01 LKPD Banyuasin 2013 Net
01 LKPD Banyuasin 2013 Net
Halaman
DAFTAR ISI ................................................................................................................... i
DAFTAR TABEL............................................................................................................ ii
DAFTAR GAMBAR ....................................................................................................... v
DAFTAR LAMPIRAN ................................................................................................... vi
LAPORAN HASIL PEMERIKSAAN ATAS LAPORAN KEUANGAN ..................... 1
LAPORAN KEUANGAN ............................................................................................... 3
1. LAPORAN REALISASI ANGGARAN ............................................................... 3
2. NERACA ............................................................................................................... 5
3. LAPORAN ARUS KAS ........................................................................................ 7
4. CATATAN ATAS LAPORAN KEUANGAN ..................................................... 9
GAMBARAN UMUM PEMERIKSAAN ....................................................................... 87
LAMPIRAN
Tabel 2.1 PDRB Kabupaten Banyuasin Menurut Lapangan Usaha atas Dasar
Harga Berlaku ......................................................................................... 14
Tabel 2.2 Laju Pertumbuhan Ekonomi Kabupaten Banyuasin Menurut Sektor
(%) 2009-2012 ........................................................................................ 14
Tabel 2.3 Anggaran dan Realisasi Belanja Masing-Masing SKPD Tahun 2013 .... 18
Tabel 4.1 Realisasi Pendapatan per Kelompok Pendapatan Kabupaten Banyuasin
Tahun Anggaran 2013............................................................................. 31
Tabel 4.2 Anggaran dan Realisasi PAD Kabupaten Banyuasin Tahun
2013……………………………………………………………. 32
Tabel 4.3 Rincian Pendapatan Pajak Daerah Kabupaten Banyuasin Tahun 2013 .. 32
Tabel 4.4 Rincian Pendapatan Retribusi Daerah Pemerintah Kabupaten
Banyuasin Tahun 2013………………………………………………. 34
Tabel 4.5 Rincian Retribusi Jasa Umum Pemerintah Kabupaten Banyuasin
Tahun 2013 ............................................................................................. 34
Tabel 4.6 Rincian Retribusi Jasa Usaha Pemerintah Kabupaten BanyuasinTahun
2013 ........................................................................................................ 35
Tabel 4.7 Rincian Pendapatan Retribusi Jasa Perizinan Tertentu Pemerintah
Kabupaten Banyuasin Tahun 2013 ......................................................... 35
Tabel 4.8 Rincian Lain-lain Pendapatan Asli Daerah yang Sah Pemerintah
Kabupaten Banyuasin Tahun 2013 ......................................................... 36
Tabel 4.9 Daftar Bunga Deposito ........................................................................... 37
Tabel 4.10 Pendapatan atas Bunga Deposito yang Ditangguhkan ............................ 37
Tabel 4.11 Rincian Penerimaan Lain-lain Pemerintah Kabupaten Banyuasin
Tahun 2013 ............................................................................................. 38
Tabel 4.12 Rincian Realisasi Pendapatan Lelang Lebak Lebung Tahun 2013 ......... 38
Tabel 4.13 Rincian Pendapatan Transfer - Dana Perimbangan Pemerintah
Kabupaten Banyuasin Tahun 2013 ......................................................... 39
Tabel 4.14 Rincian Pendapatan Transfer Pemerintah Pusat - Lainnya Dana 40
Penyesuaian Tahun 2013 ........................................................................
Tabel 4.15 Rincian Pendapatan Transfer Pemerintah Provinsi Dana Bagi Hasil 40
Pajak Tahun 2013 ...................................................................................
Tabel 4.16 Rincian Lain-lain Pendapatan yang Sah Tahun 2013 ............................. 41
Tabel 4.17 Rincian Belanja Daerah Pemerintah Kabupaten Banyuasin Tahun 2013 42
Tabel 4.18 Rincian Belanja Pegawai Pemerintah Kabupaten Banyuasin Tahun
2013 ........................................................................................................ 43
Tabel 4.19 Rincian Belanja Barang dan Jasa Pemerintah Kabupaten Banyuasin
Tahun 2013 ............................................................................................. 43
Tabel 4.20 Rincian Belanja Hibah PPKD Tahun 2013 ............................................. 44
Tabel 4.21 Rincian Belanja Hibah SKPD Tahun 2013 ............................................. 44
Tabel 4.22 Belanja Bantuan Sosial yang dikelola oleh PPKD.................................. 45
Tabel 4.23 Belanja Bantuan Sosial yang dikelola oleh SKPD Tahun 2013 ............. 46
Tabel 4.24 Rincian Belanja Bantuan Keuangan Tahun 2013 ................................... 46
Tabel 4.25 Rincian Belanja Bantuan Keuangan Partai Politik ................................. 47
Tabel 4.26 Daftar Belanja Modal menjadi Aset Tetap ............................................. 48
ii
BPK Perwakilan Provinsi Sumatera Selatan
Tabel 4.27 Rincian Belanja Modal Tanah Tahun 2013 ............................................ 50
Tabel 4.28 Rincian Belanja Modal Peralatan dan Mesin Tahun 2013 ...................... 51
Tabel 4.29 Rincian Belanja Modal Gedung dan Bangunan Tahun 2013 .................. 52
Tabel 4.30 Rincian Belanja Modal Jalan Irigasi dan Jaringan Tahun 2013.............. 53
Tabel 4.31 Rincian Belanja Modal Aset Tetap Lainnya Tahun 2013 ....................... 53
Tabel 4.32 Rincian Belanja Tak Terduga Tahun 2013 ............................................. 54
Tabel 4.33 Rincian Pengeluaran Pembiayaan Daerah Tahun 2013 .......................... 54
Tabel 4.34 Rincian SiLPA ........................................................................................ 55
Tabel 4.35 Rincian Aset Pemerintah Kabupaten Banyuasin .................................... 56
Tabel 4.36 Rincian Aset Lancar Pemerintah Kabupaten Banyuasin ........................ 57
Tabel 4.37 Rincian jumlah Kas danSetara Kas ......................................................... 57
Tabel 4.38 Rincian Kas di Kas Daerah Pemerintah Kabupaten Banyuasin .............. 57
Tabel 4.39 Rincian Kas di Bendahara Pengeluaran .................................................. 58
Tabel 4.40 Rincian Piutang Dana Perimbangan ....................................................... 60
Tabel 4.41 Rekapitulasi piutang terhadap anggota DPRD........................................ 60
Tabel 4.42 Rincian Piutang PFK............................................................................... 61
Tabel 4.43 Rincian Piutang Lainnya ......................................................................... 61
Tabel 4.44 Rincian Persediaan per Jenis Persediaan ................................................ 61
Tabel 4.45 Rincian Penyertaan Modal Pemerintah Kabupaten Banyuasin ............... 62
Tabel 4.46 Perhitungan Alokasi Kerugian atas Penyertaan pada PDAM Tirta
Betuah ...................................................................................................... 63
Tabel 4.47 Rincian Mutasi Aset Tetap Pemerintah Kabupaten Banyuasin .............. 63
Tabel 4.48 Rincian Mutasi Aset Tanah..................................................................... 63
Tabel 4.49 Rincian Mutasi Aset Peralatan dan Mesin .............................................. 64
Tabel 4.50 Rincian Mutasi Aset Gedung dan Bangunan .......................................... 65
Tabel 4.51 Rincian Mutasi Aset Jalan Irigasi dan Jaringan ...................................... 66
Tabel 4.52 Rincian Mutasi Aset Tetap Lainnya........................................................ 67
Tabel 4.53 Rincian Konstruksi dalam Pengerjaan .................................................... 67
Tabel 4.54 Rincian Aset Lainnya.............................................................................. 68
Tabel 4.55 Rincian Aset Lain-lain ............................................................................ 68
Tabel 4.56 Rincian Tagihan Kepada Anggota DPRD .............................................. 69
Tabel 4.57 Rincian Detail Engeneering Design (DED) Dinas PU Bina Marga ....... 70
Tabel 4.58 Rincian Detail Engeneering Design (DED) Dinas PU Cipta Karya ....... 70
Tabel 4.59 Rincian Detail Engeneering Design (DED) Dinas PU Pengairan .......... 71
Tabel 4.60 Rincian Detail Engeneering Design (DED) BAPPEDA ........................ 71
Tabel 4.61 Rincian Detail Engeneering Design (DED) Dinas Kebersihan,
Pertamanan dan Pemakaman ................................................................... 72
Tabel 4.62 Rincian Detail Engeneering Design (DED) Dinas Tenaga Kerja dan
Transmigrasi ............................................................................................ 72
Tabel 4.63 Rincian Detail Engeneering Design (DED) Dinas Pariwisata Seni, 73
Budaya, Pemuda dan Olahraga ................................................................
Tabel 4.64 Rincian Detail Engeneering Design (DED) Dinas Pelayanan Keluarga
Berencana ................................................................................................ 73
Tabel 4.65 Rincian Detail Engeneering Design (DED) Dinas Pertanian dan 73
Peternakan ...............................................................................................
Tabel 4.66 Rincian Detail Engeneering Design (DED) Badan Lingkungan Hidup .
74
iii
BPK Perwakilan Provinsi Sumatera Selatan
Tabel 4.67 Rincian Detail Engeneering Design (DED) Badan Perpustakaan dan
arsip daerah ............................................................................................. 74
Tabel 4.68 Rincian Barang Rusak/Penghapusan ...................................................... 74
Tabel 4.69 Aset yang belum ditemukan fisiknya ...................................................... 75
Tabel 4.70 Rincian Utang Perhitungan Fihak Ketiga (PFK) .................................... 76
Tabel 4.71 Rincian Ekuitas Dana Lancar.................................................................. 77
Tabel 4.72 Rincian Sisa Lebih Pembiayaan Anggaran (SiLPA) .............................. 77
Tabel 4.73 Rincian Ekuitas Dana Investasi .............................................................. 78
Tabel 4.74 Rincian Arus Kas dari Aktivitas Operasi ................................................ 80
Tabel 4.75 Arus Kas dari Aktivitas Investasi Aset Non Keuangan .......................... 81
Tabel 4.76 Arus Kas dari Aktivitas Pembiayaan ...................................................... 82
Tabel 4.77 Arus Kas dari Aktivitas Non Anggaran .................................................. 82
Tabel 4.78 Rincian Saldo Akhir Arus Kas ................................................................ 83
iv
BPK Perwakilan Provinsi Sumatera Selatan
DAFTAR GAMBAR
Halaman
Menurut opini BPK, laporan keuangan yang disebut di atas menyajikan secara wajar,
dalam semua hal yang material, Realisasi Anggaran dan posisi keuangan Pemerintah
Kabupaten Banyuasin tanggal 31 Desember 2013 dan 2012, serta Arus Kas untuk tahun
yang berakhir pada tanggal-tanggal tersebut sesuai dengan Standar Akuntansi
Pemerintahan.
(dalam rupiah)
1 PENDAPATAN 4.1.1
2 PENDAPATAN ASLI DAERAH 4.1.1.1
3 Pendapatan Pajak Daerah 4.1.1.1.1 19.053.055.123,10 31.068.706.961,50 163,06 25.771.804.113,50
4 Pendapatan Retribusi Daerah 4.1.1.1.2 27.829.108.900,00 30.834.820.843,10 110,80 24.074.875.998,77
5 Pendapatan Hasil Pengelolaan Kekayaan Daerah yang
4.1.1.1.3 817.451.610,00 1.891.776.235,73 231,42 2.809.634.764,67
Dipisahkan
6 Lain-lain Pendapatan Asli Daerah yang Sah 4.1.1.1.4 6.570.656.599,42 17.569.082.842,91 267,39 15.110.892.373,75
7 Jumlah Pendapatan Asli Daerah (3 s.d 6) 54.270.272.232,52 81.364.386.883,24 149,92 67.767.207.250,69
8 PENDAPATAN TRANSFER 4.1.1.2
9 Transfer dari Pemerintah Pusat – Dana Perimbangan 4.1.1.2.1
10 Dana Bagi Hasil Pajak 4.1.1.2.1.1 169.641.690.439,00 164.445.668.681,00 96,94 150.904.713.706,00
11 Dana Bagi Hasil Sumber Daya Alam 4.1.1.2.1.2 207.673.789.312,92 210.745.575.432,00 101,48 216.033.376.450,00
12 Dana Alokasi Umum 4.1.1.2.1.3 772.464.315.000,00 772.464.315.000,00 100,00 651.357.692.000,00
13 Dana Alokasi Khusus 4.1.1.2.1.4 147.190.480.000,00 147.190.480.000,00 100,00 97.453.050.000,00
14 Jumlah Pendapatan Transfer Dana Perimbangan
1.296.970.274.751,92 1.294.846.039.113,00 99,84 1.115.748.832.156,00
(10 s.d 13)
15 Transfer dari Pemerintah Pusat – Lainnya 4.1.1.2.2
16 Dana Otonomi Khusus 4.1.1.2.2.1 0,00 0,00 0,00 0,00
17 Dana Penyesuaian 4.1.1.2.2.2 170.389.389.500,00 168.721.797.000,00 99,02 148.274.598.709,00
18 Jumlah Pendapatan Transfer Pemerintah Pusat
170.389.389.500,00 168.721.797.000,00 99,02 148.274.598.709,00
Lainnya (16 s.d 17)
19 Transfer Pemerintah Provinsi 4.1.1.2.3
20 Pendapatan Bagi Hasil Pajak 4.1.1.2.3.1 28.711.914.400,00 6.568.401.600,00 22,88 29.096.882.836,27
21 Pendapatan Bagi Hasil Lainnya 4.1.1.2.3.2 0,00 0,00 0,00 0,00
22 Jumlah Pendapatan Transfer Pemerintah
28.711.914.400,00 6.568.401.600,00 22,88 29.096.882.836,27
Provinsi (20 s.d 21)
23 Jumlah Pendapatan Transfer (14+18+22) 1.496.071.578.651,92 1.470.136.237.713,00 98,27 1.293.120.313.701,27
24 LAIN-LAIN PENDAPATAN YANG SAH 4.1.1.3
25 Pendapatan Hibah 4.1.1.3.1 0,00 - 0,00 197.729.094,00
26 Pendapatan Dana Darurat 4.1.1.3.2 0,00 0,00 0,00 0,00
27 Pendapatan Lainnya 4.1.1.3.3 105.609.349.000,00 112.179.164.654,00 106,22 31.552.357.924,00
28 Jumlah Lain-lain Pendapatan yang Sah
105.609.349.000,00 112.179.164.654,00 106,22 31.750.087.018,00
(25 s.d 27)
29 JUMLAH PENDAPATAN (7+23+28) 1.655.951.199.884,44 1.663.679.789.250,24 100,47 1.392.637.607.969,96
30 BELANJA 4.1.2
31 BELANJA OPERASI 4.1.2.1
32 Belanja Pegawai 4.1.2.1.1 652.137.729.331,36 592.097.166.177,00 90,79 539.395.295.010,00
33 Belanja Barang 4.1.2.1.2 410.217.893.550,45 377.872.151.087,63 92,11 320.918.526.678,99
34 Belanja Bunga 4.1.2.1.3 0,00 0,00 0,00 0,00
35 Belanja Subsidi 4.1.2.1.4 0,00 0,00 0,00 408.000.000,00
36 Belanja Hibah 4.1.2.1.5 122.298.329.765,00 101.749.175.090,00 83,20 33.443.595.775,00
37 Belanja Bantuan Sosial 4.1.2.1.6 6.751.901.150,00 6.244.534.000,00 92,49 5.142.580.000,00
38 Belanja Bantuan Keuangan 4.1.2.1.7 29.343.760.000,00 29.158.727.525,00 99,37 29.298.154.525,00
39 Jumlah Belanja Operasi (32 s.d 38) 1.220.749.613.796,81 1.107.121.753.879,63 90,69 928.606.151.988,99
40 BELANJA MODAL 4.1.2.2
41 Belanja Tanah 4.1.2.2.1 10.388.211.410,00 6.209.266.322,00 59,77 7.016.917.912,83
42 Belanja Peralatan dan Mesin 4.1.2.2.2 113.281.823.835,00 106.884.769.126,00 94,35 57.277.278.559,00
43 Belanja Gedung dan Bangunan 4.1.2.2.3 107.220.486.235,00 103.380.603.400,00 96,42 123.141.646.175,00
44 Belanja Jalan, Irigasi dan Jaringan 4.1.2.2.4 331.804.014.643,00 319.532.260.175,00 96,30 140.221.582.232,50
45 Belanja Aset Tetap Lainnya 4.1.2.2.5 42.515.805.000,00 25.746.763.636,00 60,56 10.075.558.420,00
46 Belanja Aset Lainnya 4.1.2.2.6 0,00 0,00 0,00 0,00
47 Jumlah Belanja Modal (41 s.d 46) 605.210.341.123,00 561.753.662.659,00 92,82 337.732.983.299,33
48 BELANJA TAK TERDUGA 4.1.2.3
49 Belanja Tak Terduga 4.1.2.3.1 284.360.169,00 25.213.322,00 8,87 554.660.000,00
50 Jumlah Belanja Tidak Terduga (49) 284.360.169,00 25.213.322,00 8,87 554.660.000,00
51 JUMLAH BELANJA (39+47+50) 1.826.244.315.088,81 1.668.900.629.860,63 91,38 1.266.893.795.288,32
NO URAIAN Ref ANGGARAN 2013 REALISASI 2013 % REALISASI 2012
52 TRANSFER
53 TRANSFER BAGI HASIL KE KAB/KOTA
54 Bagi Hasil Pajak 0,00 0,00 0,00 0,00
55 Bagi Hasil Retribusi 0,00 0,00 0,00 0,00
56 Bagi Hasil Pendapatan Lainnya 0,00 0,00 0,00 0,00
57 Jumlah Transfer/Bagi Hasil ke Desa (54 s.d 56) 0,00 0,00 0,00 0,00
58 JUMLAH BELANJA DAN TRANSFER (51+57) 1.826.244.315.088,81 1.668.900.629.860,63 91,38 1.266.893.795.288,32
59 JUMLAH SURPLUS/DEFISIT (170.293.115.204,37) (5.220.840.610,39) 3,07 125.743.812.681,64
60 PEMBIAYAAN 4.1.3
61 PENERIMAAN PEMBIAYAAN 4.1.3.1
62 Penggunaan Sisa Lebih Perhitungan Anggaran (SILPA) 4.1.3.1.1 192.422.116.156,00 192.443.988.035,43 100,01 88.754.577.587,29
63 Penerimaan Piutang Daerah 4.1.3.1.2 0,00 14.638.602.897,00 0,00 55.253.836,00
64 Jumlah Penerimaan Pembiayaan (62 s.d 63) 192.422.116.156,00 207.082.590.932,43 107,62 88.809.831.423,29
65 PENGELUARAN PEMBIAYAAN 4.1.3.2
66 Pembentukan Dana Cadangan 4.1.3.2.1 0,00 0,00 0,00 0,00
67 Penyertaan Modal (Investasi) Pemerintah Daerah 4.1.3.2.2 5.000.000.000,00 5.000.000.000,00 100,00 5.000.000.000,00
68 Pembayaran Pokok Utang 4.1.3.2.3 17.129.000.951,63 11.447.334.963,50 66,83 17.109.656.069,50
69 Jumlah Pengeluaran Pembiayaan (66 s.d 68) 22.129.000.951,63 16.447.334.963,50 74,32 22.109.656.069,50
70 PEMBIAYAAN NETTO (64-69) 170.293.115.204,37 190.635.255.968,93 111,95 66.700.175.353,79
71 SISA LEBIH PEMBIAYAAN ANGGARAN (SiLPA) (59+70) 0,00 185.414.415.358,54 0,00 192.443.988.035,43
Catatan atas Laporan Keuangan merupakan bagian yang tidak terpisahkan dari Laporan Keuangan Pokok
2. NERACA
(dalam rupiah)
1 ASET 4.2.1
2 ASET LANCAR 4.2.1.1
3 Kas di Kas Daerah 4.2.1.1.1 99.384.566.996,54 182.240.776.880,43
4 Kas di Bendahara Pengeluaran 4.2.1.1.2 5.994.378.732,00 198.882.083,00
5 Kas di Bendahara Penerimaan 4.2.1.1.3 90.221.300,00 6.145.000,00
6 Kas dan Setara Kas (Deposito) 4.2.1.1.4 80.344.128.953,60 10.232.596.863,00
8 Piutang Pajak 4.2.1.1.5 30.876.570.111,62 806.682.754,62
9 Piutang Retribusi 4.2.1.1.6 46.985.000,00 81.835.142,00
10 Piutang Dana Perimbangan 4.2.1.1.7 48.121.965.663,72 24.897.397.913,72
11 Bagian Lancar Tuntutan Ganti Rugi 4.2.1.1.8 42.100.000,00 471.157.660,61
12 Piutang PFK 4.2.1.1.9 35.469.630,00 6.269.805,00
13 Bagian Lancar Piutang Dewan 4.2.1.1.10 1.336.779.914,00 0,00
14 Piutang Lainnya 4.2.1.1.11 156.800.000,00 86.200.000,00
15 Persediaan 4.2.1.1.12 9.929.754.640,77 9.632.090.066,33
16 Jumlah Aset Lancar (3 s.d 15) 276.359.720.942,25 228.660.034.168,71
37 KEWAJIBAN 4.2.2
38 KEWAJIBAN JANGKA PENDEK 4.2.2.1
39 Utang Perhitungan Fihak Ketiga (PFK) 4.2.2.1.1 0,00 1.940.733,00
40 Utang kepada Pemerintah Provinsi 4.2.2.1.2 2.175.865.863,35 2.175.865.863,35
41 Utang Pihak Ketiga 4.2.2.1.3 31.191.989.332,70 14.436.544.381,13
42 Jumlah Kewajiban Jangka Pendek ( 39 s.d 41) 33.367.855.196,05 16.614.350.977,48
(dalam rupiah)
9
4. menyediakan informasi mengenai bagaimana pemerintah daerah mendanai
seluruh kegiatannya dan mencukupi kebutuhan kasnya;
5. menyediakan informasi mengenai posisi keuangan dan kondisi pemerintah
daerah berkaitan dengan sumber-sumber penerimaannya, baik jangka pendek
maupun jangka panjang, termasuk yang berasal dari pungutan pajak dan
pinjaman;
6. menyediakan informasi mengenai perubahan posisi keuangan pemerintah
daerah, apakah mengalami kenaikan atau penurunan, sebagai akibat kegiatan
yang dilakukan selama periode pelaporan.
10
20. Peraturan Menteri Dalam Negeri Nomor 21 Tahun 2011 tentang Perubahan
Kedua Atas Peraturan Menteri Dalam Negeri Nomor 13 Tahun 2006 tentang
Pedoman Pengelolaan Keuangan Daerah;
21. Peraturan Menteri Dalam Negeri Nomor 17 Tahun 2007 tentang Pedoman
Teknis Pengelolaan Barang Milik Daerah;
22. Peraturan Menteri Dalam Negeri Nomor 4 Tahun 2008 tentang Pedoman
Pelaksanaan Reviu Laporan Keuangan;
23. Peraturan Menteri Dalam Negeri Nomor 32 Tahun 2011 tentang Pedoman
Pemberian Hibah dan Bantuan Sosial yang bersumber dari Anggaran
Pendapatan dan Belanja Daerah dan perubahannya;
24. Peraturan Daerah Nomor 27 Tahun 2006 tentang Pokok-Pokok Pengelolaan
Keuangan Daerah.
25. Peraturan Daerah Nomor 27 Tahun 2012 tentang Anggaran Pendapatan dan
Belanja Daerah Kabupaten Banyuasin Tahun 2013;
26. Peraturan Daerah Nomor 2 Tahun 2013 tentang Perubahan Anggaran
Pendapatan dan Belanja Daerah Kabupaten Banyuasin Tahun 2013;
27. Peraturan Bupati Banyuasin Nomor 911 Tahun 2012 tentang Kebijakan
Akuntansi Pemerintah Kabupaten Banyuasin.
11
4.3.4. Aktivitas Non Anggaran
V. Penjelasan Atas Informasi-Informasi Non Keuangan
5.1. Informasi Tambahan
5.2. Pengungkapan Lainnya
5.2.1. Domisili
5.2.2. Ketentuan Perundang-undangan yang Menjadi Landasan
Kegiatan Operasional
5.2.3. Struktur Organisasi
VI. Penutup
12
II. EKONOMI MAKRO, KEBIJAKAN KEUANGAN DAN IKHTISAR
PENCAPAIAN KINERJA KEUANGAN
2.1. Ekonomi Makro
Visi Kabupaten Banyuasin Tahun 2009-2013 yaitu “Banyuasin Sebagai
Kawasan Yang Mandiri dan Berdaya Saing”. Dalam rangka mewujudkan visi
maka perlu disusun misi yang merupakan rumusan umum mengenai upaya-upaya
yang akan dilaksanakan untuk mewujudkan harapan di masa depan. Sesuai dengan
visi di atas maka dirumuskan Misi dalam pemerintahan Kabupaten Banyuasin
untuk periode 2009 – 2013, sebagai berikut.
1. Meningkatkan kualitas sumber daya manusia;
2. Meningkatkan pengelolaan sumber daya alam yang berwawasan lingkungan;
3. Mewujudkan tata kelola pemerintahan yang akuntabel;
4. Meningkatkan pemerataan dan pertumbuhan ekonomi daerah.
Kabupaten Banyuasin dibentuk karena adanya pertimbangan pesatnya
perkembangan pembangunan di Provinsi Sumatera Selatan umumnya dan
khususnya di Kabupaten Musi Banyuasin yang diperkuat oleh aspirasi masyarakat
untuk meningkatkan penyelenggaraan pemerintah, pelaksanaan pembangunan dan
pelayanan guna menjamin kesejahteraan masyarakat. Kabupaten Banyuasin
dibentuk atas dasar Undang-Undang Nomor 6 Tahun 2002 yang diresmikan tanggal
2 Juli 2002 oleh Menteri Dalam Negeri atas nama Presiden dengan ibukota
Pangkalan Balai.
Kabupaten Banyuasin mempunyai wilayah seluas 11.832,99 km2, dan
memiliki topografi 80% wilayah berupa lahan rawa pasang surut dan rawa lebak,
sedangkan 20% berupa lahan kering. Secara administratif Kabupaten Banyuasin
mempunyai batas-batas wilayah, sebagai berikut.
- Sebelah Utara: Berbatasan dengan Kabupaten Tanjung Jabung Timur Provinsi
Jambi dan Selat Bangka;
- Sebelah Timur: Berbatasan dengan Kecamatan Pampangan dan Air Sugihan
Kabupaten Ogan Komering Ilir;
- Sebelah Selatan: Berbatasan dengan Kecamatan Jejawi Kabupaten Ogan
Komering Ilir, Kota Palembang, Kecamatan Sungai Rotan dan Talang Ubi
Kabupaten Muara Enim;
- Sebelah Barat: Berbatasan dengan Kabupaten Musi Banyuasin.
Pertumbuhan Ekonomi
Pertumbuhan ekonomi pada suatu daerah menjadi parameter atau ukuran yang
menunjukkan sejauh mana aktivitas perekonomian terutama sektor ekonomi kreatif
yang dilakukan oleh berbagai stakeholder dapat menghasilkan tambahan pendapatan
bagi masyarakatnya. Keberhasilan pembangunan pada suatu daerah termasuk di
Kabupaten Banyuasin, salah satunya juga dicirikan dengan perbaikan pertumbuhan
ekonomi yang pada akhirnya akan memperbaiki kesejahteraan masyarakat
Kabupaten Banyuasin. Secara teoritis perekonomian mengalami pertumbuhan
apabila pendapatan riil masyarakat pada tahun tertentu lebih besar daripada
pendapatan riil masyarakat pada tahun sebelumnya.
13
Produk Domestik Regional Bruto (PDRB)
Indikator yang lazim digunakan untuk mengukur pertumbuhan ekonomi
adalah tingkat pertumbuhan Produk Domestik Regional Bruto (PDRB). PDRB
adalah jumlah nilai tambah yang dihasilkan oleh seluruh aktivitas produksi dalam
perekonomian. Peningkatan PDRB mencerminkan peningkatan balas jasa kepada
faktor produksi yang digunakan dalam aktivitas produksi tersebut.
PDRB Kabupaten Banyuasin didominasi oleh sektor pertanian, yaitu sebesar
30,35% pada Tahun 2012 lebih dari seperempat nilai PDRB Kabupaten Banyuasin.
Kemudian diikuti sektor industri pengolahan yang mempunyai peranan sebesar
24,89%. Sektor pertambangan dan penggalian menduduki peringkat ketiga dalam
memberikan kontribusinya terhadap PDRB Kabupaten Banyuasin, yakni
menyumbang 14,39%. Lalu di peringkat ke empat adalah sektor perdagangan, hotel
dan restoran sebesar 13,05%. Dibawahnya ada sektor bangunan sebesar 9,19%.
Sektor jasa-jasa ada di posisi ke enam yang pada Tahun 2012 sebesar 6,69%. Lalu
setelah itu ada sektor keuangan, persewaan dan jasa perusahaan sebesar 0,74%.
Sektor pengangkutan dan komunikasi ada di urutan dua dari yang terkecil di
sembilan sektor yaitu sebesar 0,66%. Dan yang mempunyai peranan terkecil berada
di sektor listrik, gas dan air bersih menyumbang sebesar 0,04%.
14
No. Lapangan Usaha 2009 2010 2011 2012
Laju Pertumbuhan Ekonomi (PDRB dengan Migas) 5,47 6,10 6,14 6,23
PDRB dengan migas 2012 = (71,16/70,30 x 100) - 100
1. Kebijakan Pendapatan
Pendapatan daerah merupakan faktor sangat penting berkaitan dengan
kemampuan daerah untuk menyelenggarakan pelayanan umum bagi masyarakat,
melaksanakan pembangunan disamping menyelenggarakan pemerintahan itu
sendiri di daerah. Pendapatan daerah terdiri dari tiga kelompok pendapatan, yaitu
Pendapatan Asli Daerah, Pendapatan Dana Perimbangan dan Lain-lain Pendapatan
yang Sah. Adapun jenis kelompok pendapatan tersebut, adalah sebagai berikut.
a. Pendapatan Asli Daerah, terdiri atas:
1) Hasil Pajak Daerah;
2) Hasil Retribusi Daerah;
3) Hasil Pengelolaan Kekayaan Daerah yang Dipisahkan;
4) Lain-lain Pendapatan Asli Daerah yang Sah.
b. Pendapatan Transfer, terdiri atas:
1) Transfer Pemerintah Pusat-Dana Perimbangan;
a) Dana Bagi Hasil Pajak;
b) Dana Bagi Hasil Sumber Daya Alam;
c) Dana Alokasi Umum;
d) Dana Alokasi Khusus.
2) Transfer Pemerintah Pusat Lainnya;
3) Transfer Pemerintah Provinsi.
c. Lain-lain Pendapatan yang Sah, terdiri atas:
1) Pendapatan Lain-lain;
2) Bantuan Keuangan Provinsi.
Terkait dengan upaya untuk mencapai target pendapatan daerah pada
Tahun Anggaran 2013, terdapat tiga kebijakan penting sebagaimana yang telah dan
akan terus dikembangkan di masa depan, yaitu:
a. Menumbuhkembangkan pemikiran kewirausahaan pada masing-masing SKPD
untuk tidak hanya berorientasi kepada belanja, tetapi sebaliknya juga
berorientasi kepada sikap/perilaku menghasilkan, termasuk pelayanan prima
yang pada akhirnya meningkatkan pendapatan daerah.
b. Menggalang potensi-potensi daerah yang dapat memperbesar skala ekonomi
masyarakat Banyuasin sehingga dapat bertambahnya objek-objek pajak dan
atau retribusi baru.
15
c. Melaksanakan secara kontinyu upaya intensifikasi pendapatan daerah, tanpa
menyebabkan pemberatan ekonomi masyarakat di daerah.
Disamping tiga hal di atas, terdapat dua kebijakan strategis yang akan tetap
dijalankan pemerintah daerah sebagaimana kebijakan yang dimuat dalam
Anggaran Pendapatan tahun sebelumnya, yaitu sebagai berikut.
a. Melakukan penyertaan modal daerah yang telah dilakukan mulai Tahun 2004
kepada unit-unit usaha komersial yang sehat (solvable) dan memiliki
rentabilitas usaha tinggi sebagimana penyertaan modal pada Bank
SumselBabel.
b. Mendorong dan memfasilitasi terjadinya kemitraan investasi antara Investor,
masyarakat dan pemerintah daerah dalam bidang usaha yang mampu
membesarkan skala perekonomian daerah. Pembesaran skala ekonomi daerah
akan berdampak sangat luas, bukan saja pendapatan daerah akan meningkat
melalui Bagi Hasil PBB, Bagi Hasil Pajak Orang Pribadi, akan tetapi lebih dari
itu akan terjadi efek ganda terhadap pendapatan keluarga karena banyak orang
bekerja yang otomatis akan membesarkan aktivitas perdagangan dan
penyediaan jasa-jasa dalam masyarakat.
16
2) Belanja Subsidi
Dalam rangka pemenuhan kebutuhan dasar dan hajat hidup orang banyak
dilakukan subsidi terhadap produk tertentu agar harga jualnya terjangkau
oleh masyarakat yang daya belinya terbatas.
3) Belanja Hibah
Digunakan untuk menganggarkan pemberian hibah kepada masyarakat
dan organisasi kemasyarakatan yang secara spesifik telah ditetapkan
peruntukannya dan diberikan secara selektif dengan mempertimbangkan
kemampuan keuangan daerah, rasionalitas serta ditetapkan dengan
keputusan kepala daerah.
4) Belanja Tak Terduga
Digunakan untuk mendanai kegiatan yang sifatnya tidak biasa atau tidak
diharapkan terjadi berulang berupa kebutuhan tanggap darurat bencana,
penanggulangan bencana alam dan bencana sosial yang tidak tertampung
dalam bentuk program dan kegiatan pada Tahun Anggaran 2013.
b. Belanja Langsung
Kebijakan dan Prioritas Pembangunan Daerah Tahun 2013, yaitu sebagai
berikut.
1) Mewujudkan pertumbuhan ekonomi daerah minimum sebesar 6,00%
melalui peningkatan aktivitas sembilan sektor ekonomi.
2) Meningkatkan ketahanan pangan daerah melalui peningkatan produksi
gabah.
3) Menurunkan angka persentase kemiskinan penduduk.
4) Meningkatkan kualitas kehidupan sosial dalam masyarakat, melalui
perbaikan mutu pendidikan dan peningkatan derajat kesehatan
masyarakat.
5) Memantapkan jalannya penyelenggaraan pemerintahan tingkat
desa/kelurahan dan kecamatan.
c. Pembiayaan Daerah
1) Kebijakan Penerimaan Pembiayaan
Membuka perkiraan yang dimungkinkan pada sektor penerimaan
pembiayaan yaitu melakukan estimasi SiLPA dengan mempertimbangkan
perkiraan realisasi anggaran tahun lalu.
2) Kebijakan Pengeluaran Pembiayaan
Kebijakan pada sisi Pengeluaran Pembiayaan adalah memenuhi seluruh
komitmen daerah pada pihak ketiga yang telah jatuh tempo serta
penyertaan modal pada Bank SumselBabel.
2.3. Pendekatan Penyusunan Laporan Keuangan
Laporan Keuangan Pemerintah Kabupaten Banyuasin merupakan gabungan
keseluruhan laporan keuangan entitas akuntansi, sehingga tersaji sebagai satu
entitas tunggal. Proses penggabungan antara akun-akun yang diselenggarakan oleh
suatu entitas pelaporan dengan entitas akuntansi lainnya, dengan mengeliminasi
akun-akun timbal balik agar dapat disajikan sebagai satu entitas pelaporan
konsolidasian. Laporan keuangan konsolidasi terdiri dari Laporan Realisasi
Anggaran (LRA), Neraca, Laporan Arus Kas (LAK) dan Catatan atas Laporan
Keuangan (CaLK). Laporan keuangan konsolidasi disajikan untuk periode
17
pelaporan yang sama dengan periode pelaporan keuangan entitas akuntansi dan
disajikan secara komparatif dengan periode sebelumnya.
Tabel 2.3 Anggaran dan Realisasi Belanja Masing-Masing SKPD Tahun 2013
Kode SKPD Anggaran Realisasi Lebih/Kurang %
1 2 3 4 5 6
18
Kode SKPD Anggaran Realisasi Lebih/Kurang %
1 2 3 4 5 6
19
III. KEBIJAKAN AKUNTANSI
Basis akuntansi yang digunakan dalam pelaporan keuangan ini adalah basis kas
menuju akrual (cash towards accrual). Dalam basis kas menuju akrual, pendapatan dan
belanja serta pembiayaan dicatat berdasarkan basis kas, sedangkan aset, utang, dan
ekuitas dana dicatat berdasarkan basis akrual. Kebijakan akuntansi pokok yang
diterapkan dalam penyusunan Laporan Keuangan Pemerintah Kabupaten Banyuasin
Tahun 2013, sebagai berikut.
Pengakuan
Pengakuan pendapatan, adalah sebagai berikut.
1. Pendapatan diakui pada saat diterima di Rekening Kas Umum Daerah.
2. Dengan mempertimbangkan Bendahara Penerimaan adalah pejabat fungsional yang
melaksanakan tugas kebendaharaan dalam rangka pelaksanaan anggaran pada SKPD,
yang secara fungsional bertanggung jawab atas pelaksanaan tugasnya pada PPKD
selaku BUD.
3. Dalam kriteria pengakuan pendapatan, konsep keterukuran dan ketersediaan
digunakan dalam pengertian derajat kepastian bahwa manfaat ekonomi masa depan
yang berkaitan dengan pos pendapatan tersebut akan mengalir ke pemerintah daerah
dalam periode tahun anggaran yang bersangkutan atau segera dapat digunakan untuk
membayar kewajiban pada periode anggaran yang bersangkutan. Konsep ini
diperlukan dalam menghadapi ketidakpastian lingkungan operasional pemerintah
daerah. Pengkajian atas keterukuran dan ketersediaan yang melekat dalam arus
manfaat ekonomi masa depan dilakukan atas dasar bukti yang dapat diperoleh pada
saat penyusunan laporan keuangan pemerintah daerah.
4. Pencatatan dari setiap jenis pendapatan dan masing-masing nilai pendapatannya
dicatat sampai dengan rincian obyek.
5. Pengembalian yang sifatnya normal dan berulang (recurring) atas penerimaan
pendapatan pada periode penerimaan maupun pada periode sebelumnya dibukukan
sebagai pengurang pendapatan.
6. Koreksi dan pengembalian yang sifatnya tidak berulang (non-recurring) atas
penerimaan pendapatan yang terjadi pada periode penerimaan pendapatan dibukukan
sebagai pengurang pendapatan pada periode yang sama.
7. Koreksi dan pengembalian yang sifatnya tidak berulang (non-recurring) atas
penerimaan pendapatan yang terjadi pada periode sebelumnya dibukukan sebagai
pengurang ekuitas dana lancar pada akun SiLPA pada periode ditemukannya koreksi
dan pengembalian tersebut.
8. Dalam hal Badan Layanan Umum Daerah, pendapatan diakui dengan mengacu pada
peraturan perundangan yang mengatur mengenai Badan Layanan Umum Daerah.
9. Akuntansi pendapatan disusun untuk memenuhi kebutuhan pertanggungjawaban
sesuai dengan ketentuan dan untuk keperluan pengendalian bagi manajemen
pemerintah daerah, baik yang dicatat oleh SKPD maupun PPKD.
20
10. Transaksi pendapatan dalam bentuk barang dan jasa harus dilaporkan dalam Neraca
dan Catatan atas Laporan Keuangan. Contoh transaksi berwujud barang dan jasa
adalah hibah dalam wujud barang, dan barang rampasan.
11. Biaya-biaya transaksi pendapatan dalam wujud barang dikapitalisasi ke dalam nilai
perolehan barang yang diperoleh.
Pengukuran
1. Pendapatan diukur dan dicatat berdasarkan azas bruto, yaitu dengan membukukan
penerimaan bruto, dan tidak mencatat jumlah netonya (setelah dikompensasikan
dengan pengeluaran).
2. a. Pengukuran pendapatan menggunakan mata uang Rupiah berdasarkan nilai
sekarang kas yang diterima.
b. Pendapatan dalam mata uang asing diukur dan dicatat pada tanggal transaksi
menggunakan kurs tengah Bank Indonesia.
Pengungkapan
Hal-hal yang harus diungkapkan dalam Catatan atas Laporan Keuangan terkait dengan
pendapatan adalah:
1. Penerimaan pendapatan tahun berkenaan setelah tanggal berakhirnya tahun
anggaran.
2. Penjelasan mengenai pendapatan yang pada tahun pelaporan yang bersangkutan
terjadi hal-hal yang bersifat khusus.
3. Penjelasan sebab-sebab tidak tercapainya target penerimaan pendapatan daerah.
4. Konversi yang dilakukan akibat perbedaan klasifikasi pendapatan berdasarkan
Permendagri Nomor 13 Tahun 2006 dan Permendagri Nomor 59 Tahun 2007
tentang perubahan atas Permendagri Nomor 13 Tahun 2006 tentang Pengelolaan
Keuangan Daerah, dengan PP Nomor 24 Tahun 2005 tentang Standar Akuntansi
Pemerintahan.
5. Informasi lainnya yang dianggap perlu.
Pengakuan
1. Belanja diakui pada saat terjadinya pengeluaran dari Rekening Kas Umum Daerah
untuk seluruh transaksi di SKPD dan PPKD setelah dilakukan pengesahan definitif
oleh BUD untuk masing-masing transaksi yang terjadi di SKPD dan PPKD.
2. Khusus pengeluaran melalui bendahara pengeluaran pengakuannya terjadi pada saat
pertanggungjawaban atas pengeluaran tersebut disahkan oleh pengguna anggaran.
3. Dalam hal badan layanan umum, belanja diakui dengan mengacu pada peraturan
perundangan yang mengatur mengenai badan layanan umum.
4. Realisasi anggaran belanja dilaporkan sesuai dengan klasifikasi yang ditetapkan
dalam dokumen anggaran.
5. Koreksi atas pengeluaran belanja (penerimaan kembali belanja) yang terjadi pada
periode pengeluaran belanja dibukukan sebagai pengurang belanja pada periode
21
yang sama. Apabila diterima pada periode berikutnya, koreksi atas pengeluaran
belanja dibukukan dalam lain-lain PAD yang sah.
6. Akuntansi belanja disusun selain untuk memenuhi kebutuhan pertanggungjawaban
sesuai dengan ketentuan, juga dapat dikembangkan untuk keperluan pengendalian
bagi manajemen dengan cara yang memungkinkan pengukuran kegiatan belanja
tersebut.
7. Suatu pengeluaran belanja akan diperlakukan sebagai belanja modal (nantinya akan
menjadi aset tetap) jika memenuhi seluruh kriteria berikut.
a. Manfaat ekonomi barang yang dibeli lebih dari 12 bulan;
b. Perolehan barang tersebut untuk operasional dan pelayanan, serta tidak untuk
dijual;
c. Nilai rupiah pembelian barang material atau pengeluaran untuk pembelian
barang tersebut melebihi batasan minimal kapitalisasi aset tetap yang telah
ditetapkan;
d. Barang yang dibeli merupakan objek pemeliharaan;
e. Perolehan barang tersebut untuk digunakan dan tidak untuk dijual/dihibahkan
disumbangkan/diserahkan kepada pihak ketiga.
8. Suatu pengeluaran belanja pemeliharaan akan diperlakukan sebagai belanja modal
(dikapitalisasi menjadi aset tetap) jika memenuhi seluruh kriteria berikut.
a. manfaat ekonomi atas barang/aset tetap yang dipelihara;
b. bertambah ekonomis/efisien, dan/atau;
c. bertambah umur ekonomis, dan/atau;
d. bertambah volume, dan/atau;
e. bertambah kapasitas produksi, dan/atau;
f. bertambah estetika/keindahan/kenyamanan;
g. nilai rupiah pengeluaran belanja atas pemeliharaan barang/aset tetap tersebut
material/melebihi batasan minimal kapitalisasi aset tetap yang telah ditetapkan.
9. Belanja hibah adalah pengeluaran anggaran untuk pemberian hibah dalam bentuk
uang, barang dan/atau jasa kepada pemerintah atau pemerintah daerah lainnya,
perusahaan daerah, masyarakat, dan organisasi kemasyarakatan yang secara spesifik
telah ditetapkan peruntukannya.
10. Belanja hibah diberikan secara selektif dengan mempertimbangkan kemampuan
keuangan daerah, rasionalitas dan ditetapkan dengan keputusan kepala daerah.
11. Pemberian hibah dalam bentuk uang atau dalam bentuk barang atau jasa dicatat dan
diakui sebesar nilai yang dikeluarkan dan dapat diberikan kepada pemerintah daerah
tertentu sepanjang ditetapkan dalam peratutan perundang-undangan.
12. Hibah kepada pemerintah daerah bertujuan untuk menunjang peningkatan
penyelenggaraan fungsi pemerintahan di daerah.
13. Hibah kepada pemerintah daerah lainnya bertujuan untuk menunjang peningkatan
penyelenggaraan pemerintah daerah dan layanan dasar umum.
14. Hibah kepada masyarakat dan organisasi kemasyarakatan bertujuan untuk
menunjang peningkatan partisipasi penyelenggaraan pembangunan daerah atau
secara fungsional terkait dengan dukungan penyelenggaraan pemerintah daerah.
15. Belanja bantuan sosial adalah pengeluaran anggaran untuk pemberian bantuan yang
bersifat sosial kemasyarakatan dalam bentuk uang dan/atau barang kepada
kelompok/anggota masyarakat, dan partai politik.
16. Pemberian bantuan sosial dalam bentuk uang atau dalam bentuk barang atau jasa
dicatat dan diakui sebagai belanja bantuan sosial sebesar nilai yang dikeluarkan.
22
17. Bantuan sosial tersebut diberikan secara selektif, tidak terus menerus/tidak mengikat
serta memiliki kejelasan peruntukan penggunaannya dengan mempertimbangkan
kemampuan keuangan daerah dan ditetapkan dengan keputusan kepala daerah.
18. Bantuan sosial yang diberikan secara tidak terus menerus/tidak mengikat diartikan
bahwa pemberian bantuan tersebut tidak wajib dan tidak harus diberikan setiap
tahun anggaran.
19. Khusus kepada partai politik, bantuan diberikan sesuai dengan ketentuan peraturan
perundang-undangan dianggarkan dalam bantuan keuangan.
20. Belanja bagi hasil dicatat dan diakui sebesar nilai yang dikeluarkan. Apabila pada
akhir tahun belum direalisasi, maka akan menjadi utang sebesar nilai yang harus
dibayar.
Kemudian di-reverse pada awal tahun berikutnya, dan pada saat realisasi belanja
bagi hasil, mekanismenya melalui belanja bagi hasil.
21. Bantuan keuangan dalam bentuk uang, barang dan jasa dicatat dan diakui sebagai
belanja bantuan keuangan sebesar nilai yang dikeluarkan.
22. Bantuan keuangan, baik bersifat umum atau khusus dari provinsi kepada
kabupaten/kota, pemerintah desa, dan pemerintah daerah lainnya atau dari
pemerintah kabupaten/kota kepada pemerintah desa, dan pemerintah daerah lainnya
dalam rangka pemerataan dan/atau peningkatan kemampuan keuangan.
23. Belanja tak terduga dicatat dan diakui sebagai belanja tak terduga sebesar nilai yang
dikeluarkan.
24. Kriteria untuk belanja tak terduga ialah belanja untuk kegiatan yang sifatnya tidak
biasa atau tidak diharapkan berulang, termasuk pengembalian atas kelebihan
penerimaan daerah tahun-tahun sebelumnya yang telah ditutup.
Pengukuran
Belanja diukur dan dicatat berdasarkan nilai sekarang kas yang dikeluarkan.
Pengungkapan
Hal-hal yang perlu diungkapkan sehubungan dengan belanja, antara lain:
1. Pengeluaran belanja tahun berkenaan setelah tanggal berakhirnya tahun anggaran.
2. Penjelasan sebab-sebab tidak terserapnya target realisasi belanja daerah.
3. Konversi yang dilakukan akibat perbedaan klasifikasi belanja berdasarkan
Permendagri Nomor 13 Tahun 2006 dan Permendagri Nomor 59 Tahun 2007
tentang perubahan atas Permendagri Nomor 13 Tahun 2006 tentang Pengelolaan
Keuangan Daerah, dengan PP Nomor 24 Tahun 2005 tentang Standar Akuntansi
Pemerintah.
4. Informasi lainnya yang dianggap perlu.
23
Pengakuan
1. Penerimaan pembiayaan diakui pada saat diterima pada Rekening Kas Umum
Daerah kecuali untuk SiLPA.
2. Pengeluaran pembiayaan diakui pada saat dikeluarkan dari Rekening Kas Umum
Daerah.
Pengukuran
1. Akuntansi penerimaan pembiayaan dilaksanakan berdasarkan azas bruto, yaitu
dengan membukukan penerimaan bruto, dan tidak mencatat jumlah nettonya (setelah
dikompensasikan dengan pengeluaran).
2. Akuntansi pengeluaran pembiayaan dilaksanakan berdasarkan azas bruto.
3. Pembiayaan netto adalah selisih antara penerimaan pembiayaan setelah dikurangi
pengeluaran pembiayaan dalam periode tahun anggaran tertentu. Selisih lebih/kurang
antara penerimaan dan pengeluaran pembiayaan selama satu periode pelaporan
dicatat dalam pos Pembiayaan Netto.
4. Sisa lebih/kurang pembiayaan anggaran adalah selisih lebih/kurang antara realisasi
penerimaan dan pengeluaran selama satu periode pelaporan. Selisih lebih/kurang
antara realisasi penerimaan dan pengeluaran selama satu periode pelaporan dicatat
dalam pos SiLPA/SiKPA.
24
e. Pemerintah dapat menarik kembali dana bergulir.
4. Dana Bergulir dalam APBD dianggarkan pada Pengeluaran Pembiayaan, untuk
pengembalian pokok Dana Bergulir dicatat pada Penerimaan Pembiayaan pos
Penerimaan Kembali Pinjaman dan bagi hasil jasa usaha Dana Bergulir dicatat pada
Pendapatan Asli Daerah-Lain-lain Pendapatan Asli Daerah yang Sah.
5. Alokasi anggaran Dana Bergulir berada di BUD tetapi pelaksanaan pengelolaannya
didelegasikan kepada SKPD yang membidangi.
6. Dana Bergulir disajikan dalam Laporan Realisasi Anggaran sebagai Pengeluaran
Pembiayaan sebesar jumlah kas yang dikeluarkan dalam rangka perolehan Dana
Bergulir.
7. Dana Bergulir disajikan di Neraca sebagai Investasi Jangka Panjang-Investasi Non
Permanen-Dana Bergulir. Pada saat perolehan dana bergulir dicatat sebesar harga
perolehan dana bergulir, tetapi secara periodik pemerintah daerah harus melakukan
penyesuaian terhadap Dana Bergulir, sehingga nilai Dana Bergulir yang tercatat di
Neraca menggambarkan nilai bersih yang dapat direalisasikan (Net realizable Value).
Penyesuaian tersebut berdasarkan data yang dilaporkan oleh SKPD yang membidangi
atas pencatatan penatausahaan dana bergulir.
Pengungkapan
Hal-hal yang perlu diungkapkan sehubungan dengan pembiayaan, antara lain:
1. Penerimaan dan pengeluaran pembiayaan tahun berkenaan setelah tanggal
berakhirnya tahun anggaran.
2. Penjelasan landasan hukum berkenaan dengan penerimaan/pemberian pinjaman,
pembentukan/pencairan dana cadangan, penjualan aset daerah yang dipisahkan,
penyertaan modal pemerintah daerah.
3. Konversi yang dilakukan akibat perbedaan klasifikasi pembiayaan berdasarkan
Permendagri Nomor 13 Tahun 2006 dan Permendagri Nomor 59 Tahun 2007 tentang
perubahan atas Permendagri Nomor 13 Tahun 2006 tentang Pengelolaan Keuangan
Daerah, dengan PP Nomor 24 Tahun 2005 tentang Standar Akuntansi Pemerintah.
4. Informasi lainnya yang dianggap perlu.
25
Pengakuan Aset
Aset Tetap
Aset Tetap adalah aset berwujud yang mempunyai masa manfaat lebih dari 12 bulan
untuk digunakan dalam kegiatan pemerintah daerah atau dimanfaatkan oleh masyarakat
umum.
Aset Tetap, terdiri atas:
1. Tanah;
2. Peralatan dan Mesin;
3. Gedung dan Bangunan;
4. Jalan, Jaringan dan Instalasi;
5. Aset Tetap Lainnya;
6. Konstruksi Dalam Pengerjaan;
7. Akumulasi Penyusutan.
Tujuan utama dari perolehan aset tetap adalah untuk digunakan oleh pemerintah
daerah dalam mendukung kegiatan operasionalnya dan bukan dimaksudkan untuk dijual.
Pengakuan aset tetap akan sangat andal bila aset tetap telah diterima atau diserahkan hak
kepemilikannya dan atau pada saat penguasaannya berpindah.
Saat pengakuan aset akan lebih dapat diandalkan apabila terdapat bukti bahwa
telah terjadi perpindahan hak kepemilikan dan/atau penguasaan secara hukum, misalnya
sertifikat tanah dan bukti kepemilikan kendaraan bermotor. Apabila perolehan aset tetap
belum didukung dengan bukti secara hukum dikarenakan masih adanya suatu proses
administrasi yang diharuskan, seperti pembelian tanah yang masih harus diselesaikan
proses jual beli (akta) dan sertifikat kepemilikannya di instansi berwenang, maka aset
tetap tersebut harus diakui pada saat terdapat bukti bahwa penguasaan atas aset tetap
26
tersebut telah berpindah, misalnya telah terjadi pembayaran dan penguasaan atas
sertifikat tanah atas nama pemilik sebelumnya.
27
Untuk keperluan penyusunan neraca awal suatu entitas, biaya perolehan aset
tetap yang digunakan adalah nilai wajar pada saat neraca awal tersebut disusun. Untuk
periode selanjutnya setelah tanggal neraca awal, atas perolehan aset tetap baru, suatu
entitas menggunakan biaya perolehan atau harga wajar bila biaya perolehan tidak ada.
Aset Donasi/Hibah
Aset tetap yang diperoleh dari sumbangan (donasi) harus dicatat sebesar nilai
yang dinyatakan oleh pemberi donasi/hibah atau nilai wajar pada saat perolehan.
Sumbangan aset tetap didefinisikan sebagai transfer tanpa persyaratan suatu aset
tetap ke suatu entitas, misalnya perusahaan nonpemerintah memberikan bangunan yang
dimilikinya untuk digunakan oleh satu unit pemerintah daerah tanpa persyaratan apapun.
Penyerahan aset tetap tersebut akan sangat andal bila didukung dengan bukti perpindahan
kepemilikannya secara hukum, seperti adanya akta hibah. Nilai penerimaan aset donasi
dari pihak ketiga meliputi nilai yang dinyatakan oleh pemberi hibah atau nlai taksir,
ditambah dengan biaya pengurusan.
Tidak termasuk aset donasi, apabila penyerahan aset tetap tersebut dihubungkan
dengan kewajiban entitas lain kepada pemerintah daerah. Sebagai contoh, satu
perusahaan swasta membangun aset tetap untuk pemerintah daerah dengan persyaratan
kewajibannya kepada pemerintah daerah telah dianggap selesai. Perolehan aset tetap
tersebut harus diperlakukan seperti perolehan aset tetap dengan pertukaran.
Apabila perolehan aset tetap memenuhi kriteria perolehan aset donasi, maka
perolehan tersebut dapat diakui sebagai pendapatan pemerintah daerah dan jumlah yang
sama juga diakui sebagai belanja modal dalam laporan realisasi anggaran atau disajikan
di Neraca sesuai dengan aset donasi yang diterima dengan penjelasan pada Catatan atas
Laporan Keuangan.
28
datang dalam bentuk kapasitas, mutu produksi, atau peningkatan standar kinerja, harus
ditambahkan pada nilai tercatat aset yang bersangkutan.
Setelah perolehan, masih terdapat biaya-biaya yang muncul selama penggunaan
aset tetap. Misalnya biaya pemeliharaan (maintenance), penambahan (additions),
penggantian (replacement) atau perbaikan (repairs).
Pada dasarnya, pengeluaran-pengeluaran untuk aset tetap setelah perolehan, dapat
dikategorikan menjadi belanja modal (capital expenditures) dan pengeluaran pendapatan
(revenue expenditures).
Belanja modal adalah pengeluaran-pengeluaran yang harus dicatat sebagai aset
(dikapitalisir). Pengeluaran-pengeluaran yang akan mendatangkan manfaat lebih dari satu
periode akuntansi termasuk dalam kategori ini, misalnya penambahan satu unit AC dalam
sebuah mobil atau penambahan teras pada gedung yang telah dimiliki, merupakan belanja
modal.
Demikian juga halnya dengan pengeluaran-pengeluaran yang akan menambah
efisiensi, memperpanjang umur aset atau meningkatkan kapasitas atau mutu produksi.
Contoh mengenai pengeluaran-pengeluaran yang akan memperpanjang umur aset atau
meningkatkan kapasitas produksi adalah pengeluaran untuk perbaikan besar-besaran.
Kapitalisasi Aset
Kapitalisasi aset tetap ditetapkan dalam kebijakan akuntansi ini berupa suatu
batasan jumlah biaya (capitalization thresholds) tertentu untuk dapat digunakan dalam
penentuan apakah suatu pengeluaran harus dikapitalisasi atau tidak.
Pengeluaran yang dikapitalisasikan dilakukan terhadap pengadaan tanah,
pembelian peralatan dan mesin sampai siap pakai, pembuatan peralatan, mesin dan
bangunan, pembangunan gedung dan bangunan, pembangunan jalan/irigasi/jaringan,
pembelian aset tetap lainnya sampai siap pakai.
Batasan jumlah pengeluaran yang dapat dikapitalisir sebagai aset, adalah sebagai berikut.
1. Pengeluaran untuk per satuan peralatan dan mesin, dan alat olah raga yang sama
dengan atau lebih dari Rp1.000.000,00 (satu juta rupiah).
2. Pengeluaran untuk gedung dan bangunan berupa rehab berat dengan kriteria
menambah manfaat, daya, usia, volume dan pengeluaran untuk pemeliharaan dengan
nilai yang sama dengan atau lebih dari Rp30.000.000,00 (tiga puluh juta rupiah).
3. Untuk aset tanah, jalan/irigasi/jaringan dan BMD lainnya berupa koleksi
perpustakaan dan barang bercorak kesenian dikecualikan dari nilai kapitalisasi point
(a) dan (b).
Pemeliharaan aset tetap yang bersifat rutin dan berkala tidak dikapitalisasi.
Rehabilitasi yang bersifat sedang dan berat dikapitalisasi atau menambah nilai aset tetap
tersebut, apabila memenuhi salah satu kriteria yaitu biaya pemeliharaan tersebut cukup
besar, menambah volume, menambah kapasitas, meningkatkan fungsi, meningkatkan
efisiensi dan/atau menambah masa manfaat.
29
c. akumulasi penyusutan dan perubahan nilai, jika ada;
d. mutasi aset tetap lainnya.
3. Informasi penyusutan (jika ada), meliputi:
a. nilai penyusutan;
b. metode penyusutan yang digunakan;
c. masa manfaat atau tarif penyusutan yang digunakan;
d. nilai tercatat bruto dan akumulasi penyusutan pada awal dan akhir periode.
Laporan keuangan juga harus mengungkapkan:
1. Eksistensi dan batasan hak milik atas aset tetap;
2. Kebijakan akuntansi untuk kapitalisasi yang berkaitan dengan aset tetap;
3. Jumlah pengeluaran pada pos aset tetap dalam konstruksi; dan
4. Jumlah komitmen untuk akuisisi aset tetap.
Jika aset tetap dicatat pada jumlah yang dinilai kembali, hal-hal berikut harus
diungkapkan:
1. Dasar peraturan untuk menilai kembali aset tetap;
2. Tanggal efektif penilaian kembali;
3. Jika ada, nama penilai independen;
4. Hakikat setiap petunjuk yang digunakan untuk menentukan biaya pengganti; dan
5. Nilai tercatat setiap jenis aset tetap.
30
IV. PENJELASAN POS-POS LAPORAN KEUANGAN
4.1 Penjelasan Pos-Pos Laporan Realisasi Anggaran (LRA)
4.1.1 Pendapatan
Jumlah anggaran pendapatan Tahun 2013 adalah sebesar
Rp1.655.951.199.884,44 sebagaimana tertuang dalam Peraturan Daerah Nomor 2
Tahun 2012 tentang Perubahan Anggaran Pendapatan dan Belanja Daerah
Kabupaten Banyuasin Tahun 2013. Pendapatan ini dapat dicapai sebesar
Rp1.663.679.789.250,24 atau 100,47% dari target yang ditetapkan. Komposisi
pencapaian realisasi pendapatan per kelompok pendapatan disajikan pada tabel di
bawah ini:
Tabel 4.1 Realisasi Pendapatan per Kelompok Pendapatan
Kabupaten Banyuasin Tahun Anggaran 2013
Kenaikan
Kelompok Pendapatan Anggaran (Rp) Realisasi (Rp) %
/(Penurunan)
31
4.1.1.1. Pendapatan Asli Daerah
Realisasi Pendapatan Asli Daerah mencapai sebesar Rp81.364.386.883,24
lebih besar Rp27.094.114.650,72 atau 149,92% dari anggaran sebesar
Rp54.270.272.232,52. Pelampauan target Pendapatan Asli Daerah terjadi antara
lain karena optimalisasi implementasi kegiatan intensifikasi dan ekstensifikasi
pajak daerah dan retribusi daerah. Nilai realisasi Pendapatan Asli Daerah
memberikan kontribusi terhadap pendapatan daerah sebesar 4,89%. Berikut
realisasi komponen Pendapatan Asli Daerah Kabupaten Banyuasin Tahun 2013:
Tabel 4.2 Anggaran dan Realisasi PAD Kabupaten Banyuasin Tahun 2013
No. Jenis PAD Anggaran (Rp) Realisasi (Rp) Lebih/(kurang) (Rp) %
Tabel 4.3 Rincian Pendapatan Pajak Daerah Kabupaten Banyuasin Tahun 2013
Lebih/Kurang
No. Jenis Pajak Anggaran (Rp) Realisasi (Rp) %
(Rp)
32
Banyuasin I, yang semula tidak diperhitungkan potensinya dalam
penganggaran Tahun 2013.
2. Anggaran Pajak Restoran sebesar Rp119.841.250,00 dicapai sebesar
Rp1.006.667.018,00 atau 840,00%. Tingginya pencapaian ini dikarenakan
adanya penambahan rumah makan dan restoran di wilayah Kabupaten
Banyuasin, serta adanya penyediaan jasa catering oleh pihak PT
Pertamina, dan juga adanya restoran siap saji CFC di Kecamatan
Rambutan yang masih beroperasi.
3. Anggaran Pajak Hiburan sebesar Rp36.147.500,00 berhasil dicapai
sebesar Rp40.160.000,00 atau 111,10%. Pencapaian ini berasal dari
Karaoke Clp yang terletak di Desa Gasing Kecamatan Talang Kelapa, dan
masih beroperasinya wisata danau yang terletak di Kelurahan Tanah Mas.
4. Pencapaian Pajak Reklame sebesar Rp229.227.187,50 atau 123,54% dari
anggaran sebesar Rp185.552.392,95. Pencapaian ini karena meningkatnya
jumlah reklame yang dipasang di Kabupaten Banyuasin.
5. Pencapaian Pajak Penerangan Jalan sebesar Rp9.498.653.100,00 atau
173,72% dari anggaran sebesar Rp5.467.730.862,40, hal ini seiring
dengan semakin banyaknya masyarakat yang sudah menikmati listrik.
6. Pencapaian realisasi Pajak Air Tanah sebesar Rp19.485.729,00 atau hanya
83,34% dari anggaran sebesar Rp23.381.583,75. Rendahnya pencapaian
ini disebabkan objek pajak air tanah tersebut hanya terdapat di Kecamatan
Talang Kelapa dan masih banyak pihak perorangan yang memiliki usaha
jual beli air yang belum memiliki izin.
7. Pencapaian realisasi Pajak Sarang Burung Walet sebesar Rp8.037.500,00
atau 44,30% dari anggaran sebesar Rp18.145.000,00. Rendahnya
pencapaian ini karena banyak Wajib Pajak Sarang Burung Walet yang
belum mempunyai izin dan sulitnya mengetahui saat panen serta harga
jual sarang burung walet di pasaran mengalami penurunan secara
permanen.
8. Pencapaian realisasi Pajak Mineral Bukan Logam dan Batuan sebesar
Rp469.326.275,00 atau 309,90% dari anggaran sebesar
Rp151.445.250,00. Pencapaian anggaran ini berasal dari lokasi kegiatan
pembangunan di Kabupaten Banyuasin.
9. Anggaran Bea Perolehan Hak atas Tanah dan Bangunan (BPHTB) sebesar
Rp13.011.136.684,00 tercapai sebesar Rp19.256.148.089,00 atau
148,00%. Pencapaian ini disebabkan adanya upaya intensifikasi BPHTB
melalui verifikasi lapangan.
33
Tabel 4.4 Rincian Pendapatan Retribusi Daerah
Pemerintah Kabupaten BanyuasinTahun 2013
Lebih/Kurang
No. Jenis Retribusi Anggaran (Rp) Realisasi (Rp) %
(Rp)
34
Tabel 4.6 Rincian Retribusi Jasa Usaha
Pemerintah Kabupaten Banyuasin Tahun 2013
Lebih/Kurang
No. Jenis Retribusi Jasa Usaha Anggaran (Rp) Realisasi (Rp) %
(Rp)
35
Dari tiga jenis pendapatan Retribusi Perizinan Tertentu di atas, dua jenis
retribusi yaitu Retribusi Izin Mendirikan Bangunan (IMB) dan Izin
Gangguan/Keramaian, realisasinya melampaui anggaran, sedangkan Retribusi
Izin Trayek tidak mencapai anggaran. Retribusi IMB dan Izin
Gangguan/Keramaian realisasinya melampaui anggaran antara lain disebabkan
semakin pesatnya pembangunan dan perkembangan dunia usaha di Kabupaten
Banyuasin.
Retribusi Izin Trayek hanya terealisasi 49,77% atau sebesar Rp4.345.000,00
dari anggaran sebesar Rp8.730.000,00, dikarenakan kendaraan yang sudah
tidak layak jalan tidak lagi melakukan perpanjangan izin trayek sesuai dengan
Peraturan Daerah Nomor 30 Tahun 2009. Selain itu penyebab penurunan
realisasi Retribusi Izin Trayek adalah masih kurangnya kesadaran pemilik
kendaraan untuk membayar perpanjangan izin trayek.
