ID Task Name Start Finish 01 January Duration 21 February 11 April 01 June

18/02 11/03 01/04 22/04 13/05 03/06 24/06 15/07


1 PROJECT BANGUNAN MB2
2 A.Pekerjaan Kolom Lantai 1, Balok Lantai Wed 01/05/19 Tue 04/06/19 25 days
2 & Plat Lantai 2
3 A1. Pekerjaan Kolom Lantai 1 Wed 01/05/19 Fri 10/05/19 8 days
4 A.1.1 Material On Site (Pembesian, Wed 01/05/19 Thu 02/05/19 2 days
Scaffolding & Begisting)
5 A.1.2 Fabrikasi Pembesian Thu 02/05/19 Mon 06/05/19 3 days
6 A.1.3 Instal Pembesian Sun 05/05/19 Tue 07/05/19 3 days
7 A.1.4 Instal scaffolding & Pas.Dinding Mon 06/05/19 Thu 09/05/19 4 days

8 A.1.5 Pengecoran Tue 07/05/19 Fri 10/05/19 4 days


9 A2. Pekerjaan Balok Lantai 2 Thu 02/05/19 Thu 16/05/19 11 days
10 A.2.1 Material On Site (Pembesian, Thu 02/05/19 Fri 03/05/19 2 days
Scaffolding & Begisting)
11 A.2.2 Fabrikasi Pembesian Sun 05/05/19 Mon 06/05/19 2 days
12 A.2.3 Instal Pembesian Sat 11/05/19 Tue 14/05/19 3 days
13 A.2.4 Instal scaffolding & Pas.Dinding Sat 11/05/19 Thu 16/05/19 5 days

14 A3. Pekerjaan Plat Lantai 2 Thu 02/05/19 Wed 05/06/19 25 days


15 A.3.1 Material On Site (Pembesian, Thu 02/05/19 Fri 03/05/19 2 days
Scaffolding & Begisting)
16 A.3.2 Fabrikasi Pembesian Mon 06/05/19 Tue 07/05/19 2 days

Task Manual Task Deadline

Split Duration-only Baseline

Milestone Manual Summary Rollup Baseline Milestone

Project: RENCANA PERCEPATA Summary Manual Summary Baseline Summary


Date: Thu 02/05/19 Project Summary Start-only Progress

Inactive Task Finish-only Manual Progress

Inactive Milestone External Tasks

Inactive Summary External Milestone

Page 1
ID Task Name Start Finish 01 January Duration 21 February 11 April 01 June
18/02 11/03 01/04 22/04 13/05 03/06 24/06 15/07
17 A.3.3 Instal scaffolding & Pas.Dinding Thu 16/05/19 Tue 21/05/19 4 days

18 A.3.4 Instal Pembesian Tue 21/05/19 Thu 23/05/19 3 days


19 A.3.5 Pengecoran Balok & Lantai 2 Thu 23/05/19 Wed 05/06/19 10 days

Task Manual Task Deadline

Split Duration-only Baseline

Milestone Manual Summary Rollup Baseline Milestone

Project: RENCANA PERCEPATA Summary Manual Summary Baseline Summary


Date: Thu 02/05/19 Project Summary Start-only Progress

Inactive Task Finish-only Manual Progress

Inactive Milestone External Tasks

Inactive Summary External Milestone

Page 2