Anda di halaman 1dari 11

REKAPITULASI

RENCANA ANGGARAN BIAYA


(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

JUMLAH HARGA
NO. URAIAN PEKERJAAN
( Rp.)
1 2 3

I PEKERJAAN PERSIAPAN 19.900.000,00


Sub Total 19.900.000,00
II Lantai 1
A PEKERJAAN PONDASI TAPAK 9.766.031,52
B PEKERJAAN PONDASI SUMURAN 177.096.166,45
C PEKERJAAN PONDASI MENERUS 143.724.655,30
D PEKERJAAN BETON BERTULANG 468.781.972,66
E PEKERJAAN TANGGA 54.707.240,56
F PEKERJAAN TANAH & PENUTUP LANTAI 195.305.212,88
G PEKERJAAN PASANGAN DINDING & PLASTERAN 175.556.751,38
H PEKERJAAN KUSEN KAYU, DAUN PINTU & JENDELA, ALUMANIUM 37.932.458,02
I PEKERJAAN KACA TEMPERED 10mm 17.244.672,50
J PEKERJAAN PLAFOND 28.230.892,80
K PEKERJAAN LANTAI TERAS DEPAN DAN BELAKANG 85.969.966,28
L PEKERJAAN PENGECATAN 34.970.656,69
M PEKERJAAN LISTRIK 34.787.900,00
N PEKERJAAN PENGANTUNG DAN KUNCI 47.479.600,00
O PEKERJAAN SANITASI 57.249.152,73
P PEKERJAAN KOLAM RENANG 143.648.169,68
Q PEKERJAAN DRAINASE 19.255.073,25
R PEKERJAAN PAGAR RUMAH 98.202.536,55
Sub Total 1.829.909.109,24
III Lantai 2
A PEKERJAAN BETON BERTULANG 237.895.844,31
B PEKERJAAN PLAT LANTAI 60.016.969,46
C PEKERJAAN TANGGA 51.724.338,38
D PEKERJAAN PENUTUP LANTAI 67.625.134,37
E PEKERJAAN PASANGAN DINDING & PLASTERAN 114.651.024,28
F PEKERJAAN KUSEN KAYU, DAUN PINTU & JENDELA, ALUMANIUM 43.997.043,62
G PEKERJAAN KACA TEMPERED 10 mm 89.580.293,00
H PEKERJAAN ATAP DAN PLAFOND 457.268.496,01
I PEKERJAAN PENGECATAN 26.813.641,50
J PEKERJAAN LISTRIK 14.435.400,00
K PEKERJAAN PENGANTUNG 34.178.700,00
L PEKERJAAN SANITASI 41.450.664,73
M PEKERJAAN LAIN-LAIN 221.588.575,96

Sub Total 1.461.226.125,63

Sub Total I+II+III 3.311.035.234,88


Dibulatkan 3.311.030.000,00

Terbilang :
Tiga Milyar Tiga Ratus Sebelas Juta Tiga Puluh Ribu Rupiah
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN
1 Pemasangan Bouwplank 1,00 Ls Taksir 4.900.000,00 4.900.000,00
2 Sewa Scafolding 1,00 Ls Taksir 5.000.000,00 5.000.000,00
3 Bedeng Pekerja + MCK 1,00 Unit Taksir 10.000.000,00 10.000.000,00
Sub Total 19.900.000,00
II Lantai 1
A PEKERJAAN PONDASI TAPAK
a Pondasi Tapak Type 1
1 Galian Tanah Pondasi Tapak TP1 Menggunakan Alat Berat 48,96 m³ A.2.3.1.2.b 106.269,90 5.202.974,30
2 Urugan Kembali 3/4 Galian TP 1 36,72 m³ A. 2.3.1.9 48.026,00 1.763.514,72
3 Urugan Pasir Bawah Pondasi Tapak TP 1 1,44 m³ A. 2.3.1.11 140.131,20 201.788,93
4 Aan Stamping TP 1 4,32 m³ A. 3.2.1.9 398.101,11 1.719.796,80
b Pondasi Tapak Type 2
1 Galian Tanah Pondasi Tapak TP2 Menggunakan Alat Berat 2,45 m³ A.2.3.1.2.b 106.269,90 260.148,72
2 Urugan Kembali 3/4 Galian TP 2 1,84 m³ A. 2.3.1.9 48.026,00 88.175,74
3 Urugan Pasir Bawah Pondasi Tapak TP 2 0,07 m³ A. 2.3.1.11 140.131,20 10.089,45
4 Aan Stamping TP 2 0,14 m³ A. 3.2.1.9 398.101,11 57.326,56
c Pondasi Tapak Type 3
1 Galian Tanah Pondasi Tapak TP 3 Menggunakan Alat Berat 2,05 m³ A.2.3.1.2.b 106.269,90 217.640,76
2 Urugan Kembali 3/4 Galian TP 3 1,54 m³ A. 2.3.1.9 48.026,00 73.767,94
3 Urugan Pasir Bawah Pondasi Tapak TP 3 0,13 m³ A. 2.3.1.11 140.131,20 17.936,79
4 Aan Stamping TP 3 0,38 m³ A. 3.2.1.9 398.101,11 152.870,83
Sub Total 9.766.031,52
B PEKERJAAN PONDASI SUMURAN
1 Galian Tanah Pondasi Sumuran Menggunakan Alat Berat 317,52 m³ A.2.3.1.2.b 106.269,90 33.742.818,65
2 Urugan Kembali Galian 79,38 m³ A. 2.3.1.9 48.026,00 3.812.303,88
3 Urugan Pasir Bawah Pondasi 1,51 m³ A. 2.3.1.11 140.131,20 211.878,37
4 Pek. Batu Kosong 3,02 m³ A. 3.2.1.9 398.101,11 1.203.857,76
5 Pek. Pipa Beton Diameter 60mm 220,50 m Taksir 350.000,00 77.175.000,00
6 Cor Cyclope 62,37 m³ A. 4.1.1.5 976.011,03 60.873.807,79
7 Pek. Besi Angker 4,50 m Taksir 17.000,00 76.500,00
Sub Total 177.096.166,45
C PEKERJAAN PONDASI MENERUS
1 Galian Tanah Pondasi Menerus Menggunakan Alat Berat 84,20 m³ A.2.3.1.2.b 106.269,90 8.947.585,52
2 Urugan Kembali 1/4 Galian 21,05 m³ A. 2.3.1.9 48.026,00 1.010.908,88
3 Urugan Pasir Bawah Pondasi 9,22 m³ A. 2.3.1.11 140.131,20 1.292.273,11
4 Pek. Batu Kosong 37,99 m³ A. 3.2.1.9 398.101,11 15.123.319,75
5 Pek. Batu Gunung 132,13 m³ A. 3.2.1.1 878.916,23 116.135.068,04
6 Pek. Besi Angker 71,50 m³ Taksir 17.000,00 1.215.500,00
Sub Total 143.724.655,30
D PEKERJAAN BETON BERTULANG
a Pekerjaan Tapak
1 Tapak Type 1 5,00 m³ Supl-T.1 4.313.806,00 21.569.030,00
2 Stick Type 1 5,15 m³ Supl-T.1' 7.313.255,00 37.626.696,98
3 Tapak Type 2 0,25 m³ Supl-T.2 4.313.806,00 1.078.451,50
4 Stick Type 2 0,26 m³ Supl-T.2' 7.313.255,00 1.881.334,85
5 Tapak Type 3 0,70 m³ Supl-T.3 5.562.918,00 3.894.042,60
6 Stick Type 3 0,10 m³ Supl-T.3' 5.873.497,00 563.855,71
b Pekerjaan Sloof
1 Sloof 30 x 45 12,32 m³ Supl-S.1 4.765.976,00 58.727.666,92
2 Sloof 20 x 25 3,63 m³ Supl-S.2 4.174.546,00 15.132.729,25
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