36
1. Hasil penjualan aset yang tidak dipisahkan terealisasi sebesar
Rp204.262.127,00 terdiri dari hasil penjualan kendaraan dinas roda empat
sebesar Rp199.388.127,00 dan hasil penjualan aset daerah yang tidak
dipisahkan lainnya sebesar Rp4.874.000,00. Penjualan aset daerah ini
antara lain adalah hasil penjualan aset yang dihapuskan/rusak berat dari
inspektorat kabupaten, BKD dan Diklat, BPMD, Bappeda dan Penanaman
Modal, Dinas Pengelolaan Pasar, Badan Perpustakaan, Dinas Koperasi,
Dinas Sosial, Dinas PU CK, Dinas Kehutanan dan Perkebunan, Dinas PU
Pengairan, DPPKAD, Dinas Kesehatan dan Dinas Pertambangan.
2. Pendapatan Jasa Giro sebesar Rp3.366.263.132,00 merupakan jasa giro
dari Rekening Kas Umum Daerah.
3. Pendapatan Bunga Deposito dapat dilihat pada tabel di bawah ini:
Jumlah 11.251.867.023,97
Jumlah 344.128.953,60
37
- Atas nama Hy Rp550.000,00
- Atas nama EAm Rp1.520.000,00
- Atas nama AA, S.Pd Rp1.250.000,00
5. Pendapatan Denda Keterlambatan pelaksanaan pekerjaan terealisasi
sebesar Rp3.432.000,00 merupakan denda keterlambatan atas pekerjaan
dengan SPK Nomor 027/23/PPK/BLH/2013 tanggal 13 September 2013
untuk pekerjaan pembangunan instalasi pengelolaan air limbah (IPAL)
Puskesmas Daya utama Kecamatan Muara Padang Kabupaten Banyuasin.
6. Pendapatan Hasil Eksekusi Jaminan terealisasi sebesar Rp17.582.400,00
merupakan uang jaminan penawaran dari pihak ketiga/rekanan yang
mengundurkan diri.
7. Pendapatan dari Pengembalian terealisasi sebesar Rp1.184.743.642,21,
terdiri dari pengembalian gaji dan tunjangan sebesar Rp899.803.073,00.
Termasuk di dalamnya adalah pengembalian dari PT Taspen sebesar
Rp774.831.758,00 yang merupakan penerimaan atas pengembalian
kelebihan pembayaran gaji dan tunjangan lainnya yang dipotong
langsung dari pembayaran pensiun pegawai.
Pendapatan dari pengembalian kelebihan pembayaran perjalanan dinas
sebesar Rp2.915.000,00 dan pendapatan pengembalian kelebihan bayar
dan tindak lanjut hasil pemeriksaan dan pengembaliannya sebesar
Rp282.025.569,21.
8. RJTP Askes terealisasi sebesar Rp18.106.000,00 dari anggaran sebesar
Rp9.643.000,00.
9. Penerimaan Lain-lain terealisasi sebesar Rp835.649.173,04 dari anggaran
sebesar Rp1.000.121.669,42 terdiri dari pendapatan dari Lelang Lebak
Lebung dan Penerimaan Lainnya. Adapun rincian dari penerimaan lain-
lain yang merupakan bagian dari Lain-Lain PAD yang Sah dapat dilihat
pada tabel berikut.
Tabel 4.12 Rincian Realisasi Pendapatan Lelang Lebak Lebung Tahun 2013
No. Lokasi Realisasi (Rp)
38
No. Lokasi Realisasi (Rp)
Jumlah 685.653.000,00
39
Bagi Hasil dari Pertambangan Minyak
57.922.386.000,00 64.584.492.446,00 6.662.106.446,00 111,50
Bumi
Bagi Hasil dari Pertambangan Gas Bumi 100.632.558.009,47 114.029.543.863,00 13.396.985.853,53 113,31
Bagi Hasil dari Pertambangan Panas Bumi 15.075.565,00 18.471.620,00 3.396.055,00 122,53
Bagi Hasil dari Cukai Hasil Tembakau 101.786.103,45 44.528.074,00 (57.258.029,45) 43,75
Bagi Hasil dari Pajak Kendaraan Bermotor 5.484.801.500,00 1.436.064.600,00 (4.048.736.900,00) 26,18
Bagi Hasil dari Pajak Kendaraan di Atas Air 2.597.600,00 0,00 (2.597.600,00) 0,00
Bagi Hasil dari Bea Balik Nama Kendaraan
8.480.866.100,00 2.072.192.100,00 (6.408.674.000,00) 24,43
Bermotor
Bagi Hasil dari Bea Balik Nama Kendaraan
329.800,00 0,00 (329.800,00) 0,00
di Atas Air
Bagi Hasil dari Pajak Bahan Bakar
14.616.953.000,00 3.060.144.900,00 (11.556.808.100,00) 20,94
Kendaraan Bermotor
40
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
Pendapatan Transfer Pemerintah Provinsi ini berasal dari dana bagi hasil pajak
provinsi bagian Kabupaten Banyuasin dari bulan Januari sampai dengan bulan
Februari Tahun 2013 sedangkan untuk bulan Maret sampai dengan Desember
2013 belum diterima dari Provinsi Sumatera Selatan sebesar
Rp29.193.935.680,53.
4.1.1 Belanja
Dalam Tahun 2013, realisasi belanja daerah untuk membiayai penyelenggaraan
pemerintahan dan pelaksanaan pembangunan serta pelayanan masyarakat sebesar
Rp1.668.900.629.860,63 atau terdapat sisa anggaran sebesar
Rp157.343.685.228,18 yaitu 91,38% dari anggaran sebesar
Rp1.826.244.315.088,81, terdiri atas:
41
Tabel 4.17 Rincian Belanja Daerah Pemerintah Kabupaten Banyuasin Tahun 2013
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
Berdasarkan tabel di atas, semua belanja terserap di bawah anggaran. Kondisi ini
menghasilkan sisa anggaran Pemerintah Kabupaten Banyuasin sebesar
Rp157.343.685.228,18 atau efisiensi 8,62%, karena adanya penghematan
pemakaian dana dari berbagai kegiatan.
42
Tabel 4.18 Rincian Belanja Pegawai Pemerintah Kabupaten Banyuasin Tahun 2013
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
43
Realisasi Belanja Barang sebesar Rp377.872.151.087,63 termasuk realisasi
belanja yang tidak melalui mekanisme penerimaan dan belanja dari kas daerah
yaitu premi asuransi kesehatan berupa realisasi belanja BOK pada Dinas
Kesehatan sebesar Rp2.446.373.000,00 dan realisasi belanja BOS pada Dinas
Pendidikan sebesar Rp73.995.510.000,00. Khusus belanja premi asuransi
terjadi pelampauan terhadap anggarannya sebesar Rp143.203.242,63
disebabkan adanya klaim yang terjadi setelah terbit APBD Perubahan Tahun
2013 seiring dengan penerimaan pendapatan premi tersebut.
44
Kecamatan Banyuasin III 237.500.000,00 237.500.000,00 0,00 100,00
Kecamatan Betung 95.000.000,00 95.000.000,00 0,00 100,00
Kecamatan Talang Kelapa 285.000.000,00 285.000.000,00 0,00 100,00
Kecamatan Makarti Jaya 47.500.000,00 47.500.000,00 0,00 100,00
BPMPD 13.495.000.000,00 13.394.500.000,00 (100.500.000,00) 99,26
Dinas Pertanian dan Peternakan 12.304.980.000,00 9.694.622.850,00 (2.610.357.150,00) 78,79
Dinas Kehutanan dan Perkebunan 3.079.033.000,00 2.982.188.000,00 (96.845.000,00) 96,85
Dinas Pariwisata, Seni Budaya, Pemuda dan
2.086.750.000,00 2.002.426.126,00 (84.323.874,00) 95,96
Olahraga
Dinas Perikanan dan Kelautan 110.000.000,00 108.526.000,00 (1.474.000,00) 98,66
Belanja Hibah tersebut di atas termasuk hibah kepada pemerintah desa berupa
uang sebesar Rp665.100.00 yang seharusnya dikelompokkan dalam Belanja
Bantuan Keuangan.
Rincian Belanja Bantuan Sosial yang dikelola oleh PPKD pada Lampiran 2,
sedangkan Belanja Bantuan Sosial yang disalurkan oleh SKPD yaitu Dinas
Sosial dari anggaran sebesar Rp1.977.251.150,00 terealisasi sebesar
Rp1.968.834.000,00, sebagai berikut.
45
Tabel 4.23 Belanja Bantuan Sosial yang dikelola oleh SKPD Tahun 2013
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang
46
Legislatif Tahun 2009 dikalikan dengan nilai bantuan persuara yaitu
Rp3.041,00 per suara, yang dikelola berdasarkan Peraturan Bupati Nomor 148
Tahun 2011 tentang Pedoman Tata Cara Perhitungan, Pengajuan, Penyaluran
dan Laporan Pertanggungjawaban Penggunaan Bantuan Keuangan Partai
Politik di Kabupaten Banyuasin, dengan rincian sebagai berikut.
Jumlah 846.967.525,00
Gambar 4.3
Perbandingan Realisasi Belanja Modal Tahun Anggaran 2013
47
Dari total realisasi Belanja Modal Tahun 2013 sebesar Rp561.753.662.659,00
tidak seluruhnya diakui sebagai penambah aset tetap Tahun 2013. Berdasarkan
Standar Akuntansi Pemerintahan (SAP) dan kebijakan akuntansi sebagaimana
tertuang dalam Peraturan Bupati Banyuasin Nomor 911 Tahun 2012 tentang
Kebijakan Akuntansi Pemerintah Kabupaten Banyuasin. Belanja Modal harus
dikecualikan dari aset tetap jika diperuntukkan sebagai hibah ke masyarakat dan
atau secara nilai tidak dapat dikapitalisasi.
Rincian mutasi belanja modal yang dihibahkan/pakai habis dan yang tidak dapat
dikapitalisir karena kebijakan akuntansi (asset extracomptable) dan reklasifikasi
antar akun belanja, adalah sebagai berikut.
48
Perhubungan dan belanja modal Aset Tetap Lainnya sebesar
Rp194.600.000,00 pada Dinas Pendidikan.
Mutasi kurang belanja modal Peralatan dan Mesin sebesar
Rp6.816.049.500,00 merupakan reklasifikasi ke:
- Belanja modal gedung dan bangunan sebesar Rp1.076.285.500,00
pada SKPD Dinas Pendidikan, Sekretariat DPRD, Dinas
Kependudukan dan Catatan Sipil, Badan Pelayanan Terpadu dan
Badan Kepegawaian Daerah, Dinas Perhubungan dan Kominfo,
Perpustakaan, Badan Perpustakaan dan Arsip Daerah;
- Belanja modal Jalan, Irigasi, dan Jaringan sebesar
Rp2.168.750.000,00 pada SKPD Dinas Perhubungan dan Kominfo;
- Belanja modal aset tetap lainnya sebesar Rp3.571.014.000,00.
3. Belanja Modal Gedung dan Bangunan sebesar Rp103.380.603.400,00 yang
menjadi aset sebesar Rp92.166.310.873,65. Hal ini disebabkan:
Belanja modal Gedung dan Bangunan sebesar Rp11.104.644.162,35 tidak
menjadi aset karena merupakan belanja:
- Hibah ke sekolah swasta sebesar Rp10.894.622.162,35 pada SKPD
Dinas Pendidikan;
- Hibah ke kelompok tani berupa bibit tanaman sebesar
Rp90.750.000,00 pada SKPD Dinas Kehutanan dan Perkebunan;
- Belanja Modal yang asetnya dikategorikan extracomptable sebesar
Rp103.272.000,00 pada SKPD Sekretariat DPRD.
- Belanja pemeliharaan gedung sebesar Rp16.000.000,00 pada SKPD
Badan Kepegawaian dan Diklat Daerah.
Mutasi tambah belanja modal Gedung dan Bangunan sebesar
Rp1.076.285.500,00 merupakan reklasifikasi dari belanja modal
Peralatan dan Mesin sebagaimana dimaksud pada angka 2 tersebut di
atas.
Mutasi kurang Belanja modal Gedung dan Bangunan sebesar
Rp1.185.933.864,00 merupakan reklasifikasi pada SKPD Dinas
Perikanan dan Kelautan Kabupaten Banyuasin, yaitu reklasifikasi ke
belanja modal Jalan, Irigasi, dan Jaringan sebesar Rp843.123.864,00 dan
sebesar Rp342.810.000,00 merupakan KDP.
4. Belanja Modal Jalan, Irigasi, dan Jaringan sebesar Rp319.532.260.175,00
yang diakui sebagai aset tetap adalah Rp322.345.034.039,00. Hal ini
disebabkan karena adanya mutasi tambah sebesar Rp3.011.873.864,00 yang
merupakan reklasifikasi dari belanja Peralatan dan Mesin sebesar
Rp2.168.750.000,00 sebagaimana dimaksud pada angka 2 tersebut di atas dan
sebesar Rp843.123.864,00 sebagaimana dimaksud pada angka 3, serta mutasi
kurang sebesar Rp199.100.000,00 yang merupakan reklasifikasi ke Belanja
Modal Peralatan dan Mesin pada Dinas Perhubungan dan Kominfo.
5. Belanja Modal Aset Tetap Lainnya sebesar Rp25.746.763.636,00 yang
menjadi aset sebesar Rp28.828.527.636,00. Terdapat belanja modal sebesar
Rp342.650.000,00 tidak menjadi aset tetap lainnya karena merupakan Barang
Habis pakai (Belanja Plakat pada Sekretariat Daerah sebesar
Rp146.150.000,00 dan belanja buku tabloid pada Sekretariat DPRD sebesar
Rp196.500.000,00). Mutasi tambah sebesar Rp3.619.014.000,00 merupakan
reklasifikasi dari belanja modal tanah sebesar Rp48.000.000,00 dan dari
49
belanja peralatan dan mesin sebesar Rp3.571.014.000,00 pada Dinas
Pendidikan. Mutasi kurang sebesar Rp194.600.000,00 merupakan reklasifikasi
ke peralatan dan mesin pada Dinas Pendidikan. Rincian Belanja Modal yang
diakui sebagai aset per SKPD disajikan dalam Lampiran 3.
50
4.1.2.2.2 Belanja Modal Peralatan dan Mesin
Realisasi belanja modal Peralatan dan Mesin mencapai sebesar
Rp106.884.769.126,00 atau 94,35% dari anggaran sebesar
Rp113.281.823.835,00. Belanja Peralatan dan Mesin, terdiri atas:
Tabel 4.28 Rincian Belanja Modal Peralatan dan Mesin Tahun 2013
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
51
Tabel 4.29 Rincian Belanja Modal Gedung dan Bangunan Tahun 2013
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
52
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
Tabel 4.30 Rincian Belanja Modal Jalan Irigasi dan Jaringan Tahun 2013
Uraian Anggaran (Rp) Realisasi (Rp) Lebih/Kurang %
53
Tabel 4.32 Rincian Belanja Tak Terduga Tahun 2013
Uraian Jumlah
Belanja Tak terduga guna klaim dana RS untuk korban kecelakaan speed boat
10.213.322,00
pada bulan April 2013 sesuai SK Bupati No. 957/KPTS/KES/2013
Belanja Tak Terduga untuk korban kebakaran di Wilayah Kabupaten Banyuasin
15.000.000,00
sesuai SK Bupati No. 956/KPTS/DINSOS/2013
Jumlah 25.213.322,00
4.1.3. Pembiayaan
Pembiayaan (financing) adalah seluruh transaksi keuangan pemerintah, baik
penerimaan maupun pengeluaran, yang perlu dibayar atau akan diterima kembali,
yang dalam penganggaran pemerintah terutama dimaksudkan untuk menutup
defisit dan atau memanfaatkan surplus anggaran, yang terdiri atas:
1. Penerimaan Pembiayaan Daerah;
2. Pengeluaran Pembiayaan Daerah.
54
4.1.4. Sisa Lebih Pembiayaan Anggaran
Realisasi Sisa Lebih Pembiayaan Anggaran (SiLPA) dalam Tahun Anggaran
2013 sebesar Rp185.414.415.358,54 merupakan selisih lebih antara surplus dan
defisit dengan pembiayaan netto. SiLPA ini terdiri atas:
Jumlah 185.414.415.358,54
55
4.2 Penjelasan Pos-pos Neraca
Penjelasan pos-pos neraca ini menguraikan secara singkat mengenai posisi saldo
rekening neraca yang disajikan dengan rincian secara detail dalam daftar lampiran
yang merupakan bagian tidak terpisahkan dari Laporan Keuangan ini. Dalam
penjelasan pos-pos neraca ini diuraikan mengenai posisi neraca untuk tahun yang
berakhir pada tanggal 31 Desember 2013 dan 2012, dengan rincian sebagai berikut.
4.2.1. Aset
Penjelasan Aset di Neraca diuraikan dengan rincian sebagai berikut.
Berdasarkan rincian pada tabel 4.35 di atas secara umum terjadi kenaikan aset
yang dimiliki oleh Pemerintah Kabupaten Banyuasin pada Tahun 2013
dibandingkan dengan Tahun 2012 sebesar Rp588.617.760.838,68 atau 20,42%.
Penyebab terjadinya kenaikan dan penurunan aset dijelaskan pada masing-masing
pos. Berikut adalah komposisi aset Kabupaten Banyuasin.
56
Tabel 4.36 Rincian Aset Lancar Pemerintah Kabupaten Banyuasin
Kenaikan/Penurunan
Uraian 2013 (Rp) 2012 (Rp) %
(Rp)
Jumlah Kas dan Setara Kas adalah sebesar Rp185.813.295.982,14 dengan rincian
sebagai berikut.
Tabel 4.37 Rincian jumlah Kas dan Setara Kas
Kenaikan/Penurunan
Uraian 2013 (Rp) 2012 (Rp) %
(Rp)
Selain lima rekening kas daerah diatas, Pemerintah Kabupaten Banyuasin juga
memiliki rekening yang digunakan dalam transaksi penerimaan dan
pengeluaran yang setiap akhir hari akan di-overbooking (dipindahbukukan) ke
rekening kas daerah 167300xxxx (Rekening Dana Rutin), sehingga bersaldo
nol. Rincian terdapat pada Lampiran 4.
57
4.2.1.1.2 Kas di Bendahara Penerimaan
Kas di Bendahara Penerimaan sebesar Rp90.221.300,00 merupakan saldo kas
yang ada di bendahara penerimaan SKPD yaitu pada RSUD Kabupaten
Banyuasin.
58
Jasa Giro UYHD 2012 Jasa Giro
SKPD UYHD 2013 (Rp)
2013 (Rp) (Rp) 2012 (Rp)
59
Tabel 4.40 Rincian Piutang Dana Perimbangan
Uraian 2012 (Rp) Tambah (Rp) Kurang (Rp 2013 (Rp)
Jumlah pembayaran atas piutang anggota dewan yang diterima pada Tahun
2014 sebesar Rp543.301.110,00 diperoleh berkat kerjasama berdasarkan nota
kesepahaman kerjasama antara Pemerintah Kabupaten Banyuasin dengan
Kejaksaan Negeri Pangkalan Balai tentang Penanganan masalah hukum
bidang perdata dan tata usaha negara nomor 164/VIII/11/2013 dan nomor
01/N.6.19.6/Gs.1/11/2013. Rincian lebih lanjut disajikan dalam Lampiran 7.
60
4.2.1.1.10 Piutang PFK (Perhitungan Fihak Ketiga)
Piutang PFK merupakan saldo per 31 Desember 2013 sebesar
Rp35.469.630,00, terdiri atas:
Tabel 4.42 Rincian Piutang PFK
Uraian 2013 2012 Kenaikan
Kelebihan PFK berupa IWP, Taperum, Askes dan PPh Pasal 21 terjadi karena
adanya pengembalian pembayaran gaji pegawai pada beberapa SKPD.
Terhadap kelebihan pembayaran tersebut akan diperhitungkan pada saat
rekonsiliasi antara Pemerintah Kabupaten Banyuasin dengan PT Taspen,
Bapertarum, dan PT Askes.
4.2.1.1.12 Persediaan
Persediaan adalah aset lancar dalam bentuk barang atau perlengkapan yang
dimaksudkan untuk mendukung kegiatan operasional pemerintahan, dan
barang-barang yang dimaksudkan untuk dijual dan/atau diserahkan dalam
rangka pelayanan kepada masyarakat, meliputi persediaan Alat Tulis Kantor,
barang cetakan, alat kebersihan, obat-obatan, Barang Habis Pakai (BHP) alat
kesehatan, bahan kimia/bibit, sebesar Rp9.929.754.640,77, dengan rincian
sebagai berikut.
Tabel 4.44 Rincian Persediaan per Jenis Persediaan
Jenis Persediaan 2013 (Rp) 2012 (Rp)
61
Jenis Persediaan 2013 (Rp) 2012 (Rp)
Rincian lebih lanjut saldo persediaan per 31 Desember 2013 pada masing-
masing SKPD pada Lampiran 9.
62
Tahun 2012 sebesar Rp36.780.410,76 sesuai dengan Laporan Keuangan
PDAM Tirta Betuah (Unaudited) Tahun 2013.
Tabel 4.46 Perhitungan Alokasi Kerugian atas Penyertaan pada PDAM Tirta Betuah
Kerugian yang
Uraian Tahun Neraca PDAM % ditanggung
Pemkab
Jumlah 2.363.243.929,94
4.2.1.3.1. Tanah
Saldo Tanah Tahun 2013 sebesar Rp147.511.496.882,78, dirinci sebagai
berikut.
Tabel 4.48 Rincian Mutasi Aset Tanah
Uraian Saldo 2013 (Rp) Saldo 2012 (Rp)
Saldo Awal 141.350.230.556,78 138.615.659.420,12
Muitasi Tambah 6.209.266.326,00 8.207.086.921,66
-Belanja Modal Tahun 2013 6.209.266.322,00 7.016.917.912,83
-Kapitalisasi - 10.500.000,83
-Hutang pembebasan tanah - -
-Penilaian tanah bernilai Rp0,00 - 1.179.669.008,00
-Hibah 1,00 -
-Koreksi Saldo Awal 3,00 -
Mutasi Kurang (48.000.000,00) (5.472.515.785,00)
-Belanja Modal dihibahkan/pakai habis/kebijakan akuntansi - (1.027.345.785,00)
-Tanah ex Dekonsentrasi/Tugas Pembantuan - (4.010.550.000,00)
-Reklasifikasi aset ke JIJ - (63.470.000,00)
-Reklasifikasi aset ke Aset Tetap Lainnya (48.000.000,00) -
-Hibah ke KPU dan Pengadilan Tinggi - (371.150.000,00)
Jumlah 147.511.496.882,78 141.350.230.556,78
63
Rincian lebih lanjut dijelaskan pada Lampiran 10.
Nilai aset tanah di atas terdiri dari 1.095 persil, sebanyak 1.053 persil belum
disertifikasi atas nama Pemerintah Kabupaten. Pencatatan aset tanah di atas
belum termasuk aset tanah Hutan Larangan/ ex Marga milik Pemerintah
Kabupaten Banyuasin seluas 751.533 m2. Dokumen pendukung atas
kepemilikan tanah Hutan Larangan/ ex Marga berupa Surat Keterangan Lurah
Kedondong Raye Nomor 593/26/KR/2008 tanggal 28 April 2008.
Selain nilai aset tanah tersebut di atas terdapat harga perolehan tanah atas jalan
sebesar Rp43.381.777.810,00 yang diperoleh dari penilaian link jalan di
Kecamatan Talang Kelapa dan Kecamatan Rambutan oleh tim yang dibentuk
Bupati Banyuasin berdasarkan Peraturan Menteri Dalam Negeri Nomor 17
Tahun 2007 tentang Pedoman Teknis Pengelolaan Barang Milik Daerah pasal
51 dan pasal 52 dan dituangkan dalam Keputusan Bupati Banyuasin Nomor
1051/KPTS/DPPKAD/2013 tentang Penilaian berupa Aset Tetap Link Jalan di
Lingkungan Pemerintah Kabupaten Banyuasin.
64
Uraian Saldo 2013 (Rp) Saldo 2012 (Rp)
-Kurang penghapusan Tahun 2011 - (8.139.000,00)
-Kelebihan reklas barang dan jasa 2011 - (90.110.500,00)
-Kurang catat Hibah Tahun 2011 - (210.000.000,00)
-Kelebihan catat Tahun 2011 - (23.000.000,00)
-Koreksi LK 2012 (2.404.205.305,00) -
-Extracomptable (8.910.039.909,98) -
Jumlah 347.370.402.669,06 262.012.524.140,20
65
4.2.1.3.4. Jalan, Irigasi dan Jaringan
Saldo aset tetap Jalan, Irigasi dan Jaringan Tahun 2013 sebesar
Rp1.693.958.575.500,75, dirinci sebagai berikut.
66
Tabel 4.52 Rincian Mutasi Aset Tetap Lainnya
Uraian Saldo 2013 (Rp) Saldo 2012 (Rp)
Saldo Awal 18.338.112.536,50 18.141.562.536,50
Muitasi Tambah 42.588.968.786,00 10.278.086.470,00
-Belanja Modal Tahun 2013 25.746.763.636,00 10.075.558.420,00
-Reklasifikasi dari Barang 60.000.000,00 170.169.000,00
-Reklasifikasi dari Peralatan dan Mesin 3.571.014.000,00 27.600.000,00
-Reklasifikasi dari tanah 48.000.000,00 -
-Hutang 13.163.191.150,00 4.759.050,00
Mutasi Kurang (11.636.341.436,43) (10.081.536.470,00)
-Belanja Modal dihibahkan/pakai habis/kebijakan akuntansi (342.650.000,00) (483.478.200,00)
-Ex Bangunan dari Dekonsentrasi dan Tugas Pembantuan (585.000.000,00)
-Reklasifikasi ke aset peralatan dan mesin (194.600.000,00) -
-Reklasifikasi ke aset JIJ (2.111.830.050,00)
-Pemeliharaan/Barang Jasa (2.753.148.591,00) -
-Koreksi LK 2012 (245.475.000,00) -
-Hibah (8.100.467.845,43) -
-Reklasifikasi ke aset lainnya (6.856.728.220,00)
-Reklasifikasi ke persediaan (44.500.000,00)
Jumlah 49.290.739.886,07 18.338.112.536,50
Koreksi tambah Tahun 2013 merupakan belanja modal Gedung dan Bangunan
serta Jalan, Irigasi, dan Jaringan atas pembangunan balai benih ikan pada
Dinas Perikanan dan Kelautan yang belum selesai dan belum bisa digunakan
sampai dengan 31 Desember 2013. Koreksi kurang merupakan reklasifikasi
Ke JIJ pada SKPD Dinas PU Bina Marga.
Selain Aset Tetap yang tercatat dalam Laporan Keuangan Pemerintah
Kabupaten Banyuasin terdapat aset yang dananya berasal dari Anggaran
Pendapatan dan Belanja Negara (APBN) yaitu aset dari dana Dekonsentrasi,
67
Tugas Pembantuan, dan Urusan Bersama sebesar Rp105.260.174.613,00 atau
terdapat penambahan sebesar Rp32.422.444.177,00 dibandingkan tahun
sebelumnya. Informasi tersebut disajikan pada Lampiran 15. Aset tersebut
tidak dimasukan dalam Laporan Keuangan Pemerintah Kabupaten Banyuasin
Tahun Anggaran 2013 karena belum ada penyerahan dari instansi vertikal
terkait.
68
No. Uraian 2013 (Rp) 2012 (Rp)
69
Tabel 4.57 Rincian Detail Engeneering Design (DED) Dinas PU Bina Marga
Tahun Uraian 2013 (Rp) 2012 (Rp)
Tabel 4.58 Rincian Detail Engeneering Design (DED) Dinas PU Cipta Karya
Tahun Uraian 2013 (Rp) 2012 (Rp)
70
c) Dinas PU Pengairan sebesar Rp5.427.502.500,00, dengan rincian
sebagai berikut.
71
Tahun Uraian 2013 (Rp) 2012 (Rp)
72
g) Dinas Pariwisata Seni, Budaya, Pemuda dan Olahraga sebesar
Rp1.111.880.000,00, dengan rincian sebagai berikut.
73
j) Badan Lingkungan Hidup Rp48.400.000,00, dengan rincian sebagai
berikut.
Tabel.4.66 Rincian Detail Engeneering Design (DED)
Badan Lingkungan Hidup
Tahun Uraian 2013 (Rp) 2012 (Rp)
4) Barang Rusak/Penghapusan
Jumlah barang rusak berat yang belum dihapuskan sebesar
Rp6.261.891.898,00 merupakan aset rusak berat pada beberapa SKPD,
dengan rincian sebagai berikut.
74
Uraian 2013 (Rp) 2012 (Rp)
Sekretariat Daerah
Saldo awal 124.270.000,00
Mutasi tambah 0,00
Mutasi kurang 0,00
Saldo akhir 124.270.000,00 124.270.000,00
Dinas Pendidikan
Saldo awal 119.927.300,00
Mutasi tambah 0,00
Mutasi kurang 0,00
Saldo akhir 119.927.300,00 119.927.300,00
75
lanjut dari peraturan daerah sampai 31 Desember 2013 masih dalam
proses.
4.2.2. Kewajiban
Pos kewajiban per 31 Desember 2013 merupakan Kewajiban Jangka Pendek.
76
Koreksi penghapusan hutang pihak ketiga sebesar Rp67.698.606,00
merupakan koreksi atas hutang yang sudah potong dengan denda pada SKPD
Dinas PU Cipta Karya dan Dinas PU Bina Marga. Sedangkan sisanya sebesar
Rp502,00 merupakan selisih pencatatan pada SKPD Sekretariat Daerah dan
Sekretariat DPRD.
Mutasi kurang atas utang Jaminan Sosial Kesehatan sebesar
Rp1.109.640.323,63 merupakan pembayaran hutang yang dilakukan dengan
mekanisme pembayaran melalui kegiatan pelayanan kesehatan penduduk
miskin di puskesmas dan jaringanya sesuai dengan SP2D Nomor
5825/TU/1.20.01.16.01/5.2/2013 tanggal 29 November 2013 berupa belanja
premi asuransi kesehatan.
Rincian lebih lanjut Utang pihak ketiga disajikan pada Lampiran 18.
Jumlah 185.414.415.358,54
77
4.2.3.1.2 Pendapatan yang Ditangguhkan
Saldo Pendapatan yang Ditangguhkan per 31 Desember 2013 sebesar
Rp434.350.253,60 merupakan saldo kas di Bendahara Penerimaan sebesar
Rp90.221.300,00 dan bunga deposito yang ditangguhkan pada Bank Mandiri
Rp160.273.972,60 dan pada Bank BNI sebesar Rp183.854.981,00.
4.2.3.1.5 Dana yang Harus Disediakan untuk Pembayaran Utang Jangka Pendek
Saldo Dana yang Harus Disediakan untuk Pembayaran Utang Jangka Pendek
sebesar Rp33.367.855.196,05 merupakan contra account dari saldo Utang
Jangka Pendek yaitu utang kepada Pemerintah Provinsi sebesar
Rp2.175.865.863,35 dan Utang Pihak Ketiga sebesar Rp31.191.989.332,70.
78
4.2.3.2.3. Diinvestasikan Dalam Aset Lainnya
Saldo Diinvestasikan Dalam Aset Lainnya per 31 Desember 2013 sebesar
Rp39.341.847.564,00 merupakan contra account dari nilai Aset Lainnya yang
dimiliki oleh Pemerintah Kabupaten Banyuasin.
79
4.3 Penjelasan Pos-Pos Laporan Arus Kas (LAK)
Laporan arus kas menyajikan informasi penerimaan dan pengeluaran kas selama
periode Tahun 2013 yang diklasifikasikan berdasarkan aktivitas operasi, investasi
aset non keuangan, pembiayaan, dan non anggaran.
80
Uraian Tahun 2013 Tahun 2012
Arus Kas Bersih dari Aktivitas Investasi Non Keuangan (561.549.400.532,00) (337.732.983.299,33)
81
Saldo Arus kas bersih aktivitas pembiayaan per 31 Desember 2013 sebesar
(Rp1.808.732.066,50). Arus kas dari aktivitas pembiayaan, sebagai berikut.
Tabel 4.76 Arus Kas dari Aktivitas Pembiayaan
Uraian Tahun 2013 Tahun 2012
82
Tabel 4.78 Rincian Saldo Akhir Arus Kas
Uraian Tahun 2013 Tahun 2012
83
Palembang sebagai pusat kegiatan industri, perdagangan, dan pusat kehidupan
modern.
Kabupaten Banyuasin dibentuk berdasarkan Undang-undang Nomor 6
Tahun 2002 tentang Pembentukan Pemerintah Kabupaten Banyuasin di Provinsi
Sumatera Selatan. Luas wilayah Kabupaten Banyuasin sekitar 11.832,99 km2
atau sekitar 12,18% luas Provinsi Sumatera Selatan, dan terletak antara 1,3 0-40
lintang selatan dan 1040 40’- 1050 15’ bujur timur.
Sedangkan secara administratif, Kabupaten Banyuasin mempunyai batas-
batas wilayah, sebagai berikut.
a. Sebelah Utara : Berbatasan dengan Kabupaten Tanjung Jabung
Timur Provinsi Jambi dan Selat Bangka.
b. Sebelah Timur : Berbatasan dengan Kecamatan Pampangan dan Air
Sugihan Kabupaten Ogan Komering Ilir.
c. Sebelah Selatan : Berbatasan dengan Kecamatan Jejawi Kabupaten
Ogan Komering Ilir, Kota Palembang, Kecamatan
Sungai Rotan, dan Kecamatan Talang Ubi
Kabupaten Muara Enim.
d. Sebelah Barat : Berbatasan dengan Kecamatan Sungai Lilin, Sungai
Lais, dan Bayung Lencir Kabupaten Musi
Banyuasin.
5.2.2. Ketentuan Perundang-undangan yang Menjadi Landasan Kegiatan
Operasional
a. Undang-Undang Nomor 6 Tahun 2002 tentang Pembentukan Kabupaten
Banyuasin di Provinsi Sumatera Selatan (Lembaran Negara Nomor 19
Tahun 2002, Tambahan Lembaran Negara Nomor 4181);
b. Peraturan Daerah Nomor 27 Tahun 2012 tentang Anggaran Pendapatan dan
Belanja Daerah Kabupaten Banyuasin Tahun 2013;
c. Peraturan Daerah Nomor 2 Tahun 2013 tentang Perubahan Anggaran dan
Belanja Daerah Kabupaten Banyuasin Tahun 2013.
5.2.3.Struktur Organisasi
Pemerintah Kabupaten Banyuasin dipimpin oleh Bupati/Wakil Bupati,
membawahi:
a. Sekretariat Daerah;
b. Sekretariat DPRD.
c. Berdasarkan Perda Nomor 14 Tahun 2008 dan perubahannya, Organisasi
Dinas Daerah Kabupaten Banyuasin terdiri atas 50 SKPD
Dinas/Badan/Kantor/Inspektorat/Kecamatan, yaitu:
1) Dinas Pendidikan;
2) Dinas Kesehatan;
3) Rumah Sakit Umum Daerah;
4) Dinas PU Cipta Karya;
5) Dinas PU Bina Marga;
6) Dinas PU Pengairan;
7) Bappeda dan Penanaman Modal;
8) Dinas Perhubungan;
9) Badan Lingkungan Hidup;
10) Dinas Kebersihan, Pertamanan dan Pemakaman;
84
11) Dinas Kependudukan dan Catatan Sipil;
12) Badan Pelaksana Keluarga Berencana;
13) Dinas Sosial;
14) Dinas Tenaga Kerja dan Transmigrasi;
15) Dinas Koperasi, Perindustrian, Perdagangan, UKM;
16) Kesbangpol;
17) Satuan Polisi Pamong Praja;
18) Inspektorat;
19) Dinas Pendapatan, PengelolaanKeuangandanAset Daerah;
20) Kecamatan Banyuasin I;
21) Kecamatan Banyuasin III;
22) Kecamatan Betung;
23) Kecamatan Rantau Bayur;
24) Kecamatan Pulau Rimau;
25) Kecamatan Talang Kelapa;
26) Kecamatan Rambutan;
27) Kecamatan Tungkal Ilir;
28) Kecamatan Tanjung Lago;
29) Kecamatan Sembawa;
30) Kecamatan Suak Tapeh;
31) Kecamatan Banyuasin II;
32) Kecamatan Makarti Jaya;
33) Kecamatan Muara Padang;
34) Kecamatan Muara Sugihan;
35) Kecamatan Muara Telang;
36) Kecamatan Air Salek;
37) Kecamatan Sumber Marga Telang.
38) Kecamatan Air Kumbang;
39) Badan Kepegawaian dan Diklat Daerah;
40) Badan Perizinan Terpadu;
41) Badan Ketahanan Pangan;
42) Badan Pemberdayaan Masyarakat dan Pemerintah Desa;
43) Badan Perpustakaan Arsip Daerah dan Dokumentasi;
44) Dinas Pertanian dan Peternakan;
45) Badan Pelaksana Penyuluhan Pertanian, Perikanan dan Kehutanan;
46) Dinas Kehutanan dan Perkebunan;
47) Dinas Pertambangan dan Energi;
48) Dinas Pariwisata Seni Budaya, Pemuda dan Olahraga;
49) Dinas Perikanan dan Kelautan;
50) Dinas Pengelola Pasar.
85
VI. PENUTUP
Laporan Keuangan Pemerintah Kabupaten Banyuasin Tahun Anggaran 2013
merupakan bentuk pelaksanaan peraturan perundang-undangan di bidang pengelolaan
keuangan dan peraturan terkait lainnya, untuk memberikan informasi yang lengkap dan
andal kepada pemangku kepentingan (stakeholder) guna meningkatkan good governance.
Demikian Catatan atas Laporan Keuangan (CALK) sebagai bagian yang tidak
terpisahkan dari Laporan Keuangan Kabupaten Banyuasin Tahun 2013 secara
keseluruhan.
86
GAMBARAN UMUM PEMERIKSAAN
2. Tujuan Pemeriksaan
Tujuan pemeriksaan LKPD Tahun Anggaran (TA) 2013 adalah untuk memberikan
opini atas tingkat kewajaran informasi keuangan yang disajikan dalam laporan
keuangan yang didasarkan pada kriteria:
a. Kesesuaian dengan Standar Akuntansi Pemerintahan (SAP);
b. Kecukupan pengungkapan (adequate disclosures);
c. Kepatuhan terhadap peraturan perundang-undangan;
d. Efektivitas sistem pengendalian intern.
3. Sasaran Pemeriksaan
Sasaran pemeriksaan LKPD TA 2013 meliputi pengujian atas:
a. Efektivitas desain dan implementasi sistem pengendalian intern termasuk
pertimbangan hasil pemeriksaan sebelumnya;
b. Kepatuhan terhadap peraturan perundang-undangan yang berlaku;
c. Penyajian saldo akun-akun dan transaksi-transaksi pada Laporan Realisasi
Anggaran (LRA) dan Laporan Arus Kas (LAK) TA 2013 sesuai dengan SAP;
d. Penyajian saldo akun-akun dalam Neraca per 31 Desember 2013;
e. Pengungkapan informasi keuangan pada Catatan atas Laporan Keuangan.
4. Standar Pemeriksaan
Peraturan BPK Nomor 1 Tahun 2007 tentang Standar Pemeriksaan Keuangan
Negara (SPKN).
5. Metode Pemeriksaan
Metodologi pemeriksaan atas LKPD Tahun 2013 meliputi perencanaan, pelaksanaan,
dan pelaporan hasil pemeriksaan, yaitu sebagai berikut.
a. Perencanaan Pemeriksaan
1) Pemahaman Entitas dan Sistem Pengendalian Intern
Pemahaman atas entitas dan sistem pengendalian intern dapat diperoleh
dari laporan hasil pemeriksaan sebelumnya, laporan hasil pemeriksaan
pendahuluan, catatan atas laporan keuangan yang diperiksa, pemantauan
tindak lanjut, dan database yang telah dimiliki serta peraturan atau kebijakan
tertulis/formal kepala daerah terkait.
Pemahaman atas entitas tersebut meliputi pemahaman atas latar
belakang/dasar hukum pendirian pemerintah daerah, kegiatan utama entitas
termasuk sumber pendapatan daerah, lingkungan yang mempengaruhi, pejabat
terkait sampai dengan dua tingkat vertikal ke bawah di bawah kepala daerah,
dan kejadian luar biasa yang berpengaruh terhadap pengelolaan keuangan
daerah. Pemeriksa perlu mengidentifikasi kelemahan-kelemahan signifikan
atau area-area kritis yang memerlukan perhatian mendalam, sehingga
membantu Pemeriksa untuk (1) mengidentifikasi jenis potensi kesalahan, (2)
mempertimbangkan faktor-faktor yang mempengaruhi risiko salah saji yang
material, (3) mendesain pengujian sistem pengendalian intern (SPI), dan (4)
mendesain prosedur pengujian substantif.
2) Pertimbangan Hasil Pemeriksaan Sebelumnya
Pemeriksa harus mempertimbangkan hasil pemeriksaan dan tindak
lanjut hasil pemeriksaan sebelumnya. Pemeriksa harus meneliti pengaruh hasil
pemeriksaan sebelumnya dan tindak lanjutnya terhadap LKPD yang diperiksa,
terutama terkait dengan kemungkinan temuan-temuan pemeriksaan yang
berulang dan keyakinan pemeriksa atas saldo awal akun atau perkiraan pada
neraca yang diperiksa.
3) Penentuan Metode Uji Petik
Penentuan metode uji petik berdasarkan pertimbangan profesional
pemeriksa dengan memperhatikan beberapa aspek, antara lain:
a) Tingkat risiko;
b) Jika hasil pengujian SPI disimpulkan pengendalian intern suatu akun lemah
6. Waktu Pemeriksaan
Jangka waktu pemeriksaan adalah selama 32 hari (sejak tanggal 14 April s.d 15 Mei
2014).
7. Objek Pemeriksaan
Laporan Keuangan Pemerintah Daerah (LKPD) Kabupaten Banyuasin Tahun
Anggaran 2013, yang terdiri atas Laporan Realisasi Anggaran (LRA), Neraca per 31
Desember 2013, Laporan Arus Kas (LAK), dan Catatan atas Laporan Keuangan
(CaLK).
Halaman 1 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembuatan Pagar Makam Dusun 2 Desa Saleh Agung Kecamatan Air Saleh (*R34). 10.000.000 - 10.000.000 -
- Desa Lubuk Karet Kec. Betung untuk Tiang Listrik (PR19). 40.000.000 - 40.000.000 -
- Desa Daya Kusuma Kec. Muara Sugihan untuk Lapangan Sepakbola (PR2). 10.000.000 - 10.000.000 -
- Dusun II Upang Jaya Kec. Muara Telang (PR4). 50.000.000 50.000.000 - 100,00
- Dusun III Upang Jaya Kec. Muara Telang (PR4). 25.000.000 25.000.000 - 100,00
- Desa Upang Karya Kec. Muara Telang (PR4). 50.000.000 50.000.000 - 100,00
- Desa Telang Makmur Kec. Muara Telang (PR4). 50.000.000 50.000.000 - 100,00
- Desa Sumber Mulya Kec. Muara Telang (PR4). 25.000.000 25.000.000 - 100,00
- Desa Marga Mulya Jalur 16 Kec. Muara Sugihan (PR10). 25.000.000 - 25.000.000 -
- Desa Tirta Harja Jalur 14 Kec. Muara Sugihan (PR10). 25.000.000 - 25.000.000 -
- Desa Terusan Muara Kec. Sumber Marga Telang (PR16). 10.000.000 - 10.000.000 -
- Desa Sumber Jaya Kec. Sumber Marga Telang (PR16). 10.000.000 - 10.000.000 -
- Desa Meranti Kec. Suak Tapeh (PR20). 15.000.000 - 15.000.000 -
- Desa Tanjung Tiga Kec. Rantau Bayur. (Pemindahan Sistem Listrik Curah ke PLN) 58.800.000 58.800.000 - 100,00
- Desa Tanjung Pasir Kec. Rantau Bayur. (Pemindahan Sistem Listrik Curah ke PLN) 135.800.000 135.800.000 - 100,00
Halaman 2 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pramuka Kwartir Kabupaten Banyuasin. 400.000.000 400.000.000 - 100,00
- Komite Nasional Pemuda Indonesia (KNPI) Kab. Banyuasin. 300.000.000 300.000.000 - 100,00
- Komisi Penyuluh Pertanian Kab. Banyuasin. 100.000.000 100.000.000 - 100,00
- Kelompok Tani Nelayan Andalan (KTNA) Kab. Banyuasin. 50.000.000 50.000.000 - 100,00
- Muhammadiyah Kabupaten Banyuasin. 150.000.000 150.000.000 - 100,00
- Ikatan Cendekiawan Muslim Indonesia (ICMI) Kab. Banyuasin. 300.000.000 300.000.000 - 100,00
- DEKRANASDA Kab.Banyuasin 400.000.000 400.000.000 - 100,00
- Ikatan Bidan Indonesia (IBI) Kab. Banyuasin. 50.000.000 50.000.000 - 100,00
- Ikatan Dokter Indonesia (IDI) Kab. Banyuasin. 50.000.000 50.000.000 - 100,00
- BKPRMI Kabupaten Banyuasin. 75.000.000 75.000.000 - 100,00
- BKMT Kabupaten Banyuasin. 100.000.000 100.000.000 - 100,00
- Ikatan Mahasiswa Kabupaten Banyuasin (IMBAS) 30.000.000 - 30.000.000 -
- GMPI Kabupaten Banyuasin. 25.000.000 - 25.000.000 -
- Gerakab Pemuda Islam (GPI) Kabupaten Banyuasin. 15.000.000 - 15.000.000 -
- Gerakan Mahasiswa Kosgoro (GEMA KOSGORO) Kab. BA. 25.000.000 - 25.000.000 -
- Forum Pendamping Keluarga Harapan (FPKH) Kab. Banyuasin. 15.000.000 - 15.000.000 -
- Gerakan Pemuda Kebangkitan Bangsa (GARDA) Kab. Banyuasin 10.000.000 10.000.000 - 100,00
- Gerakan Pemuda Ansor Kabupaten Banyuasin. 15.000.000 - 15.000.000 -
- Persatuan Dokter Umum Indonesia (PDUI) Kabupaten Banyuasin. 25.000.000 25.000.000 - 100,00
- Angkatan Muda Ka'bah (AMK) Kabupaten Banyuasin. 20.000.000 - 20.000.000 -
- Ikatan Pelajar Nahdathul Ulama (IPNU) Kab. Banyuasin. 20.000.000 20.000.000 - 100,00
- Muslimat Nahdathul Ulama Kab. Banyuasin. 20.000.000 20.000.000 - 100,00
- Fatayat Nahdathul Ulama Kab. Banyuasin. 20.000.000 20.000.000 - 100,00
- Jam'iyyatul Qurra'wal Huffazh Kab. Banyuasin. 50.000.000 50.000.000 - 100,00
- Persatuan Wartawan Indonesia (PWI) Cabang Sumsel Pewakilan Kab. Banyuasin. 50.000.000 50.000.000 - 100,00
- Pengurus Wilayah Radio Antar Penduduk Indonesia Wilayah 13 Kab. Banyuasin. 5.000.000 - 5.000.000 -
- Forum Pengusaha Banyuasin (FPB). 10.000.000 10.000.000 - 100,00
- Komite Komunikasi Demokrasi Banyuasin (KKDB). 15.000.000 - 15.000.000 -
- Pengurus Forum Komunikasi Ikatan Masyarakat Lekipali (FKIM-LEKIPALI). 20.000.000 - 20.000.000 -
- Generasi Independen Bakti Anak Sriwijaya (GIBAS) Kabupaten Banyuasin. 10.000.000 10.000.000 - 100,00
- Dewan Komite Cabang Jaringan Pembaharuan Nusantara (DKC JPN) Kab. Banyuasin. 5.000.000 5.000.000 - 100,00
- Ikatan Masyarakat Banyuasin (IMB) Kabupaten Banyuasin. 10.000.000 10.000.000 - 100,00
- Majelis Sinergi Kalam icmi Orda Banyuasin (MASIKA Banyuasin). 15.000.000 - 15.000.000 -
Halaman 3 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Gerakan Muda Persatuan Banyuasin (GMP) Banyuasin. 20.000.000 - 20.000.000 -
- Generasi Muda Sriwijaya (GMS) Kabupaten Banyuasin. 25.000.000 25.000.000 - 100,00
- Forum Komunikasi Studi Mahasiswa Kekaryaan (FOSMAKER) 25.000.000 25.000.000 - 100,00
- Angkatan Muda Tarekhat Islam (AMTI). 25.000.000 25.000.000 - 100,00
- Karang Taruna ARMEAS Desa Sei Pinang Kecamatan Rantau Bayur (*R1) 50.000.000 50.000.000 - 100,00
- Karang Taruna Desa Tabuan Asri Kecamatan Pulau Rimau (*R6). 25.000.000 25.000.000 - 100,00
- Karang Taruna Desa Senda Mukti Kecamatan Pulau Rimau (*R6). 10.000.000 10.000.000 - 100,00
- Karang Taruna Ds Rawa Banda Kec. Pulau Rimau (*R6). (Organisasi Pemuda Mandiri) 10.000.000 10.000.000 - 100,00
- Karang Taruna Desa Suka Mulya Kec. Pulau Rimau (*R6). 5.000.000 -
- Perbaikan Lapangan Sepak Bola Karang Taruna Ds. Sribandung Kec. BA III (*R31). 10.000.000 - 10.000.000 -
- Karang Taruna Dusun I Desa Saleh Agung Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 2 Desa Saleh Agung Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 3 Desa Saleh Agung Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 4 Desa Saleh Agung Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun I Desa Srimulyo Kec. Air Saleh (*R34). 4.000.000 - 4.000.000 -
- Karang Taruna Dusun 2 Desa Srimulyo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 3 Desa Srimulyo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 2 Desa Srikaton Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 1 Desa Enggal Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 2 Desa Enggal Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 3 Desa Enggal Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 4 Desa Enggal Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 5 Desa Enggal Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 6 Desa Enggal Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 1 Desa Bintaran Rejo Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 2 Desa Bintaran Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 4 Desa Bintaran Rejo Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 2 Desa Salek Mukti Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 3 Desa Salek Mukti Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 4 Desa Salek Mukti Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 2 Desa Damarwulan Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 3 Desa Damarwulan Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Karang Taruna Dusun 4 Desa Damarwulan Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
Halaman 4 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Karang Taruna Dusun 2 Ds. Salek Makmur Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 3 Ds. Salek Makmur Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 1 Desa Salek Jaya Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 2 Desa Salek Jaya Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Karang Taruna Dusun 2 Desa Sidoharjo Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Forum Silaturrahmi Pemuda, Agama, Pelajar dan Mahasiswa Kec. Muara Telang (*R39). 40.000.000 40.000.000 - 100,00
- LVRI Kabupaten Banyuasin 5.000.000 5.000.000 - 100,00
- PWRI Kabupaten Banyuasin 70.630.000 - 70.630.000 -
- Forum Persaudaraan Mantan Kepala Desa/FPMKD Kec. BA III 8.750.000 8.750.000 - 100,00
- Himpunan Mahasiswa Banyuasin (HIMBA) Kab. Banyuasin 10.000.000 10.000.000 - 100,00
- Perhimpunan Dokter Umum Indonesia Komisariat Banyuasin 25.000.000 - 25.000.000 -
- Karang Taruna Bantul Sari Desa Sumber jaya Jalur 13 Kec. Muara Sugihan 3.800.000 - 3.800.000 -
- PGRI Kabupaten Banyuasin 15.000.000 - 15.000.000 -
- Pencab PSSI Banyuasin Kec. Pangkalan Balai (PR10) 50.000.000 - 50.000.000 -
- Karang Taruna Desa Tanjung Kepayang Kec. Banyuasin III (PR17) 7.500.000 - 7.500.000 -
- Karang taruna Desa Suka Mulya Kec. Banyuasin III (PR17) 5.000.000 - 5.000.000 -
- Karang Taruna Desa Pagar Bulan Kec. Rantau Bayur (PR17) 5.000.000 - 5.000.000 -
- Karang Taruna Desa Lubuk Karet Kec. Betung (PR19) 10.000.000 - 10.000.000 -
- Lembaga Karya Usaha Muda (PR23) 100.000.000 - 100.000.000 -
- Pengcab PSSI Kab. Banyuasin (PR34) 100.000.000 - 100.000.000 -
- PSSI Kabupaten Banyuasin (PR42) 100.000.000 - 100.000.000 -
- Karang Taruna Desa Telang Rejo Kec. Muara Telang (PR16) 7.500.000 - 7.500.000 -
- Karang Taruna Desa Srikaton Kec. Air Saleh (PR16) 7.500.000 - 7.500.000 -
- Karang Taruna Desa Sumber Jaya Kec. Sumber Marga Telang (PR14) 10.000.000 - 10.000.000 -
- Karang Taruna Desa Marga Rahayu Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Panitia rehab Jembatan Tanjung Menang (PR17) 7.500.000 - 7.500.000 -
- Pemuda karang Petai Pangkalan Balai (PR17) 5.000.000 - 5.000.000 -
- Karang Taruna Desa Enggal Rejo Kec. Air Salah (PR33) 10.000.000 - 10.000.000 -
- Karang Taruna Desa Salek Makmur (PR33) 10.000.000 - 10.000.000 -
- Karang Taruna Desa Bintaran Kec. Air Saleh (PR33) 10.000.000 - 10.000.000 -
- Karang Taruna Desa Margo Mulyo kec. Muara Sugihan (PR33) 10.000.000 - 10.000.000 -
- Karang Taruna Desa Cenana Kec. Muara Sugihan (PR33) 15.000.000 - 15.000.000 -
- Karang Taruna Desa Daya Kusuma Kec. Muara Sugihan (PR33) 30.000.000 - 30.000.000 -
Halaman 5 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Karang Taruna Desa Sungsang 4 Kec. Banyuasin II (PR11) 50.000.000 - 50.000.000 -
- Karang Taruna Kelurahan Air Batu Kec. Talang Kelapa (PR40) 50.000.000 - 50.000.000 -
- Karang Taruna Desa Rejodadi Kec. Sembawa (PR38) 35.000.000 - 35.000.000 -
- Gempur FC Desa Purwosari Kec. Sembawa (PR38) 60.000.000 - 60.000.000 -
- Forum Pemuda Sumber waras Desa Talang Kemang Kec. Rantau Bayur (PR38) 60.000.000 - 60.000.000 -
- Dewan Pengurus Cab. Perhimpunan Anak Transmigrasi RI (DPC PATRI) Kab. BA (PR17) 84.750.000 84.750.000 - 100,00
- Hibah Ormas Lainnya (PR38) 276.000.000 - 276.000.000 -
- Karang Taruna Desa Muara Damai Kec. Sembawa (PR25) 10.000.000 - 10.000.000 -
- Karang Taruna Desa Mainan Kec. Sembawa (PR25) "Karang Taruna Ardema" 10.000.000 10.000.000 - 100,00
- Karang Taruna Desa Pulau Kec. Sembawa (PR25) 10.000.000 10.000.000 - 100,00
- Muser Watch Banyuasin (PR25) 150.000.000 - 150.000.000 -
Halaman 6 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembuatan Jembatan Hewan Dusun 3 Ds Daya Kusuma Jalur 14 Kec. M. Sugihan (*R34). 10.000.000 - 10.000.000 -
- Pembuatan Jembatan Hewan Desa Salek Mukti Kecamatan Air Saleh (*R34). 10.000.000 - 10.000.000 -
- Koperasi Serba Usaha Mitra Bersama Abadi Kec. Betung (*R41). 90.000.000 90.000.000 - 100,00
- Kebun Kelapa Sawit Kas Desa Kel. Tani Sumber Agung Tunas Baru Kec. P. Rimau (*R44). 125.000.000 - 125.000.000 -
- Kebun Kelapa Sawit Kas Desa Kel. Tani Wonodadi Jaya Ds Wono Dadi Kec. P. Rimau (*R44). 60.000.000 - 60.000.000 -
- Kelompok Tani Mekar Sari Ds Rimba Jaya Kec. Air Kumbang (Asp EC). 50.000.000 50.000.000 - 100,00
- Koperasi serba usaha betuah mandiri kel. Kedondong raye Kec. BA III. 50.000.000 - 50.000.000 -
- Kelompok Budi Daya Cacing Lumberikus Makmur Kec. Sembawa (PR17). 110.000.000 - 110.000.000 -
- Kelompok Tani "Mitra Tani" Desa Panca Mukti Kec. Muara Telang (PR14). 20.000.000 - 20.000.000 -
- Kelompok Tani "Tani Sejahtera" Desa Telang Rejo Kec. Muara Telang (PR14). 10.000.000 - 10.000.000 -
- Kelompok Tani Desa Margo Mulyo Kec. Muara Sugihan (PR33). 10.000.000 - 10.000.000 -
- Kelompok Tani Desa Daya Kesuma Kec. Muara Sugihan (PR33). 10.000.000 - 10.000.000 -
- Kelompok Karya Tani Desa Rejodadi Kec. Sembawa (PR38). 30.000.000 - 30.000.000 -
- Kelompok Usaha Kecil Penjahit Desa Mainan Kec. Sembawa (PR25). 5.000.000 - 5.000.000 -
- Kelompok Usaha Bersama Budidaya Jamur Tiram Kel. Sukamoro 50.000.000 - 50.000.000 -
Kec. Talang Kelapa (PR40)
Hibah Kpd Kel. Masyarakat dg Kegiatan Bidang Pendidikan 15.050.524.400 6.597.535.500 8.452.988.900 43,84
Sharing Sekolah Gratis 13.690.724.400 5.594.035.500 8.096.688.900 40,86
- Sharing Sekolah Gratis TW. IV (Oktober-Desember) 13.690.724.400 5.594.035.500 8.096.688.900 40,86
Halaman 7 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- TK Dewa Dewi Kelurahan Air Batu Kec. Talang Kelapa (*R22). 150.000.000 150.000.000 - 100,00
- PAUD Tambatan Hati Desa Muara Damai Kecamatan Sembawa (*R26). 40.000.000 40.000.000 - 100,00
- Sekolah MI Hidayatullah Kecamatan Desa Terusan Muara Kec. Sumber Marga Telang (*R29). 50.000.000 50.000.000 - 100,00
- Gedung PAUD Kasih Bunda Awitan Desa Awitan Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Gedung Yayasan Matholiuf Falakh Desa Mekar Jaya Kecamatan Air Saleh (*R34). 10.000.000 - 10.000.000 -
- Yayasan Lembaga Pendidikan Ma'arif Desa Sumber Mulyo Kec. Muara Telang (*R37). 50.000.000 50.000.000 - 100,00
- Yayasan Lembaga Pendidikan Al-Ansor Kecamatan Talang Kelapa (*R39). 50.000.000 50.000.000 - 100,00
- PAUD Tunas Harapan Desa Wana Mukti Kec. Pulau Rimau. 7.500.000 7.500.000 - 100,00
- PAUD Harapan Bangsa Desa Taja Mulya Kec. Betung. 7.000.000 7.000.000 - 100,00
- Madrasah Diniyah Al-Hidayah Betung Kec. Betung. 2.000.000 2.000.000 - 100,00
- SMA Bina Nusa Betung Kec. Betung. 2.000.000 - 2.000.000 -
- SMK PGRI Pangkalan Balai. 4.000.000 - 4.000.000 -
- Mts. As-Sanadiyah Desa tanjung Baru Kec. Muara padang 15.000.000 - 15.000.000 -
- Mts. Darussholihin Kec. Muara Sugihan. 15.000.000 - 15.000.000 -
- PAUD Mustika Dusun III Desa upang Kec. Air saleh. 5.000.000 5.000.000 - 100,00
- PAUD Mona kelurahan Kenten Kec. Talang kelapa. 5.000.000 5.000.000 - 100,00
- PAUD Kasih Ibu Rt.67 Kel. Sukajadi Kec. Talang kelapa (PR7). 20.000.000 - 20.000.000 -
- Yayasan Islam Kunia Ilahi. 7.300.000 7.000.000 300.000 95,89
- SMP Anugrah Desa Sukajaya SP 3 Mukut Kec. Tungkal Ilir (PR15) 10.000.000 - 10.000.000 -
- PAUD untuk 15 Desa Dalam Kec. Tanjung lago (PR18). 30.000.000 - 30.000.000 -
- TK Mentari Desa Lubuk Karet Kec. Betung (PR19). 30.000.000 - 30.000.000 -
- PAUD Kasih Ibu Kel. Sukajadi Kec. Talang Kelapa (PR41). 25.000.000 - 25.000.000 -
- Madrasah Miftahul Ulum Dusun I Rt. 04 Desa Mekar Mukti Kec. Muara Telang (PR16). 10.000.000 - 10.000.000 -
- Madrasah Hidayatullah Muktadin desa Panca Mukti Kec. Muara Telang (PR14). 10.000.000 - 10.000.000 -
- TPA Desa Sumber Mulyo Kec. Muara Sugihan (PR33). 20.000.000 - 20.000.000 -
- TK Desa Mekar jaya Kec. Muara Sugihan (PR33). 5.000.000 - 5.000.000 -
- PAUD/TK Tunas Kesuma Desa Daya Kesuma Jalur 14 Kec. Muara Sugihan (PR10). 25.000.000 - 25.000.000 -
- TPA Dusun IV Sei Sembilang Desa Sungsang IV Kec. Banyuasin II (PR34). 10.000.000 - 10.000.000 -
- TPA Dusun V Sei Sembilang Desa Sungsang IV Kec. Banyuasin II (PR34). 10.000.000 - 10.000.000 -
- TPA UPT Primer V Desa Jati Sari Kec. BA II (PR34). 5.000.000 - 5.000.000 -
- TPA UPT Primer VI Desa Tabala Jaya Kec. BA II (PR34). 5.000.000 - 5.000.000 -
- Rumah Tahfiz Qur'an Desa Teluk Payo Kec. BA II(PR34). 10.000.000 - 10.000.000 -
- PAUD Desa Tanah Pilih Kec. BA II (PR34). 10.000.000 - 10.000.000 -
Halaman 8 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- TPA PAUD Masjid (PR42). 100.000.000 80.000.000 20.000.000 80,00
- Musholla Al-Barokah Kec. Tlg. Kelapa
- Masjid Al-Muhajirin Ds. Air Batu Kec. Tlg. Kelapa
- Masjid Al-Muhlisin Perum Griya Handayani Kec. Tlg. Kelapa
- Masjid Nurul Iman Ds. Muara Sugih
- Masjid Baitul Iman Kel. Sukomoro
- Masjid Baitul Makmur Ds. Saluran
- Masjid Al-Hidayah Lr. Sepakat Kel. Sukomoro
Hibah Kepada Kelompok Masyarakat dengan Kegiatan Bidang Keagamaan 8.268.100.000 4.309.600.000 3.958.500.000 52,12
Kecamatan Air Kumbang. 87.500.000 22.500.000 65.000.000 25,71
- Rehab. Gereja Desa Nusa Makmur Kec. Air Kumbang. 5.000.000 - 5.000.000 -
- Rehab. Masjid ................... Sp. 2 Desa Sido Makmur Kec. Air Kumbang (*R19). 50.000.000 - 50.000.000 -
- Pembangunan Masjid Jamiatul Muslimin Desa Sidomulyo Kec.Air Kumbang (PR34). 7.500.000 7.500.000 - 100,00
- Pembangunan Masjid Bustanul Ulum Desa Sidomulyo Kec. Air Kumbang. 15.000.000 15.000.000 - 100,00
- Pembangunan Pura Merta Sari desa Cintamanis Baru KM XI Kec. Air Kumbang. 10.000.000 - 10.000.000 -
Halaman 9 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Masjid Nurul Huda Desa Enggal Rejo Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Barokatul Huda Desa Enggal Rejo Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Taqwa Desa Salek Jaya Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Takhul Huda Desa Salek Jaya Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Huda Desa Salek Jaya Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Ikhlas Desa Salek Jaya Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Iman Desa Salek Makmur Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Baitul Mukminin Desa Salek Makmur Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Baitul Muttaqin Desa Bintaran Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Muhajirin Desa Bintaran Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Taqwa Desa Bintaran Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Huda Desa Saleh Mukti Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Baiturrohman Desa Saleh Mukti Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Darussalam Desa Saleh Mukti Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Baiturrahman Desa Sidoharjo Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Darul Taqwa Desa Damarwulan Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Hijrah Desa Damarwulan Kecamatan Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Rehab. Mushollah Nurul Huda Desa Sidoharjo Kecamatan Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Baiturrohim Desa Srimutyo Kecamatan Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Nurul Imam Dusun 2 Desa Damarwulan Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Tanwirul Qulub Dusun I Desa Saleh Agung Kec. Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Muthakbiin Dusun 2 Desa Saleh Agung Air Saleh (*R34). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Al-Hikmah Dusun 1 Desa Srikaton Kecamatan Air Saleh (*R34). 2.000.000 - 2.000.000 -
- Rehab. Mushollah Darussalam Dusun 1 Desa Srikaton Kecamatan Air Saleh (*R34). 2.000.000 - 2.000.000 -
- Rehab. Mushollah Darul Hikmah Dusun 1 Desa Srikaton Kec. Air Saleh (*R34). 2.000.000 - 2.000.000 -
- Pembangunan Gereja Kristen Muria Indonesia (GKMI) Cakranegaran Desa Saleh 10.000.000 10.000.000 - 100,00
Mukti Kec Air Saleh.
