA Diameter
Plaza Besar 15.00 0.15 176.79 26.52
TOTAL 26.52
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
DIREKTORAT
PENGEMBANGAN JENDERAL CIPTA KARYA
Jalan Cipaku V. No. 01KAWASAN
Kebayoran PERMUKIMAN
Baru, Jakarta Se
BACK UP OF QUANTITY
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
No STATION UNIT PANJANG LEBAR JUMLAH JUMLAH KELILING LUAS TUL VOLUME BJ VOLUME KET
(BH) (M) (M) (Panjang) (Lebar) (M) (M2) (M3) (KG/M3) (KG)
Beach Walk
0+000 - 0+913 913 0.24 0.80 175.30
DIREKTORAT JENDERAL
PENGEMBANGAN KAWASAN CIPTA KARYA
PERMUKIMAN
Jalan Cipaku V. No. 01 Kebayoran Baru, Jakarta Se
BACK UP OF QUANTITY
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
Beach Walk
1 0+000 - 0+913 913.00 1.70 1,552.10
913.00 1.90 1,734.70
2 0+913 - 0+953 40.00 2.00 80.00
TOTAL 3,366.80
TOTAL 176.79
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
ITEM PEKERJAAN : DIV. II, 2.1 Galian untuk Selokan Drainase dan Saluran Air
Jalan Lingkungan
Segmen A
0+000 - 0+259 2 259 1.10 0.80 456
0+259 - 0+277 2 18 1.10 0.80 32
Segmen B
0+000 - 0+179 2 179 1.10 0.80 315
0+179 - 0+267 2 88 1.10 0.80 155
Segmen C
0+000 - 0+130 2 130 1.10 0.80 229
0+130 - 0+167 2 37 1.10 0.80 65
Segmen F
0+000 - 0+164 2 164 1.10 0.80 289
0+164 - 0+167 2 3 1.10 0.80 5
Segmen H
0+000 - 0+215 2 215 1.10 0.80 378
0+215 - 0+386 2 171 1.10 0.80 301
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 2 833 1.10 0.80 1,466
Segmen A
0+000 - 0+259 2 259 0.548 284.02
0+259 - 0+277 2 18 0.548 19.74
Segmen B
0+000 - 0+179 2 179 0.548 196.29
0+179 - 0+267 2 88 0.548 96.50
Segmen C
0+000 - 0+130 2 130 0.548 142.56
0+130 - 0+167 2 37 0.548 40.57
Segmen F
0+000 - 0+164 2 164 0.548 179.84
0+164 - 0+167 2 3 0.548 3.29
Segmen H
0+000 - 0+215 2 215 0.548 235.77
0+215 - 0+386 2 171 0.548 187.52
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 2 833 0.548 913.47
Segmen A
0+000 - 0+259 2 259 0.10 0.90 46.62
0+259 - 0+277 2 18 0.10 0.90 3.24
Segmen B
0+000 - 0+179 2 179 0.10 0.90 32.22
0+179 - 0+267 2 88 0.10 0.90 15.84
Segmen C
0+000 - 0+130 2 130 0.10 0.90 23.40
0+130 - 0+167 2 37 0.10 0.90 6.66
Segmen F
0+000 - 0+164 2 164 0.10 0.90 29.52
0+164 - 0+167 2 3 0.10 0.90 0.54
Segmen H
0+000 - 0+215 2 215 0.10 0.90 38.70
0+215 - 0+386 2 171 0.10 0.90 30.78
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 2 833 0.10 0.90 149.94
RJalan DIREKTORAT
PENGEMBANGAN JENDERAL CIPTA
Cipaku V. No. 01KAWASAN
Kebayoran PERM
Baru,
BACK UP OF QUANTITY
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku U
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
Jalan Lingkungan
Segmen A
0+000 - 0+259 L+R 259 2.50 0.15 2.00
0+259 - 0+277 L+R 18 8.50 0.35 1.00
Segmen B
0+000 - 0+179 L+R 179 2.50 0.15 2.00
0+179 - 0+267 L+R 88 8.50 0.35 1.00
Segmen C
0+000 - 0+130 L+R 130 2.25 0.15 2.00
0+130 - 0+167 L+R 37 8.50 0.35 1.00