c PEKERJAAN
Pekerjaan PERSIAPAN
Kolom
1 Kolom Uk 35 x 35 12,32 m³ Supl-K.1 7.303.236,00 89.992.482,38
2 Kolom Uk 35 x 35 0,64 m³ Supl-K.2 7.303.236,00 4.652.161,33
3 Kolom Uk 20 x 20 0,64 m³ Supl-K.3 5.873.497,00 3.759.038,08
4 Kolom Praktis Uk 15 x 15 5,95 m³ Supl-Kp 7.892.846,00 46.991.834,55
d Pekerjaan Balok Latai
1 Balok Latai Uk 15 x 15 1,84 m³ Supl-BL.1 5.255.864,00 9.688.791,09
2 Balok Latai Uk 10 x 15 0,13 m³ Supl-BL.2 7.137.382,00 920.722,28
e Pekerjaan Balok Lantai
1 Balok Lantai Uk 25 x 50 17,12 m³ Supl-B.1 7.387.500,00 126.464.765,63
2 Balok Lantai Uk 20 x 35 4,24 m³ Supl-B.2 7.327.612,00 31.032.436,82
3 Balok Lantai Uk 15 x 25 1,13 m³ Supl-B.3 7.014.472,00 7.901.802,71
f Pekerjaan Ring Balok
1 Ring Balok Uk 15 x 15 0,45 m³ Supl-RB.3 6.931.119,00 3.114.325,04
2 Ring Balok Uk 10 x 20 0,54 m³ Supl-RB.4 6.960.156,00 3.789.804,94
Sub Total 468.781.972,66
E PEKERJAAN TANGGA
Tangga 1
1 Panjang Plat Tangga 0,21 m³ Supl-PT 5.579.485,00 1.171.691,85
2 Cor Anak Tangga 1,02 m³ Supl-PT 5.579.485,00 5.698.796,71
3 Baja Komposit 'I' KC 800.500.5.5 34,16 m¹ Taksir 250.000,00 8.540.000,00
4 Reling kaca Tempered Tebal 10mm 18,50 m² Taksir 935.000,00 17.296.752,00
5 Assesoris Ralling 11,00 Unit Taksir 2.000.000,00 22.000.000,00
Sub Total 54.707.240,56
F PEKERJAAN TANAH & PENUTUP LANTAI
1 Timbunan Tanah 361,89 m³ A. 2.3.1.11a 107.659,20 38.961.286,67
2 Pasir Urug 47,47 m³ A. 2.3.1.11 140.131,20 6.652.674,07
3 Rabat Beton 15,82 m³ A. 4.1.1.7 1.045.360,33 16.542.691,34
4 Lantai granite 80 x 80 "MAGNUM" 190,23 m² A. 4.4.3.13a 318.888,41 60.661.312,17
5 Lantai Keramik 50 x 50 (MOTIF BIASA) 25,04 m² A. 4.4.3.34.a 284.354,62 7.120.125,92
6 Lantai Keramik KM 50 x 50 (MOTIF KAYU) 30,25 m² A. 4.4.3.34.a 284.354,62 8.600.561,37
7 Lantai Kayu Kolam Renang "Kelas 1" 28,39 m² A. 4.5.1.6 1.282.531,36 36.414.784,65
8 Rangka Lantai Kayu Kolam Renang 28,39 m² A. 4.6.1.20 178.638,35 5.072.060,81
8 Lantai Parquet 24,91 m² A. 4.4.3.46 347.438,85 8.655.188,17
9 Keramik Anak Tangga (MOTIF KAYU) 20,99 m² A. 4.4.3.34.a 284.354,62 5.969.058,42
10 Acian 18,98 m² A. 4.4.2.27 34.526,73 655.469,28

Sub Total 195.305.212,88


G PEKERJAAN PASANGAN DINDING & PLASTERAN
1 Pas ½ Bata 1:2 102,29 m² A. 4.4.1.7 142.293,15 14.555.344,56
2 Plasteran Pas ½ Bata 1:2 204,58 m² A. 4.4.2.2 64.038,16 13.101.087,52
3 Pas ½ Bata 1:4 424,09 m² A. 4.4.1.9 130.790,96 55.467.623,21
4 Plasteran ½ Bata 1:4 848,19 m² A. 4.4.2.4 58.111,48 49.289.426,83
5 Diding Keramik KM uk 30 x 60 52,00 m² A. 4.4.3.54.a 195.590,75 10.170.719,13
6 Diding Granit Uk 80 x 80 19,06 m² A. 4.4.3.13a 318.888,41 6.076.823,55
7 Plasteran Kolom 121,05 m² A. 4.4.2.2 64.038,16 7.751.755,62
8 Plasteran Balok 164,34 m² A. 4.4.2.2 64.038,16 10.524.031,74
9 Plasteran Ring Balok 17,15 m² A. 4.4.2.2 64.038,16 1.098.510,65
10 Pas Batu Alam Kolom Lingkaran + Terpasang 8,17 m² Taksir 300.000,00 2.451.428,57
11 Pas Batu Alam Dinding Kol. Renang + Terpasang 16,90 m² Taksir 300.000,00 5.070.000,00

