RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN GEDUNG WORKSHOP - BLK KOMUNITAS


PEMBERI TUGAS : KEMENTRIAN KETENAGAKERJAAN RI
KEJURUAN : ..................................................... (GROUP B)
TAHUN ANGGARAN : 2019

NO JENIS PEKERJAAN TOTAL HARGA

A PEKERJAAN PERSIAPAN 14,620,932.00


B PEKERJAAN PONDASI & TANAH 70,423,397.01
C PEKERJAAN STRUKTUR 90,697,888.86
D PEKERJAAN ATAP & PLAFOND 32,439,029.70
E PEKERJAAN PASANGAN 135,125,878.85
F PEKERJAAN KUSEN PINTU & JENDELA 43,536,102.19
G PEKERJAAN PENGECATAN 30,009,241.43
H PEKERJAAN PLUMBING & SANITARI 11,394,393.48
I PEKERJAAN LISTRIK 41,429,331.00
J LAIN - LAIN 10,600,000.00

JUMLAH 480,276,194.50
PPN 10% 48,027,619.45
DIBULATKAN 528,303,813.95