No. Jenis Pekerjaan Vol./Sat H.Satuan Jumlah Total

1 2 3 4 5 6
I PEKERJAAN BONGKAR BANGUNAN
Pembobokan Dinding, plafon, genteng dan
1 1.00 Ls 35,000,000 35,000,000
kuda-kuda bagunan (Include pembuangan
material)
Sub total I 35,000,000 35,000,000
II PEK.KOLOM BETON (uk 150 x150 mm)
1 Beton kolom (Include Tulangan)
- Uk. 15 x 15 3.94 m3 750,000 2,953,125
Sub total II 2,953,125 2,953,125
III PEK.SLOOF BETON (uk 150 x150 mm)
1 Beton sloof (Include Tulangan)
- Uk. 15 x 15 4.50 m3 750,000 3,375,000
Sub total III 3,375,000 3,375,000
IV PEKERJAAN DINDING
1 Pas. Dinding bata ruangan 150.00 m2 240,000 36,000,000
2 Plester & aci 375.00 m2 80,000 30,000,000
Sub total IV 66,000,000 66,000,000
V PEKERJAAN LANTAI
1 Pas.krmk Ruang Tamu Uk. 30 x 30 28.10 m2 170,000 4,777,000
2 Pas.krmk Ruang Tidur 1 Uk. 30 x 30 22.50 m2 170,000 3,825,000
2
3 Pas.krmk Ruang Tidur 2 Uk. 30 x 30 29.06 m 170,000 4,940,625
4 Pas.krmk Ruang Dapur Uk. 30 x 30 7.50 m2 170,000 1,275,000
5 Pas.krmk Ruang Makan Uk.30 x 30 27.11 m2 170,000 4,609,125
2
6 Pas.krmk Teras Depan Uk.30 x 30 10.00 m 170,000 1,700,000
7 Pas.krmk KM/WC Uk.20 x 20 11.25 m2 120,000 1,350,000
Sub total V 22,476,750 22,476,750
VI PEKERJAAN PLAFOND
1 Pas. Rgk pipa holow + Pas Gypsum 135.53 m2 250,000 33,881,250
Sub total VI 33,881,250 33,881,250
VII PEK.INS.LISTRIK & Acc
A. Lantai Bawah
1 Instalasi lampu penerangan 10.00 titik 275,000 2,750,000
2 Instalasi stop kontak 10.00 titik 265,000 2,650,000
Sub total A 5,400,000 5,400,000
B Acc. Pekerjaan Listrik
1 Saklar tunggal broco 8.00 bh 19,500 156,000
2 Saklar ganda broco 8.00 bh 22,500 180,000
3 Stop kontak broco 8.00 bh 25,500 204,000
4 Lampu Biasa 8.00 bh 155,000 1,240,000
Sub total B 1,780,000 1,780,000