Sub Total 175.556.751,38


RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

H PERSIAPAN
PEKERJAAN KUSEN KAYU, DAUN PINTU & JENDELA, ALUMANIUM
Pekerjaan Kayu & Kaca 5mm
1 Pintu PG
Kosen Pintu 0,08 m³ A. 4.6.1.1 11.324.566,00 917.289,85
Daun Pintu 8,91 m² A. 4.6.1.5 750.425,50 6.686.291,21
Kaca Pintu 1,35 m² A. 4.6.2.17 161.220,36 217.647,48
2 Pintu P1
- Kosen Pintu 0,04 m³ A. 4.6.1.1 11.324.566,00 484.125,20
- Daun Pintu 1,37 m² A. 4.6.1.5 750.425,50 1.024.330,81
3 Pintu P2
- Kosen Pintu 0,12 m³ A. 4.6.1.1 11.324.566,00 1.375.934,77
- Daun Pintu 5,67 m² A. 4.6.1.5 750.425,50 4.254.912,59
4 Pintu P3
- Kosen Pintu 0,16 m³ A. 4.6.1.1 11.324.566,00 1.766.632,30
- Daun Pintu 6,72 m² A. 4.6.1.5 750.425,50 5.042.859,36
5 Pintu P5
- Kosen Pintu 0,05 m³ A. 4.6.1.1 11.324.566,00 594.539,72
- Daun Pintu 0,88 m² A. 4.6.1.5 750.425,50 657.372,74
- Kaca Pintu 4,75 m² A. 4.6.2.17 161.220,36 766.119,13
6 Pintu P6
- Kosen Pintu 0,10 m³ A. 4.6.1.1 11.324.566,00 1.104.145,19
- Daun Pintu 3,10 m² A. 4.6.1.5 750.425,50 2.323.317,35
- Kaca Pintu 9,50 m² A. 4.6.2.17 161.220,36 1.532.238,26
7 Jendela J1
- Kosen Jendela 0,05 m³ A. 4.6.1.1 11.324.566,00 586.046,29
- Daun Jendela 0,61 m² A. 4.6.1.6 538.778,90 331.025,76
- Kaca Jendela 1,77 m² A. 4.6.2.17 161.220,36 284.779,64
8 Jendela J2
Kosen Jendela 0,13 m³ A. 4.6.1.1 11.324.566,00 1.452.375,59
Daun Jendela 1,34 m² A. 4.6.1.6 538.778,90 721.532,70
Kaca Jendela 3,57 m² A. 4.6.2.17 161.220,36 575.750,14
9 Jendela J3
Kosen Jendela 0,03 m³ A. 4.6.1.1 11.324.566,00 373.710,68
Daun Jendela 0,22 m² A. 4.6.1.6 538.778,90 120.255,45
Kaca Jendela 0,60 m² A. 4.6.2.17 161.220,36 95.958,36
10 Jendela J4
Kosen Jendela 0,04 m³ A. 4.6.1.1 11.324.566,00 433.164,65
Daun Jendela 0,34 m² A. 4.6.1.6 538.778,90 181.029,71
Kaca Jendela 0,32 m² A. 4.6.2.17 161.220,36 51.074,61
11 Ventelasi V1
Kosen Ventelasi 0,02 m³ A. 4.6.1.1 11.324.566,00 280.283,01
Daun Ventelasi 0,17 m² A. 4.6.1.6 538.778,90 89.437,30
Kaca Ventelasi 0,18 m² A. 4.6.2.17 161.220,36 28.439,27
12 Ventelasi V2
Kosen Ventelasi 0,02 m³ A. 4.6.1.1 11.324.566,00 203.842,19
Daun Ventelsi 0,12 m² A. 4.6.1.6 538.778,90 62.067,33
Kaca Jendela 0,09 m² A. 4.6.2.17 161.220,36 13.929,44
Pekerjaan Alumanium
1 Pintu P4
- Kosen Pintu Alumanium 3,00 Bh Taksir 1.100.000,00 3.300.000,00
Sub Total 37.932.458,02
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

I PERSIAPAN
PEKERJAAN KACA TEMPERED 10mm
1 Kaca Tempered 10 mm (K1) 5,44 m² Taksir 935.000,00 5.082.660,00
2 Kaca Tempered 10 mm (K2) 11,07 m² Taksir 935.000,00 10.352.787,50
3 Pintu Kaca Tempered (P4) 1,94 m³ Taksir 935.000,00 1.809.225,00

