B PEKERJAAN TANAH DAN PONDASI 61.549.922,00 C PEKERJAAN BETON 161.489.896,36 D PEKERJAAN KUSEN, DAUN PINTU 90.548.985,00 E PEKERJAAN LANTAI DAN KERAMIK 105.080.107,00 F PEKERJAAN ATAP 160.140.456,00 G PEKERJAAN PLAFOND 74.699.291,00 H PEKERJAAN DINDING, DAN PENGECETAN 207.367.213,80 I PEKERJAAN SANITASI 12.594.288,70 J SEPTIC TANK 18.357.076,50 K PEKERJAAN LISTRIK 6.470.624,00 L PEKERJAAN LAIN-LAIN 29.001.978,25
JUMLAH (REAL COST) 939.851.878,61
PPN 11% - JUMLAH BIAYA 939.851.878,61 PEMBULATAN 939.850.000,00
TERBILANG :
Sembilan Ratus Tiga Puluh Sembilan Juta Delapan Ratus Lima Puluh Ribu Rupiah