- Mushola Desa Sidoharjo Kec. Air saleh (PR33) 10.000.000 - 10.000.000 -
- Masjid Desa Srikaton Kec. Air Saleh (PR33). 10.000.000 - 10.000.000 -
Halaman 10 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
Kecamatan Banyuasin I. 255.000.000 135.000.000 120.000.000 52,94
- Pembangunan Masjid Al-Mu'minin Kel. Mariana Kec. BA I. 5.000.000 5.000.000 - 100,00
- Renovasi Masjid At-Taqwa Ds. Cinta Manis Lama Kecamatan Banyuasin I. 15.000.000 15.000.000 - 100,00
- Renovasi Masjid Baitus Syahid Dusun II Ds. Sidomulyo Kec. Banyuasin I. 7.500.000 - 7.500.000 -
- Rehab. Masjid Al-Hidayah Dusun III Ds. Nusa Makmur Kecamatan Banyuasin I. 5.000.000 - 5.000.000 -
- Rehab. Masjid Al-Ikhlas Dusun II Ds. Nusa Makmur Kecamatan Banyuasin I. 5.000.000 - 5.000.000 -
- Rehab. Masjid Sabilil Mustaqim Dusun IV Desa Nusa Makmur Kecamatan Banyuasin I. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Riyyadul Jannah Ds. Pulau Borang Kec. Banyuasin I. 7.500.000 - 7.500.000 -
- Pembangunan Pure Merta Sari Desa Cinta Manis Baru Kecamatan Banyuasin I. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Taufiqurrahman Desa Pematang Palas Kecamatan Banyuasin I. 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Darul Muttaqin Desa Kumbang Padang Kecamatan Banyuasin I. 5.000.000 5.000.000 - 100,00
- Pembangunan Masjid Jami' Nurul Huda Ds. Tirto Sari Kecamatan Banyuasin I. 5.000.000 5.000.000 - 100,00
- Pembangunan Mushollah Al-Muhajirin Kelurahan Mariana Kec. Banyuasin I (*R8). 55.000.000 55.000.000 - 100,00
- Pembangunan Mushollah ................ . Lorong Vinus Kecamatan Banyuasin I (*R12). 25.000.000 - 25.000.000 -
- Pembangunan Masjid ................ . Desa Perambahan Kecamatan Banyuasin I (*R19). 25.000.000 - 25.000.000 -
- Pemb. Mushollah .............. Lrg. Selumar Kelurahan Maryana Ilir Kec. Banyuasin I (*R19). 25.000.000 - 25.000.000 -
- Pembangunan Masjid Al-Iman Desa Sidomulyo Kec. BA I. 5.000.000 5.000.000 - 100,00
- Pembangunan Musholla Hidayatullah Km.16 Dusun III Rimba Jaya Kec. BA I 5.000.000 5.000.000 - 100,00
- Pembangunan Pura Merta Sari Desa Cintamanis Baru KM XI Kec. BA I 10.000.000 - 10.000.000 -
- Pembangunan Masjid Sabilul Huda Jl. Dr. A. Rivai Abdullah Kel. Mariana Kec. BA I 5.000.000 5.000.000 - 100,00
- Pembangunan Masjid At-thohiri Jl. Sabar Jaya Kel. Mariana Kec. BA I 10.000.000 10.000.000 - 100,00
- Pembangunan Musholla Miftahul Huda Desa Sungai Gerong Kec. BA I 5.000.000 5.000.000 - 100,00
- Pembangunan Musholla Nurul Jannah Desa Merah Mata Kec. BA I 5.000.000 5.000.000 - 100,00
- Pembangunan Musholla Nurul Iman Kel. Mariana Ilir Kec. BA I. 5.000.000 5.000.000 - 100,00
Halaman 11 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Masjid Al-ikhlas sungai Jeruji Desa Sungsang II Kec. BA II 10.000.000 - 10.000.000 -
- Masjid Al-Mukmin Desa Sungsang I Kec. BA II (PR44) 5.000.000 - 5.000.000 -
- Masjid At-taqwa Desa Muara Sungsang Kec. BA II (PR44) 5.000.000 - 5.000.000 -
Halaman 12 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Masjid Al-Jihad Ujung Tanjung Kec. BA III 25.000.000 - 25.000.000 -
- Musholla Al-Furqon Pangkalan Panji Kec. BA III (PR25) 10.000.000 10.000.000 - 100,00
- Masjid Fatuljanah Desa Petaling Kec. BA III (PR20) 10.000.000 - 10.000.000 -
- Masjid Taqwa Desa Petaling Kec. BA III (PR20) 10.000.000 - 10.000.000 -
- Masjid Istiqomah Desa Petaling Kec. BA III (PR20) 10.000.000 - 10.000.000 -
- Langgar Al Hikmah Rt.08 Rw.03 Desa Petaling Kec. BA III (PR20) 20.000.000 - 20.000.000 -
- Musholla Ds. Bengkuang Desa Langkan Kec. BA III (PR25) Masjid Al-Furqon 10.000.000 10.000.000 - 100,00
- Masjid Nurussa'adah Seterio Kec. BA III (PR9) 10.000.000 10.000.000 - 100,00
- Masjid Syuhada Kel. Kedondong Raye Kec. BA III(PR9) 10.000.000 10.000.000 - 100,00
- Masjid Nurul Falah Desa Sidang Emas Kec. Ba III (PR9) 10.000.000 10.000.000 - 100,00
- Masjid Nurul Iman Desa Terlangu Kec. BA III (PR9) 10.000.000 10.000.000 - 100,00
- Masjid Al Amin Cangkring Kec. BA III (PR9) 10.000.000 10.000.000 - 100,00
Halaman 13 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Rehab. Masjid Al-Hidayah Purbolinggo Kelurahan Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Hijrah Sedempo Kelurahan Betung Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid At-Taqwa Tebing Dayat Kelurahan Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Baitul Makmur Rt. 28/08 Lk. IV Kelurahan Betung Betung (*R11). 5.000.000 - 5.000.000 -
- Rehab. Masjid Al-Muhajirin Rt. 19/06 Lk. III Kel. Betung Kec. Betung (*R11). / Al-Muhajirin Keg. Safari
5.000.000
Jumat 5.000.000 - 100,00
- Rehab. Masjid An-Nurhikmah Jl. Talang Jaya Rt. 02/01 Lk. I Kel. Betung Kec. Betung (*R11). 35.000.000 35.000.000 - 100,00
- Rehab. Masjid Baitul Rahman Jl. Gtng Royong Rt. 03/01 Lk. I Kel. Betung Kec. Betung (*R11). 5.000.000 - 5.000.000 -
- Rehab. Masjid Al-Ikhtihad Bangun Rejo Rt. 13/04 Lk. II Kel. Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Hidayah Talang Kayu Abang Rt. 53/14 Kel. Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Hidayah Bangun Rejo Rt. 09/04 Lk. II Kel. Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid An-Nur Jl. Kades Rt. 31/09 Lk. V Kel. Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Baitul Ikhsan Jl. SDN 3 Rt. 10/03 Lk. II Kel. Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Darul Fallah Jl. P2KT Rt. 28/08 Lk. IV Kel. Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Al-Muttaqin h. Mashuri Kelurahan Betung Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Mushollah SMPN 1 Kelurahan Betung Kec. Betung (*R11). 4.000.000 - 4.000.000 -
- Rehab. Masjid Al-Amin Lorong Kombet Kel. Rimba Asam Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Nurul Iman Pasar Pagi Kel. Rimba Asam Kec. Betung (*R11) + (*R20). 13.000.000 13.000.000 - 100,00
- Rehab. Masjid Al-Huda, H. Nawawi Kel. Rimba Asam Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Muhajirin Kelurahan Rimba Asam Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjidddarul Mukminin Perumnas Anugrah Kel. Rimba Asam Kec. Betung (*R11). 3.000.000 3.000.000 - 100,00
- Rehab. Masjid Nurul Huda Meranjat Kelurahan Rimba Asam Kecamatan Betung (*R11). 3.000.000 3.000.000 - 100,00
- Rehab. Masjid Al-Ikhsan Kampung Sawah Rt. 36, 38 Kel. Rimba Asam Kec. Betung (*R11). 4.000.000 - 4.000.000 -
- Rehab. Masjid Nurul Iman Dusun II Desa Lubuk Karet Kec. Betung (*R11) + (*R20) 20.000.000 20.000.000 - 100,00
- Rehab. Masjid Nurul Iman Dusun III Desa Lubuk Karet Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Nurul Hidayah, Sedongkok Desa Lubuk Karet Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Ikhsan Desa Pulau Rajak Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Jami'atutaqwa Desa Philip 2 Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Mushollah Dusun II Desa Philip 2 Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Muhajirin Dusun I Desa Philip 3 Taja Raya 1 Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Ikhlas Dusun II Desa Philip 3 Taja Raya 1 Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Darussalam Desa Philip 4 Taja Mulya Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Bakti Desa Philip 4 Taja Mulya Kecamatan Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Amaliah Dusun II Blok A Desa Taja Indah Kec. Betung (*R11). 3.000.000 - 3.000.000 -
Halaman 14 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Rehab. Masjid Amal Bakti Dusun II Blok B Desa Taja Indah Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Al-Muhajirin Dusun III Blok C Desa Taja Indah Kec. Betung (*R11). 3.000.000 - 3.000.000 -
- Rehab. Masjid Nurul Insan Blok A Desa Taja Indah Kecamatan Betung (*R11). 3.000.000 3.000.000 - 100,00
- Pemb. Masjid Baitul Makmur Jl. Plg-Jambi Pasar Pasar Lama Km. 67 Kec. Betung (*R20). 10.000.000 - 10.000.000 -
- Pemb. Masjid Nurul Huda Lk. I Meranjat No. 2 Rt. 2 Kel. Rimba Asam Kec. Betung (*R20). 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Amalia Dusun 1 Desa Taja Indah Kecamatan Betung (*R20). 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Nurussalam Dusun II Desa Taja Indah Kecamatan Betung (*R20). 10.000.000 - 10.000.000 -
- Pembangunan Mushollah Al-Fatah Perumnas Kel. Rimba Asam Kec. Betung (*R20). 10.000.000 - 10.000.000 -
- Pembangunan Musholla Al Falah Komp. Griya Mulya Kel. R. Asam Kec. Betung (PR20) 7.500.000 - 7.500.000 -
- Pembangunan Masjid Al Hikmah Km. 69 Kec. Betung. 10.000.000 - 10.000.000 -
- Pembangunan Masjid Nurul Huda LK. I Meranjat Kel. Rimba Asam Kec. Betung. 7.500.000 - 7.500.000 -
- Masjid Al Ikhlas Jl. Jambi KM 70 D2 Desa Bukit Kec. Betung (PR29) 20.000.000 20.000.000 - 100,00
- Masjid Al Ikhlas Desa Pulau Rajak Kec. Betung (PR20) 10.000.000 - 10.000.000 -
Halaman 15 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Rehab. Mushollah Al-Amin Desa Purwosari Kecamatan Muara Padang (*R32). 10.000.000 10.000.000 - 100,00
- Rehab. Masjid Al-Ikhlas Desa Sumber Makmur Kecamatan Muara Padang (*R32). 10.000.000 10.000.000 - 100,00
- Rehab. Masjid Taqwa Desa Sido Mulyo 20 Kecamatan Muara Padang (*R32). 10.000.000 10.000.000 - 100,00
- Rehab. Masjid Raudul Huda Desa Air Gading Kecamatan Muara Padang (*R32). 10.000.000 10.000.000 - 100,00
- Rehab. Masjid Mamba'ul Ulum Desa Tirta Raharja Kec. Muara Padang (*R32). 10.000.000 10.000.000 - 100,00
- Rehab Masjid Al Imanu Darussalam Desa Tirto Raharjo Kec. Muara Padang (PR32) 10.000.000 10.000.000 - 100,00
- Rehab Mushollah ............ Desa Sidomulyo Kecamatan Muara Padang (*R34). 10.000.000 - 10.000.000 -
- Rehab. Masjid Mujahidin Jalur 18 Desa Sidorejo Kecamatan Muara Padang (*R34). 5.000.000 - 5.000.000 -
- Pembangunan Masjid At-Taqwa Desa Daya Makmur Jalur 18 Kec. Muara Padang 10.000.000 - 10.000.000 -
- Masjid Nur Hikmah Dusun 5 sungai Raden Desa Muara Padang Kec. M. Padang (PR20) 10.000.000 - 10.000.000 -
- Pembangunan Masjid Al Muhajirin Dusun Sungai Desa Kec. Muara Padang 25.000.000 - 25.000.000 -
Halaman 16 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
Kecamatan Muara Telang 370.000.000 150.000.000 220.000.000 40,54
- Pembangunan Masjid Al-Hidayah Ds. Sumber Hidup Jalur 8 Kecamatan Muara Telang. 5.000.000 - 5.000.000 -
- Pembangunan Masjid An-Nur Desa Telang Kec. Muara Telang. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Hidayatul Islam Desa Sumber Mulya Kec. Muara Telang. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Muhajirin Desa Telang Jaya Dusun I Kec. Muara Telang (*R7). 50.000.000 50.000.000 - 100,00
- Pembangunan Masjid Al-Amin Desa Telang Makmur Kecamatan Muara Telang (*R38). 25.000.000 25.000.000 - 100,00
- Pembangunan Masjid Al-Huda Desa Panca Mukti Kecamatan Muara Telang (*R39). 15.000.000 15.000.000 - 100,00
- Pembangunan Masjid Hidayatul Islam Dusun III Desa Sumber Mulya Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Pembangunan Masjid Hidayatullah Dusun IV Desa Sumber Mulya Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Pembangunan Masjid Al-Baitul Rahman Dusun II Ds Sumber Mulya Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Pembangunan Masjid Al-Muhajirin Dusun IIV Ds Sumber Mulya Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Masjid Al Amin Desa Telang Jaya Kec. Muara Telang 10.000.000 - 10.000.000 -
- Masjid Baitullah Blok 6 RT 13 Dusun I Desa Marga Rahayu Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Masjid Sabillilah Dusun II Desa Telang Rejo Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Masjid Al Falah Dusun III Desa Telang Rejo Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Masjid Baitul Taqwa Dusun III Jembatan 7 Desa Telang Karya (PR16) 10.000.000 - 10.000.000 -
- Masjid Faturohman Dusun I Jembatan 6 Desa Telang Karya (PR16) 10.000.000 - 10.000.000 -
- Masjid Nurul Iman Desa Sumber Jaya Kec. Muara Telang (PR20) 25.000.000 - 25.000.000 -
- Masjid Al Hidayah Desa Mekar Mukti Kec. Muara Telang (PR20) 10.000.000 - 10.000.000 -
- Masjid Baitul Muttaqin Desa Telang Jaya RT 8 Dusun 2 Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid Al Ijtihad Desa Telang Jaya Rt 3 Dusun I Kec. Muara Telang (PR14) 20.000.000 - 20.000.000 -
- Masjid Nurul Rahmah Desa Telang Jaya Rt 3 Dusun II Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid Nurul Iman Desa Upang Jaya Rt 10 Dusun III Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid Al Muhajirin Desa Upang Jaya Rt 2 Dusun I Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid Nur Mulya Agung Desa Upang Jaya Rt 5 Dusun II Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Musholla Cahaya Iman Desa Upang Jaya Rt 8 Dusun II Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid Al Hidayah Desa Telang Makmur Rt 15 Rw 8 Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Musholla Nurul Iman Desa Telang indah Rt 4 Dusun II Kec. Muara Telang (PR14) 20.000.000 - 20.000.000 -
Halaman 17 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Masjid Nurul Iman Ds. Senda Mukti Kecamatan Pulau Rimau. 15.000.000 - 15.000.000 -
- Pembangunan Masjid Darussalam Ds. Teluk Betung Kecamatan Pulau Rimau. 15.000.000 15.000.000 - 100,00
- Rehab. Masjid Al-Huda Ds. Dana Mulya Kec. Pulau Rimau. 5.000.000 - 5.000.000 -
- Rehab. Masjid Jami' Darusalam Ds. Wonosari Kec. Pulau Rimau 30.000.000 30.000.000 - 100,00
- Rehab. Mushollah Nurul Iman Desa Wonosari Kecamatan Pulau Rimau (*R6).. 5.000.000 5.000.000 - 100,00
- Rehab. Mushollah Al-Amin Desa Wonosari Kecamatan Pulau Rimau (*R6).. 5.000.000 5.000.000 - 100,00
- Rehab. Mushollah Baitul Rohim Desa Majatra Kecamatan Pulau Rimau (*R6).. 25.000.000 25.000.000 - 100,00
- Rehab. Masjid Al-Mutakin Desa Sumber Rejo Kecamatan Pulau Rimau (*R6).. 5.000.000 5.000.000 - 100,00
- Rehab. Masjid Baitul Rahman Desa Banjar Sari Kecamatan Pulau Rimau (*R6).. 5.000.000 - 5.000.000 -
- Rehab. Masjid Al-Ikhlas Desa Songo Makmur Kecamatan Pulau Rimau (*R6).. 5.000.000 5.000.000 - 100,00
- Rehab. Masjid Al-Mutaqin Desa Penuguan Kecamatan Pulau Rimau (*R6).. 5.000.000 - 5.000.000 -
- Rehab. Masjid Baitul Mustaqin Desa Wonosari Kecamatan Pulau Rimau (*R6).. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Huda Desa Wono Dadi Kec. Pulau Rimau (*R44). 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Baiturrahman Desa wono Dadi Kec. Pulau Rimau (*R44). 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Miftahul Jannah Desa Sumber Agung Kec. Pulau Rimau (*R44). 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Baitul Muttaqin Desa Sumber Agung Kec. Pulau Rimau (*R44). 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Darussalam Desa Sumber Agung Kec. Pulau Rimau (*R44). 20.000.000 20.000.000 - 100,00
- Pembangunan Masjid Al-Muhajirin Desa Penuguan Kecamatan Pulau Rimau (*R44). 15.000.000 15.000.000 - 100,00
- Pembangunan Masjid Jami' Desa Sumber Mukti Kecamatan Pulau Rimau (*R44). 10.000.000 - 10.000.000 -
- Pembangunan Masjid Nurul Huda Desa Teluk Betung Kec. Pulau Rimau 40.000.000 40.000.000 - 100,00
- Pemb. Masjid Al-Ikhlas Desa Mekar Sari Kec. Pulau Rimau (Jami' Hidayatullah) 20.000.000 20.000.000 - 100,00
- Pembangunan Masjid Jumiriah Desa Wonosari Kec. Pulau Rimau 10.000.000 - 10.000.000 -
- Pembangunan Masjid Nurul Huda Desa Desa Teluk Betung Kecamatan Pulau Rimau 10.000.000 - 10.000.000 -
- Pembangunan Masjid Al Muhajirin Desa Buana Murti Kec. Pulau Rimau. 15.000.000 - 15.000.000 -
- Pembangunan Masjid Al Muhajirin Desa Bumi Rejo Kec. Pulau Rimau 10.000.000 - 10.000.000 -
- Masjid Al Hidayah Desa Rawa Banda Rt 01 Kec. Pulau Rimau (PR15) 25.000.000 - 25.000.000 -
- Masjid Al Muhajirin Desa Wana MuktiRt 01 Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid At Taqwa Desa Sumber Mulyo Rt 10 Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Al Huda Desa Dana Mulyo Rt 12 Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Baiturrahman Desa Sumber Rezeki Rt 10 Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Mujahidin Desa Ponogoan Dusun 06 Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Musholla Mambaul Qaryatin Islamiah Desa Kelapa Dua Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Nurul Huda Desa Mekar Sari Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
Halaman 18 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Masjid Al Muhajirin Desa Buana Murti Kec. Pulau Rimau (PR15) 15.000.000 - 15.000.000 -
- Masjid Al Muhajirin Desa Bandar Sari Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Musholla Al Husna Desa Teluk Betung Rt 01 Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Annahel Desa Tabuan Sari Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Miftahul Falah Desa Ringin Harjo Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Al Barokah Desa Karang Manunggal Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
- Masjid Hidayatullah Desa Purwodadi Dusun I Kec. Pulau Rimau (PR15) 10.000.000 - 10.000.000 -
Halaman 19 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Masjid Jami'atul Khair Desa Rantau Bayur Kec. Rantau Bayur (*R27). 5.000.000 5.000.000 - 100,00
- Masjid Jami'atul khair Ds. Rantau Bayur Kec. Rantau Bayur 10.000.000 10.000.000 - 100,00
- Masjid Muttaqin Ds. Penandingan Kec. Rantau Bayur 10.000.000 10.000.000 - 100,00
- Masjid At-Tabiin Ds. Muara Abab Kec. Rantau Bayur 10.000.000 10.000.000 - 100,00
- Masjid Quba Ds. Paldas Dusun I Kec. Rantau Bayur 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Rohmaniah II Dusun I Ds. Lebung Kec. Rantau Bayur (*R27) 25.000.000 25.000.000 - 100,00
- Pembangunan Masjid Al-Muttaqin Ds. Srijaya/Pematang Mesra Kec. Rantau Bayur 25.000.000 25.000.000 - 100,00
- Pembangunan Masjid Nurussani Ds. Lubuk Rengas Ds. 3 Kec. Rantau Bayur 5.000.000 5.000.000 - 100,00
- Pembangunan Masjid Nurul Iman Desa Sejagung Ds. I Kec. Rantau Bayur 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Al-Ikhlas Ds. Reban Piles/Sungai Pinang Kec. R. Bayur 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Al-Yakin Desa Perasinan/Sungai Pinang Kec. Rantau Bayur 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Al-Jihad Ds Seberang Pengumbuk/Tebing Abang Kec. R. Bayur 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Jamiatul Insan Kemiri Ds. Kemiri Rantau Harapan Kec. R. Bayur 5.000.000 5.000.000 - 100,00
- Pembangunan Masjid Jami"atul Khair Desa Rantau Bayur Kec. Rantau Bayur 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Huda Desa Tanjung Menang Musi Kec. Rantau Bayur 10.000.000 - 10.000.000 -
- Pembangunan Masjid Bhakti Desa Talang Kemang Kec. Rantau 10.000.000 - 10.000.000 -
- Masjid Al Istiqomah Dusun 4 Desa Semuntul Kec. Rantau Bayur (PR12) 15.000.000 - 15.000.000 -
- Masjid Muhajirin Dusun 2 Desa Sukarela Kec. Rantau Bayur (PR12) 15.000.000 - 15.000.000 -
- Masjid Rohmaniah Kampung I Desa Lebung Laut Kec. Rantau bayur (PR20) 15.000.000 - 15.000.000 -
- Masjid Al Ikhlas Ds. Lubuk Rengas Kec. Rantau Bayur (PR9)/ Ar-Rahman Ds. Tj.Agung (srt Pernytn) 10.000.000 10.000.000 - 100,00
- Masjid Nurul Iman Desa Lubuk Rengas Kec. Rantau Bayur (PR9) 10.000.000 10.000.000 - 100,00
- Masjid Darussalam Gemampo Desa Rantau Harapan Kec. Rantau Bayur (PR9) 10.000.000 10.000.000 - 100,00
- Musholla Nurul Hidayah Desa Lebung Kec. Rantau bayur (PR9) 10.000.000 10.000.000 - 100,00
Halaman 20 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Rehab Musholla Al Ikhlas Dusun IV Sribangun Desa Mainan Kec. Sembawa (*R26) 30.000.000 30.000.000 - 100,00
- Pembangunan Musholla Nurul Iman Desa Rejodadi Kec. Sembawa 20.000.000 20.000.000 - 100,00
- Pembangunan Masjid Al Ikhlas Desa Muara Damai Dusun II Kec. Sembawa 10.000.000 - 10.000.000 -
- Pembangunan Musholla Nurul Amin Dsn I Lalang Sembawa Kec. Sembawa (PR17) 7.500.000 - 7.500.000 -
- Masjid Limbang Mulya Kec. Sembawa (PR17) 10.000.000 - 10.000.000 -
- Masjid Al Muhajirin Desa Limbang Mulya Kec. Sembawa (PR16) 20.000.000 - 20.000.000 -
- Musholla Nurul Iman Desa Rejodadi Kec. Sembawa (PR 38) 15.000.000 15.000.000 - 100,00
- Musholla Al Hidayah Musi Landas Desa Mainan Kec. Sembawa (PR25) 5.000.000 5.000.000 - 100,00
- Musholla Amali Rt 009 Ds. 2 Pulau Harapan Kec. Sembawa (PR 25) 5.000.000 5.000.000 - 100,00
- Musholla Shofa Marwa Ds. 2 Rt 08 Sri Mulia Desa Pulau Kec. Sembawa (PR25) 5.000.000 5.000.000 - 100,00
- Musholla Ds. Rejang Landas Desa Mainan Kec. Sembawa (PR25) / Nurul Iman 10.000.000 10.000.000 - 100,00
- Musholla Bahrul Amal Jl. Punjung Jaya Rt 05 Ds. 3 Desa Pulau Harapan Kec. 5.000.000 5.000.000 - 100,00
Sembawa (PR25)
- Masjid Al Hijrah Perum Sembawa Azhar Permai Kec. Sembawa (PR9) 10.000.000 10.000.000 - 100,00
- Masjid Al Ikhlas Dsn. Sribangun Desa Mainan Kec. Sembawa 7.500.000 - 7.500.000 -
Halaman 21 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Masjid Aqi-Musholla Desa Karang Baru Kec. Sumber Marga Telang (PR16) 15.000.000 - 15.000.000 -
- Masjid Munawarotul Muttaqin Terusan Tengah Kec. Sumber Marga Telang (PR 16) 15.000.000 - 15.000.000 -
- Masjid Nurul Hikmah Dusun 4 Desa Sumber Jaya Kec. Sumber Marga Telang (PR16) 15.000.000 - 15.000.000 -
- Masjid Baithul Abdyadh Dusun 4 Desa Sumber Mulyo Kec. Sumber Marga Telang 10.000.000 - 10.000.000 -
- Musholla Insan Mutiara Desa Karang Baru Rt 7 Dusun II Kec. SM Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid Nurul Komar Desa Terusan Muara Kec. Sumber Marga Telang (PR14) 10.000.000 - 10.000.000 -
- Masjid/Musholla Talang Lubuk Kec. Sumber Marga Telang (PR34) 10.000.000 - 10.000.000 -
- Masjid Istiqomah Desa Karang Anyar Kec. Sumber Marga Telang (PR38) 15.000.000 - 15.000.000 -
- Masjid Munawarotul Muttaqin Desa Terusan Kec. Sumber Marga Telang (PR20) 10.000.000 - 10.000.000 -
- Musholla Nurul Huda Desa Terusan Tengah Kec. Sumber Marga Telang 10.000.000 - 10.000.000 -
- Masjid di Desa Muara Telang Marga Kec. Sumber Marga Telang (PR20) 10.000.000 - 10.000.000 -
- Masjid Desa Sritiga Kec. Sumber Marga Telang (PR20) 10.000.000 - 10.000.000 -
- Masjid Desa Sri Menanti Kec. Sumber Marga Telang (PR20) 10.000.000 - 10.000.000 -
- Masjid Aqimushollah Dusun 4 Desa Karang Baru Kec. Sumber Marga Telang (PR20) 15.000.000 - 15.000.000 -
- Mushollah Al Fauzan Desa Karang Baru Rt 5 Kec. Sumber Marga Telang (PR20) 15.000.000 - 15.000.000 -
Halaman 22 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Masjid Hidayatullah Komp. Al-Azhar Kec. Talang Kelapa (*R33) 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Ambiya Kel. Tanah Mas Kec. Talang Kelapa (*R33) 5.000.000 - 5.000.000 -
- Pembangunan Masjid Attahibul Janna Perum Tanah Mas Kec.Talang Kelapa (*R33) Kec. Talang Kelapa.5.000.000 - 5.000.000 -
- Pembangunan Musholla Al-Azhar Perum Tanah Mas Kec. Talang Kelapa (*R33) 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Huda Suka Makmur Kel. Air Batu Kec. Talang Kelapa. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Nurul Iman Suka Makmur Kel. Air Batu Kec. Talang Kelapa (*R33) 5.000.000 - 5.000.000 -
- Pembangunan Musholla At-Taubah Kel. Tanah Mas Kec. Talang Kelapa. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-iklas Kel. Talang Keramat Kec. Talang Kelapa (*R33) 5.000.000 - 5.000.000 -
- Pembangunan Musholla Al-Salihin Kec. Talang Kelapa (*R33) 5.000.000 - 5.000.000 -
- Pembangunan Masjid Hikmatullah Desa Talang Buluh Kec. Talang Kelapa. 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Ikhlas Perum Jadongan Kel. Tanah Mas Kec. Talang 5.000.000 - 5.000.000 -
- Pembangunan Masjid Baitul Jannah Perum Mega Asri Kel. Sukajadi Kec. Talang 5.000.000 - 5.000.000 -
- Pembangunan Musholla Al-AzharPrumdam Kel. Tanah Mas Kec. Talang Kelapa. 5.000.000 - 5.000.000 -
- Pembangunan Gereja HKBP Huria Sukamaju Kenten Kec. Tlg Kelapa 100.000.000 - 100.000.000 -
- Pembangunan Masjid Al-Hikmah Kel. Sukajadi Kec. Tlg Kelapa 20.000.000 - 20.000.000 -
- Pembangunan Masjid Hidayatullah Komp. Azhar KM. 14 Kel. Tanah Mas Kec. Tlg Kelapa 5.000.000 5.000.000 - 100,00
- Pembangunan Masjid Baitul Jannah Komp. RSS Griya Sukomoro Kel. T. Mas Kec. Tlg Klp 10.000.000 - 10.000.000 -
- Pembangunan Masjid Babusalam Griya Sukajadi Permai Kel. Sukajadi Kec. Tlg Klp 7.500.000 7.500.000 - 100,00
- Pembangunan Masjid Nur Hidayah Jl. Guru Harun Kec. Tlg Klp 7.500.000 7.500.000 - 100,00
- Pembangunan Musholla Al. Mubarok Komp. Griya Karya Sejahtera Kec. Tlg Klp 10.000.000 10.000.000 - 100,00
- Pembangunan Musholla Al. Hikmah Perumahan Griay Pasir Putih Kec. Tlg Klp 10.000.000 - 10.000.000 -
- Pembangunan Musholla Nurul Amal Desa Kenten Laut Kec. Tlg Klp 5.000.000 5.000.000 - 100,00
- Pembangunan Musholla Di lingkungan Kantor Lurah Sukajadi Kec. Tlg Klp 10.000.000 - 10.000.000 -
- Pembangunan Masjid Nurul Iman Jl. Kebon Jeruk Kel. Tlg Keramat Kec. Tlg Klp 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Baitussalam Komp. Griya Damai Indah Kec. Tlg Klp 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Al-Muhajirin Jl. Kebon Jeruk Kel. Tlg Keramat Kec. Tlg Klp 10.000.000 10.000.000 - 100,00
- Pembangunan Musholla Al-Ikhlas Jl. Rimba Asam Dsn. III Kenten Laut Kec. Tlg Klp 7.500.000 7.500.000 - 100,00
- Pembangunan Musholla Al-Badar Perum Kenten Azhar Permai Kec. Tlg Klp 10.000.000 10.000.000 - 100,00
- Pembangunan Musholla Nurul Hidayah Pemukiman HKTI Talang Keramat Kec. 10.000.000 10.000.000 - 100,00
- Pembangunan Musholla Aisyatun Amalia Kel. Tlg Keramat Kec. Tlg Kelapa 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Ash-Shaff Perumahan Puspasari Kel. Kenten Kec. 10.000.000 10.000.000 - 100,00
- Pembangunan Masjid Al-Azhar Komp. Azhar III Kel. Kenten Kec. Talang Kelapa (*R33) 15.000.000 15.000.000 - 100,00
- Pembangunan Masjid Al-Muhajirin Komp. Azhar Permai Lahan III Kel. Kenten Kec. 5.000.000 5.000.000 - 100,00
Halaman 23 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Musholla Amron Rasyid Kenten Azhar Permai Kec. Talang Kelapa 7.500.000 7.500.000 - 100,00
- Pembangunan Musholla Al-Mardiah Perumahan Griya Arisma Azhar Kenten Laut 7.500.000 - 7.500.000 -
- Pembangunan Langgar Nurul Mukmin Kel. Kenten Kec. Tlg Kelapa 7.500.000 7.500.000 - 100,00
- Masjid Assyfah Jl. Masjid Rt 11 Desa Gasing Kec. Talang Kelapa (PR12) 50.000.000 - 50.000.000 -
Halaman 24 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Musholla Al-Ikhlas Desa Mulya Sari Kec. Tanjung Lago. 7.500.000 - 7.500.000 -
- Pembangunan Musholla Al-Ikhlas Desa Muara Sugih Kec. Tanjung Lago. 7.500.000 - 7.500.000 -
- Pembangunan Musholla Al-Choirun Desa Telang Sari Kec. Tanjung Lago. 7.500.000 - 7.500.000 -
Halaman 25 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Rahab. Masjid Al-Mukmin Desa Bumi Serdang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Fatah Desa Teluk Tenggulang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Ikhlas Desa Teluk Tenggulang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Huda Desa Teluk Tenggulang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Iman Desa Teluk Tenggulang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Darus Salam Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Babus Salam Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Iman 1 Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Iman II Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid As-Sholihin Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Muttaqin I Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Muttaqin II Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Muhajirin Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Hidayah Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Taqwa Desa Keluang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Hijran Desa Keluang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Miftahul Jannah Desa Keluang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Hidayah Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Iman Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid At-Taqwa I Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid At-Taqwa II Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Amal Bakti Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Darus Salam Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Muttaqin Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Barokah Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Nurul Huda Desa marga Rahayu Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Muhajirin Desa Marga Rahayu Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid At-Taqwa Desa Marga Rahayu Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Baitus Solehah Desa Marga Rahayu Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rahab. Masjid Al-Hidayah Desa Marga Rahayu Kec.Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Pure Bumi Asih Desa Teluk Tenggulang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Pure Bumi Asih Desa bumi Serdang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Pure Waha Linggga Amerta Ds Karang Asem Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
Halaman 26 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pembangunan Gereja GBI Desa Suka Jaya Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Gereja GKKI Desa Suka Raja Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Gereja Panti Kosta Desa Marga Rahayu Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Gereja Tri Tunggal Desa Bentayan Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Rehab. Masjid Al-Hidayah II Desa Keluang KecamatanTungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Hijrah Desa Keluang Kec. Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Pembangunan Masjid Al-Hidayah Desa Bumi Serdang Kec. Tungkal Ilir (*R21). 15.000.000 - 15.000.000 -
- Pembangunan Musholla Miftahul Huda Desa Suka Mulya Kec. Tungkal Ilir (*R21). 7.500.000 - 7.500.000 -
- Masjid Baitul Muttaqin Desa Panca Mulya Kec. Tungkal Ilir (*R21). 10.000.000 - 10.000.000 -
- Masjid Baitul Mukarromah Desa Karang mulya Rt 13 Kec. Tungkal Ilir (PR15). 10.000.000 - 10.000.000 -
Halaman 27 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- PP Darul Ulum Ds. Sumber Mulyo Kec. Pulau Rimau. 25.000.000 25.000.000 - 100,00
- PP Darul Muthaqin Ds. Dana Mulya Kec. Pulau Rimau. 25.000.000 25.000.000 - 100,00
- PP Hidayatullah Ds. Tanjung Marbu Kec. Rambutan. 25.000.000 25.000.000 - 100,00
- PP Inayatullah Jln. Tanjung Api-api Gasing Kec. Talang Kelapa. 45.000.000 45.000.000 - 100,00
- PP Hidayatullah Jln. Simpang PU No. 230 Kenten Laut Kec. Talang Kelapa. 25.000.000 25.000.000 - 100,00
- PP Nurul Muhajirin Tanjung Api-api Ds. Sukatani Kecamatan Tanjung Lago.Lago. 25.000.000 25.000.000 - 100,00
- PP Bachlul Ulum Tanjunga Api-api Ds. Muliasari Kecamatan Tanjung Lago. 25.000.000 25.000.000 - 100,00
- PP Hidayatul Muhtadin Ds. Sido Mulyo Kec. Tungkal Ilir. + (*R21). 30.000.000 25.000.000 5.000.000 83,33
- PP Nurul Wathan Ds. Muara Sungsang Kec. Banyuasin II. 20.000.000 20.000.000 - 100,00
- Yayasan Pondok Pesantren Al Muhibbin jalan Perumnas Anugrah Kel. Rimba Asam 80.000.000 - 80.000.000 -
- Pondok Pesantren Miftahul Jannah Desa Karang Sari Primer 10 Kec. BA II (PR16) 20.000.000 - 20.000.000 -
- Pondok Pesantren Bahrul Ulum Kec. Tanjung Lago (PR30) 360.000.000 - 360.000.000 -
- Pondok Pesantren Desa Margo Mulyo Kec. Muara Sugihan (PR33) 5.000.000 - 5.000.000 -
Halaman 28 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Masjid di Kecamatan Tanjung Lago. 10.000.000 10.000.000 - 100,00
- Masjid di Kecamatan Tungkal Ilir. 10.000.000 10.000.000 - 100,00
Halaman 29 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Majelis Tak'lim Hidayatul Mutakin Desa Majatra Kecamatan Pulau Rimau (*R6) 5.000.000 5.000.000 - 100,00
- Majelis Tak'lim Al-Hidayah Desa Sumber Rejo Kecamatan Pulau Rimau (*R6) 5.000.000 - 5.000.000 -
- Majelis Tak'lim Jami'ah Istiqomah Desa Suka Karya Kecamatan Tungkal Ilir (*R6) 5.000.000 5.000.000 - 100,00
- Majelis Tak'lim Al-Husna Desa Teluk Betung Kecamatan Pulau Rimau (*R6) 5.000.000 5.000.000 - 100,00
- Majelis Tak'lim Mijatul Jannah Desa Singo Makmur Kec. Pulau Rimau (*R6) 5.000.000 5.000.000 - 100,00
- Majelis Tak'lim Al-Hikmah Desa Bumi Rejo Kec. Pulau Rimau (*R6) 5.000.000 5.000.000 - 100,00
- Majelis Tak'lim ...................................... Desa Bumi Rejo Kec. Pulau Rimau (*R6) 5.000.000 - 5.000.000 -
- Majelis Tak'lim ...................................... Desa Kelapa Dua Kec. Pulau Rimau (*R6) 5.000.000 - 5.000.000 -
- Bantuan Speed Boat untuk P3N Desa Srijaya Kecamatan Banyuasin III (*R31). 50.000.000 - 50.000.000 -
- Pembinaan Majelis Taklim Al-Hidayah Kec. Sembawa (*R35). 40.000.000 40.000.000 - 100,00
- Bantuan Speed Boat untuk P3N Desa Teluk Tenggirik Kecamatan Banyuasin I (*R30). 50.000.000 - 50.000.000 -
Dewan Pengurus Daerah Forum Pondok Pesantren (DPD Forpes) Kab. BA /POSPEDA 241.350.000 241.350.000 - 100,00
- Panpel PHBI dan Perlombaan Al-Barzanji Desa Plajau Kec. Banyuasin III. 10.000.000 - 10.000.000 -
- Majlis Manaqib Syeh Abdul Qodir Jaelani R. A Desa Sidomulyo Air Kumbang. 15.000.000 - 15.000.000 -
- Bantuan Alat Rehab dan Busana Muslim Pengajian Akbar Desa Ujung Tanjung Kec. BA III. 10.750.000 10.750.000 - 100,00
- TPA Al-Hidayah Desa Pendowoharjo Kec. Makarti Jaya 5.000.000 - 5.000.000 -
- Pesekutuan Pemuda/i Gereja Kristen Al-Kitab Indonesia (GKAI) Desa Daya Utama 5.000.000 5.000.000 - 100,00
- Pengajian Akbar se-Kecamatan Talang kelapa di Lapangan Sepakbola Sukamoro 10.000.000 - 10.000.000 -
- Biaya Percetakan Buku Fiqhul Islam Jilid II dari KH. Balian 50.000.000 50.000.000 - 100,00
- Pengurus Amal Kematian/ PAK Jl. Guru Harun Kel. Tanah Mas Kec. Talang Kelapa 5.000.000 - 5.000.000 -
- Badan Kontak Majlis Taklim Jl. Jalur 8 Telang Jaya Kec. Muara Telang 5.000.000 - 5.000.000 -
- Bantan Dana Musik Gambus Al-Hikmah KM. 69 Kec. Betung 5.000.000 - 5.000.000 -
- Pembuatan tenda untuk kematian Rt 14 dan 15 Dusun Jatimulyo Desa Bukit Kec. Bukit 5.000.000 - 5.000.000 -
- TPA Musholla Nurul Hidayah Desa Pendowo Harjo Kec. Makarti jaya 5.000.000 - 5.000.000 -
- TPA Dusun Bantul Sari Desa Sumber Jaya Kec. Sumber Marga Telang 5.000.000 - 5.000.000 -
- TPA Masjid Al-Anshor Anwar Syarif Perumahan Azhar Permai Kel. Kenten Kec. Talang Kelapa 10.000.000 - 10.000.000 -
- Kelompok Pengajian Majelis Taklim Ibu2 Ds Mainan Kec. Sembawa (PR25)/Nurul Islam 5.000.000 5.000.000 - 100,00
- Kelompok Pengajian Majelis Taklim Ibu-ibu Pulau harapan Kec. Sembawa (PR25) 5.000.000 - 5.000.000 -
- Badan Komunikasi Majelis Taklim BKMT Desa Sungai Rebo Kec. BA I 5.000.000 5.000.000 - 100,00
Halaman 30 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
Pembinaan Bidang Keagamaan 105.000.000 80.000.000 25.000.000 76,19
- Bant Panpel Maulid Nabi M SAW Masjid Jami' Nurul Huda DS Tirtosari Kec. BA I. 10.000.000 10.000.000 - 100,00
- Bant Panpel Maulid Nabi M SWA Ponpes Nurul Wathan Desa Muara Sungsang Kec. BA II. 7.500.000 7.500.000 - 100,00
- Bant Panpel Maulid Nabi M SWA Masjid Jami'atul Rahma Ds Sungsang I Kec. BA II. 15.000.000 15.000.000 - 100,00
- Hibah Majelis Taklim Ibu-ibu Kel. Rimba Asam Kec. Betung 40.000.000 40.000.000 - 100,00
- Pengajian Akbar Majelis Ta'lim Ibu-ibu se-Kecamatan Betung. 7.500.000 7.500.000 - 100,00
- Pengajian Akbar Majelis Taqlim Ibu-ibu Al-Muttaqin Ds. Durian Daun Kec. Suak tapeh 5.000.000 - 5.000.000 -
- Bantuan Panpel Maulid Nabi Muhammad SAW Ponpes Al-Hikmah Kel. Betung Kec. Betung 5.000.000 - 5.000.000 -
- Kelompok Amal Kematian Ikhlas Beramal Dusun IV Desa Lebung Kec. Rantau Bayur (PR17) 15.000.000 - 15.000.000 -
Hibah Kepada Kepada Kelompok Masyarakat dengan Kegiatan Bidang Kesenian 1.088.550.000 248.600.000 839.950.000 22,84
Hibah Bidang Kesenian. 1.088.550.000 248.600.000 839.950.000 22,84
- Panpel Gebyar Festival Band Kab. Banyuasin. 5.000.000 - 5.000.000 -
- Bantuan dana kegiatan Pagelaran Kesenian Kuda Lumping Kec. Tl Kelapa & Sembawa. 35.000.000 35.000.000 - 100,00
- Group Kesenian Kuda Lumping Setia Budaya Desa Wonosari Kec. Kec. Pulau Rimau (*R6). 10.000.000 10.000.000 - 100,00
- Group Kesenian Kuda Lumping Umi Serdang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Group Kesenian Jaranan Desa Teluk Tenggulang Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Group Kesenian Jaran Kepang Desa Sido Mulyo Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Group Kesenian Hadros Assaroya Desa Sido Mulyo Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Group Kesenian Campur Sari Al-Quroba Desa Suka Raja Kec.Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Paguyuban Seni Reog se Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Paguyuban Seni Sari Laras Desa Suka Mulya Kecamatan Tungkal Ilir (*R21). 5.000.000 - 5.000.000 -
- Group Kesenian Kuda Lumping "Mulyo Tenggoro" Musi Landas Ds II Ds Mainan Kec. Sembawa (*R26).
20.000.000 20.000.000 - 100,00
- Group Kesenian Kuda Lumping Taruno Sido Rukun Ds. Srimulyo Kec. Air Saleh (*R34). 15.000.000 - 15.000.000 -
- Group Kesenian Kuda Lumping Tri Rahayu Ds. Srimulyo Kec. Air Saleh (*R34). 5.000.000 - 5.000.000 -
- Group Kesenian Kuda Lumping Turonggo Ds. Salek Mukti Kec. Air Saleh (*R34). 10.000.000 - 10.000.000 -
- Group Kesenian Kuda Lumping Cahaya Muda Ds. Damarwulan Kec. Air Saleh (*R34). 10.000.000 - 10.000.000 -
- Kelompok Kesenian Kuda Lumping Sido Utomo Ds Sumber Mulya Kec. Air Saleh (*R34). 15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Eko Budoyo Ds. Sumber Mulya Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Ponco Budoyo Desa Panca Mukti Kec. M.Telang (*R39). 15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Tunggal Wuluh Ds Panca Mukti Kec. M.Telang (*R39). 15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Turonggo Cipto Desa Panca Mukti Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
Halaman 31 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Kelompok Kesenian Kuda Lumping Wahyu Budoyo Ds Sumber Hidup Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Turonggo Siswo Budoyo Ds. Sumber Hidup Kec. M. Telang (*R39).
15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Turonggo Mudo Ds Telang Makmur Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Turonggo Budoyo Ds Mukti Jaya Kec. M. Telang (*R39). 15.000.000 15.000.000 - 100,00
- Group Kesenian Tarling Desa Sumber Mukti Kec. Pulau Rimau (*R44). 5.000.000 - 5.000.000 -
- Group Kesenian Reok Desa Sumber Mukti Kecamatan Pulau Rimau (*R44). 10.000.000 10.000.000 - 100,00
- Group Kesenian Kuda Lumping Desa Sumber Mukti Kecamatan Pulau Rimau (*R44). 5.000.000 - 5.000.000 -
- Jaranan Campur Sari "Kencono Mukti" Desa KP Permata Kec. Air Kumbang. 8.100.000 - 8.100.000 -
- Group Qasidah Al-Hikmah Pangkalan Balai Kec. BA III. 3.600.000 3.600.000 - 100,00
- Sanggar Nerds dalam Rangka Kegiatan Pekan Kreasi Karya Sumsel Gemilang 3.150.000 - 3.150.000 -
- Kuda Lumping "Campur Sari" Desa Sumber Jaya Kec. Sumber Marga Telang 15.000.000 - 15.000.000 -
- Group Majelis Taklim Al-Ikhwan Rt 04 Mariana ilir Kec. BA I 3.700.000 - 3.700.000 -
- Group Rebana (Ledy) (Grup Rebana Darma Karya) 15.000.000 15.000.000 - 100,00
- Forum Paguyuban Kesenian (Kelompok Kesenian) Kec. Tanjung Lago (PR7) 50.000.000 - 50.000.000 -
- Kelompok Kesenian Tunas Muda Desa Lubuk Karet Kec. Betung (PR19) 100.000.000 - 100.000.000 -
- Group Band D'Orion's BA (PR23) 40.000.000 - 40.000.000 -
- Ikatan Pemuda Karya (Alat Kesenian) (PR42) 175.000.000 - 175.000.000 -
- Kesenian Kuda Lumping Turonggo Mudo Desa Telang Jaya Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Kesenian Bali Desa Mukti Jaya Jalur 10 Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Kesenian Kuda Lumping Wahyu Budoyo Desa Telang Rejo Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Kesenian Kuda Lumping Krido Budoyo Jlr III Jmbtn I Dsn III Blok E Ds Sumber Jaya (PR16) 10.000.000 - 10.000.000 -
- Kesenian Kuda Lumping Tunggul Wulung Desa Panca Mukti Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Kesenian Kuda Lumping Desa Telang Makmur Kec. Muara Telang (PR16) 10.000.000 - 10.000.000 -
- Kesenian Kuda Lumping Desa Telang Makmur RT 19 RW 8 Dusun IV Kec. Muara Telang (PR14) 10.000.000 - 10.000.000 -
- Kelompok Kuda Lumping Desa Enggal Rejo Kec. Air Saleh (PR33) 5.000.000 - 5.000.000 -
- Kesenian Kuda Lumping Desa Salek Jaya Kec. Air Saleh (PR33) 10.000.000 - 10.000.000 -
- Kelompok Kesenian Kelurahan Makarti Jaya Kec. Makarti Jaya (PR11) 100.000.000 - 100.000.000 -
- Kelompok Kesenian Kuda Lumping Krido Budaya Timbul Desa Tirta Kencana Kec. Makarti jaya 5.000.000 - 5.000.000 -
- Kelompok Kesenian Kuda Lumping Paguyuban Jaranan Kreasi Turonggo Dwipo Budoyo 5.000.000 - 5.000.000 -
- Kelompok Kesenian Kuda Lumping Bangun Trisno Desa Tirta Kencana Kec. Makarti 5.000.000 - 5.000.000 -
- Kelompok Kesenian Kuda Lumping Desa Sumber Hidup Kec. Muara Telang (PR34) 5.000.000 - 5.000.000 -
- Kelompok Kesenian Kuda Lumping Desa Telag Karya Kec. Muara Telang (PR34) 5.000.000 - 5.000.000 -
- Kelompok Kesenian Bali Panca Mukti Kec. Muara Telang (PR34) 10.000.000 - 10.000.000 -
Halaman 32 dari 33
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Kelompok Kesenian Campur Sari Desa Sumber Rezeki Kec. BA II (PR34) 10.000.000 - 10.000.000 -
- Kelompok Kesenian Reog Ponorogo Desa Sriagung Kec. BA II (PR34) 10.000.000 - 10.000.000 -
- Komunitas Pemuda Band Indie Tungkal Ilir (KOPBITI) 10.000.000 - 10.000.000 -
- Kelompok Kesenian Kuda Lumping Turonggo Putro desa Lalang sembawa Kec. Sembawa (PR25) 5.000.000 - 5.000.000 -
- Kelompok Kesenian Wayang Kulit Hesti Budaya Desa Cintamanis Baru Kec. Air Kumbang 20.000.000 20.000.000 - 100,00
- Kelompok Kesenian Kuda Lumping Turonggo Krido Campur Aduk Kel. Air Batu 7.500.000 - 7.500.000 -
- Kelompok Kesenian Kuda LumpingTuronggo Krido Makmur Kel. Air Batu 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo Rista Budoyo Kel. Air Batu 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Rowo Kidul Kel. Air Batu Kec. Talang kelapa 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo seto Kel. Air Batu Kec. Talang Klp 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo sejati Kel. Air Batu Kec. Talang Klp 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo Budoyo Kel. Air Batu Kec. Talang Klp 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo Kel. Air Batu Kec. Talang Kelapa 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Tejo Asmoro Kel. Sukamoro Kec. Talang Kelapa 7.500.000 - 7.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo Rama Putro Kel. Sukamoro 7.500.000 - 7.500.000 -
- Kelompok Kesenian Kuda Lumping Laku Bugomudo Lestari Kel. Sukamoro 7.500.000 - 7.500.000 -
- Kelompok Kesenian Kuda Lumping Taruno Budoyo Desa talang Buluh 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Turonggo Cipto Budoyo Desa Talang buluh 5.500.000 - 5.500.000 -
- Kelompok Kesenian Kuda Lumping Srimudo Tunggal Sejati Desa Talang buluh 7.500.000 - 7.500.000 -
- Kelompok Kesenian Kuda Lumping Ngudi Rahayu Kel. Sukajadi Kec. Talang Klp 6.500.000 - 6.500.000 -
- Kelompok Kesenian Kuda Lumping Pandawa Jati Kel. Sukajadi Kec. Talang Klp 6.500.000 - 6.500.000 -
Belanja Hibah Kpd Kel Masy dgn keg Bid. Keolahragaan Non Profesional 145.000.000 135.000.000 10.000.000 93,10
Bidang Olah Raga 145.000.000 135.000.000 10.000.000 93,10
- Klub Bola Kaki Harapan jaya Desa Pulau Harapan Kec. Sembawa (PR17) 5.000.000 - 5.000.000 -
- Klub Bulu Tangkis Smash Agung Desa Tanjung agung 5.000.000 - 5.000.000 -
- Klub Sepak Bola Reno Vega Desa Sidomulyo Kec. Air kumbang 15.000.000 15.000.000 - 100,00
- Panitia Banyuasin Motor Comunity (Grass Track Open 2013) 60.000.000 60.000.000 - 100,00
- Banyuasin Racing Team 60.000.000 60.000.000 - 100,00
Halaman 33 dari 33
RINCIAN BELANJA BANSOS TAHUN 2013 LAMPIRAN : 2
1 2 3 4 5
Belanja Bantuan Sosial Kpd Kelompok Masyarakat dan/Masyarakat 4.104.000.000 3.937.700.000 166.300.000 95,95
Belanja Bansos kpd Kel. Masyarakat/Masyarakat dgn tujuan Rehabilitasi Sosial. 163.000.000 158.000.000 5.000.000 96,93
Bansos kpd Kel. Masyarakat/Masyarakat dgn tujuan Rehabilitasi Sosial. 163.000.000 158.000.000 5.000.000 96,93
- Persatuan Amal Kematian (PAK) Al-Azhar Perum Azhar Baru Kel. Kenten Kec. Tl Kelapa. 5.000.000 5.000.000 - 100,00
- Bantuan Korban Bencana Kebakaran di wilayah Kab. Banyuasin (an. TJ cs) 35.000.000 35.000.000 - 100,00
- Persatuan Amal Kematian (PAKAM) Al-Hikmah Desa Petaling Kec. BA III 5.000.000 5.000.000 - 100,00
- Bantuan uang Duka Korban Bencana Alam dalam wilayah Kab. Banyuasin 29.000.000 29.000.000 - 100,00
- Bantuan biaya santunan untuk korban bencana kebakaran dan rumah roboh 62.000.000 62.000.000 - 100,00
(a.n. Sbn dkk) - -
- Bantuan biaya santunan untuk korban bencana rumah roboh akibat angin puting 17.000.000 17.000.000 - 100,00
beliung , kebakaran dan kecelakaan di laut - -
- Bantuan biaya santunan untuk korban bencana kebakaran a.n. Srn 5.000.000 5.000.000 - 100,00
- Bantuan persatuan Amal Kematian Al-Ikhlas Jl. Pangeran Ayin Kel. Kenten 5.000.000 - 5.000.000 -
Kec. Talang Kelapa
Belanja Bansos kpd Kel. Masyarakat/Masyarakat dgn tujuan Pemberdayaan Sosial. 1.941.000.000 1.792.500.000 148.500.000 92,35
Bansos kpd Kel. Masyarakat/Masyarakat dgn tujuan Pemberdayaan Sosial. 1.893.500.000 1.745.000.000 148.500.000 92,16
- Sharing PNPM 1.869.000.000 1.740.000.000 129.000.000 93,10
- Kecamatan Sembawa
- Kecamatan Rambutan
Halaman 1 dari 6
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Kecamatan Makarti Jaya
- Kecamatan Banyuasin III
- Kecamatan Rantau Bayur
- Kecamatan Banyuasin I
- Kecamatan Suak Tapeh
- Kecamatan Banyuasin II
- Kecamatan Pulau Rimau
- Kecamatan Muara Padang
- Kecamatan Muara Telang
- Kecamatan Talang Kelapa
- Peringatan Nuzulul Qur'an Masjid Nurul Ikhsan Ds. I Desa Taja Indah Kec. Betung. 2.000.000 - 2.000.000 -
- Kelompok Pengajian Baiturrahman Kel. Kedondong Raye Kec. Banyuasin III. 2.500.000 - 2.500.000 -
- Panitia Pelaksana Tausiyah dan Dialog Ramadahan Yayasan Tarbiyah Kab. BA. 2.500.000 - 2.500.000 -
- Gebyar Maulid Nabi M SAW TK/TPA Unit 117 Jami'atul Khair Kel. Sukajadi Kec. Tl Kelapa. 5.000.000 2.500.000 2.500.000 50,00
- Pembuatan Jalur2 Hijau & Bendungan oleh Himp. Klrg Petani Banyuasin (HKTNBA) 2.500.000 2.500.000 - 100,00
- Pengajian akbar ibu-ibu se-Kecamatan BA III di masjid As-Sobar Desa Lubuk 2.500.000 - 2.500.000 -
Saung Kec. BA III
- Panpel peringatan Maulid Nabi Muhammad SAW Masjid Nurul Islam desa 2.500.000 - 2.500.000 -
beringin Kec. BA III
- Panpel peringatan Maulid Nabi Muhammad SAW Masjid Nurul Iman desa 2.500.000 - 2.500.000 -
Terentang Kec. BA III
- Panpel peringatan Isro' Mi'raj Jamiyyah Yasin dan Tahlil Asy-syafaah desa 2.500.000 - 2.500.000 -
Tanjung Menang Kec. Rantau Bayur Terentang Kec. BA III
Halaman 2 dari 6
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Pengajian Ibu-ibu Masjid Al-Muttaqin Ds. Muara Baru Kec. Makarti Jaya (Darul Hijroh) 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Kecamatan Muara Padang. (Masjid Sabilunajjah) 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Kecamatan Muara Sugihan (Masjid Baitul Muttaqin) 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Al Muhajirin Ds. Telang jaya Kec. M. Telang (Jami Fathul Jannah) 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Al-Hilal Ds.Penuguan Kec. Pulau Rimau 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Kecamatan Rambutan. (Baiturohim) 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Nurul Huda Ds. Tanjung Menang Kecamatan Rantau Bayur. 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Al-Jihad ds.Muara Damai Kec. Sembawa 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid At-Taqwa Ds. Rimba Terab Kec. Suak tapeh 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Baiturrohim Ds. Sumber jaya Kec. Sumber Marga Telang 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Hidayatullah Kel. Tanah Mas Kec. Talang Kelapa 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Nurul Anwar D. Mulia Sari Kec. Tanjung lago 2.500.000 2.500.000 - 100,00
- Pengajian Ibu-ibu Masjid Al-Ikhlas Ds. Teluk Tenggulang Kec. Tungkal Ilir 2.500.000 2.500.000 - 100,00
Belanja Bansos kpd Kel. Masyarakat/Masyarakat dgn tujuan Jaminan Sosial. 2.000.000.000 1.987.200.000 12.800.000 99,36
Bansos kpd Kel. Masyarakat/Masyarakat dgn tujuan Jaminan Sosial. 2.000.000.000 1.987.200.000 12.800.000 99,36
- Ustadz/Ustazah/Guru TK/TPA 1.200.000.000 1.200.000.000 - 100,00
- P3N 700.000.000 687.600.000 12.400.000 98,23
- LVRI 100.000.000 99.600.000 400.000 99,60
Belanja Bantuan Sosial Kpd Anggota Masyarakat 328.500.000 303.000.000 25.500.000 92,24
Belanja Bantuan Sosial kpd Anggota Masyarakat dgn tujuan Jaminan Sosial. 328.500.000 303.000.000 25.500.000 92,24
Bantuan Sosial kpd Anggota Masyarakat dgn tujuan Jaminan Sosial. 233.500.000 208.000.000 25.500.000 89,08
- Biaya Pendidikan S2 a.n. KI (IAIN Raden Fatah Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. Pn (Stisipol Candradimuka Palembang). 1.000.000 - 1.000.000 -
- Biaya Pendidikan S2 a.n. RAP (IAIN Raden Fatah Palembang). 1.500.000 1.500.000 - 100,00
- Biaya Pendidikan D2 a.n. MA (UPBJJ - UT Plg). 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. ME (IAIN Raden Fatah Plg). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. HA (STIHPADA Palembang). 1.000.000 1.000.000 - 100,00
- Biaya Pendidikan s1 a.n. MT (PTIQ Jkt). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. AS (UIN Syarif Hidayatullah Jakarta. 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan D.IV a.n. ML (Univ. Kader Bangsa Plg). 2.000.000 2.000.000 - 100,00
Halaman 3 dari 6
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Biaya Pendidikan S1 a.n. Nb (Univ. PGRI Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S2 a.n. DPS (IAIN Raden Fatah Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S2 a.n. YE (IAIN Raden Fatah Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan D.III a.n. RA (Akademi Kesehatan Lingkungan Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. HG (STIM AMKOP Plg) 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. EOR (STISIPOL Candradimuka Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. MAh (Univ. Tridinanti Palembang. 5.000.000 5.000.000 - 100,00
- Biaya Pendidikan S1 a.n. Kn (STIPADA Palembang). 2.500.000 2.500.000 - 100,00
- Biaya Pengobatan a.n. RJ (Istri Anggota LVRI Bpk. AMj). 10.000.000 10.000.000 - 100,00
- Biaya Pendidikan S1 a.n. NPy (Univ. Tridinanti Plg). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. Syf (STISIPOL Plg). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. EM ( Univ. Indo Global Mandiri Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. MR (Sekolah Tinggi Satya Negara Palembang). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. Sy (IAIN Raden Fatah Plg.) 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. AWy (IAIN Raden Fatah Plg). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. AB (UNSRI Indralaya). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. IAA (Stiper SRIWIGAMA Palembang). 2.500.000 2.500.000 - 100,00
- Biaya Pengobatan a.n. ARP Bin Waluyo. 7.500.000 7.500.000 - 100,00
- Biaya Pendidikan S1 a.n. MM (STIM-AMKOP Plg). 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. AND (STIM-AMKOP Plg) 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. MF (STIM-AMKOP Plg) 2.000.000 2.000.000 - 100,00
- Biaya Pendidikan S1 a.n. NPt (FKIP PGRI Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. Ro (Universitas sriwijaya palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan D3 a.n. GS (Sekolah Tinggi Ilmu Kesehatan Yayasan 2.000.000 2.000.000 - 100,00
Siti Khodijah Palembang)
- Biaya Pendidikan S1 a.n. SH (IAIN Raden Fatah Palembang) 2.500.000 - 2.500.000 -
- Biaya Pendidikan S1 a.n. NAM (IAIN Raden fatah Plg) 5.000.000 5.000.000 - 100,00
- Biaya Pendidikan S1 a.n. IP (IAIN raden fatah Plg) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan D3 a.n. OSR (Institut Pertanian bogor) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. Sw (IAIN raden fatah palembang) 5.000.000 5.000.000 - 100,00
- Biaya Pendidikan S1 a.n. RW (STIM-AMKOP Plg) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. JA (Stisipol Candradimuka Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. KM (STAI Shalahudin Al-Ayyubi 2.500.000 2.500.000 - 100,00
jakarta Cabang Ponpes An-Nur Lempuing OKI)
Halaman 4 dari 6
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Biaya Pendidikan a.n. AMd (Akademi kebidanan Nusantara palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S2 a.n. Lf (Universitas Sriwijaya) 2.500.000 - 2.500.000 -
- Biaya Pendidikan S1 a.n. RAJ (Universitas Muhammadiyah Palembang) 2.500.000 - 2.500.000 -
- Biaya Pendidikan S1 a.n. SN (STAI DarulKalam Tangerang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. St (Universitas Terbuka) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. MAp (STISIPOL CHANDRADIMUKA Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. Z (IAIN Raden fatah palembang) 2.500.000 - 2.500.000 -
- Biaya Pendidikan D3 a.n. OR (IAIN Raden Fatah palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. HSP (Stisipol Candradimuka Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S2 a.n. WA (Universitas Utara Malaysia) 7.500.000 - 7.500.000 -
- Biaya Pendidikan a.n. Spy (STIM Amkop Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. AWd (STISIPOL CANDRADIMUKA Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. JH (STISIPOL Candradimuka Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. MH (STISIPOL Candradimuka Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. Nd (STIM AMKOP Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. Jld (STISIPOL Candradimuka Palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. SH (IAIN Raden Fatah palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. Is (STIHPADA Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. EAO (STHIPADA Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. HW (Universitas PGRI Palembang) 2.500.000 - 2.500.000 -
- Biaya Pendidikan a.n. UH (STIK Siti Khadijah Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. AR (STHIPADA Palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. MRs (Institut Pertanian Bogor) 2.500.000 - 2.500.000 -
- Biaya Pendidikan a.n. Rm (STIM AMKOP Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan a.n. Bd, S.Pd (Universitas Sriwijaya Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S2 a.n. WP (Universitas sriwijaya palembang) 5.000.000 5.000.000 - 100,00
- Biaya Pendidikan a.n. MZ (IAIN Raden Fatah Palembang) 5.000.000 5.000.000 - 100,00
- Biaya Pendidikan a.n. IJ (IAIN Raden Fatah Palembang) 5.000.000 5.000.000 - 100,00
- Biaya Pendidikan a.n. AWb (Akademi Farmasi Harapan palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. Alf (Universitas Tridinanti Palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. MI (Universitas Stisipol Candradimuka Palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. MP (Universitas Indo Global Mandiri Palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. OT (Universitas PGRI palembang) 3.000.000 3.000.000 - 100,00
- Biaya Pendidikan a.n. KA (Universitas Muhammadiyah Palembang) 3.000.000 3.000.000 - 100,00
Halaman 5 dari 6
Uraian Jumlah Anggaran Realisasi Sisa %
1 2 3 4 5
- Biaya Pendidikan a.n. NIN (Universitas Muhammadiyah Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. SP (Universitas Muhammadiyah Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. AL (STIA Satya Negara Palembang) 2.500.000 2.500.000 - 100,00
- Biaya Pendidikan S1 a.n. Spr (STIE Abdi Nusa Palembang) 1.500.000 1.500.000 - 100,00
- Biaya Pendidikan S1 a.n. RFV (Universitas PGRI Palembang) 1.500.000 1.500.000 - 100,00
- Biaya Berobat a.n. EAh (Kades Pelajau Kec. BA III) 11.000.000 11.000.000 - 100,00
- Tambahan Modal Usaha a.n. NF (Kel. Kedondong Raye Kec. BA III) 2.000.000 - 2.000.000 -
Belanja Bansos kpd Anggota Masyarakat dgn tujuan Jamsos pd Keg. Safari Ramadhan 95.000.000 95.000.000 - 100,00
- Bansos Kpd Angt Masy. Dg tujuan Jamsos kpd Anak Yatim Piatu di 19 Kec @5.000.000 95.000.000 95.000.000 - 100,00
Halaman 6 dari 6
LAMPIRAN : 3
DAFTAR BELANJA MODAL YANG MENJADI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
A. TANAH
TANAH
No SKPD BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
Halaman 1 dari 7
DAFTAR BELANJA MODAL YANG MENJADI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
B. PERALATAN DAN MESIN
PERALATAN DAN MESIN
No SKPD BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
Halaman 2 dari 7
DAFTAR BELANJA MODAL YANG MENJADI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
C. GEDUNG DAN BANGUNAN
GEDUNG DAN BANGUNAN
No SKPD BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
Halaman 3 dari 7
DAFTAR BELANJA MODAL YANG MENJADI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
D. JALAN, JARINGAN DAN IRIGASI
JALAN, JARINGAN DAN IRIGASI
No SKPD BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
Halaman 4 dari 7
DAFTAR BELANJA MODAL YANG MENJADI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
E. ASET TETAP LAINNYA
ASET TETAP LAINNYA
No SKPD BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
Halaman 5 dari 7
DAFTAR BELANJA MODAL YANG MENJADI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
F. KONSTRUKSI DALAM PEKERJAAN
KONSTRUKSI DALAM PENGERJAAN
No SKPD BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
1 DIKNAS - -
2 KESEHATAN - -
3 RSUD - -
4 PUCK - -
5 PUBM - -
6 PU AIR - -
7 BAPPEDA DAN PM - -
8 DISHUB - -
9 BLH - -
10 KEBERSIHAN - -
11 CAPIL - -
12 BAPEL KB - -
13 DINSOS - -
14 DISNAKER - -
15 KOPERINDAG - -
16 KESBANG - -
17 SATPOL - -
18 SEKDA - -
19 SETWAN - -
20 INSPEKTORAT - -
21 DPPKAD - -
22 BKD - -
23 BPT - -
24 BAKETPAN - -
25 BPMPD - -
26 PERPUSTAKAAN - -
27 PERTANIAN - -
28 BP4K - -
29 DISHUTBUN - -
30 DISTAMBEN - -
31 PARIWISATA - 342.810.000,00 342.810.000,00
32 PERIKANAN - -
33 PASAR - -
34 TANJUNG LAGO - -
35 AIR SALEH - -
36 TUNGKAL ILIR - -
37 BANYUASIN I - -
38 MUARA SUGIHAN - -
39 BANYUASIN II - -
40 BANYUASIN III - -
41 BETUNG - -
42 MUARA TELANG - -
43 MUARA PADANG - -
44 MAKARTI JAYA - -
45 PULAU RIMAU - -
46 RAMBUTAN - -
47 RANTAU BAYUR - -
48 SUAK TAPEH - -
49 SEMBAWA - -
50 SUMBER MARGA TELANG - -
51 AIR KUMBANG - -
52 TALANG KELAPA - -
-
JUMLAH - - - - 342.810.000,00 - 342.810.000,00
Halaman 6 dari 7
total
No uraian BELANJA MODAL YANG TIDAK MENJADI ASSET BELANJA MODAL YANG MENJADI
BELANJA MODAL REKLAS TAMBAH REKLAS KURANG
HIBAH BARANG/JASA EXTRACOMTABLE ASSET
(1) (2) (3) (4) (5) (6) (7) (8) (9)=(3)-(4)-(5)-(6)+(7)-(8)
Halaman 7 dari 7
DAFTAR REKENING KAS DAERAH
LAMPIRAN : 4
Per 31 Desember 2013
NO. SALDO AKHIR
NO NAMA REKENING DEBIT KREDIT
REKENING 31/12/13
KAS DI BENDAHARA
SISA KAS TAHUN UYHD 2013 UYHD 2013 SISA BELUM
KODE SKPD PENGELUARAN PER
2013 DISETOR 2013 31 DESEMBER 2013
DISETOR 2014 SETOR
1 2 3 4 5 6 7 = 5-6
1.01.01 1.Dinas Pendidikan 6.255.895.573,00 522.299.266,00 5.733.596.307,00 5.733.596.307,00 -
1.02.01 2.Dinas Kesehatan 477.077.390,74 477.077.390,74 - - -
1.02.02 3.Rumah Sakit Umum Daerah (RSUD) Tipe D 44.011.461,43 44.011.461,43 - - -
1.03.01 4.Dinas Pekerjaan Umum Cipta Karya 32.703.370,00 18.703.702,00 13.999.668,00 13.999.668,00 -
1.03.02 5.Dinas Pekerjaan Umum Bina Marga 104.166.565,00 104.166.565,00 - - -
1.03.03 6.Dinas PU Pengairan 42.742.140,00 42.630.250,00 111.890,00 111.890,00 -
1.06.01 7.Badan Perencanaan Pembangunan Daerah dan Penanaman Modal 185.313.022,00 185.313.022,00 - - -
1.07.01 8.Dinas Perhubungan Komunikasi dan Informatika 11.946.819,00 11.946.819,00 - - -
1.08.01 9.Badan Lingkungan Hidup 166.423.785,00 166.423.785,00 - - -
1.08.02 10.Dinas Kebersihan, Pertamanan dan Pemakaman 49.417.976,00 49.417.976,00 - - -
1.10.01 11.Dinas Kependudukan dan Catatan Sipil 66.833.261,00 66.833.261,00 - - -
1.12.01 12.Badan Pemberdayaan Perempuan, Perlindungan Anak dan KB 133.700.129,00 133.700.129,00 - - -
1.13.01 13.Dinas Sosial 170.851.776,00 170.751.776,00 100.000,00 100.000,00 -
1.14.01 14.Dinas Tenaga Kerja dan Transmigrasi 5.826.235,00 5.826.235,00 - - -
1.15.01 15.Dinas Koperasi, Usaha Kecil Menengah, Perindustrian dan Perdagangan 131.410.651,00 131.410.651,00 - - -
1.19.01 16.Badan Kesatuan Bangsa dan Politik 1.964.080.366,00 1.963.155.366,00 925.000,00 925.000,00 -
1.19.02 17.Satuan Polisi Pamong Praja 36.493.831,00 36.493.831,00 - - -
1.20.01 18.Dewan Perwakilan Rakyat - - - - -
1.20.02 19.Bupati dan Wakil Bupati - - - - -
1.20.03 20.Sekretariat Daerah 1.710.469.984,00 1.710.469.984,00 - - -
1.20.04 21.Sekretariat DPRD 1.372.752.888,00 1.262.684.588,00 110.068.300,00 110.068.300,00 -
1.20.05 22.Inspektorat Kabupaten 521.280.398,00 521.280.398,00 - - -
1.20.07 23.Badan Kepegawaian dan Diklat Daerah 534.288.848,00 534.288.848,00 - - -
1.20.08 24.Badan Perizinan Terpadu 11.100.198,00 11.100.198,00 - - -
1.20.09 25.Dinas Pendapatan, Pengelolaan Keuangan dan Aset Daerah 927.225.629,00 809.925.707,00 117.299.922,00 117.299.922,00 -
1.20.09 25.Dinas Pendapatan, Pengelolaan Keuangan dan Aset Daerah (PPKD) 490.376.664,00 490.376.664,00 - - -
1.20.10 26. Kecamatan Banyuasin I 17.551.960,00 17.536.960,00 15.000,00 15.000,00 -
1.20.11 27. Kecamatan Banyuasin III 19.115.703,00 19.115.703,00 - - -
1.20.12 28. Kecamatan Betung 5.005.702,00 5.005.702,00 - - -
1.20.13 29. Kecamatan Rantau Bayur - - - - -
1.20.14 30. Kecamatan Pulau Rimau - - - - -
Halaman 1 dari 2
KAS DI BENDAHARA
SISA KAS TAHUN UYHD 2013 UYHD 2013 SISA BELUM
KODE SKPD PENGELUARAN PER
2013 DISETOR 2013 31 DESEMBER 2013
DISETOR 2014 SETOR
1 2 3 4 5 6 7 = 5-6
1.20.15 31. Kecamatan Talang Kelapa 42.529.977,00 42.529.977,00 - - -
1.20.16 32. Kecamatan Rambutan 4.754.000,00 4.754.000,00 - - -
1.20.17 33. Kecamatan Tungkal Ilir 181.125,00 23.625,00 157.500,00 157.500,00 -
1.20.18 34. Kecamatan Tanjung Lago 1.948.611,00 1.948.611,00 - - -
1.20.19 35. Kecamatan Sembawa 285.637,00 285.637,00 - - -
1.20.20 36. Kecamatan Suak Tape 41.906.500,00 41.906.500,00 - - -
1.20.21 37. Kecamatan Banyuasin II 99.982,00 - 99.982,00 99.982,00 -
1.20.22 38. Kecamatan Makarti Jaya 14.545.124,00 14.545.124,00 - - -
1.20.23 39. Kecamatan Muara Padang - - - - -
1.20.24 40. Kecamatan Muara Sugihan - - - - -
1.20.25 41. Kecamatan Muara Telang 42.298.266,00 42.298.266,00 - - -
1.20.26 42. Kecamatan Air Salek 1.197,00 1.197,00 - - -
1.20.27 43. Kecamatan Sumber Marga Telang 527.915,00 527.915,00 - - -
1.20.28 44. Kecamatan Air Kumbang 17.969.100,00 - 17.969.100,00 17.969.100,00 -
1.21.01 45.Badan Ketahanan Pangan 59.097.248,00 59.097.248,00 - - -
1.22.01 46.Badan Pemberdayaan Masyarakat dan Pemerintahan Desa. 208.120.834,00 208.120.771,00 63,00 63,00 -
1.26.01 47.Badan Perpustakaan, Arsip Daerah dan Dokumentasi 10.596.422,00 10.596.422,00 - - -
2.01.01 48.Dinas Pertanian dan Peternakan 18.655.867,00 18.655.867,00 - - -
2.01.02 49.Badan Pelaksana Penyuluhan Pertanian, Perikanan dan Kehutanan 26.550.529,00 26.550.529,00 - - -
2.02.01 50.Dinas Kehutanan dan Perkebunan 109.347.343,00 109.347.343,00 - - -
2.03.01 51.Dinas Pertambangan dan Energi 4.618.111,00 4.618.111,00 - - -
2.04.01 52.Dinas Pariwisata, Seni, Budaya, Pemuda dan Olahraga 69.051.082,00 69.051.082,00 - - -
2.05.01 53.Dinas Perikanan dan Kelautan 48.465.100,00 48.429.100,00 36.000,00 36.000,00 -
2.06.01 54.Dinas Pengelolaan Pasar 1.186.711,00 1.186.711,00 - - -
TOTAL 16.210.799.006,17 10.216.420.274,17 5.994.378.732,00 5.994.378.732,00 -
Halaman 2 dari 2
DAFTAR PIUTANG TP/TGR LAMPIRAN : 6.a
Per 31 Desember 2013
(dalam rupiah)
Jenis Kasus
No. Nama SKPD Jumlah Kerugian Angsuran Sisa
(tahun)
A. TP
- - - - - -
Sub Jumlah TP NIHIL
B. TGR
1. Ed BAPEDDA TGR-2012 9.500.000,00 6.400.000,00 3.100.000,00
2. AS DPPKAD TGR-2012 14.800.000,00 9.920.000,00 4.880.000,00
3. AA, S.Pd Penyuluh KB TGR-2012 6.000.000,00 1.250.000,00 4.750.000,00
4. Hy Disnakertrans TGR-2011 13.200.000,00 550.000,00 12.650.000,00
5. EAm Dishutbun TGR-2012 18.240.000,00 1.520.000,00 16.720.000,00
- - - - - -
Sub Jumlah/TGR 61.740.000,00 19.640.000,00 42.100.000,00
Sub Jumlah TP/TGR 61.740.000,00 19.640.000,00 42.100.000,00
Catatan :
TGR a.n. Ed, AS, AA, S.Pd, Hy, dan EAm seluruhnya dimasukan ke piutang TP/TGR (lancar) karena :
1 SKTJM a.n Ed tertanggal 1 Juni 2012 menyebutkan bahwa jumlah kerugian/kekurangan tersebut diganti dalam jangka
waktu 24 (dua puluh empat) bulan tmt bulan Juli 2012 s.d. bulan Juni 2014.