Sub Total 17.244.672,50


J PEKERJAAN PLAFOND
1 Plafond Gipsum + Terpasang 160,40 m² Taksir 176.000,00 28.230.892,80
-
Sub Total 28.230.892,80
K PEKERJAAN LANTAI TERAS DEPAN DAN BELAKANG
1 Galian Tanah Menggunakan Alat Berat 58,56 m³ A.2.3.1.2.b 106.269,90 6.223.324,75
2 Urugan Pasir Bawah Pondasi 0,18 m³ A. 2.3.1.11 140.131,20 25.381,26
3 Aan Stamping 3,62 m³ A. 3.2.1.9 398.101,11 1.442.121,27
4 Pas ½ Bata 1:2 160,04 m² A. 4.4.1.7 142.293,15 22.772.653,24
5 Plasteran Pas ½ Bata 1:2 320,08 m² A. 4.4.2.2 64.038,16 20.497.386,51
6 Pasir Bawah Lantai 10,70 m³ A. 2.3.1.11 140.131,20 1.499.457,79
7 Rabat Beton 3,57 m³ A. 4.1.1.7 1.045.360,33 3.728.586,00
8 Granit 80 x 80 "MAGNUM" 14,11 m² A. 4.4.3.13a 318.888,41 4.500.892,99
9 Finising Batu Kacang + Terpasang 61,22 m² Taksir 250.000,00 15.305.475,00
11 Lantai Keramik 50 x 50 (MOTIF BIASA) 32,44 m² A. 4.4.3.34.a 284.354,62 9.224.242,05
12 Acian Motif 21,74 m² A. 4.4.2.27 34.526,73 750.445,41
-
Sub Total 85.969.966,28
L PEKERJAAN PENGECATAN
1 Pengecatan Dinding Tembok 848,19 m² A. 4.7.1.10 36.464,75 30.928.938,95
2 Pengecatan Kosen 23,71 m² A. 4.7.1.4 48.947,80 1.160.552,34
3 Pengecatan Daun Pintu 53,27 m² A. 4.7.1.4 48.947,80 2.607.645,10
4 Pengecatan Daun Jendela 5,03 m² A. 4.7.1.4 48.947,80 245.992,06
5 Pengecatan Daun Ventelasi 0,56 m² A. 4.7.1.4 48.947,80 27.528,24
-
Sub Total 34.970.656,69
M PEKERJAAN LISTRIK
1 Box MCB + Terpasang 1,00 Unit Taksir 500.000,00 500.000,00
2 Saklar Ganda "Panasonic" 15,00 Unit Taksir 30.500,00 457.500,00
3 Saklar Tunggal "Panasonic" 11,00 Unit Taksir 26.000,00 286.000,00
4 Stop Kontak Ganda "Panasonic" 16,00 Unit Taksir 25.500,00 408.000,00
5 Lampu DL 20 Watt "Hannock" 48,00 Unit Taksir 165.000,00 7.920.000,00
6 Lampu T4 P.80cm, 24 Watt (Kuning Matahari) 34,00 Unit Taksir 43.000,00 1.462.000,00
7 Lampu T4 P.40cm 20 Watt (Kuning Matahari) 2,00 Unit Taksir 35.000,00 70.000,00
8 Lampu Tangga BRDL 5 Watt "Luxmenn TR24 BR" 7,00 Unit Taksir 57.200,00 400.400,00
9 Lampu Gantung LED 1,00 Unit -
10 Lampu Taman "TE-72-BLACK" 6,00 Unit Taksir 385.000,00 2.310.000,00
11 Spotlight "VACOLUX 5 Waat" 12,00 Unit Taksir 70.000,00 840.000,00
12 Pemasangan Titik Lampu 110,00 Titik Taksir 90.000,00 9.900.000,00
13 Pemasukan Arus + Terpasang 1,00 Unit Taksir 6.500.000,00 6.500.000,00
14 Kipas Angin Plafond "PANASONIC EY153 WP 56" 3,00 Unit Taksir 828.000,00 2.484.000,00
15 Kabel / Wire 5,00 Glg Taksir 250.000,00 1.250.000,00

-
Sub Total 34.787.900,00
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

N PERSIAPAN DAN KUNCI


PEKERJAAN PENGANTUNG
1 Handle Besar "Vernochi" + Terpasang 2,00 Bh Taksir 357.500,00 715.000,00
2 Kunci Handle Besar "Dekson" + Terpasang 10,00 Bh Taksir 260.000,00 2.600.000,00
3 Handle Kecil Minimalis + Kunci "Dumont" + 10,00 Bh Taksir 234.000,00 2.340.000,00
Terpasang
4 Engsel pintu 4 "SES" + Terpasang 32,00 Bh Taksir 97.500,00 3.120.000,00
5 Engsel Jendela "SES" + Terpasang 36,00 Bh Taksir 78.000,00 2.808.000,00
6 Grendel jendela "SES" + Terpasang 18,00 Bh Taksir 84.500,00 1.521.000,00
7 Hak Angin Jendela "Dekson" + Terpasang 36,00 Bh Taksir 44.200,00 1.591.200,00
8 Rail + Assoris Pintu Sliding "UNIKEY" +Terpasang 1,00 Unit Taksir 1.878.800,00 1.878.800,00
9 Rail + Assoris Pintu Lipat "UNIKEY" + Terpasang 2,00 Unit Taksir 4.814.480,00 9.628.960,00
10 Rail + Assoris Pintu Garasi "UNIKEY" + Terpasang 1,00 Unit Taksir 11.376.640,00 11.376.640,00
11 Klam Spider 6,00 Bh Taksir 1.650.000,00 9.900.000,00
-
Sub Total 47.479.600,00
O PEKERJAAN SANITASI
1 Pek. Septitank -
a Galian 9,69 m³ A. 2.3.1.2 81.189,90 786.822,36
b Pek. Lantai Beton K-200 0,64 m³ A. 4.1.1.6 1.015.851,33 649.104,62
c Pasir Alas 0,64 m³ A. 2.3.1.11 140.131,20 89.540,47
d Trasram 6,53 m² A. 4.4.1.7 142.293,15 929.345,05
e Cor Sloof Uk 12x14 0,03 m³ A. 4.1.1.6 1.015.851,33 35.497,91
f Pek. Pembesian Sloof 3,69 m³ A. 4.1.1.17b. 11.683,44 43.057,89
g Pek. Bekesting Sloof 0,29 m² A. 4.1.1.21 165.637,23 48.233,56
2 Pek. Resapan
a Galian 5,28 m³ A. 2.3.1.1 66.198,00 349.525,44
b Ijuk 10,80 m² Taksir 50.000,00 540.000,00
c Batu mangga 0,91 m³ A. 3.2.1.9 398.101,11 363.396,25
d Kerikil 1,30 m³ A. 3.2.1.9 398.101,11 516.610,24
e Tanah urug 1,06 m³ A. 2.3.1.11a 107.659,20 113.688,12

