Pelaksanaan Pekerjaan Corewall Dengan Metode Sateco Climbing Formwork
Pelaksanaan Pekerjaan Corewall Dengan Metode Sateco Climbing Formwork
INTISARI
ABSTRACT
High rise building are complex face an structural planning internal issue and the
development process. Excelsior a consideration building of rigidity and strength of
sewer structures hardly determines in planning. These days have been many ways
which can be done to take care of rigidity and strength of high rise building especially
in arrest lateral payload for example by using sewer structures of corewall. The aims
of final task writting are to evaluate implementation method of corewall and time
effectivity sateco climbing formwork system at construction of BNI BSD building. In
practice, there are several stages in corewall work, starts from marking, restating,
formwork jobs, casting, disassembly of formwork, and curing. Based on the
information, inferential there is excess and insuffiency from the method, from the
angle of safety, this less safe method. For the purpose the workers doing work must
have experience and expertise in vertical area. Effective mean cycle time to corewall
work with sateco climbing formwork method at construction of BNI BSD building is
7,3 days. While theoretically by using slip and autojump formwork method quicker
that is 1,9 days and 1,4 days.