2 SKTJM a.n AS tertanggal 1 Juni 2012 menyebutkan bahwa jumlah kerugian/kekurangan tersebut diganti dalam jangka
waktu 24 (dua puluh empat) bulan tmt bulan Juli 2012 s.d. bulan Juni 2014.
3 SKTJM a.n AA, S.Pd tertanggal 26 April 2013 menyebutkan bahwa jumlah kerugian/kekurangan tersebut diganti dalam
jangka waktu 24 (dua puluh empat) bulan tmt bulan Juli 2013 s.d. bulan Juni 2015.
4 SKTJM a.n Hy tertanggal 17 Juli 2013 menyebutkan bahwa jumlah kerugian/kekurangan tersebut diganti dalam jangka
waktu 24 (dua puluh empat) bulan tmt bulan Agustus 2013 s.d. bulan September 2015.
5 SKTJM a.n EAm tertanggal 17 Juli 2013 menyebutkan bahwa jumlah kerugian/kekurangan tersebut diganti dalam
jangka waktu 24 (dua puluh empat) bulan tmt bulan Agustus 2013 s.d. bulan Juli 2015.
6 Karena masa pengembalian tersebut hanya menyebutkan jangka waktu pengembalian, maka piutang tersebut selalu ada
kemungkinan dapat diselesaikan selama setahun, dan oleh karenanya dalam neraca disajikan sebagai piutang lancar.
LAMPIRAN : 6.b
Halaman 1 dari 3
TOTAL PIUTANG ANGSURAN 2012 ANGSURAN 2013 Saldo per 31 ANGSURAN S/D JAN 2014
No. Nama SALDO KET
Thn. 2003 Thn. 2004 Thn. 2005 Thn. 2006 Thn. 2008 Jumlah Jumlah Tgl. Setor Jumlah Tgl. Setor Desember 2013 Jumlah Tgl. Setor
17 H. HH 17.600.000 15.000.000 3.435.800 36.035.800 36.035.800 3.000.000 04-02-2014 33.035.800
18 SSS 13.500.000 4.107.000 17.607.000 4.107.000 04-11-2013 13.500.000 13.500.000
19 AK. AR 15.000.000 15.000.000 15.000.000 1.500.000 10-03-2014 13.500.000
20 Jf 15.000.000 2.905.700 17.905.700 17.905.700 2.905.700 27-01-2014 8.905.700
6.094.300 27-01-2014
21 Adn, S.Sos 732.700 732.700 732.700 06-05-2013 - - PNS
22 Drs. Nz 220.400 220.400 220.400 06-05-2013 - - PNS
23 FS, SH 515.500 515.500 515.500 515.500 23-01-2014 - PNS
24 GS 723.400 723.400 723.400 723.400 07-01-2014 - PNS
25 H. AS 2.298.500 2.298.500 2.298.500 28-03-2013 - -
26 H. M. BDA 815.600 815.600 815.600 28-03-2013 - -
27 Ir. WK, MM 331.900 331.900 331.900 11-11-2013 - -
28 H. HZ, S. Ag 3.911.600 3.911.600 3.911.600 3.911.600 28-01-2014 -
29 Hrw 565.500 565.500 565.500 565.500 22-01-2014 -
30 IH , S. Hut 2.188.300 2.188.300 2.188.300 2.188.300 14-02-2014 -
Koreksi tahun 2005 (196.000) (196.000) (196.000) (196.000)
509.350.862 594.873.372 200.288.000 217.500.000 40.460.700 1.562.472.934 5.000.000 220.689.020 1.336.779.914 543.301.110 793.478.804
JUMLAH 2.795.143.373 3.720.588.692 567.897.000 570.000.000 105.873.200 7.759.502.265 5.000.000 - 220.689.020 - 7.533.809.245 543.301.110 - 6.990.508.135 -
Halaman 3 dari 3
REKAPITULASI PIUTANG LAINNYA
per 31 Desember 2013 LAMPIRAN : 8
Halaman 1 dari 2
BULAN DAN TAHUN SALDO AWAL PENAMBAHAN PENGURANGAN SALDO AKHIR
NO NAMA
PENSIUN PIUTANG PIUTANG PIUTANG PIUTANG
54 Syf, SH OKTOBER_2013 3.000.000,00 2.000.000,00 1.000.000,00
55 AsN NOVEMBER_2013 2.000.000,00 1.000.000,00 1.000.000,00
56 ZH NOVEMBER_2013 2.000.000,00 400.000,00 1.600.000,00
57 M. SH DESEMBER 2013 0,00 - -
58 M. Zn DESEMBER 2013 1.000.000,00 - 1.000.000,00
59 YPS DESEMBER 2013 0,00 - -
TOTAL 86.200.000,00 221.400.000,00 150.800.000,00 156.800.000,00
Halaman 2 dari 2
DAFTAR SALDO PERSEDIAAN
Per 31 Desember 2013 LAMPIRAN : 9
Jenis Persediaan
No. Unit Kerja Bahan Jumlah
Alat
ATK Alat Listrik Barang Cetakan Obat-obatan BHP Alkes Kimia/bibit/BB
Kebersihan
M/Makanan
1 Dinas Pendidikan 315.000,00 0,00 0,00 0,00 0,00 0,00 100.000,00 415.000,00
2 Dinas Kesehatan 5.357.300,00 0,00 0,00 0,00 8.334.970.930,77 0,00 0,00 8.340.328.230,77
3 RSUD Tipe D 17.632.240,00 0,00 0,00 0,00 493.882.131,00 0,00 0,00 511.514.371,00
4 DPU Cipta Karya 338.250,00 0,00 0,00 0,00 0,00 0,00 0,00 338.250,00
5 DPU Bina Marga 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
6 DPU Pengairan 4.017.000,00 0,00 500.000,00 918.000,00 0,00 0,00 141.875.000,00 147.310.000,00
7 BAPPEDA dan PM 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
8 Dishub Kominfo 865.250,00 0,00 0,00 0,00 0,00 0,00 0,00 865.250,00
9 B Lingkungan Hidup 1.100.000,00 0,00 0,00 0,00 0,00 0,00 0,00 1.100.000,00
10 Dinas Kebersihan, PP 192.000,00 0,00 0,00 0,00 0,00 0,00 0,00 192.000,00
11 Disduk dan Capil 924.400,00 87.000,00 290.072.910,00 144.000,00 0,00 0,00 0,00 291.228.310,00
12 BP Keluarga Berencana 474.400,00 0,00 0,00 0,00 0,00 0,00 0,00 474.400,00
13 Dinas Kesos 1.785.300,00 0,00 0,00 0,00 0,00 43.722.000,00 1.020.000,00 46.527.300,00
14 Dinas Nakertrans 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
15 Dinas Koperindag 1.292.000,00 0,00 0,00 0,00 0,00 0,00 0,00 1.292.000,00
16 Badan Kesbangpol 98.700,00 0,00 0,00 0,00 0,00 0,00 0,00 98.700,00
17 Satuan Polisi Pamong Praja 1.742.800,00 0,00 0,00 0,00 0,00 0,00 0,00 1.742.800,00
18 Kepala Daerah dan WKD 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
19 Sekretariat Daerah 47.477.475,00 0,00 0,00 0,00 0,00 0,00 0,00 47.477.475,00
20 DPRD 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
21 Sekretariat DPRD 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
22 Inspektorat Kabupaten 2.113.000,00 0,00 0,00 0,00 0,00 0,00 0,00 2.113.000,00
23 Dinas PPKAD 41.420.154,00 0,00 21.157.050,00 0,00 0,00 0,00 0,00 62.577.204,00
24 BKD 974.400,00 0,00 1.010.000,00 0,00 0,00 0,00 0,00 1.984.400,00
25 BPT 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
26 Baketpan 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
27 BPMPD 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
28 BPAD 4.683.400,00 741.000,00 670.000,00 1.100.000,00 0,00 0,00 0,00 7.194.400,00
29 Dinas Pertanak 2.788.750,00 0,00 0,00 0,00 0,00 0,00 369.002.500,00 371.791.250,00
30 BPPPPK 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
31 Dinas Hutbun 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
32 Dispertamben 386.800,00 0,00 187.500,00 0,00 0,00 0,00 0,00 574.300,00
33 Dis Parsosbud 263.000,00 0,00 0,00 0,00 0,00 0,00 0,00 263.000,00
34 Diskanlat 19.125.850,00 2.848.000,00 0,00 0,00 0,00 0,00 63.664.000,00 85.637.850,00
35 Dinas Pasar 618.800,00 0,00 726.550,00 0,00 0,00 0,00 0,00 1.345.350,00
36 Kecamatan Banyuasin I 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
37 Kecamatan Banyuasin III 1.375.000,00 0,00 0,00 0,00 0,00 0,00 0,00 1.375.000,00
38 Kecamatan Betung 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
39 Kecamatan Rantau Bayur 3.383.000,00 0,00 0,00 0,00 0,00 0,00 0,00 3.383.000,00
40 Kecamatan Pulau Rimau 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
41 Kecamatan Talang Kelapa 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
42 Kecamatan Rambutan 611.800,00 0,00 0,00 0,00 0,00 0,00 0,00 611.800,00
43 Kecamatan Tungkal Ilir 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
44 Kecamatan Tanjung lago 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
45 Kecamatan Sembawa 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
46 Kecamatan Suak Tapeh 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
47 Kecamatan Banyuasin II 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
48 Kecamatan Makarti Jaya 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
49 Kecamatan Muara Padang 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
50 Kecamatan Muara Sugihan 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
51 Kecamatan Muara Telang 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
52 Kecamatan Air Saleh 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
53 Kecamatan SM Telang 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
54 Kecamatan Air Kumbang 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
Jumlah 161.356.069,00 3.676.000,00 314.324.010,00 2.162.000,00 8.828.853.061,77 43.722.000,00 575.661.500,00 9.929.754.640,77
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013 LAMPIRAN : 10
A. TANAH
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
Halaman 1 dari 2
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013 LAMPIRAN : 10
A. TANAH
Mutasi Kurang
Saldo 31 Desember 2012 Saldo 31 Desember
No SKPD
(AUDITED) Reklas ke Reklas ke Aset Lainnya 2013
Reklas ke BJ Rusak Salah Anggaran Ekstracomptabel Hibah Penghapusan Koreksi LK 2012
Persediaan / Antar Aset Tetap
(1) (2) (3) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
Halaman 2 dari 2
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013 LAMPIRAN : 11
B. PERALATAN DAN MESIN
Halaman 1 dari 2
LAMPIRAN : 11
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
B. PERALATAN DAN MESIN
Mutasi Kurang
Saldo 31 Desember 2012 Saldo 31 Desember
No SKPD
(AUDITED) Reklas ke Reklas ke Aset Lainnya 2013
Reklas ke BJ Rusak Salah Anggaran Ekstracomptabel Hibah Penghapusan Koreksi LK 2012
Persediaan / Antar Aset Tetap
(1) (2) (3) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
1 DIKNAS 33.178.559.067,00 - (3.766.814.000,00) - - (7.433.541.900,98) (4.491.956.754,16) - - 58.683.386.346,86
2 KESEHATAN 34.567.349.409,00 - - (243.638.875,00) - (15.280.000,00) - - - 38.207.735.039,00
3 RSUD 7.736.788.988,00 - - - - - - (92.720.640,00) 8.696.064.172,00
4 PUCK 7.275.420.809,00 - - - - (19.842.900,00) - - (428.268.430,00) 7.485.951.479,00
5 PUBM 9.868.061.756,00 - - - - (8.175.000,00) - - - 10.406.246.756,00
6 PU AIR 5.389.199.500,00 - - - - (27.725.000,00) - - - 7.416.914.595,00
7 BAPPEDA DAN PM 4.264.584.236,00 - - (399.609.690,00) - - - - - 4.434.621.046,00
8 DISHUB 9.963.284.134,00 - (2.908.202.950,00) - - (11.010.600,00) - - - 12.592.868.534,00
9 BLH 5.852.173.700,00 - - (152.815.000,00) - (2.039.500,00) - - (2.796.800,00) 7.634.057.400,00
10 KEBERSIHAN 3.469.845.000,00 - - - - (10.000.000,00) - - - 4.857.779.026,00
11 CAPIL 3.466.531.647,20 - (391.920.000,00) - - (100.566.500,00) - - (451.406.700,00) 5.077.402.507,20
12 BAPEL KB 4.801.998.900,00 - - 2.700.000,00 - (5.000.000,00) - - (150.626.000,00) 5.375.837.900,00
13 DINSOS 1.529.630.000,00 - - (3.400.000,00) - (15.450.000,00) - - - 1.675.130.000,00
14 DISNAKER 3.190.301.000,00 - - (95.936.700,00) - (47.960.000,00) - - 4.443.193.900,00
15 KOPERINDAG 2.599.709.868,00 - - - - (17.250.000,00) - - - 2.844.439.859,00
16 KESBANG 3.689.573.922,00 - - (324.805.666,00) - (103.276.609,00) - - (30.645.652,00) 8.257.265.630,00
17 SATPOL 1.132.464.000,00 - - - - (9.110.700,00) - - - 1.183.773.300,00
18 SEKDA 48.672.550.758,00 (114.666.000,00) - - - (371.278.560,00) - - (25.770.000,00) 59.684.318.795,00
19 SETWAN 23.137.382.905,00 - (277.142.000,00) - - (273.339.000,00) - - (1.074.702.200,00) 26.737.245.705,00
20 INSPEKTORAT 2.957.764.995,00 - - (502.524.000,00) - (44.890.000,00) - - - 3.168.874.275,00
21 DPPKAD 4.809.473.659,00 - - - - (33.465.000,00) - - (10.783.452,00) 8.912.471.758,00
22 BKD 2.157.108.660,00 - (103.243.500,00) - - (21.000.000,00) - - 92.728.100 2.716.753.260,00
23 BPT 2.281.571.575,00 - (84.465.000,00) - - (759.000,00) - - - 3.375.886.975,00
24 BAKETPAN 2.890.745.393,00 - - - - - - (156.331.001,00) 12.159.471.385,00
25 BPMPD 1.829.399.366,00 - - - - - - - (36.800.030,00) 2.196.363.336,00
26 PERPUSTAKAAN 3.760.068.080,00 - (68.250.000,00) (23.715.000,00) - - (4.730.000,00) - - - 3.960.426.730,00
27 PERTANIAN 10.911.122.992,00 - - - - - - - (643.500,00) 11.965.682.037,00
28 BP4K 1.673.717.900,00 - - - - (18.860.000,00) - - - 4.920.532.700,00
29 DISHUTBUN 3.458.386.281,00 - - - - (27.635.000,00) - - (13.000.000,00) 4.347.675.481,00
30 DISTAMBEN 2.959.752.850,00 - - - - (1.500.000,00) - - (4.734.000,00) 3.672.193.850,00
31 PARIWISATA 2.011.793.937,00 - - - - - - - - 2.192.711.937,00
32 PERIKANAN 3.381.183.460,00 - (19.057.817,00) - - - (107.987.500,00) - - - 4.385.588.723,00
33 PASAR 2.577.596.025,00 - - - - (3.891.400,00) - - - 2.289.812.599,00
34 TANJUNG LAGO 3.600.000,00 - - - - (700.000,00) - - - 35.400.000,00
35 AIR SALEH 35.600.000,00 - - - - (1.595.000,00) - - (3.600.000,00) 105.414.000,00
36 TUNGKAL ILIR - - - - - (4.845.500,00) - - - 59.389.180,00
37 BANYUASIN I 24.000.000,00 - - - - - - - - 27.000.000,00
38 MUARA SUGIHAN 24.000.000,00 - - - - - - - - 40.450.000,00
39 BANYUASIN II 26.300.000,00 - - - - (12.980.000,00) - - - 89.580.000,00
40 BANYUASIN III 70.095.000,00 - - - - (23.550.000,00) - - (5.545.000,00) 104.690.000,00
41 BETUNG 7.461.368,00 - - - - - - - - 7.461.368,00
42 MUARA TELANG - - - - - (6.800.000,00) - - - 68.200.000,00
43 MUARA PADANG - - - - - (44.480.000,00) - - - 36.500.000,00
44 MAKARTI JAYA 31.000.000,00 - - - - - - - (800.000,00) 109.200.100,00
45 PULAU RIMAU - - - - - - - - - 38.000.000,00
46 RAMBUTAN 46.960.000,00 - - - - - - - (4.660.000,00) 42.300.000,00
47 RANTAU BAYUR 30.400.000,00 - - - - - - - - 45.000.000,00
48 SUAK TAPEH 38.400.000,00 - - - - (7.500.000,00) - - (3.100.000,00) 95.013.000,00
49 SEMBAWA 184.613.000,00 - - - - (21.115.240,00) - - - 173.497.760,00
50 SUMBER MARGA TELANG - - - - - (5.070.000,00) - - - 87.155.225,00
51 AIR KUMBANG - - - - - (45.840.000,00) - - - 156.875.000,00
52 TALANG KELAPA 45.000.000,00 - - - - - - - - 90.600.000,00
JUMLAH 262.012.524.140,20 (114.666.000,00) (87.307.817,00) (7.555.502.450,00) (1.720.029.931,00) - (8.910.039.909,98) (4.491.956.754,16) - (2.404.205.305,00) 347.370.402.669,06
TOTAL MUTASI TAMBAH TOTAL MUTASI KURANG (25.283.708.167,14)
Halaman 2 dari 2
LAMPIRAN : 12
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
C. GEDUNG DAN BANGUNAN
(1.052.570.500,00)
1.040.866.950,00
(2.093.437.450,00)
Halaman 1 dari 2
LAMPIRAN : 12
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
C. GEDUNG DAN BANGUNAN
Mutasi Kurang
Saldo 31 Desember 2012 Saldo 31 Desember
No SKPD
(AUDITED) Reklas ke Reklas ke Aset Lainnya 2013
Reklas ke BJ Rusak Salah Anggaran Ekstracomptabel Hibah Penghapusan Koreksi LK 2012
Persediaan / Antar Aset Tetap
(1) (2) (3) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
1 DIKNAS 365.315.872.513,00 - - - - (10.894.622.162,35) - - 402.435.454.350,65
2 KESEHATAN 63.705.868.749,00 - - - - - - - - 70.481.169.749,00
3 RSUD 3.168.395.000,00 - - - - - - - - 4.553.627.500,00
4 PUCK 51.224.517.400,00 - - - - - - - 2.339.213.700,00 73.346.398.100,00
5 PUBM 5.135.572.500,00 - - - - - - - - 5.135.572.500,00
6 PU AIR 4.554.596.085,00 - - - - - - - - 4.704.196.085,00
7 BAPPEDA DAN PM 3.842.780.000,00 - - - - - - - - 3.867.280.000,00
8 DISHUB 15.999.994.817,00 - (6.478.496.437,00) - - - - - - 15.180.901.930,00
9 BLH 3.135.541.500,00 - - - - - - - - 3.184.971.500,00
10 KEBERSIHAN 3.422.216.950,00 - - - - - - - - 3.567.216.950,00
11 CAPIL 3.645.021.000,00 - - - - - - - - 4.686.111.000,00
12 BAPEL KB 570.055.000,00 - - - - - - - - 1.531.565.000,00
13 DINSOS 196.995.000,00 - - - - - - - - 987.704.000,00
14 DISNAKER 5.647.415.000,00 - - - - - - - - 5.647.415.000,00
15 KOPERINDAG 8.135.736.675,00 - - - - - - - 87.998.825,00 19.493.605.500,00
16 KESBANG 6.775.340.000,00 - - - - - - - - 7.103.180.000,00
17 SATPOL 55.425.500,00 - - - - - - - - 55.425.500,00
18 SEKDA 83.484.484.916,00 - - - - - - - - 83.590.634.916,00
19 SETWAN 44.603.581.180,00 - - - (103.272.000,00) - - - 45.352.564.180,00
20 INSPEKTORAT 3.701.253.500,00 - - - - - - - - 4.027.703.500,00
21 DPPKAD 4.999.039.000,00 - - - - - - - - 5.370.684.000,00
22 BKD 3.754.481.900,00 - - - (16.000.000,00) - - - 228.253.255 4.434.372.670,00
23 BPT 210.854.000,00 - - - - - - 295.319.000,00
24 BAKETPAN 16.131.913.400,00 - - - - - - (12.605.364.400,00) 8.651.265.000,00
25 BPMPD 2.629.293.000,00 - - - - - - - - 2.629.293.000,00
26 PERPUSTAKAAN 8.398.644.000,00 - - - - - - - - - 8.621.259.000,00
27 PERTANIAN 7.760.365.700,00 - - - - - - - - 7.966.327.200,00
28 BP4K 2.898.211.000,00 - - - - - - - - 6.249.491.000,00
29 DISHUTBUN 4.995.434.323,25 - - - - (90.750.000,00) - (34.100.000,00) 5.581.862.323,25
30 DISTAMBEN 4.343.714.000,00 - - - - - - - - 4.493.514.000,00
31 PARIWISATA 1.823.314.000,00 - - - - - (342.927.000,00) - (98.000.000,00) 2.215.764.000,00
32 PERIKANAN 10.567.447.825,00 - (1.185.933.864,00) - - - - - (5.000.000,00) 12.306.252.658,00
33 PASAR 7.974.986.000,00 - - - - - - (475.826.000,00) - 9.193.710.000,00
34 TANJUNG LAGO - - - - - - - - - -
35 AIR SALEH - - - - - - - - - -
36 TUNGKAL ILIR - - - - - - - - - -
37 BANYUASIN I - - - - - - - - - -
38 MUARA SUGIHAN - - - - - - - - - -
39 BANYUASIN II - - - - - - - - - -
40 BANYUASIN III - - - - - - - - - -
41 BETUNG - - - - - - - - - -
42 MUARA TELANG - - - - - - - - - -
43 MUARA PADANG - - - - - - - - - -
44 MAKARTI JAYA - - - - - - - - - -
45 PULAU RIMAU - - - - - - - - - -
46 RAMBUTAN - - - - - - - - - -
47 RANTAU BAYUR - - - - - - - - - -
48 SUAK TAPEH - - - - - - - - - -
49 SEMBAWA - - - - - - - - - -
50 SUMBER MARGA TELANG - - - - - - - - - -
51 AIR KUMBANG - - - - - - - - - -
52 TALANG KELAPA - - - - - - - - - -
Halaman 2 dari 2
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013 LAMPIRAN : 13
D. JALAN, IRIGASI DAN JARINGAN
Halaman 1 dari 2
LAMPIRAN : 13
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
D. JALAN, IRIGASI DAN JARINGAN
Mutasi Kurang
Saldo 31 Desember 2012 Saldo 31 Desember
No SKPD
(AUDITED) Reklas ke Reklas ke Aset Lainnya 2013
Reklas ke BJ Rusak Salah Anggaran Ekstracomptabel Hibah Penghapusan Koreksi LK 2012
Persediaan / Antar Aset Tetap
(1) (2) (3) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
Halaman 2 dari 2
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013 LAMPIRAN : 14
E. ASET TETAP LAINNYA
Halaman 1 dari 2
LAMPIRAN : 14
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
E. ASET TETAP LAINNYA
Mutasi Kurang
Saldo 31 Desember 2012 Saldo 31 Desember
No SKPD
(AUDITED) Reklas ke Reklas ke Aset Lainnya 2013
Reklas ke BJ Rusak Salah Anggaran Ekstracomptabel Hibah Penghapusan Koreksi LK 2012
Persediaan / Antar Aset Tetap
(1) (2) (3) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
Halaman 2 dari 2
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013 LAMPIRAN : 15
F. KONSTRUKSI DALAM PENGERJAAN
1 DIKNAS - - - - - - -
2 KESEHATAN - - - - - - -
3 RSUD - - - - - - -
4 PUCK - - - - - -
5 PUBM 26.799.742.000,00 - - - 5.879.513.000,00 - -
6 PU AIR - - - - - - -
7 BAPPEDA DAN PM - - - - - - -
8 DISHUB - - - - - - -
9 BLH - - - - - - -
10 KEBERSIHAN - - - - - - -
11 CAPIL - - - - - - -
12 BAPEL KB - - - - - - -
13 DINSOS - - - - - - -
14 DISNAKER - - - - - - -
15 KOPERINDAG - - - - - - -
16 KESBANG - - - - - - -
17 SATPOL - - - - - - -
18 SEKDA - - - - - - -
19 SETWAN - - - - - - -
20 INSPEKTORAT - - - - - - -
21 DPPKAD - - - - - - -
22 BKD - - - - - - -
23 BPT - - - - - - -
24 BAKETPAN - - - - - - -
25 BPMPD - - - - - - -
26 PERPUSTAKAAN - - - - - - -
27 PERTANIAN - - - - - - -
28 BP4K - - - - - - -
29 DISHUTBUN - - - - - - -
30 DISTAMBEN - - - - - - -
31 PARIWISATA - - - - - - -
32 PERIKANAN - - - - 779.271.000,00 - -
33 PASAR - - - - - - -
34 TANJUNG LAGO - - - - - - -
35 AIR SALEH - - - - - - -
36 TUNGKAL ILIR - - - - - - -
37 BANYUASIN I - - - - - - -
38 MUARA SUGIHAN - - - - - - -
39 BANYUASIN II - - - - - - -
40 BANYUASIN III - - - - - - -
41 BETUNG - - - - - - -
42 MUARA TELANG - - - - - - -
43 MUARA PADANG - - - - - - -
44 MAKARTI JAYA - - - - - - -
45 PULAU RIMAU - - - - - - -
46 RAMBUTAN - - - - - - -
47 RANTAU BAYUR - - - - - - -
48 SUAK TAPEH - - - - - - -
49 SEMBAWA - - - - - - -
50 SUMBER MARGA TELANG - -
51 AIR KUMBANG - - - - - - -
52 TALANG KELAPA - - - - - - -
Halaman 1 dari 2
LAMPIRAN : 15
DAFTAR MUTASI ASET PER SKPD PER JENIS ASET PER 31 DESEMBER 2013
F. KONSTRUKSI DALAM PENGERJAAN
Mutasi Kurang
Saldo 31 Desember 2012 Saldo 31 Desember
No SKPD
(AUDITED) Reklas ke Reklas ke Aset Lainnya 2013
Reklas ke BJ Rusak Salah Anggaran Ekstracomptabel Hibah Penghapusan Koreksi LK 2012
Persediaan / Antar Aset Tetap
(1) (2) (3) (11) (12) (13) (14) (15) (16) (17) (18) (19) (20)
1 DIKNAS - - - - - - - - - -
2 KESEHATAN - - - - - - - - - -
3 RSUD - - - - - - - - - -
4 PUCK - - - - - - - - - -
5 PUBM 26.799.742.000,00 - (26.799.742.000,00) - - - - - - 5.879.513.000,00
6 PU AIR - - - - - - - - - -
7 BAPPEDA DAN PM - - - - - - - - - -
8 DISHUB - - - - - - - - - -
9 BLH - - - - - - - - - -
10 KEBERSIHAN - - - - - - - - - -
11 CAPIL - - - - - - - - - -
12 BAPEL KB - - - - - - - - - -
13 DINSOS - - - - - - - - - -
14 DISNAKER - - - - - - - - - -
15 KOPERINDAG - - - - - - - - - -
16 KESBANG - - - - - - - - - -
17 SATPOL - - - - - - - - - -
18 SEKDA - - - - - - - - - -
19 SETWAN - - - - - - - - - -
20 INSPEKTORAT - - - - - - - - - -
21 DPPKAD - - - - - - - - - -
22 BKD - - - - - - - - - -
23 BPT - - - - - - - - - -
24 BAKETPAN - - - - - - - - - -
25 BPMPD - - - - - - - - - -
26 PERPUSTAKAAN - - - - - - - - - -
27 PERTANIAN - - - - - - - - - -
28 BP4K - - - - - - - - - -
29 DISHUTBUN - - - - - - - - - -
30 DISTAMBEN - - - - - - - - - -
31 PARIWISATA - - - - - - - - - -
32 PERIKANAN - - - - - - - - 779.271.000,00
33 PASAR - - - - - - - - - -
34 TANJUNG LAGO - - - - - - - - - -
35 AIR SALEH - - - - - - - - - -
36 TUNGKAL ILIR - - - - - - - - - -
37 BANYUASIN I - - - - - - - - - -
38 MUARA SUGIHAN - - - - - - - - - -
39 BANYUASIN II - - - - - - - - - -
40 BANYUASIN III - - - - - - - - - -
41 BETUNG - - - - - - - - - -
42 MUARA TELANG - - - - - - - - - -
43 MUARA PADANG - - - - - - - - - -
44 MAKARTI JAYA - - - - - - - - - -
45 PULAU RIMAU - - - - - - - - - -
46 RAMBUTAN - - - - - - - - - -
47 RANTAU BAYUR - - - - - - - - - -
48 SUAK TAPEH - - - - - - - - - -
49 SEMBAWA - - - - - - - - - -
50 SUMBER MARGA TELANG - -
51 AIR KUMBANG - - - - - - - - - -
52 TALANG KELAPA - - - - - - - - - -
Halaman 2 dari 2
ASET YANG AKAN DIHIBAHKAN
DINAS PU CIPTA KARYA LAMPIRAN : 16.a
Kontrak/SPK
No. Nama Pekerjaan/Kegiatan
Nilai (Rp) Nomor/Tgl
1 2 3 4
1 Pembuatan Papan Nama SPPN Sembawa 84.418.000 11/02/SPK/PPK-P3L.I/PUCK/2012 Tanggal 12
September 2012
2 Pembangunan Gedung Serbaguna Kec. Muara Telang (Tahap I) 173.672.000 01/03/SPK/PPK-OP.II/PUCK/2012 Tanggal 13
September 2012
3 Pembangunan Gedung Serbaguna Desa Taja Indah Kec. Betung 293.991.000 10/03/PPK-P3L.II/PU.CK/2012 Tanggal 27 Agustus
2012
4 Pembangunan Gedung Serbaguna Desa Lubuk Lancang Kec. 195.985.000
Suak Tapeh 03/12/PPK/PUCK/2012 Tanggal 27 Agustus 2012
JUMLAH I 5.345.557.000
Halaman 1 dari 2
ASET YANG AKAN DIHIBAHKAN
BADAN KETAHANAN PANGAN LAMPIRAN : 16.b
Neraca / KIB
No Jenis Aset Rincian Keterangan
Nilai (Rp)
1 Peralatan Alat Penggiling Padi 6.994.174.000,00 Hibah ke masyarakat/desa
dan Mesin
Alat Pengering 1.105.500.000,00 Hibah ke masyarakat/desa
(KIB B)
2 Gedung dan Bangunan Gudang Tertutup
198.420.000,00 Hibah ke masyarakat/desa
Bangunan (Alsintan)
(KIB C) Bangunan Gudang Tertutup
198.360.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.320.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.360.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.560.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
193.360.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.540.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.500.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.300.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.640.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
193.440.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.500.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.230.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
193.400.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.440.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.280.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.280.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.440.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
193.100.000,00 Hibah ke masyarakat/desa
(Alsintan)
Bangunan Gudang Tertutup
198.300.000,00 Hibah ke masyarakat/desa
(Alsintan)
JUMLAH II 12.047.444.000,00
JUMLAH I + II 17.393.001.000,00
Halaman 2 dari 2
DAFTAR UTANG JAMSOSKES, JAMPERSAL DAN JAMKESMAS
Per 31 Desember 2013
LAMPIRAN : 17
Jamsoskes Jampersal
No Nama Jamsoskes RSUD Jamkesmas Jumlah
Puskesmas Puskesmas
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
DINAS PENDIDIKAN
1 1.01.01 CV. Li REHABILITASI KANTOR UPT TALANG 425/29/Pendidika 190.691.000,00 - - 9.534.550,00 9.534.550,00
KELAPA (SUKAJADI) n/2013
2 1.01.01 CV. LS REHABILITASI KANTOR UPT RANTAU 425/20/Pendidika 137.773.000,00 - - 6.888.650,00 6.888.650,00
BAYUR (PENGUMBUK) n/2013
3 1.01.01 CV. KY REHABILITASI KANTOR UPT 425/44/Pendidika 183.805.000,00 - - 9.190.250,00 9.190.250,00
BANYUASIN I (MARIANA) n/2013
4 1.01.01 CV. MPN PEMBANGUNAN RUANG KELAS 425/72Pendidika 176.967.000,00 - - 8.848.350,00 8.848.350,00
BARU (RKB) SDN 32 TALANG KELAPA n/2013
8 1.01.01 CV. APP PEMBANGUNAN TAMBAHAN RUANG 425/80/Pendidika 193.074.000,00 - - 9.653.700,00 9.653.700,00
KELAS (TRK) SMP NAHDATUL ISLAM n/2013
(DESA SRITIGA KEC. SUMBER
MARGA TELANG)
9 1.01.01 CV. ASa PEMBANGUNAN TAMBAHAN RUANG 425/87/Pendidika 191.712.000,00 - - 9.585.600,00 9.585.600,00
KELAS (TRK) PONPES DARUL ULUM n/2013
PULAU RIMAU (KEC. PULAU RIMAU)
12 1.01.01 CV. SmJ PEMBANGUNAN TAMBAHAN RUANG 425/115/Pendidik 169.297.000,00 - - 8.464.850,00 8.464.850,00
KELAS (TRK) SDN 10 BANYUASIN III an/2013
Halaman 1 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
15 1.01.01 CV. IPr Pengadaan Buku Refrensi dan Panduan 425/15/SP/PPK- 3.542.252.600,00 - - 3.542.252.600,00 3.542.252.600,00
Pendidik Sekolah Dasar (SD) pada Dinas Dikdas/Pendidika
Pendidikan Kabupaten Banyuasin n/2013
16 1.01.01 CV. Gns Pengadaan Buku Pengayaan Tingkat 420/20/PP/Pendid 7.168.000.000,00 - - 7.168.000.000,00 7.168.000.000,00
SMA/SMK pada Dinas Pendidikan ikan/2013
Kabupaten Banyuasin
17 1.01.01 CV. PKC Pengadaan Buku Refrensi dan Buku 420/17/PP/Pendid 1.905.837.750,00 - - 1.905.837.750,00 1.905.837.750,00
Panduan Pendidik Tingkat SMA/SMK pada ikan/2013
Dinas Pendidikan Kabupaten Banyuasin
18 1.01.01 CV. CP Pengadaan Buku Untuk Guru TK/PAUD 420/29/PP/Pendid 547.100.800,00 - - 547.100.800,00 547.100.800,00
pada Dinas Pendidikan Kabupaten ikan/2013
Banyuasin
19 1.01.01 PT. FF Pembangunan Unit Sekolah Baru (USB) 425/095/SP/Pendi 758.895.000,00 37.944.750,00 2509/LS/1.20 37.944.750,00 - -
SMAN 3 Pulau Rimau di Desa teluk Betung dikan/2012 .09.02.00/6.2/
2013
20 1.01.01 CV. BMF Pembangunan Unit Sekolah Baru (USB) 425/096/SP/Pendi 860.584.000,00 43.029.200,00 2981/LS/1.20 43.029.200,00 - -
SMAN 2 Banyuasin II di Desa Jati sari dikan/2012 .09.02.00/5.1/
2013
21 1.01.01 CV. DM Pembangunan Unit Sekolah Baru (USB) 425/097/SP/Pendi 834.334.000,00 41.716.700,00 2505/LS/1.20 41.716.700,00 - -
SMAN 1 Air Saleh di Jalur 8 Air Saleh dikan/2012 .09.02.00/6.2/
2013
22 1.01.01 CV. PL Pembangunan Unit Sekolah Baru (USB) 425/098/SP/Pendi 761.055.000,00 38.052.750,00 3945/LS/1.20 38.052.750,00 - -
SMAN 2 Banyuasin I dikan/2012 .09.02.00/6.2/
2013
23 1.01.01 CV. AS Pembangunan Unit Sekolah Baru (USB) 425/99/SP/Pendid 859.722.000,00 42.986.100,00 2135/LS/1.20 42.986.100,00 - -
SMAN 2 Tungkal Ilir ikan/2012 .09.02.00/6.2/
2013
24 1.01.01 PT. MW Pembangunan Ruang Kelas Baru (RKB) 425/108/SP/Pendi 478.700.000,00 23.935.000,00 3027/LS/1.20 23.935.000,00 - -
SMAN 3 Banyuasin III di Pangkalan Panji dikan/2012 .09.02.00/6.2/
2013
25 1.01.01 CV. Ds Pembangunan Ruang kelas Baru (RKB) 425/100/SP/Pendi 158.958.000,00 7.947.900,00 2881/LS/1.20 7.947.900,00 - -
SMA Bina Mandiri Talang Kelapa dikan/2012 .09.02.00/6.2/
2013
26 1.01.01 CV. LB Pembangunan Ruang kelas Baru (RKB) 425/101/SP/Pendi 158.674.000,00 7.933.700,00 3195/LS/1.20 7.933.700,00 - -
SMA Al-Ikhsan Tanjung Lago dikan/2012 .09.02.00/6.2/
2013
27 1.01.01 CV. IP Pembangunan Ruang kelas Baru (RKB) 425/102/SP/Pendi 159.126.000,00 7.956.300,00 4272/LS/1.20 7.956.300,00 - -
MA Bahrul Ulum Mulia Sari Tanjung Lago dikan/2012 .09.02.00/6.2/
2013
28 1.01.01 CV. MB Pembangunan Ruang kelas Baru (RKB) 425/103/SP/Pendi 159.640.000,00 7.982.000,00 3595/LS/1.20 7.982.000,00 - -
MA Darul Ulum Pulau Rimau dikan/2012 .09.02.00/6.2/
2013
29 1.01.01 CV. MPN Rehap Kantor dan Ruang Guru SMPN 3 425/092/SP/Pendi 478.200.000,00 23.910.000,00 1810/LS/1.20 23.910.000,00 - -
Muara Sugihan dikan/2012 .09.02.00/6.2/
2013
Halaman 2 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
30 1.01.01 CV. MB Pembangunan Ruang Kelas Baru (RKB) 425/057/SP/Pendi 159.010.000,00 7.950.500,00 3596/LS/1.20 7.950.500,00 - -
SMP Muhammadiyah Muara Padang dikan/2012 .09.02.00/6.2/
2013
31 1.01.01 CV. GM Pembangunan Lanjutan SMKN 1 Suak 425/056/SP/Pendi 692.692.000,00 34.634.600,00 2513/LS/1.20 34.634.600,00 - -
Tapeh (Tahap 5) dikan/2012 .09.02.00/6.2/
2013
32 1.01.01 CV. APN Pembangunan Lanjutan SMKN 1 Tanjung 425/055/SP/Pendi 694.138.000,00 34.706.900,00 4336/LS/1.20 34.706.900,00 - -
lago (Tahap 4) dikan/2012 .09.02.00/6.2/
2013
33 1.01.01 CV. BJ Pembangunan Lanjutan SMKN 1 425/93/SP/Pendid 693.250.000,00 34.662.500,00 3296/LS/1.20 34.662.500,00 - -
Banyuasin I (Tahap 2) ikan/2012 .09.02.00/6.2/
2013
34 1.01.01 CV. TW Rehap Laboratorium dan Perpustakaan 425/094/SP/Pendi 130.820.000,00 6.541.000,00 7223/LS/1.20 6.541.000,00 - -
SMPN 1 Banyuasin III dikan/2012 .09.02.00/6.2/
2013
35 1.01.01 CV. DM Pembangunan Gedung UPTD Kecamatan 425/104/SP/Pend/ 351.982.000,00 17.599.100,00 2464/LS/1.20 17.599.100,00 - -
Air Saleh 12 .09.02.00/6.2/
2013
36 1.01.01 CV. RK Pembangunan Gedung UPTD Kecamatan 425/088/SP/Pend/ 342.080.000,00 17.104.000,00 2514/LS/1.20 17.104.000,00 - -
Muara Sugihan 12 .09.02.00/6.2/
2013
37 1.01.01 CV. MTJ Pembangunan Gedung UPTD Kecamatan 425/085/SP/Pend/ 346.480.000,00 17.324.000,00 3592/LS/1.20 17.324.000,00 - -
BA III 12 .09.02.00/6.2/
2013
38 1.01.01 CV. Ri Pembangunan Gedung UPTD Kecamatan 425/059/SP/Pend/ 340.975.000,00 17.048.750,00 2243/LS/1.20 17.048.750,00 - -
Muara Padang 12 .09.02.00/6.2/
2013
39 1.01.01 CV. MJ Pembangunan Gedung UPTD Kecamatan 425/089/SP/Pend/ 341.185.000,00 17.059.250,00 2098/LS/1.20 17.059.250,00 - -
Makarti Jaya 12 .09.02.00/6.2/
2013
40 1.01.01 CV. AB Pembangunan Gedung UPTD Kecamatan 425/090/SP/Pend/ 342.366.000,00 17.118.300,00 3297/LS/1.20 17.118.300,00 - -
Banyuasin II 12 .09.02.00/6.2/
2013
41 1.01.01 CV. KB Pembangunan Gedung UPTD Kecamatan 425/086/SP/Pend/ 346.755.000,00 17.337.750,00 3452/LS/1.20 17.337.750,00 - -
Rambutan 12 .09.02.00/6.2/
2013
42 1.01.01 CV. MB Pembangunan Gedung UPTD Kecamatan 425/058/SP/Pend/ 346.480.000,00 17.324.000,00 3033/LS/1.20 17.324.000,00 - -
Sembawa 12 .09.02.00/6.2/
2013
43 1.01.01 CV. Si Pembangunan Gedung UPTD Kecamatan 425/087/SP/Pend/ 345.200.000,00 17.260.000,00 1947/LS/1.20 17.260.000,00 - -
Suak Tapeh 12 .09.02.00/6.2/
2013
44 1.01.01 CV. CJP Pembangunan Gedung Korwas dan Gudang 425/091/SP/Pend/ 691.472.000,00 34.573.600,00 2615/LS/1.20 34.573.600,00 - -
12 .09.02.00/6.2/
2013
45 1.01.01 CV. Ha Rehabilitasi 3 Ruang Kelas SDN 33 Rantau 425/113/SP/APB 401.495.000,00 20.074.750,00 2081/LS/1.20 20.074.750,00 - -
Bayur D.SD/Pend/2012 .09.02.00/6.2/
2013
Halaman 3 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
46 1.01.01 CV. IK Pembangunan 1 Unit Kantor SDN 12 425/108/SP/APB 268.520.000,00 13.426.000,00 2080/LS/1.20 13.426.000,00 - -
Sembawa D.SD/Pend/2012 .09.02.00/6.2/
2013
47 1.01.01 CV. Li Pembangunan 1 USB Rambutan 425/106/SP/APB 691.750.000,00 34.587.500,00 1879/LS/1.20 34.587.500,00 - -
D.SD/Pend/2012 .09.02.00/6.2/
2013
48 1.01.01 CV. BMF Pembangunan 1 USB Muara Telang 425/107/SP/APB 693.840.000,00 34.692.000,00 2942/LS/1.20 34.692.000,00 - -
D.SD/Pend/2012 .09.02.00/6.2/
2013
49 1.01.01 CV. KY Rehabilitasi 3 Ruang Kelas SDN 10 Muara 425/105/SP/APB 405.700.000,00 20.285.000,00 3034/LS/1.20 20.285.000,00 - -
Padang D.SD/Pend/2012 .09.02.00/6.2/
2013
50 1.01.01 CV. DC Rehabilitasi 3 Ruang Kelas SDN 9 Talang 425/115/SP/APB 219.500.000,00 10.975.000,00 2085/LS/1.20 10.975.000,00 - -
Kelapa D.SD/Pend/2012 .09.02.00/6.2/
2013
51 1.01.01 CV. RK Pembangunan 1 Unit Kantor MI/Ponpes 425/111/SP/APB 266.938.000,00 13.346.900,00 2510/LS/1.20 13.346.900,00 - -
Nurul Iman Ujung Tanjung D.SD/Pend/2012 .09.02.00/6.2/
2013
52 1.01.01 CV. LS Pembanguna 1 Unit Kantor SDN 26 Talang 425/112/SP/APB 267.018.000,00 13.350.900,00 2822/LS/1.20 13.350.900,00 - -
Kelapa D.SD/Pend/2012 .09.02.00/6.2/
2013
53 1.01.01 CV. Ca Pembanguna 1 Unit Kantor SDN 07 Talang 425/109/SP/APB 268.520.000,00 13.426.000,00 1948/LS/1.20 13.426.000,00 - -
Kelapa D.SD/Pend/2012 .09.02.00/6.2/
2013
54 1.01.01 CV. HR Pembanguna 1 Unit Kantor SDN 08 Rantau 425/110/SP/APB 269.315.000,00 13.465.750,00 3476/LS/1.20 13.465.750,00 - -
Bayur D.SD/Pend/2012 .09.02.00/6.2/
2013
55 1.01.01 CV. JB Rehabilitasi 3 Ruang Kelas SDN 14 Talang 425/102/SP/APB 332.000.000,00 16.600.000,00 2622/LS/1.20 16.600.000,00 - -
Kelapa D.SD/Pend/2012 .09.02.00/6.2/
2013
56 1.01.01 CV. SJ Rehabilitasi 1 Ruang Kelas SDN 16 Talang 425/15/SP/APBD 111.386.900,00 5.569.345,00 3003/LS/1.20 5.569.345,00 - -
Kelapa .SD/Pend/2012 .09.02.00/6.2/
2013
57 1.01.01 CV. MPN Rehab 2 lokal SMPN 4 Muara Telang 425/56/DAK- 152.400.000,00 7.620.000,00 1811/LS/1.20 7.620.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
58 1.01.01 CV. GMs Rehab 3 lokal SMPN 1 Muara Sugihan 425/58/DAK- 271.500.000,00 13.575.000,00 - - 13.575.000,00
SMP/PEND/2012
59 1.01.01 CV. La RKB 2 lokal SMPN 6 Banyuasin I 425/47/DAK- 298.000.000,00 14.900.000,00 2378/LS/1.20 14.900.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
60 1.01.01 CV. Ro RKB 1 lokal SMPN 3 Air Saleh 425/57/DAK- 151.900.000,00 7.595.000,00 3756/LS/1.20 7.595.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
61 1.01.01 CV. PB Rehab 2 lokal SMPN 1 Rambutan 425/62/DAK- 181.000.000,00 9.050.000,00 1725/LS/1.20 9.050.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
Halaman 4 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
62 1.01.01 CV. MTJ Rehab.S 2 lokal SMPN 2 Rambutan 425/63/DAK- 148.300.000,00 7.415.000,00 4278/LS/1.20 7.415.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
63 1.01.01 CV. NP RKB 2 lokal SMPN 4 Betung/2 S. Tapeh 425/51/DAK- 296.110.000,00 14.805.500,00 4281/LS/1.20 14.805.500,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
64 1.01.01 CV. La RKB 2 lokal SMPN 2 Tanjung Lago 425/55/DAK- 295.990.000,00 14.799.500,00 2353/LS/1.20 14.799.500,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
65 1.01.01 CV. La Rehab 2 lokal SMPN 2 Sugihan 425/59/DAK- 181.105.000,00 9.055.250,00 2893/LS/1.20 9.055.250,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
66 1.01.01 CV. AP RKB 1 lokal SMPN 3 Tanjung Lago 425/54/DAK- 149.045.000,00 7.452.250,00 4208/LS/1.20 7.452.250,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
67 1.01.01 CV. JU RKB 1 lokal SMPN 6 Banyuasin III 425/49/DAK- 146.860.000,00 7.343.000,00 1982/LS/1.20 7.343.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
68 1.01.01 CV. MTJ Rehab 6 lokal SMPN 2 Betung/1 S.Tapeh 425/52/DAK- 298.555.000,00 14.927.750,00 4277/LS/1.20 14.927.750,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
69 1.01.01 CV. ASa Rehab 2 lokal SMPN 1 Makarti Jaya 425/60/DAK- 180.790.000,00 9.039.500,00 2663/LS/1.20 9.039.500,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
70 1.01.01 CV. BU RKB 3 lokal SMP TMB 7 BA I 425/64/DAK- 445.000.000,00 22.250.000,00 2096/LS/1.20 22.250.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
71 1.01.01 CV. BK RKB 1 lokal SMPN 4 Banyuasin I 425/46/DAK- 147.600.000,00 7.380.000,00 6372/LS/1.20 7.380.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
72 1.01.01 CV. SK Rehab 3 lokal SMPN 2 Pulau Rimau 425/61/DAK- 147.500.000,00 7.375.000,00 2016/LS/1.20 7.375.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
73 1.01.01 CV. NPM Rehab 2 lokal SMPN 3 Betung 425/53/DAK- 180.200.000,00 9.010.000,00 4207/LS/1.20 9.010.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
74 1.01.01 CV. Fa RKB 1 lokal SMP Ar-Rahma Tj. Lago 425/65/DAK- 147.170.000,00 7.358.500,00 - - 7.358.500,00
SMP/PEND/2012
75 1.01.01 CV. ASa RKB 3 lokal SMPN 4 Banyuasin II 425/40/DAK- 307.500.000,00 15.375.000,00 2664/LS/1.20 15.375.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
76 1.01.01 CV. AJ Rehab 2 lokal SMPN 3 Banyuasin III 425/50/DAK- 180.500.000,00 9.025.000,00 3681/LS/1.20 9.025.000,00 - -
SMP/PEND/2012 .09.02.00/6.2/
2013
77 1.01.01 CV. Si Pembangunan 2 (dua) Ruang Kelas Baru 425/38/SP/DAK. 318.880.000,00 15.944.000,00 2083/LS/1.20 15.944.000,00 - -
SDN 11 Muara Padang Kec. Muara Padang SD/Pend/2012 .09.02.00/6.2/
2013
Halaman 5 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
78 1.01.01 CV. Ca Rehab Berat 2 (dua) Ruang Kelas SDN 9 425/40/SP/DAK. 288.900.000,00 14.445.000,00 2084/LS/1.20 14.445.000,00 - -
Muara Padang Kec. Muara Padang SD/Pend/2012 .09.02.00/6.2/
2013
79 1.01.01 CV. AJ Pembangunan 1 (satu) Ruang Kelas Baru 425/41/SP/DAK. 154.380.000,00 7.719.000,00 3004/LS/1.20 7.719.000,00 - -
SDN 10 Muara Padang Kec. Muara Padang SD/Pend/2012 .09.02.00/6.2/
2013
80 1.01.01 CV. CA Rehab Berat 4 (empat) Ruang Kelas SDN 425/42/SP/DAK. 298.400.000,00 14.882.000,00 1623/LS/1.20 14.882.000,00 - -
26 Pulau Rimau Kec. Pulau Rimau SD/Pend/2012 .09.02.00/6.2/
2013
81 1.01.01 CV. PL Pembangunan Gedung Perpustakaan SDN 425/43/SP/DAK. 144.378.000,00 7.218.900,00 1875/LS/1.20 7.218.900,00 - -
24 Banyuasin III Kec. Banyuasin III SD/Pend/2012 .09.02.00/6.2/
2013
82 1.01.01 CV. BJ Pembangunan 2 (dua) Ruang Kelas Baru 425/44/SP/DAK. 304.298.000,00 15.214.900,00 3715/LS/1.20 15.214.900,00 - -
SDN 16 Muara Telang Kec. Muara Telang SD/Pend/2012 .09.02.00/6.2/
2013
83 1.01.01 CV. MB Pembangunan 2 (dua) Ruang Kelas Baru 425/45/SP/DAK. 293.820.000,00 14.691.000,00 2396/LS/1.20 14.691.000,00 - -
SDN 37 Banyuasin I Kec. Banyuasin I SD/Pend/2012 .09.02.00/6.2/
2013
84 1.01.01 CV. KJ Pembangunan 2 (dua) Ruang Kelas Baru 425/46/SP/DAK. 346.130.000,00 17.306.500,00 3513/LS/1.20 17.306.500,00 - -
SDN 26 Muara Telang Kec. Muara Telang SD/Pend/2012 .09.02.00/6.2/
2013
85 1.01.01 CV. ST Pembangunan 2 (dua) Ruang Kelas Baru 425/47/SP/DAK. 348.300.000,00 17.415.000,00 2466/LS/1.20 17.415.000,00 - -
SDN 6 Banyuasin II Kec. Banyuasin II SD/Pend/2012 .09.02.00/6.2/
2013
86 1.01.01 CV. CZ Rehab Berat 2 (dua) Ruang Kelas SDN 20 425/48/SP/DAK. 189.297.000,00 9.464.850,00 - - 9.464.850,00
Banyuasin I Kec. Banyuasin I SD/Pend/2012
87 1.01.01 CV. TS Pembangunan 2 (dua) Ruang Kelas Baru 425/49/SP/DAK. 304.119.000,00 15.205.950,00 2218/LS/1.20 15.205.950,00 - -
SDN 20 Muara Telang Kec. Muara Telang SD/Pend/2012 .09.02.00/6.2/
2013
88 1.01.01 CV. AiP Pembangunan 2 (dua) Ruang Kelas Baru 425/50/SP/DAK. 348.800.000,00 17.440.000,00 4204/LS/1.20 17.440.000,00 - -
SDN 2 Tanjung Lago Kec. Tanjung Lago SD/Pend/2012 .09.02.00/6.2/
2013
89 1.01.01 CV. GMs Pembangunan 2 (dua) Ruang Kelas Baru 425/51/SP/DAK. 348.600.000,00 17.430.000,00 1836/LS/1.20 17.430.000,00 - -
SDN 1 Air Saleh Kec. Air Saleh SD/Pend/2012 .09.02.00/6.2/
2013
90 1.01.01 CV. IqP Pembangunan 2 (dua) Ruang Kelas Baru 425/52/SP/DAK. 304.361.000,00 15.218.050,00 1649/LS/1.20 15.218.050,00 - -
SDN 16 Muara Sugihan Kec. Muara SD/Pend/2012 .09.02.00/6.2/
Sugihan 2013
91 1.01.01 CV. NP Pembangunan Gedung Perpustakaan SDN 8 425/53/SP/DAK. 144.200.000,00 7.210.000,00 2367/LS/1.20 7.210.000,00 - -
Suak Tapeh Kec. Suak Tapeh SD/Pend/2012 .09.02.00/6.2/
2013
92 1.01.01 CV. JB Pembangunan 3 (tiga) Ruang Kelas Baru 425/54/SP/DAK. 507.500.000,00 25.375.000,00 2014/LS/1.20 25.375.000,00 - -
SDN 1 Makarti Jaya Kec. Makarti Jaya SD/Pend/2012 .09.02.00/6.2/
2013
93 1.01.01 CV. IK Pembangunan 2 (dua) Ruang Kelas Baru 425/55/SP/DAK. 348.620.000,00 17.431.000,00 2012/LS/1.20 17.431.000,00 - -
SDN 23 Rantau Bayur Kec. Rantau Bayur SD/Pend/2012 .09.02.00/6.2/
2013
Halaman 6 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
94 1.01.01 CV. MPN Pembangunan Gedung Perpustakaan SDN 425/56/SP/DAK. 144.160.000,00 7.208.000,00 1814/LS/1.20 7.208.000,00 - -
36 Banyuasin I Kec. Banyuasin I SD/Pend/2012 .09.02.00/6.2/
2013
95 1.01.01 CV. MJ Pembangunan 2 (dua) Ruang Kelas Baru 425/57/SP/DAK. 319.106.000,00 15.955.300,00 2371/LS/1.20 15.955.300,00 - -
SDN 12 Tungkal Ilir Kec. Tungkal Ilir SD/Pend/2012 .09.02.00/6.2/
2013
96 1.01.01 PT.T & R Pembangunan 2 (dua) Ruang Kelas Baru 425/58/SP/DAK. 294.100.000,00 14.705.000,00 2088/LS/1.20 14.705.000,00 - -
SDN 35 Banyuasin I Kec. Banyuasin I SD/Pend/2012 .09.02.00/6.2/
2013
97 1.01.01 CV. Ro Pembangunan 2 (dua) Ruang Kelas Baru 425/59/SP/DAK. 294.088.000,00 14.704.400,00 2587/LS/1.20 14.704.400,00 - -
SDN 25 Banyuasin I Kec. Banyuasin I SD/Pend/2012 .09.02.00/6.2/
2013
98 1.01.01 CV. RJ Pembangunan 2 (dua) Ruang Kelas Baru 425/60/SP/DAK. 294.334.000,00 14.716.700,00 1816/LS/1.20 14.716.700,00 - -
SDN 11 Rambutan Kec. Rambutan SD/Pend/2012 .09.02.00/6.2/
2013
99 1.01.01 CV. BU Pembangunan Gedung Perpustakaan SDN 425/61/SP/DAK. 149.250.000,00 7.462.500,00 1813/LS/1.20 7.462.500,00 - -
15 Tanjung Lago Kec. Tanjung Lago SD/Pend/2012 .09.02.00/6.2/
2013
100 1.01.01 CV. Bgn Rehab Berat 4 (empat) Ruang Kelas SDN 425/62/SP/DAK. 329.068.000,00 16.453.400,00 2392/LS/1.20 16.453.400,00 - -
13 Talang Kelapa Kec. Talang Kelapa SD/Pend/2012 .09.02.00/6.2/
2013
101 1.01.01 CV. Kh Rehab Berat 2 (dua) Ruang Kelas SDN 8 425/37/SP/DAK. 179.200.000,00 8.960.000,00 2393/LS/1.20 8.960.000,00 - -
Talang Kelapa Kec. Talang Kelapa SD/Pend/2012 .09.02.00/6.2/
2013
102 1.01.01 CV. TB Pembangunan 2 (dua) Ruang Kelas Baru 425/39/SP/DAK. 293.810.000,00 14.690.500,00 1818/LS/1.20 14.690.500,00 - -
SDN 22 Sembawa Kec. Sembawa SD/Pend/2012 .09.02.00/6.2/
2013
103 1.01.01 CV. LS Rehabilitasi 3 (tiga) Ruang Kelas + 425/104/SP/DAK 226.400.000,00 11.320.000,00 3955/LS/1.20 11.320.000,00 - -
KM/WC SDN 23 Banyuasin I Kecamatan .SD/Pend/2012 .09.02.00/6.2/
Banyuasin I 2013
104 1.01.01 CV. IB Rehabilitasi 4 (empat) Ruang Kelas SDN 28 425/105/SP/DAK 274.900.000,00 13.745.000,00 - - 13.745.000,00
Banyuasin I Kecamatan Banyuasin I .SD/Pend/2012
105 1.01.01 PT. PRa Rehabilitasi 2 (dua) Ruang Kelas SDN 2 425/106/SP/DAK 146.700.000,00 7.335.000,00 2369/LS/1.20 7.335.000,00 - -
Banyuasin I Kecamatan Banyuasin I .SD/Pend/2012 .09.02.00/6.2/
2013
106 1.01.01 CV. RAP Rehabilitasi 2 (dua) Ruang Kelas SDN 22 425/107/SP/DAK 186.570.000,00 9.328.500,00 1815/LS/1.20 9.328.500,00 - -
Banyuasin I Kecamatan Banyuasin I .SD/Pend/2012 .09.02.00/6.2/
2013
107 1.01.01 CV. GB Pembangunan 2 (dua) Ruang Kelas Baru 425/108/SP/DAK 289.200.000,00 14.460.000,00 2802/LS/1.20 14.460.000,00 - -
(RKB) SDN 38 Banyuasin I Kecamatan .SD/Pend/2012 .09.02.00/6.2/
Banyuasin I 2013
108 1.01.01 CV. DI Rehabilitasi 3 (tiga) Ruang Kelas SDN 11 425/109/SP/DAK 281.815.000,00 14.090.750,00 2465/LS/1.20 14.090.750,00 - -
Banyuasin II Kecamatan Banyuasin II .SD/Pend/2012 .09.02.00/6.2/
2013
109 1.01.01 CV. LaBe Pembangunan 1 (satu) Ruang Kelas Baru 425/110/SP/DAK 177.230.000,00 8.861.500,00 2467/LS/1.20 8.861.500,00 - -
(RKB) SDN 9 Banyuasin II Kec. Banyuasin .SD/Pend/2012 .09.02.00/6.2/
II 2013
Halaman 7 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
110 1.01.01 Cv. AILS Pembangunan Gedung Perpustakaan SDN 3 425/111/SP/DAK 177.374.000,00 8.868.700,00 - - 8.868.700,00
Banyuasin II Kecamatan Banyuasin II .SD/Pend/2012
111 1.01.01 CV. RMK Rehabilitasi 4 (empat) Ruang Kelas SDN 7 425/112/SP/DAK 315.565.000,00 15.778.250,00 2391/LS/1.20 15.778.250,00 - -
Banyuasin III Kecamatan Banyuasin III .SD/Pend/2012 .09.02.00/6.2/
2013
112 1.01.01 CV. RF Rehabilitasi 3 (tiga) Ruang Kelas SDN 3 425/113/SP/DAK 256.510.000,00 12.825.500,00 1824/LS/1.20 12.825.500,00 - -
Banyuasin III Kecamatan Banyuasin III .SD/Pend/2012 .09.02.00/6.2/
2013
113 1.01.01 Cv. RJ Rehabilitasi 3 (tiga) Ruang Kelas SDN 11 425/114/SP/DAK 280.155.000,00 14.007.750,00 1825/LS/1.20 14.007.750,00 - -
Banyuasin III Kecamatan Banyuasin III .SD/Pend/2012 .09.02.00/6.2/
2013
114 1.01.01 CV. TP Rehabilitasi 2 (dua) Ruang Kelas SDN 16 425/115/SP/DAK 186.700.000,00 9.335.000,00 2076/LS/1.20 9.335.000,00 - -
Banyuasin III Kecamatan Banyuasin III .SD/Pend/2012 .09.02.00/6.2/
2013
115 1.01.01 CV. AJy Pembangunan 2 (dua) Ruang Kelas Baru 425/116/SP/DAK 300.159.000,00 15.007.950,00 1648/LS/1.20 15.007.950,00 - -
(RKB) SDN 09 Muara Sugihan Kec. Muara .SD/Pend/2012 .09.02.00/6.2/
Sugihan 2013
116 1.01.01 CV. PK Pembangunan 2 (dua) Ruang Kelas Baru 425/117/SP/DAK 290.700.000,00 14.535.000,00 4848/LS/1.20 14.535.000,00 - -
(RKB) SDN 22 Banyuasin III Kecamatan .SD/Pend/2012 .09.02.00/6.2/
Banyuasin III 2013
117 1.01.01 CV. PP Pembangunan 1 (satu) Ruang Kelas Baru 425/118/SP/DAK 147.863.000,00 7.393.150,00 1877/LS/1.20 7.393.150,00 - -
(RKB) SDN 30 Banyuasin III Kec. .SD/Pend/2012 .09.02.00/6.2/
Banyuasin III 2013
118 1.01.01 CV. PL Pembangunan Gedung Perpustakaan SDN 425/119/SP/DAK 143.321.000,00 7.166.050,00 1622/LS/1.20 7.166.050,00 - -
27 Banyuasin III Kecamatan Banyuasin III .SD/Pend/2012 .09.02.00/6.2/
2013
119 1.01.01 CV. TP Rehabilitasi 4 (empat) Ruang Kelas SDN 23 425/120/SP/DAK 316.000.000,00 15.800.000,00 2077/LS/1.20 15.800.000,00 - -
Banyuasin III Kecamatan Banyuasin III .SD/Pend/2012 .09.02.00/6.2/
2013
120 1.01.01 CV. CA Pembangunan Gedung Perpustakaan SDN 425/121/SP/DAK 141.600.000,00 7.080.000,00 1878/LS/1.20 7.080.000,00 - -
01 Betung Kecamatan Betung .SD/Pend/2012 .09.02.00/6.2/
2013
121 1.01.01 CV. CE Rehabilitasi 4 (empat) Ruang Kelas SDN 25 425/122/SP/DAK 281.189.000,00 14.059.450,00 3607/LS/1.20 14.059.450,00 - -
Muara Sugihan Kecamatan Muara Sugihan .SD/Pend/2012 .09.02.00/6.2/
2013
122 1.01.01 CV. Do Pembangunan Gedung Perpustakaan SDN 425/123/SP/DAK 153.200.000,00 7.660.000,00 - - 7.660.000,00
10 Muara Sugihan Kecamatan Muara .SD/Pend/2012
Sugihan
123 1.01.01 CV. CE Pembangunan Gedung Perpustakaan SDN 425/124/SP/DAK 153.205.000,00 7.660.250,00 3606/LS/1.20 7.660.250,00 - -
12 Muara Sugihan Kecamatan Muara .SD/Pend/2012 .09.02.00/6.2/
Sugihan 2013
124 1.01.01 CV. AP Pembangunan 2 (dua) Ruang Kelas Baru 425/125/SP/DAK 300.474.000,00 15.023.700,00 3477/LS/1.20 15.023.700,00 - -
(RKB) SDN 24 Muara Telang Kec. Muara .SD/Pend/2012 .09.02.00/6.2/
Telang 2013
125 1.01.01 CV. JU Pembangunan 2 (dua) Ruang Kelas Baru 425/126/SP/DAK 293.210.000,00 14.660.500,00 1981/LS/1.20 14.660.500,00 - -
(RKB) SDN 24 Rantau Bayur Kec. Rantau .SD/Pend/2012 .09.02.00/6.2/
Bayur 2013
Halaman 8 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
126 1.01.01 CV. NP Pembanguan Gedung Perpustakaan SDN 25 425/127/SP/DAK 177.400.000,00 8.870.000,00 2366/LS/1.20 8.870.000,00 - -
Rantau Bayur Kecamatan Rantau Bayur .SD/Pend/2012 .09.02.00/6.2/
2013
127 1.01.01 CV. HR Pembanguan Gedung Perpustakaan SDN 32 425/128/SP/DAK 177.400.000,00 8.870.000,00 - - 8.870.000,00
Rantau Bayur Kecamatan Rantau Bayur .SD/Pend/2012
128 1.01.01 CV. CSP Rehabilitasi 4 (empat) Ruang Kelas SDN 18 425/129/SP/DAK 294.600.000,00 14.730.000,00 1823/LS/1.20 14.730.000,00 - -
Pulau Rimau Kecamatan Pulau Rimau .SD/Pend/2012 .09.02.00/6.2/
2013
129 1.01.01 CV. CHP Pembangunan 2 (dua) Ruang Kelas Baru 425/130/SP/DAK 299.500.000,00 14.975.000,00 1812/LS/1.20 14.975.000,00 - -
(RKB) SDN 15 Pulau Rimau Kecamatan .SD/Pend/2012 .09.02.00/6.2/
Pulau Rimau 2013
130 1.01.01 CV. PA Pembangunan Gedung Perpustakaan SDN 1 425/131/SP/DAK 176.400.000,00 8.820.000,00 2511/LS/1.20 8.820.000,00 - -
Pulau Rimau Kecamatan Pulau Rimau .SD/Pend/2012 .09.02.00/6.2/
2013
131 1.01.01 CV. Di Pembangunan Gedung Perpustakaan SDN 425/132/SP/DAK 152.000.000,00 7.600.000,00 - - 7.600.000,00
25 Pulau Rimau Kecamatan Pulau Rimau .SD/Pend/2012
132 1.01.01 CV. TW Pembangunan Gedung Perpustakaan SDN 425/133/SP/DAK 142.000.000,00 7.100.000,00 - - 7.100.000,00
17 Rambutan Kecamatan Rambutan .SD/Pend/2012
133 1.01.01 CV. BU Pembangunan 3 (tiga) Ruang Kelas Baru 425/134/SP/DAK 318.480.000,00 15.924.000,00 1946/LS/1.20 15.924.000,00 - -
(RKB) SDN 13 Makarti Jaya Kecamatan .SD/Pend/2012 .09.02.00/6.2/
Makarti Jaya 2013
134 1.01.01 CV. RFg Pembangunan Gedung Perpustakaan SDN 3 425/135/SP/DAK 151.800.000,00 7.590.000,00 3437/LS/1.20 7.590.000,00 - -
Tungkal Ilir Kecamatan Tungkal Ilir .SD/Pend/2012 .09.02.00/6.2/
2013
135 1.01.01 CV. PK Pembangunan 3 (tiga) Ruang Kelas Baru 425/136/SP/DAK 392.217.000,00 19.610.950,00 4847/LS/1.20 19.610.950,00 - -
(RKB) SDN 28 Talang Kelapa Kec. Talang .SD/Pend/2012 .09.02.00/6.2/
Kelapa 2013
136 1.01.01 CV. MU Rehabilitasi 4 (empat) Ruang Kelas SDN 14 425/137/SP/DAK 327.674.000,00 16.383.700,00 - - 16.383.700,00
Air Saleh Kecamatan Air Saleh .SD/Pend/2012
137 1.01.01 CV. Ro Pembangunan Gedung Perpustakaan SDN 9 425/138/SP/DAK 151.392.000,00 7.569.600,00 2588/LS/1.20 7.569.600,00 - -
Air Saleh Kecamatan Air Saleh .SD/Pend/2012 .09.02.00/6.2/
2013
138 1.01.01 CV. CPM Pembangunan Gedung Perpustakaan SDN 425/139/SP/DAK 152.665.000,00 7.633.250,00 2414/LS/1.20 7.633.250,00 - -
19 Muara Padang Kecamatan Muara .SD/Pend/2012 .09.02.00/6.2/
Padang 2013
139 1.01.01 CV. Si Pembangunan 3 (tiga) Ruang Kelas Baru 425/140/SP/DAK 403.400.000,00 20.170.000,00 2082/LS/1.20 20.170.000,00 - -
(RKB) SDN 07 Tanjung Lago Kec. Tanjung .SD/Pend/2012 .09.02.00/6.2/
Lago 2013
140 1.01.01 CV. Be Pembangunan 1 (satu) Ruang Kelas Baru 425/141/SP/DAK 151.580.000,00 7.579.000,00 4699/LS/1.20 7.579.000,00 - -
(RKB) SDN 17 Tanjung Lago Kec. Tanjung .SD/Pend/2012 .09.02.00/6.2/
Lago 2013
141 1.01.01 CV. AiP Pembangunan 2 (dua) Ruang Kelas Baru 425/101/SP/DAK 289.100.000,00 14.455.000,00 4168/LS/1.20 14.455.000,00 - -
(RKB) SDN 20 Betung Kecamatan Betung .SD/Pend/2012 .09.02.00/6.2/
2013
Halaman 9 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
142 1.01.01 CV. Be Pembangunan Gedung Perpustakaan SDN 425/143/SP/DAK 142.440.000,00 7.122.000,00 5135//LS/1.2 7.122.000,00 - -