3 Kloset Duduk "TOTO+SPLASH" 2,00 Unit A. 5.1.1.1 3.903.560,10 7.807.120,20


4 Kloset Jongkok 1,00 Unit A. 5.1.1.3 559.075,00 559.075,00
5 Bak Viber 30 lt 2,00 bh Taksir 265.650,00 531.300,00
6 Pas. Kran 1/2 inc "TL-020 STAINLESS" 1,00 bh Taksir 173.250,00 173.250,00
7 Pas. Kran Bethub "STAINLESS WASER-MBT-S610" 1,00 bh Taksir 723.000,00 723.000,00
8 Gantungan Handuk "DOUBEL SS 70 - VLTP62" 2,00 Bh Taksir 367.400,00 734.800,00
9 Bathtub "MERIDIAN" 1,00 bh Taksir 5.205.200,00 5.205.200,00
10 Pas Wastafel "TOTO L38 WHITE" 1,00 bh A. 5.1.1.5 1.094.610,00 1.094.610,00
11 Pas. Floor Drain Stailess Steel 3,00 bh A. 5.1.1.14 144.525,70 433.577,10
12 Shower "WASER-SHS-833" 3,00 bh Taksir 478.170,00 1.434.510,00
13 Sink Bak Cuci Piring + Kran " GLOBAL BCP DOUB" 2,00 bh Taksir 4.781.700,00 9.563.400,00
14 Water Tank "Pinguin" 1,00 Unit Taksir 4.195.400,00 4.195.400,00
15 Waser Pompa "CELUP PC-280E" 1,00 Unit Taksir 1.625.250,00 1.625.250,00
16 Plampung Water Tank "TIP TOP 1/2" 1,00 bh Taksir 57.200,00 57.200,00
17 Pipa Air Bersih Uk 1/2" 112,73 m A. 5.1.1.25 43.484,10 4.901.962,59
18 Pipa Air Kotor Uk 3" 76,25 m A. 5.1.1.31 180.258,05 13.744.675,93
Sub Total 57.249.152,73
P PEKERJAAN KOLAM RENANG
1 Pek. Galian Tanah 73,28 m³ A.2.3.1.2.b 106.269,90 7.787.104,92
2 Pek. Batu Kosong 6,42 m³ A. 3.2.1.9 398.101,11 2.554.250,56
3 Pek. Lantai Beton Saluran K-275 6,18 m³ A. 4.1.1.9 1.099.048,12 6.792.183,34
4 Pek. Pembesian Plat Lantai Beton 673,06 m³ A. 4.1.1.17b. 11.683,44 7.863.598,61
5 Pek. Dinding Beton t= 20, K-275 6,03 m³ A. 4.1.1.9 1.099.048,12 6.631.876,18
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

6 PEKERJAAN
Pek. PERSIAPAN
Pembesian Plat Beton Dinding 657,17 m³ A. 4.1.1.17b. 11.683,44 7.678.004,22
7 Pek. Bekisting Dinding Saluran 2x Pakai 30,17 m³ A. 4.1.1.25 185.857,10 5.607.494,56
8 Pek. Dinding Beton t= 15, K-275 0,87 m³ A. 4.1.1.9 1.099.048,12 951.226,15
9 Pek. Pembesian Plat Beton Dinding 77,40 m³ A. 4.1.1.17b. 11.683,44 904.345,54
10 Pek. Bekisting Dinding Saluran 2x Pakai 5,77 m³ A. 4.1.1.25 185.857,10 1.072.395,47
11 Pek. Dinding Keramik 41,71 m² A. 4.4.3.34.a 284.354,62 11.860.715,52
12 Pek. Lantai Keramik 35,47 m² A. 4.4.3.34.a 284.354,62 10.085.944,60
13 Water Proofing 77,18 m² Taksir 50.000,00 3.859.030,00
14 Plambing, Elektrikcal + Assesoris Kolam Renang + 1,00 Unit Taksir 70.000.000,00 70.000.000,00
Terpasang
Sub Total 143.648.169,68
Q PEKERJAAN DRAINASE
a Drain Kolam -
1 Pek. Galian Tanah 1,71 m³ A. 2.3.1.2 81.189,90 139.010,10
2 Pek. Dinding Beton Saluran K-200 0,44 m³ A. 4.1.1.6 1.015.851,33 449.940,87
3 Pek. Pembesian Plat Beton Dinding 30,83 m³ A. 4.1.1.17b. 11.683,44 360.146,22
4 Pek. Bekisting Dinding Saluran 2x Pakai 5,54 m² Taksir 76.875,00 425.618,44
5 Pek. Lantai Beton Saluran K-200 0,51 m³ A. 4.1.1.6 1.015.851,33 521.790,00
6 Pek. Pembesian Plat Lantai Beton 46,76 m³ A. 4.1.1.17b. 11.683,44 546.368,17
7 Pek. Plasteran 5,54 m² A. 4.4.1.7 142.293,15 787.806,05
b Bak Kontrol
1 Pek. Galian Tanah 0,64 m³ A. 2.3.1.2 81.189,90 51.961,54
2 Pek. Urugan Pasir Bawah Saluran t. 5 cm 0,05 m³ A. 2.3.1.11 140.131,20 7.006,56
3 Pek. Dinding Beton Saluran K-200 0,15 m³ A. 4.1.1.6 1.015.851,33 152.784,04
4 Pek. Pembesian Plat Beton Dinding 10,47 m³ A. 4.1.1.17b. 11.683,44 122.292,95
5 Pek. Bekisting Dinding Saluran 2x Pakai 0,94 m² Taksir 76.875,00 72.262,50
6 Pek. Lantai Beton Saluran K-200 0,06 m³ A. 4.1.1.6 1.015.851,33 60.951,08
7 Pek. Pembesian Plat Lantai Beton 5,46 m³ A. 4.1.1.17b. 11.683,44 63.822,09
8 Pek. Plat Beton Atas Saluran K-200 0,06 m³ A. 4.1.1.6 1.015.851,33 60.951,08
9 Pek. Pembesian Plat Beton Atas Saluran 5,46 m³ A. 4.1.1.17b. 11.683,44 63.822,09
10 Pek. Bekisting Atas Saluran 2x Pakai 0,50 m³ A. 4.1.1.24 464.719,20 232.359,60
11 Pek. Plasteran 1:2 0,94 m² A. 4.4.1.7 142.293,15 133.755,56
c Saluran Utama
1 Pek. Galian Tanah 7,58 m³ A. 2.3.1.2 81.189,90 615.114,98
2 Pek. Urugan Pasir Bawah Saluran t. 5 cm 0,69 m³ A. 2.3.1.11 140.131,20 96.515,36
3 Pek. Dinding Beton Saluran K-200 1,68 m³ A. 4.1.1.6 1.015.851,33 1.701.591,61
4 Pek. Pembesian Plat Beton Dinding 116,58 m³ A. 4.1.1.17b. 11.683,44 1.362.005,18
5 Pek. Bekisting Dinding Saluran 2x Pakai 20,94 m² Taksir 76.875,00 1.609.608,75
6 Pek. Lantai Beton Saluran K-200 0,83 m³ A. 4.1.1.6 1.015.851,33 839.601,12
7 Pek. Pembesian Plat Lantai Beton 75,25 m³ A. 4.1.1.17b. 11.683,44 879.149,32
8 Pek. Plat Beton Atas Saluran K-200 0,83 m³ A. 4.1.1.6 1.015.851,33 839.601,12
9 Pek. Pembesian Plat Beton Atas Saluran 75,25 m³ A. 4.1.1.17b. 11.683,44 879.149,32
10 Pek. Bekisting Atas Saluran 2x Pakai 6,89 m³ A. 4.1.1.24 464.719,20 3.200.753,49
11 Pek. Plasteran 1:2 20,94 m² A. 4.4.1.7 142.293,15 2.979.334,05
Sub Total 19.255.073,25
R PEKERJAAN PAGAR RUMAH
1 Pek. Kolom Uk 15 x 15 1,25 m³ Supl-Kp 7.892.846,00 9.856.191,44
2 Pek. Pas Dinding Bata 1/2 239,04 m² A. 4.4.1.7 142.293,15 34.013.755,47
3 Pek. Plateran Dinding Bata 1/2 446,58 m² A. 4.4.2.2 64.038,16 28.598.162,92
4 Pengecatan Dinding 446,58 m² A. 4.7.1.10 36.464,75 16.284.426,72
5 Pas. Batu Alam 31,50 m² Taksir 300.000,00 9.450.000,00
Sub Total 98.202.536,55
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