Segmen F
0+000 - 0+164 L+R 164 3.25 0.15 2.00
0+164 - 0+167 L+R 3 8.50 0.35 1.00
Segmen H
0+000 - 0+215 L+R 215 2.50 0.15 2.00
0+215 - 0+386 L+R 171 8.50 0.35 1.00
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 L+R 833 9.00 0.45 1.00
L CIPTA KARYA
N PERMUKIMAN STRATEGIS
an Baru, Jakarta Selatan
ANTITY
ai, Provinsi Maluku Utara
VOLUME KET
(M3)
194.25 L = 3.5M
53.55 Jalan Baru
134.25 L = 3.5M
261.80 Jalan Baru
87.75 L = 4M
110.08 Jalan Baru
996.63
1,445.85
159.90 L = 2M
8.93 Jalan Baru
161.25 L = 3.5M
508.73 Jalan Baru
446.25
1,020.43
5,589.63
3,373.65
1,721.25
5,094.90
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
RJalan DIREKTORAT
PENGEMBANGAN JENDERAL CIPTA
Cipaku V. No. 01KAWASAN
Kebayoran PERM
Baru,
BACK UP OF QUANTITY
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku U
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
Jalan Lingkungan
Segmen A
0+000 - 0+259 L+R 259 1.750 0.24 2.00
0+259 - 0+277 L+R 18 1.750 0.24 2.00
Segmen B
0+000 - 0+179 L+R 179 1.750 0.24 2.00
0+179 - 0+267 L+R 88 1.750 0.24 2.00
Segmen C
0+000 - 0+130 L+R 130 1.750 0.24 2.00
0+130 - 0+167 L+R 37 1.750 0.24 2.00
Segmen F
0+000 - 0+164 L+R 164 1.750 0.24 2.00
0+164 - 0+167 L+R 3 1.750 0.24 2.00
Segmen H
0+000 - 0+215 L+R 215 1.750 0.24 2.00
0+215 - 0+386 L+R 171 1.750 0.24 2.00
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 L+R 833 1.00 0.40 2.00
AL
AN CIPTA KARYA
an PERMUKIMAN STRATEGIS
Baru, Jakarta Selatan
ANTITY
ai, Provinsi Maluku Utara
MBER GALIAN
VOLUME KET
(M3)
217.56 L = 3.5M
15.12 Jalan Baru
150.36 L = 3.5M
73.92 Jalan Baru
109.20 L = 4M
31.08 Jalan Baru
281.40
408.24
137.76 L = 2M
2.52 Jalan Baru
180.60 L = 3.5M
143.64 Jalan Baru
126.00
288.12
2,165.52
666.40
340.00
1,006.40
KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT
Jalan Lingkungan
Segmen A
0+000 - 0+259 L = 3.5M
0+259 - 0+277 18 8.50 153.00 Jalan Baru
Segmen B
0+000 - 0+179 L = 3.5M
0+179 - 0+267 88 8.50 748.00 Jalan Baru
Segmen C
0+000 - 0+130 L = 4M
0+130 - 0+167 37 8.50 314.50 Jalan Baru
Segmen F
0+000 - 0+164 L = 2M
0+164 - 0+167 3 8.50 25.50 Jalan Baru
Segmen H
0+000 - 0+215 L = 3.5M
0+215 - 0+386 171 8.50 1,453.50 Jalan Baru
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833 9.00 7,497.00
Jalan Lingkungan
Segmen A
0+000 - 0+259 L = 3.5M
0+259 - 0+277 18 11.50 207.00 Jalan Baru
Segmen B
0+000 - 0+179 L = 3.5M
0+179 - 0+267 88 11.50 1,012.00 Jalan Baru
Segmen C
0+000 - 0+130 L = 4M
0+130 - 0+167 37 11.50 425.50 Jalan Baru
Segmen F
0+000 - 0+164 L = 2M
0+164 - 0+167 3 11.50 34.50 Jalan Baru
Segmen H
0+000 - 0+215 L = 3.5M
0+215 - 0+386 171 11.50 1,966.50 Jalan Baru
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833 12.00 9,996.00
Segmen B
0+000 - 0+179 2 179.00 0.75 0.15 40.28 L = 3.5M
179.00 5.00 0.20 179.00
Segmen C
0+000 - 0+130 2 130.00 0.50 0.15 19.50 L = 4M