20 Talang Kelapa Kecamatan Talang .SD/Pend/2012 0.09.02.00/6.
Kelapa 2/2013
143 1.01.01 CV. PI Pembangunan Gedung Perpustakaan SDN 7 425/144/SP/DAK 151.265.000,00 7.563.250,00 2413/LS/1.20 7.563.250,00 - -
Tungkal Ilir Kecamtan Tungkal Ilir .SD/Pend/2012 .09.02.00/6.2/
2013
144 1.01.01 CV. RJ Rehabilitasi 3 Ruang Kelas SDN 10 425/153/SP/DAK 236.500.000,00 11.825.000,00 1820/LS/1.20 11.825.000,00 - -
Sembawa Kec. Sembawa .SD/Pend/2012 .09.02.00/6.2/
2013
145 1.01.01 CV. PL Reahabilitasi 3 Ruang Kelas SDN 20 425/154/SP/DAK 237.500.000,00 11.875.000,00 1876/LS/1.20 11.875.000,00 - -
Sembawa Kec. Sembawa .SD/Pend/2012 .09.02.00/6.2/
2013
146 1.01.01 CV APe Pembangunan 2 Ruang Kelas Baru ( RKB ) 425/155/SP/DAK 292.700.000,00 14.635.000,00 3324/LS/1.20 14.635.000,00 - -
SDN 27 Betung Kec. Betung .SD/Pend/2012 .09.02.00/6.2/
2013
147 1.01.01 CV. SB Rehabilitasi 4 Ruang Kelas SDN 2 Muara 425/156/SP/DAK 281.200.000,00 14.060.000,00 1650/LS/1.20 14.060.000,00 - -
Sugihan Kec. Muara Sugihan .SD/Pend/2012 .09.02.00/6.2/
2013
148 1.01.01 CV. HA. P Pembangunan 2 Ruang Kelas ( RKB) SDN 425/157/SP/DAK 291.800.000,00 14.590.000,00 6153/LS/1.20 14.590.000,00 - -
18 Rantau Bayur Kec. Rantau Bayur .SD/Pend/2012 .09.02.00/6.2/
2013
149 1.01.01 CV. MJ Rehabilitasi 4 Ruang Kelas SDN 24 425/158/SP/DAK 226.800.000,00 11.340.000,00 2219/LS/1.20 11.340.000,00 - -
Rambutan Kec. Rambutan .SD/Pend/2012 .09.02.00/6.2/
2013
150 1.01.01 CV. KY Reahabilitasi 3 Ruang Kelas SDN 9 425/159/SP/DAK 237.000.000,00 11.850.000,00 2375/LS/1.20 11.850.000,00 - -
Tungkal Ilir Kec. Tungkal Ilir .SD/Pend/2012 .09.02.00/6.2/
2013
151 1.01.01 CV. RJ Rehabilitasi 4 Ruang Kelas SDN 7 Suak 425/160/SP/DAK 279.335.000,00 13.966.750,00 1822/LS/1.20 13.966.750,00 - -
Tapeh Kec. Suak Tapeh .SD/Pend/2012 .09.02.00/6.2/
2013
152 1.01.01 PT. T& R Pembangunan Gedung Perpustakaan SDN 425/161/SP/DAK 154.200.000,00 7.710.000,00 2087/LS/1.20 7.710.000,00 - -
16 Banyuasin II Kecamayan Banyuasin II .SD/Pend/2012 .09.02.00/6.2/
2013
153 1.01.01 PT. T& R Rehabilitasi 1 (satu) Ruang Kelas SDN 11 425/162/SP/DAK 94.500.000,00 4.725.000,00 2086/LS/1.20 4.725.000,00 - -
Banyuasin I Kecamatan Banyuasin I .SD/Pend/2012 .09.02.00/6.2/
2013
154 1.01.01 CV. RJ Rehabilitasi 2 (dua) Ruang Kelas SDN 07 425/163/SP/DAK 189.000.000,00 9.450.000,00 1742/LS/1.20 9.450.000,00 - -
Betung Kecamatan Betung .SD/Pend/2012 .09.02.00/6.2/
2013
155 1.01.01 CV. CJP Rehabilitasi 2 (dua) Ruang Kelas SDN 11 425/164/SP/DAK 188.700.000,00 9.435.000,00 2079/LS/1.20 9.435.000,00 - -
Suak Tapeh Kecamatan Suak Tapeh .SD/Pend/2012 .09.02.00/6.2/
2013
156 1.01.01 CV. MPN Pembangunan Gedung Perpustakaan SDN 425/165/SP/DAK 154.300.000,00 7.715.000,00 1846/LS/1.20 7.715.000,00 - -
11 Muara Telang Kecamatan Muara Telang .SD/Pend/2012 .09.02.00/6.2/
2013
157 1.01.01 CV. SmJ Pembangunan Gedung Perpustakaan SDN 425/166/SP/DAK 154.200.000,00 7.710.000,00 3716/LS/1.20 7.710.000,00 - -
09 Muara Telang Kecamatan Muara Telang .SD/Pend/2012 .09.02.00/6.2/
2013
Halaman 10 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
158 1.01.01 CV. LB Pembangunan 1 (satu) Ruang Kelas SDN 425/167/SP/DAK 149.295.000,00 149.295.000,00 0384/LS/1.20 149.295.000,00 - -
18 Rambuatan Kecamatan Rambuatan .SD/Pend/2012 .09.02.00/6.2/
2013 &
3082/LS/1.
20.09.02.00/6
.2/2013
159 1.01.01 CV. KY Pembangunan Gedung Perpustakaan SDN 425/168/SP/DAK 144.310.000,00 7.215.500,00 2397/LS/1.20 7.215.500,00 - -
22 Rambuatan Kecamatan Rambuatan .SD/Pend/2012 .09.02.00/6.2/
2013
160 1.01.01 CV. LiBe Pembangunan Gedung Perpustakaan SDN 425/169/SP/DAK 154.250.000,00 7.712.500,00 4004/LS/1.20 7.712.500,00 - -
02 Makarti Jaya Kecamatan Makarti Jaya .SD/Pend/2012 .09.02.00/6.2/
2013
161 1.01.01 CV. LiBe Pembangunan Gedung Perpustakaan SDN 425/170/SP/DAK 154.150.000,00 7.707.500,00 4005/LS/1.20 7.707.500,00 - -
06 Makarti Jaya Kecamatan Makarti Jaya .SD/Pend/2012 .09.02.00/6.2/
2013
162 1.01.01 CV. AgSe Pembangunan Gedung Perpustakaan SDN 425/171/SP/DAK 144.402.000,00 7.220.100,00 2361/LS/1.20 7.220.100,00 - -
16 Talang Kelapa Kecamatan Talang .SD/Pend/2012 .09.02.00/6.2/
Kelapa 2013
163 1.01.01 CV. GMs Pembangunan Gedung Perpustakaan SDN 425/172/SP/DAK 154.255.000,00 7.712.750,00 1835/LS/1.20 7.712.750,00 - -
15 Air Saleh Kecamatan Air Saleh .SD/Pend/2012 .09.02.00/6.2/
2013
164 1.01.01 CV. KJ Pembangunan Gedung Perpustakaan SDN 425/173/SP/DAK 154.100.000,00 7.705.000,00 4167/LS/1.20 7.705.000,00 - -
12 Muara Padang Kecamatan Muara .SD/Pend/2012 .09.02.00/6.2/
Padang 2013
165 1.01.01 CV. KPM Pembangunan Gedung Perpustakaan SDN 425/174/SP/DAK 149.180.000,00 7.459.000,00 2377/LS/1.20 7.459.000,00 - -
08 Tanjung Lago Kecamatan Tanjung Lago .SD/Pend/2012 .09.02.00/6.2/
2013
166 1.01.01 CV.GMJ Perencanaan Pembangunan Unit Sekolah 02/02/PPK- 24.820.000,00 24.820.000,00 1573/LS/1.20 24.820.000,00 - -
Baru (USB) SMAN berupa Gambar,RAB, PL.JK/Pend/2012 .09.02.00/6.2/
dan RKS 2013
167 1.02.02 CV. HJ Keg. Pengadaan Alat-Alat Kesehatan 445/431/SPK/RS 76.324.000,00 - - 76.324.000,00 76.324.000,00
Rumah Sakit Tahun Anggaran 2013 UD/2013
168 1.02.02 CV. IK Keg. Pembangunan Gedung Unit Gawat 445/129/PPK/RS 1.442.900.000,00 72.145.000,00 2568/LS/1.20 72.145.000,00 - -
Darurat (UGD) RSUD Kab. Banyuasin UD/2012 .09.02.00/6.2/
2013
169 1.03.01 KSM Tpd Pembangunan Sanitas Lingkungan Berbasis .02/01/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Salek Jaya SLBM/PUCK/20
Kec. Air Salek 13 Tgl 08 Juli
2013
Halaman 11 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
170 1.03.01 KSM. MB Pembangunan Sanitas Lingkungan Berbasis 02/02/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Saleh Mulya SLBM/PUCK/20
Kec. Air Saleh 13 Tgl 08 Juli
2013
171 1.03.01 KSM M Pembangunan Sanitas Lingkungan Berbasis 02/03/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Sido Harjo SLBM/PUCK/20
Kec. Air Saleh 13 Tgl 08 Juli
2013
172 1.03.01 KSM. Abd Pembangunan Sanitas Lingkungan Berbasis 02/04/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Teluk SLBM/PUCK/20
Tenggulang Kec. Tungkal Ilir 13 Tgl 08 Juli
2013
173 1.03.01 KSM Se Pembangunan Sanitas Lingkungan Berbasis 02/05/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Bentayan SLBM/PUCK/20
Kec. Tungkal Ilir 13 Tgl 08 Juli
2013
174 1.03.01 KSM. Tld Pembangunan Sanitas Lingkungan Berbasis 02/06/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Karang Anyar SLBM/PUCK/20
Kec. Tungkal Ilir 13 Tgl 08 Juli
2013
175 1.03.01 KSM. Mng Pembangunan Sanitas Lingkungan Berbasis 02/07/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Karang Asem SLBM/PUCK/20
Kec. Tungkal Ilir 13, Tgl 08 Juli
2013
176 1.03.01 KSM Se Pembangunan Sanitas Lingkungan Berbasis 02/08/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Indra Pura SLBM/PUCK/20
Kec. Muara Sugihan 13 Tgl 08 Juli
2013
177 1.03.01 KSM. RS Pembangunan Sanitas Lingkungan Berbasis 02/09/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Margo Rukun SLBM/PUCK/20
Kec. Muara Sugihan 13 Tgl 08 Juli
2013
178 1.03.01 KSM SJ Pembangunan Sanitas Lingkungan Berbasis 02/10/PPK 145.943.600,00 - - 43.783.080,00 43.783.080,00
Masyarakat / MCK Plus Desa Rejo Sari SLBM/PUCK/20
Kec. Muara Sugihan 13 Tgl 08 Juli
2013
179 1.03.01 CV. YMM Perbaikan Pipa PDAM Jalan Pangeran Ayin 06/SPK/APBD 199.570.000,00 - - 199.570.000,00 199.570.000,00
Simpang Talang Keramat Kec. Talang Kelapa P/PPK
19/PUCK/2013
180 1.03.01 CV. YMM Perbaikan Pipa PDAM Komplek Azhar, 07/SPK/APBD- 199.540.000,00 - - 199.540.000,00 199.540.000,00
Griya Damai, Sunter, Avila dan Bank P/PPK-
Sumsel Kec. Talang Kelapa 19/PUCK/2013
Tgl 04 Nov 2013
181 1.03.01 CV. CZ Pengecoran Jalan Lingkungan Putra Buana 34/SPK/PPK 174.415.000,00 - - 174.415.000,00 174.415.000,00
Darat Desa Sungsang III Kec. Banyuasin II 17/PUCK/2013
Tgl 28 Agustus
2013
Halaman 12 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
182 1.03.01 CV. AS Pengecoran Jalan Lingkungan Dalam Desa 18/SPK/PPK 112.073.000,00 - - 112.073.000,00 112.073.000,00
Suka Karya Kec. Tungkal Ilir 06/PUCK/2013
Tgl 06 Maret
2013
183 1.03.01 CV. SmJ Pengecoran Jalan Lingkungan Desa Sumber 09/SPK/APBD- 99.461.000,00 - - 99.461.000,00 99.461.000,00
Mulya Jalur 6 Jembatan 3 Kec. Muara Telang P/PPK-
11/PUCK/2013
Tgl 18 Nov 2013
184 1.03.01 CV. HBS Pengecoran Halaman Kantor Desa Karang 05/SPK/APBD 112.000.000,00 - - 112.000.000,00 112.000.000,00
Asem Kec. Tungkal Ilir P/PPK
07/PUCK/2013
Tgl 18 Nov 2013
185 1.03.01 CV. LaBe Pembangunan Jembatan Penghubung Di 06/SPK/APBD 124.472.000,00 - - 124.472.000,00 124.472.000,00
Desa Tirto Harjo Kec. Muara Padang P/PPK
18/PUCK/2013
Tgl 04 Nov 2013
186 1.03.01 CV. DPS Pembangunan Jembatan Penghubung Desa 07/SPK/APBD 124.472.000,00 - - 124.472.000,00 124.472.000,00
Daya Makmur Kec. Muara Padang P/PPK-
18/PUCK/2013
04 Nov 2013
187 1.03.01 CV. CGP DED Kantor PDAM Kabupaten Banyuasin 13/SPK/APBD- 49.770.000,00 - - 49.770.000,00 49.770.000,00
P/PPK-
01/PUCK/2013
18 Nov 2013
188 1.03.01 CV. PCt DED Akses PDAM ke RSUD Kabupaten 12/SPK/APBD- 49.810.000,00 - - 49.810.000,00 49.810.000,00
Banyuasin P/PPK-
01/PUCK/2013
18 Nov 2013
189 1.03.01 ID Pelanggan Tagihan Listrik PDAM IKK Merah Mata 231.292.281,00 - - 231.292.281,00 231.292.281,00
14.110.2556 (Bulan Desember 2013)
82.7
169 1.03.01 CV. EC Pembuatan Papan Nama SPPN Sembawa 11/02/SPK/PPK- 84.418.000,00 4.220.900,00 7230/LS/1.20 4.220.900,00 - -
P3L.I/PUCK/201 .09.02.00/6.2/
2 TGL. 12-09-12 2013
170 1.03.01 CV. RK Pembangunan Gedung Serbaguna Kec. 01/03/SPK/PPK- 173.672.000,00 8.683.600,00 5404/LS/1.20 8.683.600,00 - -
Muara Telang (Tahap I) OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 13-09-2012 2013
171 1.03.01 CV. EJ Pembangunan Gedung Serbaguna desa Taja 10/03/PPK- 293.991.000,00 14.699.550,00 1717/LS/1.20 14.699.550,00 - -
Indah Kec. Betung (* P3L.II/PU.CK/20 .09.02.00/6.2/
12 Tgl 27 2013
Agustus 2012
172 1.03.01 CV. RM Pembangunan Gedung Serbaguna Desa 03/12/PPK/PUC 195.985.000,00 9.799.250,00 5473/LS/1.20 9.799.250,00 - -
Lubuk Lancang Kec. Suak Tapeh K/2012 Tgl 27 .09.02.00/6.2/
Agustus 2012 2013
173 1.03.01 CV. HR Pembangunan Gedung Serbaguna Desa 03/14/PPK/PUC 146.998.000,00 7.349.900,00 4958/LS/1.20 7.349.900,00 - -
Durian Daun Kec. Suak Tapeh (lanjutan) K/2012, Tgl. 27- .09.02.00/6.2/
08-2012 2013
Halaman 13 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
174 1.03.01 CV. JP Pembangunan Gedung Serbaguna Desa 13/03/SPK/PPK/ 74.457.000,00 3.722.850,00 1974/LS/1.20 3.722.850,00 - -
Talang Ipuh Kec. Suak Tapeh (Lanjutan) PUCK/2012 Tgl .09.02.00/6.2/
10 September 2013
2012
175 1.03.01 CV. CM Rehabilitasi Gedung Serbaguna Kec. Muara 06/03/PPK- 293.787.000,00 14.689.350,00 5081/LS/1.20 14.689.350,00 - -
Padang P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 27/8/ 2012 2013
176 1.03.01 CV. CG Pembangunan Gedung Pertemuan Desa 07/03/SPK/PPK- 109.284.000,00 5.464.200,00 3551/LS/1.20 5.464.200,00 - -
Rimba Terap Kec. Suak Tapeh P3L.II/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Okt 2013
2012
177 1.03.01 CV. CG Rehab Balai Desa Serbaguna Desa Pulau 02/03/SPK/PPK- 199.211.000,00 9.960.550,00 3586/LS/1.20 9.960.550,00 - -
Harapan Kec. Sembawa P3L/PUCK/2012, .09.02.00/6.2/
15 Oktober 2012 2013
178 1.03.01 CV. BPD Pembangunan Tempat Wudhu dalam Desa 03/03/SPK/PPK- 99.317.000,00 4.965.850,00 4296/LS/1.20 4.965.850,00 - -
Suka Pindah Kec. Rambutan PP.III/PUCK/201 .09.02.00/6.2/
2 TGL. 17-09-12 2013
179 1.03.01 CV. NPM Pembangunan Asrama Santri Putra Ponpes 12/03/SPK/PPK- 197.336.000,00 9.866.800,00 2665/LS/1.20 9.866.800,00 - -
Darul Ulum Kec. Pulau Rimau P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl 12-10-2012 2013
180 1.03.01 CV. SIT Pembangunan Gedung Badan Pelayanan 03/16/PPK/PUC 1.960.522.000,00 98.026.100,00 3323/LS/1.20 98.026.100,00 - -
Terpadu (BPT) Kabupaten Banyuasin K/2012 Tgl 27-8- .09.02.00/6.2/
(tahap I) 2012 2013
181 1.03.01 CV. AS Pembangunan Kantor Kelurahan Seterio 28/03/PPK- 146.989.000,00 7.349.450,00 4579/LS/1.20 7.349.450,00 - -
Kecamatan Banyuasin III (tahap I) P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 27-08- 2013
2012
182 1.03.01 CV. Ha Penambahan Ruang Gedung DPPKAD 03/15/PPK/PUC 734.226.000,00 36.711.300,00 2422/LS/1.20 36.711.300,00 - -
Kabupaten Banyuasin K/2012 Tanggal .09.02.00/6.2/
27 Agustus 2012 2013
183 1.03.01 CV. BP Renovasi Ruang KM/WC Kantor 03/02/SPK/PPK- 99.318.000,00 4.965.900,00 3872/LS/1.20 4.965.900,00 - -
BAPPEDA Kabupaten Banyuasin TRTB.I/PUCK/20 .09.02.00/6.2/
12 Tgl 02 Juli 2013
2012
184 1.03.01 CV. EC Rehabilitasi Atap Kantor Bupati 30/03/PPK- 297.971.000,00 14.898.550,00 7231/LS/1.20 14.898.550,00 - -
P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL. 29-10- 2013
12
185 1.03.01 CV. BP Penambahan WC dan Rehab Ruang Rapat 01/03/SPK/PPK- 148.889.000,00 7.444.450,00 7170/LS/1.20 7.444.450,00 - -
Kantor BAPPEDA dan Penanaman Modal TRTB.II/PUCK/2 .09.02.00/6.2/
Kabupaten Banyuasin 012 TGL 19-10- 2013
12
Halaman 14 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
186 1.03.01 CV. MB Pembangunan Gedung Narkoba Type 46 02/03/SPPBJ/PP 198.419.000,00 9.920.950,00 2688/LS/1.20 9.920.950,00 - -
K- .09.02.00/6.2/
TRTB.II/PUCK/2 2013
012 Tgl 15
Oktober 2012
187 1.03.01 CV. KY Pembangunan Gedung KPU Kabupaten 10/03/SPK/PPK- 198.760.000,00 9.938.000,00 2684/LS/1.20 9.938.000,00 - -
Banyuasin (Tahap I) PP.V/PUCK/2012 .09.02.00/6.2/
Tgl 15 Oktober 2013
2012
188 1.03.01 CV. KSD S Rehabilitasi Ruang Asissten II 07/03/PPK- 199.156.000,00 9.957.800,00 7216/LS/1.20 9.957.800,00 - -
TRTB.II/PUCK/2 .09.02.00/6.2/
012 TGL 12-10- 2013
12
189 1.03.01 CV. EC Rehab Plapon dan Pembuatan Pintu Masuk 12/03/PPK- 197.060.000,00 9.853.000,00 7212/LS/1.20 9.853.000,00 - -
Kantor Bupati Banyuasin PP.V/PUCK/2012 .09.02.00/6.2/
TGL. 12-10-12 2013
190 1.03.01 CV. EC Pemasangan Paving Blok Rumah Dinas 14/03/PPK- 147.010.000,00 7.350.500,00 7226/LS/1.20 7.350.500,00 - -
Sekda Kabupaten Banyuasin PP.V/PUCK/2012 .09.02.00/6.2/
TGL. 12-10-12 2013
191 1.03.01 Fa. KLR Rehabilitasi TK Darmawanita Pangkalan 13/03/SPK/PPK- 198.365.000,00 9.918.250,00 2778/LS/1.20 9.918.250,00 - -
Balai Kec. Banyuasin III PP.V/PUCK/2012 .09.02.00/6.2/
Tgl 15 Oktober 2013
2012
192 1.03.01 CV. AS Rehabilitasi Sarana dan Prasaran Kantor 03/10/PPK/PUC 146.988.000,00 7.349.400,00 4578/LS/1.20 7.349.400,00 - -
Camat Talang Kelapa Kec. Talang Kelapa K/2012 TGL 27- .09.02.00/6.2/
08-2012 2013
193 1.03.01 CV. EC Pembangunan TK Adyaksa IV Sukajadi 04/03//PPK/TRT 196.731.000,00 9.836.550,00 7214/LS/1.20 9.836.550,00 - -
Kec. Talang Kelapa (lanjutan) B.II/PUCK/2012, .09.02.00/6.2/
Tgl. 29-08-2012 2013
194 1.03.01 CV. AS Rehabilitasi Sarana dan Prasaran Kantor 01/03./SPK/PPK- 198.770.000,00 9.938.500,00 4583/LS/1.20 9.938.500,00 - -
Camat Talang Kelapa Kec. Talang Kelapa P3L.III/PUCK/20 .09.02.00/6.2/
(Lanjutan) 12, Tgl. 15-10- 2013
2012
195 1.03.01 CV. AS Rahabilitasi Sarana dan Prasarana Balai 01/03./SPK/PPK- 198.750.000,00 9.937.500,00 4615/LS/1.20 9.937.500,00 - -
Serba guna Kantor Camat Tl. Kelapa P3L.III/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
196 1.03.01 CV. LK Pembangunan Mako Pos Polair upang T. 12/02/PPK- 296.090.000,00 14.804.500,00 2799/LS/1.20 14.804.500,00 - -
170 Kecamatan Makarti Jaya (Tahap II) TRTB.II/PUCK/2 .09.02.00/6.2/
012 Tanggal 01 2013
Oktober 2012
197 1.03.01 PT. SPK Pembangunan Prasarana Pemerintahan 03/07/PPK/PUC 1.618.560.000,00 80.928.000,00 2415/LS/1.20 80.928.000,00 - -
Daerah Kecamatan Sembawa K/2012 Tanggal .09.02.00/6.2/
26 Juli 2012 2013
198 1.03.01 CV. CG Pembangunan Gedung PAUD Desa 12/03/PPK/PPLi- 49.293.000,00 2.464.650,00 3557/LS/1.20 2.464.650,00 - -
Rejodadi Kec. Sembawa P3L.I/PUCK/201 .09.02.00/6.2/
2, 25 Oktober 2013
2012
Halaman 15 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
199 1.03.01 CV. PT Pembangunan Prasarana Pemerintahan 1.614.720.000,00 80.736.000,00 1932/LS/1.20 80.736.000,00 - -
Daerah Kecamatan Suak Tapeh 03/08/PPK/PUC .09.02.00/6.2/
K/2012 tanggal 2013
27 Juli 2012
200 1.03.01 CV. Su Pembangunan Prasarana dan Sarana 03/09/PPK/PUC 1.844.725.000,00 92.236.250,00 2416/LS/1.20 92.236.250,00 - -
Pemerintahan Kantor Kecamatan Muara K/2012 Tanggal .09.02.00/6.2/
Padang 26 Juli 2012 2013
201 1.03.01 CV. CG Rehabilitasi Sarana dan Prasarana Kantor 12/03/SPK/PPK- 199.825.000,00 9.991.250,00 3553/LS/1.20 9.991.250,00 - -
Camat Betung P3L.IV/PUCK/20 .09.02.00/6.2/
12 Tgl 15 2013
Oktober 2012
202 1.03.01 CV. JIL Pembangunan Los Pasar/Kalangan Desa 04/03/SPK/PPK- 197.380.000,00 9.869.000,00 3214/LS/1.20 9.869.000,00 - -
Telang Karya Kec. Muara Telang OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 13 2013
September 2012
203 1.03.01 CV. NPM Pembangunan Rumah Jabatan Komendan 16/03/SPK/PPK- 371.200.000,00 18.560.000,00 2666/LS/1.20 18.560.000,00 - -
Kodim Kel. Pangkalan Balai Kec. PP.III/PUCK/201 .09.02.00/6.2/
Banyuasin III 2 Tgl. 27-08-2012 2013
204 1.03.01 CV. CZ Rehab Komplek Rumah Jabatan Kejaksaan 01/03/SPK/PPK- 195.958.000,00 9.797.900,00 7215/LS/1.20 9.797.900,00 - -
Negeri Pangkalan Balai TRTB.II/PUCK/2 .09.02.00/6.2/
012 TGL. 17-09- 2013
12
205 1.03.01 CV. KB Pembangunan Rumah Dinas Perwira Polres 11/03/PPK- 392.076.000,00 19.603.800,00 - - 19.603.800,00
Banyuasin TRTB.II/PUCK/2
012 Tgl 29-08-
2012
206 1.03.01 CV. Ds Pemasangan Conblock lapangan Gedung 12/03/SPK/PPK- 74.278.000,00 3.713.900,00 3000/LS/1.20 3.713.900,00 - -
Serbaguna lubuk Karet Kec. Suak Tapeh OP.III/PUCK/201 .09.02.00/6.2/
2, Tgl. 12-09- 2013
2012
207 1.03.01 CV. CG Pengecoran Halaman Puskesmas Betung 13/03/SPK/PPK- 49.935.000,00 2.496.750,00 3558/LS/1.20 2.496.750,00 - -
Kota Kelurahan Betung P3L.IV/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
208 1.03.01 CV. NPM Penataan Halaman dan Pembuatan Papan No.05/03/PPK- 99.330.000,00 4.966.500,00 2561/LS/!.20. 4.966.500,00 - -
Nama Gedung Kuartir Cabang Pramuka TRTB.II/PUCK/2 09.02.00/6.2/
Kabupaten Banyuasin 012 Tgl 15-10- 2013
2012
209 1.03.01 CV. MB Pembangunan Pelantaran Halaman Ujian 06/03/SPPBJ/PP 99.302.000,00 4.965.100,00 2681/LS/1.20 4.965.100,00 - -
SIM A dan C K- .09.02.00/6.2/
TRTB.II/PUCK/2 2013
012 Tgl 15
Oktober 2012
210 1.03.01 CV. IP Pembangunan Pagar Pemakaman Umum 05/03/PPK.TRTB 49.396.000,00 2.469.800,00 4166/LS/1.20 2.469.800,00 - -
Ds. Tebing Abang Kec. Rantau Bayur .II/PUCK/2012, .09.02.00/6.2/
Tgl. 17-09-2012 2013
Halaman 16 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
211 1.03.01 CV. AS Pembangan Pagar Kantor Lurah Talang 14/03/SPK/PPK- 49.415.000,00 2.470.750,00 4617/LS/1.20 2.470.750,00 - -
Keramat Kec. Talang Kelapa OP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 14-09-2012 2013
212 1.03.01 CV. BP Rehabilitasi Siring dan Penataan Halaman 15/03/SPK/PPK- 99.546.000,00 4.977.300,00 3873/LS/1.20 4.977.300,00 - -
Parkir Dinas Pekerjaan Umum Cipta Karya PP.V/PUCK/2012 .09.02.00/6.2/
Tgl 15-10-2012 2013
213 1.03.01 CV. NP Pembuatan Tugu batas dusun dalam Desa 15/03/SPK/PPK- 49.437.000,00 2.471.850,00 - - 2.471.850,00
Mulia Sari Kecamatan Tanjung Lago (* OP.III/PUCK/201
2, Tgl. 14-09-
2012
214 1.03.01 CV. AS Pembangunan Gerbang Batas Desa Antara 31/03/SPK/PPK- 49.470.000,00 2.473.500,00 4584/LS/1.20 2.473.500,00 - -
Desa Sukaraja dengan Desa Lubuk Lancang P3L.III/PUCK/20 .09.02.00/6.2/
Kec. Suak Tapeh 12 Tgl 10 2013
September 2012
215 1.03.01 CV. BH Pembangunan MCK dalam Desa Suka 01/03/SPK/PPK- 194.464.000,00 9.723.200,00 2508/LS/1.20 9.723.200,00 - -
Pindah Kec. Rambutan (* PP.II/PUCK/2012 .09.02.00/6.2/
Tgl 24-09-2012 2013
216 1.03.01 CV. IP Pembangunan MCK dalam Desa Sungai 02/03/SPK/PPK- 74.396.000,00 3.719.800,00 3663/LS/1.20 3.719.800,00 - -
Naik Kec. Rantau Bayur (* PP.II/PUCK/2012 .09.02.00/6.2/
Tgl 24-09-2012 2013
217 1.03.01 CV. IP Pembangunan MCK dalam Desa Sejagung 03/03/SPK/PPK- 74.385.000,00 3.719.250,00 3625/LS/1.20 3.719.250,00 - -
Kec. Rantau Bayur (* PP.II/PUCK/2012 .09.02.00/6.2/
TGL 24-09-12 2013
218 1.03.01 PT. PDR Optimaliasi Sarana Air Bersih IKK 3.429.775.000,00 171.488.750,00 2217/LS/1.20 171.488.750,00 - -
Pangkalan Balai, Lokasi Lubuk Saung, 02/01/PPK/PUC .09.02.00/6.2/
Regan Agung, Plajau Ilir, Talang Bayas, K/2012, 26 Juli 2013
Talang Gebang, Talang Siring dan Lebung 2012
219 1.03.01 PT. DU Optimaliasi Sarana Air Bersih IKK Talang 03/01/PPK/PUC 4.997.685.000,00 249.884.250,00 5369/LS/1.20 249.884.250,00 - -
Kelapa, Lokasi Kenten dan Merah Mata K/2012 tgl. 26-07- .09.02.00/6.2/
2012,ADD 2013
03/01.A/PPK/PU
CK/2012 tgl 24-
09-2012
220 1.03.01 PT. TJC Optimaliasi Sarana Air Bersih IKK Betung, 03/02/PPK/PUC 3.135.772.000,00 156.788.600,00 2417/LS/1.20 156.788.600,00 - -
Lokasi Betung K/2012 tgl 26 Juli .09.02.00/6.2/
20 2013
221 1.03.01 PT. MJA Optimaliasi Sarana Air Bersih IKK 01/03/PPK- 1.372.600.000,00 68.630.000,00 2398/LS/1.20 68.630.000,00 - -
Mariana, Lokasi Sungai Rebo OP.I/PUCK/2012 .09.02.00/6.2/
tanggal 27 2013
Agustus 2012
222 1.03.01 CV. IM Optimaliasi Sarana Air Bersih IKK Makarti 03/03/PPK- 341.934.000,00 17.096.700,00 2861/LS/1.20 17.096.700,00 - -
Jaya Lokasi Makarti Jaya OP.I/PUCK/2012, .09.02.00/6.2/
Tgl. 27-08-2012 2013
Halaman 17 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
223 1.03.01 CV. AS Optimaliasi Sarana Air Bersih IKK Tungkal 05/03/PPK- 342.820.000,00 17.141.000,00 4582/LS/1.20 17.141.000,00 - -
Ilir, Lokasi Tungkal Ilir OP.I/PUCK/2012 .09.02.00/6.2/
TGL 27-08-12 2013
224 1.03.01 CV. AJM Penambahan Bak Resevoar IKK Rambutan 02/03/PPK- 843.171.000,00 42.158.550,00 5635/LS/1.20 42.158.550,00 - -
Lokasi Sungai Pinang OP.I/PU.CK/2012 .09.02.00/6.2/
tgl. 27-08-2012 2013
225 1.03.01 CV. TPP Pembangunan Pipa Distribusi Air Bersih 26/03/PPK- 1.994.000.000,00 99.700.000,00 2394/LS/1.20 99.700.000,00 - -
Lokasi Suak Tapeh P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL 26-10-12 2013
226 1.03.01 CV. CZ Pengecoran Jalan Lingkungan Dalam Desa 23/03/PPK- 244.994.000,00 12.249.700,00 2745/LS/1.20 12.249.700,00 - -
Lubuk Saung Regan Agung Kec. Banyuasin P3L.III/PUCK/20 .09.02.00/6.2/
III(* 12 TGL. 27-09- 2013
12
227 1.03.01 CV. APe Pengecoran Jalan Lingkungan dalam Desa 29/03/PPK-P3L 243.995.000,00 12.199.750,00 2743/LS/1.20 12.199.750,00 - -
Sidang Mas Kec. Banyuasin III (* III/PUCK/2012 .09.02.00/6.2/
Tgl 25 Oktober 2013
2012
228 1.03.01 CV. APe Pengecoran Jalan Lingkungan dalam Desa 25.a/03/SPK/PPK- 147.651.000,00 7.382.550,00 2744/LS/1.20 7.382.550,00 - -
Rimba Alai Kec. Banyuasin III (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 10-10- 2013
2012
229 1.03.01 CV. BU Pengecoran Jalan Lingkungan dalam Desa 09/03/PPK- 149.328.000,00 7.466.400,00 1617/LS/1.20 7.466.400,00 - -
Plajau Ulu menuju SD Kec. Banyuasin III TRTB.III/PUCK/ .09.02.00/6.2/
(* 2012 Tgl 03 Sept 2013
2012
230 1.03.01 CV. PI Pengecoran Jalan Lingkungan dalam Desa 28/03/SPK/PPK- 50.512.000,00 2.525.600,00 - - 2.525.600,00
Plajau Ilir menuju SD Kec. Banyuasin III (* P3L.III/PUCK/20
12, Tgl. 15-10-
2012
231 1.03.01 CV. BT Pengecoran Lorong Inpres Desa Ujung 29/03/SPK/PPK- 147.743.000,00 7.387.150,00 5639/LS/1.20 7.387.150,00 - -
Tanjung Kec. Banyuasin III P3L/PUCK/2012, .09.02.00/6.2/
Tgl. 03-09-2012 2013
232 1.03.01 CV. RMK Pengecoran Lorong Assholihin Kel. 01/03/SPK/PPK- 99.318.000,00 4.965.900,00 0549/LS/1.20 4.965.900,00 - -
Kedondong Raye Kec. Banyuasin III TRTB.III/PUCK/ .09.02.00/6.2/
(Lanjutan) 2012 tanggal 15 2013
Juni
233 1.03.01 CV. LS Pengecoran Jalan Bukit Indah Lorong H. 18/03/SPK/PPK- 197.120.000,00 9.856.000,00 2389/LS/1.20 9.856.000,00 - -
Sa'ari Kec. Banyuasin III (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 10 Sep 2013
2012
234 1.03.01 CV. LS Pengecoran Jalan Lingkungan dalam 19/03/PPK- 198.576.000,00 9.928.800,00 6184/LS/1.20 9.928.800,00 - -
Kelurahan Mulya Agung Kec. Banyuasin III P3L.III/PUCK/20 .09.02.00/6.2/
(* 12, Tgl. 03-09- 2013
2012
Halaman 18 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
235 1.03.01 CV. CZ Pengecoran Jalan menuju SMK Kelurahan 20/03/SPK/PPK- 195.600.000,00 9.780.000,00 7211/LS/1.20 9.780.000,00 - -
Seterio Kec. Banyuasin III (* P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL 03-09-12 2013
236 1.03.01 CV. BU Pengecoran Lorong Tenang Kelurahan 04/03/PPK- 199.361.000,00 9.968.050,00 1619/LS/1.20 9.968.050,00 - -
Seterio Kec. Banyuasin III (* TRTB.III/PUCK/ .09.02.00/6.2/
2012 Tgl 03 Sept 2013
2012
237 1.03.01 CV. CZ Pengecoran Jalan Lingkungan Fathul Mu'in 22/03/SPK/PPK- 195.933.000,00 9.796.650,00 7210/LS/1.20 9.796.650,00 - -
Tanjung Agung Kec. Banyuasin III(* P3L- .09.02.00/6.2/
III/PUCK/2012 2013
TGL 03-09-12
238 1.03.01 CV. NP Pengecoran Jalan Lingkungan Kom. Makam 14/03/PPK- 244.996.000,00 12.249.800,00 3550/LS/1.20 12.249.800,00 - -
Pedado Kel. Pkl. Balai Kec. Banyuasin III PP.III/PUCK/201 .09.02.00/6.2/
(* 2, Tgl. 08-10-12 2013
239 1.03.01 CV. NP Pengecoran Lrg H. Badri Mamak Rt.13, 15/03/PPK- 244.236.000,00 12.211.800,00 3549/LS/1.20 12.211.800,00 - -
Rt.14 Kel. Kedondong Raye Kec. PP.III/PUCK/201 .09.02.00/6.2/
Banyuasin III (* 2 Tg. 08-10-12 2013
240 1.03.01 CV. CBI Pengecoran Jalan Lingkungan RT. 09 RW. 03/03/PPK- 99.456.000,00 4.972.800,00 - - 4.972.800,00
03 Kel. Seterio Kec. Banyuasin III TRTB.II/PUCK/2
012, Tgl. 19-10-
2012
241 1.03.01 CV. CBI Pengecoran jalan Lingkungan Dalam Desa 04/03/PPK- 149.338.000,00 7.466.900,00 3571/LS/1.20 7.466.900,00 - -
Regan Agung Kec. Banyuasin III TRTB.II/PUCK/2 .09.02.00/6.2/
012 Tgl 19-10- 2013
2012
242 1.03.01 CV. CG Pengecoran Jalan Lingkungan dalam Desa 587.984.000,00 29.399.200,00 3556/LS/1.20 29.399.200,00 - -
Rejodadi Kec. Sembawa (* 03/03/PPK/PUC .09.02.00/6.2/
K/2012, Tgl. 03- 2013
09-2012
243 1.03.01 CV. Du Pengecoran Lorong dalam Desa Muara 03/05/PPK/PUC 195.989.000,00 9.799.450,00 3555/LS/1.20 9.799.450,00 - -
Damai Kec. Sembawa (* K/2012, Tgl. 3-09- .09.02.00/6.2/
3012 2013
244 1.03.01 CV. PP Pengecoran Lorong dalam Desa Purwosari 03/04/PPK/PUC 147.097.000,00 7.354.850,00 2092/LS/1.20 7.354.850,00 - -
Kec. Sembawa (* K/2012 Tanggal .09.02.00/6.2/
03 September 2013
2012
245 1.03.01 CV. CG Pengecoran Jalan Lingkungan dalam Desa 03/06/PPK/PUC 440.872.000,00 22.043.600,00 3552/LS/1.20 22.043.600,00 - -
Santan Sari Kec. Sembawa (* K/2012, Tgl 03- .09.02.00/6.2/
09-2012 2013
246 1.03.01 CV. LK Pengecoran Jalan Lingkungan Dalam Dsn. I 01/03/SPK/PPK- 59.530.000,00 2.976.500,00 2857/LS/1.20 2.976.500,00 - -
Desa Pulau Harapan Kec. Sembawa P3L.II/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Okt 2013
2012
247 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 18/03/SPK/PPK- 99.450.000,00 4.972.500,00 6106/LS/1.20 4.972.500,00 - -
Purwosari Kec. Sembawa PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
Halaman 19 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
248 1.03.01 CV. DJ Pengecoran Jalan Sri Menanti Desa 04/03/SPK/PPK- 99.460.000,00 4.973.000,00 6096/LS/1.20 4.973.000,00 - -
Rejodadi Kec. Sembawa P3L.II/PUCK/201 .09.02.00/6.2/
2, 15 Oktober 2013
2012
249 1.03.01 CV. DP Pengecoran Jalan Lingkungan Dalam Desa 05/03/SPK/PPK- 99.430.000,00 4.971.500,00 2817/LS/1.20 4.971.500,00 - -
Muara Damai Kec. Sembawa P3L.II/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Okt 2013
2012
250 1.03.01 CV. BrPs Pengecoran Jalan Lingkungan Perumahan 01/03/SPK/PPK- 99.319.000,00 4.965.950,00 2562/LS/1.20 4.965.950,00 - -
Komplek Tri Dharma Permai Kec. Talang OP.III/PUCK/201 .09.02.00/6.2/
Kelapa 2 tgl 15 Juni 2012 2013
251 1.03.01 CV. SmJ Pengecoran Jalan Lingkungan Dalam Desa 13/03/SPK/PPK- 98.594.000,00 4.929.700,00 4580/LS/1.20 4.929.700,00 - -
Kenten Laut Kec. Talang Kelapa OP.III/PUCK/201 .09.02.00/6.2/
2 TGL 14-09-12 2013
252 1.03.01 CV. HR Pengecoran Jalan Lingkungan I Kel. Air 11/02/PPK/PUC 197.325.000,00 9.866.250,00 4957/LS/1.20 9.866.250,00 - -
Batu Kec. Talang Kelapa (* K/2012 Tgl 03-09- .09.02.00/6.2/
2012 2013
253 1.03.01 CV. MB Pengecoran Lorong Barokah Kelurahan 08/03/SPK/PPK- 99.310.000,00 4.965.500,00 2687/LS/1.20 4.965.500,00 - -
Sukajadi Kec. Talang Kelapa (* OP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 09/7/2012 2013
amandemen
No.08/03/SPK-
ADD/PPK-
OP.III/PUCK/201
2 tgl 16/7/12
254 1.03.01 CV. SK Pengecoran Lorong Bukit Indah Rt. 30 / 02 09/03/SPK/PPK- 98.332.000,00 4.916.600,00 2368/LS/1.20 4.916.600,00 - -
Kel. Tanah Mas Kec. Talang Kelapa (* OP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 06 2013
September 2012.
255 1.03.01 CV. KY Pengecoran Jalan Tembus Lrg. Pinang Rt. 10/03/PPK.PP.III/ 244.260.000,00 12.213.000,00 2683/LS/1.20 12.213.000,00 - -
57/20 Kel. Sukajadi Kec. Talang Kelapa (* PUCK/2012 .09.02.00/6.2/
Tanggal 25 2013
September 2012
256 1.03.01 CV. MB Pengecoran Jalan Lingkungan Permhn Afik 11/03/PPK- 244.997.000,00 12.249.850,00 2685/LS/1.20 12.249.850,00 - -
Permai Rt. 12 Kenten Laut Kec. Talang PP.III/PUCK/201 .09.02.00/6.2/
Kelapa (* 2 Tanggal 25 2013
September 2012
257 1.03.01 CV. MB Pengecoran Lorong Balai Rt. 06/07 12/03/PPK.PP.III/ 244.878.000,00 12.243.900,00 2682/LS/1.20 12.243.900,00 - -
Kelurahan Air Batu Kec. Talang Kelapa (* PUCK/2012 Tgl .09.02.00/6.2/
25 September 2013
2012
258 1.03.01 CV. KY Pengecoran Lorong Tika Rt. 05 Kelurahan 13/03/PPK- 244.869.000,00 12.243.450,00 2686/LS/1.20 12.243.450,00 - -
Air Batu Kec. Talang Kelapa (* OP.III/PUCK/201 .09.02.00/6.2/
2 tgl 25/9/2012 2013
Halaman 20 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
259 1.03.01 CV. NPM Pengecoran Jalan Belakang Balai Desa RT. 04/03/SPK/PPK- 99.256.000,00 4.962.800,00 2667/LS/1.20 4.962.800,00 - -
13 Dusun1 Desa Kenten Laut Kec. Talang P3L.III/PUCK/20 .09.02.00/6.2/
Kelapa 12 Tgl 15-10- 2013
2012
260 1.03.01 CV. NPM Pengecoran Jalan Lingkungan Dalam 05/03/SPK/PPK- 99.409.000,00 4.970.450,00 2563/LS/1.20 4.970.450,00 - -
Kelurahan Talang Kelapa Komplek Gria P3L.III/PUCK/20 .09.02.00/6.2/
Damai Indah 12 Tgl 15-10- 2013
2012
261 1.03.01 CV. SP Pengecoran Jalan Lingkungan Perum. Bulu 06/03/SPK/PPK- 99.507.000,00 4.975.350,00 3577/LS/1.20 4.975.350,00 - -
Jadongan Rt.33 Rw.09 Kelurahan Talang P3L.III/PUCK/20 .09.02.00/6.2/
Kelapa 12 Tgl 15 Okt 2013
2012
262 1.03.01 CV. SP Pengecoran Jalan Masjid RT. II Desa 07/03/SPK/PPK- 149.242.000,00 7.462.100,00 3573/LS/1.20 7.462.100,00 - -
Gasing Kec. Talang Kelapa P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15 2013
Oktober 2012
263 1.03.01 CV. SP Pengecoran Lorong RT. 15 Desa Kenten 08/03/SPK/PPK- 99.453.000,00 4.972.650,00 3576/LS/1.20 4.972.650,00 - -
Laut Kecamatan Talang Kelapa P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL 15-10-12 2013
264 1.03.01 CV. RS Pengecoran Jalan Lingkungan Dalam 13/03/SPK/PPK- 99.290.000,00 4.964.500,00 3874/LS/1.20 4.964.500,00 - -
Kelurahan Talang Keramat Kec. Talang P3L.III/PUCK/20 .09.02.00/6.2/
Kelapa 12, Tgl. 15-10- 2013
2012
265 1.03.01 CV. RS Pengecoran Jalan Lingkungan Dalam 11/03/SPK/PPK- 99.262.000,00 4.963.100,00 3875/LS/1.20 4.963.100,00 - -
Kelurahan Sukomoro Kec. Talang Kelapa P3L.III/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
266 1.03.01 CV. HR Pengecoran Jalan Lingkungan Dalam Desa 31/03/SPK/PPK- 59.010.000,00 2.950.500,00 5261/LS/1.20 2.950.500,00 - -
Dusun Pulau Desa Kenten Laut Kec. Talang P3L.I/PUCK/201 .09.02.00/6.2/
Kelapa 2 TGL 15-10-12 2013
267 1.03.01 PT. BP Pengecoran Jalan Lingkungan Desa Cinta 11/03/PPK- 293.930.000,00 14.696.500,00 3519/LS/1.20 14.696.500,00 - -
Manis Lama Kec. Banyuasin I PP.I/PUCK/2012, .09.02.00/6.2/
Tgl. 03-09-2012 2013
268 1.03.01 PT. BP Pengecoran Jalan Lingkungan Desa Panca 12/03/PPK- 294.242.000,00 14.712.100,00 3455/LS/1.20 14.712.100,00 - -
Desa Kec. Banyuasin I PP.I/PUCK/2012, .09.02.00/6.2/
Tgl. 03-09-2012 2013
269 1.03.01 PT. BP Pengecoran Jalan Lingkungan Dalam Desa 03/17/PPK/PUC 979.546.000,00 48.977.300,00 3457/LS/1.20 48.977.300,00 - -
Sido Mulyo Kec. Banyuasin I (* K/2012 Tgl 03 .09.02.00/6.2/
September 2012 2013
270 1.03.01 PT. PRa Pengecoran Jalan Lingkungan Dalam Desa 979.458.000,00 48.972.900,00 1710/LS/1.20 48.972.900,00 - -
Tirto Sari Kec. Banyuasin I (* 03/18/PPK/PUC .09.02.00/6.2/
K/2012 Tgl 03 2013
Sept 2012
Halaman 21 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
271 1.03.01 CV. IMr Pengecoran Lrg. Jarak I Rt. 05 Kel. Mariana 15/02/SPK/PPK- 99.333.000,00 4.966.650,00 - - 4.966.650,00
Ilir Kecamatan Banyuasin I (* P3L.I/PUCK/201
2 Tgl 07 Sep
2012
272 1.03.01 CV. NJP Pengecoran Lrg. Gerunggang Rt. 07 Kel. 16/02/SPK/PPK- 99.344.000,00 4.967.200,00 1963/LS/1.20 4.967.200,00 - -
Mariana Ilir Kec. Banyuasin I (* P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl 07 sep 2012 2013
273 1.03.01 CV. IMr Pengecoran Lrg. PDAM Kel. Marianan Ilir 17/02/SPK/PPK- 99.332.000,00 4.966.600,00 - - 4.966.600,00
Kec. Banyuasin I (* P3L.I/PUCK/201
2 Tanggal 07
September 2012
274 1.03.01 CV. BaPe Pengecoran Lrg. Cakur Dusun III Desa 15/03/PPK- 198.010.000,00 9.900.500,00 1964/LS/1.20 9.900.500,00 - -
Perajen Kecamatan Banyuasin I (* P3L.III/PUCK/20 .09.02.00/6.2/
12 tgl. 03 2013
September 2012
275 1.03.01 CV. NJP Pengecoran Lorong Jelutung Mariana Rt. 16 18/02/SPK/PPK- 98.973.000,00 4.948.650,00 1962/LS/1.20 4.948.650,00 - -
Kec. Banyuasin I (* P3L.I/PUCK/201 .09.02.00/6.2/
2, Tanggal 07 2013
September 2012
276 1.03.01 PT. BRL Pengecoran Jalang Lingkungan desa Sambi 16/03/SPK/PPK- 488.994.000,00 24.449.700,00 - - 24.449.700,00
Rejo Rt. 22 dan 21 Kel. Mariana Kec. BA I P3L.III/PUCK/20
(* 12 Tgl 03 Sept
2012
277 1.03.01 CV. SmJ Pengecoran Lrg. Masjid menuju Lrg. 19/02/SPK/PPK- 118.850.000,00 5.942.500,00 5399/LS/1.20 5.942.500,00 - -
Kacang Desa Tirto Sari Kecamatan P3L.I/PUCK/201 .09.02.00/6.2/
Banyuasin I 2, Tgl. 07-09- 2013
2012
278 1.03.01 PT. BP Pengecoran Jalan Lingkungan Dalam Desa 01/03/SPK/PPK- 199.469.000,00 9.973.450,00 3341/LS/1.20 9.973.450,00 - -
Rimba Jaya RT. 08 KM. 15 Kec. Banyuasin PP.I/PUCK/2012 .09.02.00/6.2/
I Tgl 15 Oktober 2013
2012
279 1.03.01 CV. SJ Pembangunan Jalan Desa Rimba Jaya Kec. 01/03/SPK/PPK- 74.920.000,00 3.746.000,00 - - 3.746.000,00
Banyuasin I (** P3L.IV/PUCK/20
12, Tgl. 15 Okt
2012
280 1.03.01 CV. HCL Pemindahan Utilitas PDAM untuk 27/03/PPK- 2.491.400.000,00 124.570.000,00 2418/LS/1.20 124.570.000,00 - -
Pelabaran Jalan Lokasi Sungai Pinang P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL 26-10-12 2013
281 1.03.01 CV. SJ Pengecoran Lorong Swadaya Desa Merah 02/03/SPK/PPK- 99.815.000,00 4.990.750,00 3720/LS/1.20 4.990.750,00 - -
Mata Kec. Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
282 1.03.01 CV. SJ Pengecoran Jalan Lingkungan Dalam Desa 03/03/SPK/PPK- 99.815.000,00 4.990.750,00 5555/LS/1.20 4.990.750,00 - -
Muara Baru Kec. Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12 Tgl 15-10- 2013
2012
Halaman 22 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
283 1.03.01 CV. SJ Pengecoran Jalan Lingkungan Dalam Desa 04/03/SPK/PPK- 99.815.000,00 99.815.000,00 0326/LS/1.20 99.815.000,00 - -
Duren Ijo Kec. Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12 Tgl 15-10- 2013 dan
2012 6150/LS/1.20
.09.02.00/6.2/
2013
284 1.03.01 CV. SJ Pengecoran Jalan Lingkungan Dalam Desa 05/03/SPK/PPK- 99.810.000,00 4.990.500,00 4306/LS/1.20 4.990.500,00 - -
Merah Mata Kec. Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12, Tgl. 15 Okt 2013
2012
285 1.03.01 CV. TaSa Pengecoran Jalan Lingkungan Dalam Desa 08/03/SPK/PPK- 99.825.000,00 99.825.000,00 0325/LS/1.20 99.825.000,00 - -
Padang Rejo Kecamatan Banyuasin I P3L.I/PUCK/201 .09.02.00/6.2/
2, Tgl. 14-10- 2013 dan
2012 6151/LS/1.20
.09.02.00/6.2/
2013
286 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 07/03/SPK/PPK- 99.825.000,00 4.991.250,00 3724/LS/1.20 4.991.250,00 - -
Budi Mulya Kecamatan Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12, Tgl. 15 Okt 2013
2012
287 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 09/03/SPK/PPK- 99.815.000,00 4.990.750,00 3725/LS/1.20 4.990.750,00 - -
Cinta Manis Lama Kecamatan Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12 Tgl 15-10- 2013
2012
288 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 10/03/SPK/PPK- 99.815.000,00 4.990.750,00 - - 4.990.750,00
Panca Mulya Kecamatan Banyuasin I PP.IV/PUCK/201
2 TGL 15-10-12
289 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 11/03/SPK/PPK- 99.815.000,00 4.990.750,00 3869/LS/1.20 4.990.750,00 - -
Tirta Makmur Banyuasin I P3L.IV/PUCK/20 .09.02.00/6.2/
12 TGL 15-10-12 2013
290 1.03.01 CV. VIP Pengecoran Lorong Famili Desa Sungai 08/03/SPK/PPK- 79.352.000,00 3.967.600,00 - - 3.967.600,00
Pinang Kec. Rambutan PP.III/PUCK/201
2, Tgl. 15 Juni
2012
291 1.03.01 CV. LK Pengecoran Jalan Lingkungan Lebung 08/03/PPK- 119.334.000,00 5.966.700,00 2803/LS/1.20 5.966.700,00 - -
Barangan Ds. Sungai Pinang Kec. PP.I/PUCK/2012 .09.02.00/6.2/
Rambutan Tgl 03 Sep 2012 2013
292 1.03.01 CV. IB Pengecoran Jalan Lingkungan Dalam Desa 01/03/PPK- 99.317.000,00 4.965.850,00 0923/LS/1.20 4.965.850,00 - -
Sako Rt. 02 dan 04 Kecamatan Rambutan PP.I/PUCK/2012 .09.02.00/6.2/
(* Tanggal 02 2013
Agustus 2012
293 1.03.01 CV. IB Pengecoran Jalan Lingkungan dalam Desa 02/03/PPK- 99.119.000,00 4.955.950,00 5139/LS/1.20 4.955.950,00 - -
Gelebak Dalam Tlg Sekuncit Kec. PP.I/PUCK/2012 .09.02.00/6.2/
Rambutan (* Tanggal 03 2013
Agustus 2012
Halaman 23 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
294 1.03.01 CV. BPD Pengecoran Jalan Lingkungan Dalam Desa 03/03/SPK/PPK- 58.664.000,00 2.933.200,00 4298/LS/1.20 2.933.200,00 - -
Durian Gadis menuju SDN / Pemakaman (* PP.I/PUCK/2012 .09.02.00/6.2/
TGL 10-09-12 2013
295 1.03.01 CV. AP Pengecoran Jalan Lingkungan dalam Desa 04/03/PPK- 490.237.000,00 24.511.850,00 4484/LS/1.20 24.511.850,00 - -
Siju Kec. Rambuatan (* PP.I/PUCK/2012 .09.02.00/6.2/
Tgl. 07-09- 2012 2013
296 1.03.01 CV. AS Pengecoran Jalan Lingkungan dalam Desa 05/03/PPK- 79.350.000,00 3.967.500,00 4616/LS/1.20 3.967.500,00 - -
Menten Kec. Rambuatan (lanjutan) PP.I/PUCK/2012, .09.02.00/6.2/
Tgl. 03-09-2012 2013
297 1.03.01 CV. KY Pengecoran Jalan Lingkungan dalam desa 05/03/SPK/PPK- 89.520.000,00 4.476.000,00 2680/LS/1.20 4.476.000,00 - -
Baru Kec. Rambutan PP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 05 Sept 2013
2012
298 1.03.01 CV. Na Pengecoran Lrg. Dalam Dusun I Desa 05/03/SPK/PPK- 89.356.000,00 4.467.800,00 - - 4.467.800,00
Sungai Pinang kec. Rambuatan PP.III/PUCK/201
2 Tgl 05 Sept
2012
299 1.03.01 CV. AS Pengecoran Jalan Lingkungan Menuju 06/03/SPK- 89.344.000,00 4.467.200,00 6111/LS/1.20 4.467.200,00 - -
Kalangan Desa Siju Kec. Rambutan PP.III/PUCK/201 .09.02.00/6.2/
(Lanjutan) 2, Tgl. 25-09- 2013
2012
300 1.03.01 CV. BT Pengecoran Jalan Lingkungan Dalam Dsn 10/03/PPK- 198.278.000,00 9.913.900,00 1513//LS/1.2 9.913.900,00 - -
IV Ds. Sungai Pinang Kec. Rambutan (* PP.1/PUCK/2012 0.09.02.00/6.