III Lantai 2 PERSIAPAN


PEKERJAAN
A PEKERJAAN BETON BERTULANG
a Pekerjaan Kolom
1 Kolom Uk 35 x 35 10,68 m³ Supl-K.1 7.303.236,00 78.013.166,95
2 Kolom Praktis Uk 15 x 15 3,90 m³ Supl-Kp 7.892.846,00 30.770.852,09
b Pekerjaan Balok Latai
1 Balok Latai Uk 15 x 15 0,93 m³ Supl-BL.1 5.255.864,00 4.901.750,16
c Pekerjaan Ring Balok
1 Ring Balok Uk 20 x 35 10,92 m³ Supl-RB.1 7.167.345,00 78.257.373,12
2 Ring Balok Uk 15 x 25 4,21 m³ Supl-RB.2 7.014.472,00 29.558.108,20
3 Ring Balok Uk 15 x 15 0,73 m³ Supl-RB.3 6.931.119,00 5.030.952,73
d Pekerjaan Balok Gevel
1 Balok Kuda-kuda Uk 15 x 15 (Rb 3) 1,11 m³ Supl-RB.3 6.931.119,00 7.691.462,75
2 Balok Kuda-kuda Uk 10 x 40 (Rb 4) 0,53 m³ Supl-RB.4 6.960.156,00 3.672.178,31
Sub Total 237.895.844,31
B PEKERJAAN PLAT LANTAI
1 Pekerjaan Plat Lantai Bondek T = 0,85 880 mm 26,76 m² Taksir 169.000,00 4.521.912,72
2 Wiremesh M10 SNI 26,76 m² Taksir 975.000,00 26.087.958,00
3 Beton Mutu f’c = 24 MPa (K 275) 26,76 m³ A. 4.1.1.9 1.099.048,12 29.407.098,74
Sub Total 60.016.969,46
C PEKERJAAN TANGGA
Tangga 2
1 Panjang Plat Tangga 0,42 m³ Supl-PT 5.579.485,00 2.343.383,70
2 Cor Anak Tangga 0,37 m³ Supl-PT 5.579.485,00 2.058.829,97
3 Reling kaca Tempered Tebal 10mm 12,46 m² Taksir 935.000,00 11.646.360,00
4 Asseoris Reling Kaca 16,00 Unit Taksir 2.000.000,00 32.000.000,00
Tangga 3
1 Panjang Plat Tangga 0,32 m³ Supl-PT 5.579.485,00 1.767.580,85
2 Cor Anak Tangga 0,34 m³ Supl-PT 5.579.485,00 1.908.183,87
Sub Total 51.724.338,38
D PEKERJAAN PENUTUP LANTAI
1 Lantai Granite 80 x 80 "MAGNUM" 138,25 m² A. 4.4.3.13a 318.888,41 44.087.214,88
2 Lantai Keramik KM 50 x 50 7,43 m² A. 4.4.3.34.a 284.354,62 2.111.333,05
3 Lantai Parquet 21,00 m² A. 4.4.3.46 347.438,85 7.296.215,85
4 Roof Garden 16,46 m² Taksir 550.000,00 9.054.925,00
5 Keramik Anak Tangga 2 (MOTIF KAYU) 4,10 m² A. 4.4.3.34.a 284.354,62 1.165.853,94
6 Keramik Anak Tangga 3 (MOTIF KAYU) 3,80 m² A. 4.4.3.34.a 284.354,62 1.080.547,55
7 Keramik Bordes (MOTIF KAYU) 9,95 m² A. 4.4.3.34.a 284.354,62 2.829.044,11
Sub Total 67.625.134,37
E PEKERJAAN PASANGAN DINDING & PLASTERAN
1 Pas 1/2 Bata 1:2 19,16 m² A. 4.4.1.7 142.293,15 2.726.336,83
2 Pas Plasteran Bata 1:2 38,32 m² A. 4.4.2.2 64.038,16 2.453.942,41
3 Pas 1/2 Bata 1:4 311,48 m² A. 4.4.1.9 130.790,96 40.738.330,85
4 Pas Plasteran Bata 1:4 622,95 m² A. 4.4.2.4 58.111,48 36.200.739,48
5 Diding Keramik 20 x 30 19,16 m² A. 4.4.3.54.a 195.590,75 3.747.518,82
6 Diding Granit 80 x 80 16,95 m² A. 4.4.3.13a 318.888,41 5.406.127,89
7 Plasteran Kolom 95,92 m² A. 4.4.2.2 64.038,16 6.142.540,61
8 Plasteran Ring Balok 235,74 m² A. 4.4.2.2 64.038,16 15.096.260,54
9 Plasteran Balok Govel 33,41 m² A. 4.4.2.2 64.038,16 2.139.226,86
Sub Total 114.651.024,28
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