130.00 5.00 0.20 130.00
Segmen F
0+000 - 0+164 2 164.00 1.50 0.15 73.80 L = 2M
164.00 5.00 0.20 164.00
Segmen H
0+000 - 0+215 2 215.00 0.75 0.15 48.38 L = 3.5M
215.00 5.00 0.20 215.00
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833.00 7.00 0.45 2,623.95
Segmen B
0+000 - 0+179 2 179.00 1.75 0.15 93.98 L = 3.5M
0+179 - 0+267 2 88.00 1.75 0.15 46.20 Jalan Baru
Segmen C
0+000 - 0+130 2 130.00 1.75 0.15 68.25 L = 4M
0+130 - 0+167 2 37.00 1.75 0.15 19.43 Jalan Baru
Segmen F
0+000 - 0+164 2 164.00 1.75 0.15 86.10 L = 2M
0+164 - 0+167 2 3.00 1.75 0.15 1.58 Jalan Baru
Segmen H
0+000 - 0+215 2 215.00 1.75 0.15 112.88 L = 3.5M
0+215 - 0+386 2 171.00 1.75 0.15 89.78 Jalan Baru
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 2 833.00 1.00 0.15 249.90
Segmen A
0+000 - 0+259 259 5.00 1.00 1,295.00 L = 3.5M
0+259 - 0+277 18 5.00 1.00 90.00 Jalan Baru
Segmen B
0+000 - 0+179 179 5.00 1.00 895.00 L = 3.5M
0+179 - 0+267 88 5.00 1.00 440.00 Jalan Baru
Segmen C
0+000 - 0+130 130 5.00 1.00 650.00 L = 4M
0+130 - 0+167 37 5.00 1.00 185.00 Jalan Baru
Segmen F
0+000 - 0+164 164 5.00 1.00 820.00 L = 2M
0+164 - 0+167 3 5.00 1.00 15.00 Jalan Baru
Segmen H
0+000 - 0+215 215 5.00 1.00 1,075.00 L = 3.5M
0+215 - 0+386 171 5.00 1.00 855.00 Jalan Baru
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833 7.00 1.00 5,831.00
LOKASI DIMENSI
L/R Volume BJ Aspal K e t.
Berat (Ton)
Tebal ( m3 ) (Ton/m3)
Panjang Lebar (t
( STA. ~ STA ) = 4 cm )
b c d e g h i= (h x 2,30) p
Jalan Lingkungan
Segmen A
0+000 - 0+259 259.00 5.00 0.040 51.80 2.30 119.14
0+259 - 0+277 18.00 5.00 0.040 3.60 2.30 8.28
Segmen B
0+000 - 0+179 179.00 5.00 0.040 35.80 2.30 82.34
0+179 - 0+267 88.00 5.00 0.040 17.60 2.30 40.48
Segmen C
0+000 - 0+130 130.00 5.00 0.040 26.00 2.30 59.80
0+130 - 0+167 37.00 5.00 0.040 7.40 2.30 17.02
Segmen F
0+000 - 0+164 164.00 5.00 0.040 32.80 2.30 75.44
0+164 - 0+167 3.00 5.00 0.040 0.60 2.30 1.38
Segmen H
0+000 - 0+215 215.00 5.00 0.040 43.00 2.30 98.90
0+215 - 0+386 171.00 5.00 0.040 34.20 2.30 78.66
LOKASI DIMENSI
L/R Volume BJ Aspal K e t.
Berat (Ton)
Tebal ( m3 ) (Ton/m3)
Panjang Lebar (t
( STA. ~ STA ) = 6 cm )
b c d e g h i= (h x 2,30) p
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833.00 7.00 0.060 349.86 2.30 804.68
Disain
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833.00 7.00 0.15 874.65
1,258.00 1,320.90
PERHITUNGAN KUANTITAS PEKERJAAN
Nama Kegiatan : Pembangunan Kawasan Pariwisata Pulau Morotai, Provinsi Maluku Utara
Lokasi : Pulau Morotai, Provinsi Maluku Utara
Tahun Anggaran : 2017/2018
LOKASI DIMENSI
L/R Volume BJ Aspal K e t.
Berat (Ton)
( m3 ) (Ton/m3)
Tebal
Panjang Lebar (t
( STA. ~ STA ) = 4 cm )
b c d e g h i= (h x 2,30) p
Jalan Pelabuhan
Segmen G (Jalan Baru)
0+000 - 0+833 833.00 7.00 0.040 233.24 2.30 536.45