Tanggal 03 2/2013
September 2012
301 1.03.01 CV. TS Pengecoran Lorong Dalam Dusun II Ds. 04/03/SPK/PPK- 198.297.000,00 9.914.850,00 1509/LS/1.20 9.914.850,00 - -
Sungai Dua Kec. Rambutan (* PP.III/PUCK/201 .09.02.00/6.2/
2 Tanggal 05 2013
September 2012
302 1.03.01 CV. NSI Pengecoran Jalan Meritai Dalam Desa 02/03/SPK/PPK- 79.486.000,00 3.974.300,00 4487/LS/1.20 3.974.300,00 - -
Sungai Pinang PP.I/PUCK/2012, .09.02.00/6.2/
Tanggal 05 2013
September 2012
303 1.03.01 CV. DJ Pengecoran Jalan Menuju SD 1 dan 2 Desa 03/03/SPK/PPK- 99.430.000,00 4.971.500,00 2860/LS/1.20 4.971.500,00 - -
Sungai Dua PP.I/PUCK/2012 .09.02.00/6.2/
Tgl 15 Okt 2012 2013
304 1.03.01 CV. LK Pengecoran Lorong Dedek Desa Sungai 04/03/SPK/PPK- 77.350.000,00 3.867.500,00 3293/LS/1.20 3.867.500,00 - -
Pinang Kec. Rambutan PP.I/PUCK/2012 .09.02.00/6.2/
Tgl. 15-10- 2012 2013
305 1.03.01 CV. DJ Pengecoran Lorong RT. 09 Desa Sako 05/03/SPK/PPK- 99.440.000,00 4.972.000,00 2812/LS/1.20 4.972.000,00 - -
Kecamatan Rambutan PP.I/PUCK/2012 .09.02.00/6.2/
Tgl 15 Oktober 2013
2012
306 1.03.01 CV. Zu Pengecoran Jalan Lingkungan dalam Desa 14/03/SPK/PPK- 197.509.000,00 9.875.450,00 - - 9.875.450,00
Ringin Harjo Kec. Pulau Rimau (* P3L.I/PUCK/201
2 Tgl 12-09-12
Halaman 24 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
307 1.03.01 CV. NPM Pengecoran Jalan Lingkungan Dalam Desa 03/02/SPK/PPK- 99.488.000,00 4.974.400,00 4305/LS/1.20 4.974.400,00 - -
Wana Mukti Kec. Pulau Rimau OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 16-10-2012 2013
308 1.03.01 CV. NPM Pengecoran Jalan Lingk. Dlm Desa Tabuan 03/05/SPK/PPK- 99.465.000,00 4.973.250,00 4302/LS/1.20 4.973.250,00 - -
Asri Kec. Pulau Rimau OP.II/PUCK/201 .09.02.00/6.2/
2, Tgl. 16-10- 2013
2012
309 1.03.01 CV. HR Pengecoran Lorong menuju SDN 27 Rantau 10/02/SPK/PPK- 45.000.000,00 2.250.000,00 5262/LS/1.20 2.250.000,00 - -
Bayur Kec. Rantau Bayur TRTB.II/PUCK/2 .09.02.00/6.2/
012 Tgl 10-09- 13
2012
310 1.03.01 CV. APe Pengecoran Jalan Lingkungan dalam Desa 08/03/PPK- 147.398.000,00 7.369.900,00 3514/LS/1.20 7.369.900,00 - -
Srijaya Kec. Rantau Bayur (* TRTB.II/PUCK/2 .09.02.00/6.2/
012 Tgl 30-10- 2013
2012
311 1.03.01 CV. IP Pengecoran Jalan Lingkungan dalam Desa 06/03/PPK- 197.298.000,00 9.864.900,00 3527/LS/1.20 9.864.900,00 - -
Sungai Naik Kec. Rantau Bayur (* TRTB.I/PUCK/20 .09.02.00/6.2/
12 TGL 10-09-12 2013
312 1.03.01 CV. IP Pengecoran Jalan Lingkungan dalam Desa 07/03/PPK/TRTB 391.991.000,00 19.599.550,00 3662/LS/1.20 19.599.550,00 - -
Penandingan Kec. Rantau Bayur (* .II/PUCK/2012 .09.02.00/6.2/
Tgl 01Oktober 2013
2012
313 1.03.01 CV. EJ Pengecoran Jalan Menuju SD 4 Srijaya Kec. 03/03/SPK/PPK- 99.460.000,00 4.973.000,00 1817/LS/1.20 4.973.000,00 - -
Rantau Bayur OP/PUCK/2012, .09.02.00/6.2/
Tgl. 15-10-2012 2013
314 1.03.01 CV. RMK Pengecoran Jalan Lingkungan Dsn Sungai 04/03/PPK- 123.862.000,00 6.193.100,00 2360/LS/1.20 6.193.100,00 - -
Keladi Ds Rimau Sungsang Kec. Banyuasin PP.II/PUCK/2012 .09.02.00/6.2/
II (* Tgl. 24-09- 2012 2013
315 1.03.01 Pengecoran Jalan Lingkungan Dsn Sungai 05/03/SPK/PPK- 122.314.000,00 6.115.700,00 - - 6.115.700,00 audit BPK CV.
Bungin Ds Rimau Sungsang Kec. PP.II/PUCK/2012 RMK
CV. VIP
Banyuasin II (* , Tgl. 24 Sept
2012
316 1.03.01 CV. PL Pengecoran Jalan Lingkungan dalam Desa 06/03/SPK/PPK- 198.201.000,00 9.910.050,00 6575/LS/1.20 9.910.050,00 - -
Karang Sari Kec. Banyuasin II (* PP.II/PUCK/2012 .09.02.00/6.2/
Tgl 24-09-2012 2013
317 1.03.01 CV. LS Pengecoran Jalan Lingkungan dalam Desa 07/03/SPK/PPK- 99.345.000,00 4.967.250,00 6576/LS/1.20 4.967.250,00 - -
Mekar Sari Kec. Banyuasin II (* PP.II/PUCK/2012 .09.02.00/6.2/
Tgl 24-09-2012 2013
318 1.03.01 CV. CM Pengecoran Jalan Lingkungan dalam Desa 09/03/PPK- 588.944.000,00 29.447.200,00 5079/LS/1.20 29.447.200,00 - -
Indra Pura Kec. Muara Sugihan (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 03 2013
September 2012
319 1.03.01 CV. Su Pengecoran Jalan Lingkungan dalam desa 11/03/PPK- 491.164.000,00 24.558.200,00 2376/LS/1.20 24.558.200,00 - -
Cendana Kec. Muara Sugihan (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tanggal 03 2013
September 2012
Halaman 25 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
320 1.03.01 CV. JS Pengecoran Jalan Lingkungan dalam Desa 12/03/PPK- 393.393.000,00 19.669.650,00 4424/LS/1.20 19.669.650,00 - -
Margo Mulyo Kec. Muara Sugihan (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tanggal 03 2013
September 2012
321 1.03.01 CV. KJ Pengecoran Jalan Dalam Desa Sugi Waras 01/03/SPK/PPK- 198.763.000,00 9.938.150,00 4481/LS/1.20 9.938.150,00 - -
Kec. Muara Sugihan (** P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15 Okt 2013
2012
322 1.03.01 CV. PC Pengecoran Jalan Lingkungan dalam Desa 01/03/SPK/PPK- 149.262.000,00 7.463.100,00 - - 7.463.100,00
Bukit Kec. Betung (* P3L.I/PUCK/201
2 TGL 12-09-12
323 1.03.01 CV. AP Pengecoran Jalan Lingkungan dalam Dusun 02/03/SPK/PPK- 99.208.000,00 4.960.400,00 4284/LS/1.20 4.960.400,00 - -
II Desa Bukit Kec. Betung (* P3L.I/PUCK/201 .09.02.00/6.2/
2, Tgl. 12-09- 2013
2012
324 1.03.01 CV. APe Pengecoran Jalan Lingkungan dalam Desa 03/01/PPK- 293.997.000,00 14.699.850,00 3688/LS/1.20 14.699.850,00 - -
Taja Mulya Kec. Betung (* P3L/PUCK/2012 .09.02.00/6.2/
Tgl 01 Oktober 2013
2012
325 1.03.01 CV. AP Pengecoran Jalan Lingkungan dalam Desa 04/03/SPK- 148.595.000,00 7.429.750,00 4479/LS/1.20 7.429.750,00 - -
Suka Mulya I Kec. Betung (* P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl 07 Sept 2013
2012
326 1.03.01 CV. AP Pengecoran Jalan Lingkungan Kelurahan 05/03/SPK/PPK- 197.159.000,00 9.857.950,00 4483/LS/1.20 9.857.950,00 - -
Betung Kec. Betung (* P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl. 07-09- 2013
2012
327 1.03.01 CV. AP Pengecoran Jalan Lingkungan Kelurahan 06/01/PPK- 293.997.000,00 14.699.850,00 4482/LS/1.20 14.699.850,00 - -
Rimba Asam Kec. Betung (* P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl 01 Oktober 2013
2012
328 1.03.01 CV. APe Pengecoran Jalan Lingkungan dalam desa 07/03/SPK/PPK- 99.325.000,00 4.966.250,00 2859/LS/1.20 4.966.250,00 - -
Taja Raya I Kecamatan Betung (* P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl 12 2013
September 2012
329 1.03.01 CV. RM Pengecoran Jalan Lingkungan dalam Desa 08/03/SPK/PPK- 98.730.000,00 4.936.500,00 4485/LS/1.20 4.936.500,00 - -
Sri Kembang Kecamatan Betung (* P3L.I/PUCK/201 .09.02.00/6.2/
2 Tgl 07 Sept 2013
2012
330 1.03.01 CV. VAA Pengecoran Jalan Lingkungan dalam Desa 01/03/SPK/PPK- 147.383.000,00 7.369.150,00 - - 7.369.150,00
Suka Mulya II Kec. Betung (* P3L.II/PUCK/201
2 Tgl 13
September 2012
Halaman 26 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
331 1.03.01 CV. DM Pengecoran Lorong Gotong Royong 02/03/SPK/PPK- 197.483.000,00 9.874.150,00 - - 9.874.150,00
Kelurahan Betung Kec. Betung (* P3L.II/PUCK/201
2 Tgl 13-09-12
332 1.03.01 CV. IB Pengecoran Lorong Musholla Keurahan 03/03/SPK/PPK- 74.376.000,00 3.718.800,00 - - 3.718.800,00
Betung Kecamatan Betung (* P3L.II/PUCK/201
2 Tgl 12
September 2012
333 1.03.01 CV. PK Pengecoran Lrg Swadaya Bersama 04/03/SPK/PPK- 146.988.000,00 7.349.400,00 5636/LS/1.20 7.349.400,00 - -
Lingkungan Kel. Rimba Asam Kec. Betung P3L.II/PUCK/201 .09.02.00/6.2/
(* 2, Tgl. 05-09- 2013
2012
334 1.03.01 CV. AM Pengecoran jalan Lingkungan dalam Desa 06/03/SPK/PPK- 147.385.000,00 7.369.250,00 1620/LS/1.20 7.369.250,00 - -
Sri Kembang Kec. Betung (* P3L.II/PUCK/201 .09.02.00/6.2/
2, Tgl 13-09-2012 2013
335 1.03.01 CV. EJ Pengecoran Lorong Dusun III Desa Taja 07/03/PPK- 293.985.000,00 14.699.250,00 1715/LS/1.20 14.699.250,00 - -
Indah Kecamatan Betung (* P3L.II/PUCK/201 .09.02.00/6.2/
2, Tgl. 27-09- 2013
2012
336 1.03.01 CV. CD Pengecoran Jalan Lingkungan dalam Desa 08/03/SPK/PPK- 196.270.000,00 9.813.500,00 2074/LS/1.20 9.813.500,00 - -
Suka Mulya / Kpg Asute Kec. Betung (* P3L.II .09.02.00/6.2/
/PUCK/2012, 2013
Tgl. 13-09-2012
337 1.03.01 CV. CD Pengecoran Jalan Lingkungan Dusun I Desa 09/03/SPK/PPK- 196.216.000,00 9.810.800,00 2078/LS/1.20 9.810.800,00 - -
Taja Raya II Kec. Betung (* P3L.II/PUCK/201 .09.02.00/6.2/
2, Tgl. 13-09- 2013
2012
338 1.03.01 CV. LaBe Pengecoran Jalan Lingk. Rt. 29 Dalam 14/03/SPK/PPK- 99.825.000,00 4.991.250,00 3722/LS/1.20 4.991.250,00 - -
Kelurahan Betung Kec. Betung P3L.IV/PUCK/20 .09.02.00/6.2/
12 TGL 15-10-12 2013
339 1.03.01 CV. LaBe Pengecoran Jalan Menuju Masjid Al. Amin 15/03/SPK/PPK- 44.935.000,00 2.246.750,00 - - 2.246.750,00
Rt. 24 Kelurahan Rimba Asam Kec. Betung P3L.IV/PUCK/20
12, Tgl. 15-10-
2012
340 1.03.01 CV. LaBe Pengecoran Jalan Lingk. Rt. 01 Ds. I Desa 16/03/SPK/PPK- 99.825.000,00 4.991.250,00 - - 4.991.250,00
Suka Mulya Kec. Betung P3L.IV/PUCK/20
12 Tgl 15-10-
2012
Halaman 27 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
341 1.03.01 CV. LaBe Pengecoran Jalan Lingk. Rt. 02 Menuju 17/03/SPK/PPK- 79.910.000,00 79.910.000,00 0327/LS/1.20 79.910.000,00 - -
TPU Sedongkok Kec. Betung P3L.IV/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013 &
2012 3865/LS/1.20
.09.02.00/6.2/
2013
342 1.03.01 CV. LaBe Pengecoran Lorong Lubis/Telkom RT. 31 18/03/SPK/PPK- 99.825.000,00 4.991.250,00 3721/LS/1.20 4.991.250,00 - -
RW. 09 Kelurahan Betung Kec. Betung P3L.IV/PUCK/20 .09.02.00/6.2/
12 TGL 15-10-12 2013
343 1.03.01 CV. JP Pengecoran Jalan Perumnas Kec. Betung 23/03/SPK/P3L.I 99.825.000,00 4.991.250,00 1973/LS/1.20 4.991.250,00 - -
V/PUCK/2012, .09.02.00/6.2/
Tgl. 15-10-2012 2013
344 1.03.01 CV. EJ Pengecoran Jalan SD 3 JM Desa Bukit 21/03/SPK/PPK- 99.825.000,00 4.991.250,00 1716/LS/1.20 4.991.250,00 - -
Kecamatan Betung P3L.IV/PU.CK/2 .09.02.00/6.2/
012 Tgl 15 2013
Oktober 2012
345 1.03.01 CV. PuPr Penimbunan Jalan Desa Lubuk Karet Dusun 17/03/SPK/PPK- 74.348.000,00 3.717.400,00 2661/LS/1.20 3.717.400,00 - -
II Kec. Suak Tapeh (* OP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Oktober 2013
2012
346 1.03.01 CV. APe Pengecoran Jalan Lingkungan dalam Desa 16/03/SPK.PPK. 147.306.000,00 7.365.300,00 2906/LS/1.20 7.365.300,00 - -
Lubuk Lancang Kecamatan Suak Tapeh (* OP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 13/9/12 2013
347 1.03.01 CV. PuPr Pengecoran Jalan Lingkungan dalam Desa 10/03/SPK/PPK- 147.808.000,00 7.390.400,00 2662/LS/1.20 7.390.400,00 - -
Bengkuang Kec. Suak tapeh (* OP.III/PUCK/201 .09.02.00/6.2/
2 Tgl 13-09-2012 2013
348 1.03.01 CV. PP Pengerasan Jalan Menuju TPA Dalam Desa 07/03/SPK/PPK- 99.300.000,00 4.965.000,00 2586/LS/1.20 4.965.000,00 - -
Lubuk Karet KM 1,5 (* OP.III/PUCK/201 .09.02.00/6.2/
2 Tanggal 04 Juli 2013
2012
349 1.03.01 CV. TAJ Pengecoran Jalan Lingkungan dalam Desa 11/03/SPK/PPK- 147.254.000,00 7.362.700,00 1618/LS/1.20 7.362.700,00 - -
Bukit kampung Karang rejo Kec. Suak OP.III/PUCK/201 .09.02.00/6.2/
Tapeh (* 2, Tgl 13-09-2012 2013
350 1.03.01 CV. PeP Pengecoran Jalan Lingkungan dalam Desa 08/03/SPK/PPK- 149.139.000,00 7.456.950,00 2091/LS/1.20 7.456.950,00 - -
Sukaraja Kec. Suak Tapeh (* P3L.II/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Oktober 2013
2012
351 1.03.01 CV. RA Pengecoran Jalan Lingkungan dalam desa 02/03/SPK/PPK- 197.264.000,00 9.863.200,00 3210/LS/1.20 9.863.200,00 - -
Terusan Tengah Kec. Muara Telang (* OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 13 Sept 2013
2012
Halaman 28 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
352 1.03.01 CV. RA Pengecoran Jalan Lingkungan dalam Desa 03/03/SPK/PPK- 215.590.000,00 10.779.500,00 3211/LS/1.20 10.779.500,00 - -
Mukti Jaya Kec. Muara Telang (* OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 25 2013
September 2012
353 1.03.01 CV. MU Pengecoran Jalan Lingkungan Dalam Desa 01/03/SPK/PPK- 99.332.000,00 99.332.000,00 2840/LS/1.20 94.365.400,00 - 4.966.600,00
Muara Telang Kec. Muara Telang PP.III/PUCK/201 .09.02.00/6.2/
2 TGL 15-1012 2013
354 1.03.01 CV. MU Pengecoran Jalan Lingkungan Dalam Desa 02/03/SPK/PPK- 99.445.000,00 4.972.250,00 - - 4.972.250,00
Terusan Muara Kec. Muara Telang PP.III/PUCK/201
2 Tgl 15 Oktober
2012
355 1.03.01 CV. MU Pengecoran Jalan Lingkungan Dalam Desa 03/03/SPK/PPK- 99.420.000,00 4.971.000,00 - - 4.971.000,00
Terusan Tengah Kec. Muara Telang PP.III/PUCK/201
2 Tgl 15 Oktober
2012
356 1.03.01 CV. PU Pengecoran Jalan Lingkungan Dalam Desa 04/03/SPK/PPK- 99.425.000,00 99.425.000,00 2749/LS/1.20 94.453.750,00 - 4.971.250,00
Terusan Dalam Kec. Muara Telang PP. .09.02.00/6.2/
III/PU.CK/2012 2013
TGL 15-10-12
357 1.03.01 CV. PU Pengecoran Jalan Lingkungan Dalam Desa 05/03/SPK/PPK- 99.430.000,00 4.971.500,00 - - 4.971.500,00
Telang Lubuk Kec. Muara Telang PP.III/PUCK/201
2 Tgl 15-10-2012
358 1.03.01 CV. SK Pengecoran Jalan Lingkungan dalam Desa 08/03/PPK- 485.850.000,00 24.292.500,00 1837/LS/1.20 24.292.500,00 - -
Margo Mulyo 20 Kec. Muara Padang (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 03 Sept 2013
2012
359 1.03.01 CV. SK Pengecoran Jalan Desa Daya Utama Ke Ds. 25/03/PPK- 391.979.000,00 19.598.950,00 2980/LS/1.20 19.598.950,00 - -
Margo Mulyo Kec. Muara Padang (* P3L.III/PUCK/20 .09.02.00/6.2/
12, Tanggal 29 2013
Oktober 2012
360 1.03.01 CV. RK Pengecoran Jalan Lingkungan Dalam Desa 20/03/SPK/PPK- 99.380.000,00 4.969.000,00 5360/LS/1.20 4.969.000,00 - -
Tanjung Baru Kec. Muara Padang P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15-10- 2013
2012
361 1.03.01 CV. SmJ Pengecoran Jalan Lingkungan Dalam Desa 21/03/SPK/PPK- 99.336.000,00 4.966.800,00 5401/LS/1.20 4.966.800,00 - -
Karang Anyar Kec. Muara Padang P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL 15-10-12 2013
362 1.03.01 CV. BJ Pengecoran Jalan Lingkungan Dalam Desa 22/03/SPK/PPK- 99.400.000,00 4.970.000,00 6109/LS/1.20 4.970.000,00 - -
Muara Padang Kec. Muara Padang P3L.III/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
363 1.03.01 CV. SmJ Pengecoran Jalan Lingkungan Dalam Desa 23/03/SPK/PPK- 99.490.000,00 4.974.500,00 5400/LS/1.20 4.974.500,00 - -
Daya Makmur Kec. Muara Padang P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15 Okt 2013
2012
Halaman 29 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
364 1.03.01 CV. SmJ Pengecoran Jalan Lingkungan Dalam Desa 24/03/SPK/PPK- 99.400.000,00 4.970.000,00 5403/LS/1.20 4.970.000,00 - -
Sumber Makmur Kec. Muara Padang P3L.III/PUCK/20 .09.02.00/6.2/
12 TGL 15-10-12 2013
365 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Dalam Desa 02/03/SPK/PPK- 99.403.000,00 4.970.150,00 3718/LS/1.20 4.970.150,00 - -
Sukaraja Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 TGL 15-10-12 2013
366 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Dalam Desa 03/03/SPK/PPK- 99.323.000,00 4.966.150,00 3717/LS/1.20 4.966.150,00 - -
Suka Mulya Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 TGL 15-10-12 2013
367 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Dalam Desa 04/03/SPK/PPK- 99.341.000,00 4.967.050,00 - - 4.967.050,00
Karang Asem Kec. Tungkal Ilir PP.IV/PUCK/201
2 Tgl 15 Oktober
2012
368 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Dalam Desa 05/03/SPK/PPK- 99.341.000,00 4.967.050,00 4695/LS/1.20 4.967.050,00 - -
Karang Mulya Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
369 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Dalam Desa 06/03/SPK/PPK- 99.341.000,00 99.341.000,00 0324/LS/1.20 94.373.950,00 - 4.967.050,00
Karang Anyar Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Okt 2013
2012
370 1.03.01 CV. Dih Pengecoran Jalan Lingkungan Dalam Desa 07/03/SPK/PPK- 99.333.000,00 4.966.650,00 3726/LS/1.20 4.966.650,00 - -
Marga Rahayu Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 TGL 15-10-12 2013
371 1.03.01 CV. Dih Pengecoran Jalan Lingkungan Dalam Desa 08/03/SPK/PPK- 99.362.000,00 4.968.100,00 3753/LS/1.20 4.968.100,00 - -
Teluk Tenggulang Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Oktober 2013
2012
372 1.03.01 CV. Dih Pengecoran Jalan Lingkungan Dalam Desa 09/03/SPK/PPK- 99.356.000,00 4.967.800,00 3866/LS/1.20 4.967.800,00 - -
Suka Karya Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Oktober 2013
2012
373 1.03.01 CV. Dih Pengecoran Jalan Lingkungan Dalam Desa 10/03/SPK/PPK- 99.345.000,00 4.967.250,00 3867/LS/1.20 4.967.250,00 - -
Panca Mulya Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 TGL 15-10-12 2013
374 1.03.01 CV. Dih Pengecoran Jalan Lingkungan Dalam Desa 11/03/SPK/PPK- 99.336.000,00 99.336.000,00 0316/LS/1.20 94.369.200,00 - 4.966.800,00
Bentayan Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Okt 2013
2012
375 1.03.01 CV. SIT Pengecoran Jalan Lingkungan Dalam Desa 12/03/SPK/PPK- 99.237.000,00 4.961.850,00 3719/LS/1.20 4.961.850,00 - -
Bumi Serdang Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
376 1.03.01 CV. SIT Pengecoran Jalan Lingkungan Dalam Desa 13/03/SPK/PPK- 99.292.000,00 4.964.600,00 5753/LS/1.20 4.964.600,00 - -
Keluang Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 Tgl 15 Okt 2013
2012
Halaman 30 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
377 1.03.01 CV. SIT Pengecoran Jalan Lingkungan Dalam Desa 14/03/SPK/PPK- 99.356.000,00 4.967.800,00 4691/LS/1.20 4.967.800,00 - -
Sukajaya Pertak III Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 15-10-12 2013
378 1.03.01 CV. SIT Pengecoran Jalan Lingkungan Dalam Desa 15/03/SPK/PPK- 99.237.000,00 99.237.000,00 0315/LS/1.20 99.237.000,00 - -
Sido Mulyo Kec. Tungkal Ilir PP.IV/PUCK/201 .09.02.00/6.2/
2 Tgl 15-10-12 2013 dan
6152/LS/1.20
.09.02.00/6.2/
2013
379 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 16/03/SPK/PPK- 99.415.000,00 4.970.750,00 1741/LS/1.20 4.970.750,00 - -
Suka Damai Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
380 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 17/03/SPK/PPK- 99.425.000,00 4.971.250,00 1738/LS/1.20 4.971.250,00 - -
Muara Sugih Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
381 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 18/03/SPK/PPK- 99.426.000,00 4.971.300,00 1737/LS/1.20 4.971.300,00 - -
Purwosari Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
382 1.03.01 CV. PT Pengecoran Jalan Lingkungan Dalam Desa 19/03/SPK/PPK- 99.428.000,00 4.971.400,00 1734/LS/1.20 4.971.400,00 - -
Mulya Sari Kec. Tanjung Lago IV/PUCK/2012 .09.02.00/6.2/
Tgl 15 Oktober 2013
2012
383 1.03.01 CV. PT Pengecoran Jalan Lingkungan Dalam Desa 20/03/SPK/PPK- 99.418.000,00 4.970.900,00 1789/LS/1.20 4.970.900,00 - -
Telang Sari Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
384 1.03.01 CV. BT Pengecoran Jalan Lingkungan Dalam Desa 21/03/SPK/PPK- 99.432.000,00 4.971.600,00 1790/LS/1.20 4.971.600,00 - -
Sumber Mekar Mukti Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10 2013
385 1.03.01 CV. PT Pengecoran Jalan Lingkungan Dalam Desa 22/03/SPK/PPK- 99.438.000,00 4.971.900,00 1788/LS/1.20 4.971.900,00 - -
Banyu Urip Kec. Tanjung Lago PP.IV/2012, Tgl. .09.02.00/6.2/
15-10-2012 2013
386 1.03.01 CV. BT Pengecoran Jalan Lingkungan Dalam Desa 23/03/SPK/PPK- 99.430.000,00 4.971.500,00 1730/LS/1.20 4.971.500,00 - -
Manggaraya Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
387 1.03.01 CV. BT Pengecoran Jalan Lingkungan Dalam Desa 24/03/SPK/PPK- 99.410.000,00 4.970.500,00 1729/LS/1.20 4.970.500,00 - -
Tanjung Lago Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
388 1.03.01 CV. BT Pengecoran Jalan Lingkungan Dalam Desa 25/03/SPK/PPK- 99.455.000,00 4.972.750,00 1733/LS/1.20 4.972.750,00 - -
Kuala Puntian Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
Halaman 31 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
389 1.03.01 CV. PT Pengecoran Jalan Lingkungan Dalam Desa 26/03/SPK/PPK- 99.400.000,00 4.970.000,00 1735/LS/1.20 4.970.000,00 - -
Suka Tani Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
390 1.03.01 CV. BT Pengecoran Jalan Lingkungan Dalam Desa 27/03/SPK/PPK- 99.465.000,00 4.973.250,00 1731/LS/1.20 4.973.250,00 - -
Sri Menanti Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2 2013
391 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 28/03/SPK/PPK- 99.465.000,00 4.973.250,00 1740/LS/1.20 4.973.250,00 - -
Bunga Karang Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
392 1.03.01 CV. TS Pengecoran Jalan Lingkungan Dalam Desa 29/03/SPK/PPK- 99.405.000,00 4.970.250,00 1739/LS/1.20 4.970.250,00 - -
Bangun Sari Kec. Tanjung Lago PP.IV/PUCK/201 .09.02.00/6.2/
2, Tgl. 15-10- 2013
2012
393 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Rt.11 Rw.06 14/03/SPK/PPK- 99.237.000,00 4.961.850,00 4295/LS/1.20 4.961.850,00 - -
LK.II Kel. Makarti Jaya P3L.III/PUCK/20 .09.02.00/6.2/
12 07 September 2013
2012
394 1.03.01 CV. HBS Pengecoran Jalan Lingk. Rt. 07 dan Rt. 08 15/03/SPK/PPK- 99.237.000,00 4.961.850,00 3863/LS/1.20 4.961.850,00 - -
Rw.04 LK.III Kel. Makarti Jaya P3L.III/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
395 1.03.01 CV. HBS Pengecoran Lorong Manggar Rt. 02 dan Rt. 16/03/SPK/PPK- 99.292.000,00 99.292.000,00 0323/LS/1.20 99.292.000,00 - -
04 Kel. Makarti Jaya P3L.III/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013 dan
2012 3763/LS/1.20
.09.02.00/6.2/
2013
396 1.03.01 CV. Dih Pengecoran Jalan Lingkungan 1 Kelurahan 02/03/SPK/PPK- 99.351.000,00 4.967.550,00 - - 4.967.550,00
Makarti Jaya TRTB.I/PUCK/20
12 Tgl 15
Oktober 2012
397 1.03.01 CV. HBS Pengecoran Jalan Lingkungan Dalam 17/03/SPK/PPK- 99.121.000,00 4.956.050,00 3864/LS/1.20 4.956.050,00 - -
Kelurahan Makarti Jaya Kec. Makarti Jaya P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15 2013
OKtober 2012
398 1.03.01 CV. KJ Pengecoran Jalan Dalam Desa Upang Ceria 18/03/SPK/PPK- 199.247.000,00 9.962.350,00 4480/LS/1.20 9.962.350,00 - -
Kec. Makarti Jaya (** P3L- .09.02.00/6.2/
III/PUCK/2012 2013
Tgl 15 Okt 2012
399 1.03.01 CV. LS Pengecoran Jalan Lingkungan I Kel. 19/03/SPK/PPK- 199.367.000,00 9.968.350,00 2374/LS/1.20 9.968.350,00 - -
Makarti Jaya Kec. Makarti Jaya P3L.III/PUCK/20 .09.02.00/6.2/
12 2013
400 1.03.01 CV. Dih Pengecoran Lorong Garuda LK. III Kel. 03/03/SPK/PPK- 99.351.000,00 4.967.550,00 - - 4.967.550,00
Makarti Jaya Kec. Makarti Jaya TRTB.I/PUCK/20
12, Tgl. 15-10-
2012
Halaman 32 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
401 1.03.01 PT. PRa Pembangunan Jerambah Titian dalam Desa 03/19/PPK/PUC 636.959.000,00 31.847.950,00 1709/LS/1.20 31.847.950,00 - -
Sungai Rebo Kec. Banyuasin I K/2012 Tgl 03 .09.02.00/6.2/
Sept 2012 2013
402 1.03.01 PT. PRa Pembangunan Jerambah Cuci mandi Lrg. 13/03/PPK- 293.990.000,00 14.699.500,00 5136/LS/1.20 14.699.500,00 - -
Selumar Rt. 12/02 Kel. Mariana Ilir Kec. PP.I/PUCK/2012 .09.02.00/6.2/
BA I (* Tgl 03 Sept 2012 2013
403 1.03.01 CV. TS Pembangunan Jerambah Titian Sei Batang 13/03/PPK- 99.300.000,00 4.965.000,00 0921/LS/1.20 4.965.000,00 - -
Rt 10 Desa P. Borang Kec. Banyuasin I (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tanggal 02 2013
Agustus 2012
404 1.03.01 CV. IB Pembangunan Jerambah Titian Lrg Karet 14/03/PPK- 99.310.000,00 4.965.500,00 0922/LS/1.20 4.965.500,00 - -
Desa Merah Mata Kec. Banyuasin I (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tanggal 02 2013
Agustus 2012
405 1.03.01 CV. TS Pembangunan Jerambah Titian RT. 12, 13 06/03/SPK/PPK- 99.825.000,00 4.991.250,00 5556/LS/1.20 4.991.250,00 - -
dan 14 Desa Pulau Borang Kec. Banyuasin P3L.IV/PUCK/20 .09.02.00/6.2/
I 12 Tgl 15 2013
Oktober 2012
406 1.03.01 CV. AgSe Pembangunan Jerambah Titian Lrg. H. 07/03/SPK/PPK- 99.300.000,00 4.965.000,00 1231/LS/1.20 4.965.000,00 - -
Sani Desa Sungai Dua dsn. IV Kec. PP.III/PUCK/201 .09.02.00/6.2/
Rambutan 2 Tgl 06 Agustus 2013
20
407 1.03.01 CV. IB Pembangunan Jerambah Titian Desa 01/03/SPK/PPK- 99.332.000,00 4.966.600,00 5141/LS/1.20 4.966.600,00 - -
Pangkalan Gelebek Kec. Rambuatan (* PP.III/PUCK/201 .09.02.00/6.2/
2, Tgl. 05-09- 2013
2012
408 1.03.01 CV. RFg Pembangunan Jerambah Titian Tanjung .02/03/PPK- 244.999.000,00 12.249.950,00 3515/LS/1.20 12.249.950,00 - -
Macan Desa Tjg Kerang Kec. Rambutan PP.III/PUCK/201 .09.02.00/6.2/
(lanjutan) (* 2 Tgl 03-Sep- 2013
2012 Adendum
02.A/03/PPK-
PP.III/PUCK/201
2,28-09-2012
409 1.03.01 CV. DP Pembangunan Jerambah Desa Upang Marga 12/03/SPK/PPK- 99.350.000,00 4.967.500,00 2814/LS/1.20 4.967.500,00 - -
Kec. Makarti Jaya OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 07 2013
September 2012
410 1.03.01 CV. PL Pembangunan Jembatan Desa Dusun I dan 11/03/SPK/PPK- 147.480.000,00 7.374.000,00 2410/LS/1.20 7.374.000,00 - -
Dusun II Desa Tirta Mulya Kec. Makati OP.II/PUCK/201 .09.02.00/6.2/
Jaya (* 2 Tgl 13 2013
September 2012
411 1.03.01 CV. DP Pembangunan Jembatan Desa Salek Jaya 08/03/SPK/PPK- 99.310.000,00 4.965.500,00 3037/LS/1.20 4.965.500,00 - -
Kec. Air Saleh OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 07 Sept 2013
2012
Halaman 33 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
412 1.03.01 CV. BI Pembangunan Jembatan Desa Sido Enggal 09/03/SPK/PPK- 99.383.000,00 4.969.150,00 - - 4.969.150,00
Rejo Kec. Air Saleh OP.II/PUCK/201
2 Tgl 13
September 2012
413 1.03.01 CV. RK Pembangunan Jerambah Desa Saleh Agung 10/03/SPK/PPK- 81.342.000,00 4.067.100,00 5402/LS/1.20 4.067.100,00 - -
Kec. Air Saleh OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 07 2013
September 2012
414 1.03.01 CV. AJU Pembangunan Jerambah penghubung Desa 05/03/SPK/PPK- 69.336.000,00 3.466.800,00 3282/LS/1.20 3.466.800,00 - -
Terusan Tengah Kec. Muara Telang (* OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 07 Sept 2013
2012
415 1.03.01 CV. JIL Pembangunan Jerambah penghubung Desa 06/03/SPK/PPK- 69.308.000,00 3.465.400,00 3213/LS/1.20 3.465.400,00 - -
Terusan Dalam Kec. Muara Telang (* OP.II/PUCK/201 .09.02.00/6.2/
2 Tgl 07 Sept 2013
2012
416 1.03.01 CV. RA Pembangunan Jerambah penghubung Desa 07/03/SPK/PPK- 59.340.000,00 2.967.000,00 3212/LS/.1.2 2.967.000,00 - -
Telang Marga Kec. Muara Telang (* OP.II/PUCK/201 0.09.02.00/6.
2 Tgl 07 Sept 2/2013
2012
417 1.03.01 CV. JS Pembangunan Jembatan Penghubung Desa 12/03/SPK/PPK- 99.428.000,00 4.971.400,00 4423/LS/1.20 4.971.400,00 - -
Tirta Harja Kec. Muara Sugihan (* P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15-09- 2013
2012
418 1.03.01 CV. LS Pembangunan Jerambah Titian Desa 03/03/SPK/PPK- 99.444.000,00 4.972.200,00 6603/LS/1.20 4.972.200,00 - -
Sungsang I Kec. Banyuasin II*) OP.I/PUCK/2012 .09.02.00/6.2/
Tgl 15 Okt 2012 2013
419 1.03.01 CV. EJ Pengecoran Oprit Jembatan Penghubung 20/03/SPK/PPK- 39.935.000,00 1.996.750,00 1821/LS/1.20 1.996.750,00 - -
Antara RT. 19 ke RT. 32 Menuju Pasar Pagi P3L.IV/PUCK/20 .09.02.00/6.2/
Kelurahan Rimba Asam Kecamatan Betung 12 Tgl 15 2013
Oktober 2012
420 1.03.01 CV. IP Pembangunan Drainase/Gorong-gorong 06/03/PPK- 186.200.000,00 9.310.000,00 3516/LS/1.20 9.310.000,00 - -
dalam Desa Suka Pindah Kec. Rambutan (* PP.I/PU.CK/2012 .09.02.00/6.2/
Tgl 03 September 2013
2012
421 1.03.01 CV. BH Pembangunan Drainase/Gorong-gorong 07/03/PPK- 195.998.000,00 9.799.900,00 2507/LS/1.20 9.799.900,00 - -
dalam Desa Plajau Kec. Rambutan (* PP.II/PUCK/2012 .09.02.00/6.2/
Tgl 03 September 2013
2012
422 1.03.01 CV. DP Pembangunan Drainase Dsn I Rt. 03 dan Rt. 06/03/SPK/PPK- 99.470.000,00 4.973.500,00 2805/LS/1.20 4.973.500,00 - -
04 Dlm Desa Mainan Kec. Sembawa P3L/PUCK/2012, .09.02.00/6.2/
Tgl. 15-10-2012 2013
Halaman 34 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
423 1.03.01 CV. CG Pembangunan Drainase Dlm Desa Sri 19/03/SPK/PPK- 74.930.000,00 3.746.500,00 3554/LS/1.20 3.746.500,00 - -
Kembang Kec. Betung P3L.IV/PUCK/20 .09.02.00/6.2/
12, Tgl. 15-10- 2013
2012
424 1.03.01 CV. SP Pembangunan Drainase Koramil Talang 09/03/SPK/PPK- 99.405.000,00 4.970.250,00 3572/LS/1.20 4.970.250,00 - -
Kelapa Kec. Talang Kelapa P3L.III/PUCK/20 .09.02.00/6.2/
12 Tgl 15-10- 2013
2012
425 1.03.01 PT. CU Pemasangan Listrik Desa Sukarela Kec. 04/03/PPK- 249.153.000,00 12.457.650,00 3623/LS/1.20 12.457.650,00 - -
Rantau Bayur PO/PUCK/2012 .09.02.00/6.2/
Tgl 19-11-2012 2013
426 1.03.01 CV. LK Pembangunan WTP Mini Desa Saleh 01/03/PPK- 243.552.000,00 12.177.600,00 2779/LS/1.20 12.177.600,00 - -
Agung Kecamatan Air Saleh P3L.III/PU.CK/20 .09.02.00/6.2/
12 tgl. 27-09- 2013
2012
427 1.03.01 CV. DP Pembangunan WTP Mini Desa Tanjung 03/03/PPK- 246.464.000,00 12.323.200,00 3339/LS/1.20 12.323.200,00 - -
Baru Kecamatan Muara Padang P3L.III/PU.CK/20 .09.02.00/6.2/
12 tgl. 27-09- 2013
2012
428 1.03.01 CV. RK Pembangunan WTP Mini Desa Margo 10/01/PPK- 244.957.000,00 12.247.850,00 4577/LS/1.20 12.247.850,00 - -
Rahayu Kecamatan Tungkal Ilir P3L/PUCK/2012 .09.02.00/6.2/
Tgl 01-10-2012 2013
429 1.03.01 CV. AILS Pembangunan WTP Mini Desa Marga 05/03/PPK- 245.151.000,00 12.257.550,00 3209/LS/1.20 12.257.550,00 - -
Sungsang Kecamatan Banyuasin II P3L.III/PU.CK/20 .09.02.00/6.2/
12 tgl. 27-09- 2013
2012
430 1.03.01 CV. AJy Pembangunan WTP Mini Desa Taja Mulya 09/01/PPK- 218.381.000,00 10.919.050,00 - - 10.919.050,00
Kecamatan Betung P3L/PUCK/2012
tgl. 01-10-2012
431 1.03.01 CV. RK Pembangunan WTP Mini Desa Sidomulyo 04/03/PPK- 218.720.000,00 10.936.000,00 4581/LS/1.20 10.936.000,00 - -
Kecamatan Banyuasin I P3L.III/PU.CK/20 .09.02.00/6.2/
12 tgl. 27-09- 2013
2012
432 1.03.01 CV. RK Pembangunan WTP Mini Desa Durian 02/03/PPK- 218.520.000,00 10.926.000,00 5361/LS/1.20 10.926.000,00 - -
Gadis Kecamatan Rambutan P3L.III/PU.CK/20 .09.02.00/6.2/
12 tgl. 27-09- 2013
2012
433 1.03.01 CV. JS Pembagunan WTP Mini Engkel Desa Tirta 05/03/SPK/PPK- 99.494.000,00 4.974.700,00 4425/LS/1.20 4.974.700,00 - -
Mulya Kec. Makarti Jaya TRTB.I/PUCK/20 .09.02.00/6.2/
12 Tgl 15-10- 2013
2012
Halaman 35 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
434 1.03.01 CV. Su Pembangunan WTP Mini dan Kolam 02/03/SPK/PPK- 198.540.000,00 9.927.000,00 2381/LS/1.20 9.927.000,00 - -
Retensi Desa Tirta Mulya Kec. Muara OP.I/PUCK/2012 .09.02.00/6.2/
Sugihan Tgl 15-10- 2012 2013
435 1.03.01 PT. IP Pembuatan Taman dan Pembuatan Lampu 191.300.000,00 191.300.000,00 - - 191.300.000,00
Jalan Paket I
436 1.03.01 PT. IP Pembuatan Taman dan Pembuatan Lampu 290.800.000,00 290.800.000,00 - - 290.800.000,00
Jalan Paket I
437 1.03.01 CV. RM Pembangunan MCK Desa Tirta Mulya Kec. 05/14/PPK- 88.950.000,00 4.447.500,00 - - 4.447.500,00
Makrti Jaya PL/PUCK/2010,
tgl 07 Oktober
2010
438 1.03.01 CV. KBn Pengecoran Jalan Lingkungan Desa 03/04/PPK- 157.856.000,00 7.892.800,00 - - 7.892.800,00
Penuguan Kec. Pulau Rimau TRTB.III/PUCK/
2011
439 1.03.01 CV. BJC Pengecoran Lrg. Karet Desa Merah Mata 03/03/PPK- 146.867.000,00 7.343.350,00 - - 7.343.350,00
Kec. Banyuasin II TRTB.1/PUCK/2
011
440 1.03.01 CV. KBn Pengecoran Jalan Lingkungan Dalam Desa 03/13/PPK- 117.566.000,00 5.878.300,00 - - 5.878.300,00
Regan Agung Kec. Banyuasin III P2L.I/PUCK/201
1
441 1.03.01 CV. PU Pengecoran Jalan Lingkungan Dalam Desa 02/02/PPK- 99.386.000,00 4.969.300,00 - - 4.969.300,00
Muara Abab Kec. Rantau Bayur OP/11/PUCK/201
1
442 1.03.01 CV. Mu `z Pengecoran Lorong Lukman Ds. III Rt. 9 02/01/PPK- 99.719.000,00 4.985.950,00 - - 4.985.950,00
Desa Tirtosari Kec. Banyuasin TRTB.1/11/PUC
K/2011
443 1.03.01 PT. MPC Kegiatan Pengembangan sistem Air Bersih 1. KONTRAK - 200.000.000,00 7171/LS/1.20 79.556.896,00 - 80.045.450,00 Sisa Hutang
PT. PKS (Rp. 79.556.896 dan Rp. 80.045.450) 06/01/PPK- .09.02.00/6.2/ sebesar
FAB/PUCK/2010 2013 Rp.80.045.450
tgl. 12-8-10 disebabkan
2. KONTRAK terdapat koreksi
06/03/PPK- saldo awal utang
FAB/PUCK/2010 menjadi sebesar
tgl. 12-8-2010 Rp.159.602.346,00
444 1.03.02 CV. AS Pembuatan Box Culvert Type Single (2x2) NOMOR : 97.900.000,00 - - 97.900.000,00 97.900.000,00
Desa Rawa Banda Kec. Pulau Rimau 02/BOX-
RB/SPK/PPK/PU
BM/2013
TANGGAL : 1
MEI 2013
Halaman 36 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
445 1.03.02 CV. AS Pembuatan Box Culvert Type Single (2x2) NOMOR : 97.904.000,00 - - 97.904.000,00 97.904.000,00
Desa Nunggal Sari Kec. Pulau Rimau 02/BOX-
NS/SPK/PPK/PU
BM/2013
TANGGAL : 1
MEI 2013
446 1.03.02 CV. AS Pembuatan Box Culvert Type Single (2x2) NOMOR : 97.900.000,00 - - 97.900.000,00 97.900.000,00
Desa Dana Mulya Kec. Pulau Rimau 02/BOX-
DM/SPK/PPK/P
UBM/2013
TANGGAL : 1
MEI 2013
447 1.03.02 CV. RK Pembuatan Box Culvert Type Single (2x2) NOMOR : 97.902.000,00 - - 97.902.000,00 97.902.000,00
Desa Majatra Kec. Pulau Rimau 02/BOX-
MJTRA/SPK/PP
K/PUBM/2013
TANGGAL : 1
MEI 2013
448 1.03.02 CV. RK Pembuatan Box Culvert Type Single (2x2) NOMOR : 195.567.000,00 - - 195.567.000,00 195.567.000,00
Desa Sumber Agung Kec. Pulau Rimau 02/SMB-
AG/SPK/PPK/PU
BM/2013
TANGGAL : 1
MEI 2013
449 1.03.02 CV. RK Pembuatan Box Culvert Type Single (2x2) NOMOR : 195.622.000,00 - - 195.622.000,00 195.622.000,00
Desa Sumber Rejo Kec. Pulau Rimau 02/SMB-REJO
/SPK/PPK/PUBM
/2013
TANGGAL : 1
MEI 2013
450 1.03.02 CV. APe Pembuatan Box Culvert Kubu I Desa NOMOR : 142.517.000,00 - - 71.258.500,00 71.258.500,00
Keluang Kec. Tungkal Ilir 02/KLUANG/SP
K/PPK/APBDP/P
UBM/2013
TANGGAL : 12
NOPEMBER
2013
451 1.03.02 CV. Se Pengecoran Jalan Sripanji Desa Pangkalan Nomor : 293.669.000,00 - - 14.683.450,00 14.683.450,00
Panji Kec. Banyuasin III 06/08/PPK/KON
TRAK/PUBM/20
13 TANGGAL 20
MARET 2013
452 1.03.02 PT. KUBN Perkerasan Jalan Pulau Rimau Nomor : 14.624.578.000,00 - - 3.473.337.275,00 3.473.337.275,00
06/56/PPK/KON
TRAK/PUBM/20
13 TANGGAL 8
ARIL 2013
Halaman 37 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
453 1.03.02 CV. WM Pembangunan jembatan Desa parit 12 Dsn NOMOR : 118.625.000,00 - - 118.625.000,00 118.625.000,00
3 Desa Muara Baru Kec. Makarti Jaya 02/12DSN3/PJ/A
PBDP/PUBM/20
13 TANGGAL :
12 NOPEMBER
2013
454 1.03.02 CV. ISe Pembangunan Jembatan Sungai Pinang Nomor : 256.906.000,00 - - 73.860.475,00 73.860.475,00
Desa Karang Baru Kec. Sumber Marga 06/109/PPK/KO
Telang NTRAK/PUBM/2
013 TANGGAL
30 MEI 2013
455 1.03.02 CV. KJ Pembangunan Jembatan Desa Kuala NOMOR : 02/KL- 94.995.000,00 - - 94.995.000,00 94.995.000,00
Puntian Kec. Tanjung Lago PTN/SPK/PPK/A
PBDP/PUBM/20
13 TANGGAL :
12 NOPEMBER
2013
456 1.03.02 CV. NPM Pengecoran Jalan Desa Tanjung Menang 05/TM/PPK- 391.119.000,00 19.555.950,00 2364/LS/1.20 19.555.950,00 - -
Kec. Banyuasin III KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 10 2013
Oktober 2012
457 1.03.02 CV. HBS Pengecoran Jalan Sp. Regan Agung - Regan 05/RA/PPK- 684.515.000,00 34.225.750,00 3030/LS/1.20 34.225.750,00 - -
Agung Kec. Banyuasin III (Tahap III) KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 10 2013
Oktober 2012
458 1.03.02 CV. EC Pengecoran Jalan Pasar Pangkalan Balai 02/PBB/SPK/PP 196.230.000,00 9.811.500,00 7204/LS/1.20 9.811.500,00 - -
Kec. Banyuasin III (Tahap II) K/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
459 1.03.02 CV. TJ Pengecoran Jalan Taman Baru Kelurahan 02/TBKS/SPK/PP 196.126.000,00 9.806.300,00 3605/LS/1.20 9.806.300,00 - -
Seterio Kec. Banyuasin III K/PUBM/2012 .09.02.00/6.2/
Tgl. 12 Oktober 2013
2012
460 1.03.02 CV. RJ Rehabilitasi Jalan Lingkar Mulya Agung - 01/SETERIO/SP 98.288.000,00 4.914.400,00 1042/LS/1.20 4.914.400,00 - -
Seterio K/PPK/PUBM/20 .09.02.00/6.2/
12 Tgl. 20 Maret 2013
2012
461 1.03.02 CV. EC Pengecoran Jalan Menuju Rumah Staf 02/RSK/SPK/PP 196.196.000,00 9.809.800,00 7174/LS/1.20 9.809.800,00 - -
Kajari Pangkalan Balai Kec. Banyuasin III K/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
Halaman 38 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
462 1.03.02 CV. HBS Pembangunan Jembatan Penghubung Dsn. I 02/J- 146.904.000,00 7.345.200,00 3005/LS/1.20 7.345.200,00 - -
Ke Dsn. II Desa Tanjung Menang Musi TMM/SPK/PPK/ .09.02.00/6.2/
Kec. Rantau Bayur PUBM/2012 Tgl. 2013
17 Oktober 2012
463 1.03.02 CV. IP Pengecoran Jalan Desa Tanjung Menang 02/DTMM/SPK/P 73.404.000,00 3.670.200,00 4631/LS/1.20 3.670.200,00 - -
Musi Kec. Rantau Bayur PK/PUBM/2012 .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
464 1.03.02 CV. RFg Pengecoran Jalan Sidang Mas Kec. 02/S- 122.300.000,00 6.115.000,00 4612/LS/1.20 6.115.000,00 - -
Banyuasin III MAS/SPK/PPK/P .09.02.00/6.2/
UBM/2012 Tgl. 2013
12 Oktober 2012
465 1.03.02 CV. IP Pengecoran Jalan Rimba Balai Kec. 02/RB/SPK/PPK/ 121.906.000,00 6.095.300,00 4632/LS/1.20 6.095.300,00 - -
Banyuasin III PUBM/2012 Tgl. .09.02.00/6.2/
17 Oktober 2012 2013
466 1.03.02 PT. BAP Pengecoran Jalan Menuju Pondok Pesantren 05/SH/PPK- 293.577.000,00 14.678.850,00 2095/LS/1.20 14.678.850,00 - -
Sabilul Hasanah Kec. Sembawa KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 25 2013
September 2012
467 1.03.02 CV. PU Pengecoran Jalan Desa Limau Kec. 05/DL/PPK- 293.365.000,00 14.668.250,00 - - 14.668.250,00
Sembawa KONTRAK/PUB
M/2012 Tgl. 10
Oktober 2012
468 1.03.02 CV. Se Pembangunan Jembatan Desa dari dsn 3 ke 02/PH/SPK/PPK/ 195.904.000,00 9.795.200,00 - - 9.795.200,00
dsn 2 Desa Pulau Harapan Kec. Sembawa PUBM/2012 Tgl.
12 Oktober 2012
469 1.03.02 CV. AILS Pengecoran Jalan Perintis Menuju SMA 02/PERINTIS/SP 195.741.000,00 9.787.050,00 7221/LS/1.20 9.787.050,00 - -
Kel. Sukamoro Kec. Talang Kelapa (Tahap K/PPK/PUBM/20 .09.02.00/6.2/
II) 12 Tgl. 17 2013
September 2012
470 1.03.02 CV. LK Pengecoran Jalan Swadaya Kelurahan 02/SWDY/SPK/P 195.451.000,00 9.772.550,00 2800/LS/1.20 9.772.550,00 - -
Sukajadi Kec. Talang Kelapa PK/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
471 1.03.02 CV. DP Pengecoran Jalan A. Yani Kec. Talang 02/A.YANI/SPK/ 195.603.000,00 9.780.150,00 2806/LS/1.20 9.780.150,00 - -
Kelapa PPK/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
472 1.03.02 CV. DAc Pengecoran Jalan Desa Kenten Laut Kec. 02/KL/SPK/PPK/ 97.870.000,00 4.893.500,00 3649/LS/1.20 4.893.500,00 - -
Talang Kelapa PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
Halaman 39 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
473 1.03.02 CV. AnSe Pengecoran Jalan Dalam Rt. 04 Desa 02/KL/SPK/PPK/ 97.926.000,00 4.896.300,00 3650/LS/1.20 4.896.300,00 - -
Gasing Kec. Talang Kelapa PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
474 1.03.02 CV. AnSe Pengecoran Jalan Dalam Rt. 08 Desa 02/RT.08/SPK/PP 97.954.000,00 4.897.700,00 3648/LS/1.20 4.897.700,00 - -
Gasing Kec. Talang Kelapa K/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
475 1.03.02 CV. RAP Pengecoran Jalan Masjid RT. 11 Ds. Gasing 02/RT.11/SPK/PP 98.066.000,00 4.903.300,00 3520/LS/1.20 4.903.300,00 - -
Kec. Talang Kelapa K/PUBM/2012 .09.02.00/6.2/
Tgl.12 Oktober 2013
2012
476 1.03.02 CV. DAc Pengecoran Jalan dalam Rt. 02 Rw. 01 02/TK/SPK/PPK/ 195.390.000,00 9.769.500,00 4216/LS/1.20 9.769.500,00 - -
Kel.Talang Keramat Kec. Talang Kelapa PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
477 1.03.02 CV. JU Pengecoran Jalan/Lrg Puncak Permai III 02/PP- 97.901.000,00 4.895.050,00 3454/LS/1.20 4.895.050,00 - -
Rt. 02 kelurahan Tanah Mas Kec. Talang TM/SPK/PPK/PU .09.02.00/6.2/
Kelapa (Menuju Masjid Nur Hidayah) BM/2012 Tgl. 17 2013
September 2012
478 1.03.02 CV. NJ Pengecoran Jalan Tanah Mas Kec. Talang 05/T-MAS/PPK- 293.659.000,00 14.682.950,00 3036/LS/1.20 14.682.950,00 - -
Kelapa KONTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
10 Oktober 2012
479 1.03.02 CV. KY Pengerasan Jln Chandradimuka Kelurahan 02/CNDR/SPK/P 195.609.000,00 9.780.450,00 3568/LS/1.20 9.780.450,00 - -
Sukamoro Kec. Talang Kelapa PK/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
480 1.03.02 CV. An Pengecoran Jalan Dalam Komplek Dana 02/DPS/SPK/PPK 97.957.000,00 4.897.850,00 2801/LS/1.20 4.897.850,00 - -
Puspa Sari Kenten Kec. Talang Kelapa /PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
481 1.03.02 CV. An Pengecoran Jalan Depan Kantor Camat 02/KC/SPK/PPK/ 98.007.000,00 4.900.350,00 2819/LS/1.20 4.900.350,00 - -
Talang Kelapa PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
482 1.03.02 CV. LK Pengecoran Jalan Pangkalan Benteng Kec. 05/PB/PPK- 293.334.000,00 14.666.700,00 2816/LS/1.20 14.666.700,00 - -
Talang Kelapa KONTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
10 Oktober 2012
483 1.03.02 CV. DP Pengecoran Jalan Dalam Komplek 02/PI/SPK/PPK/P 195.654.000,00 9.782.700,00 2820/LS/1.20 9.782.700,00 - -
Pesantren Inayatullah UBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
Halaman 40 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
484 1.03.02 CV. DP Pengecoran Jalan Komplek Kenten Azhar 05/KA/PPK- 293.393.000,00 14.669.650,00 2818/LS/1.20 14.669.650,00 - -
Kec. Talang kelapa KONTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
10 Oktober 2012
485 1.03.02 CV. JB Pengerasan Ruas Jalan Tanjung Api-api - 05/KP/PPK- 245.334.000,00 12.266.700,00 1140/LS/1.20 12.266.700,00 - -
Kuala Puntian Kec. Tanjung Lago (Tahap KONTRAK/PUB .09.02.00/6.2/
II) M/2012 Tgl. 25 2013
September 2012
486 1.03.02 CV. PKM Pengecoran Jalan Tanjung Api-api ke Dsn I 02/TAA- 195.641.000,00 9.782.050,00 4802/LS/1.20 9.782.050,00 - -
Desa Sukatani Kec. Tanjung Lago DS/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 12 2013
Oktober 2012
487 1.03.02 CV. RMK Pembuatan Box Culvert Type Single (3x3) 02/BKP- 195.711.000,00 9.785.550,00 3201/LS/1.20 9.785.550,00 - -
Ruas Jalan Tanjung Api-api - Kuala Puntian 1/SPK/PPK/PUB .09.02.00/6.2/
Kec. Tanjung Lago - Box No. 01 M/2012 Tgl. 17 2013
September 2012
488 1.03.02 CV. RMK Pembuatan Box Culvert Type Single (3x3) 02/BKP- 195.707.000,00 9.785.350,00 3199/LS/1.20 9.785.350,00 - -
Ruas Jalan Tanjung Api-api - Kuala Puntian 2/SPK/PPK/PUB .09.02.00/6.2/
Kec. Tanjung Lago - Box No. 02 M/2012 Tgl. 17 2013
September 2012
489 1.03.02 CV. PP Pembuatan Box Culvert Type Single (2x2) 02/BOX- 97.610.000,00 4.880.500,00 2265/LS/1.20 4.880.500,00 - -
Desa Kuala Puntian Kec. Tanjung Lago KP/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
September 2012
490 1.03.02 CV. RMK Penimbunan dengan Galian Tanah 05/DII-S/PPK- 391.642.000,00 19.582.100,00 3200/LS/1.20 19.582.100,00 - -
Setempat Dsn II Desa Sukatani Kec. KONTRAK/ .09.02.00/6.2/
Tanjung Lago PUBM/2012 Tgl. 2013
10 Oktober 2012
491 1.03.02 CV. NP Pengerasan Jalan Dsn IV dan V Desa 02/BS/SPK/PPK/ 195.586.000,00 9.779.300,00 5249/LS/1.20 9.779.300,00 - -
Bangun Sari Kec. Tanjung Lago PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
492 1.03.02 CV. NP Pembangunan Jembatan Rt. 04 Desa Mulya 02/MS/SPK/PPK/ 97.705.000,00 4.885.250,00 6148/LS/1.20 4.885.250,00 - -
Sari Kec. Tanjung Lago PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
493 1.03.02 PT. SCP Pembangunan Jembatan Beton Desa Panca 05/PD/PPK/KON 981.769.000,00 49.088.450,00 5252/LS/1.20 49.088.450,00 - -
Desa Kec. Banyuasin I TRAK/PUBM/20 .09.02.00/6.2/
12 Tgl. 9 Juli 2013
2012
494 1.03.02 PT. Ar Pengecoran Jalan Talang Andong Kec. 05/TA/PPK- 831.256.000,00 41.562.800,00 2137/LS/1.20 41.562.800,00 - -
Banyuasin I (Tahap III) KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 10 2013
Oktober 2012
Halaman 41 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
495 1.03.02 PT. Ar Pengecoran Jalan Desa Duren Ijo Kec. 05/DI/PPK- 831.003.000,00 41.550.150,00 2136/LS/1.20 41.550.150,00 - -
Banyuasin I (Tahap II) KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 10 2013
Oktober 2012
496 1.03.02 CV. IB Pembangunan Jembatan Penghubung Rt. 1 02/PR/SPK/PPK/ 98.218.000,00 4.910.900,00 - - 4.910.900,00
dan 2 Desa Padang Rejo SP 1 A Kec. BA I PUBM/2012 Tgl.
17 September
2012
497 1.03.02 CV. IB Pembangunan Jembatan Penghubung Rt. 15 02/JP- 98.218.000,00 4.910.900,00 - - 4.910.900,00
SP 2 Desa Sido Makmur Kec. Banyuasin I SM/SPK/PPK/PU
BM/2012 Tgl. 17
September 2012
498 1.03.02 CV. IB Pembangunan Jembatan Penghubung Rt. 10 02/AKP/SPK/PP 98.218.000,00 4.910.900,00 - - 4.910.900,00
SP 3 AKP K/PUBM/2012
Tgl. 17
September 2012
499 1.03.02 CV. CJP Pembuatan Box Culvert Rt. 16 Kelurahan 02/KMI/SPK/PP 97.964.000,00 4.898.200,00 3338/LS/1.20 4.898.200,00 - -
Mariana Ilir Laut Kec. BA I K/PUBM/2012 .09.02.00/6.2/
Tgl. 12 Oktober 2013
2012
500 1.03.02 CV. KJ Pembangunan Jembatan Desa Panca Desa 02/PD/SPK/PPK/ 196.039.000,00 9.801.950,00 4486/LS/1.20 9.801.950,00 - -
Kec. Banyuasin I PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
501 1.03.02 CV. RJK Pembuatan Box Culvert Jln Maulana Kec. 02/BJM/SPK/PP 48.940.000,00 2.447.000,00 4630/LS/1.20 2.447.000,00 - -
Banyuasin III K/PUBM/2012, .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
502 1.03.02 CV. RMK Pembentukan Badan Jalan menuju 02/NIUT/SPK/PP 97.277.000,00 4.863.850,00 3198/LS/1.20 4.863.850,00 - -
Pesantren Nurul Iman Desa Ujung Tanjung K/PUBM/2012, .09.02.00/6.2/
Kec. Banyuasin III Tgl. 17 Oktober 2013
2012
503 1.03.02 PT. MM Pembangunan Jembatan Sungai Tapa Kec. 05/ST/PPK/KON 1.471.233.000,00 73.561.650,00 2233/LS/1.20 73.561.650,00 - -
Rambutan TRAK/PUBM/20 .09.02.00/6.2/
12 Tgl. 9 Juli 2013
2012
504 1.03.02 CV. CZ Penimbunan dengan Tanah Pilihan Jalan 05/DS-SP3/PPK- 391.529.000,00 19.576.450,00 7228/LS/1.20 19.576.450,00 - -
Desa Sebokor - SP. 3 Kec. Rambutan KONTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
10 Oktober 2012
505 1.03.02 CV. WJ Pengecoran Jalan Meritai - Sungai Pinang 02/MSP/SPK/PP 196.218.000,00 9.810.900,00 - - 9.810.900,00
Kec. Rambutan K/PUBM/2012
Tgl. 17
September 2012
Halaman 42 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
506 1.03.02 CV. KSD S Pengecoran Jalan Desa Gelebak Dalam Kec. 02/GD/SPK/PPK/ 196.231.000,00 9.811.550,00 7222/LS/1.20 9.811.550,00 - -
Rambutan PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
507 1.03.02 CV. PPe Pengerasan Jalan Desa Menten Menuju 02/DM- 98.062.000,00 4.903.100,00 3295/LS/1.20 4.903.100,00 - -
Dusun Selpa Kec. Rambutan DS/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
September 2012
508 1.03.02 CV. AP Penimbunan dengan Galian Tanah 02/DG/SPK/PPK/ 48.903.000,00 2.445.150,00 - - 2.445.150,00
Setempat Desa Durian Gadis kec. PUBM/2012 Tgl.
Rambutan 29 Oktober 2012
509 1.03.02 CV. Lg Penimbunan dan Pembuatan Tembok 02/TPDP/SPK/PP 196.162.000,00 9.808.100,00 4786/LS/1.20 9.808.100,00 - -
Penahan Jalan Desa Parit Kec. Rambutan K/PUBM/2012 .09.02.00/6.2/
Tgl. 12 Oktober 2013
2012
510 1.03.02 CV. BH Pembuatan Tembok Penahan Jalan Lintas 05/DP/PPK- 244.595.000,00 12.229.750,00 2592/LS/1.20 12.229.750,00 - -
Ds. Plaju Kec. Rambutan KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 10 2013
Oktober 2012
511 1.03.02 CV. CMAP Pembuatan Siring Pasangan Desa Siju Kec. 02/SIJU/SPK/PP 97.904.000,00 4.895.200,00 - - 4.895.200,00
Rambutan (Tahap II) K/PUBM/2012
Tgl. 29 Oktober
2012
512 1.03.02 CV. ArG Pembuatan Box Culvert Ruas Jalan Meritai - 02/MSP- 78.009.000,00 3.900.450,00 4009/LS/1.20 3.900.450,00 - -
Sungai Pinang Kec. Rambutan - Box 01/SPK/PPK/PU .09.02.00/6.2/
Culvert No. 01 BM/2012 2013
Tgl. 29 Oktober
2012
513 1.03.02 CV. ArG Pembuatan Box Culvert Ruas Jalan Meritai - 02/MSP- 78.009.000,00 3.900.450,00 4010/LS/1.20 3.900.450,00 - -
Sungai Pinang Kec. Rambutan - Box 02/SPK/PPK/PU .09.02.00/6.2/
Culvert No. 02 BM/2012 2013
Tgl. 29 Oktober
2012
514 1.03.02 CV. ArG Pembuatan Box Culvert Ruas Jalan Meritai - 02/MSP- 78.009.000,00 3.900.450,00 4008/LS/1.20 3.900.450,00 - -
Sungai Pinang Kec. Rambutan - Box 03/SPK/PPK/PU .09.02.00/6.2/
Culvert No. 03 BM/2012 2013
Tgl. 29 Oktober
2012
515 1.03.02 CV. IB Penimbunan dengan Tanah Galian 02/PG/SPK/PPK/ 98.061.000,00 4.903.050,00 - - 4.903.050,00
Setempat Desa Pangkalan Gelebak Kec. PUBM/2012 Tgl.