F PERSIAPAN
PEKERJAAN KUSEN KAYU, DAUN PINTU & JENDELA, ALUMANIUM
Pekerjaan Kayu & Kaca 5mm
1 Pintu P2
Kosen Pintu 0,12 m³ A. 4.6.1.1 11.324.566,00 1.375.934,77
Daun Pintu 5,67 m² A. 4.6.1.5 750.425,50 4.254.912,59
2 Pintu P3
- Kosen Pintu 0,04 m³ A. 4.6.1.1 11.324.566,00 441.658,07
- Daun Pintu 1,68 m² A. 4.6.1.5 750.425,50 1.260.714,84
3 Pintu P5
- Kosen Pintu 0,05 m³ A. 4.6.1.1 11.324.566,00 594.539,72
- Daun Pintu 0,88 m² A. 4.6.1.5 750.425,50 657.372,74
- Kaca Pintu 4,75 m² A. 4.6.2.17 161.220,36 766.119,13
4 Jendela J2
Kosen Jendela 0,13 m³ A. 4.6.1.1 11.324.566,00 1.452.375,59
Daun Jendela 1,34 m² A. 4.6.1.6 538.778,90 721.532,70
Kaca Jendela 3,57 m² A. 4.6.2.17 161.220,36 575.750,14
5 Jendela J3
Kosen Jendela 0,03 m³ A. 4.6.1.1 11.324.566,00 373.710,68
Daun Jendela 0,22 m² A. 4.6.1.6 538.778,90 120.255,45
Kaca Jendela 0,60 m² A. 4.6.2.17 161.220,36 95.958,36
6 Jendela J5
Kosen Jendela 0,05 m³ A. 4.6.1.1 11.324.566,00 560.566,02
Daun Jendela 0,17 m² A. 4.6.1.6 538.778,90 90.945,88
Kaca Jendela 0,45 m² A. 4.6.2.17 161.220,36 72.742,62
Kaca Mati 0,62 m² A. 4.6.2.17 161.220,36 99.956,62
7 Ventelasi V1
Kosen Ventelasi 0,07 m³ A. 4.6.1.1 11.324.566,00 840.849,03
Daun Ventelsi 0,50 m² A. 4.6.1.6 538.778,90 268.311,89
Kaca Jendela 0,53 m² A. 4.6.2.17 161.220,36 85.317,81
8 Ventelasi V5 "Segitiga"
Kosen Ventelasi 0,06 m³ A. 4.6.1.1 11.324.566,00 732.863,63
Daun Ventelsi 23,04 m² A. 4.6.1.7 929.021,50 21.404.655,36
Pekerjaan Alumanium -
1 Pintu P4
- Pintu Alumanium 3,00 bh Taksir 1.100.000,00 3.300.000,00
2 Ventelasi V3
- Ventelasi Alumanium 3,00 bh Taksir 770.000,00 2.310.000,00
3 Ventelasi V4
- Ventelasi Alumanium 2,00 bh Taksir 770.000,00 1.540.000,00
Sub Total 43.997.043,62
G PEKERJAAN KACA TEMPERED 10 mm
1 Kaca K3 4,41 m² Taksir 935.000,00 4.123.350,00
2 Kaca K4 20,04 m² Taksir 935.000,00 18.735.904,00
3 Kaca K5 7,92 m² Taksir 935.000,00 7.405.200,00
4 Kaca K6 6,27 m² Taksir 935.000,00 5.862.450,00
5 Kaca K7 2,70 m² Taksir 935.000,00 2.527.305,00
6 Kaca K8 6,02 m² Taksir 935.000,00 5.628.700,00
7 Kaca K9 12,75 m² Taksir 935.000,00 11.917.884,00
8 Kaca K10 16,32 m² Taksir 935.000,00 15.259.200,00
9 Kaca K11 8,40 m² Taksir 935.000,00 7.854.000,00
10 Kaca K12 8,64 m² Taksir 935.000,00 8.078.400,00
11 Kaca K13 2,34 m² Taksir 935.000,00 2.187.900,00
Sub Total 89.580.293,00
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

H PERSIAPAN
PEKERJAAN ATAP DAN PLAFOND
1 Gording Kayu 5 x 10 4,29 m³ A. 4.6.1.15 11.944.048,60 51.211.601,38
2 Atap Bitumen "IKO Type Cambrigre" 261,00 m² Taksir 583.821,84 152.377.500,00
3 Listplank 43,00 m² A. 4.6.1.21 114.506,70 4.923.788,10
4 Plafond Gipsum + Terpasang 84,79 m² Taksir 176.000,00 14.923.744,00
5 Furing Rangka Kayu 179,52 m² Taksir 20.000,00 3.590.422,00
6 Plafond Kayu/Lambrisering Kayu "KELAS 1" 179,52 - A. 4.5.1.6 1.282.531,36 230.241.440,53
-
Sub Total 457.268.496,01
I PEKERJAAN PENGECATAN
1 Pengecatan Pas Plasteran Bata 1:4 622,95 m² A. 4.7.1.10 36.464,75 22.715.834,48
2 Pengecatan Kosen 16,73 m² A. 4.7.1.4 48.947,80 818.774,32
3 Pengecatan Daun Pintu 16,45 m² A. 4.7.1.4 48.947,80 805.289,21
4 Pengecatan Daun Jendela 3,46 m² A. 4.7.1.4 48.947,80 169.476,86
5 Pengecatan Daun Ventelasi 47,08 m² A. 4.7.1.4 48.947,80 2.304.266,63
-
Sub Total 26.813.641,50
J PEKERJAAN LISTRIK
1 Saklar Ganda "Panasonic" 8,00 Unit Taksir 30.500,00 244.000,00
2 Saklar Tunggal "Panasonic" 8,00 Unit Taksir 26.000,00 208.000,00
3 Stop Kontak Ganda "Panasonic" 8,00 Unit Taksir 25.500,00 204.000,00
4 Lampu DL 20 Watt "Hannock" 29,00 Unit Taksir 165.000,00 4.785.000,00
5 Lampu T4 P.80cm, 24 Watt (Kuning Matahari) 14,00 Unit Taksir 43.000,00 602.000,00
6 Lampu T4 P.40cm 20 Watt (Kuning Matahari) 5,00 Unit Taksir 35.000,00 175.000,00
7 Lampu Tangga BRDL 5 Watt "Luxmenn TR24 BR" 2,00 Unit Taksir 57.200,00 114.400,00
8 Lampu Dinding LED (Kuning) 5,00 Unit Taksir 300.000,00 1.500.000,00
9 Lampu Gantung LED 2,00 Unit Taksir -
10 Lampu Taman "TE-72-BLACK" 1,00 Unit Taksir 385.000,00 385.000,00
11 Kipas Angin Plafond "PANASONIC EY153 WP 56" 6,00 Unit Taksir 828.000,00 4.968.000,00
12 Kabel / Wire 5,00 Glg Taksir 250.000,00 1.250.000,00
-
Sub Total 14.435.400,00
K PEKERJAAN PENGANTUNG
1 Handle Kecil Minimalis + Kunci "Dumont" + 7,00 Bh Taksir 234.000,00 1.638.000,00
Terpasang
2 Engsel pintu 4 "SES" + Terpasang 18,00 Bh Taksir 97.500,00 1.755.000,00
3 Engsel Jendela "SES" + Terpasang 42,00 Bh Taksir 78.000,00 3.276.000,00
4 Grendel jendela "SES" + Terpasang 21,00 Bh Taksir 84.500,00 1.774.500,00
5 Hak Angin Jendela "Dekson" + Terpasang 42,00 Bh Taksir 44.200,00 1.856.400,00
6 Rail + Assoris Pintu Sliding "UNIKEY" +Terpasang 1,00 Unit Taksir 1.878.800,00 1.878.800,00
7 Rel Pintu Kaca Tempet 2,00 Unit Taksir 6.050.000,00 12.100.000,00
8 Klam Spider 6,00 Bh Taksir 1.650.000,00 9.900.000,00

Sub Total 34.178.700,00


L PEKERJAAN SANITASI
1 Kloset Duduk 3,00 Unit A. 5.1.1.1 3.903.560,10 11.710.680,30
2 Bak Viber 30 lt 2,00 bh Taksir 265.650,00 531.300,00
3 Pas. Kran 1/2 inc "TL-020 STAINLESS" 3,00 bh Taksir 173.250,00 519.750,00
4 Pas. Kran Bethub "STAINLESS WASER-MBT-S610" 1,00 bh Taksir 723.000,00 723.000,00
5 Gantungan Handuk "DOUBEL SS 70 - VLTP62" 3,00 bh Taksir 367.400,00 1.102.200,00
6 Bathtub "MERIDIAN" 1,00 bh Taksir 5.205.200,00 5.205.200,00
7 Shower "WASER-SHS-833" 3,00 bh Taksir 478.170,00 1.434.510,00
RENCANA ANGGARAN BIAYA
(RAB)
PEKERJAAN : GAMBAR DESAIN RUMAH HUNIA 2 LANTAI
LOKASI : PROVINSI ACEH
TAHUN : 2016

HARGA SATUAN JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT. ANALISA
( Rp.) ( Rp.)
1 2 3 4 5 6 7

8 PEKERJAAN
Pas PERSIAPAN
Wastafel "TOTO L38 WHITE" 1,00 bh A. 5.1.1.5 1.094.610,00 1.094.610,00
9 Pas. Floor Drain Stailess Steel 3,00 bh A. 5.1.1.14 144.525,70 433.577,10
10 Pipa Air Bersih Uk 1/2" 102,13 m A. 5.1.1.25 43.484,10 4.441.031,13
11 Pipa Air Kotor Uk 3" 79,08 m A. 5.1.1.31 180.258,05 14.254.806,20
Sub Total 41.450.664,73
M PEKERJAAN LAIN-LAIN
1 Kanopy Rangka Baja 1,00 unit Taksir 22.000.000,00 22.000.000,00
2 Pek. Bangku Roof Garden -
Pas 1/2 Bata 1:2 2,93 m² A. 4.4.1.7 142.293,15 416.207,47
Pas Plasteran Bata 1:2 5,85 m² A. 4.4.2.2 64.038,16 374.623,25
Bangku Kayu Kelas 1 2,93 m² A. 4.5.1.6 1.282.531,36 3.751.404,23
3 Pek. Frame Kerawang Tebal 15mm -
Frame Kerawang Tebal 15mm F1 5,40 m² Taksir 1.299.037,75 7.014.803,85
Frame Kerawang Tebal 15mm F2 14,40 m² Taksir 1.299.037,75 18.706.143,60
Frame Kerawang Tebal 15mm F3 10,37 m² Taksir 1.299.037,75 13.468.423,39
Frame Kerawang Tebal 15mm F4a 3,74 m² Taksir 1.299.037,75 4.852.880,27
Frame Kerawang Tebal 15mm F4b 4,10 m² Taksir 1.299.037,75 5.323.781,46
Frame Kerawang Tebal 15mm F5 11,84 m² Taksir 1.299.037,75 15.380.606,96
Frame Kerawang Tebal 15mm F6 2,06 m² Taksir 1.299.037,75 2.673.419,69
Frame Kerawang Tebal 15mm F7 23,17 m² Taksir 1.299.037,75 30.096.106,59
Frame Kerawang Tebal 15mm F8 13,76 m² Taksir 1.299.037,75 17.874.759,44
Frame Kerawang Tebal 15mm F9 23,68 m² Taksir 1.299.037,75 30.761.213,92
Frame Kerawang Tebal 15mm F10a 3,96 m² Taksir 1.299.037,75 5.144.189,49
Frame Kerawang Tebal 15mm F10b 2,42 m² Taksir 1.299.037,75 3.143.671,35
4 Pek. Rangka Frame Kerawang 4x4 cm, t.2mm fin.
Cat Top Color Hitam Doft + Epoxy + Terpasang
Rangka Frame Kerawang F1 16,20 m Taksir 91.300,00 1.479.060,00
Rangka Frame Kerawang F2 29,50 m Taksir 91.300,00 2.693.350,00
Rangka Frame Kerawang F3 24,06 m Taksir 91.300,00 2.196.678,00
Rangka Frame Kerawang F4a 13,17 m Taksir 91.300,00 1.202.421,00
Rangka Frame Kerawang F4b 16,61 m Taksir 91.300,00 1.516.493,00
Rangka Frame Kerawang F5 27,10 m Taksir 91.300,00 2.474.230,00
Rangka Frame Kerawang F6 8,81 m Taksir 91.300,00 804.353,00
Rangka Frame Kerawang F7 53,72 m Taksir 91.300,00 4.904.636,00
Rangka Frame Kerawang F8 28,90 m Taksir 91.300,00 2.638.570,00
Rangka Frame Kerawang F9 54,20 m Taksir 91.300,00 4.948.460,00
Rangka Frame Kerawang F10a 16,00 m Taksir 91.300,00 1.460.800,00
Rangka Frame Kerawang F10a 8,80 m Taksir 91.300,00 803.440,00
5 Kanopy Carport Kaca Tempered Tebal 10mm + 12,87 m² Taksir 935.000,00 12.033.450,00
Terpasang
6 Pipa Galvanis Diametr 4" + Finising Cat Minyak 5,18 m Taksir 280.000,00 1.450.400,00
Doft Hitam -
Sub Total 221.588.575,96