Rambutan 17 September
2012
516 1.03.02 CV. KSD S Penimbunan Jalan dengan Tanah Pilihan 02/DB/SPK/PPK/ 196.194.000,00 9.809.700,00 7229/LS/1.20 9.809.700,00 - -
Desa Baru Kec. Rambutan PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
Halaman 43 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
517 1.03.02 CV. RFg Pengecoran Jalan Menuju Pelabuhan Lama 02/PL/SPK/PPK/ 196.002.000,00 9.800.100,00 4562/LS/1.20 9.800.100,00 - -
Desa Tanjung Kerang Kec. Rambutan PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
518 1.03.02 CV. BT Pembangunan Jembatan Beton Desa 05/PH/PPK/KON 1.080.005.000,00 54.000.250,00 1732/LS/1.20 54.000.250,00 - -
Pendowo Harjo Kec. Makarti Jaya TRAK/PUBM/20 .09.02.00/6.2/
12 Tgl. 9 Juli 2013
2012
519 1.03.02 CV. RS Pengecoran Jalan dari Parit I ke Parit IV Lk. 02/P1- 196.175.000,00 9.808.750,00 4614/LS/1.20 9.808.750,00 - -
2 Makarti Jaya Kec. Makarti Jaya P4/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
September 2012
520 1.03.02 CV. JB Pengecoran Jalan Dalam Desa Pendowo 02/DPH/SPK/PP 195.900.000,00 9.795.000,00 3269/LS/1.20 9.795.000,00 - -
Harjo Kec. Makarti Jaya (Tahap II) K/PUBM/2012 .09.02.00/6.2/
Tgl. 29 Oktober 2013
2012
521 1.03.02 CV. JB Pembangunan Jembatan Penghubung dalam 02/DU/SPK/PPK/ 146.799.000,00 7.339.950,00 3182/LS/1.20 7.339.950,00 - -
Desa Delta Upang Kec. Makarti Jaya PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
522 1.03.02 CV. GB Pembangunan Jembatan Parit 5 Desa Upang 02/UC/SPK/PPK/ 146.799.000,00 7.339.950,00 3194/LS/1.20 7.339.950,00 - -
Ceria Kec. Makarti Jaya PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
523 1.03.02 CV. GB Pembangunan Jembatan Parit I Lk. III Kec. 02/P1- 146.799.000,00 7.339.950,00 3180/LS/1.20 7.339.950,00 - -
Makarti Jaya L3/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
September 2012
524 1.03.02 CV. GB Pembangunan Jembatan Penghubung Desa 02/DTK/SPK/PP 146.799.000,00 7.339.950,00 3205/LS/1.20 7.339.950,00 - -
Tirta kencana Kec. Makarti Jaya K/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
525 1.03.02 CV. MU Pembangunan Jembatan Beton Desa 05/MR/PPK/KO 783.404.000,00 39.170.200,00 - - 39.170.200,00
Margarahayu Kec. Tungkal Ilir NTRAK/PUBM/2
012 Tgl. 9 Juli
2012
526 1.03.02 CV. AnSe Pembangunan Jembatan Sungai Priok Belah 02/SPB/SPK/PPK 127.031.000,00 6.351.550,00 3646/LS/1.20 6.351.550,00 - -
Ruas Jalan Desa Sukaraja - Ds Teluk /PUBM/2012 Tgl. .09.02.00/6.2/
Tenggulang Kec. Tungkal Ilir 17 Oktober 2012 2013
527 1.03.02 CV. TP Rehabilitasi Lantai Jembatan Desa Sido 02/JSM/SPK/PP 127.001.000,00 6.350.050,00 2412/LS/1.20 6.350.050,00 - -
Mulyo Kecamatan Tungkal Ilir K/PUBM/2012 .09.02.00/6.2/
Tgl. 12 Oktober 2013
2012
Halaman 44 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
528 1.03.02 CV. VIP Pengerasan Jalan Desa Bumi Serdang 05/DBS/PPK/KO 356.537.000,00 17.826.850,00 4092/LS/1.20 17.826.850,00 - -
Kecamatan Tungkal Ilir NTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
2 Nopember 2012
529 1.03.02 CV. GB Rehabilitasi / Pemeliharaan Jembatan 01/TNH- 98.503.000,00 4.925.150,00 2236/LS/1.20 4.925.150,00 - -
Tanah Kering Kec. Pulau Rimau KRNG/SPK/PPK/ .09.02.00/6.2/
PUBM/ 2012 Tgl. 2013
20 Maret 2012
530 1.03.02 CV. Bi Pengerasan Jalan Desa Dana Mulya Kec. 05/DM/PPK/KO 587.033.000,00 29.351.650,00 3583/LS/1.20 29.351.650,00 - -
Pulau Rimau NTRAK/PUBM/2 .09.02.00/6.2/
012 Tgl. 9 Juli 2013
2012
531 1.03.02 CV. HBS Pengerasan Jalan Desa Sumber Mulyo - 05/SM/PPK- 587.361.000,00 29.368.050,00 3032/LS/1.20 29.368.050,00 - -
Tanah Kering Kec. Pulau Rimau KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 25 2013
September 2012
532 1.03.02 CV. BrPs Pengerasan Jalan Penghubung Desa Rukun 05/RM-DM/PPK- 489.651.000,00 24.482.550,00 1643/LS/1.20 24.482.550,00 - -
Makmur Menuju Desa Majatra Kec. Pulau KONTRAK/ .09.02.00/6.2/
Rimau PUBM/2012 Tgl. 2013
10 Oktober 2012
533 1.03.02 CV. NPM Pengerasan Jalan Desa Rawa Banda Kec. 05/RB/PPK- 783.743.000,00 39.187.150,00 1642/LS/1.20 39.187.150,00 - -
Pulau Rimau KONTRAK/PUB .09.02.00/6.2/
M/2012 Tgl. 25 2013
September 2012
534 1.03.02 CV. APe Penimbunan dan Pengerasan Jalan Desa 05/DSA/PPK- 294.084.000,00 14.704.200,00 3929/LS/1.20 14.704.200,00 - -
Sumber Agung Kec. Pulau Rimau KONTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
10 Oktober 2012
535 1.03.02 CV. Zu Penyiapan Badan Jalan Penghubung 02/NSRB/SPK/P 195.900.000,00 9.795.000,00 - - 9.795.000,00
Nunggal Sari Menuju Rawa Banda Kec. PK/PUBM/2012
Pulau Rimau Tgl. 17 Oktober
2012
536 1.03.02 PT. PDR Pembangunan Jembatan Sungai Kumbang 05/SK/PPK/KON 4.014.375.000,00 200.718.750,00 2238/LS/1.20 200.718.750,00 - -
Kec. Air Saleh (Tahap III) TRAK/PUBM/20 .09.02.00/6.2/
12 Tgl. 9 Juli 2013
2012
537 1.03.02 PT. TCA Pembangunan Jembatan Sungai Kumbang 05/SK-V/PPK- 8.798.338.000,00 439.916.900,00 2237/LS/1.20 439.916.900,00 - -
(Tahap V) KONTRAK/ .09.02.00/6.2/
PUBM/2012 Tgl. 2013
17 Oktober 2012
Halaman 45 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
538 1.03.02 CV. Te Pembuatan Badan Jalan dengan Galian 02/GJSK/SPK/PP 195.900.000,00 9.795.000,00 2468/LS/1.20 9.795.000,00 - -
Tanah Setempat Menuju Jembatan Sungai K/PUBM/2012 .09.02.00/6.2/
Kumbang Tgl. 17 Oktober 2013
2012
539 1.03.02 CV. APG Pengecoran Jalan Dalam Desa Saleh Agung 02/SA/SPK/PPK/ 195.478.000,00 9.773.900,00 4981/LS/1.20 9.773.900,00 - -
Kec. Air Saleh (Tahap II) PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
540 1.03.02 CV. NPM Pengecoran Jalan Dalam Desa Damar 02/DDW/SPK/PP 195.271.000,00 9.763.550,00 2365/LS/1.20 9.763.550,00 - -
Wulan Kec. Air Saleh K/PUBM/2012 .09.02.00/6.2/
Tgl. 29 Oktober 2013
2012
541 1.03.02 CV. BrPs Penimbunan Jalan Desa Salek Makmur 02/DSM/SPK/PP 97.815.000,00 4.890.750,00 1645/LS/1.20 4.890.750,00 - -
Kec. Air Saleh K/PUBM/2012 .09.02.00/6.2/
Tgl. 29 Oktober 2013
2012
542 1.03.02 CV. BrPs Penimbunan Jalan Desa Awitan Ke Muara 02/AWITAN/SP 97.790.000,00 4.889.500,00 1644/LS/1.20 4.889.500,00 - -
Kec. Air Saleh K/PPK/PUBM/20 .09.02.00/6.2/
12 Tgl. 29 2013
Oktober 2012
543 1.03.02 CV. KJ Rehabilitasi Jembatan Desa Salek Mukti 02/JSM/SPK/PP 73.248.000,00 3.662.400,00 - - 3.662.400,00
Kec. Air Saleh K/PUBM/2012
Tgl. 17 Oktober
2012
544 1.03.02 CV. KJ Rehabilitasi Jembatan Desa Damar Wulan 02/JDW/SPK/PP 73.248.000,00 3.662.400,00 - - 3.662.400,00
Kec. Air Saleh K/PUBM/2012
Tgl. 17 Oktober
2012
545 1.03.02 CV. EJ Rehabilitasi Tembok Penahan Oprit Box 02/OBTR/SPK/P 58.657.000,00 2.932.850,00 2263/LS/1.20 2.932.850,00 - -
Desa Taja Raya Kec. Betung PK/PUBM/2012 .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
546 1.03.02 CV. KJ Pembangunan Jembatan Desa Sidoarjo Kec. 02/SDJO/SPK/PP 146.451.000,00 7.322.550,00 - - 7.322.550,00
Air Saleh K/PUBM/2012
Tgl. 17
September 2012
547 1.03.02 PT. SSM Pembangunan Jembatan Penghubung Desa 02/J- 146.461.000,00 7.323.050,00 5266/LS/1.20 7.323.050,00 - -
Awitan Kec. Air Saleh DA/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 29 2013
Oktober 2012
548 1.03.02 PT. SSM Pembangunan Jembatan Penghubung Desa 02/J- 146.511.000,00 7.325.550,00 5268/LS/1.20 7.325.550,00 - -
Salek Mulya Kec. Air Saleh DSM/SPK/PPK/P .09.02.00/6.2/
UBM/2012 Tgl. 2013
29 Oktober 2012
Halaman 46 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
549 1.03.02 PT. SCP Pembangunan Jembatan Penghubung Beton 02/JB- 146.608.000,00 7.330.400,00 5250/LS/1.20 7.330.400,00 - -
Desa Salek Makmur Kec. Air Saleh DSM/SPK/PPK/P .09.02.00/6.2/
UBM/2012 Tgl. 2013
29 Oktober 2012
550 1.03.02 PT. SCP Penimbunan Jalan Desa Solok Batu Kec. 02/DSB/SPK/PP 98.001.000,00 4.900.050,00 5251/LS/1.20 4.900.050,00 - -
Air Saleh K/PUBM/2012 .09.02.00/6.2/
Tgl. 29 Oktober 2013
2012
551 1.03.02 PT. MM Rehabilitasi / Pemeliharaan Jembatan 05/MP/PPK/KON 488.178.000,00 24.408.900,00 2234/LS/1.20 24.408.900,00 - -
Muara Padang TRAK/PUBM/20 .09.02.00/6.2/
12 Tgl. 9 Juli 2013
2012
552 1.03.02 CV. Ha Pengecoran Jalan Desa Purwodadi Kec. 02/PWDD/SPK/P 195.208.000,00 9.760.400,00 3181/LS/1.20 9.760.400,00 - -
Muara Padang PK/PUBM/2012 .09.02.00/6.2/
Tgl. 17 2013
September 2012
553 1.03.02 CV. RJK Penimbunan Jalan dengan Galian Tanah 02/GDU/SPK/PP 97.858.000,00 4.892.900,00 3203/LS/1.20 4.892.900,00 - -
Setempat Desa Daya Utama Kec. Muara K/PUBM/2012 .09.02.00/6.2/
Padang Tgl. 17 2013
September 2012
554 1.03.02 CV. RJK Penimbunan Jalan dengan Galian Tanah 02/GDM/SPK/PP 97.858.000,00 4.892.900,00 3202/LS/1.20 4.892.900,00 - -
Setempat Desa Daya Makmur Kec. Muara K/PUBM/2012 .09.02.00/6.2/
Padang Tgl. 17 2013
September 2012
555 1.03.02 CV. LS Penimbunan Jalan dengan Galian Tanah 02/DTJ/SPK/PPK 97.848.000,00 4.892.400,00 4700/LS/1.20 4.892.400,00 - -
Setempat Desa Tirta Jaya Kec. Muara /PUBM/2012 Tgl. .09.02.00/6.2/
Padang 29 Oktober 2012 2013
556 1.03.02 CV. RJ Pembangunan Jembatan Desa Ruas Jalan 02/DM- 97.851.000,00 4.892.550,00 1838/LS/1.20 4.892.550,00 - -
Desa Daya Makmur - Desa Sidomulyo Kec. SM/SPK/PPK/PU .09.02.00/6.2/
Muara Padang BM/2012 Tgl. 29 2013
Oktober 2012
557 1.03.02 CV. ArP Pembangunan Jembatan Desa Ruas Jalan 02/TJ- 97.298.000,00 4.864.900,00 - - 4.864.900,00
Desa Tirta Jaya - Daya Utama Kec. Muara DU/SPK/PPK/PU
Padang BM/2012 Tgl. 24
Oktober 2012
558 1.03.02 CV. PC Pembangunan Jembatan Desa Air Gading 02/J- 97.715.000,00 4.885.750,00 - - 4.885.750,00
Kec. Muara Padang AG/SPK/PPK/PU
BM/2012 Tgl. 29
Oktober 2012
559 1.03.02 CV. SaKo Pengecoran Jalan Dsn I Desa Tanah Pilih 02/DI- 97.896.000,00 4.894.800,00 3655/LS/1.20 4.894.800,00 - -
Kec. Banyuasin II TP/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 12 2013
Oktober 2012
Halaman 47 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
560 1.03.02 CV. LS Pengecoran Jalan Dsn 2 Desa Sei Semut 02/D2- 97.634.000,00 4.881.700,00 3754/LS/1.20 4.881.700,00 - -
Kec. Banyuasin II SS/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 12 2013
Oktober 2012
561 1.03.02 CV. SaKo Pembangunan Jerambah Lr. Muslimin KH. 02/LM/SPK/PPK/ 160.457.000,00 8.022.850,00 3653/LS/1.20 8.022.850,00 - -
Mesir Desa Sungsang IV Kec. BA II PUBM/2012, Tgl. .09.02.00/6.2/
17 Oktober 2012 2013
562 1.03.02 CV. TBJ Penimbunan dengan Galian Tanah 02/LY/SPK/PPK/ 97.843.000,00 4.892.150,00 3654/LS/1.20 4.892.150,00 - -
Setempat Jalan Lorong Yunan Sungsang IV PUBM/2012 Tgl. .09.02.00/6.2/
Menuju Jalan Tanjung Api-api Kec. 17 September 2013
Banyuasin II 2012
563 1.03.02 CV. SaKo Penimbunan Jalan dengan Galian Tanah 02/LB/SPK/PPK/ 97.816.000,00 4.890.800,00 3581/LS/1.20 4.890.800,00 - -
Setempat Lr. Buyut Desa Sungsang I PUBM/2012 Tgl. .09.02.00/6.2/
Menuju Jalan Tanjung Api-api Kec. 17 September 2013
Banyuasin II 2012
564 1.03.02 CV. Dih Pembangunan Jerambah Lrg Mawar 02/LM/SPK/PPK/ 195.496.000,00 9.774.800,00 3031/LS/1.20 9.774.800,00 - -
Sungsang III Kec. Banyuasin II PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
565 1.03.02 CV. Dih Pembangunan Jerambah Lrg Taruna Darat 02/JTD/SPK/PPK 97.811.000,00 4.890.550,00 3035/LS/1.20 4.890.550,00 - -
Desa Sungsang III Kec. BA II /PUBM/2012 Tgl. .09.02.00/6.2/
17 September 2013
2012
566 1.03.02 CV. TBJ Pembangunan Jerambah Lorong Kencana 02/LK/SPK/PPK/ 195.682.000,00 9.784.100,00 3651/LS/1.20 9.784.100,00 - -
Sungsang IV Kec. Banyuasin II PUBM/2012 Tgl. .09.02.00/6.2/
12 Oktober 2012 2013
567 1.03.02 CV. TBJ Pembangunan Jerambah Lr. Ratna Maida 02/RM- 98.503.000,00 5.748.800,00 3755/LS/1.20 5.748.800,00 - -
Darat Desa Sungsang I Kec. BA II DS/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
September 2012
568 1.03.02 CV. MB Pembangunan Jembatan Penghubung Dsn 02/SRIAGUNG/S 122.188.000,00 6.109.400,00 3673/LS/1.20 6.109.400,00 - -
III - Dsn IV Desa Sriagung Kec. Banyuasin PK/PPK/PUBM/2 .09.02.00/6.2/
II 012 Tgl. 12 2013
Oktober 2012
569 1.03.02 CV. MB Pembangunan Jembatan Penghubung Dsn 02/DSR/SPK/PP 122.283.000,00 6.114.150,00 3674/LS/1.20 6.114.150,00 - -
III - Dsn IV Desa Sumber Rejeki Kec. K/PUBM/2012 .09.02.00/6.2/
Banyuasin II Tgl. 17 Oktober 2013
2012
570 1.03.02 CV. NPM Pembangunan Jembatan Desa Muara Baru 02/DMB/SPK/PP 122.228.000,00 6.111.400,00 - - 6.111.400,00
Kec. Banyuasin II K/PUBM/2012
Tgl. 17 Oktober
2012
Halaman 48 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
571 1.03.02 CV. MPS Penimbunan dengan Tanah Setempat Jalan 02/KAI/SPK/PPK 195.574.000,00 9.778.700,00 2897/LS/1.20 9.778.700,00 - -
Poros Karang Agung Ilir Desa Karang Sari /PUBM/2012 Tgl. .09.02.00/6.2/
Ke Sumber Rezeki Kec. BA II 12 Oktober 2012 2013
572 1.03.02 CV. SaKo Penimbunan Jalan dengan Galian Tanah Nomor : 02/PL- 97.833.000,00 4.891.650,00 3686/LS/1.20 4.891.650,00 - -
Setempat Parit Halaman Lama - Parit Ladok TP/SPK/PPK/PU .09.02.00/6.2/
Desa Teluk Payo Kec. Banyuasin II BM/2012 tanggal 2013
17 September
2012
573 1.03.02 CV. TBJ Pengecoran Jalan Desa Tanjung Baru Kec. Nomor : 97.653.000,00 4.882.650,00 3687/LS/1.20 4.882.650,00 - -
Banyuasin II 02/TB/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 17
September 2012
574 1.03.02 CV. BrPs Penimbunan dengan Galian Tanah Nomor : 02/LM- 97.743.000,00 4.887.150,00 - - 4.887.150,00
Setempat Lr. Mawar Menuju Jalan TAA TAA/SPK/PPK/P
Desa Sungsang III Kec. Banyuasin II UBM/2012
tanggal 12
Oktober 2012
575 1.03.02 CV. NPM Penimbunan Jalan Keliling dengan Galian Nomor : 97.844.000,00 4.892.200,00 - - 4.892.200,00
Tanah Setempat di Komplek Pondok 02/PPNW/SPK/P
Pesantren Nurul Wathan Desa Muara PK/PUBM/2012
Sungsang Kec. Banyuasin II tanggal 12
Oktober 2012
576 1.03.02 CV. Ra Perkerasan Jalan Desa Nusa Makmur Kec. NOMOR : 195.717.000,00 9.785.850,00 2497/LS/1.20 9.785.850,00 - -
Banyuasin I 02/DNM/SPK/PP .09.02.00/6.2/
K/PUBM/2012, 2013
TANGGAL : 17
OKTOBER 2012
577 1.03.02 PT. SSM Pengecoran Jalan Desa Telang Jaya antara Nomor : 220.084.000,00 11.004.200,00 5267/LS/1.20 11.004.200,00 - -
Jembatan 2 - Jembatan 1 Kec. Muara 05/TJ/PPK- .09.02.00/6.2/
Telang KONTRAK/PUB 2013
M/2012 tanggal
10 Oktober 2012
578 1.03.02 PT. SSM Penimbunan dengan tanah setempat jalan Nomor : 02/J4- 195.620.000,00 9.781.000,00 5265/LS/1.20 9.781.000,00 - -
dari jembatan 4 ke jembatan 2 Jalur 8 Kec. J2/SPK/PPK/PUB .09.02.00/6.2/
Muara Telang M/2012 tanggal 2013
17 September
2012
579 1.03.02 PT. SCP Pembangunan Jembatan Desa Terusan Nomor : 183.021.000,00 9.151.050,00 5253/LS/1.20 9.151.050,00 - -
Muara Kec. Muara Telang 02/JTM/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
tanggal 17
September 2012
Halaman 49 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
580 1.03.02 PT. SCP Pembangunan Jembatan Desa Muara Nomor : 220.267.000,00 11.013.350,00 5264/LS/1.20 11.013.350,00 - -
Telang Kec. Muara Telang 05/JMT/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
10 Oktober 2012
581 1.03.02 PT. SCP Pembangunan Jembatan Desa Margarahayu Nomor : 171.077.000,00 8.553.850,00 5254/LS/1.20 8.553.850,00 - -
Kec. Muara Telang 02/JDM/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
tanggal 17
September 2012
582 1.03.02 CV. MUB Pengecoran Jalan Ruas Jalan Desa Telang Nomor : 05/TR- 489.444.000,00 24.472.200,00 5263/LS/1.20 24.472.200,00 - -
Rejo Menuju Desa Telang Karya Kec. TK/PPK- .09.02.00/6.2/
Muara Telang KONTRAK/ 2013
PUBM/2012
tanggal 10
Oktober 2012
583 1.03.02 CV. MB Pengecoran Ruas Jalan Desa Sumber Hidup Nomor : 05/SH- 489.332.000,00 24.466.600,00 5269/LS/1.20 24.466.600,00 - -
Menuju Desa Telang Rejo Kec. Muara TR/PPK- .09.02.00/6.2/
Telang KONTRAK/ 2013
PUBM/2012
tanggal 10
Oktober 2012
584 1.03.02 CV. SJ Pengecoran Jalan Desa Telang Makmur Nomor : 05/TM- 687.421.000,00 34.371.050,00 2463/LS/1.20 34.371.050,00 - -
Menuju Desa Sumber Hidup Kec. Muara SH/PPK- .09.02.00/6.2/
Telang KONTRAK/ 2013
PUBM/2012
tanggal 10
Oktober 2012
585 1.03.02 CV. SK Pengecoran Jalan Poros Desa Sumber Nomor : 489.209.000,00 24.460.450,00 2863/LS/1.20 24.460.450,00 - -
Mulya Jalur 6 Jembatan 2 Kec. Muara 05/SM/PPK- .09.02.00/6.2/
Telang KONTRAK/ 2013
PUBM/2012
tanggal 10
Oktober 2012
586 1.03.02 CV. KSK Penimbunan dengan Galian tanah setempat Nomor : 244.786.000,00 12.239.300,00 3480/LS/1.20 12.239.300,00 - -
jalan dari desa Marga Rahayu ke sumber 05/DSM/PPK/KO .09.02.00/6.2/
jaya kec. Muara Telang NTRAK/ 2013
PUBM/2012
tanggal 2
Nopember 2012
587 1.03.02 CV. RA Pembangunan Jembatan Desa Telang Nomor : 116.875.000,00 5.843.750,00 4828/LS/1.20 5.843.750,00 - -
Makmur (Menuju Pemakaman) Kec. Muara 02/JDTM/SPK/P .09.02.00/6.2/
Telang PK/PUBM/2012 2013
tanggal 12
Oktober 2012
Halaman 50 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
588 1.03.02 CV. AJU Penimbunan dengan tanah setempat jalan Nomor : 02/KA- 195.598.000,00 9.779.900,00 4966/LS/1.20 9.779.900,00 - -
dari Desa Karang Anyar Menuju Desa TM/SPK/PPK/PU .09.02.00/6.2/
Muara Telang Marga Kec. Muara Telang BM/2012 tanggal 2013
12 Oktober 2012
589 1.03.02 CV. AJU Penimbunan dengan tanah setempat jalan NOMOR : 02/JI- 156.413.000,00 7.820.650,00 4967/LS/1.20 7.820.650,00 - -
dari Jembatan I ke Jembatan II Jalur 6 Desa JII/SPK/PPK/PU .09.02.00/6.2/
Sumber Mulya Kec. Muara Telang BM/2012, 2013
TANGGAL : 12
OKTOBER 2012
590 1.03.02 CV. RA Pengecoran Jalan Desa Mekar Mukti Kec. Nomor : 489.096.000,00 24.454.800,00 4826/LS/1.20 24.454.800,00 - -
Muara Telang 05/MM/PPK- .09.02.00/6.2/
KONTRAK/ 2013
PUBM/2012
tanggal 10
Oktober 2012
591 1.03.02 CV. RA Pembangunan Jembatan Desa Sumber Nomor : 195.567.000,00 9.778.350,00 4827/LS/1.20 9.778.350,00 - -
Hidup Kec. Muara Telang 02/JDSH/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
tanggal 12
Oktober 2012
592 1.03.02 CV. KSK Pengecoran Jalan Dalam Desa Ganesha Nomor : 220.168.000,00 11.008.400,00 3002/LS/1.20 11.008.400,00 - -
Mukti Kec. Muara Sugihan 05/GM/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
25 September
2012
593 1.03.02 CV. KSK Pengecoran Jalan Dalam Desa Margo Nomor : 220.198.000,00 11.009.900,00 2875/LS/1.20 11.009.900,00 - -
Rukun Kec. Muara sugihan 05/MR/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
25 September
2012
594 1.03.02 CV. PI Pengecoran Jalan Dalam Desa Tirta Mulya Nomor : 195.650.000,00 9.782.500,00 3337/LS/1.20 9.782.500,00 - -
Kec. Muara Sugihan 02/DTM/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
tanggal 29
Oktober 2012
595 1.03.02 CV. BIh Pengecoran Jalan Dalam Desa Daya AZHAR SAMIRI 97.807.000,00 4.890.350,00 - - 4.890.350,00
Kusuma Kec. Muara sugihan CV. BUKIT
INDAH
Jl. R. Sukamto
No. 63A Kec.
Kemuning Kel.
Pipa Reja
Palembang
Halaman 51 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
596 1.03.02 CV. KSK Pembangunan Jembatan Penghubung Desa Nomor : 220.271.000,00 11.013.550,00 2874/LS/1.20 11.013.550,00 - -
Margo Mulyo Kec. Muara Sugihan 05/MM/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
25 September
2012
597 1.03.02 CV. BIh Pembangunan Jembatan Penghubung Desa Nomor : 02/JBT- 97.736.000,00 4.886.800,00 - - 4.886.800,00
Daya Kusuma Kec. Muara Sugihan DK/SPK/PPK/PU
BM/2012 tanggal
17 September
2012
598 1.03.02 CV. MU Pengecoran Jalan Serong - Semuntul Kec. Nomor : 220.003.000,00 11.000.150,00 - - 11.000.150,00
Rantau Bayur (Tahap III) 05/SS/PPK-
KONTRAK/
PUBM/2012
tanggal 10
Oktober 2012
599 1.03.02 CV. KY Pengecoran Jalan Dalam Desa Talang Nomor : 196.208.000,00 9.810.400,00 3647/LS/1.20 9.810.400,00 - -
kemang Kec. Rantau Bayur 02/TK/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 17
September 2012
600 1.03.02 CV. ArP Pengecoran Jalan Sukarela - Pulokerto Kec. Nomor : 220.007.000,00 11.000.350,00 - - 11.000.350,00
Rantau Bayur (Tahap III) 05/SP/PPK-
KONTRAK/
PUBM/2012
tanggal 10
Oktober 2012
601 1.03.02 CV. RJ Pengecoran Jalan Dalam Desa Rantau Nomor : 196.194.000,00 9.809.700,00 1819/LS/1.20 9.809.700,00 - -
Harapan Kec. Rantau Bayur 02/RH/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 12
Oktober 2012
602 1.03.02 CV. HR Pengecoran Jalan Tebing Abang - Nomor : 05/TA- 220.139.000,00 11.006.950,00 3207/LS/1.20 11.006.950,00 - -
Pengumbuk kec. Rantau Bayur (Tahap III) P/PPK- .09.02.00/6.2/
KONTRAK/ 2013
PUBM/2012
tanggal 10
Oktober 2012
603 1.03.02 CV. GB Pembangunan Jembatan Desa Semuntul NOMOR : 196.260.000,00 9.813.000,00 2235/LS/1.20 9.813.000,00 - -
Kec. Rantau Bayur 02/JDS/SPK/PPK .09.02.00/6.2/
/PUBM/2012, 2013
TANGGAL : 17
OKTOBER 2012
Halaman 52 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
604 1.03.02 CV. GPA Pembangunan Jembatan Penghubung dsn. 1 Nomor : 97.958.000,00 4.897.900,00 3318/LS/1.20 4.897.900,00 - -
- dsn III Perasinan Desa Sungai Pinang Kec. 02/PSP/SPK/PPK .09.02.00/6.2/
Rantau Bayur /PUBM/2012 2013
tanggal 17
Oktober 2012
605 1.03.02 CV. RS Pembangunan Jembatan Dsn 2 Desa Nomor : 183.006.000,00 9.150.300,00 4613/LS/1.20 9.150.300,00 - -
Sukarela Kec. Rantau Bayur 02/J2DS/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
tanggal 17
September 2012
606 1.03.02 CV. APe Pengecoran Jalan Desa Tanjung Pasir Kec. Nomor : 586.888.000,00 29.344.400,00 3294/LS/1.20 29.344.400,00 - -
Rantau Bayur 05/TP/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
10 Oktober 2012
607 1.03.02 CV. MPS Pengecoran Jalan Desa Muara Abab Kec. Nomor : 196.194.000,00 9.809.700,00 2895/LS/1.20 9.809.700,00 - -
Rantau Bayur 05/PL.12/PPK.K .09.02.00/6.2/
ONTRAK/E.PRO 2013
C/PUBM/2011
tanggal 2
Nopember 2011
608 1.03.02 CV. AiP Pengecoran Jalan Desa Penandingan Kec. Nomor : 196.194.000,00 9.809.700,00 2899/LS/1.20 9.809.700,00 - -
Rantau Bayur 02/DP/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 17
September 2012
609 1.03.02 Cv. AILS Penimbunan Jalan Penghubung Desa Nomor : 05/RB- 392.810.000,00 19.640.500,00 - - 19.640.500,00
Rantau Bayur - Tebing Abang Kec. Rantau TA/PPK-
Bayur KONTRAK/
PUBM/2012
tanggal 10
Oktober 2012
610 1.03.02 CV. HR Rehabilitasi Jembatan Sei Guntung Kec. Nomor : 73.204.000,00 3.660.200,00 7219/LS/1.20 3.660.200,00 - -
Rantau Bayur 02/SG/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 17
September 2012
611 1.03.02 CV. IP Pengecoran Jalan Desa Sejagung Kec. Nomor : 244.482.000,00 12.224.100,00 4446/LS/1.20 12.224.100,00 - -
Rantau Bayur 05/DS/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
10 Oktober 2012
Halaman 53 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
612 1.03.02 CV. EJ Pengecoran Jalan Desa Lubuk Karet - Pulau Nomor : 391.478.000,00 19.573.900,00 1139/LS/1.20 19.573.900,00 - -
Rajak Kec. Betung 05/PR/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
25 September
2012
613 1.03.02 PT. T & R Pengecoran Jalan Kampung Sawah kec. Nomor : 244.629.000,00 12.231.450,00 3206/LS/1.20 12.231.450,00 - -
Betung 05/KS/PPK- .09.02.00/6.2/
KONTRAK/PUB 2013
M/2012 tanggal
25 September
2012
614 1.03.02 CV. TBJ Pengecoran Jalan Lintas Desa Taja Indah Nomor : 244.721.000,00 12.236.050,00 - - 12.236.050,00
kec. Betung 05/KS/PPK-
KONTRAK/PUB
M/2012 tanggal
25 September
2012
615 1.03.02 CV. BT Pembangunan jembatan Desa Regan Agung NOMOR : 58.700.000,00 2.935.000,00 1793/LS/1.20 2.935.000,00 - -
Kec. BA III (Menuju Pemakaman) 02/DRA/SPK/PP .09.02.00/6.2/
K/PUBM/2012, 2013
TANGGAL : 17
OKTOBER 2012
616 1.03.02 CV. BrPs Pengecoran Jalan Seterio - Sedang Kec. Nomor : 196.220.000,00 9.811.000,00 2370/LS/1.20 9.811.000,00 - -
Soak Tape 02/SS/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 17
September 2012
617 1.03.02 CV. AiP Pengecoran Jalan dalam Desa Sukaraja Kec. Nomor : 196.218.000,00 9.810.900,00 2896/LS/1.20 9.810.900,00 - -
Soak Tape 02/DS/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
tanggal 17
September 2012
618 1.03.02 CV. MPS Pengecoran Jalan Desa Air Senggiris - Nomor : 02/AS- 196.024.000,00 9.801.200,00 2898/LS/1.20 9.801.200,00 - -
Talang Ipuh Kec. Soak Tape TI/SPK/PPK/PU .09.02.00/6.2/
BM/2012 tanggal 2013
17 September
2012
619 1.03.02 CV. PP Pengecoran Jalan Dalam Desa Lubuk NOMOR : 196.254.000,00 9.812.700,00 2264/LS/1.20 9.812.700,00 - -
Lancang Menuju SMP 02/LL/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 2013
TANGGAL : 17
SEPTEMBER
2012
Halaman 54 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
620 1.03.02 CV. LK Pengecoran Jalan Alternatif KM 12 NOMOR : 244.635.000,00 12.231.750,00 2804/LS/1.20 12.231.750,00 - -
Kelurahan Tanah Mas Kec. Talang Kelapa 05/KTM/PPK/KO .09.02.00/6.2/
NTRAK/PUBM/2 2013
012, tanggal 2
Nopember 2012
621 1.03.02 CV. Te Pemasangan Portal Ruas Jalan Sungai NOMOR : 48.939.000,00 2.446.950,00 2469/LS/1.20 2.446.950,00 - -
Gerong - Prajen 02/PSGP/SPK/PP .09.02.00/6.2/
K/PUBM/2012, 2013
TANGGAL : 17
OKTOBER 2012
622 1.03.02 CV. Te Rehabilitasi /Pemeliharaan Tugu Ketahanan NOMOR : 146.600.000,00 7.330.000,00 7169/LS/1.20 7.330.000,00 - -
Pangan 02/TKP/SPK/PP .09.02.00/6.2/
K/PUBM/2012, 2013
TANGGAL : 17
OKTOBER 2012
623 1.03.02 CV. Te Pemasangan Conblok Lapangan Upacara NOMOR : 117.283.000,00 5.864.150,00 7168/LS/1.20 5.864.150,00 - -
Komplek Perkantoran 02/CLU/SPK/PP .09.02.00/6.2/
K/PUBM/2012, 2013
TANGGAL : 17
OKTOBER 2012
624 1.03.02 CV. S & CO Pembangunan Jembatan Sungai Sili Kec. NOMOR : 196.121.000,00 9.806.050,00 2373/LS/1.20 9.806.050,00 - -
Banyuasin I 02/JSS/SPK/PPK/ .09.02.00/6.2/
PUBM/2012 , 2013
TANGGAL : 17
OKTOBER 2012
625 1.03.02 CV. NJ Pengecoran Jalan dalam Komplek Kenten NOMOR : 245.007.000,00 12.250.350,00 3057/LS/1.20 12.250.350,00 - -
Azhar Kelurahan Kenten 05/KKA/PPK/KO .09.02.00/6.2/
NTRAK/PUBM/2 2013
012 TANGGAL 2
NOPEMBER
2012
626 1.03.02 CV. BH Penimbunan dengan galian tanah setempat NOMOR : 02/DP- 97.721.000,00 4.886.050,00 2593/LS/1.20 4.886.050,00 - -
Dsa Plaju menuju Dsa Tanah Lembak Kec. TL/SPK/PPK/PU .09.02.00/6.2/
Rambutan BM/2012 2013
TANGGAL : 17
OKTOBER 2012
627 1.03.02 CV. BT Pembangunan Oprit Jembatan Pendowo NOMOR : 97.907.000,00 4.895.350,00 1792/LS/1.20 4.895.350,00 - -
Harjo Kec. Makarti Jaya 02/OJPH/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
Halaman 55 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
628 1.03.02 PT. AKT Pembangunan Jalan Jati Kelurahan Mariana NOMOR : 771.140.000,00 38.557.000,00 3894/LS/1.20 38.557.000,00 - -
Kec, Banyuasin I 05/JKM/PPK/KO .09.02.00/6.2/
NTRAK/PUBM/2 2013
012 TANGGAL 2
NOPEMBER
2012
629 1.03.02 CV. GB Penggantian Relling dan Pengencangan NOMOR : 98.005.000,00 4.900.250,00 2239/LS/1.20 4.900.250,00 - -
Baut Jembatan Tanah Kering Kec. Pulau 02/PBTK/SPK/PP .09.02.00/6.2/
Rimau K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
630 1.03.02 CV. KSK Pembangunan Jalan Desa Saleh Agung Kec. NOMOR : 195.524.000,00 56.213.150,00 0246/LS/1.20 56.213.150,00 - -
Air Saleh 02/DSA/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
631 1.03.02 CV. CM Pembangunan Jalan Desa Margo Sugian NOMOR : 195.421.000,00 56.183.537,50 0241/LS/1.20 56.183.537,50 - -
Kec. Muara Padang 02/DMS/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
632 1.03.02 CV. CM Pembangunan Jalan Desa Salek Jaya Kec. NOMOR : 195.557.000,00 56.222.637,50 0247/LS/1.20 56.222.637,50 - -
Air Saleh 02/DSJ/SPK/PPK .09.02.00/6.2/
/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
633 1.03.02 CV. MB Pembangunan Jembatan Penghubung NOMOR : 02/J- 97.651.000,00 4.882.550,00 3567/LS/1.20 4.882.550,00 - -
Dusun IV Desa Sumber Rejeki Kec. DSR/SPK/PPK/P .09.02.00/6.2/
Banyuasin II UBM/2012 2013
TANGGAL : 12
OKTOBER 2012
634 1.03.02 CV. KJ Pengecoran Jalan Desa Marga Rahayu Kec. NOMOR : 244.695.000,00 12.234.750,00 - - 12.234.750,00
Muara Telang 05/DMR/PPK/K
ONTRAK/PUBM
/2012
TANGGAL 2
NOPEMBER
2012
635 1.03.02 CV. IK Pengerasan Jalan Dalam Desa SidoMulyo NOMOR : 481.541.000,00 24.077.050,00 2395/LS/1.20 24.077.050,00 - -
Kec. Tungkal Ilir 05/DSM/PPK/KO .09.02.00/6.2/
NTRAK/PUBM/2 2013
012 TANGGAL 2
NOPEMBER
2012
Halaman 56 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
636 1.03.02 CV. AP Pengecoran Jalan Desa Meranti Kec. Soak NOMOR : 196.214.000,00 9.810.700,00 3862/LS/1.20 9.810.700,00 - -
Tape (Tahap II) 02/MERANTI/SP .09.02.00/6.2/
K/PPK/PUBM/20 2013
12 TANGGAL :
17 OKTOBER
2012
637 1.03.02 CV. Zu Pembangunan Jalan Desa Budi Asih Kec. NOMOR : 195.391.000,00 56.174.912,50 0245/LS/1.20 56.174.912,50 - -
Pulau Rimau 02/DBA/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
638 1.03.02 CV. Zu Pembangunan Jalan Desa Air Gading Kec. NOMOR : 195.696.000,00 56.262.600,00 0244/LS/1.20 56.262.600,00 - -
Muara Padang 02/DAG/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2012
TANGGAL : 17
OKTOBER 2012
639 1.03.02 CV. KSK Pembangunan Jalan Desa Salek Mulia Kec. Nomor : 195.356.000,00 56.164.850,00 0243/LS/1.20 56.164.850,00 - -
Air Saleh 02/JDSM/SPK/P .09.02.00/6.2/
PK/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
640 1.03.02 CV. Ra Pengecatan Kanstin Jalan Lingkar Mulia NOMOR : 440.160.000,00 22.008.000,00 7227/LS/1.20 22.008.000,00 - -
Agung-Seterio 05/LMA- .09.02.00/6.2/
S/PPK/KONTRA 2013
K/PUBM/2012
TANGGAL 2
NOPEMBER
2012
641 1.03.02 CV. RFg Pembangunan Jalan Desa Lebung NOMOR : 146.863.000,00 7.343.150,00 - - 7.343.150,00
02/LEBUNG/SP
K/PPK/PUBM/20
12 TANGGAL :
17 OKTOBER
2012
642 1.03.02 CV. HR Pengecoran Jalan Utama Perumahan Griya NOMOR : 97.730.000,00 4.886.500,00 7220/LS/1.20 4.886.500,00 - -
Citra Sukamoro RT. 042 Kelurahan 02/GCS/SPK/PP .09.02.00/6.2/
Sukamoro Kecamatan Talang Kelapa K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
643 1.03.02 CV. PT Pembuatan Tembok Penahan Desa Plajau NOMOR : 02/PI- 97.906.000,00 4.895.300,00 1791/LS/1.20 4.895.300,00 - -
Ilir - Rimba Alai RA/SPK/PPK/PU .09.02.00/6.2/
BM/2012 2013
TANGGAL : 17
OKTOBER 2012
644 1.03.02 CV. BPM Pengecoran Jalan Desa Durian Gadis 02/DDG/SPK/PP 195.899.000,00 9.794.950,00 - - 9.794.950,00
Kecamatan Rambutan K/PUBM/2012
Tgl. 17 Oktober
2012
Halaman 57 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
645 1.03.02 CV. BPM Pengecoran Jalan/Lorong Tembusan Desa 02/DR/SPK/PPK/ 97.924.000,00 4.896.200,00 - - 4.896.200,00
Rambutan Kecamatan Rambutan PUBM/2012 Tgl.
17 Oktober 2012
646 1.03.02 CV. BPM Pengecoran Jalan/Lorong Vinus Desa 02/VDM/SPK/PP 97.933.000,00 4.896.650,00 - - 4.896.650,00
Mariana Kecamatan Banyuasin I K/PUBM/2012
Tgl. 17 Oktober
2012
647 1.03.02 CV. PT Pembangunan Jerambah Desa Tj. Beringin NOMOR : 146.903.000,00 7.345.150,00 1736/LS/1.20 7.345.150,00 - -
Kec. BA III 02/DTB/SPK/PP .09.02.00/6.2/
K/PUBM/2012 2013
TANGGAL : 17
OKTOBER 2012
648 1.03.02 CV. Zu Pembangunan Jembatan Desa Indrapura 02/J- 195.436.000,00 139.736.740,00 0229/LS/1.20 139.736.740,00 - -
Kec. Muara Sugihan DI/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
Oktober 2012
649 1.03.02 CV. Zu Pembangunan Jembatan Desa Sidoharjo 02/J- 195.576.000,00 139.836.840,00 0230/LS/1.20 139.836.840,00 - -
Kec. Air Saleh DS/SPK/PPK/PU .09.02.00/6.2/
BM/2012 Tgl. 17 2013
Oktober 2012
650 1.03.02 CV. HBS Pembangunan Jembatan Rantau Harapan 02/JRH/SPK/PPK 97.902.000,00 4.895.100,00 3007/LS/1.20 4.895.100,00 - -
Lebung /PUBM/2012, .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
651 1.03.02 CV. NJ Pembuatan Box Culvert Desa Tanah 02/BTL/SPK/PP 97.714.000,00 4.885.700,00 4611/LS/1.20 4.885.700,00 - -
Lembak Kecamatan Rambutan K/PUBM/2012, .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
652 1.03.02 CV. GK Rehabilitasi Ruas Jalan Sp. Lubuk Lancang - 02/LL- 97.907.000,00 4.895.350,00 3578/LS/1.20 4.895.350,00 - -
Tanah Kering Kec. Pulau Rimau TK/SPK/PPK/PU .09.02.00/6.2/
BM/2012, Tgl. 17 2013
Oktober 2012
653 1.03.02 CV. GK Rehabilitasi Jalan Desa Lubuk Rengas - 02/LR- 97.600.000,00 4.880.000,00 3580/LS/1.20 4.880.000,00 - -
Desa Lebung Kec. Rantau Bayur DL/SPK/PPK/PU .09.02.00/6.2/
BM/2012, Tgl. 17 2013
Oktober 2012
654 1.03.02 CV. TW Rehabilitasi Setempat-setempat Jalan 02/LMAS/SPK/P 195.905.000,00 9.795.250,00 7207/LS/1.20 9.795.250,00 - -
Lingkar Mulya Agung - Seterio (Tahap II) PK/PUBM/2012, .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
655 1.03.02 CV. GK Rehabilitasi/Pemeliharaan Jalan Desa 02/DM/SPK/PPK 97.907.000,00 4.895.350,00 3579/LS/1.20 4.895.350,00 - -
Mukud - Dana Mulya Kec. Pulau Rimau /PUBM/2012, .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
Halaman 58 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
656 1.03.02 CV. APe Rehabilitasi Tembok Penahan Jalan Desa 02/TPDP/SPK/PP 97.773.000,00 4.888.650,00 3752/LS/1.20 4.888.650,00 - -
Petaling K/PUBM/2012, .09.02.00/6.2/
Tgl. 17 Oktober 2013
2012
657 1.03.02 CV. Ra Penimbunan dengan Timbunan Tanah 02/S- 195.669.000,00 9.783.450,00 2498/LS/1.20 9.783.450,00 - -
Pilihan Ruas Jalan Sambirejo - Petaling P/SPK/PPK/PUB .09.02.00/6.2/
Kec. Banyuasin I M/2012, Tgl. 17 2013
Oktober 2012
658 1.03.02 CV. BrPs Penimbunan Dengan Tanah Setempat Ruas 02/TJ- 195.611.000,00 9.780.550,00 - - 9.780.550,00
Jalan Desa Tabala Jaya-Majuria Karang M/SPK/PPK/PUB
Agung Ulu Kec. BA II M/2012 Tgl. 17
Oktober 2012
659 1.03.02 CV. MB Pembangunan Jembatan Sriagung 02/SRIAGUNG/S 97.778.000,00 4.888.900,00 - - 4.888.900,00
PK/PPK/PUBM/2
012 Tgl. 12
Oktober 2012
660 1.03.02 PT. ReKo Pengaspalan Jalan dengan Aspal Hotmix 04/003/PPK/KO 1.494.666.000,00 74.733.300,00 - - 74.733.300,00
Ruas Jalan Sp. Sidang Mas - Sidang Mas NTRAK/PUBM/2
Kec. Banyuasin III 008 Tanggal 31
Juli 2008
661 1.03.02 CV. KaKo Pengecoran Jalan Dalam Kota Kecamatan 979.782.000,00 12.247.275,00 - - 12.247.275,00
Betung - Jl. Gotong Royong dan Pangeran 04/044/PPK/KO
Dulkurdi NTRAK/PUBM/2
008 Tanggal 31
Juli 2008
662 1.03.02 CV. SePu Pengecoran Jalan Bima Sakti (BPDS) Kec. 04/046/PPK/KO 977.671.000,00 12.220.887,00 - - 12.220.887,00
Betung NTRAK/PUBM/2
008 Tanggal 31
Juli 2008
663 1.03.02 CV. CC Pengecoran Jalan Desa Gelebak Dalam Kec. 04/061/PPK/KO 783.145.000,00 9.789.312,00 - - 9.789.312,00
Rambutan NTRAK/PUBM/2
008 Tanggal 31
Juli 2008
664 1.03.02 CV. DP Pengecoran Jalan Dalam Kota Kecamatan 04/062/PPK/KO 195.389.000,00 9.769.450,00 - - 9.769.450,00
Betung - Jl. M. Roib NTRAK/PUBM/2
008 Tanggal 31
Juli 2008
665 1.03.02 CV. MK Pembangunan Jembatan Desa Bintaran 04/105/PPK/KO 113.327.000,00 5.666.350,50 - - 5.666.350,50
(Jembatan No. 1) Kec. Air Salek NTRAK/PUBM/2
008 Tanggal 31
Juli 2008
666 1.03.02 CV. JB Pembangunan Jembatan Desa Bintaran 04/106/PPK/KO 113.199.000,00 5.659.950,50 - - 5.659.950,50
(Jembatan No. 2) Kec. Air Salek NTRAK/PUBM/2
008 Tanggal 31
Juli 2008
Halaman 59 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
667 1.03.02 CV. MK Pembangunan Jembatan Desa Parit 1 Ruas 04/107/PPK/KO 205.494.000,00 10.274.700,00 - - 10.274.700,00
Jalan Makarti Jaya - Pangestu Kec. Makarti NTRAK/PUBM/2
Jaya 008 Tanggal 31
Juli 2008
668 1.03.02 PT. RAPra Pembangunan Jembatan Desa Damar 05/05/PPK- 99.581.000,00 4.979.050,00 - - 4.979.050,00
Wulan Menuju Dermaga - Jembatan SDU PL/KONTRAK/P
VII Primer 6 Kec. Air Salek UBM/2008
Tanggal 17
Oktober 2008
669 1.03.02 PT. HMa Pengecoran Jalan Cinta Manis Lama Kec. 05/06/PPK- 99.597.000,00 4.979.850,00 - - 4.979.850,00
Banyuasin I PL/KONTRAK/P
UBM/2008
Tanggal 17
Oktober 2008
670 1.03.02 CV. KR Pembuatan Box Culvert Type Single (2x2) 05/17/PPK- 99.568.000,00 4.978.400,00 - - 4.978.400,00
Desa Bengkuang Kec. Betung PL/KONTRAK/P
UBM/2008
Tanggal 17
Oktober 2008
671 1.03.02 CV. JB Pembuatan Box Culvert Type Single (2x2) 05/18/PPK- 99.541.000,00 4.977.050,00 - - 4.977.050,00
Desa Mukut Kec. Pulau Rimau PL/KONTRAK/P
UBM/2008
Tanggal 17
Oktober 2008
672 1.03.02 CV. LUM Pengecoran Jalan Menuju Desa Tanjung 07/43/PPK- 99.490.000,00 4.974.500,00 - - 4.974.500,00
Laga KONTRAK/PUB
M/IX/2006
Tanggal 14
September 2006
673 1.03.02 CV. Dr Pembangunan Jembatan Desa dari 07/44/PPK- 99.502.000,00 4.975.100,00 - - 4.975.100,00
Jembatan I - Muara Jalur VIII Desa Karang KONTRAK/PUB
Baru Jembatan Desa SPD I M/IX/2006
Tanggal 14
September 2006
674 1.03.02 CV. TK Penimbunan Jalan Tanjung Api-api - Sungsang 07/09/PPK- 1.950.068.000,00 27.300.952,00 - - - Tidak di tagih lagi
KONTRAK/PUBM
/IX/2006 tanggal
14 September 2006
675 1.03.02 CV. JB Pembangunan Box Culvert Taja Raya II 07/PPK- 99.000.000,00 2.475.000,00 - - 2.475.000,00
Type Single 1/1 KONTRAK/PUB
M/IX/2006
tanggal 28
November 2006
Halaman 60 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
676 1.03.02 CV. LiJa Penimbunan Oprit Box Culvert Jalan Baru 05/PPK- - 94.500.000,00 - - 94.500.000,00 Nilai Kontrak
Talang Andong - Sungai Dua Kec. PL/TASD/KONT Rp. 94.500.000
Rambutan RAK/PUBM/201
0 tanggal 11
November 2010
677 1.03.02 CV. SeJa Pembangunan Box Culvert Type Single Uk. 05/PPK-PL/DB- - 4.977.500,00 - - 4.977.500,00 Nilai Kontrak
(3x3) Jalan Desa Baru Kec. Rambutan - 1/KONTRAK/PU Rp. 99.550.000
Box Culvert No. 01 BM/2010
Tanggal 22
September 2010
678 1.03.02 CV. Ra Perkuatan Jembatan Beton Air Gading Kec. 05/GADING/PPK- - 4.950.000,00 - - 4.950.000,00 Nilai Kontrak
Muara Padang PL/KONTRAK/P Rp. 99.000.000
UBM/2010
Tanggal 01 April
2010
679 1.03.02 CV. Ra Perbaikan Tembok Penahan Tanah 05/PENAHAN/P - 4.950.000,00 - - 4.950.000,00 Nilai Kontrak
Jembatan Muara Padang Kec. Muara PK- Rp. 99.000.000
Padang PL/KONTRAK/P
UBM/2010
Tanggal 01 April
2010
680 1.03.02 CV. AAA pengawasan kegiatan rehabilitasi / penataan 03/02/PPK/PENG - 2.480.500,00 - - 2.480.500,00 Nilai Kontrak
bundaran tugu ketahanan pangan dan jalan /KONTRAK/PU Rp. 49.610.000
sekitar tugu dengan aspal hotmix kecamatan BM/ 2010
banyuasin III Tanggal 01 April
2010
681 1.03.02 CV. RMK Pengecoran Jalan Dalam Ibukota 05/PU-55/PPK- 568.412.000,00 28.420.600,00 5638/LS/1.20 28.420.600,00 - -
Kecamatan Muara Telang (Tahap II) KONTRAK/PUB .09.02.00/6.2/
M/2011 2013
tanggal 3 Agustus
2011
682 1.03.02 CV. DMM Pengecoran Jalan Desa Banyu Urip Kec. 05/02/PM- 196.993.000,00 9.849.650,00 - - 9.849.650,00
Tanjung Lago L/PPK/KONTRA
K/ PUBM/2011
tanggal 8 Juni
2011
683 1.03.02 CV. ASI Pengecoran Jalan Serasi I Kec. Talang 01/SI/SPK/PPK/P 98.751.000,00 4.937.550,00 - - 4.937.550,00
Kelapa UBM/2011
tanggal 29
September 2011
Halaman 61 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
684 1.03.02 CV. IqP Pengecoran Halaman Rumah Dinas Kajari 01/HRDK/SPK/P 49.277.000,00 2.463.850,00 - - 2.463.850,00
Banyuasin PK/PUBM/2011
tanggal 22
Nopember 2011
685 1.03.02 CV. R- D Pembangunan Box Culvert Type Single Uk. Nomor : tanggal 197.230.000,00 9.861.500,00 - - 9.861.500,00
(2x2) Desa Sungai Gerong Kec. Banyuasin 8 Juni 2011
I
686 1.03.02 CV. JU Pembuatan Box Culvert Type Single Uk. 49.257.000,00 2.462.850,00 - - 2.462.850,00
(1x1) Jl. Thalib Wali Pangkalan Balai 01/TW/SPK/PPK/
PUBM/2011
tanggal 22
Nopember 2011
687 1.03.03 CV. PL Rehabilitasi Jaringan Pengairan Sekunder 02/SPK/PPK- 199.380.000,00 - - 9.969.000,00 9.969.000,00
Desa Sumber Mulyo Kecamatan Pulau PB/PU-
Rimau PENG/2013 Tgl.
5 Februari 2013
688 1.03.03 CV. KS Rehabilitasi Saluran di Desa Tabuan Asri 03/34/PPK- 321.540.000,00 - - 321.540.000,00 321.540.000,00
Kec. Pulau Rimau OP.I/PU.PENG/2
013 Tgl. 8
Nopember 2013
(Addendum)
03.a/34/ASP/PPK-
OP.I/PU.PENG/2
013 Tgl. 20
Desember 2013
689 1.03.03 CV. HS Pengadaan dan Pemasangan Genset 11,6 600/129/GEN/PU 197.786.000,00 9.889.300,00 4692/LS/1.20 9.889.300,00 - -
KVA, 3 Phese, Silent/ATS-MF + Perbaikan .PENG/2012 Tgl. .09.02.00/6.2/
Instalasi Gedung Kantor 8 Juni 2012 2013
690 1.03.03 CV. PL Rehabilitasi Jaringan Pengairan Sekunder 03/01/PPK- 294.330.000,00 14.716.500,00 1555/LS/1.20 14.716.500,00 - -
Desa Sumber Mulyo Kecamatan Pulau PB/PU.PENG/20 .09.02.00/6.2/
Rimau 12 Tgl. 5 Juli 2013
2012
691 1.03.03 CV. PL Rehabiliatsi Jaringan Pengairan Desa 03/02/PPK- 342.520.000,00 17.126.000,00 0943/LS/1.20 17.126.000,00 - -
Penuguan Kecamatan Pulau Rimau PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
Halaman 62 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
692 1.03.03 CV. BT Normalisasi Sungai Anak Pancur Desa Taja 03/03/PPK- 292.880.000,00 14.644.000,00 1551/LS/1.20 14.644.000,00 - -
Raya Kecamatan Betung PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
(Addendum)
03.a/03/ASP/PPK-
PB/PU.PENG/20
693 1.03.03 CV. GB Normalisasi Sungai Desa Ujung Tanjung 12 Tgl 24 Juli
03/04/PPK- 495.870.000,00 24.793.500,00 0927/LS/1.20 24.793.500,00 - -
Kec. Banyuasin III PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012(Addendum)
036.1/04/PPK-
PB/PU.PENG/20
12 Tgl 03
Oktober 2012
694 1.03.03 CV. KS Rehabilitasi Jaringan Pengairan Desa 03/05/PPK- 346.410.000,00 17.320.500,00 0920/LS/1.20 17.320.500,00 - -
Limbang Mulya Kecamatan Sembawa PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
(Addendum)
03.a/05/ASP/PPK-
PB/PU.PENG/20
12 Tgl. 25 Juli
2012
695 1.03.03 CV. TS Rehabilitasi Jaringan Pengairan Desa 03/06/PPK- 337.760.000,00 16.888.000,00 1514/LS/1.20 16.888.000,00 - -
Talang Kemang Kecamatan Rantau Bayur PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
(Addendum)
03/06/ASP/PPK-
PB/PU.PENG/20
12 Tgl. 24 Juli
2012
696 1.03.03 CV. GMs Peningkatan Jaringan Pengairan Desa 03/07/PPK- 198.760.000,00 9.938.000,00 0878/LS/1.20 9.938.000,00 - -
Sejagung Kecamatan Rantau Bayur PB/PU.PENG/20 .09.02.00/6.2/
12 tgl. 05 Juli 2013
2012
697 1.03.03 CV. LS Pembangunan Tanggul Banjir Parit 1 Dusun 03/08/PPK- 341.600.000,00 17.080.000,00 2573/LS/1.20 17.080.000,00 - -
3 Upang Makmur Kecamatan Makarti Jaya PP.III/PU.PENG/ .09.02.00/6.2/
2012 Tgl. 05 Juli 2013
2012
Halaman 63 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
698 1.03.03 CV. APe Rehabilitasi Jaringan Pengairan Desa 03/09/PPK- 386.440.000,00 19.322.000,00 5625/LS/1.20 19.322.000,00 - -
Upang Makmur Kecamatan Makarti Jaya PP.III/PU.PENG/ .09.02.00/6.2/
2012 Tgl. 05 Juli 2013
2012
(Addendum)
012/09/ASP/PPK-
PP.III/PU.PENG/
2012 Tgl. 18 Juli
2012
699 1.03.03 CV. RK Peningkatan Jaringan Pengairan Desa 03/10/PPK- 197.170.000,00 9.858.500,00 5255/LS/1.20 9.858.500,00 - -
Upang Cemara Kecamatan Makarti Jaya PP.III/PU.PENG/ .09.02.00/6.2/
2012 Tgl 05 Juli 2013
2012
700 1.03.03 CV. DP Pembangunan Tanggul di Desa Merah Mata 03/12/PPK- 343.710.000,00 17.185.500,00 2813/LS/1.20 17.185.500,00 - -
Kec. Banyuasin I PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
(Addendum)
40/12/ASP/PPK-
PP.I/PU.PENG/2
012 Tgl 20 Juli
2012
701 1.03.03 CV. BJ Normalisasi Sungai Rebo Kecamatan 03/13/PPK- 795.730.000,00 39.786.500,00 1769/LS/1.20 39.786.500,00 - -
Banyuasin I PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
702 1.03.03 CV. LS Normalisasi Sungai Wimpe Kecamatan 03/14/PPK- 783.080.000,00 39.154.000,00 3085/LS/1.20 39.154.000,00 - -
Banyuasin I PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
(Addendum)
35.1/14/ASP/PPK-
PP.I/PU.PENG/2
012 Tgl. 18 Juli
2012
703 1.03.03 CV. DP Peningkatan Jaringan Pengairan Desa 03/15/PPK- 355.590.000,00 17.779.500,00 2894/LS/1.20 17.779.500,00 - -
Padang Rejo Kecamatan Banyuasin I PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
704 1.03.03 CV. EC Peningkatan Jaringan Pengairan Desa Air 03/16/PPK- 366.100.000,00 18.305.000,00 7208/LS/1.20 18.305.000,00 - -
Kumbang Bakti Kecamatan Banyuasin I PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
Halaman 64 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
705 1.03.03 CV. BT Peningkatan Jaringan Pengairan Desa 03/17/PPK- 196.560.000,00 9.828.000,00 1554/LS/1.20 9.828.000,00 - -
Rantau Bayur Kecamatan Rantau Bayur PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
706 1.03.03 CV. LK Pembangunan Jaringan Pengairan Desa 03/18/PPK- 195.970.000,00 9.798.500,00 2900/LS/1.20 9.798.500,00 - -
Baru Kecamatan Rambutan PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
707 1.03.03 CV. APe Pembangunan Jaringan Pengairan Desa 03/19/PPK- 197.080.000,00 9.854.000,00 4945/LS/1.20 9.854.000,00 - -
Durian Gadis Kecamatan Rambutan PP.I/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
708 1.03.03 CV. MI Peningkatan Jaringan Pengairan Parit 4 dan 03/20/PPK- 693.280.000,00 34.664.000,00 2027/LS/1.20 34.664.000,00 - -
Parit 6 Desa Upang Makmur Kecamatan PP.III/PU.PENG/ .09.02.00/6.2/
Makarti Jaya 2012 Tgl. 05 Juli 2013
2012
(Addendum)
012/20/ASP/PPK-
PP.III/PU.PENG/
2012 Tgl. 16 Juli
2012
709 1.03.03 CV. EC Peningkatan Jaringan Pengairan Desa 03/21/PPK- 356.770.000,00 17.838.500,00 7209/LS/1.20 17.838.500,00 - -
Upang Ceria Kecamatan Makarti Jaya PP.III/PU.PENG/ .09.02.00/6.2/
2012 Tgl. 05 Juli 2013
2012
(Addendum)
012/21/ASP/PPK-
PP.III/PU.PENG/
2012 Tgl. 18 Juli
2012
710 1.03.03 CV. BJ Peningkatan Jaringan Pengairan Desa Suka 03/22/PPK- 277.130.000,00 13.856.500,00 4007/LS/1.20 13.856.500,00 - -
Tani Kecamatan Tanjung Lago PP.III/PU.PENG/ .09.02.00/6.2/
2012 Tgl. 05 Juli 2013
2012
711 1.03.03 CV. JIL Peningkatan Jaringan Pengairan Desa 03/23/PPK- 395.630.000,00 19.781.500,00 2090/LS/1.20 19.781.500,00 - -
Muara Sungsang Kecamatan Banyuasin II PP.II/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
712 1.03.03 CV. HBS Peningkatan Jaringan Pengairan Sungai 03/24/PPK- 714.290.000,00 35.714.500,00 2746//LS/1.2 35.714.500,00 - -
Teluk Macan Kecamatan Banyuasin II PP.II/PU.PENG/2 0.09.02.00/6.
012 Tgl. 05 Juli 2/2013
2012
Halaman 65 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
713 1.03.03 CV. TBJ Rehabilitasi Jaringan Pengairan Parit 2 03/25/PPK- 198.120.000,00 9.906.000,00 2094/LS/1.20 9.906.000,00 - -
Desa Marga Sungsang Kecamatan PP.II/PU.PENG/2 .09.02.00/6.2/
Banyuasin II 012 tgl. 05 Juli 2013
2012
(Addendum)
03.a/25/ASP/PPK-
PP.II/PU.PENG/2
012 Tgl. 19 Juli
2012
714 1.03.03 CV. RK Normalisasi Parit Sam Desa Karang Baru 03/26/PPK- 298.780.000,00 14.939.000,00 2093/LS/1.20 14.939.000,00 - -
Kecamatan Muara Telang PP.II/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
715 1.03.03 CV. TS Pembangunan Tanggul Desa Mekar Sari 03/27/PPK- 356.280.000,00 17.814.000,00 5362/LS/1.20 17.814.000,00 - -
Kecamatan Muara Telang PP.II/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
(Addendum)
03.a/27/ASP/PPK-
PP.II/PU.PENG/2
012 Tgl. 23 Juli
2012
716 1.03.03 CV. PT Rehabilitasi Jaringan Pengairan Desa Tirta 03/28/PPK- 396.190.000,00 19.809.500,00 1510/LS/1.20 19.809.500,00 - -
Jaya Kecamatan Muara Padang OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
717 1.03.03 CV. NPM Rehabilitasi Jaringan Pengairan Desa 03/29/PPK- 395.750.000,00 19.787.500,00 3925/LS/1.20 19.787.500,00 - -
Sumber Rejeki Kecamatan Pulau Rimau OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
718 1.03.03 CV. AP Rehabilitasi Jaringan Pengairan Pengairan 03/30/PPK- 394.130.000,00 19.706.500,00 7178/LS/1.20 19.706.500,00 - -
Desa Suka Jaya Kecamatan Tungkal Ilir OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
719 1.03.03 CV. LK Rehabilitasi Jaringan Pengairan Desa Budi 03/31/PPK- 786.570.000,00 39.328.500,00 3892/LS/1.20 39.328.500,00 - -
Mulya Kecamatan Banyuasin I OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
(Addendum)
03.a/31/ASP/PPK-
OP/PU.PENG/20
12 Tgl. 03
September 2012
Halaman 66 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
720 1.03.03 Cv. AILS Rehabilitasi Jaringan Pengairan Desa Mukti 03/32/PPK- 395.550.000,00 19.777.500,00 3868/LS/1.20 19.777.500,00 - -
Jaya Kecamatan Muara Telang OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl 05 Juli 2013
2012
721 1.03.03 CV. BJ Rehabilitasi Jaringan Pengairan Desa 03/33/PPK- 396.680.000,00 19.834.000,00 5370/LS/1.20 19.834.000,00 - -
Sumber Jaya Kecamatan Muara Telang OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
722 1.03.03 CV. BJ Rehabilitasi Jaringan Pengairan Desa 03/34/PPK- 397.280.000,00 19.864.000,00 4006/LS/1.20 19.864.000,00 - -
Telang Karya Kecamatan Muara Telang OP/PU.PENG/20 .09.02.00/6.2/
12 Tgl. 05 Juli 2013
2012
723 1.03.03 CV. GMs Pembangunan Tanggul Jalur 6 Desa Sumber 03/35/PPK- 394.960.000,00 19.748.000,00 4693/LS/1.20 19.748.000,00 - -
Mulya Kecamatan Muara Telang PP.II/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
724 1.03.03 CV. AP Rehabilitasi Jaringan Pengairan Desa Purwo 03/36/PPK- 395.330.000,00 19.766.500,00 4944/LS/1.20 19.766.500,00 - -
Sari Kecamatan Tanjung Lago PP.III/PU.PENG/ .09.02.00/6.2/
2012 Tgl. 05 Juli 2013
2012
725 1.03.03 CV. RK Normalisasi Sungai Bungin Desa Rimau 03/37/PPK- 355.650.000,00 17.782.500,00 2089/LS/1.20 17.782.500,00 - -
Sungsang Kecamatan Banyuasin II PP.II/PU.PENG/2 .09.02.00/6.2/
012 Tgl. 05 Juli 2013
2012
726 1.03.03 CV. AiP Pembangunan Sal Penanggulangan Banjir 03/38/PPK- 444.590.000,00 22.229.500,00 4205/LS/1.20 22.229.500,00 - -
di Komp. Azhar Kenten & Pembersihan PP.III/PU.PENG/ .09.02.00/6.2/
Sal. Penanggulangan Banjir di Komp.Griya 2012 Tgl. 24 2013
Damai Indah Kec. Talang Kelapa Oktober 2012
(Addendum)
012/38/ASP/PPK-
PP.III/PU.PENG/
2012 Tgl 07
November 2012
727 1.03.03 CV. KS Normalisasi Sungai Kesambi (lanjutan) 03/39/PPK- 496.090.000,00 24.804.500,00 1603/LS/1.20 24.804.500,00 - -
Kecamatan Banyuasin III / Rantau Bayur PB/PU.PENG/20 .09.02.00/6.2/
12 Tgl 24 2013
Oktober 2012
728 1.03.03 CV. MI Pembangunan dan Peningkatan Jaringan 02/40/SPK/PPK- 198.700.000,00 9.935.000,00 5359/LS/1.20 9.935.000,00 - -
Pengairan Desa Tanjung Kerang Kecamatan PP.I/PU.PENG/2 .09.02.00/6.2/
Rambutan 012 Tgl. 01 2013
November 2012
729 1.03.03 CV. KBn Pembangunan dan Peningkatan Jaringan di 04/SP/KBP/PU.P 396.653.000,00 19.832.650,00 - - 19.832.650,00
Desa Tanjung Mas eng/2011
730 1.03.03 CV. KR Rehabilitasi Saluran Primer 19 Telang II 07/SP/KBP/PU.P 462.226.000,00 23.111.300,00 - - 23.111.300,00
Kec. Tanjung Lago eng/2011
Halaman 67 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
DINAS KEBERSIHAN, PERTAMANAN DAN
731 1.08.02 CV. PhB Kegiatan Pembangunan Tempat 027/97/PPK/SPK/ 100.000.000,00 - - 5.000.000,00 5.000.000,00
Pembuangan Sampah Sementara TPS/DKPP/2013
14 Nopember
2013
732 1.08.02 CV. BMF Pekerjaan Pemeliharaan Berkala/Rutin 012/PPK/SPK/TU 78.000.000,00 3.900.000,00 - - 3.900.000,00
Gedung Kantor .PGK/DKPP/201
2 Tgl. 2 Juli 2012
733 1.08.02 CV. CBI Kegiatan Pembangunan Tempat 016/PPK/SPK/TP 100.000.000,00 5.000.000,00 4165/LS/1.20 5.000.000,00 - -
Pembuangan Sampah Sementara S/DKPP/2012 .09.02.00/6.2/
Tgl. 16 Okt 2012 2013
734 1.08.02 CV. SA Kegiatan Pembangunan Pos Jaga Tempat 010/PPK/SPK/TP 295.714.000,00 14.785.700,00 4093/LS/1.20 14.785.700,00 - -
Pemerosesan Akhir sampah (TPA) Terlangu A-PJ/DKPP/2012 .09.02.00/6.2/
Tgl. 9 Okt 2012 2013
735 1.08.02 CV. LiBe Pengadaan Pembuatan Pagar Tempat 020/01/PPK- 99.175.000,00 4.958.750,00 - - 4.958.750,00
Pemakaman Umum Pedade Kab. Banyuasin PL/SPK/DKPP/2
012 Tgl. 8 Okt
2012
736 1.08.02 CV. KJ Pemeliharaan Gedung Kantor 36.596.000,00 1.829.800,00 - - 1.829.800,00
737 1.08.02 CV. RM Landkling Tempat Pembuangan Sampah 726.004.000,00 36.300.200,00 - - 36.300.200,00
738 1.20.03 CV. KSL Pengadaan Kendaraan Dinas Operasional 027/306/SPK/VII 2.199.980.000,00 - - 98.595.000,00 98.595.000,00
Kepala Daerah Kabupaten Banyuasin I/2013 Tgl, 06
Des 2013
739 1.20.03 CV. JU Pekerjaan Rehab Ruang Kerja 027/178/SPK/VII 106.150.000,00 - - 5.307.500,00 5.307.500,00
Bendaharawan Pembantu Urusan Gaji I/2013 Tgl, 23
Bagian Umum Setda Kabupaten Banyuasin Sept 2013
740 1.20.03 CV. EA Pengadaan Panggung dan Interior Gedung 027/266/VIII/201 295.000.000,00 14.750.000,00 - - 14.750.000,00
Graha Sedulang Setudung Kab. Banyuasin 2 Tgl. 23
Nopember 2012
741 1.20.03 CV. Ra Pekerjaan Penambahan WC VIP di Graha 027/241/VIII/201 98.170.000,00 4.908.500,00 - - 4.908.500,00
Sedulang Setudung Kab. Banyuasin 2 Tgl. 06
Nopember 2012
742 1.20.03 CV. TS Pengecatan dan Interior Ruang Kerja, 027/239/VIII/201 98.026.000,00 4.901.300,00 - - 4.901.300,00
Rapat, Asisten II pada Bagian umum Setda 2 Tgl. 31 Oktober
Kab. Banyuasin 2012
743 1.20.03 CV. AS Pengecatan Ruang Dinas Jabatan Bupati 027/224/SPK/VII 99.859.530,00 4.992.977,00 2028/LS/1.20 4.992.976,00 - -
Banyuasin pada Bagian Umum Setda Kab. I/2012 Tgl 19 .09.02.00/6.2/
Banyuasin Oktober 2012 2013
Halaman 68 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
744 1.20.03 CV. RK Pengecatan Jendela, Kusen dan Pintu 027/218/SPK/VII 99.838.470,00 4.991.924,00 2015/LS/1.20 4.991.923,00 - -
Rumah Dinas Bupati dan Guest House pada I/2012 Tgl. 10 .09.02.00/6.2/
Bagian Umum Setda Kab. Banyuasin Oktober 2012 2013
745 1.20.03 CV. RK Pemeliharaan/Perbaikan Selasar/Teras 027/182/SPK/VII 94.803.720,00 4.740.186,00 2011/LS/1.20 4.740.186,00 - -
Kantor Setda Kabupaten Banyuasin pada I/2012 Tgl. 26 .09.02.00/6.2/
Bagian Umum Kab. Banyuasin September 2012 2013
746 1.20.03 CV. AS Pemeliharaan Rumah Dinas Jabatan Bupati 027/150/SPK/VII 99.756.000,00 4.987.800,00 2013/LS/1.20 4.987.800,00 - -
Banyuasin pada Bagian Umum Setda Kab. I/2012 Tgl. 24 .09.02.00/6.2/
Banyuasin Agustus 2012 2013
747 1.20.03 CV. KSD S Pengadaan Lain-lain Penghias Ruangan 027/228/SPK/V/2 742.100.000,00 37.105.000,00 6439/LS/1.20 37.105.000,00 - -
rumah Tangga pada Bagian Administrasi 012 Tgl. 19 .09.02.00/6.2/
Pembangunan Setda Kab. Banyuasin September 2012 2013
748 1.20.03 CV. TS Rehabilitasi Lantai Dasar (Loby) Ruang 027/250/SPK/V/2 592.200.000,00 29.610.000,00 6436/LS/1.20 29.610.000,00 - -
rapat Bupati pada bagian Administrasi 012 Tgl. 14 .09.02.00/6.2/
Pembangunan Setda Kab. Banyuasin Nopember 2012 2013
749 1.20.03 CV. TW Rehabilitasi Sanitasi Kantor Pemerintah 027/260/SPK/V/2 198.115.000,00 9.905.750,00 6438/LS/1.20 9.905.750,00 - -
Kab. Banyuasin pada Bagian Administrasi 012 Tgl. 12 .09.02.00/6.2/
Pembangunan Nopember 2012 2013
750 1.20.03 CV. EC Rehabilitasi Ruang pada Bagian 027/264/SPK/V/2 197.600.000,00 9.880.000,00 6437/LS/1.20 9.880.000,00 - -
Administrasi Pembangunan Setda Kab. 012 Tgl. 12 .09.02.00/6.2/
Banyuasin Nopember 2012 2013
751 1.20.04 CV. NPM Pengadaan LED TV, Plasma TV dan DVD 027/135/PPK- 108.300.000,00 - - 108.300.000,00 108.300.000,00
Player Kegiatan Pengadaan Peralatan UMUM/SPK/SE
Gedung Kantor pada Sekretariat DPRD TWAN/2013
Kabupaten Banyuasin
752 1.20.04 CV. AK Pengadaan Kamera Keg. Penyusunan 027/147/PPK- 16.000.000,00 - - 16.000.000,00 16.000.000,00
Rencana Strategis SKPD KEU/SPK/SETW
AN/2013
753 1.20.04 CV. LS Pengadaan Almari Arsip Bagian 027/170/PPK- 96.000.000,00 - - 96.000.000,00 96.000.000,00
Persidangan dan Bagian Keuangan UMUM/SPK/SE
Kegiatan Rapat-rapat Paripurna pada TWAN/2013
Bagian Persidangan dan Humas pada
Sekretariat DPRD Kab. Banyuasin
754 1.20.04 CV. GB Pekerjaan Lanjutan Gedung Fraksi DPRD 027/110/PPK- 1.987.400.000,00 99.370.000,00 2496/LS/1.20 99.370.000,00 - -
Kabupaten Banyuasin Keg. Pembangunan UMUM/SPK/SE .09.02.00/6.2/
Gedung Kantor TWAN/2012 2013
755 1.20.04 CV. TJ Pekerjaan Pembuatan Rolling Door Garasi 027/086/PPK- 48.437.500,00 2.421.875,00 - - 2.421.875,00
Mobil Pool Keg. Pembangunan Gedung UMUM/SPK/SE
Kantor Setwan Kab. Banyuasin TWAN/2012
Halaman 69 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
756 1.20.04 CV. SDS Pekerjaan Lanjutan Pembangunan Jalan 027/118/PPK- 196.080.000,00 9.804.000,00 - - 9.804.000,00
Lingkar Belakang Gedung Fraksi UMUM/SPK/SE
TWAN/2012
757 1.20.04 CV. HR Pekerjaan Pembuatan Rumah-Rumahan 601/107/PPK/SP 59.310.000,00 2.965.500,00 - - 2.965.500,00
Genset untuk Rumah Dinas Wakil Ketua I, K-
II dan III UMUM/SETWA
N/2012
758 1.20.04 CV. LS Pekerjaan Pembangunan Parit Halaman 601/128/PPK/SP 149.400.000,00 7.470.000,00 2359/LS/1.20 7.470.000,00 - -
Rumah Dinas Ketua DPRD Kab. Banyuasin K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
759 1.20.04 CV. PL Pekerjaan Pembangunan Tambahan Gedung 601/130/PPK/SP 98.900.000,00 4.945.000,00 2575/LS/1.20 4.945.000,00 - -
Rumah Dinas Ketua DPRD Kab. Banyuasin K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
760 1.20.04 CV. JIL Pemeliharaan Pembuatan Peralatan Jemuran 601/135/PPK/SP 25.800.000,00 1.290.000,00 - - 1.290.000,00
Beton Rumah Dinas Wakil Ketua I K-
UMUM/SETWA
N/2012
761 1.20.04 CV. AP Pekerjaan Rumah Joglo di Belakang Rumah 601/136/PPK/SP 118.400.000,00 5.920.000,00 3495/LS/1.20 5.920.000,00 - -
Dinas & Renovasi Kamar Tidur Pembantu K- .09.02.00/6.2/
dan Gudang Menjadi Kamar Tidur Rumdin UMUM/SETWA 2013
Wakil Ketua II N/2012
762 1.20.04 CV. Ds Pekerjaan Pemasangan Conblok Rumah 601/131/PPK/SP 99.560.000,00 4.978.000,00 2574/LS/1.20 4.978.000,00 - -
Dinas Ketua DPRD Kab. Banyuasin K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
763 1.20.04 CV. PL Pekerjaan Tambahan Ruang Balkon Kantor 601/138/PPK/SP 148.790.000,00 7.439.500,00 2572/LS/1.20 7.439.500,00 - -
DPRD K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
764 1.20.04 CV. Ha Pekerjaan Pembangunan Tambahan Ruang 601/140/PPK/SP 149.774.000,00 7.488.700,00 2495/LS/1.20 7.488.700,00 - -
Gudang K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
765 1.20.04 CV. AiP Pekerjaan Pembangunan Garasi Mobil dan 601/134/PPK/SP 98.990.000,00 4.949.500,00 3498/LS/1.20 4.949.500,00 - -
Gudang Rumah Dinas Wakil Ketua II K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
Halaman 70 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
766 1.20.04 CV. TJ Pekerjaan Pembuatan Pagar Steinless dalam
601/202/PPK/SP 53.950.000,00 2.424.500,00 - - 2.424.500,00
Ruang Rapat Paripurna & Pemasangan K-
Wallpaper Ruang Tunggu Bupati di Gedung
UMUM/SETWA
Paripurna N/2012
767 1.20.04 CV. TP Pekerjaan Pembangunan Gedung Fraksi 601/150/PPK/SP 149.670.000,00 7.483.500,00 2504/LS/1.20 7.483.500,00 - -
DPRD Kab. Banyuasin (Interior Ruangan)K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
768 1.20.04 CV. LS Pekerjaan Pembuatan Pot Kembang & 601/139/PPK/SP 158.880.000,00 7.944.000,00 2362/LS/1.20 7.944.000,00 - -
Penanaman Pohon Halaman Kantor DPRD K- .09.02.00/6.2/
& Gedung Paripurna UMUM/SETWA 2013
N/2012
769 1.20.04 CV. PL Pekerjaan Pembuatan Rumah-Rumahan 601/142/PPK/SP 19.890.000,00 995.000,00 2382/LS/1.20 994.500,00 - -
Genset Rumah Dinas Ketua DPRD Kab. K- .09.02.00/6.2/
Banyuasin UMUM/SETWA 2013
N/2012
770 1.20.04 CV. LS Pekerjaan Pemeliharaan Rumah Dinas 027/129/PPK/SP 73.920.000,00 3.696.000,00 2363/LS/1.20 3.696.000,00 - -
Ketua DPRD Kab. Banyuasin K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
771 1.20.04 CV. AP Pekerjaan Pemeliharaan Rumah Dinas 601/164/PPK/SP 49.400.000,00 2.470.000,00 3481/LS/1.20 2.470.000,00 - -
Wakil Ketua II DPRD K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
772 1.20.04 CV. JIL Pekerjaan Pemeliharaan Rumah Dinas 601/163/PPK/SP 51.000.000,00 2.550.000,00 - - 2.550.000,00
Wakil Ketua I DPRD Kab. Banyuasin K-
UMUM/SETWA
N/2012
773 1.20.04 CV. IP Pekerjaan Pemeliharaan Rumah Dinas 601/162/PPK/SP 49.120.000,00 2.456.000,00 5132/LS/1.20 2.456.000,00 - -
wakil Ketua III DPRD Kab. Banyuasin K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
774 1.20.04 CV. AEC Pekerjaan Pemeliharaan Kantor Sekretariat 601/167/PPK/SP 79.400.000,00 3.970.000,00 - - 3.970.000,00
DPRD K-
UMUM/SETWA
N/2012
775 1.20.04 CV. KJ Pekerjaan Rehab dan Pelebaran Ruang 601/133/PPK/SP 59.040.000,00 2.952.000,00 3496/LS/1.20 2.952.000,00 - -
Tamu Rumdin Wakil Ketua II DPRD Kab. K- .09.02.00/6.2/
Banyuasin UMUM/SETWA 2013
N/2012
776 1.20.04 CV. AP Pekerjaan Renovasi Garasi Mobil Menjadi 601/137/PPK/SP 59.814.000,00 2.990.700,00 3497LS/1.20. 2.990.700,00 - -
Kamar Tidur Tamu & KM/WC Rumdin K- 09.02.00/6.2/
Wakil Ketua II UMUM/SETWA 2013
N/2012
Halaman 71 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
777 1.20.04 CV. RA Pekerjaan Rehab Ringan Rumdin Wakil 601/141/PPK/SP 74.457.000,00 3.722.850,00 - - 3.722.850,00
Ketua I K-
UMUM/SETWA
N/2012
778 1.20.04 CV. AC Pekerjaan Renovasi Ruang Kerja Wakil 601/168/PPK/SP 158.740.000,00 7.937.000,00 - - 7.937.000,00
Ketua II DPRD K-
UMUM/SETWA
N/2012
779 1.20.04 CV. EJ Pekerjaan Rehab Lantai Loby & KM/WC 601/182/PPK/SP 99.200.000,00 4.960.000,00 2240/LS/1.20 4.960.000,00 - -
Ruang Paripurna K- .09.02.00/6.2/
UMUM/SETWA 2013
N/2012
780 1.20.04 CV. APe Pemeliharaan Rumah dinas Wakil Ketua II 027/102/SPK/SE 19.900.000,00 995.000,00 - - 995.000,00
DPRD TWAN/2011
781 1.26.01 CV. DSU Pembangunan Rumah Baca di Kec. Muara 027/16/SPK/BPA 188.720.000,00 9.436.000,00 2506/LS/1.20 9.436.000,00 - -
Sugihan Keg. Penyediaan Bantuan D/2012 Tgl. 4 .09.02.00/6.2/
Pengembangan Perpustakaan dan Minat September 2012 2013
Baca di Daerah
782 2.02.01 CV. MPU Konstruksi Pembuatan Embung 522/184- 199.976.000,00 9.998.800,00 0752/LS/1.20 9.998.800,00 - -
III/HUTBUN/201 .09.02.00/6.2/
2 Tgl. 17 2013
September 2012
783 1.02.01 CV. ArG Pembuatan Lampu Penerangan BBI 027/05/LAMPU/ 65.450.000,00 - - 3.272.500,00 3.272.500,00
PPK/BBI/VI/201
3
784 1.02.01 CV. ArG Pembuatan Hatchery BBI 027/05/HACT/PP 129.200.000,00 - - 6.460.000,00 6.460.000,00
K/BBI/IV/2013
785 1.02.01 CV. Pjy Pembuatan Bak-bak Perbenihan 027/05/HACT/PP 134.000.000,00 - - 6.700.000,00 6.700.000,00
K/BAK-
BBI/IV/2013
786 1.02.01 CV. MKC Pembuatan Hatchery Skala Rumah Tangga 027/05/HSRT- 189.200.000,00 - - 9.460.000,00 9.460.000,00
TJLG/PPK/BBI/I
V/2013
Halaman 72 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
787 1.02.01 CV. CTP Pembuatan Hatchery Skala Rumah Tangga 027/05/HSRT- 109.200.000,00 - - 5.460.000,00 5.460.000,00
SBW/PPK/BBI/I
V/2013
788 1.02.01 CV. ArG Pembuatan Gapura, Papan Nama BBI dan 027/05/GPR/PPK 102.000.000,00 - - 5.100.000,00 5.100.000,00
Pos Jaga /BBI/VIII/2013
789 1.02.01 CV. SCo Pengadaan Jasa Konsultan Pengawas 027/03/PPK/PWS- 45.000.000,00 - - 45.000.000,00 45.000.000,00
BBI/IV/2013
790 1.02.01 CV. Se Penyelesaian Pembuatan Pagar Keliling 027/05/PPK/PAG 159.000.000,00 - - 159.000.000,00 159.000.000,00
AR-BBI/IX/2013
791 1.02.01 CV. KSr Pembangunan Mess 027/03/MESS/PP 342.900.000,00 - - 240.030.000,00 240.030.000,00
K/BBI/VII/2013
792 1.02.01 CV. MKC Pengadaan Peralatan dan Perlengkapan 027/03/ALAT- 415.690.000,00 - - 415.690.000,00 415.690.000,00
Perbenihan BENIH/PPK/BBI/
VII/2013
793 1.02.01 CV. TW Penyelesaian Plester Dinding Kolam dan 027/02/PPK/PLS- 772.500.000,00 - - 38.625.000,00 38.625.000,00
Saluran BBI/VIII/2013
794 1.02.01 CV. PI Penyelesaian Pintu Air 027/05/PTA/PPK 50.000.000,00 - - 2.500.000,00 2.500.000,00
/BBI/IX/2013
795 1.02.01 CV. DPM Penyelesaian Pembangunan Laboratorium 027/05/LAB/PPK 50.000.000,00 - - 9.910.000,00 9.910.000,00
/BBI/IV/2013
796 2.05.01 CV. DAc Pembangunan Menara Tangki Air 027/25/PPK/BBI/ 39.748.000,00 1.987.400,00 - - 1.987.400,00
X/2012
797 2.05.01 CV. PHP Gedung Pertemuan dan Pagar Keliling 027/02/GP/PPK/ 492.849.000,00 24.642.450,00 4476/LS/1.20 24.642.450,00 - -
BBI/IX/2012 .09.02.00/6.2/
2013
798 2.05.01 CV. RF Pembangunan Mushola BBI 027/02/MUS/PP 196.726.000,00 9.836.300,00 4343/LS/1.20 9.836.300,00 - -
K/BBI/IX/2012 .09.02.00/6.2/
2013
799 2.05.01 CV. LK Pembangunan Jalan Produksi Masuk BBI 027/02/JP/PPK/B 407.996.000,00 20.399.800,00 - - 20.399.800,00
BI/IX/2012
800 2.05.01 CV. LS Pembuatan Jalan Lingkungan BBI 027/02/JL/PPK/B 107.141.000,00 5.357.050,00 4129/LS/1.20 5.357.050,00 - -
BI/IX/2012 .09.02.00/6.2/
2013
801 2.05.01 CV. ASI Pembangunan Jembatan BBI 027/14/PPK- 99.551.000,00 4.977.550,00 4829/LS/1.20 4.977.550,00 - -
BBI/2012 .09.02.00/6.2/
2013
802 2.05.01 CV. DM Pembangunan Kolam Penampungan Air 027/02/KPAB/PP 106.325.000,00 5.316.250,00 - - 5.316.250,00
Bersih BBI K/BBI/IX/2012
803 2.05.01 CV. LK Pembangunan Saluran Pembuangan Air 027/02/SPAK/PP 186.467.000,00 9.323.350,00 - - 9.323.350,00
Kotor BBI K/BBI/IX/2012
804 2.05.01 CV. Se Pemasangan Gorong-gorong 027/23/GRG- 82.020.000,00 4.101.000,00 4399/LS/1.20 4.101.000,00 - -
BBI/IX/2012 .09.02.00/6.2/
2013
Halaman 73 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
805 2.05.01 CV. KA Konstruksi Ponton Apung TPI 523/02/SP/TANG 959.252.000,00 47.962.600,00 - - 47.962.600,00
KAP/PERIK/201
2
806 2.06.01 CV. SJ Pembangunan Pasar Marga Sungsang 640/035/PPK- 98.200.000,00 4.910.000,00 1512/LS/1.20 4.910.000,00 - -
PPP/PASAR/V/2 .09.02.00/6.2/
012 tgl.7-7-12 2013
807 2.06.01 CV. BH Pembangunan Pasar Sukapindah 640/030/PPK- 95.800.000,00 4.790.000,00 5133/LS/1.20 4.790.000,00 - -
PPP/PASAR/V/2 .09.02.00/6.2/
012 2013
808 1.15.01 CV. DP Penataan Tempat Berusaha Bagi Pedagang 03/PPK/KOPER 1.138.510.000,00 56.925.500,00 3569/LS/1.20 56.925.500,00 - -
Kakilima dan Asongan ASI,UKM&PERI .09.02.00/6.2/
NDAG/VII/12 2013
809 1.15.01 CV. AS Penyediaan sarana Maupun Prasarana 027/043/INDST- 121.558.000,00 6.077.900,00 3893/LS/1.20 6.077.900,00 - -
Klaster Industri KOP,UKM&PER ..09.02.00/6.2
INDAG/X/2012 /2013
810 1.15.01 CV. RK Penyediaan Sarana Maupun Prasarana 027/025/INDST- 145.118.000,00 7.255.900,00 3747/LS/1.20 7.255.900,00 - -
Klaster Industri KOP,UKM&PER .09.02.00/6.2/
INDAG/X/2012 2013
811 1.15.01 CV. AS Penataan Tempat Berusaha Bagi Pedagang 027/PPK/KOPER 354.790.500,00 17.739.525,00 3723/LS/1.20 17.739.525,00 - -
Kakilima dan Asongan ASI,UKM&PERI .09.02.00/6.2/
NDAG/2012 2013
808 1.02.01 RSUD Sky Hutang Klaim Jamsoskes Desember 2013 16.782.368,99 16.782.368,99
809 1.02.01 RSUD BA Hutang Klaim Jamsoskes Desember 2013 565.392.197,27 565.392.197,27
810 1.02.01 RS Kst Hutang Klaim Jamsoskes Desember 2013 3.134.421.268,66 3.134.421.268,66
811 1.02.01 RSI SK Hutang Klaim Jamsoskes Desember 2013 59.015.033,21 59.015.033,21
Halaman 74 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
812 1.02.01 Puskesmas Hutang Klaim Jamsoskes Desember 2013 1.082.685.000,00 1.082.685.000,00
815 1.02.01 CV. Ha Pekerjaan Pembangunan Poskesdes Lubuk 027/1243/SPK/K 162.459.000,00 8.122.950,00 2097/LS/1.20 8.122.950,00 - -
Keranji Kec. Banyuasin III Kab. Banyuasin ES/2012 Tgl. .09.02.00/6.2/
Tahun Anggaran 2012 27/09/2012 2013
816 1.02.01 CV. HR Pekerjaan Pembangunan Poskesdes Sumber 027/1238/SPK/K 169.600.000,00 8.484.211,00 3479/LS/1.20 8.480.000,00 - 4.211,00
Mulya Kec. Muara Telang Kab. Banyuasin ES/2012 Tgl. .09.02.00/6.2/
Tahun Anggaran 2012 27/09/2012 2013
817 1.02.01 CV. JB Pekerjaan Pembangunan Poskesdes Tabuan 027/1239/SPK/K 169.670.000,00 8.483.500,00 2134/LS/1.20 8.483.500,00 - -
Asri Kec. Muara Telang Kab. Banyuasin ES/2012 Tgl. .09.02.00/6.2/
Tahun Anggaran 2012 03/12/2012 2013
818 1.02.01 CV. MPN Pekerjaan Pembangunan Poskesdes Salek 027/1240/SPK/K 169.640.000,00 8.482.000,00 2119/LS/1.20 8.482.000,00 - -
Makmur Kec. Air Salek Kab. Banyuasin ES/2012 Tgl. .09.02.00/6.2/
Tahun Anggaran 2012 27/09/2012 2013
819 1.02.01 CV. ASa Pekerjaan Pembangunan Poskesdes Sumber 027/1241/PPK/K 169.700.000,00 8.485.000,00 4094/LS/1.20 8.485.000,00 - -
Mekar Mukti Kec. Tanjung Lago Kab. ES/2012 Tgl. .09.02.00/6.2/
Banyuasin Tahun Anggaran 2012 27/09/2012 2013
820 1.02.01 CV. TJ Pekerjaan Pembangunan Poskesdes Mekar 027/1242/SPK/K 169.600.000,00 8.480.000,00 3322/LS/1.20 8.480.000,00 - -
Sari Kec. Banyuasin II Kab. Banyuasin ES/2012 Tgl. .09.02.00/6.2/
Tahun Anggaran 2012 27/12/2012 2013
821 1.02.01 CV. AS Pekerjaan Pembangunan Poskesdes Telang 027/1243/SPK/K 162.698.500,00 8.134.925,00 - - 8.134.925,00
Jaya Betung Kec. Betung Kab. Banyuasin ES/2012 Tgl.
Tahun Anggaran 2012 27/09/2012
822 1.02.01 CV. MJ Pekerjaan Pembangunan Poskesdes Muara 027/1244/PPK/K 169.630.000,00 8.481.500,00 2111/LS/1.20 8.481.500,00 - -
Telang Marga Kec. Muara Telang Kab. ES/2012 Tgl. .09.02.00/6.2/
Banyuasin Tahun Anggaran 2012 27/09/2012 2013
823 1.02.01 CV. RK Pekerjaan Pembangunan Poskesdes 027/1245/SPK/K 169.800.000,00 8.490.000,00 - - 8.490.000,00
Rejosari Jalur 14 Kec. Muara Sugihan Kab. ES/2012 Tgl.
Banyuasin Tahun Anggaran 2012 27/09/2012
824 1.02.01 CV. CMAP Pekerjaan Rehab Gedung Puskesmas 027/1245/SPK/K 89.600.000,00 4.480.000,00 3453/LS/1.20 4.480.000,00 - -
Telang Jaya Telang Kec. Muara Telang ES/2012 Tgl. .09.02.00/6.2/
Kab. Banyuasin Tahun Anggaran 2012 27/09/2012 2013
825 1.02.01 CV. AP Pekerjaan Rehab Bangunan Kantor Dinas 027/1245/SPK/K 145.600.000,00 7.280.000,00 - - 7.280.000,00
Kesehatan Kab. Banyuasin Tahun Anggaran ES/2012 Tgl.
2012 27/09/2012
826 1.02.01 RS MP Klaim Jamsoskes Rumah Sakit - 399.373.080,33 399.373.080,33 - - Sudah Terealisasi
dari Dinas
Kesehatan
827 1.02.01 RSK dr RAPKlaim Jamsoskes Rumah Sakit - 593.973.308,46 593.973.308,46 - - Sudah Terealisasi
dari Dinas
Kesehatan
Halaman 75 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
828 1.02.01 RSUD BP Klaim Jamsoskes Rumah Sakit - 91.594.750,00 91.594.750,00 - - Sudah Terealisasi
dari Dinas
Kesehatan
829 1.02.01 RSI SK Klaim Jamsoskes Rumah Sakit - 22.613.958,91 22.613.958,91 - - Sudah Terealisasi
dari Dinas
Kesehatan
830 1.02.01 RSUD KA Klaim Jamsoskes Rumah Sakit - 770.875,93 770.875,93 - - Sudah Terealisasi
dari Dinas
Kesehatan
831 1.02.01 RSUD KP Klaim Jamsoskes Rumah Sakit - 1.314.350,00 1.314.350,00 - - Sudah Terealisasi
dari Dinas
Kesehatan
832 1.02.01 CV. EPe Pembangunan Poskesdes Tanah Pilih Kec. 900/867/SPP/KE 199.000.000,00 9.950.000,00 - - 9.950.000,00
Banyuasin II S/VII/2011
833 1.02.01 CV. AEP Pembangunan Rumah Paramedis Mekar 900/995/SPP/KE 94.171.000,00 4.708.550,00 1515/LS/1.20 4.708.550,00 - -
Sari Kec. Pulau Rimau S/VII/2011 .09.02.00/6.2/
2013
834 1.02.02 CV. PK Pengadaan Pembangunan Gedung 059/1485/Nakertr 439.710.000,00 21.985.500,00 3562/LS/1.20 21.985.500,00 - -
Workshop 1 Unit di UPTD BLK ans/2012 Tgl. 19 .09.02.00/6.2/
Disnakertrans Keg. Pembangunan Balai Juli 2012 2013
Latihan Kerja (BLK)
835 2.03.01 PT. PuCi Pemeliharaan bangunan jaringan untuk 027/98- 89.850.000,00 4.492.500,00 4256/LS/1.20 4.492.500,00 - -
pemeliharaan LPJU di Kecamatan IV/Tamben/2012 .09.02.00/6.2/
Banyuasin III Kabupaten Banyuasin Tanggal 25 April 2013
2012
836 2.03.01 PT. CIA Pemeliharaan bangunan jaringan untuk 027/110- 30.960.000,00 1.548.000,00 4231/LS/1.20 1.548.000,00 - -
pemeliharaan LPJU di Kecamatan Sembawa IV/Tamben/2012 .09.02.00/6.2/
Kabupaten Banyuasin Tanggal. 27 April 2013
2012
837 2.03.01 CV. TrTe Pemeliharaan Bangunan Jaringan untuk 027/108- 74.870.000,00 3.743.500,00 4228/LS/1.20 3.743.500,00 - -
Pemeliharaan LPJU di Kecamatan Talang IV/Tamben/2012 .09.02.00/6.2/
Kelapa Kabupaten Banyuasin Tanggal 27 April 2013
2012
838 2.03.01 CV. TJ Pemeliharaan Bangunan Jaringan Untuk 027/121- 24.400.000,00 1.220.000,00 4232/LS/1.20 1.220.000,00 - -
Pemeliharaan LPJU di Kecamatan Rantau IV/Tamben/2012 .09.02.00/6.2/
Bayur Kabupaten Banyuasin Tanggal 03 Mei 2013
2012
Halaman 76 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
839 2.03.01 CV. TJ Pemeliharaan Bangunan Jaringan Untuk 027/121.b- 29.460.000,00 1.473.000,00 4235/LS/1.20 1.473.000,00 - -
Pemeliharaan LPJU di Kecamatan Tanjung IV/Tamben/2012 .09.02.00/6.2/
Lago Kabupaten Banyuasin Tanggal 03 Mei 2013
2012
840 2.03.01 CV. HS Pemeliharaan Bangunan Jaringan Untuk 027/119- 74.390.000,00 3.719.500,00 4303/LS/1.20 3.719.500,00 - -
Pemeliharaan LPJU di Kecamatan Betung IV/Tamben/2012 .09.20.00/6.2/
Kabupaten Banyuasin Tanggal 01 Mei 2013
2012
841 2.03.01 CV. HS Pemeliharaan Bangunan Jaringan Untuk 027/119.b- 29.960.000,00 1.498.000,00 4304/LS/1.20 1.498.000,00 - -
Pemeliharaan LPJU di Kecamatan Betung IV/Tamben/2012 .09.02.00/6.2/
Kabupaten Banyuasin Tanggal 01 Mei 2013
2012
842 2.03.01 PT. CU Pengadaan dan Pemasangan Lampu 027/282- 169.200.000,00 8.460.000,00 4255/LS/1.20 8.460.000,00 - -
Penerangan Jalan Umum di Desa Air Batu IV/Tamben/2012 .09.02.00/6.2/
Kecamatan Talang Kelapa Kabupaten Tanggal 14 2013
Banyuasin Agustus 2012
843 2.03.01 CV. AgP Pengadaan dan Pemasangan Lampu Jalan 027/283- 198.000.000,00 9.900.000,00 4297/LS/1.20 9.900.000,00 - -
Umum di Desa Sungai Rebo Kecamatan IV/Tamben/2012 .09.02.00/6.2/
Banyuasin I Kabupaten Banyuasin Tanggal 14 2013
Agustus 2012
844 2.03.01 PT. PuCi Pengadaan dan Pemasangan Lampu 027/284- 198.900.000,00 9.945.000,00 4234/LS/1.20 9.945.000,00 - -
Penerangan Jalan Umum di Kelurahan IV/Tamben/2012 .09.02.00/6.2/
Kenten Kecamatan Talang Kelapa Tanggal 14 2013
Kabupaten Banyuasin Agustus 2012
845 2.03.01 PT. DPA Pengadaan dan Pemasangan Lampu 027/285- 198.300.000,00 9.915.000,00 4299/LS/1.20 9.915.000,00 - -
Penerangan Jalan Umum di Desa Suka IV/Tamben/2012 .09.02.00/6.2/
Mulya Kecamatan Betung Kabupaten Tanggal 14 2013
Banyuasin Agustus 2012
846 2.03.01 PT. DPCU Pengadaan dan Pemasangan Lampu 027/286- 198.500.000,00 9.925.000,00 4254/LS/1.20 9.925.000,00 - -
Penerangan Jalan Umum di Kelurahan IV/Tamben/2012 .09.02.00/6.2/
Talang Keramat Kecamatan Talang Kelapa Tanggal 14 2013
Kabupaten Banyuasin Agustus 2012
847 2.03.01 CV. PJL Pengadaan dan Pemasangan Lampu 027/288- 94.179.000,00 4.708.950,00 4230/LS/1.20 4.708.950,00 - -
Penerangan Jalan Umum di Kecamatan IV/Tamben/2012 .09.02.00/6.2/
Makarti Jaya Kabupaten Banyuasin Tanggal 14 2013
Agustus 2012
848 2.03.01 PT. CU Pengadaan dan Pemasangan Trafo di 027/292- 836.400.000,00 41.820.000,00 4335/LS/1.20 41.820.000,00 - -
Kecamatan Banyuasin III dan Kecamatan IV/Tamben/2012 .09.02.00/6.2/
Sembawa Kabupaten Banyuasin Tanggal 15 2013
Agustus 2012
849 2.03.01 PT. RaMa Pengadaan dan Pemasangan Lampu 027/293- 229.800.000,00 11.490.000,00 4238/LS/1.20 11.490.000,00 - -
Penerangan Jalan Umum di Batalyon Zeni IV/Tamben/2012 .09.02.00/6.2/
Konstruksi Kecamatan Banyuasin III Tanggal 15 2013
Kabupaten Banyuasin Agustus 2012
Halaman 77 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
850 2.03.01 PT. PuCi Pengadaan dan Pemasangan Lampu Jalan 027/520- 99.700.000,00 4.985.000,00 4233/LS/1.20 4.985.000,00 - -
Umum di desa Pengumbuk Kecamatan IV/Tamben/2012 .09.02.00/6.2/
Rantau Bayur Kabupaten Banyuasin Tanggal 16 2013
Oktober 2012
851 2.03.01 CV. TrTe Pengadaan Pembangkit Listrik Tenaga 027/287- 173.800.000,00 8.690.000,00 4229/LS/1.20 8.690.000,00 - -
Diesel (PLTD) di desa Pulau Parang IV/Tamben/2012 .09.02.00/6.2/
Kecamatan Rambutan kabupaten Banyuasin Tanggal 14 2013
Agustus 2012
852 2.03.01 PT. CU Pengadaaan dan Pemasangan Tiang Beton 027/517- 251.500.000,00 12.575.000,00 4237/LS/1.20 12.575.000,00 - -
Tegangan Menengah di Dusun IV desa IV/Tamben/2012 .09.02.00/6.2/
Teluk Betung Kecamatan Pulau Rimau Tanggal 16 2013
Kabupaten Banyuasin Agustus 2012
853 2.01.01 CV. Tlm Konstruksi (JUT) paket XVIII sepanjang 2 46/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Sumber Mukti Kec. Pulau Sapras/2013
Rimau tanggal 14 Juni
2013
854 2.01.01 CV. GJ Konstruksi (JUT) paket XIX sepanjang 2 47/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Wonosari Kec. Pulau Rimau Sapras/2013
tanggal 14 Juni
2013
855 2.01.01 CV. SeJa Konstruksi (JUT) paket XIII sepanjang 2 26/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Daya Murni Kec. Muara Sapras/2013
Sugihan tanggal 27 Mei
2013
856 2.01.01 CV. DM Konstruksi (JUT) paket XXIV sepanjang 2 28/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Daya Utama Kec. Muara Sapras/2013
Padang tanggal 27 Mei
2013
857 2.01.01 CV. RiP Konstruksi (JUT) paket XXVII sepanjang 2 30/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Tirta Jaya Kec. Muara Padang Sapras/2013
tanggal 27 Mei
2013
858 2.01.01 CV. ArPa Konstruksi (JUT) paket IX sepanjang 2 km 21/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Margo Rukun Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
859 2.01.01 CV. SmJ Konstruksi (JUT) paket VIII sepanjang 2 22/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Gilirang Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
860 2.01.01 CV. MIn Konstruksi (JUT) paket IV sepanjang 2 km 18/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Bangun Harjo Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
Halaman 78 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
861 2.01.01 Cv. MBK Konstruksi (JUT) paket V sepanjang 2 km 19/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Sugi Waras Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
862 2.01.01 CV. MBg Konstruksi (JUT) paket XII sepanjang 2 km 25/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Tirta Harja Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
863 2.01.01 CV. MbJ Konstruksi (JUT) paket XII sepanjang 2 km 24/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Beringin Agung Kec. Muara Sapras/2013
Sugihan tanggal 27 Mei
2013
864 2.01.01 Cv. TSu Konstruksi (JUT) paket X sepanjang 2 km 23/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Jalur Mulyo Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
865 2.01.01 CV. BJ Konstruksi (JUT) paket VII sepanjang 2 km 20/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
di Desa Daya Kusuma Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
866 2.01.01 CV. NN Konstruksi (JUT) paket XXV sepanjang 1 29/SPK/Pertanak- 89.397.000,00 - - 4.469.850,00 4.469.850,00
km di Desa Daya Makmur Kec. Muara Sapras/2013
Padang tanggal 27 Mei
2013
867 2.01.01 CV. Apr Konstruksi (JUT) paket XXV sepanjang 2 27/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
km di Desa Rejo Sari Kec. Muara Sugihan Sapras/2013
tanggal 27 Mei
2013
868 2.01.01 CV. MIn Konstruksi (JUT) sepanjang 5 km di Desa 63/SP/Pertanak- 486.321.000,00 - - 76.255.133,00 76.255.133,00 Realisasi Rp.
Tirto Harjo Kec. Muara Padang (Realisasi Sapras/VIII/2013 145.896.300 sisa
Pekerjaan 45,68%) tanggal 15 Rp. 340.424.700
Agustus 2013 dan tetapi dari laporan
107.c/SP/Pertana SKPD dikarenakan
k- pembayaran
Sapras/VIII/2013 dilakukan sesuai
tanggal 22 fisik dilapangan
Oktober 2013 sehingga Hutang
menjadi
Rp. 76.255.133
terdiri dari (Rp.
65.147.561 dan
pemeliharaan Rp.
11.107.572)
Halaman 79 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
869 2.01.01 CV. ArPa Konstruksi (JUT) sepanjang 3 km di Desa 67/SP/Pertanak- 295.069.000,00 - - 14.753.450,00 14.753.450,00
Sido Makmur Kec. Muara Sugihan Sapras/VIII/2013
tanggal 15
Agustus 2013
870 2.01.01 CV. VAA Konstruksi (JUT) sepanjang 2 km di Desa 52/SPK/Pertanak- 196.632.000,00 - - 9.831.600,00 9.831.600,00
Suka Mulya Kec. Tungkal Ilir Sapras/2013
tanggal 08 Juli
2013
871 2.01.01 CV. TDM Konstruksi (JUT) sepanjang 6,6 km di 62/SPK/Pertanak- 644.127.000,00 - - 32.206.350,00 32.206.350,00
Desa Teluk Tenggulang Kec. Tungkal Ilir Sapras/VIII/2013
tanggal 15
Agustus 2013
872 2.01.01 CV. JU Konstruksi (JUT) sepanjang 3,6 km di 73/SP/Pertanak- 353.913.000,00 - - 17.695.650,00 17.695.650,00
Desa Sri Menanti Kec. Tanjung Lago Sapras/VIII/2013
tanggal 15
Agustus 2013
873 2.01.01 CV. KuSu Konstruksi (JUT) sepanjang 5 km di Desa 72/SP/Pertanak- 483.861.000,00 - - 24.193.050,00 24.193.050,00
Purwosari Kec. Tanjung Lago Sapras/VIII/2013
tanggal 15
Agustus 2013
874 2.01.01 CV. KSK Konstruksi (JUT) sepanjang 3,5 km di 71/SP/Pertanak- 343.612.000,00 - - 17.180.600,00 17.180.600,00
Desa Mulya Sari Kec. Tanjung Lago Sapras/VIII/2013
tanggal 15
Agustus 2013
875 2.01.01 CV. PI Konstruksi (JUT) sepanjang 3,0 km di 61/SP/Pertanak- 292.968.000,00 - - 14.648.400,00 14.648.400,00
Desa Muara Baru Kec. Makartijaya Sapras/VIII/2013
tanggal 15
Agustus 2013
876 2.01.01 C, SH CV. Pembuatan tempat parkir mobil dan motor 83.c/SPK/Pertana 58.284.000,00 - - 2.914.200,00 2.914.200,00
GDP k-Sekret/2013
tanggal 30 Sept
2013
877 2.01.01 CV. KuSu Pekerjaan cor peninggian halaman kantor 83.a/SPK/Pertana 144.886.000,00 - - 7.244.300,00 7.244.300,00
k-Sekret/2013
tanggal 30 Sept
2013
878 2.01.01 CV. BH Pembuatan kandang ternak ayam di Kec 524/105.b/SPK/P 59.450.000,00 - - 2.972.500,00 2.972.500,00
Rambutan ertanak-PP/2013
tanggal 21
Oktober 2013
Halaman 80 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
879 2.01.01 CV. ANh Konstruksi (JUT) sepanjang 3,0 km di 68/SP/Pertanak- 294.045.000,00 - - 14.702.250,00 14.702.250,00
Desa Karang Sari Kec. Banyuasin II Sapras/VIII/2013
tanggal 15
Agustus 2013
880 2.01.01 CV. ANh Konstruksi (JUT) sepanjang 3,0 km di 65/SP/Pertanak- 291.691.000,00 - - 14.584.550,00 14.584.550,00
Desa Sri Agung Kec. Banyuasin II Sapras/VIII/2013
tanggal 15
Agustus 2013
881 2.01.01 CV. ANh Konstruksi (JUT) sepanjang 3,0 km di 70/SP/Pertanak- 292.157.000,00 - - 14.607.850,00 14.607.850,00
Desa Mekar Sari Kec. Banyuasin II Sapras/VIII/2013
tanggal 15
Agustus 2013
882 2.01.01 CV. DSk Konstruksi (JUT) sepanjang 3,0 km di 69/SP/Pertanak- 292.732.000,00 - - 14.636.600,00 14.636.600,00
Desa Jati Sari Kec. Banyuasin II Sapras/VIII/2013
tanggal 15
Agustus 2013
883 2.01.01 SkJ Konstruksi (JUT) sepanjang 3,0 km di 66/SP/Pertanak- 293.089.000,00 - - 14.654.450,00 14.654.450,00
Desa Upang Makmur Sapras/VIII/2013
tanggal 15
Agustus 2013
884 2.01.01 CV. JU Pekerjaan cor jalan masuk ke gedung dinas 83.b/SPK/Pertana 41.150.000,00 - - 2.057.500,00 2.057.500,00
k-Sekret/2013
tanggal 30 Sept
2013
885 2.01.01 CV. TJy Konstruksi (JUT) sepanjang 5,0 km di 64/SP/Pertanak- 485.450.000,00 - - 24.272.500,00 24.272.500,00
Desa Sri Katon Kec. Air Saleh Sapras/VIII/2013
tanggal 15
Agustus 2013
886 2.01.01 CV. Tlm Konstruksi (JUT) sepanjang 2,3 km di 60/SP/Pertanak- 184.352.000,00 - - 9.217.600,00 9.217.600,00
Desa Upang Mulya Kec. Makartijaya Sapras/VIII/2013
tanggal 15
Agustus 2013
887 2.01.01 CV. WC Pembangunan Mushollah Tahap II Kegiatan 521/25/SPK/Peta 36.653.000,00 1.832.650,00 - - 1.832.650,00
Pembangunan Gedung Kantor nak-Sekret/2012
Tgl. 25 Juni 2012
888 2.01.01 CV. ArPa Pengadaan Konstruksi JUT sepanjang 8 km 08/SP/Pertanak/I 196.374.000,00 9.818.700,00 0633/LS/1.20 9.818.700,00 - -
di Kec. Muara Sugihan X/2012 Tgl. 10 .09.02.00/6.2/
Sept 2012 2013
889 2.01.01 CV. MIn Pengadaan Konstruksi Bangunan Jaringan 09/SP/Pertanak/I 1.115.275.000,00 55.763.750,00 0634/LS/1.20 55.763.750,00 - -
Optimasi Lahan (OPL) seluas 450 Ha di X/2012 Tgl. 10 .09.02.00/6.2/
Kec. Muara Sugihan Sept 2012 2013
890 2.01.01 CV. AP Pembuatan Saluran/Parit Halaman Kantor 520/21/SPK/Perta 98.602.000,00 4.930.100,00 - 4.930.100,00
pada Dinas Pendidikan dan Peternakan nak-Sekret/2012
Keg. Pembangunan Gedung Kantor Tgl. 13 Juli 2012
Halaman 81 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
891 2.01.01 CV. SK Pembangunan Gedung UPTD pada Dinas 520/32/SPK/Perta 99.331.000,00 4.966.550,00 2858/LS/1.20 4.966.550,00 - -
Pertanian dan Peternakan Keg. nak-Sekret/2012 .09.02.00/6.2/
Pembangunan Gedung Kantor Tgl. 27 Agustus 2013
2012
892 2.01.01 PT. GIP Pengadaan Konstruksi Bangunan Jaringan 11/SP/Pertanak/2 373.884.000,00 18.694.200,00 1621/LS/1.20 18.694.200,00 - -
Optimasi Lahan (OPL) seluas 150 Ha di 012 Tgl. 12 sept .09.02.00/6.2/
Desa Sebubus Kec. Banyuasin I Keg. 2012 2013
Pengolahan Lahan dan Air
893 2.01.01 CV. BH Pembuatan Kandang Ternak Ayam di 521/53.b/SPK/Per 66.850.000,00 3.342.500,00 5134/LS/1.20 3.342.500,00 - -
kelompoktani Bina Bersama di Kec. tanak-PP/2012 .09.02.00/6.2/
Rambutan Keg. Pengembangan Agribisnis Tgl. 15 Oktober 2013
Peternakan 2012
894 2.01.01 CV. PI Pembuatan Kandang Ternak Ayam di 521/53.c/SPK/Per 66.850.000,00 3.342.500,00 3871/LS/1.20 3.342.500,00 - -
kelompoktani Mekar Sari di Kec. Betung tanak-PP/2012 .09.02.00/6.2/
Keg. Pengembangan Agribisnis Peternakan Tgl. 15 Oktober 2013
2012
895 2.01.01 CV. NB Pengadaan Konstruksi Jalan Usahatani 07/SA/Pertanak/I 171.553.000,00 8.577.650,00 - - 8.577.650,00
(JUT) Sepanjang 7 KM di Desa Borang X/2012 Tgl. 10
Kec. BA I Keg. Pengolahan Lahan dan Air Sept 2012
896 2.01.01 CV. JU Pembuatan Kandang Ternak Kambing di 524/247/SPK/Pert 40.000.000,00 2.000.000,00 - - 2.000.000,00
Kec. Tungkal Ilir Keg. Pengembangan anak-PP/2012
Agribisnis Peternakan Tgl. 05 Nov 2012
897 2.01.01 CV. NSI Pengadaan Konstruksi Jalan Usahatani 10/SP/Pertanak/I 122.466.000,00 6.123.300,00 - - 6.123.300,00
(JUT) sepanjang 5 KM di Kec. Rambutan X/2012 Tgl. 12
Keg. Pengolahan Lahan dan Air Sept 2012
843 1.21.01 CV. AiP Pembangunan Gedung Alsintan (Ds. 027/616.2/Baketp 198.420.000,00 9.921.000,00 7188/LS/1.20 9.921.000,00 - -
Sumber Mulya Kec. Muara Telang) an-II/2012 .09.02.00/6.2/
2013
844 1.21.01 CV. APe Pembangunan Gedung Alsintan (Ds. Mukti 027/616.1/Baketp 198.360.000,00 9.918.000,00 - - 9.918.000,00
Jaya Kec. Muara Telang) an-II/2012
845 1.21.01 CV. APK Pembangunan Gedung Alsintan (Ds. Rejo 027/615.1/Baketp 198.320.000,00 9.916.000,00 4162/LS/1.20 9.916.000,00 - -
Sari Kec. Muara Sugihan) an-II/2012 .09.02.00/6.2/
2013
Halaman 82 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
846 1.21.01 CV. BH Pembangunan Gedung Alsintan (Ds. Indra 027/615.6/Baketp 198.360.000,00 9.918.000,00 - - 9.918.000,00
Pura Kec. Muara Sugihan) an-II/2012
847 1.21.01 CV. BA Pembangunan Gedung Alsintan (Ds. Daya 027/616.4/Baketp 198.560.000,00 9.928.000,00 3928/LS/1.20 9.928.000,00 - -
Murni Kec. Muara Sugihan) an-II/2012 .09.02.00/6.2/
2013
848 1.21.01 CV. CZ Pembangunan Gedung Alsintan (Ds. Teluk 027/615.5/Baketp 193.360.000,00 9.668.000,00 7206/LS/1.20 9.668.000,00 - -
Tenggirik Kec. Banyuasin I) an-II/2012 .09.02.00/6.2/
2013
849 1.21.01 CV. CM Pembangunan Gedung Alsintan (Ds. Argo 027/615.3/Baketp 198.540.000,00 9.887.000,00 5137/LS/1.20.0 9.925.000,00 - (38.000,00) APBD Rp.
Mulyo Kec. Muara Sugihan) an-II/2012 9.02.00/6.2/20 9.887.000 Setelah
13 APBDP Rp.
9.925.000
(Keg.Penanganan
Pasca Panen dan
Pengolahan)
850 1.21.01 CV. CM Pembangunan Gedung Alsintan (Ds. Tirta 027/615.2/Baketp 198.500.000,00 9.965.000,00 5138/LS/1.20.0 9.927.000,00 - 38.000,00 APBD Rp.
Harja Kec. Muara Sugihan) an-II/2012 9.02.00/6.2/20 9.965.000 Setelah
13 APBDP
Rp.9.927.000
Kontrak No.
027/615.3/Baketpan-
II/12 (Keg.
Penanganan Pasca
Panen & Pengolahan)
851 1.21.01 CV. CJP Pembangunan Gedung Alsintan (Ds. 027/615.7/Baketp 198.300.000,00 9.915.000,00 3178/LS/1.20 9.915.000,00 - -
Sidoharjo Kec. Air Saleh) an-II/2012 .09.02.00/6.2/
2013
852 1.21.01 CV. Da Pembangunan Gedung Alsintan (Ds. 027/616.5/Baketp 198.640.000,00 9.932.000,00 3927/LS/1.20 9.932.000,00 - -
Ganesha Mukti Kec. Muara Sugihan) an-II/2012 .09.02.00/6.2/
2013
853 1.21.01 CV. HR Pembangunan Gedung Alsintan (Ds. 027/615/Baketpa 193.440.000,00 9.672.000,00 3611/LS/1.20 9.672.000,00 - -
Kelapa Dua Kec. Pulau Rimau) n-II/2012 .09.02.00/6.2/
2013
854 1.21.01 CV. KSD S Pembangunan Gedung Alsintan (Ds. 027/615.4/Baketp 198.500.000,00 9.925.000,00 7200/LS/1.20 9.925.000,00 - -
Timbul Jaya Kec. Muara Sugihan) an-II/2012 .09.02.00/6.2/
2013
855 1.21.01 CV. PL Pembangunan Gedung Alsintan (Kel. 027/615.9/Baketp 198.230.000,00 9.911.500,00 3069/LS/.1.2 9.911.500,00 - -
Makarti Jaya Kec. Makarti Jaya) an-II/2012 0.09.02.00/6.
2/2013
856 1.21.01 PT. PiKa Pembangunan Gedung Alsintan (Ds. Bayu 027/616.7/Baketp 193.400.000,00 9.670.000,00 3029/LS/1.20 9.670.000,00 - -
Urip Kec. Tanjung Lago) an-II/2012 .09.02.00/6.2/
2013
Halaman 83 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
857 1.21.01 CV. PK Pembangunan Gedung Alsintan (Ds. Sido 027/616/Baketpa 198.440.000,00 9.922.000,00 4469/LS/1.20 9.922.000,00 - -
Makmur Kec. Muara Sugihan) n-II/2012 .09.02.00/6.2/
2013
858 1.21.01 CV. RJK Pembangunan Gedung Alsintan (Ds. 027/616.8/Baketp 198.280.000,00 9.914.000,00 3458/LS/1.20 9.914.000,00 - -
Rimau Sungsang Banyuasin II) an-II/2012 .09.02.00/6.2/
2013
859 1.21.01 CV. RJK Pembangunan Gedung Alsintan (Ds. Jati 027/616.9/Baketp 198.280.000,00 9.914.000,00 3456/LS/1.20 9.914.000,00 - -
Sari Kec. Banyuasin II) an-II/2012 .09.02.00/6.2/
2013
860 1.21.01 CV. RiK Pembangunan Gedung Alsintan (Ds. 027/616.3/Baketp 198.440.000,00 9.922.000,00 3926/LS/1.20 9.922.000,00 - -
Margo Mulyo Kec. Muara Sugihan) an-II/2012 .09.02.00/6.2/
2013
861 1.21.01 CV. UM Pembangunan Gedung Alsintan (Ds. 027/616.6/Baketp 193.100.000,00 9.655.000,00 3028/LS/1.20 9.655.000,00 - -
Bangun Sari Kec. Tanjung Lago) an-II/2012 .09.02.00/6.2/
2013
862 1.21.01 CV. PI Pembangunan Gedung Alsintan (Ds. 027/615.8/Baketp 198.300.000,00 9.915.000,00 3870/LS/1.20 9.915.000,00 - -
Bintaran Kec. Air Saleh) an-II/2012 .09.02.00/6.2/
2013
864 2.04.01 CV. HBS Pekerjaan Pembangunan Lapangan Sepak 027/932/Parsenpo 342.927.000,00 - - 17.146.350,00 17.146.350,00
Bola Kampung Sawah Betung r-OR/2013
865 2.04.01 CV. SRM Pembangunan Lapangan Basket di 027/1145/Parsenp 367.450.000,00 18.372.500,00 - - 18.372.500,00
Lingkungan Komplek Rumah Dinas or-OR/2012
866 1.07.01 CV. BrPs Pembangunan Dermaga Sungai Pasar Suka 050.2/02/PDS1/D 269.162.000,00 13.458.100,00 2755/LS/1.20 13.458.100,00 - -
Mulya Kec. Tungkal Ilir ISHUBKOMINF .09.02.00/6.2/
O 2013
867 1.07.01 CV. CJP Pembangunan Dermaga Penghubung Desa 050.2/02/PDS2/D 371.600.000,00 18.580.000,00 3621/LS/1.20 18.580.000,00 - -
Banyu Urip Kec. Tanjung Lago ISHUBKOMINF .09.02.00/6.2/
O 2013
868 1.07.01 CV. AiP Pembangunan Dermaga Sungai Jalur 19 050.2/02/PDS3/D 269.892.000,00 13.494.600,00 3561//LS/1.2 13.494.600,00 - -
Kec. Tanjung Lago ISHUBKOMINF 0.09.02.00/6.
O 2/2013
Halaman 84 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
869 1.07.01 CV. AP Pembangunan Dermaga Sungai Upang 050.2/02/PDS4/D 269.442.000,00 13.472.100,00 4111/LS/1.20 13.472.100,00 - -
Karya Jalur 10 ISHUBKOMINF .09.02.00/6.2/
O 2013
870 1.07.01 CV. SK Pembangunan Dermaga Sungai Pasar Daya 050.2/02/PDS5/D 269.556.000,00 13.477.800,00 2815/LS/1.20 13.477.800,00 - -
Utama Kec. Muara Padang ISHUBKOMINF .09.02.00/6.2/
O 2013
871 1.07.01 CV. BrPs Pembangunan Dermaga Sungai Pasar Tirto 050.2/02/PDS6/D 269.468.000,00 13.473.400,00 2754/LS/1.20 13.473.400,00 - -
Mulyo ISHUBKOMINF .09.02.00/6.2/
O 2013
872 1.07.01 CV. LiSe Pembangunan Dermaga Sungai Pasar Teluk 050.2/02/PDS7/D 269.110.000,00 13.176.200,00 3685/LS/1.20 13.176.200,00 - -
Betung Kec. Pulau Rimau ISHUBKOMINF .09.02.00/6.2/
O 2013
873 1.07.01 CV. AP Kelanjutan Pembangunan Dermaga Sungai 050.2/02/LPDSB/ 72.830.000,00 3.641.500,00 4112/LS/1.20 3.641.500,00 - -
Bungin DISHUBKOMIN .09.02.00/6.2/
FO 2013
874 1.07.01 CV. GN Kelanjutan Pembangunan Dermaga Merah 050.2/02/LPDM 103.750.000,00 5.187.500,00 1919/LS/1.20 5.187.500,00 - -
Mata Tahap III M/DISHUBKOM .09.02.00/6.2/
INFO 2013
875 1.07.01 CV. PJ Rehabilitas Terminal Betung 050.2/02/PRTB/ 1.294.975.000,00 64.748.750,00 2623/LS/1.20 64.748.750,00 - -
DISHUBKOMIN .09.02.00/6.2/
FO 2013
876 1.07.01 CV. AP Lanjutan Pembangunan Terminal Tipe C di 050.2/02/LPTTC/ 198.960.000,00 9.948.000,00 3563/LS/1.20 9.948.000,00 - -
Simpang Lubuk Lancang DISHUBKOMIN .09.02.00/6.2/
FO 2013
877 1.13.01 CV. CG Pembangunan Gedung Gudang Buffer 027/240/PPK/Din 150.000.000,00 7.354.500,00 2753/LS/1.20 7.354.500,00 - -
Stock sos/2012 Tgl. 2 .09.02.00/6.2/
Sept 2012 2013
875 1.08.01 CV. SiB Taman Hijau di Kolam KTM Telang 027/159/PPK/BL 95.181.000,00 4.759.050,00 1945/LS/1.20 4.759.050,00 - -
Kecamatan Tanjung Lago Kab. Banyuasin H/2012 Tgl. 26 .09.02.00/6.2/
September 2012 2013
876 1.08.01 CV. API Kontruksi Keg. Pembangunan IPAL 027/150/PPK/BL 676.610.000,00 33.830.500,00 3204/LS/1.20 33.830.500,00 - -
Puskesmas Kec. Talang Kelapa dan H/2012 Tgl. 03 .09.02.00/6.2/
Puskesmas Kec. Makarti Jaya September 2012 2013
Halaman 85 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
877 1.12.01 CV. GMs Pembangunan Balai Penyuluh KB 027/46/SPK/BAP 338.050.000,00 16.902.500,00 3666/LS/1.20 16.902.500,00 - -
Kecamatan Darat EL-KB/2012 Tgl. .09.02.00/6.2/
09 Oktober 2012 2013
878 1.12.01 CV. SB Pembangunan Balai Penyuluh KB 027/44/SPK/BAP 227.350.000,00 11.367.500,00 3667/LS/1.20 11.367.500,00 - -
Kecamatan Perairan EL-KB/2012 Tgl. .09.02.00/6.2/
09 Oktober 2012 2013
879 1.12.01 CV. SB Pembangunan Papan Nama Beton dan WC 027/58.2/SPK/B 33.500.000,00 1.675.000,00 3622/LS/1.20 1.675.000,00 - -
Balai Penyuluh Kecamatan Perairan APEL-KB/2012 .09.02.00/6.2/
Tgl. 22 November 2013
2012
880 1.12.01 CV. GMs Pembangunan Papan Nama Beton dan WC 027/58.1/SPK/B 59.600.000,00 2.980.000,00 3620/LS/1.20 2.980.000,00 - -
Balai Penyuluh Kecamatan Darat APEL-KB/2012 .09.02.00/6.2/
Tgl. 22 2013
Nopember 2012
881 1.22.01 CV. PPM Kegiatan Pengadaan Taman dan 027/921/BPMPD. 174.000.000,00 - - 174.000.000,00 174.000.000,00
Pengecoran Halaman Parkir Gedung Kantor Set/2013
BPMPD Kabupaten Banyuasin Tahun
Anggaran 2013
882 1.22.01 CV. HS Penambahan Daya Listrik P1/2300- 027/864.1/BPMP 29.222.000,00 - - 29.222.000,00 29.222.000,00
33000VA D.Set/2013
883 1.22.01 Swakelola Pembangunan Kantor Kepala Desa Sebokor 460/018/BPMPD. 165.000.000,00 - - 49.500.000,00 49.500.000,00
Kepala Kec. Air Kumbang Set/2013
Desa
884 1.22.01 Swakelola Pembangunan Kantor Kepala Desa Karang 460/063/BPMPD. 170.000.000,00 - - 51.000.000,00 51.000.000,00
Kepala Anyar Kec. Muara Padang Set/2013
Desa
881 1.22.01 CV. LS Pembangunan Balai Desa Panca Mukti Kec. 027/769.1/BPMP 199.650.000,00 9.982.500,00 2207/LS/1.20 9.982.500,00 - -
Muara Telang D-SET/2012 Tgl .09.02.00/6.2/
18 Oktober 2012 2013
882 1.22.01 CV. PL Pembangunan Rehab Balai Desa Srikaton 027/768.2/BPMP 149.725.000,00 7.486.250,00 2208/LS/1.20 7.486.250,00 - -
Kec. Air Saleh D-SET/2012 Tgl. .09.02.00/6.2/
18 Oktober 2012 2013
883 1.20.09 CV. SM Pemeliharaan Rutin dan Berkala Gedung PPK/19/SPK/DPP 194.000.000,00 9.700.000,00 3208/LS/1.20 9.700.000,00 - -
Kantor KAD/2012 Tgl. .09.02.00/6.2/
22 Oktober 2012 2013
Halaman 86 dari 87
Kd Nama Saldo Awal 2013 Pembayaran Tahun Penambahan Saldo Akhir per 31
No. Pekerjaan No. Kontrak Nilai Kontrak No. SP2D KOREKSI KET
SKPD Rekanan (Hasil Audit BPK) 2013 Hutang Tahun 2013 Desember 2013
884 1.20.07 CV. PR Pemeliharaan Jalan 027/17/SPK/BKD- 44.322.900,00 2.216.145,00 1206/LS/1.20 2.216.145,00 - -
SEKR/2012 .09.02.00/6.2/
2013
885 1.20.07 CV. BuRa Pengadaan lain-lain Penghias Barang 027/18/SPK/BKD 169.730.000,00 8.486.500,00 1207/LS/1.20 8.486.500,00 - -
Rumah Tangga /2012 .09.02.00/6.2/
2013
Halaman 87 dari 87